for official use only international development … · 2020. 6. 2. · for official use only report...

79
FOR OFFICIAL USE ONLY Report No: PAD2773 INTERNATIONAL DEVELOPMENT ASSOCIATION PROJECT APPRAISAL DOCUMENT ON A PROPOSED CREDIT IN THE AMOUNT OF SDR 254.9 MILLION (US$350 MILLION EQUIVALENT) TO THE REPUBLIC OF THE UNION OF MYANMAR FOR A POWER SYSTEM EFFICIENCY AND RESILIENCE PROJECT May 7, 2020 Energy and Extractives Global Practice East Asia and Pacific Region This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 23-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

 

FOR OFFICIAL USE ONLY 

Report No: PAD2773  

 

 INTERNATIONAL DEVELOPMENT ASSOCIATION 

PROJECT APPRAISAL DOCUMENT 

ON A 

PROPOSED CREDIT 

IN THE AMOUNT OF SDR 254.9 MILLION (US$350 MILLION EQUIVALENT) 

TO THE 

REPUBLIC OF THE UNION OF MYANMAR 

FOR A 

POWER SYSTEM EFFICIENCY AND RESILIENCE PROJECT 

May 7, 2020 

 

 

    Energy and Extractives Global Practice East Asia and Pacific Region   

 

This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization. 

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

CURRENCY EQUIVALENTS (Exchange Rate Effective February 29, 2020) 

 

Currency Unit =   Myanmar Kyat (MMK) 

MMK 1,431.50 =  US$1 

US$0.7282 =  SDR 1  

 FISCAL YEAR 

October 1 – September 30  

Regional Vice President: Victoria Kwakwa 

Country Director: Mariam J. Sherman 

Regional Director: Ranjit Lamech 

Practice Manager: Jie Tang 

Task Team Leaders: Claudia Ines Vasquez Suarez; Maria Ayuso Olmedo 

Page 3: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

ABBREVIATIONS AND ACRONYMS  

CAPEX  Capital Expenditure(s) 

CCGT  Combined Cycle Gas Turbine 

CPF  Country Partnership Framework 

CPPF  Community Participation Planning Framework  

CQS  Consultant’s Qualification‐based Selection 

CSO  Civil Society Organization 

DA  Designated Account 

DPTSC  Department of Power Transmission and Systems Control 

DSI  Design, Supply, and Installation 

EAO  Ethnic Armed Organization 

EIRR  Economic Internal Rate of Return 

ENPV  Economic Net Present Value 

EPGE  Electric Power Generation Enterprise  

EPM  Electricity Planning Model 

EPP  Electric Power Project 

ESIA  Environmental and Social Impact Assessment 

ESMF  Environmental and Social Management Framework 

ESMP  Environmental and Social Management Plan 

FCV  Fragility, Conflict, and Violence 

FIRR  Financial Internal Rate of Return 

FNPV  Financial Net Present Value 

GBV  Gender‐based Violence  

GHG  Greenhouse Gas 

GOM  Government of Myanmar 

GRiF  Global Risk Financing Facility 

GRM  Grievance Redress Mechanism 

GRS  Grievance Redress Service 

HEIS  Hands‐on Extended Implementation Support 

HFO  Heavy Fuel Oil 

HRSG  Heat Recovery Steam Generator 

IA  Implementing Agency 

IFC  International Finance Corporation 

INDC  Intended National Determined Contribution 

InfraSAP  Energy Infrastructure Sector Assessment Program 

IPF  Investment Project Financing 

IPL  Inclusion and Peace Lens 

JICA  Japan International Cooperation Agency 

KfW  Kreditanstalt Fuer Wiederaufbau 

KPI  Key Performance Indicator 

LCOE  Levelized Cost of Energy 

LNG  Liquefied Natural Gas 

LTSA  Long‐term Service Agreement 

M&E  Monitoring and Evaluation 

MDI  Multidimensional Disadvantage Index 

MFD  Maximizing Finance for Development 

MLCS  Myanmar Living Conditions Survey 

Page 4: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

MOEE  Ministry of Energy and Electricity 

MOGE  Myanmar Oil and Gas Enterprise 

MOSW  Ministry of Social Welfare 

MSDP  Myanmar Sustainable Development Plan 

NEP  National Electrification Program 

NPV  Net Present Value 

O&M  Operation and Maintenance 

OAGM  Office of the Auditor General of Myanmar  

OEM  Original Equipment Manufacturer 

OPEX  Operational Expenditure(s) 

PCRA  Procurement Capacity and Risk Assessment 

PDO  Project Development Objective 

PIU  Project Implementation Unit 

PPP  Public‐Private Partnership 

PPSD  Project Procurement Strategy for Development 

PQ  Prequalification 

PV  Photovoltaic 

QCBS  Quality‐ and Cost‐based Selection 

RFB  Request for Bids 

RFQ  Request for Quotations 

RPF  Resettlement Policy Framework 

SEE  State Economic Enterprise 

SEA  Sexual Exploitation and Abuse  

SMEs  Small and Medium Enterprises 

STEP  Systematic Tracking of Exchanges in Procurement 

WACC  Weighted Average Cost of Capital 

YESC  Yangon Electricity Supply Corporation  

 

 

Page 5: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

 TABLE OF CONTENTS 

 

I.  STRATEGIC CONTEXT ........................................................................................................ 6 

A. Country Context ................................................................................................................................ 6 

B. Sectoral and Institutional Context .................................................................................................... 7 

C. Relevance to Higher Level Objectives ............................................................................................. 15 

II.  PROJECT DESCRIPTION ................................................................................................... 16 

A. Project Development Objective ..................................................................................................... 16 

B. Project Components ....................................................................................................................... 17 

C. Project Beneficiaries ....................................................................................................................... 19 

D. Results Chain .................................................................................................................................. 20 

E. Rationale for Bank Involvement and Role of Partners ................................................................... 21 

F. Lessons Learned and Reflected in the Project Design .................................................................... 22 

III.  IMPLEMENTATION ARRANGEMENTS .............................................................................. 23 

A. Institutional and Implementation Arrangements .......................................................................... 23 

B. Results Monitoring and Evaluation (M&E) Arrangements ............................................................. 23 

C. Sustainability ................................................................................................................................... 24 

IV.  PROJECT APPRAISAL SUMMARY ..................................................................................... 25 

A. Technical, Economic and Financial Analysis ................................................................................... 25 

B. Fiduciary .......................................................................................................................................... 27 

C. Safeguards ...................................................................................................................................... 29 

D. Grievance Redress Mechanism ...................................................................................................... 33 

V.  KEY RISKS ....................................................................................................................... 34 

VI.  RESULTS FRAMEWORK AND MONITORING ..................................................................... 37 

ANNEX 1: Implementation Arrangements and Support Plan .................................................. 45 

ANNEX 2: Economic and Financial Analysis ............................................................................ 49 

ANNEX 3: Inclusion and Peace Lens Note ............................................................................... 55 

ANNEX 4: Procurement Implementation Arrangements ........................................................ 61 

ANNEX 5: Financial Management Arrangements ................................................................... 70 

ANNEX 6: Maps ..................................................................................................................... 72 

  

Page 6: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

Page 1 of 74

       DATASHEET 

 

BASIC INFORMATION   BASIC INFO TABLE 

Country(ies)  Project Name 

Myanmar  Power System Efficiency and Resilience Project 

Project ID  Financing Instrument  Environmental Assessment Category 

P162151 Investment Project Financing 

B‐Partial Assessment 

 

Financing & Implementation Modalities 

[  ] Multiphase Programmatic Approach (MPA)  [  ] Contingent Emergency Response Component  (CERC) 

[  ] Series of Projects (SOP)  [  ] Fragile State(s) 

[  ] Disbursement‐linked Indicators (DLIs)  [  ] Small State(s) 

[  ] Financial Intermediaries (FI)  [  ] Fragile within a non‐fragile Country 

[  ] Project‐Based Guarantee  [  ] Conflict  

[  ] Deferred Drawdown  [  ] Responding to Natural or Man‐made Disaster 

[  ] Alternate Procurement Arrangements (APA) 

 

Expected Approval Date  Expected Closing Date 

29‐May‐2020  30‐Jun‐2026 

Bank/IFC Collaboration    

No 

 Proposed Development Objective(s)  The project development objectives are to increase the output and efficiency of power generation and improve the resilience of the power network in support of the government’s program on universal electricity access.  Components  Component Name   Cost (US$, millions) 

 

Page 7: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 2 of 74

Upgrading Ywama Power Generation Units    290.00  

Improving Resilience of the Power Network     60.00  

 Organizations  Borrower:    Republic of the Union of Myanmar  

Implementing Agency:   Electric Power Generation Enterprise   Ministry of Electricity and Energy  

 

PROJECT FINANCING DATA (US$, Millions)

 SUMMARY‐NewFin1 

Total Project Cost  350.00 

Total Financing  350.00 

of which IBRD/IDA   350.00 

Financing Gap  0.00 

  DETAILS‐NewFinEnh1 

World Bank Group Financing 

     International Development Association (IDA)  350.00 

          IDA Credit  350.00 

    IDA Resources (in US$, Millions) 

Credit Amount  Grant Amount  Guarantee Amount  Total Amount 

Myanmar   350.00     0.00     0.00   350.00 

National PBA   350.00     0.00     0.00   350.00 

Total   350.00     0.00     0.00   350.00 

    Expected Disbursements (in US$, Millions) 

  

WB Fiscal Year          2020  2021  2022  2023  2024  2025  2026 

Annual           0.00    10.00    60.00   140.00   100.00    20.00    20.00 

Page 8: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 3 of 74

Cumulative           0.00    10.00    70.00   210.00   310.00   330.00   350.00 

   

INSTITUTIONAL DATA  

Practice Area (Lead)  Contributing Practice Areas 

Energy & Extractives   

 

Climate Change and Disaster Screening 

This operation has been screened for short and long‐term climate change and disaster risks 

 

SYSTEMATIC OPERATIONS RISK‐RATING TOOL (SORT) 

 

Risk Category  Rating  

1. Political and Governance   Substantial   

2. Macroeconomic   Substantial   

3. Sector Strategies and Policies   Substantial   

4. Technical Design of Project or Program   Substantial   

5. Institutional Capacity for Implementation and Sustainability   Substantial   

6. Fiduciary   High   

7. Environment and Social   Substantial   

8. Stakeholders   Substantial   

9. Other   Moderate   

10. Overall   Substantial  

 

COMPLIANCE 

 Policy Does the project depart from the CPF in content or in other significant respects? 

[  ] Yes      [✓] No 

 

Page 9: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 4 of 74

Does the project require any waivers of Bank policies?  

[  ] Yes      [✓] No 

  Safeguard Policies Triggered by the Project  Yes  No 

 

Environmental Assessment OP/BP 4.01  ✔    Performance Standards for Private Sector Activities OP/BP 4.03    ✔  

Natural Habitats OP/BP 4.04    ✔  

Forests OP/BP 4.36    ✔  

Pest Management OP 4.09    ✔  

Physical Cultural Resources OP/BP 4.11    ✔  

Indigenous Peoples OP/BP 4.10  ✔    Involuntary Resettlement OP/BP 4.12  ✔    Safety of Dams OP/BP 4.37    ✔  

Projects on International Waterways OP/BP 7.50    ✔  

Projects in Disputed Areas OP/BP 7.60    ✔  

 Legal Covenants 

    Sections and Description The Recipient shall take all actions under its control to maintain EPGE and DPTSC, and their respective operation, and to refrain from any restructuring which, in the views of the Association, would materially and adversely affect the ability of the Recipient, DPTSC or EPGE to perform any of their respective obligations arising under or entered into pursuant to this Agreement, or to achieve the objectives of the Project (FA, Schedule 2, Section I.A.1 and 2).        Sections and Description The Recipient shall cause EPGE to: (a) enter into a turnkey contract covering the demolition, design, supply, installation, testing, and commissioning of the new combined cycle gas turbine; and (b) contract an owner’s engineer and independent consultants for environmental and social matter’s implementation and monitoring, and for the implementation of a roll out set up and operationalization of child care (FA, Schedule 2, Section I.A.3).        Sections and Description For the implementation of Part B.1 of the Project, the Recipient shall cause DPTSC to: (a) exclude: (i) the construction of new substations and new transmission lines; and (ii) activities in areas where there is an active conflict; (b) carry out an initial technical screening of proposed activities on the basis of eligibility criteria acceptable to the Association, which shall include the following: (i) substations which do not have adequate capacity and/or redundancy to support grid extension for electrification purposes; (ii) assets that are the most vulnerable to climate events; and (iii) substations which serve households that suffer from low quality of electricity supply; and (c) among 

Page 10: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 5 of 74

the activities screened under Section I.A.4(b) of this Schedule, give priority to substations which serve a substantial share of disadvantaged or vulnerable households.         Sections and Description The Recipient shall prepare, or cause to be prepared: a draft annual work plan and budget for the Project (listing all Project activities to be financed during the year covered by said plan including, without limitation, Subprojects, Training and Incremental Operating Costs) and a sequenced forecast of cash flow and disbursement needs showing all Project financing irrespective of its source for each year of Project implementation (FA, Schedule 2, Section II.B).        Sections and Description The Recipient shall ensure, and cause EPGE to ensure, that the Project is carried out: (a) with due regard to appropriate health, safety, social and environmental standards and practices and the Safeguard Instruments; (b) ensure RAP funding and implementation prior to starting activity which involves a resettlement; ensure that contractors’/subcontractor’s obligations, including undertaking a hazard and operability study to identify risks to communities, impact of labor influx and mitigation are included in the relevant bidding documents and contracts; (c) all consultancy services related to Technical Assistance and capacity building activities pay due attention to the policies of the Association; (d) take all measures necessary to regularly collect, compile, and submit the status of compliance with the Safeguards Instruments; and (c) publicize the availability of a grievance redress mechanism, hear and determine fairly and in good faith all complaints raised in relation to the Project, and take all measures necessary to implement the determinations made by such mechanism in a satisfactory manner  (FA, Schedule 2, Section I.B).        Sections and Description The Recipient shall apply (and shall cause EPGE to apply) throughout the period of implementation of the Project, the financial management manual setting forth, the Project's administrative, financial, accounting, internal control, asset management, auditing, disbursement/withdrawal and reporting procedures required for the defrayment and proper accounting of the funds of the Financing (FA, Schedule 2, Section I.C).        Sections and Description The Recipient shall: not later than thirty (30) months after the Effective Date, or such other date as may be agreed with the Association, carry out jointly with and EPGE (as relevant for each Project Part) and the Association, a midterm review of the Project (the “Midterm Review”), to assess the status of Project implementation, as measured against the indicators agreed between the Association and the Recipient and the legal covenants included in this Agreement. Such review shall include an assessment of the following: (a) overall progress in implementation; (b) results of monitoring and evaluation activities; (c) progress on procurement and disbursement; (d) progress on implementation of safeguards measures; (e) implementation arrangements and Project staffing; and (f) the need to make any adjustments to the Project and reallocate funds to improve performance, if any (FA, Schedule 2, Section II.C).      Conditions   

    

Page 11: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 6 of 74

    

I. STRATEGIC CONTEXT 

 

A. Country Context   

1. Myanmar  is a  low‐income and fragile, conflict‐affected state undergoing a profound transition  from decades of isolationist military rule. The country’s opening in 2011—both inward through democratic reforms and outward through trade,  investment, and migration—marked the beginning of a complex transition on the political, peace, and economic fronts. Despite immediate gains and high expectations of continued progress, these transitions remain incomplete and continue to face setbacks as the reform momentum has slowed down. On the political front, multiparty democratic elections in late 2015 gave substantial, but not absolute, powers to a civilian government.  The  military  has  retained  its  independence  from  civilian  oversight,  with  spillover  effects  into economic development issues and natural resource management. The transition toward durable peace has been one of  the most challenging. Myanmar has been more deeply affected by subnational conflict  than any other country in Southeast Asia. In 2016, almost a third of the country’s townships hosted ethnic armed organizations (EAOs) that challenged the authority of the Government.1 More recently, violence has flared in the northeast of the country and in Rakhine State.  

2. Although most progress has been made on  the economic  front,  challenges  remain  to make  it more inclusive. Between 2011 and 2017, the economy grew at the extraordinary rate of 7 percent a year on average, putting Myanmar  among  the  five  fastest‐growing  countries  in  the world.  The  growth was  spurred  by  capital accumulation  supported  by  foreign  direct  investment  and,  to  a  lesser  extent,  increased  productivity.  Strong growth performance translated into substantial poverty reduction and improvements in non‐monetary welfare. The poverty headcount almost halved between 2005 and 2017,  from 48 to 25 percent according to the  latest national estimates.2 However, vulnerability to poverty remains high. About 12 million people were still living in poverty in 2017. Many near‐poor are also susceptible to falling back into poverty following weather, health, or economic shocks. In addition, spatial inequalities and exclusion along geography and identity lines persist. People living in rural areas and conflict‐affected states, and ethnic and religious minorities, lag on most dimensions of welfare—from stunting to educational attainment and access to basic sanitation and electricity services. 

3. Recently implemented structural reforms have helped maintain the growth momentum but the direct and indirect  impacts of the COVID‐19 pandemic are rising. The recently  implemented reforms—including the opening of  the banking  sector  to  foreign banks,  the  liberalization of  the wholesale  and  retail  trades,  and  the loosening of export licensing requirements—helped to revive growth momentum.3 However, global and regional growth  prospects  have  been  battered  by  the  COVID‐19  pandemic.  Indirect  factors  contributing  to  the  lower economic growth expected in Myanmar in FY2019–2020 include trade and tourism reduction, and supply chain disruptions. Direct  factors  include weakened domestic  investment  and  consumption  (of  goods  and  retail  and transport  services)  stemming  from  early  social  distancing,  unemployment,  and  low  foreign  remittances.  The economy is expected to recover next year in line with regional peers. However, compared with the baseline case, a more severe domestic outbreak poses a major downside risk with greater effects on domestic demand. Deep 

1 Asia Foundation. 2017. The Contested Areas of Myanmar: Subnational Conflict, Aid, and Development.  https://asiafoundation.org/publication/contested‐areas‐myanmar‐subnational‐conflict‐aid‐development/ 2 Estimates based on: Integrated Household Living Conditions Assessment (2005) and Myanmar Living Conditions Survey (2017). 3 According to the Doing Business ranking, Myanmar is among the ‘top 20 improvers’ owing to initiatives that improved the conditions for starting business, protecting minority investors, and dealing with construction permits. World Bank Group. Doing Business 2020. https://openknowledge.worldbank.org/bitstream/handle/10986/32436/9781464814402.pdf.  

Page 12: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 7 of 74

local  impacts  in  rural  and  urban  areas  are  also  expected—particularly  in  the  tourism,  manufacturing,  and agriculture  sectors and among already vulnerable  groups. Policy priorities  going  forward  include  (a)  adjusting health policies to boost health care capacity and meet a potentially overwhelming demand over a sustained period and (b) adjusting macroeconomic policies to mitigate impacts on affected firms and households with buffers to shore up economic stability and demand. 

4. The provision of energy services remains a priority to support the implementation of health policies during the COVID‐19 outbreak and support the overall economic recovery over the medium term. Myanmar has abundant  energy  resources,  particularly  natural  gas,  hydropower  and  other  renewable  energy  resources. However,  electricity  infrastructure  development  has  not matched  the  pace  of  economic  development  and  is increasingly becoming a constraint on poverty  reduction and shared prosperity. Although  improving  in  recent years, electricity access to the public grid reached only 50 percent by end of 2019—the lowest electrification rate in the Southeast region. Improving access to reliable electricity services will be critical to ensuring the functioning of healthcare facilities during the disease outbreak and support economic recovery in the medium term. Before the pandemic,  lack of access to electricity supply already ranked among the top constraints  to doing business according to the latest Enterprise Survey available for Myanmar.4 Therefore, improving electricity access and the quality of services delivered remains a key development challenge. 

B. Sectoral and Institutional Context 

5. A large investment program launched at the beginning of the transition, with the overarching goal of achieving universal electricity access by 2030, has had positive results. The electrification rate (access to the public grid) doubled between 2010–2011 (25 percent) and 2019–2020 (50 percent) through the implementation of  the Government’s National  Electrification Program  (NEP).  This was made possible by  the  launch of  a  large investment program, which  attracted  substantial  private  sector  financing  in power  generation5  and  increased public investments in power generation and the development of the national grid. The program was led by the Ministry of Electricity and Energy (MOEE), which is the main body responsible for policy making, overseeing, and operating the state economic enterprises (SEEs). In turn, the SEEs play a major role in implementing infrastructure projects  and  service  delivery.  However,  despite  these  solid  achievements,  substantial  challenges  persist  to achieving the universal electricity access goal. These challenges and the Government’s strategy to address them are presented in the following paragraphs. 

(i) Reduce the Widening Power Supply Gap in an Environmentally Sustainable Way and at Least Cost 

6. There is a growing power supply gap which the country seeks to close by procuring emergency rental plants  in  the  short  term  and  by  developing  its  renewable  resources  in  the medium‐to‐long  term.  In  2018, Myanmar’s  installed  generation  capacity was  5,600MW6  dominated  by  hydropower, which  accounted  for  58 percent, and followed by natural gas (33 percent), and other thermal generation (10 percent). In 2019, a widening supply gap became evident when the country faced widespread power shortages with  load shedding reaching 

4 Myanmar 2016 Enterprise Survey. See https://www.enterprisesurveys.org/en/data/exploreeconomies/2016/myanmar. 5 During 2011–12 and 2018–19,  the share of private sector‐owned and  ‐operated generation  increased  from around 25 percent  to 45 percent. 6 It is estimated that only 3,600 MW is available for domestic power generation. The remaining capacity is not available due to technical issues in outdated plants and because the output from some of the larger hydropower plants is committed for exports. 

Page 13: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 8 of 74

approximately  300 MW  during  the  summer months  (March  to  June)7.  Assuming  that  electricity  demand will continue to expand at an estimated average annual rate of 11.1 percent and with a limited pipeline of projects under construction, the supply gap is expected to increase substantially in the short‐to‐medium term (see figure 1). Although the economic impact of the COVID‐19 pandemic may reduce the pace of demand growth over the next months, it is expected that demand will resume as the country and region recover from the crisis. To reduce the supply gap in the short term, the Government issued a tender for five emergency rental plants totaling 1,040 MW8  in  late  June 2019.  If  implemented within  the aggressive  timelines announced,  these could help  increase available supply, albeit at high costs. Several other projects are being discussed to reduce the supply gap in the medium‐to‐long term, including large hydropower projects that would allow Myanmar to harness its vast hydro potential, liquified natural gas (LNG)‐to‐power projects (which received Notice to Proceed in early 2018), power import projects with China and Lao PDR, and new coal‐fired power plants which have been recently announced.9 

7. To provide affordable and sustainable electricity, in line with Myanmar’s climate commitments under the  Paris Agreement,  the  country will  have  to  develop  its  indigenous  renewable  energy  resources,  rely  on electricity imports, and improve the efficiency of its gas‐fired thermal power assets. In the medium‐to‐long term, the  country must develop  its hydropower and  renewable energy  (solar photovoltaic  [PV] and wind) potential according to an indicative least‐cost generation plan prepared by the World Bank (figure 2). LNG imports for new power generation assets will also be needed due to the declining output from maturing gas fields. According to estimates from the Myanmar Oil and Gas Enterprise (MOGE), available domestic supply could decrease by two‐thirds by 2030 if the country cannot develop its domestic gas resources on time. Among the generation options, improving energy efficiency  in generation stands out as a priority. Existing gas‐fired power plants, particularly state‐owned ones, have  low thermal conversion efficiencies  (15–27 percent) compared with modern gas‐fired plants (52–55 percent). Such inefficiencies result in high system costs, wasteful natural gas consumption, and an increase  in  the  energy  sector’s  environmental  impact.  Together  with  the  development  of  renewable  energy resources, efficiency improvements have been identified as key mitigation measures in the country’s Intended National Determined Contribution (INDC).10  

8. In  the  medium  term,  combined‐cycle  gas  turbines  (CCGTs)  are  among  the  least‐cost  options  and compatible with a low‐carbon development path for the power sector. Advantages of the technology include: (a) maximum power output per unit of fuel without increasing the existing domestic gas supply requirements; (b) rapid  construction  timelines  of  approximately  30–36  months  that  enable  the  development  of  large‐scale hydropower projects, which have longer development timelines; (c) ability to be located close to a major load center to reduce the demand on the transmission system; and (d) firm capacity to help manage the seasonality of hydropower generation and the intermittency of renewable energy that should be introduced in the generation mix.  According  to  the  indicative  least‐cost  plan  analysis,  efficiency  upgrades  of  existing  assets will  help  defer 

7 The supply gap is acute in Myanmar’s largest city, Yangon, which accounts for over 40 percent of the total electricity demand while holding only 20 percent of the generation capacity. Limited transmission capacity prevents electricity supplies from being brought from the rest of the country to the city. 8 The tender included two smaller plants using domestic gas and three larger projects that would use imported liquefied natural gas (LNG). Implementation timelines were short and came with steep penalties in case the deadline was missed. 9 Although coal only accounts for 2 percent of the current power generation, the Government has been planning to develop additional coal‐fired generation to address the power shortage. In August 16, 2019, MOEE publicly announced to Parliament that the Government is working with private sector firms to develop coal‐fired power plants, which would represent up to 30 percent of the power generation mix by 2030 in line with the Myanmar Energy Master Plan.  https://www.burmalibrary.org/docs22/2015‐12‐Myanmar_Energy_Master_Plan.pdf 10 The Republic of the Union of Myanmar. 2015. Myanmar' s Intended Nationally Determined Contribution–INDC.  https://www4.unfccc.int/sites/ndcstaging/PublishedDocuments/Myanmar%20First/Myanmar%27s%20INDC.pdf 

Page 14: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 9 of 74

investments in more carbon‐intensive coal generation, high‐cost emergency power, and LNG‐fueled generation. The  net  benefits  of  increasing  high‐efficiency  thermal  generation  capacity  by  300 MW  in  Yangon  have  been estimated at US$408 million  (between 2019 and 2030)  in net present value  (NPV)  terms, after accounting  for investment costs.  

Figure 1. Forecasted Supply/Demand Gap  Figure 2. Indicative Least‐Cost Generation Expansion Plan11 

Source: World Bank estimates based on data from MOEE. 

Source: World Bank staff. 

 (ii) Remove Bottlenecks to Provide Access to Modern Electricity Services to the Poorest  

9. Access to electricity from the public electric grid is unequal, with the poorest and ethnic minorities less likely to be connected. As noted earlier, the successful implementation of electrification efforts through the NEP has increased the rate of access to the public grid to around half of Myanmar’s population. However, the poorest households are yet to benefit from access to modern electricity services. According to the latest Myanmar Living Conditions Survey (MLCS 2017),12 80 percent of the bottom 20 percent of households were not connected to the public grid. According to the World Bank Myanmar Systematic Country Diagnostic,13 ethnic minority households living predominantly in areas away from the public grid were about 20 percentage points less likely to have access to electricity compared to households living in the central zone. To reach those who continue to lack access to modern electricity services, the NEP is extending the public grid and deploying decentralized electricity solutions. 

10. In rural areas, limited availability of power supplies and limited capacity in power substations are major constraints to on‐grid electrification. As demonstrated by  international experience, not only do power supply 

11  The  analysis was  conducted  using  the World  Bank  Electricity  Planning Model  for  2019–2030, which  optimizes  system‐wide  costs—including (annualized) capital cost of new plants, operating costs of new and existing plants, and cost of unserved energy and capacity reserve.  The  Electricity  Planning Model  considers  the physical  constraints  on  transmission between north  and  south Myanmar,  hydro energy  limits on a monthly basis,  reserve margin  requirement,  annual  limit on domestic  gas,  spinning  reserve  requirement, minimum variable renewable energy limit, and hourly profile of demand and solar/wind generation. 12 Central Statistical Organization (Ministry of Planning and Finance of the Republic of the Union of Myanmar), UNDP, and World Bank. 2018. Myanmar Living Conditions Survey 2017: Key Indicators Report. https://www.undp.org/content/dam/myanmar/docs/Publications/PovRedu/MLCS‐2017.pdf.  13 World Bank. 2019. Myanmar Systematic Country Diagnostic. http://documents.worldbank.org/curated/en/507421574785059413/pdf/Myanmar‐Economic‐Transition‐amid‐Conflict.pdf 

 ‐

 10

 20

 30

 40

 50

2019 2020 2021 2022 2023 2024

TWh

Supply deficit Generation under construction

Existing supply Consumption

 ‐

 10

 20

 30

 40

 50

2020 2021 2022 2023 2024 2025 2026

TWh

Gen Exist+Cons Cap. New Hydro New GasNew LNG New VRE (incl. solar) ImportsNew Gen Rentals Consumption

+ RE -Solar

+ EfficientCCGTs

+ Imports

+ Hydro

Rentals

Page 15: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 10 of 74

shortages  discourage  the  Government  and  utilities  from  continuing  electrification  efforts,  but  persistent interruptions and voltage fluctuations also prevent households from adopting electricity, even when the public grid reaches their villages.14 In addition, power transformers, transmission, and distribution lines in Myanmar are often overloaded due to the rapid growth in demand; substations are also not well equipped with reactive power facilities. As a result, additional connections are denied or  if connected, households  in rural areas often suffer from low quality of services. 

12. Continued  efforts  to  deploy  decentralized  electricity  solutions  are  needed  to  reach  all  the  most disadvantaged households. A recent analysis based on geospatial tagging of the World Bank‐financed National Electrification Project beneficiaries (both grid and off‐grid) is presented in annex 6 (figure 6.2). It shows that the public grid is progressively reaching rural areas primarily in the central zones of Myanmar due to their proximity to the existing power network. At the same time, off‐grid solutions such as mini‐grids and solar home systems are being deployed in more remote villages, including conflict‐affected areas. The map (figure 6.1) in annex 6 shows that off‐grid beneficiary households of the National Electrification Project live in townships which are considered the most disadvantaged based on the Multidimensional Disadvantage  Index (MDI)15  score. Going forward,  the continued implementation of off‐grid solutions together with the phased rollout of the public grid will be needed to bring basic electricity services to all Myanmar households. 

14 World Bank. 2018. In the Dark: How Much Do Power Sector Distortions Cost South Asia? https://openknowledge.worldbank.org/bitstream/handle/10986/30923/9781464811548.pdf.  15 World Bank. 2018. Multidimensional Welfare  in Myanmar. The Multidimensional Disadvantage Index (MDI) uses data from the 2014 census to compare relative levels of nonmonetary development across all townships in the country. The index uses indicators relating to household education, health, water and sanitation, housing, employment and assets. A second form of  the  index, MDI‐2, places more weight on households with multiple disadvantages. 

Table 1. Electrification Rates and Welfare in the Yangon Region 

Districts  Electrification (percentage of households) 

MDI at the Township Levela 

North  76  1.9–9.4 

South  61  4.6–11.0 

West  100  0.9–5.17 

East  100  0.9–3.7 

Source: World Bank staff based on data provided by the Yangon Electricity Supply Corporation (YESC) and MDI‐2. Note: a. Provides the range of minimum and maximum MDI values at the township level within each district. The higher the index, the more disadvantaged the households living in the townships.  

11. In urban areas, the priority is to provide electricity access to the poorest households, who have  often been left  behind.  The  rate  of  access  to  the  electricity  grid  in Yangon  is  high  (87.7  percent)  when  compared  to  the national  average  (50  percent).  However,  more disaggregated access data shows, as illustrated in table 1, a stark  difference  in  electricity  access  across  different districts and townships. The most disadvantaged townships have  substantially  lower  electrification  rates,  suggesting that  many  of  the  poorest  have  been  left  behind.  For example,  in  the  southern  district,  households  living  in townships with low  electrification rates  have some of the most disadvantaged population in the Yangon region, with welfare  indicators  comparable  to  those  living  in  the Ayeyarwady  Delta  region.  This  can  be  explained  by  the growing  demand‐supply  deficit  (which  has  discouraged utilities  from  connecting  additional  consumers)  and  the lack of funding to finance the extension of the national grid.  

Page 16: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 11 of 74

 (iii) Improve the Environment for Investments 

13. Recognizing  the  large  investment  needs  to  reduce  the  growing  power  supply  gap,  the Government recently implemented two key policy reforms to improve the sector’s enabling environment for investments. First, building on analytical work carried out by the World Bank under the Energy Infrastructure Sector Assessment Program  (InfraSAP)16,  in  July  2019  the  Government  increased  electricity  tariffs  significantly  for  residential, commercial,  and  industrial  consumers, after a  five‐year gap of no  tariff  adjustments. The most affected were residential consumers with the highest consumption levels (above 200 kWh per month), whose tariff increased by 2.5 times, albeit from low levels. In addition, a lifeline tariff was established to reduce the impact of the increase on the poorest. The electricity tariff increase is expected to increase the system’s revenues by 80 percent, bringing tariffs close to current operational cost recovery levels.17 This measure has supported a substantial reduction in fossil fuels subsidies since thermal power generation accounts for the largest share of the system’s costs. Natural gas prices for domestic generation are not subsidized because they are close to export‐parity levels. Second, in January 2019 a ‘Project Bank’ and a Public‐Private Partnership (PPP) Center were launched to encourage private sector participation  in  strategic  sectors  such as power generation.  If properly  implemented,  this  initiative can improve inter‐ministerial coordination and help the Government prioritize and implement infrastructure projects that have the potential to attract private sector investment more effectively. 

14. Going forward, the remaining policy, regulatory, and institutional constraints will need to be addressed to facilitate faster and more efficient investments. On the policy front, the lack of a least‐cost development plan for the power sector limits selection and prioritization of projects based on objective criteria for both public‐ and private‐funded projects. In terms of regulatory constraints, the absence of an incentive framework for renewable energy  projects  and  inadequate  management  of  environmental  and  social  risks  limit  the  development  of investments in renewable and hydropower, respectively. To consolidate the gains with recent tariff increases, a methodology and process for regular tariff adjustments is also needed. Finally, the capacity of SEE staff needs to be strengthened to accelerate project implementation and reduce frequent delays and costs overruns in project implementation. For private sector‐led projects, government capacity also needs to improve to support bidding, negotiation, contract compliance, and monitoring. These and other key constraints identified in the World Bank’s Energy InfraSAP and recommendations to address them are presented in box 1. 

Box 1. Key Constraints on, and Recommendations to Improve, the Efficiency and Sustainability of Investments 

Constraints 

(a) The  lack  of  a  least‐cost  development  plan  and  competitive  tendering  processes  limits  the  selection  and prioritization  of  projects  based  on  objective  least‐cost  criteria.  The  use  of  unsolicited  proposals  and  direct negotiations has not resulted in reduced timelines for the negotiation and procurement of power projects. 

(b) The  increase  in  generation  costs  (for  example,  through  emergency  power  purchases)  threatens  the  financial viability of the power sector despite recent tariff increases. 

(c) Lack of government guarantees and foreign exchange convertibility in the Power Purchase Agreements increases investor risks. 

(d) Inadequate management of environmental and social risks, including issues around land acquisition, slows down projects significantly, particularly in the hydropower sector. 

16 World Bank. 2019. Myanmar: Energy Infrastructure Sector Assessment. 17 On April 3, 2020, the Government announced that all residential consumers will receive 150 kWh of free electricity during one month as an emergency measure to ease the economic  impact of the COVID‐19 pandemic for households. This payment waiver could adversely impact the financial position of the power sector, particularly if the measure is continued for an extended period. 

Page 17: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 12 of 74

 

Recommendations  

(a) Approve a least‐cost power development plan including a priority list of projects to be developed over the next 5‐7 years and implement competitive and transparent tendering processes for these projects. 

(b) Consolidate improvements in the sector’s financial viability resulting from the recent tariff increase by approving a transparent methodology and process for regular tariff adjustments to progressively cover investment costs.  

(c) Standardize  approval  processes  and  documentation  for  the  privately  financed  power  projects,  including  the adoption of standard format for Implementation Agreements and Power Purchase Agreements. 

(d) Identify environmental and social risks and integrate these into the project’s development process. To the extent possible, make unencumbered land available for projects.  

15. With substantial capacity challenges, the Government needs to create a more inclusive environment that provides opportunities for professional growth for women. According to information provided by MOEE, women  represent more  than  half  of  its  workforce  but  less  than  6  percent  occupy  technical  and managerial positions. Key findings of research18 conducted with MOEE staff suggest that women are unable to reach their full potential for professional growth and face a productivity gap. According to the survey, women indicate that due to  childcare  responsibilities,  (a)  they  are more  likely  to  be  distracted  (productivity)  than men  (49  versus  36 percent),  (b) mothers are more  likely  to have  to  take  time off work  (absenteeism)  than  fathers  (84 versus 68 percent), (c) they are also substantially more likely than men to have been unable to accept a job promotion (26 versus 0 percent), and (d) they are more likely to have been unable to attend training or studies (47 versus 32 percent).  Childcare  responsibilities  prevent  women  from  harnessing  career  opportunities  (promotions  and training) and negatively affect their potential for professional growth (productivity and absenteeism) as compared to men. In addition, the surveys reveal that about 14 percent of the employees interviewed, mostly mothers, bring their children below the age of 5 to work. Civil servants migrate from different points of the country to Naypyidaw, Myanmar’s capital,  far  from their  family support networks. The city has been established to host government offices and offers limited childcare options.  

(iv) Strengthen the Power Network Infrastructure for Increased Quality of Supply and Climate Resilience 

16. Network constraints and infrastructure vulnerabilities result in unreliable supply affecting households and  small  and  medium  enterprises  (SMEs).  Significant  constraints  in  the  transmission  system  prevent  the evacuation of low‐cost hydropower from the north to the main consumption centers of Yangon in the south and Mandalay  in  the  center,  aggravating  the  supply‐demand  imbalance.  The  power  network  lacks  adequate redundancy  and  a  single  fault  can  lead  to  cascade  tripping  of  facilities,  as  demonstrated  in  2016  when  16 countrywide blackouts were reported. As a result, Myanmar lags significantly behind its East Asian peers in all dimensions related to quality of electricity infrastructure.  

18 Surveys were undertaken to understand how childcare responsibilities affect employees working in MOEE in Naypyidaw, Myanmar. The survey covered 197 respondents out of a total population of 832 employees at the Electricity Power Generation Enterprise (EPGE) and at the Department of Power System and Control (DTPSC). It explored how childcare responsibilities affect employees and the ability of those with  preschool  children  to work  to  their  full  potential while  in  the workplace.  The  survey  used  a  similar  approach  to  a  recent  study conducted by the  International Finance Corporation (IFC) to explore the business case for employer‐supported childcare  in the private sector of Myanmar. Survey questions from that study were adapted for this public‐sector survey. 

Page 18: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 13 of 74

Figure 3. Impact of Unreliable Electricity Supply to Firms 

 

Source: World Bank staff based on the Myanmar 2016 Enterprise Survey. 

As  shown  in  figure  3,  according  to  the  latest available  Enterprise  Survey  for  Myanmar (2016), the share of small enterprises reporting electricity supply as being the biggest obstacle (15 percent) to doing business is double that of large firms (8 percent) and over three times the average  in  East  Asia  and  Pacific  region  (6 percent).  Low‐quality  services  also disproportionately  affect  low‐income households.  According  to  the  MLCS  2017,  40 percent  of  Yangon  residents  reported  voltage fluctuations as their main concern, compared to just 20 percent at the national level. Unable to afford  backup  power  generators  and  voltage regulators,  lower‐income households bear  the costs of long outages and damages to electrical equipment. 

17. The required development of power infrastructure represents an opportunity to improve the resilience of electricity services to natural hazards and climate change. Due to its location, Myanmar is among the world's most  hazard‐prone  countries.19  Climate  change  is  exacerbating  the  country's  vulnerability  to  periodic  floods, earthquakes, fires, storms, cyclones, and droughts. However, climate hazards are not considered at the planning stage and  there  is no emergency preparedness  to enable quick and effective  recovery of electricity  supply  to affected areas. For example, a rapid assessment of climate hazards revealed that 80 percent of the country’s high‐voltage substations are in areas highly prone to earthquakes. Yet, high‐voltage equipment is often not adequately anchored, exposing substations to fire and explosion risks due to oil leakages ignited by electric faults. Common barriers to the adoption of resilience measures include: (a) lack of sufficient data on the spatial distribution of natural hazards,  (b)  low understanding of  the vulnerability of  assets  and  the overall  power  system  to natural hazards and climate change, and (c) lack of resources and high perceived costs for the implementation of resilience measures. 

World Bank Group Support 

18. Making  available  electricity  access  for  the  whole  population  through  grid  extension  and  off‐grid renewable energy solutions is at the core of World Bank Group engagement in Myanmar. The World Bank Group is one of the leading developing partners in the energy sector. The World Bank supports the implementation of the  Government’s  NEP  through  the  National  Electrification  Project  (P152936;  IDA  credit  of  US$400  million equivalent). As of November 2019, more than 1.5 million people had benefited from access to modern electricity services from solar home systems, renewable energy based mini‐grids, and grid extension under the World Bank‐financed National  Electrification  Project.  The World  Bank’s  contribution  in  developing  the  electrification  plan helped leverage substantial financing from development partners, including EUR 30 million of soft loans in Italian assistance and EUR 40 million of loan and grants from KfW, the German development bank. The IFC Lighting Global Program assists companies in creating a sustainable market for high‐quality off‐grid renewable energy solutions. IFC also provides equity and debt financing to Yoma Micro Power to generate and distribute electricity to power 

19 Eckstein, D., M. L. Hutfils, and M. Winges. 2019. Global Climate Risk Index 2019. Germanwatch. https://germanwatch.org/sites/germanwatch.org/files/Global%20Climate%20Risk%20Index%202019_2.pdf  

15.18.4

68.1

96

0

20

40

60

80

100

Small firms Large firms Small firms Large firms

Bigeest obstacle to doing business Percentage of firms owning agenerator

Unit based

 on the indicator

EAP average Myanmar Lower‐middle income average

Page 19: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 14 of 74

telecom towers in rural Myanmar and off‐grid communities using solar‐based micro power plants and mini‐grids. Complementing the Government’s efforts, the World Bank and IFC also support results‐based financing for off‐grid solar to accelerate the development of a sustainable, private sector‐led market for quality solar products and increase the penetration of solar PV through solar home systems and mini‐grids. 

19. To support  the electricity access agenda,  the World Bank and  IFC contribute to the development of private‐led power generation, with a focus on low‐carbon energy technologies. The World Bank Group’s support is focused on helping Myanmar attract private investments to realize its large renewable energy potential. The Bank and the IFC have joined forces to provide advisory services for the planning, preparation and implementation of  large‐scale  grid‐connected  solar  and  other  renewable  energy  projects  through  public‐private  partnership approaches. The government recently identified these projects as a high priority to promote investments in its COVID‐19 Emergency Relief Plan.20 In 2016, IFC and the Multilateral Investment Guarantee Agency supported the first  competitive  bidding  for  an  independent  power  producer  in  the  country,  a  225  MW  gas‐fired  plant  in Myingyan,  which  stands  out  as  a  successful  example  of  private  sector  participation.  The  World  Bank  also supported the rehabilitation of existing inefficient gas‐fired power plants by extending financing for the Electric Power Project (EPP, P143988, IDA financing US$140 million), for the rehabilitation of the Thaton CCGT power plant located in Mon State to add 110 MW of additional capacity and increase efficiency in power generation. The power plant can generate four times the amount of electricity using the same amount of natural gas, thereby allowing the delivery of improved electricity services to 830,000 people.21  

20. A  comprehensive  program  of  advisory  services  and  technical  assistance  underpins  the World  Bank Group’s substantial dialogue in the sector. The World Bank’s technical assistance and capacity building under the Myanmar  Energy  Programmatic  Advisory  Services  and  Analytics  project  (P158303)  informed  the  design  and implementation of some of the key policies in the sector, including the design of the Government’s NEP and the assessment of the electricity sector’s financial viability and tariff reform. The World Bank has also provided just‐in‐time policy advice on key sector topics to the National Economic Committee, which is the highest policy‐making body  in  the  country.  The  World  Bank  is  also  working  with  MOEE  in  developing  an  electricity  tariff‐setting methodology,  which  is  critical  to  supporting  the  expansion  of  access  to  electricity,  renewable  energy development, and the financial viability of the sector. Advisory work is helping power utilities move toward more efficient  gas‐to‐power  conversion  and  improve  dispatch  practices.  Finally,  to  further  support  the  private‐led investments,  support  for  institutional  capacity‐strengthening  for prioritizing and coordinating  investments will continue to be provided to the Project Bank and the PPP Center. 

21. More recently, the World Bank is providing technical assistance to MOEE to inform the power sector’s climate adaption and resilience strategy. Financed by the Global Risk Financing Facility (GRiF), analytical work is being carried out by the World Bank under the Protecting Power Infrastructure and Energy Systems project. This ongoing work focuses on the following aspects: (a) identifying the risk exposure of power assets to climate change and disasters;  (b) designing risk mitigation strategies,  including at  the planning stage, and  identifying relevant policies and other types of interventions from national and central to local and community‐based measures; and (c)  identifying specific  investments and activities that would support  the  implementation of  the  identified risk mitigation strategies. Once completed, this analytical work will inform the identification of specific investments and measures to be implemented by MOEE. 

20 The Government of Myanmar. 2020. Overcoming as One: COVID‐19 Economic Relief Plan.  21 Estimate based on an annual output of 770,000 MWh, average annual household consumption of 3,977 MWh, and 4.3 people living in each household. 

Page 20: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 15 of 74

C. Relevance to Higher Level Objectives  

22. As part of its effort to bring electricity access to all of Myanmar’s people, the Government has sought the World Bank’s support for efforts to  improve the availability and reliability of power supply through the proposed Power System Efficiency and Resilience Project. The Government considers the provision of universal electricity access and the improvement of service delivery among its highest priorities to improve living conditions and  economic  opportunities  across  the whole  population.  The  proposed  project would  complement  ongoing government efforts by ensuring  that adequate and better‐quality electricity  supply  is available  to support  the universal access goal. 

23. The proposed project will help address Myanmar’s key energy challenges by:  (a) ensuring adequate supply; (b) increasing the capacity and climate resilience of critical infrastructure; and (c) improving the capacity of key  sector entities  in  the planning, design, and  implementation of projects. Additional power  supply  is a necessary  condition  for  consolidating  progress  and  continuing  the  implementation  of  the  country’s  universal electrification program. The investment  in upgrading the existing power plant will allow to help address acute power  shortages  in  the  country’s main  economic  center  through energy efficiency  improvements  in  gas‐fired generation. By improving the supply‐demand balance in Yangon, the project will enable the implementation of the electrification program in the Yangon region, benefiting the most disadvantaged households, and it will free up substantial resources to supply the rest of the country. The investment in the reinforcement and rehabilitation of the existing power infrastructure will help improve its resilience to climate events and increase its capacity to reduce  system  constraints,  thus  enabling  future  extension  of  the  distribution  network  to  reach  unserved  or underserved households. Finally, the technical assistance and Hands‐on Extended Implementation Support (HEIS) that will be provided under the project are expected to help build the capacity of the two main sector entities in charge  of  power  infrastructure  development:  the  Electric  Power  Generation  Enterprise  (EPGE)  and  the Department of Power Transmission and Systems Control (DPTSC). 

24. The  project  will  support  the  national  development  priorities  laid  out  in  the Myanmar  Sustainable Development Plan (MSDP)22 for 2018–2030 and is consistent with the country’s commitment to a low‐carbon development  path.  The MSDP  is  the  first  comprehensive  government  vision  for  a  democratic,  peaceful,  and prosperous country. Pillar 2 (goal 3, strategy 3.6) of the MSDP aims at building priority infrastructure to facilitate sustainable growth and economic diversification. Pillar 3 (goal 5, strategy 5.4), providing affordable and reliable energy to populations and industries, recognizes the importance of (and the direct link between) improved access to electricity and greater economic opportunities for households and firms,  including SMEs  in both urban and rural areas. Pillar 3 (goal 5, strategy 5.2), which seeks to increase climate change resilience and reduce exposure to disasters and shocks,  identifies  the development of resilient  infrastructure as an opportunity  to reduce the country’s  exposure  to  climate  change  and  embark  on  a  low‐carbon  development  path.  Finally,  the  MSDP recognizes gender empowerment, equity, and inclusion as a cross‐cutting priority to be mainstreamed into all its pillars. The project will support Myanmar’s INDC for climate mitigation and adaptation by: (i) reducing the power sector’s overall greenhouse gas (GHG) emissions through fuel savings and deferred investments in more carbon‐intensive  fuels,  such as  coal;  (ii)  increasing  the overall  efficiency of  the power  system; and  (iii)  increasing  the resilience  of  the  power  network  against  climate  events.  Recognizing  a  limited  ability  to  achieve  its  vision  for sustainable  development,  Myanmar  INDC  calls  for  support  from  the  international  community  for  financial 

22 The Government of the Republic of the Union of Myanmar. 2018. Myanmar Sustainable Development Plan, 2018–2030. 

Page 21: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 16 of 74

resources  and  capacity  building.  In  responding  to  this  call  for  assistance,  this  project  also  represents  an opportunity to provide advisory services to steer the transition towards a more sustainable future.  

25. The project also supports the new World Bank Group's Country Partnership Framework (CPF) FY20‐23 (Report No. 147607‐MM) and complies with the World Bank’s ‘Maximizing Finance for Development’ (MFD) approach.23  Specifically,  the  project  will  foster  responsible  private  sector‐led  growth  for  inclusive  economic opportunities, the second focus area in the new CPF (Objective 2.3, Narrow the infrastructure and technology gap). The project seeks to create basic infrastructure to facilitate increased and improved access to basic electricity services,  improving  individuals’  well‐being  and  economic  opportunities  at  the  community  level.  In  addition, investments aimed at improving the transmission system’s climate resilience will contribute to the fourth focus area of the new CPF, enhancing climate and disaster resilience. The proposed project  lays the groundwork for adopting the MFD approach. The Ywama power plant site is not well suited to private financing. A pre‐feasibility study completed for all state‐owned power plants in the Yangon area identified the Ywama site as the least viable for private sector financing due to: (a) the limited space available, which requires the new plant to share common auxiliary  facilities  with  the  remaining  state‐owned  units;  and  (b)  substantial  coordination  challenges  during construction to ensure continued supply from the remaining units to the Yangon region. The World Bank and IFC have worked closely with the Government to remove barriers to private participation in the power sector (see section II.E, Rationale for Bank Involvement and Role of Partners). Throughout project implementation, this work would continue through the World Bank’s extensive policy dialogue and technical assistance in collaboration with IFC  efforts  to  cascade  private  investments  in  the  energy  sector,  focusing  on  renewable  energy.  The  project supports the World Bank’s twin goals of eliminating extreme poverty and boosting shared prosperity and it was also designed using  the  Inclusion and Peace  Lens  (IPL,  see  annex 3)  to  ensure  that  it  is  conflict  sensitive  and inclusion focused. 

II. PROJECT DESCRIPTION

 

A. Project Development Objective  

26. The Project Development Objectives (PDO) are to increase the output and efficiency of power generation and improve the resilience of the power network in support of the government’s program on universal electricity access. 

PDO‐Level Indicators 

27. The achievement of the PDO will be measured by the following indicators: 

(a) Projected energy or fuel savings (in megajoules, or MJ) – core indicator (b) Generation capacity of energy constructed or rehabilitated (MW) – core indicator (c) Annual outages in targeted substations (hours) (d) Disadvantaged/vulnerable people benefiting from access to electricity or improved quality of 

service (number, thousand) 

23  MFD  is  the World  Bank  Group’s  approach  to  systematically  leveraging  all  sources  of  finance,  expertise,  and  solutions  to  support developing countries’ sustainable growth (https://www.worldbank.org/en/about/partners/maximizing‐finance‐for‐development).  

Page 22: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 17 of 74

28. Intermediate indicators are as follows: 

(a) Plant construction progress (percentage) (b) Thermal efficiency of energy conversion in the Ywama gas power plant (percentage) (c) Gap in annual time spent on childcare during working hours between male and female MOEE staff 

benefiting from the childcare pilot (days) (d) Implementation support received up to satisfaction to meet technical specifications, contract 

oversight, and safeguards monitoring contractual requirements (yes/no) (e) Mobile substations deployed for fast response and recovery to climate events (number) (f) Grievances responded to and/or addressed through the functional Grievance Redress Mechanism 

(GRM) available to citizens and within the stipulated response time (percentage)  

B. Project Components 

29. The proposed project comprises two components financed through an IDA credit. The main investment component, which supports the upgrading of the Ywama power plant (Component A), will be implemented by EPGE. The component focusing on improving the resilience and capacity of the power network (Component B) will be  implemented by DPTSC. The technical assistance to EPGE and DPTSC will be provided through external consultancy support financed under Components A and B, respectively.  

Component A: Upgrading Ywama Power Generation Units (US$290 million)  

30. The component will finance the replacement of old gas and steam turbines in the Ywama power plant with  a  highly  efficient,  state‐of‐the‐art  CCGT.  This  will  increase  the  plant’s  efficiency  from  the  current  19.9 percent to approximately 55 percent, thereby increasing its electricity output by 2.5 times using the same amount of gas. The Ywama power plant is in the suburbs of Yangon City, along the Hlaing River. It is a brownfield area partly occupied by old and inefficient gas and steam turbines, with a combined capacity of 240 MW. Due to the acute power shortages in Yangon, this equipment is still under operation despite having one of the lowest thermal conversion efficiencies of all the state‐owned gas‐fired generation plants. The efficiency and capacity upgrade will ensure that the maximum electricity output is generated to alleviate Yangon’s power shortage while using the space available within the existing footprint of the plant. Therefore, the proposed project will finance the energy‐efficient upgrade of the existing units with a highly efficient CCGT plant with a minimum capacity of 250 MW and up to approximately 300 MW (net at site conditions)24 and a thermal efficiency of above 50 percent. The initial budget allocation of US$285 million for the power plant is to be revised within the overall loan amount based on the outcome of the bidding process.  

31. The upgrade will be undertaken as a  full  turnkey project  to help address  technical  and operational challenges during implementation. In addition to the gas and steam turbines that will be upgraded, the Ywama power plant site includes a 240 MW open‐cycle gas power plant and gas engines totaling 52 MW capacity, which are owned and operated by EPGE and a private company, respectively.25 Continued supply from the remaining units in the plant is critical to ensuring a stable supply to the city of Yangon throughout the construction of the 

24 Bidders will be allowed  to propose a different  capacity  for  the CCGT as  long as  it  respects all  specifications outlined  in  the bidding documents (maximum gas consumption, equipment to be  installed  in the existing space available, and other  functional specifications). Therefore, the specific capacity of the CCGT will only be determined once the bidding is concluded.  25 All  these generation units  share a  connection  to  gas  supply  from  the Yadana offshore  field  and  they are  connected  to an adjacent switchyard, which  EPGE  is  currently  upgrading  to  a  gas‐insulated  switchyard with  financing  from  the  Japan  International  Cooperation Agency (JICA). 

Page 23: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 18 of 74

new CCGT, creating operational and coordination challenges during construction. If required, investments such as the relocation of EPGE staff housing adjacent to the plant (to mitigate noise and vibration impacts on employees) would  also  be  financed  by  the  IDA  credit.  Given  the  country’s  climate  vulnerabilities,  the  new  CCGT will  be designed  to withstand  extreme weather  conditions  including monsoon,  strong winds,  cyclones,  flooding,  and seismic events. To help address these challenges, the project will be undertaken as a full turnkey contract covering the demolition, design, supply, installation, testing, and commissioning of the new CCGT.  

32. In  addition,  technical  assistance will  be  provided  to  EPGE  for  project  implementation  and  contract management. Specifically,  two key consultancy contracts will be  financed:  (a) an owner’s engineer  to support EPGE throughout the procurement processes and project implementation, and (b) an independent consultancy firm to monitor environmental and social safeguards issues. Additional technical assistance to build capacity of EPGE and MOEE for policy making and regulation  in the power sector may be provided should the need arise during  project  implementation.  Finally,  to  help  reduce  the  gender  productivity  gap  at work  due  to  childcare responsibilities, the project will support the setup of a childcare pilot at MOEE. Specifically, this component will finance: (a) the preparation of a detailed rollout plan to guide MOEE in setting up the pilot and (b) initial start‐up funds  to  cover  setup  costs  required  for  the operationalization  of  the  pilot.  The  initial  allocation  for  technical assistance activities and the operationalization of the childcare pilot is US$5 million. 

Component B: Improving Resilience of the Power Network (US$60 million) 

33. This  component  will  finance  investments  and  measures  in  existing  substations  aimed  at  reducing system constraints and strengthening the resilience and preparedness of the power network against climate change  and  disasters.  Investments  will  include  transmission‐related  equipment, mobile  substations,  and  the implementation of adaption measures to protect existing assets functionality against the impact of climate change and emergencies. This component will also support the quick rehabilitation and recovery of the power system from climate  shocks or disasters during  the  life of  the project. Activities under  this  component will  cover  the following  aspects:  (a)  reinforcing  high‐voltage  equipment  at  substations  and/or  substation  rehabilitation  to reduce  system  constraints,  increase  system  capacity,  and  improve  network  reliability  to  meet  at  least  N‐1 redundancy criteria; (b) enhancing emergency preparedness and management capacity through investments in adaption measures to protect and harden equipment against impacts of climate change and disasters such as heat waves, flooding, hurricanes, earthquakes, and landslides; (c) enabling quick and effective recovery of the power system by procuring specialized equipment and spare parts; and (d) supporting the deployment and installation of such equipment in line with prearranged preparedness plans if eligible events happen during the life of the project. Future additional financing may be sought from the GRiF to support the preparedness measures under this component and establish a mechanism that can provide the required funding for recovery after a climate shock or disaster.26 Transmission network equipment to be financed under this component will include, but not be limited to, mobile substations, power and current transformers, power and shunt reactors, switch bays, and protection and control devices. The initial allocation for investments under this component is US$55 million. 

34. Power  substations  and  measures  under  this  component  will  be  prioritized  based  on  their  relative contribution to support for the implementation of the NEP and improvements in the quality of supply, focusing 

26  This would  support  establishing prearranged  funding  linked  to  emergency preparedness  plans  to be developed by DPTSC  for  quick recovery of the power system to ensure continuity of services. A GRiF grant could help DPTSC and MOEE set up a financing strategy by complementing project  funds under  this  component,  thus  leveraging  the work carried out by  the Ministry of Planning and Finance  to establish the Southeast Asia Disaster Risk Insurance Facility, a regional catastrophe risk insurance pool for ASEAN countries. 

Page 24: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 19 of 74

on areas where disadvantaged households live. The selection of investments will be based on technical analysis including the following key parameters: (a) substations that lack adequate capacity and/or redundancy necessary to support grid extension for electrification purposes, (b) assets that are the most vulnerable to climate events, and (c) substations that serve households suffering from low quality of electricity supply. Based on the technical screening, substations that serve a substantial share of disadvantaged households27 will be prioritized to benefit from the project’s investments. The development of new substations or new transmission lines and substations would not be financed since the project will be implemented in brownfield locations. Also, investments in areas where there is active conflict will not be supported under the project.28 

35. Technical  assistance  will  help  strengthen  the  capacity  of  DPTSC  on  resilience  aspects  and  support project implementation. Technical assistance will be provided to develop and implement policies, strategies, and measures to increase climate change and disaster resilience of the power system. Additional consultancy services will  support  DTPSC  in  the  implementation  of  the  project  activities,  including  in  the  preparation  of  technical specifications,  contract  oversight,  and  safeguards  monitoring. The  initial  allocation  for  technical  assistance activities is US$5 million. 

C. Project Beneficiaries 

36. The project will benefit the poorest households by enabling electrification of the most disadvantaged townships in the Yangon region and across the country. Capacity and efficiency upgrades in the Ywama power plant will directly benefit the most disadvantaged households in the Yangon region by making available adequate and reliable electricity supply to enable the implementation of planned investments under the NEP. The Yangon regional government and YESC have developed a detailed implementation plan and secured funding to provide electricity access to all townships across the region within the next three to four years. This electrification program will be undertaken in close collaboration with the World Bank, under the National Electrification Project, and in coordination with other development partners that are financing improvements in the high‐ and medium‐voltage network. As discussed in section I.B, villages in the southern and northern districts which remain unconnected to the national grid are home to approximately 300,000  individuals  facing the most disadvantages  in the Yangon region. In addition, investments in the transmission component would also benefit poor households. The project financing will target power substations based on their ability to facilitate electricity access, with a focus on those substations covering disadvantaged townships.  

37. Firms—particularly  SMEs,  which  are  key  to  supporting  the  economic  transition  and  sharing  its benefits—will benefit from improved quality and reliability of electricity supply. As mentioned in section I.B, SMEs suffer disproportionately from low quality of electricity services when compared to large firms. Small firms reportedly suffer from about 13 outages in a typical month; this is three times more than firms in the East Asia and Pacific region (4.5 outages per month) and almost 50 percent higher than the average small firm in lower‐middle‐income countries. However, only 64 percent of them own a generator (compared to 96 percent of large firms),  mostly  because  of  affordability  issues.  Investments  in  the  Ywama  power  plant  in  Yangon  and  in  key substations will benefit  firms, particularly SMEs,  through:  (a)  increased hours of  reliable power  supply due  to avoided load shedding and blackouts; (b) reduced costs due to outages, resulting in lower revenue losses; and (c) 

27 The criteria will be based on the MDI (World Bank 2019), which identify the most disadvantaged townships by comparing relative levels of nonmonetary development across all townships in the country. 28 These areas are defined as locations where there is continuing or has been recent violence as monitored by the World Bank based on data from the Myanmar Institute for Peace and Security. 

Page 25: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 20 of 74

higher power‐supply quality  through more‐stable voltage and  frequency, which extends  the operating  lives of electrical and industrial appliances and machines. 

38. In addition, the project will benefit the population in the rest of the country by reducing the power system’s  vulnerability  to  climate  change,  system  costs  and  losses,  and  GHG  emissions.  Investments  in  the transmission component will help improve the system’s resilience to climate change and natural disasters. Also, based on the indicative least‐cost plan developed by the World Bank, the project will contribute to reducing the power system’s costs by 5 percent by: (a) displacing higher‐cost and more carbon‐intensive generation such as coal,  emergency  power,  and  LNG‐fueled  power  plants;  (b)  reducing  the  volume of  gas  consumed per  unit  of electricity generated; and (c) reducing system transmission losses by about 11 percent, given that generation will take place closer to the main demand center. The project will also result in the reduction in the system’s GHG emissions by 12.3 million tons of CO2 equivalent until 2030.29 The project’s climate co‐benefits are related to: (a) climate change mitigation by upgrading the Ywama power plant30, and (b) the adaption of the power system to climate vulnerabilities through the design of the new CCGT and investments in the transmission infrastructure. 

39. Finally, power sector SEEs will also benefit from increased capacity and a diversified labor force. EPGE will  strengthen  its  capacity  in  project  implementation  and  supervision  of  large  and  complex  thermal  power projects. DPTSC will  enhance  its  understanding of  how  climate  change  and  disaster  risks  affect  power  sector planning  and  operation  and  improve  its  capacity  to  implement  long‐term  planning  and  climate  resilience measures. In addition, by exposing DPTSC to international procurement practices, its capacity to engage in larger and more  complex  procurement  processes would be  strengthened. MOEE  and  the  sector  entities would  also benefit from increased workforce diversity and female employees’ availability during working hours, as a result of the setup of the childcare pilot. 

D. Results Chain 

40. The proposed project  focuses  on  rehabilitating  the  Ywama power  plant  and  activities  to  improve  the reliability of the power system, particularly its resilience to climate events. Capacity and efficiency upgrades in the power plant would result in increased power output, with the same amount of gas available, in the Yangon area and enable  the  implementation of  the universal  electricity  access program.  Together with  investments  in  the transmission network, these activities will contribute to longer‐term outcomes, including: (a) improved access to reliable and affordable electricity  services  for households,  including disadvantaged households  in  Yangon and targeted areas;  (b) an  improved response to climate change mitigation and adaptation and transition towards low‐carbon technologies; and (c) improvements in the enabling environment and in sector entities’ capacity to increase public and private investments. Figure 4 illustrates the results chain in detail.  

29 According to the Joint Report on Multilateral Development Banks’ Methodology for Tracking Climate Finance. Avoided CO2 emissions are valued in line with World Bank Guidelines on Shadow Price of Carbon in Economic Analysis (see further details in the Economic and Financial Analysis section). 30 The investments in Ywama power plant will replace the existing inefficient 280 MW gas‐fired generation units with a highly efficient CCGT of up to 300 MW, including the partial demolishment of the existing installed capacity. The capacity expansion represents about 6 percent of the capacity to be installed. Out of all the capacity to be replaced, 240 MW will be kept in the site as back‐up options to respond to emergency events or to maintain supply during maintenance of the new CCGT if needed. Due to gas supply and infrastructure constraints, it will not be possible to have the new CCGT and the back‐up 240 MW capacity operating regularly and simultaneously during the lifetime of the new assets. It is not expected that these constraints will change over the lifetime of the existing asset. The system‐wide least‐cost plan conducted during the preparation of this project shows GHG emissions reduction of the overall system compared to the baseline scenario, where this project does not materialize and the existing equipment continues operation over the medium‐to‐long term.  

Page 26: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 21 of 74

Figure 4. Results Chain of the Power System Efficiency and Resilience Project 

Source: World Bank staff. Note: TA = Technical assistance. 

 E. Rationale for Bank Involvement and Role of Partners  

42. The World Bank’s support will bring  international best practices and know‐how to help address  the country’s generation challenges and pioneer approaches to mainstreaming climate resilience for critical power infrastructure. Since Myanmar started its transition, the World Bank Group has supported investments to bring state‐of‐the‐art  generation  technology  to  help  reduce  the  growing  supply‐demand  gap.  These  efforts  have complemented the World Bank Group’s main engagement in the universal electricity access agenda through both public and private sector approaches, as described  in  section  I.B. This project would be a  continuation of  the World’s Bank  leading  role  in bringing good  international practices and know‐how  to undertake efficiency and capacity upgrades  in a  challenging power generation  site. World Bank  support will  also help  the Government pioneer approaches and measures to reduce the risks and impacts of climate change and disasters to critical power infrastructure. By providing access to know‐how and finance, the project will support cost‐effective measures to overcome key barriers to mainstreaming climate resilience into the planning, project design, and implementation phases of power transmission projects. 

43. The World Bank’s financing and advisory‐services support for the proposed project complements other development partners’ activities in the power sector, coordinated by MOEE through the Energy and Electricity Sector  Coordination  Group.  Many  development  partners  are  active  in  Myanmar’s  power  sector.  In  the implementation of the Government’s NEP, there  is substantial support from bilateral  institutions such as KfW, Gesellschaft für Internationale Zusammenarbeit, and the Italian Government. These projects are implemented in close cooperation with the World Bank‐funded electrification project. To help develop network infrastructure, the 

Page 27: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 22 of 74

Asian  Development  Bank  and  JICA  are  providing  significant  financing  to  SEEs  for  the  implementation  of  grid development  and  strengthening,  including  the  construction  of  the  country’s  500  kV  transmission  backbone. Finally,  in  the  power  generation  segment,  the  French  Development  Agency  and  JICA  are  supporting  the development  of  public  sector  generation  projects  in  hydropower  and  one  natural  gas‐fired  power  plant.  The implementation of the proposed project has been coordinated and complements JICA’s activities. Power supply from the new CCGT will be delivered through the high‐voltage Ywama substation which is being rehabilitated by EPGE with financing from JICA. The overall coordination among development partners is led by MOEE through the Energy and Electricity Sector Coordination Group and the Electricity Access Sub‐Sector Coordination Group. The coordination group is facilitated by JICA and the World Bank and the coordination takes place on a regular basis. 

F. Lessons Learned and Reflected in the Project Design  

44. Early implementation—facilitated by enhanced hands‐on support, committed partners with dedicated staff, and policy dialogue anchored in a strong country program in the energy sector—has been fundamental to the project design. 

(a) Early  project  implementation.  The  project  design  builds  on  the  extensive  experience  acquired during  the  implementation  of  the  EPP  (which  closed  in  March  2020).  Lack  of  capacity  in implementing agencies (IAs) to handle large and complex procurement contracts led to significant delays.  To  address  the  capacity  constraints  and  expedite  project  implementation,  the  following measures will be introduced: (i) the IAs will initiate the procurement process for the upgrading of the  power  plant  before  loan  approval;  (ii)  HEIS,  as  allowed  by  new  procurement  regulation  in countries  affected  by  fragility,  conflict,  and  violence  (FCV),  will  be  provided  on  technical  and procurement matters to complement the external consultancy support by the owner’s engineer; and (iii) the power plant upgrade will be undertaken under a turnkey design, supply, and installation (DSI) contract to reduce the burden on procurement and contract management. 

(b) Committed partners. The World Bank Group’s FY15‐19 Myanmar Completion and Learning Review (Report  No.  147607‐MM)  finds  that  stronger  commitment  by  line  ministries  results  in  stronger staffing across all fields (technical, safeguards, fiduciary) of IAs, which is critical for more efficient project implementation. Therefore, the following actions have been undertaken: (i) MOEE and the IAs, EPGE and DPTSC, have already put in place full‐fledged Project Implementation Units (PIUs) with dedicated staff, and (ii) MOEE management has committed to expediting government approvals for the project. These actions are already yielding results: the PIUs have been actively involved during project preparation,  and procurement  activities have been  initiated before  the proposed  loan  is approved by the World Bank. In addition, MOEE has demonstrated its commitment to addressing the gender gap identified in the project through the implementation of the childcare pilot. 

(c) Policy  dialogue  anchored  in  a  robust  country  program. Globally,  an  important  lesson  has  been learned  about  the  relevance  of  undertaking  investment  projects within  a  policy  framework  that ensures  their  sustainability.  In  Myanmar,  the  World  Bank  Group’s  analytical  work,  frequently conducted  in parallel with project  implementation, has contributed  to  important policy  changes, such as the recent electricity tariff reform, national electrification policies, and introduction of best practices  for  engaging  private  sector  financing.  This  engagement  will  continue  during  the implementation of this project, anchored in substantial ongoing advisory and lending projects, such as the programmatic energy sector policy dialogue project and the National Electrification Project.

Page 28: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 23 of 74

(d) Design  considerations  regarding  childcare.  Access  to  reliable,  affordable,  and  quality  childcare services  can  benefit  employers  in  terms  of  improved  worker  productivity.  Childcare  activities supported  under  the  project  build  on  key  findings  from  a  review  of  lessons  learned  during  the implementation of similar activities in the World Bank portfolio.31 First, the review emphasizes that childcare  services  should  be  piloted  before  being  mainstreamed  to  ensure  their  quality  and applicability.  The  childcare  at MOEE will  be  designed  as  a  pilot,  which  will  help  track  data  and information  to  inform follow‐up activities  to mainstream these  services  to serve a  larger pool of MOEE employees and/or other government ministries. Second, a sound, but not overly complicated, diagnostic will be undertaken to identify key aspects of the demand and supply of childcare early during project implementation. This is particularly relevant in the context of this project and, more broadly, FCV countries, where lack of  information and baseline data for indicators is frequently a significant challenge. Finally, the partnership across government entities is highlighted in the review as  an  instrumental  factor  in  delivering  childcare  services.  The  project  will  support  a  close collaboration  of MOEE with  the Ministry  of  Social Welfare  (MOSW), which manages  a  series  of programs  to  support  early  childhood development,  including providing  training  for  the  childcare industry employees. 

III. IMPLEMENTATION ARRANGEMENTS 

 

A. Institutional and Implementation Arrangements 

45. The proposed project will be implemented by EPGE and DPTSC under the oversight of MOEE. The project will be financed by an IDA credit to the Ministry of Planning, Finance, and Industry, which will make the proceeds of the credit available to EPGE and DPTSC. Under the overall oversight of MOEE, the two entities have put in place dedicated PIUs comprising project directors, technical specialists, procurement specialists, financial management specialists,  and  environmental  and  social  specialists.  Both  entities  will  rely  on  their  existing  organizational structures and processes to implement the procurement and financial management tasks related to the project. Annex  1  provides  further  details  of  the  implementation  arrangements  and  the  implementation  support  plan, including a PIU organization chart.  

B. Results Monitoring and Evaluation (M&E) Arrangements 

46. Monitoring  the  implementation of  the proposed project will  involve  the evaluation of performance indicators  as  included  in  the  Results  Framework.  The  EPGE  and  DPTSC  PIUs  will  monitor  the  progress  of Components A and B, respectively, against the agreed performance indicators (see section VI, Results Framework and Monitoring). The PIUs are responsible for collecting data and updating the Results Framework, with support from the owner’s engineer, and  reporting progress every  six months. These biannual progress  reports will be submitted to the World Bank. The reports will include updates on the functionality of the GRM, which will be in place for citizen engagement and submission of any complaint, concern, or issue that might arise in relation to the project (see section IV.C, Safeguards). The project will also carry out annual impact assessment surveys during 

31 Haddock, S., A. Raza, and G. Palmisano. 2019. Addressing Childcare in the World Bank Portfolio: Approaches, Experiences, and Lessons Learned.  World  Bank  Group.  http://documents.worldbank.org/curated/en/646911578638203068/pdf/Addressing‐Childcare‐in‐the‐World‐Bank‐Portfolio‐Approaches‐Experiences‐and‐Lessons‐Learned.pdf

Page 29: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 24 of 74

implementation  to monitor  the  impact  of  the  childcare pilot—i.e.,  the extent  to which  it  reduces  the  gender productivity gap of staff benefiting from the childcare services (see section IV.C, Safeguards). 

47. The project will promote citizen engagement by monitoring the grievances responded as well as publicly and periodically disclosing this information. The main beneficiaries of the project will be households, SMEs, and other  firms  connected  to  the  public  power  grid  in  the  Yangon  region  (see  section  II.C,  Project  Beneficiaries). Because of the technical characteristics of the investments, specific citizens and firms or their groups cannot be identified to conduct beneficiary satisfaction surveys. Therefore, the project will monitor how citizens are affected by the project activities during implementation. The objective would be to ensure that citizens have functional mechanisms available to pose grievances and that these are responded to and, to the extent possible, addressed. The indicator will be used to capture the rate of grievances responded to and the results will be publicly disclosed. 

C. Sustainability 

48. The project has been designed considering key sustainability aspects.  For Component A, EPGE has a proven track record in operating and undertaking routine maintenance of gas‐fired power plants, which will be enhanced with  experience  in  the  installation,  commissioning,  and  operation  of  the  recently  completed  high‐efficiency Thaton CCGT. In addition, the project accounts for key spare parts and will explore long‐term service agreements (LTSAs) with manufacturers for nonroutine maintenance. For Component B, DPTSC has substantial experience  in  the  upgrading  and  operation  and  maintenance  (O&M)  of  substations.  To  further  enhance  its experience with adequate use and deployment of the mobile substations, capacity building will be provided by the manufacturer on mobile substation operation and maintenance. 

49. The sustainability of the Ywama CCGT will also depend on the availability of natural gas supply, which is of concern as domestic production will decline starting in 2021. However, according to information provided by MOGE and EPGE for the feasibility study, the gas decline will be offset by a reduction in gas exports. As a result, the current levels of domestic gas supply are expected to remain unchanged in the medium term. As such, the project design contributes to guaranteeing the project’s sustainability as consumption of the CCGT will not exceed the current allocated volume of gas supply for the Ywama gas‐fired power plant. In addition, the new CCGT will have priority for gas allocation given its efficiency and the large number of highly inefficient plants owned by EPGE. Finally, in the longer term, Myanmar plans to develop its offshore gas reserves and import LNG for new greenfield power generation stations.  

50. The financial sustainability of the power sector may affect the project in the long run. As mentioned earlier, as a result of  the recent  increase, electricity  tariffs are very close to operational current cost‐recovery levels. To consolidate the financial sustainability of the sector, regular tariff adjustments will be necessary. To this end, the World Bank is providing technical assistance to MOEE to develop a tariff methodology and put in place an adequate process for regular tariff reviews. 

Page 30: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 25 of 74

IV. PROJECT APPRAISAL SUMMARY 

 

A. Technical, Economic and Financial Analysis 

Technical Analysis 

51. The  choice  of  CCGT  technology  at  the  Ywama  power  plant  corresponds  to  the most  cost‐efficient alternative to urgently improve the availability and quality of supply. The project will support the capacity and efficiency upgrade of  the Ywama power plant by ensuring  the maximum output per unit of  fuel. This  is a key criterion given that domestic gas supply is constrained, as described earlier.32 With this efficiency level, the plant’s marginal costs would be the lowest among the country’s thermal power plants, and it is expected to be operated at base  load  in  the medium‐to‐long  term, based on  the  results  of  the  indicative  long‐term planning  exercise. Finally,  being  a  brownfield,  the plant will  use  existing  gas  and  electrical  grid  connections,  reducing  costs  and implementation timelines.  

52. The capacity of the new CCGT is based on the space available after the demolition of existing units and power evacuation constraints in the high‐voltage substation. Two CCGT configurations are possible: (a) two gas turbines, two heat recovery steam generators (HRSGs), and one common steam turbine (a 2‐2‐1 arrangement); or (b) one gas turbine, one HRSG, and one steam turbine (a 1‐1‐1 arrangement). Both configurations will have a bypass stack between the gas turbine(s) and an HRSG to allow open‐cycle operation. To achieve value for money and support innovation, the configuration will be left open for bidders to optimize in the DSI tender subject to meeting functional requirements to achieve the lowest levelized cost of electricity (LCOE) per unit of output. The capacity of the power plant will also be left for bidders to optimize based on the equipment configuration, from a minimum capacity of 250 MW up to approximately 300 MW (net at site conditions). Gas for the CCGT will be supplied by the Yadana offshore gas field, which yields gas with poor calorific value, containing about 70 percent methane and 25 percent nitrogen. Therefore, the gas turbines need to be able to operate with such fuel. Liquid fuel as backup fuel is not foreseen. To minimize the need for water intake and structures to be built in the Hlaing River,  the  recommended  cooling method  is  a  closed  system with wet mechanical‐draft  cooling  towers; water intake is also recommended using a floating deck. A pretreatment settling pond will also be necessary due to the high turbidity and suspended solids. All  facilities are  to be  located within  the existing  footprint of  the Ywama power plant. 

53. Specific investments and measures will be undertaken to improve the climate adaption and technical resilience of existing substations systemwide. The project will  implement: (a) adaption measures that seek to ‘protect/harden’  infrastructure  and  ‘accommodate/manage’  measures  to  reduce  the  sensitivity  of  assets  to climate hazard exposure—including, for instance, investments to elevate or fix equipment to protect equipment from  frequent  floods or earthquakes;  and  (b)  technical measures  to accommodate or manage  the  impacts of technical  faults—including  installing  equipment  to  ensure  at  least  N‐1  reliability  criteria  and  increasing  the capacity and  rating of high‐voltage equipment  such as power and  current  transformers,  shunt  capacitors and reactors,  switch  gears,  and  control  and  protection  systems  that  adapt  the  transmission  system  to  higher temperature‐driven demand. Mobile substations are also a proven technological solution to respond to system damage caused by climate change and natural disasters and help address the lack of contingency equipment.  

32 A feasibility study analyzed other technology options for the power plant, including reciprocating gas engines and gas turbines. The study concluded that none would represent an advantage over CCGT technology for this specific project. 

Page 31: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 26 of 74

Economic and Financial Analysis 

54. The economic benefits of the Ywama CCGT power plant derive from: (a) net reduction in the power systems costs, (b) reduction in transmission losses, (c) reduction in energy not served (ENS), and (d) reduction in CO2 emissions. The estimation of the project benefits  is based on the outputs from the indicative least‐cost generation plan, which calculated total system costs, including operation and maintenance and annualized capital investment  costs,  overall  transmission  losses,  and  amount  of  ENS  (as  the  difference  between  the  ‘with’  and ‘without project’ runs). The reduction in total system costs is due to the displacement of higher‐cost energy (LNG, coal,  and  emergency power)  over  the  30‐year  lifetime of  the project  and  it  is  estimated  at US$60 million on average annually. The project’s contribution in reducing ENS was quantified as the economic cost of operating diesel generators, which are prevalent in Myanmar (about US¢24 per kWh). Reduction in system losses due to increased generation near the main load center was valued at US¢7.1 per kWh, which is the estimated marginal cost  of  the  system.  Finally,  avoided  CO2  emissions were  valued  using  the  base  case  values  of US$30  in  2015 increasing to US$80 per Mt of CO2 equivalent by 2050 in line with the World Bank Guidance on the Shadow Price of Carbon in Economic Analysis. Project costs were estimated based on the feasibility study. Capital expenditures (CAPEX) are estimated at US$1,000 per MW installed and correspond to the full cost of the turnkey project, EPGE development costs, and contingencies. Fuel costs are valued at the economic cost of natural gas of US$8.3 per MMBtu, which is higher than the current tariff paid by EPGE of US$7.5 per MMBtu. Finally, nonoperational and maintenance costs are estimated at US$4.5 per MWh. 

55. The upgrading of the Ywama power plant has a high economic net present value (ENPV). The project’s ENPV  is estimated  to be US$165.0 million over a 30‐year discount period and  the project yields an economic internal rate of return (EIRR) of 27.9 percent, well above the hurdle rate of 15 percent (see table 2). The ENPV increases to US$241.8 million and the EIRR to 30.9 percent after the consideration of economic benefits from CO2 emissions reduction, estimated at 12.3 million metric tons. Given the uncertainty around some of the variables affecting the economics of this component, a sensitivity analysis has been carried out to assess the robustness of the project to uncertainties and changes in key input variables. Because it is not possible to assess switching value changes  in  the  least‐cost  plan,  the  sensitivity  analysis  assessed  percentage  rate  changes  in  the  following  key variables:  (a)  CAPEX  overrun,  (b)  operational  expenditures  (OPEX)  overrun,  (c)  social  discount  rate,  and  (d) electricity supply revenue.  

Table 2. Results of the Economic and Financial Analysis 

  Unit  Value 

Economic Analysis     

Social discount rate  %  15.0 

Economic internal rate of return     

    EIRR (excluding environmental benefits)  %  27.9 

    EIRR (including environmental benefits)  %  30.9 

Economic net present value     

    ENPV (excluding environmental benefits)  US$ million  165.0 

    ENPV (including environmental benefits)  US$ million  241.8 

GHG emissions avoided  Mt CO2  12.30 

Financial Analysis     

Weighted average cost of capital (WACC)  %  2.25 

Financial internal rate of return (FIRR)  %  14.9 

Financial net present value (FNVP)  US$ million  734.2 

    FNPV  MMK million  1,101,253.0 

Page 32: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 27 of 74

  Unit  Value 

Levelized cost of electricity (LCOE)  US¢/kWh  5.7 

    LCOE  MMK/kWh  86.2 

56. The project  is financially viable, as demonstrated by a financial  internal rate of return (FIRR) of 14.9 percent and a financial net present value (FNPV) of US$734.2 million. The project generates enough revenue to service its debt obligations. The estimated LCOE33 of the proposed CCGT is MMK 86.2 per kWh (US¢5.7 per kWh), which  is  below  the  average wholesale  supply  cost  of MMK 130 per  kWh  in Myanmar  and  above  the  current average EPGE's sales tariff of MMK 38.4 per kWh (US¢4.2per kWh).  

B. Fiduciary  

(i) Financial Management  

57. The  overall  financial  management  risk  is  assessed  as  Substantial.  The  main  risks  that  need  to  be addressed  are:  (a)  inadequate  documentation  of  policies  and  procedures  and  lack  of  clarity  on  applicable government  rules;  (b)  insufficient  number  of  finance  staff  at  DPTSC, with  limited  experience  in  development partner‐financed projects; (c) little experience at both EPGE and DPTSC in the use of contractors and consultants’ services—meaning they would require assistance in contracting and monitoring these services and in ensuring the quality of their outputs and products; (d) the use of manual processes; and (e) weak capacity to prepare work plans and budgets. 

58. These risks have been mitigated by implementing the following measures:  

(a) Developing  a  financial  management  manual  that  was  adopted  by  all  project  staff  members  in November 2019; 

(b) Assigning staff from the finance teams of both IAs to work specifically on the financial management matters of the project;  

(c) Providing training in financial management and contract management, including the preparation of annual work plans and budgets for all staff involved in project implementation; and 

(d) Allowing  the  use  of  Excel  to  record  transactions  (by  project  components  and  disbursement categories  according  to  government  codes)  until  the  Government  introduces  a  computerized accounting system, maintaining a proper document backup system and using online systems and email for recording, reporting, and communication. 

59. Annex 5 includes further details of the financial management arrangements.  

(ii) Procurement  

60. The  procurement  activities  financed  by  the  IDA  credit  will  be  carried  out  by  EPGE  and  DPTSC  in accordance with the World Bank’s Procurement Regulations for IPF Borrowers34 (hereinafter referred to as the ‘Procurement Regulations’) and the provision stipulated in the Financing Agreement. For procurement activities 

33 The LCOE  represents  the NPV of all unit  costs of electricity generated over  the  lifetime of a project  (assuming all  costs of building, operating, and financing the power plant).  34 World Bank. Procurement Regulations for IPF Borrowers: Procurement in Investment Project Financing; dated July 1, 2016; revised in November  2017  and  August  2018.  http://pubdocs.worldbank.org/en/178331533065871195/Procurement‐Regulations.pdf.  IPF  = investment project financing. 

Page 33: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 28 of 74

approaching the national market, the government directives on national procurement issued on April 10, 2017, with procurement documentation acceptable to the World Bank, would be adopted. EPGE will be responsible for implementing the procurement activities under Component A and DPTSC will implement procurement activities for Component B. 

61. The  World  Bank  carried  out  a  procurement  capacity  and  risk  assessment  (PCRA)  and  rated  the procurement risk High. The main contributing  factors were as  follows:  (a)  fragile operating environment with weak  institutional  structures  and  inadequate  policies,  demonstrated  through  the  absence  of  unified  and comprehensive  procurement  regulations  to  guide  procurement  implementation;  (b)  a  weak  accountability structure  for  procurement  decisions;  (c)  the  absence  of  institutional  structures  and  procedures  for  handling complaints;  (d)  a  lack  of  expertise  in  approaching  the  international  market  and  enforcing  the  international standard  contract  conditions  required  for  the  implementation  of  large‐value  and  technically  complex procurement  packages  under  the  project;  (e)  weak  and  inadequate  technical,  procurement,  and  contract management  capacities  within  EPGE  and  DPTSC;  (f)  complex  and  bureaucratic  internal  review  and  approval procedures  within MOEE  that  are  time‐consuming  and  likely  to  affect  the  timely  delivery  of  the  project;  (g) possible insufficient interest by qualified bidders; and (h) risks of noncompliance with World Bank procedures, including fraud and corruption issues. These risks would particularly negatively affect key procurement packages that  are  critical  to  achieving  the  PDO:  the  contract  for  upgrading  the  Ywama  power  plant,  the  consultancy contracts of  the owner’s engineer and environmental and  social  safeguards management consultant,  and  the supply of transmission network equipment and works. 

62. To mitigate the above risks, critical measures have been discussed and agreed with MOEE, EPGE, and DPTSC: 

(a) Establishment of strategic institutional implementation arrangements, wherein each of the IAs sets up a PIU (see annex 1 for further details on the PIU implementation arrangements) led by a senior official and adequately staffed with full‐time and experienced professional experts (assistance from international consultants will also be mobilized to supplement their capacity); 

(b) Close procurement support by the World Bank through the implementation of HEIS requested by MOEE, kicking off from the project preparation stage to catalyze key procurement activities; 

(c) Adoption of advanced procurement for critical procurement packages; (d) Commitment by MOEE to accelerate review and decision‐making processes; (e) Conducting of market engagement during feasibility studies and prequalification (PQ) processes by 

IAs and advertising of procurement notices internationally (lessons learned from similar projects and information from the market research will provide important inputs to the stages of PQ and bidding document preparation); 

(f) Development  of  key  performance  indicators  (KPIs), with  support  from  the  owner’s  engineer,  to monitor the performance of Ywama power plant contractor; and 

(g) Intensive training for IAs’ staff on the World Bank’s Procurement Regulations, contract management, and mitigation of fraud and corruption risks. 

63. EPGE and DPTSC will  implement relevant actions to mitigate  fraud and corruption risks, as detailed  in annex 4. 

64. Through EPGE and DPTSC, MOEE has prepared a Project Procurement Strategy for Development (PPSD) to  inform  fit‐for‐purpose  procurement  arrangements  and  support  the  PDO.  Based  on  its  findings,  the  IAs recommended a procurement plan that was agreed by the World Bank. Throughout the project’s implementation, 

Page 34: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 29 of 74

the PPSD and Procurement Plan will be regularly updated as appropriate. The PPSD recommends the following procurement approaches for key activities to deliver the best value for money: 

(a) A  single‐responsibility  DSI  contractor  would  implement  the  Ywama  power  plant  rehabilitation (estimated at US$285 million), which is rated high risk due to its technical complexity, high value, and critical role in achieving the PDO. A Request for Bids (RFB) with single‐stage bidding, preceded by  a  PQ  process,  will  be  applied  to  ensure  that  only  contractors  with  adequate  capacity  and experience, among all active in the region, compete for the contract award. 

(b) A Quality‐ and Cost‐based Selection (QCBS) approach would be used to engage an owner’s engineer consultancy (estimated at US$2 million) and a safeguard management consultant (estimated at US$1 million), given the strategic importance of ensuring smooth procurement, adequate supervision of the DSI contractor, and sound safeguards management and compliance during the Ywama power plant rehabilitation.  

(c) An open competition on the international market (using the single‐stage, one‐envelope RFB method) would be used to procure the transmission network equipment (such as mobile substations, power and  current  transformers,  power  and  shunt  reactors,  switch  bays,  and  protection  and  control devices), which is considered as a standard procurement approach. During the first 18 months of project  implementation,  mobile  substations  will  be  procured  with  an  estimated  value  of  US$9 million.  Other  transmission  equipment  to  be  procured  will  be  decided  during  project implementation, upon  the borrower’s  request and outcomes of  the ongoing  technical assistance work to help the country address climate resilience and adaption. 

65. More details on PCRA, procurement risk rating, mitigation measures, and PPSD summary are presented in annex 4.

C. Safeguards 

(i) Environmental Safeguards  

66. The project  triggers  the policy on Environmental Assessment  (OP/BP 4.01) because of  the potential adverse impacts associated with the implementation of Components A and B. The proposed project has been classified as category ‘B’ due to the adverse environmental and social impacts, which are primarily related to the civil works  to be conducted during construction or operation of  the project’s  investments. Physical works are expected to take place within the existing brownfield locations, particularly at Ywama power plant and in existing substations.  However,  risks  are  limited  and  site‐specific,  and mitigation measures  can  be  readily  designed  to mitigate these risks. 

67. The implementation of the project will have overall climate mitigation and adaption benefits, including by reducing GHG emissions per unit of power generated. The specific benefits expected are: (a) increased and more reliable power supply; (b) improved systems resilience to climate events; and (c) improved energy efficiency of power generation, thereby reducing GHG emissions per unit of output generated.  

68. The potential adverse impacts are associated with the implementation of Component A and, to a lesser extent,  Component  B.  The  upgrading  of  Ywama  power  generation  units,  under  Component  A,  involves dismantling two existing simple cycle power plants and relocating an existing gas turbine with steam‐powered 

Page 35: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 30 of 74

turbo generator units, as well as its auxiliary systems, to allow space for the installation of up to two high‐efficiency gas turbines and a steam generator. Component B  includes the purchase of mobile substations,  installation of high‐voltage equipment, and climate resilience works in selected system‐critical, high‐voltage substations. Works will  include  the anchoring and elevation of existing equipment  to  reduce  the  risk of equipment  failure during disasters such as earthquakes and floods. The potential adverse impacts of the project related to the dismantling of  the  existing  plant,  the  installation  of  the  new  generation  units,  and  the  works  at  substations  include  the following: (a) increased levels of dust, noise, and other emissions; (b) increased material stockpiles; (c) increased operation of heavy equipment; (d) increased transportation of construction materials and electrical equipment, and related traffic disturbance and road safety impacts; (e) hazardous waste generated during the dismantling of the old plant, especially asbestos; (f) construction site waste generation, such as construction and domestic waste and wastewater; (g) small‐scale soil erosion due to wastewater and sedimentation, affecting surface water quality and, particularly, the Hlaing River; (g) impacts related to labor influx; and (h) health and safety issues for workers and community. The impacts, however, are expected to be small to moderate, localized, and temporary, and can be mitigated. 

69. The potential negative impacts during operation of the project are associated with workers’ health and safety. These are mainly related to exposure to electric and magnetic fields, heat, noise, confined spaces, electrical fires and explosions, and chemical hazards from the power plant, high‐voltage power lines, and substations. The residents living next to the power station would be affected by increased noise. These risks can be reduced by strictly applying national and international technical regulations and standards at the project design stage and by following electricity safety regulations during project operation. The potential risk of oil leakage from transformers is addressed by constructing an emergency oil collection and storage tank. The potential risk of polychlorinated biphenyls will be strictly treated as discussed in the Environmental and Social Management Framework (ESMF) also prepared for this project. 

70. To  address  the  project’s  negative  social  and  environmental  impacts,  an  Environmental  and  Social Impact Assessment (ESIA) and an ESMF have been prepared. The safeguards instruments prepared by EPGE and DPTSC are found to be satisfactory. An ESIA for the Ywama power plant was also prepared and submitted for the approval  of  the  Government  of  Myanmar  (GOM).  The  project  will  comply  with  government  regulations  on environmental and social assessments and the World Bank’s safeguards policy requirements, as specified in the ESMF. The Environmental and Social Management Plans (ESMPs) to be prepared for the activities identified during implementation  will  follow  the  ESMF.  During  implementation,  the  contractor  will  undertake  a  hazard  and operability study to identify and evaluate problems that may represent risks to the workers and communities or equipment. Among others, the study would also focus on assessing explosion risks and their impact on the nearby residential areas. The hazard and operability study will propose mitigation measures and include follow‐up actions if it concludes that the location of the current building is in the high‐accidental‐risk zone. If such actions would require the relocation of the power plant workers, EPGE will be responsible and bear the costs of the relocation of the power plant workers. In addition, the contractor will also be required to develop and implement a detailed hazardous  waste  management  plan  and  occupational  health  and  safety  management  plan  during  both  the preconstruction and construction phases. These requirements will be included in the bidding documents and the DSI contract. This contract will also include provisions to provide plant staff with material and procedures needed to mitigate potential contagion risks related to the COVID‐19 pandemic. 

Page 36: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 31 of 74

(ii) Social Safeguards  

71. The project triggers the World Bank Involuntary Resettlement (OP/BP 4.12) policy on a precautionary basis. Although all project activities will  take place within the physical  footprint of  the existing facilities under Component B, it is possible that additional small strips of land may be required to enlarge the footprint of the substations  to  accommodate  new  equipment  or  the  installation  of  new  mobile  substations.  Therefore,  a Resettlement Policy  Framework  (RPF) has been prepared and disclosed as a  stand‐alone  section of  the ESMF report.  Involuntary resettlement does not apply to Component A since all project activites will be undertaken within the existing footprint of the power plant. However, to ensure that provisions for land adquisition and access restriction are in place for the layout areas during project construction, a site‐specific Environmental and Social Layout Areas Plan is included as part of the ESIA mitigation measures. 

72. The project triggers the Indigenous Peoples (OP/BP 4.10) policy as the specific locations of the activities to be financed under Component B will be determined during project implementation. Although this project is not expected  to negatively affect  indigenous people,  some of  the  substations may be  located  in areas where indigenous people reside or work. To ensure that they are meaningfully consulted, OP 4.10 has been triggered on a  precautionary  basis.  Therefore,  a  Community  Participation  Planning  Framework  (CPPF)  was  prepared  and included  as  a  stand‐alone  section  of  the  project's  ESMF.  Among  other  contents,  the  CPPF  discusses  how meaningful and culturally appropriate consultations should be carried out and the main contents of Indigenous Peoples Plans,  if  the plans are  required.  The CPPF was presented and discussed with  key  stakeholders at  the national level on February 28, 2020, and the feedback received was included on its final version. 

73. The main project risks  include gender‐based violence (GBV) and sexual exploitation and abuse (SEA) related  to  labor  influx  during  construction  and  noise  and  vibration  during  plant  operation.  Key  risk considerations and proposed mitigation measures are as follows: 

(a) Noise and vibration. The ESIA conducted for Component A states that noise and vibrations are one of the main risks due to the noise registered (Leq) near the residential building located next to the plant.  In  that area, noise was  found  to be 76.5 dB(A), which exceeds  the prescribed World Bank Group Environmental, Health and Safety Guidelines’  limit of 55 dB(A) during the daytime and 45 dB(A) during the nighttime for residential areas. This problem especially affects the 80 apartments (buildings E6–E10) housing EPGE staff located 100 meters from the power plant (aerial distance from the center of  the plant). Company employees and  their  families  living  there are also affected by vibrations, especially those caused by sporadic emergency shutdowns. The ESIA states that sufficient noise control and isolation measures should be adopted to protect the surrounding apartments from the impacts of noise and vibration. In case those noise thresholds cannot be met and other risks such as  explosion  cannot  be  mitigated,  the  borrower  has  committed  to  relocating  the  power  plant workers and affected residents in the nearby areas. 

(b) GBV and SEA risks related to labor influx are expected to be moderate. The project may bring direct temporary  benefits  for  skilled  and  unskilled  workers,  who  would  be  employed  during  the construction  of  the  project.  However,  there  are  GBV  and  SEA  risks.  For  Component  A, workers’ camps are not expected and  the project activities will be  carried out near  residential  areas.  It  is estimated that about 300 workers will be recruited during the dismantling of the old plant at the preconstruction stage. This will increase to about 800 during the construction phase. These workers will  be  sourced  from  Yangon  City  (with  an  estimated  population  of  over  7  million  people)  and commute  on  a  daily  basis.  Therefore,  no  labor  camps  will  be  required.  Hence,  the  ESIA  for 

Page 37: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 32 of 74

Component A consists of a GBV plan that includes the following mitigation measures: (i) provisions to promote local recruitment of the workforce, including training programs to be delivered by the plant  contractor  so  that  local  people  can become  skilled workers  and be  employed  at  the plant during construction; (ii) a workers’ code of conduct (for both worker‐community and worker‐worker interactions); and (iii)  training and public awareness activities to avoid sexual harassment,  sexual assault, and exploitation and human trafficking. For Component B, the risk seems limited since the required works will need relatively mid‐size crews of approximately 60 skilled and unskilled workers, the  majority  of  whom  will  be  recruited  locally.  Most  part  of  the  technical  staff  will  be  DPTSC employees and will be accommodated in the residential colonies of DPTSC. 

 74. Both Components A and B include mitigation measures to ensure that the local communities affected by the project works are properly notified of the timing and scope of the planned works and disturbances are minimized. Such minimization of disturbances may comprise  limiting working hours to daylight,  taking special precautions when the work is carried out near children's institutions, or traffic management including, if required, the establishment of alternative temporary traffic routes. Especially for Component A, the 650‐meter‐long access road to the plant carries a risk of accidents as it is narrow and has just enough width to allow maneuver of the vehicles. Therefore, proper mitigation measures will have to be adopted to reduce the risk of any incidents on this road. 

75. Safeguards implementation, monitoring, and training. The PIUs will be responsible for implementing and monitoring  the  environmental  and  social  safeguard  instruments  (ESMF,  ESIA,  RPF,  and  CPPF)  through  their dedicated  environmental  and  social  focal  points  during  project  implementation.  EPGE  will  therefore  be responsible for effectively implementing the environmental and social safeguards for Component A, monitoring their compliance, and regularly liaising with local authorities and communities. EPGE will also be responsible for incorporating the Environmental and Social Management Plan (ESMP) for the Ywama power plant into the standard tender documents  to be used as a basis  for contractors to  implement environmental management during the construction phase. The implementation of the ESMP will be supervised and monitored by the owner’s engineer and an  independent environmental and social management consultant  firm to be contracted by EPGE  for this purpose.  The  performance  and  compliance with  environmental  and  social  safeguard  instruments will  also  be subject  to  regular  supervision  from  the  World  Bank  task  team.  EPGE  PIU  staff,  contractors,  supervision consultants, and local community representatives will receive training on the safeguard instruments to be applied to the project. For Component B, DPTSC is responsible for implementing the ESMF, RPF, and CPPF, including the preparation  and  implementation  of  subproject  ESMPs,  Resettlement  Plans,  and  Indigenous  Peoples  Plans,  as required. 

76. Public consultations and information disclosure. Consultations on the draft ESIA for the Ywama power plant rehabilitation were conducted by EPGE PIU staff working with affected communities, local authorities, and EPGE staff resident at the plant on December 22 and 23, 2018. Consultations on the ESMF and the RPF were also organized with EPGE and DPTSC officials; the employees at the substations of Taungoo, Tharyargone, and Belin; and local communities in January 2019. A consultation for the CPPF was carried out on January 28, 2020, with representatives of civil society organizations (CSOs) working with ethnic groups at the national level. The feedback received in all these consultations has been incorporated into the project design and the ESIA, ESMF, RPF, and CPPF approved by the World Bank. The draft versions of the ESIA and ESMF, including the RPF and CPPF, were disclosed on the MOEE website on November 29, 2019, and the final versions, approved by the World Bank, were 

Page 38: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 33 of 74

disclosed on February 25, 2020. The ESIA was disclosed in the World Bank’s external website on February 6, 2020, the ESMF was disclosed on February 10, 2020, and the RPF and the CPPF were disclosed on February 12, 2020. 

(iii) Gender  

77. Gender  action  and  M&E.  To  help  reduce  the  gender  productivity  gap  at  work  due  to  childcare responsibilities (identified in section IV.B), the project will support the setup of a childcare pilot at MOEE. Specific activities  include the preparation of a detailed rollout plan,  in close collaboration with the MOSW, building on lessons learned from similar activities in Myanmar and internationally. The rollout plan set out critical aspects for the  implementation  of  the  pilot  such  as  demand  at  MOEE,  logistics,  financial  sustainability  based  on  users’ contributions, employer legal obligations, quality and safety guidelines, and safeguards instruments to be applied. Based on the plan, the project will provide funding to cover the setup costs required for the childcare pilot such as material  to  start  operations,  refurbishment  of  facilities,  and  training material  for  the  childcare  staff.35  The expected outcome of the activity will be directly linked to the indicator measuring the gap between the respective amounts of time that the male and female MOEE staff using the childcare pilot spend on childcare during working hours, as defined in the Results Framework (see section VI, Results Framework and Monitoring)36. Specifically, the project will carry out annual impact assessment surveys during implementation to monitor: (a) the impact of the childcare  pilot  on  productivity  tracking  information  on  key  impacts,  such  as  reduction  of  absenteeism  during working hours due to childcare obligations and opportunities to accept promotions and attend trainings; and (b) user satisfaction levels. The feedback collected will guide subsequent MOEE efforts to further improve the pilot for a larger impact on workforce. 

(iv) Citizen Engagement 

78. The main beneficiaries of the project will be households, SMEs, and other firms connected to the public power grid in the Yangon region. Because of the technical characteristics of the investments, specific citizens and firms or their groups cannot be identified during the conduct of beneficiary satisfaction surveys. Therefore, the project will monitor citizens affected by the project activities during implementation. The objective would be to ensure  that  feedback  received  is  adequately  captured  and  addressed  through  a  functional  GRM  available  to citizens. 

D. Grievance Redress Mechanism 

79. The project will have an internal GRM in place that the aggrieved party or parties can use to lodge their complaints and get them amicably settled. During construction, the GRM will be managed by the contractors under supervision of the PIUs. The contractors will inform the affected communities about the GRM availability to  handle  complaints  and  concerns  about  the  project.  Confirmation  that  the  mechanisms  are  maintained functional during the implementation of the project will be included in EPGE progress reports, stating if and how 

35 The batch will follow the dedicated course on early childhood education currently given at the MOSW. 36 This indicator is considered as a proxy for increased productivity of female MOEE staff because the assumption is that if their child or children are in childcare, mothers have more of an opportunity to focus on their work. While there are important drawbacks in considering time spent during working hours to measure employee productivity, it is important to note that Myanmar is an FCV country with significant lack of data and information on productivity or absenteeism in Myanmar’s public sector. Other aspects of the gender gap identified are in the compatibility of professional growth and childcare, such as promotions or trainings, tackle legislation and national laws. Thus, there was no specific action identified that this project could contemplate.  

Page 39: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 34 of 74

feedback received has been used and grievances addressed.  If  this has not been done, an explanation will be included in EPGE progress reports.  

80. In addition, communities and individuals who believe that they are adversely affected by a World Bank (WB)‐supported  project  may  submit  complaints  to  the  existing  project‐level  GRM  or  the  WB’s  Grievance Redress  Service  (GRS).  The GRS ensures  that  complaints  received are promptly  reviewed  in order  to  address project‐related concerns. Project‐affected communities and individuals may submit their complaints to the WB’s independent Inspection Panel, which determines whether harm occurred, or could occur, as a result of WB non‐compliance with its policies and procedures. Complaints may be submitted at any time after concerns have been brought directly to the World Bank's attention and Bank Management has been given an opportunity to respond. For information on how to submit complaints to the World Bank’s corporate Grievance Redress Service (GRS), please visit http://www.worldbank.org/en/projects‐operations/products‐and‐services/grievance‐redress‐service For  more  information  on  how  to  submit  complaints  to  the  World  Bank  Inspection  Panel,  please  visit www.inspectionpanel.org. 

V. KEY RISKS 

81. The  overall  implementation  risk  is  rated  Substantial,  due  to  the  following  main  factors:  (a) macroeconomic risks; (b) governance and fiduciary risks associated with the procurement and implementation of a large and complex contract; (c) technical risks due to the challenging site and operating conditions at the Ywama power plant; (d) risks related to policies in the gas sector affecting its availability; (e) low institutional capacity (particularly with regard to safeguards implementation and compliance) and competing priorities of qualified staff at IAs to focus on the project; and (e) social tensions among key stakeholders such as the population that remains unconnected to the grid. Other risk factors are rated Moderate. The measures to mitigate substantial and high risks and ensure the achievement of the PDO are outlined in the following paragraphs. 

82. Macroeconomic risks. There is substantial uncertainty surrounding the economic impact of the COVID‐19 pandemic, and economic growth is expected to slow down substantially compared to the forecasted 6.4 percent in FY19‐20 due to indirect and direct impacts of the pandemic. The economy is expected to rebound to 4 to 6 percent  in  FY20‐21  in  line  with  regional  peers.  However,  downside  risks  are  high  from  a  prolonged  crisis, compounding domestic uncertainties relating to conflict and elections by November 2020. The economic costs of the pandemic could be high, since it is likely to lead to a simultaneous supply shock (production slows or ceases due to confinement measures) and demand shock (consumption and investment weakens due confinement, loss of  income,  and  weak  prospects  of  investment  returns).  The  Government  has  recently  implemented  several measures in response including public health measures and economic stimulus actions, mostly to support cash‐constrained  firms  in  the most  vulnerable  sectors  by  reducing  interest  rates  and  intervening  in  the  exchange market. To protect households, the Government has implemented an electricity bill waiver for up to 150 kWh (as discussed  earlier)  and  will  provide  a  food  basket  containing  key  staples  to  lower‐income  and  vulnerable households. In the medium term, additional policy responses would need to focus on using existing buffers for shoring‐up stability and demand. 

83. Governance,  political,  and  stakeholder  risks.  Domestic  vulnerabilities  associated  with  the  negative spillovers from a flare‐up in conflict and violence could create further indirect economic impacts, especially with respect  to  tourism  revenue,  foreign  investor  sentiment,  and  the  possible  revocation  of  trade  preferences. Domestic  vulnerabilities  in  relation  to  increased  conflict  and  violence  can  increase  social  tensions  among  the population. In the context of the proposed project, the risk is considered substantial within those segments of the 

Page 40: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 35 of 74

population that remain nonconnected but reside or work in the proximity of project activities in substations. To mitigate  this  risk,  the  project  includes  a  selection  criterion  of  substations  and works  that would  support  the extension of the national grid, with focus on those areas where disadvantaged households live.  

84. Fiduciary risks. Ensuring a timely and transparent procurement process will be key to mitigating these high risks and achieving value for money. Myanmar faces substantial governance challenges, and the power sector is no exception. In this environment, reputable firms could decide not to participate in the tenders. To mitigate high fiduciary risks in the procurement of the Ywama power plant upgrading, the IAs will engage in a transparent market engagement process, followed by the implementation of an international DSI tender in accordance with the World Bank’s procurement processes. Due to its large value and risks, the process will be reviewed by the World  Bank’s  Operational  Procurement  Review  Committee.  To  reduce  the  risk  of  long  review  and  approval processes by MOEE, senior management has committed to expediting these reviews. Other measures to mitigate fiduciary risks are described in annex 4. 

85. Risks  related  to  the  technical  design  of  the  project.  Although  CCGT  is  a  mature  technology,  space constraints for the installation of the new CCGT, combined with the need to keep the remaining facilities operating during construction, will require careful planning and substantial coordination between the contractor, the PIU at EPGE, and plant operators. EPGE PIU staff will  receive  training  in contract management,  follow up closely  the agreed implementation schedule with the contractor, and establish direct communication channels with the plant operators.  On‐the‐ground  technical  support  from  the  owner’s  engineer  will  also  help  identify  early  any coordination issues that may arise during construction.  

86. Risks related to the sector strategies and policies. During plant operation, shortage of gas supply is a risk, particularly given the expected decline in domestic gas supplies in the medium‐to‐long term and uncertain gas allocation rules among power plants. To mitigate this risk, the technology choice was to minimize exposure to fuel shortages by increasing the efficiency of gas utilization and eliminating the need for additional supply allocation for the Ywama power plant. In the medium‐to‐long term, the supply and availability of gas will rely on MOEE and MOGE undertaking some of the actions foreseen to maintain the current levels of domestic gas supplies at around 400 million cubic feet per day (MMcfd). Key planned measures include reallocation of exports to the domestic market, production plateau extension from the Zawtika and Yadana, exploitation of recently discovered reserves, and/or pipeline de‐bottlenecking  to  increase domestic deliveries. However,  it  should be noted that success  in attracting private investments in the exploitation of recent discoveries is mixed because of an unfavorable fiscal framework for upstream gas and the recent collapse of oil prices, which will make the economics of developing  higher‐cost  gas  projects  more  challenging.  Also,  the  Government’s  approach  to  LNG  has  so  far  consisted  in procuring fully integrated power‐to‐LNG projects, thereby reducing other complementary solutions; the risk of having in place appropriate and timing sector strategies that guarantee gas supplies is perceived as substantial. The World Bank will continue its engagement with the GOM on the policy dialogue regarding upstream gas fiscal framework reform to incentivize private sector investments in gas exploration and development through parallel technical assistance and advisory services and analytics.  

87. Environmental and social risks and risks related to the institutional capacity for project implementation and sustainability. While there is adequate technical capacity in the development of thermal power plants, only a handful of qualified staff are involved in all projects under implementation and planning, and there is also a lack of  institutional mechanisms  at MOEE  and  EPGE  to  deal with  the  large  number  of  projects.  Qualified  staff  to implement and supervise compliance with social and environmental safeguards are particularly scarce within the IAs and the national safeguards framework  is relatively recent. This could make  implementation vulnerable to 

Page 41: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 36 of 74

delays and poor management. This is also the first project to be implemented with funding from the World Bank by DPTSC. While the department has been working with other international financial institutions and donors, PIU staff lack knowledge of World Bank policies and procedures. To mitigate these risks, the World Bank will provide training in fiduciary and safeguards issues to PIU staff in addition to HEIS. External support through the owner’s engineer  and  the  independent  safeguards  management  consultant  should  also  support  PIUs  in  the  overall oversight.  Together  these  capacity‐building  and  technical  assistance  activities  would  contribute  to  improving institutional capacity sustainably. 

  . 

Page 42: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 37 of 74

VI. RESULTS FRAMEWORK AND MONITORING 

       Results Framework COUNTRY: Myanmar  

Power System Efficiency and Resilience Project  

Project Development Objectives(s) 

The project development objectives are to increase the output and efficiency of power generation and improve the resilience of the power network in support of the government’s program on universal electricity access.  

Project Development Objective Indicators  

RESULT_FRAME_TBL_PDO       

Indicator Name  DLI  Baseline  End Target 

Increase the output and efficiency of power generation  

Projected energy or fuel savings (CRI, Mega Joules (MJ))     0.00  440,000,000.00 

Increase the output of power generation  

Generation capacity of energy constructed or rehabilitated (CRI, Megawatt)  

  0.00  250.00 

Improve the resilience of the power network  

Annual outages in targeted substations (Text)     N.A.  N.A. 

Support the government's program on universal electricity access  

Disadvantaged/vulnerable people benefiting from access to electricity or improved quality of service (Number (Thousand))  

  0.00  500.00 

 PDO Table SPACE 

 

Page 43: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 38 of 74

Intermediate Results Indicators by Components  

RESULT_FRAME_TBL_IO       

Indicator Name  DLI  Baseline  End Target 

Upgrading Ywama Power Generation Units  

Plant construction progress (Percentage)     0.00  100.00 

Thermal efficiency of energy conversion in the Ywama gas power plant (Percentage)     19.90  54.00 

Gap in annual time spent on childcare during working hours between male and female MOEE staff benefiting from the childcare pilot (Days)  

  15.50  7.00 

Implementation support received up to satisfaction to meet technical specifications, contract oversight, and safeguards monitoring contractual requirements (Yes/No)  

  No  Yes 

Improving Resilience of the Power Network  

Mobile substations deployed for fast response and recovery to climate events (Number)  

  0.00  4.00 

Grievances responded to and/or addressed through the functional GRM available to citizens and within the stipulated response time (Percentage)  

  0.00  100.00 

 IO Table SPACE 

  UL Table SPACE 

 

Monitoring & Evaluation Plan: PDO Indicators 

Indicator Name  Definition/Description  Frequency  Datasource Methodology for Data Collection 

Responsibility for Data Collection 

Projected energy or fuel savings   Annual  

EPGE progress report 

Measures lifetime fuel savings  (over 30 years) achieved through 

EPGE  

Page 44: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 39 of 74

  energy efficiency improvements at the Ywama power plant. Projected savings are calculated against a baseline scenario in the absence of the project in which existing units, with annual average thermal efficiency of 19.9 percent, would continue operating. Savings are defined as fuel savings calculated at plant commissioning on the basis of the guaranteed thermal efficiency by the contractor. The methodology for calculation of gas fuel savings will assume a 80 percent load factor for the new plant  

Generation capacity of energy constructed or rehabilitated 

 Annual  

EPGE progress report  

The indicator measures in megawatts (MW) the generation capacity of high‐efficiency CCGT at the Ywama power plant constructed through the project. The 

EPGE  

Page 45: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 40 of 74

capacity corresponds to the net capacity, at site conditions, guaranteed at the commissioning stage by the contractor.  

Annual outages in targeted substations 

The indicator will monitor the number hours of of outages per year in targeted substations. Targeted substations owned and operated by DTPSC benefiting from new equipment and/or measures to improve infrastructure resilience to climate change and events. 

Annual  

DPTSC progress report  

This indicator is calculated as an aggregation of outage hours in targeted substations. Since specific investments and substations will be defined during project implementation, the baseline and target values will be defined in the first six months of project implementation.   

DPTSC  

Disadvantaged/vulnerable people benefiting from access to electricity or improved quality of service 

This indicators measures the number of people living in disadvantaged townships benefiting from investments to increase electricity access in the Yangon region or to improve the quality of electricity services 

Annual  

EPGE and DPTSC Progress Report  

This indicator captures the number of individuals ho live in townships with a disadvantage index above 7.3 benefiting from the project's investments. These include people provided with access to the public electric 

EPGE and DPTSC  

Page 46: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 41 of 74

grid in the Yangon region or benefiting from investments in substations financed by the project. The disadvantage index by township is based on the MDI‐2 indicator calculated by the World Bank (Multi‐Dimensional Welfare in Myanmar, 2018).   

ME PDO Table SPACE 

 

Monitoring & Evaluation Plan: Intermediate Results Indicators 

Indicator Name  Definition/Description  Frequency  Datasource Methodology for Data Collection 

Responsibility for Data Collection 

Plant construction progress 

This indicator measures the completeness of the construction works to implement the new CCGT unit in Ywama gas power plant. 

Six‐monthly  

EPGE progress report  

This indicator is calculated as design, supply and installation activities completed by the contractor according to the milestones and implementation schedule specified in the contract.  

EPGE  

Thermal efficiency of energy conversion in the Ywama gas power plant 

The indicator measures the thermal conversion 

Annual  

EPGE progress 

This indicator is measured as the share 

EPGE  

Page 47: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 42 of 74

efficiency at the Ywama power plant. 

report  

(%) of thermal energy of the associated gas consumption (based on its lower heating value). The indicator will be based on the guaranteed thermal efficiency by the contractor at the plant commissioning stage.  

Gap in annual time spent on childcare during working hours between male and female MOEE staff benefiting from the childcare pilot 

The indicator will monitor the difference of time spent by men staff and female staff at the Ministry of Electricity and Energy and men on childcare during working hours. The time spent by female will be based on surveys of those benefiting from the childcare pilot implemented by EPGE. 

Annual  

EPGE progress report  

This indicator will me monitored through impact surveys conducted to an statistically significant number of MOEE staff benefiting from the childcare pilot, which will be implemented by EPGE during project implementation.   

EPGE  

Implementation support received up to satisfaction to meet technical specifications, contract oversight, and safeguards monitoring contractual requirements 

This indicator monitors whether implementation support has been provided to the client throughout the implementation of component A of the project. Implementation support, in this case, refers to: (i) assistance from an owner's 

Six‐monthly  

EPGE progress report  

This indicator will be monitored through EPGE's periodical revision of compliance with the contracts signed between the implementing agency and the external consultants. Any 

EPGE  

Page 48: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 43 of 74

engineer, and (ii) assistance from an environmental and social management consultant. 

violation or deviation from compliance with contractual requirements will be reported in EPGE progress reports.  

Mobile substations deployed for fast response and recovery to climate events 

This indicator measures the number of mobile substations deployed in key locations of the transmission network to support enhanced system recovery in case of climate change events or disasters. 

Annual  

DTPSC progress report  

This indicator is calculated as an aggregation of mobile substations deployed and available for use in case of emergency for fast system recovery.  

DPTSC  

Grievances responded to and/or addressed through the functional GRM available to citizens and within the stipulated response time 

This indicator measures whether the GRM available to citizens during the project implementation is functional to engage citizens and addresses their feedback. 

Semi‐annual  

EPGE progress report  

The indicator will capture: (i) the numbers (aggregated) of grievances received and the number of those responded within the stipulated response time, (ii)  if/how grievances are addressed, and (iii) if/how feedback has been used. In the event that grievances are not responded within the stipulated response time or addressed, an 

EPGE  

Page 49: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 44 of 74

explanation will be included in EPGE progress reports.     

ME IO Table SPACE 

       

Page 50: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 45 of 74

  

ANNEX 1: Implementation Arrangements and Support Plan 

 COUNTRY: Myanmar  

Power System Efficiency and Resilience Project 

Strategy and Approach for Implementation 

1. The planned implementation period for the Power System Efficiency and Resilience Project is five years. The proposed closing date for the IDA credit is June 30, 2026. 

Institutional Implementation Arrangements 

2. Lending  arrangement.  There  will  be  a  Financing  Agreement  between  IDA  and  Myanmar represented  by  the Ministry  of  Planning,  Finance,  and  Industry.  The Ministry  of  Finance will  make  the proceeds of  the  credit  available  to  the  IAs  under  the Government’s  budget.  The  IAs operate under  the control of MOEE.  

3. IAs. Component A of  the project will be  implemented by EPGE, which will own and operate the Ywama  power  plant.  EPGE  will  engage  an  experienced  engineering  consultant  to  assist  as  an  owner’s engineer providing technical and operational support during project preparation and implementation of the project. DPTSC will be the IA for Component B of the project. Technical assistance activities that are not identified  at  this  stage,  and  hence  not  described  in  this  document,  will  be  agreed  during  project implementation. In that case, if these activities were proposed to be implemented by an agency other than EPGE or DPTSC, MOEE and the World Bank will need to agree on the arrangements before authorizing the activity.  

4. PIU and focal points. The IAs have appointed focal staff, confirming PIUs, who will work with the World Bank to accomplish the fiduciary, safeguards, and supervisory tasks over the project implementation. The PIUs include designated staff for each project management area, comprising one project coordinator and  two  or  more  chief  engineers,  procurement  specialists,  financial  management  specialists,  and environmental and social specialists (see figure 1.1). The chief engineers will manage all technical aspects of  the  project.  The  project  coordinators will  act  as  liaison  and  nexus  between  the World  Bank  and  all designated focal points. The focal points will be responsible for implementing and supervising the project in each specific domain and coordinating with their equivalents in the other PIU as necessary, particularly on contract management and fiduciary issues. These focal points are expected to help distribute the burden of implementation tasks among various specialized offices, accelerating project processes and alleviating the administrative load on specific officials (see section II.F, Lessons Learned and Reflected in the Project Design). 

5. Technical implementation and supervision. The PIUs of the proposed project, EPGE and DPTSC, will be responsible for the technical implementation of the project under the overall oversight of MOEE. The PIUs will  use  their  existing  organizational  structures  and  processes  to  implement  the  procurement  and financial  management  project  implementation  tasks.  Among  other  tasks,  these  will  include  preparing budget  and  annual work  plans, managing  project  funds  in  line with  eligibility  guidelines,  operating  the Designated Accounts (DAs), enabling the project funds’ disbursements, and applying for withdrawals. The PIUs will also be responsible for the technical supervision of the project, supported by the owner’s engineer and the environmental and social safeguards consultants. As part of this task, EPGE and DPTSC will supervise the  contractor’s  performance  and monitor  the  overall  project  implementation.  This  includes  arranging annual financial audits and coordinating the submission of the annual financial audit reports to the World Bank Group.  

Page 51: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 46 of 74

Figure 1.1. Institutional Implementation Structure 

 

6. Monitoring.  EPGE  and  DPTSC  will  monitor  the  progress  of  Components  A  and  B,  respectively, against the agreed performance indicators (see section VI, Results Framework and Monitoring). The PIUs are responsible for updating the Results Framework and reporting progress every six months. The biannual progress reports will be submitted to the World Bank Group. The progress reports will include updates on the functionality of the GRM, which will be in place for citizen engagement and submission of any complaint, concern, or issue that might arise in relation to the project (see section IV.C, Safeguards).  

Implementation Support Plan 

World Bank 

7. The  World  Bank  team  members  for  procurement,  financial  management,  and  social  and environmental safeguards will be based in East Asia and Pacific country offices to ensure closer support for the client.  

8. Formal supervision and field visits will be carried out semiannually. Through these regular visits, the World Bank will provide support to the implementing units, identify arising issues impeding the project’s progress, and discuss actions to resolve critical bottlenecks. The World Bank will closely monitor the overall progress of project  implementation by  reviewing  the  semiannual progress  reports,  the execution of  the Procurement Plan, the actual disbursements of the IDA credit, and so on.  

9. Detailed inputs from the World Bank team are outlined below and summarized in table 1.1: 

(a) Technical inputs. Inputs of technical specialists will be required to review bid documents and associated technical specifications to ensure that adequate technical standards are observed and that they enable a fair competition. Technical specialists will also be needed to review bid evaluation  reports  and  monitor  implementation  of  the  project  during  construction  and commissioning.  

(b) Fiduciary requirements and inputs. The World Bank team will help MOEE, EPGE, and DPTSC to  identify  capacity building needs  to  strengthen  its  financial management  capacity and  to improve procurement management efficiency. Training will be provided by the World Bank's financial management and procurement specialists before the commencement of, and during, project  implementation to the extent needed. Formal supervision of  financial management 

Page 52: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 47 of 74

will be carried out semiannually, while procurement supervision will be carried out as required by the client and project implementation timeline. In addition, a procurement specialist and technical  experts  of  the World  Bank  have  been  assigned  to  provide  HEIS  to  facilitate  the procurement of major  complex packages  and ensure  the  smooth application of  the World Bank’s Procurement Regulations. 

(c) Safeguards  inputs.  Inputs  from  an  environment  specialist  and  a  social  specialist  will  be required. The support will focus on institutional capacity building for environmental and social safeguards for EPGE and DPTSC as well as at Ywama power plant and substations as needed. Field visits will be based on the project needs and are expected to be semiannual during the first 18–24 months of project implementation. 

(d) Inputs on EPGE’s financial performance. Input will be required from a financial specialist for a regular review of EPGE’s financial status to monitor its financial capability. This exercise will be  combined with  the  supervision of  other World  Bank‐financed projects  implemented  by EPGE through semiannual reviews. 

(e) Inputs on sector policies. The World Bank will provide, through its staff and consultants as needed, experts who will engage in policy support to MOEE, complementing the activities of other donors.  

Table 1.1. Summary of the Implementation Support Focus 

Time  Focus  Skills Needed 

First 12 months  Monitor and assist in procurement of them main contracts, as appropriate 

Procurement Technical 

Monitor implementation of institutional capacity building on environmental and social safeguards 

Environmental and social 

Sector policies including financial viability of EPGE and other sector entities 

Power sector policy Financial 

After the first year until project closing 

Monitor project implementation (including construction progress) 

Technical Procurement 

Monitor financial management and disbursement  Financial 

Monitor performance of environmental and social impact management plan 

Environmental and social 

Sector policies  Power sector policy Financial 

10. Table 1.2 presents the skills mix required to provide these inputs. 

Table 1.2. Skills Mix for World Bank Inputs 

Skills Needed Number of Staff Weeks Per Year 

Number of Trips Per Year 

Comments 

Procurement   12  2  Based in the region 

Financial management  3  2  Based in the region 

Technical  4  2  Based in the region and the headquarters 

Environment  3  2  Based in the region 

Social  3  2  Based in the region  

Power sector policy  8  4  Based in the region and the headquarters 

Others (administrative)  6    Field based 

Page 53: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 48 of 74

External Consultancy and Specialized Advisory Services 

11. To support EPGE and DPTSC on the technical supervision of the project, a firm will be procured as owner’s engineer. The owner’s engineer will work in close collaboration with EPGE and DPTSC to oversight the implementation of all components. Given the limited institutional capacities for safeguards compliance of  EPGE  and DPTSC,  the  project  is  also procuring  an  ESIA  expert  to  reinforce  supervision of  safeguards implementation throughout the development of the project. The consultants will work closely with EPGE and DPTSC operational staff and focal points and provide training and build capacity within departments and report directly to EPGE PIU project coordinator. 

Proceedings 

Fiduciary Proceedings 

(a) Financial  management  and  disbursements.  The  financial  management,  disbursement arrangements,  and  reporting  requirements  will  be  conducted  as  detailed  in  the  financial management  manual  developed  for  the  project.  The  document  also  presents  staffing, budgeting,  and  accounting  proceedings  as  well  as  the  internal  controls,  funds  flows,  and auditing. The disbursements of the credit shall be made against the expenditure categories defined in table 1.3. 

(b) Procurement. Procurement of goods, works, and services will be conducted as detailed in the PPSD and the Procurement Plan developed for the project (see annex 4). These documents also further define the procurement support contemplated under the project.  

Environmental and Social Safeguards 

12. Detailed  proceedings  for  environmental  and  social  safeguards were  specified  in  the  safeguards instruments  developed  and  publicly  disclosed  for  the  project:  the  ESIA,  ESMF,  RPF,  and  CPPF.  These documents also detail the stakeholders’ consultation and disclosure processes as well as M&E activities to be conducted throughout project implementation.  

Table 1.3. Expenditure Categories 

Expenditure Category Allocation (US$) 

Allocation (SDR) 

Financing Percentage (inclusive of taxes) 

Goods, Works, Non‐Consulting Services, Consulting Services, Incremental Operating Costs, and Training for the Project 

350,000,000  254,900,000  100% 

Total  350,000,000  254,900,000  100% 

   

Page 54: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 49 of 74

ANNEX 2: Economic and Financial Analysis 

COUNTRY: Myanmar Power System Efficiency and Resilience Project 

 

1. This annex presents the economic and financial analysis for the investments under Component A (Upgrading Ywama Power Generation Units, covering 82 percent of total investments), given that the costs and benefits can be better quantified. The methodology used to assess the economic and financial viability of  the  project  is  consistent  with  the  World  Bank  Guidelines  for  Economic  Analysis  of  Power  Sector Investment Projects and the Guidelines on Shadow Price of Carbon in Economic Analysis 2017.  

Project Rationale 

2. Through this component, the proposed project aims at addressing a growing gap between supply and demand in Myanmar’s power sector due to inadequate generation capacity. Key issues regarding power generation capacity are summarized as follows:  

Peak demand is expected to grow at an average of 11 percent per year according to MOEE’s estimates. This means peak demand would increase from the current level of ~3,500 MW to approximately 10,000 MW by 2030. 

Most of the demand growth is concentrated in the Yangon region, which currently accounts for 40 percent of total demand of the entire country. Therefore, electricity supply options are needed  to mitigate  future shortfalls  in  this  region and  free up electricity  in  the  rest of  the country. 

The current supply capacity is limited and therefore an increase in peak demand in the range of 6,000–9,000 MW over the next decade would require 8,000–11,000 MW of firm capacity addition. 

Myanmar’s power generation cost—the so‐called “merit order curve”—is already quite steep, with costs jumping from MMK 50 per kWh (US¢3.3 per kWh; US$1 = ~MMK 1,500) or less for half of the capacity that are hydro units to more than MMK 100 per kWh (if not more than MMK 200 per kWh) for the rest of the thermal units. 

To address power shortfalls expected in the next two years, discussions are already under way regarding emergency power in the range of 1,000 MW (LNG ships/barges and other thermal generation). 

Because emergency power is the most expensive alternative for meeting demand, the country needs to develop lower‐cost options to reduce the need for emergency power in the medium term and meet the expected growth of demand in the long term. 

Least‐cost Justification 

3. There  is no government‐approved  least‐cost power development plan. To evaluate whether  the proposed 300 MW CCGT power plant (Ywama CCGT) to be commissioned by 2023 is among the least‐cost options to meet electricity demand, the World Bank developed an indicative least‐cost analysis based on data and information provided by MOEE. 

Page 55: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 50 of 74

4. The analysis was conducted using the World Bank’s Electricity Planning Model (EPM) for 2019–2030, which optimizes system‐wide costs including (annualized) capital cost of new plants, operating costs of new and  existing  plants,  and  cost  of  unserved  energy  and  capacity  reserve.  The  EPM considers  the  physical constraints on transmission between north and south Myanmar, hydro energy limits on a monthly basis, reserve  margin  requirement,  annual  limit  on  gas,  spinning  reserve  requirement,  minimum  variable renewable  energy  limit,  and  hourly  profile  of  demand  and  solar/wind  profile  (2–3  representative days/month). 

5. The results of the analysis show the following: 

Investment requirements would be at least MMK ~30 trillion (US$20 billion) over 2019–2030 even for the lower end of demand growth and slightly higher at MMK ~32–33 trillion (that is, US$1–2 billion more) for other variants of the demand forecast.  

Existing  and  under‐construction  generation  will  not  be  sufficient  to  meet  the  country’s growing demand  in  the short and medium terms; no single  fuel or  technology will be able ensure  that electricity supply  is provided at  least  cost  to support electrification efforts and economic growth. 

Myanmar will have to rely on a combination of different generation fuels and technologies. The country needs to develop its domestic renewable energy resources (solar and wind in the short‐to‐medium term) and its hydroelectricity potential (in the medium‐to‐long term). Power imports can also help meet demand at a low costs. 

The need  for developing  cheaper  resources on  time—hydro,  solar/wind, and  imports—can barely be overstated given the substantially more expensive alternatives in terms of LNG/HFO that  are  responsible  for  the  steep  supply  curve.  In  the medium  term, Myanmar  can  save around US$2 billion by developing variable renewable energy generation on a priority basis and  in  the  long  term,  savings  could  reach additional US$4 billion  (in discounted  terms)  by developing hydro power. The development of renewable energy generation and hydropower would reduce the reliance on more costly LNG. 

Among the power generation options, at a levelized electricity cost of about US¢7.3 per kWh (or MMK 110 per kWh), energy efficiency improvements of gas‐fired generation are a least‐cost option. Given that domestic gas is constrained at 415 MMcfd, efficiency improvements in the aging gas‐fired power plants will support the systems’ cost reductions and environmental footprint by decreasing the need for imported LNG and other costly fossil fuels such as HFO and  coal.  Finally,  gas‐fired  generation  will  support  increased  penetration  of  seasonal hydroelectricity and variable energy generation by providing firm capacity in the system. 

Scenario Analysis 

6. The EPM is used to model the following two scenarios: 

(a) Without project (base case). It models the physical limits on flows, gas availability, a central view on demand reaching 10.4 GW by 2030, and expansion of the north‐to‐south 500 kV link in  2023.  Short‐term  rentals  (1,000 MW  as  discussed  earlier)  also  form  part  of  the  supply options over 2020–2022 (for a five‐year period). It does not account for the new 300 MW CCGT power plant in the Yangon region, Ywama CCGT. 

Page 56: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 51 of 74

(b) With project (alternative case). In addition to the earlier assumptions, a new 300 MW CCGT power plant is added to the generation capacity of the Yangon region.  

Project Costs 

7. CAPEX costs. The analysis uses estimated costs provided in the feasibility study37 of US$1,000 per kW  for  the  proposed  highly  efficient  CCGT.  The  costs  correspond  to  a  full  turnkey  project.  Estimated investment costs include EPGE’s owner’s development costs and 10 percent contingencies. Implementation time  is  assumed  to  be  36  months.  Given  that  the  plant  will  be  in  a  brownfield  and  will  not  require improvements  in  the existing auxiliary  services,  land,  gas  infrastructure,  and  substation upgrading  costs were not considered in the study.  

8. OPEX costs. Nonfuel costs include fixed O&M costs and variable O&M costs, which are estimated at US$4.5 per MWh according to the feasibility study. Specifically, the following OPEX costs are included: LTSA for the gas turbines, fixed and variable costs of the HRSG and balance of plant systems maintenance, unplanned maintenance, costs of asset management during operation such as turbine rotor replacement and distributed control system refurbishments after 15 or 20 years, operator personnel costs, overhead, and other services, oil, and chemicals. 

9. Fuel costs. These are based on the export parity cost of natural gas at US$8.3 per MMBtu (in 2018 US$), which is slightly higher than the current tariff applied by MOGE for thermal power plant of US$7.5 per MMBtu. 

Table 2.1. Key Characteristics Assumed for the Ywama CCGT 

Plant Name  Start Year Capacity (MW) 

Fuela Nonfuel O&M Cost 

(US$/MWh) CAPEX 

(US$ millions/MW) Efficiencyb 

Ywama CCGT  2023  300  Gas  4.5  1,000  54% 

Note: a. Assuming Yadana gas. b. Site condition.  

Project Benefits 

10. Based  on  the  EPM  modelling,  total  output  from  all  generation  sources  to  meet  demand  was estimated based on a least‐cost dispatch from 2023 to 2030 for both scenarios. 

(a) Reduced system costs. Reduced system costs were estimated at US$60 million per year on average.  Cost  reductions  are  derived  from  lower  electricity  generated  from  higher‐cost generation options including coal (7 percent lower output), LNG (7 percent lower output), and emergency power (4 percent lower output).  

(b) Reduced unmet demand. The amount of unmet demand was estimated to be reduced by 459 GWh or a 54 percent reduction compared to the scenario without project. Reduced unmet demand is priced at a willingness to pay of US¢24 per kWh. This is derived from the estimated fuel cost of US¢20–25 per kWh for using diesel generators in Myanmar.  

(c) Reduced transmission losses. Given that the proposed plant will be located near the main load center, Yangon, transmission losses are expected to fall by 69.3 GWh by 2030. The reduction in technical losses is quantified at a system average marginal cost of US$7.1 per MWh. 

37 Feasibility Study for YWAMA CCPP, undertaken by consultant Tractebel‐Engie for the GOM. 

Page 57: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 52 of 74

(d) Avoided CO2 emissions. The project is expected to reduce carbon emissions by 12.3 million tons of CO2 equivalent. The carbon emission reductions are valued based on the World Bank Guidance on the Shadow Price of Carbon in Economic Analysis of Carbon (2017) and using the base case values of US$30 in 2015 through US$80 in real terms by 2050.  

Cost‐Benefit Analysis 

11. The economic viability of the component was assessed through a cost‐benefit analysis. A business‐as‐usual ‘without the project’ counterfactual sought to assess the economic merits of the project relative to a scenario where the project infrastructure is not constructed. An ENPV of the project was calculated based on the incremental annual net economic benefits of the project, derived from a comparison of total system costs and benefits with and without the project cases. Costs and benefits were discounted over a 30‐year period, where  the  benefits  start  accruing  in  2023.  This  economic  analysis  applied  a  conservative  social discount  rate  of  15  percent.38  The  GHG  emissions  reductions  were  estimated  using  the  World  Bank’s recommended estimate of the Shadow Price of Carbon in Economic Analysis.39  

12. The analysis demonstrates that the Ywama CCGT project is economically viable (see table 2.2). The project  yields  an  EIRR  of  27.9  percent, which  is well  above  the  hurdle  rate  of  15  percent.  The  ENPV  is estimated at US$165.0 million over a 30‐year discount period. The project is likely to reduce GHG emissions by 12.3 million metric  tons of CO2 over  its  life, mainly by  improving the efficiency of power generation. Including the benefits of avoided environmental damage, the project’s EIRR yields 30.9 percent and ENPV increases to US$241.8 million. 

Table 2.2. Results of Economic Analysis  

  Unit  Value 

Social discount rate  %  15.0 

Economic internal rate of return     

   EIRR  %  27.9 

   EIRR (including environmental benefits)  %  30.9 

Economic net present value     

   ENPV  US$, million  165.0 

   ENPV (including environmental benefits)  US$, million  241.8 

GHG emissions avoided  Mt CO2  12.30 

Financial Analysis 

13. The  financial  viability of  the project depends on  its ability  to generate  sufficient  cash  flow  from operations  to  satisfy  the  debt  repayment  requirements  toward  financial  institutions.  Key  financial assumptions were derived from a feasibility study of Ywama CCPP.40 The analysis was carried out from a public owner’s perspective and evaluates changes in free cash flows, under the assumption of 100 percent IDA debt financing with a 2.25 percent financing cost. A weighted average cost of capital (WACC) of 2.25 percent was assumed as a discount rate for the Ywama CCGT financial cash flows. This corresponds uniquely to the net cost of concessional debt financing.  

14. The project’s main financial costs are associated with the capital and operating expenditures of the plant.  The  project  starts  generating  revenues  from  the  sale  of  additional  power  to  customers  in  2023, 

38 The World Bank Interim Guidelines (issued in May 2016) recommend using a discount rate equivalent to twice the average rate of growth of the projected gross domestic product per capita in real terms. 39 World Bank. 2017. Guidance Note on Shadow Price of Carbon in Economic Analysis. 40 Tractebel Engineering S.A. 2018. Feasibility Study for Ywama CCPP. 

Page 58: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 53 of 74

contributing annually to additional cash inflow of approximately MMK 280.6 billion per year (including 5 percent commercial losses). The earnings before interest and taxes amount to MMK 74.3 billion on average per year. Debt is disbursed over a three‐year period starting in 2020, following a 20‐60‐20 percent scheme.  

15. As shown in table 2.3, the project renders an FIRR of 14.9 percent well above the hurdle rate and an FNPV of US$734.2 million. These figures demonstrate the financial viability of the project. The analysis also estimates that the LCOE41 of the proposed CCGT will be MMK 86.2 per kWh (US¢5.7/kWh), which is below the average wholesale supply cost of MMK 130 per kWh in Myanmar. With a minimum annual debt‐service coverage ratio of 3.0, the project generates sufficient revenues to cover its debt obligations.  

Table 2.3. Results of Financial Analysis  

  Unit  Value 

WACC  %  2.25 

FIRR  %  14.9 

FNPV  US$, millions  734.2 

FNPV  MMK, millions  1,101,253 

LCOE  US¢/kWh  5.7 

LCOE  MMK/kWh  86.2 

Sensitivity Analysis 

16. Given the uncertainty around some of the variables affecting the economics of this component, a sensitivity analysis will be carried out to assess the robustness of the project in terms of uncertainties and changes in key input variables, as shown in table 2.4. These are tested based on switching values (ceteris paribus) of the percentage changes in key parameters, including (a) CAPEX overrun, (b) OPEX overrun, (c) social discount rate, and (d) electricity supply revenue. The analysis demonstrates that a CAPEX overrun of 73 percent would  render  the project  economically unviable;  a  20 percent  drop  in  the  electricity  supply revenue would lead to a negative FNPV.  

Table 2.4. Switching Value Analysis to Base Case Scenario: Project Cumulated Results 

  EIRR (%) ENPV (US$, millions) 

FIRR (%) FNPV (US$, millions) 

Baseline  27.9  165.0  14.9  734.2 

CAPEX overrun         

  +5% versus baseline  26.5  153.6  14.26  719.8 

  +10% versus baseline  25.3  142.3  13.59  705.5 

  +15% versus baseline  24.1  130.9  12.96  691.1 

OPEX overrun         

  +5% versus baseline  27.7  162.8  13.09  609.5 

  +10% versus baseline  27.6  160.5  11.09  484.7 

  +15% versus baseline  27.4  158.2  8.92  360.0 

Social discount rate         

  ~10%  27.9  321.2  14.9  734.2 

  ~12.5%  27.9  231.3  14.9  734.2 

Electricity supply revenue         

  +10% versus baseline  27.9  165.0  19.3  1,086.0 

  −10% versus baseline  27.9  165.0  9.3  382.6 

41 The LCOE represents the NPV of all unit costs of electricity generated over the lifetime of a project (assuming all costs of building, operating, and financing the power plant).  

Page 59: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 54 of 74

17. Additional sensitivity analysis was carried out for a scenario where additional  investments in the amount of US$50 million are added to Component B. When these investments are considered on a pure capital cost basis and without considering accrual of economic benefits or financial cash flows associated exclusively with this component, the project still renders viable economical and financial results. 

Table 2.5. Key Assumptions  

  Value  Source 

CAPEX   US$1,000 per MW  Tractebel feasibility study 

Nonfuel O&M cost   US$4.5 per MWh  Tractebel feasibility study 

Fuel O&M cost  US$8.3 per MMBtu  Tractebel feasibility study 

Average power supply revenue  MMK 125 per kWh  World Bank estimate 

Marginal generation cost  US$24 per MWh  World Bank estimate 

Generation cost of diesel emergency plants  US$7.1 per MWh  World Bank estimate 

Tax rate   0%  Project is exempt of tax  

Page 60: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 55 of 74

ANNEX 3: Inclusion and Peace Lens Note 

 COUNTRY: Myanmar  

Power System Efficiency and Resilience Project  

Project Name and P code: 

Power System Efficiency and Resilience Project (P162151) 

Name of Task Leader: 

Claudia Ines Vasquez Suarez Maria Ayuso Olmedo 

Estimated financing: 

IDA: US$350 million  Total: US$350 million 

Name of Staff/Consultant assisting with IPL: 

Maria Ayuso Olmedo 

Key project activities: 

Component A: Upgrading Ywama Power Generation Units (US$290 million)  

Component B: Improving the Resilience of the Power Network (US$60 million)  The proposed project aims at increasing the output and efficiency of power generation and improving power network resilience. To do so, project activities will include the upgrading of the Ywama power plant (Component A), which is a brownfield location, and upgrading works in existing substations countrywide of the power system (Component B). Among other benefits, this will help connect the most disadvantaged townships of the Yangon region to the grid. The project also seeks to strengthen institutional capacities by providing implementation support to the IAs of this project and helping MOEE reduce the productivity gap facing women staff due to childcare responsibilities.  

Geographic area(s) of intervention: 

The main area of intervention is the Yangon metropolitan area (Insen township), where the Ywama power plant is located, with direct benefits across Yangon townships and indirect benefits across the country. Works to improve the resilience and capacity of the power network will be undertaken within the footprint of existing high‐voltage substations. Power substations are located across Myanmar. Specific substations to benefit from the project’s investments will be decided based on technical and climate risks assessments and will be prioritized based on their coverage of disadvantaged households (according to the MDI). Substations in areas where there is continuing or has been recent violence/conflict, as monitored by the World Bank based on data from the Myanmar Institute for Peace and Security, will not be supported under the project. 

Inclusion 

1. Background. Has the project  identified any specific groups that are particularly excluded from the sector of intervention?  

The project has identified that households without access to modern electricity services are excluded in the sector of intervention, which is power generation and supply. Many of these households are in more remote  rural  areas, where most  of Myanmar’s  poor  and  vulnerable  live,  as well  as  in  disadvantaged townships within the Yangon region. The MLCS 201742 shows that,  in 2017, only 4.8 percent of urban 

42 Central Statistical Organization (Ministry of Planning and Finance of the Republic of the Union of Myanmar), UNDP, and World Bank. 2018. Myanmar Living Conditions Survey 2017: Key Indicators Report. https://www.undp.org/content/dam/myanmar/docs/Publications/PovRedu/MLCS‐2017.pdf 

Page 61: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 56 of 74

households were not connected to the public grid versus 75.3 percent of households in rural settings. Lack of access to electricity is particularly notable in border areas, many of which are affected by conflict, as these areas are far from the existing grid infrastructure (see figures 6.2 and 6.3 in annex 6). Although electricity access in the Yangon region is relatively high (70 percent), there is a stark difference among townships. Those with low access to electricity are also facing the most disadvantages across the region (see section I.B for further details).  

To address the concerning rates of electricity access in the country, the Government launched the NEP, which seeks to achieve universal access by 2030 through grid extension and off‐grid initiatives. Under this program, the electrification rate increased from 25 percent in 2010–2011 to 50 percent in 2018–2019, according  to  recent estimates  from MOEE.  To  support  the NEP,  the World Bank  is  implementing  the National Electrification Project (IDA credit of US$400 million) to extend the public grid and provide off‐grid solutions for the country’s most disadvantaged households. As of November 2019, more than 1.4 million  had  benefited  from  access  to  modern  electricity  services  under  this  project.  Alongside  this progress,  the  use  of  distributed  generation  technologies  (such  as  solar  PV  home  systems  and  local micro/mini  grids)  has  expanded  in Myanmar—particularly  in  rural  areas without  access  to  electricity where the use of candles or kerosene is prevalent. The regional government and the Yangon electricity utility, YESC, have also recently designed a detailed plan and secured funding to electrify all households in the Yangon region within the next three to four years. 

This  project  has  also  identified  that  SMEs  and  low‐income  households  connected  to  the  grid  are disproportionally affected  in the sector of  intervention by  low‐quality electricity services that result  in blackouts and brownouts, particularly during the summer season. In Yangon, where electrification rate is high  (80  percent),  40  percent  of  the  residents  reported  voltage  fluctuations  as  their main  concern.43 Specifically,  the bottom 20 percent of households  identified power  interruptions  as  the most  serious problem of electricity supplied by the public grid. Unable to afford backup power generators and voltage regulators, lower‐income households bear the costs of long outages and damaged electrical equipment. SMEs, which represent 95 percent of the country’s business landscape and are considered one of the key engines for economic growth and job creation, identify the lack of access to reliable electricity supply as one of the main obstacles holding back their growth. In terms of procedures, time, cost, and reliability of electricity  supply,  the  Doing  Business  202044  report  ranks  Myanmar  148  out  of  the  190  economies analyzed. 

In addition, female professionals are often excluded in the technical streams in the power sector and in the  specific  sector  of  intervention.  The  gender  assessment  and  the  literature  reviewed  during  the preparation of this project suggest that the public energy sector in Myanmar offers wide opportunities to develop more inclusive workplaces and diverse workforces. There are barriers for women to realize their full professional development potential due to childcare responsibilities, among others. Key findings of research  and  interviews  conducted  with  EPGE  and  DPTSC  staff  show  women  face  a  productive  gap compared to men given that (a) they are more likely to be distracted while at work, (b) mothers are more likely to take time off work than fathers, (c) they are more likely to be unable to accept a job promotion, and (d) they are more likely to pass on training opportunities. Childcare responsibilities are compounded by the fact that Myanmar’s administrative capital, Naypyidaw, offers limited services, and staff are far from their family support networks.  

43 World Bank staff calculations based on data from the MLCS 2017.  44 World Bank Group. 2020. Doing Business 2020: Comparing Business Regulation in 190 Economies. Economy Profile: Myanmar.  

Page 62: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 57 of 74

2. Targeting.  How  are  individual  beneficiaries  or  beneficiary  groups  selected  for  participation  in  the project? Does the project include specific actions or design features that focus on inclusion of specifically identified excluded groups?  If not, should  it? Does the project seek  to strengthen or build systems with relevant agencies to address and/or measure social exclusion? 

All groups identified as excluded or particularly affected by the sector of intervention are expected to become direct and indirect beneficiaries of the proposed project. 

Unelectrified  lower‐income  households.  The  project  complements  the  NEP  by making  available  the power supply required for Myanmar to continue its electrification efforts. Specifically, the project will support the  implementation of the regional government and YESC to electrify around 300,000 people living in townships facing the most disadvantages in the Yangon region. In addition, substations will be identified and prioritized based on  their potential  to support electrification efforts,  focusing on  those serving the most disadvantaged townships.  

Firms  and  SMEs  in  particular, will  benefit  from  (a)  increased  hours  of  reliable  power  supply  due  to avoided  load shedding and blackouts,  (b) reduced risk of power system collapse and outages, and  (c) higher power‐supply quality through more‐stable voltage and frequency. While all electricity consumers in the Yangon region will also benefit from these results, the positive impact on SMEs is expected to be greater as it translates into monetary gains due to (a) lower revenue losses, (b) less need for use of backup generators, particularly for SMEs; and (c) extended operating life of electrical and industrial appliances and machines, which translates into less spare parts and purchases of new equipment. 

Female  professionals  at  MOEE  will  benefit  from  improved  access  to  quality  childcare.  The  project activities include the development of a rollout plan and support for the setup of a childcare pilot program at MOEE. It is expected that the productivity gap between women staff benefiting from the childcare and men  will  decrease,  as  measured  by  reduced  absenteeism  during  working  hours  (due  to  childcare obligations) and increased opportunities to accept promotions and attend trainings.  

3. Consultations. Have representatives of excluded groups been engaged in project consultations? How widespread were consultations  (both geographically,  in number, and with different population groups)? What languages other than Myanmar were used? 

As part of the project preparation, an ESIA and an ESMF, including an RPF and a CPPF, have been prepared in compliance with national requirements and the World Bank’s safeguard policies.  

Consultations  were  organized  by  EPGE  and  DPTSC  with  support  from  an  independent  consultant  to integrate stakeholder concerns into the safeguards instruments. Consultations were carried out in the Myanmar  language and  included stakeholders such as  representatives of  low‐income households and SMEs (for example, tea shops) from areas near the Ywama power plant. These groups are identified as being disproportionally affected in the specific sector of intervention. 

About 30 representatives of CSOs representing several ethnic groups from across the country participated in  the  CPPF  consultation  of  the  project.  Consultations were  conducted  in  the Myanmar  language  in Yangon. Given that specific investments are not yet identified, the objective of the consultation was to bring together CSOs working in areas with significant number of households yet to be connected to the national  grid.  Key  suggestions  included  engaging  early  on  with  local  stakeholders,  gaining  a  good understanding  of  the  subproject's  local  context,  and  considering  sensitive  areas  like  the  ones  under conflict. CSOs also recommended a modification of the term ‘ethnic minorities’ in the Myanmar‐language 

Page 63: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 58 of 74

version of  the safeguard’s documents. These  recommendations were  incorporated  into  the CPPF and other relevant documents. 

During  the  project  preparation,  a  gender  assessment  was  also  conducted  to  identify  potential  gaps between the experiences and status of women and men. As part of the gender assessment, consultations were also held with MOEE staff in focus groups (male staff with children, female staff with children, and female workers without children or expecting). In addition, a survey was undertaken to understand how childcare responsibilities affect employees working in MOEE in Naypyidaw, Myanmar. The survey covered 197 respondents out of a total population of 832 employees at EPGE and DTPSC. 

4. Assessment and mitigation of exclusion risks in project design. In what ways could implementation of project activities exacerbate social exclusion? How are these risks mitigated? Could the way the Project Management Unit/Agency is perceived by project beneficiaries hinder access to project benefits by certain groups? How is this mitigated?  

The project activities have a low risk of further aggravating the issues of social exclusion identified in this note (see section 1) as the project does not introduce new infrastructure or services in the country, but seeks to retrofit existing infrastructure (Ywama power plant and substations) within its current footprint. 

The  risk  of  perpetuating  the  social  exclusion  of  nonconnected  households  and  SMEs  is mitigated  by targeting criteria for the selection of substations under Component B and by supporting the electrification in the Yangon region. More broadly, the project will complement the Government‐led NEP and the IDA‐funded National Electrification Project.  

By improving the quality of service of all connected customers, the project will alleviate the impacts of low‐quality electricity services on low‐income connected households and SMEs, which are more exposed to the economic  impacts of revenue losses due to blackouts, expenditures on backup generators, and replacement of spare parts for damaged devices.  

Finally, it is expected that by providing improved access to reliable electricity, the project will contribute to private sector investment and job creation. This effect might be mainly observed in Yangon (where Ywama power plant  is  located), which has one of the highest electrification rates  in the country. As a growth pole, Yangon may attract internal migrants from poorer areas of the country, thus playing a role in poverty reduction and, indirectly, in inclusion. 

5. Assessment and mitigation of exclusion risks in project design (gender). Has the project considered adaptations to promote gender equality and inclusion of women, especially for those who are unable to leave the home, or who are illiterate? 

The project includes specific actions that focus on the inclusion of women in the sector of intervention, as described in section IV.C(iii). To do so, the project will provide technical assistance and start‐up capital to MOEE for the establishment of a childcare pilot at MOEE premises in Naypyidaw.  

6. Assessment and mitigation of exclusion risks in project design (access). Has the project anticipated and mitigated potential resistance of government officials to travel to certain types of villages or conflict‐affected areas given fears for personal security? What adaptations to project design and implementation approaches are being considered to reach communities whose movement is restricted?  

Page 64: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 59 of 74

Substations located in areas in which there is conflict will not be eligible for financing under the project. 

It is not considered that there is a high likelihood of potential resistance of government officials to travel to  conflict‐affected  areas  or  certain  types  of  villages  in  this  project  given  that  (a)  the  presence  of government officials is expected to be required mostly in Yangon; (b) physical works will take place in existing facilities, which are already maintained and operated by utility employees; and (c) high‐voltage substations are mostly located in central Myanmar, where there is currently no substantial conflict. 

7. Assessment and mitigation of exclusion risks in project implementation. Has the project considered the  role  that  military‐controlled  ministries  and  security  forces  may  play  in  influencing  project implementation on the ground?  

Military‐controlled ministries are not involved in the provision of grid‐connected electricity services and are unlikely to influence the implementation of the project on the ground.  

8. M&E.  Does  the  Results  Framework  include  indicators  to  adequately  monitor  social  inclusion?  Is technology  being  used  to  overcome  challenges  to  monitoring  inclusion?  What  other  aspects  of  social inclusion are monitored by the project through other mechanisms (surveys, studies, consultations, etc.)? 

The Results Framework will monitor the number of households  in disadvantaged townships that have gained access  to  the public grid.  Increased access will be  facilitated by  (a)  investments  in  the Ywama power plant, which will support the achievement of 100 percent electricity access in the Yangon region, and  (b)  investments  in  power  substations  to  allow  the  expansion  of  the national  grid.  The  improved inclusion of women in the public energy sector will be monitored through the reduced productivity gap between women and men while at the workplace resulting from the implementation of the pilot childcare at MOEE.  

Peace 

9. Consultations. If the project is implemented in conflict‐affected areas, has the task team consulted widely with local CSOs on relevant conflict dynamics and between Government and EAOs? 

The  project’s  main  activity,  the  upgrading  of  Ywama  power  plant,  is  not  in  a  conflict‐affected  area. However, given that substations are scattered across the country, the team consulted with CSOs working in close collaboration with EAOs on the CPPF, as described earlier. Activities and works to be implemented in high‐voltage substations will be consulted with local population and stakeholders, including CSOs and EAOs as appropriate, in line with the requirements of the ESMF and the CPPF.  

10. Assessment and mitigation of the risk for the project to exacerbate tensions. In what ways might project  implementation  exacerbate  conflict?  How  is  this  risk mitigated? What  are  the  attitudes  of  the relevant EAOs toward the Government, service delivery, the potential project? Are relevant EAOs providing similar  services  in  their  areas  of  control  or  influence?  How will  these  parallel  delivery mechanisms  be reconciled?  

How  are  different  groups/stakeholders  likely  to  perceive  the  project? Would  differences  in  perception potentially lead to intergroup violence? What ‘bridging’ mechanisms (to connect different social groups) are or might be contemplated to address possible tensions?  

Will the project support internally displaced person camps? If so, how will these services affect discussions around the permanency of camps? 

Page 65: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 60 of 74

The  risk  of  exacerbating  conflicts  or  intergroup  violence  due  to  the  implementation  of  substation strengthening and climate resilience works is low. Mainly, the works are to be implemented within the footprint of existing infrastructure (substations). No new transmission line or power substation will be financed under the project. As mentioned earlier, the project will not implement investments in areas where there is conflict.  

11. Assessment and mitigation of the risk for the project to fuel the conflict. Does the project allocate indirect benefits (employment opportunities, etc) that could be captured or be a cause of local conflict? How is this mitigated?  

What direct or  indirect effect might  the project have on  (a)  local authority/power,  (b) access  to natural resources, and (c) illegal trade/activities that may create tensions?  

See answer to question 10 above. 

12. Assessment  and  mitigation  of  conflict‐related  risks  to  project  implementation. Do  obstacles  to including conflict‐affected communities need to be addressed? (for example, eligibility based on presence of government administrative staff, past results achieved or level of governance, recognized communities by township General Administration Departments, etc.). Are security provisions adequate to allow World Bank implementation support to conflict‐affected areas?  

See answer to questions 6 and 9 above. 

13. Supporting peace.  Is  the project  expected  to  support peace  (for example,  related  to  the national peace process, in terms of trust building delivery of development assistance, etc)? 

The project is not expected to support peace directly. 

14. M&E.  What  is  the  team’s  plan  to  continuously  monitor  the  project’s  impact  on  peace  during implementation? Will technology be applied to ease monitoring constraints? 

See response to question 8 above. 

   

Page 66: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 61 of 74

ANNEX 4: Procurement Implementation Arrangements 

 COUNTRY: Myanmar  

Power System Efficiency and Resilience Project

Procurement Capacity and Risk Assessment 

1. Starting from October 2018 and throughout project preparation,  the World Bank has conducted PCRAs for the two IAs, EPGE (Component A) and DPTSC (Component B). These assessments revealed the following findings. 

Experience Implementing Public Procurement and Projects Funded by International Financial Institutions

(a) EPGE has some experience in implementing international bidding funded by the World Bank and JICA. Under the World Bank‐financed EPP, EPGE successfully procured a CCGT power plant with a contract value of US$110 million. During  that process, EPGE was heavily assisted by independent consultants, who were provided to the GOM by the Norwegian Government on pro bono basis. EPGE’s  involvement in the process was mainly reviewing Norconsult’s work and coordinating with the World Bank. EPGE has also acquired some experience in selection of consultants. EPGE hired Tractebel to carry out a feasibility study of Ywama power plant. EPGE’s involvement was also limited since this was a direct selection to an existing contract competitively procured by MOEE as owner’s engineer under the EPP. Hence, a limited number of  EPGE  staff  have  been  involved  in  these  procurement  activities.  In  October  2018,  EPGE successfully awarded a DSI  contract of US$140 million  financed by  JICA’s  loan. Despite  the procurement experience acquired while  interacting with multilateral  and bilateral  financial institutions, EPGE has rather  limited competent resources and largely relies on consultancy assistance to implement procurement activities. 

(b) Overall,  DPTSC  has  limited  experience  in  carrying  out  procurement  under  international competitive approaches. Although DPTSC has been exposed to JICA procurement procedures, most  procurement  has  been  carried  out  using  government  procedures  with  the  largest awarded  contract  of  about  US$4  million.  The  scope  of  goods  to  be  procured  under  the proposed project is of regular and standard nature for DPTSC and, therefore, the elaboration of  technical  specifications  is  not  considered  a  constraint. However,  this  project  represents DPTSC’s first procurement under the World Bank policies. 

(c) All procurement documents are subject to concurrence and approval of, sequentially, the IAs’ Management  Executive  Tender  Committees  (headed  by  the  managing  directors)  and  the MOEE’s Management Executive Tender Committee (chaired by the minister). All contracts are, however, signed by the respective Managing Director.  

Contract Management Capacity 

(a) All  payment  requests,  variation  orders,  and  decisions  on  assigned  officials  and  personnel employed must  be  submitted  for  the managing director’s  approval  under  the  government approval  procedures.  In  the  case of  import of  goods,  the  import  permissions  and  customs clearance  are  issued  by  the material  planning  department  of DPTSC  and  the  procurement department  of  EPGE  as  part  of  their  duties  and  responsibilities.  The  detailed  payment procedures, authorizations, and internal control issues applying to the project are laid out in the financial management manual of the project. 

Page 67: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 62 of 74

(b) EPGE has limited contract management capacity. According to the EPP experience, the owner’s engineer support was key for EPGE to manage the contract with the contractor. Nonetheless, EPGE  faced  challenges  in  administering  a  contract  following  international  standards  and practices. Takeover of completed works was time‐consuming. Under the proposed contractual arrangements,  the  integration  of  EPGE  staff  with  the  contractor’s  team  throughout implementation will be an area for consideration to ease the takeover upon the completion of works.  

(c) To date,  the  largest  contract ever handled by DPTSC was about US$4 million. DPTSC has a contract‐supervision  and  quality‐assurance mechanism  in  place  managed  through  its  own personnel. MOEE also has an  independent quality‐control  team managed by  the minister’s office  with  members  from  different  departments.  Upon  receiving  approval  from  MOEE’s independent quality control team, DPTSC prepares acceptance certificates and consults with the MOEE’s Executive Committee before issuing official certificates to the contractors. 

Complaint Management and Dispute Resolution System 

(a) The complaint procedures will follow the revised government tender Directive No. 1 of April 2017  and  the  World  Bank’s  Procurement  Regulations.  However,  the  IAs  do  not  yet  have experience  in  applying  complaint  procedures  under  the  directive.  During  the  EPP implementation, EPGE received several complaints from bidders, which were resolved with the World Bank’s assistance and support from consultants. Based on this experience, it could be expected that the complex and technical nature of potential complaints will require HEIS and strong technical support from World Bank and consultants.  

Need for Hands on Extended Support 

(a) Both  IAs  have  capacity  constraints  in  carrying  out  large‐value,  complex,  competitive procurement  activities,  which  they  have  not  implemented  under  the  World  Bank’s Procurement Regulations. Given the complexity and size of procurement contracts and the necessity to start some activities before consultants are hired, both IAs expressed the need for World  Bank’s  procurement HEIS.  HEIS  for  both  procurement  and  technical  aspects will  be provided by the World Bank staff (one procurement specialist and at least one power engineer will work closely with the client). The procurement specialist providing HEIS will be different from the procurement specialist assigned to undertake the World Bank’s fiduciary functions for the project. This arrangement will enhance HEIS quality and guarantee the independence between HEIS providers and fiduciary staff from the World Bank side. The specific scope and modalities of the HEIS have been detailed in the HEIS memo request, which is included in the project document package submitted to the World Bank’s management for approval. 

(b) It is expected that HEIS will be provided to EPGE and DPTSC for strategic contracts, including, among  others,  (i)  the  owner’s  engineer  and  the  environmental  and  social  management consultancy contracts, (ii) the DSI contract for Ywama power plant, and (iii) the supply contract for key transmission equipment. This expanded support is envisioned for the first 18 months from the initiation of the procurement activities.  

Procurement Risks and Mitigation Measures 

(a) Based on the World Bank PCRA and the PPSD findings, the procurement risk of the proposed project is rated high. Table 4.1 presents the major procurement risks identified and mitigation measures agreed with MOEE and the IAs during the project preparation. 

Page 68: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 63 of 74

PPSD and Procurement Plan 

2. Through EPGE and DPTSC, MOEE prepared a PPSD, which was agreed by the World Bank. The PPSD presents how major procurement activities under the project will support its development objective and deliver the best value for money. In addition, the PPSD includes the rationale for key procurement decisions, such as the market approach and procurement methods selected. Throughout the project implementation, the  PPSD  and  the  Procurement  Plan  of  the  project  will  be  regularly  updated  as  appropriate  (the procurement plan should be updated annually, at least, or as required). The World Bank will arrange the publication of the agreed initial procurement plan and all subsequent updates on its external website once a no‐objection is provided. 

3. The PPSD identified the following major procurement activities to support the PDO achievement:  

(a) Ywama power plant rehabilitation DSI contract (US$285 million) 

(b) Owner’s engineer consultancy contract (US$2 million) to support both IAs, EPGE and DPTSC, with the procurement and contract management under Components A and B of the project  

(c) Environmental  and  social  safeguards  management  consultancy  contract  (US$1  million)  to support  both  IAs,  EPGE  and  DPTSC,  in  management  and  compliance  of  safeguards requirements under Components A and B of the project 

(d) Contracts for supply of transmission network equipment (such as mobile substations power, current  transformers,  power  and  shunt  reactors,  switch  bays,  and  protection  and  control device) and works for strengthening and improved resilience of existing substations (estimated at about US$55 million in total).  

(e) Technical assistance on strengthening the capacity of DPTSC on climate resilience aspects and support project implementation (estimated at about US$5 million in total). 

4. Key findings and recommendations of the PPSD are as follows:  

(a) The procurement related to Ywama power plant rehabilitation (US$285 million) is rated high risk due to its technical complexity, critical role in the project, relatively large value, and long‐term contractual period. Therefore, a procurement approach based on a single‐responsibility contractor was recommended. Under this approach, the contractor will be responsible for the overall design, engineering, procurement, construction, commissioning, and testing activities (for  the  purpose  of  this  project,  abbreviated  DSI).  This modality  is  considered  particularly relevant given the low capacity assessed for EPGE to conduct these activities. The market of DSI  contractors  is  growing  fast  in  Myanmar  and  in  the  region.  Hence,  this  procurement package will  benefit  from an  international market  approach. A  single‐stage bidding will  be applied as the feasibility studies conducted during project preparation helped select the most appropriate  technology  for  the  power  plant,  CCGT,  and  set  clear  functional  requirements. Based on experiences from similar projects, it was also recommended to opt for a PQ phase to help ensure that only contractors with adequate capacity and experience, among all active in the region, compete for the contract award.  

(b) The consultancy support for an owner’s engineer (US$2 million) and the environmental and social safeguards expert  (US$1 million) are considered of strategic  importance. Despite  the relatively low value of these contracts, the support to EPGE is critical to ensure an adequate procurement and supervision of the DSI contractor as well as a sound safeguards management 

Page 69: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 64 of 74

and compliance during Ywama power plant rehabilitation. Therefore, the owner’s engineer and the environmental and social safeguards consultants will be selected through a QCBS.  

(c) The procurement of transmission equipment and works to strengthen existing substations and improve their resilience (US$55 million in total) is considered of standard nature. There is a global competitive market for this equipment in the power industry. During the first 18 months of  the project,  the procurement of  some mobile  substations, estimated at US$9 million,  is identified as necessary. This equipment package will be procured through a single‐stage one‐envelope RFB with international and open market approach. The capacity of local contractors to implement the works to strengthen substations is perceived to be adequate, which justifies a  national market  approach. Other  specific  investments  in  transmission  equipment will  be decided  during  project  implementation  upon  the  borrower’s  requests  and  outcomes  of technical assistances to help the country address climate adaptation and resilience.  

(d) EPGE and DPTSC have not yet implemented the World Bank’s Procurement Regulations of July 2016. At the same time, the procurement of the proposed project is complex and has a large value.  Thus,  the  IAs  requested  the  World  Bank’s  procurement  HEIS  to  facilitate  the procurement of major and key packages and to ensure the smooth application of the World Bank’s Procurement Regulations. HEIS was therefore  initiated from the project preparation stage  to  catalyze  key  procurement  activities  (see  ‘Need  for  Hands  on  Extended  Support’ section). The PPSD proposed conducting advance procurement of the owner’s engineer, the environmental and social safeguards consultant, and the DSI contractor for the power plant upgrading, given the timelines required to accomplish them.  

5. Table 4.2 presents the proposed procurement arrangements. 

Procurement Method and Prior Review Thresholds 

6. Based  on  the  high  procurement  risk  of  the  proposed  project  at  the  appraisal  stage,  table  4.3 presents the procurement methods and prior review thresholds that will be applied.  

7. Contracts below the prior review thresholds in table 4.3 shall be subject to post‐review auditing by the  World  Bank  team  on  an  annual  basis,  according  to  the  procedures  set  forth  in  the  Procurement Regulations.  The  sampling  rate  of  post  review  is  at  least  10  percent  of  the  total World  Bank‐financed contracts awarded across the World Bank portfolio that have not been subject to prior review by the World Bank.  

Monitoring by STEP 

It  is  mandatory  for  the  proposed  project  to  use  the  World  Bank’s  online  tool  Systematic  Tracking  of Exchanges  in Procurement (STEP) for procurement information exchanges and recording. The use of the system will facilitate the efficient management of procurement‐related communications and records. EPGE has significant experience in operating STEP under the EPP. An EPGE STEP account for the proposed project has  been  opened  and  activated.  EPGE  has  been  already  trained  in  its  use  and  has  used  the  system  to communicate  procurement  information with  the World  Bank. DPTSC  is  in  the  process  of  submitting  its registration form to open a STEP account. Throughout project implementation, the World Bank will provide hands‐on support and training to both IAs to ensure their proficiency in using STEP. 

Page 70: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 65 of 74

Table 4.1. Major Procurement Risks Identified and Mitigation Measures Agreed with MOEE and IAs  

No.  Risk Descriptions  Mitigation Measures  Timelines 

1.  Inadequate technical and procurement capacities of the IAs 

For the proposed project, strategic institutional implementation arrangements were planned from project preparation stage. For each IA, a PIU led by a senior official (for example, the chief engineer) will be established with full‐time working staff from various specialized divisions (project coordination, engineering, procurement, financial management, and safeguards). Assistance from international consultants will also be mobilized to complement the capacity resources.   For the purposes of project preparation and advance procurement implementation, each IA has assigned a project team consisting of engineers from technical departments and procurement officers from the procurement department.   The World Bank will provide HEIS for strategic contracts.  Procurement staff of the IAs will receive intensive training in the World Bank’s Procurement Regulations and contract management.  

Throughout project implementation  

2.  Insufficient interest of bidders  It was agreed that EPGE must conduct market outreach/engagement during the preparation of feasibility studies and PQ processes.  EPGE and DPTSC will advertise procurement notices internationally. 

Before/during PQ   Before PQ documents/RFB issuance 

3.  Delays in procurement processes of major packages (CCGT plant, mobile substations, power transformers and reactors, switch bays, and so on) 

The World Bank will encourage and advise MOEE to accelerate the review and decision‐making process.  The project will introduce advanced procurement actions.  The project will introduce the World Bank’s HEIS as well as support from the owner’s engineer and environmental and social management consultant.  

Throughout project implementation  

4.  Evaluated prices of bids exceeding the costs estimates of the project’s owner 

To use realistic costs, the feasibility studies conducted for the project have considered the borrower’s engineering estimates and budgetary proposals from two original equipment manufacturers (OEMs).   The budget of the project includes adequate price contingencies. 

During the preparation of feasibility studies and procurement documents  

Page 71: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 66 of 74

No.  Risk Descriptions  Mitigation Measures  Timelines 

5.  Lack of adequate experience and qualification of the selected contractor 

The qualification requirements based on market research will be carefully prepared at the PQ stage. Lessons learned from similar projects (for example, EPP) will also be incorporated into the qualification criteria. 

During PQ or/and bidding stages 

6.  Lack of coordination between the main DSI contractor and OEM 

Generally, the DSI contractor is the sole responsible party. The possibility to request an OEM’s performance guarantee will be explored. 

During the preparation of procurement documents and contract management 

7.  Budget and time overruns during the execution of contracts; change orders to accommodate unexpected works  

A detailed feasibility study has been prepared to consider the full scope of works necessary for the completion of the plant. For unforeseen change orders, adequate price contingencies are included. For transmission equipment, lump‐sum contracts will be used. 

During the preparation of procurement documents, technical specifications, and contract management 

8.  Delayed payment due the IAs’ lengthy internal management systems and procedures 

Contracts’ payment terms and conditions must be aligned with the World Bank’s standard procurement documents and be fully enforceable.  The detailed payment procedures, authorizations, and internal control issues are laid out in the financial management manuals of the project. The managing director will be supported by a qualified team to accelerate the review and approval process. 

During the preparation of procurement documents and contract management 

9.  Sustainability risks related to O&M issues after completion 

An LTSA will be included in the DSI contract.  During contract management 

10.  Noncompliance with World Bank procedures (including fraud and corruption issues), which may occur at different levels during project implementation 

Procurement staff of EPGE and DPTSC will receive intensive training in the World Bank’s Procurement Regulations and contract management, including mitigation of fraud and corruption risks. The project will implement relevant actions to mitigate fraud and corruption risks, such as (a) bid evaluators to sign code of ethics; (b) IAs to conduct due diligence to detect fraud and corruption allegations for, at least, the recommended bidder; and (c) IAs to implement a contract management plan with KPIs to ensure quality, timeliness, value for money, and integrity.  

Throughout project implementation  

  

Page 72: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency and Resilience Project (P162151)

Page 67 of 74

Table 4.2. Proposed Procurement Arrangements and Procurement Plan for the First 18 Months 

Package/ Contract 

Category Es mated Cost (US$ million) 

Procure‐ment 

Method 

Market Approach 

Contract Form 

Review by Bank 

PQ/ REOI 

Adversement 

PQ/REOI Sub‐

mission Deadline 

PQ/SL Evalua‐

on Report 

RFB/ RFP 

Issuance 

Bid/ Proposal Submissi

on Deadline 

Bid/ Proposal Evalua‐

on Report 

Contract Award 

Contract Period 

Component A 

Upgrading of the Ywama Power Plant 

Works (Plant, DSI) 

285  RFB  Interna onal  Lump sum 

Prior Review 

Apr 15, 2020 

May 29, 2020 

Sept 15, 2020 

Dec 15, 2020 

Mar 1, 2021 

Jul 30, 2021 

Aug 31, 2021 

30 months 

Owner’s Engineera 

CS 2  QCBS  Interna onal  Time 

based Prior Review 

Apr 15, 2020 

May 15, 2020 

Jul 1, 2020 

Aug 1, 2020 

Sep 15, 2020 

Nov 15, 2020 

Dec 1, 2020 

48 months 

Environmental and Social Safeguards Managementa 

CS 

1  QCBS  Interna onal  Time based 

Prior Review 

Apr 15, 2020 

May 15, 2020 

Jul 1, 2020 

Aug 1, 2020 

Sep 15, 2020 

Nov 15, 2020 

Dec 1, 2020 

48 months 

Setup of the childcare pilot  

Works 0.5  RFB  Na onal  Lump 

sum Post  n.a.  n.a.  n.a.  Oct 15, 

2020 Nov 15, 2020 

Nov 30, 2020 

Jan 1, 2021 

6 months 

Component B 

Mobile substa ons 

Goods 9  RFB  Interna onal  Lump 

sum Prior Review 

n.a.  n.a.  n.a.  Nov 1, 2020 

Dec 1, 2020 

Mar 1, 2021 

Apr 1, 2021 

12 months 

Works for substa on strengthening (resilience)  Works 

1  RFB  Na onal  Lump sum 

Post Review 

n.a.  n.a.  n.a.  May 1, 2021 

Jun 1, 2021 

Aug 1, 2021 

Sep 1, 2021 

10 months 

Technical advisory consultant 

CS 2  QCBS  Interna onal   Time 

based Prior review 

Apr 15, 2020 

May 15, 2020 

July 1, 2020 

Aug 1, 2020 

Sep 15, 2020 

Nov 15, 2020 

Dec 1, 2020 

30 months 

Note: CS = Consul ng Services; n.a. = Not applicable; REOI = Request for expressions of interest; RFP = Request for Proposal; SL = Shortlist. a. Consultant to be mobilized before the bid submission deadline of the Ywama power plant. 

Page 73: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency Iand Resilience Project (P162151)

Page 68 of 74

Table 4.3. Procurement Methods and Prior Review Thresholds 

Category Indicative Procurement Method Thresholds  Prior Review Thresholds 

Threshold (US$)  Note  Threshold (US$)  Note 

Goods and Non‐Consulting Services 

Request for bids (RFB) using open, international market approach 

≥1 million    All contracts   

RFB using open, national market approach 

<1 million  International competition approach will be used for goods not available in Myanmar, even though the value of contract is less than US$1 million 

None   

Request for Quotations (RFQ)  <0.5 million    None   

Direct Selection  n.a.    Same as for competitive selection 

The justification to use direct selection is included in the Procurement Plan. 

Works 

RFB using open, international market approach 

≥3 million    All contracts   

RFB using open, national market approach 

<3 million    ≥2 million   

RFQ  <1 million    None   

Direct Selection  n.a.    Same as for competitive selection 

The justification to use direct selection is included in the Procurement Plan. 

Consulting Services 

Consultants (firms), international, open market approach 

≥0.1 million    Consultant firms: ≥0.3 million 

 

Consultants (firms), national, open market approach 

<0.1 million    None   

Page 74: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power System Efficiency Iand Resilience Project (P162151)

Page 69 of 74

Category Indicative Procurement Method Thresholds  Prior Review Thresholds 

Threshold (US$)  Note  Threshold (US$)  Note 

Consultant’s Qualification‐based Selection (CQS) 

≤0.5 million  Other methods (QCBS, QBS, FBS, LCS) can be applied for contracts with value under US$0.5 million, if appropriate. Use of full RFP is mandatory for CQS above US$0.3 million 

≥0.3 million  

 

Individual consultant  n.a. depending on the nature of services 

Limits on market approach do not apply to individual consultants. The most appropriate market approach will be used 

≥0.2 million   

Direct selection of consulting firms and individuals 

n.a.    Same as for competitive selection 

The justification to use direct selection is included in the Procurement Plan. 

Note: FBS = Fixed Budget Selection; LCS = Least‐Cost Selection; n.a. = Not applicable; QBS = Quality‐based Selectio

Page 75: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power SystemEfficiency and Resilience Project (P162151)

Page 70 of 74

 

ANNEX 5: Financial Management Arrangements 

 COUNTRY: Myanmar  

Power System Efficiency and Resilience Project

Staffing 

1. EPGE and DPTSC will officially assign staff to work on financial management matters as part of the PIUs. EPGE will assign the same financial management staff who were involved in the operations of the EPP. Similarly, DPTSC will also assign at least two dedicated finance officials. DPTSC is assessed to have an adequate capacity to manage Component  B  despite  its  limited  experience  in  handling  donor‐financed  projects.  Overall,  at  least  three  staff members from each team will work on the project’s financial management. The General Manager of EPGE Finance Unit and the Director of DPTSC Finance Unit will oversee and supervise their respective financial management teams and matters. The officials assigned to work on the project will be responsible for all aspects of its financial management  including,  but  not  limited  to,  budgeting,  accounting,  reporting,  making  payments  to consultants/suppliers, liaising with the Office of the Auditor General of Myanmar (OAGM) for external audits, and executing any day‐to‐day financial operations.

Planning and Budgeting  

2. Although  both  IAs  follow  the GOM budgeting  processes,  they  have  limited  knowledge  and  experience  in preparing  annual  work  plans  for  projects.  Given  that  the  current  GOM  budgeting  processes  must  obtain parliamentary approval, project planning and budgeting will have to be prepared on time to avoid delays during implementation.  To  manage  this  project,  annual  work  plans  will  be  prepared  by  each  IA  separately  and  in consultation with  the PIUs’  technical  team and the World Bank. This will be done with sufficient details  to be submitted to the respective Head of Department and the World Bank for request of no‐objection letters before or at the same time as submission to the Parliament. The work plans should also be detailed enough to allow an estimation of the activities’ cost, and the budget should show cost breakdowns by component/subcomponent and expenditure category. The fluctuations between the estimated budget and the actual expenditures will be reported and explained in detail  in the biannual  interim financial reports (to meet the requirements regarding external audit information) and will be linked to the physical progress of project implementation.  

Accounting Policies and Procedures 

3. EPGE’s  accounting  policy  is  based  on  the  principles  of  double‐entry  bookkeeping  and  public  enterprise accounting. For DPTSC, the accounting policy is based on single‐entry bookkeeping and public works enterprise accounting, where Accounts Codes (A Codes) and Departmental Codes (D Codes) are used to record receipts and expenditures. Currently, the Finance Department records most of its transactions manually and on hard copies. Based  on  these  manual  records  and  summary  transaction  sheets,  Excel  spreadsheets  are  consolidated  for budgeting and reporting purposes. DPTSC engineers and finance staff members are familiarized with the manual recording on stipulated forms. Thus, the current public works enterprise accounting, A Codes and D Codes are considered appropriate for accurate and timely transaction recording and financial reporting. More details on this 

Page 76: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power SystemEfficiency and Resilience Project (P162151)

Page 71 of 74

point have been outlined  in  the  financial management manual  to  further guide both PIUs  in  carrying out  the project’s day‐to‐day financial management.  

Funds Flow 

4. Each IA will open two DAs at Myanmar Economic Bank: one in U.S. dollars and another one in Myanmar kyat. The ceilings of the DAs will be variable based on biannual cash expenditure forecasts. Funds will flow from the World Bank to the DAs based on the IAs’ requests made through submission of withdrawal applications and cash forecasts approved by the World Bank. Supporting documentation required for documenting eligible expenditures paid from the DA will be the Statement of Expenditure. The frequency for documenting expenditures paid from the DA will be every six months. The  reimbursement,  special  commitment, and direct payment disbursement methods  will  be  used.  The  minimum  application  size  for  reimbursements,  special  commitments,  and  direct payments will be US$100,000 equivalent. 

5. The project will have a disbursement deadline date of four months after the closing date. This is the final date on which World Bank will accept applications for withdrawal from the recipient or documentation on the use of credit proceeds already advanced by  the World Bank. This  ‘grace period’  is  granted  to permit orderly project completion  and  closure  of  the  credit  account  through  the  submission  of  applications  and  supporting documentation  for  expenditures  incurred  on  or  before  the  closing  date.  Expenditures  incurred  between  the closing date and the disbursement deadline date are not eligible for disbursement except as otherwise agreed with the World Bank. 

Recording and Reporting 

6. The financial system of MOEE is adequate. MOEE has in place internal control and reporting processes through a manual system that can support the financial management requirements of the project. Excel may at times be used to support their accounting and reporting.  

7. Both IAs will be responsible for preparing the financial and progress reports of their components. The reports will be  shared with  the World Bank no  later  than 45 days after  the end of each  semester. The  format of  the financial reports will be agreed before the project implementation starts.

External Audits 

8. The capacity assessment of the OAGM indicates that this office has sufficient capacity to carry out audits for World  Bank‐funded  projects  in Myanmar.  Therefore,  for  this  project,  the  annual  financial  statements will  be prepared by each IA and sent to the OAGM within three months after the end of each fiscal year. The OAGM will conduct separate audits for EPGE and DPTSC on an annual basis. Thus, separate audit reports will be required for EPGE and DPTSC under this project. Each IA will submit copies of the audited financial statements (including audit opinion and auditors’ management letters) to the World Bank no later than 9 months after the end of the financial year (that is, by June 30 of each fiscal year). The audit reports and audited financial statements must be publicly disclosed in accordance with the World Bank policy on ‘Access to Information’. 

   

Page 77: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power SystemEfficiency and Resilience Project (P162151)

Page 72 of 74

ANNEX 6: Maps 

Figure 6.1. Map of Republic of the Union of Myanmar 

 

Page 78: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power SystemEfficiency and Resilience Project (P162151)

Page 73 of 74

Figure 6.2. MDI in Myanmar and National Electrification Project On‐ and Off‐grid Solutions  

 

 

Page 79: FOR OFFICIAL USE ONLY INTERNATIONAL DEVELOPMENT … · 2020. 6. 2. · for official use only report no: pad2773 international development association project appraisal document on

The World Bank Power SystemEfficiency and Resilience Project (P162151)

Page 74 of 74

Figure 6.3. Myanmar Power System Network (2018)