future of hydro power in india- private sector performance
DESCRIPTION
Future of Hydro Power in India- Private Sector PerformanceTRANSCRIPT
FUTURE OF HYDRO - PRIVATE SECTOR PERFORMANCE
RAHUL VARSHNEY
2
Hydro Power- Private Sector Performance
Hydro Power contributes to16.36% of total electricity generation in India.
Around 90000 MW capacity is still untapped and is yet to be developed
Private sector participation is growing in Hydro Power segment.
Hydro is a major source of peaking power, ancillary services and black start.
Most flexible and sustainable source of generation
Cost of generation of BBMB plants after 40 years of operation is only 20 paisa/kwh
ALL India State Private Central0
50001000015000200002500030000350004000045000
0%
20%
40%
60%
80%
100%
120%40661
27482
2694
10485
100%
68%
7%26%
Hydro Capacity under operation
ALL India State Private Central0
2000400060008000
10000120001400016000
0%
20%
40%
60%
80%
100%
120%14410
22424837
7331
100%
16%
34%
51%
Hydro Capacity under Construction
3
No development from Private sector
Around 41000 MW Hydro Projects have been allotted to various Private developers
Not much development is taking place in Arunachal Pradesh, remote locations of Himachal and Uttarakhand
3600 11001800
1100
33000
Private Sector Allotted Hydro Projects, yet to be taken for construction
Himachal Pradesh Uttarakhand SikkimMeghalaya Arunachal Pradesh
Jaypee Tata Power Bhilwara & Statkraft
0
500
1,000
1,500
2,000 1,700
447 278
Top 3 players make up ~90% of the installed private capacity
4
Challenges for the private sector CHALLENGES- Bad Infrastructure / Road conditions - Delay in Award of Clearances (environment &
forest) , Land Acquisition- Delay in Financing / getting Financial Closure or
additional funding due to cost & time overrun.- High free power component and cost plus tariff- Financial upheaval and changes in company
strategy. No M&A policy or clarity
REWARD- Cost plus tariff giving 15.5% ROE subject to an
available buyer- Benefits to the Electrical system -spinning
reserve & frequency response, voltage support, black start capability
5
Bad Infrastructure CHALLENGES- Bad Infrastructure / Road conditions affecting
schedule of Project
WAY FORWARD- Access to the projects should be part of state
government initiative. - Common Infrastructure – funding, development
and utilisation- Defining the share of Government and Project
Developers in infrastructure costs
6
Approval and Clearances
CHALLENGES- Approval and clearance
WAY FORWARD- Defining of standard clearances with
required papers and procedures- Land acquisition under the New Act- Evolution of Single window; avoid
multiplicity of examination - Fixing timelines for statutory and non-
statutory clearances- Dispute Resolution
- More than 30% of the projects get stuck due to Environment clearances
- Land diversion / Forest Clearance takes at least 2-3 years and is considered into critical path of Project Activity.
- Environment clearance of Uttarakhand HEPs stalled by Supreme court from Aug’13 onwards.
7
Change in ownership
CHALLENGE- Change of ownership and control- Change of ownership in the Implementation
Agreements of most of the Hydro states are restrictive or ambiguous.
- Loss of expenditure and intellectual property.
WAY FORWARD- Remove restrictions on change of ownership - If required pre-define the technical and Financial
credentials of incumbent.
8
Enabling Environment
The Risk Reward should be reviewed. Much higher Risk
State should take Project Management role and be enabler to clear bottlenecks
Evolving of single window clearance; avoid multiplicity of examinations of similar issues at different levels
Viability of free power requirement
Clear M&A policy enabling certain developers to exit and unlocking value.
THANKS