global aggregation working group 15 th september 2010
TRANSCRIPT
2
Global Aggregation - Recap
What is Global Aggregation?
Process of providing an aggregation for all registered Suppliers
Includes aggregation of Host Suppliers
Current implementation means Host Supplier calculated by difference
Error Supplier Unit in the SEM
Not just Host Supplier volumes but also other errors included
Data Aggregation
NHH Meters(STS only)
Readings
AUFs and EUFs
Profiled Demand for NHH
customers
Generator Output
Tran Loss factors
Units delivered to
BSP in Each
Jurisdiction
HHM metered
units
Meter data processing
Meter data processing
HH Meters
ReadingsDifference
Residual volume assigned to NIEES /ESBN using Error Supplier Units
Metered or profiled volumes are uplifted in DA to reflect distribution line losses
Global Aggregation - Recap
Data Aggregation
Readings
AUFs and EUFs
Profiled Demand for NHH
customersInclude DN
LLFs
Generator Output
HHM metered
unitsInclude DN
LLFs
Meter data processing
Meter data processing
HH Meters
Readings
Variance is ‘smeared’ across Suppliers, method to be determined through SEMO
Metered or profiled volumes are uplifted in DA to reflect distribution line losses (reports show both vols)
Variance
Tran Loss factors
Units delivered to
BSP in Each
Jurisdiction
Global Aggregation - Recap
5
Global Aggregation - Recap
Causes of imbalance?
Power Stations &interconnectors
Transmission Network Distribution Networks Customers(end users)
Physical inaccuracyBack door suppliesInterconnector lossesMeter errors
Meter errorsUmetered embedded generationTheftLine losses
Transformer losses
6
Global Aggregation - Recap
Causes of imbalance?
Power Stations &interconnectors
Transmission Network Distribution Networks Customers(end users)
Data Errors
Umetered SupplyProfilesEnergisation StatusTLAFs DLAFs
Station aggregation rules
7
Global Aggregation - Recap
Causes of imbalance?
Elexon experience of Global Aggregation;
Incorrect profiles of non-interval meters considered chief contributor;
Modification 34_09 developed with a view to smearing residual volume
across all suppliers, taking account of each suppliers share of non-interval
metered consumers;
8
Global Aggregation - Recap
Mod 34.09 raised by ESB CS
Mod proposed separation of SU into Interval SU and Non-Interval SU
Raised at Mods Meeting 24 (29.09.09)
Mods Panel recommended setting up Working Group to explore further
Terms of reference for Working Group circulated, Nov 2009
9
Global Aggregation - Recap
Working Group 1, held on 19th November 2009.
Presentations & Discussion –
ESB CS suggested assigning ESU to non-competing Party under the Code;
MDPs presented on impact on systems;
Actions –
SEMO & RA to meet to further develop options;
ESB CS & NIE to provide estimation of error;
Mods Panel to decide if impact assessments should be sought;
10
Global Aggregation - Recap
SEMO & RA met December 1st to develop options paper;
Four options written up and circulated –
Option A – recovered through SEMO balancing cost;
Option B – smear across Suppliers based on annual factors;
Option C – smear across Supplier based on monthly factors;
Option D – as set out in modification proposal;
11
Global Aggregation - Recap
Working Group 2, held on 23rd February 2010.
Presentations & Discussion –
Suppliers presented on magnitude of actual error;
SEMO & MDPs presented results of impact assessments;
MRSO proposed option E, further enhancement on option C;
Actions –
SEMO & MDPs to meet to further review options D and E;
SEMO to impact assess options A+ and E;
12
Meeting between MRSO, NIE T&D and SEMO took place on March 5th;
Further review of Options D and E;
Option E confirmed as
Aggregation for Supplier Units as normal;
Inclusion of a % value for each Trading Period;
% value will indicate at a MW level the proportion of the aggregation that is
made up of non-interval metering;
Global Aggregation - Recap
13
Global Aggregation - Recap
Working Group 3, held on 27th April 2010.
Presentations & Discussion –
SEMO presented on MDP meetings and further impact assessments;
EirGrid presented on TUoS impacts;
Actions –
SEMO to issue consultation on options A+ and E;
TSO to review implementation of Option A for TUoS;
14
Global Aggregation - Recap
Consultation document issued on June 17th;
Participants asked to express preference between Option A+ and Option E;
Responses welcomed on discarded options B, C and D;
Nine responses received to Consultation
Five responses favoured Option E (2 Participants, 3 service providers)
Three responses favoured Option A+
One response recommended either option
15
Global Aggregation - Recap
Working Group 4, held on 26th August 2010.
Presentations & Discussion –
Recap and review of consultation responses;
Full impact assessment on SEMO systems is approx 1200 hours or €210 K
Noted flexibility in Option E to allow for implementation in one jurisdiction
ahead of the other;
Stressed importance of decision;
Consensus reached on recommendation of Option E;
16
Global Aggregation - Recap
Metered Generation Loss Adjusted
Metered Demand by Supplier Unit
MGLF - NDLF Error Supplier Unit
Current Design
17
Global Aggregation - Recap
Metered Generation Loss Adjusted
Metered Demand by Supplier Unit
MGLF - NDLF Error Supplier Unit
Option E Design
Metered Generation Loss Adjusted
Metered Demand by Supplier Unit
MGLF - NDLFResidual Meter
Volume & Smearing
Global Aggregation - Recap
ANINDeh
NIEPvhNDvhRMVIPy
AINDeh
NIEPvhNDvhRMVIPyREVLFehNDAvh 1
1
After calculation of residual error volume;
Allocated across all Suppliers in the SEM;
Residual Meter Volume Interval Proportion – sets how much of the error
volume is allocated based on a Suppliers interval metered customers;
Non-Interval Energy Proportion – advises what portion of the aggregated
Metered Demand is based on non-interval metered customers;