hampton roads bridge tunnel expansion: overview of … · 65 years of tunneling in hampton roads...

18
Hampton Roads Bridge Tunnel Expansion: Overview of Tunnel Construction Methods February 21, 2018 James S. Utterback HRBT Project Director Virginia Department of Transportation

Upload: lamtruc

Post on 01-Sep-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Hampton Roads Bridge Tunnel Expansion: Overview of Tunnel Construction Methods

February 21, 2018James S. UtterbackHRBT Project DirectorVirginia Department of Transportation

2/21/2018

Ten Hampton Roads Tunnels

2

Thimble Shoal Tunnel (1964)

Chesapeake ChannelTunnel (1964)

Monitor-MerrimacMemorial Bridge-

Tunnel (1992)

Hampton RoadsBridge-Tunnel(1957 & 1976)

MidtownTunnel

(1962 & 2016)Downtown

Tunnel(1952 & 1987)

2

2/21/2018

Dow

ntow

n Tu

nnel

#1

Ham

pton

Roa

ds #

1

Mid

tow

n Tu

nnel

#1

Thim

ble

Sho

al #

1

&

Che

sape

ake

#1

Ham

pton

Roa

ds #

2

Dow

ntow

n Tu

nnel

#2

Mon

itor-

Mer

rimac

Mid

tow

n Tu

nnel

#2

1950

1955

1960

1965

1970

1975

1980

1985

1990

1995

2000

2005

2010

2015

2020

65 Years of Tunneling in Hampton Roads

• 9 tunnels are steel-shell immersed tubes

• 1 tunnel is concrete-box immersed tube

• Future tunnel #11 at Thimble Shoal will be bored tunnel

3

8888

4

2/21/2018

Proposed Tunnel Alignment(Hampton Side)

55

2/21/2018 6

Proposed Tunnel Alignment(Norfolk Side)

6

2/21/2018

Proposed Lane Configuration for Tunnel and Approach Bridges

2+1+1 concept in each direction:

• 2 free General Purpose lanes

• 1 full-time HOT lane

• 1 peak-hour HOT lane on left shoulder

7

2/21/2018

Landside work has risks but is largely conventional

Tunnel work is less conventional and will generate greater risks from a contracting standpoint

• E.g. Midtown Tunnel contract’s limit of liability was tested against a potential scenario involving construction impacts to existing tunnel

This is a rare location where both immersed-tube and bored-tunnel construction methods are feasible

• All ten Hampton Roads tunnels to date have been immersed tubes• Until recently, bored tunnels were not feasible in soft soils • But recent advances in technology now make bored tunnels

possible in soft soils

These methods were directly compared in the nearby Thimble Shoal Tunnel procurement in 2015

8

Tunnel Considerations

2/21/2018

Immersed-Tube Tunneling (ITT)

9

Images property of respective owners.

2/21/2018

Jet Fans

Utility Corridor

EgressCorridor

New Midtown Tunnel Section

10

Images propertyof respective owners.

11

#2 Island

Existing Thimble Shoal Channel Tunnel (NB Traffic)

#1 Island

Proposed Thimble Shoal Channel Tunnel (SB Traffic)

Approximate Edge of Existing Island

11

Parallel Thimble Shoal Tunnel(initial concept)

2/21/2018

Bored Tunneling

Tunnel boring machine “Bertha,” recently at work in Seattle

12

Images propertyof respective owners.

2/21/2018 13

Interior of SR99 Tunnel in Seattle(57.5’ external diameter, 52’ internal diameter)

2/21/2018

Key Differences between Boredand Immersed-Tube Tunneling

Alignment• ITT alignment must be further away from existing tunnel (Hampton

Roads typical practice about 200 feet)• Bored tunnel can be much closer to existing facilities (estimate on

other projects about one diameter ≈ 50 feet)

Geotechnical• ITT method has limited concern for soil properties, since soil along

tunnel path is dredged out and removed• Bored method is specifically tailored to local soil properties

Environmental and Permitting• Section 408 coordination with marine stakeholders / federal channel• Section 103 concurrence for offshore disposal of ITT spoils• Joint permit covering upland disposal of bored-tunnel spoils

14

2/21/2018

Immersed Tunnel Considerations

Concept design• Approx. 7,500 ft. long• Approx. 3.5 million cubic yards dredged material• Dredged trench approx. 90 ft. wide with 3:1 side slopes

Navigational considerations at channel• Trench dredging• Placement & screeding of gravel bedding• Immersion of tunnel elements• Placement of cover fill

Other navigational considerations• Barge transport of dredged material for ocean disposal• Island expansion (fill & armor stone)• Limited additional geotechnical investigation is anticipated

15

2/21/2018

Bored Tunnel Considerations

Concept design• Approx. 8,300 ft. long• Deeper than immersed-tube tunnel because more cover is needed

e.g. for buoyancy control – therefore tunnel is longer• 4% roadway grades likely require island expansion lengthwise• Approx. 1 million cubic yards excavated tunnel material• Ground improvement at islands to support weight of tunnel boring

machine

Navigational considerations• Additional geotechnical investigations• Island expansion (fill & armor stone)

16

2/21/2018

Procurement Milestones and Next Steps

Initial outreach to industry in April 2017

Follow-up with potential proposers in January/February 2018

Firms expressed interest in both tunnel-construction methods

17

Milestones Target Date

Request for Qualifications December 15, 2017

Qualifications Due March 2, 2018

Shortlist Announcement April 2018

Request for Proposals Spring 2018

Contract Award Early 2019

Project Completion 2024

Questions?

18