Summer 2017 Prepared by Supervised by INFS7570 Applied Research Mohammad Balgoname Dr. John C. Turchek

Project Management Report

Green Computing Research Project Document ID: 01

Version: 1.0

Release Date: May 15th, 2017

Page 2: Green Computing Research: Project management report

Balgoname 2017

2

Table of Contents 1. Project Integration Management ............................................................................................................. 8

1.1 Definition of Green Computing ........................................................................................................... 8

1.3 Financial Analysis of Business case ................................................................................................... 14

1.4 Project Charter .................................................................................................................................. 15

1.5 Integrated Project Change Control ................................................................................................... 16

2. Project Scope Management .................................................................................................................... 20

2.1 Requirements Specifications ............................................................................................................. 20

2.1.1 Project Overview ........................................................................................................................ 20

2.1.2 Purpose and Scope of this Specification .................................................................................... 20

2.1.3 Traceability Matrix ..................................................................................................................... 21

2.1.4 Questions for Project Sponsor ................................................................................................... 23

2.2 Project Scope Statement .................................................................................................................. 23

2.3 Work Breakdown Structure 2.3.1 Work Breakdown Structure Table .............................................. 24

2.3.2 Work Breakdown Structure Tree ............................................................................................... 26

2.4 Gantt Chart ........................................................................................................................................ 27

3. Project Time Management ..................................................................................................................... 29

3.1 Review of WBS and Gantt Chart ....................................................................................................... 29

3.2 Project Milestones ............................................................................................................................ 30

3.3 Gantt Chart with Duration and Dependencies ................................................................................. 32

3.3.1 Gantt Chart ................................................................................................................................. 32

3.3.2 Network Diagram ....................................................................................................................... 32

3.4 Resource Assignment Matrix ............................................................................................................ 33

4. Project Cost Management ...................................................................................................................... 36

4.1 Project Planned Cost Budget ............................................................................................................ 36

4.1.1 Weekly Budget ........................................................................................................................... 36

4.1.2 Resource Usage .......................................................................................................................... 38

4.2 Project BAC and Planned Value ........................................................................................................ 39

4.3 Earned Value Analysis ....................................................................................................................... 39

4.4 Corrective Actions ............................................................................................................................. 41

5. Project Quality Management .................................................................................................................. 43

5.1 Quality Management Requirements ................................................................................................ 43

5.1.1 Quality Management Approach ................................................................................................. 43

Page 3: Green Computing Research: Project management report

Balgoname 2017

3

5.1.2 Quality Objectives and Standards Identification ....................................................................... 43

5.1.3 Project Reviews and Assessments ............................................................................................. 44

5.1.4 Deliverable Acceptance Criteria ................................................................................................. 44

5.2 Seven Basic Tools of Quality ............................................................................................................. 45

5.3 Summary of High Quality Research Report ...................................................................................... 46

6. Project Human Resource Management .................................................................................................. 48

6.1 MBTI Types in Work Environments ................................................................................................... 48

6.1.1 MBTI Personality types .............................................................................................................. 48

6.1.2 Introductory Email ..................................................................................................................... 50

6.2 Responsibility Assignment Matrix RACI ............................................................................................ 50

6.3 Human Resources Related Concerns ................................................................................................ 52

7. Project Communication Management .................................................................................................... 55

7.1 Project Issue Log ............................................................................................................................... 55

7.2 Applications of Wikis ......................................................................................................................... 56

7.3 Conflict Resolution ............................................................................................................................ 57

8. Project Risk Management ....................................................................................................................... 60

8.1 Risk Register ...................................................................................................................................... 60

8.2 Risk Assessment and Impact Matrix ................................................................................................. 61

8.3 Risk Response and Contingency Plans .............................................................................................. 62

9. Project Procurement Management ........................................................................................................ 64

9.1 Contract Agreement with Anne Consulting Firm .............................................................................. 64

9.2 Content of Research Report .............................................................................................................. 70

9.2.1 Executive Summary .................................................................................................................... 70

9.2.2 Table of Contents ....................................................................................................................... 70

9.3 Lesson Learned ........................................................................................................................... 71

10. Periodic Reporting: Project Monitoring and Controlling ...................................................................... 73

10.1 Week 13 Work Progress .................................................................................................................. 73

10.1.1 Gantt Chart Update .................................................................................................................. 73

10.1.2 Network Diagram Update ........................................................................................................ 74

10.1.3 Budget Report Update ............................................................................................................. 75

10.1.4 EVM Analysis ............................................................................................................................ 75

10.1.5 Status Report ........................................................................................................................... 76

10.2 Week 14 Work Progress .................................................................................................................. 77

Page 4: Green Computing Research: Project management report

Balgoname 2017

4

10.2.1 Gantt Chart Update .................................................................................................................. 77

10.2.2 Network Diagram Update ........................................................................................................ 78

10.2.3 Budget Report Update ............................................................................................................. 79

10.2.4 EVM Analysis ............................................................................................................................ 79

10.2.5 Status Report ........................................................................................................................... 80

10.3 Week 15 Work Progress .................................................................................................................. 81

10.3.1 Gantt Chart Update .................................................................................................................. 81

10.3.2 Network Diagram Update ........................................................................................................ 82

10.3.3 Budget Report Update ............................................................................................................. 83

10.3.4 EVM Analysis ............................................................................................................................ 83

10.3.5 Status Report ........................................................................................................................... 84

10.4 Week 16 Work Progress .................................................................................................................. 85

10.4.1 Gantt Chart Update .................................................................................................................. 85

10.4.2 Network Diagram Update ........................................................................................................ 86

10.4.3 Budget Report Update ............................................................................................................. 87

10.4.4 EVM Analysis ............................................................................................................................ 87

10.4.5 Status Report ........................................................................................................................... 88

10.5 Week 17 Work Progress .................................................................................................................. 89

10.5.1 Gantt Chart Update .................................................................................................................. 89

10.5.2 Network Diagram Update ........................................................................................................ 90

10.5.3 Budget Report Update ............................................................................................................. 91

10.5.4 EVM Analysis ............................................................................................................................ 92

10.5.5 Status Report ........................................................................................................................... 93

10.6 Week 18 Work Progress .................................................................................................................. 93

10.6.1 Gantt Chart Update .................................................................................................................. 93

10.6.2 Network Diagram Update ........................................................................................................ 94

10.6.3 Budget Report Update ............................................................................................................. 95

10.6.4 EVM Analysis ............................................................................................................................ 96

10.6.5 Status Report ........................................................................................................................... 96

10.7 Week 19 Work Progress .................................................................................................................. 97

10.7.1 Gantt Chart Update .................................................................................................................. 97

10.7.2 Network Diagram Update ........................................................................................................ 98

10.7.3 Budget Report Update ............................................................................................................. 99

Page 5: Green Computing Research: Project management report

Balgoname 2017

5

10.7.4 EVM Analysis ............................................................................................................................ 99

10.7.5 Status Report ......................................................................................................................... 100

10.8 Week 20 Work Progress ................................................................................................................ 101

10.8.1 Gantt Chart Update ................................................................................................................ 101

10.8.2 Network Diagram Update ...................................................................................................... 102

10.8.3 Budget Report Update ........................................................................................................... 103

10.8.4 EVM Analysis .......................................................................................................................... 103

10.8.5 Status Report ......................................................................................................................... 104

10.9 Week 21 Work Progress ................................................................................................................ 105

10.9.1 Gantt Chart Update ................................................................................................................ 105

10.9.2 Network Diagram Update ...................................................................................................... 106

10.9.3 Budget Report Update ........................................................................................................... 107

10.9.4 EVM Analysis .......................................................................................................................... 107

10.9.5 Status Report ......................................................................................................................... 108

10.10 Week 22 Work Progress .............................................................................................................. 109

10.10.1 Gantt Chart Update .............................................................................................................. 109

10.10.2 Network Diagram Update .................................................................................................... 110

10.10.3 Budget Report Update ......................................................................................................... 111

10.10.4 EVM Analysis ........................................................................................................................ 111

10.10.5 Status Report ....................................................................................................................... 112

10.11 Week 23 Work Progress .............................................................................................................. 113

10.11.1 Gantt Chart Update .............................................................................................................. 113

10.11.2 Network Diagram Update .................................................................................................... 114

10.11.3 Budget Report Update ......................................................................................................... 115

10.11.4 EVM Analysis ........................................................................................................................ 115

10.11.5 Status Report ....................................................................................................................... 116

10.12 Week 24 Work Progress .............................................................................................................. 117

10.12.1 Gantt Chart Update .............................................................................................................. 117

10.12.2 Network Diagram Update .................................................................................................... 118

10.12.3 Budget Report Update ......................................................................................................... 119

10.12.4 EVM Analysis ........................................................................................................................ 119

10.12.5 Status Report ....................................................................................................................... 120

10.13 Week 25 Work Progress .............................................................................................................. 121

Page 6: Green Computing Research: Project management report

Balgoname 2017

6

10.13.1 Gantt Chart Update .............................................................................................................. 121

10.13.2 Network Diagram Update .................................................................................................... 122

10.13.3 Budget Report Update ......................................................................................................... 123

10.13.4 EVM Analysis ........................................................................................................................ 123

10.13.5 Status Report ....................................................................................................................... 124

10.14 Week 26 Work Progress .............................................................................................................. 125

10.14.1 Gantt Chart Update .............................................................................................................. 125

10.14.2 Network Diagram Update .................................................................................................... 126

10.14.3 Budget Report Update ......................................................................................................... 127

10.14.4 EVM Analysis ........................................................................................................................ 127

10.14.5 Status Report ....................................................................................................................... 128

10.15 Week 27 Work Progress .............................................................................................................. 129

10.15.1 Gantt Chart Update .............................................................................................................. 129

10.15.2 Network Diagram Update .................................................................................................... 130

10.15.3 Budget Report Update ......................................................................................................... 131

10.15.4 EVM Analysis ........................................................................................................................ 131

10.15.5 Status Report ....................................................................................................................... 132

Page 7: Green Computing Research: Project management report

Balgoname 2017

7

Part 1

Page 8: Green Computing Research: Project management report

Balgoname 2017

8

1. Project Integration Management

1.1 Definition of Green Computing The concept of green computing has started to grow in the past few years, attaining

increasing popularity. Asides of the widespread sensitivity to ecological issues, such attention

also stems from economic needs, as both energy expenses and electrical requirements of IT

industry around the word show a continuously growing trend. This project aim is to define green

computing and provide actual application examples where green computing applications made a

positive impact.

The concept of green computing can be defined as "the environmentally responsible and

eco-friendly use of computers and their resources" (Techopedia, 2017). Green computing is also

defined as the examination of designing, manufacturing/engineering, utilizing and dumping of

computing devices in a way that lessens their environmental impact. Today, many IT

manufacturers and vendors are continually investing in designing energy efficient computing

devices, reducing the use of hazardous materials and encouraging the recyclability of digital

devices and papers. Recently, green computing concept expanded to include software code. The

advances of coding languages enabled the implementation of effective and efficient software

coding that saves power through making software less dependent on the use of hardware while

maintaining superior performance and less utilization of energy. (Singh & Vatta, 2016)

Green computing practices came into being in 1992 when the Environmental Protection

Agency (EPA) launched the Energy Star program - a government-backed labeling program that

helps individuals and organizations save money and reduce greenhouse gas emissions thought to

identify factories, office equipment, home appliances and electronics that have superior energy

efficiency. The EPA has more than 19,000 partner organizations across the United States to

Page 9: Green Computing Research: Project management report

Balgoname 2017

9

lessen emissions and achieve significant environmental and economic gains. EPA programs

prevent more that 416 million metric tons of U.S. GHG emissions. Also, reducing net energy

bills by more than $31 billion reductions in methane emissions by $7.7 billion in 2014 alone

(U.S. Environmental Protection Agency, 2016).

There are also other non-governmental organizations that support and apply green

computing concept throughout their organizations. One of these companies is VIA Technologies,

a Taiwanese company that manufactures motherboard chipsets, CPUs, and other computer

hardware. In 2001, VIA introduced an initiative for green computing that aims to design and

build efficient and effective hardware products that utilize less power. VIA's environmentally

friendly products are produced using a variety of clean-computing approaches. "In 2005, the VIA

launched its VIA C7-M and VIA C7 CPUs that have a maximum power consumption of 1W"

(Sultana, Suvarchala, & Ramay, 2016). These energy-efficient CPUs produced more than four

times less carbon during their operations and can be efficiently embedded in solar-powered

devices.

IBM is also one of the long supporters of green computing concept. In the 1960s, IBM

originated computer virtualization, which refers to the abstraction of computer resources, such as

the process of operating two or more logical computer systems on one set of physical hardware.

With virtualization capability, a system admin could merge many physical systems into virtual

machines on one single, robust system, thereby unplugging the original hardware and reducing

power and cooling consumption. Moreover, virtualization can assist in distributing work, so that

servers are either busy or put in a low-power sleep state.

Microsoft, Google, and Yahoo are addressing the environmental concerns about their

data center's carbon footprint, "the measure of the environmental impact of an individual or

Page 10: Green Computing Research: Project management report

Balgoname 2017

10

organization's lifestyle or operations, measured in units of carbon dioxide generated" (Rouse,

2010). In recent years, Microsoft and other corporations have built data centers in central

Washington to gain an advantage of the hydroelectric power produced by two dams in the

region. The Microsoft facility, which consumes up to 27 megawatts of energy at any given time,

is powered by hydroelectricity. Another Microsoft data center, located in Dublin, Ireland, that

started operation in 2009, thanks to Ireland's moderate climate, the 51,000-square-meter facility

is air cooled, making it 50& more energy-efficient than other comparable sized data warehouses.

(Kurp, 2008)

Google has committed to being carbon-neutral starting from 2007 and beyond, says Bill

Weihl, Google's director of energy strategy. According to Google, its data centers uses half the

industry's average amount of power. Google attributes this improved energy usage to the cooling

technologies, such as ultra-efficient evaporative cooling, that the company has customized for

itself. Yahoo’s data warehouses also went carbon-neutral, in part because of its use of carbon

offsets. (Kurp, 2008)

Many of industry-leading companies, such as Cisco Systems, Dell, Digital Reality,

Hewlett-Packard, IBM, and Intel to name few have joined efforts to reduce their carbon footprint

and promote the eco-friendlier environment through the establishment of a non-profit

organization called The Green Grid Association in 2007. The non-profit, open industry

consortium of information and communication technology (ICT) industry end-users, policy

makers, technology providers, facility architects have come together to improve data center and

IT resource efficiency globally, through sharing expertise and insights of best practices of

running data centers (The Green Grid, 2017). Overall green computing is a continuous non-

Page 11: Green Computing Research: Project management report

Balgoname 2017

11

endless innovation, and practices that make the use of hardware and software eco-friendlier and

saves energy and money. 1.2 Weighted Decision Matrix for Evaluation

The evaluation process of the project manager position of green computing research project

starts with identifying essential criteria that should be found in the nominees for this position.

After examining key characteristics of project manager, six criteria have been selected. Those

criteria are:

1. Project Management Experience

2. Knowledge level of IT

3. Leadership

4. Communication & Coordination

5. Analytical skills

6. Time Management

Each criterion is assigned by a rank of priority and weight factor which will be used to calculate

the final decision once candidates have been selected.

Table 1: Criteria selection

Once the priority has sorted, and weighted criteria, the process proceed to select candidates for

this position. Five candidates: Mia, Isabella, James, William, and Sophia nominated.

Page 12: Green Computing Research: Project management report

Balgoname 2017

12

Each candidate assigned points from a 1 – 10 scale. Then raw scores and weighted scores are

calculated to determine the rank of each candidate. The following chart shows the conclusion of

the decision matrix process.

Table 2: Decision Matrix

Based on the calculations that appear above, Mia has got the highest weighted score among other

candidates; therefore, she has been selected for this post. The following charts illustrate each

candidate weaknesses and straights. It also shows candidates total scores.

Page 13: Green Computing Research: Project management report

Balgoname 2017

13

Figure 2: Chart of total candidates’ scores

Figure 1: Chart of candidates’ straights and weaknesses

Page 14: Green Computing Research: Project management report

Balgoname 2017

14

1.3 Financial Analysis of Business case

Table 3: Project’s Financial Analysis

Page 15: Green Computing Research: Project management report

Balgoname 2017

15

1.4 Project Charter

PROJECT CHARTER

PROJECT NAME DATE AREA OF FOCUS

Green Computing Research 5/15/2017 Research and Development

BUSINESS CASE SCOPE In line with our strategic goal, which is to help improve

the environment while increasing revenues and reducing

costs. The VP of Operations, Natalie called for starting a

green computing research project.

IN SCOPE OUT OF SCOPE Thin client solutions Electronic waste disposal &

recycling

Development of green computing

solutions for internal use

Telecommuting Server resources virtualization Potential sale to other organizations

Open sources software Data center & Energy efficiency

MEASURABLE KEY DELIVERABLES

TARGET/GOAL DATE Financial analysis Standard work and reporting

Finalize Financial analysis 7/20/2017 Possible technologies to implement Orientation completion

Finalize recommended solutions 8/18/2017 Recommended Solutions

Finalize standard work and reporting 11/15/2017

SUCCESS FACTORS TIMELINE

Achieving scope of project ACTIONS/MILESTONES TARGET DATE/ STATUS Meeting time constraint Development of high level requirements 5/18/2017

Execute project within budget Team job descriptions approval 5/21/2017

Achieving high quality processes Selection of team members 5/25/2017

STAKEHOLDERS FINANCIALS

NAME FUNCTION BUSINESS IMPACT INVESTMENT Natalie VP of Operations The project shall provide environmental and financial

solutions that will save money and reduce the carbon

footprint of operating computers.

Total invested amount in the

project $356,000.00 Ben CIO & project sponsor

Mia Project Manager

ASSUMPTIONS/ CONSTRAINTS RISK PLANNING Project must complete in 6 moths Team members must be selected carefully as the project will be conducted online. Transacting

information among team members should be highly encrypted to assure the security. Team must be functioning by 5/15/2017

Work on project will be virtual (online

Sign-off:

VP of Operations: ……………… CIO & Project Sponsor: ……………… Project Manager: ………………

Page 16: Green Computing Research: Project management report

Balgoname 2017

16

1.5 Integrated Project Change Control The principal focus of Integrated Change Control is to measure the impact of changes or

modifications on all project constraints. Changes to any component of the project might be

requested at any given time during the development of the project, especially during the project

executing & monitoring, or control phases. It is not essential to achieve all changes. In the

Perform Integrated Change Control, changes or modifications are accepted or rejected based on

their evaluation and impact to the project by the project Change Control Board (CCB).

Mainly, there are three reasons for change request which are: preventive actions, corrective

actions, and defect repair. Whenever a change is received, suggested, or identified, it will be

logged in the Change log of the project. Regardless of the size of the change or the impact of the

change, each and every change will be recorded in the Change Log. The project manager, Ms.

Mia, alone cannot do the impact analysis, inputs from the project team and if required from the

stakeholders are needed. In the impact analysis, the impact of the proposed change is analyzed

on all project constraints scope, cost, schedule, quality, or any other dimension. This is a critical

step in the process as impact analysis will be regarded as input for the change request’s rejection

or approval. Once the impact analysis is done, it should be provided to the CCB along with

change request for the decision of approval, postponed, or rejected.

In case the change request is approved, the work associated to change request becomes part of

the project, and all associated project documents, plans, and charter get updated. If the change or

modification request is postponed or rejected, the CCB will send to the project sponsor the

reasons of postponed or rejection. Finally, the Change Log will be updated for all details

regarding change request such as the decision that has been taken on, reasons for postponed, or

rejection, and if accepted follow-up steps.

Page 17: Green Computing Research: Project management report

Balgoname 2017

17

Figure 3: Flowchart of Change Request Process

Page 18: Green Computing Research: Project management report

Balgoname 2017

18

Change Request Form

Project Name Project Sponsor

S

T

E

P

1

Urgency

Change Request # Originator Change Requested by Date Requested

JU

ST

IFIC

AT

ION

Description of Change Request #

Reason for Change

Proposed Approach to Resolve

PROJECT PLAN AREA IMPACT OF PROPOSED CHANGE(S)

S

T

E

P

2

IMP

AC

T

Impact on Scope

Impact on Schedule

Impact on Spending

Impact on Risk

Other

APPROVALS TO PROCEED

S

T

E

P

3

Originator/ Date Project Manager Sponsor/ Date Customer/ Date

Table 4: Change Request Form

Page 19: Green Computing Research: Project management report

Balgoname 2017

19

Part 2

Page 20: Green Computing Research: Project management report

Balgoname 2017

20

2. Project Scope Management

2.1 Requirements Specifications

2.1.1 Project Overview

The project calls for researching possible eco-friendly technologies that reduce carbon footprint

to reduce global warming and save money to reduce the financial burden of the organization.

2.1.2 Purpose and Scope of this Specification

This requirements specification document describes the functions and requirements specified for

green computing research project. The purpose of the specification document is to apply

constraints to what and what not is included in the scope of the research. There are several

requirements for this project, including but not limited to the establishment of project charter,

plan, scope baseline, cost baseline, and activity plan.

In Scope

❖ Thin client solutions

❖ Electronic waste disposal & recycling

❖ Telecommuting

❖ Server resources virtualization

❖ Open sources software, and

❖ Data center & energy efficiency technologies

Out of Scope

❖ Development of green computing solutions for internal use

❖ Potential sale to other organizations

Page 21: Green Computing Research: Project management report

Balgoname 2017

21

2.1.3 Traceability Matrix

Requirements Traceability Matrix

Project Name: Green Computing Research Project

Cost Center: Environmental Technologies Program

Project Description: Researching possible green computing applications

ID Associated ID

Requirements

Description

Business Needs,

Opportunities, Goals,

Objectives

WBS

Deliverables

Owner Source Status

001

1.0 Project Charter Project Justifications Project Charter

Project

Sponsor

Business Case Accomplished

1.1 Team Selection Candidates screening and evaluation

Project Team

Formation

Project

Manager

Project Charter Ongoing

1.2 Project Management Plan

Project execution and control guide

documentation

Project

Management Plan

Project

Manager

Project Charter Ongoing

1.2.1 Scope Management Plan Collection of all project's processes Project Statement

Project

Manager

Project Charter Pending

1.2.2

Requirements Management

Plan

Documentation of project's

requirements

Project

Management Plan

Project

Manager

Project

Management Plan

Pending

1.2.2.1

Requirements

Documentation

Project’s definition, traceability

matrix, and deliverables

Requirements

Management Plan

Project

Manager

Requirements

Management Plan

Ongoing

Page 22: Green Computing Research: Project management report

Balgoname 2017

22

002

2.0 Develop WBS

Organizes team's work into

manageable sections

WBS

Project

Manager

Scope

Management Plan

Pending

2.1 Scope Baseline

Finalized WBS, WBS dictionary, and

the project scope statement

Scope

Management Plan

Project

Team

Scope

Management Plan

Pending

003

3.0 Schedule Management Plan

Establish policies and procedures used

to develop, execute, monitor and

control the project schedule

Schedule

Management Plan

Project

Team

Project

Management plan

Pending

3.1 Activity Plan

Develop detailed list of all project’s

activities

List of Activities

Project

Team

Project

Management plan

Pending

3.2 Schedule Baseline

Establish fixed timeline measurement

for accomplishment of project tasks

Schedule Baseline

Project

Manager

Schedule

Management Plan

Pending

004 4.0 Cost Baseline

Develop time-phased spending plan

for the project

Cost Baseline

Project

Manager

Cost Management

Plan

Pending

005 5.0

Stakeholder Management

Plan

Develop management strategies to

engage stakeholders effectively

Stakeholders

Registration

Project

Manager

Project

Management Plan

Pending

Table 5: Requirements Traceability Matrix

Page 23: Green Computing Research: Project management report

Balgoname 2017

23

2.1.4 Questions for Project Sponsor

▪ What is the project context, including organization's political considerations?

▪ What do you regard the main functions and features to be?

▪ What are your expectations of schedule and budget?

▪ What are the tradeoffs that will have to be made?

▪ What could be a high-level potential risk?

2.2 Project Scope Statement

Scope Statement Project Name Green Computing Research Project

Project Manager Mia

Date 05/23/2017

Version History

Version Date Comments

1.0 05/16/2017 Preliminary Scope statement

2.0 5/23/2017 Finalized Scope Statement

Project Justifications

As a strategic goal for the Environmental Technologies program at the organization, this

project will help to improve the environment, while at the same time increase corporate

revenues and decrease computers operational costs. It also helps to promote a positive

corporate image and shows social responsibility.

Project Scope

To produce a comprehensive research report including detailed financial analysis and

recommendations on what green computing technologies can be applied internally and

potentially sold to other organization.

Project Deliverables

Financial analysis

Recommended Solutions

Orientation completion

Possible technologies to

implement

Standard work and reporting

Project Budget

Total invested amount in the project $356,000.00

Project Deadline

6 Months starting form 05/15/2017

Table 6: Scope Statement

Page 24: Green Computing Research: Project management report

Balgoname 2017

24

2.3 Work Breakdown Structure 2.3.1 Work Breakdown Structure Table

Work Breakdown Structure Project Name Green Computing Research Project Project # 2

Project Manager Mia Sponsor Ben

Project Artifacts Business Case, and Risk Assessment Version 1.0

ID Task Depen-dencies

Status Cost Start Date Planned

Completion Estimate to Completion

Actual Completion

Resou-rces

1 Project Initiation 1.0 Completed $21,747.00 05/15/2017 11 Mia, Ben

2 Team Member Selection 1.1 Completed 5,931.00 05/15/2017 3

3 Stakeholders Meeting 1.2 Completed 1,977.00 05/17/2017 1

4 Project Management Plan 1.3 Completed 7,908.00 05/18/2017 4

5 Project Scope Statement 1.4 Completed 1,977.00 05/21/2017 1

6 Project Change Control 1.4.1 Completed 1,977.00 05/21/2017 1

7 Charter Signed 1.4.1.1 Completed 1,977.00 05/22/2017 1

8 Planning 2.0 Ongoing $108,735.00 05/23/2017 55 Mia, Project Team

9 Project Kick-Off Meeting 2.1 Ongoing 1,977.00 05/23/2017 1

10 Develop Work Plan 2.2 Ongoing 59,310.00 05/24/2017 30

11 Develop Project Control Plan 2.3 Ongoing 39,540.00 06/23/2017 20

12 Finalize Project Plan 2.4 Ongoing 5,931.00 07/15/2017 3

13 Gain Approvals 2.5 Ongoing 1977.00 07/16/2017 1

15 Execution 3.0 Pending $205,608.00 07/17/2017 104 Mia, Project Team

16 Survey Analogous Researches 3.1 Pending 45,471.00 07/17/2017 23

17 Conduct Research 3.2 Pending 108,735.00 08/09/2017 55

18 Technologies Examination 3.2.1 Pending 39,540.00 10/4/2017 20

19 Analyze Findings 3.2.1.1 Pending 9,885.00 10/25/2017 5

20 Report Findings 3.3 Pending 1,977.00 10/30/2017 1

21 Monitoring and Controlling 4.0 Pending $2,117.00 11/01/2017 1 Mia

Page 25: Green Computing Research: Project management report

Balgoname 2017

25

24 Performance Reporting 4.1 Pending 2,117.00 11/01/2017 1

25 Closing 5.0 Pending $17,793.00 11/01/2017 9 Mia, Project Team

26 Conduct Post Project Review 5.1 Pending 15,816.00 11/4/2017 8

27 Approve Project Closeout 5.2 Pending 1,97700 11/14/2017 1

Total $356,000.00 180

Table 7: Work Breakdown Structure table

Page 26: Green Computing Research: Project management report

Balgoname 2017

26

2.3.2 Work Breakdown Structure Tree

Figure 4: Work Breakdown Structure Diagram

Page 27: Green Computing Research: Project management report

Balgoname 2017

27

2.4 Gantt Chart

Figure 5: Gantt Chart of the Project

Page 28: Green Computing Research: Project management report

Balgoname 2017

28

Part 3

Page 29: Green Computing Research: Project management report

Balgoname 2017

29

3. Project Time Management

3.1 Review of WBS and Gantt Chart

Figure 6: An updated WBS and Gant Chart

Shown above, an up-to-date picture of the WBS and Gantt chart. It includes all the dependencies,

milestones, and timeline. There are, however, few tasks that suggested to be added to the project.

Three tasks to be exact.

The first task is quality control monitoring. Since the scope of this project revolves around

research, there should be a quantitative and qualitative quality metrics that measure the processes

Page 30: Green Computing Research: Project management report

Balgoname 2017

30

of the project and its procedures. The role of this task is to assure that the work is not only done

as planned, but also in accordance with national and international quality standards.

The second suggested task is to establish a knowledge management (KM) logging to aid the

project team along the way. The KM log has short and long-term benefits to the project team and

the organization. When utilized correctly, it enables sharing of tacit knowledge among the

project team, which shorten the time required to perform tasks. It also benefits the organization

as its quality increase the more knowledge is logged.

The last suggested task for the project is communication coordination tool. Since two of the

project team are working remotely. It is important to facilitate the communication among the

project team systematically. Without such a tool, the work might get delayed, or done

incorrectly.

3.2 Project Milestones

The project has four milestones. Each milestone signifies a major achievement of the project's

components. The process of selecting project's milestones is based on SMART, which is an

acronym of four words that was created by Peter Drucker's Management by Objectives concepts.

Those four words are Specific, Measurable, Achievable, Relevant, and Time-bound (Drucker,

1954). Each of the three milestones is carefully selected to assure that it meets the criteria of

SMART. If one of these three milestones did not meet the constraints, it would cause problems

later the project life cycle.

The first milestone of green computing research project is the signature of the project charter. It

is chosen as the first milestone, due to the importance of this task. The signature of the project

charter means that everything that is required for the project to go is in place, including scope

Page 31: Green Computing Research: Project management report

Balgoname 2017

31

and time management, and budget. The second milestone is gaining the approval of the planning

phase. This milestone is of high importance due to the sensitivity of the entire planning phase. It

is known that during the planning phase, all the procedures, requirements, and tools get selected;

therefore, a successful planning shall increase the possibility of having a successful project.

The third milestone of this project is report the findings process, which is the final stage of the

research processes. This process has been selected as a milestone because it is the fruit of the

project and the final outcome. The last milestone of green computing research project is

conducting post review of the project. This task has been selected as a milestone due to the

importance of work review. No work is complete without its been reviewed. The rest of the

project procedures and tasks are not as important as the mentioned three processes; furthermore,

most of the tasks are pre-requisite for meeting the project's three milestones.

Page 32: Green Computing Research: Project management report

Balgoname 2017

32

Figure 7: Gantt Chart with milestones, and duration

3.3 Gantt Chart with Duration and Dependencies

3.3.1 Gantt Chart

3.3.2 Network Diagram

Figure 8: Network diagram of the project dependencies, and tasks

Page 33: Green Computing Research: Project management report

Balgoname 2017

33

3.4 Resource Assignment Matrix

Table 7: Resource Assignment Matrix

Shown above, is an assignment matrix of the project resources. As explained in the case, the

team consists of five team members including the project manager. Assumptions made while

assigning the resources matrix:

❖ The project sponsor and manager are responsible for selecting team members

❖ Full-time engagement in the project means 8 hours a day and six months commitment

Page 34: Green Computing Research: Project management report

Balgoname 2017

34

Three members of the team, the project manager, James, and Teresa are available 100% to

engage in the project. While two of members, Matt, and Lee are available 50% to engage in the

project. The project manager is responsible for monitoring and coordinating the project and team

members. She is also responsible for reporting performance of the team members. Meanwhile,

the remaining four members, Teresa, Matt, James, and Lee are responsible for executing the

research. They are also responsible for conducting the post-project review before the final

submission of the project. According to the case, attention should be drawn that, one of the team

members, Lee, will not be available to work on the project the first four weeks. He will join the

team during the planning phase and beyond. Outsourced labor are requested based on specific

tasks that require extra manpower, or certain expertise that is not available in the project

resources.

Page 35: Green Computing Research: Project management report

Balgoname 2017

35

Part 4

Page 36: Green Computing Research: Project management report

Balgoname 2017

36

4. Project Cost Management

4.1 Project Planned Cost Budget

4.1.1 Weekly Budget

Year Quarter Week Budget Cost Baseline

Cost Cost Actual Cost

20

17

Q2

Week 17

4282.00 4282.00

4282.00 4282.00

Week 18

7980.00 8190.00 8190.00 8190.00

Week 19

4956.00 5005.00 5005.00 5005.00

Week 20

4956.00 5005.00 5005.00 5005.00

Week 21

4956.00 5005.00 5005.00 5005.00

Week 22

4956.00 5005.00 5005.00 5005.00

Week 23

4956.00 5005.00 5005.00 5005.00

Week 24

4100.00 4004.00 4004.00 4004.00

Q2 Total $41,142.00 $41,501.00 $41,501.00 $41,501.00

Q3

Week 25

7150.00 7260.00 7260.00 7260.00

Week 26

7150.00 7260.00 7260.00 7260.00

Week 27

7150.00 7260.00 7260.00 7260.00

Week 28

7150.00 7260.00 7260.00 7260.00

Week 29

12149.00 12251.00 12251.00 0.00

Week 30

16290.00 17300.00 17300.00 0.00

Week 31

16290.00 17300.00 17300.00 0.00

Week 32

16290.00 17300.00 17300.00 0.00

Week 33

16300.00 17300.00 17300.00 0.00

Week 34

13142.00 13284.00 13284.00 0.00

Page 37: Green Computing Research: Project management report

Balgoname 2017

37

Week 35

14430.00 14520.00 14520.00 0.00

Week 36

7150.00 7260.00 7260.00 0.00

Q 3 Total $140,641.00 $145,555.00 $145,555.00 $29,040.00

Q4

Week 37

7260.00 7260.00 7260.00 0.00

Week 38

7260.00 7260.00 7260.00 0.00

Week 39

7260.00 7260.00 7260.00 0.00

Week 40

7150.00 7260.00 7260.00 0.00

Week 41

7260.00 7260.00 7260.00 0.00

Week 42

7150.00 7260.00 7260.00 0.00

Week 43

7150.00 7260.00 7260.00 0.00

Week 44

7260.00 7260.00 7260.00 0.00

Week 45

8852.00 8952.00 8952.00 0.00

Week 46

14479.00 15975.00 15975.00 0.00

Week 47

18745.00 19475.00 19475.00 0.00

Week 48

18745.00 19475.00 19475.00 0.00

Q 4 Total $118,571.00 $121,957.00 $121,957.00 $-

2017 Total $300,354.00 $309,013.00 $309,013.00 $70,541.00

201

8

Q1

Week 1

0.00 0.00 17153.00 0.00

Week 2

0.00 0.00 12078.00 0.00

Week 3

0.00 0.00 10090.00 0.00

Week 4

0.00 0.00 4036.00 0.00

Week 5

0.00 0.00 0.00 0.00

Week 6

0.00 0.00 0.00 0.00

Page 38: Green Computing Research: Project management report

Balgoname 2017

38

Week 7

0.00 0.00 0.00 0.00

Week 8

0.00 0.00 0.00 0.00

Week 9

0.00 0.00 0.00 0.00

Week 10

0.00 0.00 0.00 0.00

Week 11

0.00 0.00 0.00 0.00

Week 12

0.00 0.00 0.00 0.00

Q 1 Total $- $- $43,357.00 $-

2018 Total $- $- $43,357.00 $-

Grand Total $300,354.00 $309,013.00 $352,370.00 $70,541.00

Table 8: Weekly Budget

4.1.2 Resource Usage

Page 39: Green Computing Research: Project management report

Balgoname 2017

39

Figure 9: Gantt chart shows resource usage

Table 9: Resource usage total hours and cost

4.2 Project BAC and Planned Value

Budget at Completion and Planned Value

BAC $356,000.00

Planned Value

End of Week 4 (BAC x 0.10) $35,000.00

End of Week 8 (BAC x 0.25) $89,000.00

End of Week 12 (BAC x 0.50) $178,000.00

End of Week 15 (BAC x 0.60) $213,600.00

Table 10: BAC and PV values

4.3 Earned Value Analysis Given

BAC $366,000.00

PV $180,500.00

EV $191,500.00

AC $206,500.00

Part (A)

CV = EV – AC = $ (15,000.00)

SV = EV – PV = $11,000.00

Page 40: Green Computing Research: Project management report

Balgoname 2017

40

CPI = EV / AC = 0.93

SPI = EV / PV = 1.06

Part (B)

EAC = BAC / CPI = $394,668.41

Table 11: Budget analysis

Figure 10: Earned Value Chart

Shown above, a chart for the earned value (EV) for the given problem. The five indexes, PV,

EV, AC, EAC, and BAC that have been utilized examines the Budget at Completion (BAC)

against the Variance at Completion (EAC). This project has a variance $28,668 from the planned

budget. This overspending occurred due to low-cost performance index (CPI) of this project at

0.93. The project is also behind schedule as the CPI and SPI indexes illustrate. This analysis, is

an alarming benchmark. The sponsor, and manager of this project have to take actions to return

this project on track to assure its successfulness.

$366,000.00

$180,500.00

$191,500.00

$206,500.00

$394,668.41

0

200000

400000

600000

800000

1000000

1200000

1400000

1600000

1 2 3 4 5 6

Earned Value Chart

EAC

AC

EV

PV

BAC

Timeline

Page 41: Green Computing Research: Project management report

Balgoname 2017

41

4.4 Corrective Actions

Many corrective actions can be made for this given problem to overcome it. First, before hiring

consultancy, the project manager has to ensure that he or she have clear specification

requirements documentation. The purpose of this document that it specifies in in-depth details

the processes and procedures to conduct the project. Any confusion this document causes will

cause defects, and errors, that eventually causes delays or complete failure of the project.

Another method that assures good outcomes is through measurable quality indexes. These

indexes are pre-determined by the project management office or the organization, which reflect

what work is considered meets the quality of a certain entity.

Lastly, while considering assigning consultant, it is better to test the company through the

Capability Maturity Model (CMM). This model is a ranking system consists of five ranks. A

company with level one is considered chaotic, while companies with level five considered well

established and provide quality work.

In this light, and when having good specification requirements, the project team or consultant is

closer to achieve better outcomes. A good specification requirement is a road map that illustrates

the details of the project including costs. A good quality matrix protects the project from any

creeps in scope or budget. Finally, selecting project team including consultants should be

systematic and using models such as CMM which identify good from bad consultant to assign.

Page 42: Green Computing Research: Project management report

Balgoname 2017

42

Part 5

Page 43: Green Computing Research: Project management report

Balgoname 2017

43

5. Project Quality Management

5.1 Quality Management Requirements

5.1.1 Quality Management Approach

The objectives of quality management for Green Computing Research Project are to assure:

❖ Project deliverable meet their standards

❖ Project management processes are appropriately developed.

Quality management is performed throughout the entire project lifecycle with attention to:

1. Quality Planning

2. Quality Assurance

3. Quality Control

4. Independent Verification and Validation (IV&V)

Quality management planning determines quality policies and procedures relevant to the project

for both project deliverables and project processes, defines who is responsible for what, and

documents compliance.

Key Component of Quality Management Plan Objects of quality review Quality Measure Quality Evaluation Method Project Deliverables Deliverables Quality Standards

Customers Satisfaction

Quality Control Activities

Project Processes Processes Quality Standards

Stakeholders Expectations

Quality Assurance Activities

Table 12: Components of QMP

5.1.2 Quality Objectives and Standards Identification

5.1.2.1 Project Deliverables

❖ The research should be well formulated, and the purpose of the study should be clear

❖ The research should be well designed and executed

❖ The research should demonstrate an understanding of related studies

❖ The research should utilize best available data and information

❖ The research assumptions should be explicit and justified

❖ The findings should advance knowledge and bear on important policy issues

❖ Implications and suggestions should be logical, warranted by the findings, and explained

thoroughly, with appropriate caveats

❖ Documentations should be accurate, understandable, clearly structured, and temperate in

tone

❖ The research should be compelling, useful, and relevant to stakeholders and decision

makers

❖ The research should be objective, independent, and balanced

5.1.2.2 Project Processes

❖ The PDCA Cycle

❖ Cause and Effect Diagram

Page 44: Green Computing Research: Project management report

Balgoname 2017

44

❖ Pareto Charts;

❖ Control Charts

❖ Maturity Models

5.1.3 Project Reviews and Assessments

Review Type Frequency Tools Reviewer Reports Project Charter Constant reviews until

approval of charter

ISO, IEEE

Project Manager

Attach finalized reports of all reviews conducted under the project quality management document

Project Management Plan

Scope Management Plan

Requirements Management

Plan

Requirements Documentation Once after completion

WBS

Constant reviews

Microsoft Project

Scope Baseline Microsoft Project, Microsoft Excel

Schedule Management Plan

Activity Plan

Schedule Baseline

Cost Baseline

Stakeholder Management Plan Once after completion ISO, IEEE

Table 13: project reviews and assessments table

5.1.4 Deliverable Acceptance Criteria

Deliverable Final Approval Process Stakeholder Acceptance Criteria Financial analysis Ongoing Proper mathematical calculations

Recommended Solutions Ongoing Based on logical comprehension

approach Orientation completion Ongoing

Possible technologies to implement Ongoing

Standard work and reporting Ongoing Follow American reporting and

citation standards

Table 14: project deliverable acceptation criteria table

Page 45: Green Computing Research: Project management report

Balgoname 2017

45

5.2 Seven Basic Tools of Quality

The Project Management Institute (PMI), references the seven basic tools in a guide to the

Project Management Body of Knowledge (PMBOK), as an example of a set of general tools

useful for planning or controlling project quality. The Seven Basic Tools of Quality is a name

given to a set of graphical models, which are identified as being most helpful in troubleshooting

issues related to quality. Since they are basic, they are easy to utilize as they require little formal

training in statistics. Also, they can be used to solve most of, much of quality related issues.

(Project Management Institute, 2013)

The seven tools are the following:

❖ Cause-and-effect diagram also known as the "Ishikawa diagram" or "fishbone"

❖ Control Chat

❖ Check sheet

❖ Pareto chart

❖ Histogram

❖ Scatter diagram

❖ Stratification (alternately, flow chart or run chart)

The Cause and Effect diagram can be utilized in Green Computing research to examines why

something happened or might happen by potential causes into smaller categories. It also can be

useful for showing the relationship between contributing factors. Another useful tool is the

histogram, which is a graphical depiction of how many times different, mutually exclusive

events are inspected in an experiment. The two explained tools and all other seven tools have to

be utilized in the project to guarantee more high level of quality.

Page 46: Green Computing Research: Project management report

Balgoname 2017

46

5.3 Summary of High Quality Research Report

In 2014, the Journal of Chemical and Pharmaceutical Sciences (JCHPS), published a report by

Namburi Anupama concerning green computing. Mr. Anupama has done phenomenal work in

explaining green computing. The report describes and defines in depth green computing and its

implications.

The paper aims to urge organizations to apply green computing through many practices, such as

saving energy during idle operation, using eco-friendly sources of energy, reducing harmful

effects of computing resources, and reducing computing wastes. Furthermore, the author

provided tangible examples where green computing practices have positively impacted

organization financially, environmentally, and socially.

For instance, one of the programs that were mentioned in this paper is about cooling database

centers through the leveraging of local climate to cool down data center instead of using air

conditions to do so. The program was effective and shown tremendous financial and

environmental benefits. (Anupama, 2014)

This paper is of high-quality sources that would aid the team in conducting the research due to

many facts. First, this paper has been revised by academic researchers and published in a

scientific journal. Second, the author has provided an excellent definition of green computing,

and its practices in the organization. Third, this report contains many useful sources that; when

considering, it will enlighten the project team to enrich their work further. Due to these reasons, I

believe this paper must be one of the sources that will be used to build upon out green computing

research.

Page 47: Green Computing Research: Project management report

Balgoname 2017

47

Part 6

Page 48: Green Computing Research: Project management report

Balgoname 2017

48

6. Project Human Resource Management

6.1 MBTI Types in Work Environments

6.1.1 MBTI Personality types

MBTI stands for The Myers-Briggs Type Indicator. MBTI was designed by Carl Jung’s theory

of psychological type. It indicates individuals’ personality preferences in four dimensions:

❖ Where individual focus his/her attention - Extraversion (E) or Introversion (I)

❖ The way individual take information - Sensing (S) or Intuition (N)

❖ How individual makes decisions - Thinking (T) or Feeling (F)

❖ How individual deal with the world - Judging (J) or Perceiving (P)

There are 16 unique MBTI personalities:

• ISTJ

• ISFJ

• INFJ

• INTJ

• ISTP

• ISFP

• INFP

• INTP

• ESTP

• ESFP

• ENFP

• ENTP

• ESTJ

• ESFJ

• ENFJ

• ENTJ

Each four letters make up individuals personality type. When individuals know their personality

type, it can help them understand their behavior and interacting with others better. While there

are no personalities better than others; there are, however, a preference to certain personality

types based on the nature of this project that requires the ability to conduct research. To narrow

the search scope of the preferred personality types. (Jung, 1971)

The 16 personality types can be break into four sub-sets:

Analysts

This group of personality type contains four personalities all of which revolve around analytical

skills. Those four personality types are: INTJ, INTP, ENTJ, and ENTP. The first personality

INTJ individual is an imaginative and strategic thinker. While INTP individual is an inventor

with a thirst for knowledge. The ENTJ personality individual is bold, imaginative and strong-

Page 49: Green Computing Research: Project management report

Balgoname 2017

49

willed leader, and always trying to find a way or solution to a certain problem. Lastly, ENTP

personality individual is a smart and curious thinker who cannot resist an intellectual challenge.

Diplomats

This group also contains four personality types whom skills lean toward diplomacy. Those four

types are INFJ, INFP, ENFJ, and ENFP. The INFJ individual is a quiet and mystical person, yet

very inspiring and tireless idealists. An individual with INFP personality type is a poetic, kind

and altruistic person, always eager to help a good cause. The ENFJ individual is charismatic and

inspiring leaders, and able to mesmerize their listeners. Lastly, the ENFP individual is

enthusiastic, creative and sociable free spirit, who can always find a reason to smile.

Sentinels

This four personality types group consists of ISTJ, ISFJ, ESTJ, and ESFJ. The first type ISTJ

individual is a rational and fact-minded individual, whose reliability cannot be doubted. The

second personality individual ISFJ is very dedicated and warm protector, and always ready to

defend their interests. The third personality individual, ESTJ is an excellent administrator, and

unsurpassed at managing things, or people. Finally, the ESFJ individual is an extraordinarily

caring, social, and accessible person and always eager to help.

Explorers

This group of four personality types consists of ISTP, ISFP, ESTP, and ESFP all of which have

skills related to exploration. The ISTP personality individual is a bold and practical

experimenter, and master of all kinds of tools. The ISFP individual is a flexible and charming

artist, and always ready to explore and experience something new. An individual with ESTP

personality type is a smart, energetic, and very perceptive person, who truly enjoy living on the

Page 50: Green Computing Research: Project management report

Balgoname 2017

50

edge. Lastly, ESFP individual is a spontaneous, energetic, and enthusiastic person, who is

admired by his peers. (Meade, 2017)

6.1.2 Introductory Email

Project team,

Myself and on behalf the project sponsor, I am delighted to welcome you to the Green

Computing Research Project. As you may all know that our project is a high priority to our

organization, as it will provide solutions to overcome the consumption of energy problem and

reduce the bad impact on our environment. Dear team members, I am fully confident in your

abilities to make this project reality. You all have shown good competencies and you have been

selected among others according to this fact. Thank you for being part of our team and I hope our

project with your participation and cooperation sees the light.

Best regards,

Project Manager

6.2 Responsibility Assignment Matrix RACI

The Responsibility Assignment Matrix (RAM), or Linear Responsibility Chart (LRC), represents

the participation by different duties in achieving tasks or deliverables for a project or business

process. It is valuable in defining duties and obligations in cross-functional/ departmental

projects and processes.

Assumptions for the RAM

The RACI acronym is derived from four key responsibilities most typically used:

❖ Responsible - Individuals who do the work to achieve the task

Page 51: Green Computing Research: Project management report

Balgoname 2017

51

❖ Accountable - The ultimately responsible person for the correct and thorough completion

of the deliverable or tasks

❖ Consulted - Individuals whose opinions are sought, typically subject matter experts

❖ Informed - Individuals who are kept up-to-date on progress

Table 15: Resources Assignment Matrix (RAM) with RACI responsibilities.

Page 52: Green Computing Research: Project management report

Balgoname 2017

52

6.3 Human Resources Related Concerns

Human resources are the most important element of any work. They are the real asset and

working power of any organization or organized work. The influence of human resources is so

powerful and reflects, either positively or negatively on their work based on the challenges and

circumstances. This paper spotlight some of the challenges and concerns that might encounter a

project's human resources.

There are many human resources contributing factors for project failure, such as stakeholders,

motivation, diversity in (culture, ethnicity, and protected groups), work environment. One factor

that contributes to project failure is related to the lack of project management expertise in an

organization. When a project team's risks are given little or no prominence, it creates resistance,

apathy, and lack of engagement, which have a significant impact on the procedures and timelines

of the project plan.

The project's human resource management is a multifaceted process. The project manager is

solely responsible for lead, direct and orchestrate the project team, customers, contributors,

partners, and any other stakeholders to achieve the desired results for the project's purpose,

which is a huge challenge and subject to wrong personal judgment. Therefore, throughout the

project, the project manager has to address project team retention, labor relations, and

performance appraisal and depending on the nature of the project work, health and safety

concerns.

The number of stakeholders in the project sometimes change; therefore, the project manager and

project team need to be aware of the incoming flux of interested parties and how this shift may

affect the dynamics of the project work and the project team. One approach to project human

Page 53: Green Computing Research: Project management report

Balgoname 2017

53

resources may work well in one phase of the project, yet it might not work in another phase due

to the stakeholders who involve. Since individuals drive processes, it is logical to build

competencies in employees’ management skills as well as in quantitative and analytical process

management. The project manager may have to pull together teams of employees who do not

work for the same organization. For instance, contractors view themselves as peers or colleagues

and where they must be managed differently from the organization's employees.

The workforce is diverse more than ever before, not only culturally and ethnically, but also in

other ways as well. It includes older workers, women, disabled individuals and other protected

groups by law from discrimination. Moreover, with the demands for skilled, high-tech workers at

all levels, employees’ searches span the globe and cross-cultural barriers. In project work

environment, organizations cannot offer permanent employment, nor can they guarantee raises,

benefits, job definition, management stability. Moreover, they cannot repay loyalty with loyalty

or hard work with compensation. Thus, the challenges of motivating employees go beyond their

abilities.

A stressful work environment results in stressed employees, and when employees are stressed,

they are more likely to make mistakes and perform at less than their optimal levels. The more

mistakes employees make, the worse they feel about their jobs and themselves, and the more

likely they are experience burnout. A high burnout rate leads to a high turnover rate, and

eventually, more time for a project manager spent on rehiring and retraining.

Staying within time and budget limits goes a long way toward stress-free project management

within the process and human resources issues that come with the job. Many problems can

happen to throw project processes off schedule; however, managing personnel matters properly

can do a great deal towards maintaining the project running smoothly.

Page 54: Green Computing Research: Project management report

Balgoname 2017

54

Part 7

Page 55: Green Computing Research: Project management report

Balgoname 2017

55

7. Project Communication Management

7.1 Project Issue Log

Project Green Computing Research Project

Project Manager Mia

Project Description Research possible green computing application for internal use and possible sale to other organizations

ID Status Priority (L/M/H)

Issue Disruption Assigned to

Expected Resolution Date

Escalation Required (Y/N)

Impact Summary

1

Work in progress H Couple of team members do not use the share site to post their work and use e-mails instead.

Teressa 6/20/2017 Yes This issue hinders the progress of work as it requires more time to check on work done and provide feedback though wiki tools.

2 Open

M Some of team members are not using webcams during conference calls.

Matt 7/17/2017 Yes This issue prevents visualized meetings, which enhance the team meeting experience. It also hinders the credibility to participation.

3 Closed

L Lack of time commitment during team meetings. Meeting times goes beyond what is planned.

Project Manager

7/20/2017 No This issue consumes some of the team members time, which can be spent on other necessary work.

4 Open H Lack of enough date.

Recommendation deliverable is behind schedule.

Teressa 7/28/2017 Yes This issue might cause possible delay to the project as it part of the project core.

Table 16: Issue Log

Page 56: Green Computing Research: Project management report

Balgoname 2017

56

7.2 Applications of Wikis

Wiki is one of the most common buzzwords on the internet. The term wiki means quick in

Hawaiian, and it also defined as a website tool that enables collaborative editing of its content

and structure by its users. What makes wiki a useful instrument in the project work, is it

collaborative editing environment that allows brainstorming, and discussion of various ideas

without the need of having the participants in one place. Wiki is widely adapted in many

organization today, due to its swiftness, and effectiveness of allowing participants to generate

contents. (LeBar, 2017)

Some of the project team members have concerns about using wiki because they do not want

other team members to change, or edit their work; therefore, they are not using the wiki tool to

post their work. They instead use the email to send their work, which consumes a precious time

for the rest of the team. The use of wiki can be very chaotic or very organized. If there are rules

and policies of using wikis, the tool is organized and fruitful; on another hand, if there are no

rules or policies on who do what, the tool is causing chaos. Having rules and policies of using

wiki will satisfy the concerns of some of the team members and assure the effectiveness of

utilizing the tool.

In conclusion, wiki is very valuable tool, given the nature of the project is heavily research. It

will allow team members to brainstorm and share their ideas, which will positively reflect on the

work. The fact, that wiki is a tool that allow participant to share and edit the content, made some

of the project members withdrawal from participating and preferred traditional communication

method – the e-mails. However, if there are rules and polices of the way participant generate,

edit, and share content, the team members’ concerns are solved.

Page 57: Green Computing Research: Project management report

Balgoname 2017

57

7.3 Conflict Resolution As part of the project management, there must be a method to approach conflict and control it in

a way that limits the negative impact on the project and the team. Conflict management is the

means of limiting the adverse aspects of conflict while increasing the positive side of the

conflict. The purpose of conflict management is to enhance learning and group outcomes,

including effectiveness or performance in an organization setting. When conflicts managed

properly, it can improve team results and reduces the negative impact

Conflict resolution is a method for two or more parties to find a peaceful solution to

disagreement among them, due to personal, financial, political, or emotional reasons. Conflict

resolution conceptualized as the method and processes implicated in facilitating the peaceful

ending of conflict. A project manager can attempt to resolve a conflict by communicating about

conflicting ideologies, or motives to the individual(s), and by involving in bilateral negotiation.

There are procedures for addressing conflicts, including negotiation, mediation, and arbitration. .

(Afzalur Rahim, 2002)

For the Green Computing Research Project, the aim of conflict resolution is to solve a problem

through negotiation immediately, once a problem or conflict occurs. By doing so, most of the

conflicts would not escalate to require mediation and or arbitration. the project, few conflicts

occurred among the project team in the communication management. Here are some of these

issues and how they can be solved.

First, James and other team members did not seem uncomfortable using collaboration tools to

post their work, arguing that other team members might change, or edit their work, which

eventually leads to delaying the work and impedes the progress of the project. Solving this issue

requires knowing that one's enemy is unknowingness; in this case, it is possible that the team

members are not aware of how to use the wiki tool and control it in a way that allows only

authorized an individual to edit a certain post. It is also recommended during the training

Page 58: Green Computing Research: Project management report

Balgoname 2017

58

sessions to explain how to use wiki tool efficiently and adequately and at the same time

emphasize the benefits that it brings to the project and its team members from agility, flexibility,

and security.

Another conflict arose while in project management was that some team members failed to use

webcams during team meetings. In this case, the project manager should stress the importance of

having webcam during video conferences. Since few of the project team are working remotely, it

makes them feel isolated from the work environment and lead to losing their motivation to work.

Having a webcam during conferences stimulates the team members to work better because they

are metaphorically meeting face-to-face with their peers and it also increases the participant's

seriousness to share their arguments and inputs.

Another issue that arose was that during meetings the team did not adhere to the predetermined

meeting time, which affects other team members because they are occupied with other important

matters. The project manager should state three important policies at the beginning of each

meeting to increase the effectiveness of meetings. First, the manager should indicate the subject

of the meeting, what and what not it includes for discussion during the meeting. The project

manager also must remind the team of the meeting time boundaries, when it starts, and when it

ends. Finally, it is important that the project manager state what he or she is looking forward to

accomplishing by the end of the meeting.

Overall, conflicts are an inevitable matter. It could be caused for legitimate or illegitimate

reasons, and it might happen anytime. The ability to deal with conflict and manage it is

extremely important to assure a steady progress of the work. There are many approaches to

achieving conflict resolution such as negotiation, mediation, and arbitration. The leader's ability

to encounter conflicts and solve them are a pivotal point that can sway the dispute to an end or an

escalation.

Page 59: Green Computing Research: Project management report

Balgoname 2017

59

Part 8

Page 60: Green Computing Research: Project management report

Balgoname 2017

60

8. Project Risk Management

8.1 Risk Register

Table 17: Risk register table contacting seven possible risks for Green Computing Project

Page 61: Green Computing Research: Project management report

Balgoname 2017

61

8.2 Risk Assessment and Impact Matrix

Table 18: Risk Assessment and Impact matrix

Page 62: Green Computing Research: Project management report

Balgoname 2017

62

Table 19: Risk Response and Contingency Plans

8.3 Risk Response and Contingency Plans

Page 63: Green Computing Research: Project management report

Balgoname 2017

63

Part 9

Page 64: Green Computing Research: Project management report

Balgoname 2017

64

9. Project Procurement Management

9.1 Contract Agreement with Anne Consulting Firm

Service Contract Agreement

THIS SERVICE AGREEMENT (the “Agreement”) dated this 5th day of July, 2017

BETWEEN:

We Are Big, Inc.

(the “Client”)

-AND-

Anne Consulting

(the “Contractor”).

BACKGROUND:

A. The Client is of the evaluation that the Contractor has the required experience, abilities,

and qualifications to provide services to the Client.

B. The Contractor is amenable to granting such services to the Client on the conditions and

terms set out in this Agreement.

IN CONSIDERATION OF the matters explained above and of the mutual benefits and

commitment outlined in this Agreement, the receipt and sufficiency of which consideration is

hereby acknowledged, the Client and the Contractor (independently the “Party” and collectively

the “Parties” to this Agreement) agree as follows:

Services Provided

1. The Client hereby accepts to engage the Contractor to provide the Client with the

following services (the “Services”):

• Support project team in research work to generate ideas for green computing

• Provide consultants for the project as per need for the project

2. The Services will include any other duties which the Parties shall agree on. The

Contractor hereby consents to provide such Services to the Client.

Page 65: Green Computing Research: Project management report

Balgoname 2017

65

Term of Agreement.

3. The term in this Agreement (the “Term”) will be effective on the date of this Agreement

and will abide in full force effect until the completion of the Services, subject to earlier

termination as provided in this Agreement. The Term of this Agreement may be extended

with the written consent of the Parties.

4. In the event that either Party violates an article provision under this Agreement, the non-

defaulting Party against all reasonable damages.

Performance

5. The Parties consent to do everything necessary to ensure that the terms of this Agreement

take effect.

6. Except as otherwise granted in this Agreement, all monetary amounts indicated to in this

Agreement are in US Dollars (USD).

Compensation

7. The Contractor will charge the Client an hourly rate of $190.00 for Anne’s Services. The

Contractor will also charge the Client $150.00 per hour for any other consultants that is

subject to a maximum of 100 hours (the “Compensation”).

8. The Client will be billed when the Services are finished.

9. Invoices handed by the Contractor to the Client are due within 30 days of submission.

10. In the event that the Client ended this Agreement prior to completion of the Services, but

where the Services have been partly performed, the Contractor will be entitled to pro rata

payment of the Compensation to the date of end provided that there has been no breach of

contract on the part of the Contractor.

11. The Compensation as declared in this Agreement does not include sales tax or other

applicable duties as may be required by law. Any charges and sales tax required by law

will be charged to the Client in addition to the Compensation.

Reimbursement of Expenses

12. The Contractor will be repaid from time to time for reasonable and necessary expenses

incurred by the Contractor in relation to providing the Services.

Page 66: Green Computing Research: Project management report

Balgoname 2017

66

13. All expenditures must be previously approved by the Client.

Confidentiality

14. Confidential information (the “Confidential Information”) attributes to any data or

information relating to the business of the Client that would reasonably be considered to

be proprietary to the Client including, but not limited to, business processes, accounting

records, and client records and that is not generally known in the industry of the Client

and wherever the reveal of that Confidential Information could reasonably be expected to

cause harm to the Client.

15. The Contactor agrees that they will not disclose, divulge reveal, report or use for any

purpose, any confidential information that the Contractor has obtained, except as

authorized by the Client or as required by law. The responsibilities of confidentiality will

apply during the term of this Agreement and will survive indefinitely upon termination of

this Agreement.

16. All oral and written information and materials disclosed or provided by the Client to the

Contractor under this Agreement are Confidential Information despite whether it was

provided before or after the date of this Agreement or how it was presented to the

Contractor.

Ownership of Intellectual Property

17. All intellectual property and associated material, including any trade secret, moral rights,

goodwill, relevant registrations or applications for registration, and rights in any

copyright, patent, trademark, trade dress, industrial design and trade name (the

“Intellectual Property”) that is produced or developed under this Agreement, is a “work

made for hire” and will be the individual property of the Client. The utilize of the

Intellectual Property by the Client will not be bound in any way.

18. The Contractor may not utilize the Intellectual Property for any purpose other than that

contracted for in this Agreement except with the written agreement of the Client. The

Contractor will be liable for any and all damages occurring from the unauthorized

utilization of the Intellectual Property.

Return of Property

Page 67: Green Computing Research: Project management report

Balgoname 2017

67

19. Upon the expiration or termination of this Agreement, the Contractor will return to the

Client any property, records, documentation, or Confidential Information which is the

property of the Client.

Capacity/Independent Contractor

20. In providing the Services in accordance with this Agreement, it is expressly agreed that

the Contractor is acting as an autonomous contractor and not as an employee. The

Contractor and the Client reckon that this Agreement does not constitute a joint venture

or partnership between them, and is solely a contract for service. The Client is not

required to pay, or make any contributions to, any social security, local, state or federal

tax, unemployment compensation, workers’ compensations, insurance premium, profit-

sharing, pension or any other employee benefit for the Contractor during the Term. The

Contractor is obligated for paying and complying with reporting requirements for, all

local, state and federal taxes associated with payments made to the Contractor under this

Agreement.

Notice

21. All notices, requests, demands or other communications required or permitted by the

terms of this Agreement will be given in writing and hand over to the Parties at the

following addresses:

• 700 Liberty Ave, Pittsburgh, PA 15222

• 201 Fifth Ave, Pittsburgh, PA 15222

Or to other address as either Party shall notify the other, and will be deemed to be

properly hand over (a) immediately upon being served personally, (b) two days after

being deposited with the postal service is served by registered mail, or (c) the following

day after being deposited with an overnight courier.

Indemnification

22. Except to the amount paid in settlement from any applicable insurance policies, and to

the extent permitted by applicable law, each Party accepts to indemnify and hold

harmless the other Party, and its respective employees, officers, agents, affiliates,

Page 68: Green Computing Research: Project management report

Balgoname 2017

68

officers, and permitted successors and assigns against any and all claims, damages,

losses, penalties, liabilities, punitive damages, expenses, reasonable legal fees and costs

of any kind or amount whatsoever, which arise or result from out of any act or omission

of the indemnifying party, its own affiliates, officers, agents, employees, and permitted

successors and assigns that occurs in connection with this Agreement.

Modification of Agreement

23. Any amendment or modification of this Agreement or additional obligation assumed by

either Party in connection with this Agreement will only be obligated if evidenced in

writing signed by each Party or an authorized representative of each Party.

Time of the Essence

24. Time is the essence in this Agreement. No variation or extension of this Agreement will

operate as a waiver of this provision.

Assignment

25. The Contractor will not willingly, or by operation of law, assign or otherwise transfer its

obligations under this Agreement without the prior written approval of the Client.

Entire Agreement

26. It is agreed that there is no representation, warranty, collateral agreement or condition

affecting this Agreement except as expressly provided in this Agreement.

Enurement

27. This Agreement will guarantee to the benefit of and be binding upon the Parties and their

respective administrators, executors, heirs, and permitted successors and assigns.

Titles/Headings

28. Headings are inserted for the convenience of the Parties only and are not to be considered

when interpreting this Agreement.

Gender

Page 69: Green Computing Research: Project management report

Balgoname 2017

69

29. Words in the plural mean and include the singular and vice versa. Words in the masculine

mean and include the feminine and vice versa.

Governing Law

30. This Agreement will be ruled by and construed in accordance with the law of the State of

Pennsylvania.

Severability

31. In the event where any of the terms of this Agreement are held to be unenforceable or

invalid in whole or in part, all other terms will nevertheless continue to be enforceable

and valid with the invalid or unenforceable parts severed from the remainder of this

Agreement.

Waiver

32. The waiver by either Party of a delay, breach, default, or omission of any of the

provisions of this Agreement by the opposite Party will not be construed as a waiver of

any following breach of the same or other provisions.

IN WITNESS OF THIS the Parties have duly affixed their signatures under hand and seal on

this 5th day of July 2017

___We Are Big, Inc._________________

____________________________(Client)

__Anne Consulting__________________

________________________(Contractor)

Page 70: Green Computing Research: Project management report

Balgoname 2017

70

9.2 Content of Research Report

9.2.1 Executive Summary

This project was commissioned by the Environment Technologies Program of We Are Big, Inc.

The project aims to find possible green computing technologies that reduces energy consumption

and increases the efficiency of computing power. Green computing or eco-friendly computing is

a term that refers to the environmental responsibility use of computers and their resources, where

the designing, engineering, manufacturing, and disposing of computing devices have minimal

impact on the environment. Through researching, the project team will work to generate ideas,

methods, and technologies that work in accordance with the definition of green computing and

based on the financial analysis. The prospect outcomes will help the We Are Big, Inc. to

rationalize energy consumption, which would reflect on savings of budget money. Once the

technology proves effective, the company aims to provide its expertise and technologies to other

company to harvest the benefits of green computing.

9.2.2 Table of Contents

Preface …………………………………………………………………………………………. 2

Executive Summary ……………………………………………………………………………. 3

Table of Content ………………………………….……………………………………….……. 4

Introduction ……………………………………………………………………………………... 5

Green computing Solutions …………………………………………………………………..…. 8

Financial Analysis …………………………………………………………………………….... 10

Conclusion ……………………………………………………………………………………... 12

Page 71: Green Computing Research: Project management report

Balgoname 2017

71

9.3 Lesson Learned

1. Having a realistic financial planning will allow the project manager to avoid spending issues

during the span of project life cycle.

2. The quality of the project is how it is defined; therefore, it is important to search for best

standards, and practices to guarantee optimum results.

3. Outsourced labors do overcome workers shortages; however, it is tough to control the work

quality.

4. Conflicts among team members are inevitable, therefore, the project manager ability to

resolve conflicts is very crucial to maintain the progress of the project and avoid expensive

costs.

Page 72: Green Computing Research: Project management report

Balgoname 2017

72

Part 10

Page 73: Green Computing Research: Project management report

Balgoname 2017

73

10. Periodic Reporting: Project Monitoring and Controlling

10.1 Week 13 Work Progress

10.1.1 Gantt Chart Update

Page 74: Green Computing Research: Project management report

Balgoname 2017

74

10.1.2 Network Diagram Update

Page 75: Green Computing Research: Project management report

Balgoname 2017

75

10.1.3 Budget Report Update

10.1.4 EVM Analysis

Page 76: Green Computing Research: Project management report

Balgoname 2017

76

10.1.5 Status Report

Week 13 goes as planned with work and budget. Currently, the project team has successfully

finished the first two phases – initiation, and planning. We are waiting for the approval to

proceed with the project execution. The indexes of schedule performance (SPI) and cost

performance (CPI) are showing a positive performance of the project processes.

Page 77: Green Computing Research: Project management report

Balgoname 2017

77

10.2 Week 14 Work Progress

10.2.1 Gantt Chart Update

Page 78: Green Computing Research: Project management report

Balgoname 2017

78

10.2.2 Network Diagram Update

Page 79: Green Computing Research: Project management report

Balgoname 2017

79

10.2.3 Budget Report Update

10.2.4 EVM Analysis

Page 80: Green Computing Research: Project management report

Balgoname 2017

80

10.2.5 Status Report

Week 14 goes as planned with work but with a variance of actual spending that is less than

budget by $6,250. So far, the project team has successfully finished the processes of the second

phases – planning. We are currently waiting for the sponsor approval to proceed with the project

execution. The project Schedule Performance Index (SPI) is indicating a normal progress, while

Cost Performance Index (CPI) is showing a positive performance due to the cost variance.

Page 81: Green Computing Research: Project management report

Balgoname 2017

81

10.3 Week 15 Work Progress

10.3.1 Gantt Chart Update

Page 82: Green Computing Research: Project management report

Balgoname 2017

82

10.3.2 Network Diagram Update

Page 83: Green Computing Research: Project management report

Balgoname 2017

83

10.3.3 Budget Report Update

10.3.4 EVM Analysis

Page 84: Green Computing Research: Project management report

Balgoname 2017

84

10.3.5 Status Report

Week 15 goes as planned with work and budget. Currently, the project team has successfully

finished the first two phases – initiation, and planning. The project team received the approval to

proceed with the project execution. The indexes of schedule performance (SPI) and cost

performance (CPI) are showing a positive performance of the project processes.

Page 85: Green Computing Research: Project management report

Balgoname 2017

85

10.4 Week 16 Work Progress

10.4.1 Gantt Chart Update

Page 86: Green Computing Research: Project management report

Balgoname 2017

86

10.4.2 Network Diagram Update

Page 87: Green Computing Research: Project management report

Balgoname 2017

87

10.4.3 Budget Report Update

10.4.4 EVM Analysis

Page 88: Green Computing Research: Project management report

Balgoname 2017

88

10.4.5 Status Report

Week 16 goes as planned with work but with a positive variance of actual spending that is more

than budget by $6,250. So far, the project team has successfully finished the processes of the

second phases – planning. Currently, the project team are executing the first task of the project’s

WBS. The project Schedule Performance Index (SPI) and Cost Performance Index (CPI) are

showing a normal progress.

Page 89: Green Computing Research: Project management report

Balgoname 2017

89

10.5 Week 17 Work Progress

10.5.1 Gantt Chart Update

Page 90: Green Computing Research: Project management report

Balgoname 2017

90

10.5.2 Network Diagram Update

Page 91: Green Computing Research: Project management report

Balgoname 2017

91

10.5.3 Budget Report Update

Page 92: Green Computing Research: Project management report

Balgoname 2017

92

10.5.4 EVM Analysis

Page 93: Green Computing Research: Project management report

Balgoname 2017

93

10.5.5 Status Report

Week 17 goes as planned with work and budget. Currently, the project team has successfully

finished the first two phases – initiation, and planning. The project team has successfully finished

the processes of the first task of the execution phases – survey analogues researches and

currently, they are executing the second task of the project’s WBS. The indexes of schedule

performance (SPI) and cost performance (CPI) are showing a positive performance of the project

processes.

10.6 Week 18 Work Progress

10.6.1 Gantt Chart Update

Page 94: Green Computing Research: Project management report

Balgoname 2017

94

10.6.2 Network Diagram Update

Page 95: Green Computing Research: Project management report

Balgoname 2017

95

10.6.3 Budget Report Update

Page 96: Green Computing Research: Project management report

Balgoname 2017

96

10.6.4 EVM Analysis

10.6.5 Status Report

Week 18 went as planned schedule and budget. Both cost and schedule performance indexes are

indicating a normal to positive work progress

Page 97: Green Computing Research: Project management report

Balgoname 2017

97

10.7 Week 19 Work Progress

10.7.1 Gantt Chart Update

Page 98: Green Computing Research: Project management report

Balgoname 2017

98

10.7.2 Network Diagram Update

Page 99: Green Computing Research: Project management report

Balgoname 2017

99

10.7.3 Budget Report Update

10.7.4 EVM Analysis

Page 100: Green Computing Research: Project management report

Balgoname 2017

100

10.7.5 Status Report

Only 50% of scheduled work has been done while planned budget has been consumed. Both

schedule and cost performance indexes are showing a negative progress.

Page 101: Green Computing Research: Project management report

Balgoname 2017

101

10.8 Week 20 Work Progress

10.8.1 Gantt Chart Update

Page 102: Green Computing Research: Project management report

Balgoname 2017

102

10.8.2 Network Diagram Update

Page 103: Green Computing Research: Project management report

Balgoname 2017

103

10.8.3 Budget Report Update

10.8.4 EVM Analysis

Page 104: Green Computing Research: Project management report

Balgoname 2017

104

10.8.5 Status Report

Only one-half of what was planned got completed, but spend all the budget on the tasks

scheduled for week 20. We have not expected any delays as we have rescheduled delayed work

to meet the deadline. Based on the schedule and cost performance indexes, during weeks 5, and 6

work was ahead of what was scheduled, which will substitute to the delays occurred week 20.

Page 105: Green Computing Research: Project management report

Balgoname 2017

105

10.9 Week 21 Work Progress

10.9.1 Gantt Chart Update

Page 106: Green Computing Research: Project management report

Balgoname 2017

106

10.9.2 Network Diagram Update

Page 107: Green Computing Research: Project management report

Balgoname 2017

107

10.9.3 Budget Report Update

10.9.4 EVM Analysis

Page 108: Green Computing Research: Project management report

Balgoname 2017

108

10.9.5 Status Report

Week 21 went as planned. The delays occurred during week 20 has been taken care of and work

is gradually moving to planned schedule thanks to the actions that have been taken to overcome

the schedule issues.

Page 109: Green Computing Research: Project management report

Balgoname 2017

109

10.10 Week 22 Work Progress

10.10.1 Gantt Chart Update

Page 110: Green Computing Research: Project management report

Balgoname 2017

110

10.10.2 Network Diagram Update

Page 111: Green Computing Research: Project management report

Balgoname 2017

111

10.10.3 Budget Report Update

10.10.4 EVM Analysis

Page 112: Green Computing Research: Project management report

Balgoname 2017

112

10.10.5 Status Report

Total work planned is completed for this stage of the project and budget meets the original

budget for week 22. Based on the schedule and cost performance indexes, the project is

progressing as scheduled with no positive or negative variance of the budgeted costs.

Page 113: Green Computing Research: Project management report

Balgoname 2017

113

10.11 Week 23 Work Progress

10.11.1 Gantt Chart Update

Page 114: Green Computing Research: Project management report

Balgoname 2017

114

10.11.2 Network Diagram Update

Page 115: Green Computing Research: Project management report

Balgoname 2017

115

10.11.3 Budget Report Update

10.11.4 EVM Analysis

Page 116: Green Computing Research: Project management report

Balgoname 2017

116

10.11.5 Status Report

Only one-half of scheduled work has been achieved during week 23. We have experienced a

positive variance of budgeted costs by $7,000 more. The project manager with the project team

has met to discuss options that can be taken to overcome this problem.

Page 117: Green Computing Research: Project management report

Balgoname 2017

117

10.12 Week 24 Work Progress

10.12.1 Gantt Chart Update

Page 118: Green Computing Research: Project management report

Balgoname 2017

118

10.12.2 Network Diagram Update

Page 119: Green Computing Research: Project management report

Balgoname 2017

119

10.12.3 Budget Report Update

10.12.4 EVM Analysis

Page 120: Green Computing Research: Project management report

Balgoname 2017

120

10.12.5 Status Report

Week 24 went as planned with schedule and budget. Based on the cost and schedule performance

indexes for this week, the project has been affected by week’s 23 delays and over spending. The

project manager is assessing the possibility of eliminating some of executable tasks of the project

if the schedule performance does not meet the planned schedule time by week 26.

Page 121: Green Computing Research: Project management report

Balgoname 2017

121

10.13 Week 25 Work Progress

10.13.1 Gantt Chart Update

Page 122: Green Computing Research: Project management report

Balgoname 2017

122

10.13.2 Network Diagram Update

Page 123: Green Computing Research: Project management report

Balgoname 2017

123

10.13.3 Budget Report Update

10.13.4 EVM Analysis

Page 124: Green Computing Research: Project management report

Balgoname 2017

124

10.13.5 Status Report

Week 25 went as planned with budget and schedule.

Page 125: Green Computing Research: Project management report

Balgoname 2017

125

10.14 Week 26 Work Progress

10.14.1 Gantt Chart Update

Page 126: Green Computing Research: Project management report

Balgoname 2017

126

10.14.2 Network Diagram Update

Page 127: Green Computing Research: Project management report

Balgoname 2017

127

10.14.3 Budget Report Update

10.14.4 EVM Analysis

Page 128: Green Computing Research: Project management report

Balgoname 2017

128

10.14.5 Status Report

By the end of week 26 work and budget wet as planned.

Page 129: Green Computing Research: Project management report

Balgoname 2017

129

10.15 Week 27 Work Progress

10.15.1 Gantt Chart Update

Page 130: Green Computing Research: Project management report

Balgoname 2017

130

10.15.2 Network Diagram Update

Page 131: Green Computing Research: Project management report

Balgoname 2017

131

10.15.3 Budget Report Update

10.15.4 EVM Analysis

Page 132: Green Computing Research: Project management report

Balgoname 2017

132

10.15.5 Status Report

All the work planned for week 27 have been completed on planned schedule. The project

experienced a positive variance of actual cost by $5,500 more. The project cost performance is

showing a negative performance while the schedule performance index is still maintaining a

normal performance. As the project continues the project manager might take necessary actions

to maintain an actual spending based on what is budgeted.

Page 133: Green Computing Research: Project management report

Balgoname 2017

133

References

Afzalur Rahim, M. (2002). Toward A Theory of Managing Organizational Conflict. The International

Journal of Conflict Management, Vol. 13(No. 3), pp. 206-235.

Anupama, N. (2014, October). Green Computing, A Smart Computing. Journal of Chemical and

Pharmaceutical Sciences, 1(3), 170-171. Retrieved from

http://jchps.com/specialissues/Special%20issue3/40%20jchps%20si3%20addn%20anupama%20

170-171.pdf

Drucker, P. F. (1954). The Practice of Management. New York, NY: Harper Collins Inc. . Retrieved May 30,

2017

Jung, C. G. (1971, August 1). Psychological Types. Collected Wrks of C.G. Jung, Vol. 6.

Kurp, P. (2008, October 1). Green Computing. Communications Of The ACM, Vol. 51(No. 10), pp. 11-13.

LeBar, Z. (2017, April 3). What Are Wikis, and Why Should You Use Them? Retrieved June 18, 2017, from

Envato Tuts+: https://business.tutsplus.com/tutorials/what-are-wikis-and-why-should-you-use-

them--cms-19540

Meade, J. (2017, April 13). This Is Why People Are Intimidated By You, Based On Your Personality Type.

Retrieved from http://thoughtcatalog.com: http://thoughtcatalog.com/jennifer-

meade/2017/04/this-is-why-people-are-intimidated-by-you-based-on-your-personality-type/

Project Management Institute. (2013). A guide to the project management body of knowledge (PMBOK

guide). Newtown Square, PA, USA: Project Management Institute.

Rouse, M. (2010, March 4). Carbon Footprint. Retrieved from Tech Target:

http://whatis.techtarget.com/definition/carbon-footprint

Singh, J. V., & Vatta, S. (2016, January-February 1). Green Computing: Eco Friendly Technology.

International Journal of Engineering Research and General Science, Vol. 4(No. 1), pp. 280-283.

Sultana, A., Suvarchala, C., & Ramay, A. (2016, January 10). A Study on Green Computing: The Future

Computing and Eco-Friendly Technology. International Journal of Innovation Research &

Development, Vol. 5(No. 2), pp. 35-39.

Techopedia. (2017, May 5). Green Computing Definition . Retrieved from

https://www.techopedia.com/definition/14753/green-computing

The Green Grid. (2017, May 6). About. Retrieved from The Green Grid:

https://www.thegreengrid.org/en/about-us

U.S. Environmental Protection Agency. (2016). Climate Protection Partnerships 2014 Reprot. Washington

D.C. : Office of Atmospheric Programs.