government of india northern regional power committee … · government of india northern regional...

51
1 भारत सरकार उर ेीय विुत सविवत 18-, .जीत सह ि, कटिाररया सराय, नई दिली- 110016 Government of India Northern Regional Power Committee 18-A, S. Jeet Singh Marg, Katwaria Sarai, New Delhi-110016 No. . . वि. ./चालन/106/01/2017/3895-3935 दिनाक: 05.04.2017 सेवा : चालन समवय उपसममति के सदय To: Members of OCC विषय: चालन सििय उपसविवत की 133 ि बैठक का कायगिृत Subject: Minutes of 133 rd OCC meeting. चालन सििय उप-सविवत की 133 ि बैठक 15.3.2017 & 17.3. 2017 को, िशः नई दिली एिं लखनऊ ि, आयोवजत की यी थी। बैठक का कायगिृ उर ेीय विुत सविवत की िसाइट http://www.nrpc.gov.in पर उपलध है 133 rd meeting of the Operation Co-ordination sub-committee was held on 15.3.2017&17.3.2017 at New Delhi and Lucknow, respectively. The Minutes of this meeting have been up-loaded on the NRPC web-site http://www.nrpc.gov.in. हताररत / (हेिंत कु िार पांडेय) अधीण अवभयंता (चालन) फोन: 011-26521046 , 26868681 फै स: 011- 26865206 ई िेल: [email protected] िबसाईट: www.nrpc.gov.in

Upload: lamquynh

Post on 31-Aug-2018

225 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

1

भारत सरकार

उत्तर क्षते्रीय विद्यतु सविवत

18-ए, श.जीत ससह िार्ग, कटिाररया सराय,

नई दिल्ली- 110016

Government of India Northern Regional Power Committee

18-A, S. Jeet Singh Marg, Katwaria Sarai, New Delhi-110016

No. उ. क्ष.े वि. स./प्रचालन/106/01/2017/3895-3935 दिनाांक: 05.04.2017

सेवा में : प्रचालन समन्वय उपसममति के सदस्य । To: Members of OCC

विषय: प्रचालन सिन्िय उपसविवत की 133 िीं बैठक का कायगितृ ।

Subject: Minutes of 133rd OCC meeting.

प्रचालन सिन्िय उप-सविवत की 133 िीं बैठक 15.3.2017 & 17.3. 2017 को, क्रिशः नई दिल्ली एिं

लखनऊ िें, आयोवजत की र्यी थी। उक्त बैठक का कायगिृत्त उत्तर क्षेत्रीय विद्युत सविवत की िेब साइट

http://www.nrpc.gov.in पर उपलब्ध ह ै।

133rd meeting of the Operation Co-ordination sub-committee was held on

15.3.2017&17.3.2017 at New Delhi and Lucknow, respectively. The Minutes of this

meeting have been up-loaded on the NRPC web-site http://www.nrpc.gov.in.

हस्ताक्षररत /

(हिेतं कुिार पाडंये)

अधीक्षण अवभयतंा (प्रचालन)

फोन: 011-26521046 , 26868681

फैक्स: 011- 26865206

ई िेल: [email protected]

िेबसाईट: www.nrpc.gov.in

Page 2: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

2

Minutes of 133rd OCC meeting, held on 15th at New Delhi & 17th March 2017 at

Lucknow

133nd meeting of the Operation Coordination Sub Committee (OCC) of NRPC was

held on 15th March at New Delhi. & 17th March, 2017 at Lucknow . List of

participants is enclosed at Annexure-I.

1. Confirmation of Minutes:

The Minutes of the 132nd meeting of the OCC held on 16h and 17th Febuarary, 2017,

at New Delhi issued vide letter dated 8.3.2017 were confirmed by the Sub-

Committee.

2. Maintenance Programme of Generating Units and Transmission Lines:

2.1 Maintenance programme for Generating Units.

The maintenance programme for Generating Units for the month of April, 2017 was

discussed on 15.3.2017. The details of approved/deferred outages of generating

units as per deliberations in OCC has been issued vide letter no.3229-3269 dated

22.3.2017.

OCC advised all the generating utilities specially, hydro, to complete all the

maintenance related activities by April end, keeping in view ensuing peak demand

and high hydro season.

(Action : All generating utilities ; Timeline: by April,2017 end)

2.2 Outage programme for Transmission Elements.

The Outage programme of NLDC & NRLDC oversight transmission assets for the

month of March, 2017 was discussed on 16.2.2017. The details of approved/deferred

outages of transmission assets as per deliberations in OCC has been issued vide

letter no. 3229-3269 dated 22.3.2017.

OCC advised to complete all the transmission system maintenance related activities

by April end, keeping in view ensuing summer months, when it would be difficult to

allow shutdown.

(Action: All transmission utilities; Timeline: by April, 2017 end)

NLDC and NRLDC representative stated that on several occasions RVPNL had got

the shutdown approved in OCC but neither shutdown was availed nor was

information in advance given to NLDC /NRLDC for deferment of shutdown, due to

which outage request of other utilities affected. OCC advised RVPNL to apply

shutdown with proper planning, after consultation with other concerned utilities, so

that approved shutdowns are availed.

(Action: RVPNL)

Page 3: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

3

3. Planning of Grid Operation for April 2017:

3.1 Anticipated vis-à-vis Actual Power Supply Position (Provisional) for January,

2017:

SE (Operation), NRPC stated that there are much variations (i.e. > 5.0%) in the

Anticipated vis-à-vis Actual Power Supply Position (Provisional) for the month of

February 2017 in the terms of Energy requirement for Delhi, Haryana & Rajasthan

and in the terms of Peak demand for Haryana, HP, Uttrakhand & Rajasthan and in

terms of Peak Demand for Punjab & Rajasthan. The variation in anticipated and

actual energy requirement and peak demand was discussed and the reason, as

explained by Haryana, HP, Uttrakhand, Punjab & Rajasthan was due to unexpected

weather condition (i.e. high temperature/ low cold/ heavy rain/fog) and less demand

by Agricultural consumers in Uttarakhand during the month of February, 2017.

OCC expressed concern regarding sub-optimal demand estimates, as most of the

reasons mentioned by the constituents for variation were normally anticipated during

these months.

Members were advised to analyze and specify the reasons in detail, in case the

variation in demand or availability as compared to anticipated figures was more than

5%, and submit the same along with the provisional/revised Power Supply Position

Data (preferably along with form 29, provisional PSP data, by 2nd day of the next

month for the subject month) as well as in the OCC meeting, regularly.

(Action: All SLDCs; Time line: by 2nd / 15th day of every month)

3.2. Power Supply Position:

SE, NRPC stated that the provisional Power Supply Position and Notified Power Cuts

for the month of 1.2017 are available on CEA website.

All SLDCs were once again requested to furnish the provisional and final power

supply position in prescribed formats positively by 2nd and 15th day of the month,

respectively so that the same can be forwarded to CEA in time.

OCC advised all the members that the reasons regarding, demand not met/energy

not supplied, if any, must be specified in the report being submitted. It was also

advised that the reason for any substantial variation (more than 5%) in

demand/availability as compared to last month/year must be given along with the

PSP data.

(Action: All SLDCs; Time line: by 2nd / 15th day of every month)

4. Power Supply Position for NCR:

SE, NRPC stated that NCR Planning Board (NCRPB) is closely monitoring the power

supply position of National Capital Region. Monthly power supply position for NCR till

the month of November, 2016 is placed on NRPC website.

Page 4: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

4

Members were requested to submit the updated information on regular basis. (Action: SLDCs of UP, Haryana, Delhi and Rajasthan;

Time line: 15th day of every month)

5. Monitoring of schemes funded from PSDF(Agenda by NPC)

Representative of NPC stated that in the 6th meeting of NPC held on 19th December 2016, it was decided that all the RPCs in the monthly OCC meetings may follow up with entities to expedite completion of the scheme by giving due priority. The implementation of most of these schemes is based on the recommendation of the Enquiry Committee on Grid Disturbance of July 2012 headed by Chairperson, CEA. Therefore, timely implementation of these schemes would enhance the grid security and reliability.

Utilities were again requested in the meeting to submit the status of implementation

of the above schemes (physical as well as financial progress) on monthly basis, in

the prescribed format.

The details as available with NRPC Sectt. are enclosed Annexure- II.

The concerned utilities may submit the progress, physical and financial both, of

implementation of these schemes on monthly basis.

(Action: UPPTCL, PSTCL, HPSEBL, DTL, DHBVN/HVPNL, RVPNL;

Time Line: 10th Day of every month)

6. Information about variable charges of all the generating units in the Region.

As per decision taken in 103rd OCC meeting, all generating entities were required to

furnish the variable charges of their generating units on monthly basis to NRPC

secretariat. It was also decided that SLDCs would submit the variable charges of the

generating units located in their control area. The details of variable charges as

submitted by utilities from April to February 2017 are available on NRPC website.

All SLDCs and generating entities were requested to furnish the variable charges on

regular basis.

(Action: All SLDCs and Generating Entities;

Timeline: by 8th day of every month)

7. Sub-stations likely to be commissioned in next 6 months.

As decided in the 108th OCC meeting, utilities were requested to submit details of

substations at 220 KV and above level, likely to be commissioned within next 6 months

in the prescribed format.

The available status of the sub-stations to be commissioned by POWERGRID in the

states of NR and the status of down-stream assets of the concerned STU has been

uploaded on the NRPC website.

Page 5: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

5

In the meeting POWERGRID NR-1&2 were requested to update the status. They were

requested to update the information so that the downstream network in the states

could be monitored.

POWERGRID NR-3 had submitted the details of the Transmission Elements expected

to be commissioned in the next six months. The same is uploaded on NRPC website.

UPPTCL was requested to submit the status of the downstream network from the

POWERGRID sub-stations including Orai & Aligarh.

RVPN was also requested to submit the status of the downstream network from the

POWERGRID sub-stations including Ajmer & Chittorgarh situated in their state.

PTCUL updated the status regarding down-stream network from the POWERGRID

sub-station in their state which is available on NRPC website.

OCC advised all the members to expedite the down-stream network to ensure optimal

utilisation of transmission assets and to obviate system constraints.

(Action: POWERGRID NR-1&2, all transmission utilities; Time line: 05.04.2017)

8. Cleaning and Replacement of porcelain insulators:

The updated status as submitted by utilities regarding the cleaning of

insulators/replacement of porcelain insulators has been uploaded on the NRPC

website. All the members were requested to submit the progress of the work of

cleaning of insulators/ replacement of porcelain insulators in the previous month.

All the utilities including POWERGRID were again requested to specifically

submit the detailed status of Replacement of Porcelain Insulators as outages

for a number of lines had been taken for the insulator replacement work

during recent months.

(Action: All transmission utilities; Time line: 05.04.2017)

9. Recommendation of Enquiry committee for grid disturbances on 30th July, 2012

& 31st July, 2012:

Discussions on implementation of recommendations: Recommendations

pertaining to operational aspects made by the Enquiry committee for grid disturbances

on 30th July, 2012 & 31st July, 2012 are as under:

9.1 Healthiness of defense mechanism: Self- certification

(i) It was decided in the 27th meeting of NRPC held on 30th November, 2012 that all

STUs would ensure load relief as per target and settings of UFR and df/dt relays.

Mock exercise for healthiness of UFRs was to be carried out by utilities

themselves on quarterly basis and report was to be submitted to NRPC Secretariat

and NRLDC. Further, it was decided in the 31st meeting of NRPC held on

Page 6: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

6

24.7.2016 that the quarterly test report of UFR and df/dt would be uploaded on the

website of respective SLDC.

All utilities were stressed to maintain the healthiness of the UFR Relays in

view of the upcoming summer months. Also all utilities were asked to ensure

that the Report of testing ending March 2017 is submitted in the next OCC

Meeting.

(Action: All transmission utilities; Time line: 05.04.2017)

(ii) In earlier meetings, BBMB had informed that conversion of static relays into

numerical relays at 7 sub-stations (2 sub-stations in Punjab at Jamalpur & Sangrur

and 5 stations in Haryana at Panipat, Dhulkot, Kurukshetra, Jagadhari & Hissar)

by PSTCL and HVPNL was pending.The issue has been discussed in several

OCC meetings.

HVPNL, in this meeting, intimated that the procurement of new relays was in final

stage and the order will be placed by first week of April 2017. PSTCL informed that

the relay had been repaired and the same will be installed positively in the next

one week.

(Action: HVPNL, PSTCL; Time line: 05.04.2017)

(iii) On scrutiny of the UFR report ending June 2016, it was noted that the static

type UFRs were still installed on Transformers/feeders emanating from 132KV

Majra and Jwalapur Substations and 220KV Ramnagar, Roorkee and

Rishikesh Substations.

The matter is under discussions since many OCC meetings.

In this meeting, it was decided that PTCUL should expedite the work and submit the updated status and the target date for completing the work.

(Action: PTCUL; Time line: 05.04.2017)

9.2 Strengthening of Intra-State transmission system

Recommendation of the Enquiry Committee: “Intra-State transmission system

needs to be planned and strengthened in a better way to avoid problems of

frequent congestion.”

In the NRPC meeting held on 30th November, 2012, it was decided that SLDCs

should give half yearly feedback to STU regarding bottlenecks, constraints and

overloading in the State transmission network for proper transmission planning.

This exercise was to be completed by 10.10.2012 and thereafter repeated

regularly at half yearly intervals i.e. on 1st January and 1st July of every year. All

SLDCs were requested to submit copy of SLDC’s advice to their STUs, even if no

constraints were observed.

In the 132nd OCC meeting, it was noted that all utilities had submitted the

report ending December 2016. All the members were requested to submit the

Page 7: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

7

information regarding the action taken/action plan of the STU on the

feedback given by respective SLDCs. It was also deliberated that CEA may

be apprised of the SLDCs’ feedback for optimal planning of the network in

the respective States.

In this meeting, it was noted that UPPTCL, RVPNL and PSTCL had submitted

the information.

OCC was apprised that feedbacks of some SLDCs were sent to CEA for

considering in transmission planning. It was also deliberated that SLDCs

should give more details in feedbacks in line with the operational feedback

being submitted by NRLDC to planners.

OCC advised all the SLDCs to submit the next half yearly feedback with

more details in line with the feedback by NRLDC.

(Action: DTL, PTCUL, HPSEBL, HVPNL; Time Line: 05.04.2017)

9.3 Installation of adequate static and dynamic reactive power compensators.

9.3.1 Based on the studies carried out by POWERGRID for identifying compensation

required in intra-State network at 220 kV level, discussions in the 29th Meeting

of NRPC and subsequent discussion, reactors were to be installed at 9

locations, out of which 6 have been installed. The updated status of remaining

3 reactors are as under:

S.No. SUBSTATION MVAR Implementation

by

Updated Status in

133rd OCC

1 HINDAUN 125 RVPNL Expected by

31.04.2017.

2 MANESAR 125 POWERGRID Expected by

30.04.2017

3 MERTA 125 RVPNL Expected by

31.06.2017

9.3.2 Study by POWERGRID for reactive compensation at 220 kV level:

The proposal for installation of bus reactors at 12 nos. 400 kV and 17 nos. 220

kV sub-stations was discussed in the 29th meeting of NRPC held on 13th

September 2013. After deliberations, NRPC had approved installation of

reactors at 400 kV sub-stations of POWERGRID and RVPNL. As regards 220kV

bus reactors, POWERGRID had stated that the requirement would be firmed up

in consultation with the States. Subsequently, POWERGRID, vide email dated

30.09.2016 had submitted report of the study. In this report, reactors at 13

locations at 220 kV levels and at 24 locations at 400 kV level had been

proposed.

Page 8: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

8

The report was discussed in 34th TCC/38th NRPC meeting held on 24th /25th

October, 2016 wherein Delhi had requested to review the system study for its

system. POWERGRID agreed for the same. Subject to review of requirement for

Delhi, NRPC approved the report.

In this meeting, Delhi representative informed that the review would be

completed by 31.3.2017.

On the query raised by some utilities regarding quantum of reactive

compensation required, keeping in view recent installation of reactors, it

was clarified that the data for study by POWERGRID was taken from

respective utilities. Thus, utilities should be aware that, which reactor has

been taken into account in the study. It was also emphasized that the report

had already been approved by TCC and NRPC in October,2016. There

should not be any doubt regarding the reactors proposed in the study

report by POWERGRID. It was suggested that in case of any query

regarding the report, the concerned utility should directly take up with

POWERGRID.

OCC advised all the members to submit action plan for installation of

reactors, as approved by NRPC, at the earliest.

(Action: POWERGRID, UPPTCL,DTL,PSTCL, RVPNL,PTCUL;

Time Line: 05.04.2017)

10. System Protection Schemes (SPSs) in Northern Region:

10.1 SPS for Interruption of import by NR at 765 kV Agra (from WR).

Review of SPS for 765 kV Agra-Gwalior line

The revised SPS for contingency of 765 kV Agra-Gwalior was approved in 32nd

TCC/36th NRPC meeting held on 23rd /24th December, 2015. It was also agreed

in the 36th NRPC meeting that POWERGIRD would implement the revised

scheme within 06 months after the receipt of the feeder details from the states.

In the 129th OCC POWERGRID stated that the scheme would be commissioned

by 31.05.2017.

In the 132nd OCC meeting representative of POWERGID proposed that provision

of AMC of the scheme for 05 years could also be included in the scope of the work

for implementation of the revised scheme. Members agreed to the proposal of

POWERGIRD.

The representative of POWERGRID further stated that the cost of implementation

of revised SPS for 765KV Agra-Gwalior lines could be booked in any ongoing

project/ work of Northern Region. SE (O), NRPC stated that the same had already

been recommended by OCC in its 129th OCC meeting. POWERGRID

representative informed that they were waiting for NRPC approval in this regard.

After detailed deliberation it was decided that keeping in view urgency of the work,

POWERGRID should carry out tendering activities for timely implementation of the

Page 9: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

9

revised scheme. The recommendation of the OCC would be put up for

concurrence of NRPC in next meeting.

Representative of POWERGRID stated that it may not be possible to adhere to the

commissioning schedule agreed in 129th OCC meeting. Members were of the

opinion that in view of the criticality of the scheme POWERGRID should strive to

complete the commissioning of the scheme.

In this meeting, POWERGRID representative stated that tendering activities

were in process. The POWERGRID representative submitted that as the

tendering process takes time, the implementation would be done till

August/September 2017. NRLDC representative stated that all out efforts

should be made to complete the work before Paddy season, as per earlier

schedule of implementation.

( Action: POWERGRID; Time line: May,2017)

In the 132nd OCC meeting, it was informed that during the mock testing of this

SPS, at Jamsher the signal was received but the counter did not increase.

In this meeting, POWERGRID representative submitted that the needful

action has been taken at Jamsher.

Regarding mapping of feeders identified for the SPS load relief, in SCADA, it was

noted that there was no progress. OCC advised all concerned utilities to take

action in this regard at the earliest and inform the action taken/Action Plan.

(Action: All STUs; Time line :05.04.2017)

UP representative raised issue of DTPC defect at Muzaffarnagar.

POWERGRID representative stated that the issue would be looked into and

would be resolved shortly.

(Action: POWERGRID; Time line :10.04.2017)

10.2 SPS for ICTs at 765 kV Unnao sub-station:

A discussion was held on 06.05.2015 in NRPC secretariat with the officers from

UPRVUNL in the presence of officers from NRLDC, POWERGRID and NRPC sect.

UPRVUNL was briefed about the basic philosophy along with the hardware

requirement of the System Protection Scheme (SPS) for evacuation of Anpara-D

generation. It was agreed that UPRVUNL along with UP SLDC would prepare the

SPS for safe power evacuation of Anpara-D. Further the scheme would be

submitted to the OCC for approval. Thereafter, the matter was under discussion in

various OCC meetings without much progress.

As decided in the 121st OCC meeting, the scheme was to be implemented by

UPPTCL.

In 34th TCC/38th NRPC meeting held on 24th /25th October, 2016 UPPTCL informed

that LOA would be placed on 25.10.2016 and scheme would be implemented in 03

months thereafter.

Page 10: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

10

Representative of UPPTCL intimated in this meeting that the scheme will be

implemented by 15.4.2017.

(Action: UPPTCL; Time line: 15.04.2017)

10.3 SPS for Kawai-Kalisindh-Chhabra generation complex:

SPS for Kawai-Kalisindh-Chhabra generation complex recommended in 122nd OCC

meeting held on 22nd April, 2016. RVPNL, vide email dated 26.07.2016 has confirmed

that the SPS for Kawai-Kalisindh-Chhabra generation complex has been put into

operation. However, it is understood that the automatic load shedding recommended in

part (c) of the scheme has not been implemented by RRVPNL. The scheme was

discussed in 34th TCC/38th NRPC meeting held on 24th/25th October, 2016 wherein

RRVPNL stated that feeders have been identified and the scheme would be completed

by March 2017.

In the 129th OCC representative of Rajasthan intimated that, the part of the scheme

related to load shedding would be completed by March, 2017.

In 131st OCC, representative of RVPNL intimated that load shedding part of the

scheme has been installed on trial basis for 100MW load. Mock testing of the SPS

would be done for the shortlisted load and if successful the scheme would be extended

for complete 700 MW load.

OCC had advised RVPNL to implement the SPS scheme for the identified load at the

earliest and submit the report to NRLDC and NRPC Secretariat.

In this OCC meeting, representative of RVPNL submitted that the administrative

approval for implementation of the Automatic Load shedding for identified

feeders have been obtained and the NIT for the work would be floated soon.

As regard revision in SPS scheme after commissioning of Chhabra stage - II

(Unit 5), RVPNL representative stated that the same is under consideration and

information in this regard would be submitted shortly.

(Action: RVPNL; Time Line: 10.04.2017)

11. System Study for Capacitor Requirement in Northern Region for the year 2016-

17 and 2017-18.

The matter was discussed in 34th TCC and 38th RPC meetings, held on 24th & 25th

Oct, 2016. It was decided that LOA should not be cancelled and the study should be

carried out for the year 2017-18 and 2018-19 through CPRI. It was also decided that

all the states would submit the data by 31.10.2016 for carrying out study for the

period 2017-18. Subsequently, the data would be submitted for carrying out study for

2018-19.

OCC was again apprised that data for 2017-18 had been received from all the

utilities and the same was already sent to CPRI. It was also informed that CPRI

Page 11: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

11

had sought some clarification regarding UPPTCL data, due to which CPRI

could not carry out study. Matter was taken up by NRPC Sectt. with the

concerned UPPTCL officials, but the information was pending. In the meeting,

UPPTCL representative assured that the requisite information would be sent to

CPRI on the same day.

(Action: UPPTCL; Timeline: Immediate)

With regard to data for capacitor Study for 2018-19, it was noted that the same

had been received from Haryana, Rajasthan, Punjab and Himachal Pradesh.

OCC directed PTCUL, UPPTCL & DTL to submit the information for the year

2018-19, at the earliest, so that study would be carried out by CPRI.

( Action: PTCUL, UPPTCL & DTL; Timeline: Immediate)

12. Status of data trough Automatic Meter Reading (AMR)

In the 13th NRPC meeting held on 27th June 2009, scheme of Automatic Meter

Reading from Interface Meters in Northern Region was approved. He added that in

last OCC meeting, it was decided that NRLDC and POWERGRID would submit the

joint status report of AMR at the end of every month.

In the 34th TCC meeting, held on 24th Oct, 2016, NRLDC stated that out of 1235

interface meters, data from 973 meters was being received. Further, Site Acceptance

Test (SAT) was completed and data through AMR was being regularly used by

NRLDC for 764 interface meters. POWERGRID informed that the data from all the

meters will be available by January 2017. TCC and NRPC expressed concern over

tardy progress of the implementation of AMR.

The issue is being discussed regularly in OCC meetings.

In the 132nd OCC meeting, POWERGRID informed that the work would be completed

by March 2017.

POWERGRID updated that the work is targeted to be completed by April 2017.

(Action: POWERGRID; Time line:30.04.2017)

13. Planning, procurement and deployment of Emergency Restoration System.

The issue was discussed in the 33rd meeting of NRPC held on 11.11.2014 and it

was suggested that CEA should evolve guidelines regarding ERS. Later, Secretary

(Power), GoI vide letter dated 05.12.2014 addressed to Chief Secretaries of all the

states had requested to issue directions to transmission utilities / transmission

licensees to procure adequate number of Emergency Restoration Systems. The

guidelines formulated by CEA for planning, procurement and deployment of

Emergency Restoration System were also enclosed with that letter. Copy of the

aforesaid letter was enclosed as Annexure-VIII to the agenda notes of 30th TCC &

34th NRPC meetings held on 19th & 20th March, 2015.

The matter was discussed in 34th TCC and 38th RPC meetings, held on 24th & 25th

Oct, 2016.

The latest status as updated by the members in this meeting is as under:

Page 12: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

12

DTL:-Order had been placed for 02 nos. of ERS. Supply expected by May, 2017.

PSTCL:- The tendering under process.

UPPTCL:-Order for 02 nos. of ERS has been placed. Supply is expected by

25.03.2017.

RRVPNL:-Proposal pending with management.

HVPNL:-In place of ERS, spare towers worth Rs. 2 Crore would be procured. PO

issued in this regard.

PTCUL-Tender is under process.

HPSEBL –For exploring potential use of ERS in hilly state like H.P., vendors were

invited but there was no response

BBMB:-Partner states have agreed to provide the ERS as and when required by

BBMB.

OCC noted the information.

14. Targets fixed for Load Relief from operation of df/dt & UFR relays in Punjab –

Review thereof

This agenda item was brought in the 127th OCC meeting by PSTCL. In short, PSTCL

had contended that variation in their load from summer to winter was such that they

were not in a position to meet targets of automatic load shedding under UFR, df/dt

and SPS.

In the 127th OCC meeting, it was informed that the issue was deliberated in 5th NPC

meeting held on 05.04.2016 wherein it was decided that it would suffice if NR as a

whole is able to meet the desired load relief. It was decided that to work out the

same, a format would be circulated to submit the load data of the feeders where UFR

based load shedding scheme have been installed. For submission of data two typical

scenarios of July and January were to be taken. Accordingly, the format was

finalized and SLDCs were requested to furnish the information regarding automatic

load shedding under UFR scheme in the prescribed. The format was enclosed at

Annex – XII of the minutes of 127th OCC meeting

The matter was under discussion in OCC meetings. It was noted that PSTCL has

submitted the data whereas other utilities were asked to submit the requisite data.

In this meeting, it was noted that Punjab, Haryana, Rajasthan and Himachal

had submitted the information. The remaining utilities were requested to

expedite the submission of the data positively by 31.3.2017.

(Action: DTL, UPPTCL,PTCUL; Time line:31.3.2017)

Page 13: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

13

15. Transmission System Outage planning up gradation:

In the 130th OCC meeting, SE, NRPC stated that NRPC Secretariat was in the process of upgrading the Transmission System Outage Planning (TSOP) Software. The existing data was uploaded on the website htpp://www.nrpc.gov.in/meetings/OCC/Transmission lines.pdf. All utilities were requested to review the data and inform the NRPC Secretariat regarding any discrepancy or any addition in the data. It was also informed that the list of substations in NR System as received from NRLDC had been uploaded on the NRPC website at htpp://www.nrpc.gov.in/meetings/OCC/List of substations NR.pdf. All the utilities concerned were requested that the details of the elements e.g. ICT, Bus and Reactors in these substations may be provided to this office so that these elements can be included in the TSOP software. All utilities were requested to ensure that the updated data is submitted by 31.3.2017, positively. It was also deliberated that if data is not provided by the utility, then OCC would not discuss the outage.

(Action: All Transmission Utilities; Time line: 31.03.2017)

16. High Transmission Losses in Northern Region:

In the 131st OCC meeting NRLDC informed that weekly average transmission losses of

Northern Region were increased substantially, as compared to normal range of 3 to

4% . The probable reasons for such high transmission losses could be due to various

reasons including incorrect CT/PT ratios of the meters and/or non-incorporation of

some drawl points in the metering / SCADA system of NRLDC. The state-wise list of

meters at drawl points along with their C.T./ P.T. ratio were enclosed as Annex-AA of

131st OCC additional agenda. All utilities States were requested to examine their

transmission losses, CT/PT ratio and drawl points within their jurisdiction and submit a

report to NRLDC and NRPC secretariat by 31.01.2017.

PSTCL submitted the report.

OCC requested that all other utilities should submit report even if everything is

found to be in order, within 15 days positively.

17. Certification of Non-ISTS line for inclusion in PoC Charges

Central Electricity Regulatory Commission (Sharing of Inter State Transmission

Charges and Losses) (Third Amendment) Regulations, 2015 provides as under:

“Certification of non-ISTS lines carrying inter-State power, which were not

approved by the RPCs on the date of notification of the Central Electricity

Regulatory Commission (Sharing of Transmission Charges and Losses)

Regulations, 2009, shall be done on the basis of load flow studies. For this

Page 14: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

14

purpose, STU shall put up proposal to the respective RPC Secretariat for

approval. RPC Secretariat, in consultation with RLDC, using WebNet Software

would examine the proposal. The results of the load flow studies and

participation factor indicating flow of Inter State power on these lines shall be

used to compute the percentage of usage of these lines as inter State

transmission. The software in the considered scenario will give percentage of

usage of these lines by home State and other than home State. For testing the

usage, tariff of similar ISTS line may be used. The tariff of the line will also be

allocated by software to the home State and other than home State. Based on

percentage usage of ISTS in base case, RPC will approve whether the

particular State line is being used as ISTS or not. Concerned STU will submit

asset-wise tariff. If asset wise tariff is not available, STU will file petition before

the Commission for approval of tariff of such lines. The tariff in respect of these

lines shall be computed based on Approved ARR and it shall be allocated to

lines of different voltage levels and configurations on the basis of methodology

which is being done for ISTS lines.”

Accordingly, it was decided in 31st TCC/35th NRPC meeting held on 08th /09th July,

2015 to constitute a group to recommend a methodology for the study to be

conducted by NRPC Secretariat, in consultation with RLDC. Based on the

methodology suggested by the group, the study is to be carried out every year for

certification. The study for certification of the non-ISTS lines for 2017-18 was carried

out for UP, Haryana and Rajasthan.

The transmission lines, which fulfill the criteria recommended by the group and are to

be recommended for certification as ISTS for the current Financial Year 2017-18 by

NRPC Secretariat are listed below:

S. No.

Name of Transmission Line Owner STU

1. 220KV PGCIL Panchgaon-Mau D/C line HVPNL

2. 400KV NTPC Jharli-Daultabad D/C line HVPNL

3. 400KV Sec-72 PGCIL-Daultabad D/C line HVPNL

4. 400KV CLP(Jhajjar)-Dhanonda D/C line HVPNL

5. 400kV S/C Jodhpur-Merta Line-I RVPN

6. 400kV S/C Jodhpur-Merta Line-II RVPN

7. 400kV S/C Merta - Ratangarh Line RVPN

8. 400kV S/C Merta - Heerapura Line RVPN

9. 220kV D/C Aau – Baithwasia Line RVPN

10. 220kV D/C Baithwasia – Bhawad Line RVPN

11. 220kV D/C Badisid- Aau Line RVPN

Page 15: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

15

12. 220kV S/C Bhadla- Bap Line RVPN

The complete list of transmission lines submitted by STU can be sub-divided in

following categories:

(i) Transmission lines, which fulfill the criteria recommended by the Group and

hence are recommended to be certified as ISTS.

(ii) Transmission lines, which do not fulfill the criteria recommended by the Group

and hence may not be certified as ISTS.

(iii) The lines, which were claimed to be used for inter-state transmission by STUs

but were not modeled in the PoC transmission charge calculation and hence

exercise to see whether or not these lines carry inter-state power could not be

carried out. It may be mentioned that the responsibility to submit the requisite

details for modeling the lines in PoC transmission charge study rests with STU

concerned.

(iv) The transmission lines which are natural inter-state lines and hence need not to

be certified as ISTS by RPC.

The complete category wise list of transmission lines submitted by STUs was

enclosed at Annex- I of the Agenda of this meeting.

UP representative raised the issue of non-certification of 400 kV Sultanpur-PGCIL

(Kursi Road) line for which the average utilization by the States other than UP was

49.9%. It was clarified that as per the agreed methodology , for qualification as ISTS,

average utilization by other states should be more than 50%. Thus, this line did not

meet the criterion.

Up representative had also raised the issue of certification of STU lines being used to

deliver share of other states from ISGS embedded in UP. He cited following provision

in Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges and

Losses) (Third Amendment) Regulations, 2015:

"(vii) In case an ISGS is connected only to STU network and the shares of the beneficiaries of

the said station are being delivered through the STU network, such a line of the STU network

shall be considered as an ISTS for the purpose of these regulations.”

After detailed deliberations, OCC decided that since, as per CERC Regulations, such

lines are to be considered as ISTS, these lines do not come under the purview of

RPC for certification as ISTS lines.

Rajasthan representative had raised that some of the lines, which were proposed for

certification by them, were not included in the list given in the Agenda. On a query,

he assured that details would be provided to NRPC Sectt.

Page 16: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

16

OCC after detailed deliberation recommended for approval of NRPC the non-

ISTS lines mentioned in the table given above, for certification as ISTS lines for

the year 2017-18.

18. Review of Grid Operations for last month (Feb2017)

Representative of NRLDC made a presentation on grid operation during Feb, 2017

and highlighted the following:-

Frequency of the grid remained within the normal band 73.98% of the time during February, 2017 which is better than last year during same month (February, 2016) when frequency (within normal band) remained 70.65 % of the time. It was emphasized that since almost a year now (except for few days), % of time operation of grid in normal band is remaining only about 70% of time ,therefore NRLDC again requested all utilities to take concerted efforts to further improve the frequency regime through various measures viz. staggering of load connection/disconnection, better scheduling, keeping reserves and effective primary response by the generators etc.

Maximum load met & minimum load met for the region during February, 2017

was 43481 MW and 26009 MW respectively. The maximum and minimum

frequencies were 50.27 Hz and 49.77 Hz., respectively.

Average consumption of the Region for February, 2017 increased just by 3.84% of corresponding month in previous year.

Average Thermal generation in February, 2017 was decreased 3.89% (21 MU/Day) of corresponding month in previous year.

Average Hydro generation in February, 2017 increased by 13.93% (15MU\day) of corresponding month in previous year

Average nuclear generation in February, 2017 increased by 4.08 MU/day as compared to corresponding month in previous year.

Average renewable generation in February, 2017 increased by 3.42 MU/day as compared to corresponding month in previous year.

Net Average Inter-Regional import was increased by 30.21 MU/day during February, 2017 as compared to corresponding month in previous year.

Net Average Import from remained same in February, 2017 as compared to corresponding month in previous year.

Net Average Import from ER increased by approx. 40.62 MU/day during February, 2017 as compared to corresponding month in previous year.

Net Average Export to NER was 10 MU/day during February, 2017. Total availability during February 2017 was 893.04MU/day. Total outages during Feb, 2017 were 491 including Planned S/downs (280) and

Forced Shut /downs (Trippings-145+Emergency S/Ds-66). Different 765/400 kV Transmission lines were manually opened/ tripped

(971times) on high voltage conditions during February, 2017. The difference between data, received from SCADA and SEM in terms of %age

was shown as Haryana (0.33) Punjab (1.72), Rajasthan (4.25), Delhi (5.9), Uttrakhand (1.05), UP (1.41) & UT Chandigarh (2.46). Rajasthan was advised to look into the matter.

Page 17: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

17

Maximum deviation was observed in HP followed by Uttrakhand, UP and Haryana during February, 2017.These utilities were requested to review their load and accordingly minimize their deviation.

The load pattern of the states in which elections held, were discussed. It was noted that in some states there was substantial load reduction on the day of election. It was suggested that States may analyse such events and use the results in fine tuning the load forecast during such special days, which would help states in managing the load-generation balance.

Transmission losses since week no. 35 were quite high. All utilities were requested to review their transmission losses, drawl point and CT/PT ratio. All utilities were again advised to look into the matter and report so that the reasons can be analyzed.

Number of transmission element trippings, for POWERGRID followed by UP, and Rajasthan, were high. The OCC advised the representative of these transmission utilities to look into these and take necessary action to reduce such tripping.

The details of the Generating Stations and Transmission Elements that are in

Long Outage were also discussed (ANNEXURE-B). All the concerned utilities

were requested to update the target date by which these generating units

/transmission elements would be operational.OCC advised concerned

utilities to bring back these elements at the earliest.

Some constituents were uploading data for estimated demand, regularly, on

FTP server of NRLDC, while some constituents were not uploading data

regularly or sending in different formats. All SLDCs were requested to upload

the data regularly on the server.

As discussed during 130th OCC meeting, the usage of space technology could

be very helpful for power sector and all constituents should make use of it.

Ministry of Power (MoP) is also putting lot of emphasis on the utilization of

space technology data. Some of these decisions at MoP level are as follows:–

All Power Sector Organizations were directed to prepare specific target

oriented projects along with timelines and expected outcomes.

Directive is for all Ongoing projects as well as new emerging areas

POWERGRID is nodal agency for compilation of Road Maps and onward

Submission to MOP.

MOP to monitor the progress of achievement.

Silt Level forecast in Hydro Power Plants.

Disaster support services to Ministry of Power

Contact Person in NRSC, ISRO Hyderabad: Dr. C. S. Jha 9392048008

OCC again advised all utilities to take advantage of above and take help in inflow, silt forecasting for hydro stations as well as load forecasting based on weather conditions.

The list of elements charged in the month of February 2017 is placed at ANNEXURE-C.

Page 18: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

18

19 .Summer Preparedness – 2017

In view of coming summer month, which is peak demand period of Northern region,

OCC discussed about the load generation balance planning of all the state

constituents during upcoming summer month. NRLDC stated that with the

temperature rise, load would start picking up and respective line loading, Voltages,

frequency, drawl from the grid should be kept within operational limits to maintain

the grid security.

OCC advised all entities to start summer preparedness and suggested that all the

utilities should formulate their action plans for following:

• Change in load-generation balance

• Skewed load profile

• Voltage profile,

• Inter-regional exchanges

• Import capability of state control areas,

• Weather beating load (higher loads)

• Thunder Storm/dust storm leading to Load crash, tower collapse etc.

• Managing outage of plants due to Silt conditions

The detailed agenda on above points was discussed during 132nd OCC meeting

wherein all the entities were requested to share the action plans, preparations and

related information on the above for discussion and adaptation.

19.1 Power Supply Position

OCC discussed that as load of Northern region remain highest during

summer/monsoon, load generation balance/Power supply position planning on

monthly basis is very crucial for grid management.

OCC directed all the state to forecast the load and availability during the

summer month as under:

Load forecast (Peak & off peak)

Own generation availability

Availability from Central sector generating stations, banking &

bilateral arrangements

Short term arrangements

Shortages, if any

In the OCC meeting the last year Demand profile vis-à-vis the expected

Demand scenario worked out by NRLDC was also discussed. The

Page 19: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

19

anticipated Power Availability and shortages for different states was also

highlighted. It was emphasised that the states of UP, Punjab, J& K and

Haryana may experience shortage of power. It was deliberated that

advance planning should be done to meet the demand these states.

All the states utility of Northern region were advised to anticipate its load for

upcoming month, availability of own generation, short term arrangements etc.

and share the respective action plan for meeting the projected load. It was

deliberated that in view of Power availability and various short term products,

load forecasting has become pre-requisite for all states to manage their

portfolio. Hence, focus should be on forecasting, network congestions, network

adequacies etc.

Maximizing the internal generation in view of foreseen congestion of inter-

regional corridor: Import from WR used to be higher and the import capability

from WR is limited. In case of summer scenario, as the load of northern region

increases, import also increases. Therefore, in order to reduce the congestion

on inter-regional corridor, keeping machines on bar within NR and maximizing

internal generation as and when required is necessary. Gas diversion to NR is

also part of increasing the internal generation within NR.

OCC advised all utilities to take necessary steps to ensure maximizing of

Internal Generation to reduce the congestion on inter-regional corridor. It

was emphasized that maintaining load-generation balance and grid

security should be given priority over financial issues.

19.2 Maintenance of reserves: Sudden outage of large hydro on silt, or tripping of

large generating station of state control area or tripping of regional entity

generator, some sort of reserves should be maintained to balance the load

generation of the region.

OCC directed all utilities to take necessary steps for following:

. Maximizing the internal generation & Maintenance of reserve

. Keep the optimum generation on bar

.Ramp up/down the generation as and when required

19.3 Assessment of respective state control area TTC/ATC: It was deliberated

that in line with CERC regulation and procedures on congestion management,

state control area should compute its import capability in co-ordination with

NRLDC. In view of peak demand scenario of NR and skewed loading, all the

states were requested to assess its state control area TTC/ATC for upcoming

summer month in advance in following manner:

i. Updating of base case

Page 20: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

20

Projected load generation balance

New element that has been commissioned & synchronized

Network configuration (line kept opened, Bus split etc.)

ii. Assessment of TTC/ATC & RM as per CERC approved methodology

iii. Report stating TTC/ATC, Constraints

iv. Action plan for the constraints observed

NRLDC presented the TTC/ATC of respective state control areas as per the data

available at NRLDC. TTC/ATC of the state of NR and the constraints for summer

scenario is given below:

S.No. State TTC/ATC (MW)

Constraints observed

1 Punjab ~6400 N-1 contingency of Amritsar, Ludhiana, Makhu, Dhuri ICTs.

2 Haryana ~6500 N-1 contingency of Kaithal. Gurgaon ICTs, 220kV network around Hisar; Hisar(PG)-Hisar(IA) &220kV Charkhi Dadri-Lula Ahir

3 Rajasthan ~6200 N-1 contingency of Sikar, Jodhpur, Merta ICTs. N-1 contingency of 765/400kV Phagi ICTs, 400kV Bassi-Phagi ckts

4 Delhi ~4800-5050 N-1 contingency of Mundka, Bamnoli, Harshvihar ICTs and its underlying 220kV network

5 Uttar Pradesh

~7500 N-1 contingency of Agra (UP), Mainpuri (PG), Meerut (PG), Muradnagar(UP), Sultanpur(UP) and underlying network. 400/220 kV Gr. Noida: Underlying 220kV network. Low voltages: 400kV Agra (UP), Muradnagar (UP), Muradnagar New(UP), Sultanpur & several 220kV nodes.

6 Uttarakhand ~1600 N-1 contingency of Kashipur and 220kV lines of Roorkee interconnection, Baikunthpur-Panthnagar etc.

7 Himachal Pradesh

~1050 N-1 contingency of 220 kV Madanpur-Kunihar leads to the overloading of 220 kV Baddi-Kunihar. Loading on 220/132 kV Kunihar, Hamirpur and Jassore ICTs

Page 21: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

21

8 Jammu & Kashmir

~1800 N-1 non-compliance of Wagoora ICT, underlying 220kV network of Wagoora, Kishenpur)

The TTC/ATC of each state and the constraints in the state network were

discussed in detail.

OCC advised all members to calculate the TTC/ATC for respective state and share

with NRLDC as well as NRPC Sectt.

(Action: All STUs/SLDCs; Time line 31.03.2017)

It was also advised that action plan must be prepared by all SLDCs to maintain

load-generation balance, in consultation with Discoms and STUs, considering the

available ATC and the constraints in the State network and submit to NRLDC and

NRPC Sectt.

(Action: All SLDCs; Time line: 10.04.2017)

All the State utilities were advised to limit the drawl from grid within the ATC limits.

19.4 Weather Monitoring & Load forecast

NRLDC representative stated that Weather monitoring is an important factor in

estimating the load forecast in both short term / long term period. Monitoring of

weather information therefore also help in better load portfolio management.

OCC advised that apart from IMD website links, temperature and humidity

telemetry from various substations should be monitored at SLDCs for better

information of local area weather. (ANNEXURE-E).

OCC also suggested all the users to explore the available tools e.g. weather

monitoring website/link, historical weather information and respective load,

SCADA telemetry of temperature and humidity etc. in assessing the load

behavior/load pattern of respective state control area.

It was highlighted that in the last summer season 4 events of Load crash in NR

had occurred. During these events the load crash was to the tune of 8500 MW

to 15000 MW and 15-41 EHV lines had tripped.

To deal with thunder storms/dust storms, load crash following actions were

discussed and agreed upon:

1. Backing down of generation in minimum possible time.

2. Identification of 11kV feeders that can remain connected during

thunderstorm/wind storm, in line with decision in the meeting dated 23rd June

2016, taken by JS,MoP.

3. Avoiding manual tripping of distribution feeder or LV lines.

Page 22: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

22

4. Strengthening of transmission lines towers.

5. Keeping Emergency Restoration System (ERS) ready for any eventuality.

OCC expressed concern regarding delay in identification of 11 KV feeders

that can remain connected during such eventualities, in spite of repeated

requests. OCC advised all the SLDCs to identify such feeders in

consultation with respective DISCOMS and submit the details to NRLDC

and NRPC Sectt latest by 31.03.2017.

(Action: All SLDCs & DISCOMS; Time line: 31.03. 2017).

19.5 Hydro Generation and Silt monitoring

OCC discussed optimal utilization of hydro generation during summer as it is

known, that most of the hydro station of NR are snow fed and inject its peak

generation during summer/Monsoon scenario. In view of above, OCC

recommended that any kind of maintenance in Generating

station/Units/associated transmission line etc. should be completed at the

earliest.

As already discussed in previous OCC meetings, it was again stressed that

following action should be taken by respective agencies:

Actions by Generator

• Better forecasting and silt monitoring

• Avoid sudden shut down of generation

• Reduction of Generation/Tripping of Units as per protocol

(Staggering of generation outage)

Actions by SLDC/Constituents

• Generation reserve to be maintained

Hot Reserves

Cold reserves

Contracted Generation from Other surplus entities/Traders

• Load management to be planned

• Silt forecasting with the help of ISRO

19.6 Reactive Power Management

NRLDC highlighted that during summer as the load increases, reactive power

drawl also increases which causes voltages to drop. To maintain the voltage

profile of Grid within IEGC band during summer, following actions that has

already been suggested and discussed during previous OCC meetings were

reiterated as given below:

• Switching on Capacitors

• Switching off Reactors

Page 23: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

23

• Dynamic reactive support from Generator as per its capability curve.

• Tap Optimization at 400/220kV ICTs by NRLDC and 220/132kV ICTs by

respective state control area based on scatter plots of ICTs, offline

studies, NRPC RE account etc.

• Synchronous condenser operation

• SCADA Displays of capacitors and Reactors for better visualization

19.7 Defense mechanism

Existing defense mechanism as recommended by various committees and its

importance had been discussed in many previous meetings. These defense

mechanisms cover protection from under voltage, under frequency, rate of

change of frequency, SPS for line/ICTs loading/generator complex evacuation

etc. OCC has recommended and directed all to implement and keep in healthy

condition all these mechanism as per approved settings.

NRLDC representative stated that during summer months (high demand period)

UVLS plays an important role to prevent cascade tripping on sinking of voltage.

During low voltage, UVLS relay disconnects pre-identified feeder to shed the

load to control the low voltage.

OCC decided that as the system size is increasing, role of UVLS relay is

significant in Grid stability during low voltages in the system. Therefore, UVLS

data and monitoring of status of UVLS similar to UFR or df/dt is also necessary.

NRLDC presented the updated status of UVLS, available with NRLDC:

State Nos of

locations* Voltage set (kV)

Delay in Second

Load relief (MW)

Status (06.05.16)

Uttar Pradesh

13 190 5 873.8 No

Punjab 3 (220kV Moga,

Malerkotla & Bahadurgarh)

190 10 265

Details Received (185MW

load relief)

Uttarakhand 1 (220kV

Rishikesh) 190 30-60 No

Delhi 1 (400kV Bamnoli)

360 50-100 No

Rajasthan

3 (132kV Mandan,

K.G.Bas & 220kV

Neemrana

90% of Normal voltage

30 15,22 &30

No

Page 24: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

24

OCC recommended the following based on above deliberation:

Instantaneous tripping for UVLS operation needs to be corrected with

minimum 5 second time delay.

Voltage setting for UVLS needs to be corrected in UP.

All the utilities shall submit the UVLS details of their system in the

prescribed format

OCC also advised all state control area/Users to ensure that their protection and

defense system are in working conditions and settings are as recommended. In

addition, all states/user shall update changes or modification if any carried out in

the information submitted earlier.

In addition, OCC suggested reviewing the various Islanding Scheme of states

(Delhi, Rajasthan, Haryana & Uttar Pradesh) for upcoming summer month as

per anticipated load/Generation.

States/Generators were advised to suggest changes or action plan, if any,

for modification in existing islanding schemes to NRPC.

19.8 Telemetry and Visualization

OCC discussed and advised all the members for following action:

a) Ensure telemetry & wide observability

b) SCADA displays updating/ Correctiveness

c) Important document updating and availability at control room

19.9 Protection and Transmission System pre-summer maintenance

i. Avoiding tripping of transmission elements during higher loading

ii. Reviving the elements under outages

iii. Expediting new elements to be commissioned

iv. Faster clearance of faults

OCC discussed on the above issues and directed all concerned utilities to

take requisite action.

20. SPS for HVDC Champa- Kurukshetra Line :

NRLDC representative informed that +/- 800KV HVDC Bi pole between Champa Pooling Station (Western region,Chattisgarh) - Kurukshetra (Northern region, Haryana) line (with provision to upgrade HVDC terminal to 6000MW at later date) was under trial testing since Feb-Mar’17. It is an inter-regional HVDC link between WR (Chattisgarh) and NR (Haryana). Following are the associated transmission network of WR - NR HVDC Interconnector for IPP Projects in Chattisgarh (WR) & Trans. System Strengthening in NR for IPP Projects in Chattisgarh.

Page 25: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

25

S.No. WR NR

1 HVDC Rectifier Module of 3000MW capacity at Champa

HVDC Rectifier Module of 3000MW capacity at Kurukshetra

2 765 kV Champa pooling station 400/220KV Kurukshetra S/Stn. (GIS) 2× 500 MVA

3 765 KV D/C Champa Pooling station – Raipur Pooling Station line

400KV D/C Kurukshetra - Jallandhar line (Quad) (one ckt vis 400/220KV Nakodar(PSTCL) S/Stn.)

4 765 KV S/C Champa Pooling station - Dharamjaygarh/ near Korba Switching Station

400KV D/C Kurukshetra - Jind line (Q)

5 765 KV S/C Raigarh Pooling Station(Near Kotra)- Champa Pooling station line

400 kV D/C Kurukshetra-Malerkotla Line

6 765 KV D/C Raigarh Pooling station (Near Kotra) - Raigarh Pooling station (Near Tamnar)

400 kV D/C Malerkotla-Amritsar Line

7 LILO of Abdullapur - Sonepat 400KV D/C at Kurukshetra (Triple)

At present, HVDC Champa – Kurukshetra Bipole is for 3000 MW power transfer from Champa Pooling to Kurukshetra substation (pole-1 is under commissioning at present). Associated transmission network at 765 & 400kV in NR has already been commissioned and synchronized. In view of important HVDC link between WR-NR, N-1 or N-1-1 contingency of this bipole should also be planned. It was also informed that at present, inter connection of WR & NR is as:

S.No.

AC link S.No. HVDC link

1 765kV Gwalior-Agra-1 1 HVDC Vindhyachal B-t-B (2×250 MW)

2 765kV Gwalior-Agra-2 2 HVDC Mundra-Mahindergarh Bipole (2 × 1250MW)

3 765kV Gwalior-Phagi-1 3 Upcoming Champa-Kurukshetra Bipole (2 × 1500 MW)

4 765kV Gwalior-Phagi-2

5 400kV Sujalpur-RAPP-C

6 400kV Zerda-Kankroli

7 400kV Zerda-Bhinmal

8 220kV Morak-Badod

9 220kV Morak-Kota

10 220kV Malanpur-Auraiya

11 220kV Mehgaon-Auraiya

Under N-1 or N-1-1 contingency of this pole, it would result in overloading of already stressed 765kV Gwalior-Agra/Phagi ckts. In order to take automatic

Page 26: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

26

action for such bulk power carrying HVDC outage, a SPS must be designed with its implementation.

NRLDC representative shared the sensitivity of HVDC Champa-Kurukshetra on the inter-regional links of NR based on system studies as given below:

- Sensitivity Champa - Kuruksherta

- on WR-NR about 60-70%

- on ER-NR about 30-40% - Sensitivity of 765 kV Agra-Gwalior among WR-NR is again about 60%

Thus tripping of Champa-Kurukshetra pole -1 with 1500 MW loading would

result in about 1000 MW increase on WR-NR as well as about 500 MW on

ER-NR corridors. This approximates to about 500-600 MW increase on 765

kV Agra-Gwalior lines. As 765 kV Agra-Gwalior links already have flow

based SPS, this SPS would cater to the single pole tripping of Champa-Kurukshetra also.

However, with the outage of Champa-Kurukshetra, situation would revert

back to present conditions and therefore TTC/ATC of NR import would need

to be revised immediately. All the utilities would have to take immediate

action to reduce drawal (also by increasing internal generation) under such situation.

He added that as commissioning of SPS also takes lot of time, it is better to

strengthen SPS for 765 kV Agra-Gwalior lines.

After detailed deliberation, it was decided that revised SPS of 765 kV Agra-Gwalior D/C line should be expedited and the work of design and implementation of SPS for 3000 MW Champa –Kurukshetra Bipole should be initiated.

( Action: POWERGRID NRLDC; Time line: Immediate)

21. Augmentation of Transformer capacity at Dehar BBMB:

NRLDC representative stated that in line with approval of Standing Committee

on power system planning, augmentation of Transformer capacity was done at

Dehar (BBMB) by replacing old ICT of 250 MVA(ownership with BBMB) with

315 MVA ICT(ownership with POWERGRID) by POWERGRID. Regarding this

all pre charging documents were submitted by POWERGRID including SCADA

and Protection undertakings as well as consent was conveyed by BBMB in

compliance of CERC (IEGC) Regulations, 2010 and CEA (standard of

Connectivity to the Grid) Regulations, 2007.

Page 27: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

27

He added that after the completion of trial run of new ICT, NRLDC did not

receive Disturbance Recorder and Event recorder data. POWERGRID had

conveyed that as per old existing system there is no SCADA and event

recorder. Non-availability of Event Logger and Disturbance Recorder is a

violation of CERC (Indian Electricity Grid Code) Regulations, 2010 and CEA

(Standards of Connectivity to the Grid) Regulation, 2007. The relevant

provisions of IEGC and CEA are quoted below:

IEGC Grid code clause 4.6.3:

“Recording instruments such as Data Acquisition System/Disturbance

Recorder/Event Logging Facilities/Fault Locator (including

time synchronization equipment) shall be provided and shall always be

kept in working condition in the ISTS for recording of dynamic

performance of the system. All Users, STUs and CTU shall provide all

the requisite recording instruments and shall always keep them in

working condition.”

As per Standards of Connectivity to the grid: Part 1 General Clause

(7) Disturbance Recording and Event logging facilities:

“Every generating station and sub-station connected to grid at 220kV or

above shall be provided with Disturbance Recording and Event logging

facilities. All such equipment shall be provided with time synchronization

facilities for global common time reference. “

BBMB informed that DR was already there. He assured EL would be

installed within 3 months. BBMB detailed upon that it is in the process of

integrating 61850 compliant Numerical Relays with the Siemens RTUs for

recording the event in SCADA.

(Action: BBMB; Timeline 15th June,2017)

22. Multiple element tripping events in Northern region since last OCC

meeting:

NRLDC representative informed that a total of 15 grid events occurred since last

OCC meeting. Out of these 15 events, 7 no. of events were of GD-1 category.

The preliminary report of all the events had been issued from NRLDC. A list of

all these events along with the status of details received was attached at

Annexure-II of the agenda of this meeting.

OCC discussed and requested concerned utilities that they should take

expeditious actions to avoid such tripping in future. Further, all the

concerned utilities were requested to provide the DR/EL & Detailed Report

of the events in line with the regulations.

Page 28: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

28

(Action: BBMB, POWERGRID, NHPC, PSTCL, RVPNL, UPPTCL, NTPC,

HVPNL, APCPL, JSW (Karcham); Time line: Immediate)

23. Details of tripping of Inter-Regional lines from Northern Region for

February’17:

NRLDC representative informed that two inter-regional lines tripping occurred in

the month February’17. The details were attached at Annexure-III of the Agenda

of this meeting. He added that as per regulations, all the utilities should furnish

the DR/EL, flag details & preliminary report to RLDC/RPC within 24hrs of the

event. They should also furnish the detailed investigation report within 7 days of

the event, if fault clearance time is higher than mandated by CEA (Grid

Standard) Regulations.

It was noted that the not all information regarding the tripping was received from

the utilities.

OCC requested all the concerned utilities for taking corrective action to avoid such tripping as well as timely submission of the information. (Action: RVPNL, POWERGRID Time line: Immediate)

24. Frequency response characteristic:

NRLDC representative informed that four FRC based event had occurred since

last OCC meeting. The FRC had been computed by NRLDC as well as request

was sent to state control areas along with other regional entities to compute the

same at their end. Descriptions of the events are as given below:

S.No. Event Date Time (in

hrs) Event Description

Starting Frequency

(in Hz)

End Frequen

cy (in Hz)

Δf

1 21-Feb-17 15:59

Due to tripping of Kalisindh Unit-I & II the generation loss of 830 MW took place.

50.01 49.90 -0.10

2 23-Feb-17 16:15 Kudankulam Unit-II generating 1000 MW went under house load.

49.99 49.92 -0.07

3 02-Mar-17 01:57 Krishnapatnam Unit - 1 & 2 tripped.

50.14 49.99 -0.15

4 05-Mar-17 15:14 Load rejection Test of unit II(1000 MW) Kudankulam

50.15 50.04 -0.11

Page 29: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

29

NRLDC representative further mentioned that the Hon’ble CERC approved

procedure had already been shared with all concerned during previous OCC

meetings. FRC observed for each state control area for the events is tabulated

below:

State Name

For past 27 FRC events

FRC

Average FRC

Median FRC

21-Feb-17

23-Feb-17

02-Mar-17

05-Mar-17

PUNJAB 16% 8% 23% 0% 5% 36%

HARYANA 29% 19% 5% 0% 23% 20%

RAJASTAN 18% 9% 50% 6% 0% 44%

DELHI 27% 19% * 33% 19% 31%

UTTAR PRADESH

21% 10% * * 4% 37%

UTTARAKHAND 18% 22% * * 23% 0%

CHANDIGARH 33% 24% 37% 45% * *

HIMACHAL PRADESH

18% 10% * 100% * 10%

JAMMU & KASHMIR

8% 5% 33% 34% * *

NR 19% 16% 29% 8% 3% 19%

Major Thermal Generation in

NR 8% 15% 27% 18% 8% 16%

Major Hydro Generation in

NR 5% 4% 2% 23% 1% 17%

* Unreliable FRC due to SCADA data error or schedule change

He informed that the Average FRC in line with the decisions taken during

various OCC meetings, the time and date of the FRC events were e-mailed to

respective utilities.

Concerned utilities were requested to submit the FRC of their control areas.

OCC expressed concern over such continuous poor frequency response

and stressed upon all utilities to take corrective measures.

24. Tripping of all line at Kurukshetra HVDC substation on high voltage

protection:

NRLDC representative informed that as reported, at 15:19hrs on 17.02.2017,

seven number of Filter banks inadvertently got connected due to mal-operation

of control system (presently testing phase) leading to sudden injection of 955

Page 30: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

30

MVAR.Voltage shot up to above 440kV resulting in tripping of all 400 kV lines at

Kurukshetra on over voltage protection.

He added that the over voltage settings for Stage-1 is having a time delay of 4

sec, while, the usual practice is to keep the grading in parallel or same station

lines in the range of 5-6 sec and 110-112% of rated voltage. He suggested that

logic should be revised so that at least 4-5 lines, preferably of lesser length,

should remain connected.

POWERGRID representative informed that the problem occurred due to some

logic issue, which would be resolved before commissioning. He informed that

Grading for some of the lines had also been done. He assured that action would

be taken to avoid recurrence of the such events.

(Action: POWERGRID; Timeline: 05.04.2017)

25. Unavailability of PLCC at GSS Sakatpura for 220Kv RAPP B-Kota Circuit

In the 132nd OCC meeting, NPCIL representative informed that RAPP B-Kota (circuit-

II) PLCC was not available since last two years. End zone faults occurring in line were

getting cleared in zone-2 time delay, instead of carrier aided trip.

This also results in simultaneous tripping of RAPP B-C tie line at RAPP-C end on

backup earth fault protection, in addition to RAPP B-Kota circuit-II tripping in zone-2

time of 350msec. With outage of two evacuation lines with both generators in service,

remaining three lines RAPP B-Chittor-I, RAPP B-Chittor-II & RAPP B-Debari becomes

loaded. There is risk of cascade tripping of these lines and risk of both units outage

due to offsite power failure. He added that RRVPNL informed that PLCC cards were

faulty and needs repair / replacement and emphasized that PLCC issue should be

resolved on highest priority to make PLCC available at GSS Sakatpura for 220kv

RAPP-B-Kota ckt.

In 132nd OCC meeting, the matter was discussed in detail. The issue of ownership

came up during the deliberations. RRVPNL was advised to submit information within

15 days.

In this meeting, RVPNL representative intimated that the communication wing will

restore the PLCC at the earliest.

(Action: RVPNL Time line: 15.4.2017)

Page 31: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

31

26. LVRT issues of wind/solar generation

It was deliberated that as per the Technical Standards for Connectivity to the Grid,

(Amendment), regulations, 2012, B.2 (3) states the following:

“Wind generating stations connected at voltage level of 66kV and above shall

remain connected to the grid when voltage at the interconnection point on any

or all phases dips up to the levels depicted by the thick lines in the following

curve:

Provided that during the voltage dip, the individual wind generating units in the

generating station shall generate active power in proportion to the retained

voltage;

Provided further that during the voltage dip, the generating station shall

maximize supply of reactive current till the time voltage starts recovering or for

300ms, which ever time is lower.”

Further as per the regulation, the station connected to the grid 06 months after

publication of these regulation (i.e.15.04.2014) shall have the LVRT capability.

Regarding wind turbines commissioned before 15.042014, CERC in order

dated 05.01.2016 in Petition No. 420/MP/2014 LVRT had directed that LVRT

should be implemented for all wind turbines (except Stall Types) commissioned

before 15.04.2014 having installed capacity equal to or more than 500 KW.

Page 32: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

32

In the 36th NRPC meeting, the LVRT issue of wind/solar generation was raised

wherein representative of RVPNL stated that LVRT is being enforced for wind

stations. He agreed to submit the status of LVRT for wind stations

OCC expressed concern over long pending issue. RVPNL representative

intimated that the issue has been taken up with the RE generators. OCC

advised that the information should be submitted at the earliest.

( Action: RVPNL, Time line 15.04.2017)

Additional Agenda

AA1. Change in terminology used in power supply position reports.

SE, NRPC informed about communication received from CEA, wherein was

mentioned stated that Grid Management Division, CEA publishes the monthly Power

Supply Position reports based on data submitted by state utilities through RPCs.

These reports show state-wise details of demand of demand, supply and shortage of

electricity in terms of energy and peak MW. Keeping in view ample un-utilized

generation capacity in the country, demand-supply gap of electricity in various states

cannot be attributed to non-availability of power in the present scenario. Accordingly, it

is not considered appropriate to term the demand-supply gap and energy/peak

shortage but energy not supplied/demand not met. Thus, the terms ‘peak deficit’ and

‘energy deficit’ appearing in various reports including power supply position reports are

not reflective of the actual situation in the country today.

CEA had conveyed decision to change the terminology used in Power Supply

Position report w.e.f. January,2017(Revised) as under:-

Energy Power Supply Position Report

Energy Requirement (MU)

Energy Supplied (MU)

Energy not supplied

(MU) (%)

Peak Power Supply Position Report

Peak Demand (MW)

Peak Met (MW)

Demand not met

(MW) (%)

OCC advised all members to take note of the decision and incorporate the

changes in all the communications regarding power supply position including

the monthly power supply position data in format 28 and 29 being furnished by

SLDCs to NRPC Secretariat.

( Action: All SLDCs; Time line: Immediate)

Page 33: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

33

T1: Table agenda by NAPS

NAPS representative informed that NAPS Generating station combined with

Harduaganj TPS is connected to NR Grid through 220 kV transmission lines

emanating from NAPS & Harduaganj TPS Switchyards. Some of these lines have

been LILOed by UPPTCL for fulfilling their requirements, namely;

i) NAPS is connected to Moradabad by NAPS-Moradabad line has been made

LILO at Sambhal.

ii) NAPS is connected to Meerut by NAPS-Simbholi line.

iii) NAPS is connected to Harduaganj TPS by NAPS-Khurja lines (D/C) out of two

lines one has been made LILO at Dibai recently and NAPS-Harduaganj line

LILOed at Atrauli.

iv) Harduaganj TPS is further connected to Mainpuri by Hrduaganj- Maipuri lines

(D/C), both lines have been made LILO at Etah and Sikandrarao respectively.

He added that the above 220kV transmission lines between these generating stations

are repeatedly opened at one or more LILO points simultaneously probably for load

control and kept open for longer durations and also not being reported to NAPS

authorities. This reduces the system stability especially in case of tripping of any other

line connected at NAPS.

The details are given below;

i) NAPS are connected to Moradabad by NAPS-Moradabad line kept open either

at Sambhal or Moradabad.

ii) NAPS are connected to Harduaganj by NAPS-Harduaganj line is kept open at

Atrauli.

iii) NAPS is connected to Harduaganj TPS via Khurja lines(D/C) is also kept open at

Dibai.

iv) Harduaganj TPS is further connected to Mainpuri by Harduaganj-Maipuri line(via

Etah) is kept open at Etah.

v) Harduaganj TPS is further connected to Mainpuri by Harduaganj-Maipuri line (via

Sikandrarao) is kept open at Sikandrarao.

He stated that the practices for opening of interconnecting lines at one or more LILO

points simultaneously is a serious issue resulting in weakening connectivity between

various parts of grid system and generating station. It had been experienced in past

that the opening of interconnecting lines resulted in transient and finally loss of

generation at NAPS as well as Harduaganj TPS.

UPPTCL representative assured that the issue would be resolved in coordination

with NAPS.

( Action: UPPTCL; Time line: 15.04.2017)

Page 34: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

Annexure 1

Name Designation Organization Fax No. Phone/Mobile e-mail ID

[email protected]/

Pecomml.inNRPC.rediffmail.com

S.K.Mishra SM(E) NHPC 9910103478 [email protected]

Vijay Kumar E(E) NHPC 9818696821 [email protected]

R.D.Yadav STE(E&I) NPCIL 9413354527 [email protected]

Prabhat Sharma SO/F NPCIL 9412768008 [email protected]

Sameer Rai SO/G-Operation NPCIL 9412768052 [email protected]

Kamaldeep Dy.Mgr NRLDC 9971700422 [email protected]

D.K.Jain Addl.GM NRLDC 011-26852747 9910344127 [email protected]

Rajeev Porwal DGM NRLDC 011-26852747 9871581133 [email protected]

P.K.Agarwal GM NRLDC 9910064320 [email protected]

V.Jolly Sr.Mgr NTPC 9650996340 [email protected]

Rakesh Chopra GM(comml) NTPC 8004911131 [email protected]

Mohd.Zia AGM(OS),NRHQ NTPC 9415005883 [email protected]

P.K.Saini Sr.Mgr(OS) NTPC 9650991759 [email protected]

D.Chakraborty Addl.GM PGCIL 9873549050 [email protected]

D.Kushwaha AGM PGCIL 9425409591 [email protected]

Rajiv Mohan GM(AM)NR-III PGCIL 9431820304 [email protected]

S.C.Sharma Chief Manager PGCIL 9873918526 [email protected]

Praveen Kumar DGM PGCIL 9419213490 [email protected]

Rajeev Agarwal Manager SJVNL 9418045426 [email protected]

Vishalakshi Malan Sr.Engineer THDC 8755297715 [email protected]

Naveen Kumar AM(T),SLDC DTL 9999533883 [email protected]

Sunilesh Mohari DGM(p/m) DTL 9999533655 [email protected]

B.L.Gujar Manager(T)Prot. DTL 9999533985 [email protected]

S.K.Sinha DGM(T),SLDC DTL 9999533673 [email protected]

N.K.Makkar EE HVPNL 9466219042 [email protected]

Er.K.S.Sambyal ASE(PC) HPPTCL 9418030537 [email protected]

Er.Suresh Sharma AE HPPTCL 9418040918 [email protected]

Saleem Mohammad ASE/SLDC PSTCL 96461-18001 [email protected]

V.K.Gupta AEN(SOLD) RVPNL 9413383201 [email protected]

Atul Sharma EE(SOLD) RVPNL 9413382632 [email protected]

C.L.Koli SE(PP) RVPNL 9413385340 [email protected]

M.M.Ranwa CE(RUVNL) RVPNL 9413359050 [email protected]

Sanjay Kumar

Chaurasiya

EE UPPTCL 8005461633 director)[email protected]

A.J.Siddiqui EE UPPTCL 9415609363 [email protected]

Brijesh Singh EE,VVNL UPPTCL 9415901993 [email protected]

Kavindra Singh Tech.Advisor UPPTCL 9412749803 [email protected]

P.N.Upadhyaya CE(SLDC) UPPTCL 8004941065 [email protected]

B.K.Jha SE(O) UPPTCL 9415311206 [email protected]

Chnadra Mohan D(O) UPPTCL 9415311221

Dheeraj Jain DGM(comml) APCPL 9650993884 [email protected]

Manoj Taunk GM AD Hydro 9099005517 [email protected]

P.S.Mhaske MS NRPC

Hemant Pandey SE(S) NRPC

B.S.Meena EE(S) NRPC

K.N.Rao Chf.Mgr NRPC

Sonia Chauhan ASE NRPC

Akshay Dubey AEE NRPC

Satyendra Prakash AGM(T)-COS IPGCL-PPCL 9717694813 [email protected]

List of Participants in the 133rd OCC meeting held on 17.03.2017

Kuldeep.S.Manderna Addl.SE/PC BBMB 0172-2653297 9417200352

Page 35: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

( Amount in Rs. Crores) As on 27.02.2017

State / UT No. of Schemes Scope of Work (Scheme) Approved Cost Grant Sanctioned Date of Sanction Funds Released % of fund Disbursed against grant Sanctioned Status

Annexure-2

Sr.

No.

State / UT No. of

Schem

es

Scope of Work (Scheme) Approved

Cost

Grant

Sanctioned

Date of Sanction Funds

Released

Status/Remark

Renovation and Upgradation

of protection system in the

substations of Jammu.

140.04 140.04 28/10/2015 0.00 0.00 %

Renovation and Upgradation

of protection system of

substations in Kashmir area.

146.12 146.12 17/03/2016 0.00 0.00 %

Installation of Bus bar

protection scheme in the state

of Punjab

18.21 16.39 17/03/2016 0.00 0.00 %As per information received

from PSTCL vide mail dated

26.03.2017 Progress is NIL

Provision of second DC

Source at 220 kV & 132 kV

Grid Sub Stations of PSTCL

15.30 13.78 01-02-2017 0.00 0.00 %

3 Himachal

Pradesh

1 Renovation and Upgradation

of Protection System of

substations of HPSEBL.

55.44 55.44 01-05-2016 0.00 0.00 %

4 Uttrakhand 1 Renovation and Upgradation

of Protection System of

substations in PTCUL.

125.05 125.05 17/03/2016 12.50 10.00 %

5 Haryana 1 Renovation and

Modernization of distribution

system of DHBVN, Haryana.

364.27 273.2 09-05-2016 0.00 0.00 %

Renovation and Upgradation

of protection system of 220kV

and 400kV substations in the

state of Rajasthan in order to

rectify Protection related

deficiencies

159.53 143.58 31/12/2014 10.79 7.51 %

Installation of 1 no each new

400kV, 125MVAR Bus Type

Shunt Reactor at 400kV

Hindaun and 400kV GSS

Merta City, alongwith shifting

of 400kV, 50MVAR Bus

Type shunt reactor from

400kV Merta City to 400kV

Bhilwara and associated bays

at these stations.

23.87 21.48 31/12/2014 6.45 30.03 %

7 Delhi 1 Rectification and Upgradation

of protection system and

replacement of outlived

equipments in DTL

substations

125.98 113.38 17/03/2016 11.34 10.00 %

8 Northern

Regional

Power

Committee

(NRPC)

1 Study program on the

integration of renewable

energy resources of NRPC

6.45 6.45 28/10/2015 4.49 69.61 % Completed

Installation of Capacitors

banks in the state of Uttar

Pradesh in order to improve

Voltages

39.29 35.36 05-11-2015 7.76 21.95 %

Supply completed

Renovation and Upgradation

of Protection and control

Systems, UFR Mapping and

Islanding scheme in the state

of Uttar Pradesh to rectify

Protection related deficiencies

202.94 182.65 05-11-2015 38.03 20.82 %

The details enclosed with

Reconductoring of 11 Nos of

132kV Lines of the state

network of UPPTCL for

Relieving Congestion

80.00 60.00 17/03/2016 0.00 0.00 %

14 1502.49 1332.92 91.36 6.85 %

NORTHERN REGION SCHEMES FUNDED FROM PSDF

% of fund Disbursed

against grant

Sanctioned

21 Jammu &

Kashmir

TOATAL

( Amount in Rs. Crores) As on 27.03.2017

NOTE: One scheme of Uttar Pradesh for relieving congestion (Rs. 60 crores sanctioned grant during 2015-16) is not eligible as the LoA has already been placed

before the approval of the scheme.

2 2

Uttar

Pradesh

3

Punjab

Rajasthan 26

9

Page 36: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC
Page 37: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC
Page 38: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC
Page 39: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC
Page 40: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC
Page 41: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC
Page 42: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC
Page 43: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC
Page 44: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

LIST OF NEW TRANSMISSION ELEMENTS CHARGED IN THE MONTH OF FEB - 2017

Transmission Lines(220kV 109.43 ckt km & 400kV 236.79 ckt km )

Si. No.

Transmission Elements Owner Type Charging

Date Charging

Time Details of Transmission

Elements

1 220 kV Dehradun- Jhajra-I PTCUL Line 01.02.2017 19:08 6.11 km Twin Zebra

2 220 kV Dehradun- Jhajra-II PTCUL Line 01.02.2017 22:27 6.11 km Twin Zebra

3 400 kV Allahabad(PG)- Meja(NTPC)-II PGCIL Line 08.02.2017 20:30 28.19 km ACSR Twin

Moose

4 400 kV Amritsar-Jalandhar-S/C { LILO of 400 kV Amritsar-Hamirpur at Jalandhar}

PGCIL Line 11.02.2017 19:50 71.436 km ACSR Twin

Moose

5 220 kV Orai(PG)-400kV Orai(UP){LILO of 220 kV Kanpur(PG)-220kV Orai at 400 kV

Orai} UPPTCL Line 11.02.2017 17:25 12.80 km Single Zebra

6 400 kV Hamirpur-Jalandhar-S/C { LILO of 400 kV Amritsar-Hamirpur at Jalandhar}

PGCIL Line 12.02.2017 10:03 135.16 km ACSR Twin

Moose

7 CB No X14 & 400 kV Interconnector

between Unit 5,6 and Unit 7,8 SSCTPP RVUNL ICT 14.02.2017 21:09 2.0 km

ACSR Quad Moose

8 Kanpur(PG)-765kV Orai(UP) {LILO of 220

kV Kanpur(PG)-220kV Orai at 400 kV Orai}

UPPTCL Line 16.02.2017 15:37 84.41 km Single Zebra

Page 45: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

LIST OF NEW TRANSMISSION ELEMENTS CHARGED IN THE MONTH OF FEB 2017

ICTs (3045 MVA) / Bus Reactor (365 MVAR) / Line Reactors

Si. No.

Transmission Elements Owner Type Charging

Date Charging Time

9 315 MVA ICT(PG) at Dehar replacing 250 MVA ICT(Augmentation of capacity)

PGCIL ICT 01.02.2017 18:15 (on load)

10 125 MVAR B/Reactor at RAPP C NPCIL B/Reactor 02.02.2017 16:34

11 100 MVA ICT-II at Anpara(Replacing damage ICT) UPPTCL ICT 03.02.2017 17:43

12 CB No 425R of 125 MVAR L/Reactor at Gorakhpur of Barh-Gorakhpur-I

PGCIL PGCIL 03.02.2017 15:47

13 CB No 427R of 125 MVAR L/Reactor at Gorakhpur of Barh-Gorakhpur-II

RRVPNL PGCIl 07.02.2017 13:48

14 315 MVA,400/220kV ICT-II at Sohawal PGCIL ICT 10.02.2017 1205 (on no load)

15 315 MVA,400/220kV ICT at Orai UPPTCL ICT 11.02.2017 17:25

16 3x275,400/21 GT at Suratgarh Super Critical Thermal Power Plant

RRVPNL GT 14.02.2017 21:09

17 500 MVA,400/220kV ICT-III at G.Noida UPPTCL ICT 19.02.2017 17:10(on load)

18 240 MVAR B/Reactor at Fatehbad (UP) UPPTCL B/Reactor 27.02.2017 19:43

19 1500 MVA ICT-II at Fatehabad (UP) UPPTCL ICT 27.02.2017 14:59 (on load)

Page 46: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

LIST OF NEW TRANSMISSION ELEMENTS CHARGED IN THE MONTH OF FEB 2017

Other Elements / Lines for antitheft purpose / old line on new bays

SI. No. Transmission Elements Owner Type Charging

Date Charging Time

(Hrs)

20 220 kV Bay 203, 208 &209 at Sohawal (PG) PGCIL Bays 10.02.2017 12:05,12:27 &13:45 hrs

21 400 kV Bays at Dehradun of

Abdullapur(407,408,409 & 410) PGCIL Bays 18.02.2017 14:02/14:07/13:49/14:50

Page 47: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

Long Outages Generating Units : Feb-

2017

Si. No Station Location Owner Unit No Capacity Reason(s) Outage

Date Time

1 RAPS-A RAJASTHAN NPC 1 100 Subject to regulatory

clearance 09-10-2004 22:58

2 Dehar HPS HP BBMB 6 165 Renovation work. 21-03-2014 18:00

3 Bhakra-L HPS HP BBMB 5 108 Annual maintenance 12-04-2016 09:50

4 Badarpur TPS DELHI NTPC 4 210 Manually closed due to pollution in Delhi NCR

area. 07-11-2016 17:14

5 Bhakra-R HPS HP BBMB 1 157 Annual maintenance 09-11-2016 08:00

6 Dehar HPS HP BBMB 1 165 Penstock repairement 20-12-2016 11:10

7 Dehar HPS HP BBMB 2 165 Penstock repairement 20-12-2016 11:10

8 Chamera-III HPS HP NHPC 3 77 HRD inspection work. 01-02-2017 00:00

9 Chamera-III HPS HP NHPC 2 77 HRD inspection work. 01-02-2017 00:00

10 Chamera-III HPS HP NHPC 1 77 HRD inspection work. 01-02-2017 00:00

11 Obra TPS UP UPRVUNL 7 100 R & M work 01-07-2010 13:44

12 Obra TPS UP UPRVUNL 12 200 Annual maintenance 01-10-2016 14:01

Page 48: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

Long Outages Generating Units : Feb-

2017

Si. No Station Location Owner Unit No Capacity Reason(s)

Outage

Date Time

13 Rajwest (IPP) LTPS RAJASTHAN RRVUNL 2 135 Bad material leakage 20-12-2016 01:55

14 RGTPP (Khedar) HARYANA HPGCL 2 600 Annual maintenance 04-02-2017 21:33

15 Bhakra-R HPS HP BBMB 4 157 Ash handling problem Capital maintenance of

pen stock head gate 22-02-2017 08:30

16 Giral (IPP) LTPS RAJASTHAN RRVUNL 1 125 Bad materials leakage. 11-07-2014 08:20

17 Giral (IPP) LTPS RAJASTHAN RRVUNL 2 125 Boiler tube leakage 27-01-2016 15:27

18 Guru Gobind Singh

TPS (Ropar) PUNJAB PSEB 4 210 Boiler tube leakage 02-10-2016 22:00

19 Panki TPS UP UPRVUNL 3 110 Boiler tube leakage 21-12-2016 11:50

20 Paricha TPS UP UPRVUNL 2 110 Boiler tube leakage 18-01-2017 13:37

21 Rajwest (IPP) LTPS RAJASTHAN RRVUNL 3 135 Boiler tube leakage

DUE TO BED MATERIAL LEAKAGE.

25-02-2017 02:02

Page 49: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

Long Outages Transmission

Elements : Feb- 2017

Si. No Element Name Type

Voltage Level

Owner Outage

Reason / Remarks Date Time

1 New Wanpoh 125 MVAR Bus

Reactor 1

Bus

Reactor 400 kV PGCIL 10-10-2016 10:09 Take out due to low voltage.

2 FSC of Pampore-2 at Kishenpur FSC 220 kV PGCIL 30-10-2012 12:00 Line length has reduced after

LILO work completion

3 FSC of Pampore-1 at Kishenpur FSC 220 kV PGCIL 30-10-2012 12:00 Line length has reduced after

LILO work completion

4 Bamnauli(DTL)-Jatikala(PG) 1 Line 400 kV DTL 22-05-2016 20:29

Tower damage (First dead end

tower from Bamnauli S/S) / Ckt-II

charge through ERS tower

5 Kalisindh 315 MVA ICT ICT 400/220 kV RRVPNL 04-06-2016 15:50 Buchholz relay operated.

6 Bawana 315 MVA ICT 1 ICT 400/220 kV DTL 11-12-2016 08:37 Fire in ICT-1

7 Anpara 100 MVA ICT 2 ICT 400/132 kV UPPTCL 15-02-2017 20:25 DGA test values are poor

8 Sarnath 50 MVAR B/R Bus

Reactor 400 kV UPPTCL 16-02-2009 06:14 Failure of Reactor

9 Wagoora 50 MVAR B/R Bus

Reactor 400 kV PGCIL 22-04-2015 18:56 Take out due to low voltage.

10 FSC ( 50% ) of Koteshwar Pool -2

at Meerut (PG) FSC 400 kV PGCIL 16-07-2015 13:01 Fire in FSC-2 at Meerut.

11 FACT at BLB in Knp-BLB Line FACTS 400 kV PGCIL 02-07-2016 10:20 Y-Phase current imbalance

Page 50: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

Long Outages Transmission

Elements : Feb- 2017

Si. No Element Name Type

Voltage Level

Owner

Outage

Reason / Remarks Date Time

12 400/220 kV ,315 MVA ICT- II at

Jodhpur ICT 400 kV RRVPNL 24-12-2016 14:11 R-ph Bushing burst.

13 Kishenpur - Meerbazar (JK)

Line

220 kV J & K 08-02-2017 15:23

Line tripped on R-Y-N fault.

Tower no. 175 collapsed.{11Km

from Ramban (towards

Kishenpur direction) }

14 TCSC1 of Muzaffarpur-1 at

Gorakhpur TCSC 400 kV PGCIL 17-09-2016 11:23 Signal problem

15 FSC of 400 kV Aligarh - Muradnagar

at Muradnagar end FSC 400 kV UPPTCL 09-10-2015 12:28

LILO of 400 kV Panki –

Muradnagar at Aligarh.

16 FSC of 400 kV Balia- Sohawal –I at

Sohawal FSC 400 kV UPPTCL 14-10-2016 10:52 Low current.

17 FSC of 400 kV Fatehpur-Mainpuri I

at Mainpuri end ICT 400/220 kV DTL 12-08-2016 15:49

Due to self-triggering of spark-

gap

18 FSC of 400 kV Kanpur-Ballabgarh- I FSC 400 kV

PGCIL

20-07-2016 20:55 Due to Signal column fail

Page 51: Government of India Northern Regional Power Committee … · Government of India Northern Regional Power Committee 18-A, ... sub-station in their state which is available on NRPC

Weather Monitoring IMD: Press release on 28th Feb 2017

Action: States should assess the load behavior with rise in temperature.