Hitendra Dev Shakya
System Planning Department
Nepal Electricity Authority
GRID SOLUTIONS for
ENERGY ACCESS FOR ALL
Sustainable Energy for All
S D G 7 -
Affordable and Clean Energy - Ensure access to affordable, reliable, sustainable and modern energy for all.
Energy <- - Grid Electricity
• What SDG 7 means to an Electric Utility - Energy is presumed as Electricity Electricity is presumed as Grid Electricity And in Nepal, Grid Electricity is presumed as Hydro-
electricity
Half the assumption is corrected as Electricity is Off-grid in Remote areas On-grid Electricity follows far behind But it is still about Electricity only. Hydro-electricity
AND electricity as a source of energy is increasing with
technology and time – (18% world average/ 2% Nepal)
Renewable, other
1% Petroleum
9% Electricity
2%
Coal 3%
Biomass 87%
Grid Map of Nepal Areas covered by Grid Electricity
Off-Grid Nepal Map of areas covered by AEPC
How Long to wait for Reliable Electricity?
Connecting the two –’Haves’ and ‘Have Nots’
Nepal facts – 1. Mountainous country - Road access is limited
2. Grid Electricity – 60% of the population, Geographical coverage – Central hills, southern plains and eastern border region and western border region – < 40% of populated areas
3. Off-Grid – claims of 15% access, but not functioning, many fall to disrepair within few years of operation
4. Subsidy to Off-Grid Micro-hydro power or solar grid – conditional on distance from Grid > 5 years (No Economics)
Where there is a will, there is a way..
A Snapshot – hard work for
Energy in Remote Areas
1. Grid expansion is targeted towards large loads and generators
2. Market-based Transmission Development – Only suitable for Large Generators and Consumers
3. Grid Expansion is Capital intensive and low returns
4. Grid expansion is afflicted by ROW issues and large affected areas – Forces transmission lines to Government domain in order not to increase cost of energy up-front
5. Transmission Network is centrally planned (Top-down approach) and the expansion is slow
How Long to wait for Reliable Electricity?- >> From Grid Expansion Direction >> Grid expansion is targeted
towards large loads and generators
Market-based Transmission Development – Only suitable for Large Generators and Consumers
Grid Expansion is Capital intensive and low returns
Grid expansion is afflicted by ROW issues and large affected areas - Forces transmission lines to Government domain
Transmission Network is centrally planned (Top-down approach) and the expansion is slow
>>Looking from the Rural Off-Grid>> A look at the Off-Grid MHP model
• The distribution network – Poor, not safe for grid connection.
• Low Income ( low plant factor/ low productive uses) forces low quality of Operation.
• Distance from Road-head increases O&M time and cost • MHP - Design at river discharge of high exceedence (Q90);
yet Plant factor is 20-30% only. • The Electronic Load Controller (ELC) is used. Controls
frequency by dummy load - Useful where raw material is free – Water/wind/solar etc.
• The switchgear - Not ready for grid-interconnection.
BUT most villages would find a viable river source for MHP ( pico, micro or mini) if a workable business model and funding available
MHP - Design at river discharge of high exceedence (Q90); yet Plant factor is 20-30% only.
One MHP aspect - The Electronic Load Controller (ELC) is used. Controls frequency by dummy load - Useful where raw material is free – Water/wind/solar etc.
The switchgear - Not ready for grid-interconnection The distribution network – Poor, not
safe for grid connection.
Problem of MHPs - Low Income ( low plant factor/ low productive uses) forces low quality of Operation.
Distance from Road-head increases O&M time and cost
BUT most villages would find a viable river source for MHP ( pico, micro or mini) if a workable business model and funding available
Low skill/ knowhow, low p.f. and low revenue, accessibility, less room for industrial use >> tendency to fail
Success factors
Creativity and adaptation
Grid Solutions to Off-Grid distribution 1. Inter-connection of Clusters of small power plants in a mini-grid
ready for Connectivity with Grid
2. Help / subsidy >> Grid-readiness for remote/ offgrid generators/ users >> synchronizing switchgear and relaying
Grid Energy is mostly cheaper and reliable than Isolated systems. 1. Distributed Generation has Multiple Impacts on Local economy that
offsets the Initial high costs of electricity
2. Spin-off for Grid - Reduces demand on Reinforcement of grid & Reactive power management by doing Distributed generation
Most rural areas in Nepal have Some sources to produce Electricity
1. Mountain areas – Hydro and Solar; Remote areas in Terai – Solar and Biopower, some areas – wind etc.
2. Government support for Grid Connectivity – Sustainability of the DG and also enable expansion of grid. ‘Biggest Bang for a Buck’
>> EARLY ACCESS TO CLEAN ELECTRICITY BY ALL >>
Electronic Load Controller - as governor of MHP
Role of Switched ELC in Grid-operated MHP – 1. Protective device against Over-speed during Grid-disconnect 2. Allows Operator mobility and free to work within village
Typical costs of Interconnection of a <100 kW MHP
VCB - 6 lakh, ..\..\temp\VisitSriLanka\Option I_Mini Grid Drawing_VCB on both Feeder.pdf
Transformer - 4 lakh,
CT,PT - 0.5C + meter - 2 lakhs,
synchronizing eqpt, ELC+ AVR modification - 4 lakh
Switchyard, LA and Isolator, Earthing - 3 lakh
Commissioning - 2 lakh
VAT + contingency - - 3 lakh
Total -24 lakh ~ 24,000 $
Providing for O&M costs and interest of loan,
the Payback period is 7/8 years for 20kW, and 4/5 years for 30 kW,
excluding Plant costs and interests if any.
Hence, Interconnection requirement at 11kV with VCB and metering
is Not Viable for very small MHP
Example –
20kW Syaure MHP –
Grid-connection costs- 2.4 mill
Subsidy
- Cash 0.5 million
-Credit 0.5 million – soft loan
at 5% interest
-Yet, the Revenue– 1,035,000.
-O&M + int costs - 750,000.
Profit – 285,000.
= 7 yrs Payback
14
SUBSIDY or VGF is required to make MHPs Inter-connected / Grid Ready
15
BangDovan Mini-grid- Baglung District >> Along Mid-hill highway; Grid is within 50 km reach >> Population and electricity demand is increasing – it is Off-Grid >> Planning for a sub-transmission and mini-grid subsidy will deliver Grid supply quickly
Usually, Isolated MHPs fall into disrepair (the community is not
well-synthesized, and tariff does not support major repair, nor quality operation)
MHPs when connected to grid - provides incentive to operate due to Profit from Energy supplied to Grid. Becomes Sustainable
◦ Sustainability of MHP is a net gain for community and the government.
◦ No sunk costs, Local economic activity boosted, jobs, technical base
◦ Technical - Voltage boost, losses reduction, less capacity investment, dry season energy
Challenges - Feed In tariff- comparably Low [NRs 4.8 (8mth)/8.4
(4mth)]
Financing for Interconnection equipment – High costs
Once grid-connected, capacity can be upgraded (from Q90 to Q40)
Plant Factor may increase from 30% to 90%.
Private equity injection to MHP/ Isolated mini-grid and private management models are being explored to make them sustainable. 16
What works for MHP … will also help Access for Rural areas, So…
Source – World Bank report on Nepal:Scaling up Access through mini-grid
Get Bigger for survival !
Get Inter-connected and Grid Ready
Connecting Off-Grid to Grid-> Best of Both Worlds
18
• Off-Grid MHP - Subsidy for Grid-Connectivity
• Required -> Sub-transmission networks – radial 132kV line, 132/33/11
kV substations and 33/11 kV lines to villages/ MHP
• Investment in Sub-transmission lines by Govt. - as Integrated subsidy
plan to clusters of MHPs , padded with soft Loans - in Build – Own –
Transfer BOT model -
• After Subsidy, remaining Amortized costs to be recovered as Local
Transm. Charges from present and future Users of the Line
Optimized Network planning – from sub-transmission line requirements
from villages – “Bottom Up but Coordinated” approach
Subsidy to Off-Grid electrification with “Biggest Bang for the Buck “ -
Distributed Generation bringing multiple local benefits + system benefits
What Next? CEUG .
Financial Initiative that worked – Grid Connected – Community Electricity Users Group CEUG
Subsidized distribution of electricity at NRs 3.60 / kwh to Community Electricity User Groups (CBOM)
Community Electrification – 90% subsidy by Government – 10% community - enabled expansion of rural networks at 400V / 11 kV and 33 kV
It has worked – No of CEUG increasing and its consumer members The technical (distribution- 6-8%) and non-technical loss (> 8-10%) that
otherwise occur justify the reduction in tariff below cost of generation, Generation and transmission cost = 27382 M NRS, Total energy = 4794
(6% system loss) M units, = 5.70 / unit Cost of Energy for NEA at 11kV delivery - w/o operating costs /depreciation / overhead)
Tariff needs revisit due to increased purchase price. Administrative cost of NEA ( Losses ) to administer the Rural Distribution
is saved. For Embedded Generators within CEUG, Purchase tariff is Bounded. For Larger MHPs, near such CEUG, it should be connected to Grid directly
before the CEUG point – to enable it to get the Regular PPA Tariff.
Options for Grid Solutions
1. Optimized network planning and Extensive Public Investment
2. Private Investment for the Funding Gap - > Market -based Transmission Development – Only suitable for Large Generators and Consumers
NEPAL High Voltage Transmission Lines &
Substations
21
Transmission Lines Existing
(Circuit km)
Under
Construction
(Circuit km)
Planned
(Circuit km)
66kV Voltage Level 511.16 -
132kV Voltage Level 2337.7 1010.0 1320.0
220kV Voltage Level - 659.0 949.8
400kV Voltage Level - 648.0 6495.6
Total 2848.86 2317.0 8765.4
Substations Existing
(Numbers/Capacity)
Under
Construction (Numbers/Capacity
)
Planned (Numbers/Capacity)
66kV Voltage Level 13/509.15MVA -
132/66kV Voltage Level 28/1622.4MVA 10/506.5MVA 21/917MVA
220kV Voltage Level - -(*) 18/3876MVA
400kV Voltage Level - - 5/2025MVA
22
Investment on Transmission
Label 2015 2020 2025 2030 2035
All Zones Commissioning from 2015 2020 2025 2030 2035 Total
to year 2019 2024 2029 2034
MUSD MUSD MUSD MUSD MUSD MUSD
Lines Comm. 412.8 621.1 214.2 0.0 0.0 1248.1
Lines Planned 138.1 332.6 181.7 0.0 0.0 652.3
Lines All 550.9 953.7 395.9 0.0 0.0 1900.5
S/S Existing 123.0 60.2 13.2 34.5 26.1 257.1
S/S Comm. 410.0 231.3 82.7 81.5 0.0 805.4
S/S Planned 47.4 358.0 215.2 67.1 5.3 693.1
S/S All 580.5 649.5 311.1 183.0 31.4 1755.6
Total Existing 123.0 60.2 13.2 34.5 26.1 257.1
Total Comm. 822.8 852.4 296.9 81.5 0.0 2053.6
Total Planned 185.5 690.6 396.9 67.1 5.3 1345.4
Total All 1131.4 1603.2 707.0 183.0 31.4 3656.0
Connection Lines 142.6 584.2 420.4 76.8 4.1 1228.1
Connection Bays 38.5 83.6 118.4 25.4 6.5 272.4
Grand Total 1312.5 2270.9 1245.9 285.2 42.0 5156.5
The core of the transmission network is to be commissioned during the next 10 years. The total investment cost planned for the whole 2015-2035 period amounts to 5.15 billion USD and is mainly concentrated in first ten years, i.e. between 2015 and 2025:
Grid Expansion Issues ... 1. Optimized network planning and Extensive Public
Investment 2. Private Investment for the Funding Gap - > Market -based
Transmission Development – Only suitable for Large Generators and Consumers
3. For challenge faced from PAF by ROW and Towers – 1. Considering options of Long-Term Lease in lieu of Purchase/
one-time compensation – Yet to be proven. 2. Pro-rata allocation of Project developer equity from the lot
given to affected people – Long-term benefit sharing by the people – Yet to be proven
4. Build, Own and Transfer (BOT) model for transmission / distribution lines by communities and Build Transfer model for isolated generators – Policy in process
5. Policy of declaration of shallow Grid – Not done yet
Grid Solutions
Integrated Planning for
Sub-transmission
network
Community Electricity
Users Groups CEUG– Hand-
over
Build and Transfer BT Policy for
Private Generators
Change Approach –
Grid Planning for DG and
Rural Access
Policy for Transmission charges and Private Trans
owner / operator
MHP subsidy
Extend TO Grid
Synchro equipment
Subsidy / Soft Loan for 33 and 11 kV sub-trans /distrib links to
Grid Energy to All by
National Grid
Access
Focus- DG and Village
Load potential
Funding Deficit-> Private Capital
Use Hydro-developers’ strength for Construction
& ROW
Efficient Admin of
Rural Consumers
Sustainable / Profitable
MHP – “Most Bang
for Buck”
Earlier Access ->
Amortized costs
Off-Grid
Grid Side
What has worked? MHP and distribution network with larger consumer base and
anchor loads– Case - Khumbu Bijuli (900kW), Salleri Chyalsa (400kW) ) Having Periodic oversight and Support
Subsidized tariff to CEUG ( having small consumers & capped to 5 A users) – Successful CEUGs adapting the lessons learnt.
What needs reform? Stand-alone MHPs with weak consumer base – Scale –up ! Top-down Rural Electrification without Regional Optimized
planning –> Reverse direction ! Subsidy for MHP / Rural electrification – Include Grid
Connectivity with Partial Payback (90/10 model ) in the Integrated Subsidy model !
What can be learnt? for Rapid Grid Expansion Involve community – allow BOT for sub-transmission networks
and Use subsidy/ VGF model Involve Private / Developers – and / or allow BT model for
rapid expansion of Main Grid
25
Creativity and adaptation
Top-down approach of grid-planning coordinated with Bottom-Up approach to Identify/Prioritize and
Investment Rethink - Need to support/ subsidize community-driven / owned grid-connection and expansion coupled with local DG economics.
Thank you ! Namaste !
Q&A and discussion