hot n2...hot n2 feb-2007 11 8.delivery record (1) semiconductor ti-tin tel alcatel - 6months 61 61...

14
Feb-2007 Hot N2 1 Hot N 2

Upload: others

Post on 17-Feb-2021

4 views

Category:

Documents


1 download

TRANSCRIPT

  • Feb-2007Hot N2 1

    Hot N2

  • Feb-2007Hot N2 2

    1.Overview

    Hot N2 System has been developed as a solution for the problem of

    piping choke caused during the process of diffusion/CVD, etching, etc.

    Hot N2

    Emitting hot (100-200℃)swirling N2 gas into the piping.

    Extending maintenance period

    Productivity improvement !

  • Feb-2007Hot N2 3

    HEATER & TRANSFER

    SENSOR

    HEATER

    N2 GAS

    CONTROLLER

    2.Configuration

    Hot N2 unitHeating N2 gas.

    Piping with heater integrated.

    Controller

    Controlling amount of N2 gas flow and

    temperature of the gas supplied.

    3 channels are available.

    Powder transfer

    Emitting heated swirling N2 gas

    along the wall of piping.

    PUMP Exhaust(gas + powder)

    Hot swirlingN2 gas flow

    N2 gas

  • Feb-2007Hot N2 4

    3. Installation example

    Exhaust outlet of

    vacuum pump – Scrubber

    ①. Immediately above the exhaust outlet of vacuum pump

    ②. Switching valve section

    Effective length of one unit:approx. 4 – 6m

    (varying according to actual use conditions)

    HOT N2 CONTROLLER

    HOT N2 UNIT #2

    HOT N2 UNIT #1 (SWITCHING VALVE)

    (MAIN TOOL)

  • Feb-2007Hot N2 5

    4. Effect of the installation (1)

    -CVD PSIN process

    Maintenance period 1 month→8 – 12months

    -Metal etching process

    Maintenance period 2 months→12 months

    Additional effect by putting thermal insulator on piping.

  • Feb-2007Hot N2 6

    5.Specifications (1)

    HOT N2 Unit & Transfer : 200(w) x 173(d) x 150(h) (mm), 3 Kg

    PID controlcontrol

    type-Kthermo couple

    4 – 6m/uniteffective length

    50l/min. (adjustable)amount of flow

    200℃ or less (adjustable)temperature setting

    500W/800Wwattage

    AC 220V/100V 1P 2A/5A 50/60Hzinput power

    Ni-Crheater

    Controller : 275(w) x 275(d) x 160(h) (mm), 4 Kgunit size

    SUS316piping materials

    SpecificationsItems

  • Feb-2007Hot N2 7

    Example of useProduct shape

    separated type

    combined type

    5.Specifications (2)

  • Feb-2007Hot N2 8

    6. Safety device

    - Leakage breakerElectric leakage

    - Heater cut off at 1kgf/cm2N2 gas pressure drop

    - Circuit breaker - Fuse

    Over current

    -Thermostat to prevent overheat (standard setting: 200℃)

    Temperature anomaly

    MeasuresTroubles

    * Red light on in case of above troubles.* Please contact for additional safety function.

  • Feb-2007Hot N2 9

    7. Test results of Hot N2 system (1)

    Contaminant caused in many processes of semiconductor manufacturing is condensed in the piping. < trouble >exhaust piping chokevalve lock/malfunction

    vacuum pump: performance degradation and malfunction increased down time and increased parts maintenancedecrease in production volume

    Before using the system

    (30 days later)

    significant decrease of contaminant adhesionAfter using the system

    (180 days later)

    RemarksPiping inside (photo)

  • Feb-2007Hot N2 10

    Piping above silencer(2)

    Piping above silencer(1)

    Before usingHot N2 system

    (30 days later )

    After usingHot N2 system

    (60 days later )

    Piping above silencer(2)

    Piping above silencer(1)

    7. Test results of Hot N2 system (2)

  • Feb-2007Hot N2 11

    8.Delivery record (1)Semiconductor

    61616months-ALCATELTELTi-TiN

    46

    4

    2012months2monthsLOT

    EDWARDMATTSON

    ARC

    CVD

    412months2monthsLOTNOVELLUS

    12

    6

    76

    6

    70

    27

    90

    33

    3

    24

    Number of the systems delivered

    2months

    1month

    1month

    2months

    2months

    1month

    1month

    before installation

    Maintenance period of piping

    12months

    6months

    12months

    8months

    8months

    8months

    8months

    after installation

    27

    LOT

    EDWARDNOVELLUS

    PSIN

    Pump manufacturer

    Equipment manufacturer

    AMAT

    AMAT

    AMAT

    AMAT

    GENUS

    AMAT

    LOT

    ALCATEL

    EDWARD

    LOT

    LOT

    EDWARD

    LOT

    EDWARD

    EDWARD

    436

    6HDP

    97BW

    123WSiX

    76BPSG

    Total

    Process

  • Feb-2007Hot N2 12

    Semiconductor

    16166months1monthEBARATELNITRIDE

    DIFF556months1monthEDWARDKE

    11118~12months2monthsALCATELLAM

    POLY

    51518~12months2monthsALCATELAMAT

    12128~12months2monthsEDWARDHITACHI

    15158~12months2monthsEDWARDIPS

    METAL

    3615

    218~12months2monthsEDWARD

    ALCATELLAM

    69698~12months2monthsEDWARDAMAT

    12128~12months2monthsEDWARDIPS

    W-ETCH BACK

    Total

    after installation

    before installation

    254

    ETCH

    Process

    POLY

    LAM

    Equipment manufacturer

    EDWARD

    Pump manufacturer

    2months

    Maintenance period of piping

    8~12months 324

    Number of the systems delivered

    27

    8.Delivery record (2)

  • Feb-2007Hot N2 13

    Semiconductor (300mm)

    5912months2monthsAMATTi TiN

    2412months2monthsLAMAL METAL

    ETCH 312months2monthsAMATW BL ET

    212months2monthsLAMMETAL

    312months2monthsLAMW EB

    212months2monthsAMATPE-CVD

    T/F

    412months2monthsGENUSWSiX

    612months2monthsTELTEOS

    112months2monthsTELHTO

    212months2monthsAMATSA-CVD

    112monthsmonthsAMATTOINBDIFF

    1412months2monthsAMATP-HDP

    412months2monthsNOVELLUSCVD-W

    Total 159

    1512months2monthsAMATSTI-HDP

    512months2monthsTEL

    16months1month TEL(Fomura)

    D-POLY

    after installationbefore installationProcess

    NITRIDETEL(303i)

    Equipment manufacturer

    1month

    Maintenance period of piping

    12months 13

    Number of the systems delivered

    8.Delivery record (3)

  • Feb-2007Hot N2 14

    LCD

    96months1monthEDWARDAKTP-Si CVD

    LCD

    863months1monthEBARA

    EDWARDS

    KASHIYAMA

    AKTCVD

    Pump manufacturerEquipment manufacturer before installation

    Maintenance period of piping

    after installation

    95Total

    Number of the systems

    deliveredProcess

    8.Delivery record (4)