HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 1 of 36
HINDUSTAN PETROLEUM CORPORATION LIMITED (A GOVERNMENT OF INDIA ENTERPRISE)
INVITATION TO BID
THRU
PUBLIC TENDER
ITB NO: 8000009 HD 10147 Dated 05/12/2008
Due Date: 29.12.08, Time: 1600 Hrs
FOR
ENGINEERING, PROCUREMENT AND
CONSTRUCTION MANAGEMENT SERVICES
FOR
VISAKHA LPG TERMINAL PROJECT
VISAKHAPATNAM
SCOPE OF WORK
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 2 of 36
SCOPE OF WORK
VISAKHA LPG TERMINAL PROJECT, VISAKHAPATNAM
A. GENERAL B. SCOPE OF BASIC DESIGN C. EPCM SERVICES IN PROCUREMENT AND MATERIALS MANAGEMENT
OF MATERIALS AND EQUIPMENTS D. SCOPE OF PROJECT MANAGEMENT SERVICES E. EXCLUSIONS FROM SCOPE OF WORK
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 3 of 36
A. GENERAL
a) Definition of “Project”:
The word “Project” appearing in Scope of Work shall mean construction of
LPG Terminal for receipt, storage , bottling, distribution of LPG ,
propylene, auto LPG including the product receipt and dispatch pipelines,
approach road etc.
b) Project implementation Strategy:
The PROJECT IMPLEMENTATION STRATEGY developed for the Project is
based on the basic philosophy that Engineering and Project Management
Consultant will be appointed to manage and control all aspects of the
Project execution on behalf of the Owner. The Consultant shall be
responsible for all project activities to a small group of Owner’s
executives.
c) Standardisation of Equipments / Instruments:
Consultant shall endeavor to standardise the type of equipments /
instruments being considered in LPG Terminal.
B. SCOPE OF BASIC DESIGN:
1.0 - Introduction
2.0 - Facilities Proposed
3.0 - Scope of Work
4.0 - Design Standards
5.0 - Studies to be performed
6.0 - Design Reviews
7.0 - Document Requirements
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 4 of 36
1.0 INTRODUCTION
GENERAL:
HPCL proposes to construct a Greenfield LPG Terminal with bottling
facilities at a plot leased from VPT as resitement of the existing LPG Installation
at Malkapuram, Visakhapatnam. The proposed site Opp. INS Dega is proposed
for a POL (White Oil) Terminal as well as the LPG Terminal. The site is approx. 4
away from Visakhapatnam Refinery. The INS Dega plot is admeasuring 110
Acres approx. , out of which LPG Terminal shall be put up on approx. 45 acres,
including the Tank Wagon loading facility. Please note that the White Oil
Terminal shall be constructed by others and is in not in scope of this
tender, except integration and automation of White Oil Terminal’s fire
fighting facilities, as detailed below. A tentative layout plan showing the
proposed plot is enclosed as Annexure - I.
It is proposed that the Terminal will receive the product inputs by two sources,
the summary of which is:
1) LPG, Auto LPG, Propylene by dedicated pipelines to be laid from the Refinery.
2) LPG from SALPG Cavern storage, which will be connected in the Refinery to
the above mentioned LPG pipeline, after interlocks.
The products to be received, stored and distributed are:
LPG, Auto LPG, propylene
2.0 FACILITIES PROPOSED
The information provided below is meant for general guidance only. The
actual facilities to be provided shall be firmed up by Owner during the
implementation of the project.
GENERAL:
The details of the facilities to be installed in the LPG Terminal have
been clearly indicated in the project report attached. However
tentative summary of the same is listed below.
The facilities at the Terminal shall include: the Storage tanks for each
product, product un-loading/loading pumps, Internal pipelines, Tank
truck loading gantry, Tank wagon loading/unloading gantry(railway
siding and structure not included) , Fire fighting system, Automation,
Office and other amenity buildings, Roads and drains, Total Electrical
systems includes HT/LT System, Yard, MCC room, Lighting, Panels, DG
room, etc. Godowns/ stores, Effluent treatment plant,
Telecommunication system, Development of the Green belt,
Landscaping etc as detailed in the project report or in the above report
but shall not be limited to the same and shall include all other jobs
required to fully commission and capitalize the installation.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 5 of 36
External facilities shall include pipelines (with CP system) for product
inputs from Visakha Refinery located at approx. 4 -5 Kms from the
plot; Power supply for the proposed will be sourced from the nearest
APSEB Substation/transformer.
A tentative layout plan (Annexure II) showing the facilities proposed is
enclosed. The Plan is to provide general guidance regarding the scope
of facilities proposed and it is likely to be revised as per the actual
requirements. The layout of the facilities shall confirm to OISD-144.
Storage Tanks: Mounded LPG Storage for LPG, Auto LPG, propylene
and vertical mild steel storage tanks without roof for Fire water. Please
note the following:
• Design of mounded storage can be kept in the scope of vendor
(mechanical design will be provided by HPCL).
• BQ plates for mounded storage and Steel plates for Fire water
tanks shall be procured by HPCL, including third party inspection.
• If bidder is not a PESO approved third party inspection agency for
mounded LPG storage works, they shall outsource the same to an
approved agency, who shall do stage-wise inspection and issue
certificate of control for the pressure vessels.
• All third party inspection, apart from above, shall be in scope of
EPCM consultant.
Loading/ Unloading Pumps: Vertical canned LPG /propylene
Loading/ unloading pumps coupled with FLP motors are to be installed
in the pump house. Pumps of adequate capacity to be selected based
on the flow requirement of loading / unloading.
Tank Truck Unloading/Loading Gantry: Each loading bay shall
have provision for loading one product( LPG in 4 bays, auto
LPG/propylene in one bay each). Loading shall be done in the tank
trucks thru automated flowmeter, batch controller, loading arms etc.
Tank truck unloading arrangement shall also be provided as required.
Invoicing shall be on the basis of weight measured on weighbridge.
Provision shall be made in headers/ piping to be made for using each
bay for another product.
Tank Wagon Loading Gantry: Each loading bay shall have provision
for loading ( 1 product). Product shall be loaded in the tank trucks thru
automated flow meter, batch controller, loading arms etc. Tank wagon
unloading arrangement shall also be provided as required for sick tank
wagons.
Product receipt and delivery: The product shall be received from
refinery/SALPG and shall be bottled in cylinders or distributed in tank
trucks and tank wagons. In additional there shall be pumping to GAIL’s
Visakh Secunderabad pipeline. Connectivity by tapping into GAIL’s
pipeline (approx. 700m away) and pumping arrangement and well as
bottling and dispatch facilities shall be provided.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 6 of 36
Fire fighting System: Entire installation shall be covered with
fire/heat/gas detection systems and fighting system as per OISD –
144/150.
Please note that the LPG Terminal will have common fire
fighting system with White Oil terminal which shall be
constructed (not in scope) adjacent to the LPG terminal.
Design, execution and commissioning of the entire fire fighting system
shall be in the scope, except all mechanical and piping work (hydrant
network including fixing of hydrants/monitors, foam systems, sprinkler
systems) within the White Oil terminal.
Automation System: The LPG Terminal shall be fully automated.
Automation shall cover automation of the tank farms,
loading/unloading of the tank trucks, TT entry system, operation of fire
fighting system and security system.
Office and other amenities / Plant buildings: Office, security
room, invoicing room, canteen, workers’ change room, godown, MCC
room, DG room, fire pump house, product pump house etc. to be
constructed at the Terminal. The buildings shall be integrated basis
the functional requirements and shall be well designed architecturally,
for elegant appearance and pleasing finish. The Administrative
building shall be Green Certified.
Roads, Drains & leveling of plot: Entire installation shall be
provided with adequately wide roads and drains and side development
for proper water drainage. The plot should be raised to requisite level
prior to formation of roads and site gradation shall be designed to
provide proper drainage. Please note that tender for land development
shall be floated and finalized by HPCL. Supervision of land
development job shall be in scope of consultant.
Electrification: Electrification system to be designed and provided as
per the Central Electricity Rules and guidelines of APSEB. All HT system
and LT system to be suitably designed for meeting the operational
requirements of the Terminal There should be provision of DG sets of
adequate capacity as standby source of power. Energy saver/
intelligent lighting/VFD and also utilization of non conventional energy
viz Solar energy shall duly considered and included in the system.
Development of Green Belt: Adequate area of Green belt to be
developed in the Terminal as per the guide lines and the requirement
of the local PCB (Pollution Control Board) and MOEF (Ministry of
Environment and Forests). Terminal should have adequate coverage of
Lawns and flower beds to provide excellent land scaping to ensure Soil
conservation and also water conservation by providing Drip irrigation
and sprinkler systems where ever feasible.
Effluent treatment plant: Effluent treatment plant of required
capacity to be installed at the Terminal in line with the requirements of
the PCB.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 7 of 36
Telecommunication system: Entire LPG Terminal shall be covered
by telecommunication system, Internal and external paging system
and VHF sets and the three systems shall be interconnected. However
interconnection between the Installations may be limited to LPG and
POL facilities.
Turnkey Instrumentation: For all Pumping / receiving / and other
places where ever Interlock logics are required for both product
pumping operations and Electric substation operations, PLC based
turnkey instrumentation systems to be installed. SCADA shall be
developed for the existing LPG line and the same integrated with the
proposed lines from refinery to out Plant.
Piling work: The job shall include necessary design and supervision of
piling work as applicable for foundation of various structures.
Railway sidings: It may be noted that consultancy for construction of
railway lines to VPT connecting points and siding gantry structure is not
in scope of this tender. However, piping, loading arms, electrical, fire
fighting works, gas monitoring systems, and emergency response
systems are included in scope .
3.0 SCOPE OF WORK
The scope of work is divided mainly under following heads but not to be
limited to the following:
• Planning, designing of facilities
• Finalizing the specifications
• Procurement of materials / equipments
• Floating and finalizing the tender enquiry as per the procedure laid
down in this Tender. E tendering of all major tenders is preferred
• Supervision of the execution of work orders
• Handling and accounting the materials received at site
• Timely certification of bills for releasing payment by HPCL
• Co-ordination with HPCL, suppliers, contractors, for expediting
supplies/works
• Assistance in Capitalization of total cost of all assets
• QC/Inspection/Testing and maintaining of records as required by
the statutory and inspecting authorities like CTE, HPCL auditors etc
• Maintaining of records on behalf of HPCL as required by the Labour
inspectorate and factories inspector etc that are to be maintained
by the principal Employer
• Safety during construction
• Obtaining Green Certification for buildings proposed to be Green
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 8 of 36
3.1 Basic design and description:
Consultant shall deploy qualified personnel to carry out Basic Design,
Detailed Engineering of individual facilities to facilitate action on
procurement of materials/equipment and finalisation of specifications for
works/service contracts. While doing so, Consultant shall ensure proper
integration of all Project facilities.
3.2 Preparation of process package covering the following items:
1. Design basis
2. P&IDs.
3. Process Flow Diagram.
4. Equipment list and process data sheets.
5. Instrument list and data sheets.
6. Utilities requirement and their specifications.
7. Material specifications.
8. Operation and control philosophy
Midway through Basic Design, the Consultant shall advise Owner the
requirements of water and power for operating the various facilities of the
Terminal:
4.0 DESIGN STANDARDS
The following design standards shall be used as a minimum in the
Scope of work:
4.1 Published standards:
Indian Standards:
Oil Industry Safety Directorate (OISD)
Tariff Advisory Committee (TAC)
Bureau of Indian Standards (BIS)
(In case of conflict among Indian standards or with International
standards, owner should be consulted for deviations, which may have
impact of cost as per the opinion of the Consultant)
4.2 International Standards:
ANSI
ASME
ASTM
API
OCIMF
ISA
NACE
EEMUA
Automation international standards.
4.3 Owner supplied Standards/ Documents:
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 9 of 36
The following Owner supplied design standards/documents shall, in
addition to the above, form the basis of the work:
1. Brief regarding the Operational philosophy and facilities to be provided .
2. Petroleum Product specifications.
3. Soil Investigation report.
4. Survey details of the plot, Contours etc.
5. Pipeline route survey.
6. Relevant part of the DFR report
5.0 STUDIES TO BE PERFORMED
The following process and engineering studies are to be performed as a
part of the Work but not be limited to the following:
1. Design of the tanks and mounded storage
2. Design of external piggable pipe lines - CP system.
3. Sizing of Internal Pipeline / Optimisation of pump head.
4. Optimisation of Drives for various pumps including Fixed motor drive,
Variable Speed Drives etc.
5. Design of the mechanical structures.
6. Design of the electrical equipments.
7. Architectural / structural drawings for various buildings / Structures/sheds
for LPG Plant.
8. Site grading plan, plinth levels of structures / tank pads and layout of
roads / storm water disposal / sewage disposal.
9. Fully automatic Fire Fighting facilities (including integration of hydrant/
sprinkler network of White Oil Terminal).
10. Heat tracing and insulations for tanks and pipelines.
11. Development of Green belt and environmental protection plan.
12. Conveyors, filling and testing and auxiliary equipment for storage,
handling and bottling of LPG cylinders.
13. Crushing facilities for condemned cylinders/ regulators and cold repair of
cylinders.
14. Facilities for Mandatory periodic retesting and painting of LPG cylinders.
15. Providing Gas monitoring system and heat/fire detection systems for LPG
Plant and integrating the same with Fire fighting system for automatic
response in case of emergencies.
6.0 DESIGN REVIEW(S)
Formal periodic review (every two weeks) and informal reviews (on issue
of drawings, details, etc at site) shall be held, wherein the plan / design
work shall be required. Consultant shall provide time and personnel to
participate in these reviews.
7.0 DOCUMENT REQUIREMENTS
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 10 of 36
The following document/review requirements during the performance of
the Work shall be met:
1. Documents for Approval:
Three copies of all documents are required for Owner’s approval.
2. Drawings for Approval:
Each drawing shall be approved by the Owner.
3. Studies for Approval:
The studies listed in the section STUDIES must be submitted as draft
reports and not as notes for approval.
4. Approval Turnaround:
Owner shall have fourteen days of review to make comments or approve
all documents / drawings.
5. Final Approved Documents & Drawings and Studies :
Eight copies of the final approved documents, full size & shot down
drawings and studies are required. Floppies/CDs and CAD diskettes shall
also be provided.
C. EPCM SERVICES IN PROCUREMENT AND MATERIALS MANAGEMENT
OF MATERIALS AND EQUIPMENTS.
Consultant shall provide procurement & materials management services
for all Materials and Equipments required for completion of the work.
The scope shall include but not be limited to:
1. Developing detailed procurement procedures, in consultation
with the Owner.
2. Establishing vendor lists.
3. Preparing and floating tender enquiries.
4. Follow-up and review of responses.
5. Recommendation on placement of PO/WO.
6. Approval of Drawings/Designs submitted by suppliers.
7. Monitoring of the progress of procurement.
8. Inspection of materials / equipment.
9. Maintaining the inventory of materials and statements of
reconciliation.
Please note that all Third party inspection of materials/ equipment
shall be in the scope of EPCM vendor (except MS Steel plates and Boiler
quality steel plates at manufacturers’ premises).
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 11 of 36
Procurement Procedure:
A detailed procurement procedure shall be prepared immediately after
award of contract submitted to Owner for approval. In general the
procurement procedure should be in line with the Existing Purchase
policies and procedures of the owner. The same will be shared with
consultant upon award of contract.
The tenders shall be preferred to be floated through E tendering and the
“Purchase request” to “Purchase Order” time shall be Bench Marked as 45
Days.
Quality Assurance:
Consultant’s participation in the quality assurance program will focus on
the vendor’s compliance with applicable quality control measures.
Vendor List:
A vendor list is to be prepared for supply of Materials and Equipments in
consultation with HPCL. This list will be based on Consultant’s experience
& HPCL enlisted vendor list with Indian and worldwide vendors. Wherever
feasible, the endeavor shall be to include as many Indian vendors as
possible. The vendor list is to be submitted for approval by Owner.
Warranties and Guarantees:
Consultant shall obtain from the vendors, the best possible warranties and
guarantees covering workmanship and materials for the benefit of Owner.
Sourcing of Materials and Equipments:
Indian sources of supply shall be solicited for material based on the Owner
approved vendor list. Any decision to purchase materials outside India for
reasons of schedule conflict, lack of competitive pricing or critical nature
of the materials will be subject to Owner’s review and concurrence.
Cost Estimate:
Consultant shall prepare item wise cost estimate for each material
requisition. This cost estimate will form the basis for comparison of bids
and negotiations, if required.
Tender Enquiries:
A central procurement team is to be assigned by the Consultant to
manage and conduct the purchase of all equipments and materials. It is
proposed to procure various important materials like steel plates, pipes,
pumps, valves, equipments directly and float tenders for works contract
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 12 of 36
on integrated package basis. Such packages may include the different
types of works and shall be discussed with the owner and finalised in line
with the requirements.
Tender Inquiries are intended to be prepared and floated for all the
material/works required for completion of project, preferably in e-
tendering.
Consultant will be responsible for issuing Tender enquiries to those
vendors on the approved vendor lists, expediting receipt of quotations,
evaluating the bids and submitting recommendations to Owner for
approval.
Enquiries shall, generally, be issued to sufficient number of vendors on
two bid basis, so as to ensure receipt of competitive bids from them or
from more acceptable vendors, unless the number of vendors on the
approved vendor list is specifically limited or where a sole source is
stipulated in the Project specifications.
Public/Global Tenders shall be invited in case of insufficient number of
approved vendors (less than min. 6 Nos.) or for specialized items /
equipments or for procurement tenders whose value is over Rs.300 Lakhs.
With out prejudice to the above, Owner reserves the right to decide the
nature of tenders to be floated for various procurement items and
consultant shall abide by the Owner’s decision.
Bids will be solicited directly from manufacturers except where trade
practice in specific geographical locations necessitates the use of
distributorships.
All requests for quotations shall be prepared in English and shall contain
the requirement that formal proposals also be submitted in English.
Inspection by Consultant or a duly authorized third party on behalf of
Consultant will be indicated on all enquiry documents.
Evaluation of Bids:
Consultant shall techno-commercially evaluate the Bids to assess the bid’s
compliance with the technical specifications and commercial terms and
conditions.
Consultant shall ensure that all information received from vendors of
either a commercial or technical nature will remain confidential and will
not be disseminated to unauthorized persons.
Consultant shall prepare technical evaluation sheet indicating comparison
between specification of materials/equipments required and offered by
various vendors clearly bringing out technically acceptable and not
acceptable deviations with reasons thereof.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 13 of 36
The commercial evaluation sheet shall include, but not be limited to, the
following information:
a. Requisition and item number.
b. Equipment or tag number.
c. Brief description of equipment or materials.
d. Quantity.
e. Comparison of delivery promise with required delivery period.
f. Validity of quotation.
g. Terms of payment.
h. List of exceptions to Terms and conditions.
As deemed necessary by Consultant, pre-award meetings shall be scheduled
with vendors to ensure that all aspects of the inquiry and proposal have been
properly interpreted and evaluated.
Purchase Recommendations:
At the conclusion of the techno-commercial evaluation phase, an evaluation
sheet shall be prepared by consultant and submitted to Owner for approval
before opening of the priced bids. On receipt of Owner’s approval, Consultant
shall open Priced bids in the presence of Owner’s representatives as necessary
and shall prepare price evaluation sheet. The consultant shall submit
recommendations for placement of order on the selected vendor on the basis of
price evaluation. Upon approval of purchase recommendations by Owner, a Draft
Purchase Order (DPO) including Purchase Requisition (PR) shall be submitted by
Consultant to Owner for releasing Purchase Order on the successful vendor.
DPOs will include a statement that the equipment concerned is subject to
inspection and the Owner’s representatives will have access to the supplier's
work during all stages of manufacturing/testing.
Review/Approval of Supplier Data/Drawings/Design:
Consultant shall ensure expeditious submission of data/drawings/designs by the
supplier and review the same within 10 days of receipt at Consultant’s office.
Inspection:
The proper control of purchased materials includes both expediting and
inspection of materials throughout the manufacturing cycle. The objective of this
material control effort is to ensure that such fabrication of manufacture is
accomplished in accordance with the technical requirements and specifications of
the project. Accordingly, inspection shall be performed by Consultant or
Consultant appointed organizations approved by Owner and statutory bodies in
accordance with data sheets, drawings, and specifications incorporated in the
commitment documents transmitted to the vendor.
Materials Management:
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 14 of 36
Consultant shall be responsible to Owner for materials management for goods
purchased from various suppliers. Consultant shall keep proper custody of goods
and report losses / damages / shortages, if any, to the Owner immediately on
noticing the same. Consultant shall be required to submit the stock report on
weekly basis after due verification. Owner will provide necessary security
personnel for stores / stockyards at Owner’s cost, who will report to the
Consultant’s stores manager. However any loss due to theft shall be brought to
the notice of HPCL within 24 Hrs of the incident. It shall be the responsibility of
the consultant to ensure the same.
The various project materials shall be located at the Visakha LPG Project site.
The scope of Materials Management Services to be provided by Consultant shall
include, but not be limited to, the following:
1. Receive equipments / materials from suppliers and certify their invoices
for payment.
2. Inspect the condition of goods received and issue ‘goods receipt vouchers’
to suppliers / transporters.
3. Maintain a register of suppliers covering all equipments and materials
distinguishing between manufacturers / stockists / supply houses.
4. Provide a unified materials coding system including catalog structure and
compatability with other systems.
5. Prepare and submit reports every week indicating the stores on hand,
goods in transit, goods issued to contractors and balance goods to be
received as per respective purchase orders .
6. Maintain stores at site to properly store all the equipment / material and
certify bills of handling contractors and transporters. The space for storing
equipment / material and the office space for stores manager / assistant
shall be provided by Owner. Cost of all labour for handling material /
equipment in the stores and cost of transportation of materials from
delivery point to stores shall be to Owner’s account.
7. Issue material for construction to contractors and prepare ‘goods issue
vouchers’ thereof.
8. Receive unused material returned by contractors and prepare goods
returned vouchers’ thereof.
9. Prepare reconciliation statements to enable Owner to check and take over
the balance stores.
10. Separate material/equipment utilisation statements (with value) for jointly
identified list of capital asset items to be submitted at the end of the
project to facilitate Owner do proper capitalisation of assets.
11. A Material Manager shall be identified in the HQO of the consultant who
shall be responsible material planning and receipt of all bought out items
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 15 of 36
and also vendors bought out items at site in line with their requirement.
He shall be required to take all corrective action to ensure material is
received in time and there is no stoppage of job due to material
shortage/non availability.
D. SCOPE OF PROJECT MANAGEMENT SERVICES:
Article 1. Scope of Project Management Services -
Overview.
Article 2. Preparation for Work contracts.
Article 3. Quality Management.
Article 4. Project Implementation Procedure.
Article 5. Cost Control.
Article 6. Project Planning, Control and Progress
Measurement.
Article 7. Management Control and Reporting
Structure.
Article 8. Inspection.
Article 9. Engineering.
Article 10. Construction.
Article 11. Commissioning, Startup and Performance
tests.
Article 12. Acceptance
Article 13. Initial Operation and Training
Article 14. Health, Safety and The Environment.
Article 15. Documentation.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 16 of 36
ARTICLE 1
SCOPE OF PROJECT MANAGEMENT SERVICES - OVERVIEW
In addition to providing the engineering, procurement services for the
Materials and Equipments described in the EPCM Services, Consultant
shall establish a team for the Engineering and Project Management
Services consisting of members with all the necessary skills and discipline
needed for professional management of the Project on behalf of Owner.
Members of the team shall be stationed at the project site for efficient
management of the Project.
In general, Consultant shall act and be responsible, for managing the
overall Project in detail and directing various contractors and others on
behalf of Owner, for taking or recommending all appropriate action to
complete the Project on time and within budget. The following indicate the
minimum activities the Project Management Services are likely to
comprise which include, without limitation:
a. Preparation of Anticipated Final Cost (AFC) of Project value within two
months of appointment.
b. Preparation and issue of tender documents, tender evaluation and
recommendation of award and administration of such other contracts as
are needed for the Project; It may be necessary to float Tenders on LSTK
basis to expedite the works as decided by HPCL.
c. Preparation of itemwise cost estimate.
d. Administration, on behalf of Owner, of all contracts placed for execution of
the Project;
e. Timely release of “Approved For Construction Drawings” to enable
contractors to maintain agreed schedule of work;
f. Coordination of the activities of various contractors engaged by Owner for
the engineering, procurement and construction of the Project to assure
effective project execution particularly at points of interface between
respective contractor’s activities;
g. Monitoring, appraising and reporting to Owner on the cost estimation and
cost control performance and scheduling, and schedule control
performance of all contractors;
h. Development and maintenance of an appropriate system for control of
documents relating to the Project including drawings, specifications,
letters, memoranda and other administrative records but particularly
those certificates, operating and other manuals and other documentation
to be retained for maintenance, operational or statutory reasons by Owner
on completion of the Project;
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 17 of 36
i. Monitoring, appraising and reporting to Owner on the quality and safety
aspects of engineering design and construction by all contractors involved
in the Project;
j. Compliance to labour laws and other statutory requirements with regard
to Construction works.
k. Monitoring the progress of various works using ‘S’ curve method.
l. Capitalization of the assets.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 18 of 36
ARTICLE 2
PREPARATION FOR WORK CONTRACTS
The Basic Design and Detailed Engineering work done by Consultant
should lead to developing a Design package comprehensive enough for
inviting contract bids for various works for Visakha LPG Terminal Project.
Midway through the Detailed Engineering work, Consultant shall prepare
draft Invitation to Bid for respective work contracts/ Services and submit
the same for Owner’s approval. The basic inquiry principles like type of
contract, bidding limit dates, conditions of payments and various other
controlling parameters will have previously been proposed to Owner and
approval obtained prior to issuance of final ITBs.
The tenders shall be preferred to be floated through E tendering and the
“Purchase request” to “Purchase Order” time shall be Bench Marked as 45
Days.
1. Pre qualification of Contractors:
Consultant shall prepare document for pre-qualification of bidders and
obtain approval of Owner for the same. The pre-qualification criteria shall
be published in Newspapers for estimated contract values exceeding
Rs.300 lakhs for inviting bids from prospective bidders meeting the pre-
qualification criteria or through E tendering. Consultant shall obtain
Owner’s approval for sending tender inquiry to the pre-qualified bidders.
Consultant shall evaluate Prequalification Documents and obtain Owner’s
approval for opening / evaluating Techno-Commercial bids of pre-qualified
bidders.
For estimated contract values less than Rs.300 lakhs Limited tender
inquiry shall be floated by Consultant to contractors drawn from vendor
list maintained by Owner / Consultant. Such list has to be approved by
Owner prior to floating the Tender.
2. Preparation of tenders:
Based on the Detailed Engineering, Consultant shall propose draft tenders
for work contracts/ Services and upon approval of the same by Owner,
release the same to prequalified bidders.
The tenders shall contain detailed technical specifications and terms &
conditions to facilitate submission of unambiguous bids.
Consultant shall structure the tender to include but not limited to the
following:
- Instructions to Bidders.
- Scope of work.
- Conditions of contract.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 19 of 36
- Engineering/ Technical specifications and drawings (which will include
but not be limited to ) depending upon their applicability for respective
tender.
� Project design data (Hydrographic, Geotechnical and Meteorological),
soil bearing, battery limit conditions, etc.
� General engineering standards, specifications, codes and local customs
regulations and/or agency requirements.
� Process flow diagrams (PFDs) where ever applicable.
� Process description.
� Preliminary plot plans and layout.
� Process and instrumentation diagrams (P&IDs).
� Equipment lists.
� Technical data sheets of equipment and machinery.
� List of materials / equipments included in contractor’s scope.
� Specification of supply items included in contractor’s scope.
� Instrument lists.
� Detailed specifications of works.
� Electrical single line diagrams.
� Safety instructions and basic design data for fire fighting.
� Job procedure instructions.
� Environmental considerations.
� Preliminary Drawings to enable the bidder to quote.
- Bill of quantities (BOQ).
- Schedule of Rates (SOR).
- Construction specification.
- Testing and inspection requirements.
- Commissioning procedure.
- Acceptance procedure.
The tender will specify a comprehensive training program for the Owner’s
personnel pertaining to Turnkey Instrumentation, Automations etc. to be
able to operate and maintain the Project facilities. This training program
will be provided by the contractors and will be organized under the
guidance of the Consultant.
3. Evaluation of Bids:
The evaluation of bids against each tender shall be done in five
Stages as described below:
First Stage:
After Unpriced Bids are opened, the Consultant shall check that the
required documents have actually been supplied and duly signed, that the
period of validity is correct and that the bids as a whole are correct.
Second Stage: Techno-commercial evaluation of Unpriced Bids.
The detailed review shall concern:
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 20 of 36
- Scope of services and supply.
- Compliance with the technical requirements set out in the project
specification.
- Compliance with commercial and general terms and conditions.
- Compliance with Acceptance Procedure.
Third stage:
The Consultant shall submit detailed evaluation sheet of unpriced bids to
owner clearly specifying the technical and commercial acceptability/non-
acceptability of offers. Upon approval by Owner, the price bids of
technically and commercially acceptable parties shall be opened by
Consultant.
Fourth stage:
Detailed review of price bids.
- Basic price including break-up in INR and respective Foreign
Currency, quoted against BOQ in the SOR.
- Unit rates.
- Delivered Cost.
Fifth stage:
After completion of price evaluation, a purchase recommendation shall be
submitted to Owner.
Upon decision by Owner on bidder with whom negotiations are to be done,
the Consultant shall assist Owner in this process.
4. Draft Agreement / Draft Purchase Order
Upon approval of purchase recommendations by Owner, the Consultant
shall submit Draft Agreement / Draft Purchase Order to Owner.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 21 of 36
ARTICLE 3
QUALITY MANAGEMENT
Consultant has overall responsibility to Owner for quality management
throughout the Project. Consultant shall prepare an integrated overall
Quality Assurance Program (QAP) which satisfies recognized international
standards approved by Owner e.g. ISO, BS, ASME, OISD, ASTM, API etc.
Consultant shall have an established quality management organization
which shall be responsible for monitoring and auditing compliance with the
QAP throughout the whole Project. The organization shall comprise
sufficient numbers of suitably trained and qualified staff to ensure that all
requirements of the QAP are satisfactorily implemented by the
Contractors.
The QAP shall cover, but shall not be limited to:
a. Verification and approval of methods used and documentation
produced during engineering and construction work;
b. Inspection, handling and identification of equipment and materials,
and proper documentation ;
c. Field inspection and testing procedures;
d. Operating, maintenance and training manuals.
Owner reserves the right, with due notice, to carry out audits of
Consultant’s activities for compliance with QAP.
ARTICLE 4
PROJECT IMPLEMENTATION PROCEDURE
The Project Implementation Procedure shall include, but shall not be
limited to the following:
1. The overall management information system and interface
philosophy to be used in the Project.
2. Consultant’s co-ordination Mechanism: Including correspondence,
contact persons, correspondence format and system; Administration
of instructions and inspection reports, Review of designs and
technical detailing; Reports on project cost control, estimates and
progress; Document control, safety review procedures, field
inspections and acceptance test.
3. List of reports to be submitted by Consultant to Owner. Formats of
these reports.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 22 of 36
4. Co-ordination procedures for contracts including procedures between
contractors, Owner and Consultant.
5. Procedures for:
- Safety and technical audits.
- Quality management at various stages.
- Construction supervision and inspection.
- Schedule control.
- Cost control.
- Document control and handing over to Owner.
6. Plans for monitoring contractors’ activities at each stage.
7. Summary Project schedule.
Consultant shall critically review and obtain approval from Owner for the
above Project Implementation Procedure within two months of award of
contract.
ARTICLE 5
COST CONTROL
Consultant shall provide a comprehensive control service using a Work
Breakdown Structure (WBS) which is compatible with job control and
planning requirements, and a Cost Breakdown Structure (CBS) which is
compatible with Owner’s accounting code structure. All coding structures
are to be approved by the Owner.
1. Reporting:
The following reports are to be generated by Consultant for Owner
on the basis of its own observations and reports received from other
contractors and suppliers of long lead items:
Cost Reports: Consultant is to provide monthly, a comprehensive
cost report set out in accordance with WBS/CBS. The cost report is to be
summarized to an intermediate level into logical Project areas for other
contracts and supply items and then summarized further into a top level
management reporting summary. These reports shall show the following
information as a minimum requirement:
(a) Initial control estimates
(b) Current control estimates
(c) Expenditure to date (Value of work done)
(d) Estimates of work to be completed
(e) Anticipated final cost (“AFC”);
(f) Over/under run of AFC against current control estimate;
(g) Expenditure for the period;
(h) Commitment to date (approved purchase requisition value);
(i) Commitment for the period;
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 23 of 36
(J) Value of invoices paid.
Anticipated Final Cost: Consultant shall regularly review the AFC of
the Project. The implications of these reviews shall be discussed with
Owner prior to the monthly input into Consultant’s reporting system.
Explanation of variances shall be provided on a monthly basis.
2. Expenditure:
Consultant shall maintain the records of expenditure, all in accordance
with the WBS/CBS, the following information:
(a) Expenditure (the value of work done and materials received to
date);
(b) Phasing of expenditure forecasts;
(c) Explanation of variance between planned and actual expenditure.
Consultant shall submit with the monthly cost report total project
expenditure curves showing actual expenditure plotted against planned
expenditure.
3. Asset Register:
Consultant shall compile and update monthly an asset register including
cost of each asset for the complete Project for hand over to Owner on
completion of the Project. Consultant shall submit quarterly reports
indicating assets completed during the period and on cumulative basis and
cost thereof.
4. Diary of Events:
Consultant shall maintain a Chronological Diary of Events recording all
major milestone achievements. This shall be appended to monthly
reports.
ARTICLE 6
PROJECT PLANNING AND CONTROL AND PROGRESS MEASUREMENT
The Consultant’s responsibilities in terms of project planning and control
are twofold. First, the Consultant shall ensure that the various contractors
develop and maintain a comprehensive planning, progress monitoring and
control service as required by contract. Second, the Consultant shall
operate a similar service, at summary level, that interacts directly with
systems used by the contractors and provides the vehicle for informing
Owner of all aspects of Project scheduling, progress and control. The
service shall incorporate modern systems and techniques for the
acquisition, analysis and presentation of data. The Consultant shall ensure
that the service is compatible with similar service on the Project and that
program and progress charts align with the approved WBS for the Project
in such a manner as to facilitate the establishment of a clear, hierarchical
path from detail to summary level.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 24 of 36
The principal objective of the planning service is to provide an effective
work planning and control system. Physical progress against work
packages shall be measured and reported, highlighting trends and actions
required to maintain or improve progress. Future activities shall be
reviewed in advance of execution to ensure sufficient data and resources
are available to maintain the project schedule.
1. Project Master Schedule:
Consultant shall submit to Owner for approval prior to award of the
contract, a Project Master Schedule that shall clearly identify all project
milestones and targets and reflect the Consultant’s Tender Schedule.
Subsequent to approval by Owner the schedule shall be used as the
management control schedule for the Project and shall be updated and
issued monthly. The schedule shall be developed as a summary critical
path network and be presented as a logic-linked bar chart.
The master schedule shall define in appropriate detail the sequence and
timing of work packages and activities by which the services shall be
performed and by which progress shall be monitored. Where necessary it
shall identify all key interactions, reviews and approvals between suppliers
and the other contractors, outside agencies, and third parties to ensure
uninterrupted progress to timely Project completion. In line with the
project WBS, the master schedule shall be updated using details
generated at lower level in terms of physical progress achieved.
An essential part of the schedule submission shall be a
Cost/Time/Resource (CTR) activity catalog, prepared to an agreed format,
showing scheduled start and finish dates, resource requirements,
dependencies and deliverables as a minimum.
2. Trend Reports:
Consultant shall highlight and give early warning of trends to result in
deviations from Project activities/schedules/cost, identifying the reason,
and reporting the appropriate remedial actions taken to Owner.
5. Exception Reports:
Consultant shall provide a report itemized in conjunction with the master
schedule declaring any activities behind program at each update and
defining contract discipline, delay to the Project and reason for the delay.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 25 of 36
PROGRESS MEASUREMENT
Achieved progress shall be based on a detailed physical assessment of
work done, in percentage terms, and summated to contract and project
summary level, using assigned weightages, Consultant shall be
responsible for making sure that the physical progress measured is a fair
reflection of work status and that summations are accurately calculated.
1. Progress “S” Curves:
For reporting purposes, Consultant shall maintain a composite set of
progress S curves and tabulations that show, by major elements, planned,
achieved and forecast figures.
2. Updating:
At monthly intervals during the life of the Project, Consultant shall update
all summary progress documents using, where necessary, detailed figures
produced by the contractors. Consultant shall update the project master
schedule monthly using a superimposed time on line that indicates
slippage to each element of the Project and to the Project as a whole.
ARTICLE 7
MANAGEMENT CONTROL AND REPORTING STRUCTURE
This Article describes Consultant’s responsibilities with respect to
management control, co-ordination and reporting of the Project Scope of
Work. Proven computer systems shall be used to assist with these
functions, and agreed coding structures shall be used to integrate service
functions and ensure compatibility of contract and Project systems.
1. WBS:
The WBS is a Project model providing a framework for management
of the scope. The model shall be used to define the Project in a
manner that facilitates the integration of all functions and progress
assessment at detail and summary levels. Deliverables and services to be
provided under the various contracts and by third parties shall be
assigned to work packages and, at a more detailed level,
Cost/Time/Resource (“CTR”) activities. Proposed work packages and CTRs
shall form the essential structure of the Project and control programs and
their breakdown will depend on the other contractors work organization
and methods.
Here it may be noted that the three parts may be executed and controlled
as three different projects with different project groups with one
controlling office for over all control. The scope of job at the inter
connections shall be clearly specified with battery limits.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 26 of 36
2. Coding Structure:
The Project coding structure shall be developed by the Consultant within
two weeks of award and include work package, CTR, discipline, area and
system.
3. CTR Activities:
CTRs shall be used to plan and control the execution of services under the
various contracts and, where necessary, in other areas of the Project. It
shall be the Consultant’s responsibility to ensure that the other
contractors submit CTR catalogs as required by contract, and that the
following information is included on each CTR sheet as a minimum:
(a) Code and description;
(b) Reference to inputs required to perform the activity;
(c) Output deliverables generated as a product of the CTR;
(d) Reference to other CTRs which are dependent on the completion of
the current activity;
(e) Estimate of man-hours and cost by discipline for the CTR at both
detail and summary level;
(f) Work package and program reference;
(g) Scheduled start and finish dates.
4. Reports:
The following lists the reports to be provided as part of the Consultant’s
services:
Weekly Report: At the end of each week during the Project, Consultant
shall report to Owner by e-mail. The essential information in the report
shall be:
(a) Main events, problem areas and remedial actions during the
Week;
(b) Information and decisions urgently required by the contractors.
Monthly Report: Consultant shall prepare a comprehensive monthly
progress report with a cutoff on the last Friday of each month. The report
shall be delivered to Owner within six working days following the cut-off.
The format and content of the report shall be agreed with Owner and, as a
minimum, contain the following information:
(a) A summary statement on the Project, highlighting Problem areas
and remedial actions (with their impact on schedule/cost analyzed
through computer schedule network vis-a-vis alternatives
available); achievements made during the month shall be itemized
and compared against the plan;
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 27 of 36
(b) A Statement on procurement referring to material /equipment
control schedules and indicating activities that have slipped or
become critical;
(c) A statement on construction, citing achievements in the period, with
an explanation of deviations from the program, problems
encountered and remedial actions. This shall cover status of the
work relative to the program, including variations and subcontracts;
(d) Cost report;
(e) QA report;
(f) Graphical and tabular section containing:
- Updated project master schedule;
- Progress S curves for design and construction showing
planned and achieved figures for the various contracts;
- Summary tabulations showing the status of
deliverables/drawings, procurement of materials, equipment
and procedures;
- Interface matrix showing data urgently required by various
contractors.
5. Project Systems:
Consultant shall monitor the other contractors’ project information
systems throughout all phases of the other contracts to ensure
compliance with the overall Project systems strategy detailed in other
areas of this ITB and shall monitor the delivery and integrity of
electronic data between the other contractors, Consultant and Owner.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 28 of 36
ARTICLE 8
INSPECTION
Consultant shall be fully familiar with the guide lines as requirements to be
complied with; as stipulated by the statutory bodies, relevant codes / Standards
for Certification. Where inspection is required, it will be carried out by
Consultant/Consultant approved organizations who meet the approval of Owner
and the statutory bodies concerned.
ARTICLE 9
ENGINEERING
1. Detailed Engineering:
Consultant shall ensure that all specification, drawings and requisitions
are produced in a timely manner in accordance with contract.
Consultant shall review and approve, on behalf of Owner the
drawings/designs submitted by contractors pertaining to the design
facilities included in the contractors’ scope. Consultant shall endeavor to
approve designs/drawings submitted by various contractors in the
shortest possible time but not later than 15 days. Any delay beyond 15
days shall be brought to the notice of Owner, along with reasons.
Consultant shall ensure compliance with all statutory rules and
regulations, in particular national regulations concerning environmental
protection, labour laws.
ARTICLE 10
CONSTRUCTION
Consultant shall manage and supervise contractors’ activities at site and
coordinate with contractors, such that the construction of the Project is
carried out by the contractors according to the procedures and quality
assurance program agreed between Owner, Consultant and the
contractors.
Consultant shall be deemed to have full knowledge of the applicable codes
and standards, laws and regulations, safety rules and regulations,
conditions of labour, local conditions and environmental aspects as
applicable in the State of Andhra Pradesh and also at National level, and
shall comply with the requirements thereof where applicable.
Consultant shall assign construction specialists at site to ensure that the
Project is built according to the time schedule and to approved codes and
standards, specifications and drawings. These activities shall include, but
not be limited to, the following:
I. Coordinate the activities of contractors.
II. Review the contractors’ plans and make recommendation to Owner on
the actions to be taken to maintain schedules;
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 29 of 36
III. Review and recommend regularly on contractors’ allocation of manpower
and construction equipment;
IV. Review and approve, on Owner’s behalf, contractors’ work methods, with
special emphasis on safety and quality ;
V. Review and approve the procedures proposed by contractors for the
inspection by Consultant of each item
VI. Supervise, inspect and certify that quality of the contractors’ work to
ensure that all work is adequate for the purpose intended, is in
accordance with good engineering and construction standards and
practices, drawings and specification, and is in accordance with the quality
assurance program and conforms to the provisions of the contract;
VII. Ensure that adequate records are maintained at site by respective
contractors.
VIII. Review and certify the contractors’ bills. Certify and recommend to Owner
on the progressive payments of the work according to the work
completed;
IX. Supervise on behalf of Owner and agree with contractors on a phased
completion program, to facilitate a logical, mechanical completion of
works.
X. Review contractors’ detailed proposals for the startup and the conduct of
the performance tests, and advise Owner and the contractor accordingly
to ensure that all the activities will be carried out in a safe and efficient
manner.
XI. Supervise close-out of contractors’ work and certify and make
recommendations to Owner on the acceptance of construction completion
certificates, mechanical completion certificates, provisional acceptance
certificates and final acceptance certificates for the Project, by plant
system unit and block as relevant.
XII. Supervise all works requiring modifications as requested or approval by
Owner in accordance with the standard procedure.
XIII. Review and recommend safety and labour relations procedures prepared
by other contractors in line with all applicable codes, regulations and
Owner requirements. Monitor safety and labour relations and take action
on behalf of Owner on all problems, violations and inquiries;
XIV. Inspect and record site activities and oversee that documentation is kept
up-to-date and in first rate condition in preparation for completion of the
Project. Consultant shall ensure that all as- built drawings for the Project
are recorded correctly and compiled and submitted by the contractors as
stated in the contract. Consultant shall submit the same to Owner after
approval
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 30 of 36
ARTICLE 11
COMMISSIONING, STARTUP AND PERFORMANCE TESTS
1. Mechanical Completion
Consultant shall review and recommend for approval the program, and
supervise the mechanical completion work performed by contractors.
Upon successful completion of mechanical completion work, Consultant
shall review and recommend approval of construction completion
certificate documentation. The construction completion of individual
sections of the Project shall be programmed in accordance with the overall
commissioning plan. Consultant ensures that all necessary personnel from
equipment suppliers are called to attend the pre-commissioning activities
as provided for in the equipment purchase orders.
Consultant shall supervise contractors’ work such that phased mechanical
completion and commissioning takes place as determined by Owner’s
business needs.
2. Commissioning and Startup:
Upon Owner’s approval of the mechanical completion of the work, and
when it is deemed suitable by Owner, the commissioning work may
commence according to the plans and schedules prepared by Consultant.
Consultant shall form and organize a start-up team to supervise and
monitor the commissioning, startup, performance test and initial operation
of the facilities consisting of representative of Owner operating personnel,
equipment suppliers, Consultant and contractors and shall ensure that the
contractors provide sufficient numbers of skilled labor that is needed to
complement the Owner startup personnel and to perform activities which
include the running or operation of equipment, necessary adjustments
and hot alignment checks and the running of component parts as unified
system. This shall also include a demonstration of the operability of spare
equipment.
Consultant shall ensure that the contractors provide sufficient manpower,
special tools and spare parts necessary for the commissioning activities.
Consultant shall ensure that all defects and deficiencies found during the
course of commissioning shall be rectified by the contractors. Party shall
supervise and monitor all commissioning and startup activities and all
performance test runs which will be carried out by the contractors. All
performance test results shall be reviewed and certified by Consultant and
subsequently recommended for Owner’s approval. Consultant shall report
to Owner on a weekly basis on the progress and status of commissioning
and startup work. Consultant shall ensure that all commissioning records
and log sheets are properly collated and submitted to Owner as part of
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 31 of 36
contractors’ mechanical completion certificate approval documents and
provisional acceptance documents as relevant.
3. a) Factory Acceptance Tests:
Consultant shall witness the Factory Acceptance Tests in the premises of
contractor for Turnkey Instrumentation system etc. which will be carried
out by the respective contractors.
b) Site Acceptance Tests:
Respective contractors shall carry out the Site Acceptance Tests of
Instrumentation system etc. which shall be witnessed by Consultant at
site.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 32 of 36
ARTICLE 12
ACCEPTANCE
1. Construction Completion Certificate:
Consultant shall review submittals from contractors for construction
completion as defined in the respective contract and advise Owner on
approval and issue of construction completion certificate to the
contractors. Consultant will be responsible for all punch listing to allow
recommendation of construction completion certificate.
2. Mechanical Completion Certificate:
Consultant shall review submittals from contractors for mechanical
completion as defined in the contract and advise Owner on approval and
issue of certificates of mechanical acceptance. Consultant shall review the
certificates of mechanical completion issued and advise Owner when the
various parts of the Project are ready to start up and are in accordance
with contract and specification.
3. Provisional Acceptance:
Consultant shall prepare and recommend approval of certificates of
provisional acceptance when requested by the contractors and
recommend their issuance when the commissioning work, start up and
test runs of the Project have been carried out successfully, and the
performance test results are to the satisfaction of Owner in accordance
with the contract and specification.
4. Final Acceptance:
Final acceptance for the facilities defined in contract shall be issued by
Owner on request from contractors at the expiry of the defects liability
period of one year, in accordance with respective contract.
5. Provisional Acceptance of Consultant’s Work:
Provisional acceptance of Consultant’s work occurs when the last
contractor’s provisional acceptance certificate is approved by Owner.
6. Final acceptance of Consultancy Work:
Final acceptance of Consultant’s work occurs at the expiry of the defects
liability period of one year of the last contractor in accordance with the
contract if there is no deficiency in Consultant’s or contractors’ work.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 33 of 36
ARTICLE 13
INITIAL OPERATION AND TRAINING
During the engineering and construction of the Project, Consultant shall
prepare programs and schedules and perform initial operation and training
services which shall include, but not be limited to the following:
a) assist Owner’s personnel in familiarizing with vendor’s and contractor’s
drawings and specifications and in familiarizing with lines and equipment
check lists.
b) prepare programs for training the Owner’s supervisory staff and
operating/ maintenance personnel to start up, operate and maintain the
various facilities and systems of the Terminal. Actual training itself shall
be conducted by others. In preparing the overall training plans, Consultant
shall identify suitable resources to assist Owner in training its staff.
ARTICLE 14
SAFETY, HEALTH, AND THE ENVIRONMENT
It is Owner’s objective policy to ensure that potential safety and health factors
and environmental effects are assessed for all projects and activities and
acquisitions.
The specific requirements include:
Project Safety Review: A formal project safety review is to be carried out by
Owner and integrated across the various contracts. Consultant shall make all
necessary arrangements for such reviews as required by Owner and shall ensure
that contractors make available such data, personnel and locations as are
required. Consultant shall ensure that all recommendations and findings from
safety reviews are implemented by contractors in a timely manner.
Environmental Impact Assessment (“EIA”): Consultant shall ensure that all
recommendations resulting from the EIA/RA studies, on approval by Owner, are
implemented by contractors.
Health, Site Safety and Security: Consultant shall be responsible, on behalf of
Owner for ensuring a high standard of occupational health and site safety
management and for ensuring the requirements for health, safety and security
to be maintained by contractors, subcontractors and other personnel working at
the site. Consultant shall compile the safety requirement on contractors.
The purpose of these safety requirements shall be to prevent any accidents,
incidents or events that could result in injury or fatality to personnel from
contractors, subcontractors. The requirements shall be intended to supplement
any government authority of India, state, municipal, local or other regulations
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 34 of 36
applicable at the Site which Consultant shall be obliged to enforce on behalf of
Owner.
1. Site Safety Organization:
Consultant is to appoint a safety officer whose responsibility is to monitor
all safety activities on the job site and report his findings to Consultant.
The safety officer shall make periodic safety inspections of the job site on
a schedule that will provide ongoing coverage. The inspections should be
made jointly with the superintendents of the contractors responsible for
ongoing work in the areas to be inspected.
2. Site Safety Planning :
Prior to start of Site work, Consultant shall plan job safety requirements
in conjunction with contractors.
3. Safety Activities:
Consultant shall ensure contractor carry out their activities in accordance
with the safety plan throughout the course of the construction of the
project to inculcate and maintain safety awareness among their
employees.
4. Accident Investigation and Reporting:
Any accident or incident resulting in a lost time injury, death, or damage
to property or equipment is to be investigated by Consultant. Every
incident shall be documented promptly after the incident including the
results of investigation and recommendations for preventive action.
Consultant shall also ensure that all necessary publicity is given, within
the site, to ensure further incidents do not occur. This investigation and
report shall not preclude any similar investigations and reports required
by governmental regulation, but may be handled concurrently with them.
Consultant shall maintain safety performance and accident statistics
records for the entire site works in conformity to an agreed international
standard or system to be approved by Owner. Updated safety
performance and statistics of accidents shall be included in monthly
progress report of the project.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 35 of 36
ARTICLE 15
DOCUMENTATION
Consultant shall ensure all documentation and engineering data are
delivered in a timely manner. The quality and technical integrity of this
information shall be monitored to ensure compliance with the Quality
Assurance Program. The delivery mechanism shall be the responsibility of
Consultant i.e. The electronic media use, indexes, sizes and number of
copies of hardcopy, etc.
Consultant shall also be responsible for modifying the documentation and
data requirements to reflect any existing and new statutory requirements
from both government and certifying authority sources.
Consultant shall be responsible for production of the operating manual(s).
This will include scheduling for the preparation of the materials making up
the operating manuals. It shall also include the review of drafts of the
material in consultation with Owner. Regular progress meetings shall be
held at the appropriate time to ensure completion, commissioning and
operation.
E. EXCLUSIONS FROM SCOPE OF WORK
The following activities are specifically excluded from the Consultant’s
Scope of Work:
a) Sanction / Release of Power and Water both for operational and
construction purposes including liaising with supply authorities,
however all technical support shall be provided by the consultant.
b) Obtaining approvals, clearances and permits from statutory bodies
including liaising with these bodies; necessary
assistance/clarification may be provided as required by the owner.
c) Acquiring land.
d) Obtaining Customs clearances for imported materials / equipments.
e) Arranging transportation from port to sites for imported materials /
equipments.
f) Taking Insurance policies for Project materials / equipments,
lodging claims and liaising for realization of claims, however all
technical support shall be provided by the consultant.
g) Provision of stores / stock yards and store offices including utilities
like power, water, telephone etc. However the same shall have to
be included in one of the first packages for execution through a
vendor. However, necessary site office may be provided by the
party at their own cost.
HINDUSTAN PETROLEUM CORP. LTD EPCM, VISAKH LPG TERMINAL PROJECT GM – MKTG. PROJS. OFFICE
Signature & Seal of the Bidder Page 36 of 36
h) Participation in Arbitration proceedings. However, the Consultant
shall provide necessary assistance to Owner in connection with
these proceedings or disputes with other contractors / suppliers, for
a period of 3 years from the date of Final Acceptance of work. They
may be required to participate only as a helping group to the
owner.
i) The costs towards press advertisements of NIT/bid invitation which
shall be borne by Owner and paid directly at actuals to the agency
on submission of the bills of the agency by the Consultant to
Owner.
j) Consultant shall process the Contractors’ bills and certify the same.
HPCL shall process the certified bills for effecting payment.