hcal000011_2014

86
A B C D E F G H I J K L M N O P Q R S A B C D E F G H I J K L M N O P Q R S HCAL 11/2014 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTITUTIONAL AND ADMINISTRATIVE LAW LIST NO 11 OF 2014 _______________ BETWEEN BUILDING AUTHORITY Applicant and APPEAL TRIBUNAL (BUILDINGS) Respondent THE METHODIST CHURCH, HONG KONG Interested Party _______________ Before: Hon Au J in Court Dates of Hearing: 20 and 21 November 2014 Date of Judgment: 4 September 2015 J U D G M E N T

Upload: pschil

Post on 12-Dec-2015

213 views

Category:

Documents


0 download

DESCRIPTION

real estate bubbles and frenzy in Hong Kong

TRANSCRIPT

Page 1: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

HCAL 11/2014

IN THE HIGH COURT OF THEHONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCECONSTITUTIONAL AND ADMINISTRATIVE LAW LIST

NO 11 OF 2014

_______________

BETWEEN

BUILDING AUTHORITY Applicant

and

APPEAL TRIBUNAL (BUILDINGS) Respondent

THE METHODIST CHURCH, HONG KONG Interested Party

_______________

Before: Hon Au J in Court

Dates of Hearing: 20 and 21 November 2014

Date of Judgment: 4 September 2015

J U D G M E N T

A. INTRODUCTION

1 This is the Building Authority (“the BA”)’s application to

judicially review the decision (“the Decision”) of the Appeal Tribunal

(Buildings) (“the Tribunal”) dated 7 November 2013.

Page 2: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

2 The Decision allows with certain conditions the Methodist

Church (“the Church”)’s appeal against the BA’s disapproval of the

Church’s general building plan (“the General Plan”) submitted on 4

December 2009 for the redevelopment of its site (“the Site”) located at

around the junction of Kennedy Road and Queen’s Road East. The

disapproval is contained in a letter dated 28 December 2009 (“the

Disapproval Letter”).

3 The BA seeks in this judicial review an order to quash the

Decision on the bases that it is tainted by a number of errors of law and

that the various conclusions therein are irrational. I will elaborate on

these grounds later. The BA is represented by Mr Ambrose Ho SC,

leading Mr Abraham Chan.

4 The Tribunal (as the respondent) has remained neutral and

not taken any steps in this application. The Church (as the interested

party) opposes the application and is represented by Mr Ismail.

5 To put the Decision in proper context, I need to first set out

the relevant background leading to the appeal before the Tribunal.

B. BACKGROUND

B1. The relevant statutory provisions

6 The following statutory provisions are relevant for the

present purposes.

Page 3: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

7 Under section 14 of the Buildings Ordinance (Cap 123) (“the

BO”), plans for building works must be submitted for approval by the BA

before any building works could commence.

8 Section 16(1) of the BO provides for the grounds upon

which the BA may refuse to approve any plans for building works.

Relevantly, the BA may refuse to approve a building works plan on,

among others, the following grounds:

(1) Where the carrying out of the building works shown thereon

would contravene the provisions of the BO or any other

enactments (section 16(1)(d)).

(2) Where the BA in its opinion consider it necessary to have

further particulars of such plans or of the building works

shown thereon (section 16(1)(i)).

(3) Where it is not satisfied with the further particulars related to

the plan provided to it upon its earlier refusal under

section 16(1)(i) (section 16(1)(j)).

9 At the same time:

(1) Regulation 18A of the Building (Planning) Regulations (Cap

123F) (“the Planning Regulations”) provides for the

classification of a site into a Class A, B or C site. In essence,

to classify as a Class B site, the site has to be a corner site

that has at least 40% of its boundary abutting on two

“specified streets”.

(2) Regulation 18A(3) provides for when a street can be

regarded as a “specified street”.

Page 4: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

(3) Regulations 19, 20 and 21 of the Planning Regulations

provide the maximum site coverage and plot-ratio of

permissible under each of these site classes, with the largest

permissible under Class C and the least under Class A.

10 Further, Regulation 41 of the Planning Regulations provides

that every building which exceeds six storeys in height shall be provided

with a second staircase (in addition to the main staircase) as means of

escape (“MOE”) in case of emergency. In this respect, the MOE Code of

Practice (“the MOE Code”) published by the BA provides at paragraph

8.2 that every exit route of the MOE should lead directly to a street or an

open area at ground level having unobstructed access.

11 Finally, Regulation 90 of the Building (Construction)

Regulations (Cap 123B) (“the Construction Regulations”) provides that

every building shall be constructed to have the necessary fire resistance

construction.

B2. The Site and the General Plan

12 The Site is on the Remaining Portion of Inland Lot No 1316

at 271 Queen’s Road East. It is a corner site located at the South-West

corner of Queen’s Road East and Kennedy Road.

13 To facilitate an easier understanding of the issues raised in

the appeal and also this judicial review, I have attached to this judgment

as Annex I a plan (“the Site Plan”) of the Site. This is the same plan that

is included in the Decision under paragraph 12.

Page 5: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

14 It can be seen from the Site Plan that Queen’s Road East lies

on the northern boundary of the Site, while the adjoining Kennedy Road

lies on its eastern boundary.

15 On the Site, the Church erected the existing church building

in the 1960s. It consisted of a 2-storey building and a 3-storey extension.

The respective layout plans of the church building and the proposed

extension for the church building were respectively approved by the BA

on 21 March 1964 and 21 March 1978.

16 The Church intends to redevelop the Site. The proposed

church is a 25-storey building with a basement. It is proposed to be used

for church, religious and charitable users as well as the minister’s

residence.

17 The Church initially submitted to the BA a general building

plan (“the November Plan”) of proposed redevelopment for approval in

October 2009. This was rejected by the BA in a letter dated 4 November

2009 (“the November Disapproval Letter”). On 9 December 2009, the

Church through its authorised person (“AP”) re-submitted the General

Plan as the latest plan to the BA seeking its approval.

18 In the General Plan and the AP’s application, the Site was

submitted as a “Class B site”. It is the Church’s position that the Site has

at least 40% of its boundary abutting Queen’s Road East and Kennedy

Road. The proposed site coverage was therefore also prepared on the

basis of the plot-ratio permissible under a Class B site.

Page 6: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

19 As can be seen from the Site Plan, there is no question that

the Site abuts Queen’s Road East. However, the south eastern corner of

the Site is separated from the existing Kennedy Road by a triangular

shaped area (“the Triangular Area”). The Triangular Area is created over

the years by the step-by-step straightening and widening of Kennedy

Road. Thus, historically, before the creation of the Triangular Area as a

result of those straightening and widening works, Kennedy Road wound

around and along the south east side of the Site.

20 The Triangular Area is a government land, which was

allocated to the Department of Health for the Wan Chai Polyclinic. It

was part of the site of the Polyclinic in 1979, and is now occupied as part

of the open car park of the Polyclinic. The Triangular Area almost

touches the existing Kennedy Road at its northern tip and is more than

4.5m wide at the southern portion.

21 By the Disapproval Letter, the BA disapproved the General

Plan on the following bases:

(1) Under section 16(1)(d) of the BO, in that the building works

proposed:

(a) Contravened Regulations 19, 20 and 12 of the

Planning Regulations, as the AP’s Class B

classification for the Site was incorrect. As such, the

proposed site coverage also exceeded the permissible

plot-ratio (“the Classification Ground”).

(b) Contravened Regulation 41 of the Planning

Regulations as the MOE relating to the exit stairs

discharging from upper ground floor into the adjoining

Page 7: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

site (which is in the Triangular Area) was not

acceptable in light of paragraph 8.2 of the MOE Code

(“the MOE Ground”).

(c) Contravened Regulation 90 of the Construction

Regulations, as external wall with adequate fire

resisting construction at the common boundary with

the Polyclinic had not been provided in the General

Plan as required under paragraph 7.4 of the Fire

Resisting Construction Code (“the Firewall Ground”).

(2) The BA required the Church to provide further information

to address comments and queries from the Assistant

Commissioner for Transport (“the ACT”) as set out in

Appendix I of the Disapproval Letter. (“the Traffic

Information Ground”)

B3. The appeal

22 The Church lodged an appeal with the Tribunal against the

BA’s said disapproval of the General Plan.

23 The appeal was heard before the Tribunal for three days in

October 2011. At that time, the Tribunal members made a visit to the

Site with the parties. As recorded in the Decision, the Tribunal members

also later paid their own visits to the Site after the hearing in the absence

of the parties. In the appeal, the Church was represented by Mr Ismail,

and the BA by Mr Abraham Chan.

24 Some two years after the hearing, on 7 November 2013, the

Tribunal gave its Decision.

Page 8: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

B4. The Decision

25 In the Decision:

(1) In relation to the Classification Ground, the Tribunal

concludes that the Site satisfies the requirements to be

classified as a Class B site. It therefore finds that the BA’s

disapproval of the Plan on this ground is incorrect (see

paragraphs 18 - 78 of the Decision) (“the Classification

Conclusion”).

(2) In relation to the MOE and Firewall Grounds, the Tribunal is

of the view that its Classification Conclusion would affect

the consideration of these two grounds. As such, it decides

that these two issues should be reconsidered by the BA upon

the Church re-submitting a revised buildings plan to the BA

with revisions made concerning only these two issues (see

paragraphs 79 - 92 of the Decision) (“the MOE and Firewall

Conclusions”).

(3) In relation to the Traffic Information Ground, the Tribunal

finds that there was in fact no traffic issue arising and

observes that this may be an after-thought on the BA as an

additional blanket ground to disapprove the General Plan. It

therefore concludes that the BA’s disapproval on this ground

is incorrect (see paragraphs 93 - 97 of the Decision) (“the

Traffic Information Conclusion”).

26 The Tribunal therefore allows the appeal but with the further

conditions that (a) the Church should re-submit within 90 days a revised

building plan to the BA for approval but only with revisions relating to

the MOE and Firewall issues; and (b) the BA shall within 45 days

thereafter decide whether to approve the revised building plan only in

Page 9: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

relation to the MOE and Firewall issues and the BA cannot adopt their

prior grounds (ie, the MOE and Firewall Grounds) in that consideration.

It has also ordered costs against the BA (see paragraphs 98 - 109 of the

Decision).

C. THIS JUDICIAL REVIEW

27 In this judicial review, the BA challenges each of the

Tribunal’s above conclusions, including the way in which its final order

is made. I will deal with each of these challenges below.

C1. The Classification Conclusion

28 There is no dispute that the crucial question in the appeal in

relation to the Classification Ground is whether the Site can be regarded

as having at least 40% of its boundary abutting two “specified streets” for

the purpose of Regulation 18A.

29 Before the Tribunal, the Church’s case on how the Site abuts

Kennedy Road was run on the following submissions:

(1) Primarily, given its historical development, and in light of

the “once a highway, always a highway” principle,1 the

Triangular Area should continue to be regarded as part of

Kennedy Road. As such, the Site in abutting the Triangular

Area, which should continue to be regarded as part of

Kennedy Road, is abutting a specified street (as part of

Kennedy Road). In this respect, the Church also says that

1 See for example: Winsome Investment Co Ltd v The AG (unreported, HCMP 714/1980, 23 June 1982, per Jackson-Lipkin J)

Page 10: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

the Underground Area‍ 2 including the retaining wall

supported its case that the Triangular Area is part of

Kennedy Road (“the Once a highway, Always a highway

Submissions”3).

(2) Secondly, even if the Triangular Area cannot continue to be

regarded as part of Kennedy Road, the Triangular Area on its

own is a specified street under Regulation 18A(3)(a)(iv) as

the Church has been given a right of way by the Department

of Medical and Health over it sometime in late 1970s. This

is evidenced by a series of relevant correspondence made in

1977 and later (“the Right of Way Submissions”4).

(3) Alternatively, even if the Triangular Area cannot continue to

be regarded as part of Kennedy Road, the Site can be

regarded as abutting Kennedy Road notwithstanding the

intervention of space created by the Triangular Area by

applying the fact and degree test as recognised in AG v

Mightystream Ltd [1983] 1 WLR 980 and Building Authority

v Appeal Tribunal (Buildings) and Estoree Ltd (unreported,

HCAL 147/2002, 25 July 2003, per Hartmann J). The

Church also relied on the evidence that certain parts of the

Underground Area including the retaining wall are included

in the Site and have been used and occupied by the Church

to support this abutment on the basis of the fact and degree

test (“the Fact and Degree Submissions”5).

2 This is an area shown in the 1964 and 1978 general building plans relating to the Site.

3 See paragraphs 42.1 - 42.12 of the Church’s Opening Submissions for the appeal, paragraphs 13 and 20 of Closing Submissions, and paragraphs 2 - 7.2 of the Church’s Additional Submissions on Underground Area.

4 See paragraphs 42.13 - 42.14 of the Church’s appeal Opening Submissions and paragraphs 4 - 12, 14 - 19 of the Church’s appeal Closing Submissions

5 See paragraph 43 of the Church’s appeal Opening Submissions, paragraphs 22 - 37 of the Church’s appeal Closing Submissions, and paragraph 7.3 of the Church’s Additional Submissions on the Underground Area.

Page 11: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

30 Moreover:

(1) It was the unchallenged evidence in the appeal that, given

the abutment on Queen’s Road East, the Church needed only

to show that there was another 4.4m length of abutment from

the tip of the Site along its eastern boundary on the existing

Kennedy Road to satisfy the 40% abutment requirement to

be classified as a Class B site.6

(2) There was also no dispute between the parties in the appeal

that the fact and degree test is as laid down in Estoree and

Mightystream Ltd. The fact and degree test is in essence that

the word “abut” does not always import actual contiguity or

adjoining or touching, and whether a site can be regarded as

abutting on a “specified street” notwithstanding the existence

of a gap in between is to be determined as a matter of fact

and degree by reference to the width and function of the

intervening gap. Thus, in Mightystream, the Privy Council

rules that the presence of a “nullah” between the site and the

street prevented there being any abutment of the two, while

in Estoree, the court (in distinguishing Mightystream)

refused to disturb the Tribunal’s finding that an

“insignificant drainage channel” did not prevent the

abutment in question.

31 The Tribunal in considering the Classification Ground in the

Decision has on its own motion divided the Triangular Area into four

portions, namely, the Tip Section, the Sidewalk Section, the Right-of-

6 See the witness statement of Mr Nelson Chan at paragraph 15 and the plan (as exhibit NC-19 to the witness statement) with which a green coloured portion (“the Green Portion”) of the necessary length was marked of the Triangular Area to show the minimum necessary length abutting Kennedy Road that the Church was required to show to succeed in its classification of the Site.

Page 12: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

Way Section and the Remaining Section (see paragraphs 40 - 41 of the

Decision).

32 For convenience, I have also attached to this judgment as

Annex II the diagram whereby the Tribunal has divided the Triangular

Area into those four sections. This is the same diagram included at

paragraph 40 of the Decision. As mentioned by the Tribunal, these

sections are:

(1) The northern portion/tip extending from to in front of the

Church entrances and steps (the “Tip Section”);

(2) The adjacent triangular section from to to the south of the

Tip Section (the “Sidewalk Section”);

(3) The right-of-way section including from to to the south of

the Sidewalk Section (the “Right-of-Way Section”); and

(4) The remainder of the Triangular Area from its most

southerly “border” to the crossed hatch Right-of-Way

Section (the “Remaining Section”), located to the south of .

33 It must be noted that in dividing these four sections, the

Tribunal has not provided any basis or measurements as to how the

Triangular Area is divided into these sections. In other words, one

reading the diagram and the Decision would not be able to identify with

any precision or certainty as to the position and actual dimensions of each

of these sections.

34 After setting out these four sections, the Tribunal then went

on at length to decide section by section as to whether each of these

sections can be regarded as a “specified street” under the various criteria

Page 13: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

provided at Regulation 18A(3)(a) of the Planning Regulations. For

example:

(1) Paragraph 46 of the Decision states that the Tribunal

“determines that the Tip Section also falls within the

definition of a ‘specified street’” under Regulation 18A(3)(a)

(i).

(2) Paragraph 50 of the Decision states that the Tribunal “must

now consider whether the Right of Way Section is a

‘specified street’” and it then goes on at paragraphs 51 - 59

of the Decision to decide effectively that it is a “specified

street”.

(3) Paragraph 64 also states that the Sidewalk Section (given its

conclusions on the Tip Section and the Right of Way

Section) is also a “specified street”.

(4) In relation to the Remaining Portion, the Tribunal did not

find it necessary to determine whether it is a “specified

street” as it is already satisfied that the abutment requirement

has already been satisfied by the other necessary portion of

the Triangular Area (see paragraph 67 of the Decision).

35 The Tribunal’s above approach in determining whether the

Triangular Area is a “specified street” has led to the BA’s primary

challenge in this judicial review. It is submitted by Mr Ho that the

Tribunals’ above decision under the Classification Ground is premised

solely on its finding that the relevant portions of the Triangular Area can

on their own right be regarded as a “specified street”, but those

conclusions are wrong in law as the basis upon which those conclusions

are made are either without any evidential basis or by wrongly applying

Page 14: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

the legal principles. Mr Ho has made elaborate and persuading

submissions in support of these contentions.

36 Mr Ismail accepts in this application that it is true that the

Tribunal did make certain conclusions on whether the various portions of

the Triangular Area are “specified street” on their own right. However,

counsel also submits that the Tribunal has in any event also made factual

findings based on the fact and degree test that, at the least, the Tip Section

and the northern part of the Sidewalk Section do not prevent the Site from

abutting Kennedy Road. This finding is sufficient to enable the Site to

have the necessary abutment to satisfy the 40% requirement to make it

classified as a Class B site. Given that this is a factual finding based on

evidence, which the court in judicial review should not normally

interfere, there is simply no basis for the court to quash the Decision

based on a challenge of the Tribunal’s alternative and further conclusions

on “specified street”, as this finding has nothing to do with those

conclusions even if they were all wrong in law as submitted by the BA.

37 These contentions require me to examine the Tribunal

various conclusions made under the Classification Conclusion to see:

(1) Whether, independently of its conclusion that these two

sections themselves are a specified street, the Tribunal has

made a separate conclusion applying the fact and degree test

based on evidence.

(2) Whether the Tribunal is correct as a matter of law in its

conclusion that various sections of the Triangular Area is a

specified street under Regulation 18A(3)(a)(iv) given that

Page 15: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

there is right of way created over it by virtue of an

instrument.

C1.1 Has the Tribunal made a proper fact and degree finding

38 It is clear that the Tribunal is fully aware of the fact and

degree test, as set out at paragraphs 33 - 37 of the Decision.

39 The question is whether it has applied this test based on the

evidence to the Tip Section and at the least the northern part of the

Sidewalk Section to find the necessary abutment.

40 As to the Tip Section and the northern part of the Sidewalk

Section, the Tribunal explains why there is the necessary abutment

through these sections at paragraphs 44 - 49 and 76 - 77 of the Decision

as follows:

“1. The Tip Section

44. In the case of the Tip Section of the Triangular Area (reference the Diagram  – ), it is the Tribunal’s finding that the Tip Section clearly falls within the definition of a ‘street’ under Section 2 of BO, as it is a footpath.

45. The Tribunal further finds as a fact that Kennedy Road has on its western edge in front of the Site a standard pedestrian sidewalk. Between the Site and the pedestrian sidewalk lies the Tip Section of the Triangular Area. The Site visit by Members on the first day of the hearing revealed that the Tip Section is a mere few inches to a few feet in width between the existing pedestrian sidewalk and the Site without any obstruction whatsoever. It was also revealed that the paving stones for the pedestrian sidewalk have been continued across the Tip Section of the Triangular Area up to the site boundary of the Site.

Page 16: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

46. The Tribunal therefore determines that the Tip Section also falls within the definition of a ‘specified street’ under [Regulation] 18A(3)(a)(i).

2. The Sidewalk Section -

47. From the South of the Tip Section of the Triangle Area, the pedestrian sidewalk continues up to a point where it branches off in two directions, the pedestrian sidewalk towards the south abutting the existing carriageway of Kennedy Road and the other pedestrian sidewalk which winds towards the entrance way of the neighboring property to the south-west boundary of the Site, an area currently occupied by the Wan Chai Polyclinic. As the Tribunal’s designation of the phrase ‘Sidewalk Section’ implies, this is a standard sidewalk allowing pedestrians to use without exclusion this pathway to enter further into the Triangular Area.

48. As above, the Tribunal must first determine whether this Sidewalk Section is a street. Having viewed the Sidewalk Section, the Tribunal concludes that based on the definition of street under Section 2 of the BO, the Sidewalk Section is a street being a footpath. One part of the footpath runs towards the south abutting the existing carriageway of Kennedy Road, and the other towards the south west abutting the site boundary of the Site; the ‘Sidewalk Section’ refers to the area commencing at and ending at , per the Diagram.

49. As with the Tip Section the Tribunal had no difficulty in determining that the north section of the Sidewalk Section allows the Site to continue to abut Kennedy Road, as stated in the case of Estoree, Hartmann J: ‘In determining that the EVA abutted the southern boundary of the site, the Appeal Tribunal found as a fact that not only should the “decorative border” be counted as part of the “street” but that the drainage channel immediately beyond it should also be counted.’ (paragraph 56) and ‘… that “abut” does not always import actual contiguity. …’ (paragraph 57). This abutment is found as a fact to extend only 4.4 metres along the sidewalk/Site boundary therefore allowing the Site to continue to abut Kennedy Road thereby achieving an additional perimeter (the ‘Necessary Additional Boundary’) and enabling the Site to achieve Class B boundary status.   -   abuts a specified street and that specified street is in effect more than 4.5M wide since the footpath in question continues and abuts the footpath of Kennedy Road. Therefore the length of

Page 17: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

boundary  -  should be included in calculating the length of abutment in determining the ‘Class’ of the site.

76. The Tribunal has concluded at Paragraphs 44-46 that the Tip Section does abut Kennedy Road; the fact that the [Underground] Area exists, supports the contention that the Site abuts Kennedy Road since the [Underground] Area of the Tip Section is under the entrance way of the Site and even runs under the current public sidewalk to the very edge of the old Kennedy Road retaining wall.

77. The Tribunal therefore concludes that through the Tip Section and the Sidewalk Section, the Site abuts Kennedy Road. This abutment occurs notwithstanding the ‘intervening’ Tip Section; this is so because of the lack of interference of this minor intervening ‘third-party’ land (i.e. the Tip Section). The Tribunal has reviewed the authorities and concludes that the current facts are clearly distinguishable from the nullah example in Mightystream and rather fall within the continuity of the Site concept as is discussed in Estoree.”

41 I must agree with Mr Ho that these paragraphs depict a

rather confusing analyses by the Tribunal as to on what basis it says the

Site abuts Kennedy Road through the Tip Section and the Sidewalk

Section. For example, it seems to first say that the Tip Section itself is a

specified street in meeting the criterion under Regulation 18A(3)(a)(i) (ie,

the section was maintained by the Highways Department) (see paragraphs

44 - 46 of the Decision). However, this cannot be correct, as firstly the

Church did not advance any argument in the appeal that any part of the

Triangular Area can be regarded as a specified street by reason of

Regulation 18A(3)(a)(i), and secondly, it is accepted by the Tribunal

itself that there are submissions that the Tip Section is not maintained by

the Highways Department (see paragraph 69 of the Decision). The

Tribunal also then appears to suggest that the Tip Section and the

Sidewalk Section are also specified street themselves as they are the

Page 18: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

continuation of the footpath of the existing Kennedy Road (which is in

essence part of the Church’s contentions made under the Once a highway,

Always a highway Submissions). However, at the same time, the

Tribunal refers here and there to the Estoree and Mightystream cases in

making or referring to the above observations, which seems to suggest

that it has in its mind the fact and degree test (see in particular paragraphs

49 and 77 of the Decision).

42 I therefore agree with Mr Ho’s submissions that it simply

cannot be worked out with any degree of confidence and certainty that the

Tribunal does make an independent finding of fact based on the fact and

degree test (which is backed by clear reasons and evidence) that the Site

abuts the existing Kennedy Road notwithstanding the separation created

by the Tip Section and northern section of the Sidewalk Section.

43 Seeking to reconcile these paragraphs, Mr Ismail however

submits that reading the above paragraphs objectively, in particular, the

underlined parts, it is clear that the Tribunal has separately and

independently made a finding based on the fact and degree test that the

Site abuts Kennedy Road by reason of its finding that these sections

should continue to be regarded as part of the Kennedy Road, but not on

the basis that the Tip and northern part of the Sidewalk Sections are on

their own a specified street.

44 To illustrate his above contentions, Mr Ismail submits at this

hearing that paragraph 46 of the Decision should be read and understood

as with the following underlined words: “The Tribunal therefore

determines that the Tip Section also falls within the definition of a

Page 19: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

‘specified street’ under [Regulation] 18A(3)(a)(i) as part of Kennedy

Road”. This is so as (says Mr Ismail) it was his primary submissions7

made before the Tribunal that the Triangular Section should be regarded

as being maintained by the Highways Department because it was part of

Kennedy Road. Since it was not his case that there is evidence in the

appeal to show that any parts of the Triangular Area are in fact

maintained by the Highways Department, Mr Ismail therefore emphasises

that the Tribunal’s reference to Regulation 18A(3)(a)(i) 8 in this paragraph

must therefore be based on this part of his submissions and should be

understood as such.

45 Thus, Mr Ismail confirms that it is the Church’s case in this

judicial review that Tribunal has ruled on the fact and degree test in

relation to the Tip Section and at least the northern part of the Sidewalk

Section by finding that these sections should continue to be regarded as

part of Kennedy Road. Counsel then submits that this is a fact finding

conclusion, which cannot be said to Wednesbury unreasonable, in

particular given that the Tribunal members had personally visited the

Site. The court in judicial review has no basis to interfere it.

46 With respect to Mr Ismail, even taking his case to the

highest, I have come to the view that this conclusion on the part of the

Tribunal is not supported by any rational basis and is thus unlawful. My

reasons are as follows.

7 Under the Once a highway, Always a highway Submissions.8 Which provides that a street is a “specified street” if it is vested in the Government

and maintained by the Highways Department.

Page 20: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

47 It must be noted, as I have summarised above, that the

Church’s primary case before the Tribunal is that the Triangular Area

should continue to be regarded as part of Kennedy Road given its

historical development considered under the once a highway, always a

highway principle. In other words, the case of the Triangular Area

continuing to be part of Kennedy Road is part and parcel of the Church’s

case run on the Once a highway, Always a highway Submissions. There

were no separate submissions made by the Church that Triangular Area

could still be regarded as part of Kennedy Road by applying the fact and

degree test.

48 However, the Tribunal has concluded at paragraph 69 of the

Decision that it does not need to decide on the Church’s case on the Once

a highway, Always a highway Submissions. It explains this as follows:

“69.According to the submissions at the hearing, the Triangular Area was not maintained by the Highways Department and that the Triangular Area had not been ‘lawfully closed’ by the Highways Department or the Government. However, the Tribunal finds there are simply not enough facts to support or dispute whether this portion of Kennedy Road continues to be a highway: (for example, whether there were notices to the members of the public, including the Appellant, including whether the normally required publishing in the Gazette). As the Tribunal has found that the Necessary Additional Boundary has been proven there is no immediate need to advance this argument. Given the above, the Tribunal has not found it necessary to determine the Appellant’s contention that the Triangular Area remains a ‘highway’. Such a determination would require further evidence and submissions that were not called for nor presented, though there were submissions that such closure (if any) was never properly gazette.”

49 Thus, the Tribunal is unable to decide on whether the

Triangular Area can in fact be considered as part of a highway (being part

of Kennedy Road) because of the lack of evidence and submissions.

Page 21: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

50 As such, once it has decided not to determine the Once a

highway, Always a highway case for lack of relevant evidence and

submissions, there is no more rational basis for the Tribunal to then

conclude that these relevant sections of the Triangular Area can continue

to be regarded as part of Kennedy Road. This is so since, as I have noted

above, the Church’s case in continuing to regard the Triangular Area as

part of Kennedy Road is part and parcel of its case on the Once a

highway, Always a highway Submissions.

51 In my view, the Tribunal’s above irrational conclusion on

finding those sections of the Triangular Area as part of Kennedy Road

notwithstanding its refusal to deal with the Once a Highway, Always a

highway submissions is a result of having confused the Church’s

submissions based on the Fact and Degree Submissions and the Once a

highway, Always a highway Submissions. This confusion is probably

further contributed by the fact that (a) the Church had relied on the

Underground Area to support both its primary Once a highway, Always a

highway Submissions as well as the alternative Fact and Degree

Submissions (see paragraphs 29(1) and (3) above); and (b) the two years

lapse of time between the hearing and the Decision. This finding of the

Decision is thus unlawful for lack of a rational underlying basis.

52 Further, and in any event, this conclusion is in my view also

tainted with procedural unfairness as the BA had not been given an

opportunity to make any submissions to deal with the case that, by way of

a fact and degree test but not otherwise, these sections can continue to be

regarded as part of Kennedy Road. As I observed above, that there were

no separate submissions in the appeal made by the Church that Triangular

Page 22: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

Area could still be regarded as part of Kennedy Road by applying the fact

and degree test.

53 I therefore agree with Mr Ho that this part of the conclusion

is unlawful and should be quashed.

C1.2 The Right of Way finding

54 Regulation 18A(3)(a)(iv) provides that a street is a

“specified street” if it is on “land over which the owner of the site is

expressly granted, by or by virtue of an instrument, a right of way

exercisable at all times”.

55 The Tribunal at paragraphs 50 - 59 of the Decision finds that

the Tip Section, the Sidewalk Section and the Right of Way Section

satisfy Regulation 18A(3)(a)(iv) and thus are a specified street. It

explains its conclusion relevantly as follows:

“3. The Right-of-Way Section -

50. The Tribunal, having determined that the Tip Section and the northern portion of the Sidewalk Section allow the Site to abut a specified street as above, the Tribunal must now consider whether the Right of Way Section is a ‘specified street’:

50.1. Whether any of the circumstances set out in [Regulation] 18A(3)(a) exist; or

50.2. Whether failing the above, one or more of such circumstances exist with respect to different parts of the street and those parts together constitute the street.

51. In determining this question, the Tribunal must consider the Appellant’s submission on the Right of Way Section. The Appellant’s position is that the Appellant enjoys a right of way across the Triangular Area and that a series

Page 23: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

of discussions and correspondence/letters both to and from the Appellant (together as a valid instrument) has granted to the Appellant a right of way over said Triangular Area.

52. The Appellant submits that in a letter from the then Director of Medical and Health Services of 20 Sept 1977 (the ‘1977 Letter’), a right of access was expressively given to the existing Church to facilitate access for the disabled members of the congregation through the small area of the Triangular Area currently used as the Wan Chai Polyclinic car-park and the Triangular Area is effectively a ‘specified street’ under [Regulation]‍18A(3).

53. Thus, it is for the Tribunal to determine: Is the street on land over which the owner of the site is expressly granted, by or by virtue of an instrument, a right of way exercisable at all times?

54. Given that:-

54.1. a letter can be a valid instrument;

54.2. the then-Director of Medical and Health had apparent authority to issue such letter for and on behalf of the Medical and Health Services Department and that the said Department had the legal right over the relevant land at the material time;

54.3. the intention of the parties; and

54.4. the relevant correspondence/letters between the parties; then the Tribunal determines that the 1977 Letter (together with the series of communication) is a valid instrument within the meaning of [Regulation] 18A(3)(a)(iv) for the purpose of expressly granting a right of way.

55. In granting the right of way, the 1977 Letter does not stipulate any expiration date or time limit on such grant. In addition, there is also the continued conduct of the parties over many years and continuing to date in support of the Appellant’s position of there being a grant of the right of way. As one example, the Appellant was given the keys to the gate entering the Polyclinic parking lot on which a portion of the Triangular Area covers. There is no doubt that the

Page 24: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

Appellant has a right of way and access through the Triangular Area exercisable at all times.

Can the Right-of-Way Section be regarded as a Specific Street?

56. The Tribunal acknowledges its indebtedness to Mr. Chan of the BA in referring to the February 2004 paper prepared for discussion on 24 February 2004 by the Legislative Council Panel on Planning, Lands and Works which sets out the background for the concept of ‘specified street’ against the back drop of the ‘uncertainties about the definition of street in relation to site classification’ created by the Siu Sai Wan site development case. In that paper it was stated that the site ‘would abut a street for the purpose of site classification’ (i.e. a ‘specified street’), if ‘the owner of the site has been expressly granted a right of way over the street exercisable at all times’. This paper was the precursor of the current [Regulation] 18A(3).

57. Although the final regulation has adopted slightly different working, the Tribunal can now better determine the solution that the regulations were drafted to achieve. The Appellant has therefore rightly contended that the right of way that has been granted as a result of various conversations and specifically letters to and from the owner of the Site would be an exception to the ‘standard’ determination of abutment. The Tribunal also has concluded that this series of letters can be and should be regarded as a set of documents that constitutes an instrument under the requirements of [Regulation] 18A(3).

58. The Tribunal finds as a fact that the Appellant has been allowed both pedestrian (e.g. the Church’s disabled members) and vehicular access and a right of way through the Triangular Area (across the Right of Way, the Tip Section and the Sidewalk Sections) from Kennedy Road to the Site. As such, the Right of Way Section further enables the Tribunal to concludes that the Site abuts Kennedy Road through the Tip Section, the Sidewalk Section and the Right of Way Sections of the Triangular Area by operation of the Right-of-Way and as above and as such complies with the [Regulation]‍18(A)3.

59. Hence, the Tribunal further determines that, in practice, pedestrian access (the ‘Pedestrian Access’) and vehicles (the ‘Vehicular Access’) take two different paths/accesses to the existing car-parking space as

Page 25: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

evidenced by the evidence given at this hearing and observations by the Tribunal members during their Site Visits. As the Tribunal has found that the Right-of-Way Section contains a right of way, that fact allows that entire area to be considered a ‘street’ as set out at Paragraph 41. above, whether such right-of-way is all or a combination of a ‘square’, ‘court’, ‘land’, ‘road’, ‘footpath’ or ‘passage’. This is so because the Pedestrian Access and Vehicular Access pass over the Right-of-Way Section notwithstanding some portion of this is as well, the footpath (and/or the southward extension of the footpath mentioned above commencing from Paragraph 44. With the finding of a right-of-way and with distinction of these two different paths in mind, we will turn to the consideration of boundary ratio.”

56 In gist, the Tribunal concludes that the Tip Section, the

Sidewalk Section and the Right of Way Section by themselves are such a

specified street under Regulation 18A(3)(a)(iv). This is so because it has

found as a fact that the Church “has been allowed both pedestrian (eg the

Church’s disabled members) and vehicular access and a right of way

through the Triangular Area (across the Right of Way, the Tip Section

and the Sidewalk Section) from Kennedy Road to the Site…” (see

paragraph 58 of the Decision).

57 The Tribunal finds that there is such a right of way created

by reference to a letter to the then Director of Medical and Health

Services (“the Director”) dated 20 September 1977 (“the 1977 Letter”)

and a series of letters exchanged between the relevant parties around that

time (see paragraphs 52 and 57 of the Decision). It also holds that these

series of letters, including the 1977 Letter, can be treated as “instrument”

under Regulation 18A(3)(a)(iv).

Page 26: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

58 The 1977 Letter was written by the Director to the Church in

response to the Church’s letter dated 29 August 1977. At that time, the

Church was planning to build an extension at the Site. The Church in the

August letter indicated that they wished to provide access for “disabled

and wheelchair members of the congregation” going to the Church to

enter on one level without having to negotiate stairs. They also wished to

provide a “car space” for the minister who would have his office in the

new extension building. They therefore wanted to explore the possibility

of asking for a surrender to the Church of a small area of the Triangular

Area to create the said access and car space. In that letter, it was stated

expressly that the Church understood that “no approach can be made to

the appropriate authority without first having” the goodwill and

agreement of the Medical and Health Department (“the Department”).

59 In the 1977 Letter and in response to the Church’s August

letter, the Director stated relevantly as follows:

“This department would certainly wish to do everything possible to facilitate access for disabled members of your congregation but from an initial reading of your letter it would seem that this could be simply arranged by giving you a right of access through the small area of the existing car-park referred to and, in this case, it would not be necessary for the department to surrender any portion of the land to the English Methodist Church on a formal basis. I should be grateful to receive your confirmation that this is all that will be required.”

60 Other than these two letters, included in the evidence for the

appeal are also a number of other correspondences exchanged between

the Department (and the Chief Physician of the Polyclinic) and the

Church between September 1977 and May 1980, 9 which effectively show

9 For example, a letter by the Director of Medical and Health Services to the Church dated 20 September 1977, a letter by the Church to the Director dated 11 October 1977, a handwritten letter by the Church to the Consultant Chest Physician of the Polyclinic [B2/342-

Page 27: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

that the Department or the Polyclinic was agreeable to allow the Church’s

disabled and wheelchair members and the minister’s car to have access

through a small area of the Polyclinic carpark (which is in the Triangular

Area) to go to the Church building.

61 Mr Ho for the BA challenges the Tribunal’s conclusion that

a right of way has been created over these sections of the Triangular

Area. He submits that the conclusion is tainted by a number of errors of

law or Wednesbuary unreasonable. Mr Ho has made elaborate

submissions on these errors, and I hope I can be forgiven for summarising

them briefly as follows:

(1) First, it is contended that as matter of proper construction,

the word “instrument” under Regulation 18A(3)(a)(iv) mean

“formal legal document”10 and letters as those seen in this

case cannot fall within that definition. As such, the Tribunal

is wrong in law to treat the 1977 Letter and the other

correspondences as instrument for the purpose of this

regulation.

(2) Second, and in any event, the Tribunal’s construction that a

right of way exercisable at all time over the Triangular Area

has been granted by “the owner” to the Church under the

1977 Letter and the other correspondences is wrong in law

or irrational given that:

(a) It has not taken into account the fact that these

correspondences written by the Department or its

3] and a letter from the Assistant Director of Medial and Health Department to the Church dated 13 May 1980

10 See: The Shorter Oxford English Dictionary (5th edn), Vol 1, 1391. Further, Mr Ho says given the legislative history of this provision and the context that this provision deals with important matters relating to site classification and thus plot ratio by reference to an interest in land exercisable at all time, as a matter of purposive construction, the word should be given a restrictive and narrow construction.

Page 28: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

representative were not representing the owner of the

land, who is the Government. The land was only

allocated to the Department for use. In this respect, it

is pertinent to note that the Church itself accepted in

the 1977 Letter that it would need to look to the

“relevant authority” but not the Department to

formally ask for a surrender of a small part of the

Triangular Area once it had got the “goodwill and

agreement” of the Department.11 This shows that (Mr

Ho submits) the Church itself recognised that the

Department was not the owner of the Triangular Area

and cannot by itself give or deal with any interest in

that piece of land.

(b) The Tribunal is wrong in law in taking into account

irrelevant factors by looking at subsequent conducts

(such as the giving of keys etc, see paragraph 55 of the

Decision) to construe the intention of the parties at the

time when the right was created.

(c) Alternatively, if subsequent conduct is relevant, the

Tribunal is wrong in failing to take into account the

letter dated 13 May 1980 from the then Assistant

Director of the Department to Reverend Hopkins of

the Church, which made clear that even by that point

the Church did not consider itself to have any general

permission to access through the Triangular Area.12

11 See paragraph 58 above.

12 In material part, the letter stated: “I refer to your [the Church’s] letter…requesting for permission for your car to gain access to the parking area adjacent to the Methodist Church via the Polyclinic Car Park. This is to inform you that your request has been approved” (emphasis added)

Page 29: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

(d) The nature of the “right” granted to the Church under

these correspondences is at most a revocable licence

and cannot be an interest in land in the form of a right

of way over. In particular, it is clear that the Church

was only given a right to access through a small part

of the Triangular Area only to enable its disabled

members and the minister to go to the Church. This

cannot amount to an interest in land, in particular in

light of the Church’s initial request to have a surrender

which was apparently not given. In this respect, the

Tribunal also has not explained at all why it rejects the

BA’s case in the appeal that the right only amounted

to a licence.

(e) Further, taking it to the highest, the “right” granted

cannot be regarded as to cover the entire Triangular

Area. There is no indication in these correspondences

as to the area upon which the right is granted.

Alternatively, from the context of the access as

expressly requested, it is clear that the “right” covers

only a small portion of the Triangular Area.

62 I think there is much force in Mr Ho’s above submissions.

63 However, I do not think it is right and appropriate for me to

give a final conclusion on these submissions at this stage. Instead, I think

it is only right for me to quash this part of the conclusion and remit it

back to the Tribunal for reconsideration for the following reasons.

64 It is important to first note that the Tribunal in arriving at

this right of way conclusion has relied on and referred to the 1977 Letter

Page 30: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

and a series of correspondences. However, the Tribunal has singularly

failed to identify what these series of correspondences are. Related to

this, it has also not identified the latest time as to when (and why at that

time) it says the right of way was created. Without identifying these in

this part of the Decision, one can only be speculative as to the bases and

reasons why the Tribunal has come to the view that the totality of these

correspondences gives rise to the relevant right of way over the

Triangular Area. For example, one simply is unable to know which parts

of what other correspondences that the Tribunal has taken into account to

support its finding of the right of way. Without these, one is also unable

to form an intelligible understanding as to the reason why the Tribunal

find those parts of the unidentified correspondences support a right of

way. As such, in my view, the Tribunal has failed to give adequate

reasons to allow a legitimate and intelligible understanding of its

conclusion. This part of the finding should thus be quashed for lack of

adequate reasons.

65 The Tribunal’s failure to give adequate reasons on the other

hand makes it inappropriate for this court to come to a firm conclusion in

relation to Mr Ho’s above complaints as, in my view, the merits of these

contentions are highly contextual based.

66 For example, I think there is substance in the contention, as a

matter of purposive construction that the word “instrument” should be

given a narrow meaning as “formal legal document” given the legislative

history of this provision and the context that this provision deals with

important matters relating to site classification and thus plot ratio by

reference to an interest in land exercisable at all time. However, as Mr

Page 31: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

Ho fairly emphasises and accepts, the word “instrument” does not only

mean “deed” and it is also not necessary for the court to give an

exhausting meaning of the word “instrument”. He also accepts that it is

not his case that a letter or a series of letters can never constitute formal

legal documents. What he however asks this court to conclude is that the

types of letters shown in the present case cannot fall within the meaning

of “formal legal document”. With respect, I do not think the court can

come to that conclusion at this stage without knowing which of these

correspondences the Tribunal has relied on to reach its conclusion and the

reasons for doing so.13 I should therefore refrain from forming a

conclusion now, in particular when the matter is to be remitted for

reconsideration by the Tribunal.

67 Similarly, for the validity of the other complaints made by

Mr Ho, they are also dependent on looking at say (a) what are the

correspondences that the Tribunal has relied on and the reasons for

coming to that conclusion; and (b) when the Tribunal say at the latest the

right was created (for example, the complaint relating to the Tribunal’s

taking into account subsequent conducts). The court at this stage should

not pre-empt any conclusions which are evidence linked.

68 For these reasons, I would also quash the Tribunal’s

conclusion based on the finding of the right of way for lack of adequate

reasons, and remit the same to the Tribunal for reconsideration.

13 Although there are only a number of correspondences and letters that are relied on by the Church and included in the hearing bundles in the appeal to support the Right of Way Submissions, I do not think it is appropriate for the court to speculate on which of these correspondences the Tribunal has relied on and its reasons for treating them as instrument.

Page 32: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

C2. The Traffic Information Conclusion

69 Relevant to this are sections 16(1)(h) to (j) of the BO, which

are as follows:

“(1)The Building Authority may refuse to give his approval of any plans of building works where –

(a) …

(h) the building works consist of, or any part thereof involves, the construction, formation or laying out of any means of access or other opening, not being a street or access road, to or from any street, and the place at or manner in which such means of access or other opening opens on to the street is, in his opinion, such as to be dangerous or likely to be dangerous or prejudicial to the safety or convenience of traffic using the street, or which may be expected to use the same;

(i) in his opinion, it is necessary for him to have further particulars of such plans or of the building works shown thereon or, where all the plans prescribed by regulations have not been submitted, to have one or more of the other plans prescribed by regulations, to enable him fully to consider such plans;

(j) any further particulars or other plans delivered to him, upon his refusal, under paragraph (i), to give his approval to any plans, are not to his satisfaction;

…”

70 Thus:

(1) Under section 16(1)(h), the BA can disapprove a buildings

plan on the ground that any means of access provided in the

plan is dangerous or likely to be dangerous.

(2) Under section 16(1)(i), the BA can disapprove a plan on the

basis that it is necessary to have further particulars of the

Page 33: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

plan or the building works to enable him to consider further

of the plan.

(3) Under section 16(1)(j), the BA can disapprove a plan on the

basis that it is not satisfied with the further particulars

provided after the BA has previously disapproved the plan

under section 16(1)(i).

71 As mentioned above, in the Disapproval Letter, the BA also

referred to the Church’s failure to deal with certain traffic related issues

as follows:

“7B. Under Buildings Ordinance section 16(1)(j), you are required to provide further information to address the comments from Assistant Commissioner for Transport/Urban, Transport Department in paragraph 11 below and to demonstrate the right of way through the adjoining lot. I hereby reserve my position under Buildings Ordinance section 16(1)(b).

11. The Assistant Commissioner for Transport/Urban, Transport Department (Contact Officer: Ms. Chiny LEUNG at tel. no. 2294 2600) has comments at Appendix I.”

72 Annex I set out the ACT’s comments as follows:

“(a) The AP should demonstrate if the provision of internal transport facilities is in accordance with the HKPSG.

(b) The AP should demonstrate if the proposed vehicular access is in line with relevant lease conditions.

(c) Information on the capacity of church and other uses should be provided. Traffic generation and attraction should be assessed according.

(d) The AP should demonstrate the adjoining road(s) and junction(s) can accommodate the additional traffic generated by significant increase of development intensity.

Page 34: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

In absence of the above details, we reserve to provide further comment on the proposal.”

73 In relation to this disapproval ground, the agreed issue in the

appeal is whether the Church has provided sufficient particulars in

answering the ACT concerns. See the “Traffic Issue” identified under

paragraph 13 of the Decision as follows:

“13. At the hearing, the parties agreed the Disapproval Letter raised the following issues for determination by the Tribunal:-

13.1. Whether the Triangular Area constitutes a ‘specified street’ for the purposes of [Regulation] 18A(3)(iv) and whether the Site falls within the definition of a Class B site (the ‘Triangular Area Issue’);

13.2. Whether the GBP provides for an adequate means of escape (‘MOE’) for the Site (the ‘MOE Issue’);

13.3. Whether the GBP provides for an adequate fire wall near the common boundary with the Wan Chai Polyclinic (the ‘Fire Wall Issue’); and

13.4. Whether the Appellant has provided sufficient particulars in answering the Assistant Commissioner for Transport’s (the ‘ACT’) concerns (the ‘Traffic Issue’).

74 Thus, the issue is whether it is correct for the BA to

disapprove the plan on the ground that the Church needed to provide

further particulars relating to the ACT’s concerns on traffic related

matters. In gist, the ground under section 16(1)(i).

75 However, the Tribunal in the Decision decides in substance

that the ACT’s concerns raised are not proper traffic matters that the BA

is entitled to look into. The Tribunal arrives at that view by reference to

Page 35: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

the CFA judgment in China Field Ltd v Appeal Tribunal (Buildings)

(2009) 12 HKCFAR 342. It therefore concludes that there is no valid

traffic issue and there is therefore also no question for asking for further

particulars. It even goes further to suggest that this is an afterthought of

the BA. The Tribunal explains this at paragraphs 93 - 97 of the Decision

as follows:

“The Traffic Issue

93. Under paragraph 7B of the Disapproval Letter, the BA required the [Church] to provide further information to address the comments from the Assistant Commissioner for Transport (Urban), Transport Department and to demonstrate the right of way through the adjoining lot (the ‘Traffic Issues’). In the Disapproval Letter, the BA stated: ‘In reliance on the comments given by the Assistant Commissioner for Transport (Urban) of the Transport Department (the “ACT”) at paragraph 11 of the Disapproval Letter, the Authorised Person was required to provide further information to address the ACT’s comments given in Appendix I to the Disapproval Letter (“Appendix I”)’. Hence, the AP was required to address the following issues for the Tribunal’s consideration:-

Hong Kong Planning Standards and Guidelines (‘HKPSG’)

93.1. ‘The AP should demonstrate if the provision of internal transport facilities is in accordance with the HKPSG.’

Lease Conditions (re. Proposed Vehicular Access)

93.2. ‘The AP should demonstrate if the proposed vehicular access is in line with relevant lease conditions.’

Traffic Generation and Attraction

93.3. ‘Information on the capacity of church and other uses should be provided. Traffic generation and attraction should be assessed according(ly).’

Right of Way

Page 36: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

93.4. The BA also requested the [Church], via its AP, to demonstrate the right of way through the adjoining lot: ‘The AP should demonstrate the adjoining road(s) and junction(s) can accommodate the additional traffic generated by significant increase of development intensity.’

94. In response to this Traffic Issue the Tribunal is mindful of the fact that this ‘issue’ was not raised in response to the [Church’s] earlier building plans: this fact of late consideration was not a surprise to the Tribunal since the ‘traffic’ in question concerns only entrance and exit of vehicles accessing the Site’s two parking spaces. The Disapproval Letter states: ‘the AP should demonstrate the adjoining road(s) and junction(s) can accommodate the additional traffic generated by significant increase of development intensity.’

95. This particular request from the BA in the Disapproval Letter to the [Church], with respect, appears to be an afterthought put in for good measure. In the recent case (October 2009) of China Field Ltd and Appeal Tribunal (Buildings) (No 2) FACV No. 2 of 2009 , the Traffic Issue consideration was placed in its proper context and the Tribunal would rely on that case to determine that IN THIS CASE there is no Traffic Issue:-

‘… the Authority would not be entitled to reject, building plans which involved the addition of further floors above an existing building but no alteration to the existing access to the street, because the building works would not involve the construction, formation or laying out of any means of access but only the use of an existing one. The fact that the massive increase in the volume of traffic using the street would cause danger or inconvenience to traffic even in the immediate vicinity of the site would not be sufficient.’

96. As the Appellant rightly indicates in his submission, and the Tribunal is of the view that in any event one or two parking spaces would be insignificant (i.e. no ‘massive increase in the volume of traffic’) in term of generating additional traffic in the area especially considering the Site is adjacent to a parking lot of the Wan Chai Polyclinic whose parking lot already has an unspecific number of vehicles coming in and out of it accessing Kennedy Road.

97. Furthermore, the Tribunal is of the view that the BA’s invoking of BO sections 16(1)(d) and (j) may appear to

Page 37: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

be an effort for the sole purpose of creating a ‘blanket rejection’:-

‘The Building Authority may refuse to give his approval of any plans of building works where-

(d) the carrying out of the building works shown thereon would contravene the provisions of this Ordinance or of any other enactment, or would contravene any approved or draft plan prepared under the Town Planning Ordinance (Cap 131);

(j) any further particulars or other plans delivered to him, upon his refusal, under paragraph (i), to give his approval to any plans, are not to his satisfaction;’ (emphasis added)

76 I agree with Mr Ho that this conclusion of the Tribunal is

faulted with errors of law for the following reasons.

77 First, the Tribunal has erred in law and exceeded its

jurisdiction in the appeal by assessing the Traffic Information Ground on

a substantive footing.

78 As the Court of Appeal noted in Lau Siu Kin Rembert v

Building Authority [2013] 4 HKLRD 74 at paragraph 102, the extent of

the Tribunal’s powers vary according to the subject matter of the appeal.

Insofar as the subject matter concerns a request for particulars or further

particulars (ie, under section 16(1)(i) or (j)), then the Tribunal can do

more than confirm, vary or reverse the BA’s decision or substitute its

own decision on whether particulars are required.

79 What the Tribunal cannot do is to determine the existence

(or otherwise) of substantive grounds of refusal under section 16(1) (for

Page 38: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

example under section 16(1)(d) or (h)) by reference to the subject matter

of the BA’s request for particulars. That is a matter for the BA. Since the

BA itself had not made a decision either way on whether substantive

grounds for refusal existed in respect of traffic, it was not for the Tribunal

to take that decision for itself. See also Building Authority v Appeal

Tribunal (Buildings) and Dobrowen Investment Ltd (unreported, HCAL

20/2011, 20 December 2011) at paragraphs 69 - 76 (per Lam J as he then

was).

80 Mr Ismail however submits that under this ground in the

appeal, it must be open to the Tribunal to consider whether the BA was

justified in the first place to ask for those particulars.14 The Tribunal is

therefore entitled to rely on China Field to effectively conclude that there

was no justification for the BA to ask for further particulars.

81 In this respect, I accept Mr Ho’s further submissions that the

Tribunal’s reliance upon the CFA’s judgment in China Field (see

paragraph 59 of the Decision) is also an error of law.

82 The issue in that case was whether the BA was entitled to

invoke section 16(1)(h) as a ground for substantively rejecting the plans

before it on traffic grounds:

(1) It was not a holding in China Field that traffic concerns are

generally irrelevant as grounds for substantive disapproval

under section 16(1). On its facts the case was confined to an

issue of the scope of section 16(1)(h), which requires on its

14 This is distinguishable from Dobrowen Investment Ltd, supra, where Lam J noted at paragraph 70 that “it is not disputed that the comments needed to be addressed and the BA was justified in asking for such information.”

Page 39: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

terms building works themselves involving “means of

access”. The quoted words from China Field at paragraph

95 of the Decision were stated in and restricted to the

immediate context of section 16(1)(h).

(2) Further, even if section 16(1)(h) were a relevant

consideration at this stage, the vehicular access to the

proposed carpark for the Site falls within the meaning of

“means of access” as stipulated in that provision. As the

proposed access involves construction of new vehicular

access to Kennedy Road from the subject site via the

Triangular Area which is within the adjoining lot, the BA

would be entitled to reject the General Plan if concerns as to

the traffic impact of the proposal were inadequately

addressed by the Church.

83 That is not the situation in the present appeal before the

Tribunal. China Field therefore has no application to the appeal before it.

84 It follows that, in deciding that there was no traffic issue in

the sense addressed in China Field (being a substantive reason for

rejecting the plans), the Tribunal has misdirected itself by asking and

answering the wrong legal question and acted inconsistently with the

formulation of the Traffic Issue (being an agreed one) at paragraph 13.4

of the Decision. Its decision is tainted by an error of law.

85 In further response, Mr Ismail seeks also to argue at this

hearing that the BA relied expressly on section 16(1)(j) instead of section

16(1)(i) in the Disapproval Letter to support this ground. Thus, this is a

disapproval based on substantive ground in being dissatisfied with the

Page 40: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

earlier particulars provided by the Church after the BA had disapproved

an earlier plan submitted in October 2009 on the basis of section 16(1)(i).

This is a disapproval based on section 16(1)(j) on substantive ground but

not on section 16(1)(i) in seeking further particulars. As such, the

Tribunal is fully entitled and right to consider whether there is any

substance in the traffic concern.

86 In relation to the plan submitted on 8 October 2009, the

BA’s disapproval is contained in a letter dated 4 November 2009 (ie, the

November Disapproval Letter). The relevant parts of that letter are

paragraphs 7B and 11, which state as follows:

“7B. Under Buildings Ordinance section 16(1)(i), you are required to indicate the means of access for the 2 carparking spaces on upper ground floor for my consideration. Your attention is drawn to the comments from the Assistant Commissioner for Transport/Urban at paragraph 11 below and I hereby reserve my position under Building Ordinance section 16(1)(h).

11. The Assistant Commissioner for Transport/Urban, Transport Department (Contact Officer: Ms. Chiny LEUNG at tel. no. 2294 2600) has the following comments:-

It is noted that there are two parking spaces proposed at the upper ground floor, the AP should demonstrate if the number of such car parking provision is in accordance to the HKPSG. Also the vehicular access to such parking spaces is not shown on plan, and we may offer further comment on the vehicular access when it is indicated.”

87 One can immediately see that the concerns raised by the

ACT as recorded in the November Disapproval Letter are different from

the ones set out in Appendix I of the Disapproval Letter.

Page 41: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

88 It is also obvious that the BA in paragraph‍ 7B of the

Disapproval Letter was asking the Church to provide particulars in

answer to the ACT’s second batch of concerns set out in Appendix I.

These have nothing to do with the particulars provided under and after the

November Disapproval Letter. This is also recognised by the Tribunal at

paragraph 94 of the Decision (see above).

89 As such, although the BA only referred to section 16(1)(j) in

the Disapproval Letter, properly understood objectively in context, it

clearly also disapproved the General Plan on this occasion on the basis

that further particulars were required to be provided in relation to the

other concerns raised by the ACT, ie, on the basis of section 16(1)(i).

This must have been so similarly understood by the parties as reflected by

the Traffic Issue in the appeal as recorded by the Tribunal at

paragraph 13.4 of the Decision.

90 In the premises, I reject Mr Ismail’s submissions that the BA

did not disapprove the General Plan also on a section 16(1)(i) ground.

91 I therefore accept Mr Ho’s submissions that the Tribunal has

erred in law in determining the Traffic Information Ground on a

substantive basis.

92 Second, even assuming that it was proper for the Tribunal to

make its own substantive assessment of the traffic situation, in doing so,

the Tribunal has failed to take into account relevant considerations in

only referring to the number of parking spaces at the Site as a reason for

Page 42: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

concluding there was no legitimate traffic concern as regards the General

Plan.

93 From the comments raised by the ACT as recorded in

Appendix I of the Disapproval Letter, the real concern as to traffic was

not just that additional traffic would be caused by increased parking

spaces at the Site but that additional traffic would inevitably be caused

by:

(1) The formation of vehicular run-in/out to Kennedy Road.

(2) The greatly increased capacity of the Church, by reason of

its increased size and expanded facilities, to accommodate

people and activities on Sundays and throughout the week.

94 This is turn could potentially give rise to grounds for

disapproval based on, among others, possible dangers posed to users of

the Site and the general public.

95 In failing to address the above concerns, the Tribunal

overlooked material and relevant considerations as to traffic impact. This

amounts to an error of law.

96 In the premises, the Tribunal’s conclusion is also unlawful in

failing to take into account relevant consideration.

97 Finally, Mr Ho also challenges this part of the Decision by

saying that there is procedural unfairness or irrationality in the Tribunal’s

observation that the BA’s disapproval of the General Plan based on the

Page 43: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

Traffic Information Ground is an “afterthought” and “for the sole purpose

of creating a blanket rejection”.

98 As far as I can see, reading objectively this part of the

Decision, the Tribunal’s above observation does not form part of the

reasons for or basis of the Traffic Information Conclusion. Therefore, I

do not think it is necessary for the BA to challenge that in order to

succeed in seeking to quash that part of the Decision.

99 However, in case I am wrong on this, I agree with Mr Ho

that this part of the observation is obviously tainted with procedural

unfairness or is unlawful since:

(1) This observation is a serious allegation, but one which was

not raised against the BA at any point in the proceedings

either by the Church or the Tribunal. Thus, the BA had been

given no opportunity of addressing it.

(2) The observation in effectively saying that the BA was acting

in bad faith or otherwise improperly is not supported by any

evidence (given that this allegation was ever raised against

the BA).

100 In the premises, if this observation forms part of the basis of

the Traffic Information Conclusion, it is tainted by unfairness and is

otherwise irrational, and should also be quashed on this basis.

101 For all these reasons, the BA also succeeds in this ground of

judicial review. The Traffic Information Conclusion of the Decision

should be quashed and remitted back to the Tribunal for reconsideration.

Page 44: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

C3. The MOE and Firewall Conclusions and the final order

102 The challenges of the MOE and Firewall Conclusions and

the final order made in the Decision can and should be considered

together, as they are interlinked.

103 The MOE Ground arose in the following way.

104 Paragraph 8.2 of the MOE Code provides as follows:

“Every exit route should lead directly to a street or to an open area at ground level having unobstructed access, not less in width than the total required width of exit routes discharging into such an area, to a street. Such access to a street should not be closed with doors or gates unless such doors or gates are capable of being readily opened from inside without the use of key(s) and in the direction of exit.”

105 In the General Plan, as a proposed MOE, there is a staircase

leading from the upper floors of the proposed building discharging people

to the Triangular Area in front of the Polyclinic.

106 It is the BA’s view that this proposed MOE is not in

compliance of paragraph 8.2 of the MOE Code, since the proposed exit

does not lead directly to a “street” or “an open area” having unobstructed

access. In particular, it is the BA’s view that the Triangular Area being

part of the space of the Polyclinic is under the control of the Department.

107 The Church however argued that the BA was wrong in

treating the Triangular Area as if it was not part of Kennedy Road. It is

the Church’s contention that the Triangular Area came within the

definition of a street and the MOE satisfied the MOE Code.

Page 45: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

108 Whether the BA is correct in this view is a mixed question of

law and fact, including what is the nature and use of the Triangular Area.

109 In the MOE Conclusion, the Tribunal however decides that

this issue should be reconsidered by the BA in light of its earlier

conclusion that at least a major part of the Triangular Area can continue

to be regarded as part of Kennedy Road or that it is a specified street by

reason of the right of way.

110 The Firewall Ground arose the following way.

111 Paragraph 7.4 of the Fire Resisting Construction Code (“the

FRC Code”) provides as follows:

“Any part of any building within a distance of not more than 900 mm of a common boundary with an adjoining site should be enclosed by imperforate external walls and roof having the same FRP as that of the internal elements of the construction. Openings protected by fixed lights having and FRP of not less than 1/2 hour, 1 hour in the case of a required staircase or its lobby, may however be made in such external walls and roof provided they are not less than 450 mm from such boundary.”

112 The BA in disapproving the General Plan on the Firewall

Ground was of the view that, contrary to paragraph 7.4 of the FRC Code,

the proposed building does not provide the requisite fire resistant wall

with the adjoining site, being the Triangular Area.

113 After looking at various other paragraphs of the FRC Code

and taking note of the Church’s contentions that the “site” referred to in

paragraph 7.4 should be interpreted to mean a building instead of an

existing open site, the Tribunal agrees with the BA that the “site” could

Page 46: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

mean an open site as the FRC Code should be “forward looking” (see

paragraphs 88 - 90 of the Decision).

114 However, the Tribunal further forms the view that the issue

arising under the Firewall Ground is whether the majority part of the

Triangular Area can be regarded as a “specified street”, since if it is so,

then “the BA’s contention that the boundary of the site ends at the edge of

the sidewalk abutting the ‘public’ Kennedy Road sidewalk” cannot be

correct (see paragraphs 91 and 92 of the Decision).

115 For this, the Tribunal then says given its earlier conclusion

that at least some parts of the Triangular Area is a “specified street”, this

Firewall issue should also be remitted back to the BA together with the

MOE issue for further consideration in light of the Tribunal’s finding vis-

à-vis the Triangular Area.

116 The Tribunal says these at paragraphs 84, 85, 91, 92, and

101 - 108 of the Decision on the MOE and Firewall issues and as to how

they should be dealt with:

“84. If the [Church’s] abutment-to-Kennedy-Road-argument succeeds in whole or part it may affect:-

84.1 Site classification as a lengthening of the boundary could result in classification as a Class B site;

84.2 The MOE Issue and the Fire Wall Issue would have to be reconsidered as to where the discharge onto the Triangle Area takes place.

85. The Tribunal determines that their findings regarding the MOE Issue should be considered together with the Fire Wall Issue below.

Page 47: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

91. The Tribunal must determine where the [Church’s] Site ceases to border a specified street. The tribunal has found that the Necessary Additional Boundary requirement extends past the existing car park. As such the 40% hurdle has been met by considering the Right-of-Way and the Remaining Sections, which boundary ends at the west edge of the existing car park of the Site. As above, the Tribunal has found that the Tip Section, the Sidewalk Section and the Right-of-Way Section are all not only streets as defined but also specified streets. As such, the boundary of the Church’s land that borders specified streets continues along with Tip Section, along the Sidewalk Section until the edge of the [Church’s] car park (as this is the far boundary edge of the Right-of-Way Section of the Triangular Area) (see Tribunal’s Diagram at Paragraph 40).

92. As such, the [Church’s] contention that the boundary area compasses the entire Southern Boundary of the site is incorrect but, so is the BA’s contention that the boundary of the site ends at the edge of the sidewalk abutting the ‘public’ Kennedy Road sidewalk: the Tribunal has determined that the boundary of the Site to a specified street ends at the edge of the [Church’s] current car park area (referenced near in the attached Diagram). This is so because the boundary (from to on the Tribunal Diagram at paragraph 40 as well as the Brown hatched area on the Tribunal Diagram are subject to a Right of Way and/or abutment as above detailed. As such, the Church and BA must collectively reconsider both the MOE Issue and the Fire Wall Issue as it relates to the [general building plans (‘the GBP’)] in this new context. The Tribunal encourages the parties to make the appropriate determination on the basis of the Tribunal’s finding of the extent of the boundary as above and the resultant finding that the Site is a Class B Site. The parties should refer to the Final Decision and Costs section below.

The Conditions

101. The [Church] is required to comply with the following criteria and conditions (the ‘Conditions’) before a final order can be issued by this Tribunal:-

Page 48: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

101.1. The [Church] is to submit a revised GBP with only modifications aiming to address the MOE Issue and the Fire Wall Issue to the BA; and

101.2. The BA must reconsider the revised GBP by the [Church] and must only approve or disapprove the revised GBP based solely on the MOE Issue and the Fire Wall Issue.

102. The Members of the Tribunal noted the suggestion by Rev. Cyril Clarke in his letter in 1977 to the then-Director of Medical and Health Services:-

‘… The only effective solution, as we see it, is a request to you to consider surrendering this small triangle to the English Methodist Church.’.

103. The Tribunal humbly agrees with Rev. Clarke that this certainly would have been an ‘effective solution’ to the future problems that this rather ‘restricted-use’ piece of land has caused. Had Rev. Clarke’s suggestion been followed up at that time, this Case may not have been necessary.

Conclusion

104. Having considered all relevant issues, facts and legal principles, the Tribunal has determined that the BA erred in not exercising its discretion to approve the [Church’s] GBP. The BA should have looked at entire re-development project as a whole and should also have considered each issue in relation to other aspects and issues in order to exercise its statutory powers and discretion.

105. Furthermore, without criticizing the BA, the BA could have assisted the [Church] more fully in discussing fully the necessary amendments to the GBP and taking positive actions in order to comply with the relevant regulations, industrial standards and preferred guidelines (i.e. HKPSG).

106. Under s.50(2) of the BO: ‘In determining an appeal, the Appeal Tribunal may make an order confirming, varying or reversing the decision that is appealed against or substituting therefor such other decision or make such other order as it thinks fit.’, the Tribunal is hereby empowered to give this decision in favor of the [Church].

Page 49: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

Final Decision and Costs

107. The Appeal is therefore unanimously allowed. The grounds set out in the Disapproval Letter from the Building Authority in its disapproval be set aside.

108. The [Church] within 90 days from the date of this judgment should resubmit a new set of building plans by making and only making the necessary adjustments (in order to fulfill the grounds from the [Church’s] last submitted building plans, for the BA’s consideration (the ‘Revised Building Plans’). Upon the receipt of the Revised Building Plans from the Appellant, the BA shall consider these new plans without adopting their prior grounds within 45 days.”

117 In substance, the Tribunal decides not to determine the MOE

and Firewall Grounds in the appeal as the validity of these grounds would

be affected by the Tribunal’s conclusion that the Triangular Area is either

a specified street as part of Kennedy Road or by reason of the right of

way. It further directs that the BA shall reconsider these and only these

two issues upon the Church submitting a revised building plan for

approval, where the revision shall also only be made in relation to these

two matters.

118 Mr Ho submits that these parts of the decision as well as the

final order made should be quashed for being wrong in law. This is so as

the Tribunal has either abdicated its statutory duty under section 50 of the

BO in not determining the MOE and Firewall Grounds (in particular in

light of the Tribunal’s power to call for and hear additional evidence if

necessary), or is acting unlawfully in making the final order which limits

what the BA may do in deciding whether to approve or disapprove the

revised plan.

119 Section 50 of the BO provides as follows:

Page 50: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

“(1) The following shall apply in relation to the hearing and determination of an appeal or a preliminary hearing held under section 49—

(a) every question shall be determined by the opinion of the majority of the members of the Appeal Tribunal;

(b) where there is an equality of votes, the Chairman shall have a casting vote;

(c) the Appeal Tribunal may—

(i) receive and consider any oral, documentary or other evidence, (including any written statement), whether on oath, affirmation or otherwise, and whether or not it would be admissible in evidence in proceedings in a court;

(ii) by summons issued in the prescribed manner, require any person to attend before it at any hearing to give evidence or to produce any document;

(iii) administer oaths or affirmations;

(iv) examine on oath, affirmation or otherwise any person attending before it and require such person to answer any question put by or with the consent of the Tribunal.

(2) In determining an appeal, the Appeal Tribunal may make an order confirming, varying or reversing the decision that is appealed against or substituting therefor such other decision or make such other order as it thinks fit.”

120 I think there is some force in Mr Ho’s contention that the

Tribunal has abdicated its duty. However, I also note that section 50(1)

(c) (by the use of the word “may”) does not compel the Tribunal to

receive and hear new evidence in determining any issues before it, while

section 50(2) is drafted in wide terms in giving the power to the Tribunal

to make “any such other orders as it thinks fit”. It is unlikely to be the

intention of the legislature to limit the form of order that the Tribunal can

make which it thinks is justified in all the circumstances of each case.

Page 51: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

121 At the same time, in light of section 15 of the BO, I also

think there are merits in Mr Ho’s contention that the conditional order

made by the Tribunal is unlawful in limiting the bases upon which the

BA may disapprove the revised plan submitted.

122 Section 15 of the BO provides as follows:

“(1) Where an application is made in the specified form for the Building Authority to approve plans or to consent to the commencement of building works or street works, he shall be deemed to have given his approval or consent, as the case may be, unless within the period prescribed by the regulations he has notified his refusal to give his approval or consent, as the case may be, in writing setting out the grounds for such refusal, and where one of such grounds is that further particulars and plans are required, he shall specify such plans and particulars. (Amended 68 of 1993 s. 7)

(2) The grounds set out for any refusal to approve plans shall not be treated as being exhaustive, and no such refusal shall be construed as implying any approval of any part of such plans.” (emphasis added)

123 Thus, by statue, the BA is not to be prohibited from relying

on other grounds of disapproval even if it has set out expressly certain

grounds of disapproval in a letter.

124 As such, I cannot see how the Tribunal can by its order in

requiring the BA to reconsider a revised plan limit the grounds upon

which the BA can reject the plan. For example, even if the BA after

looking at the revised plan (and even if the revisions only relate to the

MOE and Firewall issues) finds that there are other good grounds to

reject the plan although they have not been considered or set out

previously in the Disapproval Letter, by reason of the order, it can no

longer rely on those to disapprove the plan. That in my view would

Page 52: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

arguably be contrary to section 15(2) of the BO. Moreover, in revising

the General Plan even only in relation to the MOE and Firewall issues as

directed by the Tribunal, one cannot rule out the possibilities that that

may result in making corresponding or necessary changes in relation to

other parts of the plan. These changes may give rise to new grounds or

legitimate concerns for the BA to disapprove the revised plan. I cannot

see why and how the Tribunal can by way of its order dealing with the

appeal lawfully and legitimately restrict the BA’s authority under

section 16 to disapprove that revised plan on other grounds.

125 This also perhaps underlines the proposition as to why it is

not a preferred or satisfactory way to deal with the MOE and Firewall

issues in the way as the Tribunal has done. This would only result in

further uncertainty.

126 However, I do not find it necessary to come to a firm

conclusion on these contentions raised by Mr Ho, as the Tribunal’s MOE

and Firewall Conclusions should be quashed on the basis that I have also

quashed its conclusion that the Triangular Area is part of Kennedy Road

or is a specified street by reason of a right of way. As such, there is no

more rational and lawful basis to support the Tribunal MOE and Firewall

Conclusion, and they must therefore be quashed.

127 Moreover, given that I have in the above quashed the

Classification Conclusion, the MOE and Firewall Conclusions as well as

the Traffic Information Conclusion, the final order must also be quashed.

Page 53: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

D. CONCLUSION

128 For the above reasons, the BA succeeds in this judicial

review.

129 I will quash the Decision and remit the appeal back to a

differently constituted Tribunal for reconsideration. I do not find it

necessary or desirable to remit the matter to the same Tribunal. Leaving

aside the practical question as to whether all the same members could still

be reconstituted, these members heard the appeal almost four years ago

and it would be unrealistic to expect that they could still usefully

remember the evidence heard in the original appeal in October 2011.

Coupled with my conclusion that the Tribunal had likely to have already

confused the Church’s submissions in reaching the Classification

Conclusions in the Decision, I do not think there is any advantage to be

gained by remitting the appeal back to the same tribunal for

determination.

130 In relation to costs, since the BA is successful in this judicial

review, there are no reasons why costs should not follow the event. I

would make an order nisi that the BA’s costs of this application to be

borne by the Church, to be taxed if not agreed, with certificate for two

counsel. This order shall become absolute 14 days from today unless any

of the parties applies by summons to vary it.

131 Finally, I would like to thank counsel’s assistance in this

matter.

Page 54: HCAL000011_2014

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

R

S

T

U

V

(Thomas Au)Judge of the Court of First Instance

High Court

Mr Ambrose Ho SC and Mr Abraham Chan, instructed by Department of Justice, for the applicant

The respondent was not represented, absent

Mr Anthony Ismail, instructed by Mayer Brown JSM, for the interested party

Page 55: HCAL000011_2014
Page 56: HCAL000011_2014