Variable Frequency Drives Inspection and Test Plan for Installation
TABLE OF CONTENTS
1. SCOPE OF WORK ..................................................................................................... 2 2. PURPOSE ................................................................................................................... 2 3. REFERENCE DOCUMENTS .................................................................................... 4
3.1. EMPLOYERS REQUIREMENTS: ..................................................................... 4
3.2. INTERNATIONAL CODES AND STANDARDS ............................................. 4
3.3. STANDARDS COMPLIANCE (IEEE/ANSI) .................................................... 5
3.4. GUPC DOCUMENTATION ............................................................................... 5
3.5. SUBCONTRACTOR'S DOCUMENTATION .................................................... 6
3.6. DRAWINGS ......................................................................................................... 6
4. RESOURCES ......................................... ERROR! BOOKMARK NOT DEFINED. 4.1. PLANT & EQUIPMENT ..................................................................................... 6
4.2. PERSONNEL ....................................................................................................... 8
5. MATERIALS .............................................................................................................. 8 6. QUALITY FORMS AND INSPECTION PROGRAMS ............................................ 8 7. INSPECTION AND TEST PLAN .............................................................................. 9
7.1. GENERAL NOTES AND PRE-REQUITSITES ................................................. 9
7.2. INSPECTIONS ..................................................................................................... 9
8. HEALTH AND SAFETY ......................................................................................... 10 9. ENVIRONMENT ...................................................................................................... 11 APPENDIX 1 ................................................................................................................... 12 APPENDIX 2 ................................................................................................................... 12 APPENDIX 3 ................................................................................................................... 17
Doc. No.: G91/ETNWPR0007_UA
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
Date: 16/12/14
Page: 2 of 21
1. SCOPE OF WORK
This document has been generated by Eaton Electrical Services and Systems (EESS) as
the Inspection and Test Plan for the installation of the EATON Variable Frequency
Drives (VFD’s) for:
The Panama Canal Third Set Of Locks Project
Other manufacturers of similar type are covered by this Guideline as well. The following
Guideline provides EATON Electrical Services & Systems “Accepted Standards” for
installations.
These guidelines cover the minimum details, variations, or combinations of the
equipment, its installation, checkout, and safe operation. Care must be exercised to
comply with local, state, and national regulations, as well as safety practices for this class
of equipment. Consult specific instruction manuals and drawings for detailed installation
and operating procedures. Variable Frequency Drives should be installed, operated, and
maintained by qualified personnel as defined by OSHA 29CFR1910 subpart 5 and ACP.
2. PURPOSE
This document is to ensure product quality and provide product data gathered during the
installation phases. This document is to ensure that the VFD’s and dynamic brakes are
handled and installed as per EATON 9000X AF Drives User Manual and Post Glover
installation instructions as a guideline. This procedure applies to the following
equipment:
Ref. Designation Description
A01 RG1-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 1 Main Winch A.
A02 RG1-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 1 Main Winch B.
A03 RG1-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 1 Emergency Winch.
A04 RG2-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 2 Main Winch A.
A05 RG2-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 2 Main Winch B.
A06 RG2-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 2 Emergency Winch.
A07 RG3-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 3 Main Winch A.
A08 RG3-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 3 Main Winch B.
A09 RG3-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 3 Emergency Winch.
A10 RG4-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 4 Main Winch A.
Doc. No.: G91/ETNWPR0007_UA
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
Date: 16/12/14
Page: 3 of 21
A11 RG4-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 4 Main Winch B.
A12 RG4-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 4 Emergency Winch.
A13 RG5-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 5 Main Winch A.
A14 RG5-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 5 Main Winch B.
A15 RG5-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 5 Emergency Winch.
A16 RG6-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 6 Main Winch A.
A17 RG6-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 6 Main Winch B.
A18 RG6-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 6 Emergency Winch.
A19 RG7-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 7 Main Winch A.
A20 RG7-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 7 Main Winch B.
A21 RG7-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 7 Emergency Winch.
A22 RG8-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 8 Main Winch A.
A23 RG8-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 8 Main Winch B.
A24 RG8-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 8 Emergency Winch.
P01 RG1-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 1 Main Winch A.
P02 RG1-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 1 Main Winch B.
P03 RG1-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 1 Emergency Winch.
P04 RG2-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 2 Main Winch A.
P05 RG2-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 2 Main Winch B.
P06 RG2-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 2 Emergency Winch.
P07 RG3-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 3 Main Winch A.
P08 RG3-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 3 Main Winch B.
P09 RG3-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 3 Emergency Winch.
P10 RG4-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 4 Main Winch A.
P11 RG4-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 4 Main Winch B.
P12 RG4-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 4 Emergency Winch.
P13 RG5-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate
Doc. No.: G91/ETNWPR0007_UA
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
Date: 16/12/14
Page: 4 of 21
the Rolling Gate 5 Main Winch A.
P14 RG5-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 5 Main Winch B.
P15 RG5-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 5 Emergency Winch.
P16 RG6-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 6 Main Winch A.
P17 RG6-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 6 Main Winch B.
P18 RG6-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 6 Emergency Winch.
P19 RG7-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 7 Main Winch A.
P20 RG7-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 7 Main Winch B.
P21 RG7-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 7 Emergency Winch.
P22 RG8-M1 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 8 Main Winch A.
P23 RG8-M2 Drive to be rated at 185 kW (325 kW ED10) and installed in locations suitable to operate the Rolling Gate 8 Main Winch B.
P24 RG8-M3 Drive to be rated at 55 kW and installed in locations suitable to operate the Rolling Gate 8 Emergency Winch.
3. REFERENCE DOCUMENTS
3.1. EMPLOYERS REQUIREMENTS:
The following Sections are applicable:
• SECTION 01 33 00 - Submittal Procedures
• SECTION 01 40 00 - Quality Requirements
• SECTION 09 96 00 - Corrosion Control Coatings
• SECTION 01 32 00 - Project Communications and Document
Management
• SECTION 01 31 00 - Project Management and Coordination
• SECTION 26 29 23 – Variable Frequency Drive
3.2. INTERNATIONAL CODES AND STANDARDS
• American Institute of Steel Construction (AISC)
• American National Standard Institute (ANSI)
• American Society of Mechanical Engineers (ASME)
• American Society for Non-destructive Testing (ASNT)
• American Welding Society (AWS)
• National Association of Corrosion Engineers (NACE)
• Society for Protective Coatings (SSPC)
• Occupational Safety and Health Administration (OSHA)
• International Organization for Standardization (ISO)
Doc. No.: G91/ETNWPR0007_UA
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
Date: 16/12/14
Page: 5 of 21
3.3. STANDARDS COMPLIANCE (IEEE/ANSI)
• ISO 9001 – Quality Management Systems: Requirements
• NFPA 70: National Electrical Code
• NFPA 70E – Standard for Electrical Safety in the Workplace
• ANSI 958 –03 Guide for the Application of AC Adjustable-speed
Drives on 2,400 and 13,800V Auxiliary Systems in Electric
Power Generating Stations
• ANSI C57.110 – 04 Recommended Practice for Establishing Transformer
Capability when Supplying Non-sinusoidal Load
Currents
• ANSI C57.16 – 01 Standard requirements, Terminology, and Test Code
for Dry-Type Air-Core Series-Connected Reactors
• ANSI 18 – 02 Standard for Shunt Power Capacitors
• ANSI P1036 – 06 Guide for Application of Shunt Power Capacitors • IEEE 519 – 04 Recommended Practice and Requirements for Harmonic Control
in Electrical Systems
• NEMA ICS 61800-4 - 04 Adjustable Speed Electrical Power Drive Systems Part
4: General Requirements Rating Specifications for AC
Power Drive Systems Above 1,000VAC and not
exceeding 35kV
• NEMA ICS 6 – 06 Industrial Control and Systems Enclosures
• NEMA ICS 7 – 06 Industrial Control and Systems: Adjustable-Speed Drives
• NEMA 250 – 03 Enclosures for Electrical Equipment (1000 volts maximum)
• NEMA 1283 – 2005 UL Standard for Safety for Electromagnetic Interference
Filters
3.4. GUPC DOCUMENTATION
• G00/CICTSP-E0003 General Electrical Requirements
• G00/UPCMGP-0002 Coding of Documents
• G00/UPCMGP0005 Definition & Application of Quality Levels
• G00/UPCMGP0016 Material Receiving Inspection, Handling and Storage
• G00/UPCMGP0017 - Control Nonconformance
• G00/UPCMGP0019-UB Corrective and Preventive Actions
• G00/UPCQMM0001 Quality Management Manual
• G00/UPCWPR0015 Shipping of Electromechanical Permanent Plant
Material and Equipment
• G80/CICDSR-E0001 PD Integration Management Plan
• G80/CICTSP-E0224 Electrical Systems Integration
• G91/CICTSP-E0008 Section 26 29 23 Variable Frequency Drives
Technical Specifications
• G00/UPCHSI0008 Lock Out/ Tagout “LOTO”
• P00-UPCSCP0001 Pacific Security Plan
Doc. No.: G91/ETNWPR0007_UA
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
Date: 16/12/14
Page: 6 of 21
3.5. SUBCONTRACTOR'S DOCUMENTATION
• G91/ETNITP0001 Inspection & Test Plan
• G91/ETNMQP0001 Manufacturing Quality Plan
• G91/ETNMGP0003 Internal Audit Procedure
• G91/ETNQPN0001 Quality Plan
• G91/ETNWPR0001 Work Procedures
• G91/ETNQMM0001 Quality Management Manual
• G91/ETNWPR0007 Work Procedure for VFD Installation
• G91/ETNWPR0008 Work Procedure for VFD Testing
3.6. DRAWINGS
• 5806-A-V-E-6001 Low Voltage Variable Frequency Drive Drawings
• 5806-A-V-E-6002 Low Voltage Variable Frequency Drive Drawings
• 5806-P-V-E-6001 Low Voltage Variable Frequency Drive Drawings
• 5806-P-V-E-6002 Low Voltage Variable Frequency Drive Drawings
• 5806-A-C-E-1001 Atlantic Overall One Line
• 5806-P-C-E-1001 Pacific Overall One Line
• 5806-A-C-E-2269 TO 2274 Atlantic RG5 Main Winch Motor 1 VFD
• 5806-A-C-E-2277 TO 2278 Atlantic RG5 Main Winch Motor 2 VFD
• 5806-A-C-E-2291 TO 2292 Atlantic RG6 Main Winch Motor 1 VFD
• 5806-A-C-E-2294 TO 2295 Atlantic RG6 Main Winch Motor 2 VFD
• 5806-P-C-E-2269 TO 2274 Pacific RG5 Main Winch Motor 1 VFD
• 5806-P-C-E-2277 TO 2278 Pacific RG5 Main Winch Motor 2 VFD
• 5806-P-C-E-2291 TO 2292 Pacific RG6 Main Winch Motor 1 VFD
• 5806-P-C-E-2294 TO 2295 Pacific RG6 Main Winch Motor 2 VFD
3.7. PLANT & EQUIPMENT
3.7.1. PROCURE AND REVIEW:
• Drawings associated with the device being tested
• Instruction books
• Inspection Checklist(ICL)
• EATON Engineering System and Services (EESS) forms.
• Safe working procedures and MSDS forms that apply to this task
• Site safety rules and emergency procedures
• Install safety locks and tags and safety grounds as required to provide
for a safe working environment
3.7.2. VERIFY:
• That the equipment nameplate information is compatible with the
drawings
• Test Schedules and areas availability
3.7.3. RECORD ON THE INSPECTION FORM:
Doc. No.: G91/ETNWPR0007_UA
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
Date: 16/12/14
Page: 7 of 21
• Customer and job information
• Field data
• As found conditions in the comment area
• Test equipment data
• Service engineer/technician name & test date
Doc. No.: G91/ETNWPR0007_UA
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
Date: 16/12/14
Page: 8 of 21
3.8. PERSONNEL
Technicians performing these electrical tests and inspections shall be trained and
experienced concerning the apparatus and systems being evaluated. These
individuals shall be capable of conducting the tests in a safe manner and with
complete knowledge of the hazards involved (OSHA, NFPA70). They must
evaluate the test data and make a judgment on the serviceability of the specific
equipment.
4. MATERIALS
The following list suggests the basic equipment to perform the inspections.
Inspection crew shall verify with the site for any additional equipment required.
1. PPE as per NFPA 70, equipment and site requirements
2. Insulated Phillips, Slotted, Torx screwdriver sets
3. HV, LV Voltage detector Kit
4. Grounding clamps and cable
5. Emergency Response Kit
6. Barricade Tape, Red
7. Lockout, Electrical, Kit
8. Faceshield Frame w/ Lockdown, Dielectric
9. Glove,Linemans,Rubber,Sz 10,Blk,Pr
10. Glove,Linemans,Rubber,Black,Sz 10,Pr
11. Bag,Glove,14 In
12. Glove Protector, Cowhide, Size 10,PR
13. Current Probe
14. Goggles, Protective
15. Harness, Full Body
16. Extinguisher, 2.6#
17. Glove Protector, Tan/Black, Size 10,PR
18. Emergency Burn Kit
19. Project folder or note book
20. Product line contacts and phone numbers
5. QUALITY FORMS AND INSPECTION PROGRAMS
Throughout the equipment installation process, points of inspection must be recorded in a
clear manner in order to prevent confusion and/or errors. Below is a list of the documents
that are used to record the inspection data. These items are mentioned within the
Inspection and test plan (ITP) itself.
Inspection Checklist (ICL) – A document that states the inspection and/or test
conducted conforms to the requirements of the project specifications. It is
included on Appendix 2 and must be signed and approved by the inspection
party
Doc. No.: G91/ETNWPR0007_UA
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
Date: 16/12/14
Page: 9 of 21
6. INSPECTION AND TEST PLAN
6.1. GENERAL NOTES AND PRE-REQUITSITES
DO NOT ATTEMPT TO INSTALL OR WORK ON EQUIPMENT WHILE IT IS ENERGIZED
Always verify that no voltage is present before proceeding with testing. Assume all
circuits are energized. Confirm primary sources of power are disconnected, tagged, and
locked out. Always follow all local, state, and national regulations including OSHA,
ACP requirements and generally accepted safety procedures.
• Verify that equipment areas are available and safe to perform all related
inspections.
• Confirm that a power source is available for the installation equipment operation
prior to arriving to site.
• Inspect rigging devices and equipment. Lifting equipment shall have their
inspection up to date and labeled by a competent person.
• Workers shall bring to site all of the Personal Protective Equipment (PPE)
required to perform the tests and to comply with site requirements.
• Installation personnel shall comply with ACP 2600SEG-118 and
G00/UPCHSI0008 whenever required to perform Lock Out/Tag Out procedures
to isolate, from energy systems, machinery or equipment to be inspected,
serviced, or repaired. Energy sources may be electrical, mechanical, pneumatic,
chemical, thermal, or of other types that could cause injury to personnel or
damage to equipment.
6.2. INSPECTIONS
Equipment installations shall be made to ensure a correct installation according to
EATON’s User Manual for 9000X AF Drives and Post Glover Dynamic Brakes
installation Instructions. Verify reference drawings for additional information
regarding mounting diagrams, mounting locations and details. Inspections shall be
performed on the VFD’s and Dynamic brakes as a whole unit following the
Inspection and test plan included on Appendix 1. This plan details by line item the
activity to be inspected and the expected results as follows:
Doc. No.: G91/ETNWPR0007_UA
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
Date: 16/12/14
Page: 10 of 21
ITEM
No.
ITEM OF
INSPECTION
REFERENCE
DOCUMENTS
FOLLOW-UP
DOCUMENTS
TYPE OF INSPECTION /
INSPECTION PARTY NOTES/
ACCEPTANCE CRITERIA EATON GUPC ACP
1
Equipment
Received in Compliance
G91/ETNWPR0007 G91/ETNICL0006 W
Equipment shipping list match the received
components, no damaged boxes or missing equipment.
Inspections shall be documented on the Inspection Checklist (ICL) included on
Appendix 2. See below an itemized example of an inspection for reference:
Item
No.
ITEM OF
INSPECTION
OTHER
FOLLOW-
UP Doc.
Inspection Status/Party/Type/Date
WIR
Status
Remarks (NCR, CPP issued)
EATON GUPC ACP
1 Equipment Received in
Compliance
EESS-
VFD-002
X
OEV
X
ABC
X All boxes in good shape and no evident damage. All items
accounted as per shipping list.
5 6 R MM/D
D/YY R
• Finish recording data on the required checklists, completely filling in all the
appropriate blocks.
• Note corrective actions taken, deficiencies and recommendations, and any
general comments.
• Review and organize all test results and forms.
• Contact a customer representative to report results and follow-up actions.
GUPC can raise a CAR or a NCR every time that it may be necessary.
7. HEALTH AND SAFETY
Prior to working on any equipment or related component the employees shall review:
• Safe working procedures and MSDS forms that apply to this task.
• Site safety rules and emergency procedures.
• Perform a Job Safety Analysis to address the work environment and necessary
measures for a safe environment. This shall include:
• Identification of safety locks and tags and safety grounds installation
location as required to provide for a safe working environment
• Grounding points
• Barricade areas
• Minimum clearances based on NFPA70
• Emergency/Egress plan
• Contact information
• Required Work permits
• Required notifications
• Employee shall follow all OSHA guidelines for the work environment.
Doc. No.: G91/ETNWPR0007_UA
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
Date: 16/12/14
Page: 11 of 21
Any identified substandard condition or requirement (for the protection of workers)
that may come up during the development of works is under this WPR, will be
implemented regardless of the fact that it may have been inadvertently been left out.
8. ENVIRONMENT
Inspection crew shall familiarize with all environmental pre-requisites on site prior to
mobilization. As part of the acceptance testing the following shall be observed:
• Familiarize and follow all local guidelines for environmental compliance.
• Review the Material Safety Data Sheets (MSDS) of the materials to be used and
carry a copy to the site. This includes:
o Lubricants
o Corrosion inhibitors
o Adhesives
o Other that apply
• Bring oil absorbent material and proper disposal recipient.
Areas and equipment conditions shall be documented prior to start any activity. All
areas shall be clean at all times and left in operational conditions prior to leaving the
site. Contact a customer representative to report activity completion and any follow-
up actions.
Doc. No.: G91/ETNWPR0007_UA
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
Date: 16/12/14
Page: 12 of 21
APPENDIX 1
Doc. No.: G91/ETNWPR0007_UA
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
Date: 16/12/14
Page: 13 of 21
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
INSPECTION AND TEST PLAN FOR INSTALLATION
LOW VOLTAGE SYSTEM
VARIABLE FREQUENCY DRIVES
Date: 16/12/14
Doc. No.: G91/ETNITP0007_UA
Page: 14 of 21
ITEM
Nº ITEM OF INSPECTION
REFERENCE
DOCUMENTS
FOLLOW-UP
DOCUMENTS
TYPE OF INSPECTION /
INSPECTION PARTY NOTES/
ACCEPTANCE CRITERIA INSTALLER EATON GUPC ACP
1 Equipment Received in Compliance G91/ETNWPR0007 G91/ETNICL0006
W W
Equipment shipping list match the received
components, no damaged boxes or missing equipment.
Frequency: All assembly components.
2 Review Nameplate Data G91/ETNWPR0007 G91/ETNICL0006
W W Equipment nameplate data conforms to the project
specifications and drawings.
3 Physical and Mechanical Inspection G91/ETNWPR0007G91/ETNICL0006
W W
No physical damage, scratches or broken components
observed. All covers installed with all hardware fastened.
4 Safety Compliance G91/ETNWPR0007
G91/ETNSWP0002
G91/ETNICL0006 W W
Equipment stored and installed on a flat level surface, LOTO provisions on the equipment and energy sources
controlled.
5 Verify equipment clearances and conduit entry
points. G91/ETNWPR0007
G91/ETNICL0006 W W
Equipment clearances comply with the minimum of 4”
on top, 3” clearance on the sides unless otherwise specified on the design drawings and 36” on the front.
Conduit entry points are as per design documentation.
6 Verify mounting surface level G91/ETNWPR0007G91/ETNICL0006
W W
The VFD assembly is secured on a true and level
surface. Finished foundation (within 0 .06 in .[1 .5 mm] clearance) must extend under the VFD a minimum of
0” to a maximum of 3 .0 in. (76 .2 mm) unless
otherwise specified on the design drawings.
7 Verify Equipment is leveled G91/ETNWPR0007G91/ETNICL0006
W W The VFD assembly is leveled and plumb by bubble
level.
8 Verify equipment is anchored G91/ETNWPR0007G91/ETNICL0006
W W Equipment is anchored properly on suggested locations.
It must be tightened with pressure washers installed.
9 Equipment sections assembly G91/ETNWPR0007G91/ETNICL0006
W W Equipment sections are assembled in order and properly secured with the supplied hardware. All bolts are
installed and tightened.
10 Components Mechanical operation G91/ETNWPR0007G91/ETNICL0006
W W
Pass/Fail:
All mechanical operation of components functions
properly and aligned. Hinges, latches and levels operate freely.
11 Grounding System Installation G91/ETNWPR0007G91/ETNICL0006
W W Installed as per User Manual Power Wiring Section. Grounding System installed on the equipment
grounding points. Grounding points identified.
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
INSPECTION AND TEST PLAN FOR INSTALLATION
LOW VOLTAGE SYSTEM
VARIABLE FREQUENCY DRIVES
Date: 16/12/14
Doc. No.: G91/ETNITP0007_UA
Page: 15 of 21
ITEM
Nº ITEM OF INSPECTION
REFERENCE
DOCUMENTS
FOLLOW-UP
DOCUMENTS
TYPE OF INSPECTION /
INSPECTION PARTY NOTES/
ACCEPTANCE CRITERIA INSTALLER EATON GUPC ACP
12 Equipment bonding installation G91/ETNWPR0007G91/ETNICL0006
W W Visual Inspection of bonding jumpers installation if
applicable on equipment components.
13 Motor Cables separated from other control
cables G91/ETNWPR0007
G91/ETNICL0006 W W
Minimum distance between control cables is 1’ for cables lengths below 164’(50m), 3.3’ for cable lengths
less than 656’(200m)
14 Short circuit bracing G91/ETNWPR0007G91/ETNICL0006
W W Current carrying parts or cables shall be secured on the supplied supports.
15 Power and Control wires, terminal blocks
connection G91/ETNWPR0007
G91/ETNICL0006 W W
Internal control wires and power cables have to be connected on their respective terminal blocks. No loose
terminals or wires shall be observed.
16 Proper load cable length G91/ETNWPR0007G91/ETNICL0006
W W
Cable length for motors shall be less than:
328ft(100) for 1-2 hp motors
984(300m) for all other hp units
17 Proper field connections bolts torque G91/ETNWPR0007
G91/ETNWPR0008
G91/ETNICL0006 W W W
All field installed current carrying hardware has to be
torqued and marked. Refer to equipment data or G91/ETNWPR0008 Appendix 1 for torque values
18 Equipment Cleaning G91/ETNWPR0007G91/ETNICL0006
W W
No foreign objects or material is present inside the
assembly. All parts and components are dust free.
Equipment top and exterior is cleaned.
19 Environmental Compliance G91/ETNWPR0007G91/ETNICL0006
W W
All cleaning materials and remnants are properly
stored/disposed. All shipping & Packaging material is disposed properly.
20 Release for testing G91/ETNWPR0007
G91/ETNICL0006
G91/ETNWPR0008
H H H All ICL items completed successfully.
INSPECTION CODE: W – Witness Point H – Hold Point R – Review
Note: Inspections shall be performed in the full assembly (VFD &
Dynamic Brake).
Page: 12 of 1
APPENDIX 2
Doc. No.: G91/ETNWPR0007_UA
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
Date: 16/12/14
Page: 16 of 21
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
INSPECTION CHECKLIST FOR INSTALLATION
LOW VOLTAGE SYSTEM
VARIABLE FREQUENCY DRIVES
ICL SEQUENCIAL No.
ICL No.
G 9 1 / E T N I C L 0 0 0 6 - U A
LEGEND / LEYENDA INSPECTION PARTY / ENTIDAD INSPECTORA COMPLETENESS VERIF:
VERIF. RELLENO
QI FINAL CHECK
VERIF. FINAL DEL IC
Signature
Firma
Insp. Type
Tipo de Insp.
Insp. Status
Estado de Insp. 1 QCI EM 4
EATON
Supervisor 7 10 Sign.: Sign.:
W: Witness Point
Punto de Presencia
H: Hold Point
Punto de Parada
X: Conforming
Conforme
O: To Correct
Para corregir
: Corrected
Corregido
2 EM Prod. 5 8 11
Name: Name:
Date
Fecha 3
Installer/
Technician 6 9 12
Date: Date:
Page: 15 of 20
WORK SECTION SITIO ETF No.
/ E T F -
PART OF WORK PARTE DE TRABAJO ITP No.
G 9 1 / E T N I T P 0 0 0 6 - u U A
ITEM
No. ITEM OF INSPECTION
PUNTO DE INSPECCIÓN
OTHER
FOLLOW-UP DOC.
OTROS DOC. DE
SEGUIMIENTO
INSPECTION STATUS/PARTY/TYPE/DATE
ESTADO/ENTIDAD/TIPO/FECHA DE INSPECCIÓN WIR
STATUS/No.
REMARKS
(NCR, CPP issued)
NOTAS Installer EATON GUPC GUPC
1 Equipment Received in
Compliance G91/ETNITP0006
3 4
W W
2 Review Nameplate Data G91/ETNITP0006
3 4
W W
3 Physical and Mechanical
Inspection G91/ETNITP0006
3 4
W W
4 Safety Compliance G91/ETNITP0006
3 4
W W
5 Verify equipment clearances and
conduit entry points. G91/ETNITP0006
3 4
W W
6 Verify mounting surface level G91/ETNITP0006
3 4
W W
7 Verify Equipment is leveled G91/ETNITP0006
3 4
W W
8 Verify equipment is anchored G91/ETNITP0006
3 4
W W
9 Equipment sections assembly G91/ETNITP0006
3 4
W W
10 Components Mechanical
operation G91/ETNITP0006
3 4
W W
11 Grounding System Installation G91/ETNITP0006
3 4
W W
12 Equipment bonding installation G91/ETNITP0006
3 4
W W
13 Motor Cables separated from
other control cables G91/ETNITP0006
3 4
W W
14 Short circuit bracing G91/ETNITP0006
3 4
W W
15 Power and Control wires, terminal
blocks connection G91/ETNITP0006
3 4
W W
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
INSPECTION CHECKLIST FOR INSTALLATION
LOW VOLTAGE SYSTEM
VARIABLE FREQUENCY DRIVES
ICL SEQUENCIAL No.
ICL No.
G 9 1 / E T N I C L 0 0 0 6 - U A
LEGEND / LEYENDA INSPECTION PARTY / ENTIDAD INSPECTORA COMPLETENESS VERIF:
VERIF. RELLENO
QI FINAL CHECK
VERIF. FINAL DEL IC
Signature
Firma
Insp. Type
Tipo de Insp.
Insp. Status
Estado de Insp. 1 QCI EM 4
EATON
Supervisor 7 10 Sign.: Sign.:
W: Witness Point
Punto de Presencia
H: Hold Point
Punto de Parada
X: Conforming
Conforme
O: To Correct
Para corregir
: Corrected
Corregido
2 EM Prod. 5 8 11
Name: Name:
Date
Fecha 3
Installer/
Technician 6 9 12
Date: Date:
Page: 16 of 20
16 Proper load cable length G91/ETNITP0006
3 4
W W
17 Proper field connections bolts
torque G91/ETNITP0006
3 4 1
W W W
18 Equipment Cleaning G91/ETNITP0006
3 4
W W
19 Environmental Compliance G91/ETNITP0006
3 4
W W
20 Release for testing G91/ETNITP0006
3 4 1 2
H H H H
Page: 1 of 1
APPENDIX 3
Doc. No.: G91/ETNWPR0007_UA
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
Date: 16/12/14
Page: 19 of 21
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
VISUAL INSPECTION CHECKLIST FOR INSTALLATION
LOW VOLTAGE SYSTEM
VARIABLE FREQUENCY DRIVES
EESS No.
V F D - 0 0 1 -
G91ETNITP0006 Page 18 of 20
EXAMINE VFD FOR: ACCEPTABLE ACTION ITEM OR COMMENT
Equipment Received in Compliance
Yes
No
Review Nameplate Data
Yes
No
Physical and Mechanical Inspection
Yes
No
Safety Compliance
Yes
No
Verify equipment clearances and conduit
entry points
Yes
No
Verify mounting surface level
Yes
No
Verify Equipment is leveled
Yes
No
Verify equipment is anchored
Yes
No
Equipment sections assembly
Yes
No
Components Mechanical operation
Yes
No
Grounding System Installation
Yes
No
Equipment bonding installation
Yes
No
Motor Cables separated from other control
cables
Yes
No
VISUAL INSPECTION CHECKLIST
CUSTOMER: GUPC TECHNICIAN
NAME:
JOB LOCATION: DATE
TESTED:
FIELD DATA
EQUIPMENT
LOCATION:
EQUIPMENT
ID:
MANUFACTURER:
SERIAL #:
Contract No. CMC-221427, Design and Construction of the Third Set of Locks
VISUAL INSPECTION CHECKLIST FOR INSTALLATION
LOW VOLTAGE SYSTEM
VARIABLE FREQUENCY DRIVES
EESS No.
V F D - 0 0 1 -
G91ETNITP0006 Page 19 of 20
EXAMINE VFD FOR: ACCEPTABLE ACTION ITEM OR COMMENT
Main feeder installations
Yes
No
Short circuit bracing
Yes
No
Control wires, terminal blocks connection
Yes
No
Proper field connections bolts torque
Yes
No
Isolating Barriers installation
Yes
No
Cable lengths less than the maximum
allowed distance
Yes
No
Equipment Cleaning
Yes
No
Environmental Compliance
Yes
No
ADDITIONAL COMMENTS OR REMARKS
COMPLETENESS VERIF:
VERIF. RELLENO:
Signature: Date: