geotech and foundation -x
TRANSCRIPT
By
Engr. Saeedullah jan Mandokhail Assistant Professor
GEOTECHNICAL AND FOUNDATION ENGINEERING
Balochistan University Of Information Technology Engineering & Management Sciences
(BUITEMS), Quetta
1
BEARING CAPACITY OF SOILS
2
3
BEARING CAPACITY OF SOILS
4
•Terzaghi’s Ultimate Bearing Capacity
•Meyerhof’s Method
•Brinch Hansen’s Method
•Vesic’s Method
THE BEARING CAPACITY OF SHALLOW FOUNDATION
5
A shallow foundation must:
1. be safe against an overall shear failure in the soil
that supports it.
2. cannot experience excessive displacement (in
other words, settlement).
THE BEARING CAPACITY OF SHALLOW FOUNDATION
6
Bearing capacity is the power of foundation soil to
hold the forces from the superstructure without
undergoing shear failure or excessive settlement.
Foundation soil is that portion of ground which is
subjected to additional stresses when foundation and
superstructure are constructed on the ground.
Ultimate Bearing Capacity (qf) is the maximum
pressure that a foundation soil can withstand without
undergoing shear failure or which will produce shear
failure in the soil.
THE BEARING CAPACITY OF SHALLOW FOUNDATION
7
Net ultimate Bearing Capacity (qn) :
It is the maximum extra pressure (in addition to initial overburden pressure) that a foundation soil can withstand without undergoing shear failure.
qn = qf - qo
Here, qo represents the overburden pressure at foundation level and is equal to γ.D for level ground without surcharge where ү is the unit weight of soil and D is the depth to foundation bottom from Ground Level.
THE BEARING CAPACITY OF SHALLOW FOUNDATION
8
Safe Bearing Capacity (qs): it is the maximum value of
contact pressure to which the soil can be subjected
without risk of shear failure. This is based solely on
the strength of the soil and is simply the ultimate
bearing capacity divided by a suitable factor of safety.
Allowable Bearing Pressure (qa): It is the maximum
pressure the foundation soil is subjected to
considering both shear failure and settlement.
BEARING CAPACITY FAILURE
9
General shear failure
Local shear failure
Punching shear
failure
Failures
Local shear
Intermediate case
+/- gradual failure
Punching
Loose sands,
weak clays (dr.)
F. surf. not defined
Gradual failure
General shear
Dense soils,
Rock, NC clays
Defined failure
surf.
Fast failure
10
COMMENTS ON SHEAR FAILURE
Usually only necessary to analyze general shear failure.
Local and punching shear failure can usually be anticipated by settlement analysis.
Failure in shallow foundations is generally settlement failure; bearing capacity failure must be analyzed, but in practical terms is usually secondary to settlement analysis.
11
Terzaghi’s Bearing Capacity Theory
Terzaghi developed the theory for continuous foundations
(simplest, 2D problem).
BNqNNcq qcult '5.0'
BNNNcq qzDcult '4.0''3.1
BNNNcq qzDcult '3.0''3.1
From model tests, he expanded the theory to:
12
Nc = cohesion factor
Nq = surcharge factor
Nγ = self wt factor
TERZAGHI’S BEARING CAPACITY THEORY
13
THE BEARING CAPACITY OF SOILS
14
THE BEARING CAPACITY OF SOILS
15
THE BEARING CAPACITY OF SOILS
16
17
18
GROUNDWATER LEVEL EFFECTS
D
19
Case I
w '
GROUNDWATER LEVEL EFFECTS
20
B
DDw
11'
Case II
GROUNDWATER LEVEL EFFECTS
21
Case III
'
GROUNDWATER LEVEL EFFECTS
22
For total stress analysis:
'
regardless of the case
(gw effects are implicit in cT and fT)
GROUNDWATER LEVEL EFFECTS
23
GROUNDWATER LEVEL EFFECTS
24
In case the water table lies at any intermediate depth less than
the depth (Df+ B), the bearing capacity equations are affected
due to the presence of the water table.
Case 1. When the water table lies above the base of the foundation.
25
GROUNDWATER LEVEL EFFECTS
26
GROUNDWATER LEVEL EFFECTS
SOLVED EXAMPLE:
A strip footing of width 3 m is founded at a depth of 2 m below the ground
surface in a (c - ɸ) soil having a cohesion c = 30 kN/m2 and angle of
shearing resistance ɸ = 35°. The water table is at a depth of 5 m below
ground level. The moist weight of soil above the water table is 17.25 kN/m3.
Determine (a) the ultimate bearing capacity of the soil, (b) the net bearing
capacity, and (c) the net allowable bearing pressure and the load/m for a
factor of safety of 3. Use the general shear failure theory of Terzaghi.
27
28
If the water table in Ex. 12.1 rises to the ground level, determine the net
safe bearing pressure of the footing. All the other data given in Ex. 12.1
remain the same. Assume the saturated unit weight of the soil ɣsat= 18.5
kN/m3.
29
30
THE GENERAL BEARING CAPACITY
EQUATION
Meyerhof (1963) presented a general bearing capacity equation which
takes into account the shape and the inclination of load. The general form
of equation suggested by Meyerhof for bearing capacity is
31
32
STANDARD PENETRATION TEST
The method has been standardized as ASTM D-1586 (1997) with periodic
revision since 1958. The method of carrying out this test is as follows:
1. The split spoon sampler is connected to a string of drill rods and is lowered
into the bottom of the bore hole which was drilled and cleaned in advance.
2. The sampler is driven into the soil strata to a maximum depth of 18 in by
making use of a 140 Ib weight falling freely from a height of 30 in on to an
anvil fixed on the top of drill rod. The weight is guided to fall along a guide rod.
The weight is raised and allowed to fall by means of a manila rope, one end
tied to the weight and the other end passing over a pulley on to a hand
operated winch or a motor driven cathead.
3. The number of blows required to penetrate each of the successive 6 in
depths is counted to produce a total penetration of 18 in.
4. To avoid seating errors, the blows required for the first 6 in of penetration
are not taken into account; those required to increase the penetration from 6
in to 18 in constitute the N-value.
The SPT is conducted normally at 2.5 to 5 ft intervals. The intervals may be
increased at greater depths if necessary.
33
34
ULTIMATE BEARING CAPACITY OF FOOTINGS
BASED ON SPT VALUES (N]
Standard Energy Ratio Res Applicable to N Value
The empirical correlations established in the USA between N and soil
properties indicate the value of N conforms to certain standard energy ratios.
Some suggest 70% (Bowles, 1996) and others 60% (Terzaghi et al., 1996).
The relation between Ncor and ɸ established by Peck et al., (1974) is given in a
graphical form in Fig. The value of Ncor to be used for getting ɸ is the corrected
value for standard energy. The angle ɸ obtained by this method can be used
for obtaining the bearing capacity factors, and hence the ultimate bearing
capacity of soil.
Cohesive Soils
Relationship Between Ncor and qu (Unconfined Compressive Strength)
Relationships have been developed between Ncor and qu (the undrained
compressive strength) for the ɸ = 0 condition. This relationship gives the value
of cu for any known value of Ncor. The relationship may be expressed as Eq.
where the value of the coefficient & may vary from a minimum of 12 to a
maximum of 25
35
SETTLEMENT ANALYSIS/CONSOLIDATION
SETTLEMENT ANALYSIS/CONSOLIDATION
INTRODUCTION
Structures are built on soils. They transfer loads to the subsoil
through the foundations. The effect of the loads is felt by the soil
normally up to a depth of about two to three times the width of the
foundation. The soil within this depth gets compressed due to the
imposed stresses. The compression of the soil mass leads to the
decrease in the volume of the mass which results in the settlement
of the structure.
This compression of the soil mass due to the imposed stresses may
be almost immediate or time dependent according to the
permeability characteristics of the soil.
The compressibility characteristics of a soil mass might be due to any
or a combination of the following factors:
1. Compression of the solid matter.
2. Compression of water and air within the voids.
3. Escape of water and air from the voids.
It is quite reasonable and rational to assume that the solid matter and
the pore water are relatively incompressible under the loads usually
encountered in soil masses. The change in volume of a mass under
imposed stresses must be due to the escape of water if the soil is
saturated.
SETTLEMENT ANALYSIS/CONSOLIDATION
CONSOLIDATION
When a saturated clay-water system is subjected to an external
pressure, the pressure applied is initially taken by the water in the
pores resulting thereby in an excess pore water pressure. If drainage
is permitted, the resulting hydraulic gradients initiate a flow of water
out of the clay mass and the mass begins to compress. A portion of
the applied stress is transferred to the soil skeleton, which in turn
causes a reduction in the excess pore pressure. This process,
involving a gradual compression occurring simultaneously with a
flow of water out of the mass and with a gradual transfer of the
applied pressure from the pore water to the mineral skeleton is
called consolidation
SETTLEMENT ANALYSIS/CONSOLIDATION
SPRING ANALOGY
Valve
Springs
SETTLEMENT ANALYSIS/CONSOLIDATION
The process of consolidation of a clay-soil-water system may be
explained with the help of a mechanical model as described by
Terzaghi and Frohlich (1936).
Consolidation may be due to one or more of the following factors:
1. External static loads from structures.
2. Self-weight of the soil such as recently placed fills.
3. Lowering of the ground water table.
4. Desiccation/Dryness
SETTLEMENT ANALYSIS/CONSOLIDATION
DURING CONSOLIDATION
42
remains the same (=q) during consolidation. u decreases (due to
drainage) while ’ increases transferring the load from water to the
soil.
GL
saturated clay
q kPa
A
u
’
u
’
q
CONSOLIDATION THEORY
43
44
SETTLEMENT
Immediate Settlement: The portion of the settlement of a structure
which occurs more or less simultaneously with the applied loads.
This is computed using elasticity theory (Important for Granular
soil)
Primary Consolidation: Due to gradual dissipation of pore pressure
induced by external loading and consequently expulsion of water
from the soil mass, hence volume change. At the present time the
only theory of practical value for estimating time-dependent
settlement due to volume changes, that is under primary
consolidation is the one-dimensional theory. (Important for
Inorganic clays)
Secondary Consolidation: Occurs at constant effective stress with
volume change due to rearrangement of particles. (Important for
Organic soils)
45
SETTLEMENT The total Settlement/compression of a saturated clay strata under
excess effective pressure may be considered as the sum of
1. Immediate compression,
2. Primary consolidation, and
3. Secondary compression.
STRESS HISTORY
Normally Consolidated Clay
If the present effective stress is the maximum to which
the clay has ever been subjected
CLAY 100,000 years ago
80,000 years ago
30,000 years ago
10,000 years ago
5,000 years ago
1,000 years ago
Today
STRESS HISTORY
Overconsolidated Clay
If the effective stress at some time in the past has been
greater than the present value
20,000 years ago
100,000 years ago
80,000 years ago
30,000 years ago
CLAY
ICE AGE 18,000 years ago
5,000 years ago
Today
OVERCONSOLIDATION RATIO, OCR
present
c
σ'
σ'OCR
OVERCONSOLIDATION RATIO, OCR
Normally Consolidated: OCR =1
Overconsolidated: OCR > 1
How can OCR > 1?
Erosion of overburden
Recession of glacial ice sheets
Permanent rise of water table
TERZAGHI’S THEORY OF 1.D CONSOLIDATION
Terzaghi (1925) advanced his theory of one-dimensional consolidation
based upon the following assumptions.
1. The clay layer is homogeneous.
2. The clay layer is saturated.
3. The compression of the soil layer is due to the change in volume
only, which in turn, is due to the squeezing out of water from the void
spaces.
4. Darcy’s law is valid.
5. Deformation of soil occurs only in the direction of the load
application.
6. The coefficient of consolidation C v is constant during the
consolidation.
TERZAGHI 1-D CONSOLIDATION EQUATION
51
x
z
y dx dy
dz
Qin
Qout
TERZAGHI ONE-DIMENSIONAL EQUATION
To derive the equation for time rate of settlement using an element of the soil sample of thickness dz and cross-sectional area of dA = dxdy, we will assume the following:
The soil is saturated, isotropic and homogeneous
Darcy’s law is valid
Flow only occurs vertically
The strains are very small
52
TERZAGHI ONE-DIMENSIONAL EQUATION
53
dxdydtvdtAvdtqQ zzvin
dxdydtdzz
vvdtqqQ z
zzzout
dzdxdydtz
vdtvAdtqdt
t
V
QQdtt
VV
zzz
inout
TERZAGHI ONE-DIMENSIONAL EQUATION
Since the change in volume of the soil (V) is
equal to the change in volume of pore water
expelled (Vw), which is equal to the change in
volume of the voids (Vv) therefore,
54
TERZAGHI ONE-DIMENSIONAL EQUATION
55
dtt
Vedt
t
eVdt
t
V
dtt
eVdt
t
V
dtt
Vdt
t
V
ss
s
v
)(
ONE-DIMENSIONAL EQUATION
56
As there is no change in the volume of solid
therefore,
dtt
eVdt
t
Vs
e
dxdydz
e
VVs
eV
Vs
111
1
As we know that
TERZAGHI ONE-DIMENSIONAL EQUATION
57
dxdydzdtt
e
edt
t
e
e
dxdydzdt
t
V
1
1
1
t
e
ez
v
dxdydzdtt
e
edzdxdydt
z
v
z
z
1
1
1
1
TERZAGHI ONE-DIMENSIONAL EQUATION
58
From Darcy’s law
w
w
w
zz
zz
zz
uhhu
z
ukv
z
hi
z
hkv
ikv
TERZAGHI ONE-DIMENSIONAL EQUATION
59
By Partial Differentiation with respect to depth z gives
2
2
z
uk
z
v
z
uk
zv
z
w
zz
w
zz
TERZAGHI ONE-DIMENSIONAL EQUATION
60
As we know that the change in total vertical pressure
is equal to the change in pore water pressure. i.e., u
=v we can write
v
vv
v
ea
t
ua
t
e
t
ue
t
e
TERZAGHI ONE-DIMENSIONAL EQUATION
61
t
u
e
a
z
v vz
1v
v me
a
1where
t
um
z
vv
z
Therefore,
62
TERZAGHI 1-D CONSOLIDATION EQUATION
2
2
z
uC
t
uv
2
2
2
2
z
u
m
k
t
u
z
uk
t
um
wv
z
w
zv
v
wv
z Cm
k
63
TERZAGHI 1-D CONSOLIDATION EQUATION
2
2
z
uC
t
uv
64
COEFFICIENT OF CONSOLIDATION
For a given load increment, the coefficient of consolidation Cv can
be determined from the laboratory observations of time versus dial
reading.
There are several procedures presently available to estimate the
coefficient of consolidation, some of which are described below.
Logarithm-of-time method
The logarithm-of-time method was originally proposed by
Casagrande and Fadum (1940) and can be explained by referring to
Figure
65
COEFFICIENT OF CONSOLIDATION
66
COEFFICIENT OF CONSOLIDATION
1.Plot the dial readings for specimen deformation for a given load
increment against time on semi log graph paper as shown in Figure.
2. Plot two points, P and Q, on the upper portion of the
consolidation curve, which correspond to time t1 and t2,
respectively. Note that t2=4t1.
3. The difference of dial readings between P and Q is equal to x.
Locate point R, which is at a distance x above point P.
4. Draw the horizontal line RS. The dial reading corresponding to
this line is d0, which corresponds to 0% consolidation.
5. Project the straight-line portions of the primary consolidation and
the secondary consolidation to intersect at T . The dial reading
corresponding to T is d100, i.e., 100% primary consolidation.
67
COEFFICIENT OF CONSOLIDATION
6. Determine the point V on the consolidation curve that corresponds
to a dial reading of d0 +d100/2 = d50. The time corresponding to
point V is t50, i.e., time for 50% consolidation.
68
COEFFICIENT OF CONSOLIDATION
69
COEFFICIENT OF CONSOLIDATION
SOLUTION TO TERZAGHI EQUATION
70
v
m
m
av TMM
U 2
02
exp2
1
2/)12( mMWhere
2
2
z
uC
t
uv
SOLUTION TO TERZAGHI EQUATION
71
%)100log(933.0781.1T
:%10053
100
%
4T
:%530
v
av
2
v
av
av
av
U
UFor
U
UFor
DEGREE OF CONSOLIDATION
The ratio, expressed as a percentage, of the
amount of consolidation at a given time within a
soil mass, to the total amount of Consolidation
obtainable under a given stress condition.
It is the ratio of the settlement occurred at a
particular time and depth to the total expected
settlement. This parameter can be expressed as
72
DEGREE OF CONSOLIDATION
73
t
v
t
tv
s
sU
s
ssU
1
DEGREE OF CONSOLIDATION
74
0
0
0
1u
uU
u
uuU
v
v
0
0
0
1e
eU
e
eeU
v
v
SOLUTION TO TERZAGHI EQUATION
75
SOLUTION TO TERZAGHI EQUATION
76
Tv Tv U
0.00 0.00 0
0.00 0.04 5
0.01 0.09 10
0.02 0.13 15
0.03 0.18 20
0.05 0.22 25
0.07 0.27 30
0.10 0.31 35
0.13 0.35 40
0.16 0.40 45
0.20 0.44 50
0.24 0.49 55
0.28 0.53 60
0.34 0.58 65
0.40 0.63 70
0.48 0.69 75
0.57 0.75 80
0.68 0.83 85
0.85 0.92 90
1.13 1.06 95
100
U-Tv RELATION
77
0
20
40
60
80
100
0 0.25 0.5 0.75 1 1.25 1.5 1.75 2
U (
%)
Tv
U-Tv RELATION
78
0
20
40
60
80
100
0 0.25 0.5 0.75 1 1.25 1.5
U (
%)
Tv
U-Tv RELATION
79
0
20
40
60
80
100
0 0.25 0.5 0.75 1 1.25 1.5
U (
%)
Tv
U-Tv RELATION
80
0
20
40
60
80
100
0 0.25 0.5 0.75 1 1.25 1.5
U (
%)
Tv
U-Tv RELATION
81
0
20
40
60
80
100
0 0.25 0.5 0.75 1 1.25 1.5
U (
%)
Tv
U-Tv RELATION
82
0
20
40
60
80
100
0 0.25 0.5 0.75 1 1.25 1.5
U (
%)
Tv
U-Tv RELATION
83
0
20
40
60
80
100
0 0.25 0.5 0.75 1 1.25 1.5
U (
%)
Tv
a b
U-Tv RELATION
84
0
20
40
60
80
100
0 0.25 0.5 0.75 1 1.25 1.5
U (
%)
Tv
a b = 0.15 a
b/a =0.15
U-Tv RELATION
85
0
20
40
60
80
100
0 0.25 0.5 0.75 1 1.25 1.5
U (
%)
Tv
50
90
100
CONSOLIDOMETER
OBTAINING T90 FROM THE EXPERIMENTAL RESULTS
CONSOLIDATION PARAMETERS
rS
wGe 0
90
2
90
2
90 848.0
tt
TC HH dd
v
)1( 0
0
eH
He
k = cvmvw
)1(
)1`(
0
0
e
am
e
em
vv
v
v
`
v
v
ea
modulus Constraint1
vmE
EXAMPLE
For the following given information of an Oedometer test calculate
the consolidation parameters of the soil.
Moisture content, % w= 32
Specific gravity, G = 2.7
Diameter, mm D = 74.94
Height, mm H =19.22
EXAMPLE
t[min] t After stress-1: 50 kPa After stress-2: 100 kPa After stress-3: 200 kPa
0 0.00 0.0 0.0 0.0
0.25 0.50 0.5 0.177 0.213
1 1.00 0.58 0.254 0.314
2 1.41 0.689 0.316 0.383
4 2.00 0.81 0.399 0.468
6 2.45 0.887 0.454 0.51
9 3.00 0.977 0.506 0.543
16 4.00 1.095 0.553 0.569
25 5.00
36 6.00
1.095 0.553 0.569
Elasped time Vertical displacment /Dial Gauge reading (mm)
Total Displacement
EXAMPLE
0.0
0.2
0.4
0.6
0.8
1.0
1.2
0 1 2 3 4 5
Ver
tica
l dis
pla
cem
ent
Square root of time
3.4
TIME FOR 90% CONSOLIDATION T90
From the graph
90
90
3.4
11.56 minutes
t
t
0 0
0 0.32 2.7 0.864
se w G
e
0.41mm
0
0
`
19.22 0.41 18.81
H H
H mm
From the graph
Total vertical displacement after each stage
1
2
3
1.095 0 1.095 (for 50 kPa)
0.553 0 0.553 (for 100 kPa)
0.569 0 0.569 (for 200 kPa)
H mm
H mm
H mm
0
01
18.8110.09
1 0.864
s
s
HH
e
H mm
11
22
33
1.0950.108 (for 50 kPa)
10.09
0.5530.055 (for 100 kPa)
10.09
0.5690.056 (for 200 kPa)
10.09
s
s
s
He
H
He
H
He
H
0
1 0 1
2 0 2
3 0 3
0.864 0.108 0.756
0.756 0.055 0.701
0.701 0.056 0.645
f
f
f
f
e e e
e e e
e e e
e e e
Final void ratio
COEFFICIENT OF CONSOLIDATION CV
Coefficient of consolidation Cv
2 2 3 2
90 90
6 2
0.848 0.848(18.81 10 / 2)
11.56
6.49 10 / min
vv
v
T d dC
t t
C m
Coefficient of volume compressibility mv
6 2
3
0
0.10810 1.158 m /MN
(1 ) 50 10 (1 0.864)v
em
e
COEFFICIENT OF PERMEABILITY, K
6 6 3
10
3
(6.49 10 / 60) (1.158 10 ) 9.8 10
12.275 10 /
4.4 10 /
v v wk c m
k
k m s
k mm hour
COMPRESSION CURVE
0.6
0.64
0.68
0.72
0.76
0.8
10 100 1000
Void
rat
io ,e
Effective pressure, kPa
ANALYSIS OF THE LABORATORY MEASUREMENTS FOR EACH
STAGE
Loading stage 1 2 3
Pressure `z[kPa] 50 100 200
Initial void ratio, e0 0.864 0.756 0.701
Initial height, H0 [mm] 18.81 17.715 17.162
Height change, H 1.095 0.553 0.569
Void ratio change, e 0.108 0.055 0.056
Final void ratio, ef 0.756 0.701 0.645
t90 [min] 11.56
Cv [m2/in] 6.4910-6
mv [m2/MN] 1.158
K [m/s] 12.27510-10
An 8 ft clay layer beneath a building is overlain by
stratum of permeable sand and gravel and is underlain
by impermeable bedrock. The total expected total
settlement for the clay layer due to the footing load is
2.5 in. the coefficient of consolidation (cv) is 2.68 10-3
in2/min. How many years it will take for 90 % of total
expected consolidation settlement to take place.
Compute the amount of consolidation settlement that
will occur in one year? How many years will it take for
consolidation settlement of one inch to take place?
EXAMPLE
EXAMPLE
Sand and gravel
Impermeable bedrock
Clay 8.0 ft
St = 2.5 in
cv = 2.68 10-3 in2/min
tyears = ? for U = 90%
S 1 year = ? for t = 1 year
t = ? for S = 1 in
v
drv
dr
vv
C
Tt
tCT
H
H2
2
years 55.5
min 109168.2
1068.2
)96)(848.0(
6
3
2
t
t
t
15.0
)96(
)60243651(1068.22
3
2
v
v
dr
vv
T
T
tCT
H
For TV = 0.15, U = 43 %
in 075.1
)5.2(43.0
)(
s
s
sUs
s
sU
in 075.1
)5.2(43.0
)(
s
s
sUs
s
sU
EXAMPLE
EXAMPLE
%40
4.05.2
1
U
U
s
sU
For U = 40 %, TV = 0.126 years 82.0
min 1033.2
1068.2
)96(126.0
5
3
2
2
t
t
t
C
Tt
v
drv H
EXAMPLE
A foundation is to be constructed on a site
where the soil profile is as shown in the figure,
the coefficient of consolidation CV = 4.9610-6
m2/min. How long it will take for half the
expected consolidation settlement to take place
if the clay layer is underlain by (a) permeable
sand and gravel? (b) Impermeable bedrock?
EXAMPLE
Elev. 185.6 m
Elev. 192 m
Elev. 198 m
Elev. 200 m
Water table
Sand and gravel
Unit weight = 19.83.0 kN/m3
Clay
Unit weight = 17.10 kN/m3
Water table
Elev. 195.5 m
EXAMPLE
Elev. 185 m
Elev. 190 m
Elev. 198 m
Elev. 200 m
Water table
Sand and gravel
Unit weight = 20 kN/m3
Clay
Unit weight = 17 kN/m3
Water table
Elev. 195 m
EXAMPLE
CV = 4.9610-6 m2/min
Hdr = H/2 = 6.4/2 = 3.2 m (two way drainage)
t =?
U = 50 %
For U = 50 %, Tv = 0.196
years 77.0
min 10046.4
1096.4
)2.3(196.0
5
6
2
2
t
t
t
C
Tt
v
drv H
FIELD CONSOLIDATION LINE
The modified curve of the logarithm of vertical effective stress
versus void ratio (e- log`) is called the field consolidation line.
There are two methods for determining the field consolidation
line, one for normally consolidated clay, and the other for over
consolidated clay.
In the case of normally consolidated clay, determination of the
field consolidation line is fairly simple. However for over
consolidated clay, finding the field consolidation line is
somewhat difficult.
FIELD CONSOLIDATION LINE
In the case of normally consolidated clay, with the
given (e- log`) curve develop from the laboratory
test, the point on the (e- log`) curve
corresponding to 0.4 eo is determined let point f. a
straight line connecting points a (point a is the
point designated by a pressure of `0 and void
ratio of eo) and f gives the field consolidation line
for normally consolidated clay.
NORMALLY CONSOLIDATED CLAY
FIELD CONSOLIDATION LINE
Normally consolidated clay
e
log `
NORMALLY CONSOLIDATED CLAY
FIELD CONSOLIDATION LINE
Normally consolidated clay
e
log `
NORMALLY CONSOLIDATED CLAY
FIELD CONSOLIDATION LINE
a
Normally consolidated clay
e
eo
`o
log `
NORMALLY CONSOLIDATED CLAY
point a is the point designated by a pressure of `0 and void ratio of eo
FIELD CONSOLIDATION LINE
a
Normally consolidated clay
e
eo
`o
0.4 eo
log `
f
NORMALLY CONSOLIDATED CLAY
Point f on the (e- log`) curve corresponding to 0.4𝑒𝑜 is determined
FIELD CONSOLIDATION LINE
a
Normally consolidated clay
e
eo
`o
0.4 eo
log `
f
NORMALLY CONSOLIDATED CLAY a straight line connecting points a and f gives the field consolidation
line for normally consolidated clay.
FIELD CONSOLIDATION LINE
a
Normally consolidated clay
e
eo
`o
0.4 eo
log `
f
af is called field
consolidation line
NORMALLY CONSOLIDATED CLAY
COMPRESSION INDEX
a
e
e1
log `1
e2
log `
f
log `2
The slope of the field consolidation line is called compression index
12
12
`log`log
eeCc
COMPRESSION INDEX
0
0
0
0
1
212
12
)(log
)(loglog
loglog
c
c
Ce
eeeeC
MAXIMUM PAST PRESSURE The earliest and the most widely used method was
the one proposed by Casagrande (1936).
The method involves locating the point of maximum
curvature on the laboratory e-log p curve of an
undisturbed sample,
a tangent is drawn to the curve and a horizontal line
is also constructed.
The angle between these two lines is then bisected.
The abscissa of the point of intersection of this
bisector with the upward extension of the inclined
straight part corresponds to the preconsolidation
pressure `m
MAXIMUM PAST PRESSURE
e
` (log scale)
locating the point of maximum curvature
g
MAXIMUM PAST PRESSURE
h
i
e
` (log scale)
Horizontal line
tangent is drawn to the curve and a horizontal line is
also constructed
MAXIMUM OVERBURDEN PRESSURE
g
h
j
e
` (log scale)
i
angle between these two lines is then bisected
MAXIMUM OVERBURDEN PRESSURE
k
g
h
j
e
` (log scale)
i
Draw upward extension of the inclined straight part of
the curve
MAXIMUM PAST OVERBURDEN PRESSURE
g
h
j
e
` (log scale)
`m
k
i
The abscissa of the point of intersection of this bisector with the
upward extension of the inclined straight part corresponds to the
preconsolidation pressure `m
DEEP FOUNDATIONS PILE FOUNDATIONS
INTRODUCTION
Pile foundation used to support structure
poor quality soil
bearing capacity failure
excessive settlement
End-bearing pile
Pile driven until it comes to rest on a hard
impenetrable layer of soil or rock
Friction pile
load of the structure must come from the skin
friction or adhesion between surface of the pile
and the soil
PILE TYPES
Timber pile
Concrete pile
Cast-in-Place
Precast
Steel
H-pile
Pipe
PILE CAPACITY
Structural strength of the pile
Material, size and shape
Supporting strength of the soil
Load transmitted by friction between soil and sides
of pile
Load transmitted to the soil directly to the soil
below the pile tip
THEORETICAL PILE FOUNDATION ANALYSIS
Friction piles in Cohesionless and Cohesive
soils.
Ultimate Load determined by Geotechnical
Engineer
Allowable Load determined by building code
Factor of Safety determined by Engineer
PILE-DRIVING FORMULAS
In theory one can calculate the load-bearing capacity of a pile based on the amount of energy required to drive the pile by the hammer and resulting penetration of the pile.
Engineering news formula – Not accurate
Danish formula
Use factor of safety of 3 for determination of the design load, Q(a).
Q(d) = eh(Eh)/(S + 1/2(So)))
eh = efficiency of pile hammer
Eh = hammer energy rating (Table 10-7)
S = avg. penetration of the pile from the last
few driving blows
So = elastic compression of the pile
[(2ehEhL)/(AE)]1/2
L = length of the pile
A = cross sectional area of the pile
E = modulus of elasticity of the pile material
EXAMPLE PROBLEM
Pile Driving Formula
To determine the number of impacts required for
the last foot of penetration based on the given
design capacity.
Note it can be the last foot or more and the
ultimate capacity may be given rather than the
design capacity.
PILE LOAD TESTS
Design based on estimated loads and soil
characteristics
Load test piles
Hydraulic jack
static weight
bearing failure
excessive settlement
PILE GROUPS AND SPACING
Piles placed in groups of three or more
Pile groups tied together by a pile cap
attached to the head of the individual piles and
causes several piles to work together.
Pile spacing
minimum spacing
CONSTRUCTION OF PILE FOUNDATIONS
Piling types
Timber, concrete and steel
Pile hammers
Top of the Pile
Cap, cap-block and cushion
Hammer-Pile systems
Base of the Pile
Driving shoes
BS8004 defines deep foundation with D>B or D>3m.
Pile foundation always more expensive than shallow foundation but will overcome problems of soft surface soils by transferring load to stronger, deeper stratum, thereby reducing settlements.
Pile resistance is comprised of
end bearing
shaft friction
For many piles only one of these components is important. This is the basis of a simple classification
PILE FOUNDATIONS
ROCK
SOFT SOIL PILES
End bearing pile rests on a
relative firm soil . The load of the
structure is transmitted through
the pile into this firm soil or rock
because the base of the pile bears
the load of the structure, this type
of pile is called end bearing pile
Most of the piles used in Hong
Kong are end bearing piles.
This is because the majority of
new developments are on
reclaimed land
END BEARING PILES
SOFT SOIL PILES
FRICTION PILES If the firm soil is at a considerable
depth, it may be very expensive to
use end bearing piles. In such
situations, the piles are driven
through the penetrable soil for some
distance. The piles transmit the load
of structure to the penetrable soil by
means of skin friction between the
soil.
TYPES OF PILE
The pile installation procedure varies considerably, and
has an important influence on the subsequent response
Three categories of piles are classified by method of
installation as below:
Large displacement piles
They encompass all solid driven piles including precast concrete
piles, steel or concrete tubes closed at the lower end
Small displacement piles
They include rolled steel sections such as H-pile and open-end
tubular piles
Replacement piles
They are formed by machine boring, grabbing or hand-digging.
Combinations of vertical, horizontal and moment
loading may be applied at the soil surface from the
overlying structure
For the majority of foundations the loads applied to
the piles are primarily vertical
For piles in jetties, foundations for bridge piers, tall
chimneys, and offshore piled foundations the lateral
resistance is an important consideration
The analysis of piles subjected to lateral and moment
loading is more complex than simple vertical loading
because of the soil-structure interaction.
Pile installation will always cause change of adjacent
soil properties, sometimes good, sometimes bad.
LOADS APPLIED TO PILES V
M H
MODES OF FAILURE
The soil is always failure by punching shear.
The failure mode of pile is always in buckling
failure mode.
TOTAL AND EFFECTIVE STRESS ANALYSIS
To determine drained or undrained condition, we may need to consider the following factors:
• Drainage condition in the various soil strata
• Permeability of soils
• Rate of application of loads
• Duration after the application of load
A rough indicator will be the Time Factor (Tv=cvt/d2)
DISPLACEMENT PILE (A/D)
Advantage Disadvantages
Pile material can be inspected for
quality before driving
May break during driving
Construction operation affect by
ground water
Noise and vibration problems
Can driven in very long lengths Cannot be driven in condition of
low headroom
Construction operation not affected
by ground water
Noise may prove unacceptable.
Noise permit may be required
Soil disposal is not necessary Vibration may prove unacceptable
due to presence of sensitive
structures, utility installation or
machinery
REPLACEMENT PILE (A/D)
Advantage Disadvantages
Less noise or vibration problem Concrete cannot be inspected after
installation
Equipment can break up practically all
kinds of obstructions
Liable to squeezing or necking
Can be installed in conditions of low
headroom
Raking bored pile are difficult to
construct
No ground heave Drilling a number of pile groups may
cause ground loss and settlement of
adjacent structures
Depth and diameter can varied easily Cannot be extended above ground
level without special adaptation
ULTIMATE CAPACITY OF AXIALLY LOAD SINGLE PILE IN SOIL
Estimated by designer based on soil data and
somewhat empirical procedures. It is common
practice that the pile capacity be verified by pile load
test at an early stage such that design amendment
can be made prior to installation of the project piles.
The satisfactory performance of a pile is, in most
cases, governed by the limiting acceptable
deformation under various loading conditions.
Therefore the settlement should also be checked.
W
Q u
Q b
Q s
Basic Concept
The ultimate bearing capacity (Qu )of a pile
may be assessed using soil mechanics
principles. The capacity is assumed to be the
sum of skin friction and end-bearing
resistance, i.e
Qu =Qb+Qs-W ……………………….(1)
where
Qu total pile resistance,
Qb is the end bearing resistance and
Qs is side friction resistance
behavior
Shaft resistance fully mobilized at small pile
movement (<0.01D)
Base resistance mobilized at large movement
(0.1D)
W
Qs
QB
QT
ho
D
QDES = QB/FB + Qs /Fs –W……(2)
d
ULTIMATE LIMIT STATE DESIGN
Where FB and FS is the factor of safety
of components of end bearing strength
and shaft friction strength
Qb=Ab [ cb Nc + Po(Nq-1) + d/2N+Po] - Wp
Where Ab is the area of the base , cb is the
cohesion at the base of the pile, Po is the
overburden stress at the base of the pile and d
is the width of the pile.
QU = QB + Qs–W……(3)
DRIVEN PILE IN GRANULAR SOILS
The concepts of the calculation of end-bearing
capacity and skin friction for bored piles in granular
soils also apply to driven piles in granular soils. The
pile soil system involving effects of densification
and in horizontal stresses in the ground due to pile
driving.
BORED PILE IN CLAYS
The ultimate end bearing resistance for piles in clays is
often related to the undrained shear strength, cu, as
qB=Nccu
QB=ABNccu
where
Nc= 9 when the location of the pile base below
ground surface exceeds fours times the pile diameter
BORED PILE IN CLAYS
The ultimate shaft friction (qs) for soils in stiff over-
consolidated clays may be estimated on the semi-
empirical method as:
qs=aCu
a is the adhesion factor (range from 0.4 to 0.9)
DRIVEN PILE IN CLAYS
The design concepts are similar to those
presented for bored piles in granular soils.
However, based on the available instrumented
pile test results, a design curve is put forward
by Nowacki et al (1992)
PREDICTION OF ULTIMATE CAPACITY OF PILE
Pile Driving Formula
Pile driving formula relate the ultimate bearing capacity of driven
piles to final set (i.e. penetration per blow). In Hong Kong, the Hiley
formula has been widely used for the design of driven piles as:
Rd=(hhWhdh)/(s+c/2)
Where
Rd is driving resistance, hh is efficiency of hammer, Wh is the weight
of hammer, dh is the height of fall of hammer, s is permanent set of
pile and c is elastic movement of pile
Note: Test driving may be considered at the start of a driven piling
contract to assess the expected driving characteristics.
PREDICTION OF ULTIMATE CAPACITY OF PILE
Pile Load Test
Static pile load test is the most reliable means of
determining the load capacity of a pile. The test
procedure consists of applying static load to the pile in
increments up to a designated level of load and
recording the vertical deflection of the pile. The load is
usually transmitted by means of a hydraulic jack placed
between the top of the pile and a beam supported by
tow or more reaction piles. The vertical deflection of the
top of the pile is usually measured by mechanical
gauges attached to a beam, which span over the test
pile.
SOIL IMPROVEMENT
SOIL IMPROVEMENT
Soil improvement in its broadest sense is the
alteration of any property of a soil to improve its
engineering performance.
This may be either a temporary process to permit the
construction of a facility or may be a permanent
measure to improve the performance of the
completed facility.
The result of an application of a technique may be
increased strength, reduced compressibility, reduced
permeability, or improved ground water condition.
METHODS OF SOIL IMPROVEMENT
Removal and replacement
Precompression
Vertical drains
In-situ densification
Grouting
Stabilization using admixtures
Reinforcement
REMOVAL AND REPLACEMENT
One of oldest and simplest methods is simply
to remove and replace the soil
Soils that will have to be replaced include
contaminated soils or organic soils
Method is usually practical only above the
groundwater table
PRECOMPRESSION
Simply place a surcharge fill on top of the soil that
requires consolidation
Once sufficient consolidation has taken place, the fill
can be removed and construction takes place
Surcharge fills are typically 10-25 feet thick and
generally produces settlement of 1 to 3 feet.
Most effective in clay soil
ADVANTAGES OF PRECOMPRESSION
Requires only conventional earthmoving
equipment
Any grading contractor can perform the work
Long track record of success
DISADVANTAGES OF PRECOMPRESSION
Surcharge fill must extend horizontally at least
10 m beyond the perimeter of the planned
construction, which may not be possible at
confined sites
Transport of large quantities of soil required
Surcharge must remain in place for months or
years, thus delaying construction
VERTICAL DRAINS
Vertical drains are installed under a surcharge load to
accelerate the drainage of impervious soils and thus
speed up consolidation
These drains provide a shorter path for the water to
flow through to get away from the soil
Time to drain clay layers can be reduced from years to
a couple of months
VERTICAL DRAINS
WICK DRAINS
Geosynthetics used as
a substitute to sand
columns
Installed by being
pushed or vibrated into
the ground
Most are about 100
mm wide and 5 mm
thick
IN-SITU DENSIFICATION
Most effective in sands
Methods used in conventional earthwork are
only effective to about 2 m below the surface
In-situ methods like dynamic deep compaction
are for soils deeper than can be compacted
from the surface
DYNAMIC VS. VIBRATORY
178
VIBROFLOTATION
From Das, 1998
Vibroflotation is a technique for
in situ densification of thick
layers of loose granular soil
deposits. It was developed in
Germany in the 1930s.
179
VIBROFLOTATION-PROCEDURES
Stage1: The jet at the bottom of the Vibroflot is turned on and lowered into the ground
Stage2: The water jet creates a quick condition in the soil. It allows the vibrating unit to
sink into the ground
Stage 3: Granular material is poured from the top of the hole. The water from the lower jet
is transferred to he jet at the top of the vibrating unit. This water carries the granular
material down the hole
Stage 4: The vibrating unit is gradually raised in about 0.3-m lifts and held vibrating for
about 30 seconds at each lift. This process compacts the soil to the desired unit weight.
From Das, 1998
VIBRATORY PROBE COMPACTION
Long probe mounted onto a vibratory pile driver
compacts the soil around the probe;
penetrations spaced in a grid pattern similar to
vertical drains
VIBRATORY PROBE COMPACTION
BEWARE OF TRANSMISSION OF GROUND
VIBRATIONS
VIBROFLOTATION
Probe includes the vibrator mechanism and water jets
Probe is lowered into the ground using a crane
Vibratory eccentric force induces densification and water jets assist in insertion and extraction
Vibratory probe compaction is effective if silt content is less than 12-15% and clay is less than 3%
Probes inserted in grid pattern at a spacing of 1.5 to 3 m
VIBROFLOTATION
Ground Type Relative
Effectiveness
Sands Excellent
Silty Sands Marginal to Good
Silts Poor
Clays Not applicable
Mine Spoils Good (if granular)
Dumped Fill Depends upon nature
of fill
Garbage Not Applicable
VIBRO-REPLACEMENT STONE COLUMNS
Vibro-Replacement extends the range of soils
that can be improved by vibratory techniques to
include cohesive soils. Reinforcement of the
soil with compacted granular columns or "stone
columns" is accomplished by the top-feed
method.
Top-feed vibroflot rig
Adding stone in top-feed installation Bottom-feed vibroflot rig
VIBRO-REPLACEMENT STONE COLUMNS
187
DYNAMIC COMPACTION
Dynamic compaction was first used in
Germany in the mid-1930’s.
The depth of influence D, in meters, of soil
undergoing compaction is conservatively
given by
D ½ (Wh)1/2
W = mass of falling weight in metric tons.
h = drop height in meters
From Holtz and Kovacs, 1981
Uses a special crane to lift 5-30 tons to heights of 40 to 100 feet then drop these weights onto the ground
Cost effective method of densifying loose sands and silty soils up to 15 to 30 feet deep
DYNAMIC COMPACTION
GROUTING
Defined as the injection of a special liquid or
slurry material called grout into the ground for
the purpose of improving the soil or rock
Types of grouts
Cementitious grouts
Chemical grouts
GROUTING METHODS
Intrusion grouting
Consists of filling joints or fractures with grout
Primary benefit is reduction in hydraulic conductivity
Used to prepare foundation and abutments for dams
Usually done using cementitious grouts
Permeation grouting
Injection of thin grouts into the soil
Once the soil cures, becomes a solid mass
Done using chemical grouts
Used for creating groundwater barriers or preparign ground before tunneling
GROUTING METHODS
Compaction grouting
When low-slump
compaction grout is
injected into granular soils,
grout bulbs are formed that
displace and densify the
surrounding loose soils.
Used to repair structures
that have excessive
settlement
GROUTING METHODS
Jet grouting
Developed in Japan
Uses a special pipe with horizontal jets that inject grout into the ground at high pressures
Jet grouting is an erosion/replacement system that creates an engineered, in situ soil/cement product known as Soilcretesm. Effective across the widest range of soil types, and capable of being performed around subsurface obstructions and in confined spaces, jet grouting is a versatile and valuable tool for soft soil stabilization, underpinning, excavation support and groundwater control.
STABILIZATION USING ADMIXTURES
Most common admixture is Portland Cement
When mixed with soil, forms soil-cement which is comparable to a weak concrete
Other admixtures include lime and asphalt
Objective is to provide artificial cementation, thus increasing strength and reducing both compressibility and hydraulic conductivity
Used to reduce expansion potential of clays
Used in surface mixing applications
REINFORCEMENT
Soil is stronger in compression than in
tension
To improve strength in tension,
geosynthetics placed in soil for soil
reinforcement
REINFORCED EARTHWALL CONSTRUCTION
SOIL NAILING
The fundamental concept
of soil nailing consists of
reinforcing the ground by
passive inclusions, closely
spaced, to create in-situ a
coherent gravity structure
and thereby to increase
the overall shear strength
of the in-situ soil and
restrain its displacements.
SLOPE STABILITY ANALYSIS
197
SLOPE STABILITY ANALYSIS
198
SLOPE STABILITY ANALYSIS
199
SLOPE STABILITY ANALYSIS
The field of slope stability encompasses the
analysis of static and dynamic stability of
slopes of earth and rock-fill dams.
200
SLOPE STABILITY ANALYSIS
201
TYPES OF LANDSLIDE
Rock failure
failure plane pre-
determined
Soil failure
failure plane along line
of max stress
TYPES OF LANDSLIDE
Rock failure
failure along pre-determined planes of weakness
Soil failure
failure along lines of max. stress
frictional, cohesive = rotational
frictional, incohesive = planar
MASS MOVEMENTS CLASSIFICATION
FALLS, FLOWS, SLIDES AND SUBSIDES.
Falls and subsides involve vertical drops. Slides and flows involve downward and outward motion.
Sliding involves a coherent mass.
Flowing involves the moving mass behaving like a viscous fluid.
MASS MOVEMENTS FALL
MASS MOVEMENTS SLIDES
ROTATIONAL
Downward and outward
movement on a curved
surface.
Note the rotation of head
and the up movement of
the toe.
MASS MOVEMENTS TRANSLATIONAL SLIDES
THREE TYPES
1. Move as coherent blocks.
2. May deform and break-up as a debris slide.
3. Involve lateral spreading where the underlying
material fails and flows,
MASS MOVEMENTS FLOWS
Movements that behave like fluids with internal reorganization
Loess flows - the flow of loose silt,
Earth flows - wet flows moving slowly on slick surface,
Debris flows - massive rock falls that convert into highly
fluidized rapidly moving Debris flows.
MASS MOVEMENTS FLOWS
EARTH FLOW: PORTUGUESE BEND
View of the toe of the bulged up earth flow in 1959. Note the remains of the houses and the roads and the damaged pier.
TYPES OF SLOPE FAILURE
The common modes of slope failure in soils are
by:
Translational failure
Rotation failure
Flow failure and
Block movement failure
210
SLOPE FAILURE
211 TRANSLATIONAL SLOPE FAILURE
SLOPE FAILURE
212 ROTATIONAL SLOPE FAILURE
SLOPE FAILURE
213
FLOW SLOPE FAILURE
SLOPE FAILURE
214
BLOCK MOVEMENT SLOPE FAILURE
SLOPE FAILURE
EXTERNAL PROCESSES CAUSING FAILURE
Processes include: 1) steepen slope, 2) remove support from bottom of slope, and 3) add mass high up on slope.
ROTATIONAL LANDSLIP ANALYSIS
For undrained frictionless failure
total stress analysis
For cohesive and frictional failure
method of slices
Bishop’s conventional method (can take into
account pore water pressure)
METHODS OF SLOPE STABILITY ANALYSIS
Limit equilibrium method
Total stress analysis
Effective tress analysis
217
LIMIT EQUILIBRIUM METHOD
It is not a rigorous theoretical method but is used
because it gives simple and reasonable estimates of
collapse. The method has advantages over Rankin’s
method.
It can cope/handle with any geometry, It can cope with
applied loads and Friction between soil and retaining
walls (and other structural elements) can be accounted.
For any point on the failure plane we have:
218
f tannc
TOTAL STRESS ANALYSIS
If analysis is of undrained stability then the failure
criterion must be expressed in terms of total stress using
undrained parameters cu and fu.
A total stress analysis is only valid if the soil is
saturated and does not drain.
In practice this generally means total stress analysis is
limited to assessment of the short term stability of
clayey soils.
Must use total stresses and undrained parameters cu
and fu
219
unuc f tan
EFFECTIVE TRESS ANALYSIS
An effective stress analysis can be performed
whenever the pore pressures are known.
In practice this usually means that effective
stress analysis can only be used to assess the
long term stability. When performing effective
stress stability calculations the critical state
parameters c = 0, f = fult should be used.
220
``tan` f c
LIMIT EQUILIBRIUM METHODS OF SLOPE STABILITY
All limit equilibrium methods of slope stability
analysis have four characteristics in common
(Duncan and Wright, 1980):
1) All use the following definition of the factor of
safety (F):
221
mequilibriufor required stressShear
soil ofstrength Shear
F
sF
LIMIT EQUILIBRIUM METHODS OF SLOPE STABILITY
2) Placing a factor of safety is appropriate
3) All assume that the strength parameters are
independent of stress-strain behavior.
4) All use some or all of the equations of
equilibrium to calculate the average values of
and n on each slice, where n is the normal
stress on the base of the slice.
222
UNDRAINED INFINITE SLOPES
Consider an infinite slope in a cohesionless soil
without seepage. The thickness is supposed to
be unity. The soil is often assumed to be
homogeneous; however, in real situations. The
soil may be highly stratified with widely varying
shear strengths. If we isolate an element and
examine the forces for stability that is:
223
224
z
z
W
FD
N
FR
b
l
cos
sin
WN
WFD
From the geometry of figure
And the resisting force
against the failure FR can be
expressed as:
f
f
tancos
tan
WF
NF
R
R
cos
)1(
lzW
zbVW
UNDRAINED INFINITE SLOPES
Applying limit equilibrium conditions
225
f
f
f
f
tantan
cos/sintan
sintancos WW
FF DR
It shows that for stability conditions slope angle
should be less or equal to angle of internal friction-f.
UNDRAINED INFINITE SLOPES
Factor of safety (in terms of resisting to driving
force)
226
f
f
tan
tan
sin
tancos
F
W
WF
F
FF
D
R
UNDRAINED INFINITE SLOPES
227
Factor of safety (in terms of undrained shear
strength )
2sin
2
)sincos2(
2
sincos
sin
z
SF
z
SF
z
SF
W
SF
F
FF
u
u
u
u
D
R
UNDRAINED INFINITE SLOPES
Critical depth against slope failure
It is the depth at which the slip surface may be
expected to develop. If the FS is taken as unity
the depth z is supposed to be the critical depth
zc. It can be expressed as:
228
2sin
2
2sin
2
uc
u
Sz
z
SF
EXAMPLE
Calculate the factor of safety relating to the
undrained stability of a long slope of 1 V:1.5 H if
at a depth of 1.8 m a weak layer of cohesive soil
occurs for which Su = 24 kPa and for the
overburden = 18.5 kPa.
229
u2SF
zsin 2
2 24F
18.5 1.8sin(2 33.69)
F 1.56
EXAMPLE
The soil in a long slope has undrained shear
strength of 50 kPa and a unit weight of 18 kPa.
Using the infinite slope method, estimate the
depth at which a shear may develop when the
slope angle is 220.
230
uc
c
c
2Sz
sin 2
2 50z
18sin(2 22)
z 8.0 m
ROTATIONAL SLIP
total stress analysis or
fu = 0
strength parameters
are those of undrained
soil
We
CrF
2
where
F = restraining moment
disturbing moment
C = cohesive strength (Pa)
r = slip circle radius (m)
= slip sector in radians
W = weight of sliding sector (N)
e = eccentricity of sliding sector (m)
LOCATION OF SLIP CIRCLE CENTRE
No simple way – trial and error
THE METHOD OF SLICES
When the soil forming the slope has to be analyzed
under a condition where full or partial drainage
takes place the analysis must take into account both
cohesive and frictional soil properties based on
effective stresses. Since the effective stress acting
across each elemental length of the assumed
circular arc failure surface must be computed in this
case, the method of slices is one of the convenient
methods for this case. The method of analysis is as
follows:
233
THE METHOD OF SLICES
234
THE METHOD OF SLICES
235
THE METHOD OF SLICES
236
THE METHOD OF SLICES
237
O
A
B R
THE METHOD OF SLICES
238
O
A
B R
THE METHOD OF SLICES
239
THE METHOD OF SLICES
240
THE METHOD OF SLICES
241
Xn+1
l
W N
FR
FU
Xn
En
En+1
FD
THE METHOD OF SLICES 1) The soil mass above the assumed
slip circle is divided into a number
of vertical slices of equal width.
2) The number of slices may be
limited to a maximum of eight to
ten to facilitate computation.
3) In this method it is assumed that
the interslice forces are equal and
opposite and cancel each other,
i.e., Xn = Xn+1, En = En+1
4) The forces used in the analysis
acting on the slices are shown in
the figure
242
Xn+1
l
W N
FR
FU
Xn
En
En+1
FD
O
A
B R
THE METHOD OF SLICES
243
Xn+1
l
W N
FR
FU
Xn
En
En+1
FD
The forces are:
W = the weight of the slice.
N = the normal component of the weight
FD = Driving force
FR = Resisting force
FU = Pore water force
Xn = Xn+1 = Interslice forces
Pore pressure ratio ru
h
uur
v
u
THE METHOD OF SLICES
244
Xn+1
l
W N
FR
FU
Xn
En
En+1
FD
It is now only necessary to resolve the
forces acting on the base of slices
``tan` fNcFR
uWN
FWN U
cos`
cos`
sinWFD
`tan)cos(` f ulWcFR
THE METHOD OF SLICES
245
Xn+1
l
W N
FR
FU
Xn
En
En+1
FD
The factor of safety is then given as:
f
sin
`tancos`
W
uWcFS
F
FFS
D
R
THE METHOD OF SLICES
246
This can also be expressed as:
Xn+1
l
W N
FR
FU
Xn
En
En+1
FD
b
pn
n
n
pn
n
nn
pn
n
n
pn
n
nn
pn
n
D
pn
n
R
W
ulWc
FS
W
ulWc
FS
F
F
FS
1
1
1
1
1
1
sin
`}tan)cos(`{
sin
`tancos`
f
f
OTHER METHODS OF ANALYSIS
Taylor’s stability analysis
used for frictional and cohesive soils
uses a dimensionless number to iterate towards a
solution
Bishop’s method
effect of forces on each side of slice considered
iterative method
SLOPE STABILIZATION METHODS
Slopes Flattened or Benched
Berm Provided at Toe
Protection Against Erosion Provided at Toe
Lowering of GWT to Reduce the Pore Pressures
Drainage of Slopes
Use of Driven or Cast-in-Place Piles
Retaining Wall OR Sheet piling OR Cylinder
Piles Provided to Increase Resistance to Sliding
SLOPES FLATTENED OR BENCHED
BERM PROVIDED AT TOE
Weight Increases the Resistance to Sliding
PROTECTION AGAINST EROSION PROVIDED AT TOE
LOWERING OF GWT TO REDUCE THE PORE PRESSURES
DRAINAGE OF SLOPES
Drains are added to stabilize slopes
USE OF DRIVEN OR CAST-IN-PLACE PILES
RETAINING WALL OR SHEET PILING OR CYLINDER PILES
PROVIDED TO INCREASE RESISTANCE TO SLIDING
PLAN FOR BUILDING DESIGN TO AID SLOPE STABILITY
EARTH AND ROCK FILL
DAMS
DAM
Dam is a solid barrier constructed at a suitable
location across a river valley to store flowing
water.
Storage of water is utilized for following
objectives:
Hydropower
Irrigation
Water for domestic consumption
Drought and flood control
Other additional utilization is to develop fisheries
COMPONENTS OF DAM
Body of Dam
Foundation
Top road
Gates and lifting devices
Spill way or Sluice
Canal
Reservoir
Main river course
Stilling Basin
Drainage gallery
COMPONENTS OF DAM
Reservoir
Water
Foundation Soil
Dam Body
Foundation
Upstream Down Stream
Drainage Gallery
Spill Way
Gate
Sluice gate
Heel: contact with the ground on the upstream side
Toe: contact on the downstream side
Abutment: Sides of the valley on which the structure of the dam rest
Galleries: small rooms like structure left within the dam for checking operations.
Diversion tunnel: Tunnels are constructed for diverting water before the construction of dam. This helps in keeping the river bed dry.
Spillways: It is the arrangement near the top to release the excess water of the reservoir to downstream side
Sluice way: An opening in the dam near the ground level, which is used to clear the silt accumulation in the reservoir side.
COMPONENTS OF DAM
Abutment
Abutment
Main River Course
Right bank Canal
Reservoir
Left Bank Canal
Upstream
Downstream
Plan of Dam
Function Example
Power
generation
Hydroelectric power is a major source of electricity in the
world. many countries have rivers with adequate water flow, that
can be dammed for power generation purposes.
Stabilize
water flow /
irrigation
Dams are often used to control and stabilize water flow, for
agricultural purposes and irrigation. They can help to stabilize or
restore the water levels of inland lakes and seas. They store water
for drinking and other direct human needs,
Flood
prevention Dams are created for flood control.
Land
reclamation
Dams (often called dykes or levees) are used to prevent ingress of
water to an area that would otherwise be submerged, allowing its
reclamation for human use.
Water
diversion Dams are used for the purpose of diversion.
FUNCTIONS OF DAMS
CLASSIFICATION OF DAMS
Based on Size
Based on function
Based on material used
CLASSIFICATION BASED ON SIZE
Small Dam (<10 m high)
Medium size Dam (10 – 25 m high)
Large Dam (>25 m high)
Major Dam (>150 m high)
CLASSIFICATION BASED ON PURPOSE
Hydro-electric dam
Irrigation dam
Water supply dam for city for the purposes of drinking water, recreation, navigation thro canals, industrial use.
Flood Control
Habitat dam for fishes & wild life
Effluent containing dams from industry, mine, factory etc.
Multi-purpose dam
CLASSIFICATION BASED ON MATERIAL OF CONSTRUCTION
Masonry Dam
Concrete Dam
Timber Dam
Steel Dam
Earth Dam
Rockfill Dam
Composite Dam
Combined Earth & Rockfill Dam
Earth Dam
EARTH DAMS They are trapezoidal in
shape
Earth dams are constructed where the foundation or the underlying material or rocks are weak to support the masonry dam or where the suitable competent rocks are at greater depth.
Earthen dams are relatively smaller in height and broad at the base
They are mainly built with clay, sand and gravel, hence they are also known as Earth fill dam or Rock fill dam
Earth-Fill Embankment Dam
A earth-fill dam in Australia.
Earth-Fill Embankment Dam
Homogeneous Embankment Dam
Diaphragm Earth Dam
Embankment Dam
Rock fill Dam with RC facing
MATERIALS FOR CONSTRUCTION
Earthfill dam – Locally materials
Rockfill dam – Rocks of all sizes are used for
stability and impervious membrane for water
seal.
METHODS OF CONSTRUCTIONS
Rockfill Dam
Rock placed in layers – Materials are dumped
on the embankment surface and pushed over
the advancing construction face with a
buldozer
Dumped in high sluiced lift – The material is dumped down the sloping face of the construction lift and sluiced with high pressure water jets from monitors. The fines and smaller rocks are deposited at the top of the lift and the larger rocks slide and rolled down the face of the slope to the lower part of the lift.
Earthfill Dam
Excavate the materials
Hauling to the dam,
METHODS OF CONSTRUCTIONS
Mixe to predetermine water content and
unformity of properties
Sread it in layers and
Compact to desire density
METHODS OF CONSTRUCTIONS
ADVANTAGES OF CONSTRUCTION IN LAYERS
Rock with a higher percentage of fines can be placed, there is less danger segregation of fines accumulations
Embankment obtained is more denser, uniform and less compressible
It can be built with any slide slope inclination but rockfill dumped in high lift is placed on the angle of repose of the materials
etc
STABILITY
The stability of an embankment lies in its ability
to resist shearing stresses created by external
applied loads such as reservoiur water
pressure and internal forces caused by the soil
mass and embankment slope
STABILITY OF DOWNSTREAM SLOPE DURING
STEADY SEEPAGE
Examine the most critical condition i.e when the reservouir is full and the seepage is taking place at full rate
Draw the flow net and determine the points of intersections of equipotentiallineswith failure arc
Get the critical arc
Calculate the shear strength developed on the slices and find the net shear strength
About 1,600 cubic meter per second of water is
diverted from the Indus River near the town of
Ghazi about 7 km downstream of Tarbela
Dam (3,478 MW).
It then runs through 52 km long , 100 metre wide
and 9 meter deep open concrete-lined channel
down to the village of Barotha where the power
complex is located.
After passing through the powerhouse, the water
is returned to the Indus.
The project took about 10 years and $2.2 billion
to complete, 1,450MW powerhouse at Barotha.
FOUNDATION DYNAMICS
Initially intended for the calculation of the vibrations of the
massive foundations of heavy machines, the analyses of
dynamic soil-structure interaction have also been long used for
seismic calculations.
in the first case the machine (or the rail or road traffic) is in
general the source of the vibrations
in the second case the soil directly provides the loads.
In both cases however, the objectives are identical, i.e. to
evaluate the movements of the foundation under the action of
external loads, and consequently anticipate the displacements
of the machine or of the structure keeping in mind both the
characteristics of the foundation and the properties of the soil.
FOUNDATION DYNAMICS
SIMPLEST FORM OF VIBRATING SYSTEM
D
d = D sinnt
m
k
T
Time
Displacement
Frequency 1
T
Period, Tn in [sec]
Frequency, fn= in [Hz = 1/sec] 1
Tn
Displacement
k
m n= 2 fn =
MASS AND SPRING
time
m1
m
Increasing mass
reduces frequency
1
nmm
k2
nf
MASS, SPRING AND DAMPER
Increasing damping
reduces the amplitude
time
m
k c1 + c2
)()()()( tftKxtxCtxM
M = mass (force/acc.)
C = damping (force/vel.)
K = stiffness (force/disp.)
)t(x)t(x)t(x
Acceleration Vector
Velocity Vector
Displacement Vector
)t(f Applied force Vector
BASIC SDOF MODEL f(t)
x(t)
k c
m
INTRODUCTION TO
LIQUEFACTION
WHAT IS LIQUEFACTION?
Liquefaction-when the strength and
stiffness of a soil is reduced due to
earthquake shaking
Liquefaction occurs in saturated soils
NIIGATA 1964 AND KOBE, JAPAN 1995
HISTORY
Serious attention because of Japan, Alaska and Nigata
earthquake in 1964.
CYCLIC MOBILITY
OVERTURNING
SAND BOILING
1. WHY IS LIQUEFACTION DANGEROUS?
2. WHAT DO YOU NEED FOR LIQUEFACTION TO
OCCUR?
A. DRY SOIL AND AN EARTHQUAKE
B. SATURATED SOIL AND AN EARTHQUAKE
C. SATURATED SOIL
1. WHY IS LIQUEFACTION DANGEROUS?
LIQUEFACTION CAN CAUSE BUILDINGS AND
INFRASTRUCTURE TO COLLAPSE.
2. WHAT DO YOU NEED FOR LIQUEFACTION TO
OCCUR?
A. DRY SOIL AND AN EARTHQUAKE
B. SATURATED SOIL AND AN EARTHQUAKE
C. SATURATED SOIL