getting aegis to sea: the aegis ships
TRANSCRIPT
Getting AEGIS to Sea:The AEGIS Ships& Randall H. Fortune, Captain Brian T. Perkinson, USN (Ret.) and Robert C. Staiman
IntroductionWhile combat system engineers developed the
AEGIS system, ship system engineers and naval
architects invented, developed, engineered, and
designed the ship systems and ships that took
AEGIS to sea. Their efforts included studies to
evaluate new construction alternatives and
modifications to existing designs, engineering to
address ship system developments, and work to
solve unique integration issues. It began with the
challenge of integrating the AEGIS Weapon Sys-
tem Engineering Development Model-1 in USS
NORTON SOUND for initial at-sea testing of
AEGIS, and continued through the evolution of
the AEGIS Combat System from Baseline 1 to
Baseline 7, special AEGIS BMD modifications,
and the ongoing modernization of the fleet.
Overall, their efforts have spanned nearly 40
years and may continue for years to come.
AEGIS inUSSNORTONSOUND (AVM-1)USS NORTON SOUND (AVM-1), a World War
II CURRITUCK-class seaplane tender, was used
as the initial test ship for the AEGIS Weapon
System. The ship had served as a guided missile
trials ship since 1948; and, in 1973, was outfitted
with a single SPY-1 array (forward, starboard), a
Mk 99 fire control illuminator, a Mk 26 Mod 0
twin-rail guided missile launching system, and a
rudimentary combat direction system. An AN/
SPS-40 radar was substituted for the existing
AN/SPS-52. Her ammunition included the
STANDARD Missile (1 and 2). Figure 1 shows
the arrangement of the ship as converted.
AEGIS Shipbuilding Significant Events
1967 Major Fleet Escort Study proposes ‘‘Family of
Ships’’—DX, DXG, DXGN
1970 DX becomes DD 963, and Litton wins con-
tract to build entire SPRUANCE class
1975 Preliminary Design for DDG 47 begins
1976 Contract Design for DDG 47 begins
May 1978 DDX Study Group Convenes to Define Op-
erational Requirements and Characteristics
for Future Surface Combatant
Sept 1978 Detail Design & Construction Contract for
DDG 47 signed with Litton Ingalls Shipbuild-
ing Division
May 1981 CG 47 Christened USS TICONDEROGA—
Nancy Reagan is Sponsor
May 1982 USS TICONDEROGA Sea Trials Begin
Jan 1983 CG 47 Commissioned in Pascagoula, MS
1983 Contract Design for DDG 51 Begins
1985 Detail Design and Construction Contract for
DDG 51 signed between USN and Bath Iron
Works
Sept 1985 First cruiser with vertical launcher, USS
BUNKER HILL (CG 52), C, commissioned
Jun 1987 First Bath Iron Works-built AEGIS Cruiser,
USS THOMAS S. GATES, CG 51 Commissioned
Feb 1989 First AEGIS Cruiser with AN/SPY-1B radar
commissioned USS PRINCETON (CG 59)
Jul 1991 DDG 51, USS ARLEIGH BURKE Commissioned
Dec 1991 CNO Endorses DDG 51 Flight IIA Configura-
tion, starting with last FY94 ship
Mar 1993 First Japanese AEGIS Ship Commissioned,
JMSDF KONGO (DDG 173)
Jul 1994 Final (27th) AEGIS Cruiser, USS PORT ROYAL,
Commissioned
Sept 2002 First Spanish AEGIS Ship Commissioned,
ALVARO DE BAZAN (F-101)
& 2009, American Society of Naval Engineers
DOI: 10.1111/j.1559-3584.2009.00208.x
The Story of AEGIS &155
One particularly important ship integration is-
sue required calculating the relative stiffness and
mutual alignment of the SPY-1 array, Mk 99
illuminator, and the Mk 26 launcher, since the
radar and illuminator were located amidships,
forward atop the superstructure, while the
launcher was recessed into the fantail. In 1979,
ship designers faced similar challenges in plan-
ning for the installation of the Mk 41 Vertical
Launching System (VLS) to replace the Mk 26
dual-rail launcher, when USS NORTON
SOUND was designated the ship for all VLS at-
sea firings and tests. The modifications to USS
NORTON SOUND were successful and she
fired dozens of missiles in support of VLS and
AEGIS engineering tests. Her configuration was
changed again in the 1980s when a second AE-
GIS array was added to test the AN/SPY-1B/D
radar upgrades.
TheHunt for the ShipAlthough AEGIS was a research and develop-
ment project in the early 1970s, the debate over
the ship classes in which it would reside began
almost from the project’s inception. The Ad-
vanced Surface Missile System (ASMS) Study in
1965 had addressed notional ship sizes and
classes. Part of this effort included defining the
ship impacts of the proposed elements of ASMS,
including internal volume, topside arrange-
ments, weight, stability, electrical power,
cooling, and other parameters. In 1967, a ‘‘fam-
ily of ships’’ concept, in which the US Navy
would build related DX, DXG, and DXGN
classes, had been promoted in the Major Fleet
Escort Study. The DXG and the DXGN were to
be cruisers, and the DX a destroyer. The Navy
wanted cruisers, armed to deal in an uncertain
future as part of the nation’s strike forces. The
Office of the Secretary of Defense (OSD), on the
other hand, saw only the need for destroyers
armed to engage submarines. OSD won out, and
the DX program began in the 1960s, albeit using
the top-level requirements for a cruiser, with a
lot of space and weight margin for future sys-
tems. Ultimately, DX became the DD 963 class,
with the lead ship, USS SPRUANCE, put under
contract in 1970 (close to the time of engineering
development contract signing for AEGIS). AE-
GIS was planned for initial employment in the
DXGN (later DLGN,1 and even later CGN 38),
with 30 ships proposed. By the spring of 1971,
this plan had been scrapped, and no nuclear
powered ship was projected to be armed with
AEGIS. The ‘‘Family of Ships’’ concept had not
yielded an AEGIS ship.
At the end of 1971, Chief of Naval Operations
(CNO), ADM Elmo Zumwalt proposed to put
AEGIS in a DG ‘‘austere ship’’—a single-mission
ship armed solely for anti-air warfare, weighing
Sept 2004 USS TICONDEROGA, 1st AEGIS Cruiser, De-
commissioned
Apr 2006 First Norwegian AEGIS Ship Commissioned,
FRIDTJOF NANSEN (F310)
Dec 2008 First Korean AEGIS Ship Commissioned, KING
SEJONG THE GREAT (DDG 991)
Oct 2009 USS WAYNE E. MEYER Commissioned,
named for the ‘‘Father of AEGIS’’
Figure 1: AEGIS Engineering Development Model-1 in USSNORTON SOUND. Although the ship appeared to have tworadar arrays, the port array was a blank piece of steel
1In this time period, DLGNs were nuclear powered frigatesand DGs were to be conventionally powered destroyers.
NAVAL ENGINEERS JOURNAL 2009156& The Story of AEGIS
Getting AEGIS to Sea: The AEGIS Ships
no more than 5,000 tons and costing no more
than $100 million. ADM Hyman Rickover and
the nuclear power lobby intervened. At their
prompting, Congress amended Title VIII of the
1975 Defense Authorization Act in August 1974
to require that all new construction major com-
batants would have nuclear propulsion. This
legislation ended the DG as proposed by Zum-
walt, and the program once again became
focused on a nuclear-powered ship—a strike
cruiser, CSGN. In the midst of this process, the
decision was made to take AEGIS through an-
other round of development. A new engineering
development model (EDM), EDM-3C, was un-
derway by 1975. Its aim was to incorporate
lessons from the USS NORTON SOUND and
remove weight from the system. This develop-
ment ultimately reduced the weight of the
topside phased arrays and illuminators by al-
most 20 tons. Initially driven by the now
cancelled DG design, EDM-3C made AEGIS an
option for smaller ships.
In its 1974 hearings on the Fiscal Year 1975
budget, Congress made continued AEGIS fund-
ing dependent on, ‘‘Definition and approval by
both the Navy and the Department of Defense of
the platform(s) for AEGIS . . .’’2 From then until
1978, the Navy, OSD, and the Congress debated
this issue. Numerous studies, budget requests,
and Defense System Acquisition Review Council
decisions were made. In general, the Navy was
seeking strike cruisers; OSD was seeking DDG
47s built on the DD 963; and Congress was
advocating the conversion of USS LONG
BEACH in addition to the other options. The
numbers and timing of the shipbuilding program
varied almost on a daily basis. The Project Office
had to invent novel tracking methods just to
keep up. Some of the issues that were addressed
included single-mission versus multi-mission
ships, nuclear propulsion, and cost caps. Ulti-
mately, by the end of the Ford Administration,
only funds for converting USS LONG BEACH
had been appropriated. Unfortunately, President
Ford’s final budget request for Fiscal Year 1978
proposed rescinding even those funds. DDG 47s
and CSGNs were programmed for later years.
The resolution of AEGIS shipbuilding fell to the
Carter Administration.
President Carter’s Fiscal Year 1978 revised bud-
get request not only rescinded the USS LONG
BEACH funds, but also killed the strike cruiser.
In the CSGN’s place, a new nuclear cruiser, CGN
42, to be built on the existing CGN 38 hullform,
was substituted, and long lead funding for the
nuclear plant was requested in Fiscal Year 1978
for a Fiscal Year 1979 ship start. The budget also
requested $930M for the first DDG 47. Con-
gress approved both of these requests.
Later, as part of the Fiscal Year 1979 budget
workups, CGN 42 was killed. Thus, after years
and years of work on AEGIS ships, only one
class had emerged—DDG 47. Ultimately, class
planning settled at 27 ships—two for each Car-
rier Battle Group (12) and one for each Surface
Action Group (3). In 1980, the DDG 47 class
was redesignated a cruiser class, CG 47.
ShipFeasibility StudiesThe debate over what the first AEGIS ship
should be was supported by numerous ship fea-
sibility and ship design studies. In 1972–1973,
those studies were carried out under the general
nomenclature of ‘‘DG AEGIS’’—the Zumwalt
ship. These studies considered various options
including split versus consolidated AEGIS deck-
houses, single and multiple Mk 13 single-rail
launchers versus Mk 26 twin-rail launchers, and
various self-defense gun systems and helicopter
facilities. Figure 2 shows one of the variants
considered, which included a consolidated
deckhouse, two Mk 13 launchers, two self-
defense guns, and a hangar for a single helicop-
ter. One of the ship integration issues with this
particular design was that the helicopter had to
fly over the aft launcher to land.
The studies led to a final DG configuration
that was 488 feet long and displaced 5,884 long
tons. It was powered by two FT-9 gas turbines
2Congressional Record, House of Representatives, July24, 1974.
NAVAL ENGINEERS JOURNAL 2009 The Story of AEGIS &157
driving twin controllable pitch propellers; how-
ever, as discussed above, support for the DG was
lacking and the preliminary design was cancelled.
As mentioned previously, in 1975 Congress di-
rected definition and approval by Navy and
DoD of the platform(s) for AEGIS. This led to a
long series of feasibility studies. One was aimed
at backfitting AEGIS into the existing CGN 38
class. Installation was not technically feasible,
however, without significant changes to the ship
and the estimated costs proved prohibitive. A set
of studies aimed at a CSGN and later CGN 42
were also undertaken.
In 1974, Ingalls Shipbuilding, now Northrop
Grumman Ship Building, proposed installing the
AEGIS system in a DD 963 hullform and pre-
sented it to the Navy and then CAPT Wayne E.
Meyer, the AEGIS Project Manager. The Navy
engineering review of the Ingalls studies led to
rejection of the option, as it did not meet all of
the Navy’s new ship design criteria and service
life margins. Meyer, through RCA Moorestown,
NJ, then contracted with the naval architecture
firm of John J. McMullen Associates (JJMA) to
perform an independent feasibility study of in-
stalling AEGIS in the DD 963 hull. The Navy
ship engineering community participated in the
review of the JJMA studies. These studies used
the DDG 993 (USS KIDD class) as the baseline,
and showed that it was feasible to install the
AEGIS Weapon System in such a hull, provided
there were significant changes to the DD 963
design, combined with a relaxation of certain
new ship design, construction, and service life
margins. It was treated as a ‘‘modified repeat
design,’’—something called a ‘‘forward-fit con-
version.’’ This study moved the DDG 47 option
to center stage as the earliest practical path for
deployment of AEGIS.
DDG47TOCG47 CLASS (CG 47^73)DDG 47 was to be a modified repeat of the DD
963 class and incorporate the AEGIS Weapon
System with four AN/SPY-1A array faces; four
Mk 99 illuminators; two Mk 26 twin-rail
launchers, each with a 44 missile magazine;
UYK-7 and UYK-20 computers and UYA-4 con-
soles; two quadruple-tube HARPOON missile
launchers; two PHALANX Close-In weapon
systems; two 5 inch/54 caliber guns; as well as
the sonar and hangar of the DD 963. The only
changes were to be those necessary to install the
AEGIS Weapon System. Figure 3 illustrates the
configuration of DDG 47. The preliminary de-
sign for the DDG 47 began in 1975, followed by
the contract design in 1976. The detail design
and construction contract was let in September
1978. In 1980 during detail design, the ship was
re-designated a cruiser—‘‘CG 47.’’ The DD 993
was the baseline for the design since several of
the design changes already made to the DD 963
class were applicable to the CG 47. There were a
number of design issues to resolve however, in-
cluding the impact on stability, freeboard and
Figure 2: 1973 Art-ist’s Rendition of the‘‘DG AEGIS’’—A Sin-gle-Mission Destroyer
NAVAL ENGINEERS JOURNAL 2009158& The Story of AEGIS
Getting AEGIS to Sea: The AEGIS Ships
hull girder strength of the significant increase in
displacement (over 1,100 tons) relative to the
DD 963; the large increases in 60 and 400 Hz
electrical power; the topside design changes
needed to land the AEGIS array faces while ac-
commodating the existing port and starboard
gas turbine intakes and exhausts; new masts to
carry other topside antennas; and design im-
provements to resolve existing DD 963
deficiencies and upgrades to some of her ship
systems. The AEGIS Weapon System required
significant increases in electrical power and the
three existing DD 963 60 Hz generators were
upgraded from 2,000 to 2,500 kW, each; and
solid state 400 Hz converters and a 400 Hz dis-
tribution system were added. The increased
electrical power also increased the heat loads
above those on DD 963 and required additional
cooling capacity. The DD 993 design had al-
ready added a fourth air conditioning plant to
the DD 963 and these units were further up-
graded to accommodate the increased heat loads
from the AEGIS Combat System. In order to in-
stall the AEGIS array faces, the pilot house was
raised two deck levels and the forward/starboard
arrangement was adopted to avoid significant
changes to engine rooms, gas turbine installa-
tions, turbine uptake routings, and other interior
ship arrangements. The forward missile direc-
tors were arranged port and starboard on top of
the pilothouse to avoid blockage of other sensors
on the forward mast. The helicopter hangar was
enlarged to accommodate two Seahawk SH-60B
helicopters and structurally redesigned to allow
a two-level AEGIS equipment room containing
the after AEGIS array faces. These faces were
installed in an aft/port orientation to provide the
ship with 3601 radar coverage. The aft missile
directors were arranged in a traditional fore/aft
configuration on top of the hangar. The split
deckhouse arrangement of the AN/SPY-1A radar
had many system components installed high in
the superstructure creating survivability and sta-
bility issues. The installation of the forward
AEGIS array faces and the raising of the pilot
house significantly increased the sail area of the
ship and further impacted stability.
Ship stability was a major DDG 47 design issue.
Numerous enhancements were added to improve
the ship’s stability condition. The bulkhead
deck and V lines were raised to increase reserve
Figure 3: DDG 47 Configuration
NAVAL ENGINEERS JOURNAL 2009 The Story of AEGIS &159
buoyancy and increase the limiting center of
gravity, or KG. Lighter weight, high-strength
steel was incorporated into certain areas of the
hull. The external propulsion shafting was rede-
signed to increase weight low in the ship. All gas
turbine exhaust silencers were eliminated and the
gas turbine generator exhaust tubes were rede-
signed with lighter weight materials.
The aluminum superstructure of the DD 963 had
to be retained for stability reasons despite the
Navy’s ban on the use of aluminum after the se-
vere superstructure fire damage to USS
BELKNAP (CG 26) following the 1975 collision
with USS JOHN F. KENNEDY (CV 67). The
need to retain aluminum raised concerns relative
to fire protection and distortion between combat
system elements due to hull/deckhouse bending
and torsion. These concerns were recognized
and extensive structural and survivability ana-
lyses of the deckhouse were performed.
Significant improvements were installed, includ-
ing advanced lightweight fire protective
insulation.
Combat system design and integration issues in-
cluded alignment of the split array faces in the
separated AEGIS deckhouses as well as having
the arrays facing port and starboard/forward
and aft. The issues of relative alignment between
arrays and directors and waveguide runs were
studied extensively. Inclusion of a Unit Com-
mander on the ship and providing necessary
consoles and equipment spaces in CIC as well as
in other areas created significant issues in the
combat system design and CIC arrangement. In
order to ensure full operational and maintenance
capability of the combat system, nondeviational,
contract design arrangements for all critical
spaces were developed.
Contract design completed in 1977 and the lead
ship contract was awarded to Ingalls Shipbuild-
ing in September 1978. To permit ship detailed
design and combat system development (which
was underway at the CSED site in Moorestown,
NJ) to proceed in parallel, the Design Budgeting
concept was employed on the lead ship contract.
Design Budgeting established limits on services
and arrangeable volumes of all combat system
equipment and scheduled release of detailed in-
terface data of the combat system components to
the shipbuilder on dates after contract award.
Combat system developers could not exceed the
specified budgets for services or arrangeable
volumes and the shipbuilder could not start de-
tailed design in the Design Budgeted areas of the
ship until the Navy provided the detailed inter-
face data. The interface data was released to the
shipbuilder on preset dates and the shipbuilder’s
detailed design approach was scheduled to ac-
commodate these post contract award releases.
Design Budgeting permitted an additional year
of combat system development, eliminated the
numerous change orders that would have oc-
curred without the Design Budgeting
constraints, and saved the Navy considerable
money and schedule time.
During construction, the ship weight and center
of gravity increased despite the numerous weight
reduction efforts. CG 47 was commissioned in
January 1983 with 110 tons of solid ballast. She
is shown in Figure 4 on the battle line off Leba-
non in 1984, having deployed just 9 months after
commissioning. CG 48, the second ship of the
class, also built by Ingalls, was commissioned in
July of 1984 and had the same tight weight and
stability margins that CG 47 experienced.
The contract design of CG 49, the third ship,
was undertaken as a modified repeat of CG 47
with several significant design changes. The
LAMPS Mk III helicopter with a Recovery
Figure 4: USSTICONDEROGA Offthe Coast ofLebanon in 1984
NAVAL ENGINEERS JOURNAL 2009160&The Story of AEGIS
Getting AEGIS to Sea: The AEGIS Ships
Assist, Secure and Traverse (RAST) system was
included in the design. This and other directed
systems resulted in a 35 long ton weight increase
in CG 49 over CG 47. However, there were other
design changes, which reduced the overall weight
of CG 49. These primarily came from a program,
which was later called TOTS, which stood for
Take Off Tons Sensibly. The TOTS Program was
led by a group of senior leaders from PMS 400,
NAVSEA 05, RCA and Ingalls, detached from
their normal responsibilities and co-located in
Pascagoula, MS. Several hundred weight and
vertical center of gravity reduction proposals
were evaluated, authorized for concept explora-
tion, approved, and incorporated into
subsequent ship designs. All of the AEGIS
Weapon System electronics cooling water sys-
tems were relocated lower in the ship. The 04
level in the forward deckhouse was deleted and a
new structure on the 03 level was incorporated
into a new tripod main mast design. Other sig-
nificant weight reduction efforts were the
increased use of high strength steel in the hull;
the use of advanced lightweight marine power
cabling, and substitution of light-weight corro-
sion resistant honeycomb in the main engine
exhaust ducting. These weight reductions com-
bined with improved shipbuilding practices
allowed CG 49 to ultimately be delivered 180
tons lighter than CG 47—and no ballast was re-
quired. These improvements were also applied to
CG 50 at Ingalls and, later, in CG 51—the first of
the cruisers to be built at Bath Iron Works.
The other force driving TOTS was the Navy’s
decision to install the Mk 41 VLS in CG 52 and
all subsequent ships in the class. The substitution
of VLS for the Mk 26 launchers increased the
missile capacity from 88 to 122 and accommo-
dated the installation of TOMAHAWK cruise
missiles. The ship impact of this change was over
225 long tons of increased displacement and a
0.2 feet increase in the height of the ship’s center
of gravity. In order to accommodate the VLS, the
TOTS team addressed major weight and ship
center of gravity reductions beyond those imple-
mented on CG 49. The goal was to deliver CG
52, with VLS, without ballast and with increased
service life margins. The TOTS team achieved
this by redesigning major ship structures—in-
cluding the aft superstructure, relocating four
critical combat system spaces lower in the ship,
relocating or eliminating more than 35 spaces,
redesigning the helicopter hangar to reduce the
height of the aft AEGIS array faces, and signifi-
cantly changing other service systems on the
ship. As a result of the continuing TOTS weight
reduction program, CG 52 was commissioned
with VLS installed, increased service life mar-
gins, and no ballast.
The success of TOTS and the leadership,
engineering, organization, dedication, and
focus which it exemplified made it possible
for the CG 47 class to incorporate profound
new warfighting capabilities as it was being
constructed and to achieve its promised
weight reduction goals. Ultimately, while
from a combat system perspective the cruisers
were commissioned in Baselines (1–4), the
ship class from a naval architecture perspective
can be viewed as CG 47-48, CG 49-51, and
CG 52-73.
DDG51FLIGHT I (DDG51^71)The 1975 decision to put AEGIS to sea in the
DDG 963 hullform turned out to be an expedi-
ent thing to do. It may have saved the AEGIS
program and certainly got AEGIS to sea in a
warship sooner than almost any other alterna-
tive. However, as with all ship conversions or
major modifications, it did not result in an opti-
mum total ship design. The Navy did not give up
on the concept of an AEGIS ship designed from
the hull up. After the award of the CG 47 con-
tract to Ingalls another series of concept design
studies, called DDX/DDGX, were performed
between 1978 and 1982. These further evalu-
ated AEGIS combatants with VLSs, helicopter
facilities and other combat system upgrades, as
well as a wide range of hull, mechanical and
electrical (HM&E) options. The DDX Study
Group convened in 1978 to define the opera-
tional requirements for future surface
combatants, followed by a series of feasibility
studies in 1979 including five baselines and 27
NAVAL ENGINEERS JOURNAL 2009 The Story of AEGIS &161
variants. These led to a selected variant of 7,000
tons displacement at a cost of $550 million. Af-
ter it had received initial support from OPNAV,
the Vice CNO raised several issues with this de-
sign. This resulted in a number of redesign
cycles. Major input from fleet operators was also
integrated into the designs. This led to a recom-
mended ship of 9,100 tons.
At this point a Request for Proposal was issued to
industry for the contract design, with options for
detail design and construction of a lead ship for a
new DDG 51 class. Responses were received
from five shipbuilders and a Source Selection was
held in late 1982. However, before the contract
could be awarded, the Source Selection was can-
celled by the Secretary of the Navy. In February
1983, NAVSEA was ordered to take the contract
design of DDG 51 in-house before further bids
were requested from industry. Bringing the con-
tract design in-house was a challenge. Since the
days of Total Package Procurement, a 1960s
Secretary of Defense-mandated plan to contract
for construction and design with industry, fewer
and fewer contract designs had been done by the
Navy. In order to accomplish the design in-house
a large Navy team was assembled in a building
near PMS 400 and NAVSEA, augmented by se-
nior participants from Ingalls, Bath Iron Works,
Todd Shipyards, RCA, and ship designers in-
cluding Gibbs and Cox, JJMA, M. Rosenblatt &
Son, and Designers and Planners.
The contract design used AEGIS Combat System
configurations similar to earlier baselines in-
stalled in the cruisers. Figure 5 is an artist’s
rendering of the DDG 51, incorporating split
AEGIS arrays located relatively low in the su-
perstructure, with a VLS, 5 inch gun, and two
PHALANX close-in weapons system (CIWS).
This design did not include a helicopter facility.
A number of other baselines examined the im-
pact of adding both helicopter landing facilities
as well as full helicopter support (hangars, mag-
azines, maintenance facilities, air detachment
berthing, etc.). Because of the impact of full he-
licopter facilities on ship size and cost, as well as
the large number of helicopter-capable ships in
the Navy at the time, the Navy decided to pro-
vide a landing zone but no hangar or other
facilities in the DDG 51 Flight I design.
Early into the process, the first ship of the new
class was named for a former CNO, ADM
Arleigh A. Burke. Burke had been a famous
destroyerman in World War II, and was affec-
tionately known as ‘‘31 Knot Burke.’’ The
ARLEIGH BURKE (DDG 51) class was con-
ceived as the first totally new design for AEGIS,
suitable for the threats of the 1990s and beyond.
It was to replace several classes of ships that
would reach the end of their service lives as
DDG 51s commissioned. As a destroyer, it was
to be nominally less capable than a cruiser. A
displacement limit of 8,300 long tons was estab-
lished and a lead ship not-to-exceed cost limit of
$1.1 billion was edicted from the Navy Secre-
tariat. Follow ships 6 through 10 were to
average $750 million per ship. The cost goals
were in Fiscal Year 1983 dollars. Like the CG
47s before, the class was to be designed and built
with increasingly capable combat and ship sys-
tem baselines. Significant upgrades to the class
were to be called ‘‘Flights.’’
The DDG 51 class incorporated a number of
unique features to increase combat system per-
formance, improve survivability, and reduce
ship signatures. Except for the aluminum mast,
these ships are all steel, including the ship’s
superstructure. Its ‘‘seakeeping’’ hullform,
with a relatively wide beam and smaller than
traditional length-to-beam ratio, was selected to
Figure 5: DDG(X)Concept, 1984
NAVAL ENGINEERS JOURNAL 2009162 &The Story of AEGIS
Getting AEGIS to Sea: The AEGIS Ships
allow the ship to make high speeds in high sea
states before the onset of ship slamming. This
seakeeping hullform was selected to enable the
class to maintain speed with Soviet ships in the
North Atlantic. However, the stocky shape of
this hullform required greater horsepower for a
given speed than the slender hullform in the CG
47s. The stated operational requirement was for
a top speed in excess of 30 knots. Yet early
model basin tests showed that a top speed of
only 29 knots would be achieved with the
80,000 shaft horsepower installed in the CG 47s.
Consequently, the DDG 51 class LM 2500 ma-
rine gas turbine engines were up-rated 25%
from those aboard CG 47 to deliver 100,000
shaft horsepower to the propellers.
Significant passive ship survivability features
were also incorporated into DDG 51. Full
chemical–biological–radiological protection,
topside shaping to reduce radar cross section
(RCS), reduced radiated noise and infrared sig-
natures, and extensive armor to protect vital
spaces were key features of the ship’s design. The
Combat Information Center and Radio Rooms
were located inside the hull, rather than in tra-
ditional superstructure locations. Increased
resistance to nuclear blast overpressure was de-
signed into the ship’s structure.
The combat system represented a reduction in
capacity compared with CG 47. The DDG 51
class included one less illuminator (3 versus 4)
(one forward; two aft, one above the other), one
less 5 inch gun, no helicopter hangar, and no ro-
tating air search radar. The 5 inch gun fire
control system employed the AN/SPY-1D and
AN/SPS-67 radars to detect surface targets.
There were also two VLS Mk 41 MOD 0 (29
missile cells forward, 61 cells aft for a total of 90
cells compared with 122 cells in the CGs), two
PHALANX CIWS on the ship’s centerline (one
forward and one aft), and two 4-canister HAR-
POON launchers.
The first six ships of the class were built with the
Baseline 4 AEGIS Combat System, the same sys-
tem that was designed, installed, tested, and
delivered in the last new construction CG 47s.
The AEGIS SPY-1D system included four arrays
in a consolidated deckhouse called the Vital
Tower with the faces at 451 to the centerline, and
a smaller transmitter than the CG 47. The Vital
Tower permitted the ship’s design to include one
set of AEGIS transmitters and receivers versus
the two sets required by the fore/aft separated
arrays in CG 47’s design. The coverage of the
four arrays from the Vital Tower was enabled by
locating the marine gas propulsion turbine up-
takes on the ship’s centerline versus to port and
starboard, above the turbines, as in CG 47’s de-
sign. This configuration introduced two bends
into the uptakes not found on CG 47. These
bends as well as the uptakes themselves were
designed to minimize pressure drop in the tur-
bine exhaust so that the Main Propulsion
Turbines could perform at full power.
During contract design, several studies on the
impact of adding a helicopter hanger were con-
ducted, but the increases in ship cost and
displacement exceeded the Secretariat’s goals.
Thus, the Navy decided to provide only a land-
ing zone and in-flight refueling for SH-2 and SH-
60 helicopters. Figure 6 illustrates the configura-
tion of USS ARLEIGH BURKE and DDG 51
Flight I ships. As a result of Congressional pres-
sures to increase helicopter capability in the
class, a small torpedo rearming magazine and
on-deck helicopter refueling was added in DDG
52 and follow ships.
The topside configuration of DDG 51 was stud-
ied extensively during preliminary design. The
superstructure shape required special design at-
tention to avoid interference with the AN/SPY-
1D array beams, which overlapped the center-
line by 51 and depressed 51 below the horizon.
Avoiding radar side lobe effects also drove top-
side configuration. These requirements resulted
in locating the Vital Tower high enough for the
aft beams to clear the transom and aft decks. The
centerline stack shrouds were trapezoidal in
shape, with the aft stack narrower than the for-
ward stack, to clear the beams in the crossover
position. The minimum height above baseline
NAVAL ENGINEERS JOURNAL 2009 The Story of AEGIS &163
for the arrays was based on the desired radar
horizon.
The Design and Construction contract for
ARLEIGH BURKE was awarded to Bath
Iron Works in April 1985. As with CG 47,
Design Budgeting was employed in the DDG
51 contract. This again permitted an additional
year of combat system integration and develop-
ment before release to the shipbuilder for
incorporation into the ship. Design Budgeting
reduced the risk, cost, and time required to
integrate the AEGIS Weapon System into the
DDG 51.
The DDG 51 design goal to significantly reduce
RCS resulted in a radically different ship pro-
file—where all the hull and superstructure sides
were sloped in a way not normally seen on pre-
vious warships. However, the original ship’s mast
was a conventional ‘‘pole’’ mast with many stan-
dard structural shapes forming a stiffened four
legged mast. This abrogated much of the RCS
reduction obtained from sloping the superstruc-
ture and hull. The actual mast configuration was
issued as a ‘‘guidance’’ drawing in the shipbuild-
ing contract; only the locations of the equipment
on the mast were ‘‘nondeviational.’’ As a part of
the Navy’s first comprehensive post award engi-
neering effort to reduce ship signatures
(especially RCS), PMS 400, along with NAVSEA
05, the Office of Naval Research, Bath Iron
Works and their design agent, Gibbs and Cox,
studied available geometric shapes and arrange-
ments capable of meeting the mast equipment
locations and strength requirements while effect-
ing a dramatic reduction in RCS. The new mast
was also required to meet the same shock, vibra-
tion, and strength requirements of the original
mast concept. Several mast configurations with
sloped or tapered structural elements were inves-
tigated. One approach was a trussed square mast
trunk. This approach allowed sufficient support
for platforms and placed yardarms in the correct
locations, but did not gain the RCS reduction
desired. A further iteration turned the faces of the
mast trunk with the points forward and aft and
toward the beam and increased the mast slope.
This distinctive mast design chosen by the AEGIS
Project Office met the RCS goals, as well as
structural and antenna location requirements.
The unique topside appearance in DDG 51
prompted a shipbuilder’s comment to ADM
Burke and his wife Roberta that the ship,
‘‘appeared to be making 31 knots while tied fast
to the pier.’’ Admiral and Roberta Burke are
shown at the DDG 51 commissioning, July 4,
1991, in Figure 7.
Figure 6: DDG 51 Flight I Configuration
NAVAL ENGINEERS JOURNAL 2009164 & The Story of AEGIS
Getting AEGIS to Sea: The AEGIS Ships
The large number and locations of topside emit-
ters required extensive evaluation to avoid
radiation interference between emitters as well
as radiation hazards to personnel and ordnance.
The location of the VLS cells required analysis
of missile fly out patterns, particularly for
TOMAHAWK missiles, to avoid excessive
heat and pressure against the deckhouse struc-
ture and topside equipment. The close
working relationship between the combat
system engineer (RCA), Bath Iron Works, and
Navy laboratories, fostered by AEGIS Project
Office leaders, made this complicated task
successful.
DDG51FLIGHT II (DDG 72^78)To meet program cost and ship displacement re-
quirements, the Navy decided during Flight I
preliminary design that the Shipboard Signal
Exploitation System (SSES) would not be incor-
porated into DDG 51. The logic behind this
decision was the same as the decision not to in-
corporate a helicopter hangar, namely other
battle group ships such as the DD 963s had this
capability. However, as the DD 963s reached
their midlife, the Navy realized that planned
early retirements of these ships would affect
SSES assets and decided to incorporate the ca-
pability into the DDG 51 class. OPNAV
approved the plan to incorporate SSES and other
new capabilities into the last ship authorized in
Fiscal Year 1992 and named this configuration
DDG 51 Flight II.
The Flight II upgrade added Combat DF, the lat-
est SSES version. Of all the changes in Flight II,
this had the largest impact on the ship since, in
addition to numerous sensors that were inte-
grated into the ship’s topside, it required
accommodations for nine additional crew to
maintain and operate the system. Other changes
included the addition of the Joint Tactical Infor-
mation Distribution System or JTIDS, AN/SLQ-
V(3) (versus the V(2)), track initiation processor
(TIP), and reverse osmosis desalinators. To in-
troduce these upgrades in the midst of serial ship
construction, Fiscal Year 1991 Advanced Pro-
curement Funds were used to initiate detailed
design at the shipyards a year before the first
Flight II ship was appropriated. This allowed in-
troduction of the upgrades in the last Fiscal Year
1992 ship and eliminated the cost and schedule
Figure 7: ADM Arleigh and Roberta Burke atDDG 51 Commissioning, July 4, 1991
NAVAL ENGINEERS JOURNAL 2009 The Story of AEGIS &165
risk of concurrent design and construction.
DDG 72 was the first Flight II ship. Since the
impacts of all but Combat DF were relatively
minor, the first Fiscal Year 1992 ship, DDG 68,
actually received all of the other Flight II up-
grades.
DDG51FLIGHT III (PROPOSED)In April 1988, OPNAV tasked NAVSEA to in-
vestigate the cost and feasibility of incorporating
various upgrades into the DDG 51 class begin-
ning in 1994 or 1995 without disrupting serial
construction at either the Bath Iron Works or
Ingalls building yard. Based on CNO guidance,
the following priorities were established for
Flight III: (1) commonality with Flight II; (2)
upgraded combat system capability; (3) man-
ageable risk; (4) survivability; (5) Battle Group
interoperability; (6) speed and endurance; (7)
design flexibility and growth; and (8) habitabil-
ity. Three levels of major concepts were
developed:
&Level I with limited combat and HM&E sys-
tem upgrades and maximum commonality
with Flight II DDG 51s;
&Level II with increased hull length and the ad-
dition of 32 vertical launch cells, a helicopter
hangar and maintenance facilities, Warfare
Commander and additional combat system
upgrades;
&Level III which expanded on the Level II up-
grades by incorporating the AN/SQQ-89(I)
Block 3 sonar and integrated electric drive.
NAVSEA took a six-step approach to define the
most affordable and capable alternative for
Flight III:
&The entire NAVSEA R&D Master Plan was
reviewed and meetings between PMS 400 and
developers of candidate systems were held to
evaluate risk and determine their readiness for
integration into Flight III.
&A risk assessment process was employed to
define development and integration risks and
to permit risk ranking of all candidate up-
grades.
&Bimonthly, face-to-face meetings with an
oversight flag panel, including OP-03,
were held to keep the evolving design in
line not only with the operational require-
ments but also the cost and schedule
requirements.
&Engineering of Flight III was performed by
NAVSEA in close cooperation with the AEGIS
Shipbuilding Program.
&Warfighting assessments of both active and
passive systems proposed for candidate Flight
III configurations were conducted at the Battle
Group level and Flight III upgrades were
ranked by their contribution to Battle Group
success.
&NAVSEA 017 provided all cost and price
evaluations.
A total of 16 alternative configurations were
considered, across the spectrum of Levels I, II,
and III. OPNAV selected the Level II configura-
tion as the most capable and affordable
alternative. This configuration incorporated a
helicopter hangar for two LAMPS Mk III heli-
copters, an additional 32 VLS cells, added
Warfare Commander facilities, and other com-
bat system upgrades. The final configuration
was generally recognized as an approach toward
achieving the long sought strike cruiser, sans nu-
clear power.
The Flight III, Level II ship concept was 40 feet
longer than Flight II. The hangar required 28 feet
and the added VLS cells forward required 12 feet
of hull lengthening. While many hull lengthen-
ing alternatives were studied, the so-called
‘‘Plug and Slide’’ concept was adopted. This
concept added a shell plug at the hull’s maxi-
mum station where the hull lines are parallel to
the ship’s centerline and baseline. Forward and
aft of this parallel midbody, the lines were iden-
tical to Flight II. To provide arrangeable volume
where the hangar and missiles were to be lo-
cated, existing subdivisions were relocated
within the lengthened hull and the new
arrangeable volume was located exactly where
required. Figure 8 depicts the ‘‘Plug and Slide’’
technique.
NAVAL ENGINEERS JOURNAL 2009166 & The Story of AEGIS
Getting AEGIS to Sea: The AEGIS Ships
The 28-foot added length and the hangar struc-
ture aft of the ship’s vital tower created blockage
of the aft facing SPY arrays. The aft SPY faces
were raised one deck level to eliminate this
blockage and provide beam clearance for the
extended hull and hangar. This innovative solu-
tion eliminated the need of a major redesign of
the ship’s vital tower.
Figure 9: DDG 51 Flight III Proposed Configuration
Figure 8: ‘‘Plug and Slide’’ Technique for DDG 51Flight III Concept
NAVAL ENGINEERS JOURNAL 2009 The Story of AEGIS &167
PMS 400 and NAVSEA created a complete
feasibility design for the Flight III Level II ship,
Figure 9, and presented it to the CNO’s Ship Char-
acteristics Improvement Board (SCIB) in spring of
1989. The ship was approved by the SCIB but
with the dissolution of the Soviet Union in 1991,
the Navy decided not to build Flight III ships.
DDG51FLIGHT IIA (DDG79^112)As the result of changing world and threat con-
ditions in the wake of the collapse of the Soviet
Union, the CNO initiated the Destroyer Variant
(DDV) study in 1991 to evaluate a wide range of
destroyer designs from low-end non-AEGIS
ships to high-end ships similar to DDG 51
Flight III. Ten ship variants were developed and
assessed. They covered a range of capabilities
from 8 to 128 VLS cells. One of this article’s
references, Scott and Moak (1994), describes
these variants in more detail. The study resulted
in direction from the CNO to design and con-
struct DDG 51 class Flight IIA ships beginning
with the last ship appropriated in Fiscal Year
1994 to meet the Navy’s peacetime forward
presence and warfighting requirements of the
21st Century. Flight IIA was to be based on the
Flight II configuration.
The specific CNO direction for Flight IIA ship
characteristics was as follows:
&Aviation Facility: Add a dual helicopter facil-
ity including hangar and ammunition stowage
compatible with existing flight deck arrange-
ment and capable of Level I/Class I handling
of two SH-60B helicopters (one ASW LAMPS
Mk III SH-60 and one general purpose armed
SH-60).
&Combat Systems: Remove the HARPOON
weapon system and AN/SQR-19 passive
acoustic array and associated equipments.
Delete the CIWS mounts, and replace with
Evolved NATO SEA SPARROW missile if its
development progress permits. Maintain the
ability to reconstitute the SQR-19 and HAR-
POON if needed.
&HM&E: Make appropriate and affordable
changes from the candidates identified in the
DDV study, which included shifting to fiber
optics where appropriate.
As a result of CNO’s direction, the AEGIS Ship-
building Program and NAVSEA created a
contract design for Flight IIA with the following
specific changes from Flight II:
&Added dual helicopter facility with mainte-
nance and ammunition stowage capable of
Level I Class 1 handling for two SH-60B heli-
copters.
&Extended the transom 5 feet to enlarge the
flight deck.
&Raised the aft Vertical Launcher one deck
level and positioned the launcher hatches flush
with the top of the hangar.
&Added the RAST System and a Landing Sta-
tion Officer station.
&Added an enclosed Helicopter Control Station.
&Raised the aft facing SPY arrays 8 feet, as in
Flight III.
&Added a stern flap extending aft of the tran-
som, to regain the speed lost from added
weight.
&Reduced superstructure scantlings and in-
creased ship bottom scantlings to lower ship’s
center of gravity.
&Added five blast-hardened bulkheads in the
midship area.
&Added DC Wirefree Communications.
& Shifted from copper to Fiber Optics Data
Multiplexing System.
&Redesigned the electrical distribution
system to a zonal electric distribution config-
uration.
&Eliminated one collective protection system
zone.
&Removed at-sea missile handling systems in-
cluding VLS strike-down cranes and
associated handling equipment.
&Replaced existing air conditioning and refrig-
eration units with non-CFC units.
&Upgraded the solid waste management sys-
tem.
&Removed HARPOON weapon system
and all associated equipment
(reconstitutable).
NAVAL ENGINEERS JOURNAL 2009168 & The Story of AEGIS
Getting AEGIS to Sea: The AEGIS Ships
&Removed the AN/SQR-19 passive acoustic
array (reconstitutable).
&Retained both CIWS mounts because verti-
cally launched Evolved SEA SPARROW
missile was not ready.
The ‘‘foundation move’’ that made Flight IIA
feasible and affordable was eliminating reduced
radar coverage aft created by the hangar struc-
ture by merely raising the aft facing SPY arrays
one deck level. This relocation gives the Flight
IIA ships their distinctive profile with the for-
ward and aft facing arrays at different heights.
This approach, shown feasible during the Flight
III study, enabled the Navy to add the helicopter
hangar to the ship without an extensive redesign
of the ship’s arrangements or combat system ar-
chitecture.
Detailed design of Flight IIA began 2 years be-
fore the ship construction contract was signed.
Advanced procurement funds financed the ship-
builder’s detailed design beginning in 1992 and
eliminated design and construction concurrency
in the first Flight IIA ship, DDG 79, USS OSCAR
AUSTIN, shown in Figure 10. All DDG 51 class
ships that follow DDG 79 are Flight IIA ships.
However, a variety of combat and HM&E
upgrades have been incorporated into these
ships since.
InternationalAEGISProgramsThe capability of the AEGIS Weapon System to
defend itself and the battle group, the measured
evolution of the system in baselines of higher
levels of performance and the success of the
US AEGIS shipbuilding programs were recog-
nized by our allies as achievements to be
incorporated into their own navies. In 1988,
Congress approved the first sale of an AEGIS
Weapon System to the Japanese Maritime Self-
Defense Force. Since that time, Foreign Military
Sales programs have resulted in the sale of
AEGIS to navies in Spain, the Republic of Korea,
Norway, and Australia.
The Japanese Maritime Self-Defense Force has
built four KONGO-class AEGIS destroyers,
Figure 12: Spain’sALVARO DE BAZANAEGIS Frigate in Syd-ney Harbor
Figure 11: Japan’s1st AEGIS Ship, theDestroyer JDSKONGO
Figure 13: Nor-way’s FRIDTJOFNANSEN AEGIS Frig-ate
Figure 10: USSOSCAR AUSTIN, theFirst DDG 51 FlightIIA Ship
NAVAL ENGINEERS JOURNAL 2009 The Story of AEGIS &169
shown in Figure 11, which are quite similar in
appearance to DDG 51. The Spanish Navy is
building the ALVARO DE BAZAN (F100)
AEGIS frigates, Figure 12. The lead ship entered
service in 2002 and the sixth ship is scheduled to
enter service in 2012. The Royal Norwegian
Navy has authorized five FRIDTJOF NANSEN-
class AEGIS frigates, Figure 13, to enter service
between 2006 and 2010. These ships are deriva-
tives of the Spanish Navy F100. The Republic Of
Korea has authorized the KDX III destroyers,
which are similar in appearance to DDG 51. The
first ship, KING SEJONG THE GREAT, Figure
14, was commissioned in 2008, with three ships
to follow and options for three more. The Royal
Australian Navy Air Warfare destroyer, recently
announced as a variant of the Spanish Navy
F100, will incorporate AEGIS and provide the
Royal Australian Navy with a greatly enhanced
air defense capability. An artist’s concept is
shown in Figure 15.
ConclusionBuilding the AEGIS ships required an evolution
in organization and processes to match their un-
precedented integration of ship and combat
systems. Each of the project’s partners was given
responsibility and accountability for their role in
getting AEGIS to sea. OPNAV was an active
participant throughout and even had its own
AEGIS Program Office code, ‘‘PMS 400Z.’’
Contracts rewarded excellence and cooperation.
Doing the difficult job of systems engineering up
front avoided classical problems commonly en-
countered in major shipbuilding programs. The
‘‘cradle-to-grave’’ charter and organization of
the AEGIS project instilled the long view in all
players. The AEGIS Project Office was unques-
tionably in charge, and was the final arbiter of
disputes between the shipbuilders and combat
system developers. The decisions made were ul-
timately what were best for the nation, not any
single contractor or government organization.
As stated by the Honorable Sean Stackley, As-
sistant Secretary of the Navy for Research,
Development, and Acquisition (himself a retired
naval officer with shipbuilding experience), at
the October 17, 2008, Christening ceremony of
USS WAYNE E. MEYER:
At the peak of this Cold War, our Navy sought to
put to sea a weapon system that would command
the seas, wherever East met West. So, after having
served his Nation with distinction for over a quar-
ter-century, Wayne E. Meyer was given the task of
bringing this vision—AEGIS—to reality. And for
the next 13 years, RADM Meyer would lead
America’s best and brightest and would turn our
great industrial might into great military might.
RADM Meyer’s goal was to deliver a 100% war-
ready ship to the fleet on schedule, within bud-
get, manned by a trained crew, and supported by
the Navy. This monolithic goal inculcated ev-
eryone on the project. The processes developed
and efforts exerted by the project, including its
developers and constructors, and led by the AE-
GIS Project Office, made this goal a reality. It is
worth remembering how and why these pro-
cesses and organizations were brought about
Figure 14: Korea’sKING SEJONG THEGREAT AEGISDestroyer
Figure 15: Artist’sConcept for Austra-lia’s Air WarfareDestroyer, WhichWill Carry the AEGISWeapon System
NAVAL ENGINEERS JOURNAL 2009170 &The Story of AEGIS
Getting AEGIS to Sea: The AEGIS Ships
when embarking on future shipbuilding pro-
grams, lest those assigned have to relearn
decades worth of lessons by trial and error.
AcknowledgmentsThe authors would like to acknowledge the con-
tributions of Robert Scott and Jerry Fee in
writing this article, and those of Jerry Fee in ed-
iting this article.
ReferencesBaker, A.D. III, Combat Fleets of the World 1998–1999,
Naval Institute Press, Annapolis, MD, 1998.
Couhat, J.L., Combat Fleets of the World 1980/81,
Naval Institute Press, Annapolis, MD, 1980 (English
translation by A. D. Baker III).
Defense Update. ‘‘Israel’s Littoral Combat Ship Program
(LCS-I),’’ November 14, 2007.
Federation of American Scientists website. Available at
http://www,fas.org/man/dod-101/sys/ship/arsenal_
ship.htm, accessed March 2009.
Scott, R. and Moak K., ‘‘Studies of helicopter capable
DDG 51 variants,’’ ASNE Naval Engineers Journal, Vol.
106, No. 5, p. 33, September 1994.
Shackleton, D., ‘‘Choices and consequences-choosing
the AWD design,’’ Australian Defense Magazine, Febru-
ary 2007.
Sims, P., ‘‘Bulging merchant ships,’’ Naval Engineers
Journal, Vol. 119, No. 3, 2007.
Stepanchick, J. and A. Brown, ‘‘Revisiting DDGX/DDG 51concept exploration,’’ Naval Engineers Journal, Vol. 119,
No. 3, 2007.
AuthorBiographiesRandy Fortune was born in Richmond, VA, and
attended Virginia Tech where he received Bach-
elor and Master of Science degrees in
Engineering Mechanics in 1968 and 1970, re-
spectively. In 1971, Mr. Fortune began his Navy
career at Naval Ship Research and Development
Center, Carderock, MD, where he developed
and applied total ship survivability assessment
techniques to early stages of surface ship design
to improve battle survivability. In 1980, he
joined RADM Meyer in PMS 400 as Design
Budget Manager and Ship Systems Engineer
during design, construction, and testing of
CG47, USS TICONDEROGA. In 1983, Mr.
Fortune transferred to the DDG 51 Program
where he was PMS 400’s systems engineer dur-
ing contract design of the lead ship of the DDG
51 class. Following award of lead ship to Bath
Iron Works, he led all navy participation, con-
trol, and monitoring of the shipbuilder’s detail
design. In 1989, Mr. Fortune was selected as
Deputy Program Manager of the Arleigh Burke
Shipbuilding Program where he led the Navy
enterprise in design, construction, test, delivery,
and commissioning of 46 of the 62 ships in the
DDG 51 class. He introduced several innovative
shipbuilding acquisition strategies, including
Negotiated Allocation, Competitive Allocation,
and Multi-Year contracting. He established and
executed procedures to monitor and control all
shipbuilder detail design and construction ef-
forts in the DDG 51 program while introducing
three flights and seven combat system baselines.
In 1999, Mr. Fortune was awarded the ASNE
Gold Medal for his sustained leadership of the
DDG 51 Program and introduction of Flight
IIA. Mr. Fortune retired from civil service in
2005 and joined AMERICAN SYSTEMS as
Vice President of Integrated Shipbuilding
Programs.
Captain Brian T. Perkinson, USN (Ret.), was
born and raised in Waterbury, CT. He graduated
from the United States Naval Academy in June
1963 and retired from active duty in June 1993.
He joined Northrop Grumman Ship Building on
March 1, 2000 as Director of the Washington
Technical Office. In May 2003 he was promoted
to Deputy Program Manager, DDG 1000
Program.
He reported to his first ship, USS SOLEY
(DD 707), in Jeddah, Saudi Arabia, serving as
Communications and Electronics Officer.
After graduation from the Naval Destroyer
School in 1965, he was assigned to USS
HARLAN R. DICKSON (DD 708) as Chief
Engineer. He was reassigned to Commander
Destroyer Squadron 24 in 1967 as Staff
NAVAL ENGINEERS JOURNAL 2009 The Story of AEGIS &171
Engineer and was selected as an Engineering
Duty Officer in April 1969.
Attending the Naval Postgraduate School in
Monterey, CA, he was awarded a Master of
Science in Mechanical Engineering in 1972 and a
Master of Science in Financial Management in
1973. He then reported to Supervisor of
Shipbuilding, USN, Newport News, VA as the
Surface Ship Engineering and Quality Assurance
Officer. He subsequently transferred to the Staff,
Commander in Chief, US Pacific Fleet, Pearl
Harbor serving as Maintenance Plans and Policy
Officer. Reporting to the AEGIS Shipbuilding
Project, Naval Sea Systems Command,
Washington, DC in August 1979, he was
assigned as Production Officer for CG 47 Class
AEGIS ships. In October 1983, he reported to
the staff of the Assistant Secretary of the Navy
(Shipbuilding and Logistics) as Deputy Director
of Shipbuilding. In January 1986, he was reas-
signed as the AEGIS Destroyer Program
Manager responsible for the design and con-
struction of the ARLEIGH BURKE (DDG 51)
Class. After its commissioning (DDG 51) on
July 4, 1991, he was reassigned as the Security
Assistance Program Manager, responsible for all
foreign military sales in the Naval Sea Systems
Command.
Captain Perkinson was awarded the Legion of
Merit with Gold Star, the Meritorious Service
Medal with Gold Star, and the Navy Commen-
dation Medal. He is also a registered
Professional Engineer (Mechanical) in the State
of California.
After retiring from the US Navy, Mr. Perkinson
joined a naval architectural firm as Director of
Programs and was responsible for their USN and
international programs.
Robert C. Staiman graduated from the Univer-
sity of Florida in 1960 with a Bachelor’s Degree
in Mechanical Engineering. In 1966, after 6
years with the Army Corps of Engineers, Mr.
Staiman began his Navy career in the Machinery
Systems Division of the Naval Ship Systems
Command. At the Naval Ship Systems Com-
mand he worked in various engineering
positions before becoming the Machinery Sys-
tems Engineer for the IIN DDG 998 Ship
Design in 1974. In 1976 he was assigned as the
Deputy Ship Design Manager and Systems En-
gineer for the DDG 47 Ship Design
(redesignated as CG 47). In 1980 he was named
CG 47 Ship Design Manager and was respon-
sible for the design of follow-on flights, the
monitoring and approval of the shipbuilder s
detail design and construction, as well as pro-
viding support for ship trials. In 1987 he was
selected as Division Director of the Combatant
Ships Design Management Division where he
was responsible for the technical supervision of
all Combatant Ship Design Managers, including
the CG 47 and DDG 51 Ship Design Managers.
While in this position Mr. Staiman was also
assigned as the US Design Director for the
NATO Frigate (NFR 90) Project from 1989 to
1990. In 1991 Mr. Staiman transferred to the
Amphibious, Auxiliary and Special Ships Design
Management Division as Division Director with
similar ship design manager responsibilities. Mr.
Staiman retired from the Naval Sea Systems at
the end of 1993 and joined John J. McMullen
Associates (JJMA) as a Program Manager re-
sponsible for the technical management of all
design contracts with NAVSEA. Mr. Staiman
retired from JJMA in 2003 and became a private
consultant working with JJMA on the DDG
1000 Program. He retired for the third time in
July 2004 and now resides in Virginia and
spends the winters in South Florida.
NAVAL ENGINEERS JOURNAL 2009172&The Story of AEGIS
Getting AEGIS to Sea: The AEGIS Ships