general & technical condition of contract

10
Ref: 22.CTMASJID.001 Date: 17-08-2015 Name of Work: Construction of Masjid building at C-Type for Vapi GIDC Estate Muslim Society trust, Valsad. Contract Type: Labour work for building construction on Built Up area (Sft.) basis. GENERAL CONDITION OF CONTRACT The Labour contract (Excavation, Refilling, GSB, PCC, RCC, Masonry, Plaster & Water proofing) includes following work: 1. Setting out of building with substantial reference marks, bench marks etc. 2. Excavation, Levelling, GSB, PCC work below footing. Also includes lead for excavated soil 500m. 3. Refilling of excavated soil and plinth filling with murrum with watering, ramming, compacting, etc. 4. GSB & PCC work in plinth as directed by Architect. 5. Footing, Column, Ground Beam, Lintel beam, Tie beam, Stair, Slab beam, DPC, Slab, RCC Chajjah, Pardi, Coping, etc. 6. Cutting, Bending, Placing, Binding of Reinforcement for above items. 7. Masonry work as directed by Architect including box masonry (Brick work or Siporex block) for elevation. 8. Chajjah at Window sill and Lintel or wherever required as directed by Architect. 9. Arches for Window & Door. Template for Arches as per Architectural drawing shall be prepared with proper dimensions with steel plate and get approved by Architect. 10. Cornices. Template for cornice as per Architectural drawing shall be prepared with proper dimensions with steel plate and get approved by Architect. 11. Minars till terrace parapet height level. 12. Septic tank & Soak Pit. 13. Mehrab dome 14. Underground water tank (Hauz) without top slab (Clear depth 3’-6”). 15. Cement godown & Temporary office. 16. Water & Power will be supplied by owner at free of cost. One point for power & water will be given by owner. Contractor will arrange for additional points with extra pipes and cables as required for satisfactory completion of project. Mode of Measurement: 1. The slab area with projection for elevation at slab level shall only be considered. 2. The bottom slab area of water tank at 2 nd floor lintel level shall be considered separately. 3. The top slab area of septic tank will be considered for septic tank.

Upload: arifrubin

Post on 23-Jan-2016

27 views

Category:

Documents


1 download

DESCRIPTION

Technical Condition

TRANSCRIPT

Page 1: General & Technical Condition of Contract

Ref: 22.CTMASJID.001 Date: 17-08-2015

Name of Work: Construction of Masjid building at C-Type for Vapi GIDC Estate Muslim Society trust, Valsad.

Contract Type: Labour work for building construction on Built Up area (Sft.) basis.

GENERAL CONDITION OF CONTRACT

The Labour contract (Excavation, Refilling, GSB, PCC, RCC, Masonry, Plaster & Water proofing) includes following work:

1. Setting out of building with substantial reference marks, bench marks etc. 2. Excavation, Levelling, GSB, PCC work below footing. Also includes lead for excavated soil

500m. 3. Refilling of excavated soil and plinth filling with murrum with watering, ramming,

compacting, etc. 4. GSB & PCC work in plinth as directed by Architect. 5. Footing, Column, Ground Beam, Lintel beam, Tie beam, Stair, Slab beam, DPC, Slab, RCC

Chajjah, Pardi, Coping, etc. 6. Cutting, Bending, Placing, Binding of Reinforcement for above items. 7. Masonry work as directed by Architect including box masonry (Brick work or Siporex block)

for elevation. 8. Chajjah at Window sill and Lintel or wherever required as directed by Architect. 9. Arches for Window & Door. Template for Arches as per Architectural drawing shall be

prepared with proper dimensions with steel plate and get approved by Architect. 10. Cornices. Template for cornice as per Architectural drawing shall be prepared with proper

dimensions with steel plate and get approved by Architect. 11. Minars till terrace parapet height level. 12. Septic tank & Soak Pit. 13. Mehrab dome 14. Underground water tank (Hauz) without top slab (Clear depth 3’-6”). 15. Cement godown & Temporary office. 16. Water & Power will be supplied by owner at free of cost. One point for power & water will

be given by owner. Contractor will arrange for additional points with extra pipes and cables as required for satisfactory completion of project.

Mode of Measurement:

1. The slab area with projection for elevation at slab level shall only be considered. 2. The bottom slab area of water tank at 2nd floor lintel level shall be considered separately. 3. The top slab area of septic tank will be considered for septic tank.

Page 2: General & Technical Condition of Contract

Multibuild Consultants, Vapi

Page 2 of 3

Time for Completion of Project:

1. Up to Plinth - 45 Days 2. 1st Slab - 30 Days 3. 2nd Slab - 30 Days 4. 3rd Slab - 30 Days (including water tank base slab & Pardi)

Retention money of 5% shall be deducted from each certified bill which shall be released after one monsoon.

Mode of Payment:

1. Plinth - 12% 2. RCC @ Ground Floor - 9% 3. RCC @ 1st Floor - 10% 4. RCC @ 2nd Floor - 10% 5. RCC @ Terrace Floor - 3% 6. Brick Work @ Ground floor - 6% 7. Brick Work @ 1st floor - 5% 8. Brick Work @ 2nd floor - 5% 9. Brick Work @ Terrace Floor - 4% 10. External Plaster @ Ground floor - 5% 11. External Plaster @ 1st floor - 4% 12. External Plaster @ 2nd floor - 4% 13. External Plaster @ Terrace floor - 3% 14. Internal Plaster @ Ground floor - 5% 15. Internal Plaster @ 1st floor - 4% 16. Internal Plaster @ 2nd floor - 4% 17. Internal Plaster @ Terrace floor - 3% 18. Water Proofing in Sunken slab & Terrace - 4%

Total - 100%

All bills shall be certified by Architect. After submission of bill, 10 days of duration shall be considered for final payment.

Equipment:

Minimum 1 Bag Concrete mixer, Needle Vibrator, Elevator/Lift, Concrete cube mould, Volume batch pharma, etc.

Addition/Deletion of Work:

All Addition/Deletion of work, if any shall be expressly approved in writing by the owner. However, work shall not be interrupted or slowed down or stopped under any circumstances for want of settlement of claims/adjustment in rates, etc.

Page 3: General & Technical Condition of Contract

Multibuild Consultants, Vapi

Page 3 of 3

Progress of Work:

In case, if the contractor is unable to progress to the satisfaction of the owner with adequate plant and machinery, tools, labour, skilled or semi-skilled personnel, the owner shall be free to replenish the same at the cost of contractor.

Insurances:

The contractor will have to obtain full risk insurance for their manpower, workman compensation policy and equipment/machineries deployed at site under the all applicable law. All the contractor’s workmen shall be covered under the Employee state insurance or Janta Policy or any other scheme which may be specified by the statutory authorities from time to time. The Copy of insurances paid is to be submitted to the owner / Architect. The insurances shall be valid till successful completion of work. This will be the prime requirement and should be strictly adhering to in case of any injury, loss, theft or accident. The contractor shall report within two days of occurrence of such event and lodge FIR with police department.

Safety:

All precautions necessary, not only for the safe working of the contractor’s workmen at site, but also take all precautions to safeguard existing structures, equipments and workmen of other agencies in and around the job site shall be taken by contractor.

For carrying out of works at heights exceeding 4’-0” or over and near openings in floors, roofs, etc following precautions shall be taken:

i. All workers engaged on overhead work shall be experienced men in such work. ii. Whenever required timber staging or platforms shall be erected with planks of minimum

thickness of 2” and minimum width of 12”. When the nature of work demands staging greater width than one plank additional plank shall be added and lashed securely together.

iii. Staging shall be provided with simple safety rails or ropes throughout its length, at waist height and on each open side.

iv. Staging supports shall be of standard timber or steel scaffolding, safely secured and supported on firm level or slung from overhead beams. The support shall be situated at a maximum distance of 8’-0” apart and the staging shall be secured to each support.

v. In case the site or the nature of work is unsuitable for erection of a proper staging, all workers shall wear safety belt around their waist and secure their lifelines to strong, rigid scaffolding or structural member.

vi. Whenever it is not possible to put up staging and/or use safety belts, safety nets or sheets shall be beneath the place of work.

vii. Safe access to all points of work should be provided in the form of suitable ladders, stairways, etc.

Signature of Contractor Signature of Architect Signature of Owner

Page 4: General & Technical Condition of Contract

Ref No. 22.CTMASJID.002 Date: 17-08-2015

TECHNICAL CONDITION FOR GENERAL BUILDING WORK

A. EXCAVATION

1. Excavation shall include removal of all materials of whatever nature at all depths and whether wet or dry necessary for the construction of foundation and sub-structure. The excavation depth shall be up to yellow good soil. (Excavation depth to consider shall be greater of 10’0” or up to good yellow soil approved by Architect from E.G.L.)

2. The sides of the excavations should be timbered and supported in such a way as is necessary to secure these from falling in, and the shoring shall be maintained in position as long as necessary.

3. Contract includes pumping out water which may accumulate in the excavation during the progress of work either from seepage, springs, rain or any other cause and diverting surface flow if any by bunds or other means.

4. Setting out - The contractor shall set out the building or other involved works after clearing the site and get the same approved by Owner/Architects. It shall be the responsibility of the Contractor to install substantial reference marks; bench marks etc. and maintain them as long as required by the Owner/Architects. The contractor shall assume full responsibility for proper setting out, alignment, elevation and dimension of each and all parts of the work.

B. BACKFILLING AROUND FOUNDATION & PLINTH

5. Filling in pits and trenches around foundation of structure – As soon as the work in foundations has been accepted and measured, the spaces around the foundations, structures, pits, trenches etc., shall be cleared of all debris, and filled with earth in layers not exceeding 45 cm. each layer being watered, rammed and properly consolidated, before the succeeding one is laid. Each layer shall be consolidated to the satisfaction of Engineer. Earth shall be rammed with approved mechanical compaction machines. Usually no manual compaction shall be allowed unless Engineer is satisfied than in some cases manual compaction by tampers cannot be avoided. The final backfill surface shall be trimmed and levelled to proper profile as directed by Architect or indicated on the drawings.

6. Filling in Plinth – Plinth filling shall be carried out in layers not exceeding 20 cm, watered and compacted with mechanical compaction machines. When filling reaches the finished level, the surface shall be flooded with water, for at least 24 hours, allowed to dry and then the surface again compacted as specified above to avoid settlements at a later stage. The finished level of the filling shall be trimmed to the level/slope specified in drawing. Rolling shall commence from the outer edge and progress towards the centre and continue until compaction is to the satisfaction of Engineer, but in no case less than 10 passes of the roller will be accepted for each layer.

C. GRANULATED SUB BASE (GSB) WORK

7. GSB/Rubble Soling shall be laid under footing and Plinth and other areas where shown in the drawings.

8. A layer of GSB / Rubble soling shall be spread and consolidated on the sub-grade surface (compacted earth) prepared. The GSB/Rubble Soling layer shall be thoroughly consolidated

Page 5: General & Technical Condition of Contract

Multibuild Consultants, Vapi

Page 2 of 7

with mechanical rollers of 8 to 10 tonne weight starting at the edges and working towards the centre. For areas where mechanical roller access is difficult or restricted heavy hand rammers and hand rollers may be used if approval for this has been obtained from the Architect / Owner. The voids shall be filled with quarry dust powder or other material provided by owner.

D. CONCRETING (CASTING, PLACING, VIBRATING & MATERIAL HANDALING/TESTING)

9. PCC of grade specified in drawing shall be laid below footing & at plinth. 10. The aggregate shall be batched by volume; the form as used shall be of the correct sizes to

be certified by the Owner/Architects before use. Heaping of aggregates on the form is prohibited and aggregates shall be filled level in form and struck off with a horizontal timber or steel rule.

11. Water shall be measured either by volume in calibrated tanks/vessels. 12. Concrete shall be mixed in Mechanical Mixer. Minimum 1 bags mixer is compulsory. 13. Minimum 6 cubes shall be casted for each grade at the time of concreting. 14. Concrete shall be thoroughly compacted during operation of placing by the use of

Mechanical Vibrators. Sufficient number of vibrators (including stand by) of adequate capacities shall be used for compaction of concrete. Vibration shall be carried out by trained men and in the presence of a qualified supervisor trained in the use of vibrators and vibrated concrete. In certain portions where vibration is not effective, careful rodding and taping shall be carried out and sufficient men employed to ensure that thorough consolidation takes place.

15. Cement at site shall be stored in dry weather proof godown (or shed). 16. Concreting shall be commenced only after the Owner / Consultant has inspected and passed

the sub-base / base or the centering, shuttering and reinforcement. 17. Concrete shall not be dropped into position from a height greater than 1.0 metre unless

directed otherwise by Owner/Architect. 18. All debris saw dust etc. shall be removed from the shuttering before any concrete is placed.

Care shall be taken to see that the shuttering is water-tight and has been properly treated with approved composition to prevent absorption of water.

19. All concrete work shall be water cured for a minimum period of 14 days after concreting or as directed by Owner/Architects. Horizontal surfaces shall be kept covered with water ponded by means of bunds and vertical surfaces like those of columns, RCC Wall etc. by gunny bags kept constantly wet with water sprays. Mere sprinkling of water on vertical surface without sacks will not be allowed.

20. It is essential that the contractor's supervisor who is in charge of the construction of all concrete work whether reinforced or not, shall be skilled in this class of work and shall superintend personally the whole construction and pay special attention to :- a) the quality, testing, proportioning and mixing of the materials and particularly control of water cement ratio. b) Laying of materials in place and thorough consolidation of the concrete to ensure solidity and freedom from voids. c) Position of reinforcements.

21. A minimum of one set of 6 cubes shall be taken for every 20 cum or part thereof in case of beam, slabs & connected columns, one set for 5 cum or part thereof of concrete poured for columns and the cubes shall be cured as per IS Code of Practice. The cubes shall be initialled, numbered, dated jointly by the contractor's representatives and the Site Engineer of Owner/Architects' representative with a piece of wire or nail so that an indentation of the initials is left on the cubes. The contractor shall arrange to transport the cubes to the approved laboratory and arrange to have the test results forwarded (in duplicate) directly

Page 6: General & Technical Condition of Contract

Multibuild Consultants, Vapi

Page 3 of 7

from the laboratory to the Owner/Architects. The contractor shall bear all expenses in connection with the preparation of test cubes, i.e. provision of moulds, labour and transportation charges to the approved laboratory, laboratory testing charges etc.

E. FORMWORK

22. The form work shall be of approved dressed timber of not less than 3.5 cms thick except where otherwise stated. As an alternative sufficiently rigid steel/ply board shuttering of approved design may be used. Joints of the shuttering must not allow loss of liquid from concrete. In timber shuttering the joints shall therefore be either tongued or grooved or the joints must be perfectly closed and lined with craft paper or other types of approved materials. All shuttering and framing must be adequately stayed and braced to the satisfaction of the Owner/Architects for properly supporting the concrete during the period of hardening. The forms shall have sufficient strength and rigidity to hold concrete and withstand the pressure of ramming and vibration without deflection from the prescribed lines and levels. The vertical shuttering shall be carried down to such solid surface as is sufficiently strong to afford adequate support and shall remain in position until the newly constructed work is able to support itself. Props shall be securely braced against lateral deflection. Steel props of approved quality shall be used. In case timber props and bullies are allowed to use these shall be of minimum 10 cm diameter and shall be straight and adequately strong. Bamboo props shall not be used.

23. The Contractor shall ensure that the forms are checked for water tightness just before concreting operation starts and shall make good any deficiencies. If instructed by the Owner/Architects building paper or any other approved materials will have to be used without any extra charge for the same.

24. Form shall be left in place until their removal is authorised by the Owner/Architects and shall then be removed with care so as to avoid injury to concrete. In normal circumstances the stripping time of formwork shall be as directed by Architect.

25. Non-staining form release oil (white oil) shall be applied to the faces of forms against which concrete is to be placed. The form release oil shall be applied before placing reinforcement.

F. POOR WORKMANSHIP, DISMANTALING, RECTIFICATION

26. If in the Owner's/Architects' opinion there is doubt as to the strength of the structure due to the works test cube failing to attain specified strength due to poor workmanship like honeycombing etc. or any reason accounting to negligence on the part of the contractor then the Owner's/Architect's decision regarding dismantling, of such concrete or rectification if concrete is allowed to be retained in its place shall be final and binding on the contractor. Where honeycombed surface are noticed in the concrete, the contractor shall not patch up the same until examined by the Owner/Architects and decision given regarding the acceptance with rectification or rejection of the same. If the contractor patches up such defects without the knowledge of the Owner/Architects the Owner/Architects will be at liberty to order demolition of the concerned concrete members to the extent they consider necessary. In such case, the contractor at his expense, shall demolish and reconstruct defective work. The demolished work shall not be measured and paid for.

Page 7: General & Technical Condition of Contract

Multibuild Consultants, Vapi

Page 4 of 7

G. REINFORCEMENT

27. Before steel reinforcement is placed in position, the surface of the reinforcement shall be cleaned of rust, dust, grease and any other objectionable substances. On receipt of structural drawing, Contractor shall prepare bar bending schedule of reinforcement and shall obtain approval of the Owner/Architects. Before steel reinforcement bars are cut, the contractor shall study the lengths of bars required as per drawing and shall carry out cutting only to suit the sizes required as per drawing.

28. Reinforcement bars shall be accurately placed and secured in position and firmly supported by precast concrete blocks of suitable thickness at sufficiently close intervals so that they will not sag between the supports or get displaced during the placing of concrete or any other operation of the work.

29. Bends, cranks, etc. in steel reinforcement shall be carefully formed as directed by Architect’s drawing. Heating of reinforcement of bars to facilitate bending will not be permitted. The bars shall always be bent cold.

30. No concreting shall commence until the Owner/Architects have inspected the reinforcement in position and until their approval have been obtained. A notice of at least 72 hours shall be given to the Owner/ Architects by the contractor for inspection of reinforcement. If in the opinion of the Owner/Architects any materials are not in accordance with the specification or the reinforcement is incorrectly spaced, bent or otherwise defective, the contractor shall immediately remove such materials from the site and replace with new and rectify any other defects in accordance with the instruction of the Owner/Architects and to their entire satisfaction.

H. BRICK MASONARY WORK

31. For Brick Masonry work, Unless otherwise specified, mortar for brick work shall be composed of 1 part of cement to 6 parts of approved sand for walls of one brick thick (25 cm) and over and 1 part of cement to 4 parts of approved sand for half brick thick and brick on edge walls.

32. All brick shall be immersed in water for 24 hours before being put into work so that they will be saturated and will not absorb water from the mortar.

33. The bricks shall be laid in mortar to line, level and shapes shown on the plan, slightly pressed and thoroughly bedded in mortar and all joints shall be properly flushed and packed with mortar so that they will be completely filled with mortar and no hollows left anywhere. The verticality of the walls and horizontality of the courses shall be checked very often with plumb bob and spirit level respectively.

34. Joints shall not exceed 10 mm (about 3/8") in thickness and this thickness shall be uniform throughout. The joints shall be raked out not less than 10mm (about 3/l8") deep when the mortar is green where pointing is to be done. When the brick surface are to be plastered, the joints shall be raked to a depth of 5 mm when the mortar is green, so as to provide good key to plaster.

35. All brick works shall be kept well watered for l4 days after laying. While pozzalana cement is used for mortar the curing shall be extended by one week at contractor’s expense.

I. HOLD FAST FOR DOOR FRAMES

36. For Door frame, three holdfasts shall be fixed to each post of the door frame. The M.S. holdfasts shall be of the size as directed by Architect shall be fixed to the fames by means of

Page 8: General & Technical Condition of Contract

Multibuild Consultants, Vapi

Page 5 of 7

screws and not nails. The other end of the holdfasts shall be fixed into jambs with 1:2:4 P.C.C. of dimensions as directed. Ends of holdfasts will be fish tailed.

J. PLASTER (EXTERNAL & INTERNAL)

37. The cement plaster shall be 12 mm, 15 mm or 20 mm thick as specified in the item. For all exposed brick work or tile work double scaffolding independent of the work having two sets of vertical supports shall be provided. The supports shall be sound and strong, tied together with horizontal pieces over which scaffolding planks shall be fixed. For all other work in buildings, single scaffolding shall be permitted. In such cases the inner end of the horizontal scaffolding pole shall rest in a hole provided only in the header course for the purpose. Only one header for each pole shall be left out.

38. The walls to be plastered to have all joints raked out to a depth of 10 mm, if not already done. R.C.C surface shall be properly hacked to get good key to the plaster. All dust and oily matter, if any, shall be brushed and cleaned and surface to be plastered shall be kept wet for 6 hours before plastering is commenced.

39. Ceiling plaster shall be completed before commencement of wall plaster. Plastering shall be started from the top and worked down towards the floor. All putlog holes shall be properly filled in advance of the plastering as the scaffolding is being taken down. To ensure even thickness and a true surface, plaster about 15 × 15 cm shall be first applied, horizontally and vertically, at not more than 2 metres intervals over the entire surface to serve as gauges. The surfaces of these gauged areas shall be truly in the plane of the finished plaster surface. The mortar shall then be laid on the wall, between the gauges with trowel. The mortar shall be applied in a uniform surface slightly more than the specified thickness. This shall be brought to a true surface, by working a wooden straight edge reaching across the gauges, with small upward and sideways movements at a time. Finally the surface shall be finished off true with trowel or wooden float according as a smooth or a sandy granular texture is required. All corners, arises, angles and junctions shall be truly vertical or horizontal as the case may be and shall be carefully finished. Rounding or chamfering corners, arises, provision of grooves at junctions etc. where required shall be done without any extra payment. Such rounding, chamfering or grooving shall be carried out with proper templates or battens to the sizes required.

40. When suspending work at the end of the day, the plaster shall be left, cut clean to line both horizontally and vertically. When recommencing the plastering, the edge of the old work shall be scrapped cleaned and wetted with cement slurry before plaster is applied to the adjacent areas, to enable the two to properly join together. Plastering work shall be closed at the end of the day on the body of wall and not nearer than 15 cm to any corners or arises. It shall not be closed on the body of the features such as plasters, bands and cornices, nor at the corners of arises. Horizontal joints in plaster work shall not also occur on parapet tops and copings as these invariably lead to leakages. The plastering and finishing shall be completed within half an hour of adding water to the dry mortar.

41. Curing shall be started as soon as the plaster has hardened sufficiently not to be damaged when watered. The plaster shall be kept wet for a period of at least 7 days. During this period, it shall be suitably protected from all damages at the contractor’s expense by such means as the Engineer-in-Charge may approve. The dates on which the plastering is done shall be legibly marked on the various sections plastered so that curing for the specified period thereafter can be watched.

42. The plaster shall be finished to a true and plumb surface and to the proper degree of smoothness as required. The work shall be tested frequently as the work proceeds with a true straight edge not less than 2.5 m long and with plumb bobs. All horizontal lines and

Page 9: General & Technical Condition of Contract

Multibuild Consultants, Vapi

Page 6 of 7

surfaces shall be tested with a level and all jambs and corners with a plumb bob as the work proceeds.

43. Any cracks which appear in the surface and all portions which sound hollow when tapped, or are found to be soft or otherwise defective, shall be cut out in rectangular shape and redone as directed by the Engineer-in-Charge.

44. External plaster of 20mm thick shall in two coats. Generally coarse sand shall be used for the under coat and fine sand for the finishing coat. The plaster shall be applied in two coats i.e. 12 mm under coat and then 8 mm finishing coat and shall have an average total thickness of not less than 20 mm. The finishing coat shall be applied after the under coat has sufficiently set but not dried and in any case within 48 hours.

K. WATER PROFFING OVER ROOF & SUNKEN SLAB

45. Before taking up the water proofing work the construction of parapet walls, including finishing should be completed. Similarly, the ancillary items like fixing up of all down take pipes, water pipes and electric conduits etc. should be completed and no such work should be allowed on the area to be treated during the progress of water proofing treatment or even later.

46. The surface of the slab should be roughened by scrapping when the slab concrete is still green, however, the surface need not be hacked. In case the slab is already cast and surface fairly finished, the same shall be cleaned neatly of all mortar droppings, loose materials etc. with brooms/cloth.

47. Providing and Laying of Slurry under Base Coat - The quantity of water required to prepare the slurry with 2.75 kg. of blended cement + water proofing compound as per manufacturer specification to be painted over an area of 1 sq m. Depending upon the area of surface that has to be covered, the required quantity of slurry should be prepared using 2.75 kg. blended cement + water per sq. m. area to be covered, taking particular care to see that only that much quantity of slurry shall be prepared which can be used within half an hour of preparation i.e. before the initial setting time of cement. The prepared slurry shall be applied over the dampened surface with brushes very carefully, including the joints between the floor slab and the parapet wall, holes on the surfaces, joints of pipes, masonry/concrete etc. The application of the slurry should continue up to a height of 300 mm on the parapet wall. Slurry should also be applied up to a height of 150 mm over pipe projections etc.

48. Laying Base Coat 20 mm thick - Immediately after the application of slurry and when the application is still green, 20 mm thick cement plaster as base coat with cement mortar 1:5 (1 blended cement: 5 coarse sand) shall be evenly applied over the concrete surface taking particular care to see that all the corners and joints are properly packed and the application of the base coat shall be continued up to a height of 300 mm over the parapet wall.

49. Laying Brick Bat Coba - Brick bat of size 25 mm to 115 mm out of well burnt bricks shall be used for the purpose of brick bat coba. The brick bats shall be properly dampened for six hours before laying. Brick bats shall be laid to required slope/gradient over the base coat of mortar leaving 15-25 mm gap between two bats. Cement mortar 1:5 (1 blended cement: 5 coarse sand) shall be poured over the brick bats and joints filled properly. Under no circumstances dry brick bats should be laid over the base coat. The haunches/vata at the junction of parapet wall and the roof shall be formed only with brick bat coba. In case the brick bat coba is laid on the base coat immediately on initial set there will be no necessity of applying cement slurry over the base coat before laying the brick bat coba. However, if the brick bat coba is to be laid on the subsequent day, cement slurry prepared as described above shall be applied over the top surface of the base coat, and then only the brick bat coba shall be laid.

50. After two days of curing of brick bat coba cement slurry prepared as applied in 1st layer shall be applied on the surface of brick bat coba The application of slurry shall be the same as

Page 10: General & Technical Condition of Contract

Multibuild Consultants, Vapi

Page 7 of 7

described above which should cover the haunches/vata, and the remaining small portion of parapet wall and also inside the groove of parapet wall. Immediately on applying the cement slurry over the surface of the brick bat coba and when the slurry applied is still green, the fibre glass cloth shall be spread evenly on the surface without any kink & pressed to see that no air spaces exist. 20 mm thick layer of cement plaster, without leaving any joints shall be applied with cement mortar 1:4 (1 blended cement: 4 coarse sand) over the entire fibre glass cloth including the haunches/vata and the small portion on the parapet wall. The surface of the finishing layer (protective coat) shall be neatly finished with cement slurry prepared as mentioned above. The finished surface shall be allowed to dry.

51. The entire surface thus treated shall be flooded with water by making kiaries with weak cement mortar, for a minimum period of two weeks.

52. The average thickness of brick bat coba shall not be more than 100 mm. 53. Water Proofing in sunken Slab - The water proofing procedure mentioned in water proofing

of terrace shall be applied for sunken slab. The remaining sunk depth shall be filled with chharu or equivalent light weight material which shall be confirmed by Architect.

L. Standard Specification:

54. Unless otherwise specified elsewhere in this contract, all work under this contract shall be carried out in accordance with the technical specification and the latest issue of the Indian Standard Specification applicable to the particular class of work. In case of any confusion or dispute regarding the meaning and interpretation of any specification for the respective works, the decision of the Owner/Architects shall be final and binding on the contractor.

Signature of Contractor Signature of Architect Signature of Owner