hs - slac national accelerator laboratory · actual pressure distribution may be quite complex and...
TRANSCRIPT
- 9 -
Gu.nelicl' r.1I3.terioJ. HS bo,cl\:fHl aC;{l,:lnct the accelcl'ntor walls nnel thc Klystron
waJ.l in order to minimiz,e la.teral earth pressures. However, there may not, be
6'U.ffic1en't; select mnterial to use it at a.ll locations desired.
Select sandy material placed as fill for support of the accelerator
or the Klystron housing should be compacted to approximately 95 percent of the
maximum density determined by the Modified A.A.S.H.O.* method of compact ton
testing. Any shale placed beneath the structures should be compacted to at
least 90 percent of maximum Modified A.A.S.H.O. denSity. There should be a
provision for modifying the degree of compaction based on field observation
during construction and further detailed study of' comprcasibHUy character
istics.
We understand the degree of compaction of the Shielding soil :l.s not
critical. However, we suggest that a compaction of approx1Jna.tely 90 percent
of maxlmum t.t>dified A.A. S.H.O. denSity be used. Based on this compact:Lon, we
believe that 1'111 slopes for the entire alignment and end station areas would
be stable when constructed on 1-1/2:1 (one and one-half horizontal to one
vertical) with 10 .. to 12-foot wide benches every 30 feet vertically. Although
the slopes would be generally safe against failure, considerable surface
erosion could ooour unless special provision were to prevent eros10n--th1s
'should inClude compaction of the slopes, probably by rolling up and down the
Glopes, and suitable planting or other measures. Drainage ditches should be
provided at the tops of slopes and along the benches. Periodic maintenance
should be provided to keep the ditches clear and to correct any surface slough···
ing that may occur.
*American Association of State Highway Officials.
L
- 10 -
Based on a comparison of field density of the material and density of
the compacted material, we expect approx.:i.mately the following volume factors
between cut and fill:
Required Compacted Density Percent of Maximum
MOdified A.A.S.H.O. Density
85
90
95
100
Cubic Yards of Fill Obtained from One Cubic Yard of Cut
Shale
1.05
1.00
Sandstone
1.09
1.04
1.00
NOTE: In arriving at the above factors, we have estimated that actual compaction percentage will be about 2 percent greater than the required percentage.
~undation Support: Fbundation loads along the accelerator
alignment are expected to be fairly light on the order of a few thousand
pounds per linear foot of accelerator. Based on present information, settle-
ment due to the weight of fill placed would be more critical than foundation
bearing pressures. Fill placed as recommended above would provide suitable
support for the accelerator and Klystron housings. Dead load plus design live
load bearing pressures on the order of 4000 pounds or more per square foot
could be used. Higher values could be used in the rock cut areas; however, it
does not appear that they would be required for support of the accelerator and
Klystron housings.
L
.. 11 ..
Lateral Pressures: Our present information indicates 'that about ten
feet of fill will bem'" against the IG.y&'tron housing wall. The slope of the
fill will impose some additional surcharge. The accelerator housing will be
surrounded on tbree sides by fill. Pressure against the walls will depend on
rigidity and shape of the wall, cllaracteristics of the fill as placed, height
and slope of fill, drainage, and construction sequenoe. We have based our
estimates on the following:
1. Non-yielding vertical walls 'Will be constructed and the
backfill will be placed against them.
2. The sandy or shale backfill will be compacted to approxi
mately 90 percent of ma:x::inn.un Modified A.A. S.H.O. denSity at
a max:Lmum moisture content about 3 percent above optimum.
3. The accelerator hoUSing will have backfill on the sides
and tops. The KLystron housing wall will have about 10
feet of backfill against it.
4. Drainage will be provided to prevent the build-up of
l~ostatic presrnxre.
Under these conditions, we believe that lateral earth pressure
coefficients of about 0.4 to 0.5 for sandy material, and 0.6 to 0.7 for clayey
material could develop.
For p:r.esent preliminary design of lateral pressure against side walls
of the accelerat()r housing, we recornIltond tha.t the backfill be considered to act
as a fluid with a density of 60 pounds per cubic foot for the sandy soil, and
80 pounds per cubic foot for the cla;yey soil or clay shale. Since present
- 12 -
plans call for a horsehoe~shaped section for the accelerator housing, the
actual pressure distribution may be quite complex and be dependent upon the
plastiCity of the backfill materiaJ..
In considering lateral earth pressures against the Klystron housing
WIlll, some allowance should be made for the increased pressures due to
compaction equipment, possible surface loads on the fill adjacent to the \ffill,
and the adjacent fill slope. For preliminary deSign, we recommend using a
lateral pressure of 200 pounds per square foot in addition to the equivalent
fluid pressure given above.
Settlement: Near Borings lOA, 12, 13, and 14, q~ite compressible
clayey aLluvium exists at accelerator floor e1e~v.ation. For instance, in
Boring lOA, where clayey soils were encountered to a depth of 24 feet, we
estimate one foot or more of consolidation 'tIlOuld take place vTithin the clayey
soils under a 75-foot high fill. Accordingly, in the Section IISite Preparation
and Filling, It we have recommended excavation and replacement of this alluvium
under the acclerator housing and other important structural areas.
The shale would also compress under the proposed fill loads" The
amount cannot be accurately assessed. For a given load, it 'fill depend
largely on the proportion of' shale to sandstone, and the degree of weathering
and distortion. The greatest consolidation is e::A':Pected in the sJ:1.ales that
have been highly weathered to a clay. We antl.cipate that in the shale areas
settlement on the order of six inches may occur under fill loads of 75 feet.
A large portion of this would occur as the fill is p.laced. He expect that most
of the settlement would occur within t'WO years af'ter placement and that subse
quent settlement would be a fraction of an inch per year.
L
- 13 -
Settlement in the Miocene sandstone also cannot be accurately
a.ssessed. However, we e:lq>ect it to be much less than in the clay shale.
Settlements under fj.lls up to 75 feet deep are estimated to be on the order
of one inch. Where shales are interbedded with the sandstone, the settlement
may be greater.
Additional settlement will take place within the fill. The amount
and rate will depend on type of fill material, compaction procedures and degree
of compaction, water content, and height of fill. If fill is placed as recom
mended under "Site Preparation and Fill Placement," we believe that settlement
of fill can be limited to tolerable amounts. In the areas where alluvium will
be stripped, it appears that a maximum of about 45 feet of fill will be required
below accelerator grade. Settlement of this fill due to its own weight, if it
is sandy as recommended for fill under the accelerator housing, shouJ.d be
substantially complete prior to construction of the accelerator housing. We
expect that sub sequent settlement of the supporting fill due to the weight of
the shielding fill and structure wHl be limited to a few inches, most of i-lhich
,.,ill take place during placement of shielding fill and within two years after~
ward.
We recommend that provision be made to establish settelement
observation pOints as fills are placed, in order to record magnitude and time
rate of settlem.ent. Subsequent settlement behavior can thus be better
predicted, and where necessary, construction procedures planned to aid in
keeping structure settlements within tolerable amounts. As plans are further
advanced, specific procedures for settlement observations can be developed.
,; I ~
.. 14 -
.EAST END AREA:
FOundations: FOundation materials at this end are good, consisting
primarily of Miocene sandstone. Some shale or cemented gravel could be
encountered, although none was evident in the borings at foundation depth.
Cut slopes of 1:1 (one horizontal to one vertical) may be used, with
10- to 12-foot wide benches at no greater than 30 feet vertically. Cuts less
than 19 feet high may be made one-half horizontal to one vertical.
Although some seepage could occur upon cutting, we do not expect it
to be a major problem in this area. However, the same type of slope erosion
protection should be provided as for slopes along the accelerator alignment.
FOr major footings on the sandstone, preliminary design bearing
pressures of 12,000 pounds per square foot may be used for dead and live loads,
increased one-third for wind or seismic loading. If shales or very weakly
cemented sands are encountered, some refutction will probably be necessary.
:b'inaJ. design values should also consider foundation size and depth; narrow,
shallow footings may require smaller bearing pressures. Design bearing
pressures of about 6000 pounds per square foot would be appropriate for
footings two feet wide and t\~ feet deep, where the material is very weakly
cemented.
Rebound during excavation, and subsequent settlement due to
structural loading, will be small in the sandstone area. We expect less than
one inch for all but extremely heavy loading. For instance, '-Ie 140uld expect
less than one inch for column loads of several hundred thousand pounds, with
foundations imposing up to 12,GOO pounds per square foot,
- 15 -
WEST END .AREA:
~: This area is in Eocene shale with interbedded layers of
harder gray sandstone. We believe the shale can be readily ripped with heavy
equipment, but that the sandstone will require some blasting where it is in
thick layers. Although the sandstone will serve to strengthen the shale,
design cut slopes should be based on shale properties. Permanent cuts in this
area will be deeper than elsewhere.
For present deSigns, we recommend cut slopes no steeper than 1-3/4:1
for slopes over 30 feet high, or 1-1/2:1 for lower slopes, with 10- to 12-foot
wide benches at no greater than 30-foot vertical intervals. Sufficient space
should be available at the tops of slopes to permit flattening to about 2-1/2 :1,
in case it should be necessary in some places either during or after cutting.
Urainage: The seepage problem in this area would probably be more
severe than in other areas, because of the dee)? permanent cuts and type of
formation. The amount of seepage at time of excavation 'dll depend largely on
w'eather conditions. Provision should be made to install horizontal drains and
collection systems. Locations where these are required must be determined in
the field as excavation proceeds; this will require careful inspection by
trained engineers or geologists. The same type of erosion protection should
be provided as for slopes along the accelerator alignment.
Foundation Support and Settlement: Preliminary deSign bearing
pressures on the order of 8000 pounds per square foot may be used for dead
plus live loads. In general, foundations in shale should be established at
- 16 -
least three feet below grade, to help minimize effects of swelling and
shrinking. Somewhat higher bearing pressures would be appropriate at greater
depth, and somewhat lower pressures may be required in local areas.
It is expected that some rebound will occur in the shale when the
overburden load is removed, with subsequent recompression on reloading. We
expect that rebound could be several inches in deep cuts. The amount will
depend considerably on the mineralogy of the shale, availability of water to
permit swelling, and the depth of cut. SUbsequent settlement of heavy building
or shielding loads could be several inches. We believe much of the settlement
would take place as load is applied. Where structures are to be built in cut
areas, they should be built as soon as feasible, to minimize moisture changes
and the amount of s'rell and recompression within the cut area. Deep foun
dations can help minimize the effects of rebound, swelling, and settlement.
It may even be desirable in some cases to overexcavate and replace undesirable
material with compacted fill.
We recommend that settlement markers be established in the proposed
structure areas as excavation proceeds, and on selected four.dations after they
are poured, in order to better determine the magnitude and time-rate of rebound
and settlement. It will be desirable to establish settlement observation
monuments at the bottoms of deep holes in the cut areas, to observe the amount
of rebound upon excavation. Specific procedures can be developed as plans are
further advanced.
.. 17 ...
If the reservoir water level 1s at Elevation 275, it will be against
the accelerator embankment at several locations. We believe that fill slopes
below this level should be 2-1/2%1 or flatter, and protected from erosion with
rock rip~rap or by other means. Occasion~ flood water rising above Elevation
275 would probably cause some erosion and surface sloughing of the fill, which
would reqUire maintenance, but we do not believe it wouJ.d cause any major
insta.bility.
Long"''&erITl storage of '\{"dter would permit infiltration into the soils
and rock under the accelerator, However, the proposed storage level of
Elevation 260 is Well belm., the proposed accelerator housing Elevation 275.
AlthoUGh access to imter could cause a s:welling tendency in some shales, 'Ire
believe the weight of overlying fills would prevent appreciable svrelling. Also,
we do not believe that W<1ter infLltration or the weight of ~dter in the
reservoir wou.ld cause appreciable ad,ditional c:onsolidation.
report:
The follOWing Plates and Appendixes are attached and complete this
Plats 1 - Plot Plan
PMte 2 ... I-T.ofile Along Center. Line of Proposed Linea.t' Accelerator
Appendix A - l"ield E::<r>loration and ulboratory Testing
.l\Wendix B - Geo:logy H~X't by }"'rank \'J. Atchley, Consulting Geologist
Respectf'u~ly suJ)mittcd,
DAMES & MOORE
~~,._~r:://L. William \-l, Moore
~~/;!//./d Charles L. Nichols
~) ~ON
/
Note: Sta. 0 +00 = Intersection of Stanford University Coordinate 1,496,000 E a West end of Accelerator Alignment
D PHOTO CONTOUR Map by R. M. TOWILL, Inc.
Date of Photography: July 19,1960
Grid is based on California Coordinate System, Zone 3 Mean Sea Level Datum, 1927 Adj.
Produced under the process of US. Letter Patent No 2,811,445
\'&
.14
.13
PLOT P 500 o 500 IO( -----------
Sca Ie in Feet
Contour Interval
-
~ LJ LJO: -
~ ~ LAN )0 1500 2000
; !
20' VICINITY MAP
lJJ
§-~ ~ It) ,
o It) ~
'\
,/
zoo ---
__ M ••• Moo •• C ..... UL ....... ' .. ......... '.O ....... IC •• OOC ...
""'" ... c" .... "" , .. "' ...... , .. " .... OLOG.· (;(O-'_SO<:I
PLATE 1 -
.. WEST
irBORING NO.
~ I GROUND SURFACE
34 65 77A 8 9 10 lOA II 12 12A 14 1516
II ! I II I
~ --I
I I I I I
II I I
400-~ w w u...
I I I I
I z ---z 300-0
~ f275--::> w SH -I w
II
SH
IT SH
200 ---1 0+-00'" ~ See "NOTE"
, ,------ 1
20+00 40+00 60+00
ACCELERATOR HOUSING INVERT
TOP OF ACCELERATOR HOUSING FILL KEY:
i i ALLUVIUM
ROCK
SH = SHALE SS = SANDSTONE
SI.S = SILTSTONE
PROFILE ALONG CENTER LINE OF PR HORIZONTAL SCALE: I" = VERTICAL SCALE: I" =
-
EAST ~
1817AI7 19 20A20 21 22 23 24 2625 28
I I
I I II
I I
I I
I -400 l-
I
I ILl
--cF~----I__ .325 ~
SS SS SS
-300 z o ~ ::> ~
---275
TSS SS ILl
I I roo 80tOO 100+00 120+00
NOTE: Sta. 0+00 = Intersection of Stanford University Coordinate 1,496,000 E a West end of Accelerator Alignment
:OPOSED LINEAR ACCELERATOR 500' 100'
DAM ••• MOO ... co .... u~ ...... ~ .. , .............. , ... Y" IIe,H":::._
"""L .. ~c ...... 'c .... G, ..... , ....... rOLaG·· GIO_ •• oet
PLATE 2 -
APPENDIX A
E'.'Jm.D EXPLORATION AND LA;BORATORY TEs:gNG
FIELD EXPLORATION: ,
SUbsurface conditions along the accelerator alignment and at both
end station areas were invest.igated by drilling 28 test borings and by
trenching. Rotary-bucket drilling equipment was used for the relatively
shallow 'borings and rotary-wash equipment for the deeper borings and. also J i.n
some' instances, for the borings in which hard rock was encountered 1""hieh the
rotary-bucket equipment could not drill. The soils and rock encountered were
logged by your engineers, with periodic site visits and advice on logging and
sampling provided by Da1nes & Moore. Dr. Frank Wo Atchley, Consulting Geologist,
also rna,de frequent site visits to observe thedrU1.ing and to obtain geological
information. Representative bul.k samples and undisturbed core samples were
obtained for visual eY.amination and la.boratory testing~ Undisturbed core
Sf.urrples were obtained utilizing the Dames & J:.100re Type D Sampler ShOvffi on
Plate A6. Rock was also corei using both tungsten carbide and diamond bits
with NX size core barrels. Graphical representation of the soil a.nd rock
encountered in the borings is presented on Plates A lA through A lW, Log of
Borings. The nomenclature used in classifying the 50ils is defined. by the
Soil Classification Chart shown on Plate A'2..
The drilllng program was planned by John A. Blume & Associates,
Engineers, and ·by~mes & Moore with additional advice by Dr. Atchley.
Originally proposed B(..)rings 1, 2, and 27 were not drilled.
- A-2 ~
Some trenching Ims done under the supervision of Dr. Atchley to aid
him in delineating rock types and distribution and other detailed geology.
The locations of the trenches are sho'lrm in Dr. Atchley! s report in A:ppendix B.
LABORATORY TESTWG:
Selected undisturbed core samples obtained during the drilling
program were tested in double direct shear, strain control, to aid in evalu
ating-the stability of slopes and the supporting capacity of soil and rock
encountered under the accelerator and target building structures. The results
of the shear tests and moisture-d.ensity determinations are presented to the
.left of the appropriate boring logs. The method of performinG these shear
tests is shown on Plate K(, Bethod of Performing Direct Shear Tests. No rock
samples were tested in triaxial sheer because the samples became disturbed
upon removal from the soil rings as a result of the friable or fractured
nature of the rock.
To provide data for use in settlement calculations, consolidation
(confined compression) tests ,,,ere performed, The results of the consolidation
tests are presented on Plates A 3A through A 3C, Consolidation Test D3.ta. The
methods used are explained on Plate A8, l'~ethod of Performing Consolidation
'rests.
Compaction tests were performed on representative srunples of sandstone
and shale by the Modified A.A.S.H.O. Jv1ethod shown on Plate A9, Method of
Performing Compaction Tests. The results of the tests are presented on
Plates A 4A through A 4c, Compaction Test rnta. Representative direct double
... A-3 ....
shear tests were performed on cores compacted to varying densities at varying
moisture contents and. under surcharGes applicable to expected. field conditions.
'.':iC ::.'csults are tabulated on Plate A'j, Shear rl'est Data, Compacted. COI'es.
~rhe following Plates are attached and complete this Appendix.:
Plates A lA through A lW - Log of Borings (Borings 3 tlrrough 26,
and 28)
Plate A2 - Soil Classification Chart
Plate:; A 3A, A 3B, and
A 3C - Consolidation Test lata
Plate A4, A 4B, and A 4c - Compaction Test Data
Plate A5 - Shear Test Data, Compacted Cores
Plate A6 - Soil 8aTnpler, Type D
Plate A7 - Method of Performing Direct Shear Tests
Plate A8
Plate: A9
... Method of Performing Consolidation Tests
... Method. of Performing Compaction Tests
•
i ~ 'V
~ ~ '"
t-w w u.
~
2 0 f= ~ w ...J w
t- t-U.
U. 0 0 ~ t-~ t- u. V) u.
::j V) ID :::> U ID ...J
~ "-...J
en '" - W V) ID t-:x: '" '" ID
'" ...J «t- a: a: ...J a: ::I'" <[ :::> >' ::::J >' _2 :x: t- t- t-f-,w u V) t- V) en Ja: a: 0 U; 0 2 ::::Jt; ::::J ::IE 2 ::IE W V) W
0 a: 0 0 0 <[ t- ...J >- ...J >-W V) W w a: :x: w u:: a: u:: 0 V) t- O
W ...J a.
----::; <[ ~ V)
W 0 a: V)
0 en u
'" IDV)
~ >- o '" ...J UJ
...J a: ~ g t-
...J W a: ( ~ 8 ::::J U t- - 2 ::::J::; V) :x: :J CJ) ..
W W _ a. ...J V)w a: a: o <[ _ W::;
8 ~ 2 a: a: a:-::::J '"
o a.t-
360
355
350
345 22
340 Imm,---=-_
335
330
325
320
315
310 ~
305-----------------------------------------+-------800 - 500 - 12% - 124 5000 - 3000 - 12% - 124
300-------------------------------------+----~
295-----j 1000 - 200 - 15% - 113 3500 - 2500 - 15% - 113 12% -' 124
290 ~
BORING 3 DRILLED 7-26-60 TO 7-27-60 WITH
5· DIA~ETER ROTARY WASH EOUIP~ENT
ELEVATION 359.0'
ISH-BROWN CLAY (TOP SOIL LIGHT BROWN FINE GRAIN SANDSTONE,
POORLY CEMENTED, WITH INTERBEDDED LA YER S OF GRAY I SH-BROWN SHALE (SANDSTONE TOO HARD TO RIP)
(OCCASIONAL S~LL GRAVEL IN SANDSTONE
GRAYISH-BROWN FRACTURED SHALE (CAN BE RIPPED)
(GRADING GRAYISH-BLACK IN COLOR)
(OCCASIONAL LAYERS OF HARD GRAY FINE GRAIN SANDSTONE)
INTERBEDDED GRAY FINE GRAIN SANDSTONE & BLACK SHALE
GRAYISH-BLACK SHALE WITH OCCASIONAL THIN LAYERS OF HARD GRAY FINE GRAIN SANDSTONE
LOG OF
290 - ... ,
285 ~
280 ~ 1000 - 500 - 16% - 118 - I~ 3500 - 2500 - 16% - 118 - I~
275 li:k~ -
270-----------------------------------------------
265 ~~
260 lWAi
100 2H ~m
300/4 250-----------------------------------------+~
100
245 fll!a!J :?:~/,:
240
BORING
(LENS OF GRAY FINE. GRAIN SANDSTONE. TOO HARD TO RIP)
HARD GRAY FINE GRAIN SANDSTONE (TOO HARD TO RIP)
INTERBEDDED GRAYISH-BLACK SHALE & HARD GRAY FINE GRAIN SANDSTONE
(100' OF 2· PLASTIC PIPE WITH II." PERFORATIONS PLACED)
DA_ ••• _OO ... CON.ULTANT& 'N "' __ 'UI .AIn"H ICI._ ••
_L .. U:H ..... OC .. · ._' ... ,U"_G. __ 1'· ._~
PLATE AlA -
I-- I--
"- "-
~I 0 0 (j) 'C I-- I--,
(j) "- "- ~, (j) m m ::i =>
~I -' -' ~ '" '" . w (j) (j) I-I (.!)
W '" '" «I-- 0:: -' W -'
~l (.!)
~~ « 0:: cr BORING 4 I => ,: => ,: 5~ l- I--t) (j) I-- Ul t- W 0
=>t;; 0:: 6 Vi 6 Vi ~ -' DRILLED 7-28-60 WITH 24" DIAMETER => (j) ~ z ::;; z
=>[ u ROTARY BUCKET EQUIPMENT w w I-- -0::
0 0 D (j) I « I-- D - "-W (j) -' >- -' >- D « I W W 0:: W 0:: Z 0::
'" I-- LL D LL D => '"
295 ELEVATION 294.0' , , SH-BROWN CLAY : SOIL)~CL~ 18% - 110 BROWN CLAY CL
290 (GRADING TO DARK BROWN SILTY CLAY)
13% - 114 BROWN SANDY CLAY WITH MANY ROCK 285 FRAGMENTS (CL)
> ::>
(ROCK FRAGMENTS TO 6" DIA.) ..J
19fo - 101 ..J « 280
"J GRAY CLAYEY SANn (SOME SEEPAGE) c ~ 275 BROWNISH-GRAY FRACTURED SHALE (SOME ! SEEPAGE IN FRACTURES)(SOME RAVELING)
I J (CAN BE RIPPED)
1500 - 500 - 13% - 118 17% - 124 GRAYISH-BLACK FRACTURED SHALE I ~ 270 (GRAD ING DRYER)
I--w
(THIN LAYERS OF GRAY FINE GRAIN w "- SANDSTONE) 265 - (BUCKET IS DRIFTING TO ONE SIDE
BECAUSE OF SANDSTONE ON ONE SIDE OF HOLE)
260 GRAY FINE GRAIN SANDSTONE (TOO HARD
TO DRILL WITH BUCKE~ CANNOT BE I
RIPPED) ~ 255 NOTE: WATER LEVEL AT ELEV. 263' ,
jj 7-29-60
250 ~ ~ o 0 ,
i
, ! ,I 245 'j ~ . 240
235
LOG OF BORING
DAMES a MOORE SOIL MECHANICS ENGINEERS
PLATE AlB
365
w --'
~ ~--LL. « Z :J (j)-
U a ;;; ~ C/)'
W m U (f)
~ ~ ~I >- ~I "'I "3~ BORING 5 5Q t: j 5 aJ 9 w:J DR I LLED 7-28-60 TO 7-29-60 WITH ~ ~ gs ~ ~II ~I g:;~ 5" DIAMETER ROTARY WASH EQUIPMENT Q 0 wi ~ ~ j ~u.i ~ h: ~I ~ ~ ii~;; u... 0 u 0' ~ 0 CL..~
ELEVATION
GRAYISH-BROWN CLAY (TOP SOIL) (CL)
360 220/4 310 240/3
I ~""f--2l<-4'0/4 LIGHT BROWN FINE GRAIN SANDSTONE 8% - 129 (MODERATELY HARD)(PROBABLY CAN BE
355 RIPPED) 305
350 I F"'~ 300 100
INTERBEDDED BROWN SHALE & HARD BROWN FINE GRAIN SANDSTONE (TOO HARD TO
280/5 320/1
345 ~Z4Ufll RIP) 295
34G 260/5 290 t;:;' (HARO LAYER OF SANDSTONE) w "-
~
~ 335 1millr--z-40/41 (BAOL Y SHEARED) 285 ,.. §! w --' W 330 280
325 215
320
315
310
305
(GRADING GRAY IN COLOR)
100
LOG OF BORING
o
DAM •• a MOO". CONSULTANTS 1N .. ~IEO ' .. 10TH SCIINC ...
.oIL W«:HANICS· '[1 ... , ...... "'_ GEOLOGy· GIEO_YSOC:,
PLATE Ale -
- I f-' f-' lL lL
0 0
~ ~ f-' lL
<Ii (,/) :;j '" '" --' 0 --'
W • ...; <Ii f-'r ~ '" W C(f-' I>: I>: --' :z~ C( :::> _2 >" f-'w r f-' ..II>: 0 (,/) f-' "'f-' I>: (5 iii :::> (,/)
(,/) ~ 2 w
I>: 0 0 C( t- --' W (,/) uJ >-r w u: a:: (,/) t- o
345
340
335
330
1000 - 500 - 2~ - 100 2500 - 1500 - 2~ - 100
325
320 t-W W lL
~ 315
2 0 f= ~
~ W --' W
310 '\:
~ 305
300
~ ~
295 , i;\ ~
290
285
W I>: :::> f-' (,/)
(5 ~
0 --' !!! lL
I 1 1 1 I
20% -
f-' lL
'" 0 , (,/)
'" --' ,: t-iii 2 w 0
>-a:: 0
, I I I t
107
- 98
11% - 127
13% - 129
W --'
:1 U
~I >- ~ 81 --' a:: --' w
~ "I ~! ~ :::> U
~I I 10
WI W a:: a:: o ,!! U 0
---2 -0 (,/)
(,/)
'::~ BORING 6 ...;~ DR I LLED 8-1-60 TO 8-2-60 WITH
~I ~':§ 5- DIAMETER ROTARY WASH EOU I PMENT :]1 "''''; _ uJ~ a:: or_ o eLt-
ELEVATION 341.0'
GRAY CLAY (TOP SOIL) (CL)
BROWN SHALE (MODERATELY SOFT)(CAN BE RIPPED)
(GRADING GRAYISH-BLACK IN COLOR)
INTERBEDDED MODERATELY HARD GRAYISHBLACK SHALE WITH OCCASIONAL LAYERS OF HARD GRAY FINE GRAIN SANDSTONE WHICH PROBABLY CANNOT BE RIPPED
LOG
290 ~
285 ~
280 v I
275 W"A----
210 I .vv t::i
265 ~_
2~ I
255---------------------------------------+----~
250
OF BORING
BLACK SHALE (MODERATELY S OFl. CAN BE RIPPED)
DAM.S a MOO •• COf<.ULT ... NT., .... ~"(D .. "'"HKII['<CE.
""L .. "e ....... ..;' . ENGINEIU",_ GIOLoaV . <iI:~V.I(:.
PLATE AID -