hareket
CONTENTS
• PROJECT INFORMATION
• LOAD DETAILS
• TRANSPORT ROUTE
• TRANSPORT CONFIGURATION
• TECHNICAL DETAILS OF TRAILER
• REASONS FOR CHOOSING SPMT
• OBSTACLES ON THE ROUTE
• TRANSPORT OPERATION
• INSTALLATION OPERATION
hareket
3 Sayfa
• Project area: Mine site is 20 km away from Gördes Town by an asphalt road and it is
nearly 45 km from Akhisar Town, 115 km from Manisa and 180 km from İzmir Aliaga
Petkim Port. The nearest state railway is about 40 km away.
• A total of 230,000 tons of nickel ore was produced from two open pits and 150,000
tons of ore was exported to Greece, Macedonia and China, since 2003.
Approximately 80,000 tons of the remained nickel ore was stocked at the mine site,
to be used during trial production of the process plant, which is under construction.
• After several researches Meta Nickel Management decided to use HPAL (High
Pressure Acid Leaching) process with 255 C° and 55 bar pressure to separate
Nickel.This is the latest technology to produce nickel and cobalt cakes with low acid
usage and environment protections. That’s why an Autoclave ordered to Morimatsu
Nantong.
PROJECT INFORMATION
hareket
• MAIN CONTRACTOR: META NICKEL
• SUBCONTRACTOR:PANALPINA WORLD TRANSPORT
• TRANSPORT CONTRACTOR: HAREKET HEAVY TRANSPORT
PROJECT INFORMATION
SCOPE OF HAREKET
• ROUTE SURVEY AND PLANING
• TRANSPORT 600T AUTOCLAVE FROM PETKIM PORT TO GORDES JOB SITE
• INSTALLATION CARGO ONTO FOUNDATION
hareket
LOAD DETAILS Autoclave weight :600 tones
Dimensions :L = 34 m W = 7.05 m H = 7.15 m
Loaded height :H = 8.15 m
hareket
TRANSPORT ROUTE
• Petkim Port-Aliağa-Bergama-Kınık-Soma-Akhisar-Gördes Job site
• Total 180 km
• 335 critical points
• %12 percentage slopes and downhills
• All route survey done with gps system
hareket
TRANSPORT CONFIGURATION
• Traction Force Calculation
PST/SL-E Driving Performance Data with PFV 490/60-31
PST/SL-E Fahrleistungsdaten mit PFV 490/60-31
Combination Selection Kombinationszusammenstellung
PST
/SL-
E
33 66 x 24
Standard - SL-E - Modules Units Anzahl
Driven
AL Antr.-
Ali.
DW/Module EG/Modul
Deadweight
total EG
gesamt
Powerpacks PFV 490/60-31 2 - - - 7.500 kg 15.000 kg
SL-E 4-08x02 1 driven AL 1 1 17.300 kg 17.300 kg
SL-E 6-12x04 2 driven AL 3 6 25.700 kg 77.100 kg
SL-E 8-16x04 2 driven AL 0 0 33.700 kg 0 kg
SL-E 4-08x00 split 0 driven AL 0,5 0 17.500 kg 8.750 kg
SL-E 6-12x00 split 0 driven AL 1,5 0 25.700 kg 38.550 kg
SL-E 8/6-12x04 2 driven
AL 0 0 29.100 kg 0 kg
more (+) or less (-) driven axle
lines
5 460 kg 2.300 kg mehr (+) oder weniger (-) angetriebene Achslinien
Non-driven THP/SL axle
lines
0 - - - 3.400 kg 0 kg nicht angetriebene THP/SL Achslinien
Additional equipment (e.g. P-consoles, decks, etc.) Zubehör (z.B. P-
Konsolen) 680 kg
Axle lines total Anzahl Achslinien gesamt 33 AL
thereof driven axle lines davon angetriebene Achslinien 12 AL
Technical Data Technische Daten
Deadweight Eigengewicht 159.680 kg
Axle load unladen Achslast unbeladen 4.900 kg
Selected laden axle load ausgewählte beladene Achslast (ma
x. 45.000 kg) 23.021 kg
Gross weight Gesamtgewicht 759.680 kg
Payload approx. Nutzlast ca. 600.000 kg
Driving Performance Data Fahrleistungsdaten
Rolling resistance factor Rollwiderstand
5,0 % Traction factor Kraftschlussbeiwert
50 %
Empty Drive Leerfahrt
Driven axle lines angetriebene Achslinien 4 8 12 AL
Max. speed level ground Max. Geschwindigkeit Ebene 14,1 7,8 5,3 km/h
Laden Drive Lastfahrt
Driven axle lines angetriebene Achslinien 4 8 12 AL
Max. speed level ground Max. Geschwindigkeit Ebene 4,2 3,8 3,5 km/h
Max. grade max. Steigung 1,3 7,6 14,0 %
Speed on max. grade Geschwindigkeit max. Steigung 3,4 1,7 1,1 km/h
Max. tractive force max. Zugkraft )* 118 kN/AL 471 942 1.413 kN
Max. speed selected grade ausgewählte Steigung 12,0 % 0,0 0,0 1,3 km/h
Max. speed of tire max. Geschw. des Reifens 15,0 km/h
PST/SL-E Driving Performance Data with PFV 490/60-31
PST/SL-E Fahrleistungsdaten mit PFV 490/60-31
Combination Selection Kombinationszusammenstellung
PST
/SL-
E
33 66 x 24
Standard - SL-E - Modules Units Anzahl
Driven
AL Antr.-
Ali.
DW/Module EG/Modul
Deadweight
total EG
gesamt
Powerpacks PFV 490/60-31 2 - - - 7.500 kg 15.000 kg
SL-E 4-08x02 1 driven AL 1 1 17.300 kg 17.300 kg
SL-E 6-12x04 2 driven AL 3 6 25.700 kg 77.100 kg
SL-E 8-16x04 2 driven AL 0 0 33.700 kg 0 kg
SL-E 4-08x00 split 0 driven AL 0,5 0 17.500 kg 8.750 kg
SL-E 6-12x00 split 0 driven AL 1,5 0 25.700 kg 38.550 kg
SL-E 8/6-12x04 2 driven
AL 0 0 29.100 kg 0 kg
more (+) or less (-) driven axle
lines
5 460 kg 2.300 kg mehr (+) oder weniger (-) angetriebene Achslinien
Non-driven THP/SL axle
lines
0 - - - 3.400 kg 0 kg nicht angetriebene THP/SL Achslinien
Additional equipment (e.g. P-consoles, decks, etc.) Zubehör (z.B. P-
Konsolen) 680 kg
Axle lines total Anzahl Achslinien gesamt 33 AL
thereof driven axle lines davon angetriebene Achslinien 12 AL
Technical Data Technische Daten
Deadweight Eigengewicht 159.680 kg
Axle load unladen Achslast unbeladen 4.900 kg
Selected laden axle load ausgewählte beladene Achslast (ma
x. 45.000 kg) 23.021 kg
Gross weight Gesamtgewicht 759.680 kg
Payload approx. Nutzlast ca. 600.000 kg
Driving Performance Data Fahrleistungsdaten
Rolling resistance factor Rollwiderstand
5,0 % Traction factor Kraftschlussbeiwert
70 %
Empty Drive Leerfahrt
Driven axle lines angetriebene Achslinien 4 8 12 AL
Max. speed level ground Max. Geschwindigkeit Ebene 14,1 7,8 5,3 km/h
Laden Drive Lastfahrt
Driven axle lines angetriebene Achslinien 4 8 12 AL
Max. speed level ground Max. Geschwindigkeit Ebene 4,2 3,8 3,5 km/h
Max. grade max. Steigung 3,5 12,0 20,5 %
Speed on max. grade Geschwindigkeit max. Steigung 2,1 1,1 0,7 km/h
Max. tractive force max. Zugkraft )* 159 kN/AL 634 1.269 1.903 kN
Max. speed selected grade ausgewählte Steigung 12,0 % 0,0 1,1 1,3 km/h
Max. speed of tire max. Geschw. des Reifens 15,0 km/h
Graveled Road Paved Road
hareket
REASONS FOR CHOSING SPMT
• Steering possibilities and less construction works on the route acc. to conventional
hydraulic trailer that are pulled by prime movers.
• 12 unit tyres per axle line-4 unit tyre per axle line more than 2.44m width spmt trailers
• Less loading height and less cable obstacles on the route
• No need big crane for installation at site
• %12 percentage slopes on the route.
hareket
Bridge by pass constructions 11 unit Removed Electricity and Telephone Cables 280 unit Removed Pedestrian Overpass Bridge 2 unit Road widening constructions 20 unit Removed Traffic Light 16 unit Removed Camera Tower and Traffic Signs 6 unit
OBSTACLES ON THE ROUTE
hareket
RECEIVE AUTOCLAVE ONTO TRAILER (SPMT)
Autoclave Discharge Operation in the Petkim Port, Aliaga Izmir, on 26 Apr 2013 Geared
vessel from SAL with a combined lift capacity of 1500 ton was engaged. Goldhofer
PST/SL-E (also called SPMT) placed along side vessel to receive the 600 ton autoclave
TRANSPORT OPERATION
hareket
The exit route is challenging since we have to manage 5 x 90 degree turns on route inside
Petkim Factory. The basic road profile and structure is suitable but improvements are
needed at some locations. Steel plates and filling material will be kept on stand by, so that
same can be used up on request.
TRANSPORT OPERATION
hareket
Snap shot showing one of the first by pass road constructions with the autoclave convoy in
position to cross over. Each and every by pass construction was different and a detailed
engineering plan was established to identify number of pipes, filling material, and time
frame for construction
TRANSPORT OPERATION
hareket
• Detailed Road Survey Done for the possible obstacles on our way.
• Applied to (KGM) Road Dept. of TR HQ for the road permissions and removing
permissions of two overpass pedestrian bridges.
• For 11 Bridges loading test reports prepared , application projects drawn and applied to
( DSI ) Government Water Supply Department for By-Pass Road construction
permissions.
• All of these preparations, planning's and surveys took 18 mounts of labor and
countless meetings in Shanghai ,Izmir , Gordes , Ankara and Memmingen.
TRANSPORT OPERATION
hareket
Two pedestrian crossings had to be partially removed while on route from port to job
site. Dismantling extent and method was studies well in advance to identify equipment
needs and time consumption
TRANSPORT OPERATION
hareket
The Last By-Pass Construction on
Medar Creek
TRANSPORT OPERATION
600t Autoclave on the main road
hareket
Sample Drawings for Mountain Road Journey
TRANSPORT OPERATION
All route at mountain road are checked with gps and turning simulation is made on
Autocad programme and minimum backfilling and widening works planned.
hareket
`The beginning of the “mountain road” was
narrow, winding and had an incline of up to 12
%. The fuel consumption of the SPMT at this
location and with 750 ton gross weight is
around 80 liter per km.
TRANSPORT OPERATION
Before transportation, journey plan is made,
and all parking points are defined and 11 unit
parking place is constructed.
hareket
A number of corners on route had to be extended significantly to accommodate the convoy
as shown below. The road extension work has to be removed again once the convoy
passed by to comply with instructions from the road safety department
TRANSPORT OPERATION
Autoclave transported
from sea level up to
totally 1500m altitude
hareket
Remember …! Everybody who was part of the SPMT operation and supervision had to
walk the whole distance of 180 km. Below a snap shot at km 155.
TRANSPORT OPERATION
hareket
Road and air temperatures rose every day a bid more and we had only a few hours
available per day to move the convoy. Usually the convoy started to move at 04: 30 AM and
stopped prior to noon. Water tankers were engaged to spray water and to cool the road
down as much as possible to prevent melting of asphalt.
TRANSPORT OPERATION
hareket
After 64 days on route convoy makes its approach to the temporary foundation. The
autoclave needs to be offloaded in order to place the autoclave onto final foundation and to
reconfigure the SPMT
TRANSPORT OPERATION
hareket
Autoclave is now placed on temporary storage supports or also called
“elephant legs” SPMT is removed from under the autoclave and will be
reconfigured.
INSTALLATION OPERATION
hareket
The transfer of the autoclave from the temporary foundation onto final foundation
required a number of different step and scopes. Each of the scopes had to be
engineered well in advance and in detail which sounds easier than it is.
INSTALLATION OPERATION
hareket
Permanent foundation received
final touch in order to receive the
autoclave
Ground preparation work between
the temporary and permanent
foundation was completed in time
and left to rest over night.
INSTALLATION OPERATION
hareket
Day 67 autoclave was loaded onto SPMT’s early in the morning and as per plan and
schedule. Autoclave was lashed and secured once total weight was transferred onto
SPMT’s. The transfer operation was executed as planned and without any problems
INSTALLATION OPERATION
hareket
Final line with permanent
foundation required experience
and patient
The actual space available between the bolts
and the bolt holes was =/- 5mm only. The 746
tons are lined up with all 48 bolts with a
accuracy of +/- 5 mm… ready to place
autoclave slowly onto its final foundation
INSTALLATION OPERATION
hareket
Autoclave was delivered on to permanent foundations on 30.06.2013 at
17:00 without any incident.
INSTALLATION OPERATION
hareket
THANKS TO META NICKEL AND PANALPINA WORLD TRANSPORT FOR THEIR TRUST AND
GIVING CHANCE TO HAREKET HEAVY LIFTING AND PROJECT TRANSPORTATION COMPANY
FOR SUCH A CHALLENGING TRANSPORTATION JOB.
.