Experimental Methods in Marine Hydrodynamics Lecture in week 46
Contents: •Types of tests •How to perform and correct speed trials •Wave monitoring
•Measurement •Observations
•Motion measurement •Hull monitoring •Propeller cavitation observations
Covers Chapter 11 in the Lecture Notes
3
Sea trials are conducted under the following circumstances:
• Delivery of newbuildings (Contractual Trials) – Speed-power (compliance with contracted performance) – Bollard Pull test (tugs and offshore vessels – compliance with
contracted performance) – Maneuvering (compliance with IMO criteria) – Sea keeping (only high speed craft)
• If a special problem has arisen, for instance: – Propeller noise and/or erosion – Steering problems – Excessive fuel consumption
• For research purposes (quite rare due to high costs) – Mainly seakeeping and sea loads tests
4
Delivery Sea trials (Contractual trials)
• Ship building contracts contain specific requirements for speed-power performance – Failure to meet requirements means fees to be paid and ultimately
that the ship owner has the right to refuse to accept the ship
• There might be requirements also for maneuvering trials : – Emergency stop test – Turning circles – Zig-zag tests
• High speed craft – requirements also for seakeeping tests – IMO: 2000 HSC Code (IMO 185E)
5
Applicable standards
• ISO 19019:2005 Sea-going vessels and marine technology -- Instructions for planning, carrying out and reporting sea trials
• ISO 15016 Guidelines for the assessment of speed and power performance by analysis of speed trial data
• ITTC Recommended procedure 7.5-04-01-01.1 Preparation and Conduct of Speed/Power Trials
• IMO: 2000 HSC Code (IMO 185E) – Requirements for testing of high speed craft
6
IMO HSC testing requirements
• Stopping – Normal stop from max speed to zero – Emergency stop – Crash stop
• Cruise performance in two sea states – Normal conditions – Worst intended conditions – Measurements of accelerations, speed, relative wave heading
• Failure tests – Check that the ship, crew and passengers are not at risk if for
instance the steering fails
7
Organization of Delivery Trials
• The Shipbuilder is responsible • Trial Leader
– From the shipbuilder – Responsible for the execution of all phases of the trial
• Ship masters – There is one ship master hired by the shipbuilder who is in charge
of handling the ship – There is usually one or more ship masters hired by the shipowner
who is going to take over the ship • Measurements are performed by shipbuilder or by third
party (like Marintek or Maskindynamikk)
8
Execution of speed trials
• Always run back and forth at same engine setting • Run back and forth at the same track • Perform runs at different speeds (at least three) • If possible, orient the track with and against the wind
direction
•Steady Approach
> 5 min and 1 mile
•Steady Approach
> 5 min and 1 mile
Wind, current
9
Measured mile
10
Trial Conditions – max acceptable
• Sea state – Preferably ≤ sea state 3 – Ultimately ≤ sea state 5 (or up to sea state 6 for ships with L>100 m)
• Wind – ≤ Beufort 6 (20 knots) (for ships with L>100 m) – ≤ Beufort 5 (for ships with L ≤ 100 m)
• Water depth h – h>6.0*Am
2 and h>½V2
– Smaller depths require corrections for shallow water • Current
– Current of more than a few knots is unacceptable
11
Trial Conditions – Contractual
• Sea state – No waves – In practice: Beufort 1 (Wave height 0.1 m)
• Wind – No wind – In practice: Beufort 2 (Wind speed ≤ 6 knots)
• Water depth h – Deep, – In practice: h>6.0*(Am)½ and h>½V2
• Current – No current – No practical limit for when corrections are made. Use of double runs
means that corrections are always included
12
Correction of trial results
• When trial conditions are not fulfilled corrections must be made
• Typical corrections: – Draught – interpolation in model test results on two draughts – Wind – calculation of wind resistance using empirical drag coef. or
results from wind tunnel tests – Shallow water – empirical formulas – Waves – calculation of added wave resistance and speed loss
• Standards for how corrections shall be performed: – ISO 15016 Guidelines for the assessment of speed and power … – ITTC Procedure for the Analysis of Speed/Power Trial Data
13
Speed measurement
• “Speed over ground” and “Speed through water” • Timing a measured mile
– the old-fashioned way, only applicable to dedicated speed trials – Gives speed over ground
• GPS – The obvious choice, always used – Gives speed over ground
• Speed log – Device to measure speed through water – Always installed on ships – The accuracy is questionable!
14
Measurement of shaft power • Strain gauges glued directly to the shaft
– Calibration factor must be calculated, so shaft dimensions and material properties must be known exactly
– Tachometer to measure shaft speed
• Commercial power meters – Made for permanent installation – The best, but most expensive alternative
• Poor, but cheap alternatives are – fuel rack measurements (measurement of fuel consumption,
combined with supplier data for fuel quality) – measurement of cylinder pressure (used on large, slow speed
engines)
15
Shaft measurements
Torque measurement Thrust measurem.
16
Bollard Pull Tests
Good location Poor location
17
Maneuvering trials
• Trial types and execution same as in model scale • Measurements:
– (D)GPS position measurement – Gyro compass course – Rudder angle – Propeller revs
18
Measurements – environmental conditions • Water depth
– Echo sounder (ship instrument) or nautical charts • Water quality
– Temperature: Cooling water intake temperature can be used – Density: From nautical charts or density measurements
• Wind – Velocity and direction from anemometer – A separate, calibrated instrument is preferable – Watch out for influence of superstructure on the measurement
• Current – Nautical charts and tables – the difference in speed between double runs – a 360º turning test at low speed – The difference between log speed and GPS speed
• often, one doesn’t trust the speed log sufficiently for this purpose
19
Wave measurements
• Visual observation and estimation – Estimates by yard representative, ship-owner representative, and
possibly a neutral third party are compared and averaged
• Mobile wave buoy – Accurate (but only at a single point) – Recovery of the buoy is difficult (high risk of loosing it)
• Fixed weather station – Good solution if one is nearby
• Wave radar (Wavex) • Bow-mounted altimeter
20
Wavex by Miros AS
21
Bow-mounted altimeter
• Measures relative wave motion • Ship motions must also be measured
in order to calculate absolute wave height
SM - 055
SM - 094
22
Directional wave radar
• Microwave radar • On fixed or on moving “platforms” • Big and expensive • Used on offshore installation, not on ships
SM - 050
23
Beufort wind scale with related sea conditions Sea Description term Wind sp. [knots] Wave height [m]
Beufort state Wind Wave min max Probable Max0 0 Calm Calm 0 1 0 0 1 0 Light air Ripples 1 3 0.1 0.1 2 1 Light breeze Small wavelets 3 6 0.2 0.3 3 2 Gentle breeze Large wavelets 6 10 0.6 1 4 3 Moderate breeze Small waves 10 16 1 1.5 5 4 Fresh breeze Moderate waves 16 21 2 2.5 6 5 Strong breeze Large waves 21 27 3 4 7 6 Near gale Large waves 27 33 4 5.5 8 7 Gale Moderately high waves 33 40 6 7.5 9 8 Strong gale High waves 40 47 7 10
10 9 Storm Very high waves 47 55 9 12.5 11 9 Violent storm Exceptionally high waves 55 63 11.5 16 12 9 Hurricane Exceptionally high waves 63 71 14 16 13 9 Hurricane Exceptionally high waves 71 80 >14 >1614 9 Hurricane Exceptionally high waves 80 89 >14 >1615 9 Hurricane Exceptionally high waves 89 99 >14 >16
24
25
•Illustrations of Beufort wind (and wave) scale •From: http://en.wikipedia.org/wiki/Beaufort_scale
27
Measurement of motions
• Accelerations: Conventional accelerometers • Angles: Gyros, magnetic compass, accelerometers • Rate gyro to measure rate of change of angles • Inertial Measurement Units (IMU)
– Consists of a number of accelerometers built into one compact unit – Gives out accelerations, velocities and motions at any point – Konsberg Seatex MRU is a good example of a commercial IMU
28
Measurement of forces: Hull Monitoring - Sensors
• Strain gauges most common sensor
• Short and long gauges • Cabling exposed to
damage, gauges work loose
• Sensors based on fiber-optics - polarimetric and bragg-grating suggested as alternative
Hull Monitoring System:
Strain gauge in protective casing:
29
Rolls-Royce Health and Monitoring System - HEMOS
30
Propeller Cavitation Observations
Seen from below Seen from the side
31
Cavitation observation techniques
1. generation borescope
2. generation borescope
Source: marin.nl
32
Sample picture from full scale propeller cavitation observation
Summary: •Types of tests •How to perform and correct speed trials •Wave monitoring
•Measurement •Observations
•Motion measurement •Hull monitoring •Propeller cavitation observations