geotechnical investigation report part-2 - … · table 12: estimated capacity of precast r.c.c....

333
BANGLADESH-INDIA FRIENDSHIP POWER COMPANY (PVT.) LIMITED 2x660MW MAITREE SUPER THERMAL POWER PROJECT RAMPAL, BANGLADESH OWNER’S CONSULTANT: M/s FICHTNER GmbH & Co KG. STUTTGART, GERMANY GEOTECHNICAL INVESTIGATION REPORT PART-2 COAL HANDLING/COAL STOCK AREA DOC. NO. : - Maitree-00-UTX-ED-421602C001PEM-B BHARAT HEAVY ELECTRICALS LIMITED PROJECT ENGINEERING MANAGEMENT NOIDA-201301 C TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

Upload: hoangdieu

Post on 09-Jun-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • BANGLADESH-INDIA FRIENDSHIP POWER COMPANY (PVT.) LIMITED

    2x660MW MAITREE SUPER THERMAL POWER PROJECT RAMPAL, BANGLADESH

    OWNERS CONSULTANT:

    M/s FICHTNER GmbH & Co KG. STUTTGART, GERMANY

    GEOTECHNICAL INVESTIGATION REPORT

    PART-2

    COAL HANDLING/COAL STOCK AREA

    DOC. NO. : - Maitree-00-UTX-ED-421602C001PEM-B

    BHARAT HEAVY ELECTRICALS LIMITED PROJECT ENGINEERING MANAGEMENT

    NOIDA-201301

    C

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • House 11, Road 19/A, Sector 04,Uttara Model Town, Dhaka 1230

    Phone +880-2-58957231, Fax +880-2-58957283

    Email: [email protected], Web: http://www.dcl-fcl.com

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    i

    T A B L E O F CO N T E N T S CHAPTER PAGETABLE OF CONTENTS ....................................................................................................................... i

    LIST OF TABLES............................................................................................................................. iii LIST OF FIGURES .............................................................................................................................. iv CHAPTER - I INTRODUCTION ....................................................................................................... 1

    1.1 DESCRIPTION ............................................................................................................................ 1 1.2 SCOPE OF WORK ...................................................................................................................... 1

    1.2.1 FIELD INVESTIGATION WORK....................................................................................... 1 1.2.2 LABORATORY WORK ...................................................................................................... 2

    1.3 STRUCTURE OF REPORT......................................................................................................... 2 CHAPTER - II TOPOGRAPHIC & GEOLOGICAL SETTINGS ................................................. 3

    2.1 TOPOGRAPHY AND LANDSCAPE ......................................................................................... 3 2.2 REGIONAL GEOLOGY ............................................................................................................. 3 2.3 SEISMICITY ................................................................................................................................ 3

    CHAPTER- III INVESTIGATION METHODOLOGY ................................................................... 5 3.1 DRILLING OF BOREHOLES ..................................................................................................... 5 3.2 SPT TEST AND DISTURBED SAMPLE COLLECTION ......................................................... 5 3.3 UNDISTURBED SAMPLE COLLECTION ............................................................................... 6 3.4 MEASUREMENT OF GROUND WATER ................................................................................ 6 3.5 ELECTRONIC STATIC CONE PENETRATION TEST WITH PORE PRESSURE (CPT-U) . 6 3.6 FIELD VANE SHEAR TEST ...................................................................................................... 7 3.7 ELECTRICAL RESISTIVITY TEST .......................................................................................... 7 3.8 PLATE LOAD TESTS.................................................................................................................8

    CHAPTER-IV INVESTIGATION RESULTS ................................................................................... 9 4.1 CLASSIFICATION OF SOIL ...................................................................................................... 9 4.2 SUMMARY OF FIELD INVESTIGATION ...............................................................................9 4.3 LABORATORY TEST ..............................................................................................................11 4.4 GEOTECHNICAL PROPERTIES ............................................................................................. 11

    4.4.1 SOIL GRADATION ........................................................................................................... 11 4.4.2 SOIL PLASTICITY ............................................................................................................ 12

    4.5 Correction to SPT-N value: ........................................................................................................ 12 CHAPTER-V ANALYSIS & RECOMMENDATIONS ................................................................... 14

    5.1 GENERAL.................................................................................................................................. 14 5.2 ANALYSIS FOR FOUNDATION SYSTEM ............................................................................ 14

    5.2.1 DESIGN SOIL PROFILE ................................................................................................... 14 5.3 ANALYSIS FOR SHALLOW FOUNDATION ........................................................................ 14

    5.3.1 BEARING CAPACITY ...................................................................................................... 14 5.4 DEEP FOUNDATION ............................................................................................................... 14

    5.4.1 BORED CAST-IN SITU PILES & DRIVEN CAST IN SITU PILE: ................................ 14 5.4.2 ANALYSIS BORED CAST-IN-SITU PILES .................................................................... 15 5.4.3 SIDE RESISTANCE FOR CAST-IN-SITU PILES ........................................................... 15 5.4.4 TIP RESISTANCE FOR CAST-IN-SITU PILES .............................................................. 16 5.4.5 ESTIMATED PILE CAPACITY FOR CAST-IN-SITU PILES ......................................... 16

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    ii

    5.4.6 ESTIMATED PILE CAPACITY FOR CAST-IN-SITU PILES ......................................... 17 5.4.7 ANALYSIS OF PRECAST DRIVEN PILES ..................................................................... 18 5.4.7.1 SIDE RESISTANCE FOR DRIVEN PILES ................................................................... 18 5.4.7.2 TIP RESISTANCE FOR DRIVEN PILES ...................................................................... 18 5.4.8 ESTIMATED PILE CAPACITY FOR PRECAST DRIVEN PILES ................................. 18 5.4.9 ESTIMATED PILE CAPACITY FOR PRECAST DRIVEN PILES ................................. 19 5.4.10 ESTIMATED PILE CAPACITY FOR PRECAST PSC HOLLOW CORE CONCRETE PILES ........................................................................................................................................... 19

    CHAPTER VI ANALYSIS FOR LIQUEFACTION POTENTIAL ............................................... 21 6. 1 EXCAVATION, COMPACTION, AND GROUND IMPROVEMENT CRITERIA: ............. 21

    I. SUITABILITY OF ON SITE SOIL AS STRUCTURAL FILL ...........................................21 II. SLOPES FOR EXCAVATION: .......................................................................................21 III. CEMENT FOR UNDERGROUND FOUNDATIONS/STRUCTURES:.........................21 IV. GROUND IMPROVEMENT ...........................................................................................21

    6.2 METHODS FOR ANALYSIS OF LIQUEFACTION POTENTIAL ........................................ 22 6.2.1 GENERAL .......................................................................................................................... 22 6.2.2 METHOD ............................................................................................................................ 22 I. CALCULATION OF CYCLIC STRESS RATIO ................................................................22 II. CALCULATION OF CYCLIC RESISTANCE RATIO ..................................................22

    6.3 ANALYSIS OF RESULT .......................................................................................................... 23 CHAPTER VII REFERENCES ........................................................................................................ 24 CHAPTER-VIII RECOMMENDATIONS & CONCLUSIONS ..................................................... 25

    8.1 RECOMMENDATIONS FOR FOUNDATION SYSTEM ....................................................... 25 8.2 RECOMMENDED PILE CAPACITY FOR BORED CAST-IN-SITU RCC PILES ................ 26 8.3 RECOMMENDED PILE CAPACITY FOR PRECAST DRIVEN PILES ................................ 26 8.4 RECOMMENDED PILE CAPACITY FOR PRECAST PSC HOLLOW CORE CONCRETE PILES ............................................................................................................................................... 26 8.5 RECOMMENDATIONS FOR CHEMICAL ANALYSIS ........................................................27

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    iii

    LIST OF TABLES

    TABLE PAGETABLE 1: LOCATION COORDITATES & GROUND ELEVATION OF BORE HOLES ................ 9

    TABLE 2: TEST LOCATIONS FOR ISCPT ....................................................................................... 10

    TABLE 3: TEST LOCATIONS FOR IDCPT ...................................................................................... 10

    TABLE 4: TEST LOCATIONS FOR IERT ......................................................................................... 10

    TABLE 5: TEST LOCATIONS FOR IPLT ......................................................................................... 11

    TABLE 6: LIST OF LABORATORY TESTS. .................................................................................... 11

    TABLE 7: CORRECTED SPT & DESIGN SPT VALUE ................................................................... 13

    TABLE 8: DESIGN SOIL PROFILE CONSIDERED ......................................................................... 14

    TABLE 9: ESTIMATED DRILLED SHAFT CAPACITY FOR DIFFERENT DIAMETER BASED

    ON SPT ................................................................................................................................................. 17

    TABLE 10: ESTIMATED DRILLED SHAFT CAPACITY FOR DIFFERENT DIAMETER BASED

    ON CPT (CUT OFF LEVEL 2.0M BELOW G.L) ............................................................................... 17

    TABLE 11: ESTIMATED CAPACITY OF PRECAST R.C.C. DRIVEN PILE (SQUARE SHAPED

    FOR DIFFERENT SIZE BASED ON SPT .......................................................................................... 19

    TABLE 12: ESTIMATED CAPACITY OF PRECAST R.C.C. DRIVEN PILE FOR DIFFERENT

    SIZE BASED ON SCPT (PILE TOP CONSIDERED AT 2M DEPTH FROM G.L).......................... 19

    TABLE 13: ESTIMATED CAPACITY OF PRECAST PSC HOLLOW CORE CONCRETE PILE

    FOR DIFFERENT SIZE BASED ON SPT (PILE CUT OFF LEVEL IS CONSIDERED AT GL) .... 20

    TABLE 14: RECOMMENDED PILE CAPACITY FOR BORED CAST-IN-SITU RCC PILES ...... 26

    TABLE 15: RECOMMENDED PILE CAPACITY FOR PRECAST DRIVEN PILES ...................... 26

    TABLE 16: RECOMMENDED PILE CAPACITY FOR PRECAST PSC HOLLOW CORE

    CONCRETE PILES .............................................................................................................................. 26

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    iv

    L I S T O F F I G U R E S FIGURE 1: AERIAL PHOTO OF THE PROPOSED SITE .................................................................. 3

    FIGURE 2: SEISMIC MAP OF BANGLADESH (BNBC 2006) .......................................................... 4

    FIGURE 3: ELECTRICAL RESISTIVITY TEST SET-UP .................................................................. 7

    FIGURE 4: SOIL GRADATION ENVELOPE .................................................................................... 12

    FIGURE 5: PLASTICITY OF SOIL SAMPLE ................................................................................... 12

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    CHAPTER - I I N T R OD U C TI O N

    1.1 DESCRIPTION

    This report presents report on Geotechnical Investigation (field and laboratory tests) including

    recommendation for proposed 2X660 MW MAITREE STPP, Rampal, Bagerhat. The whole

    report has been divided into three parts covering the following.

    Part 1: Main power block and Balance of Plant & Non-plant Areas

    Part 2: Coal Handling/Coal Stock Area

    Part 3: Ash Dyke Area < ii > Jetty Area

    This report has covered the Part 2: Coal Handling/Coal Stock Area. The project location

    map is shown in Fig-1.

    1.2 SCOPE OF WORK

    The scope of work is given hereunder:

    Performing geotechnical investigation including field tests on land and laboratory

    tests for disturbed/undisturbed soil samples, chemical analysis of soil and water

    samples.

    Preparing a Geotechnical Report based on engineering analysis to present the data

    obtained through investigation.

    Recommendation for foundation etc.

    1.2.1 FIELD INVESTIGATION WORK

    Field work including drilling and in-situ testing at various instructed locations has been

    carried out since March, 2016.

    The following list of the field work has been undertaken:

    Setting out test locations using and establishing their elevation from nearest survey

    benchmark as provided by BHEL using total station.

    Drilling using rotary drilling rig only.

    Performing Standard Penetration Test (SPT) using automatic trip hammer according

    to ASTM D1586.

    Recovering undisturbed soil samples from borehole according to ASTM D1587.

    Electronic Static Cone Penetration Test (SCPT) as per ASTM D5778.

    Conducting in-situ Vane Shear Test (VST) as per ASTM D2573.

    Conducting Electric Resistivity Test (ERT) as per ASTM G57.

    Performing Plate Load Test (PLT) as per IS: 1888.

    Performing Pressure-meter Test (PMT) as per ASTM D4719.

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    Performing Dynamic Cone Penetration Test (DCPT) as per IS: 4968-II.

    Performing Pump out Type Field Permeability Test (POTFPT) as per IS: 5529-I.

    Performing Cross-hole Shear Test (CST) as per ASTM D4428.

    Performing Seismic Refraction Test (SRT) as per ASTM D 5777.

    1.2.2 LABORATORY WORK

    All soil samples were subjected to visual-manual soil classification procedures in accordance

    with ASTM D-2488. In order to evaluate the engineering properties of the sub-soil, laboratory

    tests were performed on selected soil samples obtained from exploratory boreholes.

    The following laboratory tests were performed by DCL at its Geotechnical Testing

    Laboratory in Uttara, Dhaka during April to August, 2016:

    Bulk Density/Unit Weight ASTM D7263

    Moisture Content Test ASTM D2216

    Particle Size Distribution ASTM D0422

    Atterberg Limits ASTM D4318

    Specific Gravity Test ASTM D0854

    Shrinkage Limit Test ASTM D 427

    Direct Shear Test ASTM D3080

    Consolidation Test ASTM D2434

    Unconfined Compression Strength ASTM D2166

    Standard Proctor Compaction Test ASTM D1557-70

    Modified Proctor Compaction Test ASTM D1557-12E1

    Relative Density Test ASTM D1556-64

    1.3 STRUCTURE OF REPORT

    The outcomes of the geotechnical investigations carried out on the project location have been

    divided into the following segments:

    Appendix A contains the layout for test location.

    Appendix B contains field test results

    Appendix C contains the laboratory test reports.

    Appendix D contains the analysis of results.

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2x660MW Maitree Super Thermal Power Project; Rampal, Bagerhat

    4

    RAMPAL COAL BASED

    POWERPLANT-[PROPOSED]

    CHAPTER - II T O P O G R A P H I C & G E O L O G I C A L S E T T I N G S

    2.1 TOPOGRAPHY AND LANDSCAPE

    The site is located at Rampal Upazilla under Bagerhat district. The site is proposed to be

    used as 2 X 660 MW Maitree Super Thermal Power Project on the north-east bank of river

    Pussur. The plot is fairly flat with dredge filling, of which a part is bounded by masonry

    boundary wall. The site is accessible through a feeder road.

    2.2 REGIONAL GEOLOGY

    xviii. Geological map of Bangladesh published by Geological Survey of Bangladesh (GSB) indicates that this area falls under Zone PPC (Paludal deposits) and this area is

    subsiding.

    Figure 1: Aerial Photo of the Proposed Site

    R U P S H A R I V E R

    3

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2x660MW Maitree Super Thermal Power Project; Rampal, Bagerhat

    Geomorphology During periods of maximum glaciation, marine regression led to increasederosional processes whereas Holocene transgression revitalized the sedimentationprocesses. Thus Geomorphologically, Bangladesh can be divided into four distinct regionseach having distinguishing characters of its own. a) The Holocene Floodplains of the Ganges, the Brahmaputra and the Meghnariver systems. b) The Bengal Delta. c) The Eastern and Northeastern Tertiary Hills Regions. d) The Pleistocene Terrace or the Pleistocene Uplands. The Flood plain and the Bengal Delta regions occupy seventy two (72) percent of the total land area of Bangladesh and the Pleistocene Terrace and the Tertiary Hills Regions cover rest 28% (Ref: Report of the ground water task force,ministry of Local Government, Rural Development and Local GovernmentDivision,2002). The project site locates in the southern part of the Delta plain. This area is tidedominated and is considered as the active part of the delta. The landforms are characterized by tidal low land with weakly developed natural levees distributed in an irregular pattern. Numerous rivers, channels, tidal creeks have criss-crossedthe area. Swamps and depressions are also present in the area. Estuarine depositsof silt, silty clay dominates in this area. The landforms in the area are temporal as they are changing due to the cyclonesand other natural calamities.

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    Figure 2: Seismic Map of Bangladesh (BNBC 2006) 2015)

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    C H A P T E R - I I I I N V E S T I G AT I O N M ET HO D O L O GY

    Following describes in brief each of the field works undertaken in the geotechnical

    investigation at the proposed location.

    3.1 DRILLING OF BOREHOLES

    Boreholes have been drilled by rotary boring methods using a bladed bit to produce a

    nominal diameter for 150mm. Flushing of the hole was achieved by the addition of bentonite

    to form a mud of sufficient density to lift soil cutting satisfactorily. Careful attention was

    given to drilling rates with slow rotation speeds and a slow bit advance to ensure that soil

    particles cut by the bit was able to rise in bentonite mud column and thus ensure a 'clean' base

    to the bore hole. Casing of 150 mm diameter was used in the uppermost few meters of each

    boring.

    3.2 SPT TEST AND DISTURBED SAMPLE COLLECTION

    Standard Penetration Test (SPT) according to ASTM D 1586 has been executed using

    automatic trip hammer at 1.0m intervals for first 5m and 1.5m interval for greater depths to

    determine relative density/consistency and classification of soil at different elevation

    inclusive collection of disturbed soil samples from each interval in accordance to the

    requirements of the specification of the Engineer. An exploratory boring with a diameter

    150mm was bored to the depth of the first test. A SPT sampler, connected with required

    length of BW size rod to a 63.5 kg hammer, is inserted in to the boring. SPT sampler is split-

    spoon sampler with a ball valve to permit exit of air or water from the top during driving and

    to assist in retaining sample during withdrawal; in addition, the sampler has a tapered shoe for

    allowing penetration in to the ground. The number of blows required to progress the sampler

    450 mm was recorded in three 150 mm intervals. The SPT N-value has been calculated by

    summing the hammer blows required to advance the sampler during the last two intervals of

    the test. The blow count for the first 150 mm was recorded; however, this number is ignored

    during the N-value since the soil immediately below the drilling rod is generally considered to

    be disturbed.

    When the test has been completed, the SPT sampler was withdrawn and opened. The

    amount of soil recovered in the sampler was recorded including its description. After that, the

    sample has been transferred to an airtight container. The uncorrected SPT results are shown in

    the borehole records. Disturbed samples from split spoon at all SPT location labelled and

    preserved in airtight container before transferring them to DCLs laboratory in Dhaka.

    Boring logs with SPT records has been enclosed in Appendix B-1.

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    3.3 UNDISTURBED SAMPLE COLLECTION

    Undisturbed Shelby tube sampling was under taken in drill holes as per ASTM

    D1587 of the contract document. An exploratory boring with a diameter 150mm was bored to

    the depth of the first test. A sampler, connected with a connector rod to a 63.5 kg (140 lb)

    hammer, has been inserted in to the boring. The Shelby sampler of 72mm diameter is an open

    drive sampler with holes on top to permit exit of air or water from the top during driving.

    When driving has been completed, the sampler rotated through two complete

    revolutions to shear the superficial deposits horizontally at the bottom; afterwards, the

    sampler was withdrawn. Next, the sample tube has been sealed on the both ends using three

    alternating layers of 20mm wax and aluminium foil and rubber capped. Sample tubes were

    properly labelled and a marking TOP was attached on the tube. All tubes were stored and

    transported vertically.

    3.4 MEASUREMENT OF GROUND WATER

    Water level inside the casing was measured for all boreholes 24 hour after completion

    of drilling. Measurement of water level was recorded by using a measuring tape and data was

    recorded. But it should be noted that this recorded data may not reflect long term ground

    water level due to the presence of perched water table, monsoon, and drilling operation.

    Therefore, recorded ground water data may not accurately reflect actual or long term ground

    water elevation.

    3.5 ELECTRONIC STATIC CONE PENETRATION TEST WITH PORE PRESSURE (CPT-U)

    Electronic Cone Penetration Testing was carried out using a 15cm2 projected area

    electronic cones with 60o apex angle and 225cm2 friction sleeve area advance using a 20Ton

    hydraulic penetrometer. A total of fifteen (15) out of fifteen (15) soundings (designated

    SCPT-1 through SCPT-10 and ISCPT-1 through ISCPT-5) were performed at selected

    locations. CPT tests were terminated 60m (maximum) below existing grade and tests were

    conducted in accordance to ASTM D 5778. Throughout the test the cone was advanced by

    applying thrust on 1m long 36mm diameter rod at a rate of 2.0cm/sec. After advancement of

    each 1m segment subsequent rod was attached and operation was repeated.

    The cone manufactured by GeoMil is a subtraction type cone equipped with

    instruments to measure (a) Cone Pressure, (b) Sleeve Friction, and (c) Dynamic Pore

    Pressure; furthermore, the cone is also equipped with two inclinometers to monitor its

    verticality at all times. Depth of the cone was recorded using an opto-electric encoder. All

    data was recorded for every centimetre automatically in a computer running proprietary

    software.

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    Prior to commencement of each test, the pressure transducer of the cone was saturated using

    silicon oil. The cone was calibrated prior to commencement and at the end of each test

    conforming to the specification using CPTest software (from GeoMil), this software also

    automatically recorded all data from the cone.

    After completion of the test all collected data has been plotted using CPTask

    software, which was also used to estimate engineering parameters from the in situ test data.

    This software has been used to estimate following engineering parameters: Friction Angle,

    Undrained Shear Strength, Relative Density, and Classification.

    CPT logs have been enclosed in Appendix B-2.

    3.6 FIELD VANE SHEAR TEST

    Field Vane Shear Test has been done for measuring the undrained shear strength

    parameter of cohesive soil by means of rotating a vane in boreholes.

    The test has been performed in a pre-drilled hole, pushing from the surface. A

    reaction casing was set to transfer forces to the torque head without twist or slippage. The

    drilling work was stopped at 750mm above test level to conform at least five times the outside

    diameter of the hole. The vane was advance from the bottom of the hole carefully in a single

    thrust to the test depth. The vane was pushed down without giving any blow, vibration, or

    rotation. No torque was applied to the rods during the thrust. Vane rod friction in this case

    was negligible.

    The time from the end of vane penetration to beginning rotation was no more than 5

    minutes. Keeping the vane at its position, the torque has been applied to the vane at a rate of

    0.1 deg/sec until failure.

    The test results have been presented in APPENDIX B-3.

    3.7 ELECTRICAL RESISTIVITY TEST

    Electrical resistivity tests was carried using a Chauvin-Arnoux (Model: CA6460) Soil

    Resistivity Meter at ground surface with electrode spacing of 0.5m, 1.0m, 2.0m 3.0 m, 4.0m,

    6m, 8m, and 10m utilizing the Wenner - 4 Pin method. Steel electrode pegs of 2m length were

    hammered into the ground at the required spacing and were connected to the resistance meter

    as detailed in the diagram below [ASTM G57 95(a)].

    Figure 3: Electrical Resistivity Test Set-up

    A low voltage 97 Hz square wave current was passed between the two (outer) current

    electrodes E, H. The detector measures the voltage drop between the two (inner) potential

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    electrodes ES, S, and compares this with internal standard resistors and indicates the

    resistance reading in ohms on a LCD display. Soil resistivity is then calculated using the

    following formula for the Wenner electrode configuration:

    ESSw dR 2 The test results have been presented in APPENDIX B-4.

    3.8 PLATE LOAD TESTS

    Plate bearing tests were performed in accordance with Indian Standard (IS 1888-82).

    A square steel plate 600x600mm size (25mm thick) was bedded horizontally onto the surface

    of the test location. Vertical loads were applied incrementally using a hydraulic ram reacting

    against the weight of a loaded Kentledge. Loads were determined by reference to a calibrated

    pressure gauge connected to the hydraulic ram. Settlement of the test plate was monitored

    using two 50mm travel, 0.01mm division dial gauges spaced equally around the plate

    perimeter and mounted on an independent tubular reference frame shaded from direct sunlight

    and protected from disturbance by wind.

    Initial seating loads were then applied to give some compensation for any surface

    loosening caused during preparation of the test areas. The seating loads were then released

    and the dial gauge readings noted at zero load. Test pressures were then applied as specified.

    The plate settlement, as an average of the readings of the two dial gauges, was noted for each

    pressure increment until completion of the sequence. The pressure-settlement and settlement-

    time graphs of the plate bearing test are presented in Appendix B.

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    C H A P T E R - I V I N V E S T I G AT I O N R E S U LT S

    4.1 CLASSIFICATION OF SOIL

    The Unified Soil Classification System (ASTM D2487) was used to classify the soil

    encountered in boring.

    4.2 SUMMARY OF FIELD INVESTIGATION

    Following list presents borehole number, location coordinates and chainage and ground

    surface elevation. Borehole location plans are included in Appendix A. Borehole logs are

    included in Appendix B. Table 1: LOCATION COORDITATES & GROUND ELEVATION OF BORE HOLES

    BH NO CO-ORDINATES GROUND ELEVATIONNORTHING EASTING

    IBH 02 1579.00 1386.00 5.687mIBH-04 1317.00 1395.00 5.366mIBH 05 1031.00 1766.00 5.228mIBH 06 1197.00 1766.00 5.669mIBH 08 967.00 819.00 5.394mIBH 09 1050.00 819.00 5.318mIBH 10 1133.00 819.00 5.495mIBH 11 1216.00 819.00 5.211mIBH 12 1317.00 819.00 5.621mIBH 18 1245.00 1167.00 5.311mIBH 19 1240.00 1635.00 5.321mIBH 20 1165.00 925.00 5.111mIBH 21 1160.00 1431.00 5.229mIBH 22 1163.00 1635.00 5.052mIBH 23 1083.00 925.00 5.532mIBH 24 1164.00 1083.00 5.312mIBH 25 997.00 925.00 5.309mIBH-26 1005.00 1431.00 5.215mIBH-27 1003.00 1635.00 5.521mIBH-28 1280.00 1006.00 5.316mIBH-29 1280.00 1274.00 5.331mIBH-30 1280.00 1546.00 5.312mIBH-31 1216.00 1017.00 5.389mIBH-32 1197.00 1290.00 4.791m

    1083.00 1164.00

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    Table 2: Test locations for ISCPT

    Table 3: TEST LOCATIONS FOR IDCPT

    Table 4: Test locations for IERT

    BH NOCO-ORDINATES GROUND

    ELEVATIONNORTHING EASTINGIBH 33 1216.00 1547.00 4.965mIBH 34 1133.00 1017.00 5.125mIBH 35 1114.00 1291.00 5.259mIBH 36 1133.00 1547.00 4.846mIBH 37 1050.00 1015.00 5.301mIBH 38 1031.00 1299.00 5.045mIBH 39 1050.00 1554.00 4.957mIBH 40 967.00 1022.00 4.998mIBH 41 967.00 1309.00 4.942mIBH 42 967.00 1557.00 4.992mIBH 46 920.00 1766.00 5.611mIBH 47 1417.00 1798.00 5.461mIBH 48 1317.00 1587.00 5.313mIBH 49 1317.00 1214.00 5.232mIBH 50 1318.00 943.00 5.108mIBH 56 1266.00 1802.00 5.350mIBH 57 1114.00 1796.00 5.151mIBH 67 1264.00 2133.00 0.802mBH 101 951.00 992.00 4.415mBH 104 951.00 1512.00 4.825m

    Test NoCO-ORDINATES

    NORTHING EASTINGIDCPT 04 1207 1798

    Test NoCO-ORDINATES

    NORTHING EASTINGIERT-03 836.00 1344.00IERT-04 1346.00 1578.00IERT-06 1009.00 819.00IERT-10 1031.00 1625.00

    987 18031243 1414998 1124

    1344.001344.00 836.00

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    Table 5: TEST LOCATIONS FOR IPLT

    4.3 LABORATORY TEST

    Following table lists the schedule of laboratory test undertaken. All tests were under taken at

    DCLs own laboratory in Dhaka. A table summarizing all tests result is enclosed in

    Appendix-D, and all laboratory test reports are enclosed in Appendix-C.

    Table 6: List of Laboratory Tests.

    LABORATORY TESTSBulk Density/Unit Weight

    Moisture Content TestParticle Size Distribution

    Atterberg LimitsShrinkage Limit Specific Gravity

    Direct Shear TestUnconfined Compression Strength Test

    Standard Proctor Compaction TestModified Proctor Compaction Test

    Consolidation TestOrganic Content Test of Soil Sample

    Underground Water Sample Test

    4.4 GEOTECHNICAL PROPERTIES

    4.4.1 SOIL GRADATION

    Figure 4 shows the soil gradation envelope of all tests performed under the current

    investigation program.

    Test NoCO-ORDINATES

    NORTHING EASTINGIPLT 04 1240.00 925IPLT 05 1083.00 1635.00IPLT 06 1304.00 1703.00

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    Figure 4: Soil Gradation Envelope

    4.4.2 SOIL PLASTICITY

    Figure 5 shows the plasticity chart of all soil samples tested under the current investigation

    program.

    Figure 5: Plasticity of Soil Sample

    4.5 Correction to SPT-N value:

    SPT N-value has been corrected using the following formula:

    N60 = (ER / 60%) N

    Where:

    N60 = SPT blow count corrected for hammer efficiency (blows/ft)

    Size (mm)

    Per cent Passing

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    ER = Hammer efficiency expressed as % of theoretical free fall energy delivered

    by the hammer system actually used (80% for automatic trip hammer used in

    the field)

    N = uncorrected SPT blow count (blows/ft)

    Table 7: Corrected SPT & Design SPT Value

    C indicates clay/silt of high plasticity type soil

    S indicates sandy soil.

    Star

    t dep

    th

    (m)

    End

    dep

    th

    (m)

    Lay

    er

    Thi

    ckne

    ss

    (m)

    Mid Soil Type

    (kPa) Pore

    -Pr

    essu

    re

    (kPa

    ) '

    (kPa)N N60 N1(60)

    0 6 6 3 S 57 29.43 27.57 4 5 8

    6 14 8 10 C 190 98.1 91.9 5 7 7

    14 19 5 16.5 C 313.5 161.87 151.64 16 21 20

    19 30 3 20.5 S 389.5 201.11 188.4 27 36 29

    30 40 3 23.5 S 446.5 230.54 215.97 31 41 28

    40 50 5 27.5 S 522.5 269.78 252.73 44 59 35

    50 60 10 55 S 1045 539.55 505.45 54 72 38

    11

    10

    10

    24.5

    35.0

    45.055.010

    Note: unconfined compression test is done on undisturbed soil (UDS) samples. In this project site collection of UDS sample is very difficult and in some cases notpossible. Hence other test results viz field vane shear test etc. is considered.

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    C H A P T E R - V A N A L Y S I S & R E C O M M E N D A T I O N S

    5.1 GENERAL

    A soil anticipated profile diagram is enclosed in Appendix B. As such, recommendations and

    calculations for foundation are given per-location basis.

    5.2 ANALYSIS FOR FOUNDATION SYSTEM

    5.2.1 DESIGN SOIL PROFILE

    Based on the field and laboratory test results, design soil profile has been considered as

    follows.

    Table 8: DESIGN SOIL PROFILE CONSIDERED

    Start depth (m) End Depth (m)

    Layer Thickness (m) Soil Type

    0.00 6 6 S 6.00 14 8 C

    14.00 19 5 C 19.00 22 3 S 22.00 25 3 S 25.00 30 5 S 30.00 40 10 S 40.00 50 10 S 50.00 60 10 S

    5.3 ANALYSIS FOR SHALLOW FOUNDATION

    5.3.1 BEARING CAPACITY

    Due to the presence of very loose to loose dredged material (sand filled) followed by soft silty

    soil at the upper horizon, it is not recommended to implement shallow foundation in the

    proposed site for heavy or major structure with bearing capacity greater than 50 KN/m2; as it

    is likely to consolidate under induced pressure of shallow foundation resulting in excessive

    settlement. In the liquefaction analysis (referred on Chapter VI) it is found that, the filled up

    dredged sand up to 6m below the G.L is susceptible to liquefaction Hence, minor structures

    having a pressure intensity less than 50 kN/m2 may be rested on isolated shallow foundation

    with necessary ground improvement as described elsewhere.

    5.4 DEEP FOUNDATION

    5.4.1 BORED CAST-IN SITU PILES & DRIVEN CAST IN SITU PILE:

    Due to presence of dredged sand fill and very soft to soft Organic/ Inorganic Silt up to 14m

    depth from G.L, pile foundation shall be adopted for structures having pressure intensity

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    greater than 50 kN/m2 with pile terminating below the 14m depth .In case of Bored Cast In-

    situ Piles, temporary casing can be provided up to the depth of about 16 m below the existing

    G.L.

    5.4.2 ANALYSIS BORED CAST-IN-SITU PILES

    Ultimate Pile capacities have been calculated based on methods outlined in "Nominal Axial

    Compression Resistance of Single Drilled Shaft" in AASTHO LRFD 2007 -Section 10. The

    ultimate unit is given by the relationship following relationship for drilled shaft:

    = + In which:

    =

    = Where:

    = Nominal Shaft Tip Resistance

    = Nominal Shaft Side Resistance

    = Unit Tip Resistance

    = Unit Side Resistance

    = Resistance factor for tip resistance

    = Resistance factor for side resistance

    5.4.3 SIDE RESISTANCE FOR CAST-IN-SITU PILES

    Nominal side resistance in cohesive soil is determined by following equation:

    =

    In which:

    Where:

    = Undrained Shear Strength (MPa)

    = Adhesion Factor (dimensionless)

    = Atmospheric pressure (= 0.101MPa)

    Side Resistance in cohesionless sandy soil:

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    Nominal side resistance in cohesion-less soil is determined by following equation ( -

    method):

    For :

    For :

    Where:

    = Vertical effective stress at soil layer mid-depth

    Load Transfer coefficient (dimensionless)

    z = Depth below ground, at soil layer mid-depth

    N60 = Average SPT blow count (corrected only for hammer efficiency) = (ER/60%)N and

    ER=80% for automatic trip hammer (Equation 10.4.6.2.4-2 of AASHTO LRFD 2007)

    5.4.4 TIP RESISTANCE FOR CAST-IN-SITU PILES

    Tip Resistance in cohesionless soil may be estimated using following equation:

    Where:

    = Atmospheric pressure (=0.101MPa)

    = vertical effective stress at the tip elevation of the shaft (MPa)

    N60 = Average SPT blow count (corrected only for hammer efficiency) in the design zone

    under consideration (blows/300mm)

    Based on the above design SPT N-values and data obtained from field and laboratory tests,

    following pile capacity has been estimated (Calculation is enclosed in the Appendix-D):

    5.4.5 ESTIMATED PILE CAPACITY FOR CAST-IN-SITU PILES

    Using AASHTO LRFD -2007 procedure following working load capacities of different sizes

    was calculated based on SPT Value.

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    Table 9: Estimated Drilled Shaft Capacity for different diameter based on SPT

    5.4.6 ESTIMATED PILE CAPACITY FOR CAST-IN-SITU PILES

    Using LCPC procedure following working load capacities of different sizes was calculated

    based on CPT Test (Calculation is enclosed in the Appendix-D):

    Table 10: Estimated Drilled Shaft Capacity for different diameter based on CPT

    (Cut off Level 2.0m below G.L)

    The geotechnical capacity of bored cast-in-situ R.C.C Pile terminating in non-cohesive sandy

    could be enhanced up to 25% of the above recommended capacity by Tube-a-Manchette

    method of Base Grouting.

    However, the capacity shall be confirmed by Load Test for particular soil

    formation around Toe Level of piles.

    Pile diameter

    (mm)

    Length(m)

    Cut-offLevel (m)

    Pile capacity(kN)

    Compression(kN)

    Tension(kN)

    Lateral Capacity

    Free

    H

    ead

    Fixe

    dH

    ead

    600 30

    03

    1053 498 40 80760 38 1834 885 55 115900 45 2911 1365 80 1501000 50 3789 1802 100 175600 30

    4.5

    1111 532 40 80760 38 1924 939 55 115900 45 3035 1439 80 1501000 50 3941 1893 100 175

    COL Pile diameter(mm) Length(m)Pile capacity(kN)

    Compression(kN) Tension(kN)

    3.0m600 30 1365.85 409.4750 38 2377.83 786.2850 45 2809.04 990.161000 50 4483.54 1346.388

    4.5m600 30.0 1338.04 411.438750 38.0 2114.68 729.624850 45.0 2666.57 995.9081000 50.0 4955.16 1414.396

    789.624

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    5.4.7 ANALYSIS OF PRECAST DRIVEN PILES

    5.4.7.1 SIDE RESISTANCE FOR DRIVEN PILES

    For cohesionless soil:

    Nominal side resistance in cohesionless soil for driven displacement pile is determined by

    following equation:

    Where:

    f = unit skin friction for driven piles (kPa)

    po = effective overburden pressure at the point

    = friction angle between soil and pile wall

    Nominal side resistance in cohesive soil is determined by following equation:

    =

    Where:

    x = coefficient that is a function of cx, and

    cx = undrained shear strength at depth x.

    ax is taken equal to 1 for c less than 24 kPa. For c in excess of 24kPa but less than or

    equal to 72 kPa ax decrease linearly from unity at c equal to 24kPa 0.5 at c equal to 72 kPa.

    For c in excess of 72 kPa ax is taken as 0.5.

    5.4.7.2 TIP RESISTANCE FOR DRIVEN PILES

    Tip Resistance (Cohesionless):

    Tip Resistance in Cohesionless soil may be estimated using following equation:

    Where:

    q = unit tip resistance for driven piles (kPa)

    po = effective overburden pressure at pile tip

    Nq = bearing capacity factor

    5.4.8 ESTIMATED PILE CAPACITY FOR PRECAST DRIVEN PILES

    Using AASHTO LRFD -2007 procedure following working load capacities of different sizes

    was calculated based on SPT Value (Calculation is enclosed in the Appendix-D):

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    Table 11: Estimated Capacity of Precast R.C.C. Driven pile (Square Shaped for different

    size based on SPT

    5.4.9 ESTIMATED PILE CAPACITY FOR PRECAST DRIVEN PILES

    Using LCPC procedure following working load capacities of different sizes was calculated

    based on CPT Test Results (Calculation is enclosed in the Appendix-D):

    Table 12: Estimated Capacity of Precast R.C.C. Driven pile for different size based on

    SCPT (Pile top considered at 2m depth from G.L)

    The estimated capacity shall be confirmed by load test.

    5.4.10 ESTIMATED PILE CAPACITY FOR PRECAST PSC HOLLOW CORE

    CONCRETE PILES

    Using AASHTO LRFD -2007 procedure following working load capacities of different sizes

    was calculated based on SPT Value (Calculation is enclosed in the Appendix-D):

    Pile cut off level (m)

    Pile size

    (mm)Length(m)

    Pile capacity(kN)

    Compression(kN) Tension(kN)Lateral(kN)Free Head

    Fixed Head

    2.0

    350 21.0 568 256 27 50400 24.0 672 293 35 60450 24.0 782 329 40 70450 26.0 897 393 40 70

    Borehole Pile Size(mm) Length(m)Pile capacity(kN)

    Compression(kN) Tension(kN)

    Design CPT

    350 24.0 534 153400 24.0 635 175450 24.0 732 197

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    Table 13: Estimated Capacity of Precast PSC Hollow Core Concrete pile for different size

    based on SPT (Pile cut off level is considered at GL)

    The estimated capacity shall be confirmed by load test.

    Pile cut off level (m)

    Pile size

    (mm)Length(m)

    Pile capacity(kN)

    Compression(kN) Tension(kN) Lateral(kN)

    At GL

    400 24.0 461 191 50600 25.0 839 312 80600 30.0 1006 380 80800 25.0 1261 416 110800 30.0 1507 506 110

    PSC Hollow core concrete pile considered as circular and thickness considered as 90mm.

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    C H A P T E R V I A N A L Y S I S F O R L I Q U E F A C T I O N P O T E N T I A L

    6. 1 EXCAVATION, COMPACTION, AND GROUND IMPROVEMENT CRITERIA:

    I. SUITABILITY OF ON SITE SOIL AS STRUCTURAL FILL

    The materials covering the site near the surface consist of mostly dredged fill

    comprises of silty sand material, which are suitable for general backfilling purpose.

    Material below Pavements:

    Material selected for use in the top 500mm for cut or fill areas in the roadway shall be

    in addition to meeting the requirements; the materials passing the #200 (0.076mm) sieve shall

    not exceed 35%, the liquid limit & plasticity index for these material shall not be more than

    35% & 10% respectively and the swell not exceed 2%.

    II. SLOPES FOR EXCAVATION:

    The materials covering the site near the surface consist of mostly silty sand. Open

    excavation at 1H:1V slope may be permitted for up to 1m depth. Appropriate shoring should

    be used for greater excavation particularly during rainy seasons or where it is required.

    III. CEMENT FOR UNDERGROUND FOUNDATIONS/STRUCTURES:

    Chemical analysis indicates the presence of medium to high sulphate content and falls

    in medium to severe Sulphate attack hazard (Ref: Kosmatka and Panarese, 1988, and

    Portland Cement Association, 1991). Cement to be used for this project should conform to

    the requirement of ASTM Standard Specification C150 or equivalent. Cement shall be

    Sulphate resisting type. Cement Type V is recommended in all class of concrete for

    foundation structures to be used. It is recommended to use at least 400kg cement per cubic

    meter of concrete for pile foundation. It is recommended to undertake a mix-design program

    under supervision of a structural engineer for finalizing mix-design of concrete.

    IV. GROUND IMPROVEMENT

    Very loose to loose dredged material (sand filled) at the upper horizon up to 6m depth

    below the existing G.L is susceptible to liquefaction, it is not recommended to implement

    shallow foundation at the proposed site for heavy or major structure with bearing capacity

    greater than 50kN/m2.

    In order to mitigate the liquefaction of site, the following ground improvements are

    recommended.

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    Pile Foundation shall be adopted for the structures having pressure intensity more

    than 50kN/m2 with piles resting below 14 m depth from the existing G.L.

    Wherever the pile foundations are provided, in case the pile cut off level is above 4.0

    m depth from G.L then dynamic compaction should be done at G.L before installation

    of piles; incase pile cut off level is below 4.0 m depth from the G.L, piles can be

    directly installed. However, the back filling shall be done with excavated sandy soil

    with relative density not less than 80%.

    Wherever lightly loaded shallow foundations/ roads/structures having pressure

    intensity less than 50kN/m2 are adopted, dynamic compaction should be done prior

    to excavation.

    6.2 METHODS FOR ANALYSIS OF LIQUEFACTION POTENTIAL

    6.2.1 GENERAL

    The shear stress induced/developed at different depth during an earthquake depends upon the

    overburden pressure while the shear resistance can be calculated based on the SPT values.

    The shear stress induces/developed and the shear resistances offered by the soil are evaluated

    in terms of Cyclic Stress Ratio (CSR) and the Cyclic Resistance Ratio (CRR) respectively.

    The CSR is the ratio of the shear stress developed to the effective over burden pressure at

    various depths while the CRR is the ratio of the shear resistance of the soil to the effective

    overburden pressure at various depths.

    6.2.2 METHOD

    I. CALCULATION OF CYCLIC STRESS RATIO

    For the determination of the CSR values at various depths, a peak horizontal ground

    acceleration coefficient of 0.12 as stated in Bangladesh National Building Code (BNBC 2006)

    has been taken in to consideration.

    CSR values have been determined using the well-established and widely accepted

    methods given by Seed & Idriss (1971) which also included the stress reduction coefficient

    which varies with depth.

    II. CALCULATION OF CYCLIC RESISTANCE RATIO

    The CRR values have been determined using the method given by Robertson (2010)

    for an earthquake magnitude of 7.5 giving due consideration to the fact that earthquake of

    magnitude greater than 7 have been recorded in Bangladesh. The procedure is an update on

    procedure originally published in NCEER-97-0022 (Proceedings of the Workshop on

    Evaluation of Liquefaction Resistance of Soils).

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    6.3 ANALYSIS OF RESULT

    The variations of the CSR and the CRR with depth based on the results of each of the

    SPT have been presented in Appendix-D. Factor of safety (F.S) are also included in the

    calculation sheet.

    Factor of safety has been calculated based on ratio between CRR and CSR. A factor

    of safety of less than 1.0 indicates liquefiable soil (Seed and Idriss, 1982, Earthquake

    Engineering Research Institute).

    Soil is liquefiable up to 6m from ground level as indicated by low factor of safety for

    all the boring location.

    In view of the above, to mitigate liquefaction, the ground improvement recommended

    as discussed above may be adopted.

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    C H A P T E R V I I R E F E R E N C E S

    1. Geological Map of Bangladesh (1990). Md. Md. Khurshid Alam, AKM Shahidul

    Hasan, and Mujibur Rahman Khan, Geological Survey of Bangladesh and John

    W. Whitney, United States Geological Survey of Bangladesh. Published by

    Geological Survey of Bangladesh.

    2. Bangladesh National Building Code (2006). Director, Housing and Building

    Research Institute, Ministry of Housing and Public Works.

    3. American Society for Testing and Materials (ASTM).

    4. American Association of State Highway and Transportation Organization

    (AASHTO).

    5. Indian Standard (IS).

    (2015)

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    C H A P T E R - V I I I R E C O M M E N D A T I O N S & C O N C L U S I ON S

    8.1 RECOMMENDATIONS FOR FOUNDATION SYSTEM

    Minor structures having a pressure intensity less than 50 kN/m2 may be rested on isolated

    shallow foundation with necessary ground improvement as described elsewhere.

    Pile Foundation shall be adopted for the structures having pressure intensity more than

    50kN/m2 with piles resting below 14 m depth from the existing G.L.

    Wherever the pile foundations are provided, in case the pile cut off level is above 4.0 m depth

    from G.L then dynamic compaction should be done at G.L before installation of piles; incase

    pile cut off level is below 4.0 m depth from the G.L, piles can be directly installed. However,

    the back filling shall be done with excavated sandy soil with relative density not less than

    80%.

    Wherever lightly loaded shallow foundations/ roads/structures having pressure intensity less

    than 50kN/m2 are adopted, dynamic compaction should be done prior to excavation.

    The recommended safe load carrying capacity of piles as follows.

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    8.2 RECOMMENDED PILE CAPACITY FOR BORED CAST-IN-SITU RCC PILES

    Table 14: RECOMMENDED PILE CAPACITY FOR BORED CAST-IN-SITU RCC

    PILES

    8.3 RECOMMENDED PILE CAPACITY FOR PRECAST DRIVEN PILES

    Table 15: RECOMMENDED PILE CAPACITY FOR PRECAST DRIVEN PILES

    8.4 RECOMMENDED PILE CAPACITY FOR PRECAST PSC HOLLOW CORE CONCRETE PILES

    Table 16: RECOMMENDED PILE CAPACITY FOR PRECAST PSC HOLLOW CORE

    CONCRETE PILES

    * Pile Length is evaluated considering maximum L/D ratio 50.

    Pile diameter

    (mm)

    Length(m)

    Cut-offLevel (m)

    Pile capacity(kN)

    Compression(kN)

    Tension(kN)

    Lateral Capacity

    Free

    H

    ead

    Fixe

    dH

    ead

    600 30

    03

    1053 498 40 80760 38 1834 885 55 115900 45 2911 1365 80 1501000 50 3789 1802 100 175600 30

    4.5

    1111 532 40 80760 38 1924 939 55 115900 45 3035 1439 80 1501000 50 3941 1893 100 175

    Pile cut offlevel (m)

    Pile size

    (mm)Length(m)

    Pile capacity(kN)

    Compression(kN) Tension(kN)Lateral(kN)

    Free Head

    Fixed Head

    2.0

    350 21.0 568 256 27 50400 24.0 672 293 35 60450 24.0 782 329 40 70450 26.0 897 393 40 70

    Pile cut off level (m)

    Pile size

    (mm)Length(m)

    Pile capacity(kN)

    Compression(kN) Tension(kN) Lateral(kN)

    At GL

    400 24.0 461 191 50600 25.0 839 312 80600 30.0 1006 380 80800 25.0 1261 416 110800 30.0 1507 506 110

    409.4787.51016

    1346.38411.43790.41040.41414.396

    485635732843

    153175197

    216

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • G E O T E C H N I C A L I N V E S T I G A T I O N R E P O R T O N 2X660MW MAITREE SUPER THERMAL POWER PROJECT; RAMPAL, BAGERHAT

    P A R T 2 . 0 : V O L U M E - 0 1 : C O A L S T O C K A R E A

    ** The recommended pile Capacities shall be confirmed by conducting pile load test.

    8.5 RECOMMENDATIONS FOR CHEMICAL ANALYSIS

    Electrical resistivity of subsoil is given in Appendix B: ERT Results.

    Cement to be used for this project should conform to the requirement of ASTM Standard

    Specification C150 or equivalent. Cement shall be Sulphate resisting type. Cement Type V is

    recommended in all class of concrete for foundation structures to be used. It is recommended

    to use at least 400kg cement per cubic meter of concrete for pile foundation. It is

    recommended to undertake a mix-design program under supervision of a structural engineer

    for finalizing mix-design of concrete.

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • House 11, Road 19/A, Sector 04,Uttara Model Town, Dhaka 1230

    Phone +880-2-58957231, Fax +880-2-58957283

    Email: [email protected], Web: http://www.dcl-fcl.com

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • 1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    9.0

    10.0

    11.0

    12.0

    13.0

    14.0

    15.0

    16.0

    17.0

    18.0

    19.0

    20.0

    21.0

    22.0

    23.0

    24.0

    25.0

    26.0

    27.0

    28.0

    29.0

    30.0

    Dep

    th (m

    )

    Sam

    ple

    No.

    10 20 30 40 500Typ

    e

    eo CcGsYdYtw

    (%)P.I.L.L.Fines(%)

    Sand(%) Cr

    GrainSize

    AtterbergLimits

    UnitWeight(kN/m)

    Consolidation ShearStrength

    Laye

    r Sym

    bol

    Spe

    cific

    Gra

    vitY

    ClaySiltSandGravel

    Moi

    stur

    eC

    onte

    nt

    Gravel(%) E

    lev

    (m)

    Borehole: IBH- 4Depth:70m

    Start: 02.08.16End: 05.08.16

    D1

    D3

    D4

    D5

    D6

    D7

    D8

    D12

    D13

    D14

    D15

    D16

    D17

    D18

    D19

    D2

    Sam

    ple

    Rec

    . (m

    m)

    150m

    m

    150m

    m

    150m

    m

    N-V

    alue

    01 02 03 05

    03 03 04 07

    03 04 05 09

    02 03 04 07

    06 08 14 22

    07 09 16 25

    08 11 13 24

    c /s(kN/m)

    u u

    D9

    D10

    D1102 02 03 05

    D20

    C = Compression IndexcG = Specific Gravitys

    Y = Dry Unit WeightdY = Bulk Unit Weightt

    w = Moisture ContentP.I. = Plasticity IndexL.L. = Liquid Limit

    C = Re-compression Indexr

    D = Disturbed SampleUD = Undisturbed Sample

    WD = Depth of Water Measured 24h after Completion of DrillingLeg

    end e = Initial Void Ratioo

    C = Undrained CohesionS = Undrained Shear Strengthu

    u

    250

    (Deg)

    = Angle of Internal Friction

    DST = Direct Shear Test

    01 02 02 04

    01 02 02 04

    E: 1395mN: 1317mGL : 5.366m

    WD(m) 2.80m

    260

    270

    280

    450

    450

    420

    430

    330

    320

    290

    270

    00 00 00 00

    02 03 04 07

    09 12 14 26

    D21 28006 11 12 23

    3.0

    2.0

    1.0

    0.0

    -1.0

    -2.0

    -3.0

    -4.0

    -5.0

    -6.0

    -7.0

    -8.0

    -9.0

    -10.0

    -11.0

    -12.0

    -13.0

    -14.0

    -15.0

    -16.0

    -17.0

    -18.0

    -19.0

    -20.0

    -21.0

    -24.0

    -23.0

    -22.0

    5.0

    4.0

    450

    450

    00 00 01 01

    DEVELOPMENT CONSTRUCTIONS LIMITED.Geotechnical Engineering Laboratory. Dhaka.House 11. Road 19A. Sector 4. Uttara. Dhaka 1230. Bangladesh.Phone: +880-2-58957231. Fax: (880) 2-58957283. Email: [email protected]. Client: Bharat Heavy Electricals Limited.

    Project: 2x660MW Maitree SuperThermal Power Project.Location: Rampal,Bagerhat.

    Owner:Bangladesh India FriendshipPower Company (Pvt) Limited.(BIFPCL)

    01 01 02 03

    UDS-1 420

    01 01 01 02

    UDS-2 430

    -25.0

    Checked BY: Priodeep ChowdhuryApproved BY: Eng. Roknuz zaman

    Drawn BY: Md. Emran Uddin

    Date : 27.09.16

    01 02 02 04

    260

    01 01 02 03

    00 00 00 00

    450

    450

    450

    450

    450

    02 02 03 05

    00 53 47 N P

    00 08 92 37 10

    00 05 95 53 24

    00 81 19 N P

    SM- Silty Sand.Medium. Grey.

    ML- Silt. Stiff. Mediumto Very stiff. Grey.

    MH- Elastic Silt. VerySoft. Grey.

    SM- Silty Sand. VeryLoose to Loose.Grey.

    44.0217.7012.29 2.66

    Standard Penetration TestDia/Depth of Casing:- 150mm/6.5m

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • Dep

    th (m

    )

    Sam

    ple

    No.

    10 20 30 40 500Typ

    e

    eo CcGsYdYtw

    (%)P.I.L.L.Fines(%)

    Sand(%) Cr

    GrainSize

    AtterbergLimits

    UnitWeight(kN/m)

    Consolidation ShearStrength

    Laye

    r Sym

    bol

    Spe

    cific

    Gra

    vitY

    ClaySiltSandGravel

    Moi

    stur

    eC

    onte

    nt

    Gravel(%) E

    lev

    (m)

    Sam

    ple

    Rec

    . (m

    m)

    150m

    m

    150m

    m

    150m

    m

    N-V

    alue c /s

    (kN/m) u u

    C = Compression IndexcG = Specific Gravitys

    Y = Dry Unit WeightdY = Bulk Unit Weightt

    w = Moisture ContentP.I. = Plasticity IndexL.L. = Liquid Limit

    C = Re-compression Indexr

    D = Disturbed SampleUD = Undisturbed Sample

    WD = Depth of Water Measured 24h after Completion of DrillingLeg

    end e = Initial Void Ratioo

    C = Undrained CohesionS = Undrained Shear Strengthu

    u

    (Deg)

    = Angle of Internal Friction

    DST = Direct Shear Test

    D23 27010 12 15 27

    34.0

    35.0

    D24 26011 12 17 29

    36.0

    D25 25010 14 18 34

    D26 24012 16 20 36

    D27 23010 15 22 37

    37.0

    38.0

    39.0

    40.0

    31.0

    32.0

    33.0

    D22 29008 10 20 30

    -28.0

    -29.0

    -30.0

    -31.0

    -32.0

    -33.0

    -34.0

    -27.0

    -26.0

    D28 22010 19 20 39

    DEVELOPMENT CONSTRUCTIONS LIMITED.Geotechnical Engineering Laboratory. Dhaka.House 11. Road 19A. Sector 4. Uttara. Dhaka 1230. Bangladesh.Phone: +880-2-58957231. Fax: (880) 2-58957283. Email: [email protected]. Client: Bharat Heavy Electricals Limited.

    Project: 2x660MW Maitree SuperThermal Power Project.Location: Rampal,Bagerhat.

    Owner:Bangladesh India FriendshipPower Company (Pvt) Limited.(BIFPCL)

    D29 24012 18 20 38

    D30 45006 07 07 14

    D31 24016 17 27 44

    D32 18034 61 (50 blows/150mm)

    D33 21022 34 42 76

    D34 22020 30 40 70

    D35 230

    D36 19026 40 24 64

    D37 20024 38 38 76

    D38 22025 25 25 50

    D39 23020 32 37 69

    41.0

    -35.0

    42.0

    -36.0

    43.0

    -37.0

    44.0

    -38.0

    45.0

    -39.0

    46.0

    -40.0

    47.0

    -41.0

    48.0

    -42.0

    49.0

    -43.0

    50.0

    -44.0

    51.0

    -45.0

    52.0

    -46.0

    53.0

    -47.0

    54.0

    -48.0

    55.0

    -49.0

    56.0

    -50.0

    57.0

    -51.0

    58.0

    -52.0

    59.0

    -53.0

    60.0

    -54.0

    D40 18030 62 08 70 (210mm/ Frist 50 blows)

    D41 23016 22 24 46

    D42 180 61.0

    -55.0

    Checked BY: Priodeep ChowdhuryApproved BY: Eng. Roknuz zaman

    Drawn BY: Md. Emran Uddin

    Date : 27.09.16

    UDS-3 380

    14 15 19 34

    35 64 (50 blows/150mm)

    (402mm/ Frist 50 blows)

    (265mm/ Frist 50 blows)

    (300mm/ Frist 50 blows)

    (260mm/ Frist 50 blows)

    (250mm/ Frist 50 blows)

    (450mm/ Frist 50 blows)

    (400mm/ Frist 50 blows)

    (280mm/ Frist 50 blows)

    00 92 08 N P

    00 67 33 N P

    00 02 98 40 13

    00 46 54 N P

    SP-SM - Poorly gradedSand with Silt. Denseto Very Dense. Grey.

    SM- Silty Sand. VeryDense. Grey.

    ML- Silt. Stiff. Grey.

    ML- Sandy Silt. VeryStiff to Hard. Grey.

    28.5019.3715.07 2.68

    Standard Penetration TestDia/Depth of Casing:- 150mm/6.5m Borehole:

    IBH- 4Depth:70m

    Start: 02.08.16End: 05.08.16

    E: 1395mN: 1317mGL : 5.366m

    WD(m) 2.80m

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • Dep

    th (m

    )

    Sam

    ple

    No.

    10 20 30 40 500Typ

    e

    eo CcGsYdYtw

    (%)P.I.L.L.Fines(%)

    Sand(%) Cr

    GrainSize

    AtterbergLimits

    UnitWeight(kN/m)

    Consolidation ShearStrength

    Laye

    r Sym

    bol

    Spe

    cific

    Gra

    vitY

    ClaySiltSandGravel

    Moi

    stur

    eC

    onte

    nt

    Gravel(%) E

    lev

    (m)

    Sam

    ple

    Rec

    . (m

    m)

    150m

    m

    150m

    m

    150m

    m

    N-V

    alue c /s

    (kN/m) u u

    C = Compression IndexcG = Specific Gravitys

    Y = Dry Unit WeightdY = Bulk Unit Weightt

    w = Moisture ContentP.I. = Plasticity IndexL.L. = Liquid Limit

    C = Re-compression Indexr

    D = Disturbed SampleUD = Undisturbed Sample

    WD = Depth of Water Measured 24h after Completion of DrillingLeg

    end e = Initial Void Ratioo

    C = Undrained CohesionS = Undrained Shear Strengthu

    u

    (Deg)

    = Angle of Internal Friction

    DST = Direct Shear Test

    END OF BORING

    DEVELOPMENT CONSTRUCTIONS LIMITED.Geotechnical Engineering Laboratory. Dhaka.House 11. Road 19A. Sector 4. Uttara. Dhaka 1230. Bangladesh.Phone: +880-2-58957231. Fax: (880) 2-58957283. Email: [email protected]. Client: Bharat Heavy Electricals Limited.

    Project: 2x660MW Maitree SuperThermal Power Project.Location: Rampal,Bagerhat.

    Owner:Bangladesh India FriendshipPower Company (Pvt) Limited.(BIFPCL)

    D43 17062.0

    -56.0

    63.0

    -57.0

    64.0

    -58.0

    65.0

    -59.0

    66.0

    -60.0

    67.0

    -61.0

    68.0

    -62.0

    D44 180

    D45 24030 40 30 70 (220mm/ Frist 50 blows)

    D46 25022 24 25 49 (320mm/ Frist 50 blows)

    D47 24020 24 28 52 (325mm/ Frist 50 blows) 69.0

    -63.0

    70.0

    -64.0

    -65.0

    Checked BY: Priodeep ChowdhuryApproved BY: Eng. Roknuz zaman

    Drawn BY: Md. Emran Uddin

    Date : 27.09.16

    33 68 (50 blows/150mm)

    30 66 (50 blows/150mm)

    D47 25022 23 27 50 (322mm/ Frist 50 blows)

    SP-SM - Poorly gradedSand with Silt. Denseto Very Dense. Grey.

    Standard Penetration TestDia/Depth of Casing:- 150mm/6.5m Borehole:

    IBH- 4Depth:70m

    Start: 02.08.16End: 05.08.16

    E: 1395mN: 1317mGL : 5.366m

    WD(m) 2.80m

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • 1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    9.0

    10.0

    11.0

    12.0

    13.0

    14.0

    15.0

    16.0

    17.0

    18.0

    19.0

    20.0

    21.0

    22.0

    23.0

    24.0

    25.0

    26.0

    27.0

    28.0

    29.0

    30.0

    Dep

    th (m

    )

    Sam

    ple

    No.

    10 20 30 40 500Typ

    e

    eo CcGsYdYtw

    (%)P.I.L.L.Fines(%)

    Sand(%) Cr

    GrainSize

    AtterbergLimits

    UnitWeight(kN/m)

    Consolidation ShearStrength

    Laye

    r Sym

    bol

    Spe

    cific

    Gra

    vitY

    ClaySiltSandGravel

    Moi

    stur

    eC

    onte

    nt

    Gravel(%) E

    lev

    (m)

    Borehole: IBH- 6Depth:40m

    Start: 30.06.16End: 01.07.16

    D1

    D3

    D4

    D5

    D6

    D7

    D8

    D12

    D13

    D14

    D15

    D16

    D17

    D18

    D19

    D2

    Sam

    ple

    Rec

    . (m

    m)

    150m

    m

    150m

    m

    150m

    m

    N-V

    alue

    00 01 01 02

    02 02 03 05

    10 12 15 27

    08 13 16 29

    09 11 12 23

    11 13 17 30

    08 12 15 27

    10 14 18 32

    09 13 20 33

    c /s(kN/m)

    u u

    D9

    D10

    D1105 07 08 15

    D20

    C = Compression IndexcG = Specific Gravitys

    Y = Dry Unit WeightdY = Bulk Unit Weightt

    w = Moisture ContentP.I. = Plasticity IndexL.L. = Liquid Limit

    C = Re-compression Indexr

    D = Disturbed SampleUD = Undisturbed Sample

    WD = Depth of Water Measured 24h after Completion of DrillingLeg

    end e = Initial Void Ratioo

    C = Undrained CohesionS = Undrained Shear Strengthu

    u

    450

    (Deg)

    = Angle of Internal Friction

    DST = Direct Shear Test

    01 01 02 03

    03 05 05 10

    E: 1766mN: 1197mGL : 5.669m

    WD(m) 1.15m

    470

    430

    440

    420

    430

    420

    420

    400

    380

    420

    370

    400

    420

    390

    360

    01 01 01 02

    02 02 03 05

    06 09 12 21

    16 17 21 38

    D21 41013 15 18 33

    3.0

    2.0

    1.0

    0.0

    -1.0

    -2.0

    -3.0

    -4.0

    -5.0

    -6.0

    -7.0

    -8.0

    -9.0

    -10.0

    -11.0

    -12.0

    -13.0

    -14.0

    -15.0

    -16.0

    -17.0

    -18.0

    -19.0

    -20.0

    -21.0

    -24.0

    -23.0

    -22.0

    5.0

    4.0

    440

    470

    440

    450

    02 03 03 06

    01 01 02 03

    01 02 02 04UDS-1 300

    01 01 02 03

    UDS-2 340

    (445mm/ Frist 50 blows)

    Checked BY: Priodeep ChowdhuryApproved BY: Eng. Roknuz zaman

    Drawn BY: Md. Emran Uddin

    Date : 27.09.16

    DEVELOPMENT CONSTRUCTIONS LIMITED.Geotechnical Engineering Laboratory. Dhaka.House 11. Road 19A. Sector 4. Uttara. Dhaka 1230. Bangladesh.Phone: +880-2-58957231. Fax: (880) 2-58957283. Email: [email protected]. Client: Bharat Heavy Electricals Limited.

    Project: 2x660MW Maitree SuperThermal Power Project.Location: Rampal,Bagerhat.

    Owner:Bangladesh India FriendshipPower Company (Pvt) Limited.(BIFPCL)

    00 92 08 N P

    00 92 08 N P

    00 92 08 N P

    00 92 08 N P

    SM- Silty Sand.Medium to Dense.Grey.

    MH- Elastic Silt. Soft toStiff. Grey.

    SP - Poorly gradedSand.Very Loose toLoose. Grey.

    46.4617.5611.99 2.68

    Standard Penetration TestDia/Depth of Casing:- 150mm/6.5m

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • 1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    9.0

    10.0

    11.0

    12.0

    13.0

    14.0

    15.0

    16.0

    17.0

    18.0

    19.0

    20.0

    21.0

    22.0

    23.0

    24.0

    25.0

    26.0

    27.0

    28.0

    29.0

    30.0

    Dep

    th (m

    )

    Sam

    ple

    No.

    10 20 30 40 500Typ

    e

    eo CcGsYdYtw

    (%)P.I.L.L.Fines(%)

    Sand(%) Cr

    GrainSize

    AtterbergLimits

    UnitWeight(kN/m)

    Consolidation ShearStrength

    Laye

    r Sym

    bol

    Spe

    cific

    Gra

    vitY

    ClaySiltSandGravel

    Moi

    stur

    eC

    onte

    nt

    Gravel(%) E

    lev

    (m)

    Borehole: IBH- 5Depth:40m

    Start: 27.06.16End: 29.06.16

    D1

    D3

    D4

    D5

    D6

    D7

    D8

    D12

    D13

    D14

    D15

    D16

    D17

    D18

    D19

    D2

    Sam

    ple

    Rec

    . (m

    m)

    150m

    m

    150m

    m

    150m

    m

    N-V

    alue

    00 01 01 02

    02 02 03 05

    10 12 15 27

    08 13 16 29

    09 11 12 23

    11 13 17 30

    08 12 15 27

    10 14 18 32

    09 13 20 33

    c /s(kN/m)

    u u

    D9

    D10

    D1105 07 08 15

    D20

    C = Compression IndexcG = Specific Gravitys

    Y = Dry Unit WeightdY = Bulk Unit Weightt

    w = Moisture ContentP.I. = Plasticity IndexL.L. = Liquid Limit

    C = Re-compression Indexr

    D = Disturbed SampleUD = Undisturbed Sample

    WD = Depth of Water Measured 24h after Completion of DrillingLeg

    end e = Initial Void Ratioo

    C = Undrained CohesionS = Undrained Shear Strengthu

    u

    450

    (Deg)

    = Angle of Internal Friction

    DST = Direct Shear Test

    01 01 02 03

    03 05 05 10

    E: 1766mN: 1031mGL : 5.228m

    WD(m) 1.20m

    470

    430

    440

    420

    430

    420

    420

    400

    380

    420

    370

    400

    420

    390

    360

    01 01 01 02

    02 02 03 05

    06 09 12 21

    16 17 21 38

    D21 41013 15 18 33

    3.0

    2.0

    1.0

    0.0

    -1.0

    -2.0

    -3.0

    -4.0

    -5.0

    -6.0

    -7.0

    -8.0

    -9.0

    -10.0

    -11.0

    -12.0

    -13.0

    -14.0

    -15.0

    -16.0

    -17.0

    -18.0

    -19.0

    -20.0

    -21.0

    -24.0

    -23.0

    -22.0

    5.0

    4.0

    440

    470

    440

    450

    02 03 03 06

    -24.0

    01 01 02 03

    01 02 02 04UDS-1 300

    01 01 02 03

    UDS-2 340

    (445mm/ Frist 50 blows)

    Checked BY: Priodeep ChowdhuryApproved BY: Eng. Roknuz zaman

    Drawn BY: Md. Emran Uddin

    Date : 27.09.16

    DEVELOPMENT CONSTRUCTIONS LIMITED.Geotechnical Engineering Laboratory. Dhaka.House 11. Road 19A. Sector 4. Uttara. Dhaka 1230. Bangladesh.Phone: +880-2-58957231. Fax: (880) 2-58957283. Email: [email protected]. Client: Bharat Heavy Electricals Limited.

    Project: 2x660MW Maitree SuperThermal Power Project.Location: Rampal,Bagerhat.

    Owner:Bangladesh India FriendshipPower Company (Pvt) Limited.(BIFPCL)

    00 11 89 53 22

    00 17 83 37 10

    00 14 86 40 13

    ML- Silt.Very Stiff.Grey.

    ML- Silt with sand.Stiff.Grey.

    MH- Elastic Silt. Softto Mediume. Grey.

    42.8016.3411.44

    43.1017.4212.17

    SP - Poorly gradedSand.Very Loose toLoose. Grey.

    2.67

    Standard Penetration TestDia/Depth of Casing:- 150mm/6.5m

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • Dep

    th (m

    )

    Sam

    ple

    No.

    10 20 30 40 500Typ

    e

    eo CcGsYdYtw

    (%)P.I.L.L.Fines(%)

    Sand(%) Cr

    GrainSize

    AtterbergLimits

    UnitWeight(kN/m)

    Consolidation ShearStrength

    Laye

    r Sym

    bol

    Spe

    cific

    Gra

    vitY

    ClaySiltSandGravel

    Moi

    stur

    eC

    onte

    nt

    Gravel(%) E

    lev

    (m)

    Sam

    ple

    Rec

    . (m

    m)

    150m

    m

    150m

    m

    150m

    m

    N-V

    alue c /s

    (kN/m) u u

    C = Compression IndexcG = Specific Gravitys

    Y = Dry Unit WeightdY = Bulk Unit Weightt

    w = Moisture ContentP.I. = Plasticity IndexL.L. = Liquid Limit

    C = Re-compression Indexr

    D = Disturbed SampleUD = Undisturbed Sample

    WD = Depth of Water Measured 24h after Completion of DrillingLeg

    end e = Initial Void Ratioo

    C = Undrained CohesionS = Undrained Shear Strengthu

    u

    (Deg)

    = Angle of Internal Friction

    DST = Direct Shear Test

    END OF BORING

    D23 42014 14 20 34

    34.0

    35.0

    D24 37019 29 32 61

    36.0

    D25 39017 20 28 48

    D26 36012 15 17 32

    D27 44007 08 09 17

    37.0

    38.0

    39.0

    40.0

    31.0

    32.0

    33.0

    D22 39018 20 25 45

    -28.0

    -29.0

    -30.0

    -31.0

    -32.0

    -33.0

    -34.0

    -27.0

    -26.0

    D28 42009 11 14 25

    (380mm/ Frist 50 blows)

    (290mm/ Frist 50 blows)

    (360mm/ Frist 50 blows)

    -35.0

    Checked BY: Priodeep ChowdhuryApproved BY: Eng. Roknuz zaman

    Drawn BY: Md. Emran Uddin

    Date : 27.09.16

    DEVELOPMENT CONSTRUCTIONS LIMITED.Geotechnical Engineering Laboratory. Dhaka.House 11. Road 19A. Sector 4. Uttara. Dhaka 1230. Bangladesh.Phone: +880-2-58957231. Fax: (880) 2-58957283. Email: [email protected]. Client: Bharat Heavy Electricals Limited.

    Project: 2x660MW Maitree SuperThermal Power Project.Location: Rampal,Bagerhat.

    Owner:Bangladesh India FriendshipPower Company (Pvt) Limited.(BIFPCL)

    00 24 76 34 08 ML- Silt with sand.VeryStiff to Hard. Grey.

    DST 25.9 30.7

    Standard Penetration TestDia/Depth of Casing:- 150mm/6.5m Borehole:

    IBH- 5Depth:40m

    Start: 27.06.16End: 29.06.16

    E: 1766mN: 1031mGL : 5.228m

    WD(m) 1.20m

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • Dep

    th (m

    )

    Sam

    ple

    No.

    10 20 30 40 500Typ

    e

    eo CcGsYdYtw

    (%)P.I.L.L.Fines(%)

    Sand(%) Cr

    GrainSize

    AtterbergLimits

    UnitWeight(kN/m)

    Consolidation ShearStrength

    Laye

    r Sym

    bol

    Spe

    cific

    Gra

    vitY

    ClaySiltSandGravel

    Moi

    stur

    eC

    onte

    nt

    Gravel(%) E

    lev

    (m)

    Sam

    ple

    Rec

    . (m

    m)

    150m

    m

    150m

    m

    150m

    m

    N-V

    alue c /s

    (kN/m) u u

    C = Compression IndexcG = Specific Gravitys

    Y = Dry Unit WeightdY = Bulk Unit Weightt

    w = Moisture ContentP.I. = Plasticity IndexL.L. = Liquid Limit

    C = Re-compression Indexr

    D = Disturbed SampleUD = Undisturbed Sample

    WD = Depth of Water Measured 24h after Completion of DrillingLeg

    end e = Initial Void Ratioo

    C = Undrained CohesionS = Undrained Shear Strengthu

    u

    (Deg)

    = Angle of Internal Friction

    DST = Direct Shear Test

    END OF BORING

    D23 42014 14 20 34

    34.0

    35.0

    D24 37019 29 32 61

    36.0

    D25 39017 20 28 48

    D26 36012 15 17 32

    D27 44007 08 09 17

    37.0

    38.0

    39.0

    40.0

    31.0

    32.0

    33.0

    D22 39018 20 25 45

    -28.0

    -29.0

    -30.0

    -31.0

    -32.0

    -33.0

    -34.0

    -27.0

    D28 42009 11 14 25

    (380mm/ Frist 50 blows)

    (290mm/ Frist 50 blows)

    (360mm/ Frist 50 blows)

    -35.0

    Checked BY: Priodeep ChowdhuryApproved BY: Eng. Roknuz zaman

    Drawn BY: Md. Emran Uddin

    Date : 27.09.16

    DEVELOPMENT CONSTRUCTIONS LIMITED.Geotechnical Engineering Laboratory. Dhaka.House 11. Road 19A. Sector 4. Uttara. Dhaka 1230. Bangladesh.Phone: +880-2-58957231. Fax: (880) 2-58957283. Email: [email protected]. Client: Bharat Heavy Electricals Limited.

    Project: 2x660MW Maitree SuperThermal Power Project.Location: Rampal,Bagerhat.

    Owner:Bangladesh India FriendshipPower Company (Pvt) Limited.(BIFPCL)

    -26.0

    -25.0

    ML- Silt with sand.VeryStiff to Hard. Grey.

    Standard Penetration TestDia/Depth of Casing:- 150mm/6.5m Borehole:

    IBH- 6Depth:40m

    Start: 30.06.16End: 01.07.16

    E: 1766mN: 1197mGL : 5.669m

    WD(m) 1.15m

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • 1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    9.0

    10.0

    11.0

    12.0

    13.0

    14.0

    15.0

    16.0

    17.0

    18.0

    19.0

    20.0

    21.0

    22.0

    23.0

    24.0

    25.0

    26.0

    27.0

    28.0

    29.0

    30.0

    Dep

    th (m

    )

    Sam

    ple

    No.

    10 20 30 40 500Typ

    e

    eo CcGsYdYtw

    (%)P.I.L.L.Fines(%)

    Sand(%) Cr

    GrainSize

    AtterbergLimits

    UnitWeight(kN/m)

    Consolidation ShearStrength

    Laye

    r Sym

    bol

    Spe

    cific

    Gra

    vitY

    ClaySiltSandGravel

    Moi

    stur

    eC

    onte

    nt

    Gravel(%) E

    lev

    (m) Borehole: IBH- 8

    Depth:40mStart: 30.07.16End: 01.08.16

    D1

    D3

    D4

    D5

    D6

    D7

    D8

    D12

    D13

    D14

    D15

    D16

    D17

    D18

    D19

    D2

    Sam

    ple

    Rec

    . (m

    m)

    150m

    m

    150m

    m

    150m

    m

    N-V

    alue

    02 03 03 06

    03 04 05 09

    04 06 06 12

    07 09 10 19

    08 13 15 28

    10 16 17 33

    08 14 15 29

    05 06 08 14

    c /s(kN/m)

    u u

    D9

    D10

    D1103 04 05 09

    D20

    C = Compression IndexcG = Specific Gravitys

    Y = Dry Unit WeightdY = Bulk Unit Weightt

    w = Moisture ContentP.I. = Plasticity IndexL.L. = Liquid Limit

    C = Re-compression Indexr

    D = Disturbed SampleUD = Undisturbed Sample

    WD = Depth of Water Measured 24h after Completion of DrillingLeg

    end e = Initial Void Ratioo

    C = Undrained CohesionS = Undrained Shear Strengthu

    u

    360

    (Deg)

    = Angle of Internal Friction

    DST = Direct Shear Test

    03 03 04 07

    E: 819mN: 967mGL : 5.394m

    WD(m) 0.95m

    340

    330

    370

    350

    340

    400

    400

    370

    340

    360

    380

    350

    380

    360

    01 02 02 04

    00 00 00 00

    03 04 04 08

    07 10 12 22

    D21 37009 11 15 26

    3.0

    2.0

    1.0

    0.0

    -1.0

    -2.0

    -3.0

    -4.0

    -5.0

    -6.0

    -7.0

    -8.0

    -9.0

    -10.0

    -11.0

    -12.0

    -13.0

    -14.0

    -15.0

    -16.0

    -17.0

    -18.0

    -19.0

    -20.0

    -21.0

    -24.0

    -23.0

    -22.0

    5.0

    4.0

    390

    420

    380

    390

    04 05 06 11

    02 03 03 06

    00 01 01 02

    (50 blows/305mm)

    (50 blows/305mm)

    (50 blows/310mm)

    03 03 04 07 (50 blows/310mm)

    (50 blows/305mm)

    (50 blows/310mm)

    VST-1

    (50 blows/320mm)

    UDS-1 325

    00 01 01 02 (50 blows/310mm)

    VST-2

    (50 blows/320mm)

    UDS-2

    01 02 02 04 (50 blows/320mm)

    (50 blows/315mm)

    (50 blows/310mm) 380

    (50 blows/305mm)

    Checked BY: Priodeep ChowdhuryApproved BY: Eng. Roknuz zaman

    Drawn BY: Md. Emran Uddin

    Date : 27.09.16

    DEVELOPMENT CONSTRUCTIONS LIMITED.Geotechnical Engineering Laboratory. Dhaka.House 11. Road 19A. Sector 4. Uttara. Dhaka 1230. Bangladesh.Phone: +880-2-58957231. Fax: (880) 2-58957283. Email: [email protected]. Client: Bharat Heavy Electricals Limited.

    Project: 2x660MW Maitree SuperThermal Power Project.Location: Rampal,Bagerhat.

    Owner:Bangladesh India FriendshipPower Company (Pvt) Limited.(BIFPCL)

    -25.0

    00 93 07 N P

    00 03 97 56 25

    00 51 49 N P

    00 65 35 N P

    43.6416.8211.71

    ML- Silt. Very Stiff .Grey.

    SM- Silty Sand.Medium to Dense.Grey.

    MH- Elastic Silt. Soft toStiff. Grey.

    SP-SM - Poorly gradedSand with Silt. Loose toMedium. Grey.

    2.67

    Standard Penetration TestDia/Depth of Casing:- 150mm/6.5m

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • Dep

    th (m

    )

    Sam

    ple

    No.

    10 20 30 40 500Typ

    e

    eo CcGsYdYtw

    (%)P.I.L.L.Fines(%)

    Sand(%) Cr

    GrainSize

    AtterbergLimits

    UnitWeight(kN/m)

    Consolidation ShearStrength

    Laye

    r Sym

    bol

    Spe

    cific

    Gra

    vitY

    ClaySiltSandGravel

    Moi

    stur

    eC

    onte

    nt

    Gravel(%) E

    lev

    (m)

    Sam

    ple

    Rec

    . (m

    m)

    150m

    m

    150m

    m

    150m

    m

    N-V

    alue c /s

    (kN/m) u u

    C = Compression IndexcG = Specific Gravitys

    Y = Dry Unit WeightdY = Bulk Unit Weightt

    w = Moisture ContentP.I. = Plasticity IndexL.L. = Liquid Limit

    C = Re-compression Indexr

    D = Disturbed SampleUD = Undisturbed Sample

    WD = Depth of Water Measured 24h after Completion of DrillingLeg

    end e = Initial Void Ratioo

    C = Undrained CohesionS = Undrained Shear Strengthu

    u

    (Deg)

    = Angle of Internal Friction

    DST = Direct Shear Test

    END OF BORING

    D23 40008 11 13 24

    34.0

    35.0

    D24 39008 10 12 22

    36.0

    D25 34007 11 14 25

    D26 33010 13 15 28

    D27 28009 12 12 24

    37.0

    38.0

    39.0

    40.0

    31.0

    32.0

    33.0

    D22 38007 07 10 17

    -28.0

    -29.0

    -30.0

    -31.0

    -32.0

    -33.0

    -34.0

    -27.0

    -26.0

    D28 30011 14 16 30

    Checked BY: Priodeep ChowdhuryApproved BY: Eng. Roknuz zaman

    Drawn BY: Md. Emran Uddin

    Date : 27.09.16

    DEVELOPMENT CONSTRUCTIONS LIMITED.Geotechnical Engineering Laboratory. Dhaka.House 11. Road 19A. Sector 4. Uttara. Dhaka 1230. Bangladesh.Phone: +880-2-58957231. Fax: (880) 2-58957283. Email: [email protected]. Client: Bharat Heavy Electricals Limited.

    Project: 2x660MW Maitree SuperThermal Power Project.Location: Rampal,Bagerhat.

    Owner:Bangladesh India FriendshipPower Company (Pvt) Limited.(BIFPCL)

    -35.0

    00 13 87 36 11

    ML- Silt. Very Stiff .Grey.

    Standard Penetration TestDia/Depth of Casing:- 150mm/6.5m Borehole:

    IBH- 8Depth:40m

    Start: 30.07.16End: 01.08.16

    E: 819mN: 967mGL : 5.394m

    WD(m) 0.95m

    TENDER NO - PSER:SCT:KLN-C1860:17 (TCN-02)

  • 1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    9.0

    10.0

    11.0

    12.0

    13.0

    14.0

    15.0

    16.0

    17.0

    18.0

    19.0

    20.0

    21.0

    22.0

    23.0

    24.0

    25.0

    26.0

    27.0

    28.0

    29.0

    30.0

    Dep

    th (m

    )

    Sam

    ple

    No.

    10 20 30 40 500Typ

    e

    eo CcGsYdYtw

    (%)P.I.L.L.Fines(%)

    Sand(%) Cr

    GrainSize

    AtterbergLimits

    UnitWeight(kN/m)

    Consolidation ShearStrength

    Laye

    r Sym

    bol

    Spe