gsi-191 resolution approach of the apr1400 · 2012-11-23 · gl 2004-02, “potential impact of...
TRANSCRIPT
GSI-191 Resolution Approach of GSI 191 Resolution Approach of the APR1400
Introduction
Sump performance evaluation approachSump performance evaluation approach
Conclusion
w M
eeti
ng
tio
n R
evie
wP
re-a
pp
lica
t8
th P
Introduction
Overview
NRC regulatory requirements
Clean plant criteria
w M
eeti
ng
tio
n R
evie
wP
re-a
pp
lica
t8
th P
1
GSI-191 Approach
Overview
Background Examined ECCS sump performance evaluation based on SKN 3&4 Examined ECCS sump performance evaluation based on SKN 3&4
Reviewed SECY 12-0093, ‘Closure Options for GSI-191’
Chose the option 1 to close the GSI-191 Chose the option 1 to close the GSI 191
SKN 3&4 sump performance evaluation
Mee
tin
g Fibrous insulation was used inside containment.
Debris generation and transportation evaluation were performed.
tio
n R
evie
w
Strainer performance analysis was performed by strainer supplier.
Pre
-ap
pli
ca
2
8th
APR1400-E-N-EC-120013-NP
GSI-191 Approach
Overview
Purpose Introduce GSI-191 resolution approaches for the APR1400 Introduce GSI 191 resolution approaches for the APR1400
– Clean-plant strategy
– Sump strainer performanceSump strainer performance
– In-vessel downstream effect
E t NRC t ff’ t th GSI 191 l ti
Mee
tin
g
Expect NRC staff’s comments on the GSI-191 resolution approach
tio
n R
evie
wP
re-a
pp
lica
3
8th
APR1400-E-N-EC-120013-NP
GSI-191 Approach
NRC regulatory requirements
RG 1.82, Rev.4, Water Sources for Long-Term Recirculation Cooling Following a Loss-Of-Coolant AccidentFollowing a Loss Of Coolant Accident
Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at PWR
Mee
tin
g GL 2004-02, “Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at PWRs”
tio
n R
evie
w
Application Methodology for ECCS Sump Performance Evaluation NEI 04 07 “Pressurized Water Reactor Sump Performance Evaluation
Pre
-ap
pli
ca
NEI 04-07, Pressurized Water Reactor Sump Performance Evaluation Methodology”
NRC Safety Evaluation Report (SER) for NEI 04-07
4
8th
APR1400-E-N-EC-120013-NP
GSI-191 Approach
Clean plant criteria
SECY-12-0093, Closure Options for GSI-191, specifies three options.
Option 1 : clean-plant criteria
Option 2 : graded approach
Mee
tin
g Option 3 : separated resolution
tio
n R
evie
wP
re-a
pp
lica
5
8th
APR1400-E-N-EC-120013-NP
GSI-191 Approach
Clean plant criteria (cont.)
Option 1, May 2, 2012 letter from NRC to NEI, ‘Clean Plant Acceptance Criteria’Acceptance Criteria
Most straightforward of the three available options to close GSI-191
Strainer and in-vessel issues can be resolved by satisfying 15g/FA
li it “ l l t” it i
Mee
tin
g
limits as “clean-plant” criteria.
– Bypass test results can be used to meet the clean plant criteria.
tio
n R
evie
w – In-vessel downstream effect test can be exempted.
If the quantity of fiber transported to strainer is less than 1/16”
Pre
-ap
pli
ca
If the quantity of fiber transported to strainer is less than 1/16
theoretical debris bed, a head loss test is not required.
6
8th
APR1400-E-N-EC-120013-NP
Sump PerformanceSump PerformanceEvaluation Approach
Break selection
Debris generation
D b i t tDebris transport
Debris bypass
Debris head lossDebris head loss
Downstream effect
w M
eeti
ng
tio
n R
evie
wP
re-a
pp
lica
t
7
8th
P
GSI-191 Approach
Break selection
In accordance with RG 1.82 Rev. 4, following break selection criteria are considered.
1) Pipe break in the RCS or MS/FW line with largest potential for debris
2) Large breaks with two or more different types of debris2) Large breaks with two or more different types of debris Not applicable, since no fibrous and particulate insulations inside
ZOI (zone of influence) are used for the APR1400.
Mee
tin
g 3) Break in the most direct path to the sump Not applicable, since there is no direct path to sump.
tio
n R
evie
w 4) Large break with the largest potential particulate debris to insulation ratio by weight Not applicable, since no fibrous and particulate insulations inside
Pre
-ap
pli
ca ZOI are used for the APR1400.
5) Breaks that create a relatively high head loss from 1/8” fiber bed
8
8th
APR1400-E-N-EC-120013-NP
GSI-191 Approach
Break selection (cont.)
The APR1400 postulated break pipe line analysisBreak Location
Pipe linesSize
ID (in)Inside Secondary Shield Wall Outside
Secondary Shield Wall
SG Compartment PZR CompartmentNo. 1 No. 2
Hotleg lines 42 ⅹ ⅹ
Coldleg lines 30 ⅹ ⅹ
PZR Surge line 12 ⅹ
Mee
tin
g
PZR Surge line 12 ⅹ
Shutdown Pump inlet lines 12.812 ⅹ ⅹ
Direct Vessel Injection lines 10.126 ⅹ ⅹ
Charging line 2 624 ⅹ
tio
n R
evie
w Charging line 2.624 ⅹ
PZR aux. spray line 2.624 ⅹ
POSRV lines 7.75 ⅹ
Pre
-ap
pli
ca SIT injection lines 10.126 ⅹ ⅹ ⅹ
Main steam lines 30.907 ⅹ ⅹ ⅹ
Feedwater lines 20.376 ⅹ ⅹ ⅹ
9
8th
APR1400-E-N-EC-120013-NP
Lines are selected based on the need for ECCS sump recirculation. Hotleg line break is the limiting case that generates the largest amount of debris.
GSI-191 Approach
Debris generation
RMI application
RMI Application APR1400
Equipment
• Reactor Vessel (RV), • Reactor Coolant Pump (RCP), • Steam Generator (SG),
Mee
tin
g
( ),• Pressurize (PZR)
• RV/SG/RCP Connecting Pipe Lines,
tio
n R
evie
w
Pipe Lines
g p• MS/FW Pipe Lines,• Pipe Lines located inside the ZOI which are
subject to the jet impingement
Pre
-ap
pli
ca
10
8th
APR1400-E-N-EC-120013-NP
GSI-191 Approach
Debris generation (cont.)
Fibrous insulation application
Exclude fibrous insulation inside ZOI for the APR1400.
Assumed 30lbs of latent fibrous debris inside containment
Mee
tin
g
Assumed 30lbs of latent fibrous debris inside containment.
– 30 lbs of latent fibrous debris for conservatism in accordance with
tio
n R
evie
w
NEI 04-07
Pre
-ap
pli
ca
11
8th
APR1400-E-N-EC-120013-NP
GSI-191 Approach
Debris generation (cont.)
3D Section view for break location of RCS hotleg pipe
Mee
tin
gti
on
Rev
iew
Break Location
Pre
-ap
pli
ca
12
8th
APR1400-E-N-EC-120013-NP
GSI-191 Approach
Debris generation (cont.)
Damage pressure and corresponding volume-equivalent spherical ZOI radius based on SER for NEI 04 07ZOI radius based on SER for NEI 04-07
Destruction Pressure ZOI Radius/Insulation types Destruction Pressure
[psig] Break Diameter[L/D]
Transco RMI 114 2 0
Mee
tin
g
Darchem DARMET 114 2.0
Unjacketed Nukon, Jacketed Nukon with 6 17.0
tio
n R
evie
w
Jacketed Nukon with standard bands
6 17.0
Epoxy Coatings(Qualified) - 4.0
Pre
-ap
pli
ca
(Qualified)
13
8th
APR1400-E-N-EC-120013-NP
GSI-191 Approach
Debris generation (cont.)
Debris generation for pipe breaks sampled for the limiting case
BreakDebris type and amount
RMI Fibrous Coating
Hotleg pipe3.22 m3
[114 ft3]0 m3 0.084 m3
[3.1 ft3]
Mee
tin
g
MS pipe3.03 m3
[107 ft3]0 m3 0.07 1m3
[2.6 ft3]
tio
n R
evie
w
[ ] [ ]
FW pipe2.88 m3
[102 ft3]0 m3 0.018 m3
[0 7 ft3]
Pre
-ap
pli
ca
[102 ft ] [0.7 ft ]
14
8th
APR1400-E-N-EC-120013-NP
GSI-191 Approach
Debris generation (cont.)
Analysis of debris generation for the APR1400 hotleg break
Insulation types Amount
RMI [m3/ft3] 3.22 / 114
Mee
tin
g Fibrous Insulation [m3/ft3] 0 / 0
Coating [m3/ft3] 0 084 / 3 1
tio
n R
evie
w Coating [m3/ft3] 0.084 / 3.1
Latent Debris
Fiber [kg/lb] 13.6 / 30.0
Particle [kg/lb] 77 1 / 170 0
Pre
-ap
pli
ca
• 200 lb is used as the upper bound amount of latent debris for conservatism per NEI 04-07.
Debris Particle [kg/lb] 77.1 / 170.0
15
8th
APR1400-E-N-EC-120013-NP
GSI-191 Approach
Debris transport
IRWST section view Strainer in IRWST sump
Break Location
IRWST Sump #2IRWST
Sump #4SPILLWAY
24 in.
Debris Flow Path
Mee
tin
g
HVT
tio
n R
evie
w
IRWST Sump #1
IRWST Sump #3
SPILLWAY24 in.
Pre
-ap
pli
ca
16
8th
APR1400-E-N-EC-120013-NP
GSI-191 Approach
Debris bypass
The 15g/FA limit as “clean plant criteria” will be used for the
APR1400
Bypass test to confirm the supportable plant fuel debris
limit(15g/FA) will be performed after the strainer supplier is
Mee
tin
g selected.
tio
n R
evie
w
Strainer will be designed and installed in IRWST to meet the
15g/FA limit .
Pre
-ap
pli
ca
g
17
8th
APR1400-E-N-EC-120013-NP
GSI-191 Approach
Debris head loss
SECY-12-0093 allows head loss test exemption.
If quantity of fiber transported to strainer is less than 1/16” theoretical
debris bed, head loss test is not required.
After the strainer supplier is selected, the debris bed thickness will
Mee
tin
g be calculated.
Purchase specification requirement to meet 1/16” limit.
tio
n R
evie
w
If debris bed thickness exceeds 1/16”, head loss test will be
performed.
Pre
-ap
pli
ca
18
8th
APR1400-E-N-EC-120013-NP
GSI-191 Approach
Downstream effect (cont.)
In-vessel effect
15 /FA li it “ l l t it i ” i d f th i l i f 15 g/FA limit as “clean plant criteria” is used for the in-vessel issue of
GSI-191.
Bypass test will be performed to verify if 15 g/FA limit is met after
strainer supplier selected.
Mee
tin
g
Ex-vessel effect
tio
n R
evie
w
The hole size of strainer will be limited to prevent plugging and severe
wear of pumps, HXs, orifices, nozzles and valves of ECCS.
Pre
-ap
pli
ca
19
8th
APR1400-E-N-EC-120013-NP
Conclusionw
Mee
tin
gti
on
Rev
iew
Pre
-ap
pli
cat
22
8th
P
GSI-191 Approach
Conclusion
We will follow the SECY 12-0093, option 1.
The APR1400 is designed to meet clean plant criteria.
Only RMI will be used in ZOI.
Containment cleanliness program will be established.
Mee
tin
g
Strainer performance test will be performed after strainer supplier
tio
n R
evie
w is selected.
Pre
-ap
pli
ca In-vessel issue of GSI-191 can be resolved by satisfying
the 15 g/FA limit as clean plant criteria.
21
8th
APR1400-E-N-EC-120013-NP
g p