flr30!3'30 · connection points at a-spacings (i,e., distance between each electrode) of 0.5," 1,...
TRANSCRIPT
-
. TECHNICAL MEMORANDUMSUBTASK 8.2
REMEDIAL INVESTIGATION REPORTFIRST PIEDMONT ROCK QUARRY/
ROUTE 719 SITE
VOLUME IIAppendices
Prepared by:
Westinghouse Environmental and Geotechnical Services, Inc.P.O. Box 130S - - - - - - - - - - -
Gary, North Carolina 27512
February 1990
flR30!3'30
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112̂ 88-9Q8A . 11 January 1990
APPENDIX A
METHODS OF INVESTIGATION
BR30I33I
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A rt-January 1990
APPENDIX A.I
SENSITIVE RECEPTOR SURVEY (SUBTASK 2.2)
The size of the human population is based on data from a variety of sources.
These sources include aerial photographs from the Virginia Department of
Transportation (VADOT) and Dewberry and Davis, Inc., a U.S. Geological Survey
(USGS) topographic map, county tax records, a site reconnaissance, and previous
site documents.
Information describing environmental—receptors was obtained from the
Virginia Department of Game and Inland Fisheries (VDGIF), and the Soil
Conservation Service (SCS) of Pittsylvania County.
C The wetlands delineation included topographic map and aerial photography
analysis and a field mapping program (Appendix A.6).
AR30I332.
-
FPRQ Task 8.1 RI DRAFT - Appendix A _ . . Revision 0Westinghouse Project No. 4112-88̂ SO,8A 11 January 19-90
APPENDIX A. 2
TOPOGRAPHIC, AERIAL, AND GEOLOGICAL SURVEYS (SUBTASK 4.1)
The objectives of this sub task are to provide aerial photography, and
topographic and geologic mapping of the probable study area, in the vicinity of
the FPRQ site. The deliverables will be used in subsequent remedial
investigation tasks,
A.2.1 . .,-TOPOGRAPHIC AND AERIAL SURVEYS
Westinghouse subcontractor Dewberry and Davis, Inc. of Danville, Virginia,
a Virginia certified surveying company, provided both aerial photography and
topographic mapping for-the FPRQ RI/FS. Due to scheduling difficulties, the
aerial photography of the site was not taken until May 2, 1988. The dense
vegetation present at that time limited the photographic resolution and
consequently, the topographic mapping of the site area. The area was reflown
in January 1989 and the topographic mapping was generated from this photography
(see Drawing 1).
Appendix A presents the aerial photograph of the site area provided by
Dewberry and Davis. This photograph was taken at an altitude of 3000 feet and
is at a scale of one-inch equals five hundred feet.
Additional aerial photographs were obtained from the Pittsylvania County
Soil Conservation Service, the Virginia Department of Transportation, and the
U.S. Department of Agriculture. .These photographs include:
fiR30l333
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
Soil Conservation Service
Date Flown
4-18-82
Date Flown
4-03-72
1-16-86
Date Flown
10-05-63
04-26-71
03-22-82
04-18-82
Approx. Scale
1"-1000 '
Virginia
Approx. Scale
1"-200'
1--200'
U.S.
Approx. Scale
1--1600 '
1--1600 '
1--47QO '
1"-2800'
Composition
Black and White
I.D. Number
51083-178
Department of Transportation:
Composition
Black and White
Black and White
Department of Agriculture:
Composition
Black and White
Black and White
Color Infra Red
Black and White
I.D. Number
3-071-428-84
3-071-794-27
I.D, Number
DGG 10DO-19a,20
DGG 3MM-195,196a
367806 577-71a,72
51143-178-250*, 251
a. Copies provided in Appendix B.
Copies of the U.S. Department of Agriculture aerial photographs noted above
are provided in Appendix B. Partial copies of the Virginia Department of
Transportation aerial photographs showing the site are also presented in
Appendix B. Complete copies of these photographs could not be reproduced here
because of their size; however, they may be obtained from the Virginia Department
of Transportation.
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A "11 January 1990
A. 2.2 - __ .GEOLOGY
This section presents the results of the preliminary geologic survey of
the site area. A geologic map of the site is not presented due to the incomplete
topographic coverage. Figure 2 presents a regional geologic map.
The geologic survey included a field reconnaissance, as well as aerial
photography and topographic map analysis. The field survey included describing,
measuring, and mapping geologic and hydrogeologic features exposed at the ground
surface. Recorded observations of the exposed geologic units included lithology,4
mineralogy, and weathering characteristics. Measurements o£ structure included
strike and dip, fracture frequency, and foliation in the bedrock.
The aerial photographs and topographic maps were evaluated for indications
of larger scale linear̂ features.
flR301335
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11. January 1990
APPENDIX A.3
SURFACE GEOPHYSICAL SURVEYS (SUBTASK 4.2)
To meet the objectives the following geophysical surveys were performed:
1. Magnetometer Survey2. Direct Resistivity Survey
The magnetometer survey was designed to characterize and identify, the
occurrence of significant metallic fill within the landfill area. The resistivity
survey was designed to determine the depth of fill, depth to the water table and
bedrock surface, and depth of fracturing within the bedrock.
The third geophysical survey, electromagnetics, specified in the RI/FS Work
Plan, was to be performed in this subtask. However, as the objective of the
electromagnetic survey is to determine fracture occurrence at the proposed
monitor well locations, Westinghouse recommended, and the U.S. EPA concurred (R,
Rzepski 1988, Personal Communication) that the electromagnetic survey be
performed during Subtask 4.8: Monitor Well Siting Analysis.
This section presents the specific methods employed during the magnetometer
and resistivity surveys,
A.3.1 MAGNETOMETER SURVEY
The magnetometer survey was conducted using an EG&G GeoMetrics Model 856
AX proton precession magnetometer equipped with a gradiometer. The instrument
AR30I336
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A „ 11 January 1990
was configured with one sensor mounted at the top of -a ten £oot aluminum shaft
and the second mounted one meter below the upper sensor.
Proton magnetometer sensors are inherently calibrated, as their operation
is based on nuclear precession. The field calibration for the instrument
included checking the internal clock function and line number counter followed
by tuning the instrument to the proper background intensity of the area under
investigation. From maps supplied by the manufacturer, the background total
magnetic field for Southern Virginia was set at 53,000. gammas.
A. rectangular grid was established at the site with the zero base line
located along the eastern highwall and oriented N80°W (Drawing #1). The base
line was divided and staked oh 10 foot centers with A-0 being the southern most
point and X-0 being the northern most point. After establishing the baseline,
perpendicular lines were extended across the quarry. An additional line (AA)
was established for a short distance in accessible areas along the southern
quarry highwall. Reference stakes on fifty foot centers were established over
the grid.
Following the grid construction, magnetometer data were collected at 10
foot intervals along each line beginning with line A. Both the total field at
the upper sensor and total field at the lower sensor were measured and stored
in the memory of the magnetometer unit. The vertical gradient was calculated by
subtracting the lower total-field reading from the upper total field reading.
To check data reproducibility, the gradient at the first station in each
of the survey lines was remeasured immediately after all stations in that line
were recorded. .In addition, duplicate measurements were^made at the starting
7
AR301337
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
points for all lettered lines and along the 250-ft. interval for all lettered
lines.
A.3.2 RESISTIVITY SURVEY
Ten resistivity soundings were performed at the site. Instrumentation used
for the soundings were the Bison Instruments, Inc., Signal Enhancement Earth
Resistivity System Model 2390 consisting of a current transmitter and voltage
receiver, and the Bison Instruments Offset Sounding System, Model 2365, or "BOSS"
system. The BOSS is essentially a switching unit which incorporates a series
of electrodes laid out on a single cable with a central electrode and electrode
connection points at A-spacings (I,e., distance between each electrode) of 0.5,"
1, 2, 4, 8, 16, 32 and 64 meters. Once set up, five Wenner-type resistivity
soundings are made at each electrode spacing by switching the electrode array
configuration and spacing on the BOSS unit.'
The BOSS system provides a quick method of collecting resistivity sounding
data and exploits the redundancies and cross-checks inherent in a five electrode
array. The effect of these "Offset Wenner" electrode configurations is to
provide greater detail in the resistivity soundings and reduce the interpretation
problems resulting from near-surface lateral resistivity variations. The offset
Wenner resistivity method enables calculation of theoretical resistivity values
for non-existent electrode spacings of 1.5, 3, 6, 12, 24, and 48 meters in
addition to the actual field A-spacings.
Ten resistivity soundings were made parallel to selected magnetometer survey
lines previously established in the quarry (Drawing #1) . One sounding line (#10)
was set up near the eastern edge of the quarry, and oriented in a north-south
AR3EH338
-
FPRQ Task 8.1 RI-DRAFT -: Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
direction. Six soundings (#1, #2, #6, #7, #8, and #9) were placed and orientated
to adequately cover the landfill area. Three sounding (#3, #4, and #5) were
performed along the downgradient (western.) edge of the quarry (Drawing #1) .
The instruments were set up at a known position corresponding to a
magnetometer station. The cables were then extended parallel to the magnetometer
grid and staked with the electrodes to a maximum spacing of 32 or 64 meters
depending on available space.
At each sounding, the instruments were set-up in accordance with the
manufacturers directions. Set-up included checking the batteries, synchronizing
the transmitter and receiver, checking the transmitter output, and confirming
control settings.
Soundings were begun at an electrode spacing of 0..5 meter and the standard
Wenner electrode arrangement. After confirming signal reproducibility at that
setting, the electrode arrangements were switched to the following
configurations: ___i
Center MeasuredElectrodes: __ 1 2 3 _ 4 5 Resistance ,
1st measurement C P __. - P . .. C RA
2nd measurement C C — - - - -.- P P RJJ
3rd measurement C P - - - C P RC
4th measurement C . .. P ..... -P C _ ----- RD^
5th measurement --- C P P C R
AR30I339
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A " 11 January 1990
where:C.— Current electrode,P — Potential electrode, andR - Resistance for specific electrode configurations:
A,B,C, D]_, and D2-
This procedure was followed for each electrode spacing at each sounding,
until no signal was receivable. The maximum electrode spacing obtained was 32
meters at sounding #1. Once the sounding data were collected, the electrodes were
pulled and the cables were reeled in for set-up at another position.
Quality checks of the sounding data were made continuously in the field.
Cable leakage, instrument malfunction, and high contact resistance at the
electrodes were easily identifiable by the observational error (EQ) calculation:
E0 - RA - ( RE + Rc ") x 100% ._... . ._...__
where; RA, Rg, and R^ are resistivity measurements from the electrode
configurations previously described. EQ values consistently outside the range
of + 5 percent indicate high contact resistance, instrument malfunction, and/or
current leakage from damaged cables. Also, the typical relationships of
RA>Rc»Rg and RQ + Rg — RA (within ± 5 percent), were continuously evaluated.
As discussed in Section 3.2.2, the quality of the data are good, although
considerable lateral and offset errors were encountered over the landfill due
to the highly variable electrical properties of the fill.
Apparent Wenner resistivity (Py) calculations were also made in the field
for the Wenner array using the RJJ measurements. These data were plotted on
log-log paper relative to the electrode spacing. These plots provided a means
10
ARSOI'SUO
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
of visually inspecting the quality of the Wenner resistivity data. The
calculation used to determine the apparent resistivity is:
Ptf - 27T X A X RpI ----- - - - - — - - - - - - - - ----- - - - - - . -
where; Py — the apparent Wenner Resistivity in ohm-meters,
A - electrode spacing in meters,
RD * (RD1 + RD2^ = t*ie resistivity measurement In millivoltsI for the Wenner electrode configuration,
and ;I — transmitted current in milliamperes.
At several soundings, resistivities for the short spacings (0.5m and 1m)
were off the instrument scale. Attempts were made to, lower the contact
resistance by driving the electrodes deeper and by pouring salt water into the
ground at the electrodeŝ These attempts were unsuccessful.
The BOSSIX modeling program by Interpex, Ltd. of Golden, Colorado was used
to generate earth resistivity models from the Offset-Wenner resistivity data
(Appendix H3) . BOSSIX provides for user interactive interpretation of a sounding
curve displaying observed data and allowing user input of depth and resistivity
of the earth model layers. . - ;
Forward and inverse model calculations are -initiated by the user for
generating a theoretical̂ sounding curve and' fine-tuning the match between the
theoretical and observed data. The forward calculation uses a Ghosh style
digital filtering technique to carry out the required Hankel transforms and is
capable of modeling resistivity contrasts of 1,000:1. Once a starting model is
defined by the user, the inverse solution can be initiated in the BOSSIX program.
11
AR3QI3U
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
The inverse solution utilizes an Inman-style ridge regression technique to
quickly adjust the model parameters for an optimal fit of the observed data in
a least squares sense (Interpex, 1988). Essentially, this means the computer
program mathematically smooths the data by filtering out data points that stray
too far from the overall trend and transforms the data from resistivity vs.
electrode spacing to apparent resistivity vs. depth. Then, the program
calculates depths and resistivities for a series of layers which produce a
sounding curve that best fits the observed data. Fixing of model parameters by
the user is possible so that known geological or geophysical information can be
used in the interpretation to obtain the best solution based on the known site
conditions.
\ The resistivity sounding data generally support the available data on the
physical setting of the landfill and adjacent undisturbed areas. The results
of the computer modeling are presented in Appendix H3 and are summarized on Table
1 1 . - . . . . . . . .
A.3.3 ELECTROMAGNETIC SURVEY
This section presents the methods used in performing the Electromagnetic
Survey which was conducted in conjunction with the monitoring well siting
analysis.
The EM survey was conducted using an ABEM Wadi Very Low Frequency (VLF)
Instrument. The Wadi consists o£ a hand-held keyboard connected to belt^mounted
measuring and antenna units allowing the instrument to be run by a single
operator.
AR30i3l>2
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
The Wadi operates by measuring the magnetic components of the
electromagnetic field generated by already-existing radio transmitters that use
the'VLF band (15-30 KHz). Electrically conductive structures, such as water.
filled fractures, in the subsurface locally affect the direction and strength
of the field generated by the transmitted radio signal. A weak secondary field
builds up around the geological structure which the Wadi measures and analyzes.
The Wadi is factory-calibrated and does not require calibration during use
in the field. The Wadi unit retains each measurement in its memory, and
constructs a profile of the readings for each survey line which is displayed on
the Wadi keyboard. This profile allows the field personnel to graphically
identify those areas along each survey line which display anomalous EM readings
which may indicate zones of .̂ncreased bedrock fracture, occurrence. By
identifying additional peaks in the profiles of adjacent survey lines it is
possible to trace the trend of the anomaly and measure its orientation. Also,
the Wadi unit contains an Interpret function which can be used to display the
unit's interpretation of the peaks on a given profile. Under ideal conditions,
the dip, dip direction and depth to the top of the anomalous structure causing
the profile peak may be estimated from the data.
The EM survey was conducted by first choosing the approximate areas of the
site where the proposed wells would be located. A total of seven areas were
chosen in accordance with the criteria discussed in Section 4.1. Four of these
areas are located west of the landfill between the north and west drainages and
east of Lawless Creek (well sites FPT005, FP̂ 006, FP-007, and FP-008) . Well site
FP-005 is located adjacent to existing piezometer P-5. The remaining three areas
13 :
flR3Q73i*3
-
FPRQ Task 8.1 RI DRAFT - Appendix A _ Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990"
are located adjacent to existing piezometer P-l, the waste pile, and existing
piezometer P-3 (well sites FP-001, FP-002, and FP-003, respectively). Drawing
1 shows the locations of the existing piezometers, EM survey areas, and proposed
monitor well sites.
EM surveys were conducted at four of the seven proposed well areas including
FP-001, FP-006, FP-007, and FP-008 (the designation referring to the proposed
well nest to be installed in that area). Additional areas were survey in the
vicinity of FP-006 and FP-008 in order to provide sufficient coverage. The
areas around FP-003, FP-004, and FP-005 were not surveyed for reasons discussed
in Section 4.3.
In general, the EM surveys were conducted by establishing a baseline in the
areas of interest varying from 50 feet to 200 feet in length. EM measurements
were then collected along this line at 10-foot intervals. Additional lines were
surveyed at 10-foot spacings on either side of and parallel to the baseline until
the field personnel determined that sufficient data had been collected to
characterize the potential monitor well site. The location of apparent anomalies
were marked in the field with survey tape. To locate the survey lines at a later
time, the endpoints of each line in the grid or the four corners of the survey
grid were marked with stakes or survey tape.
14
/SR30I3H
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse- Project No, 4112-88-908A '. 11 January 1990
APPENDIX A.4
SOURCE AREA SAMPLING (SUBTASK 4.5)
To meet the objectives, eight environmental samples (five solid and three
aqueous) were collected from the following selected locations at the site:
o South Pond (aqueous)o North Pond (aqueous and solid)o Leachate (aqueous and solid)o Waste Pile (solid)o Grey Drum (solid) . : _. . .._. .... . . . _ . _ . _ . .o Black Drum (solid) ;
In addition, duplicate samples were collected at the, North. Pond (solid)
and Leachate (aqueous) to evaluate quality control. Trip, field, and rinsate
blanks were also collected. All samples were analyzed by Industrial and
Environmental Analysts (IEA) of Gary, North Carolina for Target Analyte List
(TAL) and Target Compound List (TCL) parameters in accordance with the most
recent U.S. EPA Contract Laboratory Program (CLP)-Statement of Work (SOW).
This section presents a discussion of the methods employed during the source
area sampling. All procedures were in accordance with the project Sampling and
Analysis Plan. Audit reports (Westinghouse, 1988a, 1988b) on the source area
sampling field methods and laboratory procedures were previously submitted' to
the EPA. :
A total of eight environmental samples (three aqueous and five solid) were
collected on September 13 and 14, 1988. Sample locations are presented on Figure
2 and Drawing No. 1, The sample locations were mutually selected by on-site
representatives of Westinghouse, U.S. EPA Region III (EPA), and EPA's oversight
15.
1345
-
FPRQ Task 8.1 RI DRAFT - Appendix A ..._ _. Revision 0Westinghouse Project No. 4112-88-908A 11 .January 1990
contractor, CDH Federal Programs Corporation (CDM). Duplicate samples were
concurrently collected by CDM.
In addition to the eight environmental samples, two locations were sampled
in duplicate (i.e., north pond, FP-402 and FP-403 and leachate sediment, FP-407
and FP-408). One field blank and one equipment blank were also collected.
A.4.1 AQUEOUS SAMPLING PROCEDURES
This section presents the methods used during collection of the aqueous
samples at the south pond (FP-401) , north pond (FP-402 and FP-403) and leachate
seep (FP-404) (Figure 2). Sample bottles and equipment were assembled on
polyethelene sheeting at each sample location. The volatile organic samples were
C collected first by totally immersing each 40-milliliter (ml) vial sample bottle,
and securing the cap before withdrawing the vial from the water. The remaining
sample bottles were then filled. Water was collected for these samples using a
800 ml stainless steel beaker. The beaker was slowly lowered into the water to
a point approximately midway in the water column. An attempt was made not to
disturb the bottom sediments. Each beaker of water was split equally among the
sample bottles.
Field parameters obtained during the sampling included dissolved oxygen,
pH, temperature, and specific conductance. Field parameters were obtained after
collecting samples by placing instrument probes directly into the area sampled.
Matrix spike and matrix spike duplicate samples were also collected at FP-401.
16
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A - . " " 11 January 1990̂
A.4.2 SEDIMENT SAMPLING PROCEDURES :
This section presents the methods employed for collection of the north pond
sediment (FP-409) and leachate sediment (FP-407 and FP-408) samples. Sediment
samples were collected with a steel shovel which had been cleaned and
decontaminated prior to use. Material was placed in an aluminum foil lined pan.
Volatile samples were collected prior to mixing of the material. The remaining
sample bottles were then filled,. The shovel then was cleaned and decontaminated
prior to use at the next"sample location.
A.4.3 WASTE PILE SAMPLING __ _ _ J - - - - - . - .
The waste pile (FP-410) consists of shredded rubber, and nylon cord and
could not be directly sampled. Therefore, the soils immediately beneath the
waste pile were sampled. The waste pile soils were samplediwith a steel shovel,i
which had been cleaned and decontaminated prior to use. Material was collected
from three different locations underneath the waste pile, and one locationi
immediately downgradient of the waste pile. Sample material was placed in an
aluminum foil lined pan. Volatile samples were collected prior to mixing of the
sample material. Low concentration solid matrix spike and matrix spike duplicate
samples were also collected at FP-410. _ : "I
A. 4.4 DRUM SAMPLING PROCEDURES
Two drums (FP-411 and FP-412) were sampled. The drums sampled were selected
based on accessibility. The content of these drums are believed to be
representative of many drums at the site. Both drums were; open top and contained
17 . - - -- ,
•AR3til3i*7
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 19-9-0
solid materials. FP-411 contained a black tar like substance whereas FP-412
contained grey ash material. Each drum sample was collected with a new, small,
steel shovel which had been cleaned and decontaminated prior to use. Sample
material was placed in an aluminum foil lined pan. Volatile samples were
collected first. The remaining sample bottles were then filled. Prior to
sampling, the drum contents and surrounding vicinity were checked with an organic
vapor analyzer (OVA) and an oxygen/explosimeter. These readings were entered in
the field log book. Medium concentration solid, matrix spike and matrix spike
duplicate analyses were performed on the FP-411 sample.
A.4.5 FIELD BLANK
A field blank was collected at the leachate source sampling location.
Volatile samples were first collected by pouring laboratory supplied volatile
free water from laboratory supplied volatile organic analysis (VOA) bottles, into
sample VOA bottles. Second, laboratory supplied organic free water was poured
into amber sample bottles for semi-volatile, pesticide, and PCB analysis. Last,
laboratory supplied inorganic free water was poured into one liter nalgene sample
bottles for inorganics and cyanide analysis.
A.4.6 EQUIPMENT BLANK
An equipment blank sample was collected in the decontamination area
immediately following sampling at the leachate seep. The sample was collected
by pouring laboratory supplied waters (listed in section 2.5) into the
decontaminated stainless steel beaker, utilized during leachate sampling, and
18
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
then into the sample containers. The order of sample collection was; 1)
volatiles, 2) organics, and 3) inorganics.
A.4.7 "SAMPLE HANDLING PROCEDURES
All sample bottles were labeled prior to sample collection with the
following information:
o site project numbero sample identification numbero date and time collectedo sample source ; . v - - . . . - . 'o preservatives used . -.. - - .-, -..-:-:-----: - r: ,o sample,locationo analysis requiredo collector's initials _
Samples were placed in iced coolers, and the coolers were sealed with
chain-of-custody sample seals. A separate cooler was used to,hold sample bottles
for each sample location. Samples were delivered the day after sampling was
completed (September 15, 1988) to the contract laboratory by Westinghouse
personnel under established chain-of-custody procedures. The chain-of-custody
form is presented in Appendix A.
A.4.8 EQUIPMENT DECONTAMINATIONi
All equipment that came into contact with sample material was decontaminated
according to the following procedure:
1, Wash with an liquanox solution2. Deionized water rinse.3. Isopropyl alcohol rinse.4. Deionized water rinse.
19
AR30f3l*9
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
5. Air dry.6. Wrap in aluminum foil (shiny side out).
Decontamination of equipment occurred in a designated decontamination area
which consisted of polyethelene sheeting laid out and constructed to collect
water in a sump at one end.
20
-
FPRQ Task 8.1 RI DRAFT - Appendix A . [ Revision 0Westinghouse Project No. 4112-88-908A . 11 January 1990 !
APPENDIX A.5 - ;
PRIVATE WELL SAMPLING
Sampling of private wells in the Beaver Park community was conducted on
November 30 and December 1, 1988. Sara Lantizer Stinger and Sharon E. Schaeffer
of CDM Federal Programs Corporation were on site to conduct the sampling. Ten
private wells were sampled. The locations of the wells are shown on Figure 4.i
The purging and sampling protocols, as well as the collection of the field
parameters, and preservation and storage of -the samples were consistentr
throughout the sampling of all the privatejwells._ ̂ All̂ of the residences sampled
had plumbing that was a combinatipn_of ABS, PVC, copper, bronze, and galvanized
steel. Because of the uniformity of sampling techniques and plumbing
configurations, only exceptions are noted below.
Prior to sample collection, the well was run for 15! minutes to purge the
well and pressure tank. On the average about 45 _ gallons of water were
discharged. :: : . ;
The samples were collected by first filling three-40 ml vials for volatile
analysis, then three one-half gallon amber glass bottles for semi-volatiles,
pesticides, and PCS analysis. Last, two one-quart plastic containers for
inorganic analysis were filled. After the samples for laboratory analysis werje
collected, a sample was collected for measurement of temperature, pH, and
conductivity,, The bottles were taken to the field vehicle where they were
properly preserved and stored in iced sample coolers. ;
21
flR30I35
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
Sampling began on November 30, 1988 with the collection of sample HW-2 from
the residence of Gladys Coleman. Sample HW-2 was collected from the kitchen
sink of the residence because the well is under the house and not accessible and
the residence has no outdoor taps. The sample tap was an aeration device
installed with a screen type filter which remained in place during sampling.
The plumbing in the house was a combination of ABS and PVC with galvanized and
copper fittings.
The next sample collected was HW-3 at the residence of Elisa Wimbush. Just
prior to collecting this sample, Ruth Rzepski and Leslie Brunker of the U.S.
EPA arrived on site to observe the sampling procedures. The sample was collected
from the kitchen sink tap following the protocols outlined above.
Sample HW-5 was collected at the residence of Sarah Wimbush. This sample
was collected at the kitchen sink tap also. Matrix spike and duplicate samples,
designated HW-11, were collected at this location.
Sample HW-6, from" the residence of Debbie Lewis, was collected from a tap
in the well house which is located in the side yard of the house. The sample
tap was located between the pump and the pressure tank. The plumbing materials
consisted of ABS and galvanized steel with a bronze tap. One notable feature
at this well site was an ash dump located six feet up-slope from the well house.
The ash pile was a mound approximately six feet in diameter and 1.5 feet deep
which contained ashes, cinders and partially burned wood. During the purging
of this well, David 0. Johnson of CDM arrived on site to conduct a performance
audit of the sampling effort. He was present and observed the collection of the
remaining samples.
22 - ... „ .:_flR301352
-
FPBQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A _ ; 11 January 1990;
Sample HW-7 was collected from the well serving the residences of Richard
Stone and Michael Anderson. The sample was collected from a tap located under
the Stone residence in the crawl space at the rear of the house.
Sample HW-4, at the residence of John A. Motley, was collected from thei
kitchen sink tap following the standard protocol.... Following the collection of
sample HW-4, a field blank sample was prepared.- -This .field blank sample was
collected-using High Pressure Liquid Chromatography grade water, which was poured
into the sample containers following the same protocols used for collecting the
samples from the wells.
The final sample of the day, HW-10, was collected at the residence of Obey
Davis.-. .-This sample was collected from a tap located :between the pump and
pressure tank in the basement of the residence. The plumbing is a combination
of ABS, copper, and galvanized pipe.
The remaining samples were obtained on December 1, 1988. Personnel on site
included Ruth Rzepski and Leslie Brunker of the U.S. EPA, Sara Stinger, Sharon
Schaef f er.. and David Johnson of CDM, and Doug Fraser and Bill Robertson of
Westinghouse. :
The first site investigated was the spring house behind the Carter
residence. The sampling team determined 'that the spring was not flowing.
Therefore, this site was not sampled and an additional private well was
substituted. ..... ... .. ...... ...._ .......
Sample HW-1 was c6llected from the residence of David Gunn. The sample
was collected from an outside tap located at the right rear of the house. The
sample was collected and handled following the standard protocol.
23 , . , :: ;
AR30I353
-
FPRQ Task 8,1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
Sample HW-8 was the second sample collected on December 1. This sample
was collected from an outside tap located on the north-side of the residence of
Roy Williams.
Sample HW-9 was the final sample collected during this event. This sample
was collected from a tap located at the well house in the side yard of Juanita
Wadell's residence.
24
-
FPRQ Task 8.1 RI DRAFT - "Appendix A Revision 0Westinghouse Project No. 4112-88-908A _ 11 January 1990;
APPENDIX A. 6
ECOLOGICAL INVESTIGATIONS (SUBTASK 2 ,,2)
A preliminary wetland delineation was performed at the FPRQ site to
determine if there are any areas in the vicinity of the site which would be
classified as wetlands. The purpose of the preliminary delineation was not to
define the exact wet land-up land boundaries, but to determine the location and
type of wetlands, if any.̂ in the vicinity of the site which may be influenced
by actions occurring at the quarry. The scope of work is based on the May 18,
1988 meeting between the U.S. EPA, the Participants and Westinghouse, and
subsequent correspondence with the U.S. EPA.
The basic guidance document utilized in determining wetland areas was the
Wetland Identification and Delineation Manual. by William S. Sipple, Office of
Wetlands Protection, Office of Water, U.S. EPA, April 1986, Interim Final. To
determine the indicator status of plant species, the National List of Plant
Species that occur in Wetlands, Region I -" Northeast; found in the Corps of
Engineers Wetlands Delineation Manual, Appendix C, Technical Report Y-87-1,
January 1987, was used. Terminology to describe the wetland areas was taken from
Classification of Wetlands and Deepwater Habitats of the United States, by L.M.
Cowardin, et al. (1979).
A. 6.1. PRELIMINARY DATA GATHERING • - - - - =
Preliminary data were collected to help determine where the wetlands areas
would be likely to occur. The U.S.G.S. Blairs, VA quadrangle topographic map,
25- .,- , ".. : , .
fiR3QI355
-
FPRQ Task 8,1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 199-0
a preliminary soils map from the Soil Conservation Services (SCS) (1988), and
black and white and infra-red aerial photographs were examined to determine
potential wetland areas.
A.6.2 WETLAND DETERMINATION TECHNIQUES
Three criteria were considered in determining if an area was to be
classified as a wetland. These criteria were hydrophytic vegetation, hydric
soils, and wetland hydrology. The simple jurisdictional approach as outlined
in the EPA (1988) wetland manual was used in performing the wetland delineation.
In summary, all thre_e of these criteria need to be met for classification as
wetland.
A.6.2.1 Vegetational Analysis _
The site and nearby downgradient areas were inspected and classified into
different broad vegetational units. The dominant plant species in each
vegetations! unit was determined by the following steps:
1. Visual estimates of percent areal cover of individual herbaceous plantspecies were recorded. Cover was defined as the vertical projectionof plant crowns onto the ground.
2. Each herbaceous species was given a cover class and a correspondingmidpoint of the cover class. The cover classes (and midpoints) were:Trace
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A _ -_ - - H January 1990
6. A cumulative total of the ranked species was performed until 50% ofthe sum of the midpoints for all species was reached. All speciescontributing cover to the cumulative 50% threshold were considereddominants. _....-_-. . — ._._. :
7. These steps were repeated for shrub species and samplings. For treespecies, relative basal area was used instead of percent aerial coverto calculate cover classes.
Once dominant plant species within a vegetational unit were identified,
their indicator status was determined using the Region 1 - Northeast wetland
plant list (Corps of Engineers, 1987). "
A.6.2.2 ExajrLinaj:ijDn̂ of̂ Soils ''"'
Pittsylvania County SCS soil maps (1988) were examined to determine the
soil series for the vegetational units. A list of hydric soils was consulted
to determine if the soil series for the vegetational units were classified as
hydric. -••— "- = "" "~- --:- -'----' .... ..'̂ r":......-._ -.- .; .; -- - . ;
Soils cores were obtained from each vegetative unit and examined for
indications of .hydric soil conditions. Hydric soil indicators include:
1. Organic.-soils (Histosols) or mineral soils with a histic epipedon.
2. Gleying or mottling of mineral soils.
3. Sulfidic materials.
A soil was considered to be a hydric soil if any of the above conditions
were encountered. ,
27
flR30)357
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0( Westinghouse Project No. 4112-88-908A 11 January 1990
A.6.2.3 Hydrologic Observations
Evidence of surface inundation, such as sediment deposits, standing water,
surface scouring, drainage channels, and seeps were recorded. Plant
morphological adaptations, such as adventitious roots and buttressed tree bases,
were also used as indicators of saturated soil conditions.
A.6.3 AERIAL PHOTOGRAPHS
A series of aerial photograph was also examined to determine the historical
presence of wetland areas. Black and white aerial photographs from 1963, 1971,
1972, 1982, 1986, and 1988 and an infrared 1982 photograph were examined.
A. 6.4 WILDLIFE PRESENT IN WETLANDS
During the wetland determination, any animal species observed in the wetland
areas were recorded.
28
flR30I358
-
FPRQ Task 8,1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A __ ; _11 January 1990;
APPENDIX A.7
BOREHOLE DRILLING, SAMPLING AND GEOPHYSICS (SUBTASKS VlO AND 4.11)
The following four~ tasks were, implemented to meet the objectives of the
subtasks. " . - . . " " . " , :
1. Installation and development of 10 monitor wells at strategiclocations, with these wells completed at various depths.
2. Collection of rock cores from two boreholes drilled on the landfillperimeter. " ~; - ;
3. Performance of a suite of borehole geophysical logs includingtemperature, caliper, and conductivity in six deep wells and oiieshallow well on the perimeter of the landfill.. :
4. Excavation of two test pits in the surficial deposits within thelandfill area. .."." . . . " " ' '
This section presents a discussion of the procedures and protocols employed
during the borehole drilling, sampling, and geophysics; the Phase II well
installation; and the test pit investigation. All procedures employed were in
accordance with the project operation plans. Based on the Phase I results,
several modifications to the project operation plans were agreed to by the EPA,
the PRP's, and Westinghouse. The modifications were as follows:
1. Sampling and analysis of the diabase dike _were not required.
2. Sampling and analysis of the near-surface materials encountered whiledrilling the boreholes were not required, --.--.•
3. Four of the five Phase I piezometers" were used as Phase II monitorwells. ' "" ~ ..-——.-- -.— — - ...
4. Specific locations and completion intervals for the Phase II monitorwells were adjusted. . " . ! . . . .
29
flR301359
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
5. Rock cores from two locations were collected.
6. Dedicated Waterra pumps were used for well development, purging, andsampling.
7. Acoustical well logs were not required.
These modifications are described in the following references;
o Technical .Memorandum, Subtask 4.8: Monitor Well Siting Analysis(Westinghouse, February, 1989)
o April 24, 1989 Westinghouse letter to Lesley Brunker (Westinghouse,April 24, 1989)
o May 9, 1989 Personal Communication between Westinghouse and LesleyBrunker (Brunker, May 9, 1989)
A.7.1 BOREHOLE DRILLING
Ten boreholes, FP-001B, FP-003B, FP-004, FP-005B, FP-006A, FP-006B, FP-
007A, FP-007B, FP-008A, and FP-008B (Drawing 1, Figure 2), were drilled during
the period May 11, 1989 to June 1, 1989 as part of the Phase II monitor well
installation process. The "FP-OO" designation refers to the well installed in
the borehole although, for identification, it is also used to identify the
boreholes described in this section. The ten boreholes were drilled as three
nested pairs terminated at shallow and deep intervals, three deep boreholes
drilled adjacent to existing shallow wells, and one individual shallow borehole
drilled at the perimeter of the landfill. The locations of these boreholes, and
the subsequent wells installed in them, are shown on Drawing 1 and Figure 2.
The boreholes were drilled using a truck-mounted Schramm TH-64 air-rotary
drilling rig. The shallow boreholes were advanced to a depth of 5 to 10 feet
30
-
FPRQ Task 8.1 RI DRAFT - Appendix A : Revision 0Westinghouse Project No. 4112-88-968A " - - -Q January 1990
below the water table to ensure a sufficient column of water in the completedi
monitor well. The FP-004 borehole was drilled to. approximately 25 feet below
the water table to allow the screen interval of well FP-004 to extend across
the full thickness of-the nearby landfill material.
The deep boreholes were completed by first drilling a 10.0 inch O.D.
borehole to the completion depth, or greater, of the adjacent shallow well. A
6.25 inch O.D. galvanized steel surface casing was then installed and grouted
into the borehole in order to case-off the water table zone monitored by the
shallow wells. The surface casing was grouted using a Portland cement and
tremmie pipe. The FP-005B borehole required the installation of a 12.0 inch O.D.
surface casing from ground surface to 4.5 feet-to prevent excessive caving during
the drilling process. The surface casing was installed using a poured Portland
cement grout. After the grout for the surface casing had set-up, the borehole
was advanced further using a 6.0 inch O.D. bit. The borings were advanced a
minimum of 20 feet past the completion depth of the adjacent shallow well to
allow a minimum 10 feet- separation between the screen intervals of the shallow
and deep wells. Several deep boreholes, however, had to be drilled further than
20 feet in order to intercept substantial water-bearing fractures. Ground water
occurred at depths ranging from 7 to 18 feet.
A minimal amount of .potable water obtained from City of Danville fire
hydrants was utilized during drilling to aid in removing cuttings from the
borehole, to lubricate the drill bit, and to suppress dust. The water and
cuttings ejected from the boreholes during drilling were collected on plastic
sheeting placed on the ground around the borehole. The sheeting was sloped to
31
• A R30136I
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A . . .11 January 1990
a plastic-lined collection sump which collected water blown from the borehole.
The water and cuttings were transferred to 55-gallon drums, sealed, then stored
in two fenced-in enclosures located at the site. Each drum was labeled for
content identification.
Prior to drilling or redrilling each borehole, all. drilling equipment was
decontaminated by steam cleaning. The decontamination area was lined with
plastic sheeting which sloped to a liquids collection sump. When necessary, the
sump was pumped into labeled 55-gallon drums which were stored in the fenced-
in enclosures at the site.
A.7.2 BOREHOLE SAMPLING
A.7.2.1 Overburden Soil Sampling'
The collection of overburden soil samples was attempted during the drilling
of the shallow boreholes. The frequency of sample collection was determined by
soil characteristics, but was generally every 5 feet or less. The samples were
collected by pushing a decontaminated 1.375 inch I.D. split-barrel sampler into
the unconsolidated sediments. Due to the thin to non-existent overburden at the
drilling locations and to stiff soil characteristics at some sites, few split-
barrel samples were collected. The samples were classified in the field by the
site geologist. The soil lithologies of the deep wells were considered to be
identical to those of the adjacent shallow wells. Bedrock lithology was
determined from rock cores and, drill cuttings produced during the borehole
drilling procedure. Borehole logs for all shallow and deep wells at the site
are presented in Appendix A.
32 :
SR30I362
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990 :
A.7.2.2 Bedrock Coring ... .-,
Bedrock cores were collected from two boreholes, FP-003B and FP-004, to
provide undisturbed samples of the bedrock material. The core samples provide
information on bedrock mineralogy and petrology, and fracture occurrence and
orientation. .. _ :
Bedrock was cored using an ATV-mounted CME-75 auger rig. The cores were
cut using a 10-foot Longyear wirellne core barrel and diamond bit. FP-003B was
cored from 18.0 to 37.8 feet. This interval extended from the bottom of the
outer casing to the expected final borehole termination depth; however, the
borehole had to be drilled deeper to intercept a suitable fracture zone. FP-
004 was cored from 15.5 to 27.2 feet. This interval includes the middle 11.7
feet of the final screened interval of well FP-004.
The cores" were~~classified and logged by the site geologist. The rock core
logs are presented in Appendix B.
A.7.3 """'BOREHOLE GEOPHYSICS
To help characterize subsurface conditions and aid in the placement of well
screens, a suite of borehole geophysical logs was run in all deep boreholes as
well as in FP-004 located adjacent to the landfill. The logs included
temperature, caliper, and borehole induction (conductivity) and were used mainly
to aid in the detection of fractures zones in the bedrock. The logs were run
in two phases, except for FP-004, due to drilling constraints of the deep
boreholes.- - - — — - - •• :
33
AR30I363
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
The logging system was comprised of a Mount Sopris Model 25.00 Logger, a
Mount Sopris Model DLP-2481 temperature probe, a Microtec Model 1104 3-arm
caliper tool, and Geonics EM-39 borehole conductivity unit. The EM-39 unit
utilized a programmable Polycorder digital logger to record and store
conductivity data for later retrieval using a personal computer. The temperature
and caliper logs were run using the Mount Sopris Model 2500 logger as the control
unit which stored data on graph paper within the logger.
The caliper tool was calibrated several times during the logging process
using pieces of pipe of known inner diameter. This allowed a later
quantification of the actual diameter of the borehole. The temperature probe
was not calibrated since the temperature of any borehole fluids would later be
\ determined during well development. Also the actual borehole fluid temperature
was not as important as its amount of change during the logging run. Any changes
in borehole fluid temperature, indicating possible fractures contributing cooler
or warmer water, were evident on the graph produced during the logging run so
temperature probe calibration was not necessary. The EM-39 unit was calibrated
according to the Geonics Operating Manual prior to its use in each borehole.
Since the deep boreholes utilized a surface casing., it was necessary to
perform the logging operation in two phases. The first phase of logging was
completed prior to the installation of the surface casing and involved logging
the upper portion of the borehole. Good geophysical data could not be obtained
for the upper portion of the hole once the surface casing was installed,
The second phase of logging was completed after the borehole had been
advanced to its completion depth. The portion of the borehole between the bottom
' 34 -.
fiR30136U
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A _ " """."'. '. ' ' 11 January 1990
of the surface casing and the bottom of the borehole was then logged. The two
logs were later combined to form a complete logging record for the entire depth
of the borehole. FP-004 required only one logging run as it did not require the
use of a surface casingT
The order of logging was first, temperature; second, caliper; and third
conductivity. This logging order was utilized to maximize efficiency of the
logging operation and to minimize any effects of an individual logging run on
the borehole fluid which could affect a subsequent" logging run. After each
logging run the tools and tool cables were decontaminated by wiping with a sponge
soaked in a water/alconox solution and then rinsed with distilled water and
allowed to dry. ' "~ ~ . ~ ... :
Operation of the three logging tools was in accordance with the
manufacturer's instructions. Measurements of temperature and conductivity were
collected both on the up and down log runs. Caliper measurements were collected
only on the up log run. The temperature, and caliper logging runs produced a hard
copy of the results in the form of a graph which was available for study
immediately after these two logging runs had been completed. The EM-39 unit
utilized a Polycorder digital data recorder to store the data points for lateri
retrieval using a personal computer. The unit also had an analog dial which
displayed real-time readings of conductivity as the logging run progressed. The
unit did not, however, utilize a data recording device which could produce a hard
copy of the data at the time of the logging. The analog dial was observed during
logging in order to determine.....whether any soil or bedrock zones exhibited
increased conductivity, thereby indicating the possible presence of water-
35 "v .::... " ; :
AR301365
-
FPRQ Task 8.1 HI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
bearing fractures. After the well installation process was completed the
polycorder was sent to Geonics to retrieve the EM- 39 data and print it out.
Geonics personnel informed us that the Polycorder unit was faulty and, though
it gave no indication of malfunction during use, did not store the conductivity
data measured when logging the wells. Geophysical logs for the temperature and
caliper runs are presented in Appendix C.
( 36flR301366
-
FPRQ Task 8.1 RI_DRAFT - Appendix A Revision 0Westinghouse Project _Np,_ .4.1J.2-88-908A .____ ;/.__ "" : .... 11 January 1990 -
APPENDIX A.8
MONITOR WELL AND PIEZOMETER INSTALLATION AND DEVELOPMENT :
A monitor well was installed in each borehole at the completion of
drilling/logging. The monitor wells consisted of_steam-cleaned two-inch I.D.
schedule 40 PVC with flush-threaded joints. For most wells, ten feet of No. 10^
mill slot screen was installed at the end of the casing string. However, well
FP-004 had a thirty-foot screened interval in order to monitor the entire
thickness of the nearby landfill deposits. Well FP-OOEA had a fifteen-foot
screen interval in order to screen across a major fracture zone while still
placing the top of the screen above the water table.
A filter pack consisting of torpedo silica sand was placed around the screen
interval by pouring to a level 0.6 to 3.5. feet above the top of the screen. An
annular seal consisting of 1.0 to 5.0 feet of: 1/4 to 1/2-ihch bentonite pellets
was placed above the filter pack. If the annular seal was above the water table
it was wetted with several gallons of potable water. The remainder of the
annulus was filled to the land surface with a Type 1 Portland cement grout mixed
with approximately 5 percent (by weight) bentonite powder. The grout was
emplaced by pouring it into the borehole. After emplacement of the grout for
the shallow Wells, a 4-inch I.D. protective steel casing was placed over the well
head into the grout and cemented in place. For the deep wells the surface casing
was cut off above the ground surface to act as the protective casing. A Portland
cement grout/torpedo sand mix was mounded around the protective casings to
provide support and aid in diverting surface run-off from the wells. A lockable
37
flR301367
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A "" 11 January 1990
lid was affixed to each protective casing and secured with a keyed padlock.
Construction logs for all wells and piezometers at the site are contained in
Appendix D, A summary of completion details for all wells and piezometers at
the site is presented on Table 1.
The newly installed wells and the four piezometers being redesignated as
monitor wells (P-l, P-2, P-3, P-5) were developed to remove the residual effects
of drilling. The development procedure consisted of using a dedicated Waterra
inertial pump (delrin foot valve and polyethylene tubing) to purge water from
the wells until the water cleared and/or indicator parameters of temperature,
pH, and conductivity stabilized. The water in most wells cleared fairly well.
Although wells FP-007A and FP-008A did not clear up after extensive pumping,
their indicator parameters did stabilize. The initial pH values for FP-001B were
anomalously high, so a decontaminated stainless steel air-lift pump was used to
pump a large amount of water from the well to attempt to lower the pH. After
pumping a total of 195 gallons from the well, the pH was lowered from 9.59 to
6.40, Field meters were calibrated at the beginning of the day in accordance
with manufacturer's instructions. The field values for each well are presented
in Appendix E, along with other well development data. The development water
was contained in labeled 55-gallon drums and stored in the fenced-in enclosures
at the site.
38
AR30I368
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-8.8-908A . 11 January 1990
APPENDIX A.9
HYDRAULIC TESTING . : .
This section presents a discussion of the procedures and protocols employed
in the Preliminary Hydrologic Study. For this study the following work tasks
were performed: T . . . . . . . . ' . ....,_,. '.I
1. installation and development of five piezometers,
2. establishment of eight surface water stations,
3. periodic water level measurements, and
4. bail/recovery hydraulic tests at each piezometer..
All procedures employed were in accordance with the project operation plans.
The only modification to the project operation plans is that the piezometers were
installed per the monitor well installation specifications in order to utilize
some of the piezometers as monitor wells during Phase II of the RI. This
modification and the use of schedule 40 PVC was approved by the U.S. EPA project
manager. ...'.. .._.. .... . ....... ; .... ._!_ -.-."„:.- ..__-._"'-••" . - - _ . . - :: :-
A.9.1 PIEZOMETER INSTALLATION AND DEVELOPMENT
Five piezometers, P-l, -2, -3, -4, and -5 (Figure 2) were installed during
the period October 27, 1988 to November 1, 1988 in order to determine ground
water conditions and overburden and bedrock lithologies. The locations of the
piezometers were mutually selected by Westinghouse, CDM, and EPA project
personnel. .. ,___._._._!.__... \ ...... " ."""-, . ' . . - . . , .
3 9 . . . • . . = . ' :
SR30I369
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A _. ... 11 January 1990
The boreholes for the piezometers were drilled using a truck-mounted Chicago
Pneumatic air-rotary drilling rig. The 6.25 in. diameter boreholes were advanced
to the water table. The boreholes were then drilled five -to ten feet deeper to
ensure a sufficient column of water in the completed piezometer. The collection
of soil samples was attempted at the surface and at approximate five-foot:
intervals while drilling in the overburden. These samples were collected by
pushing a decontaminated 2.5 inch ID split barrel sampler approximately two feet
into the unconsolidated sediments. Due to the thin overburden in most areas of
the site, very few split barrel samples were collected. The samples were
classified in the field by the onsite geologist. Borehole logs are presented
in Appendix A.
i The piezometers installed in each borehole consisted of two-inch ID schedule
40 PVC threaded-flush joint casing. Ten feet of No.10 mill slot screen was
installed at the end of the casing string. A filter pack consisting of torpedo
silica sand was placed around the screen interval by pouring to a level 1.0 to
2.5 feet above the top of the screen. An annular seal consisting of 1.5._to 5.0
feet of 1/4-inch bentonite pellets was placed above the filter pack and then
wetted with water bailed from the piezometer. The remainder of the annulus was
filled to the land surface with a Type I Portland cement grout mixed with 5
percent (by weight) bentonite powder. For piezometer P-3, Sakrete was
substituted for the Portland cement due to the very short interval which needed
to be grouted. Since the interval to be grouted ranged from only 2.5 to 15,9
feet, the grout was emplaced by pouring it into the borehole. -After emplacement
of the grout, a 4.5-inch OD protective steel casing with a lockable lid was
40
AR30I370
-
FPRQ Task 8.1 RI DRAFT ^ Appendix A Revision 0Westinghouse Project No. 4112-88-908A .—... ...._ '.. 11 January 1990
placed over the well head into the grout and cemented in place. The lid was then
secured with a keyed padlock. Well construction logs are contained in Appendix
B. A summary of piezometer completion details is presented on Table 1.
Prior to drilling each borehole, the drilling rig, associated tools, and
the piezometer casing were decontaminated by steam cleaning using a steam jenny.
Decontamination water was obtained from the Goodyear Tire: and Rubber plant in
Danville, Virginia. All drill bits, drill rods, drilling tools, split barrel
samplers, PVC casing, screen, and the rig itself were also cleaned in this manner
to prevent any cross-contamination among the piezometers. The decontamination
area was located east of the quarry and consisted of an area of smooth ground
covered with several overlapping sheets of heavy plastic. The area was
surrounded by a low berm and sloped to a plastic-lined sump which collected the
water produced by the decontamination procedure. The water was subsequently
pumped into labeled 5 5-*-gal Ion drums for storage onsite in the fenced-in storage
area. At the completion of the piezometer installation, the sump pits were
backfilled to land surface and all the plastic- sheeting used as liner material
was collected and stored in 55-gallon open-top drums in the, storage area. In
addition, the well cuttings from the downgradient piezometers, P-3 and P-5, were
collected and placed in labeled SS^gallon open-top drums in the storage area.
On November 2, 1988 the piezometers were developed to remove the residual
effects of drilling. The development procedure consisted of using the same
teflon bailer used to wet the bentonite seal to surge and evacuate the piezometer
until the bailed water was fairly clear. Since all but one,of the piezometers
were screened completely in the bedrock, relatively clear water was obtained
41 ...'.
AR30137I
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
after bailing only 1.5 to 4.5 gallons of water from the piezometers. Following
development, a water sample was collected and measured twice for field values
of pH, specific conductance, and temperature. Field meters were calibrated prior
to use at each piezometer in accordance with the SAP. The field values are
presented in Appendix C, along with other piezometer development data. The
development water from the piezometers was collected and stored in a labeled
55-gallon open-top drum in the on-site storage area. Piezometers to be used in
the Phase II ground water sampling will be developed further at that time.
SR301372
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A . " _ 11 January 1990
APPENDIX A. 10
WATER LEVEL MONITORING
Static water levels in the five piezometers were measured on four occasions,
November 2, November 7, December 1, and December 15, 1988. Depth to the static
water level was measured to the nearest hundredth of a foot using an electric
well probe referenced to the top of the PVC casing. The probe was rinsed with
distilled water between measurements. The elevation of the top of the well
casing (referenced to mean sea level) was determined to the nearest hundredth
of a foot by a survey completed on November 7, 1988 by personnel of Dewberry arid
Davis, Virginia registered surveyors from Danville,- Virg5.nia. The water level
data for the five piezometers are presented in Appendix I).
Water level recorders were "ins tailed on P-l, P-2, and P-3 in early December.
Data from the recorders installed on the three piezometers will be submitted in
the near future as an addendum "to this report. . :
43
AR301373
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
APPENDIX A. 11
GROUND-WATER SAMPLING AND ANALYSIS (SUBTASK 4.13)
To meet the objective of this subtask, ground-water samples were collected
from 14 ground-water monitor wells (Drawing 1) . Installation of these wells is
described in Technical Memorandum 4.10 (Westinghouse, 1989) previously submitted
to the U.S. EPA.
The scope of work related to ground-water monitoring (Subtask 4.13) was
specified in a letter to Lesley Brunker of U.S. EPA dated May 9, 1989
(Westinghouse, May 9, 1989). Specific ground-water monitoring information can
be found in Table 3-1 of that communication (Appendix A).
The ground water monitoring program included the sampling of fourteen wells.
\ All wells were analyzed for Target Compound List (TCL) and Target Analyte List
(TAL) constituents. Additionally, total .dissolved solids (TDS), chloride,
sulfate, and bicarbonate were analyzed. One trip, one duplicate, one field, and
one equipment blank were obtained at well FP-002A for quality assurance and
quality control (QA/QC) purposes. All analyses and methods used by the contract
laboratory were to be performed according to the methods and protocols in the
most recent Contract Laboratory Program (CLP) Statement of Work (SOW).
This section presents a discussion of the procedures and protocols employed
during the ground-water sampling and analysis. All procedures employed were in
accordance with the Sampling and Analysis Plan (SAP) and the Quality Assurance
Project Plan (QAPjP).
A total of 14 monitor wells were sampled from June 13 to 16, 1989. Well
locations are shown on Drawing 1 and Figures 2 and 3. For quality control
*• 44
-
FPRQ Task 8.1 RI DRAFT -.Appendix A Revision 0Westinghouse Project No, _4112-_8_8-9Q8A . 11 January 1990 :
checks, one duplicate sample, matrix spike, matrix spike duplicate, equipment
blank, and field blank were also collected. Ground-water samples were also split
with U.S.EPA"s oversight contractor, CDM Federal Programs Corporation from wellsi
FP-001A, FP-003A, FP-003B, FP-004, and FP-007A.
Table 1 .presents" sampling results. Appendix B presents the laboratory
data. Field sampling and analysis summary forms are presented as Appendix C.
i
A.11.1 SAMPLING METHODS . . '
This section describes the methods used in collecting the ground-water
samples. All monitor wells were developed one to two 'weeks prior to sampling.
Well development is described in the technical memorandum for Subtask 4.10/4.11
(Westinghouse, 1989). The date of well development, date and time of purging
and sampling, and order of sampling are shown in Table 2,. '.
Ground-water samples were collected using the following procedures:,i
o The protective cap was unlocked and removed. The well cap was removedand the headspace was monitored with an HNu system portablephotoanalyzer. The water level was measured and recorded.
o The monitor wells were evacuated, using'dedicated Waterra pumps, toremove stagnant—water prior to sampling. Temperature, pH, specificconductance, oxidation-reduction potential, and the volume of waterremoved were recorded in the field log book. When the indicatorparameters had stabilized and a minimum of three well volumes had beenremoved, the wells were considered ready to sample. All wells exceptFP-001A were sampled within 24 hours of the time that well evacuationhad occurred.
o Some of the wells were sampled immediately after evacuation. However,most wells required a -recovery period prior to sampling in order toobtain sufficient water.. In these cases, the well caps were replacedand the protective caps were locked until time for sampling.
45
flR30I375
-
FPRQ Task 8,1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
o Immediately prior to sampling, a new length of Norton food-grade Tygontubing was attached to the Wattera pump. Approximately one gallon ofvater was pumped and wasted into the water collection drum.
o The sample bottles for volatile organic analysis were filled first,by pumping water directly from the well through the Tygon tubing.
o The remaining bottles for organic analysis were filled by pumpingwater directly from the well through the Tygon tubing.
o Bottles for inorganic analysis were filled last. Sample bottles fortotal metals contained preservative, previously placed in the bottlesat the laboratory. Additional water samples for dissolved metals werecollected in laboratory-supplied Nalgene bottles without -preservativesfor subsequent filtration in the site 'trailer.
o Field parameters were measured on water pumped into a stainless steelbeaker. Parameters recorded were temperature, pH, specificconductance, oxidation-reduction potential, dissolved oxygen, andalkalinity.
f ' o The well cap was replaced and the protective cap locked.
Information concerning the development, evacuation, and sampling of the wells
can be found in Table 2. Field sampling forms are presented in Appendix C.
A duplicate water sample was collected at well FP-003A and submitted as
FP-009A. Matrix spike and matrix spike duplicate samples were collected at well
FP-005B.
A.11.1.1 Filtering Inorganic Samples
Samples for both total inorganic compounds and dissolved inorganic compounds
were collected. Sample water for dissolved inorganics was filtered prior to
placement in the sample bottle. The filtering apparatus consisted of a stainless
steel backflush filter holder (Geotech Environmental Equipment, Inc.) containing
a glass fiber prefilter (Geotech Geofilter No. 24) and a 0.45-micron cellulose
AR30I376
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project _No. 4112-88-908A .11 January 1990
acetate filter. Sample water was collected in a Nalgene bottle and then pumped
from the sample collection bottle through the filter system into the sample
bottle containing nitric acid preservative,-- The pump system consisted of a
Masterflex Quickload peristaltic pump head connected to a Masterflex pump drive
with Norton Food-grade Tygon tubing.
The filter system was decontaminated between samples by the following
procedure. Used filters were rempved and discarded. The filter holder was
cleaned by rinsing with deionized water. The filter holder was reassembled
without filters and approximately 200 ml of deionized water was pumped thorough
the filter and tubing system. An effort was made to remove as much deionized
water from the tubing system as possible.
To filter a sample the following procedure was used. A new filter and
prefilter were installed on the 'filter holder and the holder was assembled. The
pump system was turned on and the intake tube inserted into the Nalgene bottle
of sample water collected from the well. The initial 10- to 20 ml of water to
discharge from the tubing was wasted to a collection container. The remaining
sample was pumped into a laboratory-supplied bottle containing preservative.
A.11.1.2 Field Blanks
A field blank (FP-010) was produced at the location of well FP-008.
Volatile samples were first collected by pouring laboratory-supplied volatile-
free water into 40 ml VOA sample .bottles. Second, laboratory-supplied organic-
free water was poured into amber sample bottles for semi-volatiles, pesticides,
47
AR30I377
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0( Westinghouse Project No. 4112-88-908A .. 11 January 1990
and PCS analysis. Last, laboratory-supplied, inorganic-free water was poured
into nalgene sample bottles for inorganic and cyanide analysis.
A.11.1.3 Equipment Blank
An equipment blank (FP-011) was produced at the site trailer. Because new
sections of Tygon tubing were used for each sample, the sample for organic
analysis was collected by pouring laboratory-supplied waters through a length
,of new Tygon tubing and into the bottles. To produce the sample for inorganic
analysis, laboratory-supplied water was pumped through the filtration system,
with filters installed and collected in a sample bottle. The technique used was
the same used in processing ground-water samples previously described in
\ Section A.11.1.1.
A.11.1.4 Sample Handling Procedures
Samples were handled in accordance with Section 3.13 of the SAP. Sample
bottles were labeled, prior to sample collection, with the following information:
o site project numbero sample identification numbero date and time sample was collectedo sample sourceo preservatives usedo analysis required, ando collector's initials
Samples were placed in iced coolers with additional ice added as needed.
All coolers were stored in the site trailer prior to delivery to the laboratory.
A separate cooler was used to hold sample bottles for each sample location.
C 48
AR301378
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. _4112-88-50.8A __....__.... . . . . . . . 11 January 1990
Samples were delivered to the contract laboratory by Westinghouse personnel on
June 16, 1989. All samples were handled under established chain-of-custody
procedures. Chain-of-custody forms are presented in Appendix B.
A. 11.2 - -—-LABORATORY METHODS
Industrial & Environmental Analysts, Inc. (TEA) was the contract laboratory
used for Phase II sample analysis. Ms. Patty L. Ragsdale was the Qualityi
Assurance Director at IEA during Phase II activities.
The samples from this Subtask were placed by IEA in two cases (637-8 and
637-9). Case 637-8 includes TCL and total metals analysis and Case 637-9
includes dissolved metals analysis only. This method of dividing the samples
into cases was done by IEA in accordance with the Contract. Laboratory Program -
Statement of Work (CLS-SOW) procedures and requirements.
49
flR301379
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0/ Westinghouse Project No. 4112-88-908A 11 January 1990
APPENDIX A.12
SURFACE-WATER AND SEDIMENT SAMPLING AND ANALYSIS (SUBTASK 4.14)
A.12.1 ROUND ONE
The principle objectives of this subtask were to sample and analyze surface
water and sediments upgradient and downgradient of the FPRQ site to determine
the nature and possible pathways of contamination, if any, resulting from prior
landfill operations at the site. The results of this effort will be utilized
to evaluate potential risks to human health and the environment and to evaluate
appropriate remedial actions for the site. ._
( A.12,1.1 Scope of Work
To meet the objectives of this subtask, surface-water and sediment samples
were collected from eight locations. Flow or discharge rates of Lawless Creek,
the northern and southern drainage, and several, nearby springs were also
measured.
The scope of work related to surface-water and sediment sampling (Subtask
4.14) was specified in a letter to Lesley Brunker of U.S. EPA dated May 9, 1989
(Westinghouse, May 9, 1989). Specific surface-water and sediment sampling
information can be found in Table 3-1 of that communication (Appendix A).
All samples were analyzed for Target Compound List (TCL) and Target Analyte
List (TAL) constituents. Additionally, surface-water samples were analyzed for
total dissolved solids (TDS) , chloride, sulfate, hardness, bicarbonate, and total
suspended solids. Sediment samples were analyzed for total organic carbon (TOC),
\ 50 . ;
AR301380.
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-.908.A . _. i. _.ll January 1990
cation exchange capacity (CEC), grain size (GSA), percent moisture, and percent
solid. One duplicate sample per matrix, as well as one trip, one equipment, and
one field blank were obtained for quality assurance and quality control (QA/QC)
purposes. All analyses and methods used by'the contract laboratory were to be
performed according to the methods and protocols in the most recent Contract
Laboratory Program (CLP) Statement of Work (SOW).
A.12.1.2 Methods : ... .. . : _ : . .
This section presents a discussion of the procedures and protocols employed
during the surface-.w_a.ter_sampling, sediment sampling, and stream flow measuring
activities. Except as noted, all procedures employed were in accordance with^ ̂^̂ ^̂ B̂
\̂|̂ the Sampling and Analysis Plan (SAP), and the Quality Assurance Project Plan
Surface water and sediments were sampled at a total of eight locations
from May 30 through June~2, 1989. Weekly surface-water floŵ measurements were
taken from May 24 through June 22 at 15 locations. Sample locations are shown
on Drawing 1 and Figure 2. --:--...:. -:-,—: - -- - - -—... . '. •
In addition to the samples obtained from the eight locations, one duplicate.
sample per matrix—was collected. One field blank, one trip blank, and one-
equipment blank were also collected. Surface-water and sediment samples were
also split with U.S.EPA's oversight contractor, CDM Federal Programs at locationsiFP-306, FP-309, FP-311, and FP-312. - - ----- .'- .
Sampling activities.were in accordance, .with the requirements specified in
Table 3-1 of the May 9, 198.9- letter to EPA (Appendix A) . Appendix B presents
laboratory analysis data ̂ Appendix C presents Field Sampling and Analysis forms.
si AH30I38I
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0I Westinghouse Project No. 4112-88-908A " 11 January 1990
A.12.1.2.1 Surface-Water Sampling Procedures
This section presents the methods used during the collection of the surface-
water samples. All procedures were in accordance with the SAP (Section 3.11.3)
and U.S.EPA approved methods (U.S.EPA, 1987). Except as noted later, all samples
were collected using the following procedures:
o Sample bottles and equipment were protected from potentialcontamination by placement on polyethylene sheeting at each samplelocation.
o Field parameter measurements were taken directly from the stream andentered immediately in the field log book. Parameters measured weretemperature, pH, conductivity, oxidation-reduction potential,dissolved oxygen, and alkalinity.
o Volatile organic samples were collected first by totally immersingeach 40-milliliter (ml) vial sample bottle, and securing the cap before
\ withdrawing the vial from the water.
o The remaining sample bottles were then filled by immersing the bottlein the surface water. Care was taken not to disturb the bottomsediments.
o The bottle caps were secured and sample bottles were placed in coolersand iced.
o The field log book was completed for the sample site. This includeda description of the sample location, personnel involved, weatherconditions, and any unusual occurrences or discoveries.
o Photographs were then taken of the sampling site.
At sample location FP-306, the flow fate was low and the substrate was
rock. To collect water, a flume was constructed of aluminum foil, and water was
collected in a stainless steel bowl. The 40 ml vials for volatile organics were
filled directly from the discharge from the flume. All other bottles were filled
by dipping water from the bowl with a stainless steel beaker and pouring the
^ water into the bottle. The water was split sequentially and equally among the
52 _' i__..
flR30!382
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse. Project No. 4112-88-908A \ . 11 January 1990
sample bottles. A duplicate water sample was also collected at this same
location.
Matrix spike and matrix spike duplicate samples were collected at location
FP-308 (See Drawing 1 and Figure 2).
A.12.1.2.2 Sediment Sampling Procedures ; ,
This section presents the methods used during the collection of the sedimenti
samples. The procedures used were also in accordance with the SAP (Section
3.11.4) and U.S.EPA approved methods (U.S.EPA, 1987). Sediment samples were
collected following collection of the surface-water samples. Samples were
collected using the following procedure:
o Sample bottles and equipment were protected from potentialcontamination by placement on polyethylene sheeting at each samplelocation.
o Sediments from the stream bed were collected with a clean stainlesssteel beaker. An attempt was made to collect the,finer silt or claysediments and to avoid areas with coarse .gravel. Sediments werecollected within five feet of the surface-water sampling locationexcept for FP-206, which was collected approximately ten feetupgradient of the.point of sampling for the surface water. :
o Material was placed in an aluminum foil-lined pan. Holes had beenpunched in the pan to permit water drainage.
o Volatile samples were collected first, prior to mixing the material.Latex gloves were worn while sampling. New gloves were used at eachsampling location.
o After collection of volatile samples, the material was mixed with adecontaminated, stainless steel spoon and the remaining bottles werefilled. ' ----- - ;
o Sample bottles were tightly capped, placed in coolers, and iced.Information concerning the sampling activities was recorded in thelog book, and the sites were photographed.
53 ------ ----- - :
flR30!383
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
A duplicate sample was collected at location FP-206, and matrix spike and matrix
spike duplicate samples were collected at FP-208 (See Drawing 1 and Figure 2).
A.12.1.2.3 Field Blanks
A field blank (FP-320) was produced at the northern drainage location (FP-
309). Volatile samples were first collected by pouring laboratory-supplied
volatile-free water into 40 ml volatile sample bottles. Second, laboratory-
supplied organic-free water was poured into amber sample bottles for semi-
volatiles, pesticides, and PCS analysis. Last, laboratory-supplied inorganic-
free water was poured into nalgene sample bottles for inorganic and cyanide
analysis. — - -
A.12.1.2.4 Equipment Blank __
An equipment blank was produced at the site trailer following sampling at
location FP-309 (where sediment sample FP-209 was also collected). The sample
was collected by pouring laboratory-supplied waters (listed in Section 2,3) into
the decontaminated stainless-steel beaker used at FP-209, and then into the
sample containers. Volatile samples were collected first, followed by other
organics, and then inorganics last.
A.12.1.2.5 Sample Handling Procedures
Sample handling procedures were in accordance with the SAP (Section 3.13).
All sample bottles were labeled prior to sample collection with the following
information:
o site project number
54
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Westinghouse Project No. 4112-88-908A 11 January 1990
o sample identification numbero date and time sample was collectedo sample sourceo preservatives usedo analysis required _ ' ; :o collector's initials
Samples were placed in iced coolers with additional ice added as needed.
A separate cooler was used to hold sample bottles for each sample location and
each matrix (sediment or water). Copiers were stored in the .site trailer prior
to transport to the laboratory. The coolers were sealed prior to transport with
chain-of-custody sample seals. Samples collected on May 30 and 31, 1989, were
transported to the contract laboratory by laboratory personnel on June 1, 1989.
Samples collected "on 'June "1 'and 2, 1989, were delivered to the contract
laboratory by Westinghouse personnel_pn June 2, 1989. All samples were handled
under established chain-of-custody procedures. Chain-of-custody forms are
presented in Appendix B.
A . 12.1.-2.6 Equipment Decontamination . . .
Equipment decontamination procedures were in accordance with the SAP
(Section 6). The stainless steel beaker and bowl were decontaminated prior to
sampling and between sampling locations according to the following procedure:
1, Wash with a liquanox solution2, Tap water rinse (Tap water was obtained at the Danville Goodyear Plant)3. Deionized water rinse4. Isopropyl alcohol rinse5. Deionized water rinse6, Air dry7. Wrap in aluminum foil (shiny side out)
Stainless steel spoons were'used only once at each sample site. Aluminum foil
and'aluminum foil pans were used only once and then discarded.
55 A R 3 0 1 385
-
FPRQ Task 8.1 RI DRAFT - Appendix A Revision 0Uestinghouse Project No. 4112-88-908A 11 January 1990
Decontamination of equipment occurred in a designated decontamination area
which consisted of polyethylene sheeting laid out and constructed to collect
water in a sump at one end. Collected fluids were periodically pumped into
drums and stored in the onsite enclosure.
A. 12.1.2.7 Surf ace-Water Flow Measurements
This section presents the methods used to measure the surface-water fl