hotel sonoma final eir - storage.googleapis.com€¦ · 2.1.3 report organization this revised...
TRANSCRIPT
November 2019
Hotel Project Sonoma Final EIRCity of Sonoma
SCH # 2014062041
NOVEMBER 2019
Hotel Project Sonoma Final EIRCity of Sonoma
SCH # 2014062041
1-1
1. Introduction
1.1 PURPOSE OF THE ENVIRONMENTAL IMPACT REPORT
This document provides responses to comments received on the revised Draft EnvironmentalImpact Report (revised Draft EIR) for the proposed Hotel Project Sonoma (Project). The revisedDraft EIR identified significant impacts associated with the Project and examined alternativesand recommended mitigation measures that could avoid or reduce potential impacts.
This document, together with the January 2016 Draft EIR, the October 2016 Final EIR, and theJuly 20, 2018 revised Draft EIR, will constitute the Final EIR. The City of Sonoma PlanningCommission will be asked to certify these documents as complete and adequate under theCalifornia Environmental Quality Act (CEQA).
1.2 ENVIRONMENTAL REVIEW PROCESS
According to CEQA, lead agencies are required to consult with public agencies havingjurisdiction over a proposed project, and to provide the general public with an opportunity tocomment on the revised Draft EIR. This revised Final EIR has been prepared to respond tocomments received on the revised Draft EIR.
The revised Draft EIR was made available for public review from July 20, 2018 throughSeptember 13, 2018. The revised Draft EIR was distributed to local, regional, and Stateagencies and the general public was advised of the availability of the revised Draft EIR. Copiesof the revised Draft EIR were made available for review to interested parties at:
§ City Hall at No. 1 The Plaza, Sonoma
§ Sonoma Valley Regional Library, 744 West Napa Street, Sonoma
§ The City's website at http://www.sonomacity.org/News.aspx
A Planning Commission public hearing to solicit comments on the revised Draft EIR was heldSeptember 4, 2018. The 45-day public comment period ended on September 13, 2018. Copiesof all written comments received on the revised Draft EIR are contained in this document. Thesecomments and responses to these comments are laid out in Chapter 5, Comments andResponses, of this revised Final EIR.
The revised Final EIR will be presented to the City of Sonoma for potential certification as theenvironmental document for the Project. All persons who commented on the revised Draft EIR
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
INTRODUCTION
1-2 N o v e m b e r 2 0 1 9
will be notified of the availability of the revised Final EIR and the date of the public hearingbefore the City.
All response to comments submitted on the revised Draft EIR by agencies will be provided tothose agencies at least 10 days prior to the final action on the Project. The PlanningCommission will make findings regarding the extent and nature of the impacts as presented inthe revised Final EIR. The revised Final EIR will need to be certified as complete by the Cityprior to making a decision to approve or deny the Project. Public input is encouraged at allpublic hearings before the City.
Should the Planning Commission certify the revised Final EIR, it will also consider the Projectitself, which it may approve, deny, or approve with conditions. The Planning Commission mayrequire the mitigation measures specified in this revised Draft EIR as conditions of Projectapproval, and it may also require other feasible mitigation measures. Alternatively, the PlanningCommission may find that the mitigation measures are outside of the jurisdiction of the City toimplement, or that there is no feasible mitigation measure(s) for a given significant impact. In thelatter case, the Planning Commission may nonetheless determine that the Project is necessaryor desirable due to specific overriding considerations, including economic factors, and mayapprove the Project despite an unavoidable, significant impact.
1.3 REPORT ORGANIZATION
This document is organized into the following chapters:
§ Chapter 1: Introduction. This chapter discusses the use and organization of this Responseto Comments Document.
§ Chapter 2: Executive Summary. This chapter is a summary of the conclusions of the DraftEIR and the Response to Comments Document.
§ Chapter 3: Revisions to the Revised Draft EIR. Additional corrections to the text andgraphics of the Revised Draft EIR are contained in this chapter. Underline text representslanguage that has been added to the EIR; text with strikethrough has been deleted from theEIR.
§ Chapter 4: Comments and Responses. This chapter lists the comments received fromagencies and the public on the revised Draft EIR and provides responses to thosecomments.
§ Appendices. The appendices for this document contain the following supportingdocuments:
Appendix Q: City Council Resolution to Recirculate the EIRAppendix R: Revised Technical Traffic AppendixAppendix S: Mitigation Monitoring and Reporting Plan
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
INTRODUCTION
November 2019 1-3
Appendix T: Historic Evaluation of Proposed Bulb-out (revised)Appendix U: Project VMT Benchmark Estimate and Mitigation Performance TargetAppendix V: Hotel Project Sonoma Vehicle-Miles of Travel (VMT) EstimateAppendix W: Greenhouse Gas AnalysisAppendix X: Delivery Plan
2-1Final Revised Final EIR
Executive Summary
This summary is intended to highlight the major areas of importance in the environmental analysis for the Project as required by Section 15123 of the California Environmental Quality Act (CEQA) Guidelines. The summary includes an overview of the CEQA process, brief description of the Project, a summary of alternatives to the Project, and a table summarizing (1) potential environmental impacts that would occur as a result of the Project; (2) the level of significance of the environmental impacts prior to implementation of any applicable mitigation measures; (3) the recommended mitigation measures that avoid or reduce significant environmental impacts; and (4) the level of significance after mitigation measures are implemented (refer to Table 2-1 [Summary of Impacts and Mitigation Measures] at the end of this chapter).
2.1 HOTEL PROJECT SONOMA CEQA PROCESSThe proposed Project has undergone extensive CEQA review. A Draft EIR was filed with the Office of Planning and Research (OPR) State Clearinghouse and circulated to State agencies on January 26, 2016 for a 45-day review period ending on March 10, 2016; the Draft EIR is herein referred to as “2016 Draft EIR.” A Final EIR (2016 Final EIR) was certified by the Planning Commission on April 13, 2017. The decision of the Planning Commission was appealed to the City Council, which held public hearings on June 22, 2017 and August 14, 2017. At the August 14, 2017 hearing, the City Council adopted Resolution #43-2017, (Appendix N of this revised Draft EIR) which upheld the appeal and directed that the 2016 Draft EIR be revised.
The revised Draft EIR was made available for public review from July 20, 2018 through September 13, 2018. The revised Draft EIR was distributed to local, regional, and State agencies and the general public was advised of the availability of the revised Draft EIR. Copies of the revised Draft EIR were made available for review to interested parties at:
§ City Hall at No. 1 The Plaza, Sonoma
§ Sonoma Valley Regional Library, 744 West Napa Street, Sonoma
§ The City's website at http://www.sonomacity.org/News.aspx
The 45-day public comment period ended on September 13, 2018. Copies of all written comments received on the Draft EIR are contained in this document. These comments and responses to these comments are laid out in Chapter 5, Comments and Responses, of this Final EIR.
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
EXECUTIVE SUMMARY
2-2 N o v e m b e r 2 0 1 9
2.1.1 REVISED DRAFT EIRThe revised Draft EIR was a recirculated EIR prepared in accordance with CEQA GuidelinesSection 15088.5, which contains provisions regarding recirculation of an EIR. According toSection 15088.5(a), a lead agency is required to recirculate an EIR when “significant newinformation” is added to the EIR after notice of availability of the Draft EIR has been issued, butbefore certification of the EIR. According to CEQA Guideline Section 15088.5(a), “information”can include changes in the project, changes in the environmental setting, additional data, orother information. In this case, the new information that has been added to the 2016 Draft EIR isthe addition of certain project components analyzed in Section 3.5 of this revised Draft EIR, aswell as three new alternatives analyzed in the revised Draft EIR.
According to Section 15088.5(c), the recirculated EIR need only contain the portions of the DraftEIR that have been modified. Therefore, the revised Draft EIR focused on new analysis anddoes not reproduce information from the 2016 Draft EIR unless it was critical to understandingthe analysis.
2.1.2 REVISED FINAL EIRThis document provides responses to comments received on the revised Draft EIR for theproposed Project. The revised Draft EIR identified significant impacts associated with theproposed Project and examined alternatives and recommended mitigation measures that couldavoid or reduce potential impacts.
This document, together with the January 2016 Draft EIR, the October 2016 Final EIR, and theJuly 20, 2018 revised Draft EIR, will constitute the Final EIR if the City of Sonoma PlanningCommission certifies it as complete and adequate under the California Environmental QualityAct (CEQA).
2.1.3 REPORT ORGANIZATION
This revised Final EIR is organized into the following chapters:
§ Chapter 1: Introduction. This chapter discusses the use and organization of this Responseto Comments Document.
§ Chapter 2: Executive Summary. This chapter is a summary of the conclusions of the DraftEIR and the Response to Comments Document.
§ Chapter 3: Revisions to the Revised Draft EIR. Additional corrections to the text andgraphics of the Draft EIR are contained in this chapter. Underline text represents languagethat has been added to the EIR; text with strikethrough has been deleted from the EIR.
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
EXECUTIVE SUMMARY
2-3November 2019
§ Chapter 4: Comments and Responses. This chapter lists the comments received fromagencies and the public on the revised Draft EIR and provides responses to thosecomments.
§ Appendices. The appendices for this document contain the following supportingdocuments:
Appendix Q: City Council Resolution to Recirculate the EIRAppendix R: Revised Technical Traffic AnalysisAppendix S: Mitigation Monitoring and Reporting PlanAppendix T: Historic Evaluation of Proposed Bulb-out (revised)Appendix U: Project VMT Benchmark Estimate and Mitigation Performance TargetAppendix V: Hotel Project Sonoma Vehicle-Miles of Travel (VMT) EstimateAppendix W: Greenhouse Gas AnalysisAppendix X: Delivery Plan
2.2 PROJECT LOCATION
The Project site is located near the southwest corner of the Sonoma Plaza in the City ofSonoma, California, approximately 40 miles north of San Francisco. The Project is locatedwithin the block bounded by Highway 12 (West Napa Street) to the north, First Street West tothe east, Andrieux Street to the south, and Second Street West to the west, with regionalvehicular access to the Project site provided via West Napa Street.
2.3 PROJECT SUMMARY
Kenwood Investments, LLC (Project Applicant) is proposing a 62-room hotel, 80-seat restaurant,and spa, along with 115 on-site parking spaces, located on West Napa Street in Sonoma,California, on a 71,000-square-foot lot (1.63 acres). At buildout, the Project would include a totalhotel building area of 67,478 square feet;1 a 37,655-square-foot basement parking garage; and26,962 square feet of exterior courtyards, surface parking areas, and patio areas. Additionally,the Project would include landscaped street trees in raised planters along West Napa Street,First Street West, and throughout the Project site, as well as raised planter beds.
The principle components of the Project are listed below (A detailed description of the project,including maps and figures is included in Chapter 3, Project Description of the revised DraftEIR):
§ Demolition and Site Preparation. The existing metal warehouse, 153 West Napa Streetbuilding, ancillary structures (i.e. sheds), and existing parking lots would be demolished andremoved to accommodate the Project. In total, approximately 15,412 square feet of building
1 Excludes square footage of basement parking garage and exterior courtyards.
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
EXECUTIVE SUMMARY
2-4 N o v e m b e r 2 0 1 9
space would be demolished, and approximately 30,000 square feet of existing hardscapewould be removed consisting of surface lots and other paved surfaces.
§ Hotel-Restaurant Building. The hotel restaurant building would consist of a three-story,21,281-square-foot building fronting West Napa Street and would include an 80-seat groundfloor restaurant with two upper floors consisting of 20 guestrooms.
§ Main Hotel Building. The main hotel building would consist of a three-story, 44,417-square-foot building constructed around two exterior garden courtyards. This building would includea public lobby, guest reception, two upper floors consisting of 39 guestrooms, a spa with sixtreatment rooms, three first-floor accessible guestrooms, and a fitness center. Because theProject does not include residential uses, the Project requests a waiver of a residentialcomponent pursuant to Sonoma Municipal Code Section 19.10.020(B)(3).
§ First Street West Service Support Building. The 1,780-square-foot building would includethe swimming pool mechanical room, the emergency generator room, one service elevatorto the garage, a pool refreshment service counter, storage, and exit stairs.
§ Hotel Basement Parking Garage/Surface Parking. The 37,655-square-foot basementparking garage would include parking for 94 vehicles utilizing a managed valet parkingsystem, and provide other building support, such as delivery and storage space. Additionally,the Project would include 21 on-site surface parking spaces, for a total parking capacity of115.
§ Exterior Courtyard. The Project would be constructed around three exterior courtyards,including the hotel plaza courtyard, a sheltered lobby courtyard, and a raised swimming poolveranda area. The courtyards would be landscaped with raised planting beds, and tree wellswould be irrigated with captured, stored, and recycled rain water.
§ Pedestrian Circulation. The Project is planned to be pedestrian oriented by encouraginghotel guests to park their vehicles for the duration of their stay and walk or bike in andaround the Sonoma Plaza area. Guest vehicles would enter the site via West Napa Street,and drop-off would occur in an area set back from West Napa Street to avoid the potentialfor traffic back up along West Napa Street. During non-peak traffic periods, departing guestswould exit right onto West Napa Street, and during weekday evening peak traffic periods(4:00 p.m. and 6:00 p.m.) and weekend midday peak hours (12:00 noon and 2:00 p.m.)guests would depart via a one-way vehicle ramp from the parking garage onto First StreetWest.
§ Architectural Design. The Project is expected to compliment Sonoma’s vernacular styleand character by incorporating three primary Sonoma architectural patterns, including theuse of gabled thick-walled buildings parallel to the street, the creation of exterior timberarcades at the sidewalk, and overhanging sheltered roofs.
§ Sustainable LEED Certified Design. The Project would be constructed to meet Leadershipin Energy and Environmental Design (LEED) Certification requirements by incorporatingseveral sustainability components throughout construction and operation of the Hotel.
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
EXECUTIVE SUMMARY
2-5November 2019
§ Parking and Deliveries. The Project would provide a total of 115 on-site vehicle parkingspaces, consisting of 94 parking spaces in the basement parking garage, (31 of which wouldbe managed by valet staff), and 21 surface parking spaces. Parking capacity in thebasement parking garage will be maximized through the use of a combination of 90-degreestalls and stacked tandem spaces. 25 parking spaces would be available to employeesacross the street at the Bank of Marin parking lot.
Large truck deliveries would be staged from the street on First Street West, similar to howother businesses in the area receive deliveries and would be restricted to before 10 a.m.
Small truck or van deliveries would take place inside the basement parking garage at theservice core receiving area. Three service elevators are provided in the hotel to efficientlyfacilitate the vertical transfer of deliveries inside the hotel. Designation of a truck loadingzone on First Street West located adjacent to the basement parking garage entry is beingrequested as part of the Project’s Use Permit Application.
§ Landscaping. The Project proposes three exterior courtyards, including the hotel courtyardplaza, a courtyard adjoining the hotel lobby, and a courtyard where the swimming pool andspa pool are located. Additional landscaping includes street trees in raised planters alongWest Napa Street, First Street West, and throughout the Project site, as well as raisedplanter beds. In order to accommodate the Project, mature trees are proposed to beremoved; however, they would be replaced on a one-for-one basis.
§ Stormwater. The Project site would remain connected to the City’s storm drain system, andis expected to capture, store and reuse rainwater to support landscape irrigation.
§ Water Supply. Potable water will be provided to the Project site through existingconnections.
§ Sanitary Sewer Service. Sanitary sewer service would continue to be provided throughexisting connections.
§ Utilities and Services. Electricity and natural gas would be supplied to the Project site byPacific Gas & Electric (PG&E). Solid waste recycling service for the City of Sonoma isprovided by Sonoma Garbage Collectors.
2.4 SUMMARY OF ALTERNATIVES TO THE PROJECT
Chapter 6 of the 2016 Draft EIR analyzed the following alternatives to the proposed Project:
§ No Project Alternative§ No Restaurant Alternative§ Mitigated Project Alternative
Chapter 6 of the revised Draft EIR evaluates three additional alternatives, described below:
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
EXECUTIVE SUMMARY
2-6 N o v e m b e r 2 0 1 9
2.4.1 HOTEL-RESIDENTIAL (50%-50%) ALTERNATIVE
Under this alternative, the Project’s proposed building area (excluding the underground parkinggarage) of 67,478 square feet would include 50 percent as commercial and 50 percent asresidential. In order to accommodate the residential and hotel units within the proposed buildingfootprints, it is assumed that the site could accommodate 25 hotel rooms (450 square feet perroom) and 25 residential units (800 square feet average size per unit), consisting of 12 two-bedroom units and 13 one-bedroom units. Based on a project site area of 54,000 square feet (or1.24 acres),2 25 residential units would be the maximum number of units permitted under theapplicable Commercial Zoning District, which permits 20 units per acre. To meet the City’sparking standards, the underground parking garage would be expanded to add 12 additionalparking spaces. Overall, the building would be increased by 8,750 net square feet. All otherproject components would be the same as the proposed Project.
2.4.2 HOTEL/RESIDENTIAL (8 RESIDENTIAL UNITS) ALTERNATIVE
Under this alternative, eight residential units would be added to the First Street West side of thesite, where the proposed Project would provide surface parking for staff. Under this alternative,the parking garage would be expanded to accommodate an additional 12 parking spaces. Thehotel and restaurant use of the proposed Project would be maintained.
2.4.3 HOTEL ONLY ALTERNATIVE
The Hotel Only Alternative would not include the restaurant as part of the project, and thenumber of hotel rooms would be reduced to 30, resulting in a reduction of the environmentalimpacts as compared to the proposed Project.
2.5 SIGNIFICANT IMPACTS AND MITIGATION MEASURES
Under CEQA, a significant impact on the environment is defined as a substantial, or potentiallysubstantial, adverse change in any of the physical conditions within the area affected by theProject, including land, air, water, minerals, flora, fauna, ambient noise, and objects of historicand aesthetic significance.
The Project has the potential to generate significant environmental impacts in a number ofareas. Table 2-1 summarizes the conclusions of the environmental analysis contained in therevised Draft EIR and presents a summary of impacts and mitigation measures identified. It isorganized to correspond with the environmental issues discussed in Chapters 4.1 through 4.12in the 2016 Draft EIR, and the revised analysis in the revised Draft EIR. The table is arranged infour columns: 1) environmental impacts, 2) significance prior to mitigation, 3) mitigationmeasures, and 4) significance after mitigation. For a complete description of potential impacts,
2 Although the Project site is 71,000 square feet (1.63 acres) in area, because no changes are proposed to theLynch Building or Tribune Building, the affected area is limited to 54,000 square feet (1.24 acres).
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
EXECUTIVE SUMMARY
2-7November 2019
please refer to the specific discussions in Chapters 4.1 through 4.12. In some places, Table 2-1incorporates changes to the impacts and mitigation measures of the 2016 Draft EIR as a resultof the additional analysis provided in the revised Draft EIR. Revisions are shown instrikethrough and underline in Table 2-1.
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
2-8N
ov
em
be
r 20
19
TAB
LE2-1
SUM
MA
RY OF
IMPA
CTS A
ND
MITIG
ATION
MEA
SUR
ES
Impact
SignificanceW
ithoutM
itigationM
itigation Measures
SignificanceW
ithM
itigationA
ESTHETIC
SA
ES
-1: The Project w
ould notsubstantially degrade the existing visualcharacter or quality of the site and itssurroundings.
LTSN
/AN
/A
AE
S-2: The P
roject, in combination w
ithpast, present, and reasonablyforeseeable projects, w
ould result inless than significant cum
ulative impacts
with respect to aesthetics.
LTSN
/AN
/A
AIR
QU
ALITY
AIR
-1: The Project w
ould result infugitive dust generated duringconstruction activities.
SA
IR-1: The P
roject’s construction contractor shall comply
with the follow
ing BA
AQ
MD
Best M
anagement P
ractices forreducing construction em
issions of PM
10 and PM
2.5 :§
Water all active construction areas at least tw
ice daily, oras often as needed to control dust em
issions. Watering
should be sufficient to prevent airborne dust from leaving
the site. Increased watering frequency m
ay be necessaryw
henever wind speeds exceed 15 m
iles per hour.R
eclaimed w
ater should be used whenever possible.
§P
ave, apply water tw
ice daily or as often as necessary, tocontrol dust, or apply (non-toxic) soil stabilizers on allunpaved access roads, parking areas, and staging areasat construction sites.
§C
over all trucks hauling soil, sand, and other loosem
aterials or require all trucks to maintain at least tw
o feet
LTS
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
Novem
ber 2019
TAB
LE2-1
SUM
MA
RY OF
IMPA
CTS A
ND
MITIG
ATION
MEA
SUR
ES
Impact
SignificanceW
ithoutM
itigationM
itigation Measures
SignificanceW
ithM
itigationof freeboard (i.e., the m
inimum
required space between
the top of the load and the top of the trailer).§
Sw
eep daily (with w
ater sweepers using reclaim
ed water if
possible), or as often as needed, with w
ater sweepers all
paved access roads, parking areas and staging areas atthe construction site to control dust.
§S
weep public streets daily (w
ith water sw
eepers usingreclaim
ed water if possible) in the vicinity of the project
site, or as often as needed, to keep streets free of visiblesoil m
aterial.§
Hydroseed or apply non-toxic soil stabilizers to inactive
construction areas.§
Enclose, cover, w
ater twice daily, or apply non-toxic soil
binders to exposed stockpiles (dirt, sand, etc.).§
Limit vehicle traffic speeds on unpaved roads to 15 m
ph.§
Replant vegetation in disturbed areas as quickly as
possible.§
Install sandbags or other erosion control measures to
prevent silt runoff from public roadw
ays.A
IR-2: The P
roject would result in
construction-related air quality impacts
related to fugitive dust and exhaustem
issions.
SA
IR-2: Im
plementation of M
itigation Measure A
IR-1 and A
IR-
3.LTS
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
2-10N
ov
em
be
r 20
19
TAB
LE2-1
SUM
MA
RY OF
IMPA
CTS A
ND
MITIG
ATION
MEA
SUR
ES
Impact
SignificanceW
ithoutM
itigationM
itigation Measures
SignificanceW
ithM
itigationA
IR-3: The P
roject would expose
sensitive receptors to elevatedconcentrations of TA
Cs and P
M2.5 .
SA
IR-3. The construction contractor shall use construction
equipment fitted w
ith Level 3 Diesel P
articulate Filters (DP
F)for equipm
ent of 50 horsepower or m
ore. The constructioncontractor shall m
aintain a list of all operating equipment in
use on the Project site for verification by the C
ity of Sonom
aB
uilding Departm
ent official or their designee. Theconstruction equipm
ent list shall state the makes, m
odels,and num
ber of construction equipment onsite. E
quipment
shall properly service and maintain construction equipm
entin accordance w
ith the manufacturer’s recom
mendations.
The construction contractor shall also ensure that allnonessential idling of construction equipm
ent is restricted tofive m
inutes or less in compliance w
ith CA
RB
Rule 2449.
Prior to issuance of any construction perm
it, the constructioncontractor shall ensure that all construction plans subm
ittedto the C
ity of Sonoma P
lanning Departm
ent and/or Building
Departm
ent clearly show the requirem
ent for Level 3 DP
Ffor construction equipm
ent over 50 horsepower.
LTS
AIR
-4: The Project w
ould contribute tocum
ulative air quality impacts in the
SFB
AA
B.
SA
IR-4: Im
plementation of M
itigation Measure A
IR-1 and A
IR-
3.LTS
BIO
LOG
ICA
L RESO
UR
CES
BIO
-1: Implem
entation of the proposedP
roject would not have a substantial
adverse effect on special status batspecies.
LTSN
/AN
/A
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
Novem
ber 2019
TAB
LE2-1
SUM
MA
RY OF
IMPA
CTS A
ND
MITIG
ATION
MEA
SUR
ES
Impact
SignificanceW
ithoutM
itigationM
itigation Measures
SignificanceW
ithM
itigationB
IO-2: Im
plementation of the proposed
Project w
ould not contribute tocum
ulative impacts in the area related
to special status bat species.
LTSN
/AN
/A
CULTU
RA
L RESO
UR
CES
CU
LT-1: Construction of the P
rojectw
ould not alter the historicalsignificance of the Index-Tribunebuilding.. The Index-Tribune buildingw
as remodeled in 2017. Therefore, the
warehouse additions are no longer
connected to the building anddem
olition would not affect the Index-
Tribune building because the rear wall
has been rebuilt and is not historic. TheP
roject will not im
pact this façade andthis m
itigation measure is no longer
needed.
LTSN
/ALTS
CU
LT-2: Construction of the P
rojectcould adversely change the significanceof an archaeological resource.
SC
ULT-2A
: The Project shall com
ply with the follow
ingm
easures during construction of the Project:
§O
nce the surface is cleared but before thecom
mencem
ent of construction, a cultural resourcessurvey shall be com
pleted by an archaeologist who m
eetsthe S
ecretary of the Interior's professional qualificationsstandards. Additionally, lim
ited subsurface explorationsshall be com
pleted through a series of auger hole borings.
LTS
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
2-12N
ov
em
be
r 20
19
TAB
LE2-1
SUM
MA
RY OF
IMPA
CTS A
ND
MITIG
ATION
MEA
SUR
ES
Impact
SignificanceW
ithoutM
itigationM
itigation Measures
SignificanceW
ithM
itigation§
If archaeological remains are found, w
ork at the place ofdiscovery shall be halted im
mediately until a qualified
archaeologist can evaluate the finds (Section 15064.5 [f]).
- Prehistoric archaeological site indicators include:
obsidian and chert flakes and chipped stone tools; grinding and m
ashing implem
ents (e.g., slabs andhandstones, and m
ortars and pestles); bedrock outcrops and boulders w
ith mortar cups; and locally
darkened midden soils. M
idden soils may contain a
combination of any of the previously listed item
s with
the possible addition of bone and shell remains, and
fire affected stones.- H
istoric period site indicators generally include:fragm
ents of glass, ceramic, and m
etal objects; milled
and split lumber; and structure and feature rem
ains such as building foundations and discrete trashdeposits (e.g., w
ells, privy pits, dumps).
§If archaeological rem
ains are found and judged potentiallysignificant, a treatm
ent plan shall be developed andexecuted.
§A
ll cultural materials recovered as part of the H
otelS
onoma project shall be subject to scientific analysis and
a report prepared according to current professionalstandards.
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
Novem
ber 2019
TAB
LE2-1
SUM
MA
RY OF
IMPA
CTS A
ND
MITIG
ATION
MEA
SUR
ES
Impact
SignificanceW
ithoutM
itigationM
itigation Measures
SignificanceW
ithM
itigationC
ULT-2B
: If any prehistoric or historic subsurface culturalresources are discovered during ground-disturbing activities,all w
ork within 50 feet of the resources shall be halted and a
qualified archaeologist shall be consulted to assess thesignificance of the find according to C
EQ
A Guidelines
Section 15064.5. If any find is determ
ined to be significant,representatives from
the City and the archaeologist w
ouldm
eet to determine the appropriate avoidance m
easures orother appropriate m
itigation. All significant cultural m
aterialsrecovered shall be, as necessary and at the discretion of theconsulting archaeologist, subject to scientific analysis,professional m
useum curation, and docum
entationaccording to current professional standards In consideringany suggested m
itigation proposed by the consultingarchaeologist to m
itigate impacts to historical resources or
unique archaeological resources, the City shall determ
inew
hether avoidance is necessary and feasible in light offactors such as the nature of the find, P
roject design, costs,and other considerations. If avoidance is infeasible, otherappropriate m
easures (e.g., data recovery) would be
instituted. Work m
ay proceed on other parts of the Project
site while m
itigation for historical resources or uniquearchaeological resources is being carried out.
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
2-14N
ov
em
be
r 20
19
TAB
LE2-1
SUM
MA
RY OF
IMPA
CTS A
ND
MITIG
ATION
MEA
SUR
ES
Impact
SignificanceW
ithoutM
itigationM
itigation Measures
SignificanceW
ithM
itigationC
ULT-3: C
onstruction of the Project
could directly destroy a uniquepaleontological resource or site orunique geologic feature.
SC
ULT-3: In the event that fossils or fossil-bearing deposits
are discovered during construction, excavations within 50
feet of the find shall be temporarily halted or diverted. The
contractor shall notify a qualified paleontologist to examine
the discovery. The paleontologist shall document the
discovery as needed, in accordance with S
ociety ofVertebrate P
aleontology standards (Society of VertebrateP
aleontology 1995), evaluate the potential resource, andassess the significance of the find under the criteria set forthin C
EQ
A Guidelines
Section 15064.5. The paleontologist
shall notify the appropriate agencies to determine
procedures that would be follow
ed before construction isallow
ed to resume at the location of the find. If the P
rojectproponent determ
ines that avoidance is not feasible, thepaleontologist shall prepare an excavation plan for m
itigatingthe effect of the P
roject based on the qualities that make the
resource important. The plan shall be subm
itted to the City
for review and approval prior to im
plementation.
LTS
CU
LT-4: The Project w
ould not disturbany hum
an remains, including those
interred outside of formal cem
eteries.
LTSN
/AN
/A
CU
LT-5: The Project, in com
binationw
ith past, present, and reasonablyforeseeable projects, w
ould not result inless than significant cum
ulative impacts
with respect to aesthetics.
LTSN
/AN
/A
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
Novem
ber 2019
GEO
LOG
Y, SOILS, A
ND
SEISMIC
ITYG
EO
-1: The Project w
ould not exposepeople or structures to potentialsubstantial adverse effects, includingthe risk of loss, injury, or death involvingstrong seism
ic ground shaking.
LTSN
/AN
/A
GE
O-2: The P
roject, in combination w
ithpast, present, and reasonablyforeseeable projects, w
ould result inless than significant cum
ulative impacts
with respect to geology, soils, and
seismicity.
LTSN
/AN
/A
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
2-16N
ov
em
be
r 20
19
GR
EENHO
USE G
AS EMISSIO
NS
GH
G-1: The P
roject would not generate
greenhouse gas emissions either
directly or indirectly, that may have a
significant impact on the environm
ent.
LTSThe H
otel Sonom
a includes building to LEE
D standards. To
ensure that the Project shall com
plete the LEE
D application
process and achieve LEE
D certification, conditions of
approval shall require that prior to the issuance of acertificate of occupancy, LE
ED
strategies used in the Project
shall be at a level sufficient to reduce overall annual energydem
and of the Project by at least 32 percent com
pared to aversion of the P
roject that does not include these LEE
Dstrategies. The P
roject, once designed, shall provide arevised em
ission estimate that factors in the G
HG
emissions
reductions associated with the selected LE
ED
measures. If
necessary, to demonstrate that G
HG
emissions are
consistent with the S
tate’s legislative mandate for 2030, the
Project shall im
plement additional reduction strategies,
which m
ay include the use of verifiable offsets, and am
onitoring mechanism
consistent with recom
mendations of
CE
QA
Guidelines S
ection 15183.5 for GH
G reduction
programs. The C
ity will require that the P
roject comply w
ithapplicable G
HG
reduction strategies necessary todem
onstrate GH
G em
issions that would be consistent w
iththe S
tate’s emission targets for 2030.
.
LTS
GH
G-2: The P
roject, in combination
with past, present, and reasonably
foreseeable projects, would result in
less than significant cumulative im
pactsw
ith respect to GH
G em
issions.
LTSW
ith the design features, location, and mitigation included
as a part of the Project D
escription and EIR
, and theconditions of approval, the P
roject’s emissions w
ill beconsistent w
ith State guidance on G
HG
emissions
reductions. The City has dem
onstrated that the Project w
illbe consistent w
ith the State legislative fram
ework that, in
California, has been established for assessing the
cumulative significance of G
HG
emissions im
pacts
LTS
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
Novem
ber 2019
HYD
RO
LOG
Y AN
D W
ATER Q
UA
LITYH
YDR
O-1: The P
roject would not
substantially deplete groundwater
supplies or interfere substantially with
groundwater recharge such that there
would be a net deficit in aquifer volum
eor a low
ering of the local groundwater
table level (e.g. the production rate ofpre-existing nearby w
ells would not drop
to a level which w
ould not supportexisting land uses or planned uses forw
hich permits have been granted).
LTSN
/AN
/A
HYD
RO
-2: The Project, in com
binationw
ith past, present, and reasonablyforeseeable projects, w
ould not result insignificant cum
ulative impacts w
ithrespect to hydrology and w
ater quality.
LTSN
/AN
/A
NO
ISEN
OIS
E-1: The P
roject would expose
people to or generate noise levels inexcess of standards established in theG
eneral Plan and/or the applicable
standards of other agencies.
SN
OIS
E-1: P
rior to obtaining building permits, the Project
applicant shall submit an acoustic study to the satisfaction of
the City planning director to ensure that the P
roject includesdesign features to m
eet the 45 dBA C
NE
L noise standard atall hotel room
s. The noise study shall estimate the future
long-range noise levels at the building façade and calculatethe exterior to interior noise reduction at all hotel room
sbased on specific construction plans including grading plans,building footprints and architectural plans. The study shalldescribe specific w
indows and w
all assemblies design and
materials so all hotel room
s meet the 45 dbA C
NEL noise
standard due to exterior noise sources. The projectapplicant/developer shall im
plement all recom
mended
design features.
LTS
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
2-18N
ov
em
be
r 20
19
NO
ISE
-2: Implem
entation of the Project
could result in the exposure of personsto or generation of excessivegroundborne vibration during portions ofproject construction.
SN
OIS
E-2: D
uring site preparation, demolition, and
construction activities , the following controls to reduce
potential vibration impacts shall be im
plemented:
§The use of vibratory rollers w
ould be prohibited. Theconstruction contractor shall identify alternative soilcom
paction methods such as static rollers.
§To the extent possible, the constructor contractor shallutilize sm
all- to medium
-sized bulldozers would produce
less vibration than using large bulldozers.§
To the extent possible, vibration-intense constructionactivities should take place during tim
es when nearby
sensitive receptors, such as hotels, meeting room
s, andresidences are at their low
est utilization/occupancy.§
Prior to the issuance of building perm
its the applicantand/or construction contractor shall inspect and report onthe current structural condition of the existing buildingsw
ithin 50 feet from w
here vibratory rollers, largebulldozers, and the like w
ould be used.§
During construction, if any vibration levels cause cosm
eticor structural dam
age to existing buildings in closeproxim
ity to a project site, the applicant shall imm
ediatelyissue “stop-w
ork” orders to the construction contractor toprevent further dam
age. Work shall not restart until the
building is stabilized and/or preventive measures are
implem
ented to relieve further damage to the building(s).
With im
plementation of the m
itigation measures listed
above, the Project w
ould reduce potential vibration impacts
to less than significant levels.
LTS
NO
ISE
-3: Implem
entation of the Project
would not result in a substantial
permanent increase in traffic noise
levels in the vicinity of the Project site
above levels existing without the
Project.
LTSN
/AN
/A
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
Novem
ber 2019
NO
ISE
-4: Construction activities
associated with buildout of the P
rojectw
ould result in substantial temporary or
periodic increases in ambient noise
levels in the vicinity of the Project site
above existing levels.
SN
OIS
E-4: The P
roject shall implem
ent the following
measures.§
Construction equipm
ent shall be well m
aintained and usedjudiciously to be as quiet as practical. E
quipment and
trucks used for project construction shall utilize the bestavailable noise control techniques (e.g., im
provedm
ufflers, equipment redesign, use of intake silencers,
ducts, engine enclosures, and acoustically attenuatingshields or shrouds), w
herever feasible;§
Utilize “quiet” m
odels of air compressors and other
stationary noise sources where such technology exists.
Select hydraulically- or electrically-pow
ered equipment
and avoid pneumatically pow
ered equipment w
herefeasible. Im
pact tools (e.g., jack hamm
ers, pavement
breakers, and rock drills) used for project demolition or
construction shall be hydraulically or electrically powered
wherever possible to avoid noise associated w
ithcom
pressed air exhaust from pneum
atically powered
tools. How
ever, where use of pneum
atic tools isunavoidable, an exhaust m
uffler on the compressed air
exhaust shall be used. Quieter procedures shall be used,
such as drills rather than impact equipm
ent, whenever
such procedures are available and consistent with
construction procedures;§
Locate stationary noise-generating equipment as far as
possible from sensitive receptors that adjoin construction
sites. Construct tem
porary noise barriers or partialenclosures to acoustically shield such equipm
ent where
feasible;§
Prohibit unnecessary idling of internal com
bustionengines;
§P
rior to initiation of on-site construction-related demolition
or earthwork activities, a m
inimum
12-foot-high temporary
sound barrier shall be erected along the Project property
LTS
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
2-20N
ov
em
be
r 20
19
line abutting adjacent operational businesses, residencesor other noise-sensitive land uses. These tem
porarysound barriers shall be constructed w
ith sound shieldingproperties and shall be constructed so that vertical orhorizontal gaps are elim
inated. These temporary barriers
shall remain in place through the construction phase in
which heavy construction equipm
ent, such as excavators,dozers, scrapers, loaders, rollers, pavers, and dum
ptrucks, are operating w
ithin 50 feet of the edge of theconstruction site by adjacent sensitive land uses. Thism
easure could lower construction noise levels at adjacent,
ground-floor residential units by up to 8 dB, depending on
topography andsite conditions;
§To the m
aximum
extent feasible, route construction-related traffic along m
ajor roadways and aw
ay fromsensitive receptors;
§N
otify all businesses, residences or other noise-sensitiveland uses w
ithin 500 feet of the perimeter of the
construction site of the construction schedule in writing
prior to the beginning of construction and prior to eachconstruction phase change that could potentially result ina tem
porary increase in ambient noise levels in the
Project vicinity;§
Signs shall be posted at the construction site that include
permitted construction days and hours, a day and evening
contact number for the job site, and a day and evening
contact number for the on-site com
plaint and enforcement
manager, and the C
ity’s Building Official, in the event of
problems;
§A
n on-site complaint and enforcem
ent manager shall be
available to respond to and track complaints. The
manager w
ill be responsible for responding to anycom
plaints regarding construction noise and forcoordinating w
ith the adjacent land uses. The manager
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
Novem
ber 2019
will determ
ine the cause of any complaints (e.g., starting
too early, bad muffler, etc.) and coordinate w
ith theconstruction team
to implem
ent effective measures
(considered technically and economically feasible)
warranted to correct the problem
. The telephone number
of the coordinator shall be posted at the construction siteand provided to neighbors in a notification letter. Them
anager shall notify the City’s B
uilding Official of all
complaints w
ithin 24 hours. The manager w
ill be trained touse a sound level m
eter and should be available during allconstruction hours to respond to com
plaints; and§
A pre-construction meeting shall be held w
ith the Building
Official and the general contractor/on-site project m
anagerto confirm
that noise measures and practices (including
construction hours, neighborhood notification, postedsigns, etc.) are fully operational.
The above mitigation m
easures shall be identified inconstruction contracts and acknow
ledged by the contractor.N
OIS
E-5: This P
roject, in combination
with past, present, and reasonably
foreseeable projects, would result in
less than significant impacts w
ithrespect to noise.
LTSN
/AN
/A
PUB
LIC SER
VICES
PS
-1: The proposed Project w
ould notresult in the need for new
or physicallyaltered fire protection facilities, theconstruction of w
hich could causesignificant environm
ental impacts, in
order to maintain acceptable service
ratios, response times or other
performance objectives.
LTSN
/AN
/A
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
2-22N
ov
em
be
r 20
19
PS
-2: The proposed Project, in
combination w
ith past, present andreasonably foreseeable projects, w
ouldresult in less than significant cum
ulativeim
pacts with respect to fire protection
services.
LTSN
/AN
/A
PS
-3: The proposed Project w
ould notrequire expanded facilities, theconstruction of w
hich could causesignificant environm
ental impacts, in
order to maintain acceptable service
ratios, response times, or other
performance objectives for police
services.
LTSN
/AN
/A
PS
-4: The proposed Project, in
combination w
ith past, present andreasonably foreseeable projects, w
ouldresult in less than significant cum
ulativeim
pacts with respect to police services.
LTSN
/AN
/A
TRAN
SPOR
TATION
AN
D TR
AFFICTR
AN
S-1: The P
roject would not
conflict with an applicable plan,
ordinance, or policy establishingm
easures of effectiveness for theperform
ance of the circulation system,
taking into account all modes of
transportation, including mass transit,
non-motorized travel, and relevant
components of the circulation system
,including, but not lim
ited to,intersections, streets, highw
ays andfreew
ays, pedestrian and bicycle paths,and m
ass transit.
LTSN
/AN
/A
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
Novem
ber 2019
TRA
NS
-2: The Project could potentially
increase VM
T and, while specific
standards have not been set, as theim
pact could potentially be significant,m
easures to reduce VM
T shall beim
plemented as a condition of approval
the Project
PS
The Project shall pay its fair share of Im
provements to the
intersection of West N
apa Street/First S
treet West, identified
by the City of S
onoma as part of the G
eneral Plan U
pdateprocess, and the S
ystemic Safety R
eport (March 2019) and
which m
ay include including curb extensions, stripingm
odifications, and enhanced signing /or other similar
facilities, should construct in conjunction with by the P
rojectidentified as approxim
ately $6,238 at the time of building
permit
LTS
TRA
NS
-3: The Project w
ould not resultin a change in air traffic patterns,including either an increase in trafficlevels or a change in location thatresults in substantial safety risks.
LTSN
/AN
/A
TRA
NS
-4: The Project w
ould notincrease hazards due to a designfeature (e.g., sharp curves or dangerousintersections) or incom
patible uses(e.g., farm
equipment).
LTSN
/AN
/A
TRA
NS
-5: The Project w
ould not resultin inadequate em
ergency access.LTS
N/A
N/A
TRA
NS
-6A: The P
roject would add
pedestrian trips to an intersection thathas been identified by the C
ity’s TrafficC
omm
ittee as needing improvem
ents toaccom
modate pedestrian travel safely
and efficiently.
STR
AN
S-6A
: The following shall be im
plemented:
§The P
roject shall pay its fair share of Improvem
ents to theintersection of W
est Napa S
treet/First Street W
est,identified by the C
ity of Sonom
a as part of the General
Plan U
pdate process, and the System
ic Safety Report
(March 2019) including curb extensions, striping
modifications, and enhanced signing by the P
rojectidentified as approxim
ately $6,238.§
LTS
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
2-24N
ov
em
be
r 20
19
TRA
NS
-6B: The P
roject would generate
bicycle trips on adjacent streets.LTS
TRA
NS
-6B: The follow
ing shall be implem
ented:§
Bicycle storage facilities should be provided on-site as
proposed.§
Should the project include any changes to the existing
frontage on West N
apa Street, such changes m
ustaccom
modate planned future bike lanes.
LTS
TRA
NS
-7: The Project w
ould addvehicular and pedestrian trips to W
estN
apa Street/Fifth S
treet West
intersection that is expected to operatedeficiently at LO
S E
during the weekday
peak period.
STR
AN
S-7: The follow
ing shall be implem
ented:Im
provements identified by the C
ity of Sonom
a through theG
eneral Plan C
irculation Elem
ent update process include asouthbound right-turn lane w
ith a signal timing m
odificationto include an overlap betw
een the southbound right turn(from
5th S
treet West onto W
est Napa S
treet) and eastboundleft turn (from
West N
apa Street onto 5
th Street W
est) at theW
est Napa/5
th Street W
est intersection. the project’sequitable share tow
ards these improvem
ents, either througha proportional share
fee of 1.1 percent of the $338,000estim
ated cost identified in the City’s S
ystemic S
afetyA
nalysis Final Am
ended Report, or city fees, shall be
collected at the time of building perm
it.
LTS
UTILITIES AN
D SER
VICE SYSTEM
SU
TIL-1: The Project w
ould havesufficient w
ater supplies available toserve the project from
existingentitlem
ents and resources, or new or
expanded entitlements needed.
LTSN
/AN
/A
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
Novem
ber 2019
UTIL-2: The P
roject would not require or
result in the construction of new w
atertreatm
ent facilities or expansion ofexisting facilities, the construction ofw
hich could cause significantenvironm
ental effects.
LTSN
/AN
/A
UTIL-3: Im
plementation of the P
roject,in com
bination with past, present, and
reasonably foreseeable projects, would
not result in a significant cumulative
impacts w
ith respect to water supply or
services.
LTSN
/AN
/A
UTIL-4: The project w
ould not exceedw
astewater treatm
ent requirements of
the applicable Regional W
ater Quality
Control B
oard.
LTSN
/AN
/A
UTIL-5: The project w
ould not require orresult in the construction of neww
astewater treatm
ent facilities orexpansion of existing facilities, theconstruction of w
hich could causesignificant environm
ent effects.
LTSN
/AN
/A
UTIL-6: C
onstruction of the proposedP
roject would adversely affect the
carrying capacity of the sanitary sewer
system.
SU
TIL-6: The Project Applicant shall coordinate w
ith theS
onoma Valley C
ounty Sanitation D
istrict (SVC
SD
) toupgrade the capacity of the local sanitation collectionsystem
, such that the additional flows generated by the
project shall be fully accomm
odated, specifically during peakw
et weather flow
s. This shall be accomplished using one of
the following m
eans, or combination thereof, of w
hich thefinal determ
ination of the means to use shall be at the
discretion of the SV
CS
D:
§P
ayment of In-Lieu Fee: The P
roject Applicant shall pay
an in-lieu fee into the SV
CS
D W
ater Conservation
Program
, specifically, the Direct Installation P
lumbing
LTS
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
2-26N
ov
em
be
r 20
19
Program
, which prom
otes the installation of high efficiencyplum
bing fixtures (toilets, urinals, faucet aerators,show
erheads) for SV
CS
D com
mercial and residential
customers. The am
ount of the fee, which shall be
determined by the S
VC
SD
, shall be sufficient to fundidentified conservation m
easures within the collection
system area that w
ould offset flows generated by the
project (38.44 ESD
).§
Holding Tank: The P
roject Applicant shall install a holdingtank if needed, near the dow
nstream end of the new
on-site sew
er service lateral. The tank is to be sized to storea m
inimum
of 8 hours of wastew
ater originating from the
project and discharge at a rate and time approved by
SV
CS
D. The final calculations for the required size to
accomm
odate 8 hours of storage shall be verified duringplan check. D
esign details shall be established duringplan check, and the tank shall be installed and operationalprior to occupancy of the P
roject site. The Project
Applicant shall develop an operations and m
aintenanceplan for the holding tank to ensure that the holding tankoperates correctly and leaks are prevented or repaired.
To address any potential secondary impacts, all standard
construction provisions that apply to the project shall be met,
including compliance w
ith the noise ordinance, traffic safetyprovisions (flaggers and signage), and storm
water control to
protect water quality.
Com
pletion of improvem
ent or implem
entation ofconservation m
easures shall be required prior to finaloccupancy of the project. Enforcem
ent Responsibility;
Sonoma Valley C
ounty Sanitation District, C
ity Engineer; C
ity of Sonom
a Public W
orks Departm
ent.
HO
TEL P
RO
JE
CT S
ON
OM
A R
EV
ISE
D F
INA
L E
IRC
ITY O
F S
ON
OM
A
EXECUTIVE SUM
MA
RY
Novem
ber 2019
UTIL-7: D
evelopment of the project
would adversely affect capacity of the
sewer conveyance system
that servesthe project site.
SU
TIL-7: Implem
ent Mitigation M
easure UTIL-6.
LTS
UTIL-8: Im
plementation of the P
rojectw
ould result in an increase in energyconsum
ption.
LTSN
/AN
/A
UTIL-9: The proposed P
roject would not
contribute to cumulative natural gas and
electrical service demands.
LTSN
/AN
/A
LAN
D U
SE AND
PLAN
NING
LU-1: The P
roject would not conflict w
ithany applicable land use plan, policy, orregulation adopted for the purpose ofavoiding or m
itigating an environmental
effect.
LTSN
/AN
/A
LU-2: The P
roject, in combination w
ithpast, present, and reasonablyforeseeable projects, w
ould result inless-than-significant cum
ulative impacts
with respect to land use and planning.
LTSN
/AN
/A
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
EXECUTIVE SUMMARY
2-28 N o v e m b e r 2 0 1 9
This page intentionally blank
November 2019 3-1
3. Revisions to the Revised Draft EIR
This chapter presents text revisions to the revised Draft EIR that have been made in responseto public and agency comments, as well as staff-directed changes. These text revisions includetypographical corrections, insignificant modification, amplifications and clarifications of therevised Draft EIR. In each case, the revised page and location on the page is presented,followed by the textual, tabular, or graphical revision. Underline text represents language thathas been added to the EIR; text with strikethrough has been deleted from the EIR.
None of the revisions constitutes significant new information as defined in CEQA GuidelinesSection 15088.5; therefore, this EIR does not need to be recirculated.
REVISIONS TO CHAPTER 1, EXECUTIVE SUMMARY
Page 1-5 of the revised Draft EIR is hereby amended as follows:
1.4.1 HOTEL-RESIDENTIAL (50%-50%) ALTERNATIVE
Under this alternative, the Project’s proposed building area (excluding the underground parkinggarage) of 67,478 square feet would include 50 percent as commercial and 50 percent asresidential. The proposed restaurant would be removed. In order to accommodate theresidential and hotel units within the proposed building footprints, it is assumed that the sitecould accommodate 25 hotel rooms (450 square feet per room) and 25 residential units (800square feet average size per unit), consisting of 12 two-bedroom units and 13 one-bedroomunits. ….
Page 1-16 of the revised Draft EIR is herby amended as follows: Table 1-1
Impact Significance withoutmitigation
Mitigation Measure Significant withMitigation
TRANS-6A theproject would addpedestrian trips to anintersection that hasbeen identified by the
SThe Project shall payits fair share ofImprovements to theintersection of WestNapa Street/FirstStreet West,
LTS
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
REVISIONS TO THE REVISED DRAFT EIR
3-2 N O V E M B E R 2 0 1 9
City’s TrafficCommittee asneedingimprovements toaccommodatepedestrian travelsafely and efficiently.
identified by the Cityof Sonoma as part ofthe General PlanUpdate process, andthe Systemic SafetyReport (March 2019)and which mayinclude includingcurb extensions,stripingmodifications, andenhanced signing /orother similar facilities,should construct inconjunction with bythe Project identifiedas approximately$6,238 at the time ofbuilding permit
Trans-7: the projectwould add vehicularand pedestrian tripsto West NapaStreet/Fifth StreetWest intersectionthat is expected tooperate deficiently atLOS E during theweekday peakperiod.
SImprovementsidentified by the Cityof Sonoma throughthe General PlanCirculation Elementupdate processinclude a southboundright-turn lane with asignal timingmodification toinclude an overlapbetween thesouthbound right turn(from 5th Street Westonto West NapaStreet) andeastbound left turn(from West NapaStreet onto 5th StreetWest) at the WestNapa/5th Street Westintersection. theproject’s equitableshare towards theseimprovements, eitherthrough aproportional share
N/A
LTS
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
REVISIONS TO THE REVISED DRAFT EIR
November 2019 3-3
fee of 1.1 percent ofthe $338,000estimated costidentified in the City’sSystemic SafetyAnalysis FinalAmended Report, orcity fees, shall becollected at the timeof building permit.
REVISIONS TO CHAPTER 3, PROJECT DESCRIPTION
Page 3-13 insert a new third paragraph:
The Project Applicant has offered the following to reduce delivery issues:
· Limiting deliveries on First Street West to before 10 a.m.· Prohibiting full size buses from passenger pick up or drop off at the hotel auto court,· Prohibiting idling in hotel driveways· Requiring exiting traffic to use the First Street West exit during peak hours
Page 3-13, Landscaping paragraph of the revised Draft EIR is hereby amended as follows:
Although mature trees are proposed to be removed, oak trees, they shall be replaced ona two-for-one basis, and remaining trees would be replaced on a one-for-one basis,either onsite or through a City sponsored in lieu payment to support tree plantingelsewhere within the City, consistent with or exceeding the requirements of the treeordinance contained in the Sonoma Municipal Code chapter 12.08.
Page 3-16, 3.6.1 Required Permits and Approvals is hereby amended to include the followingbullet:
· Any sign or work within Caltrans Right of Way would require an encroachment permitprior to construction.
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
REVISIONS TO THE REVISED DRAFT EIR
3-4 N O V E M B E R 2 0 1 9
REVISIONS TO CHAPTER 4.4, CULTURAL RESOURCES
Since the original Draft EIR circulated, there has been a change in circumstance to the existingsite. On April 14, 2016, the Sonoma Planning Commission approved the reconstruction of theIndex-Tribune building including the addition of a second floor. The remodel was also reviewedby the City of Sonoma Design Review and Historic Preservation Commission. The applicationincluded a March 24, 2016 study by Page and Turnbull analyzing the historic resources impactsresulting from improvements to the Index-Tribune building. The analysis found that theimprovements maintained the character defining features on the front façade of the building andthe total reconstruction of the side and rear walls would not impair the historic nature of thestructure. The rear (south) elevation was completely demolished and rebuilt with a newconcrete two story wall. The remodel was later issued all required permits and was completedin 2017. The rear (south) elevation was completely demolished and rebuilt with a new concretetwo story wall. Upon the demolition of the warehouse, the owner of the Index-Tribune buildingwill stucco the rear elevation to match the other walls of the building. For this reason, theMitigation Measure CULT-1 is no longer required, since the Hotel Project would not impact thenew rear wall.
Page 4.4-10, 2nd paragraph of the revised Draft EIR is amended as follows:
Implementation of the Project would result in the demolition of the warehouse additions.However, improvements to the Index-Tribune building have already occurred. Therefore,the warehouse additions are no longer connected to the building and demolition wouldnot affect the Index-Tribune building because the rear wall has been rebuilt and is nothistoric. Since the warehouse additions are currently connected to the Index-Tribunebuilding if once the warehouse additions are demolished, the southern elevation of themain building is not re-constructed in accordance with the Secretary of the InteriorsStandards for the Treatment of Historic Properties, the character defining features couldbe substantially altered. As a result a significant impact would occur. As a result,implementation of the proposed Project would have no potential to alter the historicsignificance of the Index-Tribune Building and Mitigation Measure CULT-1 is no longerrequired. It is recommended that the following measure be deleted:
Mitigation Measure CULT-1: To ensure the Index-Tribune building retains its historicalsignificance, the design of the altered rear (south) elevation after demolition of thewarehouse additions shall conform to the Secretary of the Interior’s Standards forRehabilitation. A consultant who meets the Secretary of the Interior’s ProfessionalQualification Standards for Historic Architecture shall prepare a report on conformanceof the design to the secretary’s Standard. The report and the architectural drawings andspecifications for shall be reviewed by the Planning Department and PlanningCommission to confirm conformance before final planning approval is granted.
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
REVISIONS TO THE REVISED DRAFT EIR
November 2019 3-5
REVISIONS TO CHAPTER 4.10, TRANSPORTATION AND TRAFFIC
Page 4.10-23 of the revised Draft EIR is modified as follows:
Mitigation Measure Trans-2: The hotel operator shall provide transit passes for employeeswilling to travel to work by bus, allow employees to work virtually if feasible for their jobclassification: The Project Applicant (or Project site operator) shall submit a VMT StrategyReport, prior to occupancy, of measures the Hotel shall implement once the Project isoperational, to reduce VMT from the baseline determined in the revised Final EIR. After theProject has been operational for six months, a report shall verify the reductions have beenachieved. If the reductions in VMT of 15% are not demonstrated in the report, theOwner/Operator shall implement additional strategies from Table 4-6 of the revised FinalEIR. The Project Applicant or operator shall submit an annual report to the City for the firstthree years demonstrating the efficacy of the selected TDM strategies in achieving the identifiedVMT reduction goal and proposing modifications as required to achieve the required VMTreduction goal. Compliance shall be monitored by the City.
Page 4.10-26 of the revised Draft EIR is modified as follows to clarify the distribution of projecttrips.
Conditions with project-generated trips added to existing volumes, as well as safetycriteria were reviewed in evaluating the need for turn lanes at the project driveway onWest Napa Street. It was conservatively assumed that all the traffic coming from the eastand north would enter via the driveway, and further that all site-generated traffic woulduse the project driveway, though some trips would be oriented to the parking lot on thenorth side of West Napa Street. For the trips routed from the south on First Street Westto access the driveway on West Napa Street, a restricted left-turn would be required andwas therefore not assumed. Given the turn restriction at West Napa Street, driversdestined for the parking lot that would take access from First Street West would beexpected to arrive from the south; as these trips would not include travel on West NapaStreet and would not result in a left turn at the driveway, they are therefore not includedin the left-turn lane warrant analysis.
Page 4.10-29 of the revised Draft EIR is hereby amended as follows:
Truck Access
The potential for delivery activity to impact operation of First Street West was consideredin light of the planned delivery schedule. It is understood that many of the vendors forthe restaurant already deliver food and beverages to the Red Grape Restaurant andother restaurants in the vicinity, so such deliveries would result in no change fromexisting conditions. Information provided by the Project Applicant indicates that theyanticipate generating 15 deliveries per week specific to their project, or an average ofjust more than two per day. Most of these deliveries will be in 14-foot box trucks or vans,
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
REVISIONS TO THE REVISED DRAFT EIR
3-6 N O V E M B E R 2 0 1 9
vehicles of a size that are routinely encountered in the area and would be consideredappropriate on even a local residential street, though and First Street West is designatedas a collector local street in the Circulation Element of the City’s General Plan. Onevendor uses a semi-truck and trailer for deliveries and this would result in two deliveriesper week, or a total of four trips by trucks larger than a box truck.
The segment of First Street West between West Napa Street and West MacArthur Streetcarries approximately 1,200 vehicles per day, including about 115 vehicles in bothdirections during the p.m. peak hour. The project would be responsible for 52 daily tripson this segment, some of which already occur due to existing businesses that will bereplaced with the Project. However, even if all 52 daily trips were new trips, the roadwaywould have a volume of approximately 1,250 daily trips, which is well below the industry-standard of 2,000 trips per day at which the residential character of a street begins tobreak down.
Given the limited number of additional truck trips, their scheduling during the earlymorning hours when traffic is generally light, and the volume that is well below thethreshold indicating a change in character for local streets, designation of First StreetWest as a collector street, which has a purpose of linking arterials to local streets andcommercial and public destinations, the impact due to delivery activity is expected to beless-than-significant.
Page 4.10-30 of the revised Draft EIR is hereby amended as follows:
The existing network of sidewalks are generally adequate to serve pedestrian trafficassociated with the proposed Sonoma Hotel, though modifications are needed at theadjacent intersection of West Napa Street/First Street West to safely serve the additionalpedestrians that would be generated by the project, including employees traveling to andfrom the off-site parking lot. This intersection, which provides the most direct pedestrianconnection between the site and Downtown destinations, also encounters highpedestrian crossing volumes during busy periods, resulting in high crosswalk use thattends to create traffic congestion along West Napa Street. Based on these factors, thisintersection was identified as a “hot spot” in the City’s 2003 Traffic Calming Plan, whichrecommended that curb extensions be considered as a means of increasing pedestrianvisibility and reducing crossing distances. Preliminary concepts for reducing the crossingdistance and improving pedestrian/bicycle access at West Napa Street/First Street Westare currently under consideration by City staff. Figure 4.10-7 shows a potentialconceptual design for the intersection that includes bulb-outs. The design of the curbextensions at the intersection of First Street West/West Napa Street should must be inconformance with applicable design standards and City policies; be consistent withpotential future bicycle improvements; and take into account potential impacts on truckmovements, as well as the potential to adversely affect the operation of the intersectionby reducing vehicle speeds or by causing increased delays at the stop-sign controlledlegs.
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
REVISIONS TO THE REVISED DRAFT EIR
November 2019 3-7
Page 4.10-31, Figure 4.10-7, is revised as shown on the following page to include three newfigures (Figure 4.10-7, 4.10-7a and 4.10-7b) showing the conceptual layout of bulb-outs.
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
REVISIONS TO THE REVISED DRAFT EIR
3-8 N O V E M B E R 2 0 1 9
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
REVISIONS TO THE REVISED DRAFT EIR
November 2019 3-9
Figure 4.10-7a Commercial Truck Access
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
REVISIONS TO THE REVISED DRAFT EIR
3-10 N O V E M B E R 2 0 1 9
Figure 4.10-7b Firetruck Access
[new figure]
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
REVISIONS TO THE REVISED DRAFT EIR
November 2019 3-11
Page 4.10-32, Mitigation Measure TRANS-6A, of the revised Draft EIR is hereby amendedas follows:
Mitigation Measure TRANS-6A: The following shall be implemented:
§ The Project shall pay its fair share of Improvements to the intersection of West NapaStreet/First Street West, identified by the City of Sonoma as part of the General PlanUpdate process, and the Systemic Safety Report (March 2019) and which may includeincluding curb extensions, striping modifications, and enhanced signing /or other similarfacilities, should construct in conjunction with by the Project at the time of buildingpermit identified as approximately $6,238.
The funds will be retained in an account specifically for construction of the identifiedimprovements. The amount to be contributed by the hotel project is just 1.1% of the totalestimated cost. The remaining funds for construction would be based on City-wide priorities forproject funding.
Page 4.10-36, Table 4.10-11, is hereby amended as follows:
TABLE 4.10-11 SUMMARY OF FUTURE AND FUTURE PLUS PROJECT PEAK HOUR INTERSECTIONLEVEL OF SERVICE CALCULATIONS
Study Intersection
Approach
Future Conditions Future plus Project ConditionsPM Peak Midday Peak PM Peak Midday Peak
Delay LOS Delay LOS Delay LOS Delay LOS1. W Spain St/FirstSt W 29.9 D 26.7 D 30.2 D 26.9 D
2. W Napa St/FifthSt W 61.7 E 44.6 D 61.9
(+0.2)E 44.9 D
Mitigated (add’lSB RT lane,phasing changes)
49.7 D 34.0 C 49.8 D 34.1 C
3. W NapaSt/Second St W 40.3 D 29.2 C 40.6 D 29.4 C
4. W Napa St/FirstSt W* 55.2 F 45.7 E 58.3
(+3.1)F 48.7
(+3.0)E
NorthboundApproach 11.3 B 12.0 B 11.4 B 12.2 B
SouthboundApproach 11.6 B 13.2 B 11.6 B 13.3 B
5. NapaSt/Broadway 80.7 F 36.5 E 82.2
(+1.5)F 38.2
(+1.7)E
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
REVISIONS TO THE REVISED DRAFT EIR
3-12 N O V E M B E R 2 0 1 9
TABLE 4.10-11 SUMMARY OF FUTURE AND FUTURE PLUS PROJECT PEAK HOUR INTERSECTIONLEVEL OF SERVICE CALCULATIONS
Study Intersection
Approach
Future Conditions Future plus Project ConditionsPM Peak Midday Peak PM Peak Midday Peak
Delay LOS Delay LOS Delay LOS Delay LOS6. E Napa St/First StE 19.8 C 22.4 C 20.1 C 22.7 C
Notes: Delay is measured in average seconds per vehicle; LOS = Level of Service; Results for minor approaches to two-way stop-controlled intersection are indicated in italics; Boldtext indicates unacceptable operation* Average for intersection based on analysis as if all-way stop-controlled.Source: W-Trans 2018.
Mitigation Measure TRANS-7: Page 4.10-37 is amended as follows:
§ Improvements identified by the City of Sonoma through the General Plan CirculationElement Update process include a southbound right-turn lane with a signal timingmodification to include an overlap between the southbound right turn (from 5th StreetWest onto West Napa Street) and eastbound left turn (from West Napa Street onto 5th
Street West) at the West Napa/5th Street West intersection. The Project’s equitableshare towards these improvements, either through a proportional share fee of 1.1percent of the $338,000 estimated cost identified in the City’s Systemic Safety AnalysisFinal Amended Report, or City fees, shall be collected at the time of building permit.
REVISIONS TO CHAPTER 4.12, LAND USE AND PLANNING
Page 4.12-2 of the revised Draft EIR is hereby amended as follows:
Existing ConditionsThe Project site is developed with commercial uses, including the Lynch Building, the Sonoma-Index Tribune Building, and a metal building that was previously used for newspaper productionby the Sonoma Index-Tribune. The Lynch Building contains seven residential units. In addition,rear parking is located behind the Tribune Building. The Project site is located in downtownSonoma, California, and is surrounded by urban development.
An existing retail building known as the Feed Store at the southwest corner of West Napa Streetand First Street West and its parking lot located on First Street West are located directly east of
H O T E L P R O J E C T S O N O M A R E V I S E D F I N A L E I RC I T Y O F S O N O M A
REVISIONS TO THE REVISED DRAFT EIR
November 2019 3-13
the Project site and are not included in the proposed Project. The Feed Store contains at leastone vacation rental.
Downtown Sonoma contains a broad mix of uses, including boutique shops, hotels, restaurants,wine tasting rooms, a shopping center, and other commercial uses, such as a gas station andconvenience store. Additionally, there are some residential neighborhoods nearby but notadjacent to the Project site, consisting primarily of single-family and mixed-use residential units.
REVISIONS TO CHAPTER 6, ALTERNATIVES TO THE PROJECT
Page 6-2 of the revised Draft EIR is hereby amended as follows:
§ Hotel/Residential (50%-50%). Under this alternative, the Project’s proposed building area(excluding the underground parking garage) of 67,478 square feet would includeapproximately 50 percent as hotel and 50 percent as residential. The proposed restaurantwould be removed. In order to accommodate the residential and hotel units within theproposed building footprints, it is assumed that the site could accommodate 25 37 hotelrooms (450 square feet per room) and 25 residential units (800 square feet average size perunit), consisting of 12 two-bedroom units and 13 one-bedroom units.1 Based on a Projectsite area of 54,000 square feet (or 1.24 acres),2 25 residential units would be the maximumnumber of units permitted under the applicable Commercial Zoning District, which permits20 units per acre. To meet the City’s parking standards, the underground parking garagewould be expanded to add 12 additional parking spaces. Overall, the building would beincreased by 8,750 net square feet. All other Project components would be the same as theproposed Project.
1 Michael Ross, AIA, NCARB, RossDrulisCusenbery Architecture, email correspondence with David Goodison,City of Sonoma. December 19, 2017.
2 Although the Project site is 71,000 square feet (1.63 acres) in area, because no changes are proposed to theLynch Building or Tribune Building, the affected area is limited to 54,000 square feet (1.24 acres).