highway / utility coordination
DESCRIPTION
Highway / Utility Coordination. Federal Requirements LPA Utility Procedures Guide Reimbursement Requirements. Highway / Utility Coordination. What is the goal of a coordinated Hwy / Utility relocation program?. AASHTO STUDY. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/1.jpg)
Highway / Utility CoordinationHighway / Utility Coordination
• Federal Requirements
• LPA Utility Procedures Guide
• Reimbursement Requirements
![Page 2: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/2.jpg)
Highway / Utility CoordinationHighway / Utility Coordination
• What is the goal of a coordinated Hwy / Utility relocation program?
![Page 3: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/3.jpg)
![Page 4: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/4.jpg)
![Page 5: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/5.jpg)
![Page 6: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/6.jpg)
![Page 7: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/7.jpg)
![Page 8: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/8.jpg)
![Page 9: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/9.jpg)
![Page 10: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/10.jpg)
![Page 11: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/11.jpg)
AASHTO STUDYAASHTO STUDY
Utility relocation is one of the main causes of delays and added expense to road construction projects!
![Page 12: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/12.jpg)
Root of the ProblemRoot of the Problem
• Communication
• Cooperation
• Coordination
![Page 13: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/13.jpg)
Federal RequirementsFederal Requirements
• Must have an approved program and procedures for utility relocation and accommodation.
• Lacking a federally approved program, local agencies must follow the ODOT approved program.
• Require written statement certifying that utility work is complete or that arrangements have been made in the bid documents which allow relocation to run concurrently with the highway construction.
![Page 14: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/14.jpg)
Federal EnforcementFederal Enforcement
• If the approved procedures are not followed, FHWA may not participate in construction delay claims caused by utilities.
![Page 15: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/15.jpg)
Approved ProceduresApproved Procedures
• LPA Utility Guide
• Highway / Utility Guide
• FHWA Program Guide
![Page 16: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/16.jpg)
![Page 17: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/17.jpg)
![Page 18: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/18.jpg)
![Page 19: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/19.jpg)
![Page 20: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/20.jpg)
Reimbursable Utility WorkReimbursable Utility Work
• Funding
• Federal Requirements
![Page 21: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/21.jpg)
Funding – UR PhaseFunding – UR Phase• 4 – Funding Phases in all STIP Projects
• Preliminary Engineering• Right of Way• Utility Relocation (UR)• Construction
• Each Phase requires separate federal funding approval.
• UR Phase is required to fund work accomplished by the Utility or its contractor.
• Adding a UR Phase to an approved project requires an amendment that can take between 1 and 6 weeks depending on the location of the project being within an MPO.
• It is important to identify potential reimbursable impacts and budget for them in the UR Phase as early as possible.
![Page 22: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/22.jpg)
Reimbursable Utility WorkReimbursable Utility Work
• Funding
• Federal Requirements
![Page 23: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/23.jpg)
Federal RequirementsFederal Requirements• Must have an agreement with the Utility and have
written Federal/State approval prior to the Utility starting Preliminary Engineering or Relocation work.
• Preliminary engineering or relocation work by a utility, prior to written approval, will not be eligible for federal funding. These expenses would then be the sole responsibility of the LPA.
• Preliminary coordination and engineering work needed to determine the extent of utility conflicts does not require approval.
• Approvals can take between 1-4 weeks once an approved reimbursement package has been received.
![Page 24: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/24.jpg)
SummarySummary
• Follow approved utility program
• Written Certification that Utility Coordination is complete
• If Utility Reimbursement - Need to set up a UR Phase fund
• Need prior written approval before utilities start PE or Const work
![Page 25: Highway / Utility Coordination](https://reader036.vdocuments.mx/reader036/viewer/2022062721/56813629550346895d9da280/html5/thumbnails/25.jpg)
End of PresentationEnd of Presentation