foundation ii
TRANSCRIPT
-
7/25/2019 Foundation II
1/4
Bahir Dar University Faculty of Engineering Department of Civil Engineering
1
Lecture Note (Amsalu G.) Academic Year: 2005/2006
CH PTER TWO
PILE FOUND TION
1. Design a pile foundation for the following soil profile and column load at foundation level.
Solution: The following assumptions are made for the soil data to compute individual pile
capacity
Kpa19.6)3/30*2tan(*1*2*17*2
1tan
2
1
1
skh
Note ve value as there may be consolidation
negative skin friction
Kpa75.332
150*45.0
2
qc u
2
Kpa5.672
300*45.0
2
qc
u
3
Individula pile capacity:
Consider the depth of imbedment to be below 10m, specifically at 13m (arbitrary), and pile
diameter of 400mm, thusSkin Friction
1(Kpa)=-6.19 2(Kpa)=33.75 3(Kpa)=68 4(Kpa)=
L1(m)=2 L2(m)=8 L3(m)=3 L4(m)=
Perimeter =pD = 1.26Qalls(KN)= 281.32
Bearing pressure
Qub(KN)= CNc* Base area=(9*C)*Base area
Qub(KN)= 169.65 Qallb(KN)= 84.82
Total Single Pile Capacity (From soil)
Qall(KN)= Qalls + Qallb = 366.15
Perimet*2)FS(
LLLLL
55443322
11all
Q
Fi l l
C = 0 , = 3 0 = 1 7 . 0 K N / m
3
+ 0 . 0 m
- 2 . 0 m
St i f f c l ay
q = 1 5 0 K P a ,
= 1 7 . 0 K N / m- 1 0 . 0 m3u
- 2 0 . 0 mu 3
- 3 0 . 0 m
F i g u r e a : S o i l D a t au lt
B a s a l t
q = 1 0 ,0 0 0 K P a
St i f f c l ay
q = 3 0 0 K P a ,
= 1 9 . 0 K N / m
o
3
D e n s e S a n d
= 3 0
= 1 9 . 0 K N / m
M = 3 00 K N mx
yM = 2 00 K N m
4 0 0 m m
600m
m x
y
F i g u r e b : L o a d D a t a
P = 2 0 0 0 K N
Use
Concrete C-30
Steel S-300
F i l l
C = 0 , = 3 0
= 1 7 . 0 K N / m3
+ 0 . 0 m
- 2 . 0 m
S t i f f c l a y
q = 1 5 0 K P a ,
= 1 7 . 0 K N / m- 1 0 . 0 m3u
- 2 0 . 0 m
S t i f f c l a y
q = 3 0 0 K P a ,
= 1 9 . 0 K N / mu 3
D e n s e S a n d
= 3 0
= 1 9 . 0 K N / m3
- 3 0 . 0 m
o
B a s a l t
q = 1 0 , 0 0 0 K P au lt
A s s u m e
/3
K = 1 . 0
A s s u m e
A s s u m e
s
P
1
2
3q
b u
-
7/25/2019 Foundation II
2/4
Bahir Dar University Faculty of Engineering Department of Civil Engineering
2
Lecture Note (Amsalu G.) Academic Year: 2005/2006
From concrete capacity: fcd=0.67fck/1.5=13.4MPa
Pall= Area*fcd= p(0.2)2*13400=1683.9KN; Hence soil strength governs. Pall=366.15KN
Number and spacing of piles
It can be easily estimated (from load and single pile capacity) that using 8 piles under a pile cap
is reasonable. A pile spacing of 3d can be adopted (EBCS 7). Thus s=3d=3*400=1200mm. The
pile cap shall be extended by 500mm (=300+d/2) from centerlines of exterior piles. Thus pilearrangement will be as shown below.
Now we can determine the load carried by each pile.
2222222
2
y
2
x
i
2.88m6.08x;14.4m6.08.14y
x
xM
y
yM
n
PP
P =2000+pile cap weight (assuming 500mm thickness)=2127KN
88.2
200x
4.14
300y
8
2127P
i
Pi x y Value Pi x y Value
PA1 -0.6 1.8 261.7 PC1 -0.6 -0.6 211.7
PA2 0.6 1.8 345.0 PC2 0.6 -0.6 295.0
PB1 -0.6 0.6 236.7 PD1 -0.6 -1.8 186.7
PB2 0.6 0.6 320.0 PD2 0.6 -1.8 270.0 Thus Pmax=345KN < Pall=366.15KN OK! (8 piles would be enough)
Check pile group capacity
Pile group capacity is considered for the right figure.
Thus Pug=fsuLi P +qbu Ab- i hi APall g= fsallLi P +qball Ab- i hi A
First lets evaluate qbu:
qbu= CNc = 150*9 = 1350Kpa
qball=1350/2=675Kpa
Group perimeter, P =2*(1.6+4) =11.2m;
2127KNP5374.5KN1452.84320.02507.34P
)6.1*4(*3*198*172*17)6.1*4(*6752.11*2
3*67.58*33.752*6.19-P
appliedug
ug
Design of Pile Cap
Try a thickness D = 500mm
d = D-100-75 = 325mm (See Fig 2.16)
a.Check wide beam shear:
i) along the long direction (Sec L-L)
1189.17KPa0.325*2.2
850.26
db
P v
26.850PP400
175PPP
w
w
B2B1A2A1w
KN
;501f0.3ctdall
v 1.28MPa)5.1(
f0.35f0.005;Assume
c
ck
ctd
0 .6
0 .4
0. 5
0. 5
1 .2
1 .2
1 .2
1 .20 .5 0 .5
y
x
1 2
A
B
C
D
4 .6
2 .2
0 .4
0 .61
2
0 .2
0 .2
1 .2
1 .2 1 .2 1 .20 .20 .2
CD
B A
4 m
1.6m
4 .61 .2 0 .6
1 .2
0 .5
1
0 .4
2
D
C
1 .2
0 .5
2 .2
0 .5
y
1 .2
x
0 .5
B
A
dd
LL
S
S
-
7/25/2019 Foundation II
3/4
Bahir Dar University Faculty of Engineering Department of Civil Engineering
3
Lecture Note (Amsalu G.) Academic Year: 2005/2006
D.increase480Kpawall
vv
Let D = 750mm d=750-100-75 = 575mm
OK!KPa6.4790.575*2.2
606.7
7.606PPP
allw
A2A1w
vv
KN
Therefore use pile cap which is 750mm thick
ii) along the short direction (Sec S-S)
OK!KPa42.330.575*4
76.88
88.76PPPP400
25P
allw
2D2C2B2Aw
vv
KN
b.Check punching shear:
Critical section is at d/2 from face of support (see fig right!)
It can be shown that about 7.24% support is contributed
from each pile reaction to resist punching. Thus,
600mmdand775mmDuseTherefore
OK!765.4KPa6.0*1.20.12
P
2020.65KNPPPP100
101272P
775mmDUseD!Increase800Kpa5010.5f
12.8290575*1.1750.9752
P
2050KNPPPP100
24.71272P
PPPP100
24.7PP
pu
pu
2C1C2B1Bpu
ctdpall,
pu
pu
2C1C2B1Bpu
2C1C2B1Bappliedpu
v
v
Kpav
Reinforcement
a) In the long direction:
Critical section is at the face of the column
300,-Sand30-Cwithand64.360.6*2.2
1063.11
bd
MK
mKN11.10633.0*PP5.1*PPM
22
u
m
B2B1A2A1max
Km= 36.64
K s= 4.08 As(mm2)= 7224.01
# 24= 16.0 Use 16bars in the long direction; better to use more bars directly above the piles.
b) In the short direction:
mKN70.12300.1*PPPPMD2C2B2A2max
Km= 27.26
K s= 3.99 As(mm2)= 8189.514
# 24= 18.1
Use 18bars in the short direction; better to use more bars directly above the piles.
0 .6
0 .4
0 .5 d
C
B
1 2
0 .5 d
0 . 4 + d = 9 7 5 m m
0.6+
d=11
75m
m
4 .61 .2 0 .6
1 .2
0 .5
1
0 .4
2
D
C
1 .2
0 .5
2 .2
0 .5
y
1 .2
x
0 .5
B
A
dd
LL
S
S
-
7/25/2019 Foundation II
4/4
Bahir Dar University Faculty of Engineering Department of Civil Engineering
4
Lecture Note (Amsalu G.) Academic Year: 2005/2006
Design of Pile shaft
Asmin=0.008Ac =1005mm2. # 16 = 5. Use 6 16 as it is circular shaft and a minimum of 6
bars are needed. Use spiral tie with a pich of
4 .6
2 .2
0 .5
1 .2
1 .2
1 .2
0 .5
0 .5 1 .2 0 .5
a
b
Se c t ion A -A
a 1 8 2 4 , L = 3 2 6 0
6 0 06 0 0
2 0 6 0
6 3 5
6 3 5
16
24,L
=
5730
b
4460
4 24
5 24
5 24
4 2 4
8
24
8
24