front end loading work flow process

1
SCOPE DEFINITION PHASE FEL 3 FEL 2 PROCESS Alternative Selection Line List Tie-In List Instrument Index Decision 15% 10% Engineering 25-30% of Engineering Ford, Bacon & Davis, LLC John Fish FELW FD-2.PPT Rev 14 Sept 2004 FRONT END LOADING WORK FLOW PROCESS FEL Modules Adapted from Strategic Project Planner, by Westney Consultants International, Inc. Responsibility Matrix Lessons Learned PDRI 1 EQUIPMENT LIST FEL 2 FEL 3 Lessons Learned SP List CLASS III ESTIMATE -25%, +30% CLASS III ESTIMATE -10% , +10% INTERACTIVE PLANNING VALUE ENGINEERING SCOPE DEFINITION PHASE FEL 3 FEL 2 PROCESS Alternative Selection Line List Line List Tie-In List Tie-In List Instrument Index Instrument Index DESIGN FOR SAFETY & CONSTRUCTABILITY: Establish Philosophy and then conduct Ongoing Constructability/Safety Reviews ENGINEERED EQUIPMENT - INQUIRY & BID EVALUATION TO DEFINE PRICING/DELIVERIES ENGINEERED EQUIPMENT - DEVELOP EQUIPMENT DATA SHEETS Create Permitting Plan INITIATE PERMITTING PROC ESS Decision FEL-L Information Management Plan FEL-C Construction Management Plan FEL-E Specialist Participation Plan FEL- A: Design Management Plan FEL- F: Cost OPERABILITY, RELIABILITY, & MAINTAINABILITY PLANNING & REVIEWS 15% 15% 10% Engineering 25-30% of Engineering FEL- B: Materials Management Plan Ford, Bacon & Davis, LLC John Fish FELW FD-2.PPT Rev 14 Sept 2004 FRONT END LOADING WORK FLOW PROCESS FEL-H Commissioning & Startup Plan FEL- I: QA/QC Management Plan Management Plan FEL- G: Schedule Management Plan FEL- J: Safety Management Plan FEL- M: Change Management Plan FEL Modules Adapted from Strategic Project Planner, by Westney Consultants International, Inc. DEVELOP MATERIALS MANAGEMENT PLANNING FOR ENGINEERED EQUIP , FABRICATED PIPE/STEEL, THEN BULKS Responsibility Matrix Responsibility Matrix Lessons Learned Lessons Learned PDRI Risk Analysis Contingency Setting EQUIPMENT LOCATION DRAWINGS Constructability Check List Formal Review Team Integration Session 2 PDRI 1 PFD's PLOT PLAN EQUIPMENT LIST FEL 2 DEVELOP P&ID'S CONDUCT HAZ ARDS REVIEW P&ID'S ISSUED FOR COMMENT P&ID's ISSUE FOR APPROVAL P&ID's ISSUE FOR DESIGN FEL 3 Responsibility Matrix PDRI Lessons Learned Risk Analysis Contingency Setting Preliminary Hazards Review Team Integration Session 1 SP List SP List Contract & Procurement Strategy Detailed Contract & Procurement PLAN CLASS III ESTIMATE -25%, +30% CLASS III ESTIMATE -10% , +10% INITIATE FORMAL MANAGEMENT OF CHANGE PROCESS DEFINE: AREAS/CBS/WBS INTERACTIVE PLANNING SCHEDULE LEVEL: III Engineering II Construction PROCESS SIMPLIFICATION VALUE ENGINEERING

Upload: acalerom3625

Post on 03-Mar-2015

294 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Front End Loading Work Flow Process

SCOPE DEFINITION PHASE FEL 3FEL 2 PROCESS Alternative Selection

Line List

Tie-InList

InstrumentIndex

DESIGN FOR SAFETY & CONSTRUCTABILITY: Establish Philosophy and then conduct Ongoing Constructability/Safety Reviews

ENGINEERED EQUIPMENT - INQUIRY & BID EVALUATION TO DEFINE PRICING/DELIVERIES

ENGINEERED EQUIPMENT - DEVELOP EQUIPMENT DATA SHEETS

Create Permitting Plan INITIATE PERMITTING PROCESS

Decision

FEL-L InformationManagement Plan

FEL-C ConstructionManagement Plan

FEL-E SpecialistParticipation Plan

FEL- A: DesignManagement Plan

FEL- F: Cost

OPERABILITY, RELIABILITY, & MAINTAINABILITY PLANNING & REVIEWS

15%

10%Engineering

25-30% of Engineering

FEL- B: MaterialsManagement Plan

Ford, Bacon & Davis, LLCJohn Fish FELWFD-2.PPTRev 14 Sept 2004

FRONT END LOADING WORK FLOW PROCESS

FEL-HCommissioning& Startup Plan

FEL- I: QA/QCManagement Plan

Management Plan

FEL- G: ScheduleManagement Plan

FEL- J: SafetyManagement Plan

FEL- M: ChangeManagement Plan

FEL Modules Adapted from Strategic Project Planner, by Westney Consultants International, Inc.

DEVELOP MATERIALS MANAGEMENT PLANNING FOR ENGINEERED EQUIP , FABRICATED PIPE/STEEL, THEN BULKS

ResponsibilityMatrix

LessonsLearned

PDRI Risk AnalysisContingency

Setting

EQUIPMENT

LOCATION

DRAWINGS

Constructability

Check List

Formal Review

Team IntegrationSession 2

PDRI

1

PFD's PLOTPLAN

EQUIPMENTLIST

FEL 2DEVELOPP&ID'S

CONDUCTHAZ ARDSREVIEW

P&ID'SISSUED

FORCOMMENT

P&ID'sISSUEFOR

APPROVAL

P&ID'sISSUEFOR

DESIGN

FEL 3

Responsibility

Matrix

PDRILessonsLearned

Risk AnalysisContingency

Setting

PreliminaryHazardsReview

Team Integration

Session 1

SP List

Contract & Procurement Strategy

Detailed Contract & Procurement PLAN

CLASS III ESTIMATE -25%, +30%

CLASS III ESTIMATE -10%, +10%

INITIATE FORMAL MANAGEMENT OF CHANGE PROCESS

DEFINE: AREAS/CBS/WBS

INTERACTIVE PLANNING

SCHEDULE LEVEL: III Engineering II Construction

PROCESSSIMPLIFICATION

VALUEENGINEERING

SCOPE DEFINITION PHASE FEL 3FEL 2 PROCESS Alternative Selection

Line ListLine List

Tie-InList

Tie-InList

InstrumentIndex

InstrumentIndex

DESIGN FOR SAFETY & CONSTRUCTABILITY: Establish Philosophy and then conduct Ongoing Constructability/Safety Reviews

ENGINEERED EQUIPMENT - INQUIRY & BID EVALUATION TO DEFINE PRICING/DELIVERIES

ENGINEERED EQUIPMENT - DEVELOP EQUIPMENT DATA SHEETS

Create Permitting Plan INITIATE PERMITTING PROCESS

Decision

FEL-L InformationManagement PlanFEL-L InformationManagement Plan

FEL-C ConstructionManagement Plan

FEL-C ConstructionManagement Plan

FEL-E SpecialistParticipation PlanFEL-E SpecialistParticipation Plan

FEL- A: DesignManagement Plan

FEL- F: CostFEL- F: Cost

OPERABILITY, RELIABILITY, & MAINTAINABILITY PLANNING & REVIEWS

15%15%

10%Engineering

25-30% of Engineering

FEL- B: MaterialsManagement Plan

Ford, Bacon & Davis, LLCJohn Fish FELWFD-2.PPTRev 14 Sept 2004

FRONT END LOADING WORK FLOW PROCESS

FEL-HCommissioning& Startup Plan

FEL-HCommissioning& Startup Plan

FEL- I: QA/QCManagement Plan

FEL- I: QA/QCManagement Plan

Management Plan

FEL- G: ScheduleManagement PlanFEL- G: ScheduleManagement Plan

FEL- J: SafetyManagement Plan

FEL- J: SafetyManagement Plan

FEL- M: ChangeManagement Plan

FEL- M: ChangeManagement Plan

FEL Modules Adapted from Strategic Project Planner, by Westney Consultants International, Inc.

DEVELOP MATERIALS MANAGEMENT PLANNING FOR ENGINEERED EQUIP , FABRICATED PIPE/STEEL, THEN BULKS

ResponsibilityMatrix

ResponsibilityMatrix

LessonsLearnedLessonsLearned

PDRI Risk AnalysisContingency

Setting

Risk AnalysisContingency

Setting

EQUIPMENT

LOCATION

DRAWINGS

EQUIPMENT

LOCATION

DRAWINGS

Constructability

Check List

Formal Review

Constructability

Check List

Formal Review

Team IntegrationSession 2

Team IntegrationSession 2

PDRIPDRI

1

PFD's PLOTPLAN

EQUIPMENTLIST

FEL 2DEVELOPP&ID'S

CONDUCTHAZ ARDSREVIEW

P&ID'SISSUED

FORCOMMENT

P&ID'sISSUEFOR

APPROVAL

P&ID'sISSUEFOR

DESIGN

FEL 3

Responsibility

Matrix

Responsibility

Matrix

PDRIPDRILessonsLearned

Risk AnalysisContingency

Setting

Risk AnalysisContingency

Setting

PreliminaryHazardsReview

Team Integration

Session 1

Team Integration

Session 1

SP ListSP List

Contract & Procurement Strategy

Detailed Contract & Procurement PLAN

CLASS III ESTIMATE -25%, +30%

CLASS III ESTIMATE -10%, +10%

INITIATE FORMAL MANAGEMENT OF CHANGE PROCESS

DEFINE: AREAS/CBS/WBS

INTERACTIVE PLANNING

SCHEDULE LEVEL: III Engineering II Construction

PROCESSSIMPLIFICATION

VALUEENGINEERING