gladstone gate office presentation

77

Upload: tony-oconnor

Post on 13-Apr-2017

261 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Gladstone Gate Office Presentation
Page 2: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

1 Description2 Initial Concept

3 Solution4 Refining Solution5 Design Method6 Fabrication7 Lift8 Lessons Learned9 Questions & Answers

Introduction

Page 3: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

• The gate was subsequently recovered & put in temporary storage

• Temporary measures to bring port back into operation

• The gate was damaged & required repairing

• Removal from the dock was required

• Solution for gate removal from the dock to be developed

In January 2004 operations at the Port of Liverpool were

brought to a halt, when, during a storm one of the lock

gates at Gladstone dock was ripped from its hinges.

Page 4: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 5: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 6: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Height 17 600 mm

Breadth 21 952 mm

Depth 2 400 mm

Weight 393 tonnes

Details of Gate`

Page 7: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Gladstone Dock GateLondon Bus

Page 8: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 9: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 10: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 11: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Initial Concept

Initial feasibility undertaken by MDHC

Options considered

•Conventional repair using dry dock

•Conventional lift of gate using crane

•Tipping cradle

Page 12: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Conventional repair using dry dock

• Condition of gate below water line unknown

• Availability of dry dock

Page 13: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Conventional lift using cranes

• Weight & size of gate would require a tandem lift using two 1000 tonne cranes

• Availability of space to accommodate the footprint

Page 14: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Tipping Cradle

Page 15: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Tipping Cradle• Distinct advantages to MDHC

• Mersey Mammoth floating crane could be used (250 t capacity)

• Wholly owned by MDHC

• Another 5 gates require refurbishment

• cradle could be reused

Page 16: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

400

t

250 t

184 t BuoyancyTotal Lift

400-184=216 t max

Page 17: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Initial Option

Use of Mersey Mammoth to rotate gate and pull it onto quay side

230 tonne of kentledge required

Requirement to rotate gate from bottom

Page 18: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

What to do when gate is horizontal Two options considered

• Slide gate onto quay side

• Provide vertical support at end of cradle

• Enter the Camel

Page 19: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

What is “The Camel” • Floating barge Used to salvage vessels

• Built circa 1958

• Length 104’ (42.67m)

• Beam 35’ (10.67 m)

• Owned by MDHC

• Laid-Up for 3-4 years

• Therefore no cost on project & ideal for use

Page 20: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 21: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 22: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 23: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Problems With Using Camel• Floating vessel

• Age – Unknown condition

• No access to inside for condition survey

• Fuel on board – No possibility of welding to deck

Page 24: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Problems With Using Camel• Floating vessel

Design calculations

• Age – Unknown condition

Lloyds survey

• No access to inside for condition survey

Lloyds survey

• Fuel on board – No possibility of welding to deck

Clamped connection to bollards

Page 25: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Details of Camel Bollard Clamp

Page 26: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Preferred solution

• Use tipping cradle to recover gate

• Mersey Mammoth used to lift cradle

• Camel used to support gate during repairs

Page 27: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Tipping Cradle

Page 28: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Design Method

• Very good drawings of gate available

• Strength an condition of dock wall uncertain

• Good Guide to gate weights & CoG’s

• Uncertainty on gate conditionAmount of leakageAmount of entrained silt

• Trial lift required

Page 29: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Trial Lift

• Trial lift undertaken May 2005

• Results inconclusive – Gate appears heavier than drawing weight

• Further investigation revealed gate was not emptied of all water for trial.

• Gate reported as being clear of silt

• 2nd trial lift not possible during design

• Uncertainty as to reason for excess weight

Page 30: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Design Brief

• To cater for uncertainty of gate weight 50 tonne allowance

• 60% / 40% split in load to cater for1.Uneven distribution in load 2. Incorrect position of gate in cradle

• Upper & lower bound load cases defined

• Upper bound – Used for member design & lifting loads

• Lower bound – Used for lifting loads

• Stability and strength of dock wall by assessment

• Lateral load resisted by shear key in foundations

Page 31: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Gate Prior to Rotation Gate in Final Position

Page 32: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 33: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

171 te

83 te72 te 75 te

100 te

74 te

329 te

201 te

230 te

195 te

168 te

142 te

0 te

50 te

100 te

150 te

200 te

250 te

300 te

350 te

400 te

450 te

0 10 20 30 40 50 60 70 80 90 100

Angle of Rotation

Mam

mot

h Lo

ad

Upper Bound Vertical Mammoth Load

Lower Bound Vertical Mammoth Load

High Predicted load on Mammoth not includingBuoyancy

Low Predicted load on Mammoth includingBuoyancy

Page 34: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Design Brief

• 250 tonne capacity of Mammoth not sufficient to rotate gate from vertical

• Additional lifting capacity required

• Additional capacity should provide horizontal pull

• Use of tugs to start lift

• Mammoth to complete lift

• Foundations provided remote from quay edge to take lateral loads

Page 35: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 36: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Method of Analysis

Simple 2D STAAD Pro models for various configurations

Vertical, 10°,22.5°, 33.75°, 45°, 67.5, 90°

Various configurations

•Gate against wall

•Gate supported on Mammoth

•Gate supported on tug

•Gate supported on Camel (final condition)

Page 37: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Testing Requirements

• Two types of testing

• NDT of welds

• Load testing of critical items

Page 38: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Testing RequirementsNDT of welds

• Many full penetration weld in highly loaded areas

• No redundant load path in these areas

• All full pen welds 100% MPI & 100% UT

Page 39: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Main Pin Detail

No positive connection to coping

Page 40: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Main Pin Detail

Page 41: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Testing RequirementsLOLER Requirements

REGULATION 9 -THOROUGH EXAMINATION AND INSPECTIONLoad testing to confirm the build quality and structural load bearing capability of the lifting equipmentFunctional and operational envelope tests to verify the satisfactory working range of the lifting equipment.Testing of lifting equipment should be undertaken at the discretion of the competent person

.

Page 42: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Testing RequirementsLoad test of critical items

Discussions with HSE

• Main pin assembly

• Tug lifting eye

• Mammoth lifting eye

Page 43: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Testing RequirementsLoad test of critical items

Programme & cost implications

•Test main pin assemblies only

•Full NDT of all components of Lifting Eyes

•Measures taken to ensure no person under the shadow of the lift

•For design of lift items FoS = 2.0

•For load test proof load = 1.5

Page 44: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Testing Frame for Main Pin

Page 45: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Testing Frame for Main Pin

Page 46: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Testing Frame for Main Pin

Page 47: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 48: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 49: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Lifting of Gate

Page 50: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 51: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 52: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 53: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 54: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 55: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 56: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 57: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 58: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 59: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 60: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 61: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 62: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 63: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 64: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 65: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 66: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 67: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 68: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 69: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 70: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 71: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 72: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 73: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 74: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Page 75: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Lessons Learned

Page 76: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Test requirements and impact

Tightening of clamp assemblies

Use of Camel

Lessons Learned

Page 77: Gladstone Gate Office Presentation

Recovery of Gladstone Gate

Questions & Answers