foundation report for proposed addition at the …
TRANSCRIPT
Corporate Headquarters (610) 277-0880 FAX 277-0878
Southern New Jersey (856) 768-1001 FAX 768-1144
Central Pennsylvania (717) 697-5701 FAX 697-5702
Lehigh Valley 149 Main Street
Emmaus, PA 18049 (610) 967-4540 FAX 967-4488
[email protected] www.earthengineering.com
FOUNDATION REPORT
FOR
PROPOSED ADDITION AT THE
ADAMSTOWN ELEMENTARY SCHOOL
COCALICO SCHOOL DISTRICT
ADAMSTOWN BOROUGH
LANCASTER COUNTY, PENNSYLVANIA
Prepared For:
AEM Architects, Incorporated 3700 Perkiomen Avenue Reading, Pennsylvania 19606-2795
EEI Project Number: 31241.00
November 21, 2018
TABLE OF CONTENTS
I. PROJECT OBJECTIVE AND SCOPE OF WORK ................................................. 1
II. SITE AND PROJECT DESCRIPTIONS ................................................................. 1
III. FIELD INVESTIGATION ........................................................................................ 4
IV. LABORATORY TESTING ...................................................................................... 5
V. SUBSURFACE CONDITIONS ............................................................................... 6
A). GEOLOGY ........................................................................................................ 6
B). SOIL / BEDROCK ............................................................................................ 6
C). GROUNDWATER ............................................................................................. 9
VI. GEOTECHNICAL ANALYSIS ................................................................................ 10
VII. FLOOR SLAB RECOMMENDATIONS .................................................................. 13
VIII. SITE PREPARATION ............................................................................................ 14
IX. EXCAVATION METHODS ..................................................................................... 15
X. LATERAL EARTH PRESSURES........................................................................... 17
XI. SITE SEISMICITY .................................................................................................. 18
XII. FILL AND COMPACTION ...................................................................................... 19
A). FILL CRITERIA ................................................................................................ 19
B). COMPACTION CRITERIA ............................................................................... 21
XIII. CONSTRUCTION QUALITY CONTROL ............................................................... 22
XIV. LIMITATIONS ......................................................................................................... 22
APPENDIX
TOPOGRAPHIC MAP OF SITE BEDROCK GEOLOGIC MAP OF SITE
BORING LOCATION PLAN BORING PROFILES
LABORATORY TESTING BORING LOGS
KEY TO BORING LOGS
1
I. PROJECT OBJECTIVE AND SCOPE OF WORK
Earth Engineering Incorporated (EEI) completed the Foundation Report for the proposed
addition to the Adamstown Elementary School located in Adamstown Borough, Lancaster County,
Pennsylvania. The objective of this project was to investigate, document, and analyze the
subsurface conditions beneath the proposed building addition. Based upon the subsurface
conditions, recommendations regarding foundation system determination and design for the
proposed addition, as well as general earthwork and construction recommendations, were
developed and are included within this Report.
The scope of work for this project included a field investigation, a geologic analysis of the
site conditions, laboratory testing of soil samples obtained in the field and a geotechnical
engineering analysis. The work was performed in general accordance with EEI proposal LV4676,
dated October 31, 2018. This Report presents the results of our work.
II. SITE AND PROJECT DESCRIPTIONS
The Adamstown Elementary School is located at 256 West Main Street in Adamstown
Borough, Lancaster County, Pennsylvania. The school is bordered by Adamstown Road to the
north, West Main Street to the east and south, and an athletic field and wooded properties to the
west. Currently, the existing school occupies the central and southern portions of the site. The
proposed location of the addition is asphalt and grass covered. A steepen slope is located adjacent
to the eastern wall of the proposed addition. A stormwater management basin is located to the
east of the proposed addition. The topography of the site slopes gently downward to the east.
Based on the surface elevations of the borings, the maximum relief across the footprint of the
addition is approximately 6.5 feet. Plate 1, included within the Appendix of this Report, shows the
general location of the overall site on a topographic map of the area. The following photographs
show the site conditions at the time of the field investigation:
2
Looking South across the Western Portion of the Looking East from the Western Portion of the Existing School (Photograph 1) School Grounds (Photograph 2)
Looking Southwest from the Northern Portion of Looking South at the Existing School School Grounds (Photograph 3) (Photograph 4)
3
The following aerial photograph from Google Maps; Satellite View, shows the location of the
entire site:
Based on the Test Boring Plan prepared by AEM Architects, Incorporated, a single story,
4,690 square foot building addition is proposed for this project. The addition will be adjacent to the
northern wall of the existing school, and will have a finished floor elevation of 540.0 feet. The
structural loadings were not established at the time of report preparation. However, based on our
experience with similar types of projects, EEI estimates maximum column and wall loads will not
exceed 100 kips and 3.0 kips per linear foot, respectively. The proposed construction, in relation to
the existing site features, is shown on the Boring Location Plan, EEI Drawing Number: 31241.00-A-
101.
4
III. FIELD INVESTIGATION
A total of ten (10) borings, designated B-101 through B-110, were conducted for this
investigation. The borings were performed on November 12 and 13, 2018, by Corcoran Drilling
Company of West Chester, Pennsylvania. Supervision and monitoring of the boring program were
performed by a representative of EEI. The boring locations were field determined by a
representative of EEI, based on the location of the borings depicted on the Test Boring Plan. The
surface elevations for the boring locations were determined by utilizing a concrete entranceway
area as a reference datum. Based on the provided plans, the concrete entranceway elevation was
539.94 feet. The location of each test boring is shown on the Boring Location Plan included in the
Appendix of this Report.
The test borings were advanced using two inch (2”) outer diameter (O.D.) split barrel
samplers and six inch (6’’) O.D. solid stem augers. Split-barrel samples, conducted in accordance
with American Society for Testing and Materials (ASTM) standard D1586, were taken at regular
intervals throughout the depths of all the borings. Standard Penetration Test (SPT) values were
recorded for each sample. The SPT values, which are a measure of soil density and consistency,
are the number of blows required to drive the two inch (2”) O.D. split-barrel sampler six inches (6”)
using a one hundred forty pound (140#) weight dropped thirty inches (30”). The number of blows
required to advance the sampler over the 12 inch interval from 6 to 18 inches is considered the "N"
value. The test boring logs, which provide sample depths, description of the materials encountered
and sampling data, are included in the Appendix of this Report. The information presented on
these logs was used to generate boring profiles that graphically represent the subsurface conditions
encountered at the boring locations. The Boring Profiles, EEI Drawing Sheet Number: 31241.00-A-
102, are also included within the Appendix of this Report.
The borings were conducted to auger refusal at depths ranging from 8.8 to 18.8 feet below
the existing ground surface. Auger refusal is typically interpreted as the drilling apparatus
encountering the bedrock surface. Hard augering, which is indicative of very dense soil conditions
and/or weathered rock, was encountered at each boring location at depths ranging from 2.0 to 14.0
feet below the existing ground surface. Groundwater was not encountered within any of the boring
locations conducted, to the depths achieved. However, perched water within the FILL materials
was documented at boring locations B-108 and B-109 at depths of 8.0 and 1.5 feet below the
5
existing ground surface, respectively. The total depth of each boring and the conditions
encountered can be observed on the Boring Logs and the Boring Profiles included in Appendix of
this Report.
IV. LABORATORY TESTING
Two (2) representative soil samples recovered during the subsurface investigation were
tested in the laboratory. The laboratory testing conducted on these samples consisted of
classification, in accordance with ASTM D2487, to verify visual classifications and to establish
engineering parameters required for analysis. The tests performed include: Particle Size Analysis
(ASTM D422), Atterberg Limits Determination (ASTM D4318) and Natural Moisture Content (ASTM
D2216). A Unified Soil Classification System (USCS) Group Symbol and ASTM Group Name were
assigned to each soil based upon the laboratory testing. The results of the laboratory testing
conducted are presented in Table I. Gradation curves, numerically and graphically depicting the
results of the analyses, are presented in the Appendix.
TABLE I
LABORATORY TESTING RESULTS
Sample Location B-104 B-107 & B-108
Sample Number S-2. S-3 S-3 & S-3
Sample Depths, ft. 3.0’-6.0’ 6.0’-7.0’ & 5.5’-7.0’
Stratum II I
Atterberg Limits
Liquid Limit Non Plastic 30
Plastic Limit Non Plastic 25
Plasticity Index Non Plastic 5
Natural Moisture Content (%) 14.4 22.2
Unified Soil Classification System (USCS) Group Symbol
ML ML
ASTM Group Name Sandy Silt Silt with Sand
6
V. SUBSURFACE CONDITIONS
A). GEOLOGY
According to the Pennsylvania Department of Conservation and Natural Resources, PA
DCNR Interactive Map, reprinted November 1, 2018, the site is underlain by the Triassic Period
Hammer Creek Formation (Geologic Symbol: Trh) Plate 2, included in the Appendix, shows the
location of the site on a geologic map of the area.
According to the Commonwealth of Pennsylvania, Topographic and Geological Survey,
Engineering Characteristics of The Rocks of Pennsylvania, Fourth (4th) series, Revised 1982, the
Hammer Creek Formation is composed of reddish brown, coarse grained sandstone having
interbeds of red shale and quartz pebble conglomerate. Bedding within this formation is well
bedded, and are thick and massive. Fracturing within this formation is moderately developed and
moderately abundant and occur regularly. The joints have a blocky pattern with displays an open
and steeply dipping. This rock type is moderately resistant, with shales highly weathered to a
moderate depth, and sandstone which weathers less rapidly. The thickness of the overlying soil
mantle is moderately thick. The ease of excavation is considered difficult.
Based upon the conditions observed during the field operation, sandstone bedrock of the
Hammer Creek Formation was determined to exist at this site, along with residual soils resulting
from the weathering of this formation.
B). SOIL / BEDROCK
The soil and weathered rock samples obtained during the field investigation were examined
and classified by EEI, both in the field and in the laboratory. Based upon the classifications and the
laboratory testing conducted, a generalized subsurface profile was developed for this site. One (1)
material designated as FILL and three (3) naturally occurring strata were characterized by EEI to
exist above the sandstone bedrock. Asphalt was encountered at the surface of six (6) boring
locations to depths ranging from 0.6 and 0.8 feet. Beneath the asphalt, a layer of subbase stone
was encountered to total depths ranging from 1.0 to 1.4 feet. The subbase stone can be described
as 2A modified aggregate. Topsoil was encountered at the surface of the remaining four (4) boring
locations to depths ranging from 0.2 to 0.3 feet below the surface. It should be noted that a 0.7 foot
thick layer of remnant topsoil was encountered at boring location B-108 at a depth of 4.8 feet below
the existing ground surface.
7
Cross sections of each testing location, displaying the various strata, as well as other
information obtained from the field investigation, are included within the Appendix on the Boring
Profiles. The testing information is also shown on the Boring Logs. A general description of the
materials encountered is as follows:
FILL
The material designated as FILL is visually described as brown, red brown to gray sandy
clay to silty sand with gravel, concrete fragments, some root fibers and topsoil, and trace slag. The
FILL material was encountered within nine (9) boring locations, excluding B-101. Where
encountered, the FILL material extended to depths ranging from 2.5 to 8.0 feet below the existing
grade.
The SPT (N) values recorded during the sampling of the FILL material ranged from 3 to 43
blows on the sample barrel per foot of penetration. The SPT (N) results indicate that the density of
the FILL material is very loose to dense. The dense portion was encountered at boring location B-
106 and can be attributed to encountering larger rock fragments, slag or concrete contained within
the soil matrix of the FILL material. The very loose portions were encountered just below the topsoil
layer at boring locations B-102, B-103 and B-104. In general, the FILL is medium dense. Based on
the variable composition and density, the FILL material was most likely not placed under
engineering supervision.
STRATUM I
The soil designated as Stratum I is visually described as brown sandy clay to silt with sand.
As determined by laboratory testing, the USCS Group Symbol for a representative sample of this
soil is ML. The assigned ASTM Group Name is Silt with Sand. The Stratum I soil was encountered
within six (6) boring locations. Where encountered, Stratum I extended to depths ranging from 6.0
to 14.0 feet below the existing grade.
The SPT (N) values recorded during the sampling of this soil ranged from 6 to 24 blows on
the sample barrel per foot of penetration. The SPT (N) results indicate that the consistency of the
Stratum I soil is soft to very stiff.
8
STRATUM II
The soil designated as Stratum II is visually described as red brown sandy silt to silty sand
with some gravel. As determined by laboratory testing, the USCS Group Symbol for a
representative sample of this soil is ML. The assigned ASTM Group Name is Sandy Silt. The
Stratum II soil was encountered at seven (7) boring locations. Where encountered, Stratum II
extended to depths ranging from 1.0 to 12.5 feet below the existing grade.
The SPT (N) values recorded during the sampling of this soil ranged from 7 to 34 blows on
the sample barrel per foot of penetration. The SPT (N) results indicate that the density of the
Stratum II soil is loose to dense.
STRATUM III
The material designated as Stratum III is visually described as weathered sandstone in the
form of red brown silty sand to sand and gravel with sandstone fragments. The Stratum III material
was encountered at each boring location, which extended to the conclusion of these borings at
depths ranging from 8.8 to 18.8 feet below the existing grade.
The SPT (N) values recorded during the sampling of this material ranged from 40 blows on
the sampling barrel per foot of penetration to 50 blows with 1 inch of penetration. The SPT (N)
results indicate that Stratum III is in a dense to very dense state.
BEDROCK
Auger refusal was encountered at each boring location at depths ranging from 8.8 to 18.8
feet below the existing ground surface. Auger refusal is typically interpreted as the drilling
apparatus encountering the bedrock surface. The corresponding bedrock elevations, where
encountered, are presented in Table II.
9
TABLE II BEDROCK ELEVATIONS
Boring Location *Surface
Elevation* (Ft.) Depth to Auger
Refusal (Ft.) Bedrock
Elevation (Ft.)
B-101 543.6 11.7 531.9
B-102 452.6 11.6 531.0
B-103 540.9 11.8 529.1
B-104 540.1 11.2 528.9
B-105 539.6 10.7 528.9
B-106 539.1 8.8 530.3
B-107 538.6 15.5 523.1
B-108 538.1 15.2 522.9
B-109 537.8 16.8 521.0
B-110 537.5 18.8 518.7
Note: * The surface elevations for each boring location were determined by utilizing a concrete entranceway area as a reference datum. Based on the provided plans, the entrance way elevation was 539.94 feet.
C). GROUNDWATER
Groundwater was not encountered within any of the testing locations conducted, to the
depths achieved. However, perched water within the FILL materials was documented at boring
locations B-108 and B-109 at depths of 8.0 and 1.5 feet below the existing ground surface,
respectively. Based upon the planned construction and subsurface conditions encountered, it is
anticipated that difficulties associated with groundwater/perched water may be experienced during
construction. If these difficulties occur during construction, the appropriate measures to be taken
for groundwater/perched water control during construction should be determined in the field at the
time of excavation and is the responsibility of the contractor. It should be noted that these
observations were made at the time of the field operations and that groundwater table elevations
may fluctuate with daily, seasonal, and climatic variations.
Also note, even if there is a lack of shallow groundwater that does not eliminate the
possibility of water-related issues, such as surficial instabilities and saturated soils, caused by
precipitation. Dewatering, whether required as a result of groundwater, surface water or
precipitation, is the responsibility of the contractor.
10
VI. GEOTECHNICAL ANALYSIS
The results of the field investigation, supported by laboratory testing, revealed that the
general geotechnical cross-section across this site consists of one (1) FILL material and three (3)
naturally occurring soil strata within the proposed addition footprint. The anticipated finished floor
elevation for the structure is 540.0 feet. Please note the building loads were not made available at
the time of report preparation. However, EEI estimates that the column loads will not exceed 100
kips, nor will the wall loads exceed 3 klf.
Based on the finished floor elevation of 540.0 feet, excavations up to approximately 3.6 feet
and structural fill placement up to 2.5 feet will be required. Based on the borings the existing FILL
materials are variable in both composition and density. Also, a remnant topsoil layer was
encountered at boring location B-108, and topsoil was observed to be mixed with the FILL material
at boring location B-109. Finally, slag was encountered at within the FILL boring location B-106.
Therefore, EEI is recommending a Soil Exchange program be implemented to ensure proper
support of the proposed addition.
A Soil Exchange consists of the complete removal of the existing FILL materials and
remnant topsoil from within the building area containing loose FILL materials and remnant topsoil (if
encountered), and subsequent replacement with controlled, compacted lifts of structural fill. The
lateral and vertical extent of the overexcavation should be field determined at the time of
construction by a qualified representative of the Geotechnical Engineer of Record following the
segregation of all deleterious materials and organics. The removal of the FILL material should
extend a minimum of ten feet (10’) beyond the footprint of the addition.
Following the removal of the FILL materials within the above mentioned area, the
underlying natural soils should be proof-rolled and densified in accordance with the SITE
PREPARATION section of this Report. It is noted that soft/loose existing FILL materials and natural
soils were encountered throughout the investigation at several boring locations. Therefore, over
excavations of the soft/loose material to a firm and stable base may be necessary as well, or these
materials can be stabilized in-place. The Soil Exchange and over excavations should be backfilled
with compacted lifts of structural fill, to the originally proposed subgrade elevation. The structural fill
should be placed and compacted to ninety eight percent (98%) of the material’s maximum dry
density in accordance with ASTM D698. The FILL material as well as implementation of the
11
foundation preparation program must be evaluated by a qualified representative of the Geotechnical
Engineer of Record. The placement of structural fill should be performed immediately after removal
of the FILL materials and commencement of the proof-rolling effort, in order to reduce the time
available for water to collect and infiltrate the open excavations.
It is very important to note that the Soil Exchange will be conducted adjacent to the existing
building. The foundation elevations are not known for the existing building. Utmost care during the
Soil Exchange operation must be taken not to undermine the existing foundations. If the
foundations are undermined, underpinning may be required.
Upon proper implementation of the Soil Exchange program and site preparations, EEI
recommends supporting the anticipated structure utilizing a shallow foundation system, bearing on
the suitably dense, approved FILL materials (areas around B-101 through B-104), natural soils
and/or newly placed structural fill. The following foundation system and soil bearing capacity
recommendations are provided by EEI, in addition to those discussed above:
1. Following implementation of the Soil Exchange program, along with site and
foundation preparation activities, a foundation system consisting of strip and spread footings along with a slab-on-grade floor system is recommended for the proposed addition.
2. The base of the strip and spread foundations should be situated within the suitably dense approved natural soil and/or structural fill placed and compacted as detailed in the FILL AND COMPACTION section of this Report. FILL materials, and/or soft/loose natural soils encountered at the footing bottom elevation should be undercut and replaced with compacted lifts of structural fill, or lean concrete. Alternately, the foundation base can be lowered to the approved soil bearing elevation. Foundations shall not bear on or above FILL materials, soft/loose residual soils and/or remnant topsoil.
3. Following these site preparation recommendations, the foundations should be designed for a maximum allowable bearing capacity of 3,000 psf, if the foundations are situated on the suitably dense, natural soils and/or newly placed structural fill. A minimum eighteen inch (18”) wide strip footing and thirty six inch (36”) spread footing should be utilized for shear and overturning considerations.
12
4. Supported on the suitably dense natural soils, weathered rock, and/or properly placed structural fill, total and differential settlements are estimated not to exceed 1.0 inch. These settlements were calculated using a bearing capacity of 3,000 psf along with the assumed maximum column (100 kips) and wall (3 klf) loads. Angular distortion of the proposed foundation is anticipated to be within the tolerable limits. Should the anticipated loads be different, EEI must be notified so that our recommendations can be reviewed and if necessary revised.
5. The elevation of the base of the new foundations should match the base elevation of the adjacent existing footings. Alternately, foundations bearing at different elevations should be positioned so that the base of the closest points of the adjacent foundation is located a minimum of one horizontal to one vertical (1:1) from each other. Care should be taken not to undermine existing foundations. Should foundations be undermined, underpinning or shoring will be required.
6. The bottom of exterior footings and footings in unheated areas should be placed at least thirty six inches (36”) below the final exterior grade for protection from frost heave.
7. All footing bottoms should be dry, tamped and completely cleaned of loose material or debris immediately prior to the placement of concrete.
8. The actual bearing conditions of the soil at the footing bottom elevation should be confirmed in the field during excavation, by inspection under the supervision of a Professional Engineer qualified in Geotechnical Engineering.
It should be noted that foundation excavation adjacent to the existing building will likely
encounter loose backfill material. Backfill material for exterior foundation walls is often not placed
and compacted under engineering control. Therefore, localized over-excavation adjacent to the
existing building foundation(s) should be anticipated. The extent of the over-excavation should be
field determined at the time of construction by a qualified representative of the Geotechnical
Engineer of Record.
13
VII. FLOOR SLAB RECOMMENDATIONS
Following the site preparations and implementation of the Soil Exchange, floor slabs may be
supported on suitably dense, approved residual soils and/or new structural fill placed and
compacted over approved subgrade soils in accordance with the FILL AND COMPACTION section
of this Report. Due to the possibility of soft/loose existing residual soils, overexcavation and
replacement may be required for proper support of the slab(s).
Floor slabs for the proposed addition may be designed as a slab-on-grade with a
recommended Modulus of Subgrade Reaction value of 150 psi/inch. The subgrade should be
prepared in accordance with the procedures described in this Report. In order to reduce capillary
rise resulting in damp floor slabs, a granular subbase is recommended. The granular subbase will
also provide uniform support distribution between the subgrade soils and the base of the concrete
slab. It is recommended that a minimum of six inches (6”) of clean, coarse-graded aggregate, (such
as PA DOT 2B) be placed and compacted beneath all floor slab areas. The floor slabs should be
suitably reinforced to control shrinkage cracking. Proper joints should be provided at the junction of
the slabs and foundation system so a small amount of independent movement can occur without
causing damage.
Furthermore, from a geotechnical perspective, a vapor retarder/barrier is not required to
address any issues with moisture intrusion from shallow groundwater. The need for a vapor
retarder/barrier from a general construction perspective depends on the floor covering and/or
humidity control requirements in the proposed building spaces. Refer to appropriate documentation
from the Portland Cement Association for guidance on the need and location of a vapor
retarder/barrier. If a moisture sensitive floor covering is used, or the building spaces are not
equipped with humidity control, then a vapor retarder/barrier is recommended. Additionally, the
location of the vapor retarder/barrier would depend on when slab construction is completed with
respect to placement of a water tight roofing system. There is some debate in the industry on the
use and location of vapor retarder/barrier. Regardless, these issues are not of a geotechnical
nature. Therefore, EEI recommends that these issues be evaluated by the Architect and/or
Structural Engineer accordingly, to determine the need for and location of a vapor retarder/barrier.
14
VIII. SITE PREPARATION
EEI performed a cursory analysis of the excavations and fill placements necessary for the
development of this site. Based on a finished floor elevation of 540.0 feet, excavations up to 3.6 feet
and fill placements up to approximately 2.5 feet will be required. Deeper excavations will be
necessary for Soil Exchange, foundation installation, stormwater management construction and
utility installation. Prior to the placement of any required fill, areas extending a minimum distance of
ten feet (10’) beyond each of the building footprint or twice (2X) the fill placement height, whichever
is greater, should generally be stripped of all vegetation, topsoil, root mats, and other deleterious
materials. Following removal of the surface materials and after excavation to the proposed grades,
the building pads should be proof-rolled and compacted. It is recommended that a steel drum
vibratory roller having a minimum static weight of ten (10) tons be utilized for this purpose. Proof-
rolling should be conducted with a minimum of two (2) passes in each direction with a smooth drum
roller in static mode. Proof-rolling and compaction procedures are necessary to densify and verify
the integrity of the upper zones of the soils. The proof-rolling effort will be an important aspect of
the development of this site, as portions of the existing FILL materials and natural soils were
encountered in a soft/ loose state. Due to the soft and loose existing soils encountered during the
field investigation, EEI anticipates that unstable areas will be encountered during the proof-rolling
effort. Any loose or unstable areas encountered during proof-rolling are most likely loose and
unstable due to excessive moisture within the soil matrix. These soils can be aerated and dried in-
place. Following adequate drying time, these soils can be densified in-place. Alternately, any loose
or soft zones of soil can be removed and replaced with structural fill, as outlined in the FILL AND
COMPACTION section of this Report.
The need to excavate and replace the soft materials will be reduced if the development of
the site occurs during periods of dry and warm conditions, such as the summer months. During
these periods, the effectiveness of scarifying and aerating will be greatly enhanced while reducing
the need to over-excavate and replace soft soils. The proof-rolling effort should be observed and
evaluated in the field by a qualified representative of the Geotechnical Engineer of Record.
15
Due to the fine-grained natural soils, it should be noted that repeated construction traffic
across the site will lead to instabilities. Therefore, construction traffic should be limited across the
site. The site should be graded during development to convey surface runoff away from
construction. The work areas should be sealed by rolling on a daily basis to promote runoff.
Careful grading and management of surface water runoff will help minimize disturbance of the
subgrade. Furthermore, it is recommended that all construction areas, including those which were
excavated to achieve the planned subgrade elevation, be proof-rolled immediately prior to the
placement of the subbase stone section and again before installation of any asphalt/concrete
sections. This will allow for soft and weak areas to be identified and remediated prior to the slab
placement and/or pavement construction.
IX. EXCAVATION METHODS
As previously mentioned, excavations up to 3.6 will be required to achieve the proposed
finished floor elevation of 540.0 feet. Deeper excavations will be necessary for implementing the
Soil Exchange, as well as for foundation and utility installation. Based on the borings conducted,
excavations to achieve the proposed grades are expected to occur within the existing FILL
materials, residual soils, weathered rock, and possibly bedrock. Based on the results of the drilling
operation, the existing FILL, Stratum I and Stratum II soils, and upper portions of the Stratum III
weathered rock, will be easy to excavate with conventional equipment and techniques.
Very dense weathered rock, as indicated by high SPT values or hard augering, was
encountered at each boring location, at depths ranging from 1.0 to 14.0 feet. As shown in the
Boring Profiles accompanying this Report, very dense weathered rock (Stratum III) varies across
the site and will be encountered during site grading activities. Table III lists the depths to the very
dense weathered rock and bedrock, as well as the corresponding elevations, at the boring
locations. Additional information regarding the foundations is presented in the GEOTECHNICAL
ANALYSIS section of this Report.
16
TABLE III DEPTHS AND REMOVAL OF VERY DENSE WEATHERED AND BEDROCK ELEVATIONS
Boring Number
1) Surface Elevation,
ft.
2) Proposed Cut Depth
for Foundation Elevation, ft.
Depth to Weathered
Rock, ft.
Weathered Rock
Elevation, ft.
Depth to Bedrock,
ft.
Bedrock Elevation,
ft.
Removal of Weathered
Rock, ft.
Removal of Bedrock, ft.
B-101 543.6 537.0 1.0 542.6 11.7 531.9 5.6 --- B-102 542.6 537.0 7.5 535.1 11.6 531.0 3)Localized ---B-103 540.9 537.0 7.5 533.4 11.8 529.1 --- ---B-104 540.1 537.0 6.0 534.1 11.2 528.9 --- ---B-105 539.6 537.0 7.5 532.1 10.7 528.9 --- ---B-106 539.1 537.0 7.5 531.6 8.8 530.3 --- ---B-107 538.6 537.0 11.5 527.1 15.5 523.1 --- ---B-108 538.1 537.0 12.5 525.6 15.2 522.9 --- ---B-109 537.8 537.0 12.0 525.8 16.8 521.0 --- ---B-110 537.5 537.0 14.0 523.5 18.8 518.7 --- ---
Notes: 1) The surface elevations for each boring location were determined by utilizing a concrete entranceway area as a reference datum. Based on the provided plans, the sill elevation was 539.94 feet. 2) The Proposed Cut Depth Elevation was based on three feet (3’) below the provided finished floor elevation, which correlates to the anticipated foundation elevation. 3) Localized – Indicates very dense weathered rock are within two feet (2’) of the proposed cut depth.
Our evaluation indicates that areas will require removal of up to approximately 5.6 feet of
very dense weathered rock during excavations for the anticipated foundation elevation in the vicinity
of boring location B-101. At boring location B-102 the very dense weathered rock was just below
(within 2’) the anticipated foundation elevation. At this juncture and based on the provided
elevations, bedrock removal is not anticipated.
As noted on the Boring Logs, the borings were advanced through the very dense weathered
rock using six inch (6”) O.D. solid stem augers. However, slow excavation rates are anticipated if
typical excavation equipment (i.e. standard backhoe) is utilized. Improved excavation rates,
specifically within the very dense portions of the weathered materials, will be realized utilizing a late
model, high power track-mounted hoe in lieu of a standard backhoe. In open excavations, the
upper portions of bedrock are expected to be rippable with a late model Caterpillar D-8 Dozer or
equivalent/larger, equipped with a hydraulic ripper. Deeper excavations for utilities are expected to
encounter the bedrock surface. Rock excavation within confined foundation and utility trenches is
expected to require hydraulic hammering, ripping or other rock removal techniques. The final
determination of the rock removal method(s) should comply with all Township regulations and
generally accepted safety guidelines.
17
As required, temporary slopes and support for excavations should be designed and installed
by the contractor in accordance with the Occupational Safety and Health Administration’s (OSHA),
Safety and Health Regulations for Construction, 29 CFR 1926, Subpart P. A competent person as
defined by the aforementioned regulation is required to confirm stability of all excavations during
construction. If required, the design of temporary bracing and shoring by the contractor needs to
consider an active earth pressure and passive earth pressure on the temporary shoring as
appropriate. Effects of any surcharges also need to be considered in the bracing design.
Permanent slopes should be designed at 3 horizontal to 1 vertical or flatter.
In the event that the excavation package for this project is not being bid as “unclassified”, it
may be prudent to include definitions for weathered rock and bedrock, as well as unit costs for
weathered rock and/or bedrock excavation/removal within the contract documents.
X. LATERAL EARTH PRESSURES
The lateral earth pressure coefficients that may be used for designing below grade walls and
retaining walls, if necessary, are shown in Table IV. Retaining walls that are restrained from
deflection should be designed for the at-rest (Ko) condition. Retaining walls that are free to deflect,
such as landscape walls, should be designed for the active (Ka) condition. Considered somewhat
conservative, the earth pressure data for the on-site materials was determined from the soil
classification testing and visual classification of the soil samples, and was compared to generally
accepted and published values for the various properties.
EEI recommends that a drainage system be installed for walls constructed below grade.
The presence of a drainage system will serve to minimize hydrostatic pressures caused by water
trapped against the walls. If adequate drainage is not provided, the walls should be designed to
resist hydrostatic loads. Additionally, consideration should be given to any surcharge loads at the
top of walls.
18
TABLE IV SOIL PROPERTIES FOR THE COMPUTATION OF LATERAL LOADS
STRATUM I FILL &
STRATUM II STRATUM III
Effective Stress Angle of Friction – φ 28.0° 28.0º 32.0º Dry Unit Weight - γd 110.0pcf 115.0pcf 120.0pcf Submerged Unit Weight - γw 47.6pcf 56.6pcf 57.6pcf Rankine Coefficient of Active Earth Pressure - Ka 0.36 0.36 0.31 Rankine Coefficient of Passive Earth Pressure - Kp 2.77 2.77 3.25 Rankine Coefficient of at Rest Earth Pressure - Ko 0.53 0.53 0.47
It should be noted that for the design of a Segmental Retaining Wall (SRW), the National
Concrete Masonry Association (NCMA) suggests that all soil placed within the reinforced zones of
the system have no more than 35% passing the #200 sieve. The soil classifications, conducted by
EEI as part of this investigation, indicate that placement of the Stratum I and Stratum II soils in the
reinforced zone of an SRW (or any MSES) is not permitted. EEI recommends additional laboratory
testing, namely a direct shear test (ASTM D3080), to be conducted on the backfill material for any
proposed SRW system’s reinforced zone after this material is identified. The results of this test may
provide more aggressive soil parameters to be used in retaining wall design, which may effectively
reduce retaining wall cost.
XI. SITE SEISMICITY
The 2009 edition of the International Building Code (IBC) specifies seismic design
requirements applicable to the structural design of the proposed addition to the Adamstown
Elementary School. In particular, Chapter 16, Sections 1613 through 1620 are relevant to this
structural design. This in turn requires that the project site be classified geotechnically as either
“Site Class” A through F based on Table 1613.5.2 of IBC 2009.
19
IBC Table 1613.5.2 SITE CLASS DEFINITIONS
SITE CLASS SOIL PROFILE
NAME AVERAGE PROPERTIES IN TOP 100 FEET, SEE SECTION
1613.5.5
Soil Shear wave velocity, Vs (ft/s)
Standard Penetration
resistance, N
Soil undrained shear strength, Su (psf)
A Hard Rock Vs>5,000 N/A N/A B Rock 2,000<Vs<5,000 N/A N/A
C Very dense soil and soft rock
1,200<Vs<2,500 N>50 Su>2,000
D Stiff soil profile 600<Vs<1,200 15<N<50 1,000<Su<2,000 E Soft soil profile Vs<600 N<15 Su<1,000
E --
Any profile with more than 10 feet of soil having the following characteristics: 1. Plasticity index PI>20 2. Moisture content w>40% and 3. Undrained shear strength Su<500 psf
F --
Any profile containing soils having one or more of the following characteristics: 1. Soils vulnerable to potential failure or collapse under seismic loading such as liquefiable soils, quick and highly sensitive clays, collapsible weakly cemented soils. 2. Peats and/or highly sensitive clays (H>10 feet of peat and/or highly organic clay where H= thickness of soil ) 3. Very high plasticity clays (H>25 with plasticity index PI>75 4. Very thick soft/medium stiff clays (H>120 feet)
For SI: 1 foot = 304.8mm, 1 square foot = 0.0929m2, 1 pound per square foot = 0.0479 kPA, N/A = Not Applicable In this regard, based on a comparison of the criteria of Table 1613.5.2 with the field data
accumulated during the drilling for this site in November, 2018, the project site should be classified
as Site Class “D” for purposes of implementing the IBC 2009 seismic structural design requirement.
According to the IBC 2009, a Site Class “D” indicates a “stiff soil” profile.
XII. FILL AND COMPACTION
A). FILL CRITERIA
Fill material which supports foundations, floor slabs, and pavements, as well as fill for
retaining wall backfill and berm construction, is considered structural fill. Excavations required to
achieve the proposed grades will make the existing FILL materials, Stratum I and Stratum II soils,
and Stratum III weathered rock available for reuse as structural fill material.
20
Based on visual observations, the existing FILL is currently considered unsuitable for use as
structural fill. Any soils or deleterious materials (i.e., metal, wood, organics, etc.) which are
unsuitable for reuse as structural fill should be stockpiled separately, and removed from the site or
placed in non-structural areas. EEI recommends that the FILL material be further evaluated by a
representative of the Geotechnical Engineer of Record at the time of excavation for reuse as
structural fill.
One (1) sample of the Stratum I soil was tested in the laboratory for natural moisture
content. The results yielded a natural moisture content of 22.2 percent. Based on visual
observations, supported by laboratory testing, this material is above optimum moisture content for
the soil type. Therefore, these soils will require time for aerating and drying prior to use as structural
fill. When these soils are encountered during construction, they should be mixed with suitable soils
for re-use or processed with a drying agent, such as lime.
One (1) sample of the Stratum II soil was tested in the laboratory for natural moisture
content. The results yielded a natural moisture content of 14.4 percent. Based on visual
observations, supported by laboratory testing, this material is at optimum moisture content for the
soil type. If moist zones are encountered, they will require time for aerating and drying prior to use
as structural fill.
Visual observations of the Stratum III weathered sandstone indicate that these materials are
suitable for use as structural fill. Rock fragments from weathered rock, and bedrock should be
processed to less than three inches (3”) in size and mixed with suitable soil materials during
placement to provide a well-graded structural fill.
The on-site soils will require careful moisture control as they are sensitive to moisture
changes. Materials stockpiled for use as structural fill should be graded to shed water and rolled to
maintain the soils. During periods of wet site conditions, travel upon the building pads and
construction areas should be limited to minimize disturbance of the subgrade which will lead to
instabilities.
21
Any structural fill imported to the site should meet the following criteria:
Granular soils such as GW, GP, GM, SW, SP or SM as classified by ASTM D2487 are preferred, however soils having soil classifications GC, SC, ML or CL may be acceptable provided the Geotechnical Engineer of Record approves the soil;
the largest particles within the fill should be no greater than three (3) inches in diameter;
not include deleterious materials such as construction debris, wood, glass, ash trash, refuse, roots and other organic matter;
not contain frozen clumps of soil, snow or ice;
have moisture contents within two (2) to three percent (3%) of the soil’s optimum moisture content and
meets the definition of clean fill according to PADEP Management of Fill Policy, Document Number 258-2182-773.
The criteria are provided as a general guideline for soil materials imported to the site. Soil
materials available for use as structural fill should be submitted to the Geotechnical Engineer of
Record for evaluation prior to use at the site.
B). COMPACTION CRITERIA
Structural fill should generally be placed in horizontal lifts not exceeding eight inches (8”) in
loose thickness and compacted with a sheepsfoot or smooth drum vibratory roller with a minimum
static weight of ten (10) tons. Due to the fine grained nature of the upper soils, a sheepsfoot roller
is recommended for this site to aerate the moist soils during placement and compaction. Where
compaction by hand-operated equipment is necessary, structural fill should be placed in minimum
horizontal lifts of six inch (6”) loose thickness. The optimum lift thickness and number of repetitions
necessary to achieve the required percentage compaction values should be determined in the field
with test passes of the chosen compaction equipment. The fill material should be placed at its
optimum moisture content (+/- 2%) as determined in accordance with ASTM D698 and compacted
to a minimum percentage of the maximum dry density as indicated in Table V.
22
TABLE V COMPACTION CRITERIA
Fill Area Percent of Maximum Dry Density as
per ASTM Standard D698 Foundation Support and Slab-on-Grade 98
Paved Areas, Walkways, and Berms 95
Non-Structural 92
XIII. CONSTRUCTION QUALITY CONTROL
As documented within this Report, the proposed construction is anticipated to include
significant earthwork procedures and foundation construction activities. The quality of this work is
an integral part of the development of this site and directly impacts the validity of the
recommendations presented in this Report. Based upon past experience, the most effective and
economical earthwork inspection is obtained through the on-site presence of a qualified
representative of the Geotechnical Engineer of Record during the placement of structural fill and the
installation of structural elements. Therefore, it is recommended that the proof-rolling effort,
excavation and placement of fill, Soil Exchange and verification of the installation of foundation and
slab elements be tested and confirmed by Earth Engineering Incorporated. However, it must be
noted, the presence of any third party Inspection Agency does not relieve the contractor from
responsibility for Means and Methods of construction and proper performance of the components
included in their work scope.
XIV. LIMITATIONS
The conclusions and recommendations contained in this Report are based upon the
subsurface data collected, and on details stated in this Report, as well as the assumption that the
subsurface conditions do not deviate appreciably from those disclosed by the test borings
performed.
Unless specifically indicated to the contrary in this Report, the scope of this Report is limited
only to investigations and evaluation of the geotechnical aspects of the site conditions, and does
not include any consideration of potential site pollution, contamination or other environmental
issues. This Report offers no opinions, conclusions or recommendations related to potential
pollution or contamination of the site.
23
The procedures followed for the subsurface exploration, analysis and conclusion
development have followed generally accepted geotechnical engineering practices, and make no
other warranties, either expressed or implied, as to the professional advice provided under the
terms of EEI’s agreement and included in this Report. The conclusions and recommendations
presented in this Report assume that recognized proper construction practices are followed
throughout construction and that a Professional Engineer qualified in geotechnical engineering will
be retained to oversee the inspection of site preparations, proof-rolling, foundation construction,
implementation of the Soil Exchange, and other critical earthwork operations.
It is important to note that at the time of report preparation, the building loads were not
established. This information is vital to providing a recommended foundation type, as well as
accurate recommendations regarding bearing capacity and settlement estimates. After the loads
are determined, EEI can better establish the foundation design recommendations best suited for the
structure.
It is emphasized that this analysis was made for the proposed addition to Adamstown
Elementary School located in Adamstown Borough, Lancaster County, Pennsylvania. Earth
Engineering Incorporated does not assume any responsibility in using this Report to generate
foundation design other than at the specific site addressed.
Respectfully submitted, EARTH ENGINEERING INCORPORATED
Michael J. Carmosky, SEO Assistant Director ~ Lehigh Valley Division Michael O. Meixell, P.E. Director of Engineering ~ Lehigh Valley Division Paul J Creneti, P.G. Director~ Lehigh Valley Division
G:\PROJECTS\31000\31241.00 - ADAMSTOWN ELEM SCHOOL - LV GEO\REPORT\31241.00 - ADAMSTOWN ES ADDITION REPORT.DOC
APPENDIX
PLATE 1 - TOPOGRAPHIC MAP OF SITE
Visit us at http://www.dcnr.state.pa.us
Created using PA DCNR Map Viewer Copyright 2011 Esri. All rights reserved Terre Hill Quadrangle Map created on Thu Nov 1 2018
PLATE 2 - BEDROCK GEOLOGY MAP OF SITE
Visit us at http://www.dcnr.state.pa.us
Created using PA DCNR Map Viewer Copyright 2011 Esri. All rights reserved Terre Hill Quadrangle Map created on Thu Nov 1 2018
6
29
0.3'
3.9'
6.0'
7.5'
11.8'
B-103EL. 540.9'
Auger RefusalHard Augering
6.0'-11.2'
7
22
3
11
33
0.2'
2.5'
7.5'
11.6'
B-102EL. 542.6'
50/4''
19
50/4''
Auger RefusalHard Augering
7.5'-11.8'
B-104EL. 540.1'
56
4
1.4'
4.0'
7.5'
10.7'
B-105EL. 539.6'
Auger RefusalHard Augering
7.5'-8.8'
6.0'
14
43
24
40
0.8'1.2'
47
0.2'
3.0'
13
11.2'
50/5''
Auger RefusalHard Augering
7.5'-10.7'
0.6'
48
520
Date:
24
32
EL
EV
AT
ION
(fe
et)
544
Geotechnical Engineers & Geologists
EARTHENGINEERINGINCORPORATED
31241.00 A-102
TOPSOIL
540
Project Number: SHEET:F.F.E.= Finished Floor Elevation
F.F.E.=
Lithology Graphics
540.0'
520
522
524
526
528
530
532
534
536
538
540
542
544
522
524
526
528
530
532
534
536
538
542
75
0.2'1.0'
11.7'
B-101EL. 543.6'
50/2''
63/9''
Auger RefusalHard Augering
7.5'-11.6'
16
4.5'
5
50/5''
Subsequent Perched Water Level
ASPHALT
SUBBASE STONE - Gray 2A Modified Aggregate
ADAMSTOWN ELEMENTARY SCHOOLADDITION
STRATUM II - Red Brown Sandy Silt to Silty Sand with SomeGravel
STRATUM III - Red Brown Silty Sand to Sand and Gravelwith Sandstone Fragments (Weathered Sandstone)
Initial Perched Water Level
Auger RefusalHard Augering
2.0'-11.7'
11/14/2018
BORING PROFILESPREPARED FOR
ADAMSTOWN BOROUGH, LANCASTER COUNTY, PENNSYLVANIA
www.earthengineering.com
FILL - Brown, Red Brown to Gray Sandy Clay to Silty Sandwith Gravel, Concrete Fragments, Some Root Fibers andTopsoil, and Trace Slag
1.0'
6.0'
7.5'
15.5'
8.0'
Auger RefusalHard Augering
12.5'-15.2'
26
50/1''
16
14
22
0.7'
12
34
18
6
31
18
1.1'
7.5'
0.6'
5.5'
7.5'
24
8
17
15
Auger RefusalHard Augering
12.0'-16.8'
11.5'
50/4''
4.8'5.0'
50/2''
B-108EL. 538.1'
15.2'
12.5'
69
B-110EL. 537.5'
14.0'
8.0'
1.1'0.7'
18.8'
19
50/1''
14
21
15
24
B-107EL. 538.6'
28
1.5'
STRATUM I - Brown Sandy Clay to Silt with Sand
8.8'
B-106EL. 539.1'
1.2'
Auger RefusalHard Augering
14.0'-18.8'
B-109EL. 537.8'
16.8'
12.0'
6.8'
0.6'
Auger RefusalHard Augering
11.5'-15.5'
14.4 Odor:
% Gravel: Coarse: 5.7 Fine: 6.8 Diameter, mm % Finer
% Sand: Coarse: 4.1 Medium: 13.1 Fine: 9.9 75 100.038.1 100.019.0 94.39.5 91.84.75 87.52.00 83.4
0.425 70.30.150 62.4
0.075 60.4
0.005 NR
0.001 NR
Gs: N/A Cu: N/A Cc: N/A
Project: LL: NP PL: NP PI: NP
Job #:
Client:
Sample:Depth:
Comments:
East Norriton, PA - (610) 277-0880 Central PA: (717) 697-5701 Southern NJ: (856) 768-1001Classification of Soils, ASTM D 2487-00 / D 2488-00
3.0'-6.0'
USCS Classification: ML, Sandy Silt
B-104 / S-2, S-3
AASHTO Classification: A-6
November 21, 2018
№ 200
Hydrometer AnalysisClay Size
Colloids
SAND
Coarse № 10Medium № 40
№ 100
Particle SizeUS Standard Sieve Size
GRAVELCoarse
3"1½"¾"
Fine
FineDilatency: N/R
⅜"№ 4
Stratum II NP - Indicates Sample is Non Plastic
Adamstown Elementary School Addition31241.00
AEM Architects
Cementation: moderate Dry Strength: medium
Reaction to HCl: N/R Toughness: N/R
Structure: homogeneous
Sand Description: rounded, flat pieces, weathered, sandstone, quartz, red, white, brown
Consistency: firm Hardness: N/R
As-rec'd water content: N/R
12.527.1
Gravel Description: rounded, flat pieces, weathered, sandstone, quartz, red, white, brown
3" 1½" ¾" ⅜" №4 №10 №40 №100 №200
0
10
20
30
40
50
60
70
80
90
100
0.010.1110100
Per
cen
t P
assi
ng
Sie
ve
Sieve Opening, mm
Particle Size Analysis of Soils
149 Main Street, Emmaus, PA 18049Tel: 610-967-4540 Fax: 610-967-4488
22.2 Odor:
% Gravel: Coarse: 0.0 Fine: 2.4 Diameter, mm % Finer
% Sand: Coarse: 1.1 Medium: 10.1 Fine: 6.8 75 100.038.1 100.019.0 100.09.5 97.84.75 97.62.00 96.6
0.425 86.50.150 81.6
0.075 79.7
0.005 NR
0.001 NR
Gs: N/A Cu: N/A Cc: N/A
Project: LL: 30 PL: 25 PI: 5
Job #:
Client:
Sample:Depth:
Comments:
East Norriton, PA - (610) 277-0880 Central PA: (717) 697-5701 Southern NJ: (856) 768-1001Classification of Soils, ASTM D 2487-00 / D 2488-00
6.0'-7.0' & 5.5'-7.0'
USCS Classification: ML, Silt with Sand
B-107 & B-108 / S-3 & S-3
AASHTO Classification: A-4
November 21, 2018
№ 200
Hydrometer AnalysisClay Size
Colloids
SAND
Coarse № 10Medium № 40
№ 100
Particle SizeUS Standard Sieve Size
GRAVELCoarse
3"1½"¾"
Fine
FineDilatency: N/R
⅜"№ 4
Stratum I
Adamstown Elementary School Addition31241.00
AEM Architects
Cementation: moderate Dry Strength: medium
Reaction to HCl: N/R Toughness: N/R
Structure: homogeneous
Sand Description: sub-angular, weathered, mica
Consistency: soft to firm Hardness: N/R
As-rec'd water content: N/R
2.418.0
Gravel Description: sub-angular, weathered, mica
3" 1½" ¾" ⅜" №4 №10 №40 №100 №200
0
10
20
30
40
50
60
70
80
90
100
0.010.1110100
Per
cen
t P
assi
ng
Sie
ve
Sieve Opening, mm
Particle Size Analysis of Soils
149 Main Street, Emmaus, PA 18049Tel: 610-967-4540 Fax: 610-967-4488
M
.
D
D
26
25
50
50/2''
50/5''
50/2''
3
13
50/3''
0.7'
11.7
1.0
0.2
BORINGLOG
Hard Augering 2.0'-11.7'NA
-
543.4
S-2
S-3
S-1
sm
sm
sm
531.9
542.6
S-4
-
-
-
Auger Refusal
DEPTH:
EQUIPMENT USED Truck Mounted Drilling Rig - CME 55
WATER:
1
;
START 11/13/18
REMARKS
CHECKED BY: MJC
Geotechnical Engineers & Geologists
0.0'
BLO
WS
/0.5
FT
.O
N S
AM
PLE
R
SA
MP
LE N
O./
TY
PE
/CO
RE
RU
N
TIME:DEPTH:R
EC
OV
ER
Y(F
t.)
DE
PT
H (
FT
)
DEPTH (feet)
PROJECT LOCATION Adamstown Borough, Lancaster County, Pennsylvania
PROJECT NUMBER 31241.00
SURFACEELEV. (FT) 543.6
NOT ENCOUNTERED
H2O
CO
NT
EN
T
DEPTH:
DRILLING METHODS 2 inch O.D. Split Barrel Sampler; 6 inch O.D. Solid Auger
RE
CO
VE
RY
(%)
DESCRIPTION
PROJECT NAME Adamstown Elementary School Addition
DATE: 11/14/2018
DATE:
www.earthengineering.com
TIME:
CASING: SIZE: N/A
DATE:
ELEVATION (feet)
EARTHENGINEERINGINCORPORATED
STRATUM III - Red Brown Sand andGravel with Sandstone Fragments(Weathered Sandstone)
STRATUM II - Red Brown Sandy Silt toSilty Sand
TOPSOIL
OF
;
SHEET
AA
SH
TO
INSPECTOR NAME D. Folk
RQ
D (
%)
END 11/13/18
DATE:
GR
AP
HIC
LO
G
BORING NO. B-101
0.4'
DRILLER NAME/COMPANY Bob Corcoran/Corcoran Drilling Company
1
X
** D = DRY, M = MOIST, W = WET
US
CS
1.5'
4.4
0.0
1.3
2.0
4.0
7.0
8.7
2.2
D
M
M
M
M
50/4''
14
16
17
32
4
5
6
10
5
6
7
8
1
2
3
6
S-1 - PP=1.50 tsf
11.6
7.5
2.5
0.2
Auger Refusal
Hard Augering 7.5'-11.6'
BORINGLOG
542.4
-
PP=Pocket Penetrometer (tsf=tons persquare foot)
S-3 - PP=3.00 tsf
S-5
S-4
S-3
S-2
S-1
sm
ml
ml
ml
cl
531.0
535.1
540.1
-
-
-
-
S-4 - PP=3.25 tsf
US
CS
WATER:
1
;
START 11/13/18
REMARKS
RE
CO
VE
RY
(Ft.
)
DRILLING METHODS 2 inch O.D. Split Barrel Sampler; 6 inch O.D. Solid Auger
S-2 - PP=4.25 tsf
CHECKED BY: MJC
BLO
WS
/0.5
FT
.O
N S
AM
PLE
R
SA
MP
LE N
O./
TY
PE
/CO
RE
RU
N
TIME:DEPTH:
EQUIPMENT USED Truck Mounted Drilling Rig - CME 55
DATE:
DEPTH:
DEPTH (feet)
PROJECT LOCATION Adamstown Borough, Lancaster County, Pennsylvania
PROJECT NUMBER 31241.00
SURFACEELEV. (FT) 542.6
NOT ENCOUNTERED
H2O
CO
NT
EN
T
DEPTH: TIME:
DE
PT
H (
FT
)
DESCRIPTION
PROJECT NAME Adamstown Elementary School Addition
DATE: 11/14/2018
DATE:
www.earthengineering.comGeotechnical Engineers & Geologists
RE
CO
VE
RY
(%)
ELEVATION (feet)
STRATUM III - Red Brown Sandy Silt withSandstone Fragments (WeatheredSandstone)
STRATUM II - Red Brown Sandy Silt toSilty Sand
RQ
D (
%)
TOPSOIL
CASING: SIZE: N/A
0.2'
1.3'
1.0'
0.5'
0.7'
FILL - Red Brown Sandy Clay with Gravel
INSPECTOR NAME D. Folk
OF
DATE:
DRILLER NAME/COMPANY Bob Corcoran/Corcoran Drilling Company
1
X
BORING NO. B-102
** D = DRY, M = MOIST, W = WET
EARTHENGINEERINGINCORPORATED
AA
SH
TO
SHEET
;
END 11/13/18
GR
AP
HIC
LO
G
8.38.0
6.0
4.0
2.0
0.0
23
50/4''D
M
M
M
M
-
12
13
16
32
2
2
4
10
8
9
10
9
1
2
2
3
S-1 - PP=0.75 tsf
11.8
7.5
6.0
3.9
0.3
Auger Refusal
BORINGLOG
540.6 PP=Pocket Penetrometer (tsf=tons persquare foot)
-S-4 - PP=4.25 tsf
S-5
S-4
S-3
S-2
S-1
sm
ml
cl
cl
cl
529.1
533.4
534.9
537.0
-
-
-
Hard Augering 7.5'-11.8'
DESCRIPTION
WATER:
1
;
START 11/13/18
REMARKS
RE
CO
VE
RY
(Ft.
)DEPTH:
GR
AP
HIC
LO
G
S-3 - PP=0.50 tsf
CHECKED BY: MJC
SA
MP
LE N
O./
TY
PE
/CO
RE
RU
N
TIME:DEPTH:
EQUIPMENT USED Truck Mounted Drilling Rig - CME 55
DATE:
US
CS
ELEVATION (feet)DEPTH (feet)
PROJECT LOCATION Adamstown Borough, Lancaster County, Pennsylvania
PROJECT NUMBER 31241.00
SURFACEELEV. (FT) 540.9
NOT ENCOUNTERED
H2O
CO
NT
EN
T
DEPTH: TIME:
DE
PT
H (
FT
)
DRILLING METHODS 2 inch O.D. Split Barrel Sampler; 6 inch O.D. Solid Auger
PROJECT NAME Adamstown Elementary School Addition
DATE: 11/14/2018
DATE:
www.earthengineering.comGeotechnical Engineers & Geologists
BLO
WS
/0.5
FT
.O
N S
AM
PLE
R
RE
CO
VE
RY
(%)
END 11/13/18
STRATUM III - Red Brown Sand andGravel with Sandstone Fragments(Weathered Sandstone)
STRATUM II - Red Brown Sandy Silt toSilty Sand
STRATUM I - Brown Sandy Clay
TOPSOIL
0.5'
1.9'
0.9'
0.4'
0.8'
FILL - Brown Clay with Gravel
EARTHENGINEERINGINCORPORATED
DRILLER NAME/COMPANY Bob Corcoran/Corcoran Drilling Company
OF1
X
BORING NO. B-103
DATE:
INSPECTOR NAME D. Folk
RQ
D (
%)
CASING: SIZE: N/A
AA
SH
TO
SHEET
;
** D = DRY, M = MOIST, W = WET
8.8
8.0
6.0
4.0
2.0
0.0
ML4
3
4
12
S-5
S-4
S-3
S-2
S-1
10
11
11
10
1
2
1
5
-
-
-
sm
ML
DESCRIPTION
1
;
START 11/13/18
REMARKS
RE
CO
VE
RY
(Ft.
)DEPTH:
DRILLING METHODS 2 inch O.D. Split Barrel Sampler; 6 inch O.D. Solid Auger
BLO
WS
/0.5
FT
.O
N S
AM
PLE
R
SA
MP
LE N
O./
TY
PE
/CO
RE
RU
N
TIME:DEPTH:
EQUIPMENT USED Truck Mounted Drilling Rig - CME 55
DATE:
US
CS
ELEVATION (feet)
PROJECT NAME Adamstown Elementary School Addition
-
cl
528.9
534.1
537.1
539.9
DEPTH: TIME:R
EC
OV
ER
Y(%
)
WATER:
sm
DATE: 11/14/2018
DATE:
www.earthengineering.comGeotechnical Engineers & Geologists
CHECKED BY: MJC
DE
PT
H (
FT
)
AA
SH
TO
BORING NO. B-104
OF
DATE:
1.2'
INSPECTOR NAME D. Folk
DRILLER NAME/COMPANY Bob Corcoran/Corcoran Drilling Company
-
25
27
29
24
1.7'
SHEET
;
1.3'
1.0'
1
X
** D = DRY, M = MOIST, W = WET
EARTHENGINEERINGINCORPORATED
RQ
D (
%)
CASING: SIZE: N/A
STRATUM III - Red Brown Sand andGravel with Sandstone Fragments andSome Silt (Weathered Sandstone)
STRATUM II - Red Brown Sandy Silt toSilty Sand with Trace Clay
FILL - Red Brown Sandy Clay with GravelTOPSOIL
6.0
M
D
M
M
M
12
11
36
40
BORINGLOG
S-3 - PP=0.75 tsf
1.5'
3.0
0.2
Auger Refusal
Hard Augering 6.0'-11.2'
END 11/13/18
GR
AP
HIC
LO
G
NOT ENCOUNTERED
11.2
S-2 - PP=2.50 tsf
SURFACEELEV. (FT) 540.1
S-1 - PP=0.50 tsf
PROJECT NUMBER 31241.00
PP=Pocket Penetrometer (tsf=tons persquare foot)
PROJECT LOCATION Adamstown Borough, Lancaster County, Pennsylvania
DEPTH (feet)
H2O
CO
NT
EN
T
2.0
10.0
8.0
4.0
0.0
6.0
50/5'' M
M
M
M
M
-
18
22
26
24
6
9
23
21
12
12
12
14
5
6
10
11
S-1 - PP=4.00 tsf
10.7
7.5
4.0
1.4
0.6
Auger Refusal
BORINGLOG
539.0PP=Pocket Penetrometer (tsf=tons persquare foot)
-
S-3 - PP=4.25 tsf
S-6
S-4
S-3
S-2
S-1
sm
sm
ml
ml
ml
528.9
532.1
535.6
538.2
-
-
-
Hard Augering 7.5'-10.7'
DESCRIPTION
WATER:
1
;
START 11/12/18
REMARKS
RE
CO
VE
RY
(Ft.
)DEPTH:
GR
AP
HIC
LO
G
S-2 - PP=4.50 tsf
CHECKED BY: MJC
SA
MP
LE N
O./
TY
PE
/CO
RE
RU
N
TIME:DEPTH:
EQUIPMENT USED Truck Mounted Drilling Rig - CME 55
DATE:
US
CS
ELEVATION (feet)DEPTH (feet)
PROJECT LOCATION Adamstown Borough, Lancaster County, Pennsylvania
PROJECT NUMBER 31241.00
SURFACEELEV. (FT) 539.6
NOT ENCOUNTERED
H2O
CO
NT
EN
T
DEPTH: TIME:
DE
PT
H (
FT
)
DRILLING METHODS 2 inch O.D. Split Barrel Sampler; 6 inch O.D. Solid Auger
PROJECT NAME Adamstown Elementary School Addition
DATE: 11/14/2018
DATE:
www.earthengineering.comGeotechnical Engineers & Geologists
BLO
WS
/0.5
FT
.O
N S
AM
PLE
R
RE
CO
VE
RY
(%)
END 11/12/18
STRATUM III - Red Brown Sand andGravel with Sandstone Fragments(Weathered Sandstone)
STRATUM II - Red Brown Sandy Silt toSilty Sand
FILL - Red Brown to Gray Sandy Silt withGravel and Trace Root Fibers
ASPHALT (7'')
0.4'
1.7'
1.4'
0.4'
1.2'
SUBBASE STONE - Gray 2A ModifiedAggregate
EARTHENGINEERINGINCORPORATED
DRILLER NAME/COMPANY Bob Corcoran/Corcoran Drilling Company
OF1
X
BORING NO. B-105
DATE:
INSPECTOR NAME D. Folk
RQ
D (
%)
CASING: SIZE: N/A
AA
SH
TO
SHEET
;
** D = DRY, M = MOIST, W = WET
9.49.0
7.0
5.0
3.0
1.0
S-4
S-3
S-2
S-1
1.2'
0.8'
0.9'
1.0'
BORINGLOG
4
6
8
8
-
-
-
-M
M
M
PP=Pocket Penetrometer (tsf=tons persquare foot)
16
17
23
50/2''
3
10
14
13
5
23
20
6
M
8.8
ml
sm
gm
sm
530.3
531.6
534.6
537.9
7.5
4.5
1.2
0.8
Auger Refusal
S-4 - PP=4.25 tsf
Hard Augering 7.5'-8.8'
S-1 - Slag Observed within SampleBarrel
538.3
DATE:
EQUIPMENT USED Truck Mounted Drilling Rig - CME 55
DATE:
DATE: 11/14/2018
PROJECT NAME Adamstown Elementary School Addition
GR
AP
HIC
LO
G
END 11/12/18
;
SHEET
www.earthengineering.com
RE
CO
VE
RY
(Ft.
)
Geotechnical Engineers & Geologists
CHECKED BY: MJC
DRILLING METHODS 2 inch O.D. Split Barrel Sampler; 6 inch O.D. Solid Auger
WATER:
1
;
START 11/12/18
DEPTH: TIME:DEPTH:
ELEVATION (feet)
DESCRIPTION
BLO
WS
/0.5
FT
.O
N S
AM
PLE
R
SA
MP
LE N
O./
TY
PE
/CO
RE
RU
N
DE
PT
H (
FT
)
REMARKS
STRATUM III - Silty Sand with Gravel andSandstone Fragments (WeatheredSandstone)
CASING: SIZE: N/A
AA
SH
TO
** D = DRY, M = MOIST, W = WET
STRATUM I - Brown Sandy Clay
FILL - Brown to Gray Sandy Silt withGravel and Slag
SUBBASE STONE - Gray 2A ModifiedAggregate
ASPHALT (9'')
OF
RE
CO
VE
RY
(%)
TIME:DEPTH:
H2O
CO
NT
EN
T
INSPECTOR NAME D. Folk
NOT ENCOUNTEREDDATE:
RQ
D (
%)
SURFACEELEV. (FT) 539.1
EARTHENGINEERINGINCORPORATED
PROJECT NUMBER 31241.00
BORING NO. B-106
PROJECT LOCATION Adamstown Borough, Lancaster County, Pennsylvania
DEPTH (feet)
DRILLER NAME/COMPANY Bob Corcoran/Corcoran Drilling Company
1
X
US
CS
3.0
8.8
5.0
1.0
7.0
3
6
6
8
-
50/1''
10
18
16
15
6
19
12
15
M
7
9
9
9
M
-
-
-
-
1.0
2
2
4
4
537.90.7
Auger Refusal
Hard Augering 11.5'-15.5'
S-3 - PP=0.25 tsf
S-2 - PP=2.75 tsf
S-1 - PP=2.50 tsf
PP=Pocket Penetrometer (tsf=tons persquare foot)
D
M
M
M
ML
-
STRATUM I - Brown Sandy Clay to Siltwith Sand
S-6
S-5
S-4
S-3
S-2
S-1
gm
sm
gm
ml
ml
523.1
527.1
531.1
532.6
537.6
;
START 11/12/18
REMARKS
RE
CO
VE
RY
(Ft.
)DEPTH:
ELEVATION (feet)
DESCRIPTION
SHEET
6.0
TIME:DEPTH:
EQUIPMENT USED Truck Mounted Drilling Rig - CME 55
DATE:
US
CS
GR
AP
HIC
LO
G
END 11/12/18
;
BLO
WS
/0.5
FT
.O
N S
AM
PLE
R
PROJECT NAME Adamstown Elementary School Addition
BORINGLOG
DEPTH (feet)
PROJECT LOCATION Adamstown Borough, Lancaster County, Pennsylvania
PROJECT NUMBER 31241.00
SURFACEELEV. (FT) 538.6
NOT ENCOUNTERED
H2O
CO
NT
EN
T
DEPTH: TIME:R
EC
OV
ER
Y(%
)
1
WATER:
DATE: 11/14/2018
DATE:
www.earthengineering.comGeotechnical Engineers & Geologists
CHECKED BY: MJC
DRILLING METHODS 2 inch O.D. Split Barrel Sampler; 6 inch O.D. Solid Auger
DE
PT
H (
FT
)
ASPHALT (8'')
0.1'
SUBBASE STONE - Gray 2A ModifiedAggregateFILL - Red Brown to Brown Sandy Siltwith Trace Clay
SA
MP
LE N
O./
TY
PE
/CO
RE
RU
N
STRATUM III - Red Brown Sand andGravel with Sandstone Fragments andSome Silt (Weathered Sandstone)
AA
SH
TO
7.5
11.5
15.5
0.8'
0.9'
0.7'
1.5'
0.7'
1
STRATUM II - Red Brown Sandy Silt toSilty Sand
EARTHENGINEERINGINCORPORATED
** D = DRY, M = MOIST, W = WET
RQ
D (
%)
CASING: SIZE: N/A
DRILLER NAME/COMPANY Bob Corcoran/Corcoran Drilling Company
BORING NO. B-107
OF
X
INSPECTOR NAME D. Folk
DATE:
9.0
7.0
5.0
3.0
1.0
13.013.1
11.0
6
7
8
9
-
.
W
50/2''
M
6
8
9
10
3
3
5
6
7
10
14
13
3
11
7
8
-
0.6
Auger Refusal
Hard Augering 12.5'-15.2'
S-5 - PP=3.25 tsf
*Perched Water @ 8.0' (4hr.)
S-4 - PP=3.50 tsf
S-3 - PP=3.00 tsf
S-2 - PP=1.75 tsf
S-1 - PP=3.75 tsf
PP=Pocket Penetrometer (tsf=tons persquare foot)
STRATUM I - Brown Sandy Clay to Siltwith Sand
M
537.5
-
NA
M
M
-
S-6
S-5
S-4
S-3
S-2
S-1
ml
ml
cl
ml
522.9
525.6
530.6
532.6
533.3
537.0
-
-
START 11/12/18
REMARKS
RE
CO
VE
RY
(Ft.
)DEPTH:
ELEVATION (feet)
DESCRIPTION
BLO
WS
/0.5
FT
.O
N S
AM
PLE
R
1
WATER: TIME:
1.1
EQUIPMENT USED Truck Mounted Drilling Rig - CME 55
DATE:
US
CS
GR
AP
HIC
LO
G
END 11/12/18
;
SHEET
AA
SH
TO
SA
MP
LE N
O./
TY
PE
/CO
RE
RU
N
ML
BORINGLOG
DEPTH (feet)
PROJECT LOCATION Adamstown Borough, Lancaster County, Pennsylvania
PROJECT NUMBER 31241.00
SURFACEELEV. (FT) 538.1
NOT ENCOUNTERED
H2O
CO
NT
EN
T
DEPTH: *8.0 TIME: 4 hr.;
DE
PT
H (
FT
)
DEPTH:
PROJECT NAME Adamstown Elementary School Addition
DATE: 11/14/2018
DATE:
www.earthengineering.comGeotechnical Engineers & Geologists
CHECKED BY: MJC
DRILLING METHODS 2 inch O.D. Split Barrel Sampler; 6 inch O.D. Solid Auger
RE
CO
VE
RY
(%)
1.5'
RESIDUAL TOPSOIL
INSPECTOR NAME D. Folk
FILL - Red Brown Sandy Silt with Gravel
ASPHALT (7'')
STRATUM III - Red Brown Sand andGravel with Sandstone Fragments(Weathered Sandstone)
0.0'
0.7'
1.0'
0.8'
1.8'
SUBBASE STONE - Gray 2A ModifiedAggregate
1
STRATUM II - Red Brown Sandy Silt toSilty Sand
CASING: SIZE: N/A
RQ
D (
%)
EARTHENGINEERINGINCORPORATED
4.8
DRILLER NAME/COMPANY Bob Corcoran/Corcoran Drilling Company
BORING NO. B-108
OF
DATE: 11/12/2018
** D = DRY, M = MOIST, W = WET
7.5
15.2
5.5
12.5
5.0
13.2
1.0
13.0
11.0
9.0
7.0
3.0
8
10
12
16
50/4''
8
7
8
11
-
5
8
6
23
M
6
16
10
12
-
-
-
S-5 - PP=2.50 tsf
8
8
8
12
S-4 - PP=2.25 tsf
S-3 - Some Topsoil Observed @ 6.5'
S-3 - PP=2.75 tsf
*Perched Water @ 5.0' (Encountered)
S-1 - PP=2.00 tsf
* Perched Water @1.5' (4hr.)
PP=Pocket Penetrometer (tsf=tons persquare foot)
BORINGLOG
M
537.2
M
M
W
W
-
S-6
S-5
S-4
S-3
S-2
S-1
-
gm
cl
cl
ml
sm
ml
521.0
525.8
531.0
536.6
START 11/12/18
REMARKS
RE
CO
VE
RY
(Ft.
)DEPTH:
ELEVATION (feet)
DESCRIPTION
BLO
WS
/0.5
FT
.O
N S
AM
PLE
R
AA
SH
TO
WATER:
Hard Augering 12.0'-16.8'
DEPTH: *5.0'
EQUIPMENT USED Truck Mounted Drilling Rig - CME 55
DATE:
US
CS
GR
AP
HIC
LO
G
END 11/12/18
;
SHEET
SA
MP
LE N
O./
TY
PE
/CO
RE
RU
N
DEPTH (feet)
PROJECT LOCATION Adamstown Borough, Lancaster County, Pennsylvania
PROJECT NUMBER 31241.00
SURFACEELEV. (FT) 537.8
NOT ENCOUNTERED
H2O
CO
NT
EN
T
DEPTH: *1.5 TIME: 4 hr.R
EC
OV
ER
Y(%
)
DE
PT
H (
FT
)
;
PROJECT NAME Adamstown Elementary School Addition
1
DATE: 11/14/2018
DATE: 11/12/2018
www.earthengineering.comGeotechnical Engineers & Geologists
CHECKED BY: MJC
DRILLING METHODS 2 inch O.D. Split Barrel Sampler; 6 inch O.D. Solid Auger
TIME: 0.25 hr.
1.2'
STRATUM I - Brown Sandy Clay
SUBBASE STONE - Gray 2A ModifiedAggregate
0.2'
STRATUM III - Red Brown Sand andGravel with Sandstone Fragments andSome Silt (Weathered Sandstone)
Auger Refusal
0.6
1.2
6.8
12.0
1.3'
0.8'
0.5'
1.0'
FILL - Brown to Gray Sandy Silt withGravel, Concrete Fragments and SomeTopsoil
16.8
** D = DRY, M = MOIST, W = WET
ASPHALT (7'')
CASING: SIZE: N/A
RQ
D (
%)
BORING NO. B-109
INSPECTOR NAME D. Folk
DATE: 11/12/2018
EARTHENGINEERINGINCORPORATED
OF1
DRILLER NAME/COMPANY Bob Corcoran/Corcoran Drilling Company
9.0
7.0
5.0
3.0
1.0
13.013.3
11.0
D
M
NA
M
M
M
M
.
BORINGLOG
50/1''
14
19
50
9
9
10
15
6
6
8
10
30
13
8
7
15
13
11
20
-
-
-
-
-
-
-
3
13
15
17
gmS-7
S-6
S-5
S-4
S-3
S-2
S-1
sm
cl
sm
ml
ml
518.7
523.5
529.5
536.4
536.8
EARTHENGINEERINGINCORPORATED
GR
AP
HIC
LO
G
US
CS
DATE:
EQUIPMENT USED Truck Mounted Drilling Rig - CME 55
TIME:
SA
MP
LE N
O./
TY
PE
/CO
RE
RU
N
BLO
WS
/0.5
FT
.O
N S
AM
PLE
R
DESCRIPTION
ELEVATION (feet)
DEPTH:
** D = DRY, M = MOIST, W = WET
X
1
END 11/12/18
RE
CO
VE
RY
(Ft.
)DATE:
INSPECTOR NAME D. Folk
AA
SH
TO
SHEET
;
BORING NO. B-110
H2O
CO
NT
EN
T
PROJECT NAME Adamstown Elementary School Addition
DE
PT
H (
FT
)
RE
CO
VE
RY
(%)
DEPTH:
DEPTH:NOT ENCOUNTERED
SURFACEELEV. (FT) 537.5
PROJECT NUMBER 31241.00
PROJECT LOCATION Adamstown Borough, Lancaster County, Pennsylvania
DEPTH (feet)
TIME:
DRILLING METHODS 2 inch O.D. Split Barrel Sampler; 6 inch O.D. Solid Auger
DRILLER NAME/COMPANY Bob Corcoran/Corcoran Drilling Company
REMARKS
START 11/12/18
;
1
DATE: 11/14/2018CHECKED BY: MJC
Geotechnical Engineers & Geologistswww.earthengineering.com
DATE:WATER:
0.0'
1.5'
0.1'
OF
0.7'
ASPHALT (8'')
SUBBASE STONE - Gray 2A ModifiedAggregateFILL - Red Brown to Gray Sandy Silt withGravel
STRATUM I - Brown Sandy Clay
14.0
PP=Pocket Penetrometer (tsf=tons persquare foot)
S-1 - PP=3.00 tsf
S-2 - PP=3.25 tsf
S-3 - PP=2.25 tsf
Hard Augering 14.0'-18.8'
Auger Refusal
0.7
1.5'8.0
0.5'
18.8
1.2'
1.1
STRATUM III - Red Brown Sand andGravel with Sandstone Fragments andSome Silt (Weathered Sandstone)
CASING: SIZE: N/A
RQ
D (
%)
13.0
18.1
14.5
11.0
9.0
7.0
5.0
3.0
18.0
1.0
INCHES
3/4"-3.0"
and
3.0"-12.0"
Loose
3/16"-3/4"
Dense
Clean Gravels (Less than 5% fines)
Over 50
> 12"
some
Clayey sands, sand-clay mixtures
Poorly-graded gravels, gravel-sand mixtures, littleor no fines
Well-graded gravels, gravel-sand mixtures, little orno fines
(more than 50% of material is larger than No. 200 sieve size)
(50% or more of material is smaller than No. 200 sieve size)
GC
SW
CLAY
Silty sands, sand-silt mixtures
SILT
SC
OL
Clayey gravels, gravel-sand-clay mixtures
CL
ML
soils; fine grained soils usually soft or very soft; granular soils exhibit no apparent cohesion
Silty gravels, gravel-sand-silt mixtures
SP
31 - 50
Moist
GeneralClassification
DESCRIPTIONSYMBOL
Slight moisture perceptible by touch; fine grained soils are usually firm;
No visible free water; sample may be cool to the touch; at or above optimum moisture;
Dr
>30
Damp
(tons/sq.ft.)
W
Dry
Very dense
Medium dense
Very loose
APPARENTDENSITY
SPT# Blows/ft
Da
No. 10
trace
Passing #200 Seive
Passing #200 Seive
#200 Seive-#40 Seive
#40 Seive-#10 Seive
KEY TO LOG OFBORINGS
AASHTO SOIL CLASSIFICATION
CONSISTENCY - FINE-GRAINED SOIL
PERCENT OR
little
silty soilsgravel and
sandSignificant Constituent
Materials
Sieve AnalysisPercent Passing
No. 40
Unconfined Compressive Strength
11 - 30
SANDS
Liquid limit50% or greater
COARSE-GRAINED SOILS
Inorganic silts, micaceous or diatomaceous finesandy or silty soils, elastic silts
Inorganic clays of low to medium plasticity, gravellyclays, sandy clays, silty clays, lean clays
SILTSANDCLAYS
Liquid limit lessthan 50%
SILTSANDCLAYS
50% or more ofcoarse fractionsmaller thanNo. 4 sieve
size
More than 50%of coarse
fraction largerthan No. 4sieve size
ASTM D 422-63 AND ASTM D2487-92
Peat and other highly organic soils
FINE-GRAINED SOILS
Well-graded sands, gravelly sands, little or nofines
COMPONENT NAME FOR VARIOUS
GRAVELS
Inorganic silts and very fine sands, rock flour, silty orclayey fine sands or clayey silts with slight plasticity
UNIFIED SOIL CLASSIFICATION AND SYMBOL CHART
Inorganic clays of high plasticity, fat clays
Gravels with fines (More than 12% fines)
Clean Sands (Less than 5% fines)
Sands with fines (More than 12% fines)
Organic silts and organic silty clays of low plasticity
35 max
Coarse SAND
Medium SAND
Fine SAND
OH
PT
Geotechnical Engineers & Geologists
EARTH
ENGINEERING
INCORPORATED
20 - 35%
www.earthengineering.com
GW
GM
SMSOIL MOISTURE
M
PROPORTION OF SOIL
51 max
PARTICAL SIZE RANGES
MH
3/32"-3/16"
Fine GRAVEL
Coarse GRAVEL
COBBLE
BOULDER
0 - 10%
COMPONENT NAME
GP
Organic clays of medium to high plasticity, organicsilts
35 max
Poorly graded sands, gravelly sands, little or nofines
0 - 4
CH
CONSISTENCY
COARSE-GRAINED SOILRELATIVE DENSITY
RELATIVEAMOUNT
DESCRIPTION
10 - 20%
Visible free water; usually soil is below water table; contains significantly more mosture than moist
HIGHLY ORGANICSOILS
granular soils have very little apparent cohesion
> 4.0
2 - 4
A-1-b
SPT# Blows/ft
A-2-4
Absence of moisture; dusty; completely dry to the touch
< 0.25
0.25 - 0.50
1.0 - 2.0
<2
40 max
Silt-Clay Materials(More than 35% of total sample
passing No. 200 sieve size)
6 max
finesand
Granular Materials(35% or less of total sample passing No. 200 sieve size)
NP
A-1-a
35 max
silty and clayeygravel and sand
10 max
36 min 36 min 36 min
A-2-5
35 maxNo. 200
5 - 10
Extruded between fingers when squeezed
Very stiff
Stiff
Medium stiff
Soft
Very soft
0.50 - 1.0
Molded by light finger pressure
Field Test
Molded by strong finger pressure
Readily indented by thumb but penetrated only with great effort
Readily indented by thumbnail
Indented with difficulty by thumbnail
41 min
granular soils might exhibit slight apparent cohesion
Hard
Plastic Index, Ip
Liquid Limit, wi
Characteristics ofFraction Passing
Wet
10 max
No. 40
41 min40 max
10 max
50 max
30 max
41 min
35 - 50%
2.0 - 4.0
GroupClassification
16 - 30
MOISTURE
10 max 36 min15 max
A-7-5A-7-6
A-2
11 min
9 - 15
11 min 11 min10 max
A-5 A-7
A-2-6 A-2-7
11 min
41 min40 max
A-4 A-6
5 - 8
40 max
A-3A-1
50 max
25 max
clayey soils