GOVERNMENT PRINTING WORKS
PERFORMANCE PRESENTATION TO DHA
PORTFOLIO COMMITTEE
QUARTER 1 PERFORMANCE REPORT
5 SEPTEMBER 2017
Celebrating 129 years
Celebrating 129 years
1. Vision, Mission, Values - Slide 3
2. Strategic Outcomes - Slide 4
3. Summary of Quarter 1 Performance - Slide 5
4. Summary of Quarter 1 Financial Report - Slide 6-7
5. Branch: Operational and Production - Slide 8-11
6. Branch: Strategic Management - Slide 12-13
7. Branch: Financial Services - Slide 14-16
8. Branch: Human Resources - Slide 17
9. Branch: Office of Executive Officer - Slide 18-19
8.1 Information, Communications &Technology
8.2 Internal Audit
Table of Contents
Celebrating 129 years
VISION, MISSION AND VALUES
MISSION
To provide:
Cost effective, secure, reliable and timeous
services to all spheres of government in
printing;
Public with equitable information
Dissemination of government information,
through technology, innovation and service
excellence.
VALUE
Reliability
Integrity
Accuracy
Stakeholder satisfaction
VISION: STATE’S MANDATED SECURITY PRINTER
HOME AFFAIRS SECURES IDENTITY GPW SECURES IDENTITY AND TRAVEL DOCUMENTS
Celebrating 129 years
GPW STRATEGIC OUTCOME-ORIENTATIVED GOALS
STRATEGIC OUTCOME 1 - STATE OWNED COMPANY
GOAL STATEMENT: Further develop the Government Component into a State Owned Company
GOAL STATEMENT: Optimise processes and facilities to increase operational effectiveness and improved customer services
STRATEGIC OUTCOME 2 - OPTIMISE PROCESSES AND FACLITIES
GOAL STATEMENT: Have an efficient, effective and well trained / developed workforce
STRATEGIC OUTCOME 3 - DEVELOPED WORKFORCE
Celebrating 129 years
SUMMARY OF GPW FINANCIAL PERFORMANCE: QUARTER 1 OF 2017-2018 APP
Budget (YTD) Actual (YTD) Variance
(R ‘000)as at June
2017
as at June
2017Bud - Act
Revenue 362,552 254,600 107,952
Cost of sales (186,334) (121,983) (64,351)
Gross Profit 176,218 132,617 43,601
Other income 18,477 14,289 4,188
Operating expenses (57,564) (43,595) (13,969)
Operating profit 137,131 103,311 33,820
Interest received - -
Profit for the year 137,131 103,311 33,820
Celebrating 129 years
-
20 000
40 000
60 000
80 000
100 000
120 000
APRIL MAY JUNE
Sales R,0000
Summary of GPW QUARTER 1 SALES
ACTUAL VS BUDGET
For the quarter ending June 2017, the GPW
underperformed in terms of revenue collection. In
determining the monthly budget for sales, the
annual sales figure is divided by 12.
The underperformance is as a result of:
– Reduction in the number of extraordinary
gazettes
– Orders from our large customers was
received in Q2
There has been an improvement in the financial
performance for the second quarter and
management is confident the sales target will be
reached.
Due to the underperformance in the sales figures,
all other figures under performed as there is a
direct relationship between sales, gross profit and
operating expenditure.
Celebrating 129 years
Branch: Operations and Production (1/2)
BRANCH
PERFORMANCE
INDICATOR
REPORTING
PERIOD
ANNUAL TARGET QUARTER 01
TARGET
Q1 PROGRESS
Number of equipment
items procured
Annual
Target
Recapitalisation plan
rescheduled for
2019/20
N/A Achieved
SLA for sorting machine
drafted – awaiting
finalisation
Identity Cards
distributed according
to clients
specifications
Quarterly 100% of Identity
Documents/ Cards
distributed must
conform to the client’s
specifications
100% of Identity
Documents/
Cards distributed
must conform to
the client’s
specifications
Achieved
100% of 614 925 Identity
Documents / Cards
distributed, conformed to
the client’s specifications.
Travel Documents
delivered according
to client’s
specifications
Quarterly 100% of Travel
Documents delivered
must conform to the
client’s specifications
100% of Travel
Documents
delivered must
conform to the
client’s
specifications
Achieved
100% of 218 381 Travel
Documents delivered.
Celebrating 129 years
Branch: Operations and Production (2/2)
*A new form of Entity in terms of Schedule 3 of the Public Service Act of 1994 as amended; Section 7(5)(c)
PERFORMANCE
INDICATOR
REPORTIN
G PERIOD
ANNUAL TARGET QUARTER 01 TARGET Q1 PROGRESS
Examinations
Scripts delivered
according to
Quality
specifications
Quarterly 100% of examination
papers delivered
must conform to the
client’s specifications
100% of examination
papers delivered must
conform to the client’s
specifications
Achieved
100% of 1 633 063
examination papers
delivered, conformed to the
client’s specifications.
Government
Gazette published
according to
Quality
specifications
Quarterly 100% of
Government
Gazettes published
to conform to quality
and timeline
specifications
100% of Government
Gazettes published to
conform to quality and
timeline specifications
Achieved
100% of 488 Editions
comprising of 42 322 pages
of Government Gazettes
published in conformance
to quality and timeline
specifications
Progress of
Construction of
Secure Facilities
Annually Construction of
pavilion 3 completed
New Head office
building completed
Construction of
Remaining GPW
Visagie Street Site
10% complete
N/A Achieved (Q1 planned)
Construction of pavilion 3 at
75% complete.
New Head office building –
Professional Team
contracting.
GPW input document with
GPW requirements ready.
Celebrating 129 years
BRANCH: OPERATIONS AND PRODUCTION
PRINTING, PACKAGING AND PUBLICATION CAPABILITY
Celebrating 129 years
Finishing Operations Craft & Mechanised Binding Machinery & Product features:
Guillotines; Folding machines; Saddle stitchers; Collators; Sewing machines; Perfect binder; case
maker; Die cutters; Counting machines; Shrink wrapper for products from all printing operations
GUILLOTINE FOLDER SADDLE STITCHER
PERFECT BINDER
SEWING MACHINE
COLLATOR
STAMPS
Celebrating 129 years
Branch: Strategy Management (1/2)
BRANCH
PERFORMANCE
INDICATOR
REPORTIN
G PERIOD
ANNUAL
TARGET
QUARTER
01
TARGET
Q1 PROGRESS
Marketing of GPW
Services - Number
of new security
products
developed for
customers
Annually
3 new
security
products
developed
N/A Achieved (quarter targets) for new
clients:
DIRCO – provision of stationery and
special printing items
Umalusi- provision of security printing
services for their Education
Certificates
Department of Trade and Industry –
provision of stationery and special
security printing items i.e. certificates
SAPS- provision of security printing of
firearm licence
SAPS Civilian Secretariat – provision
of stationery and special printing items
Celebrating 129 years
Branch: Strategic Management (2/2)
BRANCH
PERFORMANCE
INDICATOR
REPORTIN
G PERIOD
ANNUAL
TARGET
QUARTER 01
TARGET
Q1 UPDATE
SECURITY SERVICES
To protect and
secure the assets,
people and
information of GPW
Annually Implement 100%
security risk
management
programs in
accordance with the
approved plan
25% security risk
management
program.
Achieved
Implementation in progress
Percentage of
annual risk &
compliance plan
implemented
Annually
100 % of annual risk
& compliance plan as
approved by the Risk
Committee,
implemented
25% of annual risk
& compliance plan
Achieved
3 year Risk Management Plan
reviewed and submitted for approval
and update to Risk Committee
provided in the first quarter meeting
Risk Committee meeting and Special
Risk Committee for 1st quarter held.
Strategic and operational risk
registers developed and approved by
MANCO, EXCO and Risk Committee.
Celebrating 129 years
Branch: Financial Services (1/3)
BRANCH
PERFORMANCE
INDICATOR
REPORTIN
G PERIOD
ANNUAL
TARGET
QUARTER
01 TARGET
Q1 PROGRESS
Operating cost as
percentage of
revenue
Quarterly
18% Operating
cost as
percentage of
revenue
15.9%
Not Achieved
17.1% Operating cost as percentage of
revenue. Actual revenue was less than
anticipated in the target calculation due to less
order of Identity Cards by Home Affairs.
Gross profit margin Quarterly
28% gross profit
margin 48.6%
Achieved (+)
52.09% gross profit margin
Mainly due to product mix exceeding target
Debtor collection
period Quarterly
80 days
80 days
Achieved (+)
37.9 days. Average debtors days decreased
due to improved collections
Maintain a positive
working capital ratio
Quarterly
5 positive
working capital
ratio maintained
N/A
12.8 - Current liabilities were lower than
anticipated
Inventory turnover
ratio
Quarterly
3 Inventory
turnover ratio
3 Inventory
turnover ratio
Achieved
3.26 Inventory turnover ratio
Celebrating 129 years
Branch: Financial Services (2/3)
BRANCH
PERFORMANCE
INDICATOR
REPOR
TING
PERIOD
ANNUAL
TARGET
QUARTER
01
TARGET
Q1 PROGRESS
SLA’s concluded
Annually
Conclude
SLA’s with 10
external
customers 10
suppliers
SLA’s
concluded
Achieved
Finalized • Companies Intellectual Property
Commission (CIPC)- (special printing of
documents)
• Manhand Forklift services
• CM Cormas (canteen services
In progress • Companies Intellectual Property
Commission (CIPC)- (special printing of
documents)
• Manhand Forklift services
• CM Cormas (canteen services
• Batsumi CMC Contract maintenance of
examinations machine)
• Pitney Bowes SA - machine equipment for
mail sorting
• Fidelity –Security guarding services
• Aptronics- ICT services
• SAPS 1: Gun licence
• Marubeni Corporation - maintenance of
passport making machine.
Celebrating 129 years
Branch: Financial Services (3/3)
BRANCH
PERFORMANCE
INDICATOR
REPORTIN
G PERIOD
ANNUAL
TARGET
QUARTER
01 TARGET
Q1 UPDATE
Return on capital
investment Annually
19% return on
capital investment
N/A
Achieved
50.8% return on capital investment as at
the end of Quarter 1
Investment in capital planned for later
during the year
Percentage
completed
construction of
secured facilities
Annually
Construction of
pavilion 3
completed
Master plan for
remainder of
facilities
completed
N/A Achieved
Construction of pavilion 3 at 75%
(rounded) complete.
New Head office building – Tender for
Professional Team with BAC.
Development Plans ready for Sketch
Committee submission. Design Approval
in progress.
Celebrating 129 years
Branch: Human Resources (1/1)
BRANCH
PERFORMANCE
INDICATOR
REPORTING
PERIOD
ANNUAL
TARGET
QUARTER 01
TARGET
Q1 UPDATE
Fill positions in
accordance with
identified needs
Quarterly Filled 85% of posts
identified for filling
in accordance with
HR staffing plan
20% of identified
posts filled
Achieved
42.61% positions filled
Develop internal
GPW Training and
Development
Programmes
Bi - annually
Develop 3 GPW
training and
development
programmes
NA Achieved
85% of 100% graduates contracted
for 2 year period.
Recruitment process of 18
Apprenticeship technical training
learners underway.
Provide training and
development
Quarterly 2 average training
interventions per
person
25% of identified
target completed
Achieved
Out of 550 employees, 85 trained on
19 different intervention
Celebrating 129 years
Branch: Office of CEO (1/2)
BRANCH
PERFORMANCE
INDICATOR
REPORTIN
G PERIOD
ANNUAL
TARGET
QUARTER
01
TARGET
Q1 UPDATE
Completed design and
implemented procedures
identified in the business
case to support the
establishment of a State
Owned Company
Annually
Publication of Bill
and finalization of
Memorandum of
Incorporation and
Shareholder
Compact
N/A Achieved quarter targets
Business Case, Draft Bill, MoI, SEIAS
undergoing Cabinet process
Percentage of annual
internal audit plan
implemented
Annually
90% of annual
internal audit plan
implemented
N/A Achieved quarter targets
28% of the audit plan implemented.
Completed: Approved Strategic Internal
Audit Plan; Approved IAA Charter;
Approved Audit Committee Charter;
Approved Combined Assurance
Framework; Developed Quality
Assurance and Improvement
Programme; 2017/18 Q1 Audit
Committee Meeting held and 2016/17
Q4 Performance Information completed
Celebrating 129 years
Branch: Office of CEO (2/2)
BRANCH
PERFORMANCE
INDICATOR
REPORTIN
G PERIOD
ANNUAL
TARGET
QUARTER
01 TARGET
Q1 UPDATE
INFORMATION, COMMUNICATIONS AND TECHNOLOGY (ICT)
Percentage of security
vulnerabilities
(detected)
Annual
>80% ICT
services offerings
identified
implemented
N/A Achieved
• 99.5% vulnerabilities
mitigated
• 100% of detected threats
blocked
Availability of ICT
Services Quarter
>99% security
vulnerabilities
mitigated
Achieved
• 99.95% vulnerabilities
mitigated
Percentage of ICT
services offerings
identified implemented
(additional innovations)
Annual
>80% ICT
services offerings
identified
implemented
N/A Achieved
• Public Web design upgrade
• Contact centre and facilities
case management on
Microsoft CRM
• Server and systems
upgrades and ongoing
software threat analysis
• User equipment replacement
Celebrating 129 years
Thank You