foundation ii

Upload: haileab

Post on 28-Feb-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 Foundation II

    1/4

    Bahir Dar University Faculty of Engineering Department of Civil Engineering

    1

    Lecture Note (Amsalu G.) Academic Year: 2005/2006

    CH PTER TWO

    PILE FOUND TION

    1. Design a pile foundation for the following soil profile and column load at foundation level.

    Solution: The following assumptions are made for the soil data to compute individual pile

    capacity

    Kpa19.6)3/30*2tan(*1*2*17*2

    1tan

    2

    1

    1

    skh

    Note ve value as there may be consolidation

    negative skin friction

    Kpa75.332

    150*45.0

    2

    qc u

    2

    Kpa5.672

    300*45.0

    2

    qc

    u

    3

    Individula pile capacity:

    Consider the depth of imbedment to be below 10m, specifically at 13m (arbitrary), and pile

    diameter of 400mm, thusSkin Friction

    1(Kpa)=-6.19 2(Kpa)=33.75 3(Kpa)=68 4(Kpa)=

    L1(m)=2 L2(m)=8 L3(m)=3 L4(m)=

    Perimeter =pD = 1.26Qalls(KN)= 281.32

    Bearing pressure

    Qub(KN)= CNc* Base area=(9*C)*Base area

    Qub(KN)= 169.65 Qallb(KN)= 84.82

    Total Single Pile Capacity (From soil)

    Qall(KN)= Qalls + Qallb = 366.15

    Perimet*2)FS(

    LLLLL

    55443322

    11all

    Q

    Fi l l

    C = 0 , = 3 0 = 1 7 . 0 K N / m

    3

    + 0 . 0 m

    - 2 . 0 m

    St i f f c l ay

    q = 1 5 0 K P a ,

    = 1 7 . 0 K N / m- 1 0 . 0 m3u

    - 2 0 . 0 mu 3

    - 3 0 . 0 m

    F i g u r e a : S o i l D a t au lt

    B a s a l t

    q = 1 0 ,0 0 0 K P a

    St i f f c l ay

    q = 3 0 0 K P a ,

    = 1 9 . 0 K N / m

    o

    3

    D e n s e S a n d

    = 3 0

    = 1 9 . 0 K N / m

    M = 3 00 K N mx

    yM = 2 00 K N m

    4 0 0 m m

    600m

    m x

    y

    F i g u r e b : L o a d D a t a

    P = 2 0 0 0 K N

    Use

    Concrete C-30

    Steel S-300

    F i l l

    C = 0 , = 3 0

    = 1 7 . 0 K N / m3

    + 0 . 0 m

    - 2 . 0 m

    S t i f f c l a y

    q = 1 5 0 K P a ,

    = 1 7 . 0 K N / m- 1 0 . 0 m3u

    - 2 0 . 0 m

    S t i f f c l a y

    q = 3 0 0 K P a ,

    = 1 9 . 0 K N / mu 3

    D e n s e S a n d

    = 3 0

    = 1 9 . 0 K N / m3

    - 3 0 . 0 m

    o

    B a s a l t

    q = 1 0 , 0 0 0 K P au lt

    A s s u m e

    /3

    K = 1 . 0

    A s s u m e

    A s s u m e

    s

    P

    1

    2

    3q

    b u

  • 7/25/2019 Foundation II

    2/4

    Bahir Dar University Faculty of Engineering Department of Civil Engineering

    2

    Lecture Note (Amsalu G.) Academic Year: 2005/2006

    From concrete capacity: fcd=0.67fck/1.5=13.4MPa

    Pall= Area*fcd= p(0.2)2*13400=1683.9KN; Hence soil strength governs. Pall=366.15KN

    Number and spacing of piles

    It can be easily estimated (from load and single pile capacity) that using 8 piles under a pile cap

    is reasonable. A pile spacing of 3d can be adopted (EBCS 7). Thus s=3d=3*400=1200mm. The

    pile cap shall be extended by 500mm (=300+d/2) from centerlines of exterior piles. Thus pilearrangement will be as shown below.

    Now we can determine the load carried by each pile.

    2222222

    2

    y

    2

    x

    i

    2.88m6.08x;14.4m6.08.14y

    x

    xM

    y

    yM

    n

    PP

    P =2000+pile cap weight (assuming 500mm thickness)=2127KN

    88.2

    200x

    4.14

    300y

    8

    2127P

    i

    Pi x y Value Pi x y Value

    PA1 -0.6 1.8 261.7 PC1 -0.6 -0.6 211.7

    PA2 0.6 1.8 345.0 PC2 0.6 -0.6 295.0

    PB1 -0.6 0.6 236.7 PD1 -0.6 -1.8 186.7

    PB2 0.6 0.6 320.0 PD2 0.6 -1.8 270.0 Thus Pmax=345KN < Pall=366.15KN OK! (8 piles would be enough)

    Check pile group capacity

    Pile group capacity is considered for the right figure.

    Thus Pug=fsuLi P +qbu Ab- i hi APall g= fsallLi P +qball Ab- i hi A

    First lets evaluate qbu:

    qbu= CNc = 150*9 = 1350Kpa

    qball=1350/2=675Kpa

    Group perimeter, P =2*(1.6+4) =11.2m;

    2127KNP5374.5KN1452.84320.02507.34P

    )6.1*4(*3*198*172*17)6.1*4(*6752.11*2

    3*67.58*33.752*6.19-P

    appliedug

    ug

    Design of Pile Cap

    Try a thickness D = 500mm

    d = D-100-75 = 325mm (See Fig 2.16)

    a.Check wide beam shear:

    i) along the long direction (Sec L-L)

    1189.17KPa0.325*2.2

    850.26

    db

    P v

    26.850PP400

    175PPP

    w

    w

    B2B1A2A1w

    KN

    ;501f0.3ctdall

    v 1.28MPa)5.1(

    f0.35f0.005;Assume

    c

    ck

    ctd

    0 .6

    0 .4

    0. 5

    0. 5

    1 .2

    1 .2

    1 .2

    1 .20 .5 0 .5

    y

    x

    1 2

    A

    B

    C

    D

    4 .6

    2 .2

    0 .4

    0 .61

    2

    0 .2

    0 .2

    1 .2

    1 .2 1 .2 1 .20 .20 .2

    CD

    B A

    4 m

    1.6m

    4 .61 .2 0 .6

    1 .2

    0 .5

    1

    0 .4

    2

    D

    C

    1 .2

    0 .5

    2 .2

    0 .5

    y

    1 .2

    x

    0 .5

    B

    A

    dd

    LL

    S

    S

  • 7/25/2019 Foundation II

    3/4

    Bahir Dar University Faculty of Engineering Department of Civil Engineering

    3

    Lecture Note (Amsalu G.) Academic Year: 2005/2006

    D.increase480Kpawall

    vv

    Let D = 750mm d=750-100-75 = 575mm

    OK!KPa6.4790.575*2.2

    606.7

    7.606PPP

    allw

    A2A1w

    vv

    KN

    Therefore use pile cap which is 750mm thick

    ii) along the short direction (Sec S-S)

    OK!KPa42.330.575*4

    76.88

    88.76PPPP400

    25P

    allw

    2D2C2B2Aw

    vv

    KN

    b.Check punching shear:

    Critical section is at d/2 from face of support (see fig right!)

    It can be shown that about 7.24% support is contributed

    from each pile reaction to resist punching. Thus,

    600mmdand775mmDuseTherefore

    OK!765.4KPa6.0*1.20.12

    P

    2020.65KNPPPP100

    101272P

    775mmDUseD!Increase800Kpa5010.5f

    12.8290575*1.1750.9752

    P

    2050KNPPPP100

    24.71272P

    PPPP100

    24.7PP

    pu

    pu

    2C1C2B1Bpu

    ctdpall,

    pu

    pu

    2C1C2B1Bpu

    2C1C2B1Bappliedpu

    v

    v

    Kpav

    Reinforcement

    a) In the long direction:

    Critical section is at the face of the column

    300,-Sand30-Cwithand64.360.6*2.2

    1063.11

    bd

    MK

    mKN11.10633.0*PP5.1*PPM

    22

    u

    m

    B2B1A2A1max

    Km= 36.64

    K s= 4.08 As(mm2)= 7224.01

    # 24= 16.0 Use 16bars in the long direction; better to use more bars directly above the piles.

    b) In the short direction:

    mKN70.12300.1*PPPPMD2C2B2A2max

    Km= 27.26

    K s= 3.99 As(mm2)= 8189.514

    # 24= 18.1

    Use 18bars in the short direction; better to use more bars directly above the piles.

    0 .6

    0 .4

    0 .5 d

    C

    B

    1 2

    0 .5 d

    0 . 4 + d = 9 7 5 m m

    0.6+

    d=11

    75m

    m

    4 .61 .2 0 .6

    1 .2

    0 .5

    1

    0 .4

    2

    D

    C

    1 .2

    0 .5

    2 .2

    0 .5

    y

    1 .2

    x

    0 .5

    B

    A

    dd

    LL

    S

    S

  • 7/25/2019 Foundation II

    4/4

    Bahir Dar University Faculty of Engineering Department of Civil Engineering

    4

    Lecture Note (Amsalu G.) Academic Year: 2005/2006

    Design of Pile shaft

    Asmin=0.008Ac =1005mm2. # 16 = 5. Use 6 16 as it is circular shaft and a minimum of 6

    bars are needed. Use spiral tie with a pich of

    4 .6

    2 .2

    0 .5

    1 .2

    1 .2

    1 .2

    0 .5

    0 .5 1 .2 0 .5

    a

    b

    Se c t ion A -A

    a 1 8 2 4 , L = 3 2 6 0

    6 0 06 0 0

    2 0 6 0

    6 3 5

    6 3 5

    16

    24,L

    =

    5730

    b

    4460

    4 24

    5 24

    5 24

    4 2 4

    8

    24

    8

    24