form 3a written notice for building inspectors notice of

5
1 of 5 3A For building inspectors Written notice interim or final inspection Project number: Project address: Strata plan number: Occupation certificate issue date: Contact details Business name Contact name Contact phone Email address for service Secretary Secretary Manager of Strata Building Bond and Inspections Scheme (SBBIS) Request if required. Email preferred. [email protected] Developer Builder Owners corporation Building inspector Date/s of inspection 3A-1 Date/s the inspection will take place 3A-2 Strata plan number 3A-3 Time/s the inspection will take place 3A-4 Length of time access required 3A-5 Lot number in the strata plan to be inspected 3A-6 Common areas in the strata plan to be inspected Inspection type 3A-7 Type of Inspection Interim inspection Final inspection The building inspector must give at least 14 days written notice to the owners corporation and the owner and occupier of any affected lot in the strata scheme, of their intention to enter and inspect any part of the parcel of the strata scheme to conduct an interim or final inspection. Sections 203 of the Strata Schemes Management Act 2015

Upload: others

Post on 11-Jun-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Form 3A Written Notice for Building Inspectors Notice of

1 of 5

3AFor building inspectors

Written notice interim or final inspection

Project number: Project address:

Strata plan number: Occupation certificate issue date:

Contact details

Business name Contact name Contact phone Email address for service

Secretary Secretary

Manager of Strata Building Bond and Inspections Scheme (SBBIS)

Request if required. Email preferred.

[email protected]

Developer

Builder

Owners corporation

Building inspector

Date/s of inspection

3A-1 Date/s the inspection will take place

3A-2 Strata plan number

3A-3 Time/s the inspection will take place

3A-4 Length of time access required

3A-5 Lot number in the strata plan to be inspected

3A-6 Common areas in the strata plan to be inspected

Inspection type

3A-7 Type of Inspection Interim inspection Final inspection

The building inspector must give at least 14 days written notice to the owners corporation and the owner and occupier of any affected lot in the strata scheme, of their intention to enter and inspect any part of the parcel of the strata scheme to conduct an interim or final inspection.

Sections 203 of the Strata Schemes Management Act 2015

Page 2: Form 3A Written Notice for Building Inspectors Notice of

2 of 5

SignatureMaking a false or misleading statement, giving false or misleading information, or producing false or misleading documents is a serious offence which may render you liable to prosecution for offences including under the Crimes Act which may result in penalties including a fine or imprisonment.

By signing you understand the requirement to provide true and correct information and you are agreeing to our Privacy Statement (https://www.fairtrading.nsw.gov.au/privacy)

Full Name of Individual

Capacity within Company

(if applicable)

Signature

Date

Page 3: Form 3A Written Notice for Building Inspectors Notice of

3 of 5

For building inspectors 3AFact sheet

You are

here

STAGE 8Completingthe process

STAGE 1Building bondlodgement

STAGE 3Interim inspectionand report

STAGE 4Rectify defectivebuilding work

STAGE 5Final inspectionand report

STAGE 6Determine costof rectification

STAGE 7Paying thebuilding bond

STAGE 2Inspector appointment

Between 15–18 months of completion of building work: Interim inspection conducted & interim report provided

Between 18–21 months of completion of building work: Indicative period for builder to rectify defective building work

Between 21–24 months of completion of building work: Final inspection conducted and final report provided

After 24 months, but before 2 years & 90 days of completion of building work: Parties determine the cost to rectify the defective building work

After 2 years from completion of building work or within 90 days of final report (whichever is later) Secretary makes payment of amount secured by building bond

Within 3 years of completion of building work: Process must be completed

Within 12 months of completion of building work: Developer to appoint Building Inspector

Lodge bond for Secretary approval before application for OC

Bond = 2% of contract price

You are

here

STAGE 8Completingthe process

STAGE 1Building bondlodgement

STAGE 3Interim inspectionand report

STAGE 4Rectify defectivebuilding work

STAGE 5Final inspectionand report

STAGE 6Determine costof rectification

STAGE 7Paying thebuilding bond

STAGE 2Inspector appointment

Between 15–18 months of completion of building work: Interim inspection conducted & interim report provided

Between 18–21 months of completion of building work: Indicative period for builder to rectify defective building work

Between 21–24 months of completion of building work: Final inspection conducted and final report provided

After 24 months, but before 2 years & 90 days of completion of building work: Parties determine the cost to rectify the defective building work

After 2 years from completion of building work or within 90 days of final report (whichever is later) Secretary makes payment of amount secured by building bond

Within 3 years of completion of building work: Process must be completed

Within 12 months of completion of building work: Developer to appoint Building Inspector

Lodge bond for Secretary approval before application for OC

Bond = 2% of contract price

Strata building bond and inspections scheme (SBBIS) - process stages

OR

What do I do next?This form satisfies the requirement to provide written notice when provided to the owners corporation and each owner or occupier of any affected lot. This should be done at least 14 days before the inspection date noted on the form. You may attach this written notice to an email.

The Secretary’s email address is: [email protected]

Page 4: Form 3A Written Notice for Building Inspectors Notice of

4 of 5

See the illustrated process below.

Stage 3 - Interim inspection and report

Buildinginspector

Developer

Ownerscorporation

3E

3E

3E

14 days notice beforeentering strata scheme

Interim inspectionconducted 15-18 months

Developer canapply to

Secretary - nofinal inspection

required

Interim report prepared &provided 15-18 months

No defectsin report

Approved - stage 7Not Appoved - stage 4

Owners corpnotifies owners -

interim reportavailable

Form 3C

Secretary’s decision

3A

3A

3A

3B

3B

3B

3B

3B 3D

3D

Ownerof lot

3C

Builder

Secretary

5A

5A

5B

5B

Within 18 monthsof OC date

Dev re-appiontsbuilding insp

Building inspectornot available

14 days notice beforeentering strata scheme

Final inspection21-24 months

Final report prepared & provided 21-24 months

Notifies ownersreport available

Stage 5 - Final inspection and report

Buildinginspector

Developer

Ownerscorporation

Ownerof lot

Builder

3C

Form 3C

Secretary arrangesbuilding inspector

Developer notifies Secretary& Secretary to arrange

building inspector

5C

5C

5C

Secretary

3B

3B

3B

3B

3B

3A

3A

3A

OR

Page 5: Form 3A Written Notice for Building Inspectors Notice of

5 of 5

What happens next?The owners corporation, any person who has exclusive use of common property, a strata managing agent, any building manager or manager of the common property and any owner or occupier of a lot must provide any assistance that is reasonable to enable an inspection to be carried out.

A person must not, without reasonable excuse, refuse a building inspector access to any part of the parcel of a strata scheme or a lot in the strata scheme, or obstruct or hinder a building inspector, in the exercise of the inspector’s functions under this Act.

When is the interim inspection conducted and interim report due?The interim inspection must be conducted and the interim report finalised and served between 15 months and 18 months after the issue of the occupation certificate.

When is the final inspection conducted and final report due?

The final inspection must be conducted and the final report finalised and served between 21 months and 24 months after issue of the occupation certificate.

Need further information? Please refer to the Strata Building Bond and Inspections Scheme webpage on Fair Trading’s website.

Privacy and Security of InformationProviding documents to developer/owners corporation/builder/building inspector/other

Provide the document in PDF format. This minimises the recipient’s ability to change the document.

Submitting documents to the Secretary

Supply the document in PDF format.

This form and the information provided remains the property of the NSW Government.

All parties have the requirement to provide true and correct information.

The Fair Trading Terms & Conditions and Privacy Statement can be accessed at https://www.fairtrading.nsw.gov.au/privacy

AnnexureDefinition: Section 203 of the Strata Schemes Management Act 2015:

“(1) A building inspector appointed to prepare a report under this Division may enter and inspect any part of the parcel of the strata scheme.

(2) The building inspector must give at least 14 days written notice to the owners corporation and the owner and any occupier of any affected lot of an intention to enter any part of the parcel of the strata scheme.

(3) The owners corporation, any person who has exclusive use of common property, a strata managing agent, any building manager or manager of the common property and any owner or occupier of a lot must provide any assistance that is reasonable to enable an inspection to be carried out in accordance with this Division.

(4) A person must not, without reasonable excuse, refuse a building inspector access to any part of the parcel of a strata scheme or a lot in the strata scheme, or obstruct or hinder a building inspector, in the exercise of the inspector’s functions under this Act.”