green city, clean waters · 1/24/2017  · • 485 stormwater tree trenches • 73 stormwater...

101

Upload: others

Post on 22-Jul-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •
Page 2: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Green City, Clean Waters

Page 3: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Green City, Clean Waters

Accepted and endorsed by our partners:

• Regulators: PA DEP and EPA

• Non-Profits: NRDC, Sierra Club, Clean Water Action, The Nature Conservancy, Trust for Public Lands

Memorialized by:

• 2011 Consent Order and Agreement (COA) with the PA Department of Environmental Protection

• 2012 Landmark Partnership Agreement and Administrative Order for Compliance on Consent with the US Environmental Protection Agency

Signing of Green City, Clean Waters Agreement

Page 4: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Consent Order & Agreement

• COA requires that the City construct and place into operation the controls necessary to achieve the elimination of the mass of pollutants that would otherwise be removed by the capture of 85% by volume of the combined sewage collected in the Combined Sewer System during precipitation events on a system-wide annual average basis.

Page 5: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Water Quality Based Effluent Limit (WQBEL)

Metric UnitsBaseline

value

Cumulative amount as of Year 5 (2016)

Cumulative amount as of

Year 10 (2021)

Cumulative amount as of

Year 15 (2026)

Cumulative amount as of

Year 20 (2031)

Cumulative amount as of

Year 25 (2036)

NE / SW / SE WPCP upgrade: Design

percent complete

0 TBD June 2013 TBD June 2013 TBD June 2013 100% 100%

NE / SW / SE WPCP upgrade: Construction

percent complete

0 TBD June 2013 TBD June 2013 TBD June 2013 100% 100%

Miles of interceptor lined

Miles 0 2 6 14.5 14.5 14.5

Overflow Reduction Volume

million gallons per

year0 600 2,044 3,619 5,985 7,960

Equivalent Mass Capture (TSS)

Percent 62% Report value Report value Report value Report value 85%

Equivalent Mass Capture (BOD)

Percent 62% Report value Report value Report value Report value 85%

Equivalent Mass Capture (Fecal

Coliform)Percent 62% Report value Report value Report value Report value 85%

Total Greened AcresGreened

Acres0 744 2,148 3,812 6,424 9,564

Page 6: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

COA DeliverablesDeliverable Name Deliverable Date

Implementation and Adaptive Management Plan December 1, 2011

Green Infrastructure Maintenance Manual Development Process Plan

June 1, 2012

Comprehensive Monitoring Plan December 1, 2012

Facility Concept Plan for NE WPCP June 1, 2013

Facility Concept Plan for SE WPCP June 1, 2013

Facility Concept Plan for SW WPCP June 1, 2013

Updated Nine Minimum Controls Report June 1, 2013

Tributary Water Quality Model – Bacteria June 1, 2013

Tributary Water Quality Model - Dissolved Oxygen June 1, 2014

Green Infrastructure Maintenance Manual - First Edition June 1, 2014

Tidal Waters Water Quality Model - Bacteria June 1, 2015

Tidal Waters Water Quality Model - Dissolved Oxygen June 1, 2015

Page 7: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Metric Units

Cumulative amount

as of Year 25

(2036)

NE / SW / SE WPCP

upgrade: Design &

Construction

Percent complete 100%

Miles of interceptor lined Miles 14.5

Overflow Reduction

Volume

Million Gallons per

year7,960

Equivalent Mass Capture

TSS / BOD / Fecal

Coliform

Percent 85%

Total Greened Acres Greened Acres 9,564

Water Quality Based Effluent Limit

Page 8: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Green Infrastructure

Bureau of Laboratory Science planters Columbus Square planters

George W. Nebinger School rain garden Kemble Park rain garden

Greened Acre = IC * Wd Impervious

CoverRunoff Depth

Page 9: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Opportunities & Barriers

Year Greened Acres Square Miles% Impervious

cover managed

5 750 1 3%

10 2,100 3 8%

15 3,800 6 14%

20 6,400 10 23%

25 9,600 15 34%

25-Year Implementation of Green City, Clean Waters

Green Stormwater Infrastructure Requirements

Assumes GSI storage equivalent to 1.0 inch of runoff

Page 10: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Southeast Philadelphia (10th & Moyamensing), photo by Andrew Dobshinsky

Page 11: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •
Page 12: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •
Page 13: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •
Page 14: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Pathway to Green

Page 15: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Approach: Public Opportunities

Page 16: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Approach: Public Opportunities

Page 17: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Approach: Projects Initiated

Page 18: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Stormwater Tree Trench

Page 19: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Stormwater Bump-out

Page 20: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Stormwater Planter

Page 21: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Permeable Pavement

Page 22: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Rain Garden

Page 23: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

• GSI Planning Guidelines• GSI Design Process Workflow Packet• GSI Design Requirements & Guidelines• GSI Drawing Requirements Packet

– GSI CAD Standards• GSI Standard Details• GSI Project Implementation Workflows• Landscape Guidebook

www.phillywatersheds.org/gsi_design_resources

Planning and Design | Key Resources

Page 24: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Streets

• Traffic calming

• Pedestrian crossing

• Neighborhood re-investment and revitalization

• Increase in property value

Page 25: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Streets

• green infrastructure on health and safety outcomes from 2000 to 2011 in Philadelphia found…..

• Consistent and statistically significant reductions in narcotics-possession (18-27% less)

• Narcotics manufacture was also significantly reduced

Page 26: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Streets

• Urban tree cover influence on crime

• 10% increase in tree canopy was associated with a roughly 12% decrease in crime

Page 27: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Streets

• Areas that have the most trees along the streets also had fewer prescriptions for antidepressants

Page 28: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Opportunities & Barriers

• Leveraged capital investment in neighborhood anchors

• Public spaces with high pedestrian traffic

• Engagement with local communities and venues

Parks

Page 29: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Hawthorne Park

Parks

• …people reported less mental distress and higher life satisfaction when they were living in greener areas

Page 30: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Parks

Womrath Park

• Life satisfaction increased by 2% and psychological distress decreased by 4%

Page 31: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Parks

Kemble Park

• As green space increased within a 2.5-mile radius of where they lived, overall well-being increased proportionally.

Page 32: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Campuses

• Large land type with single ownership

• Opportunities for students and professors to perform research that will inform later phases of GCCW

• Highly trafficked pedestrian areas are ideal for program tours and marketing

• Coordination for projects in adjacent communities

Page 33: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Schools• …richer and poorer areas saw similar increases in scores with increasing vegetation (NVDI).

• …“that surrounding greenness has approximately equal effects on student academic performance regardless of financial status or gender.”

Page 34: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Schools

Page 35: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Photo : Jenna Stamm , courtesy of The Trust for Public Land

Schools

• …consistent and systematically positive relationships between nature exposure and student performance

Page 36: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Schools

• Views with greater quantities of trees and shrubs from cafeteria as well as classroom windows are positively associated with :

• standardized test scores, graduation rates, and percentages of students planning to attend a four-year college

Page 37: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •
Page 38: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Schools

• …linked views of nature with restoration from mental fatigue and stress reduction

Page 39: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

GSI on Streets, Schools, Parks, and other Public Property

PWD has completed or is in the process of designing:• 485 Stormwater Tree Trenches• 73 Stormwater Planters• 49 Stormwater Bump-outs• 96 Rain Gardens• 12 Stormwater Basins• 141 Infiltration/Storage

Trenches• 31 Porous Paving Projects• 28 Swales• 2 Stormwater Wetlands• 33 Downspout Planters• 15 Other Projects

137 sites, 179.7 acres

Page 40: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Private Investment: Development Regulations

New Development & Redevelopment with earth disturbance exceeding 15,000 square feet:

• Water Quality; Channel Protection; Flood Control • Meets the definition of a greened acre and manages the first inch

of runoff• Opportunity to leverage private development

Sites: Philadelphia Zoo, Shoemaker Green (Penn Campus), Paseo Verde (APM), Pashall Village (affordable housing), Radian (40th and Walnut)Photo Credits: WRT and Paul Rider

Page 41: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Local Business:PWD Storm water pioneer

Development:Granary Green Roof

Private Investment: Development Regulations

Page 42: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Stormwater Regulation Enhancements

• 2015 stormwater regulation and manual updates

• Better align to collection system response and system performance goals

• Maximize management using vegetated practices

• Website improvements

• More flexibility to the development community

Page 43: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Parcel Based Billing for Stormwater

Gross Area Charge = $ 0.69 / 500 sq ft /month

Impervious Cover = $ 4.75 / 500 sq ft / month

www.phillystormwater.org

Page 44: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Incentivized Retrofits• Up to 80% credit for the management of 1” of stormwater

• 1 acre parcel pays $500/mo, $5600/yr for stormwater / Managing 1” over property lowers bill to $100/mo, $1100/yr

Rain Garden

Porous Pavement

Sub-surface Detention PondGreen Roof

Surface Detention Pond

Stormwater Wetland

Page 45: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

68.7 Greened Acres$3.4 million SMIP GrantCost to PWD per GA: $49,000SW Fee reduced:

$250k/yr to $50k/yr

Cardone

Page 46: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Greene Street Friends School

Page 47: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Incentivized Retrofits

LaSalle Campus

MINK/Popi’s Diner

Page 48: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Incentivized Retrofits

Dependable DistributionWharton Street Lofts

Page 49: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

GSI on Private Development and Redevelopment Projects

+GSI Through Incentivized Retrofits

266 projects, 423.4 acres

38 sites, 234.6 acres

Page 50: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Philadelphia has many small spaces and tight yards.

This space belongs to two different properties!

If we can manage stormwater here…Separate

Properties

Page 51: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

You can do it

anywhere!

Page 52: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •
Page 53: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •
Page 54: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

GSI on Streets, Schools, Parks, and other Public Property

+

GSI on Private Development and Redevelopment Projects

+

GSI Through Incentivized Retrofits

137 sites, 179.7 acres

266 projects, 423.4 acres

38 sites, 234.6 acres

Page 55: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •
Page 56: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

SUCCESS!

Metric UnitsBase

Line Value

First 5-Year

WQBEL Target

Cumulative as of

Year 5

(2016)

Miles of Interceptor

LinedMiles 0 2 7.5

Overflow Reduction

Volume

Million Gallons Per Year 0 600 1,710

Equivalent Mass

Capture (TSS)Percent 62% Report value 70.5%

Equivalent Mass

Capture (BOD)Percent 62% Report value 88.9%

Equivalent Mass

Capture (Fecal

Coliform)

Percent 62% Report value 72.0%

Total Greened Acres Greened Acres 0 744 837.7

We have not only achieved out year 5 targets, we have exceeded them!

Page 57: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Public Retrofits

60 Work Numbers

• Average Project Size…………..............2.9 GAs• Average Depth Managed.................1.4 inches• Average Drainage Area....................1.9 acres

DESIGNDesign Started to Design Complete

CONSTRUCTIONDesign Complete to Construction Complete

15.0 months 7.2% GA Increase 16.3 months 2.7% GA Decrease

TOTAL TIMING 2.6 years

171.4 GAs

Page 58: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Renew/Replace

10 Work Numbers

• Average Project Size…………..............0.8 GAs• Average Depth Managed.................1.3 inches• Average Drainage Area....................0.8 acres

DESIGNDesign Started to Design Complete

CONSTRUCTIONDesign Complete to Construction Complete

48.8 months 19% GA Increase 26.2 months

TOTAL TIMING 6.3 years

8.3 GAs

Page 59: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

(Re)Development Regulations

266 Projects

• Average Project Size…………..............1.6 GAs• Average Depth Managed.................1.2 inches• Average Drainage Area....................1.3 acres

CONCEPTProject Initiation - Technical Submittal

5.1 months 3.4 months

TOTAL TIMING 2.2 years

DESIGNTechnical Submittal - Construction Started

CONSTRUCTIONConstruction Started - Verified

18.0 months

423.4 GAs

Page 60: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Incentivized Retrofits

38 Projects

• Average Project Size…………..............6.2 GAs• Average Depth Managed.................1.3 inches• Average Drainage Area....................7.0 acres

CONCEPTAwarded - Technical Submittal

8.5 months 9.4 months

TOTAL TIMINGSMIP 24.6 monthsGARP 16.4 months

DESIGNTechnical Submittal - Construction Started

CONSTRUCTIONConstruction Started - Verified

6.7 monthsSMIP

GARP 1.0 month 4.0 months 11.4 months

234.6 GAs

Page 61: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

5 Year GSI Costs – Design, Construction, Construction Mgmt (as of June 2016)

(Re)Development Regulations Greened Acres: $10M

• Spend approximately $2M/year in Operating costs to manage all aspects of the Stormwater Regulations program (Plan Review Staff, Inspections and Enforcement, Website and Data Management )

Public Retrofit Greened Acres: approx. $40M / $225k per GA

• $30.2M for Compensated Construction

• $5.5M for Professional Service Costs (Design and Construction Mgmt)

• $4M PWD Labor Costs (Design and Construction Mgmt)

Incentivized Retrofit Greened Acres: $16.5+M

• $10.5 SMIP-related Design, Construction and Construction Mgmt

• $5M GARP-related Design, Construction and Construction Management

• $1+M to date for PWD Labor (Design Reviews and Construction Inspections)

Page 62: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

5 Year Costs – Maintenance

Public Retrofit Greened Acres:

• Maintenance costs calculated as a percentage of total capital costs

• For projects with Complete Capital Costs – closed projects where we had full accounting of costs

3.9% - Sample Size 41 projects

• Projected costs when adding projects still in Construction or Design

3.5% - Sample Size 91 projects

• Projected costs for projects with anticipated Maintenance dates in FY18

3.0% - Sample Size 25 projects

• PWD Labor force to Manage all aspects of Maintenance program - $1M/yr

Page 63: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

The greater the challenge, the greater the opportunity, the greater the outcome.

Page 64: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Years 6-10 Look Ahead

Metric Units WQBEL Target

Miles of interceptor lined miles 6

Overflow Reduction Volume million gallons per year 2,044

Equivalent Mass Capture

(TSS)percent Report value

Equivalent Mass Capture

(BOD)percent Report value

Equivalent Mass Capture

(Fecal Coliform)percent Report value

Total Greened Acres Greened Acres 2,148

Page 65: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Greened Acre Projections• (Re)Development Regulations Greened Acres:

– There are 172 projects in the (Re)Development queue, ranging from technically approved (pending construction) to constructed but pending verification.

– PWD will attempt to identify opportunities to work with the property owners and engineers to maximize stormwater management potential.

• Public Retrofit Greened Acres:– PWD already has 276 projects in progress ranging from “in design” to “in

construction”. – PWD has observed that public retrofit projects take on average 2.6 years

from the point that they initiate design through construction completion. This has set the minimum pace for PWD to move projects through the implementation pipeline

• Incentivized Retrofit Greened Acres:– As of June 2016 there were 79 GAs worth of awarded projects currently in

progress; more awarded since then.– PWD plans on budgeting a combined $15 million per year to support both

SMIP and GARP grants through 2021

Page 66: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Planning

Page 67: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Planning

Page 68: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Planning

Page 69: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Planning | Large Area Disconnection

Analysis for Large Area Disconnection (LAD) is performed when there are open space areas that appear to provide the opportunity to manage runoff from areas beyond those immediately adjacent to the site.

Page 70: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Design

Page 71: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Topic Current Design Requirement/Guideline

Target depth of runoff managed 1.5”, maximum of 2”Design drainage areas Directly connected impervious areas (DCIA)

Sizing methodology Static storageInfiltration Rate > 0.25”/hr

Drain Down Time 72 hoursSlow-Release Rate 0.05 cfs/acre DCIA

Minimum Orifice Size 0.5”Underdrains Always included, (safe guard for future clogging)

Loading Ratio Target 10:1, higher rates permitted on case by case basisBuilding Setback 10 feet

Inlet Capacity Rational method, using 1 yr storm intensityInlet Selection PWD Standard Inlets preferredLandscaping Species selection from a recommended plant list

Reporting Design Report (as per GreenIT specifications)

MonitoringMinimum one observation well per system (not applicable

to rain gardens/planters without stone)Drawing Requirements OOW GSI CAD StandardsReview Requirements Based on PWD & City Standards

Submission Requirements Based on PWD Standards

Design: Requirements and/or Constraints

Page 72: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Construction

Page 73: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Construction

• Soil Compaction

• Erosion and Sediment Controls

• Prime/Sub Supervision and Communication

• Warranties

• Material availability and integrity

• Landscaping

• Grading

• Small tolerances

• Punchlist items

Page 74: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Maintenance

Page 75: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •
Page 76: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Inspection:•Visual/photographic•Record condition of vegetative and structural features•Measure sediment and water levels

Maintenance:•Trash and sediment removal•Weeding, pruning, etc.•New product testing•Structural repairs•Erosion control•Reseeding / Watering

Reporting:•Labor effort and materials required to maintain each site

Creating Standards and Protocols:•Required tools and Crew Size•Frequency of visits•Responsible party

Maintenance

Page 77: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Opportunities & Barriers

Diversity: Resources and Workforce

Professional Services Contracts

City Workforce

Adoption Programs

Requirements ContractsSpecial Service Districts

PowerCorpsPHL

Equipment, Materials, Supplies Contracts

Business Improvement Districts

Page 78: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

PowerCorpsPHL

Page 79: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •
Page 80: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Surface Maintenance

Page 81: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Relational Asset Management

SMP

Component

Attribute

Page 82: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Relational Asset

Management &Maintenance Maps

Page 83: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

CityWorks: GSI Entity Group

Page 84: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Damaged Infiltration Trench @ 12th St & Tasker

Page 85: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Monitoring

Page 86: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

• GSI project sites being actively monitored

• Pressure transducers in monitoring wells

• Water level logging stations (Tree Trench, Porous Pavement, Infiltration Trench

• Barometric Pressure Stations

• Groundwater Wells

• Smart Sensor Technologies

• Arduino microcontrollers

• Wireless data transmission

• “Hackathons” – civic minded programmers

Monitoring• Goals:

• Evaluation of GSI performance

• Inform future designs

• Inform Maintenance

Page 87: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

GSI Monitoring Philosophy

• Focus on water quantity

• Focus on individual system performance

• Focus on regulatory metric (“Greened Acre”)

– 1” of runoff from 1 acre impervious cover

Page 88: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Major Monitoring Methods

• Continuous water level monitoring

– Measure the effects of many rain events

– “How does this system perform in general?”

– “How has this system’s performance changed?”

• Simulated runoff testing

– Simulate a rain event by manually applying flow

– “How does this system respond to this storm?”

Page 89: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Monitored SMPs, by type

Page 90: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Typical Tree Trench: cross section

1. Drainage Area

2. Stage-storage Curve

3. Orifice Size &

Height

4. Pre-construction Infiltration Rate

| DATA COLLECTION

Page 91: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

PHILADELPHIA WATER | ANALYSIS METHODS

Water Budget Method

| ANALYSIS METHODS

Page 92: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Pilot Program

“Information from pilot projects will be collected to develop a cost effective GSI program by testing a variety of projects and evaluating them for a number of factors, including:

• Ability to meet performance requirements

• Ease of implementation for on-street and off-street settings

• Cost-effectiveness of various physical conditions

• Efficiency of various systems

• Effectiveness of various materials

• Ease of maintenance GSI ”

Page 93: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Pilot Program Final Report

DATA

SYSTEM

VARIABLES

STATISTICAL

ANALYSIS

Page 94: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

PilotDB

| ANALYSIS TOOLS

Page 95: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Pre- and Post-Construction Relationship: Infiltration Rate

| RESULTS

Page 96: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

CDF: Inches of rainfall for every system-event

Event Designed Overflow Actual Overflow

Rai

nfal

l (in

ches

)

| RESULTS

About 5,000 events, 500 of which are designed to overflow, and about 20 that actually overflow

Page 97: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Water Budget Analysis

• Runoff Volume

• Managed Volume

• Unmanaged Volume

Water Balance Columbus Square Planter Trench*

*12/11/2012- 12/14/2015 1,099 days

107 inches of rainfall

| RESULTS

Volu

me

(cf)

Runoff Designed Performance

Measured Performance

Page 98: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Program Performance/Pilot Results Summary

• The performance monitoring of GSI (results of infiltration rate, storage use, and drain down duration analyses together) makes a strong case that PWD’s GSI systems are performing better than predicted using current engineering design assumptions• The systems overflow less often than predicted• The systems experience higher infiltration rates and faster drain

down times than predicted• The systems have more excess storage capacity available than

predicted over a range of events• Over a range of wet weather event sizes, the fraction of storage capacity

utilized is consistently less than predicted by design assumptions, providing further evidence of over-performance.

– For 15 systems where this data was analyzed, the average maximum portion of available storage used is less than 53% during storms less than 3.0 inches of rainfall depth, and approximately 60% for storms greater than 3.0 inches of rainfall depth

• Approximately 95% of storms from 2012 to 2015 (and PWD’s “typical year” used in wet weather planning) were 2.0 inches depth or less, with 12 storms in the monitoring period above 2.0 inches depth.

– results indicate that systems are regularly managing storms in excess of 3.0 inches with significant storage capacity remaining unused

Page 99: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Piloting, Research, and Innovation

• Academic Research Partnerships

– EPA STAR Grants

– Villanova University

– Drexel University

• Pilot Projects – New Materials, Technologies, Approaches

– Bioretention soil mix

– Drainage wells

• Data Management, Visualization and Analysis Tools

Page 100: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Where we’re going next…

• Innovation!– Cost reduction and efficiencies particularly within Design, Construction,

Maintenance and Monitoring elements

– Standardizing best practices

– Expanding programs and incentives for private green infrastructure activities – Alternative Project Delivery Methods

– National GSI Practitioners Information Exchange

• Continue to generate Green Jobs

• Monitoring performance at scale

• Grow community partnerships to engage in planning and to address local needs (ReBuild)

• Integrate CSO controls with flooding and climate change

Page 101: Green City, Clean Waters · 1/24/2017  · • 485 Stormwater Tree Trenches • 73 Stormwater Planters • 49 Stormwater Bump-outs • 96 Rain Gardens • 12 Stormwater Basins •

Green City, Clean Waters

www.phillywatersheds.orgwww.phila.gov/water