 A hospital can have a simple or complex emergency power supply system (EPSS) but ensuring that the system continues contributing to safe and effective patient care with today’s challenges is rarely simple. Complexity is introduced because the EPSS powers other hospital systems such as the clinical, mechanical, vertical transportation and fire management systems. The hospital engineer must also respond to new requirements that affect the EPSS, including requirements for utility management, emergency management, patient safety, continuous quality improvement and staff education. All of these interrelationships cause complexity. An EPSS includes generator sets, generator set auxiliary systems such as cooling, combustion air, fuel oil and starting systems, paralleling switchgear, automatic transfer switches, distribution panels, lighting and power panel boards, feeders and branch circuits. Some facilities that do not have EPSSs may have a stored-energy EPSS (SEPSS). Facilities can also have an uninterruptible power supply (UPS). When the normal power fails, all normal loads are dead. All emergency loads experience a short loss of power unless they are backed up by an SEPSS or UPS. The hospital’s clinical staff must know how to deal with this condition. The monthly load testing simulates this experience as illustrated in Figure 1, although the length of time without voltage during a test is likely to be less than it would be during an actual outage. A proactive EPSS management programme will use the lessons learned from the monthly load testing, along with regular normal power shutdowns, to train the clinical staff to expect and then manage this critical element of the environment of care. Some hospitals have decided that the short period of time (10 seconds or less) that some clinical equipment, such as ventilators, would be without power during a real normal power outage is unacceptable. Those hospitals have installed UPS systems to provide uninterruptible power to their ventilators, and have identified specially marked outlets as UPS-backed outlets. Management Programme Synopsis Managing emergency power systems is more than just monthly generator load testing. It should also involve: knowing the total EPSS demand loading under the range of emergency conditions included in the hospital’s hazard vulnerability analysis; knowing the total demand on major distribution elements of the EPSS such as transfer switches; reviewing unexpected occurrences and monthly test results; analysing trends of results and problems for continuous quality improvement; investigating and resolving training and/or systemic issues identified by the trend analysis; co-ordinating the impact of construction/ renovation projects and infrastructure upgrade projects on the EPSS; and performing an extended-run EPSS load test at least once every 36 months. Emergency Power Demand Load Hospital engineers need to determine the actual EPSS peak (demand) load for due diligence and to satisfy the requirements of authorities having  juris dicti on in their local ities. Many hospit al engineers believe that the amount of load they record during their monthly EPSS load tests is the real demand load. This assumption is flawed and can lead to some negative consequences. The EPSS test load does not reflect the EPSS demand load because the EPSS test loading depends on the day and time of the test. Correspondingly, real EPSS loading during a utility power failure also depends upon the day and time of the power failure. Many hospitals test their EPSS at night or early in the morning before the bulk of the hospital’s daily activities begin. This test time was probably chosen a report by David L Stymiest Voting Member, National Fire Protection Association (NFPA) Technical Committee on Emergency Power Supplies and Senior Consultant, Smith Seckman Reid, Inc. Managing Hospital Emergency Power Programmes BUSINESS BRIEFING: HOSPITAL ENGINEERING & FACILITIES MANAGEMENT 2004 1 Reference Section David L Stymiest is a voting member of the National Fire Protection Association (NFPA) Technical Committee on Emergency Power Supplies. He is Senior Consultant at Smith Seckman Reid, Inc. (SSR), specialising in hospital facilities engineering and management, and is also a Certified Healthcare Facility Manager. Prior to joining SSR, Mr Stymiest was Senior Electrical Engineer for more than 10 years for Massachusetts General Hospital and the other 11 hospitals of the Partners HealthCare System. He has 30 years of experience in facilities engineering, during which time he has developed a comprehensive hospital electrical utility management programme. He has written 13 American Society of Healthcare Engineering (ASHE) papers and five Health Facilities Management articles on hospital facilities management and engineering, and he co-edited the 1,200-page McGraw-Hill Facilities Engineering and Management Handbook for  Commercial, Industrial, and Institutional Buildings . He is a member of ASHE, National Society of Professional Engineers (NSPE), NFPA, Illuminating Engineering Society of North America (IESNA), Institute of Electrical and Electronics Engineers, Inc. (IEEE) and Association of Energy Engineers (AEE). Mr Stymiest has a Bachelor’s degree and a Master of Engineering degree in Electric Power Engineering from Rensselaer Polytechnic Institute, a Certificate of Special Studies in Administration and Management from Harvard University and is a Registered Professional Engineer.

Upload: fndproject

Post on 03-Nov-2015

223 views

Category:

Documents


0 download

DESCRIPTION

HOSPITAL EMERGENCY POWER

TRANSCRIPT

  • A hospital can have a simple or complexemergency power supply system (EPSS) butensuring that the system continues contributing tosafe and effective patient care with todayschallenges is rarely simple. Complexity isintroduced because the EPSS powers other hospitalsystems such as the clinical, mechanical, verticaltransportation and fire management systems. Thehospital engineer must also respond to newrequirements that affect the EPSS, includingrequirements for utility management, emergencymanagement, patient safety, continuous qualityimprovement and staff education. All of theseinterrelationships cause complexity.

    An EPSS includes generator sets, generator setauxiliary systems such as cooling, combustion air,fuel oil and starting systems, paralleling switchgear,automatic transfer switches, distribution panels,lighting and power panel boards, feeders and branchcircuits. Some facilities that do not have EPSSs mayhave a stored-energy EPSS (SEPSS). Facilities canalso have an uninterruptible power supply (UPS).

    When the normal power fails, all normal loads aredead. All emergency loads experience a short loss ofpower unless they are backed up by an SEPSS orUPS. The hospitals clinical staff must know how todeal with this condition. The monthly load testingsimulates this experience as illustrated in Figure 1,although the length of time without voltage during atest is likely to be less than it would be during anactual outage. A proactive EPSS managementprogramme will use the lessons learned from themonthly load testing, along with regular normalpower shutdowns, to train the clinical staff to expectand then manage this critical element of theenvironment of care.

    Some hospitals have decided that the short period oftime (10 seconds or less) that some clinicalequipment, such as ventilators, would be withoutpower during a real normal power outage isunacceptable. Those hospitals have installed UPSsystems to provide uninterruptible power to theirventilators, and have identified specially markedoutlets as UPS-backed outlets.

    Mana g emen t P r o g r amme S y n op s i s

    Managing emergency power systems is more than justmonthly generator load testing. It should also involve:

    knowing the total EPSS demand loading underthe range of emergency conditions included in thehospitals hazard vulnerability analysis;

    knowing the total demand on major distributionelements of the EPSS such as transfer switches;

    reviewing unexpected occurrences and monthlytest results;

    analysing trends of results and problems forcontinuous quality improvement;

    investigating and resolving training and/orsystemic issues identified by the trend analysis;

    co-ordinating the impact of construction/renovation projects and infrastructure upgradeprojects on the EPSS; and

    performing an extended-run EPSS load test atleast once every 36 months.

    Eme r g e n c y P owe r D emand L o a d

    Hospital engineers need to determine the actualEPSS peak (demand) load for due diligence and tosatisfy the requirements of authorities havingjurisdiction in their localities. Many hospitalengineers believe that the amount of load they recordduring their monthly EPSS load tests is the realdemand load. This assumption is flawed and can leadto some negative consequences.

    The EPSS test load does not reflect the EPSSdemand load because the EPSS test loading dependson the day and time of the test. Correspondingly,real EPSS loading during a utility power failure alsodepends upon the day and time of the power failure.Many hospitals test their EPSS at night or early in themorning before the bulk of the hospitals dailyactivities begin. This test time was probably chosen

    a report by

    Da v i d L S t ym i e s t

    Voting Member, National Fire Protection Association (NFPA) Technical Committee on

    Emergency Power Supplies and Senior Consultant, Smith Seckman Reid, Inc.

    Manag ing Hosp i ta l Emergency Power Programmes

    B U S I N E S S B R I E F I N G : H O S P I T A L E N G I N E E R I N G & F A C I L I T I E S M A N A G E M E N T 2 0 0 4

    1

    Reference Section

    David L Stymiest is a votingmember of the National FireProtection Association (NFPA)Technical Committee on EmergencyPower Supplies. He is SeniorConsultant at Smith Seckman Reid,Inc. (SSR), specialising in hospitalfacilities engineering andmanagement, and is also a CertifiedHealthcare Facility Manager. Priorto joining SSR, Mr Stymiest wasSenior Electrical Engineer for morethan 10 years for MassachusettsGeneral Hospital and the other 11hospitals of the Partners HealthCareSystem. He has 30 years ofexperience in facilities engineering,during which time he hasdeveloped a comprehensive hospitalelectrical utility managementprogramme. He has written 13American Society of HealthcareEngineering (ASHE) papers and fiveHealth Facilities Managementarticles on hospital facilitiesmanagement and engineering, andhe co-edited the 1,200-pageMcGraw-Hill Facilities Engineeringand Management Handbook forCommercial, Industrial, andInstitutional Buildings. He is amember of ASHE, National Societyof Professional Engineers (NSPE),NFPA, Illuminating EngineeringSociety of North America (IESNA),Institute of Electrical andElectronics Engineers, Inc. (IEEE)and Association of Energy Engineers(AEE). Mr Stymiest has a Bachelorsdegree and a Master of Engineeringdegree in Electric PowerEngineering from RensselaerPolytechnic Institute, a Certificate ofSpecial Studies in Administrationand Management from HarvardUniversity and is a RegisteredProfessional Engineer.

  • B U S I N E S S B R I E F I N G : H O S P I T A L E N G I N E E R I N G & F A C I L I T I E S M A N A G E M E N T 2 0 0 4

    Reference Section

    to be one of low clinical activity, and that avoidedclinical load will not be reflected in the EPSS testloading. Many hospitals do not test their EPSSwhenever their operating theatres are in use. Also,the mechanical (see Figure 2), building, radiology (see

    Figure 3) and other clinical processes all vary during atypical hospital day. Finally, some equipment, such assmoke control systems and fire pumps, will notoperate except during internal emergencies.

    The amount of load through a piece of distributionequipment such as a transfer switch can be measuredas a function of time of day. This does not includesampling in short intervals. Repeated recordings forseveral days with portable or permanently installedpower monitors will provide the raw data fromwhich EPSS load profiles can be generated.

    During an internal emergency situation such as aworking fire, the EPSS loading may include extra firealarm system load (see Figure 4), may include theextra load of smoke control systems such as stairwellpressurisation fans or atrium exhaust fans and mayinclude a fire pump. If the emergency is external,then the EPSS load may also include extra clinicalactivity, which some medical personnel callemergency department surge.

    The authors experience reviewing thousands ofhospital load profiles has indicated that daily loadprofiles taken in the same hospital building over timetend to show similar characteristics and values. Theload profiles are most likely to change due to loadgrowth (over time), space utilisation changes anddensification of occupancy or equipment. Thefollowing is a strategy for determining the peak loadthat provides good repeatable values:

    obtain typical day load profile for each automatictransfer switch (ATS);

    add seasonal adjustments;

    adjust loading for the internal emergencycondition considered (such as a fire);

    adjust loading for the external emergencycondition considered; and

    adjust loading for lessons learned from plannednormal power shutdowns.

    Each ATS and adjustment factor is consideredindividually. Once all input data has been measured,calculated or analysed, Figure 5 can be turned into theoverall EPSS stacked area chart (see Figure 6) with a

    Fair Better Best

    Sample with hand-held ammeter Record 23 days per ATS with Use remote power management systems

    does not result in load profile portable recording instrumentation

    Sample with ATS-mounted ammeter Use power quality meter Use central data recording and storage

    does not result in load profile Use data loggers

    Table 1: Methods for Measuring Typical ATS Loads and Load Profiles

    Figure 1: Impact of an EPSS Test on ATS Current

    0

    50

    100

    150

    200

    250

    300

    350

    400

    450

    500

    7:00 am 7:30 amATS current 5 min/div horiz.

    8:00 am

    Amps

    Figure 2: Sample Mechanical Equipment System ATS One-minute Load Profile

    0

    50

    100

    150

    200

    250

    300

    Equipment system, no smoke control or fire wire

    Two days, 6:30 am start time

  • B U S I N E S S B R I E F I N G : H O S P I T A L E N G I N E E R I N G & F A C I L I T I E S M A N A G E M E N T 2 0 0 4

    3

    Reference Section

    simple spreadsheet command. It is important to ensurethat all measurements and adjustments are in the sameunits. The author prefers kilovolt-amperes since it is adirect calculation from amperes, is independent of ATSvoltage and does not require power factor assumptions.

    Eme r g e n c y P owe r T e s t i n g P r o g r amme

    The primary goal of a hospitals emergency powertesting programme is to comply with regulatoryrequirements without adversely affecting theoperation of the hospital or the wellbeing of thepatients. Additionally, the programme needs to verifythe infrastructures ability to withstand those powertransfers that will occur when utility power is lost. Asthese power transfers usually involve power qualityissues, it is also necessary to educate clinical care-givers so that patient care is not put at risk in theevent of power outages or transfers.

    A comprehensive, proactive approach to emergencypower testing should incorporate the following.

    Test the functionality of all equipment related togeneration and distribution of emergency power.

    Train both maintenance and clinical personnel inhow to deal with the loss of utility power andpower system transfers.

    Test clinical equipment response to power systemtransfers.

    Test the mechanical and building system responsesto power system transfers.

    Ascertain the causes of unexpected occurrencescaused by the EPSS testing and take correctiveaction to preclude future failures.

    Avoid conditions that compromise patienttreatment and safety.

    Table 2

    Some types of EPSS failures Possible result if not found and fixed

    before the next normal power outage

    Starting battery or cable problems No emergency power when needed

    Engine fuel oil contamination Poor operation, possible engine failure

    Faulty safety shutdown switches May shut off the generator set unnecessarily

    Engine fluid leaks Possible engine failure

    Engine mechanical failures Possible engine failure

    Transfer switch failures Failure to transfer to emergency power

    Blown control power fuses ATS fail to transfer, paralleling switchgear

    failure, generator set fail to start

    Tripped or open emergency power ATS will not transfer to a dead source

    circuit breakers

    Figure 3: Sample Radiology ATS Load Profile

    0kw

    5.0kw

    10.0kw

    15.0kw

    20.0kw

    25.0kw

    30.0kw

    35.0kw

    40.0kw

    45.0kw

    50.0kwkw

    Noon 12:30 pm

    Instantaneous Power 5 min/div horiz.

    1:pm

    Figure 4: Sample Hospital Emergency Power System Life Safety ATS Load Profile Using 15-minute Demands

  • Manag ing Hosp i ta l Emergency Power Programmes

    B U S I N E S S B R I E F I N G : H O S P I T A L E N G I N E E R I N G & F A C I L I T I E S M A N A G E M E N T 2 0 0 4

    4

    Monthly emergency power testing may also causeEPSS failures to occur during the test because theequipment is operating. Failures that do occur duringa test probably would have occurred anyway duringthe next normal power outage. Their impact on thehospital is lessened because plant operators arefocusing on the test and normal power is stillavailable. Experienced hospital engineers wouldprefer to have the next failure during the next testinstead of during the next outage.

    S e c o nd - o r d e r C o n s e q u e n c e s a n dL e s s o n s L e a r n e d f r om E P S S T e s t s

    EPSS testing can have second-order consequences,which are wide-ranging consequences beyond theprimary intent of the testing. The second-orderconsequences of the testing may signify a potentialproblem with the next power outage as well. For thisreason, hospital engineers should always follow up on thelessons learned from the monthly load testing, determine

    Figure 5: Sample Hospital Emergency Power System ATS Load Profiles Using 15-minute Demands

    Figure 6: Sample Hospital Emergency Power Supply System Load Profile Using 15-minute Demands on

    800kW/1,000kVA Generator Set

  • Manag ing Hosp i ta l Emergency Power Programmes

    B U S I N E S S B R I E F I N G : H O S P I T A L E N G I N E E R I N G & F A C I L I T I E S M A N A G E M E N T 2 0 0 4

    5

    the causes and effects of the second-order consequencesand take corrective action as soon as possible. Examplesof some types of second-order consequences are:unnecessary mechanical system tripping; UPSs thattransfer to battery during the test; clinical equipmentfailures; circuit-breaker tripping; unwanted mechanicalsystem responses; and variable-speed drive failures. Everysystem failure that coincides with or follows an EPSS testshould be analysed for its generic relevance, consideringit as a potential:

    human error; problem system interaction; test procedure inadequacy; equipment malfunction; or simple coincidence (unlikely).

    Hospital engineers should proactively assess andreduce the risk of EPSS failure. The programmediscussed here offers this. The following list providesa set of tools for quality improvement.

    Rotate testing personnel. Supervisors proactively review test results and all

    surprises. Analyse test results, look for trends:

    do not just record generator parameters. Review second-order consequences:

    look for interactions between EPSS and thesystems it powers.

    Use a testing event database: unexpected events; failures EPSS, other systems and equipment;

    and other unexplained occurrences.

    Mana g emen t o fP owe r S y s t em F a i l u r e s

    Some hospitals consider power system failures as thefailure of the incoming utility lines, maintransformer, main switchboard, etc. This can takedown the entire normal power system. In this case,the emergency power system is assumed to beavailable. As illustrated in Table 3, hospital engineersshould consider different failure points, not just at themains. The responses will be different for each typeof failure and, as people sometimes find out much totheir dismay, it is too late to formulate a responseafter the failure has occurred.

    Poorly considered emergency responses can degradepatient safety if they neglect to consider allramifications of emergency operation. Sometimesbad decisions are made by well-meaning personnelwho are under a lot of pressure to act immediately.This situation can also compromise worker safety.

    Hospital departments can plan and work together todeliver safe patient care, not just in the infection

    Types of failures that usually have written failure procedures Types of failures that often do not have written failure procedures

    Normal power Normal power

    Incoming utility line(s) Large feeder or riser (busway or

    Main utility transformer cable/conduit)

    Main service entrance Large transformers and switchboards

    switchboard Motor control centres, large distribution

    panels

    Emergency power Emergency power

    One generator of a Paralleling switchgear most critical

    multiple generator system common mode EPSS failure

    Single generator

    Normal/emergency power (still part of the EPSS but downstream of

    the transfer switch or other transfer device)

    Critical branch ATS or riser

    Critical branch feeder or panel Hard-wired equipment is very problematic

    Life safety ATS or riser Will take out all hard-wired loads (fire

    Life safety feeder or panel alarms, emergency lights, exit signs, etc.)

    Equipment system ATS or feeder Will take down many important mechanical

    loads serving critical care areas

    Will take down all loads on the UPS, Uninterruptible power supply

    usually the most electrically critical.

    Emergency system is still available

    major impact on hospital but

    expectations are lower

    Emergency system is still available lesser

    impact on hospital but expectations are

    much higher than total outage. Could be

    accompanied by fire/smoke.

    Remaining generators are still

    available

    Normal power is still available, may

    arrange for spare or rental unit

    Will take out all connected generators

    must rewire all ATSs.

    Normal power is still available but clinicians

    must be trained so that normal power can be

    the back-up

    or

    motor

    control

    centre

    Table 3: Managing Hospital Power System Failures

  • B U S I N E S S B R I E F I N G : H O S P I T A L E N G I N E E R I N G & F A C I L I T I E S M A N A G E M E N T 2 0 0 4

    6

    Reference Section

    control and clinical arenas, but in the utilitymanagement arena as well. Basic what if thinking byinnovative professionals working together will improvethe overall ability of the hospital to deliver safe patientcare under all electrical failure eventualities.

    When utility failures do occur and they will incident reports should be completed. Whenincident reports are generated, proactive utilitymanagers will fix the immediate cause of the failure(as well as the failed equipment itself), consider thegeneric relevance of the failure, improve policies andprocedures where warranted and make other changesto avoid similar future failures and improve overallutility reliability. Finally, all of these lessons learnedshould be used to improve the emergencymanagement plan.

    P l a n n e d S h u t d own s

    Hospital new construction and renovation projectsoften require carefully planned electrical shutdowns.If the critical branch panels or risers are to be shutdown, then the temporary wiring and proceduresthat are used should be included in future emergencymanagement documentation.

    It is often necessary to power more equipmentduring a planned power shutdown than just code-required equipment. This is necessitated by thehospitals operating needs and if the extra equipmentis not already on emergency power it must betemporarily wired for the shutdown. Many of theseissues were learned for the first time when hospitalsprepared themselves for Y2K.

    Finally, planned shutdowns also include whatemergency management policies call recovery -getting back to normal. This can be a burdensomeprocess if a lot of temporary wiring or back-feeds wereused to get through the shutdown. It may be necessaryto have detailed procedures for switching back to thenormal operation in order to minimise the potentialfor accidents. Equipment that had remained de-energised during the outage should also be shut offbefore recovery begins to minimise the possibility ofdamage to sensitive electronics from power surges(voltage fluctuations) during the initial power-up.

    Edu c a t i o n

    Since modern hospitals are evolving, constantlychanging entities, on-going staff education is necessary.This includes highlighting and keeping current theinterdependencies between each of the departments -facilities, clinical, support services, etc. The plannedmaintenance shutdowns and construction/renovation

    shutdowns provide excellent opportunities to highlightthese interdependencies.

    R e f e r e n c e s

    NFPA 110, Standard for Emergency and StandbyPower Systems, 2002 Edition, Quincy, MA: National FireProtection Association (NFPA), 2002.

    David Stymiest, Managing Hospital Emergency PowerTesting Programs, American Society of HealthcareEngineering (ASHE) Management Monograph, July 2003.

    Environment of Care, Essentials for Health Care,Oakbrook Terrace, IL: Joint Commission Resources, 2ndEdition, 2002.

    Environment of Care, Essentials for Health Care,Oakbrook Terrace, IL: Joint Commission Resources, 3rdEdition, 2003.

    David Stymiest, Joining Forces Integrating Utility andEmergency Management for Better Patient Safety, HealthFacilities Management Magazine, April 2003.

    David Stymiest, All Things Considered An EmergencyPower Management Program Has Many Variables, HealthFacilities Management Magazine, June 2003.

    Scott Wallask, What To Do When The Lights Go Out A Guide to Handling Power Outages in Health Care,Marblehead, MA: Opus Communications, Inc., June 2001.

    Hugh O Nash, Jr and Dan Chisholm, EssentialDistribution System Disaster Preparedness GuaranteeingPerformance of Your On-site Electric Utility, slides 5-6,Proceedings of the 39th Annual Conference of theAmerican Society of Healthcare Engineering, Chicago:ASHE, 2002.

    David Stymiest, Anand Seth and Jack Dean, Managing theCost and Impact of Emergency Power Testing Programs onHospital Operations A Case Study, Proceedings of the35th Annual Conference of the American Society ofHealthcare Engineering, Chicago: ASHE, 1998.

    D i s c l a ime r

    Although the author is a member of the National FireProtection Association (NFPA) Technical Committee onEmergency Power Supplies, which is responsible for NFPA110 and NFPA 111, the views and opinions expressed inthis article are purely those of the author and shall not beconsidered the official position of NFPA or any of its TechnicalCommittees and shall not be considered to be, nor be reliedupon as, a formal interpretation. Readers are encouraged torefer to the entire text of all referenced documents.

    WelcomeIntroductionThe PublicationAdvisory PanelForewordIndustry OverviewThe Pursuit of Curative Guidelines Using Hospital Engineering

    Hospital Planning, Design & ConstructionInvesting in Design Developing a Business Case for Good Design for Health

    Life-cycle & Asset ManagementEngineering Safer Healthcare

    Indoor Air QualityEffective Design of Heating, Ventilation and Air-conditioning Systems for Healthcare FacilitiesCase Studies on the Effects of Ultraviolet Air Purification on the Air Quality in Hospitals and ClinicsIndoor Air Quality Standards in Hospitals

    Infection Control & SterilisationFlooringVinyl Flooring Still the Best Choice for HospitalsAntimicrobial Efficacy Comparison of Floor Coverings

    Solid SurfacesEnvironmental Management of Mould Contamination in a University HospitalAlcohol-based Hand-rub Solutions Fire Modelling AnalysisLegionella Control Methods and Dental Chair Risks

    Fire & Life SafetySecurity in Modern Healthcare

    CommunicationsInformation Technology Systems A Case Study

    Power & Energy ManagementSaving Money Through Contract ManagementHealthcare is Going Green Saving Dollars and Making SenseManaging Hospital Emergency Power Programmes

    Lighting SolutionsThe Latest Theory and Practice in Using Light for Health and the Impact on Hospitals of the FutureHealthy Lighting for the Visual, Circadian and Perceptual Systems

    Directory of Contacts

    Reference SectionCollaborative Procurement of a Clinical ModalityEffective Design of Heating, Ventilation and Air-conditioning Systems for Healthcare FacilitiesHospitals and Fire Safety Law A Changing SceneInvesting in Design Developing a Business Case for Good Design for Healthe-Commerce Will Purchasing and Logistics in Hospitals be Subjected to Substantial Changes?Legionella Control Methods and Dental Chair RisksHospital Maintenance Strategic Plan at the University of Michigan Hospital and Health CentersDesign of Hospital Isolation RoomsThreat Mitigation in Hospital DesignEngineering and Procurement A Strategy for the Healthcare IndustryThe Latest Theory and Practice in Using Light for Health and the Impact on Hospitals of the FutureEnvironmental Management of Mould Contamination in a University HospitalManaging Hospital Emergency Power ProgrammesSingle-use Medical DevicesDuke University Health Systems Fire Protection Regulatory ComplianceAlcohol-based Hand-rub Solutions Fire Modelling Analysis

    Technology & Services SectionActive Power, Inc. Power Quality for Healthcare Facilities Using Flywheel Energy StorageAigis Mechtronics LLC A Customised Approach to SecurityAntec International Fighting Hospital Infection A Constant ChallengeAustin Ventures International, Inc. Options for Continuous Airflow MonitoringBOC Medical Liquid Oxygen USP Supply Safety and RegulationBWT AG Legionella in Drinking Water Distribution SystemsDalkia North America Benchmarking and Best Practice Energy Management for Healthcare in the UKDuPont Infection Control in Healthcare and Emergency Response EnvironmentsDuPont de Nemours Int. SA DuPont Corian The Original Solid SurfaceEPSCO L.L.C. (Environmental Protection Services Company) Indoor Air Quality for DummiesFagerhults Belysning AB Corporate ProfileFlkt Woods AB The Flkt Woods Econet Heat Recovery SystemForbo Flooring Floor Care Marmoleum Floor Care System for HospitalsFoster Products Corporation Proper Use of Antimicrobial Coatings is the Key to Effective Mould RemediationGE PermaCon A Revolutionary Approach to Building Within the Healthcare Industry GE PermaCon Component ConstructionHill-Rom Services, Inc. Patient SafetyKI Preliminary Questions to KILG Chem Europe LG HI-MACS Natural Acrylic Stone A High-performance Solid Surface for Hospitals, Laboratories and other Healthcare FacilitiesLifa Air Ltd A New Approach for Enhancing Supply Air FiltrationLuxo Professional Lighting for HospitalsMEIKO Maschinenbau GmbH & Co. KG Corporate ProfilePowerware UPS Power Protection Systems Health Insurance for Critical Medical EquipmentRegent Medical Natural Rubber Latex Protein Allergy and Medical GlovesResdev Limited Resin Flooring Systems in the Healthcare EnvironmentSanuvox Technologies, Inc. Case Studies on the Effects of Ultraviolet Air Purification on the Air Quality in Hospitals and ClinicsSchneider Electric Ltd Intelligent Buildings Easing the Burden on Health ManagersSimplexGrinnell New Technologies for Meeting Hospital Communications ChallengesSIS-LICHT Gebr. Lang GmbH & Co. KG Good Lighting for Healthcare Buildings Some BasicsSolatube Global Marketing, Inc. Daylighting for Everyday LivingStanley Security Solutions Security and the Healthcare IndustryThermoguard Preventive Measurements to Microbial Growth in Heating, Ventilation and Air-conditioning SystemsTrespa International BV Creating the Right Healthcare EnvironmentTri-Dim Filter Corporation Indoor Air Quality in Healthcare FacilitiesWipak Medical, Health Care Products Specialised Packaging for Hospital Sterilisation

    Sponsor SectionActive Power Corporate Presentation Web Link E-mail Link

    Aigis Mechtronics, LLC Corporate Presentation Web Link E-mail Link 1 E-mail Link 2

    Antec International A Dupont Company Corporate Presentation Web Link E-mail Link

    Austin Ventures International, Inc Web Link E-mail Link

    BOC MEDICAL Corporate Presentation E-mail Link

    BWT AG Corporate Presentation Web Link 1 Web Link 2 E-mail Link

    Carrier Corporation Web Link

    Comfort Systems USA Corporate Presentation Web Link E-mail Link

    Dalkia Corporate Presentation Web Link E-mail Link

    Dupont Corporate Presentation Web Link 1 Web Link 2 Web Link 3

    Dupont Corian Corporate Presentation Web Link E-mail Link

    EPSCO L.L.C. (Environmental Protection Services Company) Corporate Presentation Web Link E-mail Link

    Fagerhults Belysning AB Corporate Presentation Web Link

    Flkt Woods Corporate Presentation Web Link

    Forbo Flooring Corporate Presentation Web Link E-mail Link

    Foster Products Web Link E-mail Link

    GE Energy Rentals Web Link E-mail Link

    GE PermaCon Corporate Presentation Web Link

    Hill-Rom Corporate Presentation Web Link

    KI Corporate Presentation Web Link E-mail Link

    LG Chem Europe Corporate Presentation Web Link 1 Web Link 2 E-mail Link

    LIFA AIR Corporate Presentation Web Link E-mail Link 1 E-mail Link 2

    Luxo ASA Corporate Presentation Web Link E-mail Link

    MEIKO Maschinenbau GmbH + Co KG Corporate Presentation Web Link E-mail Link

    Powerware Corporate Presentation Web Link E-mail Link

    Price Industries Corporate Presentation Web Link E-mail Link

    Regent Medical Corporate Presentation Web Link 1 Web Link 2 E-mail Link

    Resdev Web Link E-mail Link

    Sanuvox Ultraviolet Air Purifiers Corporate Presentation Web Link E-mail Link

    Schneider Electric Ltd Corporate Presentation Web Link E-mail Link

    SimplexGrinnell Corporate Presentation Web Link E-mail Link

    SIS-Licht Gebr. Lang GmbH & Co. KG Corporate Presentation Web Link E-mail Link

    Solatube Global Marketing, Inc Corporate Presentation Web Link E-mail Link

    Stanley Security Solutions Corporate Presentation Web Link E-mail Link

    Thermoguard Corporate Presentation Web Link E-mail Link

    Trespa International BV Corporate Presentation Web Link E-mail Link

    TRI-DIM FILTER CORPORATION Corporate Presentation Web Link E-mail Link

    Wipak Medical Corporate Presentation Web Link E-mail Link