Development Project Design & Services Ltd.
(DPDS)
Government of the People’s Republic of Bangladesh
Planning Commission
Programming Division
ECRRP: PCMU
Consultancy Services for
Emergency 2007 Cyclone Recovery and Restoration Project (ECRRP) Component-E: Monitoring & Evaluation of Project Implementation Progress & Impact
QUARTERLY
PROGRESS REPORT
(ECRRP)
FY2016-2017
SEPTEMBER-2016
une-2016
EMERGENCY CYCLONE RECOVERY AND RESTORATION PROJECT Component-E: Monitoring and Evaluation of Project Implementation Progress and Impact
Address: House# 11, Flat# 2C, Road# 04, Banani DOHS, Dhaka-1206, Tel: 8713484, Cell: 01713040859, Fax: 9834911 e-mail: [email protected]
DPDS
To
The Director General/ Project Director,
PCMU, ECRRP,
Programming Division,
Planning Commission,
Ministry of Planning.
Date : 17.10.2016 Your Ref : Nil Our Ref : ECRRP-M&E/QPR/151 Dealt by : M&E Consultants Team Subject : Consolidated Quarterly Progress Report of ECRRP for the Quarter July to > September, 2016. . ....... .. .
Dear Sir, In fulfillment of the contract agreement signed between PCMU and the Consulting Firm DPDS on 16 September, 2014 for rendering services for the Second Spell M&E Consultancy works under ECRRP, please find herewith 2(two) copies of the Consolidated Quarterly Progress Report of ECRRP[July- September, 2016]. Regards.
Sincerely yours,
A.H.M.Mahbubur Rahman Team Leader, M&E Consultants, ECRRP
Encl.:- Consolidated QPR of ECRRP for the Quarter July-September, 2016. 2 copies
EMERGENCY CYCLONE RECOVERY AND RESTORATION PROJECT Component-E: Monitoring and Evaluation of Project Implementation Progress and Impact
Address: House# 11, Flat# 2C, Road# 04, Banani DOHS, Dhaka-1206, Tel: 8713484, Cell: 01713040859, Fax: 9834911 e-mail: [email protected]
DPDS
Copy of the Consolidated Quarterly Progress Report of ECRRP [July-September, 2016] is
forwarded for kind perusal to:-
1. Mr. Tariq-ul-Islam, Secretary, Planning Division and the Chairman of the Project Steering
Committee, ECRRP.
2. Mr. Md. Anwar Hossain, Deputy Secretary, WB Section 7, ERD, Dhaka.
3. Project Director, ECRRP, DDM Part, Dhaka.
4. Project Director, ECRRP, LGED Part, Dhaka.
5. Project Director, ECRRP, BWDB Part, Dhaka.
6. Ms. Swarna Kazi, TTL- ECRRP, World Bank, Dhaka.
7. Managing Director, DPDS, Dhaka.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | i
Abbreviations and Acronyms
BCCRF Bangladesh Climate Change Resilience Fund
BRE Brahmaputra Right Embankment
BWDB Bangladesh Water Development Board
CBO Community-Based Organization
CEIP Coastal Embankment Improvement Program
CP Contract Package
CPP Cyclone Preparedness Program
CRW Crisis Response Window
D&S Design and Supervision
DAE Department of Agricultural Extension
DLS Department of Livestock Services
DMC Disaster Management Committee
DDM Department of Disaster Management
DMRF Disaster Management Response Fund/Facility
DNA Damage and Needs Assessment
DoE Department of Environment
DoF Department of Fisheries
DPP Development Project Proposal
ECC Environmental Clearance Certificate
ECRRP
EIA
Emergency 2007 Cyclone Recovery and Restoration Project
Environmental Impact Assessment
EoP End-of-Project
ESM Environmental Supervision Manual
EMF Environmental Management Framework
EMP Environmental Management Plan
FAO Food and Agriculture Organization
FFS Farmer Field School
FG Farmers Group
FY Fiscal Year
GoB Government of Bangladesh
GFDRR Global Facility for Disaster Reduction and Recovery
HH Household
ICR Implementation Completion Report
IDA International Development Association
IEE Initial Environmental Examination
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | ii
IFM Integrated Farm Management
JDLNA Joint Damage, Loss and Needs Assessment
LGED Local Government Engineering Department
M&E Monitoring and Evaluation
MLGCRD Ministry of Local Governments, Cooperatives and Rural Development
MoA Ministry of Agriculture
MoFDM Ministry of Food and Disaster Management
MoFL Ministry of Fisheries and Livestock
MoP Ministry of Planning
MoWR Ministry of Water Resources
MTRR Mid-Term Review Report
NGO Non-Government Organization
OJT On-the-Job Training
PCMU Project Coordination and Monitoring Unit
PD Project Director
PDO Project Development Objective
PIA Project Implementation Agencies
PMF Process Monitoring Form
PMlS Project Monitoring Information System
PSC Project Steering Committee
RAP Resettlement Action Plan
RBIP River Bank Improvement Program
RDPP Revised Development Project Proposal
SJK Sokoler Jannya Kallyan
SMP Social Management Plan
S/RPF Social/Resettlement Policy Framework
SUK Shawdesh Unnayan Kendra
UAO Upazila Agriculture Officer
UARIC Upazila Agricultural Rehabilitation and Implementation Committee
UFRIC Upazila Fisheries Rehabilitation and Implementation Committee
ULO Upazila Livestock Officer
ULRIC Upazila Livestock Rehabilitation and Implementation Committee
VOSD Voluntary Organization for Social Development
WB World Bank
WCS Water Control Structure
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | iii
Executive Summary
Cyclone Sidr hit Bangladesh on 15 November 2007 resulting in loss of lives and properties and extensive damage to infrastructure. A multi sectoral umbrella project named ECRRP was taken up in the year 2010 with the PDO “To support GoB efforts to facilitate recovery from the livelihoods and infrastructure caused by Cyclone Sidr and to build long term preparedness through strengthened disaster risk management.” ECRRP has six Components, namely i) Component A- Recovery of Agricultural Sector and Improvement Program; ii) Component B- Reconstruction and Improvement of Multi-Purpose Shelters; iii) Component C: Rehabilitation of Coastal Embankments; iv) Component D.1: Long-Term Disaster Risk Management Program; v) Component –E: Monitoring & Evaluation of Project impact and vi) Component F: Project Management, Technical Assistance, Strategic Studies and Training, and Emergency Support for Future Disasters.
The activities of the Project virtually commenced in the year 2010. Component A: Agriculture (Crops, Livestock and Fisheries) has completed its assignment successfully by June 2014 supervised by FAO under a contract with PCMU and active support from the respective Agencies, DAE, DLS and DoF. The works of other agencies, BWDB and LGED will continue up to December 2017 and that of DDM is expected to continue up to December 2015.
The M&E Consultancy contract between PCMU and SMEC International will also came to an end by June 2014. Since the implementation of the project has been extended up to December 2017 with additional financing, a contract was signed with DPDS on 16 September 2014 to continue with the second spell of M&E Consultancy services. The second spell M&E consultants commenced works on 17 September 2014.
Component A – Recovery of Agricultural Sector and Improvement Program
i) Component Accomplishment
As already mentioned that all activities of Component A of ECRRP have been closed on 30 June 2014.
Under Crop Subcomponent, 241,558 HHs [Beneficiaries on Horticulture, Boro Rice seeds, Aus Rice seeds, T. Aman Rice seeds, Pulse seeds, Till seeds, Five new crops and LLP] have been benefitted against the target of 224,000 HHs. The achievement is about 108%. Details are given in Table 2-1 in Chapter 2- Agriculture.
Under Fisheries subcomponent, 37,089 HHs [Carp, Bagda/Tilapia, Galda, Mechanised boats and Seine nets] have been benefitted against the target of 33,000 HH. The achievement is about 139%. Details are given in Table 2-2 in Chapter 2-Agriculture.
Under Livestock subcomponent, 37,928 HHs [Chicken, Ducks, Goats, Sheep and Cow/ Buffalo] have been benefitted against the target of 26,700 HHs. The achievement is 112%. Details are given in Table 2-3 in Chapter 2- Agriculture.
The crops/aquaculture/capture-fishery/livestock input packages provided to beneficiaries, innovative crop cultivation, aquaculture, and livestock rearing practices were introduced and promoted through trainings and hands-on instruction as well as provision of mechanized farming implements and support farm inputs.
Majority of the beneficiaries opined during last Project Evaluation 2014 that the several improved and innovative variety interventions, training and extension support as provided under different sub components of Component A of ECRRP were very helpful.
As of close of Component A in June 2014, the overall financial achievement is 96.95% of the reallocated budget out of which achievements in Crop, Livestock and Fisheries sub components are 97.30%, 99.30% and 93.80% respectively.
As implementation of ECRRP will continue up to 2017, the independent M&E Consultants will still follow up the impact of the Component A interventions (mostly contributes on the improved livelihood standards of the affected persons) on the beneficiaries through periodic consultation process and the last Impact Assessment Survey at 2016 .
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | iv
Component B: Reconstruction and Improvement of Multi-Purpose Shelters
Component Accomplishment and Target Achievement
As of September 2016, 45 out of 50 new school-cum-shelters under Phase I have been reported to be 100% complete and the financial progress is 99%. Under Phase II, 308 new school-cum-shelters have been targeted. 184 nos. new shelters have been completed and the corresponding financial progress is 99%. Total 229 nos. newly completed shelters will provide accommodation for 343,500 persons against the target of 353 new shelters that would accommodate 529,500 persons.
All the 240 existing school-cum-shelters targeted for improvement under Phase I have been completed. Though these improved shelters will not virtually increase accommodation capacity, except vertical and horizontal extension ones, but will provide improved facilities in terms of water supply, sanitation, electricity by installation of solar panel, storage of goods, maternity facilities etc. The 65 shelters having horizontal and vertical extensions in existing shelters will provide additional accommodation for 66,000 persons.
All 219 sites for improvement under Phase II (30 in Khulna, 27 in Patuakhali, 18 in Pirojpur, 10 in Satkhira, 25 in Bagerhat, 8 in Jhalokathi, 48 in Bhola, 36 in Barguna & 17 in Barisal districts) have been identified and contract awarded. Repair/improvement activities in 10 CPs covering 220 repair shelters in Pirojpur, Jhalokathi, Khulna, Patuakhali, Satkhira, Bagerhat and Barisal districts started in Mid-July 2014. 168 nos out of 219 nos have been completed. Itemized physical progress is 98% and financial progress is 91%.
Improvement of communication networks to shelters has a total target of 350 km. Item physical progress in 69 km under phase I is 100% while disbursement is 98%. On the other hand, item physical progress in 154 km under phase II is 100% while disbursement is 99%. 104 km of shelter connecting road under AFII has been taken up where physical progress is 42% and corresponding financial progress is 34%.
In the revised targeted 15 killas, overall physical progress on earthworks in 15 killas is 100% and disbursement is 92%. For concrete works, overall physical progress in the above 15 killas is 90% and disbursement is 83%.
Component B Accomplishment.
New School cum Shelters June 2016 September 2016
Total target: 353 nos.
Completed: 224 nos. 229 nos.
Ongoing: 128(Av 36%) 123 nos.(40.51%)
Yet to be taken up: 1 no.(Dropped) 1 no.(Dropped)
Repair/ Improvement of Existing Shelters
Total target: 460 nos.
Completed: 393 nos. 408 nos.
Ongoing: 64 nos. (Av. 97%) 49 nos. (Av. 91%)
Yet to be taken up: 3 nos. (Dropped) 3 nos. (Dropped)
Improvement of Communication Network
Total target: 350 km.
Completed: 206 km. 223 km
Ongoing: 121 km. (Av. 36%) 104 km (42%)
Yet to be taken up: 23 km. 23 km.
Killas
Total Target: 15 nos.
Earthwork 15 nos.(100%) 15nos. (100%)Concrete work. 15 nos.(Av. 88%) 15 nos. (Av. 90%)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | v
Cumulative Progress June 2016 September 2016
Physical 74% 77%
Financial Tk. 126,682.11 lac Tk.128,751.46 lac
Physical Work: Quarterly Target & Achievement (FY 2016-2017)
Agency: Component B- LGED (ECRRP)
Financial: Quarterly Target & Achievement (FY 2016-2017)
Agency: Component B-LGED (ECRRP)
Item Target as per Restructuring
Completed up to June,2016
Cumulative Target & Achievement - FY2016-2017
Annual Target
Quarter
1st 2nd 3rd 4th
New School cum Shelter
353 Nos. 224 Nos. 128 Nos.
Target 32 Nos. 64 Nos. 96 Nos. 128 Nos.
Achievement
5 nos=100%
123 nos.= Av.40.51%
Improvement of Existing Shelter
460 Nos. 393 Nos. 64
Nos.
Target 16 Nos. 32 Nos. 48 Nos. 64 Nos.
Achievement
15- 100%
49 -91% (Avg.)
Improvement of Communication Network
350 Km. 206 Km. 144 Km Target (36 Km 72 Km 108 Km (144 km
Achievement
16.36km -100%
104 km -42.16%
Killas 15 Nos. 15 Nos. Earthwork -(100%)
RCC work -(88%)
15 nos.
RCC work: (12%)
Target RCC work: 3 % RCC work: 12%
Achievement
RCC work: 2%
Target as per RDPP
Spent up to June,2016
Annual Target
FY 2016-2017
Cumulative Financial Target & Achievement for FY2016-2017
Quarter
1st 2nd 3rd 4th
BDT 195,170.00 lac.
BDT Tk. 126,682.11 lac
BDT 25,100.00 lac
Target BDT 3,000.00 lac
BDT 9,000.00 lac.
BDT 16,100.00 lac
BDT 25,100 lac
Achievement
BDT 2,069.35 lac.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | vi
Component C: Rehabilitation of Coastal Embankments
Project Accomplishment and Target Achievement
As of end of September 2016, rehabilitation/construction of embankments in 16 polders out of 1st targeted 19 polders has been completed. These 16 polders are: (i) Polders 47/5 and 52/53B in CP 01; (ii) Polders 55/1, 55/2C and 55/4 in CP 04; (iii) Polders 46, 52/53A, 54/A and 47/1 in CP 05; (iv) Polders 44(P) & 47/4 in CP 06; (v) Polder 42 in CP 07; (vi) Polders 39/1D and 40/1 in CP 10; and (vii) Polders 55/2B & 50/51.
Due to poor performance, contracts of CP2 (Polders 41/6B & 41/7B) and CP3 (Polder 39/2A) had been terminated by BWDB with imposition of penalty on 5th September 2013. Incomplete works of CP2 & CP3 and additional works in Polder 52/53B have been included in CP18.
As of end of September 2016, the overall physical progress of rehabilitation/improvement activities in the polders are as follows:
Component C Accomplishment June 2016 September 2016
Total Target for Rehabilitation: 29 nos. Polders
Polders Completed: 16 nos. 16 nos.
Polders in progress: 3 nos. (Av.70%) 3 nos. (Av 71%)
7 nos. (Av.65%) 7 nos. (Av. 66%)
3nos. (Av.25%) 3 nos. (Av. 26%).
Cumulative Progress
Physical 72.57% 73.26% Financial Tk. 47,134.46 lac Tk. 47,134.46 lac
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | vii
Physical Work: Quarterly Target & Achievement (FY 2016-2017) Agency: Component C-BWDB (ECRRP)
Financial: Quarterly Target & Achievement (FY 2016-2017)
Agency: Component C-BWDB (ECRRP)
Item Target as per Cost Restructuring program
Completed upto June,2016 Annual
Target
FY2016-2017
Cumulative target & achievement - FY2016-2017
Quarter
1st 2nd 3rd 4th
Embankment
502 Km 260 Km.(100%)
184 Km((61%)
58 km(100%)
184 km(39%)
Target 58km (10%) 184km (45%)
58km(25%) 184km(60%)
5 8km(60%) 184km(80%)
. 58km(100%) 184km(100%)
Achievement
WaterControl Structure
317 Nos. 129 Nos.(100%)
164 Nos.(68%)
24 nos. (100%)
164nos(32%):
Target 24nos. (10%)
164 Nos. (40 %)
24 nos.(30%)
164 Nos. (65 %)
24 nos.(70%)
164 Nos. (80 %)
24nos. (100%)
164 Nos. (100 %)
Achievement
Protective Works
19,000 m 6,590 m(100%)
11,670 m(46%)
740m(100%)
11,670 m
( 54%)
Target 740m(5%)
11,670 m
(60%)
740 m(25%)
11,670 m (70%)
740 m(60%)
11,670 m (80%)
740m(100%)
11,670m (100%)
Achievement
Target as per RDPP
Spent up to June,2016 Annual
Target
FY 2016-2017
Cumulative Financial Target & achievement for FY2016-2017
Quarter
1st 2nd 3rd 4th
BDT 75,050.00 lac
BDT 47,134.46 lac
BDT 14,580.00 lac
Target
Tk.100.00 lac.
Tk.1,580.00 lac
Tk.6,580.00 lac.
Tk.14,580.00 lac.
Achievement
-
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | viii
Component D.1: Long-Term Disaster Risk Management Program
Project Target and Accomplishment.
The objectives of Subcomponent D.1, among others are:
(i) enhanced DDM‟s capacity for designing, standardizing and implementing a post-disaster damage and needs assessment (DNA), across all concerned government departments, and at various administrative levels, down to the district and upazila;
(ii) (ii) detailed, national level multi-hazard risk and vulnerability assessment, modelling and mapping at various levels down to the district and upazila; and
(iii) strengthened and enhanced emergency preparedness in 12 severely cyclone affected districts and upazila.
To achieve the above objectives, DDM planned to: a) engage Specialists to undertake MRVA and DNA studies, b) procure emergency search and rescue equipments, c) procure emergency vehicles and office equipments and d) undertake extensive trainings of the related stakeholders.
As of September 2016, progress status of component D.1 is summarized below:
Procurement of Emergency Search & Rescue Equipment and Office Equipment has been completed. Major training program has also reported to be completed.
The following activities are ongoing:
(i) MRVA, Modelling and Mapping: The MRVA Consultants submitted Draft Final Report on MRVA, Modelling and Mapping on December 2014. These were duly reviewed by the Standing Technical Committee. Draft Final Report had been submitted on 21 June 2015. In a meeting held on 21 December 2015, the Technical Advisory Committee accepted the reports with some recommendations. The MRVA reports were accepted with some recommendations. The final reports covering the recommendations is reported to be in the press for printing and expected to be published in October 2016.`
ii) Software Update and Integration to DNA Updating and up-gradation of the DNA software to examine compatibility of satellite information using DNA software with Real Time Information, make the software bi-lingual and develop Mobile Apps: Contract has been awarded on August 02, 2016. Progress of work is 40% as of September 30, 2016.
iii) Development of Digital Elevation Model. The DEM issue is under process with SOB and is expected to be finalized by mid October 2016.
iv) Preparation of Multi-hazard Risk Atlas. Editing of Multi-hazard Risk Atlas is going on. The final product is expected to be received by October 15, 2016.
v) Geo-Node Database. A meeting was held with Bangladesh Computer Council for integrating GIS database in geo node. The work with BCC is under process.
vi) Assessment of Component Impact. Assessment indicators and baseline status has been finalized. The impact evaluation is under process.
Cumulative Annual Progress June 2016 September 2016
Physical 96% 97% Financial Tk. 7,428.43 lac Tk. 7,490.00 lac
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | ix
Component E: Project Monitoring, Evaluation and Impact Assessment
At the end of M&E Consultancy contract with SMEC International Ltd. and Associate Firms on 30 June 2014, the second spell M&E Consultancy contract has been signed with DPDS, an associate local firm of SMEC International on 16 September 2014. The second spell consultancy services have commenced with effect from 17 September 2014.
The major tasks performed by the M&E Consultants since deployment under the second spell consultancy contract are briefly summarised below:
M&E Publications as of September 2016.
1. Inception Report The Final Inception Report of the second spell M&E consultancy services was circulated on 12 November 2014.
2. Consolidated Progress Reports
6 nos. Quarterly Progress Reports (September- December 2014 & January- March 2015, July –September 2015, October- December 2015, January- March 2016 and July- September 2016)) and 2 nos. Annual Progress Report (June 2015 and June 2016) have been published by the M&E Consultants till date.
3. Project Evaluation Report. In order to prepare the Project Evaluation Report 2014, the M&E Consultants undertook field survey (HH, FGD and KII) on 12 November 2014 and continued up to 23 November 2014. DPDS hired a renowned private social survey Firm “Serve The People” to assist the M&E Consultants in this regard.
The Project Evaluation Report 2014 was published and circulated to all concerned on 09 February, 2015. The presentation of the evaluation report was made on 22 February 2015 in the PCMU office.
The Final Project Evaluation Report of ECRRP is expected to be taken up by the M&E Consultants by December 2016 and published by February 2017.
Review and Clearance of Social Assessment Reports and Environmental Assessment Reports
The M&E Consultants review, update and recommend clearance of SA and EA reports of different packages of civil works undertaken by LGED and BWDB. The status of review and clearance is shown below:
Review of SA Reports
LGED: SA reports of 121 nos. packages have been cleared out of 123 nos. received. Comments were given for updating of 2 nos. of killa packages.
BWDB: SA reports of 26 nos. polders have been cleared out of 27 nos. received. 1 no. report was found incomplete. Comments were given to update the incomplete report of Polder No.39/1B.
Review of EA Reports
LGED: EA reports of 130 nos. packages have been cleared out of 130 nos. received.
BWDB: EA reports of 26 nos. polders have been cleared out of 28 nos. received. Comments were given to update EA reports of 2 nos. polders.
Field Visit Report
In the 1st quarter of FY2016-2017, one field visit was undertaken by the M&E Consultant in order to a) monitor, evaluate and track project progress, inputs, outputs and outcomes, b) oversee compliance of social and environmental safeguards and c) observe overall transparency and governance during project implementation.
The visit was undertaken from 24 September to 28 September 2016 to different sites of LGED and BWDB. The field visit report for LGED was circulated to all concerned vide M&E # ECRRP-E(M&E)/FVR/LGED/148 dated 03.10.2016.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | x
In the wake of the monsoon, the field is still moist and unfavourable for physical works of BWDB. However, contractors have started re-mobilizing labours to different work sites of package nos. 18, 19 and 20. The preparation of package #20 appeared to be good.
Component F: Project Management, Technical Assistance, Strategic Studies and Training, and Emergency Support for Future Disasters
PCMU in cooperation with the M&E Consultant is not only coordinating the M&E of ECRRP components‟ inputs, outputs and outcomes but is also responsible for ensuring the efficiency and effectiveness of the processes underlying the design and implementation of such processes as in the: (i) identification of studies for establishing a financing facility to fund recovery from disaster in Bangladesh; and (ii) identification of strategic studies and other studies/pilot projects, such as updating the strategy for disaster shelters and studies for improving water management in the coastal zone due to climate change. Specific activities of PCMU are listed in sub-component F.1 to F.5.
PCMU has been performing its assigned responsibilities quite satisfactorily.
Project Financial Statement
The total Project funding according to approved RDPP is Tk.31, 0532.35 million. Component wise RDPP provision including additional funding, financial achievement up to June2016.ADP allocation for FY2016-2017, financial achievement as of September 2016 (FY2016-2017) is given Table ES-1 below
Table ES-1: Project Financial Progress up to September -2016
PIA/ Component/
Subcomponent
Approved Prioject Cost Expenditure up to June -
2016 (in lac Taka)
ADP Allocation in FY 2016-2017 (in lac Taka)
Expenditure up to
September, 2016 (FY2016-
2017) (in lac Taka)
Cumulative Expenditure up to September -2016
PA+Grant (US$ in million)
Total Cost BDT: (in lac Taka)
(in lac Taka)
(% of Approved Revised
Cost)
FAO
DAE A.1: Crops
27.80 10,997.31 10,720.83 –– –– 10,720.83 97.49%
DoF A.2: Fisheries 5,989.54 5,782.80 –– –– 5,782.80 96.55%
DLS A.3: Liivestock 6,889.50 6,712.99 –– 6,712.99 97.44%
LGED B: Cyclone Shelters
201.45 195,170.00 126,682.11 25,100.00 2,069.35 128,751.46 65.97%
D3: Study of new shelters
-
BWDB C: Rehabilitation of coastal embankments
83.26 75,050.00 47,134.46 14,580.00 70.00 47,204.46 62.90%
D2: Study of CEIP & RBIP
-
DDM D1: Improving disaster preparedness
20.82 7,744.00 7,428.43 209.00 62.23 7,490.66 96.73%
PCMU E&F: M&E of ECRRP & Project Management
5.30 13,288.00 4,938.44 500.00 48.39 4,986.83 37.53%
Total 338.63 315,128.35 209,400.06 40,389.00 7,204.18 211,650.03 67.16%
As of September 2016 Cumulative weighted average Physical Progress of ECRRP : 78.16%
Cumulative Financial Progress : 67.16%.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | xi
Consultancy Services for
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP) Component-E: Monitoring & Evaluation of Project Implementation Progress & Impact
Quarterly Progress Report FY 2016 – 2017, September - 2016
Table of Contents
Executive Summary ................................................................................................................................................................ iii
1. Introduction ..................................................................................................................................................................... 1
1.1 Background ............................................................................................................................................................. 1
1.2 Project Location ...................................................................................................................................................... 2
1.3 Project Funding ....................................................................................................................................................... 2
1.4 Monitoring and Evaluation of ECRRP Impact ....................................................................................................... 3
2. COMPONENT A – RECOVERY OF AGRICULTURAL SECTOR AND IMPROVEMENT PROGRAM...................... 5
2.1 Background ............................................................................................................................................................. 5
2.1.1 Component Objective .................................................................................................................................. 5
2.2 Implementation Progress: Component A ............................................................................................................... 5
3. COMPONENT B – RECONSTRUCTION AND IMPROVEMENT OF MULTIPURPOSE SHELTERS ..................... 16
3.1 Background ........................................................................................................................................................... 16
3.1.1 Component Objective ................................................................................................................................ 16
3.1.2 M&E of the Component ............................................................................................................................. 16
3.2 Component B Targets........................................................................................................................................... 16
3.2.1 Physical Targets ........................................................................................................................................ 16
3.2.2 Financial Targets ....................................................................................................................................... 17
3.3 Component B Annual Work Plan for FY 2016 – 2017 ........................................................................................ 17
3.4 Component B: Process & Progress ..................................................................................................................... 17
3.4.1 Process Monitoring- Pre-construction Activities....................................................................................... 17
3.4.2 Component B: Progress Monitoring ......................................................................................................... 25
4. COMPONENT C – REHABILITATION OF COASTAL EMBANKMENTS ................................................................. 37
4.1 Background ........................................................................................................................................................... 37
4.1.1 Component Objective ................................................................................................................................ 37
4.1.2 M&E of Component ................................................................................................................................... 37
4.2 Component C Targets .......................................................................................................................................... 37
4.2.1 Physical Target .......................................................................................................................................... 37
4.2.2 Financial Target ......................................................................................................................................... 38
4.3 Component C: Process and Progress ................................................................................................................. 38
4.3.1 Process Monitoring .................................................................................................................................... 38
4.3.2 Component C: Progress Monitoring ......................................................................................................... 40
5. COMPONENT D – LONG-TERM DISASTER RISK MANAGEMENT PROGRAM ................................................... 43
5.1 Background ........................................................................................................................................................... 43
5.1.1 Component Objective ................................................................................................................................ 43
5.1.2 M&E of Component ................................................................................................................................... 43
5.2 Component D.1: Disaster Risk Mitigation and Reduction- Targets and Progress ............................................. 43
5.2.1 Subcomponent D.1: Targets .................................................................................................................... 43
5.2.2 Component D.1: Progress [DDM] ............................................................................................................. 44
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | xii
5.3 Subcomponent D.2: Preparation of Future Projects for River Bank Improvement, and Coastal Embankment Improvement Programs ........................................................................................................................................ 47
5.3.1 Subcomponent D.2: Preparation of Future Projects for River Bank Improvement, and Coastal Embankment Improvement Programs ...................................................................................................... 47
6. COMPONENT F – PROJECT MANAGEMENT, TECHNICAL ASSISTANCE, STRATEGIC STUDIES AND TRAINING, AND EMERGENCY SUPPORT FOR FUTURE DISASTER .............................................................. 48
6.1 Component Objective ........................................................................................................................................... 48
6.2 Component Progress ............................................................................................................................................ 48
6.3 Project Financial Statement ................................................................................................................................. 49
7. COMPONENT E – M&E of Project Impact ................................................................................................................. 50
7.1 Scope of Works ..................................................................................................................................................... 50
7.2 Comprehensive M&E Framework for ECRRP ..................................................................................................... 50
7.3 Tracking key indicators (input, output, outcome and operational risks) ............................................................. 51
7.3.1 Compliance Report on Operational Specific Risk Mitigation ................................................................... 51
7.4 Supervision in the Implementation and Compliance of the EMF and S/RPF .................................................... 51
7.4.1 Review and Supervision of EMF ............................................................................................................... 51
7.4.2 Review, Clearance and Supervision of S/RPF ........................................................................................ 54
7.5 Conduct Survey and preparation of Annual Project Evaluation Report 2014 .................................................... 57
7.6 Field Visits ............................................................................................................................................................. 57
7.7 Follow up of Key Agreed Actions ......................................................................................................................... 57
7.8 Preparation and Submission of Reports .............................................................................................................. 57
7.9 Utilization of Consultancy Inputs in Man-Months ................................................................................................ 58
Annex 1: Project Implementation Arrangements of ECRRP and Project Area Coverage ......................................... 59 Annex 3: Component B Annual Work Plan and process Monitoring .......................................................................... 63 Annex 4A: Monitoring Form PMF-C2: Process Monitoring – Polder (29 Polders) ...................................................... 91 Annex 4B: Monitoring Form PMF-C3: Polder Embankment Construction/ Rehabilitation Progress Monitoring (29 Polders) .......................................................................................................................................................................... 95 Annex 5: Subcomponent D.1 Annual Work Program FY2016-2017 ........................................................................... 98 Annex 6: Progress Monitoring - Sub-component D1: Disaster Risk Mitigation and Reduction ................................ 101 Annex 7: Quarterly Actual Vs. Target Values for Indicators of Outputs and Outcome [Per Framework] ................ 104 Annex 8: Result Framework and Monitoring .............................................................................................................. 110 Annex 9: Utilization of Consultancy Inputs in Man-Months ........................................................................................ 116
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 1
1. Introduction
1.1 Background
On 15 November 2007, cyclone Sidr struck the southwest coast of Bangladesh and moved inland breaching coastal and river embankments, flooding low-lying areas and causing extensive damage to lives and properties. The Emergency 2007 Cyclone Recovery and Restoration Project (ECRRP) supports a medium to long-term recovery program developed under the Joint Damage, Loss and Needs Assessment (JDLNA) that was undertaken after the occurrence of Cyclone Sidr on 15 November 2007. The project development objective (PDO) is to support Government of Bangladesh (GoB) efforts to facilitate recovery from the damage to livelihoods and infrastructure caused by cyclone Sidr and to build long-term preparedness through strengthened disaster risk management. Most importantly, ECRRP has supported the preparation and implementation of the first phase of a fifteen-year program for long-term disaster risk reduction.
ECRRP is designed such that its PDO will be achieved through the implementation of six project components, as follows:
Component A: Recovery of Agriculture Sector and Improvement Program.
Has four subcomponents – A.1: Support to the crops sub-sector; A.2: Support to the fisheries sub-sector; A.3: Support to the livestock sub-sector; and A.4: Support to community mobilization and facilitation and component management.
The primary implementing agency for this component is Food and Agriculture Organization (FAO) in coordination with the Ministry of Agriculture (MoA), and the Ministry of Fisheries and Livestock (MoFL).
Component B: Reconstruction and Improvement of Multipurpose Shelters
Includes four subcomponents – B.1: Construction of new shelters; B.2: Improvement of existing shelters; B.3: Improvement of communication network to shelters; and B.4: Design and construction supervision of shelters.
The Ministry of Local Governments, Cooperatives and Rural Development (MLGCRD), through the Local Government Engineering Department (LGED), is implementing this component.
Component C: Rehabilitation of Coastal Embankments
Has two subcomponents – C.1: Rehabilitation of coastal embankments; and C.2: Design and construction supervision of coastal embankments.
The implementing agency for this component is the Ministry of Water Resources (MoWR) through the Bangladesh Water Development Board (BWDB).
Component D: Long-Term Disaster Risk Management Program
Includes three subcomponents – D.1: Disaster risk mitigation and reduction; D.2: Preparation of future projects for River Bank Improvement, and Coastal Embankment Improvement Programs; and D.3: Preparation of future projects for disaster shelters and up-gradation of rural road network.
The Ministry of Food and Disaster Management (MoFDM), through the Disaster Management Bureau (DMB), is implementing sub-component D.1. Sub-component D.2 is being implemented by BWDB while sub-component D.3 by LGED.
Component E: Monitoring and Evaluation of Project Impact
The Ministry of Planning (MoP), through the Project Coordination and Monitoring Unit (PCMU), is implementing this component.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 2
Comp. A8%
Comp. B59%
Comp. C25%
Comp. D16%
Comp. E & F 2%
Figure 1-2 Percent Distribution of Funds by Component
0.00
50.00
100.00
150.00
200.00
250.00
Comp. A
Comp. B
Comp. C
Comp. D1
Comp. E & F
Additional 11.80 159.45 49.26 12.82 -3.70 229.63
Original 16.00 42.00 34.00 8.00 9.00 109.00
Total Project Funding
US$338.63M
US$27.80M
US$201.45M
US$83.26M
US$20.82M
US$5.3M
Pro
ject
Fu
nd
s (U
S$ m
il)Figure 1-1 Project Funding by Component
Component F: Project Management (Subcomponent F1), Consulting Services (F2), Strategic Studies (F3), Technical Assistance and Training (F4), and Emergency Support for Future Disasters (F5).
Besides coordination and monitoring of overall ECRRP activities, PCMU is also responsible for implementing Component F.
The Project Steering Committee (PSC) provides oversight and coordination in implementation of the Project. The PCMU, established in MoP, coordinates and manages the Project. A graphical presentation of the project implementation arrangements of ECRRP is shown in Annex 1A.
1.2 Project Location
The geographic coverage of ECRRP includes 75 upazilas in 13 districts – i.e. 5 upazilas in Barguna District, 8 in Bagerhat, 6 in Pirojpur, 6 in Patuakhali, 7 in Bhola, 10 in Barisal, 4 in Jhalokhati, 10 in Khulna, and 7 in Sathkhira, 3 in Laxsmipur, 3 in Noakhali, 1 in Feni and 5 in Chittagong. A map of Bangladesh highlighting ECRRP project area is shown in Annex 1B, while the districts and upazilas covered by each component is indicated in tabular form in Annex 1C.
1.3 Project Funding
The original fund for ECRRP was US$111.96 million – US$109 million IDA credit and US$2.96 million grant provided by GFDRR. As per the latest RDPP approved by GoB in May 2014, the total project cost stands at US$398.06 million; GoB: 1.70 million, PA: 396.36 million [IDA credit US$324.00 million, BCCRF Grant US$25.00 million, GFDRR Grant US$2.96 million, KfW US$4.90 million and others US$39.50 million]. The revised project funding as per latest RDPP is US$338.63 million.
Figure 1-1 shows the revised component-wise allocation of project funds. The allocation for Component A is 27.80 million; Component B 201.45; Component C 83.26 million; Component D.1 20.82 million; and Component E and F 5.30 million.
As shown in Figure 1-2, the largest share of 59% of the total project fund is allocated to the reconstruction and improvement of multipurpose shelters (Comp. B); 25% to the rehabilitation of coastal embankments (Comp. C); 8% to the recovery of agriculture sector and improvement program (Comp. A); 6% to Long-Term Disaster Risk Management Program (Comp. D); and 2% to Project Management, Coordination and Technical Assistance (Comp. F) and Monitoring and Evaluation of Project Impact (Comp. E).
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 3
1.4 Monitoring and Evaluation of ECRRP Impact
To perform the Monitoring and Evaluation of Project Impact (Component E), an M&E Consultant Team supports the PCMU in undertaking oversight of M&E activities, and in providing necessary feedback to the Government, PSC, WB and implementing agencies on Project performance and impact of its various components, so that corrective actions can be undertaken in a timely manner. The first spell of the M&E Consultancy services for ECRRP commenced with effect from 01 March 2010. SMEC International Pvt. Ltd in association with DPDS Ltd and ACE Ltd was entrusted with the M&E tasks. The first spell consultants completed its job on 30 June 2014. The sequence of the conduct of the M&E tasks, and their interrelationships as developed during the first spell is shown in Figure 1-3. The same sequence will be followed in the second spell; however the sequential activities like “Development & Implementation of PMIS”, “Maintenance of PMIS” and “Establishment and maintenance of project information website” will not be addressed since these activities are not included in the second spell contract.
Due to additional funding, the project implementation period has been extended up to 31 December 2017. Most of the additional fund has been allocated to LGED and BWDB to restore and rebuild damaged infrastructure. Project activities on Component A- Agriculture to restore livelihood of the affected persons was completed on 30 June 2014.
The second spell of M&E Consultancy services has been entrusted to DPDS Ltd, a local associate of the first spell consultants. The second spell M&E consultants commenced its activities with effect from 17 September 2014 keeping continuity with the first spell activities.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 4
Legend
T Task
M&E consultant‟s responsibility
Collaboration – M&E Consultant
Implementing Agencies‟ Responsibility
Start
Review/refinement of results
framework & log frames
Establishment of Baseline
Information (1st Spell)
End
T4: Review reports on
IEE/EIA and RAP prepared
by implementing agencies
Development of M&E
Framework (1st Spell)
Development and
implementation of PMIS.
Establishment of Project
Information website (1st Spell)
Establishment of Baseline
Information (1st Spell)
Supervision of implementation
and compliance of EMF and
S/RPF
On- the –job training of
implementing agencies of
monitoring of project impacts
Internal M&E by Implementing Agencies: Track key indicators during implementation of components. Carry out process monitoring of components Preparation and
Submission of
component monthly,
quarterly and annual
reports to PCMU
Independent M&E by Consultant:
T1: Track key indicators during implementation
T2: Carry out process monitoring
of the Project.
T3: Recommended appropriate corrective actions and recommendation.
T5: Preparation and Submission of consolidated quarterly and annual progress reports to the PSC
On-the –job training of
implementing agencies
on use of PMIS of
monitoring of project
impacts
Maintenance of PMIS
Maintenance of Project information website. (1st Spell)
Mid-Term
PER -2013
202013
201320
132020
142013
2013
201320
13
PER -2014
PER -2016
Preparation of midterm
review Report (1st Spell).
T8: Preparation of
Implementation Completion
Report
End
Finalization of Key indicators
for inputs, outputs, outcome
and operational risks.
End
NoProject
Project Evaluation Report
(1st Spell).
T6: Project Evaluation
Report 2014
T7: Project Evaluation
Report 2016. Yes
No
Figure 1-3: Flowchart of M&E Tasks
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 5
2. COMPONENT A – RECOVERY OF AGRICULTURAL SECTOR AND IMPROVEMENT PROGRAM
2.1 Background
2.1.1 Component Objective
The objective of Component A was to provide agriculture (crop, livestock and fishery) recovery assistance, and introduce sustainable improvements to agricultural practices. These will be achieved through the following subcomponents:
Subcomponent A.1: Support to crop subsector – meant to promote improved production and marketing technologies in the sub-sector and finance a comprehensive technology package, model demonstrations of improved technologies and agronomic practices, and farmers knowledge through technical assistance and training to increase the long-term productivity of popular and new crops/varieties and encourage agricultural diversification in the affected area and improve resilience to face such disasters in the future.
Subcomponent A.2: Support to the fisheries subsector – to promote improved production and marketing technologies in the sub-sector and finance the provision of fisheries equipment and activities to support sustainability of fisheries resources, including and improved knowledge base on the status of coastal small-scale fisheries as well as rehabilitation, technical assistance and training related to improved aquaculture practice.
Subcomponent A.3: Support to livestock subsector – to promote improvements in the overall management and production practices in the sub-sector, and finance the emergency restoration of cold chain systems for vaccination delivery, stocking of improved goats and sheep and poultry and provision of livestock feed, introduction of improved grasses for animal fodder, technical assistance and training and general healthcare of animals, and construction of improved model dairy and poultry sheds. The focus would be on improved technologies and farmer knowledge about the livestock sector that is suitable for coastal areas.
Subcomponent A.4: Support to community mobilization and facilitation and component management – meant to facilitate the identification and support of formal and informal farmer/fishers‟ groups and production and marketing community-based organization (CBOs) to best deliver knowledge, goods and services under this component. It will also include, inter alia, an awareness/communication campaign and needs assessments directly with the targeted communities and farmer groups at the start of the project. This sub-component will also finance the operations of the Component Steering Committee (providing general oversight and coordination), and of the Component Management and Coordination Unit in Dhaka with two Component Implementation Cells in Barisal directly responsible for the implementation. It will include technical assistance (mostly national consultants), provision of office equipment and vehicles, and the establishment of a M&E system for the component.FAO was the implementing agency for Component A, in coordination with MoA and MoFL.
2.2 Implementation Progress: Component A
Implementation of the three sub-components (Crops, Livestock and Fisheries) under Component A was completed on 30 June 2014. The summary of accomplishments in the implementation of the three sub components of Component A under ECRRP are shown in following Tables:
Crop Sub component- Physical Progress Table 2-1, Figure 2-1, Figure 2-2;
Training and Capacity Building Table 2-4
Fisheries Sub component- Physical Progress Table 2-2, Figure 2-3, Figure 2-4;
Training and Capacity Building Table 2-5
Livestock Sub component- Physical Progress Table 2-3, Figure 2-5.
Training and Capacity Building Table 2-6
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 6
1) Physical Progress of Crop Sub Component:
Table 2-1: District/Upazilla-Wise Number of Crop Packages, Machineries, Equipment and Infrastructure Distributed as of june 2014
District Upazila Horticulture
package
(Nos. of
Packages)
Improved
Boro Rice
Seeds (Nos.
of
Packages).
Improved
Aus Rice
Seeds
(Nos. of
Packages).
T.Aman
Rice Seeds
(Nos. of
Packages).
Improved
Pulse Seeds
(Mungbean)
(Nos. of
Packages).
Improved
Maize
Seeds
(Nos. of
Packages).
Improved
Till Seeds
(Nos. of
Packages).
Five new crops (
khesari,
Cowpea,sunflow
er,watermelon&
Ground nut
(Nos. of
Packages).
Nerica
Rice
Seeds
(Nos. of
Packag
es).
Power
Tiller
(Nos.)
Power
Thresher
(Nos.)
Batch
Dryer
(Nos.)
Knapsack
Sprayer
(Nos.)
Foot
Pump
Sprayer
(Nos.)
Seed
Storage
Silos
(Nos.)
Low Lift
Pump
(Nos.)
Irrigation
infrastru
cture-
Lined
canal,
LLP
(Nos.)
USG
Applicato
r
(Nos.)
Instru-
ments
(Nos.)
Shoronkhola 2,628 760 2,000 1,800 2,200 200 100 2,350 5 52 18 2 32 85 1,362 36 20 42 132
Morelganj 5,656 4,200 4,000 2,200 3,500 200 100 1,275 5 178 93 6 123 278 3,304 89 39 167 492
Barisal Barisal Sadar 4,585 5,000 4,000 2,900 3,700 400 800 1,600 5 120 60 5 90 203 2,183 77 39 120 312
Jhalokhati Khathalia 3,372 900 5,800 1,700 3,500 600 800 1,900 5 74 34 3 46 122 1,376 44 20 66 192
Mathbaria 4,825 3,900 5,300 3,600 4,700 1,200 200 1,300 5 132 58 5 95 197 2,314 79 25 120 342
Bhandaria 3,532 425 5,400 1,200 1,700 300 550 1,300 5 81 35 3 63 143 1,516 45 14 84 222
Mirzaganj 2,702 325 3,800 1,550 3,000 100 100 1,900 5 74 31 3 50 116 1,450 45 15 58 192
Golachipa 5,412 1,775 2,600 3,150 3,300 300 700 2,350 5 170 93 6 134 297 3,278 87 30 166 522
Kolapara 3,818 725 2,200 2,850 2,200 300 250 4,950 5 112 47 4 73 174 2,062 64 24 95 282
Pathorghata 2,956 600 4,400 2,850 4,200 100 100 1,850 5 83 39 3 52 132 1,546 50 20 81 222
Barguna Sadar 4,058 585 4,000 1,900 2,900 100 100 1,900 5 112 56 5 83 194 2,333 74 45 114 312
Amtoli 4,058 530 4,000 3,450 2,700 100 100 500 5 124 59 5 90 201 2,333 76 45 117 312
Bamna 2,456 275 2,500 850 2,400 100 100 300 5 52 21 2 30 85 1,190 35 10 39 132
50,058 20,000 50,000 30,000 40,000 4,000 4,000 23,475 65 1,364 644 52 961 2,227 26,247 801 346 1,269 3,666
100% 100% 100% 100% 100% 100% 100% - 132% 100% 15% 100% 100% 154% 127% 99% - -
50,058 20,000 50,000 30,000 40,000 4,000 4,000 23,475 - 17,050 16,100 1,300 24,025 55,675 26,247 20,025 8,650 15,862 -
End-of-Project Target 50,058 20,000 50,000 30,000 40,000 4,000 4,000 - 1,034 644 351 961 2,227 17,063 631 351 - -
Number of Beneficiaries (HH)
Bagerhat
Pirojpur
Patuakhali
Barguna
Achievement as of end
June 2014.
as % of End-of-Project Target
Horticulture Package
Boro Rice Package
Aus Rice Package
T. Aman Rice
Package
Mungbean Package
Maize Package
Till Package
Balance of End-of -Project Target 0 0 0 0 0 0 0
Distributed During FY2013-2014 0 0 0 0 0 0 0
Distributed During FY2012-2013 0 0 0 17,300 0 0 0
Distributed During FY2011-2012 25,500 12,000 38,000 12,700 32,000 2,000 2,000
Distributed During FY2010-2011 24,558 8,000 12,000 0 8,000 2,000 2,000
0
10,000
20,000
30,000
40,000
50,000
Num
ber
of P
acka
ges
Figure 2-1 Progress in the Distribution of Crop Input Packages to Agricultural Farmer Beneficiaries (June 2014).
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 7
Short Description of Crop Packages per HH
Horticulture Package
Vegetable seeds 5 types
Watering Can 1 no.
Spade 1 no.
Fruit tree saplings 5 nos.
Composting chemicals 3 types
Aus/ T.Aman/ Boro Packages
Seed/ Fertilizer 5 kg/ Urea-15 kg, TSP-10 kg, MOP-12 kg
Hybrid Maize Package
Seed/ Fertilizer 4 kg/ Urea-75 kg, TSP-38 kg, MOP-37 kg, Gypsum-20 kg, Zinc Sulphate-4 kg & Boron-1 kg
Improved Til Package
Seed/ Fertilizer 1.5 kg/ Urea-15 kg, TSP-20 kg, MOP-8 kg, Gypsum-15 kg, Zinc Sulphate-1 kg and Boron-2 kg.
Mug Bean Package
Seed/ Fertilizer 5 kg/ Urea-6 kg, TSP-12 kg, MOP-5 kg.
Power Tiller
Power Thresher
Batch Dryer
Knapsack Sprayer
Low Lift Pump
Irrigation Infrastruct
ure
USG Applicator
Balance of End-of-Project Target 0 0 0 0 0 0 0
Distributed During FY2013-2014 527 275 0 259 450 94 567
Distributed During FY2012-2013 489 103 0 0 0 119 0
Distributed During FY2011-2012 20 219 52 527 251 114 702
Distributed During FY2010-2011 328 47 0 175 100 19 0
0
200
400
600
800
1,000
1,200
Nu
mb
er
of
Mac
hin
eri
es/
Equ
ipm
en
t
Figure 2-2 Progress in the Distribution of Farm Machineries, Equipment and Infrastructures to Farmer Groups of Crop Beneficiaries (june 2014).
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 8
Carp Package Bagda/Monosex Tilapia Package Galda Package
Balance of End-of-Project Target 0 0 0
Distributed During FY2013-2014 0 0 0
Distributed During FY2012-2013 10,286 3,850 0
Distributed During FY2011-2012 1,764 1,800 1,900
Distributed During FY2010-2011 3,500 650 1,100
0
2,500
5,000
7,500
10,000
12,500
15,000
Nu
mb
er
of
Pa
ck
ag
es
Figure 2-3 Progress in the Distribution of Fish Packages to Aquaculture Beneficiaries (June 2014) .
Physical Progress of Fisheries Sub Component:
Table 2-2: District/Upazilla-Wise Number of Fisheries Inputs Distributed as of end June 2014
Poma Jal
(Nos.)
Hilsha
Nets
(Nos.)
Seine
Nets for
FFS
(Nos.)
Agro-
processing
Equipment
(Per CBO)
(Nos.)
Shoronkhola 850 250 300 21 206 21 24 2
Morelganj 1350 1350 400 - - - 39 3
Barisal Barisal Sadar 1150 800 - - - - 39 3
Jhalokhati Khathalia 1100 400 100 - - - 26 2
Mathbaria 1500 500 250 - - - 49 3
Bhandaria 1200 350 250 - - - 31 3
Mirzaganj 900 300 200 - - - 11 3
Golachipa 1300 300 300 26 396 26 39 3
Kolapara 1450 400 200 18 203 18 48 3
Pathorghata 1225 300 150 19 204 19 37 2
Barguna Sadar 1300 200 350 - - - 38 2
Amtoli 1300 650 300 9 194 9 47 4
Bamna 925 500 200 - - 36 2
15,550 6,300 3,000 93 1,203 93 464 35
100% 100% 100% 100% 100% - 31%
15,550 6,300 3,000 639 3,609 639 11,600 438
15,550 6,300 3,000 93 - 93 - 113
Fishing GearDistrict Upazila Carp
Packages
(Nos of
Pacakge)
Bagda
Packages/
Monosex
Tilapia
(Nos of
Pacakge)
Galda
Packages
(Nos of
Pacakge)
Mechanized
Fishing Boat
and Safety
Equipment
(Nos.)
Number of Beneficiaries (HH)
End-of-Project Target
Achievement as of end June 2014
Bagerhat
Pirojpur
Patuakhali
Barguna
as % of End-of-Project Target
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 9
Mechanized Fishing Boat Poma Jal Hilsha Nets Seine Nets for FFs
Balance of End-of-Project Target 0 0 0 0
Distributed During FY2013-2014 58 1,203 58 464
Distributed During FY2012-2013 35 0 35 0
0
200
400
600
800
1,000
1,200
Nu
mb
er
of
Pa
ck
ag
es
Figure 2-4 Progress in the Distribution of Fish Packages to Capture Fisheries Beneficiaries (June 2014).
Short Description of Fisheries Packages per HH
Carp Package [Catla-50%, Ruhi-30%, Mrigel-20%]
- Fingerlings: 800 nos. - Lime: 20 kg - Fertilizer 5-10 kg [ Urea, TSP, MoP] - Fish feed 100 kg.
Bagda Package Beneficiary
- Bagda PL 2,400 nos. - Lime 20 kg - Fertilizer 5 kg - Bagda feed 50 kg
Tilapia Package Beneficiary
- Fingerlings 1,200 nos. - Lime 20 kg - Fertilizer 5-10 kg - Fish feed 50-100 kg
Golda Package Beneficiary
- Golda PL 800 nos. - Lime 20 kg - Fertilizer 5 kg - Shrimp feed 50 kgp
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 10
Chicken/Ducks (x 1000)
Goat/Sheep (x 100)
Cow (x 10)
Chicken Shed (x 100)
Goat/Sheep Shed (x100)
Cow Shed
Balance of End-of-Project Target 0.0 0.0 0.0 0.0 0.0 0.0
Completed During FY2013-2014 97.83 82.24 62.60 128.08 82.06 85.00
Completed During FY2012-2013 120.96 36.62 47.20 94.87 16.94 0.00
Completed During FY2011-2012 24.16 38.3 77.7 30.0 0.0 65
Completed During FY2010-2011 20.00 34.0 20.0 10.0 0.0 0
0
50
100
150
200
250
Nu
mb
er
of
An
ima
ls/S
he
ds
Figure 2-5 Progress in the Distribution of Animals and Sheds to Livestock Farmer Beneficiaries (June 2014).
Physical Progress in Livestock Sub component:
Short Description of Livestock Packages per HH
Cow/Buffalo Beneficiary 1 no.
Cow feed 150-225 kg
Buffalo feed 300 kg
Goat/ Sheep Beneficiary 2 nos.
Goat/ sheep feed 25-50 kg
Poultry Beneficiary 10 nos.
Poultry feed 50 kg
Table 2-3: District/Upazila-Wise Number of Livestock Inputs Distributed as of end June 2014
District Upazila Chicken
(Nos.)
Ducks
(Nos.)
Goats
(Nos.)
Sheep
(Nos.)
Cow/buffalos
(Nos.)
Buck
(Nos.)
Ram
(Nos.)
Chicken/
Duck Shed
(Nos.)
Goat/
Sheep
Shed
(Nos.)
Cow
Shed
(Nos.)
Poultry
Feed (MT)
Goat/ Sheep
Feed (MT)
Dairy
Feed
(MT)
Shoronkhola 4,000 8,000 334 910 125 34 10 1,200 644 7 60.00 22.48 15.00
Morelganj 4,540 23,460 658 1,210 225 58 10 2,800 968 7 140.00 27.88 18.75
Barisal Barisal Sadar 2,800 20,200 858 212 175 58 10 2,300 569 26 115.00 22.25 21.05
Jhalokhati Khathalia 3,140 11,860 1,062 379 75 22 1 1,500 730 7 75.00 32.63 11.25
Mathbaria 4,430 15,320 1,144 610 150 46 10 1,975 906 12 90.00 32.88 18.75
Bhandaria 4,070 15,930 1,190 64 125 46 10 2,000 656 13 100.00 24.83 18.75
Mirzaganj 3,780 9,920 923 302 100 23 2 1,370 625 13 67.50 24.35 15.00
Golachipa 2,740 21,010 1,558 4 225 58 4 2,375 812 12 95.00 25.63 18.75
Kolapara 3,580 18,920 458 1,421 225 58 20 2,250 978 10 90.00 34.33 26.01
Pathorghata 7,000 16,000 1,366 472 200 34 4 2,300 938 13 115.00 24.70 15.00
Barguna Sadar 3,000 18,000 850 214 150 46 10 2,100 558 7 95.00 20.05 18.75
Amtoli 3,000 26,750 1,068 910 225 58 20 2,975 1,028 12 120.00 33.33 27.60
Bamna 3,120 8,380 916 22 75 34 4 1,150 488 11 57.50 19.70 11.25
Total 49,200 213,750 12,385 6,730
2,075 575 115 26,295 9,900 150 1220 345 236
138% - - 112% 113% 100% 104% 79% 91%
2,075 575 115 26,295 9,900 1,500 24,400 6,892 1,367
1,500 - - 23,400 8,750 150 1,170 438 259
Bagerhat
Pirojpur
Patuakhali
Barguna
as % of End-of-Project Target
Number of Beneficiaries (HH)
234,000 17,500End-of-Project Target
Achievement as of end June -2014
26,295
262,950 19,115
109%
9,558
112%
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 11
2) Training and Capacity Building Crops
Table 2-4: Number of Crop Input Beneficiaries Trained, by Fiscal Year
FY2010-2011 FY2011-2012 FY2012-20131st Quarter
FY2013-2014
2nd Quarter
FY2013-2014
3rd Quarter
FY2013-2014
4th Quarter
FY2013-2014Total
No. of FFS established 68 150 125 8 - - - 351
No. of beneficiaries trained 3,400 7,500 6,250 400 - - - 17,550
Power Tiller No. of units delivered 300 402 222 105 - - 335 1,364
No. of beneficiaries trained on O&M 600 804 444 210 - - 670 2,728
Power Thresher No. of units delivered 52 299 - 293 - - - 644
No. of beneficiaries trained on O&M 156 598 - 586 - - - 1,340
Batch Dryer No. of units delivered 52 - - - - - - 52
No. of beneficiaries trained on O&M 208 - - - - - - 208
Knapsack Sprayer No. of units delivered 351 351 - 259 - - - 961
No. of beneficiaries trained on O&M 351 351 - 259 - - - 961
Foot Pump Sprayer No. of units delivered 750 1,252 - 225 - - - 2,227
No. of beneficiaries trained on O&M 750 1,252 - 225 - - - 2,227
USG Applicator No. of units delivered - 702 - 567 - - - 1,269
No. of beneficiaries trained on O&M - 1,404 - 567 - - - 1,971
Low-Lift Pump No. of units delivered 100 251 280 - 170 - - 801
No. of beneficiaries trained on O&M 200 502 560 - 240 - - 1,502
Irrigation Infrastructure No. of units constructed 19 173 86 - 3 56 9 346
Training of WUA members on On-Farm Water Management - 625 625 - 295 330 - 1,875
Block Level Facilitator
Trainining on HorticultureNo. of batches - - 14 - - - - 14
No. of facilitators trained - - 351 - - - - 351Documentation, Basic
Accounting and Book
Keeping TrainingNo. of batches - - - - - - 22 22
No of participants - - - - - - 703 703Cross-Training of C-FFS
members (34 C-FFS
trained on poultry and 20 C-
FFS on aquaculture)
No. of batches - - - - - - 34 34
No of participants - - - - - - 850 850
Training
FFS formation and training
for beneficiaries
Training and Capacity Building Fisheries
Table 2-5: Number of Fisheries Input Beneficiaries and Other Stakeholders Trained, by Fiscal Year
FY2010-2011 FY2011-2012 FY2012-20131st Quarter
FY2013-2014
2nd Quarter
FY2013-2014
3rd Quarter
FY2013-2014
4th Quarter
FY2013-2014Total
No. of FFS established 210 396 388 - - - - 994
No. of beneficiaries trained 5,250 9,900 9,700 - - - - 24,850
Training for FFS FacilitatorsNo. of stakeholders
trained100 50 51 - - - - 201
Boat Builders TrainingNo. of stakeholders
trained20 - 15 - - - - 35
ToT Course on Coastal Fisheries for
Officials
No. of stakeholders
trained- 23 25 - - - 25 73
Orientation for SP staffNo. of stakeholders
trained69 42 - - - - - 111
Workshop with DoF OfficialsNo. of stakeholders
trained25 30 - - - 25 43 123
Orientation on Data Collection
Process for Post Survey of
Aquaculture Activities
No. of stakeholders
trained- - 34 27 - - - 61
Exchange visit to Barisal Sadar &
Amtali to observe successful
aquaculture activities & sharing
knowledge & views with the
successful participants
No. of stakeholders
trained- - 55 - - - - 55
Training on O&M of FRB boat &
engine, book accounts operation &
savings, and use of safety
equipment.
No. of beneficiaries
trained- - 175 - 56 208 200 639
Cross-training of aquaculture FFS
members (100 A-FFS on horticulture
and 34 A-FFS on poultry)
No. of beneficiaries
trained- - - - - - 2,500 2,500
Training
FFS formation and training for
beneficiaries
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 12
Training and Capacity Building Livestock Table 2-6: Number of Livestock Input Beneficiaries and Other Stakeholders Trained, by Fiscal Year
FY2010-2011 FY2011-2012 FY2012-2013 1st Quarter
FY2013-2014
2nd Quarter
FY2013-2014
3rd Quarter
FY2013-2014
4th Quarter
FY2013-2014Total
No. of FFS established 435 441 467 - - 160 - 1,503
No. of beneficiaries trained 11,003 11,045 11,277 - - 4,000 - 37,325
Training for FFS FacilitatorsNo. of stakeholders
trained26 36 38 - 26 - - 126
Orientation for SP staffNo. of stakeholders
trained20 22 21 - - - - 63
Workshop with DLS OfficialsNo. of stakeholders
trained21 91 - - - 43 - 155
Orientation on Data Collection
Process for Post Survey of
Livestock Activities
No. of stakeholders
trained- - 31 22 - - - 53
Exchange visit to other Upazila
for sharing livestock activities and
sharing knowledge and views.
No. of stakeholders
trained- - 40 - - - - 40
Training on Solar refrigerator
operation and maintenance (30
FFS members & 10 UP
representatives)
No. of beneficiaries trained - - - - - 40 - 40
Training on Livestock Value
Chain Development (Milk and
Egg based food products
processing
No. of beneficiaries trained - - - - - 70 30 100
Cross-Training of L-FFS
members (100 L-FFS on
horticulture and 20 L-FFS on
aquaculture)
No. of beneficiaries trained - - - - - - 3000 3,000
Training
FFS formation and training for
beneficiaries
FAO submitted the “Implementation Completion and Results Report” for Component A on 24 June 2014. The report however, does not categorically mention with statistical figures about the total nos. of HHs benefitted under the Component. There is of course a mention in the Executive Summary that the nos. of beneficiary HHs is 230,325 under crop sub component, 37,925 under livestock sub component and 36,994 under fisheries sub component respectively. It is indeed difficult to calculate the exact nos. of beneficiaries as several beneficiaries HHs received multiple inputs.
From Table 2-1, Table 2-2 and Table 2-3, M&E Consultants found the nos. of beneficiary HHs as under:
Crops- 241,558 HHs [Beneficiaries on Horticulture, Boro Rice seeds, Aus Rice seeds, T. Aman Rice seeds, Pulse seeds, Till seeds, Five new crops and LLP]. Most of the Crops beneficiaries HHs were members of IPM/ICM Clubs and newly formed FFS who received multiple inputs from ECRRP.
Fisheries- 37,089 HHs [Carp, Bagda/Tilapia, Galda, Mechanised boats and Seine nets].
Livestock- 37,928 HHs [Chicken, Ducks, Goats, Sheep and Cow/ Buffalo].
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 13
Title name of the technology Definition of the technology (Measuring Criteria)
Introduction of Improved alternative rice varieties
Following improved rice varieties were disseminated/adopted over 13 project upazilas:
T Aman season:
o BR11: popular variety (weakly photosensitive, Y- 6.5 t/h) o BR22: Photo sensitive variety - suitable as late sowing after
flood o BR23: Photo sensitive variety - suitable as late sowing after
flood o BRRI dhan40: Saline tolerant o BRRI dhan41: Saline tolerant o BRRI dhan44: Variety suitable for non-saline tidal area o BRRI dhan46: Photosensitive variety, suitable for late
transplanting after flood o BRRI dhan51: Submergence tolerant, new variety o BRRI dhan52: Submergence tolerant, new variety o BINA dhan7: Early variety (110 days)
Boro Season: o BRRI dhan28: Early variety (140 days) o BRRI dhan29: popular variety (Yield - 7.5 MT/ha) o BRRI dhan47: Salt tolerant o BRRI dhan50: Basmati type (aromatic variety) o BINA dhan6: Tall plant type (120 cm) with strong Culm. o BINA dhan8: Salt Tolerant
T Aus season: o BR3: High yielding, suitable for Boro and T Aman o BR14: High yielding with awn o BRRI dhan27: suitable for tidal areas o BRRI dhan42: Moderate drought tolerant o BRRI dhan43: Moderate drought tolerant o BRRI dhan48: Alternate to BRRI dhan26 but non-sticky
Adaptation Trial of NERICA 1 & NERICA 10 (upland rice variety, yet to be released by BRRI)
Introduction of Modern agronomic practices
Modern Seedbed, Line transplanting, balance fertilizer application, weeding, Irrigation, IPM, Harvest and post harvest technologies (harvest at 80% maturity, Proper drying and cleaning, seed storage, etc)
Introduction of USG & USG Applicator
Application of urea fertilizers in the form of Urea Super Granules (USG) for proper & efficient utilization of urea fertilizer which saves about 30% of urea fertilizers.
Introduction of Non-rice crops Non-rice cereal:
o Maize: BARI Hybrid-1: Hybrid variety with high yield o Maize: BARI Hybrid-7: Hybrid variety with high yield
Oil crop: o Sesame: BARI3
Pulse crop: Mung bean: o BARI Mung7: High yielding improved varieties
Introduction of Horticultural Vegetables: Plantain, Pumpkin, Yard long bean, Ash gourd, Cucumber,
Adoption of Improved Technologies - Crops
The following improved technologies have been introduced under crop subcomponent:
List of Improved Technologies Introduced- Crop Sub-Component
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 14
Adoption of Improved Technologies- Fisheries
The following improved technologies have been introduced under fisheries subcomponent:
Aquaculture Technologies Details description
Carp Culture Technologies (Carp Package)
Improved pond preparation Pond dike repairing, removal of aquatic weeds, harmful trees or branches, predator and unwanted fish remove or control, Lime and fertilizer preparation and application
Maintaining proper fish fingerlings stocking density and method
Stocking density: 40-60/decimal with poly culture
Quality fingerlings selection, transportation, adaptation and releasing in the pond.
Use of supplementary fish feed Supplementary feeding-quantity measurement, ingredient selection, feed preparation and application Regular observe fish growth and adjust feed requirement
Maintaining of pond water qualities and environment
Physical, chemical and biological parameters of pondwater-water depth, water color, turbidity, transparency, temperature, checking natural feed availability, oxygen and water pH, need based fertilizer application,
Application of fish disease prevention method
Keeping fish friendly pond environment/pond water, 6-8 hrs photoperiod maintenance, restriction on the entrance of polluted water or materials/obstacles etc. Periodic lime application, observe fish movement and growth
Golda/Bagda Culture Technologies (Golda/Bagda Package)
Improved Pond/gher preparation
Pond/gher dike repairing, removal of aquatic weeds, harmful trees or branches, predator and unwanted fish remove or control, Lime and fertilizer preparation and application
Maintaining proper prawn post larvae/juvenile stocking density and method
Post larvae rearing in pocket nursery up to 3- 4 weeks,
Quality post larvae selection, transportation, adaptation and releasing.
Use of supplementary prawn feed or pellet feed
Supplementary feeding-quantity measurement, ingredient selection, feed preparation and method of application, pelleted feed application, Regular observe prawn growth and adjust feed requirement
Maintaining of pond/gher water qualities and environment
Physical, chemical and biological parameters of pondwater-water depth, water color, turbidity, transparency, temperature, checking natural feed availability, oxygen and water pH, need based fertilizer application
Application of prawn disease prevention methods
Keeping fish friendly pond environment/pond water, 6-8 hrs photoperiod maintenance, restriction on the entrance of polluted water or materials/obstacles etc. Periodic lime application, observe prawn movement/growth
Capture Fisheries
Providing Fibre Reinforced Boats(FRB)
Two types of FRBs have been given to capture fishers. One type is relatively small in size. The fishers claim the boats do not serve the intended purpose. The other type is relatively bigger and serves the purpose.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 15
Adoption of Improved Technologies – Livestock
Lists of Improved Technologies of Livestock Sub-Component
Title name of the technology Definition of the technology (Measuring Criteria)
Technologies adopted by Cow Beneficiaries
Improved shelters Open house, easy aeration, protected from rain, regular dung disposal, regular cleaning of house and surrounding
Use concentrate feed Use of concentrate feed
Rice bran, Wheat bran, Oil cake
Rearing of vaccination animal Use of Anthelmintic , vaccination as schedule, Identification of sick and Communication with Livestock Office
Fodder cultivation Introducing fodder and fodder cultivation
Technologies adopted by Goat/Sheep Beneficiaries
Improved shelters Use of slat/platform, easy aeration, protected from rain, regular dung disposal, regular cleaning of house and surrounding.
Use concentrate feed Use of concentrate feed
Rice bran, Wheat bran, Oil cake
Rearing of vaccination animal Use of Anthelmintic , vaccination as schedule, Identification of sick and Communication with Livestock Office
Kid rearing New borne kid management and Method of Castration
Technologies adopted by Chicken/Duck Beneficiaries
Improved shed for Chicken/Ducks
Elevated place, open house, easy aeration, protected from predator
Balance feed Ingredients used in balanced feed Rice bran, wheat bran, oil cake
Rearing of vaccinated Chicken/Duck
Routine vaccination and use of Anthelmintic, Communication with ULO office in need.
Improved hazol and hatching Selection of broody hen and hatching eggs, Hazol size, Use of neem leaf as insect repellent.
Note: Since all activities under Component A have been completed on 30 June 2014, the related Annex-2 showing status progress of Component A has been omitted.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 16
3. COMPONENT B – RECONSTRUCTION AND IMPROVEMENT OF MULTIPURPOSE SHELTERS
3.1 Background
3.1.1 Component Objective
The objective of Component B is to provide greater protection for the vulnerable population and livestock in the cyclone prone areas during future disasters. This will be achieved through the following subcomponents:
Subcomponent B.1: Construction of new shelters – will support construction of 353 new multi-purpose shelters and 30 killas to build greater protection against future disaster events.
Subcomponent B.2: Improvement of existing shelters – will finance the repairs and improvement of 460 existing shelters that are damaged or cannot be used due to inadequacies.
Subcomponent B.3: Improvement of communication network to shelters – will finance the construction/ reconstruction of a total of 350 km road, 12000 m bridges and communication network to the shelters constructed under the Project to make them more accessible and effective.
Subcomponent B.4: Design and construction supervision of shelters – will finance consulting services for surveys, design, environmental and social impact assessments, environment and resettlement management plans, and construction supervision of multi-purpose disaster shelters and all works covered under Component B. This will also include resources to facilitate consultations with the local communities in identifying sites, needs and suitable design for the shelters.
LGED of the MLGCRD is the implementing agency for Component B.
3.1.2 M&E of the Component
M&E of Component B will be carried out for: (a) inputs and outputs (as specified in the component logical framework), (b) on the efficiency and effectiveness of the processes underlying the design and implementation of the component, and (c) the component‟s contribution towards the attainment of Project outcome. LGED, as the implementing agency for this component, is mainly responsible for the M&E of “a” and “b”. The M&E Consultant is responsible for the consolidation, verification, and analysis of these M&E information as to their contribution to progress in the attainment of outcome (“c”).
3.2 Component B Targets
3.2.1 Physical Targets
As per WB‟s Aide Memoire, March 2016 and last revised DPP covering AFII, the total physical targets under Component B are: repair and improvement of 460 existing shelters; construction of 353 new multi-purpose shelters, and the construction of 15 killas (revised).
The calendar year-wise cumulative targets for each of these shelters are shown in Figure 3-1. The cumulative year wise targets of the subsequent calendar years are as follows: 61% of existing shelters and 42% of new shelters up to 2014; 70% of existing shelters and 65% of new shelters by end of 2015; 87% of existing shelters and 79% of new shelters by end of 2016 and 100% of the total targeted existing shelters and new shelters by end of 2017.
2014 2015 2016 2017
improved shelter 280 320 400 460
new shelter 150 230 280 353
0
50
100
150
200
250
300
350
400
450
500
Num
ber
Figure 3-1 Physical Targets (cumulative): Numbers of New Shelters Constucted and Existing Shelters Improved
Source: WB's Aide Memoire, March 2016
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 17
The expected output of Component B is additional space, comfortable and safe protection of the vulnerable population and livestock in the cyclone prone areas during future disasters. The multi-purpose shelters can provide protection to a total of 952,700 vulnerable persons – 423,200 persons through repaired/ improved existing shelters, and 529,500 persons through new shelters. These are computed considering the total target number of shelters repaired/ improved/ constructed by the project, and the capacities of the shelters – i.e. 920 persons for existing shelter with improved facilities, and 1,500 persons for new shelter. Figure 3-2 presents the year-wise cumulative target of vulnerable population protected corresponding to the physical targets indicated in Figure 3-1.
3.2.2 Financial Targets
Shown in Figure 3-3 are the year-wise cumulative financial targets per revised DPP. The cumulative disbursement target for the repair/ improvement of existing shelters, construction of new shelters and killas are: Taka 61,879 Lakh or 49% of the total construction cost (Taka 125,391 lakh) up to FY 2013-14; Taka 87,070 lakh or 69% by end of FY2014-2015; Taka 112,260 lakh or 90% by end of FY2015-2016; and Taka 125,391 lakh or 100% by end of FY2016-2017.
3.3 Component B Annual Work Plan for FY 2016 – 2017
The work plan for the implementation of Component B in FY2016–2017 is presented in Annex 3A. This was developed based on the physical and financial targets of the component by the end of the fiscal year. The different LGED CPs includes works on:
i) Construction of 353 new multi-purpose shelters in 57 Contract Packages; ii) Improvement of 460 existing school-cum-shelters in 34 CPs; iii) Construction of 334.76 km access roads including bridges/culverts (827 m) into 39 CPs, and iv) Construction of 15 new killas in 3 CPs;
3.4 Component B: Process & Progress
Status of pre-construction and construction activities of the above mentioned 133 nos. CPs as of end of September of FY2016-2017, are discussed in the following sections:
3.4.1 Process Monitoring- Pre-construction Activities
Construction of New Shelters
a) Phase I: 50 new school-cum-shelters:
Details of the status as of end of September 2016 in the conduct of pre- construction activities for the 13 CPs for 50 new school-cum-shelters under Phase I are presented in Annex 3B: Process Monitoring Form PMF-B2: Process Monitoring – Package-wise Construction of New School-cum-Cyclone Shelters. These are summarized in Figure 3-4, and discussed below:
All the pre-construction activities for the construction of 50 new school-cum-shelters in 13 CPs under Phase I had already been completed. Pre-construction activities include the following item of works:
FY2010-2011
FY2011-2012
FY2012-2013
FY2013-2014
FY2014-2015
FY2015-2016
FY2016-2017
improved shelter 804 5,751 6,027 8,740 11,453 14,166 16,879
new shelter 1,170 5,851 30,424 52,624 74,823 97,023 107,163
killa 0 0 237 515 793 1,071 1,349
010,00020,00030,00040,00050,00060,00070,00080,00090,000
100,000110,000
Taka
(Lak
h)
Figure 3-3 Financial Targets (cumulative): Construction Cost of New Shelter, Cost of Improvement of Existing Shelters, and Construction
Cost of New KillasRDPP, 2nd Revision, LGED (February 2014)
2014 2015 2016 2017
improved shelter 257,600 294,400 368,000 423,200
new shelter 225,000 345,000 420,000 529,500
0
50,000
100,000
150,000
200,000
250,000
300,000
350,000
400,000
450,000
500,000
550,000
Num
ber
of P
erso
ns
Figure 3-2 Physical Targets (cumulative): Numbers of Vulnerable Population in Target Communities Benefited by Multi-Purpose
SheltersSource: WB's Aide Memoire, March 2016
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 18
Site Selection Design WorksIEE/EIA
Preparation
IEE/EIA Clearance from
M&E Consultant
IEE/EIA Clearance from
DoE
Social & Resettlement
Study Preparation
Social & Resettlement
Study Clearance from
M&E Consultant
Distribution of Tender Notice
Tender ReceiptContract
Award
Not Completed 0 0 0 0 0 0 0 0 0 0
Completed - FY2012-2013 0 0 0 0 0 12 12 0 0 0
Completed - FY2011-2012 0 0 42 42 0 16 16 0 0 14
Completed - FY2010-2011 50 50 8 8 50 22 22 50 50 36
0
10
20
30
40
50
Nu
mb
er
o N
ew
Sh
elt
ers
Figure 3-4 Process Monitoring: Status of Activities for the 50 New School-com-Shelters Construction, in 13 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
i) Site Selection
iii) Design Works, and Comprehensive Technical Report Approval
iii) EA Report Preparation and Clearance
iv) Social and Resettlement Study Report Preparation and Clearance, and
v) Tendering and Approval Process
b) Phase II: 308 New School-cum-Shelters in 44 CPs:
As of end June 2016 (FY2015-2016), preconstruction activity for the 44 CPs for construction of 308 new school-cum-shelters under Phase II has been reported by LGED / D&S Consultants and presented in Annex 3C: Process Monitoring Form PMF-B2: Process Monitoring – Package-wise Construction of New School-cum-Cyclone Shelter sunder Phase II. These are summarized in Figure 3-5, and discussed below:
Site Selection
The locations of the 307 additional new school-cum-shelters in 9 districts had been selected till June 2016. Assessment was made to estimate the cost of each of the 44 CPs.
Design Works, and Comprehensive Technical Report Approval
As of end June 2016, concurrence had been obtained from WB in regard to the Comprehensive Technical Reports for the 44 CPs (i.e. CPs NW 14 to NW 42, NW 08A & NW 43 to NW 56) for the construction of 307 new school-cum-shelters covering site identification, inventory, design, site-wise engineering estimates, BOQ and tender documents etc.
IEE/EIA Preparation and Clearance
As of end September 2016, 305 new school-cum-cyclone shelters in 43 CPs (CPs NW 14 to 56) had been submitted to the PCMU for review. After review, the M&E Consultant gave clearance to the reports for all 305 shelters in 43 CPs.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 19
Site Selection Design Works IEE Preparation
IEE Clearance from M&E Consultant
Social & Resettlement
Study Preparation
Social & Resettlement
Study Clearance
from M&E Consultant
Distribution of Tender Notice
Tender Receipt Contract Award
Not Completed 1 1 3 3 24 24 1 1 1
Completed - 1st quarter (Jul - Sept 2016) 0 0 1 1 1 1 0 0 0
Completed - FY 2015-2016 23 23 91 91 96 96 35 123 123
Completed - FY 2014-2015 100 100 33 33 57 57 88 0 0
Completed - FY 2013-2014 6 6 138 138 92 92 6 6 6
Completed - FY 2012-2013 1 1 42 42 38 38 14 14 75
Completed - FY 2011-2012 177 177 0 0 0 0 164 164 103
0102030405060708090
100110120130140150160170180190200210220230240250260270280290300310
Nu
mb
er
of
Ne
w S
he
lte
rs
Figure 3-5 Process Monitoring: Status of Activities for the 308 New Shelters Construction in 44 Contract PackagesAs of 1st Quarter FY2016-2017 (ending September 2016)
Social and Resettlement Study Preparation and Clearance
As of end September 2016, 284 new school-cum-cyclone shelters in 39 CPs (i.e.CPs NW 14 to 17, 19 to 28, 30 to 33, 35 to 36 & 38 to 56) had been submitted to the PCMU for review. After review, the M&E Consultant gave clearance to the reports for 284 shelters in 39 CPs (i.e. NW 14 to17, 19 to 28, 30 to 33, 35 to 36 & 38 to 56) to be in accordance with the S/RPF.
Tender Approval Process
As of end September 2016, tender notices have been floated for 307 new school-cum-cyclone shelters in 44 CPs. Tender received for the 44 CPs covering 307 new shelters. Contracts had also been awarded for the 44 CPs covering 307 new shelters.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 20
Site Selection Design WorksIEE/EIA
Preparation
IEE/EIA Clearance from M&E Consultant
IEE/EIA Clearance from
DoE
Social & Resettlement
Study
Preparation
Social & Resettlement
Study Clearance
from M&E Consultant
Distribution of Tender Notice
Tender Receipt Contract Award
Not Completed 0 0 0 0 0 0 0 0 0 0
Completed - FY2011-2012 0 0 0 0 0 0 0 0 0 11
Completed - FY2010-2011 250 250 250 250 250 250 250 250 250 239
0
50
100
150
200
250
Nu
mb
er o
Ex
isti
ng
Sh
elt
ers
Figure 3-6 Process Monitoring: Status of Activities for the Repair/Improvement of 250 Existing School-com-Shelters, in 25 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Improvement of Existing Shelters
a) Phase I: Repair/improvement of 250 existing school-cum-shelters :
Details of the status in the conduct of the activities for the 25 CPs for repair/improvement of 250 existing school-cum-shelters under Phase I as of end of September 2016 are shown in Annex 3D: Process Monitoring Form PMF-B2: Process Monitoring – Package-wise Repair/Improvement of Existing School-cum-Cyclone Shelters. These are summarized in Figure 3-6, and discussed below:
All the pre-construction activities for the repair/improvement of 250 new school-cum-shelters in 25 CPs had already been completed. Pre-construction activities include the following item of works:
i) Site Selection
ii) Design Works, and Comprehensive Technical Report Approval
iii) Environmental Assessment and Clearance
iv) Social and Resettlement Study Preparation and Clearance, and
v) Tendering and Approval Process.
b) Phase II: Repair/improvement of 220 existing school-cum-shelters :
Details of the status in the conduct of the activities for the 10 CPs for repair/improvement of 220 existing school-cum-shelters under Phase II as of end of September 2016 are shown in Annex 3E: Process Monitoring Form PMF-B2: Process Monitoring – Package-wise Repair/Improvement of Existing School-cum-Cyclone Shelters. These are summarized in Figure 3-7, and discussed below:
Site Selection
As of end September 2016, identification of existing 219 cyclone shelters (30 in Khulna, 27 in Patuakhali, 18 in Pirojpur, 10 in Satkhira, 25 in Bagerhat, 48 in Bhola, 8 in Jhalikathi, 36 in Barguna and 17 in Barisal districts) under Phase II have already been done.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 21
Site Selection
Design Works
IEE/EIA Preparation
IEE/EIA Clearance from M&E
Consultant
Social & Resettleme
nt Study
Preparation
Social & Resettleme
nt Study
Clearance from M&E Consultant
Distribution of Tender
Notice
Tender Receipt
Contract Award
Not Completed 0 0 0 0 23 23 0 0 0
Completed - 1st quarter (Jul-Sep 2016) 0 0 0 0 0 0 0 0 0
Completed - FY 2015-2016 3 3 96 96 38 38 3 3 3
Completed - FY 2014-2015 0 152 123 123 38 38 152 152 152
Completed - FY 2013-2014 216 64 0 0 120 120 64 64 64
0
50
100
150
200
Nu
mb
er
o E
xist
ing
She
lte
rs
Figure 3-7 Process Monitoring: Status of Activities for the Repair/Improvement of 219 Existing School-com-Shelters, in 10 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Design Works, and Comprhensive Technical Report Approval
As of end September 2016, concurrence had been obtained from WB in regard to the Comprehensive Technical Reports for the 10 CPs (i.e. CPs W 34 to 43) for the improvement of 219 existing school-cum-shelters covering site identification, inventory, design, site-wise engineering estimates, BOQ and tender documents etc.
Environmental Assessment and Clearance
As of end September 2016, 219 existing school-cum-cyclone shelters in 10 CPs (CPs W 34 to 43) had been submitted to the PCMU for review. After review, the M&E Consultant gave clearance to the reports for all 219 existing school-cum-cyclone shelters in 10 CPs.
Social and Resettlement Study Preparation and Clearance
As of end September 2016, 196 existing school-cum-cyclone shelters in 10 CPs (CPs W 34 to 43) had been submitted to the PCMU for review. After review, the M&E Consultant gave clearance to the reports for all196 shelters in 10 CPs (i.e. CPs W 34 to 43) to be in accordance with the S/RPF.
Tendering and Approval Process
Tender notices have been floated and received for the 10 CPs (CPs W 34 to 43) covering 219 existing school-cum-cyclone shelters in 9 districts. Contracts had also been awarded for the 10 CPs (CPs W 34 to 43) covering 219 existing school-cum-cyclone shelters.
Improvement of Communication Network to Shelters
a) Phase I: 29 Access Roads in 8 CPs :
Details of the status in the conduct of the activities, as of end June 2016, for each of the 8 CPs for the construction of 29 access roads under Phase I are presented in Annex 3F: Process Monitoring Form PMF-B2: Process Monitoring – Package-wise Improvement of Communication Network to Shelters. These are summarized in Figure 3-8, and discussed below:
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 22
Site Selection Design WorksIEE/EIA
Preparation
IEE/EIA Clearance from M&E
Consultant
IEE/EIA Clearance from DoE
Social & Resettlement
Study
Preparation
Social & Resettlement
Study
Clearance from M&E Consultant
Distribution of Tender
Notice
Tender Receipt
Contract Award
Not Completed 0 0 0 0 0 0 0 0 0 0
Completed - FY2015-2016 0 0 0 0 0 0 0 0 0 0
Completed - FY2014-2015 0 0 29 29 0 0 0 0 0 0
Completed - FY2013-2014 0 0 0 0 0 29 29 0 0 0
Completed - FY2012-2013 0 0 0 0 0 0 0 0 0 0
Completed - FY2011-2012 29 29 0 0 29 0 0 29 29 29
0
5
10
15
20
25
Num
ber
of A
cces
s Roa
ds
Figure 3-8 Process Monitoring: Status of Activities for theConstruction of 29 Shelter Connecting Roads (Total 68.64 Km) in 8 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Site Selection
The locations of the 29 access roads (total 68.64 km) in 5 districts have been selected and assessed. The result of assessment was the basis for estimating the cost of each of the 8 CPs.
Design Works, and Comprehensive Technical Report Approval
As of end September 2016, Design works have been completed for 8 CPs (i.e. CPs R 01 to 04 & R 06 to R 09) for the construction of 29 access roads.
Environmental Assessment and Clearance
As of end September 2016, IEE/ EIA reports for the 29 access roads in 8 CPs (CPs R 01 to 04 & R 06 to R 09) had been submitted to the PCMU for review. After review, the M&E Consultant gave clearance to the reports for all 29 access roads in 8 CPs (CPs R 01 to 04 and R 06 to 09).
Social and Resettlement Study Preparation and Clearance
As of end September 2016, social and resettlement study reports for the 29 access roads in 8 CPs (CPs R 01 to
04 & R 06 to R 09) had been submitted to the PCMU for review.
After review, the M&E Consultant gave clearance to the reports for all 29 access roads in 8 CPs (CPs R 01 to 04
& R 06 to R 09) to be in accordance with the S/RPF.
Tendering and Approval Process
Tender notices have been floated and received for the 8 CPs (CPs R 01 to 04 & R 06 to R 09) covering 29 access roads in Bagerhat, Barguna, Patuahaki and Pirojpur districts. Contracts had also been awarded for 8 CPs (i.e. CPs R 01 to 04 & R 06 to R 09) covering 29 access roads in Bagerhat, Barguna, Pirojpur, Barisal and Patuakhali districts.
b) Phase II: 152 Access Roads in 31 CPs :
Details of the status in the conduct of the activities, as of end September 2016, for each of the 31 CPs for the construction of 152 access roads under Phase II are presented in Annex 3G: Process Monitoring Form PMF-B2: Process Monitoring – Package-wise Improvement of Communication Network to Shelters. These are summarized in Figure 3-9, and discussed below:
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 23
Site Selection/ Damage Assessment
Design Works IEE PreparationIEE Clearance from M&E
ConsultantSocial & Resettlement
Study Preparation
Social & Resettlement Study Clearance from M&E
Consultant
Distribution of Tender Notice
Tender Receipt Contract Award
Not Completed 1 1 3 3 29 29 1 1 1
Completed - 1st quarter (Jul - Sep 2016) 0 0 0 0 1 1 0 0 0
Completed - FY 2015-2016 52 52 58 58 58 58 52 52 52
Completed - FY 2014-2015 0 0 91 91 9 9 0 0 0
Completed - FY 2013-2014 0 2 0 0 55 55 2 2 2
Completed - FY 2012-2013 99 97 0 0 0 0 97 97 97
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
105
110
115
120
125
130
135
140
145
150
Num
ber o
f Acc
ess R
oads
Figure 3-9 Process Monitoring: Status of Activities for the Construction o f 152 Shelter Connecting Roads( 260.07 Km) in 31 Contract Package As of 1st Quarter FY2016-2017 (ending Septembe
Site Selection
The locations of the 152 access roads (total 260.07 km) in 9 districts have been selected and assessed. The result of assessment was the basis for estimating the cost of each of the 31 CPs.
Design Works, and Comprehensive Technical Report Approval
As of end September 2016, Design works have been completed for 30 CPs (i.e. CPs R 10 to 37, R 5A & R 5B) for the construction of 152 access roads.
Environmental Assessment and Clearance
As of end September 2016, IEE/EIA reports for 28 CPs (R 10 to 37) covering 149 access roads had been submitted to M&E Consultant through PCMU for review. After review, the M&E Consultant gave clearance to the reports for all 149 access roads in 28 CPs (CPs R 10 to 37).
Social and Resettlement Study Preparation and Clearance
As of end September 2016, social and resettlement study reports for the 123 access roads in 25 CPs (CPs R 10 to 20, R 23, R 25 to 31, R 33 to R 37 & R 39) had been submitted to the PCMU for review.
In the construction of SCRs, additional land on both sides of the existing roads become necessary due to widening of the roads. M&E Consultants raised the issue of LA and resettlement following the S/RPF. LGED explained that the Organization is exempted from LA and resettlement in development works. A meeting was held on 17 June 2014 in the office of the DG/PD, PCMU which was attended by all concerned including WB. A consensus decision was taken in the meeting approving the LGED clarifications.
In the light of above decision, the M&E Consultant gave clearance to the reports for the 123 access roads in 25 CPs (CPs R 10 to 20, R 23, R 25 to 31, R 33 to 37 & R 39) to be in accordance with the S/RPF.
Tendering and Approval Process
Tender notices have been floated and received for the 30 CPs (CPs R10 to 37, R 5A & R 5B) covering 151 access roads in Khulna, Satkhira, Bagerhat, Pirojpur, Barguna, Jhalokathi, Barisal, Bhola and Patuakhali districts. Contracts had also been awarded for 30 CPs (CPs R10 to 37, R 5A & R 5B) covering 151 access roads in the above districts.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 24
Site SelectionDesign Works
IEE Preparation
IEE Clearance from M&E Consultant
IEE Clearance from DoE
Social & Resettlement
Study
Preparation
Social & Resettlement
Study
Clearance from M&E Consultant
Distribution of Tender
Notice
Tender Receipt
Contract Award
Not Completed 0 0 0 0 0 12 12 0 0 0
Completed - 1st quarter (Jul - Sept 2016) 0 0 0 0 0 0 0 0 0 0
Completed - FY2015-2016 0 0 0 0 0 3 3 0 0 0
Completed - FY2014-2015 0 0 15 15 0 0 0 0 0 0
Completed - FY2013-2014 0 0 0 0 0 0 0 0 0 0
Completed - FY2012-2013 0 0 0 0 0 0 0 0 0 0
Completed - FY2011-2012 15 15 0 0 0 0 0 15 15 15
Completed - FY2010-2011 0 0 0 0 15 0 0 0 0 0
0
5
10
15
Nu
mb
er
of
Kill
a
Figure 3-10 Process Monitoring: Status of Activities for the Construction of 15 Killas in 3 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Construction of Killas
Details of the status in the conduct of the activities, as of end September 2016 , for each of the 3 CPs for the construction of 15 killas are presented in Annex 3H: Process Monitoring Form PMF-B2: Process Monitoring – Package-wise Construction of Killas. These are summarized in Figure 3-10, and discussed below:
Site Selection
The locations of the 15 killas in 3 districts have been selected and assessed. The results of which were used as basis for estimating the cost of each of the 3 CPs.
Design Works, and Comprehensive Technical Report Approval
As of end September 2016, Design works have been completed for 3 CPs (i.e. CPs KW 01, KW 03 and KW 04)
for the construction of 15 killas.
Environmental Assessment and Clearance
As of end September 2016, environmental assessment study reports (IEE/EIA) for the 15 killas in 3 CPs (i.e.
CPs KW 01, KW 03 and KW 04) had been submitted to the PCMU for review.
After review, the M&E Consultant gave clearance to the reports for all 15 killas in 3 CPs (i.e. CPs KW 01, KW 03 and KW 04)
Social and Resettlement Study Preparation and Clearance
As of end September 2016, social and resettlement study reports for the 15 killas in 3 CPs (i.e. CPs KW 01, KW
03 and KW 04) had been submitted to the PCMU for review.
After review, the M&E Consultant made comments on these reports in accordance with the S/RPF.
During the current quarter, the M&E Consultant gave clearance to the report for 3 killas in 1 CP (i.e. CP KW 04)
The D&S Consultant is still addressing the comments made by the M&E Consultant on the social and resettlement study reports for 12 killas in 2 CPs (i.e. CPs KW 01 and KW 03).
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 25
Package 1 4 Shelters in
Bagerhat
Package 2 4 Shelters in
Barisal
Package 3 4 Shelters in
Barguna
Package 4 4 Shelters in
Patuakhali
Package 5 4 Shelters in
Barisal
Package 6 4 Shelters in
Pirojpur
Package 7 4 Shelters in
Barguna
Package 8 3 Shelters in
Bagerhat
Package 9 4 Shelters in
Barguna
Package 10 3 Shelters in
Bagerhat
Package 11 4 Shelters in
Patuakhali
Package 12 4 Shelters in
Patuakhali
Package 13 4 Shelters in
Pirojpur
Completed - FY2015-2016 4 0 6 0 0 0 0 0 0 0 0 0 0
Completed - FY2014-2015 11 0 10 0 0 0 0 0 0 0 0 0 0
Completed - FY2013-2014 20 0 6 0 5 0 8 0 10 19 0 23 2
Completed - FY2012-2013 35 10 13 15 27 30 27 0 20 21 50 37 33
Completed - FY2011-2012 27 70 65 80 63 65 65 21 70 60 45 40 65
Completed - FY2010-2011 3 20 0 5 5 5 0 0 0 0 5 0 0
0
10
20
30
40
50
60
70
80
90
100
Pe
rce
nt (
%)
Figure 3-11A Progress Monitoring: Physical Progress of Construction of 50 New School-com-Shelters, in 13 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Tendering and Approval Process
Tender notices have been floated and receieved for the 3 CPs (i.e. CPs KW 01, KW 03 and KW 04) covering 15 killas in Barguna, Pirojpur and Bhola districts. Contracts had also been awarded for the 15 killas in 3 CPs.
3.4.2 Component B: Progress Monitoring
Construction of New Shelters
Phase I
Construction activities of the 13 CPs covering 50 new shelters started end of April 2011. Shown in Figures 3-11A and 3-11B are the physical and financial progress, respectively, of the 13 CPs (i.e. CPs NW 01 to 13; covering 50 new shelters in 5 districts) awarded so far. Details of the construction activities for each of the 13 CPs are presented in Annex 3I: Progress Monitoring Form PMF-B3: Progress Monitoring – Package-wise Construction of 50 New Cyclone Shelters.
As of end of September 2016, physical progress in 13 CPs (i.e. CPs NW 01 to 13) in Bagerhat, Barisal, Barguna, Patuakhali and Pirojpur districts are as follows:
CPs NW 01 to 07 and NW 09 to 13 covering 45 new shelters achieved 100% physical progress. NW 08 has a mere progress of only 21% and the contract of NW 08 has thus been terminated.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 26
Package 1 4 Shelters in
Bagerhat
Package 2 4 Shelters in
Barisal
Package 3 4 Shelters in
Barguna
Package 4 4 Shelters in Patuakhali
Package 5 4 Shelters in
Barisal
Package 6 4 Shelters in
Pirojpur
Package 7 4 Shelters in
Barguna
Package 8 3 Shelters in
Bagerhat
Package 9 4 Shelters in
Barguna
Package 10 3 Shelters in
Bagerhat
Package 11 4 Shelters in Patuakhali
Package 12 4 Shelters in Patuakhali
Package 13 4 Shelters in
Pirojpur
Disbursed - 1st quarter (Jul - Sept 2016) 0 0 0 0 0 0 0 0 0 0 0 0 0
Disbursed - FY2015-2016 12 0 26 0 0 0 0 0 0 1 3 6 0
Disbursed - FY2014-2015 19 10 0 15 12 5 8 0 8 9 0 9 9
Disbursed - FY2013-2014 9 0 0 0 0 0 0 0 6 21 10 12 0
Disbursed - FY2012-2013 31 8 15 19 23 31 48 6 38 19 51 44 40
Disbursed - FY2011-2012 29 54 56 56 55 47 35 15 38 50 27 29 51
Disbursed - FY2010-2011 0 28 0 10 10 17 9 0 10 0 9 0 0
0
10
20
30
40
50
60
70
80
90
100
Perc
ent (
%) o
f Con
trac
t Cos
t
Figure 3-11B Progress Monitoring: Financial Progress of Construction of 50 New School-com-Shelters, in 13 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Phase II
Construction activities of the 44 CPs covering 307 new shelters so far awarded in Subcomponent B.1 under Phase II started during the 2nd quarter of FY 2012-2013 through 4th quarter of FY 2015-2016. Shown in Figures 3-12A and 3-12B are the physical and financial progress, respectively, of the 44 CPs (i.e. CPs NW 14 to 56 & NW 08A; covering 307 new shelters in 9 districts). Details of the construction activities for each of the 44 CPs are presented in Annex 3J: Progress Monitoring Form PMF-B3: Progress Monitoring – Package-wise Construction of Additional 307New Cyclone Shelters.
As of end of September 2016, physical progress in 44 CPs covering 307 new shelters in Barguna, Patuakhali, Satkhira, Bhola, Khulna, Bagerhat, Barisal, Pirojpur and Jhalokathi districts are as follows:
CPs NW 14 to to 42 and NW 08A covering 184 new shelters achieved 100% physical progress.
The physical progress in 14 CPs (i.e., Cps NW 43 to 56) covering 123 new shelters varies from 8% to 59%.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 27
Package 14 10 Shelters in Barguna
Package 15 10 Shelters
in Patuakhali
Package 16 9 Shelters in
Satkhira
Package 17 10 Shelters
in Bhola
Package 18 12 Shelters
in Bhola
Package 19 8 Shelters in
Satkhira
Package 20 24 Shelters
in Khulna
Package 21 4 Shelters in
Bagerhat
Package 22 4 Shelters in
Bagerhat
Package 23 5 Shelters in
Barguna
Package 24 6 Shelters in
Barguna
Package 25 8 Shelters in
Barisal
Package 26 4 Shelters in
Barisal
Package 27 5 Shelters in
Patuakhali
Package 28 5 Shelters in
Pirojpur
Package 29 4 Shelters in
Patuakhali
Package 30 4 Shelters in
Pirojpur
Package 31 5 Shelters in
Pirojpur
Package 32 5 Shelters in
Satkhira
Completed - 1st quarter (Jul - Sep 2016) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5 0
Completed - FY 2015-2016 4 0 18 0 0 11 17 0 0 5 0 0 0 0 0 0 0 22 0
Completed - FY 2014-2015 16 8 28 12 19 38 33 0 41 18 14 3 0 4 12 0 23 34 30
Completed - FY 2013-2014 29 29 28 33 41 29 33 27 47 34 37 41 26 51 32 40 77 21 35
Completed - FY 2012-2013 51 63 26 55 40 22 17 73 12 43 49 56 74 45 56 60 0 18 35
0
10
20
30
40
50
60
70
80
90
100
Pe
rc
en
t (%
)
Figure 3-12A Progress Monitoring: Physical Progress of Construction of 307 New School-com-Shelters, in 44 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Package 33 5 Shelters in
Satkhira
Package 34 4 Shelters in
Patuakhali
Package 35 5 Shelters in
Satkhira
Package 36 7 Shelters in
Jhalokathi
Package 37 1 Shelter in
Bagerhat
Package 38 5 Shelters in
Jhalokathi
Package 39 5 Shelters in
Jhalokathi
Package 40 4 Shelters in
Pirojpur
Package 41 2 Shelters in
Khulna
Package 42 1 Shelter in
Pirojpur
Package 08A 3 Shelters in
Bagerhat
Package 43 10 Shelters
in Barisal
Package 44 10 Shelters in Jhalokathi
Package 45 10 Shelters in Pirojpur
Package 46 12 Shelters
in Bhola
Package 47 12 Shelters
in Patuakhali
Package 48 13 Shelters in Barguna
Package 49 10 Shelters
in Khulna
Package 50 12 Shelters in Bagerhat
Package 51 11 Shelters in Satkhira
Package 52 5 Shelters in
Barisal
Package 53 4 Shelters in
Pirojpur
Package 54 5 Shelters in
Satkhira
Package 55 5 Shelters in
Patuakhali
Package 56 4 Shelters in
Bagerhat
Completed - 1st quarter (Jul - Sep 2016) 0 0 0 0 0 0 0 0 0 0 0 4 19 3 13 17 10 3 8 10 20 10 13 8 11
Completed - FY 2015-2016 0 0 0 0 0 0 0 0 5 0 3 39 40 37 30 41 40 34 26 32 23 24 0 0 0
Completed - FY 2014-2015 24 1 0 12 50 10 9 14 68 72 60 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Completed - FY 2013-2014 24 46 45 49 50 44 41 86 27 28 37 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Completed - FY 2012-2013 52 53 55 39 0 46 50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0
10
20
30
40
50
60
70
80
90
100
Pe
rc
en
t (
%)
Figure 3-12A Progress Monitoring: Physical Progress of Construction of 307 New Schol-com-Shelters, in 44 Contract Package , cont.)As of End of 1st Quarter FY2016-2017 (ending September 2016)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 28
Package 14 10 Shelters in
Barguna
Package 15 10 Shelters in
Patuakhali
Package 16 9 Shelters in
Satkhira
Package 17 10 Shelters in
Bhola
Package 18 12 Shelters in
Bhola
Package 19 8 Shelters in
Satkhira
Package 20 24 Shelters in
Khulna
Package 21 4 Shelters in
Bagerhat
Package 22 4 Shelters in
Bagerhat
Package 23 5 Shelters in
Barguna
Package 24 6 Shelters in
Barguna
Package 25 8 Shelters in
Barisal
Package 26 4 Shelters in
Barisal
Package 27 5 Shelters in Patuakhali
Package 28 5 Shelters in
Pirojpur
Package 29 4 Shelters in Patuakhali
Package 30 4 Shelters in
Pirojpur
Package 31 5 Shelters in
Pirojpur
Package 32 5 Shelters in
Satkhira
Disbursed - 1st quarter (Jul - Sep 2016) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Disbursed - FY 2015-2016 5 4 19 0 0 21 27 0 16 17 15 8 0 12 10 13 0 10 12
Disbursed - FY 2014-2015 17 13 27 15 29 25 20 0 27 9 6 21 16 4 15 1 35 27 33
Disbursed - FY 2013-2014 21 23 24 24 31 27 28 32 30 31 29 17 11 39 23 23 65 31 22
Disbursed - FY 2012-2013 57 60 30 61 40 27 25 68 27 43 50 54 73 45 52 63 0 10 33
0
10
20
30
40
50
60
70
80
90
100
Pe
rc
en
t (%
) o
f C
on
tra
ct
Co
st
Figure 3-12B Progress Monitoring: Financial Progress of Construction of 307 New School-com-Shelters, in 44 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Package 33 5 Shelters in
Satkhira
Package 34 4 Shelters in Patuakhali
Package 35 5 Shelters in
Satkhira
Package 36 7 Shelters in
Jhalokathi
Package 37 1 Shelter in
Bagerhat
Package 38 5 Shelters in
Jhalokathi
Package 39 5 Shelters in
Jhalokathi
Package 40 4 Shelters in
Pirojpur
Package 41 2 Shelters in
Khulna
Package 42 1 Shelter in
Pirojpur
Package 08A 3 Shelters in
Bagerhat
Package 43 10 Shelters in
Barisal
Package 44 10 Shelters in
Jhalokathi
Package 45 10 Shelters in
Pirojpur
Package 46 10 Shelters in
Pirojpur
Package 47 12 Shelters in
Patuakhali
Package 48 13 Shelters in
Barguna
Package 49 10 Shelters in
Khulna
Package 50 12 Shelters in
Bagerhat
Package 51 11 Shelters in
Satkhira
Package 52 5 Shelters in
Barisal
Package 53 4 Shelters in
Pirojpur
Package 54 5 Shelters in
Satkhira
Package 55 5 Shelters in Patuakhali
Package 56 4 Shelters in
Bagerhat
Disbursed - 1st quarter (Jul - Sep 2016) 0 0 0 0 0 0 0 0 0 0 0 0 11 4 2 6 0 0 2 8 7 5 7 0 2
Disbursed - FY 2015-2016 10 14 0 2 0 1 15 0 15 0 20 46 44 40 30 40 42 34 35 31 26 21 10 10 10
Disbursed - FY 2014-2015 27 0 19 14 54 14 7 20 61 75 52 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Disbursed - FY 2013-2014 12 33 23 33 46 26 21 80 24 25 28 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Disbursed - FY 2012-2013 51 53 58 51 0 59 57 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0
10
20
30
40
50
60
70
80
90
100
Pe
rc
en
t (
%) o
f C
on
tra
ct C
ost
Figure 3-12B Progress Monitoring: Financial Progress of Construction of 307 New School-com-Shelters, in 44 Contract Packages(cont.) As of End of 1st Quarter FY2016-2017 (ending September 2016)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 29
Package 1 8 Shelters in
Barguna
Package 2 10 Shelters in
Bagerhat
Package 3 10 Shelters in
Barguna
Package 4 12 Shelters in
Barguna
Package 5 10 Shelters in
Barguna
Package 6 11 Shelters in
Barisal
Package 7 11 Shelters in
Barisal
Package 8 12 Shelters in
Barisal
Package 9 10 Shelters in
Pirojpur
Package 10 11 Shelters in
Patuakhali
Package 11 10 Shelters in
Patuakhali
Package 12 10 Shelters in
Patuakhali
Completed - FY2012-2013 0 0 0 0 0 0 0 0 0 0 0 0
Completed - FY2011-2012 2 25 41 74 42 6 40 4 23 38 45 66
Completed - FY2010-2011 98 75 59 26 58 94 60 96 77 62 55 34
0
10
20
30
40
50
60
70
80
90
100
Pe
rce
nt (
%)
Figure 3-13A Progress Monitoring: Physical Progress of Repair/Improvement of 240 Existing School-com-Shelters, in 24 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Package 13 7 Shelters in Patuakhali
Package 14 12 Shelters in
Patuakhali
Package 15 11 Shelters in
Bhola
Package 16 10 Shelters in
Bhola
Package 17 15 Shelters in
Bhola
Package 18 8 Shelters in
Bhola
Package 19 10 Shelters in
Bhola
Package 20 6 Shelters in
Bhola
Package 21 10 Shelters in
Jhalokathi
Package 22 10 Shelters in
Khulna
Package 23 8 Shelters in
Satkhira
Package 24 8 Shelters in
Satkhira
Completed - FY2012-2013 0 0 50 0 0 0 0 0 0 0 0 0
Completed - FY2011-2012 42 48 50 38 46 63 71 85 49 71 32 36
Completed - FY2010-2011 58 52 0 62 54 37 29 15 51 29 68 64
0
10
20
30
40
50
60
70
80
90
100
Pe
rce
nt (
%)
Figure 3-13A Progress Monitoring: Physical Progress of Repair/Improvement of 240 Existing School-com-Shelters, in 24 Contract Packages (cont.) As of End of 1st Quarter FY2016-2017 (ending September 2016)
Improvement of Existing Shelters
Phase I
Repair/improvement activities in Subcomponent B.2 under Phase I started in Mid-October 2010. Shown in Figures 3-13A and 3-13B are the physical and financial progress, respectively, of the 24 CPs (i.e. CPs W 01 to 24; covering 240 existing shelters in 9 districts) awarded so far. Details of the repair/improvement activities for each of the 24 CPs in Subcomponent B.2 are presented in Annex 3K: Progress Monitoring Form PMF-B3: Progress Monitoring – Package-wise Improvement of Cyclone Shelters.
As of end of September 2016, 24 CPs (i.e. CPs W 01 to 24) covering 240 existing shelters in 9 districts were reported to be 100% complete.
Packages for Construction of Toilets
CPs W 26 to W 33 (8 nos.) are exclusive packages for construction of toilets in 57 Existing Shelters. As of end of September 2016, overall physical progress is 100% and financial progress is 100%.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 30
Package 1 8 Shelters in
Barguna
Package 2 10 Shelters in
Bagerhat
Package 3 10 Shelters in
Barguna
Package 4 12 Shelters in
Barguna
Package 5 10 Shelters in
Barguna
Package 6 11 Shelters in
Barisal
Package 7 11 Shelters in
Barisal
Package 8 12 Shelters in
Barisal
Package 9 10 Shelters in
Pirojpur
Package 10 11 Shelters in
Patuakhali
Package 11 10 Shelters in
Patuakhali
Package 12 10 Shelters in
Patuakhali
Disbursed - FY2013-2014 0 0 0 0 0 0 0 0 0 1 1 0
Disbursed - FY2012-2013 6 0 59 14 46 0 0 0 0 15 13 13
Disbursed - FY2011-2012 4 29 0 61 11 10 51 24 41 42 48 70
Disbursed - FY2010-2011 90 71 41 25 43 90 49 76 59 42 38 17
0
10
20
30
40
50
60
70
80
90
100
Pe
rce
nt
(%)
of
Co
ntr
ac
t C
ost
Figure 3-13B Progress Monitoring: Financial Progress of Repair/Improvement of 240 Existing School-com-Shelters, in 24 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Package 13 7 Shelters in
Patuakhali
Package 14 12 Shelters
in Patuakhali
Package 15 11 Shelters
in Bhola
Package 16 10 Shelters
in Bhola
Package 17 15 Shelters
in Bhola
Package 18 8 Shelters in
Bhola
Package 19 10 Shelters
in Bhola
Package 20 6 Shelters in
Bhola
Package 21 10 Shelters in Jhalokathi
Package 22 10 Shelters
in Khulna
Package 23 8 Shelters in
Satkhira
Package 24 8 Shelters in
Satkhira
Disbursed - FY2013-2014 0 0 29 0 0 0 0 0 0 0 0 0
Disbursed - FY2012-2013 3 13 32 26 0 0 0 18 33 21 0 0
Disbursed - FY2011-2012 60 57 39 46 50 72 79 77 47 64 56 62
Disbursed - FY2010-2011 37 30 0 28 50 28 21 5 20 15 44 38
0
10
20
30
40
50
60
70
80
90
100
Pe
rce
nt
(%)
of
Co
ntr
ac
t C
ost
Figure 3-13B Progress Monitoring: Financial Progress of Repair/Improvement of 240 Existing School-com-Shelters, in 24 Contract Packages (cont.) As of End of 1st Quarter FY2016-2017 (ending September2016)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 31
Package 34 18 Shelters in
Pirojpur
Package 35 8 Shelters in Jhalokathi
Package 36 41 Shelters in
Bhola
Package 37 30 Shelters in
Khulna
Package 38 27 Shelters in
Patuakhali
Package 39 10 Shelters in
Satkhira
Package 40 17 Shelters in
Barisal
Package 41 36 Shelters in
Barguna
Package 42 25 Shelters in
Bagerhat
Package 43 7 Shelters in
Bhola
Completed - 4th quarter (April-June 2016) 8 2 0 0 0 0 0 10 0 48
Completed - 3rd quarter (Jan-March 2016) 17 1 7 5 5 0 0 7 17 39
Completed - 2nd quarter (Oct-Dec 2015) 8 1 16 17 10 2 0 36 19 0
Completed - 1st quarter (Jul-Sep 2015) 7 5 13 9 7 4 2 10 10 0
Completed - FY 2014-2015 58 91 59 69 78 94 98 26 54 0
0
10
20
30
40
50
60
70
80
90
100
Pe
rce
nt (
%)
Figure 3-14A Progress Monitoring: Physical Progress of Repair/Improvement of 219 Existing School-com-Shelters, in10 Contract PackagesAs of End of 4th Quarter FY2015-2016 (ending June 2016)
Package 34 18 Shelters in
Pirojpur
Package 35 8 Shelters in
Jhalokathi
Package 36 41 Shelters in
Bhola
Package 37 30 Shelters in
Khulna
Package 38 27 Shelters in
Patuakhali
Package 39 10 Shelters in
Satkhira
Package 40 17 Shelters in
Barisal
Package 41 36 Shelters in
Barguna
Package 42 25 Shelters in
Bagerhat
Package 43 7 Shelters in
Bhola
Completed - 1st quarter (Jul-Sep 2016)
2 0 0 0 0 0 0 2 0 4
Completed - FY 2015-2016 40 9 36 31 22 6 2 63 46 87
Completed - FY 2014-2015 58 91 59 69 78 94 98 26 54 0
0
10
20
30
40
50
60
70
80
90
100
Pe
rce
nt (
%)
Figure 3-14A Progress Monitoring: Physical Progress of Repair/Improvement of 217 Existing School-com-Shelters, in 10 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September- 2016)
Package 34 18 Shelters in Pirojpur
Package 35 8 Shelters in
Jhalokathi
Package 36 41 Shelters
in Bhola
Package 37 30 Shelters in Khulna
Package 38 27 Shelters
in Patuakhali
Package 39 10 Shelters in Satkhira
Package 40 17 Shelters
in Barisal
Package 41 36 Shelters in Barguna
Package 42 25 Shelters in Bagerhat
Package 43 43 Shelters
in Bhola
Disbursed - 1st quarter (Jul-Sep 2016) 0 0 3 0 0 0 0 0 0 19
Disbursed - FY 2015-2016 34 31 49 45 43 24 15 58 53 54
Disbursed - FY 2014-2015 57 69 34 55 57 76 85 25 47 0
0
10
20
30
40
50
60
70
80
90
100
Perc
ent (
%) o
f Con
trac
t Cos
t
Figure 3-14B Progress Monitoring: Financial Progress of Repair/Improvement of 217 Existing School-com-Shelters, in 10 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Phase II
Repair/improvement activities also started in Mid-July 2014. Shown in Figures 3-14A and 3-14B are the physical and financial progress, respectively, of the 10 CPs (i.e. CPs W 34 to 43; covering 219 existing shelters in 9 districts) awarded so far. Details of the repair/improvement activities for each of the 10 CPs in Subcomponent B.2 are presented in Annex 3L: Progress Monitoring Form PMF-B3: Progress Monitoring – Package-wise Improvement of Cyclone Shelters.
As of end of September 2016, physical progress in 10 CPs covering 217 existing shelters in Pirojpur, Jhalokathi, Bhola, Khulna, Patuakhali, Satkhira, Barisal, Barguna and Bagerhat districts varies from 91% (W 41 in Barguna and W 43 in Bhola) to 100% (W 34 in Pirojpur, W 35 in Jhalokathi, W 37 in Khulna, W 38 in Patuakhali, W 39 in Satkhira, W 40 in Barisal and W 42 in Bagerhat).
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 32
Package 1 5 Access Roads in
Bagerhat
Package 2 3 Access Roads in
Barguna
Package 3 5 Access Roads in
Pirojpur
Package 4 2 Access Roads in
Barguna
Package 6 4 Access Roads in
Barisal
Package 7 3 Access Roads in
Patuakhali
Package 8 3 Access Roads in
Barguna
Package 9 4 Access Roads in Patuakhali
Completed - 1st quarter (Jul - Sept 2016)
0 0 4 0 0 0 0 0
Completed - FY 2015-2016 0 0 4 0 0 0 0 0
Completed - FY 2014-2015 0 10 25 31 0 0 19 15
Completed - FY 2013-2014 12 27 16 16 1 20 8 25
Completed - FY 2012-2013 48 13 26 28 29 55 38 50
Completed - FY 2011-2012 40 50 25 25 70 25 35 10
0
10
20
30
40
50
60
70
80
90
100
Perc
ent (
%)
Figure 3-15A Progress Monitoring: Physical Progress of Construction of 29 Access Roads (Total-68.64 Km), in 8 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Package 1 5 Access Roads
in Bagerhat
Package 2 3 Access Roads
in Barguna
Package 3 5 Access Roads
in Pirojpur
Package 4 2 Access Roads
in Barguna
Package 6 4 Access Roads
in Barisal
Package 7 3 Access Roads
in Patuakhali
Package 8 3 Access Roads
in Barguna
Package 9 4 Access Roads in Patuakhali
Disbursed - 1st quarter (Jul - Sept 2016) 0 0 11 0 0 0 0 0
Disbursed - FY 2015- 16 0 0 12 0 2 0 0 0
Disbursed - FY 2014- 15 0 38 24 46 1 13 28 44
Disbursed - FY 2013- 14 10 11 9 7 0 28 11 14
Disbursed - FY 2012- 13 58 27 28 29 22 50 36 38
Disbursed - FY 2011- 12 32 24 16 18 75 9 25 4
0
10
20
30
40
50
60
70
80
90
100
Perc
ent (
%) o
f Con
trac
t Cos
t
Figure 3-15B Progress Monitoring: Financial Progress of Construction of 29 Access Roads (Total-68.64 Km), in 8 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Improvement of Communication Network to Shelters
Phase I
Improvement activities of access roads started during the 3rd quarter FY2011-2012. Shown in Figures 3-15A and 3-15B are the physical and financial progress respectively, of the 9 CPs (i.e. CPs R 01 to R 09; covering 33 access roads in 5 districts) awarded so far under Phase I. Later on, SCR-9 in CP R02 and SCR-11 in CP R03 have been dropped and CP R05 has also been cancelled due to unavoidable circumstances. Details of the improvement activities for each of the 8 CPs in Subcomponent B.3 are presented in Annex 3M: Progress Monitoring Form PMF-B3: Progress Monitoring – Package-wise Improvement of Communication Network to Shelters.
As of end of September 2016, physical progress for 8 CPs (i.e. CPs R 01 to 04 & R 06 to R 09) covering 29 access roads (68.64 km) was reported to be 100% complete.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 33
Package 25 3 Access Roads in
Bagerhat
Package 26 5 Access Roads in
Pirojpur
Package 27 6 Access Roads in
Pirojpur
Package 5A 1 Access Road in
Bagerhat
Package 5B 1 Access Road in
Bagerhat
Package 28 9 Access Road in
Patuakhali
Package 29 9 Access Road in
Patuakhali
Package 30 9 Access Road in
Barguna
Package 31 3 Access Road in
Jhalokathi
Package 32 6 Access Road in
Barisal
Package 33 7 Access Road in
Satkhira
Package 34 7 Access Road in
Bagerhat
Package 35 10 Access
Road in
Khulna
Package 36 3 Access Road in
Barisal
Package 37 4 Access Road in
Pirojpur
Completed - 1st quarter (Jul - Sep 2016) 0 4 0 0 0 11 5 14 5 0 2 20 2 1 10
Completed - FY 2015-2016 0 25 0 30 0 43 40 41 50 43 21 20 36 32 44
Completed - FY 2014-2015 3 23 42 57 60 0 0 0 0 0 0 0 0 0 0
Completed - FY 2013-2014 63 11 42 13 40 0 0 0 0 0 0 0 0 0 0
Completed - FY 2012-2013 34 37 16 0 0 0 0 0 0 0 0 0 0 0 0
0
10
20
30
40
50
60
70
80
90
100
Pe
rce
nt (
%)
Figure 3-16A Progress Monitoring: Physical Progress of Construction of 152 Access Roads (total-260.07 Km), in 31 Contract Packages (cont.)As of End of 1st Quarter FY2016-2017 (ending September 2016)
Package 10 3 Access Roads in
Barisal
Package 11 4 Access Roads in
Patuakhali
Package 12 5 Access Roads in
Barguna
Package13 3 Access Roads in
Pirojpur
Package14 5 Access Roads in
Satkhira
Package 15 6 Access Roads in
Patuakhali
Package 16 2 Access Roads in
Bagerhat
Package 17 5 Access Roads in
Barguna
Package 18 15 Access
Roads in Bhola
Package 19 4 Access Roads in
Satkhira
Package 20 4 Access Roads in
Barisal
Package 21 6 Access Roads in
Khulna
Package 22 6 Access Roads in
Khulna
Package 23 4 Access Roads in
Satkhira
Package 24 11 Access Roads in
Jhalokathi
Completed - 1st quarter (Jul - Sep 2016) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Completed - FY 2015-2016 0 11 45 0 0 0 15 5 0 0 0 0 0 0 0
Completed - FY 2014-2015 18 35 18 0 23 2 42 42 0 17 0 15 39 59 0
Completed - FY 2013-2014 55 48 28 51 77 73 39 38 58 63 58 77 61 41 52
Completed - FY 2012-2013 27 6 9 49 0 25 4 15 42 20 42 8 0 0 48
0
10
20
30
40
50
60
70
80
90
100
Pe
rce
nt
(%)
Figure 3-16A Progress Monitoring: Physical Progress of Construction of 152 Access Roads (total-260.07 Km), in 31 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Phase II
Improvement activities of access roads started in the 3rd and 4th quarter of FY2012-2013 through 2nd quarter of FY2015-2016. Shown in Figures 3-16A and 3-16B are the physical and financial progress respectively, of the 30 CPs (i.e. CPs R 10 to 37, R 5A and R 5B; covering 162 access roads of total 263.10 Km in 9 districts) awarded so far under Phase II. Later on, SCR-96 in CP R15, SCR-91 in CP R19, SCRs-124,125,126 &132 in CP R24 and SCR-43 & 45 in CP R27 have been dropped due to unavoidable circumstances. Details of the improvement activities for each of the 30 CPs in Subcomponent B.3 are presented in Annex 3N: Progress Monitoring Form PMF-B3: Progress Monitoring – Package-wise Improvement of Communication Network to Shelters.
As of end of September 2016, physical progress for the 20 CPs (i.e. CPs R 10 to 27, R 5A and R 5B) covering 88 access roads was reported to be 100% complete.The physical progress for the remaining 10 CPs (i.e. CPs R 28 to 37) covering 63 access roads was reported to vary from 23% to 55%.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 34
Package 10 3 Access Roads in
Barisal
Package 11 4 Access Roads in
Patuakhali
Package 12 5 Access Roads in
Barguna
Package13 3 Access Roads in
Pirojpur
Package14 5 Access Roads in
Satkhira
Package 15 6 Access Roads in
Patuakhali
Package 16 2Access Roads in
Bagerhat
Package 17 5 Access Roads in
Barguna
Package 18 15 Access Roads in
Bhola
Package 19 4 Access Roads in
Satkhira
Package 20 4 Access Roads in
Barisal
Package 21 6 Access Roads in
Khulna
Package 22 6 Access Roads in
Khulna
Package 23 4 Access Roads in
Satkhira
Package 24 11 Access Roads in
Jhalokathi
Disbursed - 1st quarter (Jul - Sep 2016) 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Disbursed - FY 2015-2016 0 19 76 0 0 17 28 23 0 0 12 0 17 0 13
Disbursed - FY 2014-2015 28 34 11 0 46 19 32 41 0 39 9 31 38 73 28
Disbursed - FY 2013-2014 29 36 13 51 54 46 30 17 50 50 37 47 45 27 21
Disbursed - FY 2012-2013 33 11 0 49 0 18 10 19 50 11 42 22 0 0 38
0
10
20
30
40
50
60
70
80
90
100
Pe
rce
nt
(%)
of
Co
ntr
ac
t C
ost
Figure 3-16B Progress Monitoring: Financial Progress of Construction of 152 Access Roads (Total-260.07 Km), in 31 Contract PackagesAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Package 25 3 Access Roads in
Bagerhat
Package 26 5 Access Roads in
Pirojpur
Package 27 6 Access Roads in
Pirojpur
Package 5A 1 Access Road in
Bagerhat
Package 5B 1 Access Road in
Bagerhat
Package 28 9 Access Road in
Patuakhali
Package 29 9 Access Road in
Patuakhali
Package 30 9 Access Road in
Barguna
Package 31 3 Access Road in
Jhalokathi
Package 32 6 Access Road in
Barisal
Package 33 7 Access Road in
Satkhira
Package 34 7 Access Road in
Bagerhat
Package 35 10 Access
Road in
Khulna
Package 36 3 Access Road in
Barisal
Package 37 4 Access Road in
Pirojpur
Disbursed - 1st quarter (Jul - Sep 2016) 0 0 0 0 0 3 0 0 7 0 0 0 0 0 0
Disbursed - FY 2015-2016 0 10 0 29 0 41 37 20 52 49 10 27 35 39 41
Disbursed - FY 2014-2015 29 21 50 61 69 0 0 0 0 0 0 0 0 0 0
Disbursed - FY 2013-2014 49 14 27 10 31 0 0 0 0 0 0 0 0 0 0
Disbursed - FY 2012-2013 22 31 23 0 0 0 0 0 0 0 0 0 0 0 0
0
10
20
30
40
50
60
70
80
90
100
Pe
rce
nt (
%)
of
Co
ntr
act
Co
st
Figure 3-16B Progress Monitoring: Financial Progress of Construction of 152 Access Roads (Total-260.07 Km), in 31 Contract Packages (cont.)As of End of 1st Quarter FY2016-2017 (ending September 2016)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 35
Package 1 6 Killas in Barguna
Package 3 3 Killas in Pirojpur
Package 4 6 Killas in
Bhola
Completed - FY 2014-15 0 10 7
Completed - FY 2013-14 0 23 13
Completed - FY 2012-13 63 49 43
Completed - FY 2011-12 37 18 37
0
10
20
30
40
50
60
70
80
90
100
Perce
nt (%
)
Figure 3-17A Progress Monitoring: Physical Progress of Construction of 15 Killas (Earthwork), in 3 Contract Packages
As of End of 1st Quarter FY2016-2017 (ending September 2016)
Package 1 6 Killas in Barguna
Package 3 3 Killas in Pirojpur
Package 4 6 Killas in
Bhola
Disbursed - 1st quarter (Jul - Sept 2016) 0 0 0
Disbursed - FY 2015-16 0 37 3
Disbursed - FY 2014-15 0 8 23
Disbursed - FY 2013-14 7 23 0
Disbursed - FY 2012-13 48 15 42
Disbursed - FY 2011-12 32 17 23
0
10
20
30
40
50
60
70
80
90
100
Perce
nt (%
) of C
ontra
ct Co
st
Figure 3-17B Progress Monitoring: Financial Progress of Construction of 15 Killas (Earthwork), in 3 Contract Packages
As of End of 1st Quarter FY2016-2017 (ending September 2016)
Construction of Killas
Part A: Earthwork
Construction activities of killas i.e. earth work by CBCs started during the end of 4th quarter FY2011-2012. Shown in Figures 3-17A and 3-17B are the physical and financial progress respectively, of the 3 CPs (i.e. CPs KW 01, KW 03 and KW 04; covering 15 killas in 3 districts) awarded so far. Details of the construction activities for each of the 3 are presented in Annex 3O: Progress Monitoring Form PMF-B3: Progress Monitoring – Package-wise Construction of Killas for Earth Work.
As of end of September 2016, physical progresses for earth work by CBCs for the 3 CPs (i.e. CPs KW 01, KW 03 and KW 04) were reported to be 100% complete.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 36
Package 1 6 Killas in Barguna
Package 3 3 Killas in Pirojpur
Package 4 6 Killas in
Bhola
Completed - 1st quarter (Jul - Sept 2016) 4 0 0
Completed - FY 2015-16 7 0 9
Completed - FY 2014-15 15 13 42
Completed - FY 2013-14 10 55 49
Completed - FY 2012-13 38 32 0
0
10
20
30
40
50
60
70
80
90
100
Perce
nt (%
)
Figure 3-18A Progress Monitoring: Physical Progress of Construction of 15 Killas (Concrete Work), in 3 Contract Packages
As of End of 1st Quarter FY2016-2017 (ending September 2016)
Package 1 6 Killas in Barguna
Package 3 3 Killas in Pirojpur
Package 4 6 Killas in
Bhola
Disbursed - 1st quarter (Jul - Sept 2016) 0 0 21
Disbursed - FY 2015-16 2 58 25
Disbursed - FY 2014-15 27 0 18
Disbursed - FY 2013-14 0 24 26
Disbursed - FY 2012-13 12 18 10
0
10
20
30
40
50
60
70
80
90
100
Perc
ent (
%) o
f Con
tract
Cos
t
Figure 3-18B Progress Monitoring: Financial Progress of Construction of 15 Killas (Concrete Work), in 3 Contract Packages
As of End of 1st Quarter FY2016-2017 (ending September 2016)
Part B: Concrete work
Construction activities of killas i.e. concrete work started during the 4th quarter FY2012-2013. Shown in Figures 3-18A and 3-18B are the physical and financial progress respectively, of the 3 CPs (i.e. CPs KW 01, KW 03 and KW 04; covering 15 killas in 3 districts) awarded so far. Details of the construction activities for each of the 3 are presented in Annex 3P: Progress Monitoring Form PMF-B3: Progress Monitoring – Package-wise Construction of Killas for Concrete Work.
As of end of September 2016, physical progresses for concrete work for the 3 CPs (i.e. CPs KW 01, KW 03 and KW 04) were reported to vary from 74% to 100%.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 37
4. COMPONENT C – REHABILITATION OF COASTAL EMBANKMENTS
4.1 Background
4.1.1 Component Objective
The objective of Component C is prevention of saline inundation during normal weather and sustained crop production made possible by reducing cyclone damage. This will be achieved through the following subcomponents:
Subcomponent C.1: Rehabilitation of embankments – will finance the emergency repair to about 502 km of coastal embankments damaged during the 2007 cyclone. The repair works will be designed with improved standards so that protection can be provided in these coastal areas in future from similar storms. This will include vegetation/plantation along embankments to improve the effectiveness of these structures.
Subcomponent C.2: Design and construction supervision of coastal embankments – will finance consulting services for surveys, designs, environmental and social impact assessments, environment and resettlement management plans, and construction supervision for embankments and all works covered under Component C. This will also include resources to facilitate consultations with the local communities in identifying sites, needs and suitable design for the embankments.
The implementing agency for Component C is the BWDB of MoWR.
4.1.2 M&E of Component
M&E of Component C will be carried out for: (a) inputs and outputs (as specified in the component logical framework), (b) on the efficiency and effectiveness of the processes underlying the design and implementation of the component, and (c) the component‟s contribution towards the attainment of Project outcome. BWDB, as the implementing agency for this component, is mainly responsible for the M&E of “a” and “b”. The M&E Consultant is responsible for the consolidation, verification, and analysis of these M&E information as to their contribution to progress in the attainment of outcome (“c”).
4.2 Component C Targets
4.2.1 Physical Target
As per WB‟s Aide Memoire, March 2016 and last revised DPP covering AFII, the total physical target under Component C is the i) rehabilitation and improvement of 502.00 km of coastal embankment with following improved design standards with ii) 19000 metre bank protection, and vegetative cover over slopes. The rehabilitation/ improvement also necessitate the construction/repair of a total of 317 water control structures (WCS).
Figure 4-1 presents the cumulative targets for the rehabilitation/improvement of embankments.
The cumulative year wise targets of the subsequent calendar years are as follows: 54% of embankments by 2014; 64% of embankments by 2015; 73% of embankments by 2016 and 100% of embankments would be repaired/constructed by 2017.
The expected outcome of Component C is safety against cyclonic surges, prevention of saline inundation during high tides and drainage improvement ensuring sustained crop production.
2014 2015 2016 2017
Embankment (km) 270.00 320.00 368.00 502.00
050
100150200250300350400450500
Qu
anti
ty
Figure 4-1 Physical Targets (cumulative): Length of Embankment and Number of Water Control Strucures Rehabilitated & Improved
Source: WB's Aide Memoire, March 2016
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 38
4.2.2 Financial Target
Financial target referred to in this section is the corresponding cost for the rehabilitation/ improvement of coastal embankments and appurtenances. Indicated in Figure 4-2 are the year-wise cumulative financial targets corresponding to the physical targets shown in Figure 4-1 (Section 4.2.1).
Up to FY2013-2014, cumulative expenditure of Taka 14,848 lakh or 25% of total construction cost (Taka 59,338 lakh) has been achieved.
For subsequent fiscal years, cumulative financial targets are as follows: Taka 29,647 lakh or 50% up to FY2014-2015; Taka 46,452 lakh or 78% up to FY2015-2016; Taka 59,338 lakh or 100% up to FY2016-2017.
4.3 Component C: Process and Progress
4.3.1 Process Monitoring
As per ECRRP Project Design, a number of pre construction activities including Environmental Assessment and Social Assessment are to be carried out prior to undertaking rehabilitation/re-construction of Polders. Status of pre-construction activities of 29 polders as of end of June of FY2015-2016, are discussed in the following sections:
Contract Packages
CP 1: Polders 47/5, 52/53B (Partial works) [2 Polders]
CP 2: Polders 41/7B, 41/6B (both incomplete terminated) [2 Polders]
CP 3: Polders 39/2A (incomplete terminated) [1 Polder]
CP 4: Polders 55/2C, 55/4, 55/1 [3 Polders]
CP 5: Polders 46, 52-53A, 54/A, 47/1 [4 Polders]
CP 6: Polders 44 (P), 47/4 [2 Polders]
CP 7: Polder 42 [1 Polder]
CP 10: Polders 39/1D, 40/1 [2 Polders] CP 8 [Polder CEP] dropped & Polder 39/1A under CP 9 now included in CP 20. Polder 44(B) under CP 11 now included in CP 19; Polders 39/1B & 39/1C under CP 12 now included in CP 20; Polders 41/4 & 41/5 under CP 13 now included in CP 19.
CP 14: Polder 55/2B, 50/51 [ 2 Polders] Polder 55/2D under CP 15 now included in CP 19; Polders 45 & 43/1 under CP 16 now included in CP 19; Polder 55/3 under CP 17 now included in CP 19.
CP 18: Polders 41/6B, 41/7B & Polder 39/2A (all incomplete works), Polder 52/53B (remaining works),
CP 19: Polders 44(B), 41/4, 41/5, 55/2D, 45 43/1 & 55/3 [7 Polders]
CP 20: Polders 39/1A, 39/1B & 39/1C [3 Polders]
Details of the status of the pre-construction activities of the 29 polders are presented in Figure 4-3 & Annex 4A: Process Monitoring Form PMF-C2: Process Monitoring – Polder.
FY2010-2011
FY2011-2012
FY2012-2013
FY2013-2014
FY2014-2015
FY2015-2016
FY2016-2017
Construction cost 2,020 6,187 10,489 14,848 29,647 46,452 59,338
0
10,000
20,000
30,000
40,000
50,000
60,000
Taka
(la
kh)
Figure 4-2 Financial Target (cumulative): Construction CostSource: RDPP, 2nd Revision, BWDB (October 2013)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 39
1 2 3 4 5 6 7 8 9 10 11
Not Completed 0 0 0 3 3 3 3 0 0 0 0
Completed - 1st quarter (July - September 2016) 0 0 0 0 0 0 0 0 0 0 0
Completed - FY2015-2016 0 0 0 0 0 1 1 0 0 0 0
Completed - FY2014-2015 10 10 10 0 0 2 2 10 10 10 10
Completed - FY2013-2014 0 0 0 7 7 5 5 4 4 4 4
Completed - FY2012-2013 0 0 0 1 1 7 7 0 0 0 0
Completed - FY2011-2012 0 2 8 3 3 5 5 11 7 7 11
Completed - FY2010-2011 19 17 11 15 15 6 6 4 8 8 4
0
2
4
6
8
10
12
14
16
18
20
22
24
26
28
Nu
mb
er o
f P
old
ers
Figure 4-3 Process Monitoring: Status of Pre-construction Activities for 29 Polders As of End of 1st Quarter FY2016-2017 (ending September 2016)
Site Selection
Selection and assessment of damages of the 29 coastal polders targeted for rehabilitation/construction under ECRRP have been done.
Design Works, and Comprehensive Technical Report Approval
The embankment design of all 29 polders has been completed.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 40
Design of WCSs of all the 29 polders has also been completed.
The comprehensive technical reports of 29 polders in 12 CPs have been approved.
Environmental Assessment Report Preparation and Clearance
As of end of September 2016, IEE/EIA reports for 28 polders have been submitted by D&S Consultant to M&E Consultants through PCMU for review and clearance. Based on comments and observations of M&E Consultants, BWDB upgraded IEE/EIA reports. M&E Consultants recommended clearance of the 26 upgraded IEE/EIA reports. The polders for which IEE/EIA reports were given clearances are:
o all the 19 polders in 9 CPs o 7 polders in 2 CPs (Polders 41/4, 41/5, 45 & 43/1 in CP 19 and Polders 39/1A, 39/1B & 39/1C in CP
20).
Social and Resettlement Assessment Report Preparation and Clearance
As of end of September 2016, social and resettlement study reports for 27 polders have been submitted by D&S Consultant to M&E Consultants through PCMU for review and recommendation for clearance. Based on comments and observations of M&E Consultants, BWDB upgraded and re-submitted 26 nos. social and resettlement study reports. M&E Consultants recommended all the 26 reports for clearance. The polders for which social and resettlement study reports were given clearances are:
o all the 19 polders in 9 CPs o 7 polders [Polders 41/4, 43/1, 41/5, 45, 55/2D & 44(B) in CP 19 and Polder 39/1C in CP 20].
The social and resettlement study report for Polder 39/1B in CP20 has been reviewed by the M&E Consultant and found incomplete in so far as the complete census of the PAHs has not been furnished. BWDB has been requested to resubmit the report with the required information.
Tender Process
Contracts for the rehabilitation/improvement of the 1st targeted 19 polders in 9 CPs have been awarded.
Contracts for the pending rehabilitation/improvement works of the targeted 4 polders (Polders 41/6B, 39/2A, 52/53B & 41/7B) in CP 18 and the targeted 7 polders (43/1, 41/5, 44(B), 41/4, 45, 55/2D and 55/3) in CP 19 have been awarded. CP20 covering Polders 39/1A, 39/1B, and 39/1C has also been awarded at the end of June 2015.
4.3.2 Component C: Progress Monitoring
Rehabilitation of Polders
Rehabilitation and improvement works of the 1st targeted 9 CPs commenced in Mid-November 2010.
Rehabilitation/improvement works of 2 ICB CPs 18 and 19 have been taken up in the month of September 2014. Rehabilitation/improvement works of CP20 covering Polders 39/1A, 39/1B, and 39/1C have also been taken up during 2nd quarter of 2015-2016.
Physical Progress
The physical progress status of awarded 29 Polders is as follows:
o Works in the following polders have been completed: Polders 47/5, 52/53B (Part), 55/1, 55/2C, 55/4, 46, 52-53A, 54/A, 47/1, 47/4, 44(P), 42, 39/1D, 40/1, 55/2B & 50/51.
o Due to poor progress, contracts of polders 41/6B, 41/7B and 39/2A were terminated. At the time of termination, the progress range was between 61%-88%. These were later included in new packages.
o Polders 41/6B, 41/7B, 39/2A, and 52/53B(Part) [CP 18] : Progress range between 51% to 92%. o Polders 43/1, 41/5, 44(B), 41/4, 45, 55/2D and 55/3 [CP 19]: Progress range between 50% to 78%. o Polders 39/1A, 39/1B and 39/1C [CP 20]: Progress range between 12% to 32%.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 41
Figure 4-4 shows the physical progress of rehabilitation/improvement works of the 29 polders in 12 CPS, while Figures 4-5A and 4-5B, respectively; present the physical and financial progress in each CP. The details are shown in Annex 4B.
Pack
age 1
Polde
r 47/
5 in
Patua
khali
Pack
age 1
Po
lder 5
2/53
B in
Patua
khali
Pack
age 4
Polde
r 55/
2C
in Pa
tuakh
ali
Pack
age 4
Polde
r 55/
4 in
Patua
khali
Pack
age 4
Polde
r 55/
1 in
Patua
khali
Pack
age 5
Polde
r 46 i
n Pa
tuakh
ali
Pack
age 5
Polde
r 52-5
3A
in Pa
tuakh
ali
Pack
age 5
Polde
r 54/
A in
Patua
khali
Pack
age 5
Polde
r 47/
1 in
Patua
khali
Pack
age 6
Polde
r 44(P
) in
Patua
khali
Pack
age 6
Polde
r 47/
4 in
Patua
khali
Pack
age 7
Polde
r 42 i
n Ba
rguna
Pack
age 1
0
Polde
r 39/
1D
in Ba
rguna
Pack
age 1
0
Polde
r 40/
1 in
Bargu
na
Pack
age 1
4
Polde
r 50/
51
in Pa
tuakh
ali
Pack
age 1
4
Polde
r 55/
2B
in Pa
tuakh
ali
Pack
age 1
8
Polde
r 41/
6B
in Ba
rguna
Pack
age 1
8
Polde
r 39/
2A
in Ba
rguna
Pack
age 1
8
Polde
r 52/
53B
in Ba
rguna
Pack
age 1
8
Polde
r 41/
7B
in Ba
rguna
Pack
age 1
9
Polde
r 44(B
) in
Bargu
na
Pack
age 1
9
Polde
r 41/
4 in
Bargu
na
Pack
age 1
9
Polde
r 41/
5 in
Bargu
na
Pack
age 1
9
Polde
r 55/
2D
in Pa
tuakh
ali
Pack
age 1
9
Polde
r 45 i
n Ba
rguna
Pack
age 1
9
Polde
r 43/
1 in
Bargu
na
Pack
age 1
9
Polde
r 55/
3 in
Patua
khali
Pack
age 2
0
Polde
r39/
1A
in Ba
rguna
Pack
age 2
0
Polde
r 39/
1B
in Pir
ojpur
Pack
age 2
0
Polde
r 39/
1C
in Pir
ojpur
Comp
leted
-1st
quart
er (Ju
l -Se
pt 20
16)
00
00
00
00
00
00
00
00
01
01
10
10
00
04
10
Comp
leted
-FY2
015-2
016
00
00
00
00
00
00
00
00
2515
3127
2051
3825
4038
2028
2412
Comp
leted
-FY2
014-2
015
00
00
00
00
00
00
00
00
6135
6135
4014
3030
1040
350
00
Comp
leted
-FY2
013-2
014
00
00
00
00
00
160
00
00
00
00
00
00
00
00
00
Comp
leted
-FY2
012-2
013
4528
2219
2440
3049
7777
6954
2555
6153
00
00
00
00
00
00
00
Comp
leted
-FY2
011-2
012
2932
1721
3660
7051
2323
1046
7545
3947
00
00
00
00
00
0
Comp
leted
-FY2
010-2
011
2640
6160
400
00
00
00
00
00
00
00
00
00
00
00
00
0102030405060708090100
Percent (%)
Figur
e 4-4
Prog
ress
Mon
itorin
g: Ph
ysica
l Pro
gress
of 29
Polde
rs, in
12 Co
ntrac
t Pac
kage
s Awa
rded
As of
End o
f 1st
Quart
er FY
2016
-2017
(end
ing Se
ptem
ber 2
016)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 42
Package 1 in Patuakhali
Package 2 in Barguna
Package 3 in Barguna
Package 4 in Patuakhali
Package 5 in Patuakhali
Package 6 in Patuakhali
Package 7 in Barguna
Package 10 in Barguna
Package 14 in Patuakhali
Package 18 in Patuakhali
& Barguna
Package 19 in Patuakhali
& Barguna
Package 20 in Barguna & Pirojpur
Completed - 1st quarter (Jul - Sept 2016) 0 0 0 0 0 0 0 0 0 1 1 1
Completed - FY2015-2016 0 0 0 0 0 0 0 0 0 28 35 25
Completed - FY2014-2015 0 0 0 0 0 0 0 0 0 42 30 0
Completed - FY2013-2014 0 5 25 0 0 18 0 0 0 0 0 0
Completed - FY2012-2013 40 43 24 20 53 70 53 38 58 0 0 0
Completed - FY2011-2012 26 33 30 26 47 12 47 62 42 0 0 0
Completed - FY2010-2011 34 9 6 54 0 0 0 0 0 0 0 0
0
10
20
30
40
50
60
70
80
90
100
Pe
rce
nt (
%)
Figure 4-5A Progress Monitoring: Physical Progress in 12 Contract Packages Awardedof End of 1st Quarter FY2016-2017 (ending September 2016)
Package 1 in Patuakhali
Package 2 in Barguna
Package 3 in Barguna
Package 4 in Patuakhali
Package 5 in Patuakhali
Package 6 in Patuakhali
Package 7 in Barguna
Package 10 in Barguna
Package 14 in Patuakhali
Package 18 in Patuakhali
& Barguna
Package 19 in Patuakhali
& Barguna
Package 20 in Barguna &
Pirojpur
Disbursed - 1st quarter (Jul - Sept 2016) 0 0 0 0 0 0 0 0 0 0 0 0
Disbursed - FY 2015-2016 0 0 0 0 0 0 0 0 0 23 18 29
Disbursed - FY 2014-2015 0 0 0 0 0 0 0 0 0 43 41 0
Disbursed - FY2013-2014 0 17 36 0 0 0 0 0 0 0 0
Disbursed - FY2012-2013 40 24 2 25 55 70 60 47 55 0 0 0
Disbursed - FY2011-2012 17 21 19 28 45 30 40 53 45 0 0 0
Disbursed - FY2010-2011 43 17 20 47 0 0 0 0 0 0 0 0
0
10
20
30
40
50
60
70
80
90
100
Pe
rce
nt (
%)
of
Co
ntr
act
Co
st
Figure 4-5B Progress Monitoring: Financial Progress in 12 Contract Packages AwardedAs of End of 1st Quarter FY2016-2017 (ending September 2016)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 43
5. COMPONENT D – LONG-TERM DISASTER RISK MANAGEMENT PROGRAM
5.1 Background
5.1.1 Component Objective
The objective of Component D is to strengthen disaster risk mitigation and reduction capacity and ability of the Government in the medium- and long-term. This will be achieved through the following subcomponents:
Subcomponent D.1: Disaster risk mitigation and reduction – will support the capacity building of the DDM, support for detailed multi-hazard risk vulnerability modeling and assessment, and the strengthening of emergency preparedness at the community level.
Subcomponent D.2:Preparation of future projects for River Bank Improvement, and Coastal Embankment Improvement Programs – will finance the preparation studies for selected activities under the first phase of the identified long-term program. This includes studies related to the River Bank Improvement Program (RBIP) for revamping the Brahmaputra River Bank Embankment (BRE) starting from the town of Sirajganj to the town of Kazaipur and moving northwards, and Coastal Embankment Improvement Program (CEIP).
Subcomponent D.3:Preparation of future projects for disaster shelters and up-gradation of rural road network – will finance preparation studies for: (i) construction of new disaster shelters, and (ii) up-gradation of rural road network in the disaster prone areas. This would cover feasibility studies and surveys for the whole investment, and tender designs and bidding documents for first package.
Department of Disaster Management [DDM] of the MoDMR is the implementing agency for Subcomponent D.1, BWDB for Subcomponent D.2 and LGED for Subcomponent D.3 respectively.
5.1.2 M&E of Component
M&E for Component D will be carried out for: (a) inputs and outputs (as specified in the component logical framework), (b) on the efficiency and effectiveness of the processes underlying the design and implementation of the component, and (c) the component‟s contribution towards the attainment of Project outcome. DMB, BWDB and LGED as the implementing agencies for Subcomponents D.1, D.2 and D.3, respectively, are mainly responsible for the M&E of “a” and “b” for their respective subcomponent. The M&E Consultant is responsible for the consolidation, verification, and analysis of the information as to their contribution to progress in the attainment of outcome (“c”).
5.2 Component D.1: Disaster Risk Mitigation and Reduction- Targets and Progress
5.2.1 Subcomponent D.1: Targets
The physical targets for Subcomponent D.1 includes, among others: (i) enhanced DDM‟s capacity for designing, standardizing and implementing a post-disaster damage and needs assessment (DNA), across all concerned government departments, and at various administrative levels, down to the district and upazila; (ii) detailed, national level multi-hazard risk and vulnerability assessment, modelling and mapping at various levels down to the district and upazila; and (iii) strengthened and enhanced emergency preparedness in 12 severely cyclone affected districts and upazila. The amount of financing for this subcomponent is about Taka 7,744.00 lakh per the recently approved third RDPP.
The year-wise physical and financial targets have been taken from the third approved RDPP of DDM.
The defined activities of DDM per subcomponent D.1 are as follow:
Development of Operational Manual of the Project
Recruitment of International and National Experts and MVA firm
Establishment of a DNA Cell within DDM
Establishment of a Multi-Hazard Risk and Vulnerability Assessment (MRVA) Cell within DDM
Develop tools for education, training and awareness raising in the field
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 44
Develop awareness raising sign board, bill board, public place painting with DP message in the field
Planning, training, supporting and building the capacity of DDM
Building capacity of the various sub-national disaster management committees in selected district
DNA training at national level
DNA training for the field staff
MRVA training at Regional level
DNA training for the City Corporation Level
Stakeholder planning workshop
Training of DMC/ CPP officials
Simulation exercise within DMCs
National and field level policy workshops
Advance DM Course for Master Trainers: International
MRVA modelling and Information Management- international course
Research based field study: Hurricane and Typhoon affected countries
Hazard Maps Reproduction
Book and Report publication
DMB website development
Procurement of emergency vehicle for DDM and procurement of emergency equipment and vehicles for effective communication and response
The subcomponent‟s detailed work program for FY2016-2017 is shown in Annex-5.
5.2.2 Component D.1: Progress [DDM]
Progress as on September 2016 on key component tasks under Subcomponent D.1 are as follows:
(i) Procurement of International Consultancy Firm for Multi-hazard Risk and Vulnerability Assessment (MRVA), Modelling and Mapping – Contract for the consultancy service had been signed with ADPC on 15 December 2011. The Consultants were mobilised in the month of January 2012. Consultants summarised the major scope of works as follows:-
a) To identify all hazard prone areas in Bangladesh, b) To assess the exposure of people, property, infrastructure and economic activities to above mentioned hazards, c) To assess full range of vulnerabilities of the exposed elements experienced throughout the country with reference to above hazards, and d) To influence sectoral development strategies towards recognizing the highly dynamic form of vulnerabilities and factoring an understanding into institutional, legislative and organizational systems for preparedness, planning and mitigation.
ADPC, the Consultants submitted Interim and Quarterly Reports in phases. These were duly reviewed by the standing technical committee. Draft Final Report on MRVA had been submitted on June 2015. The MRVA Final Report and all deliverables were due in May 2016.
MRVA Cell has of late conducted the last Technical Advisory (TAC) meeting on 21 December 2015. ADPC prepared the following final documents:
Volume I: Hydro-Meteorological Hazard Assessment (Flood, Cyclone Storm Surge, Landslide and Drought) Volume II: Geological Hazard Assessment (Earthquake, Tsunami, Technological Health) Volume III: Elements and Risk Volume IV: Exposure, Vulnerability and Risk Assessment of Hydro-meteorological Hazards Volume V: Exposure, Vulnerability and Risk Assessment of Geological Hazards, and Volume VI: Summary and Recommendations.
The MRVA reports were accepted with some recommendations. The final reports covering the recommendations is in the press for printing and expected to be published in October 2016.
(ii) Recruitment of International DNA Specialist – It was not possible to recruit IDNA Specialist even after advertising in the daily news papers three times. As per recommendation of DDM, WB gave consent to hire IDNA Specialist on sole source basis but no IDNA Specialist could be procured. DDM agreed to look for an alternative person for the position of DNA Specialist through hunting, either national or
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 45
international. Dr. Khurshid Alam, a national DNA Specialist lately joined but has since quit the job. Mr. M.A Latif has joined as new national DNA Specialist in February 2015.
(iii) Recruitment of MRVAand MIS- GIS Specialist –Mr. Md. Shariful Alam Chowdhury has joined as MRVA (Multi-Hazard Risk and Vulnerability Assessment) and MIS- GIS Specialist on February, 2015.
(iv) Recruitment of Financial Management and Procurement Specialist (FMPS)-The recruitment had been completed in February 2012 but the specialist left the job. During mid-term mission, it was decided that there would be two positions, one FM Specialist and one Procurement Specialist. In the meantime, recruitment process to engage one specialist to perform as FMPS has been completed. She joined to her works on 05 May 2013 but worked only up to November 2014 when she left the job. Mr. Md. Mozibor Rahman lately joined as FMPS in July 2015.
(v) Establishment of Multi-Hazard Risk and Vulnerability Assessment (MRVA), Modeling and Mapping Cell – The MRVA Cell has since been established physically and institutionally. Formal inauguration of the MRVA and DNA Cells was done by the Secretary, Ministry of Disaster Management on 25 February, 2015. A Director and three persons have been nominated to form the MRVA cell within DDM. The cell should have been manned by full time persons who will gain expertise and will run MRVA modeling and mapping unit even after close of the project. The cell has been equipped with required equipment. As part of MRVA contract, there is provision of training and capacity building of DDM personnel. Three persons from DDM and Ministry attended 9 week training in the Netherlands [International Institute for Geo-information Science and Earth Observation, University of Twente] on Disaster Risk Management and Environmental Assessment for Spatial Planning.
(vi) Establishment of the Damage Needs Assessment (DNA) Cell –DNA Cell had been established long since but its functioning was not been quite effective in absence of the DNA Specialist. Mr. M.A. Latif has lately joined as DNA Specialist.
Per the third RDPP, DDM activities have been extended up to December 2016.
Installation of DNA Software: The DNA software has been installed in sub-domain at Bangladesh Computer Council. The URL is: dna.ddm.gov.bd.
Imparting Simulation training to DC, UNO, DRRO and PIOs of 64 districts.
Printing of the Operation Manual of the DNA Software,
Making publicity amongst the people regarding „Citizen Reporting of Disasters to Administration‟ aspect of DNA software. The task will be taken up soon.
Development of Digital Elevation Model. The DEM issue is under process with SOB and is expected to be finalized by mid October 2016.
Preparation of Multi-hazard Risk Atlas. Editing of Multi-hazard Risk Atlas is going on. The final product is expected to be received by October 15, 2016.
Software Update and Integration to DNA Updating and up-gradation of the DNA software to examine compatibility of satellite information using DNA software with Real Time Information, make the software bi-lingual and develop Mobile Apps: EOI for pre-qualification of Firm for Software update and Integration to DNA software had been floated on 6 April, 2016. Contract had been awarded on August 02, 2016. Progress of work is 40% as of September 30, 2016.
National Workshop on Multi-Hazard Risk and Vulnerability Assessment (MRVA)- has been completed in January, 2016.
DDM in-house GIS training on MRVAM products in MRVA Cell DDM has completed GIS training from 9 – 29 February, 2016.
Geo-Node Database. A meeting was held with Bangladesh Computer for integrating GIS database in geo node. The work with BCC is under process.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 46
Assessment of Component Impact. Assessment indicators and baseline status has been finalized. The impact evaluation is under process.
(vii) National DNA training for DDM and other departments– A number of training has been organized to disseminate the system and a good number of recommendations have been received. Based on recommendations from the stakeholders, fine tuning of the software has been completed.
(viii) DNA Training for field officials.- 128 training programs have been conducted
(ix) Training of CPP volunteer forces,- 144 nos. training of CPP volunteer force have been done so far against the target of 144 nos. the progress is 100%.
(x) Advanced Disaster Management Training- Training has been done.
(xi) National & Field Level Policy Workshop- One national policy workshop has been done.
(xii) Training of DMCs- 72 training sessions of DMCs have been made so far. The progress is 100%.
(xii) Simulation Exercise – 72 nos. simulation exercises with DMCs have been done so far. The progress is 100%
(xiii) Procurement of Vehicles and Equipment – 4 WD emergency vehicles, Microbus, Emergency Pick Up, Car, Computers, Hazard Mapping Equipment etc. have already been procured. Supply of Hazard Mapping Software has been completed.
(xiv) Capacity Building on Multi-hazard Risk Assessments, Modelling and Mapping (MRVA)- Capacity building trainings in 64 districts have been done. The participants were DRRO, PIO, UNO and other technical officials associated with Disaster Risk Reduction.
Detailed status of procurement and expenditure of Emergency Search and Rescue Equipment, Emergency Vehicle and Office Equipment and Training is given in Annex-6.
Financial Progress Tk. 7,490.66 lac (96.73%)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 47
5.3 Subcomponent D.2: Preparation of Future Projects for River Bank Improvement, and Coastal Embankment Improvement Programs
5.3.1 Subcomponent D.2: Preparation of Future Projects for River Bank Improvement, and Coastal Embankment Improvement Programs
The subcomponent D.2 finances under the first phase preparation studies of two identified long-term programs – i.e. River Bank Improvement Program (RBIP) for revamping the Brahmaputra River Bank Embankment (BRE) starting from the town of Sirgajanj to the town of Kazaipur and moving northwards, and Coastal Embankment Improvement Program (CEIP). BWDB undertook the studies by engaging consultants. Study of CEIP was completed in FY 2013-14 (Figure 5-1) and that of RBIP was completed in FY2014-15 (Figure 5-2).
On 18 August 2010, the Letter to Proceed for the consultancy services for the Technical Feasibility Studies and Detailed Design for Coastal Embankment Improvement Program was issued to the consortium of CES (India), DevCon (BD), Kranti Associates (BD) and DPM (BD). The Consulting Services are divided into two phases as follows:
Phase 1 / Assignment A includes: i) study of entire coastal polders to make a revamping plan, ii) make a comprehensive Coastal Embankment Improvement Study of selected polders which will have detailed feasibility study including feasibility level design. This will also include making detailed design, preparation of estimates and bidding documents for the first year implementation program
Phase 2 / Assignment B: Construction supervision, project management support for the revamping of polders prioritized under Assignment A.
The CEIP Study Consultants were mobilized on 16 September 2010. The study has since been completed by September 2012. The consultancy contract has been extended up to September 2013 to take care of some additional works relating to the study. Final Report has been submitted.
Consultants for the study of RBIP have been recruited. Study has been completed.
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
FY2010-2011
FY2011-2012
FY2012-2013
FY2013-2014
FY2010-2011 FY2011-2012 FY2012-2013 FY2013-2014
CEIP 6.6% 26.7% 50.8% 100.0%
Figure 5-1 Physical Targets (cumulative): Consultancy Services (CS) for Technical Studies (TS) & Detail Engineering (DE) for Coastal
Embankment Improvement Program (CEIP)Source: RDPP, 2nd Revision, BWDB (October 2013)
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
FY2010-2011
FY2011-2012
FY2012-2013
FY2013-2014
FY2014-2015
FY2010-2011 FY2011-2012 FY2012-2013 FY2013-2014 FY2014-2015
RBIP 4.5% 18.3% 34.7% 68.3% 100.0%
Figure 5-2 Physical Targets (cumulative): Consultancy Services (CS) for Technical Studies (TS) & Detail Engineering (DE) for River Bank
Improvement Program (RBIP)Source: RDPP, 2nd Revision, BWDB (October 2013)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 48
6. COMPONENT F – PROJECT MANAGEMENT, TECHNICAL ASSISTANCE, STRATEGIC STUDIES AND TRAINING, AND EMERGENCY SUPPORT FOR FUTURE DISASTER
6.1 Component Objective
Component F will support the Government in implementing the Project, coordinating all project related activities, and provide resources for needed strategic studies, technical assistance and training. This includes:
Subcomponent F.1: Support for the operation of the PCMU within the MoP.
Subcomponent F.2: Consulting services, studies and other related activities for establishing financing facility to fund recovery from disasters in Bangladesh i.e. establishment of disaster management response fund/facility (DMRF).
Subcomponent F.3: Strategic studies and other pilot projects which may be identified during the project implementation.
Subcomponent F.4: Technical assistance and training in such areas as disaster management and preparedness, construction, contract management, financial management, training on environmental and social assessment and Financial Audit.
Subcomponent F.5: Support for emergency recovery from a future disaster that may occur during the implementation period of the project. Presently, there is no allocation in the sub-component.
The PCMU is implementing this component.
6.2 Component Progress
Monitoring and Evaluation for Component F will be carried out for: (a) inputs and outputs (as specified in the component logical framework), (b) on the efficiency and effectiveness of the processes underlying the design and implementation of the component, and (c) the component‟s contribution towards the attainment of Project outcome. PCMU as the implementing agency for Subcomponents F.1, F.2, F.3, F.4 and F.5 is mainly responsible for the M&E of “a” and “b” of their respective subcomponent/s.
Subcomponent F.1: PCMU is responsible for overall coordination and monitoring of the project on behalf of Planning Commission. Per project concept, the Component Project Directors of LGED, BWDB and DMB and CTA of FAO are to submit quarterly and annual work plans, budgets, and progress reports to the PCMU. PCMU with the help of implementing agencies will prepare consolidated annual report of each year of project implementation.
PCMU is functioning well and carrying out co-ordination responsibility as required and helping the implementation agencies to address issues.
PCMU signed amended contract with FAO on 15 December 2011. The contract with FAO ended on 30 June 2014.
PCMU also hired SMEC INTERNATIONAL PTY LIMITED with association of DPDS and ACE Ltd. to render services for the M&E Consultancy. The contract ended on 30 June 2014.
On the expiry of the M&E Consultancy contract with SMEC International, the second spell contract for M&E Consultancy Services for ECRRP was signed on 16 September 2014 between PCMU and DPDS. The second spell M&E Consultancy service commenced on 17 September 2014 and it will continue up to end of December 2017.
Contract had also been signed with Rahman Mostafa Alam & Co. & Ahmad Akhtar JVC Chartered Accountants to conduct consultancy services for Audit of the Books of Accounts and Records of ECRRP. The Chartered Accountants Firms started their job with effect from 22 February 2012. The firms submitted draft audit report. In the mean time their contract period has ended.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 49
PA+Grant
(US$ in million)
Total Cost BDT:
(in lac Taka)(in lac Taka)
(% of Approved
Revised Cost)
FAO
DAE A.1: Crops 10,997.31 10,720.83 –– –– 10,720.83 97.49%
DoF A.2: Fisheries 5,989.54 5,782.80 –– –– 5,782.80 96.55%
DLS A.3: Liivestock 6,889.50 6,712.99 –– 6,712.99 97.44%
LGED
B: Cyclone Shelters
D3: Study of new
shelters
BWDB C:
Rehabilitation of
coastal embankments
D2: Study of CEIP &
RBIP
DDM
D1: Improving disaster
preparedness
20.82 7,744.00 7,428.43 209.00 62.23 7,490.66 96.73%
PCMU
E&F: M&E of ECRRP
& Project Management
5.30 13,288.00 4,938.44 500.00 48.39 4,986.83 37.53%
Total 338.63 315,128.35 209,400.06 40,389.00 7,204.27 211,650.03 67.16%
Cumulative Expenditure up to
September -2016PIA/
Component/
Subcomponent
Approved Prioject CostExpenditure up to
June -2016
(in lac Taka)
ADP Allocation
in FY 2016-2017
(in lac Taka)
14,580.00 47,204.46 62.90%
2,069.35 128,751.46 65.97%
70.00
Expenditure upto
September,2016
(FY2016-2017)
(in lac Taka)
Expenditure upto
September,2016
(FY2016-2017)
(in lac Taka)
27.80
201.45
83.26
126,682.11 25,100.00
75,050.00 47,134.46
195,170.00
Subcomponent F.2: Terms of Reference of the services to be rendered by the Consultants for disaster management response fund/facility is to be prepared for PCMU. One draft TOR was prepared by AHM Rezaul Kabir, former Secretary, Government of Bangladesh. No firm has been engaged to undertake study to use Disaster Management Response Fund (DMRF). PCMU engaged one experienced firm to produce a documentary film to capture outcomes of various components of the project up to mid-term. Final version of the film had been delivered. The CD of video film has been distributed to all stakeholders by PCMU. It is a good production depicting disaster scenario, component wise project interventions for improved livelihood of target group, impact status on the beneficiaries etc.
Subcomponent F.3: Ministry of Food and Disaster Management was entrusted to develop storage facilities to allow storage of grain, mostly rice that can be utilized during disasters. A MOU between Department of Food and PCMU had been signed on 30 May 2011 to conduct a feasibility study to prepare a project on “Bangladesh Modern Food Storage Facilities Project (BMFSFP). DG, Food undertook project studies involving i) assessment of storage capacity required; ii) assessment of the existing storage capacity, condition of various storages and location; iii) criteria for location of new storage capacity; iv) assessment of existing type of storages, godowns, silos of various nature and ideas best storage etc. Study Consultants submitted final feasibility study report.
Based on the findings of the study report, a new project to construct food silos, distribution of household silos etc. has been taken by the Food Ministry being financed by the World Bank.
Subcomponent F.4: PCMU selected Mr. Badrul Alam Tarafdar as the Training and Logistic Support Specialist. He submitted „National and International Training Need Assessment Report‟ on 05.01.2012. Local training programs and foreign study visits are being organized in phases. The contract with Mr. Badrul Alam Tarafdar has been completed in June 2013.
Subcomponent F.5: It was meant to make provision of keeping reserve fund to support emergency recovery from any future disaster occurrences. However, there is no allocation as reserved fund
6.3 Project Financial Statement
The total project funding according to approved 2nd RDPP is Tk.31,053.23 Million (Foreign Aid US$398.06 Million). The component-wise allocation, expenditure up to September 2016, ADP allocation during FY 2016-2017, expenditure up to the first quarter of FY 2016-17 and cumulative expenditure up to September 2016 is shown in Table 6.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 50
7. COMPONENT E – M&E of Project Impact
7.1 Scope of Works
The scope of work of Monitoring and Evaluation Consultants is to carry out independently the following activities of all Components of ECRRP:
1) Overall monitoring and evaluation of project implementation of all Components;
2) Carry out independent monitoring of project progress, inputs, outputs, outcomes and impacts of overall project activities performed by the implementing agencies;
3) Review and monitor specific social and environmental management plans and assessments, supervision of compliance of social and environmental safeguards;
4) Evaluate project impact on disaster risk reduction measures on the communities against specified indicators
5) Help reinforce overall transparency and governance during project implementation;
6) Monitor compliance of Operational Specific Risk Mitigation Matrix, and
7) Provide feedback to PSC, PCMU, Implementing Agencies on project implementation performance, issues and impact of its various components.
The M&E Consultant is directly accountable to the PSC, but the PCMU will be responsible for its contract management and supervision on behalf of the PSC.
The second spell M&E Consultant has 9 particular tasks to be performed which are listed below:
Task 1: Track key indicators (input, output, outcome and operational risks) during project implementation;
Task 2: Carry out process & progress monitoring of the Project;
Task 3: Recommend appropriate corrective actions, if any
Task 4: Supervise the implementation and compliance of the Environmental Management Framework (EMF) and Social/Resettlement Policy Framework (S/RPF);
Task 5: Prepare and submit consolidated quarterly and annual progress reports;
Task 6: Conduct and Prepare Annual Evaluation Report 2014 with necessary sample survey;
Task 7: Conduct and Prepare Annual Evaluation Report 2016 with necessary sample survey;
Task 8: Prepare Implementation Completion Report (ICR) at the end of the Project; and
Task 9: Any other related task assigned by the World Bank, ECRRP PSC and PCMU time to time as on required.
In performing the above tasks, the M&E Consultants will follow the Comprehensive M&E Framework developed in the first spell.
7.2 Comprehensive M&E Framework for ECRRP
The Comprehensive M&E framework for ECRRP describing the plan of monitoring and evaluation of project activities had been developed under the first spell SMEC contract of M&E Consultancy services. The same M&E Framework/ Strategy Report with updated Results Framework and Logical Framework (covering activities under additional funding) will be followed by the different Project Components and the M&E Consultants during the second spell of project implementation up to 2017.
The progress in the performance of the M&E tasks as of 30 September 2016 has been presented in the succeeding sections:
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 51
7.3 Tracking key indicators (input, output, outcome and operational risks)
The tracking/monitoring of project components‟ inputs and outputs (through their respective indicators), evaluation of progress towards outputs, and reporting to PCMU are mainly the responsibility of the PIAs. The M&E Consultant team in cooperation of the field staff and DS Consultants of the respective PIAs is responsible for the consolidation, verification and analysis of the information so as to determine PIAs contribution of progress in the attainment of targeted outcome. The Consultants‟ specialists also conduct regular verification/validation of information for quality control purposes with the assistance of field staffs of the PIAs.
A matrix to reflect changes in the values of the key indicators in the M&E Framework was prepared by M&E Consultants in collaboration with the PIAs during 1st phase of M&E Consultancy services by SMEC International. Right from the beginning, this has been regularly updated and included in the report as Annex 7: “Quarterly and Annual Actual Vs Target Values for Indicators of Outputs and Outcomes”. Tracking Key Project Indicators is a continuous process and it will be continued by the second spell M&E Consultants (DPDS) till end of the project. As implementation of Component A has already been completed, tracking of indicators of this Component would not be necessary.
Besides basic Key Indicators mentioned in M&E Framework, WB also proposed special indicators to track quarterly Output-Outcome status of project interventions of different Components. This has also been regularly updated and included in the progress reports as Annex 8.
7.3.1 Compliance Report on Operational Specific Risk Mitigation
PAD of ECRRP identified at appraisal stage certain operational risks as listed in „Operational Specific Risk
Mitigation Matrix‟. M&E Consultants are responsible to monitor the status of fulfilment of the various steps
taken by the PIAs to overcome the risks listed in the „Operational Specific Risk Mitigation Matrix‟. The M&E
Consultants submit compliance report on Operational Specific Risk Mitigation Matrix at regular intervals.
As part of the scope of services of the second spell M&E Consultancy contract, the Consultants would continue
to carry out periodical monitoring of compliance of the measures on the project specific Operational Specific
Risks Mitigation Matrix by different Implementing Agencies till end of the project. The last update on the risk
mitigation matrix compliance was done in June 2016.
Carry out Process and Progress Monitoring of the Project
Monitoring and evaluation of the efficiency and effectiveness of the processes underlying the design and implementation of the project components is ongoing. These are discussed in detail in Chapters 2, 3, 4 and 5 for Components A, B, C and D, respectively. As component A has already been completed, there has been no process and progress monitoring of component A since June 2014.
7.4 Supervision in the Implementation and Compliance of the EMF and S/RPF
Presented in the succeeding sections are the activities that were so far undertaken by the M&E Consultant in the supervision of implementation and compliance of the EMF and S/RPF.
7.4.1 Review and Supervision of EMF
Activities performed by the M&E Consultant with respect to project environmental safeguards are: (i) review of IEEs/EIAs prepared and submitted by the PIAs of Components B & C. If any inconsistencies or shortcomings are detected during review, the M&E consultants make observations to rectify or overcome the shortcomings. If the reports are found consistent with the EMF, M&E Consultants recommend clearance of the IEEs/EIAs with advice to the Agencies to ensure compliance of EMPs at the field level of Components B & C interventions.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 52
Review for and Recommendation Clearance of IEEs/EIAs
Subcomponent B.1: Construction of New Shelters – As of end of September 2016, 350 new school-cum-cyclone shelters in 56 CPs (CPs 1 to 13 and CPs 14 to 56 and CP 08A ) had been submitted to the PCMU for review by the M&E Consultants. On due review, M&E Consultants has recommended clearance of all 350 new shelters.
Subcomponent B.2: Improvement of Existing Shelters – As of end of September 2016, LGED had submitted IEE/EIA reports for 459 existing school-cum-cyclone shelters in 35 contract packages. Following due process, the M&E Consultants has recommended clearance for all 459 existing school-cum-cyclone shelters.
Subcomponent B.3: Improvement of Communication Network to Shelters – Environmental Assessment study reports (IEE/EIA) for 36 CPs (R 01 to R 37 except R 05) covering 178 access roads have been received so far. Following due process, the M&E Consultants has recommended clearance for 178 access roads.
Construction of Killas (Under Subcomponent B.1) – Environmental assessment study reports (IEE/EIA) for 15 Killas in 3 CPs ( KW-01, KW-03 and KW-04) have been received, evaluated and clearance recommended.
Component C: Rehabilitation of Coastal Embankments – Recommendations for clearance were given by the M&E Consultants to environmental assessment reports of 26 polders in 11 contract packages.
Details of the M&E Consultant‟s review and clearance of the IEE/EIA reports as of September 2016 is given in Table 7-1
Table 7-1: Summary of Review and Recommendation for Clearance of IEE/EIA Reports
Quarter/FY
Component B, LGED Component C, BWDB
Remarks
Construction of New Shelter (No of packages)
Improvement of Existing Shelters
(No of packages)
Improvement of Communication Network to
Shelters (No of packages)
Construction of Killa (No of packages) Rehabilitation of Coastal
Embankment (CE)
Recd.
Action taken
Recd.
Action taken Action taken Recd.
Action taken
Recd.
Action taken
Comment
s Clearance
Comments
Clearance
Recd.
Comments
Clearance
Commen
ts
Clearance
Comments
Clearance
FY2009-2010
0 0 0 0 0 0 4 0 4
Environmental reports cleared
subject to
concurrence by
WB
FY2010-2011
2 0 2 25 0 25 13 0 11
FY2011-2012
11 0 11 0 0 0 2 0 3
FY2012-2013
14 0 6 0 0 0 0 0 1
FY2013-2014
14 0 22 0 0 0 18 0 0 0 0 0 7 0 7
FY2014-2015
4 0 4 4 0 4 8 0 26 3 0 0 2 2 0
FY2015-2016
11 0 11 6 0 6 10 0 10 0 0 0 0 0 0
1st Quarter FY2016-
2017
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total 56 0 56 35 0 35 36 0 36 3 0 3 28 2 26
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 53
Environmental Management Issues in Component B Interventions (LGED)
As we know, Component B Interventions are;
i) Construction of new Shelters. ii) Rehabilitation and Improvement of old Shelters iii) Construction of Shelter Access Roads; and iv) Construction Killas.
The above activities generally give rise to following hazards:
a) Interruptions in holding classes due to space limitations b) Occupation of class rooms by labors in absence of labor sheds c) Non-availability of sweet drinking water for the labours and also for construction works d) Creation of sound pollution. e) Generation of dust pollution f) Creation of danger to safety due to construction activities g) Creation of sanitary hazards h) Creation of water logging due to unplanned works with no drainage facilities i) Piling up of construction wastes etc.
Environmental Management Plan [EMP] and its Compliance- LGED
Depending upon the nature and location of work, separate environmental management plans for each package are formulated to overcome the consequent hazards. The construction activities might cause impacts and nuisance to nearby surroundings. These need to be avoided or mitigated through application of good engineering practices and strict environmental safeguard measures including use of environment-friendly construction materials and equipments, waste management techniques especially dust and debris control, noise control, site management, safety controls, provision of clean water and sanitation facilities etc. The package specific EA reports are reviewed and cleared by the M&E Consultants.
The main responsibility of ensuring adoption of the EMP measures lies with LGED and the D&S Consultants of Component B. For the implementation of the EMP, it is essential that an effective monitoring system is established. For this purpose, an Environmental Management Unit (EMU) with skilled staff in the LGED supervision team should be established. EMP compliance will be ensured by the EMU which should be reflected in the periodical progress reports. The M&E Consultants would also periodically monitor compliance of the EMPs.
Environmental Management Issues in Component C Interventions (BWDB)
As we know, Component C Interventions are mainly;
i) Construction of New Earthen Embankments, ii) Re-construction of Existing Embankment
iii) Construction of New Regulators/ Sluices
iv) Re-construction of existing Regulators/ Sluices v) River Bank Revetment Works to protect erosion.
Construction activities of the above works generally create multiple environmental hazards. Hazards identified so far are:
a) Temporary disruption of thoroughfare b) Shortage or no accommodation for the labours c) Non-availability of sweet drinking water for the labours and also for construction works d) Creation of sound pollution. e) Generation of dust pollution f) Creation of danger to safety due to construction activities g) Creation of sanitary hazards h) Creation of water logging due to unplanned works i) Piling up of construction wastes etc. j) Cutting of trees etc
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 54
Environmental Management Plan [EMP] and its Compliance- BWDB
Depending upon the nature, type and location of work, separate environmental management plans are formulated for each polder to overcome the hazards. The construction activities envisaged might cause impacts and nuisance to nearby surroundings, they need to be avoided or mitigated through application of good engineering practices and strict environmental safeguard measures including provision of by-pass roads, use of environment-friendly construction materials and equipments, waste management techniques especially for construction dust and debris, noise control, site management, safety controls, provision of clean water and sanitation facilities etc. The package specific EA reports are reviewed, updated and cleared by the M&E Consultants.
The main responsibility of ensuring adoption of the EMP measures lies with BWDB and the D&S Consultants of Component C. For the implementation of the EMP, it is essential that an effective monitoring system is established. For this purpose, an Environmental Management Unit (EMU) in the BWDB supervision team should be established. EMP compliance will be ensured by the EMU which should be reflected in the periodical progress reports. The M&E Consultants eventually would also periodically monitor compliance of the EMPs.
7.4.2 Review, Clearance and Supervision of S/RPF
The activities performed by the M&E Consultant with respect to Project social and resettlement safeguards include: (i) review, suggest improvements and recommend clearance of social and resettlement study reports prepared by the Components B and C; and (ii) supervision of the compliance of Social Management Plans (SMPs) and Abbreviated/ Resettlement Action Plans (ARAP/RAPs).
Review and Clearance of Social and Resettlement Assessment Reports
Component B: LGED
Subcomponent B.1: Construction of New Shelters – The social and resettlement study reports for 329 new school-cum-cyclone shelters in 52 CPs were received. After review, the M&E Consultant recommended clearance to the reports for 329 shelters.
Subcomponent B.2: Improvement of Existing Shelters – Social and resettlement study reports for all the 250 existing shelters in 25 CPs under Phase I had been received by the M & E Consultants. On due review, the M&E Consultants recommended clearances of all the reports.
As of September 2016, social and resettlement study reports for 196 existing school-cum-cyclone shelters in 10 CPs (CPs W 34 to W-43) under Phase II had also been submitted for review. After due review, the M&E Consultant gave clearance to all 196 reports. in accordance with the S/RPF.
Subcomponent B.3: Improvement of Communication Network to Shelters – Social and resettlement study reports for the 152 nos. access roads in 33 CPs had been received for review. On review, the M&E Consultant made certain observations on these reports in accordance with the S/RPF. LGED in turn gave clarifications on M&E observations. To come to a common understanding on the issues raised and replies furnished by LGED, a combined meeting of LGED, M&E Consultants, representative of WB and PCMU was convened on 17 June 2014 in the Office of the DG/PD, PCMU under the chairmanship of DG/PD, PCMU. After threadbare discussion, the meeting came to a consensus that the clarifications given by LGED may be accepted in the context of field reality existing in Bangladesh. In the light of above decision, SA Reports of all 151 Shelter Connecting Roads of LGED have been recommended for clearance.
Construction of Killas (Under Subcomponent B.1) – Social and resettlement study reports for the Killas have been received for 15 Killas in 3 packages. On review, the M&E Consultant recommended clearance of 1 CP covering 3 nos. Killas. The D&S Consultant is still addressing the comments made by the M&E Consultant for 2 CPs covering 12 Killas.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 55
PackageNo.
Sub-
Project/Polder
No.
District
No.ofAff
ectedStr
ucturesf
orReha
bilitatio
ResettlementBudget(BDT)
DateofSubmis
siontoPD,PCM
UbyPMO
DateofClearance
Payment Status ResettlementCos
t
Implementation
Cost
Total
ByPCMU
ByWorldBank
1 2 3 4 5 6 7 8 9 10 11
1 W-01
1 47/5 Patuakhali 79 226,200.00 42,300.00 268,500.00 20-05-2013 30-05-2013 18-06-2013 Paymenthasbeenmadeon29-09-2013
2 52/53B Patuakhali 84 268,500.00 44,300.00 312,800.00 09-05-2013 30-05-2013 18-06-2013 Paymenthasbeenmadeon05-08-2013
2
W-02
3
41/6B
Barguna
81
353,160.00
43,000.00
396,160.00
01-01-2013
21-01-2013
16-05-2013 01- 02-2013
PaymenthasbeenmadetoEPon03-06-2013
4 41/7B Barguna 33 241,100.00 26,600.00 267,700.00 14-02-2012 20-12-2012 16-12-2012 Do
3 W-03
5
39/2A
Barguna
49
465,580.00
40,800.00
506,380.00
02-01-2013
06-01-2013
06-01-2013
PaymenthasbeenmadetoEPon02-06-2013
4
W-04
6 55/2C Patuakhali 53 230,620.00 40,000.00 270,620.00 12-02-2013 28-03-2013 08-04-2013 PaymenthasbeenmadetoEPon20-06-2013
7 55/4 Patuakhali 293 857,220.00 115,000.00 972,220.00 18-07-2013 Paymenthasbeenmadeon29-09-2013
8
55/1
Patuakhali
19
75,600.00
10,000.00
85,600.00
05-03-2013
28-03-2013
08-04-2013
PaymenthasbeenmadetoEPon20-06-2013
5
W-05
9
46
Patuakhali
87
328,240.00
45,000.00
373,240.00
02-01-2013
06-01-2013
28-07-2013
PaymenthasbeenmadetoEPon04-06-2013
10 52/53A Patuakhali 60 174,300.00 30,000.00 204,300.00 18-04-2013 02-05-2013 18-06-2013 Paymenthasbeenmadeon05-08-2013
11 54/A Patuakhali 63 184,700.00 29,600.00 214,300.00 09-06-2013 22-07-2013 28-07-2013 Paymenthasbeenmadeon29-09-2013
12 47/1 Patuakhali 49 268,060.00 40,000.00 308,060.00 20-05-2013 30-05-2013 18-06-2013 Paymenthasbeenmadeon29-09-2013
6
W-06
13
44/P
Patuakhali
27
88,220.00
20,000.00
108,220.00
12-11-2012
20-12-2012
19-11-2012&28- 07-2013
PaymenthasbeenmadetoEPon04-06-2013
14
47/4
Patuakhali
95
288,120.00
46,000.00
334,120.00
16-01-2013
28-03-2013
08-04-2013
PaymenthasbeenmadetoEPon19-06-2013
7 W-07 15 42 Barguna 16 63,620.00 11,000.00 74,620.00 21-01-2013 12-03-2013 18-04-2013 PaymenthasbeenmadetoEPon02-06-2013
8 W-10
16 39/1D Barguna 3 13,500.00 500.00 14,000.00 05-03-2013 28-03-2013 08-04-2013 Do
17 40/1 Barguna 0 - - - 26-06-2013 SIAhasbeenpreparedandsubmittedtoPCMU.
9
W-14
18 50/51 Patuakhali 264 971,200.00 90,000.00 1,061,200.00 18-04-2013 02-05-2013 18-06-2013 PaymenthasbeenmadetoEPon04-08-2013
55/2B (Squatters)
Patuakhali 36 153,600.00 19,700.00 173,300.00 05/12/2012 26-12-2012 18-12-2012 PaymenthasbeenmadetoEPon20-06-2013
19
55/2B (LandAcq.)
Patuakhali
333
5,393,110.00
180,300.00
5,573,410.00
05-12-2012
26-12-2012
18-12-2012
W-18 20 41/7B Barguna Revised LAP submitted to DC
W-19
21 43/1 Barguna 90 3,236,453.00 114,000.00 3,350,453.00 23.02.2014 19.03.2014 29.04.2014
CUL payment 95.41%; Top-up payment is under process
22 41/5 Barguna 102 1,995,512.00 76,000.00 2,071,512.00 23.02.2014 19.03.2014 29.04.2014
CUL payment 98.60%; Top-up payment is under process 23 44B Barguna 103
3,841,355.00 140,000.00 3,981,355.00 23.02.2014 19.03.2014 29.04.2014 CUL payment 94.36%; Top-up payment is under process
24 41/4 Barguna 27 1,799,600.00 75,000.00 1,874,600.00 27.02.2014 30.03.2014 26.02.2015 CUL payment 74.25%;
25 45 Barguna 18 1,942,612.00 65,000.00 2,007,612.00 30.10.2014 10.12.2014 CUL payment 55.25%
26 55/2D Patuakhali 161 6,496,520.00 190,000.00 6,686,520.00
07.04.2014 CUL payment is on-going,Final RAP will be submitted as early as possible.
27 55/3 Patuakhali LAP is pending with MoL
W-20
28 39/1A Barguna LAP is pending with DC for preparation of estimate
29 39/1B Pirojpur LAP is pending with DC
30 39/1C Pirojpur LAP is pending with DC
Component C: BWDB
Rehabilitation of Damaged Coastal Polders (Embankments and Allied Infrastructure)
The CPs are meant to strengthen cyclone damaged coastal polders to withstand natural calamities like cyclones, high tidal surges etc. compatible with Global Warming scenario leading to Sea Level Rise (SLR). The physical works generally include rehabilitation/ strengthening of embankments, water control structures, drainage improvements and protection of embankments from river erosion.
As of September 2016, Social and Resettlement Assessment Reports including RAPs (Resettlement Plans) for 27 polders in 11 CPs had been received and reviewed. On due review and updating, SA Reports of 25 polders in 11 CPs were recommended for clearance by the M&E Consultants. Out of the 25 polders, 12 polders involve Compensation Under Law (CUL) for land acquisition as paid by the DC. So far CUL payment has been made by DC for 4 Polders. Top-up value payment has been made for only 1 Polder.
Compensation to squatters of 18 Polders out of 19 Polders under the first phase has been made. 1 Polder does not need any squatter payment. Details are shown in Table 7.2 below:
Table 7.2: Status of Preparation & Implementation of Resettlement Action Plan (RAP) As of September 2016
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 56
Summary of Review and Clearance of SA Reports of LGED and BWDB
The status of SA Reports as of September 2016 is indicated in Table-7.3 below:
Table 7-3: Summary of Review and Recommendation for Clearance of Social & Resettlement Reports
Compliance of SMPs/ RAPs
Component B Interventions
The repair/improvement of existing shelters does not require resettlement. However, construction of new shelters , construction of Killas and construction of access roads might involve preparation of Resettlement Action Plans (RAPs) where acquisitions of public and private lands, resettlement of prevailing establishments may be necessary owing to likely temporary disruptions to traffic and business, shifting of religious/social establishments/structures, engulfing playgrounds etc.
In order to mitigate these negative impacts, site specific SMP/RAPs ought to be prepared by the implementing agency LGED following the SRPF guidelines.
The M & E Consultants periodically make field visits to supervise compliance of SMP and RAPs which are reported through FVR to PCMU, WB and stakeholders.
Component C Interventions
Construction works on the existing/ retired embankments may temporarily displace households and businesses that may exist. Site specific RAPs were prepared and subsequently approved by BWDB and WB. Compensation payments to PAPs of 18 polders have been disbursed so far.
Quarter/FY
Component B, LGED Component C, BWDB
Remarks
Construction of New Shelter (No of packages)
Improvement of Existing Shelters (No of packages)
Improvement of Communication Network to Shelters (No of packages)
Construction of Killa (No of packages) Rehabilitation of Coastal
Embankment (CE)
Recd.
Action taken
Recd.
Action taken Action taken Recd.
Action taken Recd.
Action taken
Comments
Clearance
Comments
Clearance
Recd. Comments
Clearance
Comments
Clearance
Comments
Clearance
FY2009-2010
0 0 0 0 0 0 4 0 4
Environmental reports cleared subject
to concurrence by
WB
FY2010-2011
2 0 2 25 0 25 13 0 11
FY2011-2012
11 0 11 0 0 0 2 0 3
FY2012-2013
14 0 6 0 0 0 0 0 1
FY2013-2014
14 0 22 0 0 0 18 0 0 0 0 0 7 0 7
FY2014-2015
4 0 4 4 0 4 8 0 26 3 0 0 2 2 0
FY2015-2016
11 0 11 6 0 6 10 0 10 0 0 0 0 0 0
1st Quarter FY2016-
2017
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total 56 0 56 35 0 35 36 0 36 3 0 3 28 2 26
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 57
Awareness Training on Environmental and Social Safeguards
Awareness trainings on environmental and social safeguards were conducted to create awareness on safeguard issues among the stakeholders of LGED and BWDB. For LGED, the trainings were done in the year 2014 and for BWDB, these were conducted in the years 2014 and 2015.
7.5 Conduct Survey and preparation of Annual Project Evaluation Report 2014
One major task of the second spell M&E Consultants is to conduct Social Survey to prepare Project Evaluation Report (PER) for 2014 and 2016. A baseline survey on the target beneficiaries was carried out at the beginning of the Project implementation in the year 2010. Random survey (HH, FGD & KII) samples in subsequent surveys in 2012 and 2013 were also taken from the beneficiaries of Component A and others to assess periodical project impact compared to the baseline situation. Till June 2014, three Social Survey Reports: Baseline Survey Report- 2010, Midterm Evaluation Report-2012 and the Project Evaluation Report-2013 were prepared, circulated and presented.
The fourth field survey for Project Impact Evaluation- 2014 was undertaken from 12 November 2014 to 22 November 2014. An experienced social survey firm named “Serve The People” had been hired by DPDS to help the M&E Consultants in conducting the survey, making data entry and analysis.
The PER-2014 focussed on the assessment of Outputs, Outcomes and overall project impact till 2014 compared to the baseline situation. The PER-2014 was distributed to all stakeholders on 09 February 2015 and the salient features of the project impact evaluation were presented on 22 February 2015 at PCMU Office. The findings of the impact evaluation showed that the project has largely been able to achieve the development objectives.
7.6 Field Visits
In the 1st quarter of FY2016-2017, one field visit was undertaken by the M&E Consultant in order to a) monitor, evaluate and track project progress, inputs, outputs and outcomes, b) oversee compliance of social and environmental safeguards and c) observe overall transparency and governance during project implementation.
The visit was undertaken from 24 September to 28 September 2016 to different sites of LGED and BWDB. The field visit report for LGED was circulated to all concerned vide M&E # ECRRP-E(M&E)/FVR/LGED/148 dated 03.10.2016.
In the wake of the monsoon, the field is still moist and unfavourable for physical works of BWDB. However, contractors have started re-mobilizing labours to different work sites of package nos. 18, 19 and 20. The preparation of package #20 appeared to be good.
7.7 Follow up of Key Agreed Actions
World Bank has carried out an Implementation Support Mission with effect from March 20 to March 24, 2016. The mission suggested some specific key agreed action plans. All the concerned implementing agencies will ensure timely compliance of the action plans and report to PCMU, WB and the M&E Consultants for information and follow up actions.
7.8 Preparation and Submission of Reports
The following reports were prepared and submitted by the M&E Consultant:
1) Inception Report – Taking into consideration the comments of different stakeholders, the final version of the Inception Report was made ready by end of October 2014. However, clearance from PCMU to publish the final version was obtained in the month of November 2014 vide no. PD/Prog/PCMU/DPDS/Inception Report/179/2014/1924 dated 12 November 2014. The final version was submitted on 12 November 2014.
2) Consolidated Progress Reports – 6 nos. Quarterly Progress Reports (September- December 2014 & January- March 2015, July –September 2015, October- December 2015, January- March 2016 and July- September 2016)) and 2 nos. Annual Progress Report (June 2015 and June 2016) have been published by the M&E Consultants till date.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 58
3) Compliance Report on Operational Specific Risk Mitigation Matrix- The project at its appraisal stage identified certain operational risks listed in PAD of WB, Annex-11: Operational Specific Risk Mitigation Matrix. As a part of its scope of services of the independent M&E Consultants contract, the Consultants would carry out monitoring of compliance of the mitigation measures on the project specific operational risks by different Implementing Agencies. The M&E Consultants undertook the task of monitoring of the compliance status in collaboration with the concerned agencies. The first compliance report had been submitted in June 2012 and thereafter follow up compliance reports are being regularly updated. The last update was given in June 2016.
4) Annual Project Evaluation Report-2014. As per decision of GoB and WB, the Annual Project Evaluation
Report assessing project impact up to 2014 has been published on 09 February, 2015. The PER-2014 was
presented by the M&E Consultants on 22 February, 2015 in PCMU conference room which was
participated by all concerned Agencies including WB.
5) Annual Project Evaluation Report-2016. Field survey for preparing the final Project Evaluation Report
(PER) to assess comprehensive project impact is expected to be taken up in December 2016 aiming at
publication of the PER by February 2017.
6) Project Implementation Completion Report (PICR) Not yet due.
7.9 Utilization of Consultancy Inputs in Man-Months
As end of September 2016, man-month utilization by national key professional specialists and the other national support staff are 64.50% and 61.18% respectively. Annex-9 presents the details of utilization of consultancy inputs as per revised staffing schedule..
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 59
Annex 1: Project Implementation Arrangements of ECRRP and Project Area Coverage
Annex 1A: Project Implementation Arrangements of ECRRP
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 60
Annex 1B: Map of Bangladesh Highlighting ECRRP Project Area
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 61
Annex 1C: Coverage of Components by District and Upazila
District Upazila
Component
Implemented Components to be Implemented
Component A Component B Component C Component D
Barguna Amtali
Bamna
Betagi -
Borguna Sadar
Patharghata
Bagerhat Bagerhat Sadar - - -
Chitalmari - - -
Fakirhat - - -
Kachua - - -
Mollahat - - -
Mongla - -
Morolganj - -
Sarankhola -
Pirojpur Bhandaria -
Kawkhali - - -
Mathbaria
Nazirpur - - -
Pirojpur Sadar - - -
Sarupkati - - -
Patuakhali Bauphal - -
Dashmina -
Galachipa
Kalapara
Mirjaganj - -
Patuakhali - - -
Bhola Bhola Sadar - -
Burhanuddin - -
Char Fasson - -
Daulatkhan - -
Lalmohan - -
Monpura - -
Tajumuddin - -
Barisal Agailjhara - - -
Babuganj - - -
Bakerganj - -
Banaripara - - -
Barisal Sadar - -
Gaumadi - - -
Hizla - - -
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 62
District Upazila
Component
Implemented Components to be Implemented
Component A Component B Component C Component D
Mehendiganj - - -
Muladi - - -
Ujirpur - - -
Jhalokhati Jhalakati Sadar - - -
Kathalia - -
Nalchiti - - -
Rajapur - - -
Khulna Batiaghata - - -
Dacope - -
Dighalia - - -
Dumuria - - -
Khulna Metro - - -
Koyra - -
Paikgachha - - -
Phultala - - -
Rupsha - - -
Terakhada - - -
Sathkhira Asasuni - - -
Debhata - - -
Kalaroa - - -
Kaliganj - - -
Satkhira Sadar - - -
Shyamnagar - -
Tala - - -
Laksmipur
Sadar - - -
Ramgati - - -
Raipur - - -
Noakhali Sadar - - -
Hatia - - -
Companiganj - - -
Feni Sonagaji - - -
Chittagong
Sandeep - - -
Sitakundu - - -
Patia - - -
Anoara - - -
Bashkhali - - -
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 63
Annex 3: Component B Annual Work Plan and process Monitoring
A
nn
ex 3
A:
Co
mp
on
ent
B A
nn
ual
Wo
rk P
lan
, FY
2016
-201
7
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 64
An
nex
3A
: C
om
po
nen
t B
An
nu
al W
ork
Pla
n, F
Y20
16-
2017
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 65
A
nn
ex 3
A:
Co
mp
on
ent
B A
nn
ual
Wo
rk P
lan
, FY
201
6-20
17
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 66
Date:30-09-2016
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
LGED/ECRRP/BAG/10-11/NW-01 4 C
Morrelgonj,
Fakirhat &
Bagerhat Sadar
Bagerhat - Completed -Design works
completed
31/1/11 &
6/6/11;
Cleared by
M&E
Consultant-
14/6/11
-
31/1/11 &
9/3/11; Cleared
by M&E
Consultant
29/3/11
30/5/2011 Completed Completed Completed Completed 27/04/11 -
LGED/ECRRP/BARI/10-11/NW-02 4 C
Barisal Sadar,
Agailjhara,
Gouronadi &
Babugonj
Barisal - Completed -Design works
completed
22/3/11 &
25/4/11;
Cleared by
M&E
Consultant-
28/4/11
-
17/10/11;
Cleared by M&E
Consultant-
13/08/12
- Completed Completed Completed Completed 03-01-11 -
LGED/ECRRP/BAR/10-11/NW-03 4 CAmtoli &
Barguna SadarBarguna - Completed -
Design works
completed
14/12/11 &
2/2/12;
Cleared by
M&E
Consultant-
8/2/12
-
24/4/11 &
1/8/2011;
Cleared by M&E
Consultant-
2/8/11
- Completed Completed Completed Completed 26/5/2011 -
LGED/ECRRP/PAT/10-11/NW-04 4 CKolapara &
GolachipaPatuakhali - Completed -
Design works
completed
27/11/11 &
15/1/12;
Cleared by
M&E
Consultant-
16/1/12
-
24/4/11; Cleared
by M&E
Consultant-
2/5/11
- Completed Completed Completed Completed 04-04-11 -
LGED/ECRRP/BARI/10-11/NW-05 4 C
Banaripara,
Ujirpur, Muladi &
Mehendigonj
Barisal - Completed -Design works
completed
27/11/11 &
31/1/12;
Cleared by
M&E
Consultant-
9/2/12
-
17/10/11;
Cleared by M&E
Consultant-
13/08/12
- Completed Completed Completed Completed 04-05-11 -
LGED/ECRRP/PIR/10-11/NW-06 4 CPirojpur Sadar &
NazirpurPirojpur - Completed -
Design works
completed
14/12/11 &
31/1/12;
Cleared by
M&E
Consultant-
14/2/12
-
23/11/11 &
29/11/11;
Cleared by M&E
Consultant-
4/12/11
- Completed Completed Completed Completed 05-11-11 -
LGED/ECRRP/BAR/10-11/NW-07 4 CPathorghata &
BetagiBarguna - Completed -
Design works
completed
14/12/11 &
31/1/12;
Cleared by
M&E
Consultant-
16/2/12
-
25/8/11 &
13/9/11; Cleared
by M&E
Consultant-
28/12/11
- Completed Completed Completed Completed 05-11-11 -
LGED/ECRRP/BAG/10-11/NW-08 3 C
Kachua,
Mollahat &
Chitolmari
Bagerhat - Completed -Design works
completed
14/12/11 &
19/2/12;
Cleared by
M&E
Consultant-
5/3/12
-
7/6/11; Cleared
by M&E
Consultant-
16/6/11
28/6/2011 Completed Completed Completed Completed Completed -
LGED/ECRRP/BAR/10-11/NW-09 4 CBarguna Sadar
& BamnaBarguna - Completed -
Design works
completed
22/12/11 &
19/2/12;
Cleared by
M&E
Consultant-
5/3/12
-
25/8/11 &
13/9/11; Cleared
by M&E
Consultant-
28/12/11
- Completed Completed Completed Completed 05-03-11 -
LGED/ECRRP/BAG/10-11/NW-10 3 CMongla, Rampal
& ShoronkholaBagerhat - Completed -
Design works
completed
22/12/11 &
19/2/12;
Cleared by
M&E
Consultant-
7/3/12
-
7/6/11; Cleared
by M&E
Consultant-
16/6/11
28/6/20111 Completed Completed Completed Completed Completed -
LGED/ECRRP/PAT/10-11/NW-11 4 C
Patuakhali
Sadar, Dumki,
Mirjagonj &
Doshmina
Patuakhali - Completed -Design works
completed
14/12/11 &
19/2/12;
Cleared by
M&E
Consultant-
7/3/12
-
24/4/11; Cleared
by M&E
Consultant-
2/5/11
- Completed Completed Completed Completed 06-06-11 -
LGED/ECRRP/PAT/10-11/NW-12 4 CBauphal &
GalachipaPatuakhali - Completed -
Design works
completed
15/1/12;
Cleared by
M&E
Consultant-
17/1/12
-
24/4/11; Cleared
by M&E
Consultant-
2/5/11
- Completed Completed Completed Completed Completed -
LGED/ECRRP/PIR/10-11/NW-13 4 C
Nesarabad,
Mothbaria &
Bhandaria
Pirojpur - Completed -Design works
completed
18/1/12;
Cleared by
M&E
Consultant-
24/1/12
-
29/8/12; Cleared
by M&E
Consultant-
4/10/12
- Completed Completed Completed Completed Completed -
Package No.
Contract
ID
Tender
received -
date
Date of
clearance by
M&E
Site Selection
Date of
clearance by
M&E
Contract signed
- date
Shelter
construction or
repair/
improvement?
(C or R) Tender
notice - date
Date of
clearance of
WB
Remarks
(any relevant
information
not yet
included e.g.
causes of
delays) Upazila District Start date Finish date
Letter of
Award - date
Tender
approval -
date
Package wise Shelter information
No. of
Cyclone
Shelter cum
School Date of
clearance of
WB
Location of the Shelter
Start date
Design
approval
date
Tender notice up to signing of contract
Design Works EIA/ IEE Study Tender Process
Preparatory works up to design approval
Social and Resettlement
Study
Annex 3B: Monitoring Form PMF-B2: Process Monitoring - Package wise Construction of New Cyclone Shelters (1st Phase)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 67
Date:30-09-2016
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
LGED/ECRRP/BAR/11-12/NW-14 10 C
Amtali, Barguna
Sadar, Betagi &
Patharghata
Barguna - Completed -Design works
completed
03/10/12;
Cleared by
M&E
Consultant-
07/03/13
-
21/11/12;
Cleared by M&E
Consultant-
05/12/12
- Completed Completed Completed Completed 28/3/12 -
LGED/ECRRP/PAT/11-12/NW-15 10 C
Bauphal,
Dasmina,
Galachipa,
Kalapara,
Mirzjagonj,
Patuakhali
Patuakhali - Completed -Design works
completed
06/02/13;
Cleared by
M&E
Consultant-
07/03/13
-
12/1/14; Cleared
by M&E
Consultant-
15/1/14
- Completed Completed Completed Completed 20/3/12 -
LGED/ECRRP/SAT/11-12/NW-16 9 C
Asasuni,
Kaligonj,
Kalaroa &
Shyamnagar
Satkhira - Completed -Design works
completed
02/04/13;
Cleared by
M&E
Consultant-
10/06/13
-
23/4/14; Cleared
by M&E
Consultant-
18/5/14
- Completed Completed Completed Completed 04-01-12 -
LGED/ECRRP/BHO/11-12/NW-17 10 C
Bhola Sadar,
Daulatkhan &
Borhanuddin
Bhola - Completed -Design works
completed
01/09/13;
Cleared by
M&E
Consultant -
05/12/13
-
28/4/14; Cleared
by M&E
Consultant-
20/5/14
- Completed Completed Completed Completed 30/5/12 -
LGED/ECRRP/BHO/11-12/NW-18 12 C
Lalmohon,
Tazumuddin,
Charfassion &
Monpura
Bhola - Completed -Design works
completed
01/09/13;
Cleared by
M&E
Consultant-
6/11/13
- - - Completed Completed Completed Completed 18/10/12 -
LGED/ECRRP/SAT/11-12/NW-19 8 C Shyamnagar Pirojpur - Completed -Design works
completed
03/6/13;
Cleared by
M&E
Consultant-
20/8/13
-
23/4/14 &
27/1/15; Cleared
by the M&E
Consultant-
16/4/15
- Completed Completed Completed Completed 21/11/12 -
LGED/ECRRP/KHU/11-12/NW-20 24 C Dacope & Koyra Khulna - Completed -Design works
completed
13/5/13;
Cleared by
M&E
Consultant-
31/12/13
-
8/5/14 & 7/1/15;
Cleared by M&E
Consultant-
08/3/15
- Completed Completed Completed 23/10/2012 12-12-12 -
LGED/ECRRP/BAG/11-12/NW-21 4 C
Bagerhat Sadar,
Sharankhola &
Chitalmari
Bagerhat - Completed -Design works
completed
02/4/13;
Cleared by
M&E
Consultant-
30/5/13
-
06/5/13; Cleared
by M&E
Consultant-
14/5/13
- Completed Completed Completed Completed 24/6/12 -
LGED/ECRRP/BAG/11-12/NW-22 4 C
Morrelgonj,
Fakirhat,
Rampal &
Mongla
Bagerhat - Completed -Design works
completed
22/05/13;
Cleared by
M&E
Consultant-
10/06/13
-
06/5/13; Cleared
by M&E
Consultant-
14/5/13
- Completed Completed Completed Completed 02-12-13 -
LGED/ECRRP/BAR/11-12/NW-23 5 C
Bamna,
Patharghata,
Betagi & Amtoli
Barguna - Completed -Design works
completed
04/12/12;
Cleared by
M&E
Consultant-
30/5/13
-
05/12/12 &
17/09/13;
Cleared by M&E
Consultant-
24/10/13
- Completed Completed Completed Completed 26/6/12 -
LGED/ECRRP/BAR/11-12/NW-24 6 CBarguna Sadar
& AmtoliBarguna - Completed -
Design works
completed
01/8/13;
Cleared by
M&E
Consultant-
14/11/13
-
05/12/13;
Cleared by M&E
Consultant-
09/12/13
- Completed Completed Completed Completed 27/6/12 -
LGED/ECRRP/BARI/11-12/NW-25 8 C
Gouranadi,
Agailjhara,
Banaripara,
Uzirpur & Sadar
Barisal - Completed -Design works
completed
14/7/13;
Cleared by
M&E
Consultant-
12/9/13
-
27/6/13;
Cleared by the
M&E Consultant-
19/5/15
- Completed Completed Completed Completed 10-08-12 -
LGED/ECRRP/BARI/11-12/NW-26 4 CBabuganj,
Muladi & HizlaBarisal - Completed -
Design works
completed
14/7/13;
Cleared by
M&E
Consultant-
12/9/13
-
27/6/13 &
27/1/15; Cleared
by the M&E
Consultant-
20/4/15
- Completed Completed Completed Completed 07-09-12
LGED/ECRRP/PAT/11-12/NW-27 5 C
Galachipa,
Kalapara &
Dumki
Patuakhali - Completed -Design works
completed
01/09/13;
Cleared by
M&E
Consultant-
21/11/13
-
17/11/13;
Cleared by M&E
Consultant-
21/11/13
- Completed Completed Completed Completed 25/7/12 -
LGED/ECRRP/PIR/11-12/NW-28 5 C
Kawkhali,
Bhandaria &
Mothbaria
Pirojpur - Completed -Design works
completed
04/7/13;
Cleared by
M&E
Consultant-
15/9/13
-
27/6/13 &
27/1/15; Cleared
by the M&E
Consultant-
14/5/15
- Completed Completed Completed Completed 15/6/12 -
LGED/ECRRP/PAT/11-12/NW-29 4 C
Patuakhali
Sadar &
Mirzaganj
Patuakhali - Completed -Design works
completed
01/09/13;
Cleared by
M&E
- - - Completed Completed Completed Completed 28/6/12 -
Date of
clearance of
WB
Location of the Shelter
Start date
Design
approval
date
Tender notice up to signing of contract
Design Works EIA/ IEE Study Tender Process
Preparatory works up to design approval
Social and Resettlement
Study
Remarks
(any
relevant
information
not yet
included
e.g. causes
of delays) Upazila District Start date Finish date
Letter of
Award - date
Tender
approval -
date
Package wise Shelter information
No. of
Cyclone
Shelter cum
School
Package No.
Contract
ID
Tender
received -
date
Date of
clearance by
M&E
Site Selection
Date of
clearance by
M&E
Contract signed
- date
Shelter
construction
or repair/
improvement?
(C or R)
Tender
notice - date
Date of
clearance of
WB
Annex 3C: Monitoring Form PMF-B2: Process Monitoring - Package wise Construction of New Cyclone Shelters (307 nos.) New Shelters under 2nd Phase)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 68
Date:30-09-2016
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
LGED/ECRRP/BAR/11-12/NW-14 10 C
Amtali, Barguna
Sadar, Betagi &
Patharghata
Barguna - Completed -Design works
completed
03/10/12;
Cleared by
M&E
Consultant-
07/03/13
-
21/11/12;
Cleared by M&E
Consultant-
05/12/12
- Completed Completed Completed Completed 28/3/12 -
LGED/ECRRP/PAT/11-12/NW-15 10 C
Bauphal,
Dasmina,
Galachipa,
Kalapara,
Mirzjagonj,
Patuakhali
Patuakhali - Completed -Design works
completed
06/02/13;
Cleared by
M&E
Consultant-
07/03/13
-
12/1/14; Cleared
by M&E
Consultant-
15/1/14
- Completed Completed Completed Completed 20/3/12 -
LGED/ECRRP/SAT/11-12/NW-16 9 C
Asasuni,
Kaligonj,
Kalaroa &
Shyamnagar
Satkhira - Completed -Design works
completed
02/04/13;
Cleared by
M&E
Consultant-
10/06/13
-
23/4/14; Cleared
by M&E
Consultant-
18/5/14
- Completed Completed Completed Completed 04-01-12 -
LGED/ECRRP/BHO/11-12/NW-17 10 C
Bhola Sadar,
Daulatkhan &
Borhanuddin
Bhola - Completed -Design works
completed
01/09/13;
Cleared by
M&E
Consultant -
05/12/13
-
28/4/14; Cleared
by M&E
Consultant-
20/5/14
- Completed Completed Completed Completed 30/5/12 -
LGED/ECRRP/BHO/11-12/NW-18 12 C
Lalmohon,
Tazumuddin,
Charfassion &
Monpura
Bhola - Completed -Design works
completed
01/09/13;
Cleared by
M&E
Consultant-
6/11/13
- - - Completed Completed Completed Completed 18/10/12 -
LGED/ECRRP/SAT/11-12/NW-19 8 C Shyamnagar Pirojpur - Completed -Design works
completed
03/6/13;
Cleared by
M&E
Consultant-
20/8/13
-
23/4/14 &
27/1/15; Cleared
by the M&E
Consultant-
16/4/15
- Completed Completed Completed Completed 21/11/12 -
LGED/ECRRP/KHU/11-12/NW-20 24 C Dacope & Koyra Khulna - Completed -Design works
completed
13/5/13;
Cleared by
M&E
Consultant-
31/12/13
-
8/5/14 & 7/1/15;
Cleared by M&E
Consultant-
08/3/15
- Completed Completed Completed 23/10/2012 12-12-12 -
LGED/ECRRP/BAG/11-12/NW-21 4 C
Bagerhat Sadar,
Sharankhola &
Chitalmari
Bagerhat - Completed -Design works
completed
02/4/13;
Cleared by
M&E
Consultant-
30/5/13
-
06/5/13; Cleared
by M&E
Consultant-
14/5/13
- Completed Completed Completed Completed 24/6/12 -
LGED/ECRRP/BAG/11-12/NW-22 4 C
Morrelgonj,
Fakirhat,
Rampal &
Mongla
Bagerhat - Completed -Design works
completed
22/05/13;
Cleared by
M&E
Consultant-
10/06/13
-
06/5/13; Cleared
by M&E
Consultant-
14/5/13
- Completed Completed Completed Completed 02-12-13 -
LGED/ECRRP/BAR/11-12/NW-23 5 C
Bamna,
Patharghata,
Betagi & Amtoli
Barguna - Completed -Design works
completed
04/12/12;
Cleared by
M&E
Consultant-
30/5/13
-
05/12/12 &
17/09/13;
Cleared by M&E
Consultant-
24/10/13
- Completed Completed Completed Completed 26/6/12 -
LGED/ECRRP/BAR/11-12/NW-24 6 CBarguna Sadar
& AmtoliBarguna - Completed -
Design works
completed
01/8/13;
Cleared by
M&E
Consultant-
14/11/13
-
05/12/13;
Cleared by M&E
Consultant-
09/12/13
- Completed Completed Completed Completed 27/6/12 -
LGED/ECRRP/BARI/11-12/NW-25 8 C
Gouranadi,
Agailjhara,
Banaripara,
Uzirpur & Sadar
Barisal - Completed -Design works
completed
14/7/13;
Cleared by
M&E
Consultant-
12/9/13
-
27/6/13;
Cleared by the
M&E Consultant-
19/5/15
- Completed Completed Completed Completed 10-08-12 -
LGED/ECRRP/BARI/11-12/NW-26 4 CBabuganj,
Muladi & HizlaBarisal - Completed -
Design works
completed
14/7/13;
Cleared by
M&E
Consultant-
12/9/13
-
27/6/13 &
27/1/15; Cleared
by the M&E
Consultant-
20/4/15
- Completed Completed Completed Completed 07-09-12
LGED/ECRRP/PAT/11-12/NW-27 5 C
Galachipa,
Kalapara &
Dumki
Patuakhali - Completed -Design works
completed
01/09/13;
Cleared by
M&E
Consultant-
21/11/13
-
17/11/13;
Cleared by M&E
Consultant-
21/11/13
- Completed Completed Completed Completed 25/7/12 -
LGED/ECRRP/PIR/11-12/NW-28 5 C
Kawkhali,
Bhandaria &
Mothbaria
Pirojpur - Completed -Design works
completed
04/7/13;
Cleared by
M&E
Consultant-
15/9/13
-
27/6/13 &
27/1/15; Cleared
by the M&E
Consultant-
14/5/15
- Completed Completed Completed Completed 15/6/12 -
LGED/ECRRP/PAT/11-12/NW-29 4 C
Patuakhali
Sadar &
Mirzaganj
Patuakhali - Completed -Design works
completed
01/09/13;
Cleared by
M&E
- - - Completed Completed Completed Completed 28/6/12 -
Date of
clearance of
WB
Location of the Shelter
Start date
Design
approval
date
Tender notice up to signing of contract
Design Works EIA/ IEE Study Tender Process
Preparatory works up to design approval
Social and Resettlement
Study
Remarks
(any
relevant
information
not yet
included
e.g. causes
of delays) Upazila District Start date Finish date
Letter of
Award - date
Tender
approval -
date
Package wise Shelter information
No. of
Cyclone
Shelter cum
School
Package No.
Contract
ID
Tender
received -
date
Date of
clearance by
M&E
Site Selection
Date of
clearance by
M&E
Contract signed
- date
Shelter
construction
or repair/
improvement?
(C or R)
Tender
notice - date
Date of
clearance of
WB
Annex 3C: Monitoring Form PMF-B2:Process Monitoring - Package wise Construction of New Cyclone Shelters (307nos.) New Shelters under 2nd Phase) Cont.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 69
Date:30-09-2016
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
LGED/ECRRP/BAR/9-10/W-01 8 R Barguna Sadar Barguna - Completed - Completed
30/9/10;
Clearance
from M&E -
05/10/10
-
30/9/10;
Clearance
from M&E -
05/10/10
30/05/2011 05-02-10 30/8/2010 - 23/8/2010 09-08-10 -
LGED/ECRRP/BAG/9-10/W-02 10 RMorrelgonj &
SharankholaBagerhat - Completed - Completed
25/8/10 &
30/9/10;
Clearance
from M&E -
-
30/9/10;
Clearance
from M&E -
05/10/10
30/05/2011 - 23/6/2010 - 14/7/2010 27/7/2010 -
LGED/ECRRP/BAR/9-10/W-03 10 R Amtoli Barguna - Completed - Completed
30/9/10;
Clearance
from M&E -
05/10/10
-
25/8/10 &
30/9/10;
Clearance
from M&E -
05/10/10
30/05/2011 - - - 09-09-10 28/09/2010 -
LGED/ECRRP/BAR/9-10/W-04 12 RBamna &
BetagiBarguna - Completed - Completed
30/9/10;
Clearance
from M&E -
05/10/10
-
30/9/10;
Clearance
from M&E -
05/10/10
30/05/2011 - 30/8/2010 - 22/11/2010 24/11/2010 -
LGED/ECRRP/BAR/9-10/W-05 10 R Pathorghata Barguna - Completed - Completed
30/9/10;
Clearance
from M&E -
05/10/10
-
30/9/10;
Clearance
from M&E -
05/10/10
30/05/2011 - 07-05-10 - 13/10/2010 18/10/2010 -
LGED/ECRRP/Bari/9-10/W-06 11 RHijla &
MuladiBarisal - Completed - Completed
25/8/10 &
30/9/10;
Clearance
from M&E -
04/10/10
-
9/9/10 &
30/9/10;
Clearance
from M&E -
05/10/10
30/05/2011 - 15/6/2010 - 20/7/2010 09-10-14 -
LGED/ECRRP/Bari/9-10/W-07 11 RMehendiganj
& BakerganjBarisal - Completed - Completed
26/1/11 &
20/2/11;
Clearance
from M&E -
24/2/11
-
30/11/10 &
26/1/11;
Clearance
from M&E -
31/1/11
30/05/2011 15/6/2010 17/8/2010 - 13/10/2010 25/10/2010 -
LGED/ECRRP/Bari/9-10/W-08 12 RUzirpur &
BabuganjBarisal - Completed - Completed
26/1/11 &
20/2/11;
Clearance
from M&E -
23/2/11
-
1/11/2010;
Clearance
from M&E -
07/11/10
30/05/2011 16/6/2011 - - 16/9/2010 27/9/2010 -
LGED/ECRRP/PIR/9-10/W-09 10 R
Mothbaria,
Bhandaria &
Nesarabad
Pirojpur - Completed - Completed
25/8/10 &
30/9/10;
Clearance
from M&E -
04/10/10
-
9/9/10 &
30/9/10;
Clearance
from M&E -
05/10/10
30/05/2011 - 15/7/2010 - 22/8/2010 09-05-10 -
LGED/ECRRP/PAT/9-10/W-10 11 RSadar &
DumkiPatuakhali - Completed - Completed
09/11/10;
Clearance
from M&E -
22/11/10
-
1/11/2010;
Clearance
from M&E -
07/11/10
30/05/2011 - 08-10-10 - 26/9/2010 13/10/2010 -
LGED/ECRRP/PAT/9-10/W-11 10 RMirjaganj &
DoshminaPatuakhali - Completed - Completed
09/11/10;
Clearance
from M&E -
22/11/10
-
1/11/2010;
Clearance
from M&E -
07/11/10
30/05/2011 - 23/8/2010 - 16/9/2010 13/10/2010 -
LGED/ECRRP/PAT/9-10/W-12 10 R Bauphal Patuakhali - Completed - Completed
09/11/10;
Clearance
from M&E -
22/11/10
-
1/11/2010;
Clearance
from M&E -
07/11/10
30/05/2011 - 06-09-10 - 10-03-10 21/10/2010 -
Tender
notice -
date
Package No.Date of
clearance
by M&E
Remarks
(any relevant
information
not yet
included e.g.
causes of
delays) Upazila District
Start
date
Finish
date
Start
date
Site Selection
Contrac
t ID
Tender
received -
date
Letter of
Award -
date
Tender
approval
- date
Package wise Shelter information
Location of the ShelterSocial and
Resettlement Study No. of
Cyclone
Shelter
cum
School
Shelter
construction
or repair/
improvement
?
(C or R)
Tender notice up to signing of contract
Design Works EIA/ IEE Study Tender Process
Contract
signed -
date
Date of
clearance
by M&E
M&E
Date of
clearance
of WB
Date of
clearance
of WB
Preparatory works up to design approval
Design
approval
date
Annex 3D: Monitoring Form PMF-B2: Process Monitoring - Package wise Improvement of Cyclone Shelters (1st Phase)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 70
Date:30-09-2016
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
LGED/ECRRP/PAT/9-10/W-13 7 R Kolapara Patuakhali - Completed - Completed
09/11/10;
Clearance
from M&E -
22/11/10
-
24/11/10 &
26/1/11;
Clearance
from M&E -
31/1/11
30/05/2011 - 23/9/2010 - 24/10/2010 27/10/2011 -
LGED/ECRRP/PAT/9-10/W-14 12 R Golachipa Patuakhali - Completed - Completed
09/11/10;
Clearance
from M&E -
22/11/10
-
24/11/10 &
26/1/11;
Clearance
from M&E -
30/05/2011 20/9/2010 26/10/2010 - 28/11/2010 12-01-10 -
LGED/ECRRP/BHO/9-10/W-15 11 R Sadar Bhola - Completed - Completed
26/1/11 &
20/2/11;
Clearance
from M&E -
23/2/11
-
24/11/10 &
26/1/11;
Clearance
from M&E -
31/1/11
30/05/2011 - 17/8/2010Complete
dCompleted Completed -
LGED/ECRRP/BHO/9-10/W-16 10 RSadar &
DaulatkhanBhola - Completed - Completed
26/1/11 &
20/2/11;
Clearance
from M&E -
23/2/11
-
24/11/10 &
26/1/11;
Clearance
from M&E -
31/1/11
30/05/2011 - 21/9/2010 - 11-04-10 12-08-10 -
LGED/ECRRP/BHO/9-10/W-17 15 RLalmohon &
TojumuddinBhola - Completed - Completed
20/2/11;
Clearance
from M&E -
24/2/11
-
24/11/10 &
26/1/11;
Clearance
from M&E -
31/1/11
30/05/2011 - 23/9/2010 - 11-04-10 28/11/2010 -
LGED/ECRRP/BHO/9-10/W-18 8 R Borhanuddin Bhola - Completed - Completed
20/2/11;
Clearance
from M&E -
24/2/11
-
24/11/10 &
26/1/11;
Clearance
from M&E -
30/05/2011 - 27/9/2010 - 11-04-10 29/11/2010 -
LGED/ECRRP/BHO/9-10/W-19 10 R Charfashion Bhola - Completed - Completed
20/2/11;
Clearance
from M&E -
24/2/11
-
24/11/10 &
26/1/11;
Clearance
from M&E -
31/1/11
30/05/2011 - 30/9/2010 - 11-04-10 12-08-10 -
LGED/ECRRP/BHO/9-10/W-20 6 R Monpura Bhola - Completed - Completed
20/2/11;
Clearance
from M&E -
24/2/11
-
24/11/10
&26/1/11;
Clearance
from M&E -
31/1/11
30/05/2011 - 11-12-10 - 21/11/2010 19/12/2010 -
LGED/ECRRP/JALO/9-10/W-21 10 R
Sadar,
Nalchity,
Rajapur &
Kathalia
Jhalokathi - Completed - Completed
28/2/11;
Clearance
from M&E -
7/3/11
-
6/12/10
&26/1/11;
Clearance
from M&E -
31/1/11
30/05/2011 - 18/8/2010 - 19/9/2010 10-11-10 -
LGED/ECRRP/KHU/9-10/W-22 10 R Dacope Khulna Completed - Completed
30/9/10;
Clearance
from M&E -
05/10/10
-
9/11/2010;
Clearance
from M&E -
21/11/10
30/05/2011 16/9/2010 - - - 2/11/2010 -
LGED/ECRRP/SAT/9-10/W-23 8 R Shyamnagar Satkhira - Completed - Completed
26/1/11 &
20/2/11;
Clearance
from M&E -
23/2/11
-
9/11/2010;
Clearance
from M&E -
21/11/10
30/05/2011 - 15/1/2010 - 29/8/2010 16/9/2010 -
LGED/ECRRP/SAT/9-10/W-24 8 RDebhata,
Kaligonj &
Assasuni
Satkhira - Completed - Completed
26/1/11 &
20/2/11;
Clearance
from M&E -
23/2/11
-
1/11/2010;
Clearance
from M&E -
07/11/10
30/05/2011 - 15/6/2010 - 29/8/2010 16/9/2010 -
LGED/ECRRP/KHU/9-10/W-25 10 RKoyra,
Paikgacha &
Dumuria
Khulna - Completed - Completed
30/9/10;
Clearance
from M&E -
05/10/10
-
1/11/2010;
Clearance
from M&E -
07/11/10
30/05/2011 - - - 10-12-10 24/10/2010 -
The Conreact
Package has
already been
taken out from
the scope of
work of RDPP
of LGED.
Date of
clearance
by M&E
Letter of
Award -
date
Contract
signed -
date
Contrac
t ID
Date of
clearance
of WB
Date of
clearance
by M&E
Date of
clearance
of WB
Tender
notice -
date
Tender
received -
date
Tender
approval
- date
Design Works EIA/ IEE Study Social and
Resettlement Study Tender Process
Upazila DistrictStart
date
Finish
date
Start
date
Design
approval
date
Package wise Shelter information Preparatory works up to design approval Tender notice up to signing of contract Remarks
(any relevant
information
not yet
included e.g.
causes of
delays)
Package No.
No. of
Cyclone
Shelter
cum
School
Shelter
construction
or repair/
improvement
?
(C or R)
Location of the Shelter Site Selection
Annex 3D: Monitoring Form PMF-B2: Process Monitoring - Package wise Improvement of Cyclone Shelters (1st Phase) Cont.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 71
Date:30-09-2016
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
LGED/ECRRP/PIR/13-14/W-34 18 R
Nesarabad,
Pirojpur Sadar,
Bhandaria,
Mothbaria &
Zianagar
Pirojpur - Completed - Completed
Receieved -
25/09/14;
Cleared by
the M&E
Consultants-
04/12/14
-
01/12/13;
Clearance
from M&E -
08/12/13
- Completed Completed Completed Completed 27/4/2014 -
LGED/ECRRP/JHA/13-14/W-35 8 R
Kathalia,
Rajapur &
Nalchity
Jhalokathi - Completed - Completed
Receieved -
25/06/14;
Cleared by
the M&E
Consultants-
16/05/16
-
13/11/13;
Clearance
from M&E -
21/11/13
- Completed Completed Completed Completed 05-06-14 -
LGED/ECRRP/BHO/13-14/W-36 41 R
Lalmohon,
Borhanuddin,
Charfassion,
Tozumuddin &
Bhola Sadar
Bhola - Completed - Completed
Receieved -
25/09/14;
Cleared by
the M&E
Consultants-
07/12/14
-
Receieved -
30/06/14 &
25/09/14;
Cleared by
the M&E
Consultants-
31/12/14 &
22/05/16
- Completed Completed Completed Completed 01-11-15 -
LGED/ECRRP/KHU/13-14/W-37 30 R
Paikgacha,
Koyra,
Dumuria,
Batiaghata,
Dacope &
Digholia
Khulna - Completed - Completed
Receieved -
25/06/14;
Cleared by
the M&E
Consultants-
16/05/16
-
06/1/14;
Clearance
from M&E -
07/1/14
- Completed Completed Completed Completed 29/10/2014 -
LGED/ECRRP/PAT/13-14/W-38 27 R
Patuakhali
Sadar,
Bauphal,
Dashmina,
Galachipa,
Kalapara &
Rangabali
Patuakhal
i- Completed - Completed
Receieved -
25/09/14;
Cleared by
the M&E
Consultants-
08/12/14
-
Receieved -
30/06/14 &
25/09/14 ;
Cleared by
the M&E
Consultants-
7/1/15 &
26/04/16
- Completed Completed Completed Completed 09-01-14 -
LGED/ECRRP/SAT/13-14/W-39 10 R
Debhata,
Shyamnagar &
Ashasuni
Satkhira - Completed - Completed
Receieved -
25/06/14;
Cleared by
the M&E
Consultants-
16/05/16
-
07/4/14;
Clearance
from M&E -
14/5/14 &
4/6/14
- Completed Completed Completed Completed 05-07-14 -
LGED/ECRRP/BARI/13-14/W-40 17 R
Babugonj,
Muladi, Hijla,
Bakergonj &
Uzirpur
Barisal - Completed - Completed
Receieved -
25/06/14;
Cleared by
the M&E
Consultants-
16/05/16
-
06/1/14;
Clearance
from M&E -
11/3/14
- Completed Completed Completed Completed 21/8/2014 -
LGED/ECRRP/BAR/13-14/W-41 36 R
Barguna Sadar,
Bamna, Betagi,
Patharghata &
Amtoli
Barguna - Completed - Completed
Receieved-
25/09/14;
Cleared by
the M&E
Consultants-
09/12/14
-
13/1/14 &
08/4/14;
Clearance
from M&E -
19/1/14 &
11/5/14
- Completed Completed Completed Completed 16/12/2014 -
LGED/ECRRP/BAG/13-14/W-42 25 R
Mollahat,
Rampal,
Mongla,
Morrelgonj &
Shorankhola
Bagerhat - Completed - Completed
Receieved -
25/06/14;
Cleared by
the M&E
Consultants-
16/05/16
-
08/4/14;
Clearance
from M&E -
12/5/14 &
14/5/14
- Completed Completed Completed Completed 06-02-14 -
LGED/ECRRP/BHO/15-16/W-43 7 R
Bhola Sadar,
Daulatkhan and
Bhorhanuddin
Bhola - Completed - Completed
Receieved -
17/04/16;
Cleared by
the M&E
Consultants-
12/05/16
-
02/12/15;
Clearance
from M&E -
22/12/15
- Completed Completed Completed Completed 14/12/2015 -
Design Works EIA/ IEE Study Tender Process
Contract
signed -
date
Date of
clearance
by M&E
Date of
clearance
of WB
Date of
clearance
of WB
Contrac
t ID
Letter of
Award -
date
Package wise Shelter information
Location of the ShelterSocial and
Resettlement Study No. of
Cyclone
Shelter
cum
School
Shelter
construction
or repair/
improvement
?
(C or R)
Tender notice up to signing of contract
Package No.
Preparatory works up to design approval
Date of
clearance
by M&E
Design
approval
date
Remarks
(any relevant
information
not yet
included e.g.
causes of
delays) Upazila District
Start
date
Finish
date
Start
date
Tender
notice -
date
Site Selection
Tender
received -
date
Tender
approval -
date
Annex 3E: Monitoring Form PMF-B2: Process Monitoring - Package wise Improvement of Cyclone Shelters (2nd Phase)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 72
Road ID /
Connected
Shelter ID
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
SCR-01/NS-37 1.045 Sharankhola Completed Completed -
SCR-02/NS-31 3.470 Chitalmari Completed Completed -
SCR-03/NS-30 2.100 Mollahat Completed Completed -
SCR-04/NS-29 2.250 Kachua Completed Completed -
SCR-05/NS-02 1.340 Fakirhat Completed Completed -
SCR-06/NS-10 7.000 Amtali Completed Completed -
SCR-07/NS-25 2.125 Patharghata Completed Completed -
SCR-08/NS-26 2.380 Patharghata Completed Completed -
SCR-09/NS-27 2.145 Patharghata Completed Completed -
SCR-10/NS-22 1.700 Sadar Completed Completed -
SCR-11/NS-21 0.050 Sadar Completed Completed -
SCR-12/NS-23 1.000 Najirpur Completed Completed -
SCR-13/NS-24 2.000 Najirpur Completed Completed -
SCR-14/NS-48 2.500 Nesarabad Completed Completed -
SCR-15/NS-47 3.000 Nesarabad Completed Completed -
SCR-16/NS-32 3.744 Barguna Sadar Completed Completed -
SCR-17/NS-12 3.106 Barguna Sadar Completed Completed -
SCR-18/NS-03 8.450 Sadar Completed Completed -
SCR-19/NS-36 4.150 Mongla Completed Completed -
SCR-20/NS-19 1.610 Muladi Completed Completed -
SCR-21/NS-08 1.500 Babugonj Completed Completed -
SCR-22/NS-07 0.495 Gournadi Completed Completed -
SCR-23/NS-17 1.535 Banaripara Completed Completed -
SCR-24/NS-13 2.950 Kalapara - Completed Completed -
SCR-25/NS-14 2.055 Kalapara Completed Completed -
SCR-26/NS-16 3.795 Galachipa Completed Completed -
SCR-27/NS-34 1.800 Bamna Completed Completed -
SCR-28/NS-35 2.050 Bamna Completed Completed -
SCR-29/NS-28 4.831 Betagi Completed Completed -
SCR-30/NS-46 4.800 Galachipa Completed Completed -
SCR-31/NS-43 1.162 Bauphal Completed Completed -
SCR-32/NS-44 0.300 Bauphal Completed Completed -
SCR-33/NS-45 1.000 Bauphal Completed Completed -
EIA/ IEE Study
Patuakhali
Barguna
Patuakhali
Completed
Completed
Completed
Barguna
Completed
Bagerhat
Date:30-09-2016
Completed Completed
Completed
Completed
LGED/ECRRP/BARI/11-12/R-06
LGED/ECRRP/BAR/11-12/R-04
District
Bagerhat
Barguna
Barisal 49.35
Completed
Completed
Completed
13.50 Completed
Completed Completed Completed
Package wise Access Road information
Location
Remarks
(any relevant
information
not yet
included e.g.
causes of
delays) Upazila Start date Finish date
12.90
51.00LGED/ECRRP/BAG/11-12/R-05
Tender notice up to signing of contractPreparatory works up to design approval
Site Selection
Letter of
Award - date
Tender
approval -
date
Tender Process
Contract
ID
Date of
clearance of
WB
Date of
Submission
to M&E
Tender
received -
date
LGED/ECRRP/PIR/11-12/R-03 46.30
28.10
LGED/ECRRP/BAG/11-12/R-01
LGED/ECRRP/BAR/11-12/R-02
Design
works - Date
of approval
36.80
Total
Access
Road in Km
Package No.
Bridge/
Culvert in
meter under
the Package
CompletedCompleted
Pirojpur
Completed
Receieved-
02/09/13;
Cleared by the
M&E consultants-
19/06/14
Completed
CompletedCompleted Completed-
Social and Resettlement
Study
Date of
clearance of
WB
Contract signed
- date
Tender
notice - date
Completed Completed
Completed
Date of
Submission to
M&E
Completed
Receieved-
02/09/13;
Cleared by the
M&E consultants-
19/06/14
Receieved-
02/09/13;
Cleared by the
M&E consultants-
19/06/14
-
-
Receieved-
02/09/13;
Cleared by the
M&E consultants-
19/06/14
-
Receieved-
02/09/13;
Cleared by the
M&E consultants-
19/06/14
-
31.25 Completed Completed Completed Completed
Completed
11.50
-
Completed
Completed
Completed
Completed
Completed
CompletedCompletedCompleted
LGED/ECRRP/PAT/11-12/R-09
Completed
Completed
Completed
Completed
Completed
CompletedLGED/ECRRP/BAR/11-12/R-08
LGED/ECRRP/PAT/11-12/R-07
Receieved-
02/09/13;
Cleared by the
M&E consultants-
19/06/14
Receieved-
02/09/13;
Cleared by the
M&E consultants-
19/06/14
-
Receieved-
02/09/13;
Cleared by the
M&E consultants-
19/06/14
-
Receieved-
02/09/13;
Cleared by the
M&E consultants-
19/06/14
-
Contract
cancelled
Receieved-
25/9/14;
Cleared by
the M&E
consultants-
19/2/15
Receieved-
25/9/14;
Cleared by
the M&E
consultants-
10/2/15
Receieved-
25/9/14;
Cleared by
the M&E
consultants-
23/2/15
Receieved-
25/9/14;
Cleared by
the M&E
consultants-
24/2/15
Receieved-
25/9/14;
Cleared by
the M&E
consultants-
21/12/14
Receieved-
25/9/14;
Cleared by
the M&E
consultants-
29/12/14
Receieved-
25/9/14;
Cleared by
the M&E
consultants-
21/12/14
Receieved-
25/9/14;
Cleared by
the M&E
consultants-
29/12/14
Receieved-
12/04/15;
Cleared by
the M&E
consultants-
13/04/16
Annex 3F: Monitoring Form PMF-B2: Process Monitoring - Package wise Construction of Shelter Connecting Road (1st Phase)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 73
Road ID /
Connected
Shelter ID
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
SCR-50/NS-190 0.875 Hizla Completed Completed -
SCR-51/NS-189 1.566 Muladi Completed Completed -
SCR-52/NS-188 2.500 Muladi Completed Completed -
SCR-60/NS-64 4.700 Galachipa Completed Completed -
SCR-61/NS-65 3.500 Galachipa Completed Completed -
SCR-62/NS-66 0.068 Galachipa Completed Completed -
SCR-108/NS-62 1.650 Bauphal Completed Completed -
SCR-98/NS-206 1.960 Amtali Completed Completed -
SCR-99/NS-53 2.912 Amtali Completed Completed -
SCR-100/NS-200 3.915 Amtali Completed Completed -
SCR-101/NS-54 4.135 Amtali Completed Completed -
SCR-107/NS-51 1.385 Amtali Completed Completed -
SCR-34/NS-139 4.169 Mothbaria Completed Completed -
SCR-35/NS-174 1.612 Mothbaria Completed Completed
SCR-36/NS-175 0.100 Mothbaria Completed Completed -
SCR-83/NS-169 1.400 Shyamnagar Completed Completed -
SCR-84/NS-172 3.342 Shyamnagar Completed Completed -
SCR-85/NS-171 2.750 Shyamnagar Completed Completed -
SCR-86/NS-166 1.750 Shyamnagar Completed Completed -
SCR-87/NS-167 0.750 Shyamnagar Completed Completed -
SCR-92/NS-213 2.060 Patuakhali Sadar Completed Completed -
SCR-93/NS-212 0.750 Patuakhali Sadar Completed Completed -
SCR-94/NS-69 0.500 Patuakhali Sadar Completed Completed -
SCR-95/NS-218 0.800 Dashmina Completed Completed -
SCR-96/NS-63 0.225 Dashmina Completed Completed -
SCR-97/NS-68 0.885 Mirjaganj Completed Completed -
SCR-48/NS-147 4.725 Mongla - Completed Completed -
SCR-49/NS-141 2.515 Sarankhola Completed Completed -
Receieved-
29/12/13 &
29/10/14;
Cleared by
the M&E
Consultants-
1/12/14
Receieved-
13/1/14 &
29/10/14;
Cleared by
the M&E
Consultants-
26/11/14
Receieved-
22/1/14 &
29/10/14;
Cleared by
the M&E
Consultants-
26/11/14
Receieved-
22/1/14 &
29/10/14;
Cleared by
the M&E
Consultants-
26/11/14
Receieved-
1/1/14 &
29/10/14;
Cleared by
the M&E
Consultants-
26/11/14
-
-LGED/ECRRP/BAG/11-12/R-16
Receieved-
20/2/14 &
29/10/14;
Cleared by
the M&E
Consultants-
1/12/14
Completed
Completed
Completed
17/10/12
22/5/2013
19/03/13
Completed CompletedCompleted
Completed
Completed
Completed
20/01/13Completed
-
Receieved-
18/5/14; Cleared
by M&E
Consultants-
18/3/15
-
Completed-
Receieved-
05/9/13; Cleared
by M&E
Consultants-
19/6/14
Receieved-
18/5/14; Cleared
by M&E
Consultants-
18/3/15
Completed
Contract signed
- date
Tender
notice - date
Completed
Date of
Submission to
M&E
-
Receieved-
05/9/13; Cleared
by M&E
Consultants-
19/6/14
-
Barguna
Completed
Receieved-
05/9/13; Cleared
by M&E
Consultants-
19/6/14
Completed
Receieved-
05/9/13; Cleared
by M&E
Consultants-
19/6/14
03-04-13
28/01/13
03-07-13
Barguna
Receieved-
17/12/13 &
25/9/14;
Cleared by
the M&E
Consultants-
02/10/14
Preparatory works up to design approval
Site Selection
Letter of
Award - date
Tender
approval -
date
Tender Process
Contract
ID
Date of
clearance of
WB
Date of
Submission
to M&E
EIA/ IEE Study Design
works - Date
of approval
Remarks
(any relevant
information
not yet
included e.g.
causes of
delays) Upazila Start date Finish date
37.00
31.00 Completed Completed
Tender notice up to signing of contractPackage wise Access Road information
Location
LGED/ECRRP/SAT/11-12/R-14 Satkhira
Bridge/
Culvert in
meter under
the Package
Pirojpur
10.80
LGED/ECRRP/BAR/11-12/R-12 20.00
36.80
Package No.
LGED/ECRRP/BAR/11-12/R-10
LGED/ECRRP/PAT/11-12/R-11
CompletedCompleted
District
Barisal
Tender
received -
date
Social and Resettlement
Study
Date of
clearance of
WB
Patuakhali 1.20
Completed
25/3/13
64.00 Completed
Completed
Completed
Receieved-
18/5/14; Cleared
by M&E
Consultants-
18/3/15
Date:30-09-2016
Completed
Bagerhat
Total
Access
Road in Km
Completed
Completed
Completed
LGED/ECRRP/PAT/11-12/R-15
LGED/ECRRP/PIR/11-12/R-13
Annex 3G: Monitoring Form PMF-B2: Process Monitoring - Package wise Construction of Shelter Connecting Road (2nd Phase)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 74
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
SCR-102/NS-59 3.096 Patharghata Completed Completed -
SCR-103/NS-197 0.630 Patharghata Completed Completed -
SCR-104/NS-205 2.460 Barguna Sadar Completed Completed -
SCR-105/NS-57 3.000 Barguna Sadar Completed Completed -
SCR-106/NS-201 4.030 Barguna Sadar Completed Completed -
SCR-64/NS-92 0.695 Lalmohan Completed Completed -
SCR-65/NS-91 1.000 Lalmohan Completed Completed -
SCR-66/NS-87 0.050 Daulatkhan Completed Completed -
SCR-67/NS-86 0.350 Daulatkhan Completed Completed -
SCR-68/NS-85 0.030 Daulatkhan Completed Completed -
SCR-69/NS-84 2.600 Daulatkhan Completed Completed -
SCR-70/NS-88 0.045 Borhanuddin Completed Completed -
SCR-71/NS-89 0.100 Borhanuddin Completed Completed -
SCR-72/NS-80 0.050 Bhola Sadar Completed Completed -
SCR-73/NS-81 0.500 Bhola Sadar Completed Completed -
SCR-74/NS-82 0.030 Bhola Sadar Completed Completed -
SCR-75/NS-86 0.863 Bhola Sadar Completed Completed -
SCR-76/NS-2225 0.580 Charfassion Completed Completed -
SCR-77/NS-226 0.220 Charfassion Completed Completed -
SCR-78/NS-96 1.400 Charfassion Completed Completed -
SCR-88/NS-152 2.250 Kalaroa Completed Completed -
SCR-89/NS-191 2.625 Kaliganj Completed Completed -
SCR-90/NS-195 0.730 Satkhira Sadar Completed Completed -
SCR-91/NS-194 0.240 Debhata Completed Completed -
SCR-53/NS-182 2.000 Agaljhara Completed Completed -
SCR-54/NS-183 1.150 Banaripara Completed Completed -
SCR-55/NS-185 1.200 Uzirpur Completed Completed -
SCR-56/NS-181 0.600 Agaljhara Completed Completed -
SCR-111/NS-134 3.950 Koyra Completed Completed -
SCR-112/NS-124 0.850 Koyra Completed Completed -
SCR-113/NS-129 0.350 Koyra Completed Completed -
SCR-114/NS-127 2.350 Koyra Completed Completed -
SCR-115/NS-128 1.200 Koyra Completed Completed -
SCR-116/NS-130 2.574 Koyra Completed Completed -
Road ID /
Connected
Shelter IDTender
notice - date
Tender
received -
date
Tender
approval -
date
Letter of
Award - date
Contract signed
- date
Contract
ID
Design
works - Date
of approval
EIA/ IEE Study Social and Resettlement
Study Tender Process
Upazila District Start date Finish date
Date of
Submission
to M&E
Date of
clearance of
WB
Date:30-09-2016
Package wise Access Road information Preparatory works up to design approval Tender notice up to signing of contract Remarks
(any relevant
information
not yet
included e.g.
causes of
delays)
Package No.
Total
Access
Road in Km
Location Bridge/
Culvert in
meter under
the Package
Site Selection
Receieved-
02/9/14 ;
Cleared by
the M&E
Consultants-
12/1/15
'Receieved-
25/9/14 ;
Cleared by
the M&E
Consultants-
10/12/14
- -
Receieved-
25/9/14 ;
Cleared by
the M&E
Consultants-
14/12/14
Receieved-
05/9/13; Cleared
by M&E
Consultants-
19/6/14
-
Receieved-
05/9/13; Cleared
by M&E
Consultants-
19/6/14
-
Date of
Submission to
M&E
Date of
clearance of
WB
Completed 22/10/12
LGED/ECRRP/KHU/11-12/R-21 Khulna 13.20 Completed 25/03/13 Completed Completed 20/5/2013
LGED/ECRRP/BARI/11-12/R-20 Barisal 68.60 Completed Completed Completed
Receieved-
05/9/13; Cleared
by M&E
Consultants-
19/6/14
-
Receieved-
25/9/14 ;
Cleared by
the M&E
Consultants-
11/12/14
Completed 18/10/12
LGED/ECRRP/SAT/11-12/R-19 Satkhira 12.40 Completed Completed Completed Completed 14/01/13
LGED/ECRRP/BAR/11-12/R-17
LGED/ECRRP/BHO/11-12/R-18 Bhola 10.50 Completed
Receieved-
05/9/13; Cleared
by M&E
Consultants-
19/6/14
-
Receieved-
24/12/13 &
25/9/14;
Cleared by
the M&E
Consultants-
27/10/14
24/01/13Completed CompletedCompleted
Completed Completed
15.80 CompletedBarguna
Annex 3G: Monitoring Form PMF-B2: Process Monitoring - Package wise Construction of Shelter Connecting Road (2nd Phase) Cont.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 75
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
SCR-110/NS-133 0.470 Koyra Completed Completed -
SCR-117/NS-125 2.100 Koyra Completed Completed -
SCR-118/NS-132 3.150 Koyra Completed Completed -
SCR-119/NS-131 3.150 Koyra Completed Completed -
SCR-120/NS-123 1.626 Dacope Completed Completed -
SCR-121/NS-126 1.550 Koyra Completed Completed -
SCR-79/NS-154 3.350 Assasuni Completed Completed -
SCR-80/NS-155 1.000 Assasuni Completed Completed -
SCR-81/NS-156 3.900 Assasuni Completed Completed -
SCR-82/NS-73 3.150 Assasuni Completed Completed -
SCR-122/NS-99 0.600 Sadar Completed Completed -
SCR-123/NS-102 1.000 Sadar Completed Completed -
SCR-124/NS-101 0.750 Sadar Completed Completed -
SCR-125/NS-221 0.050 Sadar Completed Completed -
SCR-126/NS-220 0.120 Sadar Completed Completed -
SCR-127/NS-224 1.150 Kathalia Completed Completed -
SCR-128/NS-107 0.225 Rajapur Completed Completed -
SCR-129/NS-108 0.500 Rajapur Completed Completed -
SCR-130/NS-223 0.920 Rajapur Completed Completed -
SCR-131/NS-110 0.345 Kathalia Completed Completed -
SCR-132/NS-222 0.296 Nalchity Completed Completed -
SCR-57/NS-140 3.200 Sadar Completed Completed -
SCR-58/NS-145 2.000 Chitalmari Completed Completed -
SCR-59/NS-143 1.525 Fakirhat Completed Completed -
SCR-37/NS-161 1.225 Nesarabad Completed Completed -
SCR-38/NS-160 2.048 Nesarabad Completed Completed -
SCR-39/NS-162 1.275 Nesarabad Completed Completed -
SCR-40/NS-176 1.200 Nazirpur Completed Completed -
SCR-41/NS-177 0.234 Nazirpur Completed Completed -
SCR-43/NS-47 0.035 Sadar Completed Completed -
SCR-44/NS-48 0.271 Bhandaria Completed Completed -
SCR-45/NS-43 0.034 Bhandaria Completed Completed -
SCR-46/NS-44 0.500 Kawkhali Completed Completed -
SCR-47/NS-45 0.950 Kawkhali Completed Completed -
SCR-133 1.500 Dasmina Completed Completed -
SCR-134 2.210 Galachipa Completed Completed
SCR-135 2.650 Galachipa Completed Completed
SCR-136 2.000 Dumki Completed Completed
SCR-137 2.690 Rangabali Completed Completed -
SCR-138 3.500 Rangabali Completed Completed -
SCR-139 1.300 Mirjaganj Completed Completed -
SCR-140 0.575 Kalapara Completed Completed -
SCR-141 0.100 Kalapara Completed Completed -
Road ID /
Connected
Shelter ID
Date of
clearance of
WB
Tender
notice - date
Tender
received -
date
Tender
approval -
date
Letter of
Award - date
Date of
clearance of
WB
Completed Completed Completed
Contract signed
- date
Design
works - Date
of approval
EIA/ IEE Study Social and Resettlement
Study Tender Process
Upazila District Start date Finish date
Date of
Submission
to M&E
Date:30-09-2016
Package wise Access Road information Preparatory works up to design approval Tender notice up to signing of contractRemarks
(any relevant
information
not yet
included e.g.
causes of
delays)
Package No.
Total
Access
Road in Km
Location Bridge/
Culvert in
meter under
the Package
Site Selection
Completed -LGED/ECRRP/PAT/14-15/R-28 Patuakhali -
Receieved-
23/11/15 ;
Cleared by
the M&E
Consultants-
20/12/15
Receieved-
02/6/15; Cleared
by M&E
Consultants-
05/7/15
-
Receieved-
11/3/14 &
25/9/14;
Cleared by
the M&E
Receieved-
11/3/14 &
25/9/14;
Cleared by
the M&E
Consultants-
27/10/14
- -
Receieved-
05/9/13; Cleared
by M&E
Consultants-
19/6/14
-
Receieved-
25/9/14 ;
Cleared by
the M&E
Consultants-
15/12/14
Receieved-
25/9/14 ;
Cleared by
the M&E
Consultants-
15/12/14
Date of
Submission to
M&E
Completed
Completed 22/5/2013
LGED/ECRRP/KHU/11-12/R-22 Khulna 28.20 Completed 25/03/13 Completed
LGED/ECRRP/SAT/11-12/R-23 Satkhira 0.00 Completed 25/03/13 Completed
LGED/ECRRP/JHA/11-12/R-24 Jhalokathi 8.40 Completed Completed Completed- -
Receieved-
25/9/14 &
04/2/15;
Cleared by
the M&E
Consultants-
21/5/15
(Covering 07
SCRs)
LGED/ECRRP/BAG/11-12/R-25 Bagerhat 58.20 Completed Completed Completed
Receieved-
05/9/13; Cleared
by M&E
Consultants-
19/6/14
-
LGED/ECRRP/PIR/11-12/R-26 Pirojpur 82.75 Completed Completed Completed
Receieved-
25/9/14 ;
Cleared by
the M&E
Consultants-
18/12/14
Receieved-
05/9/13; Cleared
by M&E
Consultants-
19/6/14
-
LGED/ECRRP/PIR/11-12/R-27 Pirojpur 47.60 Completed 28/03/13 Completed
Receieved-
05/9/13; Cleared
by M&E
Consultants-
19/6/14
- Completed 05-07-13
Contract
ID
06-09-13
Completed 11-07-12
Completed 22/01/13
Completed 25/3/2013
Annex 3G: Monitoring Form PMF-B2: Process Monitoring - Package wise Construction of Shelter Connecting Road (2nd Phase) Cont.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 76
Annex 3G: Monitoring Form PMF-B2: Process Monitoring - Package wise Construction of Shelter Connecting Road (2nd Phase) Cont.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
SCR-142 0.600 Sadar Completed Completed -
SCR-144 1.500 Mathbaria Completed Completed -
SCR-145 1.000 Mathbaria Completed Completed -
SCR-146 1.050 Nazirpur Completed Completed -
SCR-147 0.560 Nesarabad Completed Completed -
SCR-143 0.200 Patharghata Completed Completed -
SCR-148 0.600 Amtoli Completed Completed
SCR-149 3.350 Taltoli Completed Completed
SCR-150 2.500 Taltoli Completed Completed
SCR-152 1.200 Bamna Completed Completed -
SCR-153 1.104 Sadar Completed Completed -
SCR-154 0.500 Sadar Completed Completed -
SCR-155 3.150 Patharghata Completed Completed -
SCR-156 1.600 Taltoli Completed Completed -
SCR-157 3.550 Sadar Completed Completed -
SCR-158 0.350 Sadar Completed Completed -
SCR-159 1.980 Nalcity Completed Completed -
SCR-160 2.150 Hijla Completed Completed -
SCR-161 1.360 Hijla Completed Completed
SCR-162 0.800 Sadar Completed Completed
SCR-163 0.500 Agailjhara Completed Completed
SCR-164 1.550 Agailjhara Completed Completed -
SCR-165 2.800 Babugonj Completed Completed -
SCR-166 1.000 Shyamnagar Completed Completed -
SCR-167 0.850 Shyamnagar Completed Completed
SCR-168 3.250 Shyamnagar Completed Completed
SCR-169 3.540 Kaliganj Completed Completed
SCR-170 2.800 Assasuni Completed Completed -
SCR-171 4.091 Assasuni Completed Completed
SCR-172 2.200 Assasuni Completed Completed -
Road ID /
Connected
Shelter ID
Tender
received -
date
Date of
Submission to
M&E
Date of
clearance of
WB
Tender
notice - date
Letter of
Award - date
Design
works - Date
of approval
EIA/ IEE Study Social and Resettlement
Study Tender Process
Contract signed
- date
Contract
IDDistrict Start date Finish date
Date of
Submission
to M&E
Date of
clearance of
WB
Tender
approval -
date
Bridge/
Culvert in
meter under
the Package
Date:30-09-2016
Package wise Access Road information Preparatory works up to design approval Tender notice up to signing of contractRemarks
(any relevant
information
not yet
included e.g.
causes of
delays)
Package No.
Total
Access
Road in Km
Location Site Selection
Upazila
Completed Completed Completed Completed -LGED/ECRRP/SAT/14-15/R-33 Satkhira -
Receieved-
06/10/15;
Cleared by
M&E
Consultants-
07/2/16
Receieved-
06/10/15 &
17/12/15;
Cleared by M&E
Consultants-
18/11/15 &
19/1/16
-
Completed Completed Completed Completed -LGED/ECRRP/BARI/14-15/R-32 Barisal -
Receieved-
23/12/15;
Cleared by
M&E
Consultants-
25/1/16
-
Complete
dCompleted
Comple
ted
Complete
d-LGED/ECRRP/JHA/14-15/R-31 Jhalokathi -
Receieved-
07/12/15;
Cleared by
M&E
Consultants-
26/1/16
Receieved-
08/9/15; Cleared
by M&E
Consultants-
21/9/15
-
Completed Completed Completed Completed -LGED/ECRRP/BAR/14-15/R-30 Barguna -
Receieved-
30/11/15 ;
Cleared by
the M&E
Consultants-
13/12/15
Receieved-
02/9/15; Cleared
by M&E
Consultants-
20/9/15
-
Completed Completed Completed Completed -LGED/ECRRP/PIR/14-15/R-29 Pirojpur -
Receieved-
23/11/15 ;
Cleared by
the M&E
Consultants-
21/12/15
Receieved-
28/6/15; Cleared
by M&E
Consultants-
15/7/15
-
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 77
Annex 3G: Monitoring Form PMF-B2: Process Monitoring - Package wise Construction of Shelter Connecting Road (2nd Phase) Cont.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
SCR-173 2.341 Shyamnagar Completed Completed -
SCR-174 1.100 Shyamnagar Completed Completed
SCR-176 1.800 Shyamnagar Completed Completed
SCR-177 2.237 Kaliganj Completed Completed
SCR-178 2.100 Assasuni Completed Completed -
SCR-179 0.200 Assasuni Completed Completed
SCR-180 1.894 Assasuni Completed Completed
SCR-181 0.825 Dacope Completed Completed -
SCR-182 0.400 Koyra Completed Completed
SCR-183 3.150 Dacope Completed Completed
SCR-184 1.800 Koyra Completed Completed
SCR-185 0.837 Dacope Completed Completed -
SCR-186 0.997 Koyra Completed Completed -
SCR-187 0.200 Dacope Completed Completed -
SCR-188 2.525 Koyra Completed Completed -
SCR-189 2.050 Koyra Completed Completed -
SCR-190 1.200 Koyra Completed Completed -
SCR-192 1.997 Bakerganj Completed Completed
SCR-193 2.600 Mehendiganj Completed Completed
SCR-194 1.250 Nesarabad Completed Completed -
SCR-195 0.800 Sadar Completed Completed
SCR-196 1.250 Mathbaria Completed Completed
SCR-197 2.020 Kawkhali Completed Completed
LGED/ECRRP/BARI/15-16/R-39 SCR-201/NS-235 3.020 Bakerganj Barisal - - - - -
Receieved-
29/06/16 ;
Cleared by the
M&E
Consultants-
20/07/16
-
LGED/ECRRP/BAG/12-13/R-5A SCR-18/NS-03 8.450 Sadar Bagerhat - Completed Completed - - - - Completed Completed Completed Completed 31/12/2013
LGED/ECRRP/BAG/12-13/R-5B SCR-19/NS-36 4.150 Mongla Bagerhat - Completed Completed - - - - Completed Completed Completed Completed 31/12/2013
Tender
received -
date
Tender
approval -
date
Letter of
Award - date
Date of
Submission to
M&E
Date of
clearance of
WB
Tender
notice - date
Contract
ID
Road ID /
Connected
Shelter ID
Tender Process
Upazila District Start date Finish date
Date of
Submission
to M&E
Date of
clearance of
WB
Remarks
(any relevant
information
not yet
included e.g.
causes of
delays)
Package No.
Total
Access
Road in Km
Location
Bridge/
Culvert in
meter under
the Package
Site Selection
Design
works - Date
of approval
EIA/ IEE Study Social and Resettlement
Study
Contract signed
- date
Date:30-09-2016
Package wise Access Road information Preparatory works up to design approval Tender notice up to signing of contract
-Khulna - Completed Completed Completed CompletedLGED/ECRRP/KHU/14-15/R-35
Receieved-
04/11/15;
Cleared by M&E
Consultants-
01/12/15
-
Completed Completed Completed
Receieved-
28/12/15 ;
Cleared by
the M&E
Consultants-
08/2/16
Completed -LGED/ECRRP/BAG/14-15/R-34 Satkhira -
Receieved-
21/10/15 ;
Cleared by
the M&E
Consultants-
30/11/15
Receieved-
21/10/15 &
17/12/15;
Cleared by M&E
Consultants-
22/11/15 &
19/1/16
-
LGED/ECRRP/BARI/15-16/R-36 Barisal -
Receieved-
20/03/16 ;
Cleared by
the M&E
Consultants-
05/05/16
Receieved-
21/1/16; Cleared
by M&E
Consultants-
02/3/16
- Completed Completed Completed Completed -
LGED/ECRRP/PIR/15-16/R-37 Khulna -
Receieved-
20/03/16 ;
Cleared by
the M&E
Consultants-
10/05/16
Receieved-
28/02/16 ;
Cleared by the
M&E
Consultants-
27/04/16
- Completed Completed Completed Completed -
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 78
Killa ID
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
KL- 01 Amtali Completed Completed -
KL- 02 Amtali Completed Completed -
KL- 03 Amtali Completed Completed -
KL- 04 Amtali Completed Completed -
KL- 05 Sadar Completed Completed -
KL- 06 Bamna Completed Completed -
KL- 07Jhalokathi
SadarCompleted Completed - -
KL- 08 Rajapur Completed Completed - -
KL- 09 Kathalia Completed Completed - -
KL- 10 Nalchitty Completed Completed - -
KL- 11 Mothbaria Completed Completed - -
KL- 12 Mothbaria Completed Completed -
KL- 13 Bhandaria Completed Completed -
KL- 14 Zianagar Completed Completed -
KL- 15 Nesarabad Completed Completed -
KL- 16 Kawkhali Completed Completed -
KL- 17 Lalmohon Completed Completed -
KL- 18 Lalmohon Completed Completed -
KL- 19 Lalmohon Completed Completed -
KL- 20 Lalmohon Completed Completed -
KL- 21 Charfassion Completed Completed -
KL- 22 Charfassion Completed Completed -
LGED/ECRRP/BHO/11-12/KW-04 Bhola
Receieved-
09/9/13 &
02/06/16 ;
Cleared by M&E
Consultants-
26/06/16 (KL-13,
Kl-14 & Kl-16)
-
LGED/ECRRP/PIR/11-12/KW-03 Pirojpur
Receieved-
09/9/13;
Comments
made by M&E
Consultants-
30/10/13
Completed
Completed
Completed
Completed
Receieved-
27/4/15;
Cleared by
the M&E
Consultants-
09/6/15
Receieved-
27/4/15;
Cleared by
the M&E
Consultants-
07/6/15
(Covering 3
Killas KL-13,
14 & 16)
-
Receieved-
27/4/15;
Cleared by
the M&E
Consultants-
10/6/15
Date:30-09-2016
Completed
Receieved-
09/9/13;
Comments
made by M&E
Consultants-
30/10/13
-
-
Completed
Completed
Completed
LGED/ECRRP/JHA-SAT/11-12/KW-02
Barguna
Remarks
(any relevant
information
not yet
included e.g.
causes of
delays)
Upazila District Start date Finish dateLetter of
Award - date
Date of
clearance of
WB
Contract signed
- date
Tender
received -
date
Date of
Submission to
M&E
LGED/ECRRP/BAR/11-12/KW-01
Package No.
Completed
Tender Process
Date of
clearance of
WB
CompletedCompleted
Completed
Date of
Submission
to M&E
Completed
Tender
approval -
date
Tender
notice - date
Jhalokathi
-
Completed
Tender notice up to signing of contract
Social and Resettlement
Study
Preparatory works up to design approvalPackage wise Killa information
Contract
ID
Completed
Site SelectionLocation Design
works - Date
of approval
EIA/ IEE Study
Dropped due
to land
dispute
- -
Completed Completed
Completed
Annex 3H: Monitoring Form PMF-B2: Process Monitoring - Package wise Construction of Killa
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 79
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(No./ %)
Financial
(Taka in
lakh)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
LGED/ECRRP/BAG/10-11/NW-01 4 C
Morrelgonj,
Fakirhat &
Bagerhat Sadar
Bagerhat 746.30 527.65 27/04/201131/12/2013
(Extended)100 0 100 527.65 0.00 527.65 NS-03 dropped
LGED/ECRRP/BARI/10-11/NW-02 4 C
Barisal Sadar,
Agailjhara,
Gouronadi &
Babugonj
Barisal 804.12 895.17 03-06-1116/2/2013
(Extended)100 0 100 897.54 0.00 897.54
LGED/ECRRP/BAR/10-11/NW-03 4 CAmtoli &
Barguna SadarBarguna 878.87 786.94 25/5/2011
30/6/2013
(Extended)100 0 100 766.94 0.00 766.94
LGED/ECRRP/PAT/10-11/NW-04 4 CKolapara &
GolachipaPatuakhali 797.35 682.43 04-04-11
30/6/2013
(Extended)100 0 100 682.43 0.00 682.43
LGED/ECRRP/BARI/10-11/NW-05 4 C
Banaripara,
Ujirpur, Muladi &
Mehendigonj
Barisal 804.17 886.47 14/4/201130/6/2013
(Extended)100 0 100 886.47 0.00 886.47
LGED/ECRRP/PIR/10-11/NW-06 4 CPirojpur Sadar &
NazirpurPirojpur 763.65 840.08 05-10-11
30/6/2013
(Extended)100 0 100 841.24 0.00 841.24
LGED/ECRRP/BAR/10-11/NW-07 4 CPathorghata &
BetagiBarguna 897.75 563.59 05-03-11
31/10/2013
(Extended)100 0 100 563.59 0.00 563.59
NS-27 dropped
due to land
dispute
LGED/ECRRP/BAG/10-11/NW-08 3 C
Kachua,
Mollahat &
Chitolmari
Bagerhat 650.41 817.60 25/10/2011 05-02-13 21 0 21 171.70 0.00 171.70Contract
cancelled
LGED/ECRRP/BAR/10-11/NW-09 4 CBarguna Sadar
& BamnaBarguna 889.71 790.14 05-03-11
31/10/2013
(Extended)100 0 100 790.14 0.00 790.14
LGED/ECRRP/BAG/10-11/NW-10 3 CMongla, Rampal
& ShoronkholaBagerhat 566.84 689.44 10-03-11
30/11/2013
(Extended)100 0 100 689.44 5.00 689.44
LGED/ECRRP/PAT/10-11/NW-11 4 C
Patuakhali
Sadar, Dumki,
Mirjagonj &
Doshmina
Patuakhali 759.67 820.80 06-06-1131/12/2013
(Extended)100 0 100 820.80 0.00 820.80
LGED/ECRRP/PAT/10-11/NW-12 4 CBauphal &
GalachipaPatuakhali 703.09 669.23 08-10-11
30/6/2014
(Extended)100 0 100 672.02 0.00 672.02
LGED/ECRRP/PIR/10-11/NW-13 4 C
Nesarabad,
Mothbaria &
Bhandaria
Pirojpur 681.37 746.01 08-04-1130/10/2013
(Extended)100 0 100 749.58 0.00 749.58
9059.54
Date:30-09-2016
Total Target as per
RDPP (2nd Revised) &
AM March 2016
353 107,162.92 128 nos.
(Partly)
17275 45 nos.
(100%)
Package No.
Overall Progresss as
of end of June FY
2015-2016
Annual Target for FY
2016-2017 (As per
Annual Work Plan)
Location of the ShelterNo. of
Cyclone
Shelter cum
School
Shelter
construction or
repair/
improvement?
(C or R)
Physical Progress (%) Financial Progress (Taka in lakh)
Cumulative
as of 30th
June 2016
This quarter TotalCumulative as of
30th June 2016This quarter Total
Target date of
completion
Upazila District
Package Cost
(Tk in lakh)
Contract Cost
(Tk in lakh)
Date of
Contract
sign/
commencem
ent of work
Remarks
Annex 3I: Monitoring Form PMF-B3: Progress Monitoring - Package wise Construction of 45 New Cyclone Shelters (1st Phase)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 80
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(No./ %)
Financial
(Taka in
lakh)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
LGED/ECRRP/BAR/11-12/NW-14 10 C
Amtali, Barguna
Sadar, Betagi &
Patharghata
Barguna 2787.34 3050.05 28/3/201230/6/2014
(Extended)100 0 100 3050.63 0.00 3050.63
LGED/ECRRP/PAT/11-12/NW-15 10 C
Bauphal,
Dasmina,
Galachipa,
Kalapara,
Mirzjagonj,
Patuakhali
Sadar &
Patuakhali 2732.23 2980.07 20/3/201231/5/2014
(Extended)100 0 100 2980.07 0.00 2980.07
LGED/ECRRP/SAT/11-12/NW-16 9 C
Asasuni,
Kaligonj,
Kalaroa &
Shyamnagar
Satkhira 2369.74 2589.78 04-01-1230/4/2014
(Extended)100 0 100 2589.78 0.00 2589.78
LGED/ECRRP/BHO/11-12/NW-17 10 C
Bhola Sadar,
Daulatkhan &
Borhanuddin
Bhola 2654.12 3254.80 30/5/201222/5/2014
(Extended)100 0 100 3254.80 0.00 3254.80
LGED/ECRRP/BHO/11-12/NW-18 12 C
Lalmohon,
Tazumuddin,
Charfassion &
Monpura
Bhola 3662.37 4239.88 18/10/201230/6/2014
(Extended)100 0 100 4239.88 0.00 4239.88
LGED/ECRRP/SAT/11-12/NW-19 8 C Shyamnagar Satkhira 1876.01 2187.71 21/11/201230/6/2014
(Extended)100 0 100 2187.71 0.00 2187.71
LGED/ECRRP/KHU/11-12/NW-20 24 C Dacope & Koyra Khulna 6590.26 7596.32 12-12-1230/6/2014
(Extended)100 0 100 7596.32 0.00 7596.32
LGED/ECRRP/BAG/11-12/NW-21 4 C
Bagerhat Sadar,
Sharankhola &
Chitalmari
Bagerhat 920.94 1028.83 06-10-1225/11/2013
(Extended)100 0 100 1028.83 0.00 1028.83
LGED/ECRRP/BAG/11-12/NW-22 4 C
Rampal,
Fakirhat,
Morrelganj &
Mongla
Bagerhat 1283.65 1551.90 02-12-13 06-10-14 100 0 100 1405.42 146.48 1551.90
LGED/ECRRP/BAR/11-12/NW-23 5 C
Bamna,
Patharghata,
Betagi & Amtoli
Barguna 1190.54 1252.19 15/7/201230/4/2014
(Extended)100 0 100 1168.48 83.72 1252.19
LGED/ECRRP/BAR/11-12/NW-24 6 CBarguna Sadar
& AmtoliBarguna 1485.64 1592.80 08-01-12
30/06/2014
(Extended)100 0 100 1504.31 88.50 1592.80
LGED/ECRRP/BARI/11-12/NW-25 8 C
Gouranadi,
Agailjhara,
Banaripara,
Uzirpur & Sadar
Barisal 2003.32 2298.30 10-08-1231/5/2014
(Extended)100 0 100 2298.30 0.00 2298.30
LGED/ECRRP/BARI/11-12/NW-26 4 CBabuganj,
Muladi & HizlaBarisal 1131.43 1283.91 07-09-12
31/12/2013
(Extended)100 0 100 1283.91 0.00 1283.91
LGED/ECRRP/PAT/11-12/NW-27 5 C
Galachipa,
Kalapara &
Dumki
Patuakhali 1197.33 1242.28 25/7/201230/5/2014
(Extended)100 0 100 1242.28 0.00 1242.28
Date:30-09-2016
Total Target as per RDPP
(2nd Revised) & AM
March 2016
Package No.
Overall Progresss as
of end of June FY
2015-2016
Annual Target for FY
2016-2017 (As per
Annual Work Plan)
184 nos.
(99.87%) &
123 nos.
(30.73%)
17275128 nos.
(Partly)
107,162.92353
Location of the Shelter
No. of
Cyclone
Shelter cum
School
Shelter
construction or
repair/
improvement?
(C or R)
Contract Cost
(Tk in lakh)
Date of
Contract
sign/
commencem
ent of work
Physical Progress (%)
Target date of
completion
Upazila District
Package Cost
(Tk in lakh)
Financial Progress (Taka in lakh)
Cumulative
as of 30th
June 2016
This quarter Total
Cumulative as
of 30th June
2016
This quarter Total
68,561.60
Annex 3J: Monitoring Form PMF-B3: Progress Monitoring - Package wise Construction of Additional 307 New Cyclone Shelters (2nd Phase)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 81
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(No./ %)
Financial
(Taka in
lakh)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
LGED/ECRRP/PIR/11-12/NW-28 5 C
Kawkhali,
Bhandaria &
Mothbaria
Pirojpur 1206.78 1273.38 15/6/201230/5/2014
(Extended)100 0 100 1273.38 0.00 1273.38
LGED/ECRRP/PAT/11-12/NW-29 4 C
Patuakhali
Sadar &
Mirzaganj
Patuakhali 1037.26 1092.22 25/7/201230/4/2014
(Extended)100 0 100 1092.22 0.00 1092.22
LGED/ECRRP/PIR/11-12/NW-30 4 CPirojpur Sadar &
ZianagarPirojpur 1132.61 1219.65 06-03-13 10-03-14 100 0 100 1219.65 0.00 1219.65
LGED/ECRRP/PIR/11-12/NW-31 5 C
Mothbaria,
Nazirpur &
Kawkhali
Pirojpur 1165.02 1369.88 11-07-1230/6/2014
(Extended)95 5 100 1070.41 0.00 1070.41
LGED/ECRRP/SAT/11-12/NW-32 5 CSadar, Tala &
KolaroaSatkhira 1076.76 1302.68 25/11/2012
30/6/2014
(Extended)100 0 100 1302.68 0.00 1302.68
LGED/ECRRP/SAT/11-12/NW-33 5 C Asasuni Satkhira 1212.41 1381.30 07-04-1230/5/2014
(Extended)100 0 100 1381.30 0.00 1381.30
LGED/ECRRP/PAT/11-12/NW-34 4 C
Bauphal,
Dasmina &
Dumki
Patuakhali 1165.69 1226.10 25/7/201230/5/2014
(Extended)100 0 100 1182.17 43.92 1226.10
LGED/ECRRP/SAT/11-12/NW-35 5 C
Kaliganj,
Debhata &
Satkhira Sadar
Satkhira 1156.35 1386.21 07-08-1230/5/2014
(Extended)100 0 100 1386.21 0.00 1386.21
LGED/ECRRP/JHA/11-12/NW-36 7 C
Jhalokathi
Sadar &
Nalchity
Jhalokathi 1819.06 1890.16 27/6/201230/5/2014
(Extended)100 0 100 1805.71 84.45 1890.16
LGED/ECRRP/BAG/12-13/NW-37 1 C Bagerhat Sadar Bagerhat 361.61 363.70 27/6/2013 26/6/2014 100 0 100 363.70 0.00 363.70
LGED/ECRRP/JHA/11-12/NW-38 5 C
Nalchity,
Rajapur &
Kathalia
Jhalokathi 1177.13 1169.12 30/5/201230/5/2014
(Extended)100 0 100 1169.12 0.00 1169.12
LGED/ECRRP/JHA/11-12/NW-39 5 C
Jhalokathi
Sadar, Nalchity,
Rajapur &
Kathalia
Jhalokathi 1286.27 1443.34 07-02-1230/5/2014
(Extended)100 0 100 1443.34 0.00 1443.34
LGED/ECRRP/PIR/11-12/NW-40 4 CNesarabad &
KawkhaliPirojpur 1187.06 1233.64 19/6/2013 30/6/2014 100 0 100 1233.64 0.00 1233.64
LGED/ECRRP/KHU/11-12/NW-41 2 C Koyra Khulna 682.83 873.31 31/12/2013 06-01-15 100 0 100 873.31 0.00 873.31
LGED/ECRRP/PIR/11-12/NW-42 1 C Mothbaria Pirojpur 354.80 383.79 02-02-14 03-03-15 100 0 100 383.79 0.00 383.79
LGED/ECRRP/BAG/11-12/NW-08A 3 C
Kachua,
Mollahat &
Chitolmari
Bagerhat 895.77 999.95 03-02-14 02-06-15 100 0 100 999.95 0.00 999.95
LGED/ECRRP/BARI/14-15/NW-43 10 C
Sadar,
Mehendigonj,
Babugonj,
Muladi,
Bakergonj,
Agailjhara, Hijla
and Banaripara
Barisal 4264.74 3497.06 30/9/2015 10-06-16 39 4 43 1625.11 0.00 1625.11
LGED/ECRRP/JHL/14-15/NW-44 10 C
Sadar, Nalchity,
Kathalia and
Rajapur
Jhalokathi 3576.56 3391.27 30/8/2015 29/11/2016 40 19 59 1495.85 357.06 1852.90
LGED/ECRRP/PIR/14-15/NW-45 10 C
Sadar,
Bhandaria,
Mothbaria,
Kawkhali,
Nazirpur and
Pirojpur 3395.59 3370.70 21/9/2015 28/12/2016 37 3 40 1352.34 126.03 1478.37
LGED/ECRRP/BHO/14-15/NW-46 12 C
Sadar,Borhanud
din, Daulatkhan,
Lalmohon,
Charfassion and
Monpura
Bhola 4025.92 4349.97 22/12/2015 23/03/2017 30 13 43 1323.89 47.85 1371.74
LGED/ECRRP/PAT/14-15/NW-47 12 C
Rangabali,Kolap
ara, Golachipa,
Dashmina,
Mirzagonj,
Bauphal and
Dumki
Patuakhali 4626.74 4102.45 11-07-15 01-11-17 41 17 58 1655.45 243.15 1898.60
LGED/ECRRP/BAR/14-15/NW-48 13 C
Amtoli,Taltoli,
Patharghata,
Betagi and
Barguna Sadar
Barguna 4988.25 4488.20 24/7/2015 19/10/2016 40 10 50 1894.21 0.00 1894.21
LGED/ECRRP/KHL/14-15/NW-49 10 CDacope and
KoiraKhulna 3157.63 2895.54 11-11-15 02-08-17 34 3 37 988.96 0.00 988.96
LGED/ECRRP/BAG/14-15/NW-50 12 CMongla, Rampal
and MorrelgonjBagerhat 4709.34 4047.82 24/11/2015 23/2/2017 21 13 34 1418.76 75.24 1493.99
LGED/ECRRP/SAT/14-15/NW-51 11 C
Shyamnagar,
Kaligonj,
Debhata and
Assasuni
Satkhira 4110.40 3901.32 10-11-15 02-12-17 32 10 42 1213.65 288.71 1502.35
LGED/ECRRP/BARI/14-15/NW-52 5 C
Babugonj,
Mehendigonj
and Bakergonj
Barisal 1775.51 1515.95 27/12/2015 27/12/2017 23 20 43 394.12 108.41 502.53
LGED/ECRRP/PIR/15-16/NW-53 4 C
Kawkhali,
Mathbaria,
Nesarabad and
Pirojpur Sadar
Pirojpur 1329.33 1448.94 31/01/2016 02-07-17 24 10 34 307.81 68.93 376.74
LGED/ECRRP/SAT/15-16/NW-54 5 C
Shyamnagar,
Tala and
Assasuni
Satkhira 1637.29 1457.03 06-12-16 28/09/2017 0 13 13 145.70 103.58 249.28
LGED/ECRRP/PAT/15-16/NW-55 5 C
Dasmina,
Mirzagonj,
Bauphal and
Galachipa
Patuakhali 1693.10 1420.00 23/06/2016 17/09/2017 0 8 8 142.00 0.00 142.00
LGED/ECRRP/BAG/15-16/NW-56 4 C
Rampal,
Kachua, Mongla
and Mollahat
Bagerhat 1359.19 1454.13 06-12-16 18/08/2017 0 11 11 145.41 145.41 181.11
Date:30-09-2016
Total Target as per RDPP
(2nd Revised)
Annual Target for FY
2015-2016 (As per
Annual Work Plan)
Overall Progresss as
of end of June FY
2014-2015
Package No.
No. of
Cyclone
Shelter cum
School
Shelter
construction or
repair/
improvement?
(C or R)
Location of the Shelter
Package Cost
(Tk in lakh)
Contract Cost
(Tk in lakh)
Date of
Contract
sign/
commencem
ent of work
Target date of
completion
Physical Progress (%) Financial Progress (Taka in lakh)
Upazila District
Cumulative
as of 30th
June 2016
This quarter Total
Cumulative as
of 30th June
2016
This quarter Total
Annex 3J: Monitoring Form PMF-B3: Progress Monitoring - Package wise Construction of Additional 307 New Cyclone Shelters (2nd Phase) Cont.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 82
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(No./ %)
Financial
(Taka in
lakh)
Upazila District
Cumulative
as of 30th
June 2016
This
quarterTotal
Cumulative as
of 30th June
2016
This quarter Total
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
460 16879.46 2900.00 240 (100%) 6176.72
(100%) LGED/ECRRP/BAR/9-10/W-01 8 R Barguna Sadar Barguna 123.04 128.87 08/09/2010 05-10-11 100 0 100 128.87 - 128.87
LGED/ECRRP/BAG/9-10/W-02 10 RMorrelgonj &
SharankholaBagerhat 165.47 128.87 27/07/2010 16/6/2011 100 0 100 128.87 - 128.87
LGED/ECRRP/BAR/9-10/W-03 10 R Amtoli Barguna 272.11 216.08 28/09/2010 27/9/2011 100 0 100 216.08 - 216.08
LGED/ECRRP/BAR/9-10/W-04 12 R Bamna & Betagi Barguna 400.99 407.48 25/11/2010 21/2/2012 100 0 100 407.48 - 407.48
LGED/ECRRP/BAR/9-10/W-05 10 R Pathorghata Barguna 300.62 230.22 28/10/2010 17/10/2011 100 0 100 230.22 - 230.22
LGED/ECRRP/Bari/9-10/W-06 11 R Hijla & Muladi Barisal 181.83 195.29 16/08/2010 08-09-11 100 0 100 195.29 - 195.29
LGED/ECRRP/Bari/9-10/W-07 11 RMehendiganj &
BakerganjBarisal 387.99 453.29 25/10/2010 22/1/2012 100 0 100 453.29 - 453.29
LGED/ECRRP/Bari/9-10/W-08 12 RUzirpur &
BabuganjBarisal 339.73 384.05 27/09/2010 11-06-11 100 0 100 384.05 - 384.05
LGED/ECRRP/PIR/9-10/W-09 10 R
Mothbaria,
Bhandaria &
Nesarabad
Pirojpur 244.92 239.63 05/09/2010 09-04-11 100 0 100 239.63 - 239.63
LGED/ECRRP/PAT/9-10/W-10 11 R Sadar & Dumki Patuakhali 343.68 347.77 13/10/2010 22/11/2011 100 0 100 347.77 - 347.77
LGED/ECRRP/PAT/9-10/W-11 10 RMirjaganj &
DoshminaPatuakhali 235.48 240.10 13/10/2010 10-12-11 100 0 100 240.10 - 240.10
LGED/ECRRP/PAT/9-10/W-12 10 R Bauphal Patuakhali 286.48 294.67 27/10/2010 20/10/2011 100 0 100 293.73 - 293.73
LGED/ECRRP/PAT/9-10/W-13 7 R Kolapara Patuakhali 202.29 211.46 14/11/2010 09-07-11 100 0 100 210.80 - 210.80
LGED/ECRRP/PAT/9-10/W-14 12 R Golachipa Patuakhali 312.81 308.67 19/12/2010 30/11/2011 100 0 100 307.61 - 307.61
LGED/ECRRP/BHO/9-10/W-15 11 R Sadar Bhola 298.17 254.27 18/8/2011 17/08/2012 100 0 100 254.27 - 254.27
LGED/ECRRP/BHO/9-10/W-16 10 RSadar &
DaulatkhanBhola 292.03 290.59 8/12/2010 12-07-12 100 0 100 290.59 - 290.59
LGED/ECRRP/BHO/9-10/W-17 15 RLalmohon &
TojumuddinBhola 279.26 284.52 28/11/2010 27/11/2011 100 0 100 284.52 - 284.52
LGED/ECRRP/BHO/9-10/W-18 8 R Borhanuddin Bhola 204.26 196.87 29/11/2010 10-09-11 100 0 100 196.87 - 196.87
LGED/ECRRP/BHO/9-10/W-19 10 R Charfashion Bhola 240.10 236.75 8/12/2010 12-07-11 100 0 100 236.75 - 236.75
LGED/ECRRP/BHO/9-10/W-20 6 R Monpura Bhola 237.55 214.57 10/12/2010 18/12/2011 100 0 100 214.57 - 214.57
LGED/ECRRP/JALO/9-10/W-21 10 RSadar, Nalchity,
Rajapur & KathaliaJhalokathi 290.05 313.62 11/10/2010 10-10-11 100 0 100 313.62 - 313.62
LGED/ECRRP/KHU/9-10/W-22 10 R Dacope Khulna 328.59 221.89 2/11/2010 12-03-11 100 0 100 221.89 - 221.89
LGED/ECRRP/SAT/9-10/W-23 8 R Shyamnagar Satkhira 270.52 233.34 16/09/2010 15/9/2011 100 0 100 233.34 - 233.34
LGED/ECRRP/SAT/9-10/W-24 8 RDebhata, Kaligonj
& AssasuniSatkhira 210.49 146.53 15/09/2010 27/7/2011 100 0 100 146.53 - 146.53
70 nos.
existing
shelters(Par
tly) under
Phase II
Package No.
Annual Target for FY
2016-2017 (As per
Annual Work Plan)
Date:30-09-2016
Package
Cost
(Tk in lakh)
Shelter
construction or
repair/
improvement?
(C or R)
Overall Progresss as of
end of June FY 2015-
2016No. of
Cyclone
Shelter
cum
School
Physical Progress (%) Financial Progress (Taka in lakh)
Target date
of
completion
Location of the Shelter
Total Target as per
RDPP (2nd Revised) &
AM March 2016Contract
Cost
(Tk in
lakh)
Date of work
order/
commencement
of work
Annex 3K: Monitoring Form PMF-B3: Progress Monitoring - Package wise Improvement of Cyclone Shelters (1st Phase)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 83
Annex 3L: Monitoring Form PMF-B3: Progress Monitoring - Package wise Improvement of Cyclone Shelters (2nd Phase)
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(No./ %)
Financial
(Taka in
lakh)
Upazila District
Cumulative
as of 30th
June 2016
This
quarterTotal
Cumulative as
of 30th June
2016
This quarter Total
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
460 16879.46 2900.00 217 nos.
(Average-
97.24%)
9682.31
LGED/ECRRP/PIR/13-14/W-34 18 R
Nesarabad,
Pirojpur Sadar,
Bhandaria,
Mothbaria &
Zianagar
Pirojpur 1,163.24 1,259.31 27/04/2014 10-05-15 98 2 100 1,143.34 - 1,143.34
LGED/ECRRP/JHA/13-14/W-35 8 RKathalia,
Rajapur &
Nalchity
Jhalokathi 407.22 465.97 05/06/2014 05-05-15 100 0 100 465.97 - 465.97
LGED/ECRRP/BHO/13-14/W-36 42 RLalmohan,
Borhanuddin,
Charfassion,
Bhola 1,385.84 1,590.94 11/01/2015 01-10-16 95 0 95 1,322.28 44.37 1,366.64
LGED/ECRRP/KHU/13-14/W-37 30 RPaikgacha,
Koyra, Dumuria,
Batiaghata,
Khulna 1,350.73 1,521.34 29/10/2014 28/10/2015 100 0 100 1,521.34 - 1,521.34
LGED/ECRRP/PAT/13-14/W-38 27 RPatuakhali
Sadar, Bauphal, Patuakhali 988.63 1,064.10 01/9/2014 09-07-15 100 0 100 1,064.10 - 1,064.10
LGED/ECRRP/SAT/13-14/W-39 10 RDebhata,
Shyamnagar &
Ashasuni
Satkhira 580.72 641.41 05/7/2014 25/5/2015 100 0 100 641.41 - 641.41
LGED/ECRRP/BARI/13-14/W-40 17 RBabugonj,
Muladi, Hijla,
Bakergonj &
Barisal 538.56 604.39 21/8/2014 26/8/2015 100 0 100 604.39 - 604.39
LGED/ECRRP/BAR/13-14/W-41 36 RSadar, Bamna,
Betagi & AmtoliBarguna 1,484.29 1,710.21 18/12/2014 24/12/2015 89 2 91 1,421.26 - 1,421.26
LGED/ECRRP/BAG/13-14/W-42 28 RMollahat,
Rampal, Mongla,
Morrelgonj &
Bagerhat 1,336.03 1,377.98 02/6/2014 06-10-15 100 0 100 1,377.98 - 1,377.98
LGED/ECRRP/BHO/13-14/W-43 7 R
Sadar,
Daulatkhan &
Borhanuddin
Bhola 202.89 224.39 14/12/2015 13/12/2016 87 4 91 120.25 43.34 163.59
Contract
Cost
(Tk in lakh)
Date of work
order/
commencement
of work
Physical Progress (%) Financial Progress (Taka in lakh)
Target date
of
completion
Location of the Shelter
Total Target as per RDPP
(2nd Revised) & AM March
2016
70 nos.
existing
shelters
(Partly)
under
Phase II
Package No.
Annual Target for FY
2016-2017 (As per
Annual Work Plan)
Date:30-09-2016
Package
Cost
(Tk in lakh)
Shelter
construction or
repair/
improvement?
(C or R)
Overall Progresss as of
end of June FY 2015-
2016No. of
Cyclone
Shelter
cum
School
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 84
Road ID
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
SCR-01/NS-37 1.045 Sharankhola
SCR-02/NS-31 3.470 Chitalmari
SCR-03/NS-30 2.100 Mollahat
SCR-04/NS-29 2.250 Kachua
SCR-05/NS-02 1.340 Fakirhat
SCR-06/NS-10 7.000 Amtali
SCR-07/NS-25 2.125 Patharghata
SCR-08/NS-26 2.380 Patharghata
SCR-09/NS-27 2.145 Patharghata
SCR-10/NS-22 1.700 Sadar
SCR-11/NS-21 0.050 Sadar
SCR-12/NS-23 1.000 Najirpur
SCR-13/NS-24 2.000 Najirpur
SCR-14/NS-48 2.500 Nesarabad
SCR-15/NS-47 3.000 Nesarabad
SCR-16/NS-32 3.744 Barguna Sadar
SCR-17/NS-12 3.106 Barguna Sadar
SCR-18/NS-03 8.450 Sadar
SCR-19/NS-36 4.150 Mongla
SCR-20/NS-19 1.610 Muladi
SCR-21/NS-08 1.500 Babugonj
SCR-22/NS-07 0.495 Gournadi
SCR-23/NS-17 1.535 Banaripara
SCR-24/NS-13 2.950 Kalapara
SCR-25/NS-14 2.055 Kalapara
SCR-26/NS-16 3.795 Galachipa
SCR-27/NS-34 1.800 Bamna
SCR-28/NS-35 2.050 Bamna
SCR-29/NS-28 4.831 Betagi
SCR-30/NS-46 4.800 Galachipa
SCR-31/NS-43 1.162 Bauphal
SCR-32/NS-44 0.300 Bauphal
SCR-33/NS-45 1.000 Bauphal
Annual Target for FY 2016-
17 (As per Annual Work
Plan)
Physical
(Km)
Financial
(Taka in
lakh)
23.00 Km &
121.00 Km
(Partly)
3300.00
580.93
601.29
659.70
100
Date:30-09-2016
Physical
(Km)
Financial
(Taka in
lakh)
15/12/2011
100 0 100 580.93 0.00580.93 28/02/201230/5/2014
(Extended)
100
3 0
659.70 100
334.41
601.29
659.70
601.29 0.00
29/2/201223/5/2014
(Extended)100 0 0.00
100 0
603.53 22/11/201129/4/2014
(Extended)100 0
03-01-12 20/02/2013
030/06/2014
(Extended)100
512.61
334.41
1001.39
0.00
3
882.96 20/4/1230/06/2014
(Extended)96 4
100
512.61 16/02/201230/06/2013
(Extended)0
29/02/201231/3/2014
(Extended)
32.380.00
0.00 603.53
100
0.00 334.41
678.83
603.53
100 0 100 885.40
32.38
100 512.61
106.83 785.66
100
0.00
LGED/ECRRP/PAT/11-12/R-09 Patuakhali
LGED/ECRRP/PIR/11-12/R-03 Pirojpur
885.40
Barguna
25/4/1230/6/13
(Extended)
Patuakhali
Barguna
LGED/ECRRP/BAR/11-12/R-08
Barguna
Upazila District
Barisal
Bagerhat
LGED/ECRRP/BAG/11-12/R-05 Bagerhat
Physical
(Km /%)
Financial
(Taka in
lakh)
Package No.
Road- 360
km &
Bridge/
Culvert-
1200 m
33945.04 68.64 Km
(99.28%)
4995.91
LGED/ECRRP/BARI/11-12/R-06
LGED/ECRRP/PAT/11-12/R-07
LGED/ECRRP/BAR/11-12/R-04
LGED/ECRRP/BAR/11-12/R-02
Package wise Access Road informationTotal Target as per
RDPP (2nd Revised)
Overall Progresss as
of end of June FY
2015-2016
LGED/ECRRP/BAG/11-12/R-01
Contract
Cost
(Tk in
lakh)
Date of
Work
OrderTotal
Access
Road in Km
Location
Target date
of
completion
Physical Progress (%) Financial Progress (Taka in lakh)
Cumulative
as of 30th
June 2016
Contract
cancelled
Cumulative
as of 30th
June 2016
This quarter Total Total
SCR-9
dropped as
NS-27 is
cancelled due
to land
dispute.
SCR-11
dropped as
work will be
done under
NW-06 as
internal road.
This quarter
Remarks
885.40
Annex 3M: Monitoring Form PMF-B3: Progress Monitoring - Package wise Construction of Shelter Connecting Road (1st Phase)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 85
Road ID
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Road- 360
km &
Bridge/
33945.04 23.00 Km &
121.00 Km
(Partly)
3300.00 153.98 Km
(99.77%)
17930.51SCR-50/NS-190 0.875 Hizla
SCR-51/NS-189 1.566 Muladi
SCR-52/NS-188 2.500 Muladi
SCR-60/NS-64 4.700 Galachipa
SCR-61/NS-65 3.500 Galachipa
SCR-62/NS-66 0.068 Galachipa
SCR-108/NS-62 1.650 Bauphal
SCR-98/NS-206 1.960 Amtali
SCR-99/NS-53 2.912 Amtali
SCR-100/NS-200 3.915 Amtali
SCR-101/NS-54 4.135 Amtali
SCR-107/NS-51 1.385 Amtali
SCR-34/NS-139 4.169 Mothbaria
SCR-35/NS-174 1.612 Mothbaria
SCR-36/NS-175 0.100 Mothbaria
SCR-83/NS-169 1.400 Shyamnagar
SCR-84/NS-172 3.342 Shyamnagar
SCR-85/NS-171 2.750 Shyamnagar
SCR-86/NS-166 1.750 Shyamnagar
SCR-87/NS-167 0.750 Shyamnagar
SCR-92/NS-213 2.060Patuakhali
Sadar
SCR-93/NS-212 0.750Patuakhali
Sadar
SCR-94/NS-69 0.500Patuakhali
Sadar
SCR-95/NS-218 0.800 Dashmina
SCR-96/NS-63 0.225 Dashmina
SCR-97/NS-68 0.885 Mirjaganj
SCR-48/NS-147 4.725 Mongla
SCR-49/NS-141 2.515 Sarankhola
& 103.98
Km
(36.13%)
100 829.64
100
436.82 0.00
03-04-13 30/6/2014 100 0 100
30/6/2014 100
0
829.64
436.82
859.16859.16
0 10003-07-13896.92
0.00
0
30/6/14 0 100
520.55
Date of
Work
Order
LGED/ECRRP/BAR/11-12/R-12 Barguna
LGED/ECRRP/BAG/11-12/R-16 Bagerhat
Target date
of
completion
Physical Progress (%) Financial Progress (Taka in lakh)
Cumulative
as of 30th
June 2016
This quarter
Cumulative
as of 30th
June 2016
Remarks
This
quarterTotal
Package wise Access Road InformationTotal Target as per
RDPP (2nd Revised)
Overall Progresss as of
end of June FY 2015-
2016Contract
Cost
(Tk in lakh)Location
Upazila District
Total
Access
Road in Km
Physical
(Km)
Annual Target for FY 2016-
17 (As per Annual Work
Plan)
Physical
(Km)
Financial
(Taka in
lakh)
Financial
(Taka in
lakh)
Physical
(Km /%)
Financial
(Taka in
lakh)
Package No.
975.07
LGED/ECRRP/PIR/11-12/R-13 Pirojpur
Patuakhali
100 458.46LGED/ECRRP/BARI/11-12/R-10 Barisal
LGED/ECRRP/PAT/11-12/R-11 Barguna
LGED/ECRRP/PAT/11-12/R-15
975.07
100
0.00
0.00
0
100
896.92
31/05/14 100
26/03/2014 100
22/5/13
859.16 19/3/13
Date:30-09-2016
436.82 20/01/13
06-10-14 100
458.46 28/01/13 30/04/14 100 0
520.55
829.6373214
17/10/12
LGED/ECRRP/SAT/11-12/R-14 Satkhira
SCR-87 has
been
dropped
0.00
SCR-96 has
been
dropped
Total
458.46
975.07
896.92
520.550.00
0.00
Annex 3N: Monitoring Form PMF-B3: Progress Monitoring - Package wise Construction of Shelter Connecting Road (2nd Phase)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 86
Road ID
Upazila District
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
SCR-102/NS-59 3.096 Patharghata
SCR-103/NS-197 0.630 Patharghata
SCR-104/NS-205 2.460 Barguna Sadar
SCR-105/NS-57 3.000 Barguna Sadar
SCR-106/NS-201 4.030 Barguna Sadar
SCR-64/NS-92 0.695 Lalmohan
SCR-65/NS-91 1.000 Lalmohan
SCR-66/NS-87 0.050 Daulatkhan
SCR-67/NS-86 0.350 Daulatkhan
SCR-68/NS-85 0.030 Daulatkhan
SCR-69/NS-84 2.600 Daulatkhan
SCR-70/NS-88 0.045 Borhanuddin
SCR-71/NS-89 0.100 Borhanuddin
SCR-72/NS-80 0.050 Bhola Sadar
SCR-73/NS-81 0.500 Bhola Sadar
SCR-74/NS-82 0.030 Bhola Sadar
SCR-75/NS-86 0.863 Bhola Sadar
SCR-76/NS-2225 0.580 Charfassion
SCR-77/NS-226 0.220 Charfassion
SCR-78/NS-96 1.400 Charfassion
SCR-88/NS-152 2.250 Kalaroa
SCR-89/NS-191 2.625 Kaliganj
SCR-90/NS-195 0.730 Satkhira Sadar
SCR-91/NS-194 0.240 Debhata
SCR-53/NS-182 2.000 Agaljhara
SCR-54/NS-183 1.150 Banaripara
SCR-55/NS-185 1.200 Uzirpur
SCR-56/NS-181 0.600 Agaljhara
SCR-111/NS-134 3.950 Koyra
SCR-112/NS-124 0.850 Koyra
SCR-113/NS-129 0.350 Koyra
SCR-114/NS-127 2.350 Koyra
SCR-115/NS-128 1.200 Koyra
SCR-116/NS-130 2.574 Koyra
Contract
Cost
(Tk in lakh)Physical
(Km)
Financial
(Taka in
lakh)
Physical
(Km)
Financial
(Taka in
lakh)
Physical
(Km /%)
Financial
(Taka in
lakh)
Package No.
Total
Access
Road in Km
Location
Date:30-09-2016
Total Target as per
RDPP (2nd Revised)
Annual Target for FY 2016-
17 (As per Annual Work
Plan)
Overall Progresss as of
end of June FY 2015-
2016
Package wise Access Road Information
Cumulative
as of 30th
June 2016
This quarter Total
Cumulative
as of 30th
June 2016
Total
Remarks
100 0 100 1241.78
Date of
Work
Order
Target date
of
completion
0.00
0.00
100
540.59
0.00
583.47
30/6/14 0.00
Physical Progress (%) Financial Progress (Taka in lakh)
20/5/201420/5/13
870.05 870.05
This
quarter
Satkhira
Khulna
LGED/ECRRP/BAR/11-12/R-17
LGED/ECRRP/SAT/11-12/R-19
Bhola
Barguna
LGED/ECRRP/BHO/11-12/R-18
LGED/ECRRP/KHU/11-12/R-21
100 0 100
100028/3/14
010030/6/2014
30/06/14
100
100 014/01/13
870.05 24/1/13
LGED/ECRRP/BARI/11-12/R-20 Barisal
18/10/12
479.22
583.47 22/10/12
1241.78
540.59
SCR-69 & 77
have been
dropped
540.59
479.22
583.47
100 479.22
0.00 1241.78
SCR-91 has
been
dropped
Annex 3N: Monitoring Form PMF-B3: Progress Monitoring - Package wise Construction of Shelter Connecting Road (2nd Phase) Cont.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 87
Road ID
Upazila District
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
SCR-110/NS-133 0.470 Koyra
SCR-117/NS-125 2.100 Koyra
SCR-118/NS-132 3.150 Koyra
SCR-119/NS-131 3.150 Koyra
SCR-120/NS-123 1.626 Dacope
SCR-121/NS-126 1.550 Koyra
SCR-79/NS-154 3.350 Assasuni
SCR-80/NS-155 1.000 Assasuni
SCR-81/NS-156 3.900 Assasuni
SCR-82/NS-73 3.150 Assasuni
SCR-122/NS-99 0.600 Sadar
SCR-123/NS-102 1.000 Sadar
SCR-124/NS-101 0.750 Sadar
SCR-125/NS-221 0.050 Sadar
SCR-126/NS-220 0.120 Sadar
SCR-127/NS-224 1.150 Kathalia
SCR-128/NS-107 0.225 Rajapur
SCR-129/NS-108 0.500 Rajapur
SCR-130/NS-223 0.920 Rajapur
SCR-131/NS-110 0.345 Kathalia
SCR-132/NS-222 0.296 Nalchity
SCR-57/NS-140 3.200 Sadar
SCR-58/NS-145 2.000 Chitalmari
SCR-59/NS-143 1.525 Fakirhat
SCR-37/NS-161 1.225 Nesarabad
SCR-38/NS-160 2.048 Nesarabad
SCR-39/NS-162 1.275 Nesarabad
SCR-40/NS-176 1.200 Nazirpur
SCR-41/NS-177 0.234 Nazirpur
SCR-30/NS-46 1.325 Sadar
SCR-30/NS-47 0.035 Sadar
SCR-30/NS-48 0.271 Bhandaria
SCR-31/NS-43 0.034 Bhandaria
SCR-32/NS-44 0.500 Kawkhali
SCR-33/NS-45 0.950 Kawkhali
LGED/ECRRP/BAG/12-13/R-5A SCR-18/NS-37 8.450 Sadar Bagerhat 1,011.55 31/12/2013 27/1/2015 100 0 100 1011.55 0.00 1011.55
LGED/ECRRP/BAG/12-13/R-5B SCR-19/NS-36 4.150 Mongla Bagerhat 506.17 31/12/2013 27/1/2015 100 0 100 506.17 0.00 506.17
SCR-133 1.500 Dasmina
SCR-134 2.210 Galachipa
SCR-135 2.650 Galachipa
SCR-136 2.000 Dumki
SCR-137 2.690 Rangabali
SCR-138 3.500 Rangabali
SCR-139 1.300 Mirjaganj
SCR-140 0.575 Kalapara
SCR-141 0.100 Kalapara
LGED/ECRRP/PIR/11-12/R-27
5443
Package No.
Total
Access
Road in Km
Location
22/5/2013 21/5/2014748.30
10014/6/2014
Target date
of
completionPhysical
(Km)
Financial
(Taka in
lakh)
Physical
(Km)
Financial
(Taka in
lakh)
Physical
(Km /%)
Physical Progress (%)
Annual Target for FY 2016-
17 (As per Annual Work
Plan)
Overall Progresss as of
end of June FY 2015-
2016Package wise Access Road Information
Contract
Cost
(Tk in lakh)Financial
(Taka in
lakh)
Cumulative
as of 30th
June 2016
This quarter
687.85 47.81 735.66
687.13
582.99
0.00
0.00
402.91
LGED/ECRRP/PAT/14-15/R-28 Patuakhali 1678.32 11-04-15 11-10-15 11
Financial Progress (Taka in lakh)
748.30
402.91
699.09
0.00
748.30 0.00
Cumulative
as of 30th
June 2016
LGED/ECRRP/BAG/11-12/R-25 Bagerhat
907.80 687.13
30/4/14
30/6/2014 96 4 100
LGED/ECRRP/KHU/11-12/R-22 Khulna
LGED/ECRRP/PIR/11-12/R-26 Pirojpur
Date:30-09-2016
Total Target as per
RDPP (2nd Revised)
21/01/14 100 0
100
0
07-11-12
0
100
100
100
LGED/ECRRP/JHA/11-12/R-24 Jhalokathi
LGED/ECRRP/SAT/11-12/R-23 Satkhira
1374.58 06-09-13
Date of
Work
Order
699.09 25/3/13 100 0 100 699.09
402.91 22/01/13
1374.58 0.00
This
quarterTotal Total
0.00
Remarks
Pirojpur 582.99 05-07-13 05-06-14 100 582.990 100
SCR-43 & 45
have been
dropped
SCR-124,
125, 126 &
132 have
been
dropped
1374.58
Annex 3N: Monitoring Form PMF-B3: Progress Monitoring - Package wise Construction of Shelter Connecting Road (2nd Phase) Cont.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 88
Road ID
Upazila District
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
SCR-142 0.800 Sadar
SCR-144 1.500 Mothbaria
SCR-145 1.000 Mothbaria
SCR-146 1.050 Nazirpur
SCR-147 0.560 Nesarabad
SCR-143 0.200 Patharghata
SCR-148 0.600 Amtoli
SCR-149 3.350 Taltoli
SCR-150 2.500 Taltoli
SCR-152 1.200 Bamna
SCR-153 1.104 Sadar
SCR-154 0.500 Sadar
SCR-155 3.150 Patharghata
SCR-156 1.600 Taltoli
SCR-157 3.550 Sadar
SCR-158 0.350 Sadar
SCR-159 1.980 Nalcity
SCR-160 2.150 Hijla
SCR-161 1.360 Hijla
SCR-162 0.800 Sadar
SCR-163 0.500 Agailjhara
SCR-164 1.550 Agailjhara
SCR-165 2.800 Babugonj
SCR-166 1.000 Shyamnagar
SCR-167 0.850 Shyamnagar
SCR-168 3.250 Shyamnagar
SCR-169 3.540 Kaligonj
SCR-170 2.800 Assasuni
SCR-171 4.091 Assasuni
SCR-172 2.200 Assasuni
SCR-173 2.341 Rampal
SCR-174 1.100 Rampal
SCR-176 1.800 Mongla
SCR-177 2.237 Mongla
SCR-178 2.100 Morelgonj
SCR-179 0.200 Morelgonj
SCR-180 1.894 Morelgonj
SCR-181 0.825 Dacope
SCR-182 0.400 Koyra
SCR-183 3.150 Dacope
SCR-184 1.800 Koyra
SCR-185 0.837 Dacope
SCR-186 0.997 Koyra
SCR-187 0.200 Dacope
SCR-188 2.525 Koyra
SCR-189 2.050 Koyra
SCR-190 1.200 Koyra
SCR-191 0.200 Mehendigonj
SCR-192 1.997 Mehendigonj
SCR-193 2.600 Bakergonj
SCR-194 1.250 Nesarabad
SCR-195 0.800 Sadar
SCR-196 1.250 Mothbaria
SCR-197 2.000 Kawkhali
Cumulative
as of 30th
June 2016
This quarter Total
Cumulative
as of 30th
June 2016
This
quarter
Package wise Access Road Information
Contract
Cost
(Tk in lakh)Package No.
Total
Access
Road in Km
Total
Date of
Work
Order
Target date
of
completion
Physical Progress (%) Financial Progress (Taka in lakh)
Remarks
Physical
(Km)
Financial
(Taka in
lakh)
Physical
(Km)
Financial
(Taka in
lakh)
Physical
(Km /%)
Date:30-09-2016
Total Target as per
RDPP (2nd Revised)
Annual Target for FY 2016-
17 (As per Annual Work
Plan)
Overall Progresss as of
end of June FY 2015-
2016
Financial
(Taka in
lakh)
Location
5 45 220.39 0.004031/1/2017 220.39LGED/ECRRP/PIR/14-15/R-29 Pirojpur 597.67 31/1/2016
44 10 54 333.75 0.00 333.75LGED/ECRRP/PIR/14-15/R-37 Pirojpur 806.35 17/1/2016 24/1/2017
LGED/ECRRP/BARI/14-15/R-32 Barisal
LGED/ECRRP/SAT/14-15/R-33 Satkhira 1532.73
0.00 493.3643 0
50 5 55 271.27 35.44 306.70
14 55 218.56 0.00 218.56
43 493.36
LGED/ECRRP/JHA/14-15/R-31 Jhalokathi 522.44 02-11-15 08-11-16
997.56 11-05-15 11-12-16
LGED/ECRRP/BAR/14-15/R-30 Barguna 1094.37 19/10/2015 23/10/2016 41
10-11-15 11-08-16 21 2 23 153.27 0.00 153.27
LGED/ECRRP/BAG/14-15/R-34 Bagerhat 1128.63 18/10/2015 14/11/2016 20 20
LGED/ECRRP/KHU/14-15/R-35 Khulna 1129.62 01-04-16 01-03-17 0.00 398.25
40 303.24 0.00 303.24
1 33 146.13
36 2 38 398.25
0.00 146.13LGED/ECRRP/BARI/14-15/R-36 Barisal 378.02 24/12/2015 30/12/2016 32
Annex 3N: Monitoring Form PMF-B3: Progress Monitoring - Package wise Construction of Shelter Connecting Road (2nd Phase) Cont.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 89
Killa ID
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
KL- 01 Amtali
KL- 02 Amtali
KL- 03 Amtali
KL- 04 Amtali
KL- 05 Sadar
KL- 06 Bamna
KL- 07Jhalokathi
Sadar
KL- 08 Rajapur
KL- 09 Kathalia
KL- 10 Nalchitty
KL- 11 Mothbaria
KL- 12 Mothbaria
KL- 13 Bhandaria
KL- 14 Zianagar
KL- 15 Nesarabad
KL- 16 Kawkhali
KL- 17 Lalmohon
KL- 18 Lalmohon
KL- 19 Lalmohon
KL- 20 Lalmohon
KL- 21 Charfassion
KL- 22 Charfassion
70.65 0.00 70.6581.53 20/02/1231/12/13
(Extended)99 0 99
Financial Progress (Taka in lakh)
Cumulative
as of 30th
June 2016
This quarter Total
Cumulative
as of 30th
June 2016
Package wise Killa informationTotal Target as per RDPP
(2nd Revised)
Annual Target for FY
2016-17 (As per Annual
work Plan)Contract
Cost
(Tk in
lakh)
Date of
Work
OrderLocation
Upazila District
Physical
(Km)
Financial
(Taka in
lakh)
LGED/ECRRP/PIR/11-12/KW-03 Pirojpur
15
(Revised)
1349.01
LGED/ECRRP/BAR/11-12/KW-01 Barguna
6
(Partly)
142.5
LGED/ECRRP/BHO/11-12/KW-04
100
100
Physical
(Km)
Financial
(Taka in
lakh)
Package No.
Bhola
LGED/ECRRP/JHA-SAT/11-12/KW-
02Jhalokathi
Target date
of
completion
Physical Progress (%)
0
89.58
This quarter Total
0 0.00
Dropped
due to land
dispute
33.69
89.5897.99 05-05-12
33.69 18/3/12 33.69 0.00
Date:30-09-2016
30/4/14
(Extended)100
30/4/14
(Extended)100
Annex 3 -O: Monitoring Form PMF-B3: Progress Monitoring - Package wise Construction of Killa (Part A- Earthwork)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 90
Killa ID
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
KL- 01 Amtali
KL- 02 Amtali
KL- 03 Amtali
KL- 04 Amtali
KL- 05 Sadar
KL- 06 Bamna
KL- 07Jhalokathi
Sadar
KL- 08 Rajapur
KL- 09 Kathalia
KL- 10 Nalchitty
KL- 11 Mothbaria
KL- 12 Mothbaria
KL- 13 Bhandaria
KL- 14 Zianagar
KL- 15 Nesarabad
KL- 16 Kawkhali
KL- 17 Lalmohon
KL- 18 Lalmohon
KL- 19 Lalmohon
KL- 20 Lalmohon
KL- 21 Charfassion
KL- 22 Charfassion
109.82 18/3/12 109.82 0.00
Date:30-09-2016
15/6/2014 100
30/6/14 100
Dropped
due to land
dispute
109.82
276.71276.71 30/4/2013
0
276.71
This quarter Total
0 0.00
-
100
100
Physical
(Km)
Financial
(Taka in
lakh)
Package No.
Bhola
LGED/ECRRP/JHA-SAT/11-12/KW-
02Jhalokathi
Target date
of
completion
Physical Progress (%)
LGED/ECRRP/PIR/11-12/KW-03 Pirojpur
15
(Revised)
1349.01
LGED/ECRRP/BAR/11-12/KW-01 Barguna
6
(Partly)
142.50
LGED/ECRRP/BHO/11-12/KW-04
Package wise Killa informationTotal Target as per RDPP
(2nd Revised)
Annual Target for FY
2016-17 (As per Annual
work Plan)Contract
Cost
(Tk in
lakh)
Date of
Work
OrderLocation
Upazila District
Physical
(Km)
Financial
(Taka in
lakh)
Financial Progress (Taka in lakh)
Cumulative
as of 30th
June 2016
This quarter Total
Cumulative
as of 30th
June 2016
67.15 0.00 67.15162.76 28/12/11 30/6/14 70 4 74
Annex 3P: Monitoring Form PMF-B3: Progress Monitoring - Package wise Construction of Killa (Part B- Concrete Work)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 91
1 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
33 Km 7.1 Km ( R ) 01-12-10 28/1/2010 FY2010-2011 100%
0.59 Km 0.39 Km ( R ) 15/3/2010 29/8/2010 FY2010-2011 100%
32 Km 10.8 Km ( R) 14/1/2010 28/01/2010 FY2010-2011 100%
38 Km 29.65 Km ( R) 19/1/2010 28/01/2010 FY2010-2011 100%
42.51 Km 28.47 Km ( R)17/1/2010 28/1/2010
FY2010-2011 100%
30.6 Km 14.50 Km ( R) 06-01-10 16/6/2010 FY2010-2011 100%
Physic
al w
ork c
om
ple
ted
Contr
act te
rm
inate
d o
n 5
th S
epte
mber 2
013
Contr
act te
rm
inate
d o
n 5
th
Septe
mber 2
013
01/2010-1102-03-1120/1/201101-05-1110-07-1001-06-13W 08-12-10
Embankment
41/6B
Water Control
Stucture
52/53B
Embankment
Buramojmdar &
Sharishamuri
union
Apr-10
Barguna
41/7B7 Nos.
Barguna
09/03/10 &
30/03/10;
Clearance
from M&E -
31/03/10
04-05-10
3 ( R) & 1 (C)
100%
Barguna
2(R) & 8(C)
Sharisamuri ,
Buramajumdar
& Kadirabad
Betagi
09-02-10
10 (R) & 17 (C)
4 Nos.
02/03/10 &
21/09/10;
Clearance
from M&E -
26/09/10
24-10-2010
06-01-10
18/6/2013
3 (R) & 6 (C)20 Nos.
Barguna
Badarkhali,
Gourichanna &
Fuljhuri
Barguna
Apr-10
Apr-10
Patuakhali
Patuakhali
47/5
Embankment
Water Control
Stucture
Rangabali Union Galachipa
Water Control
Stucture
30/5/2010 29/7/2010
13/2009-
2010
04-04-10
16/12/2012
10/2009-
201011-11-10
16/5/2013
FY2010-201124/3/2010
Contract
signed date
Tender
approval
date
2
Embankment
Lalua union Kalapara
02/03/10 &
21/09/10;
Clearance
from M&E -
26/09/10
04-05-1014 Nos.
Protective Works
04-04-1018/6/2013
Tender
notice date
25/11/2010
9/5/2010 11-02-10 11-07-1024-10-2010
Contract
ID
(BWDB)
IEE/EIA Study
Date of
clearance
of WB
Tender
received
date
Jan-1024/3/2010 100%
09/03/10 &
30/03/10;
Clearance
from M&E -
31/03/10
8/7/2010
Jan-10
1 ( R) & 1 (C)
Date of
clearance of
WB
Total Rehab. /
Construction
Requirement
Approval
date of
Comprehens
ive
Technical
Report
Date of
Submission
to M&E
21/06/2010 FY2010-2011
Location of the Polder
Finish
date/
Submissio
n date to
BWDB
Union
Tender notice up to signing of contract
Start
date
Letter of
Award date
Design Works
Start
date
Tender ProcessSocial and Resettlement
Study
Design approval date
Damage
Assessment
Finish
dateUpazila District
Preparatory works
Date of
Submission
to M&E
Progress
(%)
100%FY2010-201106-01-10
04-05-10
100%
31/3/2010
08/07/10 &
12/08/10;
Clearance
from M&E -
22/08/10
21/6/2010
FY2010-2011
07/07/10 &
12/08/10;
Clearance
from M&E -
02/09/10
100%
09/03/10 &
30/03/10;
Clearance
from M&E -
31/03/10
FY2010-2011
16/5/2010
02/03/10 &
21/09/10;
Clearance
from M&E -
26/09/10
Jan-10
26/10/2010
08-08-10
27/3/2010 21/06/2010
02/03/10 &
21/09/10;
Clearance
from M&E -
26/09/10
09/03/10 &
30/03/10;
Clearance
from M&E -
31/03/10
Jan-10 04-05-10Apr-10
Jan-10 Apr-10
Polder ID (including
embankment, water control
structures,and protective works)
Total
Quantity
(Polder)
Water Control
Stucture
36 Nos.
As of 30 September 2016
Polder information
Package
No.
(WB)
39/2A
Embankment
Water Control
Stucture
ECRRP/BW
DB/W-03
Remarks
(any relevant
infromation not
yet included
e.g.causes of
delays)
ECRRP/BW
DB/W-01
ECRRP/BW
DB/W-02
Annex 4A: Monitoring Form PMF-C2: Process Monitoring – Polder (29 Polders)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 92
Annex 4A: Monitoring Form PMF-C2: Process Monitoring – Polder (29 Polders) Cont.
1 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
- 25 Km ( R) 22/6/2010 08-09-10 FY2010-2011 100%
- 3 (R) & 1 (C) 06-09-10 18/10/10 FY2010-2011 100%
- 20.78 km ( R) 22/6/2010 08-09-10 FY2010-2011 100%
- 4( R) 13/06/10 25/08/10 FY2010-2011 100%
- 4.80 Km ( R) 14/09/10 15/11/10 FY2010-2011 100%
- 3 ( R) 14/09/10 10-06-10 FY2010-2011 100%
- 12.70 Km ( R) 14/07/10 08-09-10 FY2010-2011 100%
- 8( R) & 1( C) 01-06-11 20/9/2011 1st Qtr. FY2011-2012 100%
- 7.96 Km ( R) 30/8/2010 10-05-10 FY2010-2011 100%
- 2( R) & 1( C) 06-09-10 09-04-10 FY2010-2011 100%
- 5.10 Km ( R) 15/7/2010 08-09-10 FY2010-2011 100%
27/10/10;
Clearance
from M&E -
15/11/10
- 1 ( R) 31-10-10 31/10/10 W(P) 100%
- 5.20 Km ( R) 08-12-10 10-05-10 FY2010-2011 100%
- 3( R) & 2( C) 29/09/10 22/3/11 W(P) 100%
- 800m 29/09/10 10/11/2010 FY2010-2011 100%
Physic
al w
ork
com
ple
ted
Physic
al w
ork
com
ple
ted
28/7/2013
12-02-10
29/6/2011
07-10-11
21/07/10 &
29/08/10;
Clearance
from M&E -
21/09/10
29/08/10 &
21/09/10;
Clearance
from M&E -
22/09/10
Apr-10
W
24/3/2011
Jan-10
Water Control
Stucture
08/09/10 &
21/09/10;
Clearance
from M&E -
21/09/10
Apr-10
Dhankhali Galachipa
ECRRP/BW
DB/W-05
Embankment
55/2C
Kalapara
Embankment
Water Control
Stucture
52-53A
46 Water Control
Stucture
Embankment
Bokulbonia Galachipa
Nilgonj Patuakhali
Patuakhali
Patuakhali
Patuakhali
Apr-10Apr-10
Apr-10Jan-10
Patuakhali
Kalapara
Galachipa
Patuakhali
Choto Baisdia Patuakhali
04-08-13
Jan-10
Apr-10
21/09/10 &
28/09/10;
Clearance
from M&E -
30/09/10
27/10/10 &
3/1/11;
Clearance
from M&E -
06/1/11
W
WW
Jan-10 Apr-10
Jan-10
9/11/11;
Clearance
from M&E -
10/01/12
W
15/11/11;
Clearance
from M&E -
22/7/13
28/7/2013
9/11/11;
Clearance
from M&E -
02/5/13
18/6/2013
9/11/11;
Clearance
from M&E -
29/11/11
24/11/10;
Clearance
from M&E -
25/11/10
Water Control
Stucture
55/1
55/4 Galachipa
Apr-10Jan-10
Charmomtaz
Galachipa Galachipa
Jan-10
Protective Works
Embankment
47/1
54/A
Embankment
Water Control
Stucture
Water Control
StuctureChaprabhanga
Water Control
Stucture
Jan-10
29/11/10 &
13/4/11;
Clearance
from M&E -
27/4/11
13/12/2010
27/2/2011ECRRP/BW
DB/W-04
-
Embankment
Embankment
14/2010-
201107-07-11
03-03-1101/2010-
2011
25/7/201105-11-11
14/2/201121/11/2010
Apr-10
25/6/2011
07-04-11
21-12-2010
13/03/13;
Clearance
from M&E -
28/03/13
22/11/10 &
9/10/11;
Clearance
from M&E -
10/01/12
18/6/2013
W
14-11-2010
04-08-13
Upazila
Approval
date of
Comprehens
ive
Technical
Report
Tender notice up to signing of contract
Remarks
(any relevant
infromation not
yet included
e.g.causes of
delays)
Package
No.
(WB)
Polder ID (including
embankment, water control
structures,and protective works)
Total
Quantity
(Polder)
Total Rehab. /
Construction
Requirement
Location of the PolderDamage
Assessment
UnionLetter of
Award dateDistrict
Start
date
Finish
date
30.09.2016 Polder information Preparatory works
Date of
clearance
of WB
Design Works IEE/EIA Study Social and Resettlement
Study
Finish
date/
Submissio
n date to
BWDB
Design approval dateProgress
(%)
Date of
Submission
to M&E
Tender Process
Date of
clearance of
WB
Tender
notice date
Tender
received
date
Tender
approval
date
Contract
signed date
Contract
ID
(BWDB)
2
Date of
Submission
to M&E
Start
date
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 93
1 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
- 7.7 Km ( R) 26/07/10 15/10/2010 FY2010-2011 100%
- 1 ( R) & 5 (
C)03-09-11 10-02-11 FY2010-2011 100%
- 19.35 Km ( R) 11-04-10 30/11/2010 FY2010-2011 100%
- 18( R) & 4( C) 16/08/2010 23/11/2010 FY2010-2011 100%
- 700m 7/08/2011 9/10/2011 FY2010-2011 100%
- 12.45 Km ( R) 04-06-11 05-04-11 FY2010-2011 100%
- 11 ( R) & 7 ( C) 13/2/2011 04-12-11 1st Qtr. FY2011-2012 100%
- 10.74 Km ( R) &
0.85 Km ( C)04-01-11 08-08-11 1st Qtr. FY2011-2012 100%
- 4( R) & 11( C) 19/6/2011 20/11/2011 1st Qtr. FY2011-2012 100%
- 15.06 Km (R) &
1.50 Km ( C)29/09/2010 11/08/2011 FY2010-2011 100%
- 4( R) & 5( C) 23/06/2011 07/03/2011 1st Qtr. FY2011-2012 100%
- 400m 19/06/2011 10/07/11 1st Qtr. FY2011-2012 100%
- 6.35 Km ( R) &
2.55 Km ( C)05-01-11 29/11/2011 1st Qtr. FY2011-2012 100%
- 2( R) 07-01-11 31/7/2011 1st Qtr. FY2011-2012 100%
- 21.82 Km ( R) 30/3/2011 25/4/2011 FY2010-2011 100%
- 3( R) & 1( C) 17/01/2011 13/6/2011 FY2010-2011 100%
Embankment R 1.895 ( R) 20-09-12 29/12/2013 Approved 100%
Water Control Stucture R 4 ( R) 20-09-12 20/10/2013 Approved 100%
Protective Works C 1492 m 20-09-12 20/10/2013 Approved 100%
Embankment R 8.71 ( R) 20-09-12 20/10/2013 Approved 100%
Water Control Stucture R 2 ( R) 20-09-12 20/10/2013 Approved 100%
Embankment R 18.87 ( R) 20-09-12 20/10/2013 Approved 100%
Water Control Stucture C&R 1( C) 3( R) 20-09-12 20/10/2013 Approved 100%
Embankment R 1.96 ( R) 20-09-12 20/10/2013 Approved 100%
Water Control Stucture R 2 ( R) 20-09-12 20/10/2013 Approved 100%
Protective Works C 3350 m 20-09-12 20/10/2013 Approved 100%
04-06-10Dec-13
So
me
En
gin
ee
rin
g D
esig
ns r
eq
uir
e
am
me
nd
me
nt
ba
se
d o
n t
he
site
co
nd
itio
n a
nd
th
e p
roce
ss o
f m
akin
g
am
me
nd
ed
ha
s b
ee
n in
itia
ted
.
07-05-10 27-12-2010 16/06/2010 1-Jun-10
06-04-10
27/12/2010 6-4-10 20-Dec-12
6-4-10 27-12-2010 6-4-10 21-Jan-13
20/5/201402/2013-
2014
7-12-10 04-06-10 30/05/2011
18/5/2014
04-06-10
04/2011-
201217/1/201209-06-11 25/10/2011
27-Jan-14
Physic
al
work
com
ple
ted
Remarks
(any relevant
infromation not
yet included
e.g.causes of
delays)
Execution o
f w
ork
in
pro
gre
ss
7/3/2012;
Clearance
from M&E -
28/03/13
17/1/2012
01-01-12
01-12-1220/9/2011 25/10/2011
09-08-11
04-08-13
-
30/1/2012W-7/1997
Dated30/01/
2012
Tender notice up to signing of contract
9/1/12;
Clearance
from M&E -
28/03/13
8/8/2011 &
21/8/11;
Clearance
from M&E -
16/10/201117/8/2011;
Clearance
from M&E -
16/5/2012
Jan-10
Apr-10
9/2/11 &
8/3/11;
Clearance
from M&E -
10/3/11
Preparatory works
Start
date
Progress
(%)
Finish
date/
Submissio
n date to
BWDB
Damage
Assessment
55/2B
50/51
Embankment
Finish
date
Jan-10
Embankment
Kalapara
Jan-10
Borobaisdia
DasminaRonogopaldi
Jan-10
Protective Works
Water Control
Stucture
Pathorghata
Polder ID (including
embankment, water control
structures,and protective works)
Embankment
Barguna &
Pathorghata
Ramna,
Dewatala,
Raihanpur
Protective Works
Barguna
47/4
Location of the Polder
Kalapara
Embankment
Apr-10
Jan-10
Barguna
Embankment
Barguna
Noltona
Pathorghata
ECRRP/BW
DB/W-14
Water Control
Stucture
Embankment
Water Control
Stucture
42
ECRRP/BW
DB/W-10
Patuakhali
Patuakhali
Polder information
Total Rehab. /
Construction
Requirement
Barguna
Social and Resettlement
Study
Apr-10
District
Apr-10
Jan-10
Apr-10Jan-10
Start
date
IEE/EIA Study
Date of
clearance
of WB
Union
2
ECRRP/BW
DB/W-07
Upazila
Mithagonj,
Dhulesshar,
Chapravanga
ECRRP/BW
DB/W-06
Water Control
Stucture
KalahariWater Control
Stucture
Total
Quantity
(Polder)
Chakamya44(P)
As of 30 September 2016
Package
No.
(WB)
40/1
Water Control
Stucture
39/1D
Water Control
Stucture
Embankment
Letter of
Award date
Contract
ID
(BWDB)
Tender Process
Tender
received
date
Contract
signed date
Tender
notice date
Tender
approval
date
Approval
date of
Comprehens
ive
Technical
Report
24/11/10;
Clearance
from M&E -
14/12/10
29/08/10 &
08/09/10;
Clearance
from M&E -
13/09/10
W
Design Works
28/7/2013
Date of
Submission
to M&E
Date of
clearance of
WB
Date of
Submission
to M&E
Design approval date
Finish
date/
Submissio
n date to
BWDB
03/4/2012;
Clearance
from M&E -
16/4/2012
28/9/201128/7/2011
01-03-12
27/11/11;
Clearance
from M&E -
28/3/13
22/12/11;
Clearance
from M&E -
11/3/13
27/11/11;
Clearance
from M&E -
16/1/12
19/1/2012
18/4/2013
15/1/2012
27/7/2011
18/6/2013
19/1/2012
04-08-13
Physic
al w
ork
com
ple
ted
02-09-1203/2011-
2012
P-3/1963
Dated 19-01-
2012
Physic
al w
ork
com
ple
ted
31/5/12;
Clearance
from M&E -
26-12-2012
Patuakhali Apr-10
26/2/2012 &
06/9/2012;
Clearance
from M&E -
07/3/2013
2/1/11;
Clearance
from M&E -
12/1/11
Apr-10Patuakhali
Sharisamuri,
Buramajumdar &
Kadirabad
Rangabali Union
18/12/2012
19/1/2012 02-09-12
6-4-10
07-05-10
06-04-10
N/A12-Sep-13
Barguna Barguna
Sep 2013
(Reviewe
d)
Dec-1341/6B
Badarkhali,
Gourichanna &
Fuljhuri
Galachipa Patuakhali
Sep 2013
(Reviewe
d)
Dec-1352/53B
Barguna Barguna
Sep 2013
(Reviewe
d)
Dec-1339/2A
Buramojmdar &
Sharishamuri
union
Betagi Barguna
Sep 2013
(Reviewe
d)
41/7B
ECRRP/BWD
B/W-18
Annex 4A: Monitoring Form PMF-C2: Process Monitoring – Polder (29 Polders) Cont.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 94
1 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Embankment R 19.01 ( R) 22-09-12 02-12-11 Approved 100%
Water Control Stucture C&R 14( C) 6( R) 23-09-13 28-08-14 Approved 100%
Protective Works C 1175 m 24-09-12 08-12-13 Approved 100%
Embankment C&R 2.00 (C) 13.10 ( R) 25-09-10 15-08-11 Approved 100%
Water Control Stucture C&R 4( C) 5( R) 26-09-12 01-01-14 Approved 100%
Embankment C&R 1.50 (C) 23.10 ( R) 27-09-10 02-12-11 Approved 100%
Water Control Stucture C&R 9( C) 5( R) 28-09-12 01-01-14 Approved 100%
Protective Works C 1300 m 29-09-13 21-01-14 Approved 100%
Embankment C&R 5.00 (C) 22.82 ( R) 30-09-12 01-01-14 Approved 100%
Water Control Stucture C&R 9( C) 6( R) 22/09/2013 24-06-14 Approved 100%
Protective Works C 2765 m 22-04-13 31-12-13 Approved 100%
Embankment C&R 0.98 (C) 12.80 ( R) 22-09-10 21-12-11 Approved 100%
Water Control Stucture C&R 3( C) 12( R) 22/09/2013 28-08-14 Approved 100%
Embankment C&R 2.00 (C) 25.41 ( R) 22-09-10 21-12-11 Approved 100%
Water Control Stucture C&R 9( C) 8( R) 22-09-10 10-07-11 Approved 100%
Protective Works C 1090 m 22-09-12 08-12-13 Approved 100%
Embankment C&R 8.50 (C) 10.04 ( R) 22-09-10 15-09-11 Approved 100%
Water Control Stucture C&R 11( C) 6( R) 22/09/2013 28-08-14 Approved 100%
Protective Works C 260 m 22/09/2013 30-12-13 Approved 100%
Embankment C&R 1.05 (C) 25.08 ( R) 22/09/2013 - Partly approved 100%
Water Control Stucture C&R 18( C) 24( R) 22/09/2013 10-09-12 Approved 100%
Protective Works C 2400 m 22/09/2013 02-12-14 Approved 100%
Embankment R 3.50 ( R) 22/09/2013 - Partly approved 100%
Water Control Stucture C&R 2( C) 7( R) 22/09/2013 13-09-11 Approved 100%
Protective Works C 2800 m 22/09/2013 09-10-14 Approved 100%
39/1C Embankment R 2.50 ( R) 22/09/2013 - Not approved 100%
Water Control Stucture C&R 4 ( C) 5 ( R) 22/09/2013 13-09-11 Approved 100%
Protective Works C 1450m 22/09/2013 09-10-14 Approved 100%
N/A
26th Dec, 2013Updated under
preparation
03/2013-
2014
Com
me
nce
me
nt
da
te-
30
/09
/20
14
5/2/14;
Clearance from
M&E - 18/05/14
6/3/14;
Clearance from
M&E - 18/05/14
24th Jan, 2014
06/11/14;
Comments given
by the M&E
Consultant to
update the report.
Updated under
preparation
Updated under
preparation
8/5/14;
Clearance from
M&E - 27/05/14
25/2/14;
Clearance from
M&E - 12/03/14
20th Jan, 2014
06-01-14
20th Feb, 2014
8/5/14;
Clearance from
M&E - 27/05/14
25/2/14;
Clearance from
M&E - 12/03/14
16/4/14 &
28/11/15;
Clearance from
M&E- 03/3/16
Updated under
preparation
11/2/2015;
Comments
given by the
M&E
Consultant to
update the
report
ECRR/BWD
B/W-10
Com
me
nce
me
nt
da
te-
30
/07
/20
15
07-08-14
25/2/14;
Clearance from
M&E - 12/03/14
11/2/2015;
Comments
given by the
M&E
Consultant to
update the
report
4th Feb, 2014
26th Jan, 1014
30th March
2015Jun-15
29th June
2015
30th June
2015
6/3/14;
Clearance from
M&E - 24/03/14
13/4/14;
Clearance from
M&E - 5/06/14
18/08/2014
13/4/14;
Clearance from
M&E - 28/05/14
25th Feb, 2014
10/11/14; Cleared
by the M&E
Consultant -
27/10/14
Updated under
preparation
10th February
2015
20th Jan, 2014
03-11-13
20th Jan, 2014
45
43/1
25th Feb, 2014
16/4/14 &
13/11/14; Cleared
by the M&E -
27/11/14
Feb-1444(B)
Barguna
01-01-
2014(Revi
ewed)
41/4
Borobogi,
Karbaria,
Pachakuralia &
Arpangasia Amtali Barguna
01-01-
2014(Revi
ewed)
41/5
55/2D
Feb-14
Bailatali Barguna Barguna
01-01-
2014(Revi
ewed)
Feb-14
Dhalua Barguna
01-01-
2014(Revi
ewed)
Feb-14
Borobogi Amtali Barguna
01-01-
2014(Revi
ewed)
Ronogopaldi Dasmina Patuakhali
Feb-14
Amtali
pauroshova,
Amtali, Chowra &
Kukua
Amtali Barguna
01-01-
2014(Revi
ewed)
Feb-14
01-01-
2014(Revi
ewed)
Feb-14
Barguna 39/1A
Charkajol Galachipa Patuakhali
01-01-
2014(Revi
ewed)
55/3
Pirojpur
39/1B
Feb-14
Shapleza,
Gulshakhali &
Tikikata
Mothbaria Pirojpur
01-01-
2014(Revi
ewed)
Feb-14
Kakchira,
Kalomegha,
Kathantali,
Raihanpur &
Nachnapara
Patharghata
01-01-
2014(Revi
ewed)
Feb-14
13/4/14;
Clearance from
M&E - 28/05/14
ECRRP/BWD
B/W-19
ECRRP/BWD
B/W-20
Boromachua,
Amragachia,
Betmor,
Mothbaria Sadar
Mothbaria
IEE/EIA Study Social and Resettlement
Study
As of 30 September 2016
Polder information Preparatory works Tender notice up to signing of contract
Finish
date/
Submissio
n date to
BWDB
Design approval date
Remarks
(any relevant
infromation not
yet included
e.g.causes of
delays)
Package
No.
(WB)
Polder ID (including
embankment, water control
structures,and protective works)
Total
Quantity
(Polder)
Total Rehab. /
Construction
Requirement
Location of the PolderDamage
AssessmentDesign Works
Date of
clearance of
WB
Tender
notice date
Approval
date of
Comprehens
ive
Technical
Report
Tender Process
Union Upazila DistrictStart
date
Finish
date
Start
date
Tender
received
date
Tender
approval
date
Letter of
Award date
Contract
signed date
Contract
ID
(BWDB)
2
Progress
(%)
Date of
Submission
to M&E
Date of
clearance
of WB
Date of
Submission
to M&E
Annex 4A: Monitoring Form PMF-C2: Process Monitoring – Polder (29 Polders) Cont.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 95
As of 30 September 2016
1 2 3 4 5 6 7 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Embankment
502.00 19380.17 7.10 Km ( R ) 408.82 100 0 100.00
WCS
317 11544.05
Protective
Work 19.00 25654.92
Others(Land) 82 ha 2738.95 0.39 Km ( R ) 371.47 100 0 100.00
10.8 Km ( R) 240.39 100 0 100.00
Items 67.96 95 0 95.00
29.65 Km ( R ) 195.60 85 0 85.00
28.47 Km ( R) 214.95 85 0 85.00
Items 49.57 60 0 60.00
14.50 Km ( R) 85.16 88 0 88.00
Items 29.01 66 0 66.00
25.00 Km ( R) 257.19 100 0 100.00
20.78 Km ( R) 749.02 100 0 100.00
4.80 Km ( R) 581.57 100 0 100.00
Items 71.9 95 0 95.00
12.70 Km ( R) 303.1 86 0 86.00
7.96 Km ( R) 127.97 100 0 100.00
5.10 Km ( R) 183.54 100 0 100.00
5.20 Km ( R) 96.83 100 0 100.00
3 (R) & 2 (N) 135.98 100 0 100.00
2nd Phase:
7 polders
(Avg. 65%) &
3 polders
(Avg. 25%)
0
0
100.00
70.00
100.00
100.00
Dropped
100.00
1825.21
Total
100.00
Dropped
864.75
0
Cont
ract
term
inat
ed o
n
5th
Sept
embe
r 201
3
with
pen
alty
381.68
100.00
95.00
0
381.68
1858.82 1858.82
Cont
ract
term
inat
ed o
n 5t
h Se
ptem
ber
2013
with
pen
alty
88.00
1825.21
100.00
0.00
0.00
61.00
887.2590.00
85.00
This
quarter
100.00
0.00
100.000
Cumulativ
e as of
previous
quarter
84.00
100.00
90.00
100.00
100.00
Overall
of the
Polder
100.00
100.00
100.00
100.00
100.00
1000.00
86.002 (R) & 8 (C)
24/05/2012
(Revised 24th
May 2013);
Contract
cancelled on 5th
September 2013
100
70
5/5/2012
(Revised date is
31st March
2013)
Embankment
100
39/2A
Embankment
1871.91
(Revised
1867.17)
46
Embankment
1869.13
513.39
Water Control Stucture
54/A1885.74
0 100.00
10/2009-10
Water Control Stucture
1( R) & 1(C)1441.12
(Revised
1292.25)
Others (EMP/ Supervision/
EFF)
0
Protective Works
0
8
41/6B
41/7B
Embankment
ECRRP/B
WDB/W-01
ECRRP/B
WDB/W-02
Water Control Stucture
47/5
52/53B
ECRRP/B
WDB/W-05 14/2010-11
Others (EMP/ Supervision/
EFF)
47/1
01/2010-11
55/2C
Embankment
55/1
Embankment
Embankment
Embankment
Package
No.
Contract
No.
1st Phase:
16 polders
(100%) & 3
polders
(Avg. 70%)
13/2009-
2010
Water Control Stucture
Package
Cost
(Tk in lakh)
Contract Cost
(Tk in lakh)
Physical
(%)
Financial
(Taka in
lakh)
Total Rehab. / Construction
Requirement
Date of
commen-
cement of
work
Polder ID (including embankment, water
control structures, and protective
works)
651.38
Physical Progress (%)
Overall
of the
Package
903 (R) & 6 (C)
1753.22
1272.84
(Revised
1123.95)
This
quarterTotal
Cumulativ
e as of
previous
quarter
Item of
works
Total Target - As per
RDPP (2nd Revised) &
AM 2016
Overall Progress as of
30 June 2016
Physical
(Km/ Nos.)
Financial
(Taka in
lakh)
Embankment
12851.16
24351.75
Water Control Stucture
Protective Works
2/8/2012
(According to
court verdict-
30/06/2013);
Contract
25/11/2010
161.34
Target date of
completion
175.06
10 (R) & 17 (C)
11-07-10
627.55
(Revised
567.35)
3( R) & 1(C)
1624.66
25/7/2011
100
14.63
145.67
03-09-11
Item wise
costTotal cost
02-03-11
86
177.39
100
100
22/1/2013 (2nd
Revised date is
15th June 2013)
0
67.97
0
95
183.9
626.81 100
123.758 (R) & 1 (C)
2 (R) & 1 (C)
800 m
Embankment
Water Control Stucture1 (R)
Water Control Stucture
0
03 (R)
60.67
8/6/2012
(Revised date is
15th February
2013)
1880.644 (R)
Items
22.05
Others (EMP/ Supervision/
EFF)
ECRRP/B
WDB/W-0302/2010-11
Others (EMP/ Supervision/
EFF)
52-53A
Embankment
ECRRP/B
WDB/W-04
55/4
1292.26
0.00
Embankment
3 (R) & 1 (C)
100
Water Control Stucture
Water Control Stucture
Others (EMP/ Supervision/
EFF)
1000
0Water Control Stucture
Water Control Stucture
Water Control Stucture
Remarks
Wor
k co
mpl
eted
Wor
k co
mpl
eted
Wor
k co
mpl
eted
1292.26
887.25 0.00
Financial Progress (Tk. In lakh)
100.00
Annex 4B: Monitoring Form PMF-C3: Polder Embankment Construction/ Rehabilitation Progress Monitoring (29 Polders)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 96
Annex 4B: Monitoring Form PMF-C3: Polder Embankment Construction/ Rehabilitation Progress Monitoring (29 Polders) Cont.
As of 30 September 2016
1 2 3 4 5 6 7 9 10 11 12 13 14 15 16 17 18 19 20 21 22
7.70 Km ( R ) 174.58 100 0 100.00
19.35 Km ( R) 438.99 100 0 100.00
12.45 Km ( R) 428.08 100 0 100.00
Items 17.34 100 0 100.00
10.74 Km (R); 0.85 Km (C) 232.04 100 0 100.00
15.06 km (R); 1.5 km Km (C) 346.51 100 0 100.00
12.09
18.46
400 m 383.05 0 0 0.00
Items 28.08 95 0 95.00
21.82 Km ( R) ) 397.99 100 0 100.00
55/2B 6.35 Km ( R) & 2.55 Km © 348.65 100 0 100.00
2 (R) 13.44 100 0 100.00
This
quarterTotal
8
Cumulativ
e as of
previous
quarter
This
quarterTotal
Overall
of the
Polder
Overall
of the
Package
Cumulativ
e as of
previous
quarter
Polder ID (including embankment, water
control structures, and protective
works)
Physical Progress (%) Financial Progress (Tk. In lakh)
Remarks
Physical
(Km/ Nos.)
Financial
(Taka in
lakh)
Physical
(%)
Financial
(Taka in
lakh)
Item wise
cost
Total Rehab. / Construction
Requirement
Package
Cost
(Tk in lakh)
Contract Cost
(Tk in lakh) Date of
commen-
cement of
work
Target date of
completion
Total cost
Item of
works
Total Target - As per
RDPP (2nd Revised) &
AM 2016
Overall Progress as of
30 June 2016
Package
No.
Contract
No.
90.00
0.00
972.26
ECRRP/B
WDB/W-06
03/2011-
2012
44 (P)
Embankment
18 (R) & 6 (C)Water Control Stucture
Items 90
488.19 96 0 96.00
0
ECRRP/B
WDB/W-07
P-3/1963
dated
19/1/2012
Embankment
Work
co
mp
lete
d
Water Control Stucture1 (R) & 5 (C) 88.06 100
1167.37 0
ECRRP/B
WDB/W-10
39/1D
Embankment
Others (EMP/ Supervision/
EFF)
03/2011-
2012
40/1
Embankment
Protective Works
ECRRP/B
WDB/W-14897.94 1006.75 02-09-12Embankment
Others (EMP/ Supervision/
EFF)33.16
03/2011-
2012
50/51
Embankment
02-03-12
29/10/2012
(Revised date is
23rd December
2012)4 R & 5 C 251.65 100
1557.69100.00
Water Control Stucture
3 (R) & 1 (C)
100.00
Items
213.52
1450.92
(Revised
907.32)
4 (R) & 11(C)
100.00
789.83
(Revised
822.24)
Water Control Stucture
Water Control Stucture
100.00
100 0
Water Control Stucture
Water Control Stucture
0
209.58 0 100.00
47/4
42 812.18
700 mProtective Works 92
Others (EMP/ Supervision/
EFF)
7 (C) & 11 (R)
Work
co
mp
lete
d
821.49
972.26
100
827.63
0.00
0 100.00
100.00
100.00
18/1/2013
(Revised date is
15th March
2013)
20/2/2013
(Revised date is
30th April 2013)
100.00
100
2384.16
(Revised
2343.85)
20/2/2012
92.00
100.000
0
100.00 821.49 0.00
2125.74
Work
co
mp
lete
d
827.630.00
2125.74
100.00
100
19/1/2012
Embankment
100.00
26.97
2068.71
344.41
20/2/2013
(Revised date is
15th June 2013)
Others (EMP/ Supervision/
EFF)
100.00
100.00
Work
co
mp
lete
d
100.00
100.00
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 97
As of 30 September 2016
4.127 ( R) 90.00 0.00 90.00
14 ( R) 95.00 0.00 95.00
1560 m ( C) 78.00 0.00 78.00
Others Items 96.00 0.00 96.00
10.327 ( R) 90.00 0.00 90.00
2 ( R) 88.00 0.00 88.00
1560 m ( C) 12.00 1.00 13.00
Others Items 62.00 0.00 62.00
15.31 ( R) 90.00 0.00 90.00
1( C) & 3( R) 96.00 0.00 96.00
Others Items 80.00 0.00 80.00
5.945 (C) & 5.521 (R) 60.00 0.00 60.00
4 ( R) 45.00 0.00 45.00
3350 m 73.00 2.00 75.00
Items 65.00 0.00 65.00
19.01 ( R) 32.00 0.00 32.00
14( C) & 6( R) 78.00 0.00 78.00
1175 m( C) 62.00 2.00 64.00
Others 35.00 0.00 35.00
1.00 (C) & 14.10 ( R) 60.00 0.00 60.00
4( C) & 5( R) 80.00 0.00 80.00
Others Items 50.00 0.00 50.00
1.50 (C) & 23.10 ( R) 49.00 0.00 49.00
9( C) & 5( R) 75.00 0.00 75.00
1300 m ( C) 66.00 3.00 69.00
Others Items 35.00 0.00 35.00
5.10 (C) & 22.563 ( R) 58.00 0.00 58.00
9( C) & 6( R) 70.00 0.00 70.00
2765 m ( C) 44.00 0.00 44.00
Others Items 60.00 0.00 60.00
0.98 (C) & 12.52 ( R) 30.00 0.00 30.00
3( C) & 12( R) 55.00 0.00 55.00
Others Items 50.00 0.00 50.00
0.87 (C) & 25.694 ( R) 68.00 0.00 68.00
9( C) & 8( R) 85.00 0.00 85.00
1090 m 80.00 0.00 80.00
Others Items 50.00 0.00 50.00
6.80 (C) & 13.04 ( R) 75.00 0.00 75.00
11( C) & 5( R) 52.00 0.00 52.00
260 m 45.00 0.00 45.00
Items 50.00 0.00 50.00
1.05 (C) & 24.55 ( R) 36.00 7.00 43.00
2 (C) &24( R) 30.00 18.00 48.00
1600 m ( C) 23.00 1.00 24.00
Items 40.00 0.00 40.005.55 Km ( R) & 2.86Km (
C) 11.00 6.00 17.00
10 ( C) & 19( R) 30.00 2.00 32.00
2860 m ( C) 27.00 0.00 27.00
Items 40.00 0.00 40.004.91 Km ( R) & 1.45 Km
( C) 24.00 0.00 24.00
3 ( C) & 13 ( R) 0.00 0.00 0.00
1450 m ( C) 0.00 0.00 0.00
Items 40.00 0.00 40.00
Protective Works
63.00
Wor
k is
in p
rogr
ess
65.00
69.00
55.00
44(B)
41/4
41/6B
39/2A
86.00
51.00
Embankment
Embankment
92.00
Protective Works
Protective Works
Embankment
Water Control Stucture
ECRRP/
BWDB/
W-19
41/7B
Embankment
52/53B
Protective Works
ECRRP/B
WDB/W-18
32.00
3836.14 0.00
26/8/2015
23911.42
78.00
61.00
6948.15
(Revised
9600.00)
03-09-14
3836.14ECRRP/B
WDB/W-20
Embankment
15400.00
Others(EMP/ Supervision/
EFF)
13239.232639/1B
50.00
Embankment
Water Control Stucture
41/5
55/2D
Embankment
Water Control Stucture
Protective Works
Embankment
43/1
45
Wor
k is
in p
rogr
ess
25.00
14193.62 0.00 14193.62
Water Control Stucture
Embankment
Embankment
Embankment
Water Control Stucture
7533.20 27/5/2014
Water Control Stucture
Protective Works
Water Control Stucture
Embankment
Protective Works
Others
6321.99
Water Control Stucture
6321.99
Wor
k is
in p
rogr
ess
(Ass
umin
g th
e co
ntra
ct v
alue
will
incr
ease
abo
ut 3
4 cr
ore
for B
ank
Prot
ectio
n of
Pol
der 3
9/2A
& ot
her a
dditi
onal
wor
ks)
0.00
Protective Works
Water Control Stucture
09-03-16
70.00
66.00
Water Control Stucture
Others
Embankment
Water Control Stucture
55/3
Others
Embankment
Protective Works
Protective Works
Others
25.00
39/A
Water Control Stucture
55.00
12.00Water Control Stucture
Water Control Stucture
25675.58
39/1C
Protective Works
Package
Cost
(Tk in lakh)This
quarterTotal Total
Contract Cost
(Tk in lakh)Date of
commen-
cement of
work
Target date of
completionOverall
of the
Polder
Total cost
Item of
works
Total Target as per
RDPP
Overall Progress as of
30 June 2016
Package
No.
Contract
No.Financial
(Taka in
lakh)
Remarks
Physical
(Km/ Nos.)
Financial
(Taka in
lakh)
Physical
(%)
Item wise
cost
Cumulativ
e as of
previous
quarter
Polder ID (including embankment, water
control structures, and protective
works)
Total Rehab. / Construction
Requirement Cumulativ
e as of
previous
quarter
This
quarter
Overall
of the
Package
Physical Progress (%) Financial Progress (Tk. In lakh)
Annex 4B: Monitoring Form PMF-C3: Polder Embankment Construction/ Rehabilitation Progress Monitoring (29 Polders) Cont.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 98
Annex 5: Subcomponent D.1 Annual Work Program FY2016-2017
Sl.no. Description Time
July August September October November December
1. Fund Release Proposal
2 PA Authorization
3. Interiumun-audited financial Report(IUFR)
4. IMED Report
5. Monthly progress Report
6. Procurement
7. Project Completion Report(PCR)
8
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 99
Action Plan for ECRRP, D 1 component for the revised RDPP (DNA)
Period: July 2016 to December 2016
Description
Jul Aug Sep Oct Nov Dec
Working closely with DDM staff to integrated the system into DDM (capacity building)
Updated DNA software (Bi-lingual)
Updated DNA software (Mobile Aps)
Updated DNA software (Satellite authentication)
DNA refresher training
Awareness on Citizen reporting
National workshop
Phase-out and final reporting (PCR)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 100
MultiHazard Risk and Vulnerability Assessment (MRVA)
Sl. No. Task/ Activities Months 2016
July August September October November December
1. 4 Development of DEMs (Digital Elevation Models Preferable 5 Meter/ 20 Meter Resolution ) for Coastal 12 districts
2. 5 Multi-Hazard Risk Atlas (for Districts and Upazila Perspectives) in Three Volumes (Hydrometeorological, Geological and Environmental Risk Atlas)
3. 6 GIS databases (Cyclone Shelters and others) updates
4. 7 Geo-Node web-portal with geo-database (Server installed in MRVA cell.Final Reports, database & Maps will be hosted)
5. 8 Finalization of Report on Multi-Hazard Risk and Vulnerability Assessment, Modeling and Mapping (MRVAM) Six Volumes
6. Final Workshop
7. Phase-out and final reporting (PCR)
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 101
As on September 2016.
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(Nos.)
Financial
(Taka in
lakh)
1 3 4 5 6 7 8 9 10 11 12 13 14
1 64 64 DDM Done
2 144 144 DDM Done
3 144 144 DDM Done
4 144 144 DDM Done
5 35.00 517.54 35 517.54 35 517.54 DDM Done
6 1704 147.18 1704 147.18 1704 147.18
DDM
Done
7 6.00 787.87 6 787.87 6.00 787.87 Sidr District Done
8 12 566.90 12 566.90 12 566.90 Sidr DistrictHanded over to 12
districts.
9 4 986.06 4 986.06 4 986.06 DDM
Handed over to
Coast Guard &
RAB.
10 13 50.00 13 50 Sidr District
Contract signed
11 5 2.40 5 2.40 5 2.40 Sidr District Done
12 L.S. 7.00 6 7.00 6 7.00 Sidr dist. Done
13 LS 28.58 LS 28.58 LS 28.58 Sidr dist. Done
14 LS 5.00 LS 5.00 LS 5.00 Done
15 47 25.00 47.00 25.00
16 LS 5.00 LS 5.00
17 Installation of Earthing System for Pole Fitted Megaphone LS 20.00 LS 20.00
18 Procurement of Raincoat & Life Jacket for Rescue Person. LS 10.00 LS 10.00 LS 10.00 Done
Cont.
Sl. No.
64 Hand - tool Set
Financial
(Taka in
lakh)
EMERGENCY SEARCH & RESCUE EQUIPMENT
144 First aid kit and accessories
Mobile ambulance Boat.
Rough Aquatic boat Sea Search & Rescue Box
Rescue equipment for vuluntears and CPP personnel.
26.78
Description of Procurement Package as per RDPP
Progress in FY 2016-
2017
GPS Set
Disruption- Free telecom equipment
26.78144 Handy Megaphone for Sidr Effected Districts
Installation of Solar power for uninterupted power supply to the Pole fitted
Megaphone Siren.
Procurement of Rechargable Battery for Pole Fitted Megaphone
Supply Hazard Mapping eqipment like- Server , Computer, Digitizer , Plotter,
Printer, Other Equipment.
144 Stretcher and accessories
Pole fitted 6×1 Megaphone Siren with Computerized unit.
Remarks
Physical
(Nos.)
Financial
(Taka in
lakh)
Annual Target for FY
2016-2017
Small Marine Rescue Boat
496 26.78
Training equipment for field level training (4 laptops, multi- Media Project
with screen and accessories)
2
Hamess, Orange vest & Identification card, caution tape,144 Tent & ground
sheet, 768 Flashligt/headlamp /Leather gloves,24 Portable Generator.
Physical
(Nos.)
Total Target as per
3rd RDPP
List of UsersL1
Progress as of end of
June 2016Cumulative Progress
Annex 6: Progress Monitoring - Sub-component D1: Disaster Risk Mitigation and Reduction
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 102
As on September 2016.
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(Nos.)
Financial
(Taka in
lakh)
1 3 4 5 6 7 8 9 10 11 12 13 14
19 4.00 185.96 4 185.96 4 185.96 Sidr dist.
20 1.00 21.92 1 21.92 1.00 21.92 Sidr dist.
21 12.00 341.19 12 341.19 12 341.19 DDM
22 1.00 22.90 1 22.9 1 22.9 DDM
23 4.00 4.95 4 4.95 4 4.95 Sidr dist.
24 1.00 1.73 1 1.73 1 1.73 Sidr dist.
25 21.00 8.03 21 8.03 21 8.03 Sidr dist.
26 L.S 3.27 L.S 3.27 L.S 3.27 Sidr dist.
Cont.
Car
Office Operational Equipment ( 1 Copier)
Office Operational Equipment ( Almira, Exec table, Chair, Computer
table 7 chair , file cabinet etc.
2
Office Operational Equipment (4 AC)
10 Computers, Anti- virus Software, UPS, Printers etc.
Financial
(Taka in
lakh)
Office Operational Equipment ( Almira, Exec table, Chair, Computer
table 7 chair , file cabinet etc.
Progress in FY 2016-
2017
Physical
(Nos.)
Financial
(Taka in
lakh)
Emergency Pickup for field operation in 12 SIDR Affected district
Total Target as per 3rd
RDPP
4 WD Emergency Vehicles
Microbus
Progress as of end of
June 2016
Sl
No.Description of Procurement Package as per RDPP
EMERGENCY VEHICLE & OFFICE EQUIPMENT
Cumulative Progress
List of
UsersL1
Annual Target for FY
2016-2017
Physical
(Nos.)
Remarks
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 103
As on September 2016
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(Nos.)
Financial
(Taka in
lakh)
Physical
(Nos.)
Financial
(Taka in
lakh)
1 3 4 4 5 5 6 6 7
3 6.00 3 6.00 3 6.00
4 6.00 4 4 0
70 16.80 128 128
70 16.00 81 81 0
8 16.00 1 1 1 0
1 20.00 1 20.00 1 20.00
1 60.00 1 60.00 1 60.00
1 28.00 1 28.00 1 28.00
64 64 64
144 80.64 144 80.64 144 80.64
72 43.98 72 43.71 72 43.71
72 72.00 72 72.00 72 72.00
1 17.55 1 1
1 17.55 1 1
1 17.55 1 1
1 17.55 1 17.55 1 17.55
1 17.55 1 1
Certificate Course at ITC, the Netherland on Disaster Risk
Management and Environmental Assesment for Sptial Planing
International Training Course on GIS for Disaster Risk
Management in Bangkok, Thailand
International Training Course on Multi Hazard Risk Assesment
in Korea
International Training Course on EarthquakeVulnerability
Reduction in Bangkok, Thailand
Capacity
building on
Multi-
hazard Risk
Assesments
, modeling
and
Mapping
(MRVA)
International Training Course on Flood Disaster Risk
Assesment in Bangkok, Thailand
Economic
CodeType of Traininig
Total Target as per 3rd
RDPP
Progress as of end of
June 2016Cumulative Progress
Annual Target for FY
2016-2017
Physical
(Nos.)
Financial
(Taka in
lakh)
Progress in FY 2016-2017
MRVA Modeling and Information management international
Course.
Simulation Excercises within DMCs in SIDR affected District
National DNA Training for DDM and Other department
Training of the CPP Volunteers force in SIDR affected
District
Validation D-Form
District Level Regional Training on MRVA
TRAINING
2
Stakeholder Planning Workshop
DNA Training for the field officials
Training of DMCs/ CPP members and community people in
SIDR affected District
Advanced Disaster Management Training
National Level and field Level Policy Workshops
International -Research based field study (Hurricane and
typhone affected countries) 4840
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 104
Unit Reasons for
Variance /Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Remarks
1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr.
(Col. 1) (Col. 3) (Col. 4) (Col. 5) (Col. 6) (Col. 7) (Col. 8) (Col. 9) (Col. 10) (Col. 11) (Col. 12) (Col. 13) (Col. 14) (Col. 15) (Col. 16) (Col. 17) (Col. 18) (Col. 19) (Col. 20) (Col. 21) (Col. 22) (Col. 23) (Col. 24) (Col. 25) (Col. 26) (Col. 27) (Col. 28) (Col. 29) (Col. 30) (Col. 31) (Col. 32) (Col. 33) (Col. 34) (Col. 31) (Col. 32) (Col. 33)
PDO
P-1
P-1A Target (cumulitive) nos. - - - - - - - 6,000 6,000 6,000 21,000 30,000 40,500 60,000 103,500 120,000 172,500 225,000 255,000 285,000 315,000 345,000 363,000 381,000 400,500 420,000 474,000 529,500 529,500 529,500
Actual (cumulitive) nos. - - - - - - - 6,000 6,000 6,000 21,000 30,000 40,500 67,500 111,000 127,500 156,000 225,000 243,000 249,000 274,500 336,000 336,000 336,000 343,500
Variance: value nos. - - - - - - - - - - - - - 7,500 7,500 7,500 (16,500) - (12,000) (36,000) (40,500) (9,000) (27,000) (45,000) (57,000)
% - - - - - - - - - - - - - 13 7 6 (10) - (5) (13) (13) (3) (7) (12) (14)
P-1B Target (cumulitive) nos. - - - 29,440 37,720 66,240 138,000 210,680 210,680 220,800 220,800 220,800 220,800 220,800 220,800 220,800 239,200 257,600 266,800 276,000 285,200 294,400 312,800 331,200 349,600 368,000 395,600 423,200 423,200 423,200
Actual (cumulitive) nos. - - - 29,440 37,720 66,240 138,000 210,680 210,680 220,800 220,800 220,800 220,800 220,800 220,800 220,800 220,800 220,800 220,800 247,480 248,400 264,960 356,960 361,560 375,360
Variance: value nos. - - - - - - - - - - - - - - - - (18,400) (36,800) (46,000) (28,520) (36,800) (29,440) 44,160 30,360 25,760
% - - - - - - - - - - - - - - - - (8) (14) (17) (10) (13) (10) 14 9 7
P-2
P-2A Target (cumulitive) % - - - - - - - 0.4 0.4 0.4 1.5 2.2 3.0 4.4 7.6 8.8 12.7 16.6 18.8 21.0 23.2 25.4 26.7 28.0 29.5 30.9 34.9 39.0 39.0 39.0
Actual (cumulitive) % - - - - - - - 0.4 0.4 0.4 1.5 2.2 3.0 5.0 8.2 9.4 11.5 16.6 17.9 18.3 20.2 24.7 24.7 24.7 25.3
Variance: value % - - - - - - - - - - - - - 1 1 1 (1) - (1) (3) (3) (1) (2) (3) (4)
% - - - - - - - - - - - - - 13 7 6 (10) - (5) (13) (13) (3) (7) (12) (14)
P-2B Target (cumulitive) % - - - 1.7 2.1 3.7 7.8 11.9 11.9 12.5 12.5 12.5 12.5 12.5 12.5 12.5 13.5 14.5 15.1 15.6 16.1 16.6 17.7 18.7 19.7 20.8 22.3 23.9 24.1 23.9
Actual (cumulitive) % - - - 1.7 2.1 3.7 7.8 11.9 11.9 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 14.0 14.0 15.0 20.2 20.4 21.2
Variance: value % - - - - - - - - - - - - - - - - (1) (2) (3) (2) (2) (2) 2 2 1
% - - - - - - - - - - - - - - - - (8) (14) (17) (10) (13) (10) 14 9 7
P-3 Target (cumulitive) ha - - - - - - - - - - 14,811 31,737 31,737 33,994 33,994 33,994 33,853 33,853 40,342 42,458 44,573 46,689 48,805 50,921 53,037 55,153 57,268 57,268 59,384 61,500
Actual (cumulitive) ha - - - - - - - - - - 15,740 22,811 22,811 24,961 24,961 24,961 24,961 24,961 24,962 24,963 24,963 24,963 24,963 24,963 24,963
Variance: value ha - - - - - - - - - - 929 (8,926) (8,926) (9,033) (9,033) (9,033) (8,892) (8,892) (15,380) (17,495) (19,610) (21,726) (23,842) (25,958) (28,074)
% - - - - - - - - - - 6 (28) (28) (27) (27) (27) (26) (26) (38) (41) (44) (47) (49) (51) (53)
P-4 Target (cumulitive) ha - - - - - - - - - - 3,630 7,778 7,778 8,331 8,331 8,331 8,296 8,296 9,887 10,405 10,924 11,442 11,961 12,479 12,998 13,516 14,035 14,035 14,553 15,072
Actual (cumulitive) ha - - - - - - - - - - 3,935 5,702 5,702 6,240 6,240 6,240 6,240 6,240 6,241 6,242 6,242 6,242 6,242 6,242 6,243
Variance: value ha - - - - - - - - - - 305 (2,076) (2,076) (2,091) (2,091) (2,091) (2,056) (2,056) (3,646) (4,163) (4,682) (5,200) (5,719) (6,237) (6,755)
% - - - - - - - - - - 8 (27) (27) (25) (25) (25) (25) (25) (37) (40) (43) (45) (48) (50) (52)
P-5 Target %
Actual %
Variance: value %
%
P-6 Target %
Actual %
Variance: value %
%
2014-15 2015-16 2016-17 2017-182013-14EXPECTED RESULTS INDICATORS
Values of Indicators
(Col. 2)
To support Government of Bangladesh
efforts to facilitate recovery from the damage
to livelihoods and infrastructure caused by
Cyclones Sidr and Aila, and to build long-term
preparedness through strengthened disaster
risk management.
Number of vulnerable population in target
communities that benefited from reduced
risk due to project interventions.
Persons benefited from additional capacity
through construction of new shelters
2009-10 2010-11 2011-12
Inland fishery area in the target polders
that benefited from reduced risks from
cyclone damage and saline water
inundation.
Improved capacity and preparedness for
disaster risk management.
Beneficiaries' perception on improvements
to livelihoods due to project interventions.
Vulnerable population that benefited from
reduced risk due to project interventions,
as a percentage (%) of total vulnerable
population in target communities.
2012-13
Persons benefited from adequate facilities &
accessibility through the improvement of
existing shelters
% of persons benefited from additional
capacity through construction of new shelters /
total vulnerable population in target
communities
% of persons benefited from adequate
facilities & accessibility through the
improvement of existing shelters / total
vulnerable population in target communities
Agricultural area in target polders that
benefited from reduced risks from cyclone
damage and saline water inundation.
Annex 7: Quarterly Actual Vs. Target Values for Indicators of Outputs and Outcome [Per Framework]
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 105
Unit Reasons for
Variance /Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Remarks
1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr.
(Col. 1) (Col. 3) (Col. 4) (Col. 5) (Col. 6) (Col. 7) (Col. 8) (Col. 9) (Col. 10) (Col. 11) (Col. 12) (Col. 13) (Col. 14) (Col. 15) (Col. 16) (Col. 17) (Col. 18) (Col. 19) (Col. 20) (Col. 21) (Col. 22) (Col. 23) (Col. 24) (Col. 25) (Col. 26) (Col. 27) (Col. 28) (Col. 29) (Col. 30) (Col. 31) (Col. 32) (Col. 33) (Col. 34) (Col. 31) (Col. 32) (Col. 33)
OUTPUTS
A-1 Target (cumulutive) hh. 12,690 25,380 38,070 50,761 67,279 83,797 100,315 116,831 133,130 149,429 165,728 182,027 194,882 207,737 220,592 233,445
Actual (cumulitive) hh.
Variance: value hh.
%
A-2 Target hh. - - - 100 - - - 100 - - - 100 - - - 100
Actual hh.
Variance: value hh.
%
A-3 Target nos.
Actual nos.
Variance: value nos.
%
A.1-1 Target (cumulative) hh. - - - 5,459 9,309 9,309 27,283 41,617 45,367 45,718 47,593 50,493 50,493 50,493 50,493 50,493
Actual (cumulative) hh. - - - 5,459 5,459 9,609 9,957 14,346 22,599 22,950 23,575 26,535 26,535 26,830 27,160 33,540
Variance: value hh. - - - - (3,850) 300 (17,326) (27,271) (22,768) (22,768) (24,018) (23,958) (23,958) (23,663) (23,333) (16,953)
% - - - - (41) 3 (64) (66) (50) (50) (50) (47) (47) (47) (46) (34)
A.1-2 Target % - - - 8 14 9 24 21 21 21 22 23 23 23 23 23
Actual % - - - 8 8 8 9 8 11 12 12 13 13 12 12 15
Variance: value % - - - - (6) (0) (15) (13) (10) (10) (10) (10) (10) (11) (11) (8)
% - - - - (41) (5) (64) (62) (46) (45) (46) (43) (43) (48) (48) (35)
A.1-3 Target % - - - 1.8 3.1 3.1 9.2 14.0 15.2 15.3 16.0 16.9 16.9 16.9 16.9 16.9
Actual % - - - 2 2 3 3 5 8 8 8 9 9 9 9 11
Variance: value % - - - - (1.3) 0.1 (5.8) (9.2) (7.6) (7.6) (8.1) (8.0) (8.0) (7.9) (7.8) (5.7)
% - - - - (41) 3 (64) (66) (50) (50) (50) (47) (47) (47) (46) (34)
A.1-4 Target (cumulative) hh. 5,459 14,346 20,996 20,996
Actual (cumulative) hh. 5,459 14,346 17,550 17,550
Variance: value hh. - - (3,446) (3,446)
% - - (16) (16)
A.1-5 Target % 100 34 42 42
Actual % 100 100 66 52
Variance: value % - 66 25 11
% - 190 59 26
A.1-6 Target (cumulative) hh. 43,858 107,698 207,728 228,628
Actual (cumulative) hh. 43,858 104,977 124,616 128,803
Variance: value hh. - (2,721) (83,112) (99,825)
% - (3) (40) (44)
A.1-7 Target % 100 78 76 79
Actual % 100 93 635 235
Variance: value % - 15 559 156
% - 20 738 198
A.2-1 Target (cumulative) hh. - - - 6,250 6,250 6,250 11,200 16,150 16,150 16,150 16,150 25,850 25,850 27,124 28,398 29,671
Actual (cumulative) hh. - - - 5,250 5,250 5,250 11,250 15,150 15,150 15,325 15,325 25,025 25,081 25,137 25,289 25,489
Variance: value hh. - - - (1,000) (1,000) (1,000) 50 (1,000) (1,000) (825) (825) (825) (769) (1,987) (3,109) (4,182)
% - - - (16) (16) (16) 0 (6) (6) (5) (5) (3) (3) (7) (11) (14)
A.2-2 Target % - - - 100 100 100 100 100 100 93 86 91 91 91 92 92
Actual % - - - 100 100 100 165 141 126 101 100 100 100 100 100 69
Variance: value % - - - - - - 65 41 26 8 14 9 9 9 8 (23)
% - - - - - - 65 41 26 9 16 10 10 10 9 (25)
2017-18
(Col. 2)
Values of Indicators
2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17
Component A: Recovery of Agriculture
Sector & Improvement Program
Number of marginal farmers, landless
livestock owners, and fishers in the target
area severely affected by the cyclone
adopting improved technologies.Short-term and medium-term livelihood and
agriculture (crop, livestock and fishery)
recovery assistance provided and sustainable
improvements to agricultural practices in the
project area introduced.
Marginal farmers, landless livestock owners,
and fishers in the target area severely affected
by the cyclone adopting improved
technologies, as a percentage (%) of total
marginal farmers, landless livestock owners,
and fishers provided assistance by the project.
Number of agricultural service providers
(DAE, DoF, DLS, NGOs, CBOs, etc.) able to
promote improved technologies.
EXPECTED RESULTS INDICATORS
Subcomponent A.1: Support to Crop Sub-
sector
Crop sub-sector recovered with improved
resilience to future disasters.
Number of marginal farmers in the target
area that received training and capacity
building on improved techniques.
Number of marginal farmers in the target area
that received training and capacity building on
improved techniques, as a percentage (%) of
number of marginal farmers in the target area
who were given agricultural inputs.
Number of marginal farmers belonging to local
CBOs (FFS, ICM, IPM) adopting improved
technologies disseminated by the project, as a
percentage (%) of total number of marginal
farmers who received training and capacity
building on improved techniques disseminated
by the project.
Number of crop agriculture farmers using
new farm machinery, hand tools and
processing equipment distributed to FGs.
Number of crop agriculture farmers using new
farm machinery, hand tools and processing
equipment distributed to FGs, as a percentage
(%) of total crop agriculture members of these
FGs.Subcomponent A.2: Support to Fisheries
Sub-sector
Fisheries sub-sector recovered with improved
resilience to future disasters.
Number of fishers and aquaculture farmers
in the target area that received training and
capactiy building on improved techniques.
Number of fishers and aquaculture farmers in
the target area that received training and
capactiy building on improved techniques, as
a percentage (%) of total fishers and
aquaculture farmers in the target area who
were given fisheries and aquaculture inputs.
Number of marginal farmers belonging to
local CBOs (FFS, ICM, IPM) adopting
improved technologies disseminated by
the project.
Number of marginal farmers in the target area
that received training and capacity building on
improved techniques, as a percentage (%) of
total marginal farmers in the target area.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 106
Unit Reasons for
Variance /Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Remarks
1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr.
(Col. 1) (Col. 3) (Col. 4) (Col. 5) (Col. 6) (Col. 7) (Col. 8) (Col. 9) (Col. 10) (Col. 11) (Col. 12) (Col. 13) (Col. 14) (Col. 15) (Col. 16) (Col. 17) (Col. 18) (Col. 19) (Col. 20) (Col. 21) (Col. 22) (Col. 23) (Col. 24) (Col. 25) (Col. 26) (Col. 27) (Col. 28) (Col. 29) (Col. 30) (Col. 31) (Col. 32) (Col. 33) (Col. 34) (Col. 31) (Col. 32) (Col. 33)
A.2-3 Target % - - - 3.8 3.8 3.8 6.8 9.7 9.7 9.7 9.7 15.6 15.6 16.4 17.1 17.9
Actual % - - - 3 3 3 7 9 9 - 9 15 15 15 15 15
Variance: value % - - - (0.6) (0.6) (0.6) 0.0 (0.6) (0.6) (9.7) (0.5) (0.5) (0.5) (1.2) (1.9) (2.5)
% - - - (16) (16) (16) 0 (6) (6) (100) (5) (3) (3) (7) (11) (14)
A.2-4 Target (cumulative) hh. 5,250 15,150 24,850 24,850
Actual (cumulative) hh. 5,250 15,150 24,850
Variance: value hh. - - -
% - - -
A.2-5 Target % 100 100 100 100
Actual % - 153 256 -
Variance: value % (100) 53 156 (100)
% (100) 53 156 (100)
A.2-6 Target (cumulative) hh. - - - -
Actual (cumulative) hh. - - 35 12,129
Variance: value hh. - - 35 12,129
% - - - -
A.2-7 Target % - - - -
Actual % - - 20 100
Variance: value % - - 20 100
% - - - -
A.3-1 Target (cumulative) hh. - - - 5,000 6,000 8,500 12,500 15,000 15,000 15,000 15,000 15,000 15,000 15,625 16,250 16,875
Actual (cumulative) hh. - - - 5,000 5,000 5,000 15,550 16,000 16,000 20,625 32,225 - - 1,100 5,100 5,100
Variance: value hh. - - - - (1,000) (3,500) 3,050 1,000 1,000 5,625 17,225 (15,000) (15,000) (14,525) (11,150) (11,775)
% - - - - (17) (41) 24 7 7 38 115 (100) (100) (93) (69) (70)
A.3-2 Target % - - - 45 50 57 65 68 68 68 68 68 68 71 74 77
Actual % - - - 84 84 51 156 126 106 137 191 - - 3 15 13
Variance: value % - - - 39 35 (6) 90 58 38 69 123 (68) (68) (68) (59) (63)
% - - - 85 70 (10) 138 85 56 101 180 (100) (100) (95) (80) (82)
A.3-3 Target % - - - 0.9 1.1 1.6 2.3 2.8 2.8 2.8 2.8 2.8 2.8 2.9 3.0 3.1
Actual % - - - 1 1 1 3 3 3 4 6 - - 0 1 1
Variance: value % - - - - (0) (1) 1 0 0 1 3 (3) (3) (3) (2) (2)
% - - - - (17) (41) 24 7 7 38 115 (100) (100) (93) (69) (70)
A.3-4 Target (cumulative) hh. 5,000 16,025 32,250 32,250
Actual (cumulative) hh. 5000 16025 32250 37925
Variance: value hh. - - - 5,675
% - - - 18
A.3-5 Target % 45 73 147 147
Actual % 84 126 191 100
Variance: value % 39 53 45 (47)
% 85 73 30 (32)
A.3-6 Target (cumulative) hh. 3,000 14,100 26,150 32,300
Actual (cumulative) hh. 1000 4000 15850 15850
Variance: value hh. (2,000) (10,100) (10,300) (16,450)
% (67) (72) (39) (51)
A.3-7 Target % 100 98 79 85
Actual % 100 98 100 60
Variance: value % - (0) 21 (25)
% - (0) 27 (30)
2014-15 2015-16 2016-17 2017-18
(Col. 2)
EXPECTED RESULTS INDICATORS
Values of Indicators
2009-10 2010-11 2011-12 2012-13 2013-14
Number of fishers and aquaculture farmers in
the target area that received training and
capactiy building on improved techniques, as
a percentage (%) of total number of fishers
and aquaculture farmers in the target area.
Number of aquaculture farmers adopting
improved aquaculture practices
disseminated by the project.
Number of aquaculture farmers adopting
improved aquaculture practices disseminated
by the project, as a percentage (%) of total
number of aquaculture farmers who received
training and capacity building on improved
techniques.Number of fishers using fisheries
equipment (e.g. boats, nets and safety
equipment) distributed to groups of
fishers.
Number of fishers using fisheries equipment
(e.g. boats, nets and safety equipment)
distributed to groups of fishers, as a
percentage (%) of total members of these
fishers groups.Subcomponent A.3: Support to Livestock
Sub-sector
Livestock sub-sector recovered with greater
resilience to future disasters.
Number of livestock owners in the target
area that received training and capacity
building on improved techniques.
Number of livestock owners in the target area
that received training and capacity building on
improved techniques, as a percentage (%) of
total livestock farmers in the target area who
were given improved goats, sheep, cows and
poultry.Number of livestock owners in the target area
that received training and capacity building on
improved techniques, as a percentage (%) of
total livestock farmers in the target area
Number of livestock farmers in the target
area that received training and capacity
building and adopting improved practices
for goats, sheep, cows and poultry
rearing.Number of livestock farmers in the target area
that received and adopting improves goats,
sheep, cows and poultry; as a percentage (%)
of total livestock farmers in the target area that
received these livestock.
Number of livestock farmers adopting
improved dairy and poultry production facilities
(cattle sheds and portable poultry sheds).
Number of livestock farmers adopting
improved dairy and poultry production facilities
(cattle sheds and portable poultry sheds), as a
percentage (%) of total number of livestock
farmers who received these facilities.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 107
Unit Reasons for
Variance /Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Remarks
1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr.
(Col. 1) (Col. 3) (Col. 4) (Col. 5) (Col. 6) (Col. 7) (Col. 8) (Col. 9) (Col. 10) (Col. 11) (Col. 12) (Col. 13) (Col. 14) (Col. 15) (Col. 16) (Col. 17) (Col. 18) (Col. 19) (Col. 20) (Col. 21) (Col. 22) (Col. 23) (Col. 24) (Col. 25) (Col. 26) (Col. 27) (Col. 28) (Col. 29) (Col. 30) (Col. 31) (Col. 32) (Col. 33) (Col. 34) (Col. 31) (Col. 32) (Col. 33)
A.4-1 Target nos.
Actual nos.
Variance: value nos.
%
A.4-2 Target %
Actual %
Variance: value %
%
A.4-3 Target %
Actual %
Variance: value %
%
B-1 Target (cumulative) nos. - - - - - - - 4 4 4 14 20 27 40 69 80 115 150 170 190 210 230 242 254 267 280 316 353 353 353
Actual (cumulative) nos. - - - - - - - 4 4 4 14 20 27 40 69 80 99 145 157 166 178 224 224 224 229
Variance: value nos. - - - - - - - - - - - - - - - - (16) (5) (13) (24) (32) (6) (18) (30) (38)
% - - - - - - - - - - - - - - - - (14) (3) (8) (13) (15) (3) (7) (12) (14)
B-2 Target % - - - - - - - 0.4 0.4 0.4 1.5 2.2 3.0 4.4 7.6 8.8 12.7 16.6 18.8 21.0 23.2 25.4 26.7 28.0 29.5 30.9 34.9 39.0 39.0 39.0
Actual % - - - - - - - 0.4 0.4 0.4 1.5 2.2 3.0 4.4 7.6 8.8 10.9 16.0 17.3 18.3 19.6 24.7 24.7 24.7 25.3
Variance: value % - - - - - - - - - - - - - - - - (1.8) (0.6) (1.4) (2.6) (3.5) (0.7) (2.0) (3.3) (4.2)
% - - - - - - - - - - - - - - - - (14) (3) (8) (13) (15) (3) (7) (12) (14)
B-3 Target (cumulative) nos. - - - 32 41 72 150 229 229 240 240 240 240 240 240 240 260 280 290 300 310 320 340 360 380 400 430 460 460 460
Actual (cumulative) nos. - - - 32 41 72 150 229 229 240 240 240 240 240 240 240 240 240 240 269 282 288 388 393 408
Variance: value nos. - - - - - - - - - - - - - - - - (20) (40) (50) (31) (28) (32) 48 33 28
% - - - - - - - - - - - - - - - - (8) (14) (17) (10) (9) (10) 14 9 7
B-4 Target % - - - 1.7 2.1 3.7 7.8 11.9 11.9 12.5 12.5 12.5 12.5 12.5 12.5 12.5 13.5 14.5 15.1 15.6 16.1 16.6 17.7 18.7 19.7 20.8 22.3 23.9 23.9 23.9
Actual % - - - 1.7 2.1 3.7 7.8 11.9 11.9 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 12.5 14.0 14.6 15.0 20.2 20.4 21.2
Variance: value % - - - - - - - - - - - - - - - - (1.0) (2.1) (2.6) (1.6) (1.5) (1.7) 2.5 1.7 1.5
% - - - - - - - - - - - - - - - - (8) (14) (17) (10) (9) (10) 14 9 7
B-5 Target (cumulative) % - - - 7 9 16 33 50 50 52 52 52 52 52 52 52 57 61 63 65 67 70 74 78 83 87 93 100 100 100
Actual (cumulative) % - - - 7 9 16 33 50 50 52 52 52 52 52 52 52 52 52 52 58 61 63 84 85 89
Variance: value % - - - - - - - - - - - - - - - - (4.3) (8.7) (10.9) (6.7) (6.1) (7.0) 10.4 7.2 6.1
% - - - - - - - - - - - - - - - - (8) (14) (17) (10) (9) (10) 14 9 7
C-1 Target (cumulative) km. - - - 25 25 87 100 110 110 120 120 214 227 260 260 260 265 270 282 294 307 320 327 334 342 350 432 502 502 502
Actual (cumulative) km. - - - 25 25 87 100 110 110 120 120 214 227 260 260 260 260 260 260 260 260 260 260 260 260
Variance: value km. - - - - - - - - - - - - - - - - (5) (10) (22) (34) (47) (60) (67) (74) (82)
% - - - - - - - - - - - - - - - - (2) (4) (8) (12) (15) (19) (20) (22) (24)
C-2 Target (cumulative) nos. - - - - - - - - - - 7 15 15 16 16 16 16 16 19 20 21 22 23 24 25 26 27 27 28 29
Actual (cumulative) nos. - - - - - - - - - - 7 15 15 16 16 16 16 16 16 16 16 16 16 16 16
Variance: value nos. - - - - - - - - - - - - - (0) (0) (0) - - (3.07) (4.07) (5.07) (6.07) (7.07) (8.07) (9.07)
% - - - - - - - - - - - - - (0) (0) (0) - - (16.08) (20.27) (24.05) (27.49) (30.64) (33.52) (36.17)
C-3 Target (cumulative) ha. - - - - - - - - - - 48,477 82,004 82,004 89,924 89,924 89,924 98,837 107,750 116,663 125,577 134,490 143,403 152,316 161,230 170,143 179,056 187,969 196,883 205,797 214,710
Actual (cumulative) ha. - - - - - - - - - - 48,477 82,004 82,004 89,924 89,924 89,924 89,924 89,924 89,924 89,924 89,924 89,924 89,924 89,924 89,924
Variance: value ha. - - - - - - - - - - - - - - - - (8,913) (17,826) (26,739) (35,653) (44,566) (53,479) (62,392) (71,306) (80,219)
% - - - - - - - - - - - - - - - - (9) (17) (23) (28) (33) (37) (41) (44) (47)
C-4 Target % - - - - - - - - - - 32 46 46 51 51 51 54 58 61 65 68 72 75 79 82 86 89 93 96 100
Actual % - - - - - - - - - - 32 46 46 51 51 51 51 51 51 51 51 51 51 51 51
Variance: value % - - - - - - - - - - - - - - - - (4) (7) (11) (14) (18) (21) (25) (28) (32)
% - - - - - - - - - - - - - - - - (6) (12) (17) (22) (26) (29) (33) (36) (38)
2017-18
(Col. 2)
2011-12 2012-13 2013-14 2014-15 2015-16 2016-17EXPECTED RESULTS INDICATORS
Values of Indicators
2009-10 2010-11
Subcomponent A.4: Support to
Component Management
Community mobilized, facilitated and
strengthened to improve agricultural
production.
Number of village farmers groups (FGs; i.e.
IPM/ICM Clubs, CIGs, WUAs, fishers groups,
livestock groups, etc) established and
strengthened.
The sub-components implemented and
coordinated efficiently leading to delivery of
planned outputs and achievement of
component objective.
Cumulative physical progress does not fall
below 80 percent of the cumulative target at
any given time.
Cumulative disbursement progress does not
fall below 80 percent of the cumulative target
at any given time.
Component B: Reconstruction and
Improvement of Multipurpose Shelters.
Increased protection for the vulnerable
population and livestock in the cyclone prone
areas during future disasters.
Number of newly constructed shelters with
improved design standards and connectivity
(such as access roads) with the community.
Total capacity of newly constructed shelters
with improved design standards and
connectivity (such as access roads) with the
community, as a percentage (%) of total
population in target communities.
Number of shelters repaired and improved
upon with improved connectivity (such as
access roads) with the community.
Total capacity of shelters repaired and
improved upon with improved connectivity
(such as access roads) with the community,
as a percentage (%) of total population in
target communities.Perception of beneficiaries of repaired shelters
regarding improvements in capacity and
proper water and sanitation facilities.
Component C: Rehabilitation of Coastal
Embankments.
Increased prevention of saline inundation
under normal weather and sustained crop
production made possible by reducing
cyclone damage.
Length of coastal embankments including
appurtenant structures rehabilitated and
upgraded with improved design standards,
and vegetative cover.
Number of polders with coastal
embankments (including appurtenant
structures) rehabilitated and upgraded with
improved design standards, and vegetative
cover.Total area of polders with coastal
embankments (including appurtenant
structures) rehabilitated and upgraded with
improved design standards, and vegetative
cover.Total area of polders currently protected from
saline water inundation by coastal
embankments (including appurtenant
structures) rehabilitated and upgraded with
improved design standards, and vegetative
cover; as a percentage (%) of total area of
polders previously inundated (before project)
by saline water under normal weather.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 108
Unit Reasons for
Variance /Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Remarks
1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr.
(Col. 1) (Col. 3) (Col. 4) (Col. 5) (Col. 6) (Col. 7) (Col. 8) (Col. 9) (Col. 10) (Col. 11) (Col. 12) (Col. 13) (Col. 14) (Col. 15) (Col. 16) (Col. 17) (Col. 18) (Col. 19) (Col. 20) (Col. 21) (Col. 22) (Col. 23) (Col. 24) (Col. 25) (Col. 26) (Col. 27) (Col. 28) (Col. 29) (Col. 30) (Col. 31) (Col. 32) (Col. 33) (Col. 34) (Col. 31) (Col. 32) (Col. 33)
D.1-1
a) Target nos 1
Actual nos 1
Variance: value nos -
% -
b) Target nos 1
Actual nos 1
Variance: value nos -
% -
c) Target nos 20 14 5
Actual nos -
Variance: value nos (20)
% (100)
d) Target % 5 5 5 10 20 20 20 5 5 5
Actual % 5 5 5 10 20 20 20
Variance: value % - - - - - - -
% - - - - - - -
D.1-2
a) Target nos 1
Actual nos 1
Variance: value nos -
% -
b) Target % 1
Actual %
Variance: value %
%
c) Target nos 5 5 5 5 10 10 10 10 15 15 5 5
Actual nos 5 5 5 5
Variance: value nos - - - -
% - - - -
d) Target 5 5 10 10 10 10 20 20 10
Actual 5 5
Variance: value - -
% - -
e) Target 5 5 10 10 10 10 20 20 10
Actual 5
Variance: value -
% -
f) Target 5 20 20 30 15 5 5
Actual 5
Variance: value -
% -
D.1-3
a) Target nos 8 46 22 6 33 20 46 75 32
Actual nos 8 46 22 6 33 20
Variance: value nos - - - - - -
% - - - - - -
b) Target % 1
Actual % -
Variance: value % (1)
% (100)
c) Target % 8 46 22 6 33 20 46 75 32
Actual % 8 46 22 6 33 20 -
Variance: value % - - - - - - (46)
% - - - - - - (100)
d) Target % 3 16 8 2 11 7 20 26 11
Actual %
Variance: value %
%
e) Target % 8 46 22 6 33 20 46 75 32
Actual % 8 46 22 6 33 20 -
Variance: value % - - - - - - (46)
% - - - - - - (100)
f) Target % 8 46 22 6 33 20 46 75 32
Actual % 8 46 22 6 33 20 -
Variance: value % - - - - - - (46)
% - - - - - - (100)
g) Target % 10 14 12 5 15 15 15 40 18
Actual % 10 14 12 5 15 15 -
Variance: value % - - - - - - (15)
% - - - - - - (100)
2014-15 2015-16 2016-17 2017-18
(Col. 2)
EXPECTED RESULTS INDICATORS
Values of Indicators
2009-10 2010-11 2011-12 2012-13 2013-14
Events will be
organized
after joining of
IDNA
Consultant.
%
%
%
(DMC-72 +
CPP-144 +
Simulation-
72)
CPP Training-
144 nos.
Establishment of Multi-hazard Risk and
Vulnerability Assessments and Mapping Cell
Multi-hazard risk vulnerability modeling and
management information system course
Capacity of DMB in respect of Planning,
Designing, Training and Implementation of
Disaster Risk Mitigation Measures:
Improved risk perception of DMC and CPP
members
Improved behavior of community towards
Cyclone signaling system.
Strengthened and enhanced emergency
preparedness in 12 severely cyclone
affected districts and upazilas.
DMCs at all levels are reorganized
Establishment of DNA Cell in DDM
International training of Master Trainers from
DMB and other departments
Design and implementation of Master Training
program at national level for DNA training of
concerned departments down to district and
Upazilla.
Capacity of DMB in respect of Planning,
Designing, Training and Implementation of
Disaster Risk Mitigation Measures:
Component D: Disaster Risk Reduction
and Management Program.
Disaster risk mitigation and reduction ability
of the Disaster Management Bureau
strengthened and enhanced.
Enhanced capacity of DMB for designing,
standardizing and implementing a post-
disaster DNA across all concerned
government deparments, and at various
administrative levels, down to the district
and upazila.
International Avance DM training of Master
Trainers from DMB and other department
DMC members can describe and explain the
adverse impact of disasters particularly
cyclone and are capacitated with their roles
and responsibilities in emergency response.
Capacity building of the multi-hazard risk and
vulnerability assessment, modeling and
mapping
Strengthening knowledge management for
multi-hazard
Generation of hazard mapping and
reproduction
Coordination among the DMCs and CPPs.
Multi-hazard mapping and vulnerability cell
created in DMB and detailed multi-hazard
models are used to generate maps.
Strengthening of the hazard information
system
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 109
Unit Reasons for
Variance /Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Jan-Mar Apr-Jun Jul-Sep Oct-Dec Remarks
1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr. 3rd Qtr. 4th Qtr. 1st Qtr. 2nd. Qtr.
(Col. 1) (Col. 3) (Col. 4) (Col. 5) (Col. 6) (Col. 7) (Col. 8) (Col. 9) (Col. 10) (Col. 11) (Col. 12) (Col. 13) (Col. 14) (Col. 15) (Col. 16) (Col. 17) (Col. 18) (Col. 19) (Col. 20) (Col. 21) (Col. 22) (Col. 23) (Col. 24) (Col. 25) (Col. 26) (Col. 27) (Col. 28) (Col. 29) (Col. 30) (Col. 31) (Col. 32) (Col. 33) (Col. 34) (Col. 31) (Col. 32) (Col. 33)
h) Target % 10 14 12 5 15 15
Actual % 10 14 12 5 15 15
Variance: value % - - - - - -
% - - - - - -
i) Target % 8 1 29 25 9
Actual % 8 1 -
Variance: value % - - (29)
% - - (100)
j) Target % 5 5 10 10 10 20 15 10 10 5
Actual % 5 5 10 10 10 20
Variance: value % - - - - - -
% - - - - - -
k) Target %
Actual %
Variance: value %
%
l) Target % 35 Bill board-35
Actual % -
Variance: value % (35)
% (100)
D.2-1 Target %
Actual
Variance: value
%
D.2-2 Target %
Actual %
Variance: value %
%
D.3-1 Target %
Actual %
Variance: value %
%
E-1 Target % - - - 100 - - - - - - - - - - - - - - - - -
Actual % - - - 100
Variance: value %
%
E-2 Target % - - - - - - - 100 - - - - - - - - - - - - -
Actual % - - - - - - - 100
Variance: value %
%
E-3 Target % - - - - - - - 100 - - - - - - - - - - - - -
Actual % - - - - - - - 100
Variance: value %
%
E-4 Target % - - - 5 - - - 20 - - - 25 - - - 25 - - - 25 -
Actual % - - - 5 - - - 20
Variance: value %
%
E-5 Target % - - - - - - - 25 - - - 30 - - - 30 - - - 15 -
Actual % - - - - - - - 25
Variance: value %
%
F-1 Target %
Actual %
Variance: value %
%
F-2 Target %
Actual %
Variance: value %
%
F-3 Target %
Actual %
Variance: value %
%
2017-18
(Col. 2)
2011-12 2012-13 2013-14 2014-15 2015-16 2016-17EXPECTED RESULTS INDICATORS
Values of Indicators
2009-10 2010-11
Simulation
exercise-72 nos.
The issue
revised/deleied as
per revised RDDP
Baseline level monitoring indicators
established.
Future national projects to reduce disaster
risk and damage prepared for public
investments.
Preparation of national RBIP completed.
Improved Logistic Support for effective
communication and response.
Preparation of national CEIP completed.
Preparatory studies for new disaster
shelters and upgrading of rural road
network completed.
CPPs are capable to render first aid services
and perform search and rescue operations.
Local community people are more capable to
respond to disaster through simulation
exercise.
Development of guidelines for livelihood
support in the community
Awareness development of disaster
preparedness messages through sign boards,
bill boards, paintings etc.
Project is well managed coordinated among
all implementing agencies and partners and
targets/outcomes achieved as planned.Cumulative physical progress do not fall
below 80 percent of the cumulative target
at any given time.
Cumulative disbursement progress do not
fall below 80 percent of the cumulative
target at any given time.
Financing and implementation
arrangements for disaster fund identified
and established.
Component E: Monitoring and Evaluation
of Project Impact.
Project outputs and outcomes are measured
and documented to best satisfaction of the
PCU.
M&E Consultant Team mobilized, takes on
responsibilities/tasks as described, and
prepares and submits required
deliverables.
Monitoring and evaluation
framework/strategy for ECRRP, developed
in collaboration with the PIAs, in place.
Component F: Project Management,
Technical Assistance, Strategic Studies
and Training, and Emergency Support for
Future Disaster.
Monitoring and evaluation of physical and
financial progress and performance,
project inputs, outputs, outcomes and
impacts
Review and assess environmental and
social development and safeguard
management aspects with respect to
ECRRP.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 110
RESULTS FRAMEWORK AND MONITORING
EMERGENCY 2007 CYCLONE RECOVERY AND RESTORATION PROJECT
Project Outcome
Indicators
Cor
e
D=Dropp
ed
C=Contin
ue
N= New
R=Revise
d
Unit of
Measur
e
Baseline
Results to
Date
(September
2016)
Cumulative Target Values Freque
ncy
Data
Source/
Method
ology
Responsi
bility for
Data
Collectio
n
2014 2015 2016 2017
1. Number of cyclone
affected population
benefitted due to
rehabilitation and
construction of protective
infrastructure (e.g.
embankments, disaster
shelters)
R Number 1.30 mill 2.33 mill 2.30 mill 2.90
mill
3.39
mill
4.36
mill
Quarter
ly and
annuall
y
Quarterl
y
impleme
ntation
progress
reports.
BWDB,
LGED,
PCMU,
M&E
consultan
ts
2. Number of cyclone
affected HHs whose
livelihoods have been
recovered due to
distribution of inputs,
technology and training.
R Number 0
Crops:
241,558
HH
Crops:
224,000
HH
Quarter
ly
Data
collectio
n under
M&E
FAO,M&
E
consultan
ts
Livestock:
37,928 HH
Livestoc
k: 33,000
HH
Fisheries:
37,089 HH
Fisheries
: 26,700
HH
3. Improved capacity and
preparedness for disaster
risk management in the
government (DDM) and
communities (DMCs)
R Text Limited
Capacity
Emergency
equipment in
use and
Early
Warning
System
(EWS) set
up
Emergenc
y
equipment
and EWS
in use
D-
Forms
updated
post-
disaster
and
used to
guide
funding
decision
s
Quarter
ly and
Annual
ly
Field
visits
and
Quarterl
y
progress
reports
DDM
Annex 8: Result Framework and Monitoring
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 111
Project Intermediate Indicators
Co
re
D=Dropped
C=Continue
N= New
R=Revised
Unit of Measure
Baseline
Results to Date
(September 2016)
Cumulative Target Values
Frequency
Data Source/Methodo
logy
Responsibility for
Data Collectio
n 2014 2015 2016 2017
Component A:
1. Number of Agriculture Equipment (Power tillers, Power threshers, Hand Sprayer) distributed
N Number 0 2,969 2,530 Quarterly Quarterly implementation progress reports
Data collection under M&E
Field visits
FAO, M&E consultants, PCMU
2. Improved rice seeds distributed
N MT 0 501 MT 500 MT Quarterly
3. Total fertilizers distributed N MT 0 6,894 MT 6,682 MT
Quarterly
4. Number of livestock (cow/buffalo, goat/sheep, chicken/ducks) distributed
N Number 0 240,681
280,500 Quarterly
5. Number of dairy production facilities (cattle sheds and portable poultry sheds) distributed
N Number 0 30,957 32,300 Quarterly
6. Number of Aquaculture packages (Carp, Golda,
N Number 0 24,850 24,850 Quarterly
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 112
Project Intermediate Indicators
Co
re
D=Dropped
C=Continue
N= New
R=Revised
Unit of Measure
Baseline
Results to Date
(September 2016)
Cumulative Target Values
Frequency
Data Source/Methodo
logy
Responsibility for
Data Collectio
n 2014 2015 2016 2017
Bagda+Tilapia) distributed
7. Mechanized fishing boats distributed
N Number 0 93 93
Quarterly
8. Number of Farmers‟ Field School (FFS) formed
N Number 0 2,848 2848 Quarterly
Component B:
1. Number of newly constructed shelters with improved design standards and connectivity with the community;
C Number 0 229 150 230 280 353
(WB‟s AM)
Quarterly
Quarterly implementation progress reports.
LGED, PCMU, M&E
Consultants
2. Numbers of shelters repaired and improved upon with improved connectivity (such as access roads) with the community;
C Number 0 408 280 320 400 460
(WB‟s AM)
Quarterly Field visits
Component C:
Length of coastal C Number 0 260 km 260 km 352 km 465 km 502 Quarterly Field BWDB,
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 113
Project Intermediate Indicators
Co
re
D=Dropped
C=Continue
N= New
R=Revised
Unit of Measure
Baseline
Results to Date
(September 2016)
Cumulative Target Values
Frequency
Data Source/Methodo
logy
Responsibility for
Data Collectio
n 2014 2015 2016 2017
embankments including appurtenant structures rehabilitated
completed;
188 km (ongoing)
km visits M&E Consultants, PCMU
Component D:
1. Number of emergency vehicles procured for effective communication and response to disasters
N Number 0 18 18 18 - - Quarterly and Annually
Quarterly implementation progress reports.
DDM
2. Detailed multi-hazard models are used to generate maps
N Text No map exists
- MRVA equipment procured
MRVA data collected
MRVA Maps and Atlas generated and used
MRVA Maps and Atlas generated and used
Quarterly and Annually
Quarterly progress reports.
3. Feasibility studies and bidding documents with detailed design for the preparation of future operations (CEIP, RBIP, MDSP) completed.
N Text No report -
Feasibility study of MDSP completed and design Consultant for
Feasibility study of RBIP completed and design Consultant for RBIP selected
Completion of preparation and study reports includi
Completion of preparation and study report
Quarterly and Annually
Quarterly implementation progress reports.
BWDB, LGED, PCMU
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 114
Project Intermediate Indicators
Co
re
D=Dropped
C=Continue
N= New
R=Revised
Unit of Measure
Baseline
Results to Date
(September 2016)
Cumulative Target Values
Frequency
Data Source/Methodo
logy
Responsibility for
Data Collectio
n 2014 2015 2016 2017
MDSP selected
ng design and bidding documents
s including design and bidding documents.
Component E:
1. Timely submission of quarterly & annual M&E reports N Text No report
18 Quarterly and 6 Annual progress reports submitted
18 22 26 30 Quarterly and Annually
Quarterly progress reports.
M&E Consultant, PCMU
2. Household survey completed at Baseline, MTR and once in every year thereafter.
N Text
Baseline survey done in 2010
HH survey report at MTR in 2012 and Project Evaluation Report in 2013 published. The next evaluation report will be due in December
4 4 5 5 Annual
Questionnaire and field visits
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 115
Project Intermediate Indicators
Co
re
D=Dropped
C=Continue
N= New
R=Revised
Unit of Measure
Baseline
Results to Date
(September 2016)
Cumulative Target Values
Frequency
Data Source/Methodo
logy
Responsibility for
Data Collectio
n 2014 2015 2016 2017
2014.
3. Timely submission of Implementation Completion Report
- - - 1
Component F:
1. PCMU to capture the results of the project components and submit report at MTR and at project closing. N Text
No results report
Results captured and report submitted
N/A N/A N/A
Final report
on results submit
ted
Twice
Annual implementation progress reports, filed visits. PCMU
2. Funding available for emergency response
C Text N/A N/A N/A N/A N/A N/A Quarterly and Annually
Quarterly progress reports.
Emergency 2007 Cyclone Recovery & Restoration Project (ECRRP), Component-E: Monitoring & Evaluation
Quarterly Progress Report – September 2016 P a g e | 116
Utilization - Local Consultancy Input in Man Months
(As per Revised Contract Agreement between PCMU & DPDS signed on 08.09.2016) (Up to end of September, 2016)
This
quarter
Key Professional Staff - Local
1 A.H.M. Mahbubur Rahman Team Leader, M&E Consultants 38.00 21.47 3.00 24.47 13.53
2Engr. Md. Matiur Rahman/ Engr. Md.
Bellal HossainCivil Engineer / M & E Specialist 35.00 20.00
,-20.00 15.00
3 Dr. Nazma B Ahmed Social Safeguard and Resettlement Specialist 8.00 6.00 - 6.00 2.00
4 Ahmed Al Farouq Environment Spcialist 5.00 5.00 - 5.00 -
Sub-total = 86.00 52.47 3.00 55.47 30.53
Other Local Staff
5 Md. Jahir Hossain Data Analyst 12.00 4.00 - 4.00 8.00
Sub-total = 12.00 4.00 - 4.00 8.00
Support Staff
6 Md. Nezam Uddin Manager, Office and Accounts 40.00 21.47 3.00 24.47 15.53
7 Md. Rajib Hossain Administration Support Officer 40.00 21.47 3.00 24.47 15.53
8 Md. Kamal Hossain Uzzal Office Assistant 40.00 21.47 3.00 24.47 15.53
Sub-total = 120.00 64.41 9.00 73.41 46.59
GRAND TOTAL = 218.00 120.88 12.00 132.88 85.12
No. Name Designation
Man Months
Contract Previous Cumm Balance
Annex 9: Utilization of Consultancy Inputs in Man-Months