gpa research data help save time maa eru 10 02 10
TRANSCRIPT
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 1/28
GPA USA
March 2010
USE OF GPA RESEARCH PROGRAM
DATA/SOFTWARE FOR TROUBLE SHOOTING
AND SOLVING OPERATIONAL ISSUES
DURING COMMISSIONING OF ETHANE
RECOVERY UNIT AT KNPC MAA
March 2010
89 th Annual GPA Convention
Kuwait National Petroleum Company
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 2/28
GPA USAMarch 2010 2
MAA ETHANE RECOVERY UNIT
The plant, wholly owned and operated by KNPC Ltd.,
Designed by M/s FLUOR
Constructed by M/s HYUNDAI Corporation,
Licensed by M/s Ortloff Houston, Plant has been commissioned Dec-2008.
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 3/28
GPA USAMarch 2010 3
MAA ETHANE RECOVERY UNIT
Feed gas originates from the existing lean oil plant.
The plant is designed to process 1140 (MMscfd ) of
feed gas from Lean Oil Plant (LOP) which contains
around 9% of ethane and 1% propane (max.)
without any other heavier HC. However someequilibrium amount of lean oil is present in the
feed.
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 4/28
GPA USAMarch 2010 4
MAA ETHANE RECOVERY UNIT
Plant was operating normal at around 70% capacity,
however whenever Ethane recovery level is
increased or column operating at the design level,
the ovhd system gets cooled as a result of flooding
in the top section of the column, which leads tounstable operations.
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 5/28
GPA USAMarch 2010 5
MAA ETHANE RECOVERY UNIT
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 6/28
GPA USAMarch 2010
Ethane Product
Feed
Residue Gas
Recycle Split Vapor (RSV)
MAA ETHANE RECOVERY UNIT
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 7/28
GPA USAMarch 2010
Gas Turbines
NGL Extraction 1&2Dehydration
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 8/28
GPA USAMarch 2010 8
MAA ETHANE RECOVERY UNIT
Plant was pre-commissioned and as per advise of
Ortloff extensive dry out was carried out. All the
construction debris were removed during pre-
commissioning. Initial startup was very smooth.
Flange leaks were arrested during the cool downand after that unit operations were smooth. Plant
was operating normal around 70% capacity and
column pressure drop was higher compared to
design.
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 9/28
GPA USAMarch 2010 9
MAA ETHANE RECOVERY UNIT
However, the equipment vendor has agreed to
operate at these levels. When the feed rate was
increased to design levels, the entire NGL section
was getting cooled as a result expander suction
KOD temperature was coming down and expander speed was getting reduced. Due to this the unit
went into unstable operation and cycling. Pressure
drop across the beds went up to more than 1000 mm
H2O as compared to the design of 50 mm H2O. It was concluded that the Column was flooding and
liquid was entering the cold box from overhead,
which caused the temperature reduction in
expander suction KOD and which was the main
reason for unit going into unstable operations.
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 10/28
GPA USAMarch 2010 10
MAA ETHANE RECOVERY UNIT
The flooding may be due to any one the
following:
Freeze due to moisture slip from driers Other impurities
Construction debris
CO2 Freeze in the top of the tower
Benzene freeze or Organic material freeze.
Wrong design of column internal
Change in the mode of operations.
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 11/28
GPA USAMarch 2010 11
FREEZE DUE TO MOISTURE SLIP FROM
DRIERS
Feed to this plant comes from the Lean Oil
Plant which has driers to remove the
moisture. This unit also has driers to
remove moisture up to 0.1 ppm. Driers aredesigned for 1140 mmscfd and currently the
unit is being operated around 700 mmscfd.
The Performance of the driers were
checked by UOP. Moisture in the driersoutlet is lower than the design and hence it
was not the cause of the problem. Further
more moisture will cause the blockage at
lower capacity itself;. This cause is ruled out
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 12/28
GPA USAMarch 2010 12
OTHER IMPURITIES
In addition to the obvious need of water
removal from the gas stream to protect fromblockage in the cryogenic sections of a
plant, consideration must be given to the
possible formation of other solids or semi-
solids in the gas stream. Amines, glycols,
and compressor lube oils in the gas stream
can form blockages in the system. Generally
these contaminants will form a blockage
upstream of an expander, in the lower
temperature exchange circuit, or on the
screen ahead of an expander. All the screen
and cold box were opened and no debris
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 13/28
GPA USAMarch 2010 13
CONSTRUCTION DEBRIS
From the plant data it
was found that delta pwas on the higher side
in the top two beds.
During construction any
leftover material or rust
might have closed the
liquid distributor leading
to liquid accumulationcausing flooding.
Therefore it was decided
to shutdown and open
the column to inspect.
On inspection, it was
found that there was no
construction debris andcolumn was clean as
per Figure -1 . Therefore
the same is not cause
for the flooding.
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 14/28
GPA USAMarch 2010 14
CO2 FREEZE IN THE TOP OF THE TOWER
Upstream lean oil plant do not have any amine unit, Carbon
di-oxide in the feed stream is not being removed in LOP andthe same is processed in the ERU. This problem is
recognized during the design stage. Accordingly the plant
was designed for three levels of CO2. (2 , 2.5 , 3% ) .
Carbon dioxide can form as a solid in lower temperature
systems. Fig 1 will provide a quick estimate for the possibilityof formation of solid CO2. If operating conditions are in the
Methane liquid region as shown by the insert graph, the
dashed solid-liquid phase equilibrium line is used. For other
conditions the solid isobars define the approximate CO2 vapor
concentration limits. For example a pressure of 300 psia andtemperature at ±170°F, the insert graph shows the operating
conditions to be in the liquid phase region. The dashed solid-
liquid phase equilibrium line indicates that 2.1 mol percent
CO2 in the liquid phase would be likely to form solids.
However, at the same pressure and temperature at ±150°F, the
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 15/28
GPA USAMarch 2010 15
CO2 FREEZE IN THE TOP OF THE TOWER
This chart represents an approximation of CO2 solidformation. Detailed calculations were carried out for CO2
freeze margin at each stages 8.5 ° F (2.0% CO2 at 98% recovery
), 6.6 °F (2.5% CO2 at 94% Recovery ), 6.4 °F (3.0% CO2 at
88% Recovery ) during design stage for each one of the feed
case. These correlations in HYSYS are developed based onthe GPA data. There is enough CO2 freeze margin provided in
the design so that column will not freeze due to CO2. We have
suspected that the higher pressure drop observed may be
due to CO2 freeze. Normally when the column is warmed up
the CO2 freeze temperature goes up and solid formed willslowly dissolved in the process and pressure drop will reduce.
Even after increasing the temp, the pressure drop did not
decrease significantly and in some time the pressure drop
take place in the section where the CO2 freeze margin is on
the higher side and not expected to freeze . Hence the CO2
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 16/28
GPA USAMarch 2010 16
CO2 FREEZE IN THE TOP OF THE TOWER
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 17/28
GPA USAMarch 2010 17
CO2 FREEZE IN THE TOP OF THE TOWER
This chart represents an approximation of CO2 solidformation. Detailed calculations were carried out for CO2
freeze margin at each stages 8.5 ° F (2.0% CO2 at 98% recovery
), 6.6 °F (2.5% CO2 at 94% Recovery ), 6.4 °F (3.0% CO2 at
88% Recovery ) during design stage for each one of the feed
case. These correlations in HYSYS are developed based onthe GPA data. There is enough CO2 freeze margin provided in
the design so that column will not freeze due to CO2. We have
suspected that the higher pressure drop observed may be
due to CO2 freeze. Normally when the column is warmed up
the CO2 freeze temperature goes up and solid formed willslowly dissolved in the process and pressure drop will reduce.
Even after increasing the temp, the pressure drop did not
decrease significantly and in some time the pressure drop
take place in the section where the CO2 freeze margin is on
the higher side and not expected to freeze . Hence the CO2
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 18/28
GPA USAMarch 2010 18
CO2 FREEZE IN THE TOP OF THE TOWER
This chart represents an approximation of CO2 solidformation. Detailed calculations were carried out for CO2
freeze margin at each stages 8.5 ° F (2.0% CO2 at 98% recovery
), 6.6 °F (2.5% CO2 at 94% Recovery ), 6.4 °F (3.0% CO2 at
88% Recovery ) during design stage for each one of the feed
case. These correlations in HYSYS are developed based onthe GPA data. There is enough CO2 freeze margin provided in
the design so that column will not freeze due to CO2. We have
suspected that the higher pressure drop observed may be
due to CO2 freeze. Normally when the column is warmed up
the CO2 freeze temperature goes up and solid formed willslowly dissolved in the process and pressure drop will reduce.
Even after increasing the temp, the pressure drop did not
decrease significantly and in some time the pressure drop
take place in the section where the CO2 freeze margin is on
the higher side and not expected to freeze . Hence the CO2
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 19/28
GPA USAMarch 2010 19
BENZENE FREEZE IN THE TOP OF THE
TOWER
Ortloff has designed or retrofitted over 100 gas plants since 1993.Benzene freeze is not considered in the design. Furthermore
Benzene level in the LOP plant out let is expected to very low
since most of the heavy hydrocarbons are already removed ( like
c3,c4,c5 ) . A gas plant in Malaysia has experienced similar flooding
conditions in the upper section of their tower due to Benzene freeze.
Benzene contamination was discovered as a factor limiting plantthroughput. A paper was presented at the 83rd Gas Processors
Association Conference in New Orleans.
The solubility of Benzene in NGL OVHD streams is composition
dependent. Following Figure 16-35 shows the solubility of Benzenein Methane and Figure 2 shows the solubility of Benzene in Ethane.
From these graph it is obvious that more Ethane slips in the top less
is the chances of the Benzene formation
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 20/28
GPA USAMarch 2010 20
BENZENE FREEZE IN THE TOP OF THE
TOWER
From the above it is clearly evident that for this column operatingconditions, about 400-500 ppm of Benzene is required for freeze.
From the literature it is noticeable that in order to have Potential
Benzene freeze, the Benzene concentration has to be around 400
ppm at the operating temp of around -100 °C.
In the absence of a quantitative BETX analysis, it was assumed thatvarying Benzene concentration in feed and to estimate the level in
which Benzene concentrations might freeze in the upper section of
the demethanizer. Our calculations for Benzene freeze indicated that
Benzene concentrations around 400 ppm in bed-2 of the
demethanizer will require Benzene concentration greater than 3000
ppmv in the feed. The crystallization point will change when the feedgas composition changes. In general, Benzene is more likely to
freeze in a leaner gas. In a lean gas, the solubility of Benzene is
poorer allowing Benzene to crystallize at higher temperatures. For
example, a Benzene concentration of 400 ppmv in a lean gas (90%
C1, 6.5% C2, 0.4% C3) will freeze at -97 °C. Based on calculations.Cyclohexane's crystallization point seems to be lower than the
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 21/28
GPA USAMarch 2010 21
BENZENE FREEZE IN THE TOP OF THE
TOWER
Hysys was used to predict the concentration of Benzene and cyclo-hexane in the upper section of the demethanizer from a given
specific concentration in the feed. This helped to determined
Benzene freeze at specific Benzene concentration in the feed, similar
to calculating C02 freeze. Liquid, Solid Gas Equilibrium software
provided by the Gas Producers Association is aid in calculating the
temperature and pressure at which Benzene solids will form within amixture.
The GPA has issued a computer package based on the research
results. This GPA computer program will predict the solubility of
carbon dioxide, BTEX, and heavy hydrocarbons in various
hydrocarbon mixtures at the most stringent conditions and the samewas used by M/s. Ortloff.
The analysis of the feed gas indicates that the Benzene molar
fraction is 0.0005. It probably is the most reliable data in the BTEX
group, since it has the highest concentration in the group. Therefore,
it is more reasonable to use Benzene as the key component to
calculate other variables. .
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 22/28
GPA USAMarch 2010 22
BENZENE FREEZE IN THE TOP OF THE
TOWER
Detailed Hydrocarbon analysis is carried out and found that Benzenelevels are very low and it is less than 50 ppm . Therefore the same is
excluded
Ortloff has designed or retrofitted over 100 gas plants since 1993.
Benzene freeze is not considered in the design. Furthermore
Benzene level in the LOP plant out let is expected to very low
since most of the heavy hydrocarbons are already removed ( like
c3,c4,c5 ) . A gas plant in Malaysia has experienced similar flooding
conditions in the upper section of their tower due to Benzene freeze.
Benzene contamination was discovered as a factor limiting plant
throughput. A paper was presented at the 83rd Gas Processors
Association Conference in New Orleans.
The solubility of Benzene in NGL OVHD streams is composition
dependent. Following Figure 16-35 shows the solubility of Benzene
in Methane and Figure 2 shows the solubility of Benzene in Ethane.
From these graph it is obvious that more Ethane slips in the top lessis the chances of the Benzene formation
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 23/28
GPA USAMarch 2010 23
BENZENE FREEZE IN THE TOP OF THE
TOWER
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 24/28
GPA USAMarch 2010 24
BENZENE FREEZE IN THE TOP OF THE
TOWER
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 25/28
GPA USAMarch 2010 25
BENZENE FREEZE IN THE TOP OF THE
TOWERIn the absence of any of the above issues, it is decided to study the
performance of the Column and its internals under normal operatingconditions.
It was noticed that Bed 3 is not having enough delta-T as per
Design. This clearly indicated that there could be some potential
for flooding or carry-over or blockage, etc.
Therefore, it was decided to carry out a gamma ray scanning acrossthe tower from top to bottom to identify the source of the problem
at various capacities 60, 80 and 100 %.
Gamma ray scanning was carried out at various thruput 60%,
80% and 100%. Scan revealed that at 60% of the design load (
400 kNm3/hr) the column operated stable and no significant
problems were detected .
At about 80% of design capacity (500 KNM3/HR) flooding starts to
occur in BED 3.
Scan taken at plant loads close to 100% of the design (636
KNM3/HR) identified that under these conditions flooding also
occurred in BED 2 and BED 1 at the top of de-methaniser. The scan
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 26/28
GPA USAMarch 2010 26
BENZENE FREEZE IN THE TOP OF THE
TOWER
This area of the column appears to be hydraulically limited. This is the
place where liquid carry over starts and slowly goes to top beds 1 & 2.
Down comers are restricting and hole size in this section may have to be
increased. M/s Ortloff is carrying out further simulation to identify the
issue. Based on findings, the hole sizes may need to be enlarged to
improve the hydraulics.
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 27/28
GPA USAMarch 2010 27
CONCLUSION
From the above it is clear that we have under gonetypical trouble shooting exercise to solve the
problem. GPA data / software has helped us to
identify and exclude the major issue of heavy
hydrocarbons freeze. GPA data was very usefuland has helped to rule out many potential
issues like CO2 freeze and Benzene freeze.
Based on which we have progressed and
concluded that our problem is from tray internalswhich will be checked and changed, if required.
We thank GPA for providing these important
data and we also thank M/s Ortloff for running
the software to estimate the Benzene freeze
8/7/2019 gpa research data help save time maa eru 10 02 10
http://slidepdf.com/reader/full/gpa-research-data-help-save-time-maa-eru-10-02-10 28/28
GPA USAMarch 2010
QUESTIONS & ANSWERS
28