governor response sequence bob green garland power and light ercot future as workshop january 20,...

17
Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

Upload: dale-blair

Post on 23-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

Governor Response Sequence

Bob GreenGarland Power and Light

ERCOT Future AS Workshop January 20, 2014

Page 2: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

You get the idea: if the power generated exceeds the load, frequency rises.

If the generator power is less than the total loads, frequency declines

Page 3: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

Governor Response Issues• Traditional training simplifies the reason for

frequency deviations from 60HZ. See “You get the idea” on the previous slide. In reality, power generated always equals the load.

• This training module describes what actually causes frequency deviations: mechanical power into a turbine not being equal to the electrical power output of the connected generator.

• The trip of a large generator is used to illustrate the process.

Page 4: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

Voltage Regulator

Armature

Turbine

ValvesEnergy Source

•Boiler•Reactor•Penstock

Field

Auxiliary Load

Transient Reactance

Gross Metering

Step – Up Transform

er

To Load

Net Metering

Governor Response Schematic

Governor

Page 5: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

Loss of Generation - 1

• In response to a unit trip, each real generator in the interconnected system increases their MW output in proportion to their electrical distance from where the generator tripped.

• The rotating kinetic energy in each tandem turbine-generator assembly supports the increased instantaneous power output.

• With power output greater than the power input, shaft speed [frequency] decreases.

Page 6: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

Torque and Inertial Energy• Steam input hits turbine blades creating torque

that increases rotational speed of the T-G which in turn increases the kinetic (inertial) energy.

• When the electrical torque is greater than mechanical torque, the rotation slows extracting stored inertial energy from the mass.

Page 7: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

Loss of Generation - 2• The governors sense the slower speed and

open valves between the mechanical energy sources [boiler, etc.] and the turbine to balance the generator mechanical input with the electrical output.

• When the mechanical input equals the increased electrical output, the frequency stop decreasing [this is called the C point].

• The frequency increases as the kinetic energy is replaced and settles at a new steady state frequency value [this is called the B point].

Page 8: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

Loss of Generation - 3

• The transition from the initial steady-state frequency [the B point] to restoring frequency to the scheduled value normally consists of sustained power plant control and control from the center control [AGC/LFC].1. Plant controllers need to recognize the higher

desired output [MW] due to low frequency.2. Control Centers need to send AGC signals to

increase the governor set-points and restore frequency to schedule [usually 60 HZ].

Page 9: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

Loss of Generation - 4• Traditional Control Areas and the ERCOT Zonal

Market typically started sending LFC control within 10 seconds of a unit trip.– Control Areas responded to a steady ACE value.– ERCOT Zonal QSEs responded to a Responsive

Reserve deployment.

• ERCOT Nodal sends RegUp deployments to QSEs but waits approximately 60 seconds for SCED to calculate new Base Points utilizing capacity released by RRS deployments.

Page 10: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

Loss of Generation - 5ERCOT Frequency vs. Time

"Point B" 13:51:35,

59.86899948

"Point A" 13:51:15, 60.020 Hz

"Point C"13:51:25, 59.786 Hz

59.65

59.70

59.75

59.80

59.85

59.90

59.95

60.00

60.05

60.10

13:50

:00

13:50

:35

13:51

:10

13:51

:45

13:52

:20

13:52

:55

13:53

:30

13:54

:05

13:54

:40

13:55

:15

13:55

:50

13:56

:25

13:57

:00

13:57

:35

Time

Fre

qu

en

cy

(H

z)

Page 11: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014
Page 12: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

Closing Misunderstandings

• Frequency Nadir is where the total transient mechanical turbine input equals the total electrical generator output [not the system load].

• Slope of the dark green line is also influenced by whether the generator trips [steep slope] or if the turbine trips [generator stays connected to the grid for several seconds].

• Settling Frequency is where the governors have driven the steady-state mechanical turbine input equal to the electrical generator output.

Page 13: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

Review of Frequency Control Steps1. Electrical/mechanical energy imbalance caused

by a change in load or change in generation2. Turbine-generator shaft speeds [frequency]

increase or decrease3. Initial governor response due to the resulting

change in frequency4. Stabilizing frequency at new steady-state value5. Restoring scheduled frequency [and interchange]

using Automatic Generation Control6. Preparing for next imbalance

Page 14: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

Primary versus Secondary Frequency Control

Page 15: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

After Governor Response to 7 MW of Load Added

Page 16: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

After AGC Secondary Frequency Control

Page 17: Governor Response Sequence Bob Green Garland Power and Light ERCOT Future AS Workshop January 20, 2014

Primary Control Secondary or Supplementary ControlCommon Name Governor Control/Response AGC Control/ResponseFunction-Generic Holds the system together as load changes

occur and also as un-commanded generation excursions occur

Shifts generation between units to achieve security and economic objectives plus restores frequency to the rated value.

Function-Technical Provides the correct amount of mechanical input to turbines to match the electrical output of the corresponding generators

Changes the 60HZ governor set-points of the units to achieve scheduled values established by the market.

Control Input Frequency/rotational speed of the turbine In ERCOT, the SCE for the portfolio of unitsControl Time Constant Fast - Seconds Slower - Tens of seconds and minutesStyle of Control Local within the Units/PGCs—A QSE has no

direct control over governor response.Centralized from ERCOT to Units via QSEs

Performance Optimization

Having more governors on-line (with a given droop characteristic) will minimize the magnitude of frequency deviations

Having more units being controlled by AGC will minimize the duration of frequency deviations

Key Parameters Steady state speed characteristic (droop), governor dead-band, first stage boiler pressure (steam units) and head (hydro units)

Base power schedule plus deployments of balancing energy, regulation energy, responsive and non-spinning reserve. AGC dead-band, gains and frequency bias term.

Market Characteristics If there ever is a governor response market, there will probably be bids, awards and settlement, but the market will never deploy the governor response.

Bids, awards, deployments and settlement through the Ancillary Service Market. Performance monitoring of individual Services is approximate and complicated.

Disturbance Timeline Initial governor response (to point B) is over completely by the time units start receiving secondary control signals in response to the disturbance.

There needs to be recognition of governor response and coordination between RRS and RegUp deployments to insure smooth , rapid and sustained frequency recovery.