Forest Carbon Partnership Facility
Nancy Bikondo- Omosa
Procurement Specialist, OPSOR
Agenda Procurement: Roles & Responsibilities in Project Cycle
Main Features of Selection and Employment of consultants under Bank operations
Main Features of Procurement of Goods, Works & Non-Consulting Services under Bank operations
Procurement: Roles & Responsibilities in Project Cycle
Procurement & Consultant Guidelines
Role of the PS/PAS assigned to a Project
5
• Assesses the procurement capacity & risk of the Recipient EAs
• Reviews & clears procurement Plans & procurement arrangements & drafts procurement section of PAD (Project Paper) & GA
• Prior/post reviews & clears procurement documentation & decisions
• Makes sure all necessary internal reviews (RPM / OPRC) take place Fid
uci
ary
Fu
nct
ion
s
• Makes sure Recipient assigns qualified resources to procurement
• Provides training in procurement to recipients & bidders
• Advises TTLs in application of procurement policies & procedures
• Participates in negotiations
• Assists the TTL in monitoring complaints
• Maintains procurement monitoring system
Ser
vice
F
un
ctio
ns
6
Procurement Responsibilities of TTL
TTL is the main interlocutor of the Recipient on the Project:
Signs letters to recipients on procurement on behalf of the Bank after internal clearances are obtained
Overall fiduciary responsibility
Is in charge of team leadership:
Get a PS /PAS into the team as early as at the identification
Informs line managers of progress / issues affecting procurement (ISR)
Funds procurement supervision, including post reviews;
Monitors procurement plans and its publications;
Monitors contract management and conducts physical inspections
Follows-up With the Recipient on Procurement review & supervision outcomes
Ensures Compliance with staff obligations with regards to information systems (e.g. complaints database, 384s, publication of GPN / SPN, etc.)
Maintains files on all project related procurement documents
Quality of ToR, technical specifications & other technical aspects
Role of Bank Staff in Procurement
Maintain strict neutrality & impartiality
Do not:
Recommend to Recipients the use of particular contractors/consultant
Undertake activities under the Recipient’s responsibility
Participate in evaluation
7
Identification – Concept Stage
Integrated Assessment Framework (IAF) filled by Recipients
Project Concept Note / Concept Memo (incl. Simplified Operational Risk Assessment Framework (ORAF)):
RPM/delegate reviews (virtually)
Once Trust Fund Proposal /grant process is approved, TTL requests and RPM /CPPO (if global grant by Network) assigns a PS/PAS.
PS/PAS brings a knowledge of country / region / sub-region procurement systems and practices and helps identify and mitigate risks in an efficient way.
8
Appraisal to Grant Signature
Implementation Annex
Based on IAF, PS prepares:
Procurement capacity constraints
Procurement arrangements under the project
Measures to address identified procurement issues
Mechanisms to ensure procurement plan is monitored and updated regularly
TTL discusses with Recipient:
Procurement Plan
Risk mitigation measures
PS reviews Final package
9
Procurement Plan for Small Grants The Recipient must have a Procurement Strategy to
implement the Project Procurement Plan
For Grants: Simplified Procurement Plan for the entire scope of project agreed with the Bank!
All Procurement plans are subject to Bank’s prior review
Procurement provisions legally applicable as of Grant Signature
Implementation as per approved procurement Plan
Recipient shall update the procurement Plan annually or as needed
10
Simplified Procurement Plan content Specific Plan for goods, works, consultancy and other services to be
procured during initial period of at least 18 months:
Brief description of Goods Works , Services
Procurement methods as permitted by the Grant Agreement
Bank review requirements & thresholds
Time schedule for contract signature
Any information that the Bank may reasonably require
Large number of small contracts may be clubbed together
For demand driven project (CDD / SWAPs) agree on a specific template to monitor and implement procurement (refer to Operational Manual if applicable)
11
Project Implementation What does the Bank do during Procurement implementation?
Evaluate the Recipient’s procurement action’s compliance with the GA
Monitor adherence to Procurement Plan
Monitor progress in the action Plan agreed, incl. capacity building of Recipient
How does the Bank do?
Procurement prior review
Supervision missions according to supervision arrangements’ in the Project Paper/developed concept memo:
Follow-up of the action Plan & procurement Plan
Procurement post reviews
periodic risk assessment: update of mitigation measures/action Plan ISR
Reviewing Project Progress Reports prepared by the Recipient
12
Completion
Implementation Completion Report (ICR)
Evaluates implementation performance of parties including Achievement of project objectives
Cost/Benefits
Analysis of successes and failures, inc. procurement
Sustainability
Lessons learned
13
Main Features of Selection and Employment of consultants under Bank operations
15
Consultant Guidelines (January 2011)
Consulting Services
I. Introduction
II. Quality- and Cost-Based Selection
III. Other Methods of Selection
IV. Types of Contracts and Important Provisions
V. Selection of Individual Consultants
VI. Appendices
Consultant Guidelines Section I. Introduction
Purpose
General Considerations
Applicability of Guidelines
Conflict of Interest
Unfair Competitive Advantage
Eligibility
Advance Contracting & Retroactive Financing
Association between Consultants
Bank Review, Assistance, and monitoring
Misprocurement
References to Bank
Training or Transfer of Knowledge
Language
Fraud & Corruption
Procurement Plan 16
Basic Principles of Bank Selection of Consultants
0
0.2
0.4
0.6
0.8
1Quality of services
Efficiency & Economy
TransparencyEqual opportunity
Development ofnational consultants
in developing countrymembers
18
• Quality- and Cost-Based Selection QCBS
• Quality-Based Selection QBS
• Fixed Budget FBS
• Least Cost Selection LCS
• Consultants’ Qualifications CQS
• Single Source Selection SSS
SELECTION METHODS
Process: Selection of consultants (QCBS – FBS - LCS)
Prepare Terms of
Reference (ToR) & budget
Advertise: “Request for Expression of interest”
Evaluate “Expressions of
interest” & establish a short
list
Issue a “Request for Proposals”
(RFP) to short listed firms
Receipt of proposals &
public opening of “Technical Proposals”
Technical Evaluation
Report
Public Opening of Financial Proposals
Evaluation of Financial Proposals
Preparation of the combined technical
and financial evaluation report
Negotiations of the contract
Award to the selected firm.
19
20
Selection based on Consultant’s Qualification (CQS)
Small assignment or emergency
competitive proposals not justified
Obtain expression of interest from min. 3 qualified firms
Select the most qualified firm for the assignment
Firm will prepare & submit technical & financial proposals
Evaluate technical & financial proposals
If proposal responsive & acceptable Negotiate the contract & award
21
Single Source Selection (SSS)
Natural continuation of previous work
Emergency
Very small assignment
only one firm has experience of exceptional worth
Make sure SSS is well justified & proven
Make sure price is reasonable
Make sure contract is well balanced
Selection of Individual Consultants Advertisement encouraged but not required in all cases and for
small contracts
Basis for selection: qualifications No need to submit proposals
2 selection methods:
Compare at least 3 candidates interested or approached by Borrower
Single Source Selection if:
Continuation of previous work for which consultant was selected competitively
Assignments of a total expected duration of < 6 months
Urgent situations
Unique qualification
Selection of individual consultants is mainly a technical task since selection based on qualification.
22
TTL’s Responsibility in Selection & Employment of Consultants
ToR & Cost estimate
Technical qualification of short listed firms
Evaluation criteria in the RFP
Technical quality of the technical evaluation report ( &
technical proposals as needed)
Technical aspects of the contract negotiations & final draft
contract, incl. “Description of Services” & Reporting
Supervision of implementation
23
Procurement Guidelines (January 2011)
Goods and Works & Non consulting services
I. Introduction
II. International Competitive Bidding
III. Other Methods of Procurement
IV. Appendices
24 Working for a world free of poverty
25
25
International Competitive Bidding (ICB)
One Stage
Two Stage
Limited International Bidding (LIB)
National Competitive Bidding (NCB)
Shopping
Framework Agreements
Direct Contracting (DC)
Force Account
Procurement from UN Agencies
Procurement Agents & Construction Managers
Inspection Services
Procurement in Loans to Financial Intermediary Institutions & Entities
Procurement under Public Private Partnership (PPP) Arrangements
Performance Based Procurement
Procurement under Loans Guaranteed by Bank
Community Participation in Procurement
Use of Country Systems
Methods of Procurement
Pro
cure
men
t P
roce
ss
26
Main Characteristics of Shopping
Compliance with 3.5 of GLs:
Comparison of price quotations obtained from 3 or more suppliers / contractors / service providers
If less than 3 quotations obtained Bank’s no objection!
Appropriate for:
limited quantities of readily available off-the-shelf Goods
standard specification commodities of small value
simple works
27
Shopping: Request for quotations Content of a Request for quotations:
Description / Specification of G/W Quantity Delivery / completion time & place Template for quotations (recommended for ease of comparison) Deadline for submission of quotations Where /how to submit quotations: Address, fax. No, email Min. period of validity of quotations required Conditions of the Purchase order (PO) / Contract Applicable law (as needed) Avoid use of brand names (or follow by “or equivalent”)
Quotations by letter / fax / electronic means
28
Shopping: Evaluation of quotations Same principles than open bidding:
Set a deadline & place for receipt of quotations Reject quotations received after the deadline Record name of bidders, amount of quotations in writing Alteration of quotations after the deadline not permitted Clarifications may be asked after the deadline in writing Confidentiality after deadline until disclosure of award Check:
Eligibility of bidders Proper signature of quotations Quotations must include warranty conditions (if required) and be
substantially responsive to the request for quotations
Determine the quotation with the lowest evaluated cost in accordance with the request for quotation
Prepare detailed evaluation report justifying award decision. 29
Shopping: Purchase Order Name, address, Tel., fax., etc. of supplier / contractor
Name, address, Tel., fax, etc. of client
Description / Specification of G/W + Serial number
Quantity
Delivery / completion time & place
Warranty / performance security conditions
Conditions of delivery (inspection, test, etc. if any)
Payment terms: account number, payment calendar, documents required to process payment
30
Main Characteristics of Direct Contracting
Compliance with 3.7 & 3.8 of GLs: No competition Appropriate when:
Existing G / W / NCS: extension of additional of similar nature + no advantage through further competition + awarded initially through acceptable procedures
Compatibility with existing equipment Proprietary: only one source Goods from a particular source essential to achieve the required
performance / functional guarantee of an equipment / facility Exceptions: natural disasters, emergency declared by the Borrower
& recognized by the Bank Procurement from a specific UN Agency
Advertisement of the contract award information
31
Tips for Direct Contracting
32
Make sure DC is well justified & proven
Make sure price is reasonable
Make sure contract is well balanced
LEARN MORE
33
• Procurement & Consultants Guidelines • Standard Bidding and Proposal Documents • Other
Procurement website www.worldbank.org/procure