OUTAGE REPORT
HGPI 2015 UCH Power Plant
16th Oct – 10th Nov 2015
Submitted by: Syed Fahim Abbas Kazmi
Trainee Engineer
Mechanical Maintenance Department
Contents HGPI Introduction ......................................................................................................................................... 3
Major jobs to be done by group Delta .......................................................................................................... 3
DETAILED OVERVIEW OF GROUP DELTA JOBS .............................................................................................. 4
HRSG Overview ......................................................................................................................................... 4
Hot and cold survey of hangars ................................................................................................................ 6
All drums internal inspection followed by NDT ........................................................................................ 8
Rectification of all the passing vavles according to thermography report ............................................. 14
Rectification of HRSG B HP MOV 014 ..................................................................................................... 17
Rectification of HRSG B HP MOV 013 ..................................................................................................... 21
Ice Blasting of HRSG Economizer tubes .................................................................................................. 24
Repair/Replacement of insulation in GT exhaust plenum and IFGD according to thermography report
................................................................................................................................................................ 28
HRSG C HP drum cyclones overhauling................................................................................................... 30
Lesson Learnt .............................................................................................................................................. 32
References .................................................................................................................................................. 33
HGPI Introduction
HGPI stands for Hot Gas Path Inspection which is the type of overall
preventive plant maintenance done on the gas turbines every
alternative year. It is the second biggest outage after the Major
Inspection (MI) in which the steam turbine is dismantled for
complete maintenance as well.
In HGPI, Gas turbines are dismantles and the pathways of hot gases
are inspected visually or through non destructive testing and is
consequently maintained or replaced according to the
manufacturer’s recommendation.
Major jobs to be done by group Delta
- Dry ice blasting of HRSG economizer tubes
- Bench testing of all the safety relief valves of the plant
- Repairing of piping insulation
- All drums internal inspection followed by NDT
- Rectification of all passing valves according to thermography
report.
- Rectification of vibration observed at ducts and its mountings.
- Rectification of HRSG A water leakage from HP hydrastep.
- Rectification of all hard to open valves.
- Repair/Replacement of insulation in GT exhaust plenum and IFGD
according to thermography report.
- Hot and cold survey of hangars of HRSG
- HRSG C HP drum cyclones overhauling.
DETAILED OVERVIEW OF GROUP DELTA JOBS
HRSG Overview:
Safety hazards
Injury to personnel by accidentally touching hot equipment or steam leaks: 1- Hot pipework should be insulated for heat retention and
personnel protection, where insulation is damaged, arrangements should be made to replace insulation and make the work area safe.
2- Protective clothing must be worn to operate or inspect equipment, where it is not practical to fit heat shields for personnel protection.
3- Where steam leaks are hazardous, for example Super-heated
steam leaks can be invisible, barriers should be erected to protect
personnel in the work area and arrangements made to stop the
steam leak as soon as possible.
Fire when oil impregnated insulation reaches its auto ignition
temperature:
1- Oil impregnated insulation will auto ignite at temperatures above
400°F.
2- Where leakage of oil can fall on hot pipework or contaminate
Insulation the oil should be diverted from the pipework and the
leak repaired as soon as possible. Oil contaminated lagging should
be removed from the work area.
Injury from chemicals used for treating feed water to the HRSG: 1- Hydrazine (Injected into the condensate)
2- Ammonia
3- Phosphate
Purpose of HRSG system:
1- The generation of electricity by supplying steam to the steam
turbine.
2- The Deaeration of feed water and pressure control of the
Deaerator.
The steam system consists of three Heat Recovery Steam Generators
and one Steam Turbine Generator.
A Heat Recovery Steam Generator (HRSG) is an unfired boiler,
generating steam in three separate pressure systems, from the heat in
the exhaust gas emitted by the Gas Turbine.
The three pressure systems are termed, High, Intermediate and Low
pressures steam.
1- High Pressure steam is utilised in the Steam Turbine Generator
2- Intermediate Pressure steam is used in the Steam Turbine
Generator and Deaerator.
3- Low Pressure steam is used in the Deaerator
Hot and cold survey of hangars
All the HRSG pipes are hanged with the help of stainless steel
hangars which are installed with a spring to compensate the expansion
of the pipes due to various loadings. It is very important to check the
limits of the springs as to how much they are expanding during the
plant running and how much they are contracting after the HRSG has
been cooled.
For this technique, before the shutdown of the plant, cameras were
installed to specific locations to take the reading of the expansion of all
the hangars. Then after the shutdown when all the pipes have been
cooled and got to ambient temperature, again the reading was taken
with the help of a camera.
All the readings taken were then compared to the range given in the
maintenance manuals and were within the range of the manufacturer’s
recommendation.
All drums internal inspection followed by NDT
All the HRSGs HP, IP and LP drums including the blowdown tanks
together with the Deaerator and the Feedwater tank were to be
thoroughly inspected.
The procedure started off with opening up of all the boiler drums
doors. It took almost 2 days for all the boilers inside temperature to get
normal relative to the ambient temperature since the HP temperature
is above 600 degree Celcius during normal operating conditions.
Exhaust fans were installed after opening the doors to hasten up the
cooling process.
HRSG LP drum yokes before opening
Descon workers opening Feedwater drum door after shutdown
After all the drums were cooled down to ambient temperature, they
were handed over to the 3rd party (Descon) for thorough internal visual
inspection. During this inspection, the surface inside of the boiler was
checked to ensure its quality with accordance of the manufacturer’s
recommendation. Furthermore the boilers inner parts condition was
checked for example if the baffle plates were not lose or broken.
The next step was to perform Non-destructive testing at the welds to
ensure there are no cracks or pinholes that were not visible through the
naked eye. There were two NDT techniques used.
1. Dye Penetrant Testing
DPT is based upon capillary action, where low surface tension
fluid penetrates into clean and dry surface-breaking
discontinuities. Penetrant may be applied to the test component
by dipping, spraying, or brushing. After adequate penetration
time has been allowed, the excess penetrant is removed and a
developer is applied. The developer helps to draw penetrant out
of the flaw so that an invisible indication becomes visible to the
inspector. Inspection is performed under ultraviolet or white light,
depending on the type of dye used - fluorescent or
nonfluorescent (visible).
Below are the main steps of Liquid Penetrant Inspection:
1. Pre-cleaning:
The test surface is cleaned to remove any dirt, paint, oil, grease or
any loose scale that could either keep penetrant out of a defect,
or cause irrelevant or false indications. Cleaning methods may
include solvents, alkaline cleaning steps, vapor degreasing, or
media blasting. The end goal of this step is a clean surface where
any defects present are open to the surface, dry, and free of
contamination. Note that if media blasting is used, it may "work
over" small discontinuities in the part, and an etching bath is
recommended as a post-blasting treatment.
2. Application of Penetrant:
The penetrant is then applied to the surface of the item being
tested. The penetrant is allowed "dwell time" to soak into any
flaws (generally 5 to 30 minutes). The dwell time mainly depends
upon the penetrant being used, material being tested and the size
of flaws sought. As expected, smaller flaws require a longer
penetration time. Due to their incompatible nature one must be
careful not to apply solvent-based penetrant to a surface which is
to be inspected with a water-washable penetrant.
3. Excess Penetrant Removal:
The excess penetrant is then removed from the surface. The
removal method is controlled by the type of penetrant used.
Water-washable, solvent-removable, lipophilic post-emulsifiable,
or hydrophilic post-emulsifiable are the common choices.
Emulsifiers represent the highest sensitivity level, and chemically
interact with the oily penetrant to make it removable with a
water spray. When using solvent remover and lint-free cloth it is
important to not spray the solvent on the test surface directly,
because this can remove the penetrant from the flaws. If excess
penetrant is not properly removed, once the developer is applied,
it may leave a background in the developed area that can mask
indications or defects. In addition, this may also produce false
indications severely hindering your ability to do a proper
inspection. Also, the removal of excessive penetrant is done
towards one direction either vertically or horizontally as the case
may be.
4. Application of Developer:
After excess penetrant has been removed, a white developer is
applied to the sample. Several developer types are available,
including: non-aqueous wet developer, dry powder, water-
suspendable, and water-soluble. Choice of developer is
governed by penetrant compatibility (one can't use water-
soluble or -suspendable developer with water-washable
penetrant), and by inspection conditions. When using non-
aqueous wet developer (NAWD) or dry powder, the sample
must be dried prior to application, while soluble and
suspendable developers are applied with the part still wet from
the previous step. NAWD is commercially available in aerosol
spray cans, and may employ acetone, isopropyl alcohol, or a
propellant that is a combination of the two. Developer should
form a semi-transparent, even coating on the surface.
The developer draws penetrant from defects out onto the
surface to form a visible indication, commonly known as bleed-
out. Any areas that bleed out can indicate the location,
orientation and possible types of defects on the surface.
Interpreting the results and characterizing defects from the
indications found may require some training and/or experience
[the indication size is not the actual size of the defect].
5. Inspection:
The inspector will use visible light with adequate intensity (100
foot-candles or 1100 lux is typical) for visible dye penetrant.
Ultraviolet (UV-A) radiation of adequate intensity (1,000 micro-
watts per centimeter squared is common), along with low
ambient light levels (less than 2 foot-candles) for fluorescent
penetrant examinations. Inspection of the test surface should
take place after 10- to 30-minute development time, depends
of product kind. This time delay allows the blotting action to
occur. The inspector may observe the sample for indication
formation when using visible dye. It is also good practice to
observe indications as they form because the characteristics of
the bleed out are a significant part of interpretation
characterization of flaws.
6. Post Cleaning:
The test surface is often cleaned after inspection and recording
of defects, especially if post-inspection coating processes are
scheduled.
2. Magnetic Particle Inspection
Magnetic particle Inspection (MPI) is a non-destructive testing
(NDT) process for detecting surface and slightly subsurface
discontinuities in ferromagnetic materials such as iron, nickel,
cobalt, and some of their alloys. The process puts a magnetic field
into the part.
Descon worker doing DPT inside the HP drum of the HRSG
After all the NDT work, any cracks or pinholes detected were repaired
by the welding team with the help of welding and grinding. Before
closing the boilers, they were also checked for quality by a boiler
inspector.
Rectification of all the passing vavles according to
thermography report
Before the outage, the technical service department used
thermography cameras to detect which of the valves were passing.
Thermal images, or thermograms, are actually visual displays of the
amount of infrared energy emitted, transmitted, and reflected by an
object. Because there are multiple sources of the infrared energy, it is
difficult to get an accurate temperature of an object using this method.
A thermal imaging camera is capable of performing algorithms to
interpret that data and build an image. Although the image shows the
viewer an approximation of the temperature at which the object is
operating, the camera is actually using multiple sources of data based
on the areas surrounding the object to determine that value rather
than detecting the actual temperature.
During the normal operation of the plant, it was informed by the
operations department that the blowdown of the water overall was
well above 35000 tonnes per day. This indicated that the blowdown
drain valves were heavily passing. The thermography report showed
numerous valves which had to be replaced.
The blowdown drain valves consisted of manually operated 1 inch
globe valves, manually operated 2 inch globe valves and pneumatically
operated 2 inch valves. A Globe valves is a linear motion valve and are
primarily designed to stop, start and regulate flow. The disk of a Globe
valve can be totally removed from the flowpath or it can completely
close the flowpath.
The following table shows the arrangement of these valves in an HRSG:
Blowdown drain valves diagram
The procedure of changing the valve was to first cut the valve from its
pipes at both the ends. This was followed by installation of new valve
and then welding it from both the sides. In the end these new welds
integrity was checked with the help of Dye penetrant testing.
In total 8 blowdown valves of HRSG A, 9 blowdown valves of HRSG B
and 2 blowdown valves of HRSG C were replaced with new ones.
1 inch manual isolation globe valves before replacement
MD AOV 034 B1 new valve being installed
Rectification of HRSG B HP MOV 014
HP MOV 013 is the high pressure steam bypass motor operated gate
valve. This gate valve has wedge type gates. The valve was declared
passing after the thermography survey by the technical service
department. This valve passing issue was very critical since its failure to
shut off steam would then make the job dependent on the manual
isolation valve.
Before discussing overhauling and problem diagnosis, let us see in
detail the working and components of a gate valve:
A gate valve functions by lifting a rectangular or circular gate out of the
path of the fluid. When the valve is fully open, gate valves are full bore,
meaning there is nothing to obstruct the flow because the gate and
pipeline diameter have the same opening. This bore diameter also
determines the valve size. An advantage of this full-bore design is very
low friction loss, which saves energy and reduces total cost of
ownership.
There are four primary designs for gate valves – a slab gate, an
expanding gate, a wedge valve and a knife gate valve.
Slab gate valves are comprised of a single gate unit which raises and
lowers between two seat rings and are primarily used for transporting
crude oil and NGLs.
Unlike a slab gate valve that only has one unit, an expanding gate valve
includes two units – a gate and segment. The gate and segment units
collapse against each other for travel, and separate when the valve is
fully opened or fully closed, to affect a mechanical seal.
Wedge gate valves are comprised of a tapered gate that is metal-to-
metal sealing. In contrast to a slab gate valve or an expanding gate
valve, wedge gate valves are not piggable because of the void that is
left in the bottom of the valve body when the valve is open. These
valves do not have a bore through the gate itself – instead, the gate
retracts into the valve body when open – which saves height space that
is necessary for slab and expanding gate valves.
A knife gate valve is used to cut through extremely thick fluids and dry
bulk solids. The design of this valve makes it inherently self-cleaning, as
the knife is cleared of abrasives with each stroke as it passes the seat
rings and skirts. The gate unit of this type of valve is thin compared to
other gate valve types and is guided in place by the water-type body
that sandwiches the gate.
Stem
Gate valves can have either a rising or non-rising stem design. Rising
stems are attached directly to the gate and provide a visual indicator of
the valve position. Non-rising stems are generally threaded into the
upper part of the gate and have a pointer threaded onto the top to
indicate position. Non-rising stem designs are ideally suited for
applications where vertical space is limited, in well applications and
where scraping/pigging is not required.
Bonnets
Gate valves generally have one of four types of bonnets, which provide
closure from leaks for the body of the valve. Screw-in bonnets are
simple, durable sealing units that use pressure to affect a seal. Union
bonnets provide easy access to the valve body for applications that may
require frequent maintenance or inspection. Bolted bonnets are
generally used for larger valves in higher pressure applications. Finally,
pressure seal bonnets are designed for services with high pressure in
excess of 15MPa (2250 psi).
Diagnosis of problem
After dismantling of the valve, thorough visual inspection was done of
the seat and the gate. There was a minor cut found on the seat which
was causing the passing. So lapping was done with the help of lapping
machine on the face of the seat. As an extra precaution, lapping was
also done on the face of both the gates.
After this DPT was performed on the seat and no cut was found. We
further used BLUE on the seat to check if the surface of the gate is
completely in contact with the seat which was successful. Finally the
valve was reassembled and ready to work again.
Rectification of HRSG B HP MOV 013
This is a major valve which is used to stop main HP steam. This valve is a
wedge type gate valve which is motor operated. The technical service
department, after doing thermography on this valve declared it as
passing.
Diagnosis of the problem
The dismantling of the valve was a major problem due to its weight and
its location. Rigging equipment was used to firstly remove the actuator
part and hang it nearby the valve to be reassembled later. Then the
valve was marked at every point for assembly reference.
Lapping in process of the seat of HP MOV o14
The valve was then fully closed and unbolted to first remove the gland and
the seals inside. Then the stem was removed and ultimately the two gates.
The disassembly was followed by detailed visual inspection of the
components. The gates faces were found damaged at multiple locations and
were beyond the state of repair. There was also a deep cut found on the
seat of the valve, hence being the main reason for the passing of the valve.
This valve was overall serviced with new parts installed. The new parts
included new gates, new stem and new gland seals. The seat of the valve
was lapped for two days to remove the cut. Finally DPT was done on the
seat and it was found to be clear. The valve was assembled again and the
job was complete.
The dismantled components of HP MOV 013
Seat of HP MOV 013. Cut can be seen on the left side
Dismantling of HP MOV 013 using rigging equipment
Ice Blasting of HRSG Economizer tubes
Due to the low temperature of the flue gases at the very end of the
HRSG, the economizer tubes are subjected to high sulfur deposits on
the fins which decrease the heat exchanging tendency of the tubes.
Method
Dry-ice blasting involves propelling pellets at extremely high speeds.
The actual dry-ice pellets are quite soft, and much less dense than
Damaged gate of HP MOV 013
other media used in blast-cleaning (i.e. sand or plastic pellets). Upon
impact, the pellet sublimates almost immediately, transferring minimal
kinetic energy to the surface on impact and producing minimal
abrasion. The sublimation process absorbs a large volume of heat from
the surface, producing shear stresses due to thermal shock.[2] This is
assumed to improve cleaning as the top layer of dirt or contaminant is
expected to transfer more heat than the underlying substrate and flake
off more easily. The efficiency and effectiveness of this process
depends on the thermal conductivity of the substrate and contaminant.
The rapid change in state from solid to gas also causes microscopic
shock waves, which are also thought to assist in removing the
contaminant.
Equipment
The ice used can be in solid pellet form or shaved from a larger block of
ice. The shaved ice block produces a less dense ice medium and is more
delicate than the solid pellet system.
Dry-ice blasting technology can trace its roots to conventional abrasive
blasting. The differences between an abrasive-blasting machine and a
dry-ice blasting machine are in how they handle the blast media. Unlike
sand or other media, dry ice is generally used at its sublimation
temperature. This means that a pressurized hopper system could
potentially build up dangerous amounts of pressure (see dry ice bomb).
Other differences include systems for preventing the ice from forming
snowball-like jams, and different materials to allow operation at very
low temperatures.
Single-hose dry-ice blasters share many of the advantages of single-
hose abrasive-blast systems. To avoid the potential dangers of a
pressurized hopper, single-hose dry-ice blasters make use of a quickly
cycling airlock. The single-hose system can use a longer hose than its
double-hose counterpart without a significant drop in pressure when
the ice leaves the hose. The additional power comes at the cost of
increased complexity. Single-hose systems are used where more
aggressive cleaning is an advantage. This allows heavier build-up to be
cleaned and allows moderate buildup to be cleaned faster.
Safety Hazards
Carbon dioxide is increasingly toxic starting at concentrations above
1%, and can also displace oxygen resulting in asphyxia if equipment is
not used in a ventilated area. In addition, because carbon dioxide is
heavier than air, exhaust vents are required to be at or near ground
level to efficiently remove the gas. At normal pressure dry ice is −78 °C
(−108 °F) and must be handled with insulated gloves. Eye and ear
protection are required to safely use dry ice cleaning equipment.
Compared to other blasting-cleaning methods, dry ice blasting
produces fewer waste products and does not require clean-up of a
blasting medium. The waste products can be swept up, vacuumed or
washed away depending on the containment.
Result
The total deposits of sulfur removed from the HRSG’s were as follows:
HRSG A: 820 kg
HRSG B: 460 kg
HRSG C: 480 kg
HRSG A inspection after Ice blasting. It could be seen that only the sulfur deposits from the front side were removed. The back side remains unattended.
Repair/Replacement of insulation in GT exhaust plenum and
IFGD according to thermography report
Before the outage, the Technical Service Department carried out surveys of the HRSGs hotspots which showed areas of high thermal stresses. This was also visible by a visual survey which showed areas of the casing with burned or discolored paint. After the identification of the areas with very high thermal stresses, the apparent cause was found out to be burned insulation inside the baffle plates of the HRSG. The primary area in all three HRSG’s was the expansion joint A and the diffuser side. This is because the flue gases directly hit these areas after coming out of the exhaust diffuser. Casing temperatures above 350F are especially problematic if several square feet of casing are affected. Such high temperatures combined with the affected area cause restrained expansion which, in turn, results in cracking of casing steel-sometimes severe. Most paint will discolor above 350F and cracking is a possibility, especially in areas where the casing is stiff-such as floors and roofs. After the shutdown, all the HRSG doors were opened and a selected person report was issued at first before anyone could enter the confided space. Due to safety hazard of confined space, it was necessary that at every entry point a designated person stood who would note down the name and time of every person entering and exiting. A detailed visual inspection was done by the field supervisor to identify the areas and diagnose the reason for the hotspots. This was followed by installation of scaffolding and removing of the baffle plates. Insulation was filled and inside the baffle plates and minor cleads that were broken were fixed.
Figure shows the installation of scaffolding inside the HRSG for insulation filling
Figure shows the insulation filled inside the baffle plates of HRSG before retightening of bolts
HRSG C HP drum cyclones overhauling
In small, low pressure boilers, steam-water separation can be
established with the use of a large steam drum approximately half full
of water. Natural gravity steam-water separation can be sufficient for
this case.
On the other hand, for high capacity, high pressure (HP) boilers, steam-
water separation at the steam drum is accomplished with the use of
mechanical steam-water separators. With the installation of these
devices in the steam drum, the drum's diameter and cost can be
significantly decreased.
Primary steam-water separation
Primary steam-water separation removes nearly all the steam from the
water so that very little steam is recirculated from the drum bottom
towards the heated tubes through the outlet connection (downcomer).
Primary separation equipment generally takes one of the following
three forms:
Gravity-driven separation: it is generally considered uneconomical and
its use nowadays is very limited,
Baffle-assisted separation: simple screens and baffle arrangements are
used for improving the steam-water separation process. Baffles provide
among others changes in the direction, more even distribution of the
steam-water mixture as well as additional flow resistance. Their use is
mostly limited to smaller, low capacity boilers.
Mechanical primary separators: they make use of centrifugal force or
radial acceleration. They are nowadays in use almost worldwide for
state of the art steam-water separators. Conical cyclone, horizontal
cyclone, vertical cyclone separators are some of the technologies used.
In the HP drum used in HRSG of Uch Power Plant, there are 20 cyclone
separators located on the left side and 22 located on the right side of
the boiler. They were all removed one by one and were taken to
workshop for washing and cleaning of their meshes. Those whose
meshes were of very deteriorated condition were replaced. These were
then installed back inside the drum.
Cyclone separators being overhauled at the workshop
Lesson Learnt
There were multiple lessons learnt during the outage. They are as
follows:
- One of the yokes required to shut down the door of LP drum of
HRSG C went missing. All the teams searched the nearby areas but
it was nowhere to be found. Ultimately by the decision of the
senior management a new yoke was fabricated for the job. For
the next outage it is very important to keep check on all the
dismantled equipment to avoid last minute hassle.
- The hose used for the ice blasting should be used of a different
design. The one used this time only removed sulfur content from
the front surface of the economizer tubes and not even from the
second batch behind it. The back surface of the front tubes also
remained unattended. It should be noted that using such high
cost technology yielded very unimpressive result.
- The valve HP MOV 013 that was repaired have a 12 inch diameter.
To cut and welt such a high diameter pipe, a post weld heat
treatment machine is required which the plant does not own.
Although the problem was solved without the installation of a
new valve but in case new valve had to be installed there were no
complete resources which could have caused delay in the plant
startup.
- After the startup of the plant, The HP drum of HRSG B started to
leak, resulting in tripping of the gas turbine. Later it was
diagnosed that the gasket inside the door was cut during the
closing of the door. Therefore for future reference it is necessary
that a senior supervisor attends to the process of closing of the
doors of the boilers and the vessels to ensure proper gasket
installation.
References
- UPS induction manuals - Wikipedia - http://www.answers.com/Q/When_boiler_use_cyclone_separato
r_and_why - http://www.enggcyclopedia.com/2012/01/drums-mechanical-
steam-water-separators/ - https://www.c-a-m.com/products-and-services/valves/valve-
academy/how-does-it-work-gate-valves