health and safety

15
PRELIMINARY HEALTH AND SAFETY PLAN KEADUE WWTP UPGRADE WORKS KMCF ENGINEERING DUBLIN ROAD ATHLONE 2014

Upload: group2sd1314

Post on 24-Nov-2015

23 views

Category:

Documents


0 download

DESCRIPTION

Health & Safety

TRANSCRIPT

  • PRELIMINARY HEALTH AND SAFETY PLAN

    KEADUE WWTP UPGRADE WORKS

    KMCF ENGINEERING

    DUBLIN ROAD

    ATHLONE

    2014

  • Preliminary Health and Safety Plan for Keadue WWTP

    Table of Contents

    1.0 INTRODUCTION ................................................................................................................ 1

    2.0 NATURE OF THE CONSTRUCTION WORK ......................................................................... 2

    2.1 Scope of Work .............................................................................................................. 2

    2.2 Schedule of work ......................................................................................................... 2

    2.3 Working Hours ............................................................................................................. 2

    3.0 ORGANISATIONAL ARRANGEMENTS ................................................................................... 3

    Contracting Arrangements: ................................................................................................... 3

    Construction Supervision: ...................................................................................................... 3

    4.0 APPOINTMENT OF PROJECT SUPERVISORS ......................................................................... 4

    5.0 COMMUNICATION ............................................................................................................... 5

    5.1 Communication between Designers and PSCS ................................................................ 5

    5.2 Pre-Construction Meeting ............................................................................................... 5

    6.0 THE EXISTING ENVIRONMENT ............................................................................................. 6

    6.1 Existing services: .............................................................................................................. 6

    7.0 INFORMATION ON THE PRESENCE OF PARTICULAR RISKS TO SAFETY & HEALTH .............. 6

    7.1 Construction Work Involving Particular Risks .................................................................. 7

    7.1.1 Aggravated risk of falls or burial ............................................................................... 7

    7.1.2 Risks from chemical or biological substances ........................................................... 7

    7.1.3 Risks from high voltage ............................................................................................. 7

    7.1.4 Risk of drowning ....................................................................................................... 7

    7.1.5 Risks from underground work .................................................................................. 8

    8.0 PLANS FOR CHECKING THE IMPLEMENTATION OF SAFE WORKING PROCEDURES ............ 8

    8.1 Site Meetings ................................................................................................................... 8

    8.2 Safety Inspection .............................................................................................................. 8

    8.3 Safety Audits .................................................................................................................... 8

  • Preliminary Health and Safety Plan for Keadue WWTP

    8.4 Safety Inductions ............................................................................................................. 9

    8.5 Accident / Incident Record Book ..................................................................................... 9

    8.6 Record Keeping ................................................................................................................ 9

    9.0 SITE RULES .......................................................................................................................... 10

    9.0 FIRST AID ............................................................................................................................ 12

    9.1 Emergency Contact Details ............................................................................................ 12

  • Preliminary Health and Safety Plan for Keadue WWTP

    1

    1.0 INTRODUCTION

    This document is prepared in accordance with the requirements of the Safety, Health and

    Welfare at Work (Construction) Regulations 2006 otherwise known as the Construction

    Regulations.

    This Preliminary Safety and Health Plan covers the design process for the project. Its main

    purpose is to provide information to the Project Supervisor for the Construction Stage to

    allow the preparation of the site induction meeting, Site Specific Safety Statement and help

    the PSDP compile or update the Safety File.

    The Preliminary Safety and Health Plan will be made available to all those tendering for the

    role of Project Supervisor for the Construction Stage (PSCS). It will be the duty of the

    appointed PSCS to further develop the Preliminary Safety and Health Plan during the

    construction stage. The PSCS shall develop, implement and monitor the controls deployed

    to mitigate the risks associated with the hazards identified in this plan. Having regard to the

    progression of works, additional hazards maybe identified during construction.

  • Preliminary Health and Safety Plan for Keadue WWTP

    2.0 NATURE OF THE CONSTRUCTION WORK

    2.1 Scope of Work

    The scope of work covered by this Preliminary Safety and Health Plan in to construct a

    Keadue WWTP Upgrade Works. The project includes the Tendering Team working for a

    small Civil Engineering contracting organisation. The Tendering Manager has requested that

    you prepare a submission for senior management documenting your approach to selecting a

    tender design for use in a design and build works proposal for Keadue WWTP and develop a

    Construction schedule and cost performance system and monitoring system for use during

    the contract phase.

    2.2 Schedule of work

    The starting date for the project is January of 2014. It is expected for the works to be

    completed within a 14 month period. The completion date of works is late 2015.

    2.3 Working Hours

    The permitted working hours for the site is:

    8am-5pm Monday-Friday

    Break:

    10:30am-11am

    Lunch:

    1pm-2pm

    Note:

    Permission may be granted by the client or engineer for time off or holidays.

  • Preliminary Health and Safety Plan for Keadue WWTP

    3.0 ORGANISATIONAL ARRANGEMENTS

    The Client is:

    Name: Paul Dolan

    Address: Dublin Road,

    Athlone,

    Co. Westmeath

    The designer of the Project is:

    Name: KMCF Engineering

    Address: Dublin Road,

    Athlone,

    Co. Westmeath

    Contracting Arrangements:

    A main Contractor shall be appointed to carryout the works. Contracts will be entered into

    for the main Contract.

    Construction Supervision:

    Construction will be supervised by the appointed main contractor. The designers will make

    periodic inspection visits.

  • Preliminary Health and Safety Plan for Keadue WWTP

    4.0 APPOINTMENT OF PROJECT SUPERVISORS

    Project Supervisor for Keadue WWTP:

    Name: KMCF Engineering

    Address: Dublin Road,

    Athlone,

    Co. Westmeath

    Project Supervisor for Construction Stage:

    The successful tender (Contractor) shall be appointed as Project Supervisor for the Construction Stage. Contact details to be advised:

    NAME: _____________________

    ADRESS: _____________________

    _____________________

    _____________________

    TELEPHONE: _____________________

    I wish to confirm acceptance as PSCS for the project: ______________________________.

    Health and Safety Officer for Construction Stage:

    To be Confirmed

    Any changes of personal must be formally made by writing and acknowledged by the new

    appointed personal.

  • Preliminary Health and Safety Plan for Keadue WWTP

    5.0 COMMUNICATION

    5.1 Communication between Designers and PSCS

    Arrangements shall be put in place to facilitate the provisions of any design assumptions or

    matters relating to safety as identified by the design process.

    5.2 Pre-Construction Meeting

    A pre-start meeting shall be held prior to the commencement of the construction stage. It is

    essential that the PSDP/Designer/Health and Safety Coordinator for Design Process and the

    PSCS/Contractor/Health and Safety Coordinator for Construction Stage inspect the site and

    agree on how best to minimize the impact to employees/public/other that may be affected

    by the proposed works. The purpose of the meeting is to ensure that the PSCS/Contractor is

    made aware, understands and agrees with the safety arrangements as detailed in this plan.

    The agenda shall include the following:

    The provision of information regarding the indicative control measures as identified

    in the Design Process Risk Assessment

    Agree Traffic Management Plan

    Exchange contact details of PSDP and PSCS

    Minutes from the pre-start meeting must be recorded and filed on the Safety and Health

    File.

    If the indicative or proposed Traffic Management Plan (TMP) conflicts with the

    PSCS/Contractors schedule of works a revised TMP must be agreed with between the

    PSDP and PSCS before commencement of the works.

    The PSCS is to include the revised TMP in the Developed Safety and Health Plan.

  • Preliminary Health and Safety Plan for Keadue WWTP

    6.0 THE EXISTING ENVIRONMENT

    The Keadue WWTP Upgrade Works has been approved to plan, design and develop a

    programme to manage the development. The Keadue WWTP is located off the R285 outside

    the village of Keadue in Co. Roscommon. The project team has been drafting a tender

    selection system capable of comparing a series of WWTP options for the planned

    improvement works at Keadue WWTP, to develop the schedule, cost performance system

    and monitoring system to be used during the contract phase.

    6.1 Existing services:

    The contractor is advised to visit the site to locate the exact positions of all Over ground

    services, Electrical cables, Telephone cables and Buried Cables.

    ESB:

    ESB maps have been requested and will be available for contractors on request and should

    be issued before any contract commences on site.

    Telephone:

    Eircom if contacted will mark location of underground cables running in the vicinity of all

    pipe work.

    Water mains:

    Water mains Contact water works caretaker to confirm location on the ground.

    7.0 INFORMATION ON THE PRESENCE OF PARTICULAR RISKS TO SAFETY &

    HEALTH

    The construction work referred to in this Preliminary Safety & Health plan that has been

    reviewed by the designers. In their review the designers have assumed that all construction

    work will be done in accordance with the Construction Regulations. The designers have also

    assumed that the contractors safety statement deals with the normal hazards arising from

    their particular type of construction work.

    The Particular Risks identified for this package are listed below:

  • Preliminary Health and Safety Plan for Keadue WWTP

    7.1 Construction Work Involving Particular Risks

    7.1.1 Aggravated risk of falls or burial

    Work which puts persons at work at risk of burial under earth-falls, engulfment in

    swampland or falling from a height, where the risk is particularly aggravated by the nature

    of the work or processes used or by the environment at the place of work or site.

    Particular risk identified

    There will be the normal risk of burial that might be expected on any construction project

    involving excavations greater than 1.2m deep but the risk is not aggravated in the works.

    There will be the normal risk of falls from height that might be expected on any construction

    project.

    7.1.2 Risks from chemical or biological substances

    Work which puts persons at work at risk from chemical or biological substances constituting

    a particular danger to the safety and health of such persons or involving a legal requirement

    for health monitoring.

    Particular risk identified

    There will be the normal risk of contact with chemical or biological substances that might be

    expected on any construction project but the risk is not aggravated in the works.

    7.1.3 Risks from high voltage

    Work near high voltage power lines

    Particular risk identified

    There will be the normal risk of working in the Vicinity of high voltage power lines where

    carrying out excavation work along roads etc.

    7.1.4 Risk of drowning

    Work exposing persons at work to the risk of drowning.

    Particular risk identified

    This risk does not arise within the proposed construction area.

  • Preliminary Health and Safety Plan for Keadue WWTP

    7.1.5 Risks from underground work

    Work on wells, underground earthworks and tunnels

    Particular risk identified

    The will be normal risk of working in the vicinity of foundation trenches, construction of

    dairy washings pit, etc.

    8.0 PLANS FOR CHECKING THE IMPLEMENTATION OF SAFE WORKING

    PROCEDURES

    Safe working practices will be implemented by way of site Supervision, regular monitoring

    and auditing of site activities.

    8.1 Site Meetings

    Safety will be put first item on the agenda at all progress meetings which will be attended by

    the Site Manager, Construction Team and a representative from the Client. Minutes of such

    meetings shall be circulated to the team.

    8.2 Safety Inspection

    The PSCS shall monitor and carry out regular inspections of the work area, relevant items of

    plant & equipment and the activities of all personnel on site.

    Relevant items or breaches will be discussed at our site meetings.

    Where relevant, items of equipment will be inspected and certified at the prescribed

    intervals, as per statutory regulations.

    8.3 Safety Audits

    Regular Audits will be undertaken with an emphasis on Safety, by site Management.

    External Safety Consultants, Safe Place Systems may carry out random / unannounced site

    audits, covering all aspects of the project.

    Areas / Items highlighted shall be rectified and signed-off by the Supervisor.

    Relevant items or breaches of Safety will be discussed at our site meetings.

  • Preliminary Health and Safety Plan for Keadue WWTP

    8.4 Safety Inductions

    Every Employee reporting for work on the site will receive Safety Induction from the Site

    Supervisor or his representative, prior to commencing work.

    Each person will sign an Induction Sheet on completion and a register of all such persons will

    be maintained in the Site Office.

    8.5 Accident / Incident Record Book

    This must be kept and maintained by the Site Manager.

    This accident record book must be used to record relevant details every time anyone is

    injured, however slightly.

    This includes any of the following:

    Employee

    Sub-Contractors Employees

    Anyone on site

    Any member of the public

    Any employee of the Client

    8.6 Record Keeping

    There are Statutory Requirements with respect to Health and Safety records.

    Statutory Registers (C.R. Forms) are available from the H.S.A. There are three which are

    particularly relevant to this project. There are two main parts which are particularly relevant

    to this project.

    These are:

    WH1 - known as the Scaffold Book

    AF3 - known as the Excavation Book

  • Preliminary Health and Safety Plan for Keadue WWTP

    8.7 Arrangements for Reporting and Recording of Accidents and Dangerous Occurrences

    Notification of Accidents to H.S.A. (where applicable) will be done by the injured persons

    Employer, using the approved Form IR1.

    All accidents on Site will be notified to the main contractor, and investigated by them if

    appropriate to prevent recurrence.

    Any dangerous occurrence must be investigated and steps taken to avoid a recurrence.

    Accidents involving injury to any member of the Public are immediately reported to the

    H.S.A. using the approved form IR1.

    8.8 Permits to Work

    Permits to Work shall be required for the Following operations on site: -

    Hot works

    Roof works

    Excavation works

    Termination and Connection of all Mechanical and Electrical services

    Other areas as may be required during construction

    9.0 SITE RULES

    These are generic rules for the general guidance of the all persons involved in the

    project/works and must be developed by the PSDP/Designer/Health and Safety Coordinator

    for Design Process/PSCS/Contractor/Health and Safety Coordinator for Construction Stage

    to become Site Specific Rules for the project in hand.

    Specific site rules site rules must consider the risks identified in the Design Process Risk

    Assessment and the construction stage risk assessment e.g. if a 360 excavator is to be used

    during construction, the following shall be included in the site rules for the construction

    stage:

    Only trained personnel shall operate the 360 excavator. The operator shall have his CSCS

    card or equivalent available at all times for inspection. The following CR forms shall also be

    made available for inspection: CR4, CR 4A, CR 4B.

  • Preliminary Health and Safety Plan for Keadue WWTP

    1. All site visitors, personnel and contractors are required to comply with the Site

    Safety and Health Policy and the specific Construction Stage Safety and Health Plan.

    2. The PSCS shall ensure that all subcontractors are assessed with regard to their level

    of competence and availability of resources.

    3. All risks identified in the Design Process Safety and Health Plan and in the Health,

    Safety and Welfare (Construction) Regulations 2006 are to be individually identified

    and addressed by the PSCS.

    4. Method Statements and Safety Statements should be reviewed and revised on an

    ongoing basis to take into account any new issues which arise during the course of

    the works. Revisions, which could affect safety, health and welfare, should be raised

    at site meetings.

    5. All site personnel and safety and health personnel should be advised on an ongoing

    basis of any revisions to the Safety and Health Plan by the PSCS/Health and Safety

    Coordinator for Construction Stage.

    6. Standard and proof of adequate training of personnel on site should be included in

    the Safety and Health Plan prepared by the PSCS/Health and Safety Coordinator for

    Construction Stage.

    7. Smoking is not permitted within designated working areas.

    8. Eating and drinking should not be allowed in designated working areas.

    9. The PSCS/Health and Safety Coordinator for Construction Stage should ensure that

    all excavations are supported in accordance with the requirements of the 2006

    Regulations.

    10. The PSCS/Health and Safety Coordinator for Construction Stage must ensure that all

    relevant Safety and Health Regulations are adhered to at all times.

    The information contained in this Safety and Health Plan has been prepared prior to the

    commencement of the work on site.

    Signed: ______________________________ Date: ______________

    (Project Supervisor for Design Phase)

    Signed: ______________________________ Date: ______________

    (Health and Safety Coordinator)

  • Preliminary Health and Safety Plan for Keadue WWTP

    The Health and Safety Plan must be kept and for 5 Years.

    9.0 FIRST AID

    The main contractor will provide statutory First Aid Equipment at this Site. A suitable First

    Aid Kit (fitted out in proportion to numbers employed on Site will be kept at a clearly

    indicated location in the site offices. This box shall be under the care of, and stocked by, a

    named individual.

    9.1 Emergency Contact Details

    Emergency Details

    First Aider (s): To be confirmed

    Local

    A&E/Hospital:

    Mullingar Regional Hospital 044-123456

    Cavan Regional Hospital 049-123456

    Tullamore Regional Hospital 057-123456

    Local Doctors:

    Dr. Joe Blogs 043-123456

    MIDOC GP Out of Hours Service 043-123456

    Local Gardai: 043-12345

    .