fm12 ch 11

Upload: smsm93

Post on 04-Jun-2018

232 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/13/2019 FM12 Ch 11

    1/68

    1

    Chapter 11

    The Basics of CapitalBudgeting:

    Evaluating Cash Flows

  • 8/13/2019 FM12 Ch 11

    2/68

    2

    Topics! Overview and vocabulary! Methods

    ! NPV! IRR, MIRR! Profitability Index! Payback, discounted payback

    ! Unequal lives! Economic life

  • 8/13/2019 FM12 Ch 11

    3/68

    3

    What is capital budgeting?!Analysis of potential projects.! Long-term decisions; involve large

    expenditures.!Very important to firms future.

  • 8/13/2019 FM12 Ch 11

    4/68

    4

    Steps in Capital Budgeting! Estimate cash flows (inflows &

    outflows).

    !Assess risk of cash flows.! Determine r = WACC for project.! Evaluate cash flows.

  • 8/13/2019 FM12 Ch 11

    5/68

    5

    Independent versus Mutually

    Exclusive Projects! Projects are:

    ! independent, if the cash flows of one are

    unaffected by the acceptance of the other.! mutually exclusive, if the cash flows of one

    can be adversely impacted by theacceptance of the other.

  • 8/13/2019 FM12 Ch 11

    6/68

    6

    Cash Flows for Franchise L

    and Franchise S

    10 8060

    0 1 2 310%

    Ls CFs:

    -100.00

    70 2050

    0 1 2 310%

    Ss CFs:

    -100.00

  • 8/13/2019 FM12 Ch 11

    7/68

    7

    NPV: Sum of the PVs of all

    cash flows.

    Cost often is CF0and is negative.

    NPV =!n

    t = 0

    CFt(1 + r)t

    .

    NPV =!nt = 1

    CFt(1 + r)t

    . - CF0.

  • 8/13/2019 FM12 Ch 11

    8/68

    8

    Whats Franchise Ls NPV?

    10 8060

    0 1 2 310%

    Ls CFs:

    -100.00

    9.09

    49.59

    60.11

    18.79 = NPVL NPVS= $19.98.

  • 8/13/2019 FM12 Ch 11

    9/68

    9

    Calculator Solution: Enter

    values in CFLO register for L.

    -100

    10

    60

    8010

    CF0

    CF1

    NPV

    CF2

    CF3

    I = 18.78 = NPVL

  • 8/13/2019 FM12 Ch 11

    10/68

    10

    Rationale for the NPV Method! NPV = PV inflows Cost

    ! This is net gain in wealth, so acceptproject if NPV > 0.

    ! Choose between mutually exclusiveprojects on basis of higher NPV. Addsmost value.

  • 8/13/2019 FM12 Ch 11

    11/68

    11

    Using NPV method, which franchise

    (s) should be accepted?! If Franchise S and L are mutually

    exclusive, accept S because NPVs>

    NPVL.! If S & L are independent, accept both;

    NPV > 0.

  • 8/13/2019 FM12 Ch 11

    12/68

    12

    Internal Rate of Return: IRR

    0 1 2 3

    CF0 CF1 CF2 CF3Cost Inflows

    IRR is the discount rate that forcesPV inflows = cost. This is the sameas forcing NPV = 0.

  • 8/13/2019 FM12 Ch 11

    13/68

  • 8/13/2019 FM12 Ch 11

    14/68

    14

    Whats Franchise Ls IRR?

    10 8060

    0 1 2 3IRR = ?

    -100.00

    PV3

    PV2

    PV1

    0 = NPV Enter CFs in CFLO, then pressIRR: IRRL= 18.13%. IRRS=23.56%.

  • 8/13/2019 FM12 Ch 11

    15/68

    15

    40 4040

    0 1 2 3

    -100

    Or, with CFLO, enter CFs and pressIRR = 9.70%.

    3 -100 40 0

    9.70%

    N I/YR PV PMT FV

    INPUTS

    OUTPUT

    Find IRR if CFs are constant:

  • 8/13/2019 FM12 Ch 11

    16/68

    16

    Rationale for the IRR Method! If IRR > WACC, then the projects rate

    of return is greater than its cost-- somereturn is left over to boost stockholdersreturns.

    ! Example:WACC = 10%, IRR = 15%.

    ! So this project adds extra return toshareholders.

  • 8/13/2019 FM12 Ch 11

    17/68

    17

    Decisions on Projects S and L

    per IRR! If S and L are independent, accept

    both: IRRS> r and IRRL> r.

    ! If S and L are mutually exclusive,accept S because IRRS> IRRL.

  • 8/13/2019 FM12 Ch 11

    18/68

    18

    Construct NPV Profiles! Enter CFs in CFLO and find NPVLand

    NPVSat different discount rates:

    r NPVL NPVS

    0 50 40

    5 33 29

    10 19 20

    15 7 12

    20 (4) 5

  • 8/13/2019 FM12 Ch 11

    19/68

    19

    NPV Profile

    IRRL= 18.1%

    IRRS= 23.6%

    CrossoverPoint = 8.7%

    S

    L

  • 8/13/2019 FM12 Ch 11

    20/68

    20

    r > IRRand NPV < 0.

    Reject.

    NPV ($)

    r (%)IRR

    IRR > rand NPV > 0

    Accept.

    NPV and IRR: No conflict for

    independent projects.

  • 8/13/2019 FM12 Ch 11

    21/68

    21

    Mutually Exclusive Projects

    8.7

    NPV

    %

    IRRS

    IRRL

    L

    S

    r < 8.7: NPVL> NPVS , IRRS > IRRLCONFLICT

    r > 8.7: NPVS> NPVL , IRRS > IRRLNO CONFLICT

  • 8/13/2019 FM12 Ch 11

    22/68

    22

    To Find the Crossover Rate

    ! Find cash flow differences between theprojects. See data at beginning of the case.

    ! Enter these differences in CFLO register, thenpress IRR. Crossover rate = 8.68%, roundedto 8.7%.

    ! Can subtract S from L or vice versa, buteasier to have first CF negative.

    ! If profiles dont cross, one project dominatesthe other.

  • 8/13/2019 FM12 Ch 11

    23/68

    23

    Two Reasons NPV ProfilesCross

    ! Size (scale) differences. Smaller project freesup funds at t = 0 for investment. The higherthe opportunity cost, the more valuable these

    funds, so high r favors small projects.

    ! Timing differences. Project with fasterpayback provides more CF in early years forreinvestment. If r is high, early CF especially

    good, NPVS> NPVL.

  • 8/13/2019 FM12 Ch 11

    24/68

    24

    Reinvestment RateAssumptions

    ! NPV assumes reinvest at r (opportunitycost of capital).

    ! IRR assumes reinvest at IRR.! Reinvest at opportunity cost, r, is more

    realistic, so NPV method is best. NPVshould be used to choose betweenmutually exclusive projects.

  • 8/13/2019 FM12 Ch 11

    25/68

    25

    Modified Internal Rate ofReturn (MIRR)

    ! MIRR is the discount rate which causes the PV of a projects

    terminal value (TV) to equal the PV ofcosts.

    ! TV is found by compounding inflows atWACC.

    ! Thus, MIRR assumes cash inflows arereinvested at WACC.

  • 8/13/2019 FM12 Ch 11

    26/68

    26

    10.0 80.060.0

    0 1 2 310%

    66.012.1

    158.1

    -100.010%

    10%

    TV inflows

    -100.0

    PV outflows

    MIRR for Franchise L: First,find PV and TV (r = 10%)

  • 8/13/2019 FM12 Ch 11

    27/68

    27

    Second, find discount rate thatequates PV and TV

    MIRR = 16.5% 158.1

    0 1 2 3

    -100.0

    TV inflowsPV outflows

    MIRRL= 16.5%

    $100 = $158.1(1+MIRRL)

    3

  • 8/13/2019 FM12 Ch 11

    28/68

    28

    To find TV with 10B: Step 1,find PV of Inflows

    ! First, enter cash inflows in CFLO register:! CF0= 0, CF1= 10, CF2= 60, CF3= 80

    ! Second, enter I = 10.

    ! Third, find PV of inflows:! Press NPV = 118.78

  • 8/13/2019 FM12 Ch 11

    29/68

    29

    Step 2, find TV of inflows.

    ! Enter PV = -118.78, N = 3, I = 10, PMT= 0.

    ! Press FV = 158.10 = FV of inflows.

  • 8/13/2019 FM12 Ch 11

    30/68

    30

    Step 3, find PV of outflows.

    ! For this problem, there is only oneoutflow, CF0= -100, so the PV of

    outflows is -100.! For other problems there may be

    negative cash flows for several years,and you must find the present value for

    all negative cash flows.

  • 8/13/2019 FM12 Ch 11

    31/68

    31

    Step 4, find IRR of TV ofinflows and PV of outflows.

    ! Enter FV = 158.10, PV = -100, PMT =0, N = 3.

    ! Press I = 16.50% = MIRR.

  • 8/13/2019 FM12 Ch 11

    32/68

    32

    Why use MIRR versus IRR?

    ! MIRR correctly assumes reinvestment atopportunity cost = WACC. MIRR also

    avoids the problem of multiple IRRs.! Managers like rate of return

    comparisons, and MIRR is better for thisthan IRR.

  • 8/13/2019 FM12 Ch 11

    33/68

    33

    Normal vs. Nonnormal CashFlows

    ! Normal Cash Flow Project:! Cost (negative CF) followed by a series of positive

    cash inflows.

    ! One change of signs.! Nonnormal Cash Flow Project:

    ! Two or more changes of signs.! Most common: Cost (negative CF), then string of

    positive CFs, then cost to close project.! For example, nuclear power plant or strip mine.

  • 8/13/2019 FM12 Ch 11

    34/68

    34

    Inflow (+) or Outflow (-) inYear

    0 1 2 3 4 5 N NN

    - + + + + + N

    - + + + + - NN

    - - - + + + N

    + + + - - - N

    - + + - + - NN

  • 8/13/2019 FM12 Ch 11

    35/68

    35

    Pavilion Project: NPV and IRR?

    5,000 -5,000

    0 1 2r = 10%

    -800

    Enter CFs in CFLO, enter I = 10.

    NPV = -386.78IRR = ERROR. Why?

  • 8/13/2019 FM12 Ch 11

    36/68

    36

    NPV Profile

    450

    -800

    0

    400100

    IRR2= 400%

    IRR1= 25%

    r

    NPV

    Nonnormal CFs--two signchanges, two IRRs.

  • 8/13/2019 FM12 Ch 11

    37/68

    37

    Logic of Multiple IRRs

    !At very low discount rates, the PV ofCF2is large & negative, so NPV < 0.

    !At very high discount rates, the PV ofboth CF1and CF2are low, so CF0dominates and again NPV < 0.

    ! In between, the discount rate hits CF2harder than CF1, so NPV > 0.

    ! Result: 2 IRRs.

  • 8/13/2019 FM12 Ch 11

    38/68

    38

    1. Enter CFs as before.2. Enter a guess as to IRR by

    storing the guess. Try 10%:

    10 STOIRR = 25% = lower IRR

    (See next slide for upper IRR)

    Finding Multiple IRRs withCalculator

  • 8/13/2019 FM12 Ch 11

    39/68

    39

    Now guess large IRR, say, 200:200 STO

    IRR = 400% = upper IRR

    Finding Upper IRR withCalculator

  • 8/13/2019 FM12 Ch 11

    40/68

    40

    0 1 2

    -800,000 5,000,000 -5,000,000

    PV outflows @ 10% = -4,932,231.40.

    TV inflows @ 10% = 5,500,000.00.MIRR = 5.6%

    When there are nonnormal CFs andmore than one IRR, use MIRR:

  • 8/13/2019 FM12 Ch 11

    41/68

    41

    Accept Project P?

    ! NO. Reject because MIRR = 5.6% < r= 10%.

    !Also, if MIRR < r, NPV will be negative:NPV = -$386,777.

  • 8/13/2019 FM12 Ch 11

    42/68

    42

    Profitability Index

    ! The profitability index (PI) is thepresent value of future cash flows

    divided by the initial cost.! It measures the bang for the buck.

  • 8/13/2019 FM12 Ch 11

    43/68

    43

    Franchise Ls PV of FutureCash Flows

    10 8060

    0 1 2 3

    10%

    Project L:

    9.09

    49.59

    60.11

    118.79

  • 8/13/2019 FM12 Ch 11

    44/68

    44

    Franchise Ls Profitability Index

    PIL=PV future CF

    Initial Cost

    $118.79=

    PIL= 1.1879

    $100

    PIS= 1.1998

  • 8/13/2019 FM12 Ch 11

    45/68

  • 8/13/2019 FM12 Ch 11

    46/68

  • 8/13/2019 FM12 Ch 11

    47/68

    47

    Payback for Franchise S

    70 2050

    0 1 2 3

    -100CFt

    Cumulative -100 -30 20 40

    PaybackS 1 + 30/50 = 1.6 years

    0

    1.6

    =

  • 8/13/2019 FM12 Ch 11

    48/68

    48

    Strengths and Weaknesses ofPayback

    ! Strengths:! Provides an indication of a projects risk

    and liquidity.

    ! Easy to calculate and understand.! Weaknesses:

    ! Ignores the TVM.! Ignores CFs occurring after the payback

    period.

  • 8/13/2019 FM12 Ch 11

    49/68

    49

    10 8060

    0 1 2 3

    CFt

    Cumulative -100 -90.91 -41.32 18.79

    Discountedpayback

    2 + 41.32/60.11 = 2.7yrs

    PVCFt -100

    -100

    10%

    9.09 49.59 60.11

    =

    Recover invest. + cap. costs in 2.7 yrs.

    Discounted Payback: Usesdiscounted rather than raw CFs.

  • 8/13/2019 FM12 Ch 11

    50/68

    50

    S and L are mutually exclusiveand will be repeated. r = 10%.

    0 1 2 3 4

    Project S:(100)

    Project L:(100)

    60

    33.5

    60

    33.5 33.5 33.5Note: CFs shown in $ Thousands

  • 8/13/2019 FM12 Ch 11

    51/68

    51

    NPVL

    > NPVS

    . But is L better?

    S L

    CF0 -100 -100

    CF1 60 33

    NJ 2 4

    I 10 10

    NPV 4.132 6.190

  • 8/13/2019 FM12 Ch 11

    52/68

    52

    Equivalent Annual AnnuityApproach (EAA)

    ! Convert the PV into a stream of annuitypayments with the same PV.

    !S: N=2, I/YR=10, PV=-4.132, FV = 0.Solve for PMT = EAAS= $2.38.

    ! L: N=4, I/YR=10, PV=-6.190, FV = 0.Solve for PMT = EAAL= $1.95.

    ! S has higher EAA, so it is a betterproject.

  • 8/13/2019 FM12 Ch 11

    53/68

    53

    Put Projects on Common Basis

    ! Note that Project S could be repeatedafter 2 years to generate additionalprofits.

    ! Use replacement chain to put oncommon life.

    ! Note: equivalent annual annuityanalysis is alternative method, shown inTool Kit and Web Extension.

  • 8/13/2019 FM12 Ch 11

    54/68

    54

    Replacement Chain Approach (000s).Franchise S with Replication:

    NPV = $7,547.

    0 1 2 3 4

    Franchise S:(100)

    (100)

    60

    60

    60(100)

    (40)

    60

    60

    60

    60

  • 8/13/2019 FM12 Ch 11

    55/68

  • 8/13/2019 FM12 Ch 11

    56/68

    56

    NPVS= $3,415 < NPVL= $6,190.Now choose L.

    0 1 2 3 4

    Franchise S:(100) 60 60

    (105)(45)

    60 60

    Suppose cost to repeat S in twoyears rises to $105,000.

  • 8/13/2019 FM12 Ch 11

    57/68

    57

    Economic Life versus PhysicalLife

    ! Consider another project with a 3-yearlife.

    ! If terminated prior to Year 3, themachinery will have positive salvagevalue.

    ! Should you always operate for the fullphysical life?

    ! See next slide for cash flows.

  • 8/13/2019 FM12 Ch 11

    58/68

    58

    Economic Life versus PhysicalLife (Continued)

    Year CF Salvage Value

    0 ($5000) $5000

    1 2,100 3,100

    2 2,000 2,000

    3 1,750 0

  • 8/13/2019 FM12 Ch 11

    59/68

    59

    CFs Under Each Alternative(000s)

    0 1 2 3

    1. No termination (5) 2.1 2 1.75

    2. Terminate 2 years (5) 2.1 4

    3. Terminate 1 year (5) 5.2

  • 8/13/2019 FM12 Ch 11

    60/68

    60

    NPVs under Alternative Lives (Cost ofcapital = 10%)

    ! NPV(3) = -$123.! NPV(2) = $215.! NPV(1) = -$273.

  • 8/13/2019 FM12 Ch 11

    61/68

    61

    Conclusions

    ! The project is acceptable only ifoperated for 2 years.

    !A projects engineering life does notalways equal its economic life.

  • 8/13/2019 FM12 Ch 11

    62/68

    62

    Choosing the Optimal CapitalBudget

    ! Finance theory says to accept allpositive NPV projects.

    ! Two problems can occur when there isnot enough internally generated cash tofund all positive NPV projects:

    !An increasing marginal cost of capital.! Capital rationing

  • 8/13/2019 FM12 Ch 11

    63/68

    63

    Increasing Marginal Cost ofCapital

    ! Externally raised capital can have largeflotation costs, which increase the costof capital.

    ! Investors often perceive large capitalbudgets as being risky, which drives upthe cost of capital.

    (More...)

  • 8/13/2019 FM12 Ch 11

    64/68

    64

    ! If external funds will be raised, then theNPV of all projects should be estimatedusing this higher marginal cost ofcapital.

  • 8/13/2019 FM12 Ch 11

    65/68

    65

    Capital Rationing

    ! Capital rationing occurs when acompany chooses not to fund allpositive NPV projects.

    ! The company typically sets an upperlimit on the total amount of capitalexpenditures that it will make in the

    upcoming year.(More...)

  • 8/13/2019 FM12 Ch 11

    66/68

    66

    ! Reason: Companies want to avoid thedirect costs (i.e., flotation costs) and theindirect costs of issuing new capital.

    ! Solution: Increase the cost of capital byenough to reflect all of these costs, andthen accept all projects that still have a

    positive NPV with the higher cost ofcapital.

    (More...)

  • 8/13/2019 FM12 Ch 11

    67/68

    67

    ! Reason: Companies dont have enoughmanagerial, marketing, or engineeringstaff to implement all positive NPVprojects.

    ! Solution: Use linear programming tomaximize NPV subject to not exceedingthe constraints on staffing. (More...)

  • 8/13/2019 FM12 Ch 11

    68/68