FVTX Review, November 16th, 2009 1 FVTX Mechanical Status: Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

Upload: gordon-woods

Post on 03-Jan-2016

222 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

FVTX Review, November 16th, 2009 1

FVTX Mechanical Status:

Walter Sondheim - LANL Mechanical Project Engineer; VTX &

FVTX

Page 2: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

VTX-FVTX Half Assembly for Introduction:

FVTX Review, November 16th, 2009 2

“Big Wheel” region, read-out electronics for VTX and FVTX; 5 layers – 1 stripixel, 3 pixel and 1 FVTX, (from the IP out)One of two FVTX detector assemblies per half VTX assemblyHalf VTX assembly; 4 layers - inner 2 pixel sensors, outer 2 are “stripixel” sensors.Support structure with isolation mounts for space frame and rigid mounting for ancillary system. Mounting is off support beams that run between CM poles.

Page 3: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

FVTX Half Assembly for Introduction:

FVTX Review, November 16th, 2009 3

1 Big Wheel per FVTX assembly, 6 ROCs, 8 wedges per ROC card. 4 detector stations per FVTX assembly, each off-set in phi.

Each station has its own cooling circuit, as well as one around the Big Wheel.

Each station has “wedge” silicon mini-strip detectors mounted to both sides, 4 layers per station disk.

Beryllium beam pipe 41.021 mm OD X 800.0 mm long.

Page 4: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

Wedge Sensor Module; stations 2 & 3 Upstream module, upper level:

FVTX Review, November 16th, 2009 4

Silicon sensor, 320. microns.

HDI, 334. microns.

Carbon back-plane, 1.56 mm, K13C2U. Fab at LBNL composite shop.Spacers – POCO graphite, AXM5Q, 2 versions of each.

Hirose DF18 series connector and Hirose H.FL series mini-coax for bias.

Separate ground connection point for Carbon.

FPHX read-out-chips, 13 on each side of sensor, 128 channels each, 300. – 528. microwatts per channel, 1.0 – 1.76 watts/wedge.

Each wedge assembly is mounted to a station disk by 2 #2 screws and 2 locating pins.

Page 5: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

Wedge Sensor Module assembly:

FVTX Review, November 16th, 2009 5

15 Chip large wedge prototype sensor module shown.-Chips mounted to HDI using Arclad 7876 transfer tape.-Sensor mounted to HDI using strips of Arclad 7876 and Tra-bond 2902 silver conductive epoxy.-HDI mounted to Carbon support wedge using Arclad 7876.-Graphite spacers mounted to Carbon support Arclad 7876.-Wedge assembly mounted to station disk thermal grease.-Each large wedge produces 1.33 watts at 400 microwatts/channel.

Page 6: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

Wedge Sensor Module assembly:

FVTX Review, November 16th, 2009 6

Station 1, two different HDI bends and two different spacers

Stations 2 & 3, two different HDI bends and two different spacers

Station 4, four different HDI bends and two different spacers

Page 7: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

FVTX Review, November 16th, 2009 7

Station sub-assembly, stations 2, 3 or 4:

Mounting and alignment pins in tabs, 3 per station half disk.

Thermally conductive blocks to transfer heat from wedge to support panel POCO Graphite AXM5Q. Outer block is just above cooling channel in disk.

PEEK mounting #2 screw – (phillips head)

M55J Carbon faced support panel

Four layers of 15 degree wedges, 2 layers on each side of support panel, front to back wedges rotated by 3.75 degrees.

Each wedge staggered in Z, 15 degrees between wedges on one side, upstream to downstream sides of panel offset by 7.5 degrees – hermetic in phi. Each silicon sensor covers 7.5 degrees in phi. Thermal load - 32 watts @ 400 microwatts/channel.

Page 8: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

Station Support Panel Construction:

FVTX Review, November 16th, 2009 8

Wedge locating pin

3 Holes for survey flag along edge

Hose barb PEEK

Mounting tab

M55J face sheet, .25 mm

Coolant channel, PEEK

Core – Allcomp Inc. Carbon foam, 4.76 mmCore insert PEEK,

pins SS, screws PEEK

M55J face sheet, .25 mm

Threaded insert for handle

Page 9: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

Walter Sondheim, UNM, July 16th, 2009 9

FVTX station half panel status:

• Preliminary drawings for all four stations have been completed.• Even with the “staggered” orientation of the stations, there are

only two distinct panels – one for station 1 and the second for stations 2,3 & 4. The stagger, or phi rotation, is built into the FVTX cage.

• No additional analysis for the station disk has been performed

since early 2008. The need for an analysis of a station disk laying flat is being evaluated..

• The cooling loop around the outer perimeter of the disk is of an enclosed cavity design – solid PEEK material with Carbon face sheets bonded to it as the other two sides for the channel.

• Alignment flag placements have been included at three locations around the outer perimeter of the station half disk. Targets from Hubbs Machine, Cedar Hill, Missouri, will be used.

Page 10: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

FVTX Review, November 16th, 2009 10

FVTX “Staggered” Cage:

Cage design uses CN60 carbon fabric with a EX1515 resin. FEA analysis indicates very rigid structure < 25. microns.

Blocks and flanges POCO graphite AXM5Q.

Note: the mounting blocks for the 4 stations will be clocked in 1 degree increments.

Each FVTX interfaces directly with the VTX space-frame.

For scale: 400. mm in diameter, 187. mm in length.

Penetrations in shell for survey/alignment flags.

Fabrication will take place at LBNL composite shop.Mounting points to VTX space frame

beams.

Page 11: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

Walter Sondheim, UNM, July 16th, 2009 11

FVTX Cage – staggered station positions:

Station 1 0 degree. Station 2 2.8125 degrees. Station 3 .9375 degrees. Station 4 1.8750 degrees.

Mating half cage is the same, rotates about the beam axis 180 degrees.

Page 12: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

FVTX Review, November 16th, 2009 12

Half Cage Assembly with Liquid Cooling Circuit:

Each station can be cooled in parallel or series with the other stations.

Pressure drop per stations 2,3&4-.5psi, staion1-.28psi

Delta-T per ½ station 1.8 degrees C, delta p .4 psi

Coolant 3M Novec 7200

Thermal load – 108.3 watts half cage @ 400 microwatts/channel

Inlet flow rate per station 28.2 ml/secInlets: 5.5°C,@ 20.psi

Outlets:6.16 °C,@19.5psi if parallel circuits.

Outlets:7.73ºC,@18.22psi if circuits in series

Novec 7200:Boiling point 76 degree C

Melting point -138 degree C

Vapor pressure 109 mmHg @ 25 degrees C

Neutron irradiation study at LANL’s WNR facility – total dose 6.7 X 10**11 n/cm**2, nominal energy 800 Mev. Samples were sent to 3M for analysis of free Fluoride, no indication of significant degradation.

Page 13: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

FVTX Review, November 16th, 2009 13

Coolant to FPHX Chips Thermal Path:

Approximate temperatures with 5.5°C coolant flowing at Re~14,700

Page 14: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

Coolant to FPHX Chips Thermal Path:

FVTX Review, November 16th, 2009 14

Thermal measurements made on 15 chip wedge assembly, powered LVDS at 390. ma, 2.6 V = 528.1 microwatts per channel. Measured 29 ° C to 36 ° C along 13 chips, no coolant or contact with Aluminum plate. Temperature dropped 2 ° C when spacers in contact with Aluminum @ 23 ° C. Sensor deflection and temperature differential across the wedge vary linearly with chip power.

Page 15: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

Temperature distribution along large wedge:

Constraint temperature was varied to keep peak chip temperature at 21°C

200 µW/ChannelBase Temperature 17.36° C

300 µW/ChannelBase Temperature 15.54° C

410 µW/ChannelBase Temperature 13.53° C

500 µW/ChannelBase Temperature 11.89° C

FVTX Review, November 16th, 2009

12°

23°

16.5°

Page 16: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

Total Wedge Deflection:

200 µW/Channel 300 µW/Channel 410 µW/Channel 500 µW/Channel

FVTX Review, November 16th, 2009

0.0

-0.0002 m

+0.0002 m

Page 17: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

FVTX Review, November 16th, 2009 17

Two Independent Halves:

“Big Wheel” cooling plate with coolant channel along perimeter, 3. mm Aluminum.

ROC cards, 38. watts/card – 228 watts per Aluminum disk.

Wedge readout extension cables, 16 variation – each modeled.

Gas seal between layers, Silicone.

Work will begin shortly on design for assembly jigs for disks and aids for mounting disks and cables into cage. An external support structure for the cage is needed for final assembly and testing, prior to mounting into the ends of the VTX space frame.

This half FVTX assembly is stand alone, can be tested independently of the rest of the detector in a lab, with coolant and a support stand.

Page 18: FVTX Review, November 16th, 2009 1 FVTX Mechanical Status : Walter Sondheim - LANL Mechanical Project Engineer; VTX & FVTX

FVTX Review, November 16th, 2009 18

Summary: WBS 1.6 Mechanics – Schedule Dates & Manpower

• WBS 1.6– WBS 1.6.1 Specifications 10/21/2005 – 2/9/2006– WBS 1.6.2 Support Structure Cage 4/1/2007 – 7/9/2009– WBS 1.6.3 Wedge Backplane 4/11/2008 – 10/15/2009– WBS 1.6.4 Support Disk 1/4/2007 – 12/1/2009 – WBS 1.6.5 Alignment and Assembly 8/1/2008 – 2/15/2010

• Milestones– Final design drawings for wedge components complete

• Carbon backing• HDI• Spacers• Thermal and mechanical analysis complete

– Final design drawings for the FVTX cage complete– Final design drawings for station disk complete in December