ground grid testing 101 - tsdos thompson_tsdos... · 2018. 9. 20. · construction. • components...
TRANSCRIPT
Ground Grid Testing 101Cliff Thompson
North American Substation Services, LLCDirector of Strategic Business Development
• 36+ year career with Dominion Virginia Power• Retired in 10/16 as the T&D Manager for Electric
Transmission
SEPTEMBER 5 - 7, 2018
ems and Equipment SeminarMemphis, TN
2
Safety Moment!Look before Touch!
Always check grounds before touching equipment!
SEPTEMBER 5 - 7, 2018
Copper Theft
Check grounds before touching equipment3
SEPTEMBER 5 - 7, 20184Check grounds before touching equipment
Molten Steel
SEPTEMBER 5 - 7, 20185Check grounds before touching equipment
Underload and Cooking
SEPTEMBER 5 - 7, 2018
• Grounding Systems in Substations
• Safety Hazards During Testing
•Ground Grid Test Methods
•Case Studies
Topics
6
SEPTEMBER 5 - 7, 2018
PurposeProvides a surface, under and around a substation that is:
at a uniform voltage as close to zero (0) as is economically feasible (0.75 volts or lower)
Definition: Ground Grid or Ground MatGrounded system of wires and rods interconnected beneath substations Designed to Reduce Potential (Voltage) Hazards Step and Touch Potential Provide Equipment Grounding
Grounding Systems in a Substation
7
SEPTEMBER 5 - 7, 2018
Grounding System Design
8
Grounding accomplished by: Formation of a Ground Mat or Ground Grid Includes the Fence Bury 4/0 Cable in Ground Perimeter Conductor 3 ft. outside fence Perimeter Conductor 6 ft. beyond gates
All structures/equipment connected All Neutrals of the Power System are connected
Goal: Provide a surface, under and around the substation, that is at uniform ground potential. (as close to zero as is economically feasible: 0.75 volts or lower)
SEPTEMBER 5 - 7, 2018
Components of a Ground Grid
9
Ground Rods • Copper weld or equivalent
• 5/8 inch in diameter
• Free from grease and paint
• Minimum of one 6-foot section at each location
SEPTEMBER 5 - 7, 2018
Components of a Ground Grid
10
Ground Conductors Copper
Copper Clad Steel (CCS)
SEPTEMBER 5 - 7, 2018
Components of a Ground Grid
11
Fences
SEPTEMBER 5 - 7, 2018
Grid Connections
Finished connection12
CADWELL Connections
SEPTEMBER 5 - 7, 2018
Grounding Substation Equipment
13
Goal: Provide a surface, under and around the substation, that is at uniform ground potential. (as close to zero as is economically feasible: 0.75 volts or lower)
All equipment is grounded to the station ground gridHas same potential
SEPTEMBER 5 - 7, 2018
Substation Equipment
14
Circuit Breakers Transformers
• Grounded with 2 separate connections• Connections to 2 different sections of the ground grid• When transformer neutral to be grounded directly, neutral and at least one case ground should be visibly connected together
• Tanks connected with 2 separate ground connections • Each to a different section of the grid
SEPTEMBER 5 - 7, 2018
Substation Equipment
15
Capacitor Banks Voltage Regulators
Tank or cases grounded with 2 separate ground connections, each from a different section of the grid:
• One connects to stand and then to tank• One connects to tank and to SL bushing
• Metal supporting structures are grounded regardless of whether capacitor neutral is grounded or ungrounded.
• Supporting structure is grounded on diagonal corners with the ground lead being the same size conductor as the ground grid.
SEPTEMBER 5 - 7, 2018
Personnel Potential Hazards
16
Step Voltage
http://electrical-engineering-portal.com/6-voltages-a-person-can-be-exposed-to-in-a-substation
SEPTEMBER 5 - 7, 2018
Personnel Potential Hazards
17
Touch Voltage
SEPTEMBER 5 - 7, 2018
Personnel Potential Hazards
18
Mesh Voltage = Maximum Touch Voltage
SEPTEMBER 5 - 7, 2018
•Case Studies
Topics
19
SEPTEMBER 5 - 7, 2018
Safety during a Ground Grid Test
Let’s talk about it!20
NASS Safety First We always consider these 4 Human
Performance questions:1. What are the critical tasks in this project? 2. What errors am I most likely to make? 3. What's the most likely worst-case scenario? 4. What defenses will I use to avoid errors?
SEPTEMBER 5 - 7, 2018
Ground Grid Testing
The Ground Grid Testing is used to detect faulty ground connections.
Remember, Ground Grid provides:-Personnel Safety-Equipment Safety-Reliable Operation of Electrical Devices
21
SEPTEMBER 5 - 7, 2018
Types of Safety Hazards
The following Safety Hazards may occur when Ground Grid Testing:
• Touch Potential - if fault occurs while carrying/pulling the test lead
• Fault Potential - ground fault occurring during connection or disconnection of leads- fault current has the capability of flowing through the test leads and set
22
SEPTEMBER 5 - 7, 2018
• Case Studies
Topics
23
SEPTEMBER 5 - 7, 2018
Substation Ground Grid Testing
SEPTEMBER 5 - 7, 2018
EPRI’s Smart Ground Multimeter (SGM) Presently Available Functions
1. Ground (System) Impedance Meter 2. Touch Voltage Meter 3. Step Voltage Meter 4. Tower Ground Resistance Meter 5. Soil Resistivity Meter 6. Ground Mat Impedance 7. Transfer Voltage Meter 8. Low Impedance/Continuity Meter 9. Fall of Potential Method 10. Oscilloscopic Function 11. Pole Ground
Testing Methods
Smart Ground Multimeter Training Copyright 1994-2017, A. P. Sakis Meliopoulos
SEPTEMBER 5 - 7, 2018
• Relatively High Source Current and Voltage Capability Up to 500 Volts and 15 Amperes
• Random Pulse Width Signal 0-250 hz
• State of the Art Data Acquisition Hardware 24 bit SD A/D Converter 8 Channel Simultaneous Sampling
• Advanced Signal Processing Frequency Domain AveragingCoherence Based Noise Band Rejection
• Advanced Data Analysis State Estimation Based
Smart Ground Multimeter Training Copyright 1994-2017, A. P. Sakis Meliopoulos
SGM Design Parameters
SEPTEMBER 5 - 7, 2018
High Current Test MethodPurposeTests integrity of Substation Ground Grids
MethodologyPass high current (300 amperes D.C.) through Ground Grid between Reference Point and Test Ground using:
Sorenson Model DLM8 – 350E
Record Keeping- Record Voltage drop across grid- Path of current flow
27
SEPTEMBER 5 - 7, 2018
Test Equipment Set-Up
28
VARIAC
AMPS VOLTS
P1 C1 C2 P2
Current Up
Current Down
SEPTEMBER 5 - 7, 2018
Preparing to Test
1. Position test equipment in central area near planned reference point.
2. Operator should wear Class 2 rubber gloves or be on a portable protective ground mat.
29
SEPTEMBER 5 - 7, 2018
Preparing to Test
3. Mark up grounding plan with test points and reference point. Also indicate any equipment removed or added to station.
4. Consecutively number all risers to be tested with a paint pencil.
Note: Be sure to include the fence as a test point.
5. Perform the lead to lead. Note: Make sure to record the voltage drop for the lead to lead.
30
SEPTEMBER 5 - 7, 2018
Total Voltage Drop
Goal of the test is to measure voltage drop of individual test riser only
Reference Riser Voltage Test Riser Voltage
Total VoltageDrop
Voltage Drop is the electrical effort necessary to force the testcurrent through the ground grid and back to the reference.
31
SEPTEMBER 5 - 7, 2018
Current SplitWhen Testing, the 300 amps applied splits into 2 paths:
current flowing DOWN towards the grid+
UP towards the equipment
Example: Apply 300 amps to the Test Point = Current Up + Current Down
260 amps UP + 40 amps DOWN = 300 amps
32
SEPTEMBER 5 - 7, 2018
Voltage Drop Results
4/0 Copper Riser
33
Total Voltage Drop Interpretation
Less than 0.75 volts Good Grid
0.75 volts to 1.50 volts Safe grid but weakened
1.50 volts + Bad Grid
SEPTEMBER 5 - 7, 2018
Voltage Drop Results
Copper Clad Steel (CCS)
34
Total Voltage Drop Interpretation Less than 1.40 volts Good Grid
1.41 volts to 2.79 volts Safe grid but weakened
2.80 volts + Bad Grid
SEPTEMBER 5 - 7, 2018
Trouble Shooting
35
Possible Cause Situation
Current does not flow Possible open test connection
High voltage Possible bad connection or bad specimen
Low voltage(below 0.2 volts)
Possible connection problemPossible equipment failure
Unusual current split Possible break in the ground or loose connection to structure
SEPTEMBER 5 - 7, 2018
• Case Studies
Topics
36
SEPTEMBER 5 - 7, 2018
Case Study:• Substation expansion had recently been completed.• Capacitor bank and additional cable troughs had been added.• Ground grid testing had been performed prior to
construction.• Components had been reported failing during switching of
the new capacitor bank. • Upon further investigation ground grid testing was
recommended.• Testing discovered that during construction digging inside the
station had created an islanding issue with the new capacitor bank.
• Switching created transients that were introduced into the control house via the messenger ground and control cables.
SEPTEMBER 5 - 7, 2018
Case Study:• New 1500 MW Generating Station • Collector Station and power equipment had been installed• Control house was complete• Generation plant construction had been completed• Start-up operations had begun.• Unusual line events continued to trip units off line with no
good evidence or explanation.• Discovered that during final construction activities installing
hard surface road the preparation required a final grade.• During the process of final grading sub-surface grounds were
cut between plant and collector station. • No indication or evidence of the damage was detected until
performing the ground grid testing. • Site had been properly tested prior to final grading and start-
up.
SEPTEMBER 5 - 7, 2018
Additional thoughts!• If you are under construction for substation expansion or experienced a
failure of substation equipment it is recommended to perform spot checks on the ground grid within the affected area.
• Once new construction is complete a full comprehensive ground grid test is recommended to bench mark and provide assurance for safe operations.
• Performing point to point testing is an effective and convenient method to determine ground grid integrity.
• Performing various soil resistance tests using the SGM on green field sites prior to designing will add value and possibly prevent over or under designing.
• Bench marking ground grid test data is beneficial for engineering when expanding facilities or adding ground grid monitoring.
• Ground Grid monitoring may be considered for early detection of theft or grid deterioration.
SEPTEMBER 5 - 7, 2018
Conclusion
• Ground Grids are essential for the safe protection of workers, public, power equipment, electronic components and reliability.
• Establishing and following a ground grid testing program will ensure network reliability and longevity of the installed equipment.
• Copper theft is still among the highest security challenge facing utilities.• Monitoring (Cresatech CuTZ) can provide an early detection of grid integrity
and intrusion. • A healthy and properly engineered ground grid will provide critical equipment
the best operating condition to ride through transient events and power interruptions.
• Ground grid testing can be performed online and not requiring outages. • Ground grid testing provides the assurance that an engineered ground system
is properly protecting your critical high value assets and control components.
SEPTEMBER 5 - 7, 201841