Page 1: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Florida Public Service Commission

2007 Hurricane Preparedness Briefing

May 23, 2007

Kissimmee Utility Authority

Ken DavisVice President Engineering & Operations

Page 2: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

KUA System Data

• Serves approximately 64,000 customers in Osceola County

• Distribution– 857 Miles of Distribution Lines

• 41 % Overhead• 59 % Underground

– 9 Substations– 47 Feeder Circuits– 15,000+ Poles (majority wood)

Page 3: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

KUA System Data

• Transmission–72 Miles of Transmission Lines

–230 kV and 69 kV

–63% of Poles Concrete or Steel

–37% Wood (will reduce to 27% by 2008)

Page 4: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

2004 Hurricane Experience

• Charley–100 % Customers Lost Power

• Frances–36 % of Customers Lost Power

• Jeanne–59 % of Customers Lost Power

Page 5: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Lessons Learned

• Hired James Lee Witt, Associates to Conduct Independent Assessment of Preparation for and Recovery From Storms

• Improve Communications with Customers During Restoration

• Can’t Rely Solely on Media for Communications

Page 6: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Lessons Learned

• Better Define Roles of All Employees

• Closer Coordination with EOC for Restoration Priorities

Page 7: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Hurricane Preparedness

Page 8: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Construction Standards

• Poles Designed to NESC Extreme Wind Loading–All New Construction

–Major Expansions or Relocation Projects

–Targeted Critical Structures

Page 9: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Construction Standards

• 27% of Wooden Transmission Poles to be Replaced with Steel and Concrete

• Redundant Circuits to All Hospitals with Automatic Transfer Scheme

Page 10: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Construction Standards

• Selected Overhead to Underground Conversions

• Underground Utilities Required in All New Subdivisions

Page 11: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

GIS/Outage Management

• All Transmission & Distribution Facilities Tracked in GIS

• Links to Outage Management System

• Tracks Outages Down to Individual Customer Level

Page 12: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Vegetation Management

• Transmission Circuits–Inspected/Trimmed Annually

• Distribution –Three Year Trim Cycle

• Increased funding over 75% Since 2004

Page 13: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Pole Inspection Program

• All Wood Transmission Poles Inspected Every Two Years

• Wood Distribution Poles Inspected on Eight Year Cycle

Page 14: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Facility Inspection Program

• Transmission System –Annual Visual Inspections –Annual Infrared Scanning

• Distribution System –5 Year Cycle on Inspections–Infrared Scans of All Circuits

Annually

Page 15: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Emergency Operations Plan

• All Hazards Approach

• Concentration on Hurricanes

• Reviewed and Updated Annually

• Follow National Incident Management System (NIMS)

Page 16: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Emergency Operations Plan

• All Employees Have Pre-assigned Roles

• Defined Set of Activities for Each Phase of Storm Preparation, Response and Recovery

• Pre-Defined List of Priority Facilities

Page 17: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Emergency Operations Plan

• Pre-Assigned Damage Assessment Teams –Circuits Pre-Assigned

–Area Coordinators for Teams

• Developing Electronic Reporting of Damage Assessment

Page 18: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Emergency Operations Plan

• Pre-Defined List of Restoration Priorities–Typical Top Priorities – Evacuation

Shelters, Emergency Operations Centers, Hospitals, etc.

–Priorities Can be Changed by Directive from EOC

Page 19: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Annual Mock Disaster Drill

• Full Scale Drill Practiced Annually (April 12, 2007)

• All Employees Participate • Evaluation Teams Rate Performance• Post Drill Evaluation Conducted• Action Items – Changes to

Processes, Facilities, Plan

Page 20: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Storm Response and Recovery

• Crews Assigned to Ride Out Storm at Selected Fire Stations–Assist First Responders with Wires

Down Situations

–Assist with Fire Calls for Power Disconnects

Page 21: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Storm Response and Recovery

• Personnel Assigned to EOC at All Times

• Regular Status Updates Given to EOC

• Close Coordination with EOC for Restoration Priorities

Page 22: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Storm Response and Recovery

• Mutual Aid Agreements– Florida Municipal Electric Association

(Florida Municipal Utilities)– American Public Power Associations

(National Municipal Electric Utilities)– Florida Coordinating Group (Florida

Municipal, Investor Owned and Cooperative Utilities)

Page 23: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Storm Response and Recovery

• Pre-Arranged Agreements– Transmission and Distribution Line

Contractors– Outside Engineering (damage

assessment and construction management)

– Vegetation Management (Tree Clearing)– Lodging, Catering, Laundry, etc.

Page 24: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

Customer Communications

• Call Centers Fully Staffed 24/7 Throughout Recovery Process

• Provide Status Updates to Customers – Emails – Voice Mails or Text Messages– Physically Place “Door Hangers”

Page 25: Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &

QUESTIONS?