geopacific resources (gpr) · 2020. 11. 20. · shaw and partners gpr – equity report current as...

26
Shaw and Partners GPR – Equity Report current as at –18/05/2020Pg. 1 Geopacific Resources (GPR) Rating: Buy | Risk: High | Price Target: $1.37 Gold – it’s a Lark. Initiation of Coverage Andrew Hines | Senior Analyst +61 3 9268 1178 [email protected] Event We initiate coverage on Geopacific Resources (GPR) with a Buy recommendation and A$1.37ps price target. Geopacific Resources is developing the Woodlark Gold Project on Woodlark Island in Papua New Guinea. The project is fully permitted and early construction has commenced. Highlights Woodlark is a standard and simple open cut mining operation and carbon-in- leach (CIL) processing plant which will produce ~100koz of gold per annum over a 13 year mine life. On our forecasts the project has a 2 year payback, an IRR of 52% and an NPV @10% of A$341m. Cash flow will be front end loaded due to higher grade and lower strip ratios in the early years of production. Woodlark Island is flat, access is relatively straightforward via sea or air (there is an existing airstrip), and the landowners are supportive, so Geopacific does not face the usual problems associated with operating in PNG. Once in production (expected in 2022), at today’s share price Geopacific will be trading on a PE multiple of just 1.3x and an EV/EBITDA multiple of 0.2x. Geopacific is one of the cheapest gold companies listed on the ASX with an EV/resource of A$15/oz compared to a sector average A$226/oz. The A$ gold price recently hit an all-time high of A$2,720/oz and we expect the US$ gold price to continue rising and peak at around US$2,000/oz in late 2022. At spot gold our NPV of the project increases to A$545m (A$1.57ps on a fully diluted basis). Woodlark has a resource of 47Mt at 1.04g/t for 1.57Moz gold and reserve of 28.9Mt @ 1.12g/t for 1.04Moz gold. There is significant exploration upside on the island and we expect to see ongoing resource upgrades. It would not surprise us to see the resource base increased to over 5Moz over time. GPR raised A$40m in late 2019 to fund early construction, which includes site clearing, road works, relocation of housing and construction of a new wharf facility. The project will require around $200m capex to first production. GPR released a Definitive Feasibility Study (DFS) in October 2018 which outlined a 13 year project with an NPV @ 8% of A$197m and IRR of 29% based on an A$ gold price of A$1,650/oz. Since the release of the DFS, early construction has commenced and the gold price has materially increased. The project is now even more attractive. Costs are very low due to the low strip ratio (3.9x life of mine, and less than 3x in the early years). All-in sustaining costs are estimated at A$1,033/oz (life of mine) and A$866/oz in the first five years. Recommendation We initiate coverage on Geopacific Resources (GPR) with a Buy recommendation and A$1.37ps price target. We have set our price target at a fully diluted valuation post an assumed A$60m equity raise at a share price of A$0.35ps. Catalysts for the stock to reach our price target include; Resolution of financing options. Delivery of the Woodlark project through the course of 2020/21. Resource upgrades following further exploration on Woodlark Island.

Upload: others

Post on 01-Mar-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners

0.42000 0000 000

GPR – Equity Report current as at –18/05/2020–Pg. 1

Geopacific Resources (GPR) Rating: Buy | Risk: High | Price Target: $1.37

Gold – it’s a Lark. Initiation of Coverage

Andrew Hines | Senior Analyst

+61 3 9268 1178 [email protected]

Event We initiate coverage on Geopacific Resources (GPR) with a Buy recommendation and A$1.37ps price target. Geopacific Resources is developing the Woodlark Gold Project on Woodlark Island in Papua New Guinea. The project is fully permitted and early construction has commenced.

Highlights Woodlark is a standard and simple open cut mining operation and carbon-in-

leach (CIL) processing plant which will produce ~100koz of gold per annum over a 13 year mine life. On our forecasts the project has a 2 year payback, an IRR of 52% and an NPV @10% of A$341m. Cash flow will be front end loaded due to higher grade and lower strip ratios in the early years of production.

Woodlark Island is flat, access is relatively straightforward via sea or air (there is an existing airstrip), and the landowners are supportive, so Geopacific does not face the usual problems associated with operating in PNG.

Once in production (expected in 2022), at today’s share price Geopacific will be trading on a PE multiple of just 1.3x and an EV/EBITDA multiple of 0.2x. Geopacific is one of the cheapest gold companies listed on the ASX with an EV/resource of A$15/oz compared to a sector average A$226/oz.

The A$ gold price recently hit an all-time high of A$2,720/oz and we expect the US$ gold price to continue rising and peak at around US$2,000/oz in late 2022. At spot gold our NPV of the project increases to A$545m (A$1.57ps on a fully diluted basis).

Woodlark has a resource of 47Mt at 1.04g/t for 1.57Moz gold and reserve of

28.9Mt @ 1.12g/t for 1.04Moz gold. There is significant exploration upside on

the island and we expect to see ongoing resource upgrades. It would not surprise

us to see the resource base increased to over 5Moz over time.

GPR raised A$40m in late 2019 to fund early construction, which includes site clearing, road works, relocation of housing and construction of a new wharf facility. The project will require around $200m capex to first production.

GPR released a Definitive Feasibility Study (DFS) in October 2018 which outlined a 13 year project with an NPV @ 8% of A$197m and IRR of 29% based on an A$ gold price of A$1,650/oz. Since the release of the DFS, early construction has commenced and the gold price has materially increased. The project is now even more attractive.

Costs are very low due to the low strip ratio (3.9x life of mine, and less than 3x in

the early years). All-in sustaining costs are estimated at A$1,033/oz (life of mine)

and A$866/oz in the first five years.

Recommendation We initiate coverage on Geopacific Resources (GPR) with a Buy recommendation and A$1.37ps price target. We have set our price target at a fully diluted valuation post an assumed A$60m equity raise at a share price of A$0.35ps.

Catalysts for the stock to reach our price target include;

Resolution of financing options.

Delivery of the Woodlark project through the course of 2020/21.

Resource upgrades following further exploration on Woodlark Island.

Page 2: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 2

Geopacific Resources Ltd. is developing the Woodlark Gold Project on Woodlark Island in PNG. First production is expected in 2022 and the operation will produce approximately 100koz of gold per annum over a 13 year mine life.

Page 3: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 3

Table of Contents

Geopacific Resources key financials 4

Executive Summary 5

Geopacific Resources in charts 6

Geopacific is attractively place in an attractive sector 8

Gold price 10

Geopacific Resource and Woodlark Gold Project overview 12

Woodlark Definitive Feasibility Study 13

Resources and exploration upside 14

Construction activity and progress to date 16

Woodlark financials 18

Geopacific P&L 19

Financing – balance sheet and cash flow 20

Valuation and price target 21

Key risks 22

Appendix: Key personnel 23

Page 4: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4

Geopacific Resources Key financials

Profit & Loss FY19 FY20f FY21f FY22f FY23f Company Information

Revenue 0.0 0.0 0.0 269.8 283.1 Financial Year End Date 31-Dec

Expenses -7.2 -5.0 -5.1 -96.3 -102.9 Share Price 0.42

Underlying EBITDA -7.2 -5.0 -5.1 173.5 180.2 Market Capitalisation 73

Depreciation & Amort -0.3 0.0 0.0 -17.8 -21.4 Valuation 1.37

Underlying EBIT -7.4 -5.0 -5.1 155.6 158.8 Recommendation Buy

Net Interest 0.1 -1.6 -4.0 -6.1 -1.2

Profit Before Tax -7.3 -6.6 -9.1 149.5 157.5 Per Share Data (c) FY19 FY20f FY21f FY22f FY23f

Tax 0.0 0.0 0.0 -37.4 -39.4 Shares (m) 175 346 346 346 346

NPAT (Underlying) -7.3 -6.6 -9.1 112.1 118.1 Normalised EPS -0.7 -2.5 -2.6 32.4 34.1

Exceptional items 0.0 0.0 0.0 0.0 0.0 Dividends 0.0 0.0 0.0 0.5 1.0

NPAT (reported) -7.3 -6.6 -9.1 112.1 118.1 Dividend Yield (%) 0.0% 0.0% 0.0% 1.2% 2.4%

Book Value 0.40 0.36 0.33 0.66 0.99

Balance Sheet FY19 FY20f FY21f FY22f FY23f P/E (x) -64.6 -16.5 -15.9 1.3 1.2

Cash 37.5 75.1 4.2 108.6 200.9 EV/EBITDA (x) -5.0 -7.2 -7.0 0.2 0.2

Net Receivables 0.7 0.7 0.0 22.2 23.3

Other 1.4 1.4 1.0 19.5 20.4 Valuation (fully diluted) A$m A$ps

Current Assets 39.6 77.2 5.2 150.3 244.6 Woodlark Island 341 0.99

Property, Plant & Equipment 1.9 48.8 105.7 89.2 69.2 Net debt 98 0.28

Other 39.1 87.9 146.9 150.2 153.6 Exploration upside 50 0.14

Non Current Assets 41.0 136.7 252.6 239.5 222.8 Corporate costs -15 -0.04

Total Assets 80.5 213.9 257.8 389.8 467.3 Total Valuation 474 1.37

Trade Creditors 7.0 7.0 0.0 12.5 13.4

Borrow ings 0.0 0.0 0.0 0.0 0.0 Assumptions FY19 FY20f FY21f FY22f FY23f

Other 0.1 0.1 0.1 0.1 0.1 Prices

Current Liabilities 7.1 7.1 0.1 12.6 13.5 A$/US$ 0.70 0.64 0.72 0.74 0.74

Borrow ings 0.0 80.0 140.0 110.0 70.0 Gold (US$/oz) 1425 1669 1847 1951 1946

Other 2.9 2.9 2.9 40.3 42.3

Non Current Liabilities 2.9 82.9 142.9 150.3 112.3 Operating Metrics FY19 FY20f FY21f FY22f FY23f

Net Assets 70.5 123.9 114.7 226.9 341.5 Ore processed (ktpa) 0 2000 2400

Average grade (g/t) 1.72 1.55

Shareholder Capital 149.0 209.0 209.0 209.0 209.0 Gold produced (koz) 102 108

Retained earnings -83.3 -90.0 -99.1 13.1 127.7 AISC (US$/oz) 681 690

Minorities/others 4.8 4.8 4.8 4.8 4.8 AISC (A$/oz) 920 933

Total Equity 70.5 123.9 114.7 226.9 341.5

Average price (A$/oz) 2637 2630

Cash Flow FY19 FY20f FY21f FY22f FY23f Average cost (A$/oz) 824 841

Receipts 0.0 0.0 0.0 269.8 283.1 Average margin (AS$/oz) 1813 1789

Payments -4.2 -5.0 -5.1 -96.3 -102.9

Other Operating Cash Flow 0.0 -1.6 -10.0 -34.3 -39.7 Financial metrics (%) FY19 FY20f FY21f FY22f FY23f

Operating Cash Flow -4.2 -6.6 -15.1 139.2 140.4 EBITDA margin 0.0% 0.0% 0.0% 64.3% 63.6%

Capex -1.1 -93.8 -113.9 -2.7 -2.7 EBIT margin 0.0% 0.0% 0.0% 57.7% 56.1%

Other Investing Cash Flow -1.8 -2.0 -2.0 -2.0 -2.0 ROIC 0.0% 0.0% 0.0% 47.7% 52.8%

Investing Cash Flow -2.9 -95.8 -115.9 -4.7 -4.7 Return on Assets -12.0% -4.5% -3.9% 34.6% 27.6%

Net Equity raised 42.0 60.0 0.0 0.0 0.0 Return on Equity -14.0% -6.8% -7.6% 65.6% 41.6%

Dividends Paid 0.0 0.0 0.0 0.0 -3.5

Net Borrow ings 0.0 80.0 60.0 -30.0 -40.0 Balance sheet metrics FY19 FY20f FY21f FY22f FY23f

Other -0.1 0.0 0.0 0.0 0.0 Net Debt (m) -38 5 136 1 -131

Financing Cash flow 41.9 140.0 60.0 -30.0 -43.5 ND / ND+E n/a 3.2% 48.3% 0.9% n/a

Total Cash Change 34.8 37.6 -71.0 104.5 92.3

Page 5: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 5

Executive Summary We initiate coverage on Geopacific Resources (GPR) with a Buy recommendation and A$1.37ps price target. Geopacific Resources is developing the Woodlark Gold Project on Woodlark Island in Papua New Guinea.

Core drivers & catalysts

Woodlark is a standard and simple open cut mining operation and carbon-in-leach (CIL) processing plant which will produce ~100koz of gold per annum over a 13 year mine life. On our forecasts the project has a 2 year payback, an IRR of 52% and an NPV @10% of A$341m. Cash flow will be front end loaded due to higher grade and lower strip ratios in the early years of production.

Once in production (expected in 2022), at today’s share price Geopacific will be trading on a PE multiple of just 1.3x and an EV/EBITDA multiple of 0.2x. Geopacific is one of the cheapest gold companies listed on the ASX with an EV/resource of A$15/oz compared to a sector average A$226/oz.

The A$ gold price recently hit an all-time high of A$2,720/oz and we expect the US$ gold price to continue rising and peak at around US$2,000/oz in late 2022. At spot gold our NPV of the project increases to A$545m (A$1.57ps on a fully diluted basis).

Woodlark has a resource of 47Mt at 1.04g/t for 1.57Moz gold and reserve of 28.9Mt @ 1.12g/t for 1.04Moz gold. There is significant exploration upside on the island and we expect to see ongoing resource upgrades. It would not surprise us to see the resource base increased to over 5Moz over time.

Costs are very low due to the low strip ratio (3.9x life of mine, and less than 3x in the early years). All-in sustaining costs are estimated at A$1,033/oz (life of mine) and A$866/oz in the first five years.

Key risks

The gold price is volatile and driven as much by geopolitical events as fundamental supply and demand. As such, the price of gold is relatively difficult to forecast and the actual price may differ substantially from our forecasts.

The Woodlark Gold Project is not yet producing and there is a risk that Geopacific is unable to bring the operation in to production. The project may cost more than expected to build, and may not operate as expected.

Geopacific Resources is operating in PNG. Woodlark Island is flat, access is relatively straightforward via sea or air (there is an existing airstrip), and the landowners are supportive, so Geopacific does not face the usual problems associated with operating in PNG.

Figure 1: Free cash flow (A$m) Figure 2: Valuation sensitivity to gold price

Source: Company data & Shaw and Partners analysis Source: Company data & Shaw and Partners analysis

-150

-100

-50

0

50

100

150

200

20

18

20

19

20

20

f

20

21

f

20

22

f

20

23

f

20

24

f

20

25

f

20

26

f

20

27

f

20

28

f

20

29

f

0.00

0.50

1.00

1.50

2.00

2.50

A$1600/oz A$1800/oz Shaw A$2000/oz A$2200/oz A$2400/oz A$2600/oz spot

Current share price

Page 6: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 6

Geopacific Resources in Charts

Figure 3: Production (kt) – first production in 2022 Figure 4: Revenue (A$m) – >$200mpa revenue once in production

Source: Company data & Shaw and Partners analysis Source: Company data & Shaw and Partners analysis

Figure 5: EBITDA (A$m) – strong profits from 2023 Figure 6: EBIT (A$m) – similar profile to EBITDA

Source: Company data & Shaw and Partners analysis Source: Company data & Shaw and Partners analysis

Figure 7: NPAT (A$m) – ~A$50m NPAT from 2023 Figure 8: Operating cash flow (A$m) – growth in line with EBITDA

Source: Company data & Shaw and Partners analysis Source: Company data & Shaw and Partners analysis

0

20

40

60

80

100

120

2018

2019

2020

f

2021

f

2022

f

2023

f

2024

f

2025

f

2026

f

2027

f

2028

f

2029

f

2030

f

2031

f 0

50

100

150

200

250

300

20

18

20

19

20

20

f

20

21

f

20

22

f

20

23

f

20

24

f

20

25

f

20

26

f

20

27

f

20

28

f

20

29

f

-50

0

50

100

150

200

20

18

20

19

20

20

f

20

21

f

20

22

f

20

23

f

20

24

f

20

25

f

20

26

f

20

27

f

20

28

f

20

29

f

-100

-50

0

50

100

150

200

20

18

20

19

20

20

f

20

21

f

20

22

f

20

23

f

20

24

f

20

25

f

20

26

f

20

27

f

20

28

f

20

29

f

-20

0

20

40

60

80

100

120

140

2018

2019

2020

f

2021

f

2022

f

2023

f

2024

f

2025

f

2026

f

2027

f

2028

f

2029

f

-40

-20

0

20

40

60

80

100

120

140

160

2018

2019

20

20

f

20

21

f

20

22

f

20

23

f

20

24

f

20

25

f

20

26

f

20

27

f

20

28

f

20

29

f

Page 7: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 7

Figure 9: Capex (A$m) – expansion capex in 2021 and 2022 Figure 10: Free cash flow (A$m) – funding challenge in 2021

Source: Company data & Shaw and Partners analysis Source: Company data & Shaw and Partners analysis

Figure 11: Pricing, costs and margin (US$/t ore processed) Figure 12: Returns (%)

Source: Company data & Shaw and Partners analysis Source: Company data & Shaw and Partners analysis

Figure 13: Net debt and gearing (A$m, %) Figure 14: Dividends and yield (A$cps, %) – no dividend policy has

been made, but we assume a payout increasing to 50%

Source: Company data & Shaw and Partners analysis Source: Company data & Shaw and Partners analysis

0

20

40

60

80

100

120

20

18

20

19

20

20

f

20

21

f

20

22

f

20

23

f

20

24

f

20

25

f

20

26

f

20

27

f

20

28

f

20

29

f

-150

-100

-50

0

50

100

150

200

20

18

20

19

20

20

f

20

21

f

20

22

f

20

23

f

20

24

f

20

25

f

20

26

f

20

27

f

20

28

f

20

29

f

0

500

1,000

1,500

2,000

2,500

3,000

2021

f

2022

f

2023

f

2024

f

2025

f

2026

f

2027

f

2028

f

2029

f

Revenue / ozExpense / ozEBITDA / oz

-200%

-150%

-100%

-50%

0%

50%

100%

2018

2019

2020

f

2021

f

2022

f

2023

f

2024

f

2025

f

2026

f

2027

f

2028

f

2029

f

RoE (%)RoA (%)

RoIC (%)

0.0%

10.0%

20.0%

30.0%

40.0%

50.0%

60.0%

-500

-400

-300

-200

-100

0

100

200

2018

2019

2020

f

2021

f

2022

f

2023

f

2024

f

2025

f

2026

f

2027

f

Net Debt (A$m)

ND/ND+E (%)

0%

5%

10%

15%

20%

25%

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.0

2018

2019

2020

f

2021

f

2022

f

2023

f

2024

f

2025

f

2026

f

2027

f

2028

f

2029

f

Special dividend

2H Dividend

1H Dividend

Yield (%)

Page 8: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 8

Geopacific is attractively placed in an attractive gold sector The current market turmoil is creating value opportunities across all sectors, and the gold

sector is no different. The US$ gold price has been surprisingly directionless during the

turmoil – initially down to the deflationary fears of the oil price shock, but now finding

support due to the inflationary implications of mass monetary and fiscal stimulus once the

COVID-19 lock downs are over.

The ASX gold index disconnected from the AUD gold price in Mar/Apr 2020 as every asset

class has sold off. The move into US$ pushed the A$ gold price up 20%, but the A$ gold

equities down 20%. As markets stabilise the gap is narrowing and we expect that to

continue.

Figure 15: ASX Gold Index v’s USD and AUD gold price – indexed to 1 Oct 201

Source: Factset

The following table summarises the key metrics for a selection of Australian listed gold

companies. In our view, Geopacific screens very attractively compared to its ASX peers.

Geopacific resources is one of the cheapest gold companies on the ASX on an EV/resource

basis, production costs are below average and the reserve mine life of 13 years is likely to

be significantly increased.

Figure 16: Selected Australian listed gold companies

Source: Company reports & presentations, Shaw and Partners analysis Shaw and Partners covers Newcrest (Buy, $27.65, PT $30), Evolution (Buy, $5.54, PT $3.70) and Northern Star (Buy, $13.13, PT $14.80).

60

70

80

90

100

110

120

130

10/01/19 11/01/19 12/01/19 01/01/20 02/01/20 03/01/20 04/01/20 05/01/20

ASX Gold Index

USD Gold

AUD Gold

Company Code Production Reserve Resource AISC Enterprise EV/oz EV/oz EV/oz Mine Life Hedging

koz Moz Moz A$/oz Value Prod Reserve Resource Reserve

Newcrest NCM 2150 51.2 105 1,397 24,680 11.5 482.0 234.2 24 658koz @A$1,875/oz

Northern Star NST 980 8.34 22.8 1,284 10,149 10.4 1216.9 445.1 9 544koz @A$2,020/oz

Evolution EVN 725 6.6 15.2 965 9,976 13.8 1511.5 656.3 9 350koz @A$1,860/oz

Saracen SAR 550 7 15 1,042 5,307 9.6 758.1 353.8 13 539koz @ A$1,997/oz

Regis RRL 355 4 8.2 1,160 2,346 6.6 586.6 286.2 11 429koz @ A$1,617/oz

Oceana OGC 370 5.6 12.2 1,100 1,952 5.3 348.6 160.0 15 119koz @ A$2,050/oz

St Barbara SBM 385 6.4 12.2 1,375 1,985 5.2 310.2 162.7 17 244koz @ A$1,900/oz

Resolute RSG 460 7.4 17.8 1,604 1,329 2.9 179.6 74.7 16 240koz @ A$2,700/oz

Gold Road GOR 265 3.7 6.6 1,150 1,338 5.0 361.7 202.8 14 112koz @ A$1,844/oz

Silver Lake SLR 235 1.07 6.05 1,325 1,552 6.6 1450.2 256.5 5 155koz @ A$1,900/oz

Perseus PRU 280 3.5 5.9 1,525 1,213 4.3 346.6 205.6 13 276koz @A$2,200/oz

Westgold WGX 300 2.65 9.4 1,200 884 2.9 333.4 94.0 9 230koz @A$2,010/oz

Ramelius RMS 215 0.84 4.1 1,275 1,034 4.8 1230.9 252.2 4 263koz @A$2,102/oz

West Africa WAF 250 1.7 3.1 847 863 3.5 507.7 278.4 7 unhedged

Red 5 RED 103 1.725 4.3 1425 460 4.5 266.7 107.0 17 81koz @A$2,095/oz

Pantoro PNR 45 0.2 2.6 1,300 133 2.9 663.2 51.0 4 unhedged

Geopacific GPR 0 1.04 1.57 1,033 24 n/a 23.0 15.3 13 unhedged

Average 451 7 15 1236 3837 6.2 622 226 12

Page 9: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 9

Figure 17: Selected Australian listed gold companies – mine life (yrs) v’s EV/resource (A$/oz)

Source: Company reports & presentations, Shaw and Partners analysis

Figure 18: Selected Australian listed gold companies – All in sustaining cost (A$/oz) v’s EV/resource (A$/oz)

Source: Company reports & presentations, Shaw and Partners analysis

Geopacific

0

5

10

15

20

25

30

0 100 200 300 400 500 600 700

Min

e L

ife

EV/resource (A$/oz)

NewcrestNorthern StarEvolutionSaracenRegisOceanaSt BarbaraResoluteGold RoadSilver LakePerseusRameliusWest AfricaRed 5PantoroGeopacificWestgold

Long mine life and good valuation

Ok mine life, but relatively expensive

Relatively cheapbut mine life issue

Geopacific

700

800

900

1,000

1,100

1,200

1,300

1,400

1,500

1,600

1,700

0 100 200 300 400 500 600 700

AIS

C (

A$

/oz)

EV/resource (A$/oz)

NewcrestNorthern StarEvolutionSaracenRegisOceanaSt BarbaraResoluteGold RoadSilver LakePerseusRameliusWest AfricaRed 5PantoroGeopacificWestgold

Relatively expensive and higher cost

Relatively expensive but low cost

Relatively cheap but high cost

Relatively cheap and low cost

Page 10: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 10

Gold price

Even before the COVID-19 epidemic, gold was performing well and had its best year in

2019 since 2010 (up 18.4% in US dollar terms). Gold prices hit record highs in most major

currencies except the US dollar and the Swiss franc.

The increase in 2019 was driven by central bank buying and flows into gold-backed

exchange traded funds (ETFs).

We expect the gold price to continue to strengthen and trade in a range of between

US$1,700-2,000/oz over the next three years before gradually moderating back to our

long term real price assumption of US$1,268/oz.

Figure 19: Gold price (nominal US$/oz) Figure 20: Gold price (real 2020 US$/oz)

Source: Factset, Shaw and Partners forecasts Source: Factset, Shaw and Partners forecasts

Figure 21: Gold price assumptions

Source: Factset, Shaw and Partners forecasts

There are seven major drivers of the US$ gold price, and most are currently strong

tailwinds;

1. Wealth protection – gold is seen as a safe haven during periods of economic

uncertainty. The current recession driven by the COVID-19 epidemic has seen

gold rally back to levels last seen in 2011/12.

2. Inflation expectations – gold is a hedge against high inflation. The gold price

generally increases during periods of negative real interest rates. As economic

activity resumes post the COVID-19 lockdowns, the combination monetary

stimulus from central banks and fiscal stimulus from government is likely to see

negative real interests persist.

3. Central bank buying – the recent trend has been for central banks to increase

their gold reserves to diversify away from paper reserves.

4. Movements in the US$ - the price of gold is usually inversely related to the value

of the US$. This was the reason the gold price initially fell at the start of the

COVID-19 epidemic. In the early stages the world shifting into US dollars, and all

other asset classes were sold off, including gold.

0

500

1000

1500

2000

2500

Mar

-90

Ma

r-9

1M

ar-

92

Mar

-93

Mar

-94

Mar

-95

Ma

r-9

6M

ar-9

7M

ar-9

8M

ar-9

9M

ar-

00

Mar

-01

Mar

-02

Mar

-03

Ma

r-0

4M

ar-0

5M

ar-0

6M

ar-0

7M

ar-

08

Mar

-09

Mar

-10

Mar

-11

Ma

r-1

2M

ar-1

3M

ar-1

4M

ar-1

5M

ar-

16

Ma

r-1

7M

ar-1

8M

ar-1

9M

ar-

20

Ma

r-2

1f

Mar

-22f

Mar

-23f

Ma

r-2

4f

Ma

r-2

5f 0

500

1000

1500

2000

2500

Mar

-90

Mar

-91

Mar

-92

Mar

-93

Mar

-94

Mar

-95

Mar

-96

Mar

-97

Mar

-98

Mar

-99

Mar

-00

Mar

-01

Mar

-02

Mar

-03

Mar

-04

Mar

-05

Mar

-06

Mar

-07

Mar

-08

Mar

-09

Mar

-10

Mar

-11

Mar

-12

Mar

-13

Mar

-14

Mar

-15

Mar

-16

Mar

-17

Mar

-18

Mar

-19

Mar

-20

Mar

-21

fM

ar-2

2f

Ma

r-2

3f

Mar

-24

fM

ar-2

5f

Gold Price forecast 2019 2020f 2021f 2022f 2023f 2024f 2025f Longterm

Gold price (US$/oz) 1,425 1,669 1,847 1,951 1,946 1,581 1,412 1,263

Gold price (A$/oz) 2,050 2,607 2,565 2,637 2,630 2,108 1,882 1,684

AUD/USD 0.70 0.64 0.72 0.74 0.74 0.75 0.75 0.75

Page 11: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 11

5. Investment demand – apart from primary demand for jewellery and industrial

purposes, the other primary demand driver for gold is exchange traded funds.

According to the World Gold Council, ETFs represent around 25% of total gold

demand. ETF’s have been strong net buyers of gold in recent years.

6. Supply constraints – supply of primary gold has been relatively stable in the past

four years with new production offsetting declining production from existing

mines. There have been relatively few new major discoveries in the past decade

and so mine supply constraint is likely to be a positive influence on the gold

price.

7. Jewellery demand – has been declining for the past few years due to the

increase in the gold price. Jewellery demand is likely to remain under pressure

due to the rising price of gold. Demand from central banks and ETFs has been

offsetting jewellery demand weakness since 2013 and that is likely to continue.

Overall, we anticipate supply and demand to reasonably balanced in the next two to three

years with the primary drivers of the gold price being the positive influences of movement

in real interest rates and the investment demand for wealth protection.

Figure 22: Global demand for gold (tonnes) Figure 23: Global gold supply (tonnes)

Source: World Gold Council Source: World Gold Council

Figure 24: Top 10 global ETFs have been adding to gold holdings in the past year

Source: World Gold Council

0

1,000

2,000

3,000

4,000

5,000

6,000

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019

Jewelry Technology Investment Central banks

0

1,000

2,000

3,000

4,000

5,000

6,000

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019

Mine production Recycled gold

Fund Country

Holdings

as of end-

Mar

Year-on-

year %

change

1 SPDR Gold Shares United States 966.7 ▲ 23

2 iShares Gold Trust United States 390.9 ▲ 30

3 Xetra-Gold Germany 209.0 ▲ 9

4 iShares Physical Gold ETC United Kingdom 195.2 ▲ 84

5 Invesco Physical Gold ETC United Kingdom 184.7 ▲ 49

6 WisdomTree Physical Gold United Kingdom 145.5 ▼ -11

7 Gold Bullion Securities Ltd United Kingdom 82.7 ▲ 5

8 ZKB Gold ETF Switzerland 72.1 ▲ 14

9 Xtrackers Physical Gold ETC EUR Germany 67.4 ▲ 15

10 Xtrackers Physical Gold Euro Hedged ETC Germany 57.8 ▲ 35

Page 12: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 12

Geopacific Resource and Woodlark Gold Project overview Geopacific Resources (GPR) is developing the Woodlark Gold Project (“Woodlark”) on

Woodlark Island in the Milne Bay Province of Papua New Guinea (PNG).

PNG is host to numerous large gold operations both on the mainland and on nearby

islands. Woodlark has a resource of 1.6Moz and a reserve of 1.04Moz which makes it

relatively small compared to larger nearby projects, but the island is lightly explored and

we expect to see significant resource upgrades over time.

Woodlark Island is flat, access is relatively straightforward via sea or air (there is an

existing airstrip), and the landowners are supportive, so Geopacific does not face the usual

problems associated with operating in PNG.

GPR released a Definitive Feasibility Study (DFS) in October 2018 which outlined a 13 year

project with an NPV @ 8% of A$197m and IRR of 29% based on an A$ gold price of

A$1,650/oz.

The DFS is now 18 months old and the gold price environment has significantly improved.

On our forecasts the project has a 2 year payback, an IRR of 52% and an NPV @10% of

A$341m. Cash flow will be front end loaded due to higher grade and lower strip ratios in

the early years of production.

GPR raised A$40m in late 2019 to fund early construction, which includes site clearing,

road works, relocation of housing and construction of a new wharf facility.

The project will require around $200m capex to first production, and we expect GPR to

raise around $140m from debt markets and a further $60m from equity markets.

Figure 25: Woodlark Gold Project location

Source: Geopacific Resources 2019 Annual Report

Page 13: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 13

Woodlark Definitive Feasibility Study (DFS)

In our analysis of the Woodlark Gold Project economics we draw heavily from the DFS

which was released in November 2018, but updated for the current gold price

environment. The key operating and financial parameters from the DFS are outlined in the

table below.

The key features of the DFS include;

A resource of 47Mt at 1.04g/t for 1.57Moz gold and reserve of 28.9Mt @ 1.12g/t

for 1.04Moz gold.

Standard and simple open cut mining and processing to produce ~100koz per

annum of gold.

Despite the low grade, costs are very low due to the low strip ratio (3.9x life of

mine, and less than 3x in the early years). All-in sustaining costs are estimated at

A$1,033/oz (life of mine) and A$866/oz in the first five years.

Payback of 2.2 years (at A$1,650/oz gold), IRR of 29% and NPV @ 8% of A$197m.

On our forecasts the project has a 2 year payback, an IRR of 52% and an NPV

@10% of A$341m.

Figure 26: Woodlark DFS – summary of key data

Source: Geopacific DFS November 2018

Page 14: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 14

Woodlark resources and exploration upside

Geopacific has a total of 580km2 of exploration licences and a 60km

2 Mining Lease on

Woodlark Island. The current reserve incorporates three deposits at Kulumadau,

Woodlark King and Busai.

Figure 27: Woodlark main deposit locations

Source: Geopacific Jan 2020ASX release

Figure 28: Woodlark Resources

Source: Geopacific 2019 Annual Report

Figure 29: Woodlark Reserves

Source: Geopacific 2019 Annual Report

Page 15: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 15

Exploration upside is expected to come from three areas;

1. The Kulumadau deposit is open at depth below the planned pit in all directions,

2. Areas near Kulumadau have been ‘quarantined’ from drilling due to the location

of the village, and

3. Additional discoveries on trend with existing deposits are possible.

Figure 30: Kulumadau resource remains open in all directions

Source: Geopacific 2019 Annual Report

Figure 31: Additional drilling target areas near Kulumadau West

Source: Geopacific Annual Report 2019

Page 16: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 16

Figure 32: Exploration targets along trend with existing deposits

Source: Geopacific Annual Report 2019

Construction activity and progress to date

Geopacific has already commenced early construction activity including site clearing, road

works, relocation of housing and construction of a new wharf facility.

There is an existing village at Kulumadau which will need to be relocated. Geopacific

reports that the vast majority of villagers are very happy to relocate into new housing. The

villagers historically moved to the village site to work in the original underground mine.

The village location is not culturally significant.

Figure 33: Existing house at Kulumadau village Figure 34 A new house under construction

Source: Geopacific Annual Report 2019 Source: Geopacific Annual Report 2019

Page 17: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 17

The new wharf facility will be on the south side of Kwaipan bay. There is an existing wharf

on the north of the bay, but the new facility will allow freight movements away from

existing facilities and habitations.

Figure 35: Infrastructure site plan

Source: Geopacific DFS Nov 2018

GPR is estimating a total capital cost of A$198.5m including a $13.8m contingency and

A$11.1m working capital build. The estimate has a degree of uncertainty of +/- 15%.

The main capital item is a A$65m processing plant. This will be a conventional Carbon in

Leach (CIL) plant and is being designed and constructed by GR Engineering in a turnkey

contract. The plant design was independently reviewed by Mintrex Pty Ltd.

Figure 36: DFS capital cost estimate

Source: Geopacific DFS Nov 2018

Page 18: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 18

Woodlark financials

As noted above, we have drawn on the DFS for financial model of Woodlark but have

updated the numbers for the current gold price environment. On our forecasts the project

has a 2 year payback, an IRR of 52% and an NPV @10% of A$341m.

The key assumptions in our model include;

Capital costs of A$195m to complete the mine and processing facilities.

First production in 2022.

Processing plant with capacity of 2,400tpa.

Grade profile as per the DFS (>1.5g/t in early years).

C1 and AISC costs as per the DFS. Mining cost of US$281/oz, processing at

US$324/oz and overheads/other at US$110/oz.

Production of ~100koz of gold per annum.

On our base case forecasts, we model Woodlark generating around ~A$180mpa of EBITDA

when at full production. This increases to ~A$200mpa of EBITDA at spot commodity

prices.

Figure 37: Woodlark P&L (A$m) – Shaw forecasts

Source: Shaw and Partners analysis

Figure 38: Woodlark P&L (A$m) – Spot commodity prices

Source: Shaw and Partners analysis

Woodlark (A$m) 2020f 2021f 2022f 2023f 2024f 2025f 2026f 2027f 2028f 2029f 2030f 2031f 2032f

Ore processed (kt) 2,000 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400

Grade of mi l l feed (g/t) 1.72 1.55 1.54 1.49 1.34 1.14 1.18 1.32 1.05 0.70 0.50

Gold produced (koz) 102 108 103 103 94 77 83 91 70 47 34

Revenue 270 283 218 195 181 152 167 187 147 101 74

Expenses 91 98 93 94 87 73 80 89 70 48 35

EBITDA 179 186 125 101 94 79 87 97 77 53 39

D&A 18 21 21 21 21 21 21 21 21 21 21

EBIT 161 164 104 79 73 58 66 76 55 32 18

Net Operating Assets 128 242 227 208 190 172 153 135 116 98 79 61 42

Capex 94 114 3 3 3 3 3 3 3 3 3 3 3

EBITDA Margin (%) 0% 0% 66% 66% 57% 52% 52% 52% 52% 52% 52% 52% 52%

EBIT / Assets (%) 0% 0% 71% 79% 55% 46% 47% 43% 56% 78% 70% 52% 42%

Gold (US$/oz) 1,669 1,847 1,951 1,946 1,581 1,412 1,444 1,476 1,509 1,543 1,578 1,614 1,650

AUD/USD 0.64 0.72 0.74 0.74 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75

Revenue (A$/oz) 2,637 2,630 2,108 1,882 1,925 1,968 2,012 2,058 2,104 2,151 2,200

Expenses (A$/oz) 890 907 899 910 928 947 966 986 1,006 1,026 1,046

EBITDA (A$/oz) 1,747 1,723 1,209 972 996 1,021 1,046 1,072 1,098 1,126 1,153

D&A (A$/oz) 174 199 204 204 224 273 255 233 303 449 629

EBIT (A$/oz) 1,572 1,524 1,005 768 772 748 791 839 795 676 524

Woodlark (A$m) 2020f 2021f 2022f 2023f 2024f 2025f 2026f 2027f 2028f 2029f 2030f 2031f 2032f

Revenue 288 310 304 311 290 244 267 298 234 162 118

Expenses 103 111 109 111 103 86 94 105 82 57 41

EBITDA 185 199 196 201 187 157 172 193 152 105 77

D&A 20 24 24 24 24 24 24 24 24 24 24

EBIT 164 175 171 176 162 133 148 169 128 80 52

Net Operating Assets 127 253 236 215 193 172 151 129 108 87 66 44 23

Capex 92 126 3 3 3 3 3 3 3 3 3 3 3

EBITDA Margin (%) 0% 0% 64% 64% 64% 64% 64% 65% 65% 65% 65% 65% 65%

EBIT / Assets (%) 0% 0% 70% 81% 89% 102% 108% 103% 137% 194% 195% 182% 228%

Gold (US$/oz) 1,750 1,789 1,830 1,871 1,913 1,956 2,000 2,045 2,091 2,138 2,186 2,235 2,286

AUD/USD 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65

Page 19: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 19

Geopacific P&L Woodlark will be Geopacific’s only producing asset, and so the Group P&L will look very

similar to the asset P&L – just additional corporate overheads and financing costs.

Once in production, the main driver of profitability will be movements in the gold price. In

figure 41 we show our forecast of NPAT to percentage movements in the gold price away

from our base case forecast. Every 10% move in prices is worth around A$8m to NPAT in

2023.

Figure 39: Geopacific Resources P&L (A$m)

Source: Company reports, Shaw and Partners analysis

Figure 40: NPAT (A$m) Figure 41: Geopacific NPAT sensitivity to gold price (A$m)

Source: Company reports, Shaw and Partners analysis Source: Company reports, Shaw and Partners analysis

Figure 42: Base case gold price assumptions

Source: Factset, Shaw and Partners forecasts

Profit & Loss (A$m) 2019 2020f 2021f 2022f 2023f 2024f 2025f 2026f 2027f 2028f 2029f 2030f 2031f

Ore processed (kt) 0 0 0 2,000 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400 2,400

Gold produced (koz) 0 0 0 102 108 103 103 94 77 83 91 70 47

Revenue 0 0 0 270 283 218 195 181 152 167 187 147 101

Operating costs 0 0 -91 -98 -93 -94 -87 -73 -80 -89 -70 -48

Admin & other expenses -7 -5 -5 -5 -5 -5 -6 -6 -6 -6 -6 -6 -6

Total costs -7 -5 -5 -96 -103 -98 -100 -93 -79 -86 -95 -76 -55

EBITDA -7 -5 -5 173 180 120 95 88 73 81 91 70 47

Depreciation & Amortisation 0 0 0 -18 -21 -21 -21 -21 -21 -21 -21 -21 -21

EBIT -7 -5 -5 156 159 98 74 67 52 60 70 49 25

Net Finance Expense 0 -2 -4 -6 -1 4 7 8 10 11 13 14 15

Profit before tax -7 -7 -9 150 158 102 80 75 62 71 83 63 41

Income tax (expense)/benefi t 0 0 0 -37 -39 -25 -20 -19 -16 -18 -21 -16 -10

Reported NPAT -7 -7 -9 112 118 76 60 57 47 53 62 48 30

-20

0

20

40

60

80

100

120

140

2018

2019

2020

f

2021

f

2022

f

2023

f

2024

f

2025

f

2026

f

2027

f

2028

f

2029

f

-50

0

50

100

150

200

2018 2019 2020f 2021f 2022f 2023f 2024f 2025f

+30%

+20%

+10%

basecase

-10%

-20%

-30%

Gold Price forecast 2019 2020f 2021f 2022f 2023f 2024f 2025f Longterm

Gold price (US$/oz) 1,425 1,669 1,847 1,951 1,946 1,581 1,412 1,263

Gold price (A$/oz) 2,050 2,607 2,565 2,637 2,630 2,108 1,882 1,684

AUD/USD 0.70 0.64 0.72 0.74 0.74 0.75 0.75 0.75

Page 20: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 20

Financing - balance sheet and cash flow Geopacific currently only has a market capitalisation of A$66m, and so taking on a

AS$200m capital project is a significant funding challenge.

GPR raised A$40m of equity capital in late 2019 to allow early construction works to

commence, and we anticipate an additional equity raise of A$60m in 3Q20 along with a

$140m debt financing package.

At peak funding, Geopacific will have a gearing level of 54% which appears manageable

given the strong free cash flow expected post start-up. Our base case forecast has the

company back in a net cash position by the end of 2023.

Figure 43: Geopacific Cash flow (A$m)

Source: Company reports, Shaw and Partners analysis

Figure 44: Geopacific Balance Sheet (A$m)

Source: Company reports, Shaw and Partners analysis

CASH FLOW (AS$m) 2019 2020f 2021f 2022f 2023f 2024f 2025f 2026f 2027f 2028f 2029f 2030f 2031f

Operating activities

Receipts from customers 0 0 0 270 283 218 195 181 152 167 187 147 101

Payments to suppl iers and employees -4 -5 -5 -96 -103 -98 -100 -93 -79 -86 -95 -76 -55

Income taxes paid 0 0 0 0 -37 -39 -25 -20 -19 -16 -18 -21 -16

Working capita l movement 0 0 -6 -28 -1 9 4 1 2 -1 -2 3 4

Net cash flow from operating activities -4 -7 -15 139 140 93 80 78 67 75 84 67 50

Investing activities

Payments for PPE -1 -94 -114 -3 -3 -3 -3 -3 -3 -3 -3 -3 -3

Net cash flow from investing activities -3 -96 -116 -5 -5 -5 -5 -5 -5 -5 -5 -5 -3

Free cash flow -6 -100 -129 136 138 90 77 75 64 73 82 65 47

Financing activities

Net proceeds from issue of shares 42 60 0 0 0 0 0 0 0 0 0 0 0

Proceeds from borrowings 0 80 60 0 0 0 0 0 0 0 0 0 0

Repayments of borrowings 0 0 0 -30 -40 -40 -30 0 0 0 0 0 0

Dividends paid 0 0 0 0 -3 -5 -7 -14 -24 -28 -28 -28 -24

Other 0 0 0 0 0 0 0 0 0 0 0 0 0

Net cash flow from financing activities 42 140 60 -30 -43 -45 -37 -14 -24 -28 -28 -28 -24

Net increase/(decrease) in cash 35 38 -71 104 92 43 38 59 38 43 52 35 23

BALANCE SHEET (A$m) 2019 2020f 2021f 2022f 2023f 2024f 2025f 2026f 2027f 2028f 2029f 2030f 2031f

Cash and cash equiva lents 38 75 4 109 201 244 282 341 379 422 474 509 532

Trade and other receivables 1 1 0 22 23 18 16 15 13 14 15 12 8

Other 1 1 1 20 20 16 14 13 11 12 14 11 8

Total current assets 40 77 5 150 245 278 313 369 403 448 503 532 548

Property, plant and equipment 2 49 106 89 69 49 30 10 -10 -30 -50 -69 -89

Exploration and evaluation expenditure 8 10 12 14 16 18 20 22 24 26 28 30 30

Total non-current assets 41 137 253 239 223 206 190 173 157 140 124 108 89

TOTAL ASSETS 81 214 258 390 467 484 502 543 560 589 627 640 637

Trade and other payables 7 7 0 12 13 13 13 12 10 11 12 10 7

Total current liabilities 7 7 0 13 14 13 13 12 10 11 12 10 7

Deferred tax 0 0 0 37 39 25 20 19 16 18 21 16 10

Borrowings 0 80 140 110 70 30 0 0 0 0 0 0 0

Total non-current liabilities 3 83 143 150 112 58 23 22 18 21 24 19 13

TOTAL LIABILITIES 10 90 143 163 126 71 36 34 29 32 36 28 20

NET ASSETS 70 124 115 227 342 413 466 509 532 557 591 611 617

Net debt -38 5 136 1 -131 -214 -282 -341 -379 -422 -474 -509 -532

Gearing (ND/ND+E %) 0% 4% 54% 1% 0% 0% 0% 0% 0% 0% 0% 0% 0%

Page 21: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 21

Valuation and Price Target Our preferred valuation technique is a discounted cash flow (DCF) valuation with post-tax

operational cash flows discounted at Geopacific’s weighted average cost of capital of 10%.

Our undiluted DCF valuation is $2.37ps and Geopacific is currently trading at a 84%

discount to this valuation.

In our base case forecast we assume that Geopacific will raise A$60m of equity at a share

price of A$0.35ps. In figure 46 we show a forward DCF valuation of Geopacific post the

dilutive equity raising. The valuation drops to A$1.37ps due to the dilution, but this is

highly dependent on the price the additional equity is issued at.

Figure 45: DCF valuation - undiluted Figure 46: DCF valuation - diluted for A$60m equity raising

Source: Company reports, Shaw and Partners analysis Source: Company reports, Shaw and Partners analysis

As noted earlier, the spot A$ gold price is substantially ahead of our forecast and in the

tables below we show the GPR valuation at spot prices on both an undiluted and fully

diluted basis. At spot prices, our GPR DCF valuation increases to A$3.94ps, or A$2.16ps on

a fully diluted basis.

Figure 47: DCF valuation – spot prices undiluted Figure 48: DCF valuation – spot prices diluted for A$60m equity

raising

Source: Company reports, Shaw and Partners analysis Source: Company reports, Shaw and Partners analysis

The main valuation sensitivity is to the gold price. In figure 45, we outline the Geopacific

DCF valuation at a range of A$ gold prices. Every A$200/oz move in the gold price impacts

our DCF valuation by A$0.25ps.

Figure 45: Geopacific DCF Valuation sensitivity to metal prices (A$ps v’s A$/oz gold price)

Source: Company reports, Shaw and Partners analysis

Geopacific Valuation A$m A$ps

Woodlark Is land 341 1.96

Net debt 38 0.21

Exploration ups ide 50 0.29

Corporate costs -15 -0.09

Total Valuation 414 2.37

Geopacific Valuation - diluted A$m A$ps

Woodlark Is land 341 0.99

Net debt 98 0.28

Exploration ups ide 50 0.14

Corporate costs -15 -0.04

Total Valuation 474 1.37

Geopacific Valuation A$m A$ps

Woodlark Is land 615 3.52

Net debt 38 0.21

Exploration ups ide 50 0.29

Corporate costs -15 -0.09

Total Valuation 687 3.94

Geopacific Valuation - diluted A$m A$ps

Woodlark Is land 615 1.78

Net debt 98 0.28

Exploration ups ide 50 0.14

Corporate costs -15 -0.04

Total Valuation 747 2.16

0.00

0.50

1.00

1.50

2.00

2.50

A$1600/oz A$1800/oz Shaw A$2000/oz A$2200/oz A$2400/oz A$2600/oz spot

Current share price

Page 22: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 22

Key risks As a small mining company with exposure to a single commodity and single asset we

consider an investment in Geopacific Resources to be high risk. The key risks include;

The gold price is volatile and driven as much by geopolitical events as fundamental supply and demand. As such, the price of gold is relatively difficult to forecast and the actual price may differ substantially from our forecasts.

The Woodlark Gold Project is not yet producing and there is a risk that Geopacific is unable to bring the operation in to production. The project may cost more than expected to build, and may not operate as expected.

Geopacific Resources is operating in PNG. PNG can be a difficult country in which to operate given the mountainous terrain, poor infrastructure and diverse landowner groups. However, Woodlark does not suffer from these issues. The island is flat, access is relatively straightforward via sea or air (there is an existing airstrip), and the landowners are supportive.

Geopacific is facing a significant financing challenge to develop the A$200m Woodlark project. There is a risk that capital markets are not willing to fund the project.

Forecasting future operating costs has considerable uncertainty. Our forecasts may prove to be too optimistic. If Geopacific Resources’s costs are higher than we expect then our cash flow forecasts will be too high.

Smaller companies carry more significant ‘key personnel’ risk than larger organisations. If senior management depart the company then it could delay projects or exacerbate operational risks.

Page 23: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 23

Appendix: Key Personnel

Board of Directors

Ian Clyne | Non-Executive Chairman

Mr Clyne has over 35 years’ experience in international banking having worked in senior

executive positions in ten countries in Asia, Oceania, Australia and Europe. He has

specialised in emerging markets and has held roles of President, Director, Managing

Director and Chief Executive Officer with universal banking operations that have extensive

branch networks and large employee bases.

Mr Clyne has successfully re-engineered banks in Indonesia, Italy, Poland and Papua New

Guinea.MrClyne held the role of Managing Director and Group CEO of Bank South Pacific

(BSP), based in Port Moresby (2008 –2013). He undertook a major transformation

program changing BSP from a typical emerging economy banking institution into an

innovative, technology driven, modern bank. Under his leadership, the bank grew from

having 400,000 accounts to over 1million in Papua New Guinea and 1.5 million across the

Pacific, including Fiji and the Solomon Islands, with a market capitalisation of $1.7 billion

at the end of his term.

Ron Heeks | Managing Director

With 30 years’ mining industry experience, Mr Heeks was a founder of Exploration and

Mining Consultants and has had previous experience with Western Mining Corporation,

Newcrest, Newmont (US) and RSG Consulting.

Mr Heeks has held senior roles in both mine management and exploration and is a former

General Manager –Technical for Straits Asia Indonesian Operations and Chief Technical

Officer for Adamus Resources Southern Ashanti Gold Operation. He has lived and worked

in various countries around the world gaining extensive experience in South-East Asia and

Indonesia in particular. Mr Heeks was appointed Managing Director of the Company on 28

March 2013 after the takeover of Worldwide Mining Projects Ltd.

Colin Gilligan | Non-Executive Director

Mr Gilligan is a mining engineer with over 25 years’ experience in the resources sector, in

Australia, South Africa, North America and Asia. He has held technical, executive and

director roles with a number of companies throughout his career including Mitsui, Thiess,

Anglo, Coalspur Mines and Resource Generation. During his career Mr Gilligan has

provided leadership to a number of operations, EPC contracts, mining contracts and

development projects across a range of commodities. He has also successfully contributed

to raising development funding in various forms.

Ian Murray | Non-Executive Director

Mr Murray is a Chartered Accountant with over 25 years’ of mining experience in senior

leadership positions, including the position of Managing Director of Gold Road Resources

Limited (Gold Road) and DRDGold Ltd. He has also held executive positions with

international Big 4 accounting firms.

Mr Murray brings a wealth of financial, corporate, project development and operational

experience to the Board. Most recently he held the role of Managing Director of Gold

Road and was instrumental in taking the Guyere Project from an exploration play through

to a fully funded 8.2mtpa gold operation that is set to produce 300koz per annum in joint

venture with Gold Fields Ltd.

Page 24: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 24

Executive Team

Ron Heeks | Managing Director

See bio above.

Matthew Smith | Chief Financial Officer / Company Secretary

Mr Smith has over 15 years’ experience in the resource industry across a broad range of

commodities including precious metals, industrials and bulk commodities. Mr Smith has

worked for a range of companies operating in the Asia Pacific region and most recently

held the role of Chief Financial Officer at ASX listed Kingsrose Mining Limited, with gold

operations in Indonesia. Mr Smith is a Chartered Accountant with relevant industry

experience on an array of financing transactions across debt and equity markets. Mr

Smith also brings specialist knowledge in the areas of international taxation, corporate

structuring, accounting and corporate governance. Mr Smith has previously held the role

of Company Secretary at Straits Resources Limited and is currently a Non-Executive

Director of Kula Gold Limited.

Glen Zamudio | General Manager Projects

Mr Zamudio has a strong record of operating and developing businesses in challenging

jurisdictions. Mr Zamudio has 5 years of process and engineering experience from

feasibility through to commissioning, 10 years of merchant banking experience initially as

a quantitative analyst and then in the investment banking division. From 2002, on arrival

in Australia he owned and managed private businesses for 4 years and then joined

Mawson West Limited for 8 years and held positions of Chief Financial Officer and

Company Secretary, Executive General Manager Operations and Group Executive

Commercial. Mr Zamudio holds a degree in Chemical Engineering, a Masters of Business

Administration, is a Chartered Financial Analyst and is a member of Australian Institute of

Company Directors (GAICD).

James Kerr | General Manager Geology - Consultant

Mr Kerr has over 25 years’ experience in the global mining industry, managing exploration

and mine development projects throughout Australia, Sub Sahara and Asia Pacific. His

experience also covers remote locations in the Melanesian Region including Vanuatu, The

Solomon Islands and various Islands across Indonesia. He brings specialist knowledge of

epithermal and porphyry gold system exploration, resource definition and project

development, as well as extensive global corporate management experience across a

broad range of commodities.

Mr Kerr’s experience exploring and developing porphyry and epithermal gold deposits in

the Asia-Pacific region in senior management roles for Barrick Gold Corporation, Hillgrove

Resources, Oropa, Tethyan Copper Company and Mincor Resources provides synergies to

Geopacific’s development plans on Woodlark Island. Mr Kerr holds degrees in Geology and

Mineral Economics and is a Member of the AusIMM, SEG and a Fellow of the Geological

Society of London.

Ashley Price | Manager, Community, Environment and Water

Mr Price has extensive international experience in the fields of water and environmental

management, particularly in the mining and oil and gas sectors. He has spent time with

both regulatory agencies and international consultancies, working on a wide variety of

projects across a range of environments in Australia, Mongolia, China, Kazakhstan, Liberia

and PNG. As a consultant, Mr Price has designed and managed numerous multi-

disciplinary studies for resource developments and related infrastructure projects such as

railways, roads and ports.

Mr Price holds a Science degree with majors in Environmental Science and Energy Studies,

a Masters degree in Hydrogeology and Water Management and an MBA.

Page 25: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 25

Rating Classification

Buy Expected to outperform the overall market

Hold Expected to perform in line with the overall market

Sell Expected to underperform the overall market

Not Rated Shaw has issued a factual note on the company but does not have a recommendation

Risk Rating

High Higher risk than the overall market – investors should be aware this stock may be speculative

Medium Risk broadly in line with the overall market

Low Lower risk than the overall market

RISK STATEMENT: Where a company is designated as ‘High’ risk, this means that the analyst has determined that the risk profile for this company is

significantly higher than for the market as a whole, and so may not suit all investors. Clients should make an assessment as to whether this stock

and its potential price volatility is compatible with their financial objectives. Clients should discuss this stock with their Shaw adviser before making

any investment decision.

Page 26: Geopacific Resources (GPR) · 2020. 11. 20. · Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 4 Geopacific Resources Key financials Profit & Loss FY19

Shaw and Partners GPR – Equity Report current as at –18/05/2020–Pg. 26

Disclaimer

Shaw and Partners Limited ABN 24 003 221 583 (“Shaw”) is a Participant of ASX Limited, Chi-X Australia Pty Limited and the holder of Australian Financial Services Licence number 236048. ANALYST CERTIFICATION: The Research Analyst who prepared this report hereby certifies that the views expressed in this document accurately reflect the analyst's personal views about the Company and its financial products. Neither Shaw nor its Research Analysts received any direct financial or non-financial benefits from the company for the production of this document. However, Shaw Research Analysts may receive assistance from the company in preparing their research which can include attending site visits and/or meetings hosted by the company. In some instances, the costs of such site visits or meetings may be met in part or in whole by the company if Shaw considers it is reasonable given the specific circumstances relating to the site visit or meeting. As at the date of this report, the Research Analyst does not hold, either directly or through a controlled entity, securities in the Company that is the subject of this report. Shaw restricts Research Analysts from trading in securities outside of the ASX/S&P100 for which they write research. Other Shaw employees may hold interests in the company. DISCLAIMER: This report is published by Shaw to its clients by way of general, as opposed to personal, advice. This means it has been prepared for multiple distribution without consideration of your investment objectives, financial situation and needs (“Personal Circumstances”). Accordingly, the advice given is not a recommendation that a particular course of action is suitable for you and the advice is therefore not to be acted on as investment advice. You must assess whether or not the advice is appropriate for your Personal Circumstances before making any investment decisions. You can either make this assessment yourself, or if you require a personal recommendation, you can seek the assistance of your Shaw client adviser. This report is provided to you on the condition that it not be copied, either in whole or in part, distributed to or disclosed to any other person. If you are not the intended recipient, you should destroy the report and advise Shaw that you have done so. This report is published by Shaw in good faith based on the facts known to it at the time of its preparation and does not purport to contain all relevant information with respect to the financial products to which it relates. The research report is current as at the date of publication until it is replaced, updated or withdrawn. Although the report is based on information obtained from sources believed to be reliable, Shaw does not make any representation or warranty that it is accurate, complete or up to date and Shaw accepts no obligation to correct or update the information or opinions in it. If you rely on this report, you do so at your own risk. Any projections are indicative estimates only and may not be realised in the future. Such projections are contingent on matters outside the control of Shaw (including but not limited to market volatility, economic conditions and company-specific fundamentals) and therefore may not be realised in the future. Past performance is not a reliable indicator of future performance. Except to the extent that liability under any law cannot be excluded, Shaw disclaims liability for all loss or damage arising as a result of any opinion, advice, recommendation, representation or information expressly or impliedly published in or in relation to this report notwithstanding any error or omission including negligence. DISCLOSURE: Shaw will charge commission in relation to client transactions in financial products and Shaw client advisers will receive a share of that commission. Shaw, its authorised representatives, its associates and their respective officers and employees may have earned previously or may in the future earn fees and commission from dealing in the Company's financial products. RESEARCH TEAM: For analyst qualifications and experience, refer to our website at http://www.shawandpartners.com.au/about/our-

people/research

RESEARCH POLICY: For an overview of our Research policy, refer to our website at https://www.shawandpartners.com.au/media/1267/

researchpolicy.pdf

If you no longer wish to receive Shaw research, please contact your Financial Adviser to unsubscribe.