flood management programme (fmp)ecostatjk.nic.in/ecosurvey/evaluation report on fmp jammu.pdf · 3....
TRANSCRIPT
Government of Jammu & Kashmir
Physical Verification-cum-Evaluation Report
on
Flood Management Programme (FMP) Jammu Division (2008-09 to 2011-12)
Crate Revetment on river Chenab at Narsinghpura Earth Embankment on river Tawi at Ganeshuchak
Stud at River Tawi at Bhagwati Nagar Gap at River Tawi at Sampuranpur Kullian
Regional Joint Director, Evaluation & Statistics, Jammu Directorate of Economics and Statistics, J&K
Planning and Development Department
Highlights of the study
1. The Flood Management Programme (FMP) is a centrally sponsored scheme launched with the objective of providing relief from floods by executing Flood protection works, anti-erosion works and improvement in drainages of the rivers/nallahs.
2. Under the Scheme, eight Flood Management Projects have been undertaken in Jammu Province. Two Projects were started during 2007-08 and remaining 6 Projects were started during 2008-09. As per the guidelines, FMP works were expected to be completed in a time bound manner, but none of the projects have been completed so far and all the projects are still in progress. This results in cost escalation and further burden to exchequer.
3. Out of 8 projects, 2 FMP projects where the maximum amount had been incurred, i.e. FMP of Master plan on River Tawi and FMP of Master Plan on River Chenab were selected for evaluation study. The project works on River Tawi were executed by Flood Control Division Jammu and on River Chenab were executed by Flood control Division Akhnoor.
4. Approximately 12930 mtrs. of Earth embankment, 17590 mtrs Crate Revetment and 105 studs/spurs were physically verified in both the sample projects. 90% Earth embankment executed were found intact and in good condition. The remaining 10% were damaged in both the sample projects. Likewsie 75% of crate revetment were found intact and in good condition and 25% were Partially damaged. In both the sample projects, 69% of studs/spurs were found intact and in good condition and 31% were found partially damaged.
5. The sites were found genuine and works were apparently seen on ground. It was very difficult for the investigating team to locate the works executed by the executing agency in both the sample projects as the team found that there were some other embankments also created under other schemes/projects.. None of the sites had any sign boards or hoardings and practically it was impossible for the investigating team to locate and identify the works executed without the company of the field functionaries of the Executing Agency.
6. During the course of evaluation/verification, it was also observed in master plan Tawi, that the department has left some patches of land endangering the villages namely Chak Desa Singh,Wazirachak, Tope, Lakshampura, Sumb, Sampuranpur Kullian, Indru De kothey and adjoining villages. During the course of field enquiry, two crusher sites were also found where no revetment was constructed and there is an apprehension of water entering into the
villages. Similarly, in Master Plan Chenab, certain gaps of revetments at NS pura, Pangali and Chanjwan were also left behind which may endanger the villages during floods. It is, therefore, suggested that such things must be avoided as they cause heavy loss to the community as a whole. When a gap is left in embankment/revetment, it allows the water to enter into the villages thereby causing flood like situations and thus the whole purpose of creating embankment/revetments at such sites becomes meaningless and non beneficial.
7. In both the sample projects of selected sites about 4850 kanals of irrigated land and 400 kanals of un irrigated land was protected from erosion. Besides this, approx. a total of 6900 kanals of irrigated and 1050 kanals of un-irrigated land was also protected from submergence in the sample area. The department has done commendable job in protecting the irrigated and un-irrigated land from floods and converting such land for agricultural use to help the people to earn their livelihood. Land protected at newly constructed bridge at River Tawi is an example of land protection works being done by the Executing Department.
8. A total of 12 school buildings, 08 Govt. and public buildings and 07 temples were protected in the sample area. Shamshan Ghat at Bhagwati nagar, Bapu Asa Ram Ashram and Yatri Bhawan at Bhagwati nagar , pumping station at Sikanderpur were prominent buildings being protected under the project works. So far as protection to private assets is concerned, it has been observed that wherever the work has been executed, the whole village has been protected. The impact of such protection work has also been felt in the adjoining villages. Approx. 1200 houses which are situated on banks of both the rivers, 30 shops and 13200 kanals of private land were also protected through creation of revetments, embankments and studs/Spurs.
9. In order to have an assessment of the effect and impact of various activities implemented in the project areas, enquiries were made from 60 Knowledgeable Persons from 20 nearby villages of the selected sites. 3 Knowledgeable Persons from each of the selected sites as proposed in the sample design of the study were asked to express their views in respect of various components of the project and implementation process of the scheme as observed by them in their areas. The knowledgeable persons also include Panches and Sarpanches of the concerned area. The views of such people help in construing the exact picture of work being executed by the Department.
10. 100% of Knowledgeable Persons asserted that the sites selected for execution of FPW were feasible and appropriate. In all the selected sites of both the projects, 100% works were executed. So far as nature of works is concerned, these included Erosion Control Works, Submergence Works and Flood Protection works.
11. Out of 60 Knowledgeable Persons from both the sample projects, only 38% were of the view that quality of works executed was good, 57% rated them as average and only 5% opined the quality of works executed as poor.
12. 83% of Knowledgeable Persons were of the view that works were executed with the consultation of local people. 75% of Knowledgeable Persons asserted that local people were engaged in FPWs as labourers, 85% were satisfied with the works executed by the Department, 50% asserted that they have approached to the department for the execution of works in their areas and 100% believed that the works executed were beneficial for both individual and community as a whole.
13. No doubt, the Department has done a great job in preventing villages from floods, yet as revealed by certain Knowledgeable Persons that in some areas the height of embankments was too low to protect occasional huge floods. They suggested that the gaps left during execution be filled-in immediately and the repairs done on periodical basis so that embankments, revetments and studs/spurs are protected from damage . Further-more, it was also revealed by the Knowledgeable Persons during the course of physical verification that standard crate boxes were not installed which needs to be looked into.
14. Various types of assets created have got damaged in the normal course at the hands of men, Tractor trolleys and from natural factors. Repairs and maintenance of assets be provided, otherwise the assets will be damaged/washed away. The people must be made aware by organizing awareness campaigns in the project areas so that people could understand the scope and utility of these assets and work for their safety, maintenance and protection.
15. There was no provision of maintenance of assets in the projects undertaken as per the guidelines. As such, the creation of assets out of public money has no use unless some maintenance mechanism is there. As such, it is suggested that there should be a provision of maintenance of assets in the projects or it should be maintained through other schemes like MGNREGA.
16. It was observed that no plantations were made along the earth embankments. The planting of trees/plants holds the land intact and protects the soil erosion. The Department must look into this aspect and plantation must be done at both the banks of the rivers as it can lessen future expenditures on repairs and maintenance.
17. During the course of physical verification it was observed that tractors trolleys while extracting sand, stones and other materials from the rivers cause damage to the studs/spurs and embankments. This must be stopped particularly at vulnerable spots. The extraction of material at some spots may prove fruitful
where it could be allowed/encouraged. As such the Flood Control Department should classify the spots where extraction could be allowed and those where it should be strictly dis-allowed. This way the assets would be protected and also smooth flow of rivers could also be ensured.
Contents
Chapter No Description of Chapter Page No’s
I Introduction 1 – 5 II Financial/Physical Progress 6 – 16 III Field Findings 17 – 33 IV Summary of Main Findings 34 - 40 & suggestions Annexure Schedules 41 – 49
Photographs 49
____________ ____________________________________ _________
Chapter-1
Introduction
Background:
Devastation by floods is a recurrent annual phenomenon in India.
Almost every year, some or other part of the country is affected by floods.
Floods cause enormous damage to life, property-public and private and
disruptions to infrastructure, besides psychological and emotional
instability amongst the people. Rashtriya Barh Ayog (RBA) had estimated in
1980, total flood prone area in the country as 40 million hectares which was
revised further to 45.6 million hectares by the Working Group on Flood
Management set up by the Planning Commission for the 11th Five year Plan,
based upon the information furnished by the State Governments.
Many areas of the country are very vulnerable to floods and there is
great risk of damage to National Assets like highways, roads, railway tracks
etc. apart from damages to life and property. All these aspects were given due
consideration and addressed appropriately by the Govt. of India during the
10th plan and in consequence, the following schemes were sanctioned to
provide central assistance to flood prone states to take up flood control and
river management works in critical areas:
1) Critical Anti-Erosion works in Ganga Basin States (Centrally Sponsored
Scheme),
2) Critical Flood Control and Anti Erosion Scheme in Brahmaputra and
Barrack valley States (State Sector Scheme),
3) Implementation in Drainage in critical areas in the country ( State
Sector
Scheme)
4) Critical Anti Erosion in Coastal and other than Ganga Basin States
(State Sector Scheme)
The above schemes were merged together and a restructured scheme,
namely, “Flood Management Programme” under State Sector in Central Plan
was approved in principle, for 11th five year plan.
Scope/Coverage/Objectives of the Programme:
Under this scheme, critical flood control and River Management works
in the entire country are covered. These works include river management,
flood control, anti erosion, drainage development, anti sea erosion, flood
proofing works besides flood prone area development programme in critical
regions. It also includes restoration of damaged flood control/management
works.
Funding Pattern:
The funding pattern for central assistance to Special Category States
is 90% central share and 10% State Share, while as of other states it is 75%
central share and 25% state share. The Special category states cover North
Eastern States, Sikkim, Himachal Pradesh, Jammu and Kashmir and
Uttarakhand.
Implementing Agency:
As per guidelines of the scheme, the programme is generally
implemented by Flood control/ Water Resources/Irrigation Departments of
the State Government. In exceptional and emergent cases, the work could be
entrusted to Central Govt. organizations/ undertakings with the approval of
Central Ministry of Water Resources.
In Jammu and Kashmir State, the scheme is being implemented
through Department of Irrigation and Flood Control.
Conceptualization of the study:-
In order to assess the effectiveness of the programme, the State Level
Evaluation Committee (SLEC) in its meeting held on 25-11-2011 decided to
conduct the evaluation study on ‘Flood Management Programme’ through
Directorate of Economics and Statistics during the year 2011-12. Since the
study was sanctioned at the fag end of the financial year 2011-12, the
Directorate of Economics and Statistics decided to conduct it during the
financial year 2012-13 in order to operationalise the field work effectively.
Objectives of the Study :
The study was conceived with the following objectives:
1. To assess the Physical and Financial progress of the projects under
the programme;
2. To ascertain to which extent target group of the population stood
benefitted ;
3. To assess the level of satisfaction of target group of the population
through the implementation of Flood Management Programme;
4. To physically verify and ascertain the feasibility / genuineness of soil
erosion/ Flood protection works with special reference to outcome of
works executed.
5. To assess the bottlenecks/difficulties faced, if any, during the
execution of works and suggestion of corrective measures to be taken
to explore better implementation of projects.
Source of the Data:
The official data was collected from the project authorities’ viz. Chief
Engineer/Executive Engineer, Irrigation and Flood Control, Jammu. For the
primary data, a detailed field survey was conducted to obtain information
about the assessment of the impact and effect of the programme through;
I. Physical verification of the works executed,
II. Interview of Knowledgeable Persons.
For the purpose of collection of primary and secondary data, a set of three
schedules, one for obtaining official information and remaining two for
obtaining primary data from the field were designed for the study as detailed
below:
1. Schedule for Official Data Schedule I, II and III
2. Schedule for Physical Verification Schedule IV
3. Schedule for Knowledgeable Persons Schedule V
Sample size and procedure:
There were 08 Flood Management Projects undertaken in the
Jammu Division. None of the projects was completed and all were still in
progress by the end of March, 2012. At the Ist stage, out of 08 Flood
Management Projects(FMPs) undertaken, 02 FMPs were selected, where the
maximum amount was incurred up to ending March, 2012 for instant
evaluation study. These projects were Master Plan for FPW (Flood Protection
Works) on river Tawi and Master Plan for FPW on river Chenab. At the IInd
stage, 50% of the sites where the works were executed were selected
covering thereby Soil Erosion Control Works/Flood Protection Works. At the
IIIrd stage, 3 knowledgeable persons were interviewed from each verified
spot to elicit their opinion about the implementation and effectiveness of
the programme.
Reference Period:
The reference period pertained to whole of the project implementation
period i.e.2008-09 to 2011-12.
Field Work and Tabulation:
The field work was conducted by the staff of Regional Joint Director,
Evaluation and Statistics, Jammu under her overall supervision and control.
Scrutiny and Tabulation of data:
The scrutiny and tabulation of data was done by the staff of Regional
Joint Director, Evaluation and Statistics, Jammu.
Report Writing:
The report writing was executed by Regional Joint Director,
Evaluation and Statistics, Jammu under the technical guidance and overall
supervision of Directorate of Economics and Statistics.
Analytical Tools:
The averages and other appropriate tools and techniques were applied
for analysis and drawing inferences from the data.
Chapter-1I
Physical and Financial Achievements:
Proper management of floods constitutes an important element in
National Development Activities. In order to protect human life, land and
property from flood fury in the country, the State governments had been
engaged in flood management works for the last 5 decades and a total of
18.22million hectares of area was provided a reasonable degree of protection
by the end of 10th Plan. The Working Group on Water Resources constituted
by Planning Commission had set a target to protect an additional area of
2.18 million hectares during the 11th Plan.
Government of India has also been assisting the flood prone states in
flood management and anti-erosion works for critical reaches, by providing
financial assistance to the state Governments through a number of
Centrally Sponsored Schemes.
In order to provide financial assistance to the State Governments for
undertaking Flood Management works in critical areas during the 11th Plan
period (2007-12), a state sector scheme, namely, “Flood Management
Programme” (FMP) was launched by Ministry of Water Resources under
Central Plan, at a total cost of Rs.8000 crores which was approved “in
principle” by the Cabinet in its meeting held on 01-11-2007.
In Jammu and Kashmir State, the scheme was also launched and,
accordingly, in Jammu Division, eight number of Flood Management
Programmes were undertaken by the Department of Irrigation and Flood
Control. All the projects were still in progress in March, 2012. As Jammu
and Kashmir State falls under special category states, the funding pattern is
90% central share and 10% state share.
The following are the activities that are covered under Flood Protection
Works (FPW) in Jammu division.
1. Earth Embankments:
These are man-made ridges of earth or stones which confines a waterway
alongside a road or railway line. It is a long artificial mound of stones on
earth, built to hold water back or to support a road or protect land
endangered due to floods. Further, these ridges are created on the banks
of the rivers on specific spots for protecting flood prone villages from
submerging under flood water.
Earth Embankment on FMP Tawi at Ganeshuchak
2. Crate Revetments: Crate Revetments are used to stabilize or constrain a
river. They are part of flood alleviation works in which stones are placed on
river banks to prevent erosion of natural material. These crate Revetments
form river banks and protect the adjoining villages and agricultural fields.
These artificial man made river banks also are very instrumental in stopping
Land erosion and erosion of natural river banks.
Crate Revetment on FMP Tawi at Gasitpur 3. Studs/Spurs:
The studs/ spurs are essentially anti-erosion wire created structures. The studs hold the embankment or the agriculture land from erosion, while the spurs help in deflecting the river flow. Moreover, Studs/Spurs force the water to change its direction i.e. it diverts the water to main stream which prevent the earth cutting of banks of the river.
Studs/Spur works on FMP Tawi at Seora
Table 2.0
Estimated Cost of Flood Management Projects in Jammu Division
The above table shows that there were eight number of Flood
Management Projects (PMP) undertaken in Jammu division. These included
FPW on river Tawi, river Chenab, river Ujh, FPW on major and minor nallah
in Rajouri, FPW at banganga, Dibber nallah at Chenani, left/Right banks at
river Tawi on Sidra Town and River Dera Baba Banda. Six projects were
started during the year 2008-09 and two projects namely FMP Project on
river Tawi and Chenab were started during the year 2007-08.
The total estimated cost of eight projects was Rs. 12674 lacs and the
funding pattern of all the projects was 90% central share i.e. Rs 11406.60
lacs and 10% state share i.e. Rs. 1267.40 lacs.
S No Name of the Flood Management Programme Year of Start Estimated Cost ( Rs. in lacs) State Share
Central Share
Total
1 2 3 4 5 6 1 Master Plan for FPW on River Tawi 2007-08 228.20 2053.80 2282.
00
2 Master Plan for FPW on River Chenab 2007-08 194.50 1750.50 1945.00
3 Flood Protection work at Ujh from Jakhole to Pandoria
2008-09 146.30 1316.70 1463.00
4 Flood Protection work on major/minor Nallahas in Rajouri
2008-09 139.10 1251.90 1391.00
5 FPW at Ban Ganga Shri Mata Vaishnoo Devi Ji 2008-09 113.90 1025.10 1139.00
6 FPW at Chanani to Dibber in Udhampur 2008-09 149.50 1345.50 1495.00
7 FPW on L/R bank of River Tawi at Sidera Town 2008-09 146.60 1319.40 1466.00
8 Critical A/E works on River Dera Baba Banda 2008-09 149.30 1343.70 1493.00
Total 1267.40 11406.60 12674.00
Table 2.1
Releases and Expenditure of Flood Management Projects in Jammu Division
Up to 31-12 2012
The table 2.1 read with 2.0 reveals that out of total state share of Rs.
1267.40 lacs, Rs. 1237.89 lacs were allocated under all the projects which
were fully utilized as on 31-3-2012 by the project authorities. Out of total
Central share of Rs. 11406.60 lacs an amount of Rs. 6980.90 i.e. 61% was
allocated under central share which was almost fully utilized. The balance
amount of Rs. 4425.70 lacs is still to be allocated from the central share.
The Department must ensure that all required formalities are fulfilled so
that the central share is got released at the earliest.
S NO
Name of FMP
Releases up to 31-03-2012 (Rs. In lacs) Expenditure up to 31-03-2012(Rs. In lacs)
State Share
Central Share
Total State Share
Central Share
Total
1 2 3 4 5 6 7 8 1 Master Plan for FPW on River
Tawi
228.20 1229.86 1458.06 228.20 1229.86 1458.06
2 Master Plan for FPW on River Chenab
194.50 1217.75 1412.25 194.50 1217.75 1412.25
3 Flood Protection work at Ujh from Jakhole to Pandoria
146.30 935.50 1081.80 146.30 935.50 1081.80
4 Flood Protection work on major/minor Nallahas in Rajouri
139.10 745.01 884.11 139.10 745.01 884.11
5 FPW at Ban Ganga Shri Mata Vaishnoo Devi Ji
113.87 625.05 738.92 113.87 625.05 738.92
6 FPW at Chenani to Dibber in Udhampur
120.03 450.00 570.03 120.03 450.00 570.03
7 FPW on L/R bank of River Tawi at Sidra Town
146.60 825.00 971.60 146.60 805.00 951.60
8 Critical A/E works on River Dera Baba Banda
149.29 952.73 1102.02 149.29 952.73 1102.02
TOTAL 1237.89 6980.90 8218.79 1237.89 6960.9 8198.79
Table 2.2
Financial Achievements made under Flood Management Programme
w.e.f. 2007-08 to 2011-12 in Jammu Division.
The above table exhibits that the total estimated cost of all the
projects sanctioned in Jammu Division was `.12674 lacs. Against this, only `.8218.79 lacs were released up to ending March, 2012. By the end of 2012, `.8198.79 lacs were utilized by the project authorities. It is pertinent to
mention that the state share was released almost in full where as the central
share is pending to the tune of `.4425.70 lacs. Out of eight projects, two
Projects where maximum funds were reportedly utilized were selected for the
purpose of evaluation auditing under the instant study. These projects were
Master Plan on FPW on River Tawi and Master Plan on FPW on River
Chenab. In Master Plan for FPW on River Tawi, `.1458.06 lacs and in Master
Plan for FPW on River Chenab, `. 1412.25 lacs had been utilized upto the
end of March, 2012.
S No Name of the Flood Management Programme
Year of Start Estimated Cost (`. In lacs)
Releases (`. In lacs)
Expenditure (`. In lacs)
1 2 3 4 5 6 1 Master Plan for FPW on River Tawi
2007-08 2282.00 1458.06 1458.06
2 Master Plan for FPW on River Chenab
2007-08 1945.00 1412.25 1412.25
3 Flood Protection work at Ujh from Jakhole to Pandoria
2008-09 1463.00 1081.80 1081.80
4 Flood Protection work on major/minor Nallahas in Rajouri
2008-09 1391.00 884.11 884.11
5 FPW at Ban Ganga Shri Mata Vaishnoo Devi Ji
2008-09 1139.00 738.92 738.92
6 FPW at Chanani to Dibber in Udhampur
2008-09 1495.00 570.03 570.03
7 FPW on L/R bank of River Tawi at Sidera Town
2008-09 1466.00 971.60 951.60
8 Critical A/E works on River Dera Baba Banda
2008-09 1493.00 1102.02 1102.02
Total
12674.00 8218.79 8198.79
%age 64.84 100
Table 2.3
Year-wise availability of funds and Expenditure of Sample Projects
w. e. f. 2008-09 to 2011-12
S No Name of the
Project
Year of start Availability (Rs. In lacs) Expenditure (Rs. In lacs) State Share
Central Share
Total State Share
Central Share
Total
1 2 3 4 5 6 7 8 9 1 FMP Tawi 2007-08 -- -- -- -- -- --
2008-09 110.00 125.00 235.00 110.00 125.00 235.00 2009-10 75.00 387.50 462.50 75.00 387.50 462.50 2010-11 43.20 170.63 213.83 43.20 170.63 213.83 2011-12 -- 546.73 546.73 -- 546.73 546.73
Total (A) 228.20 1229.86 1458.06 228.20 1229.86 1458.06 %age 100 2 FMP
Chenab 2007-08 -- -- -- -- -- --
2008-09 44.00 400.00 444.44 44.44 400.00 444.44 2009-10 117.78 250.00 367.78 117.78 250.00 367.78 2010-11 32.28 567.75 600.03 32.28 567.75 600.03 2011-12 -- -- -- -- -- --
Total (B) 194.50 1217.75 1412.25 194.50 1217.75 1412.25 %age 100 G Total (A+B) 422.70 2447.61 2870.31 422.70 2447.61 2870.31
2282
1945
1463
1391
1139
1495
1466
1493
1458
.06
1412
.25
1081
.8
884.
11
738.
92
570.
03
971.
6
1102
.0214
58.0
6
1412
.25
1081
.8
884.
11
738.
92
570.
03 951.
6
1102
.02
FPW on River Tawi
FPW on River Chenab
FPW on Ujh FPW on Nallahas in
Rajouri
FPW at Ban Ganga
FPW at Chanani
FPW on River Tawi at Sidera
Town
Critical A/E works on River
Dera Baba Banda
Financial Achievements made under Flood Management Programme in Jammu Division w.e.f. 2007-08 to 2011-12 (Rs. in lacs)
Estimated cost Releases Expenditure
The above table indicates the year wise releases and expenditure of
both the selected projects. 100% funds were utilized by the project
authorities against the releases of Rs. 1458.06 lacs and Rs 1412.25 lacs in
case of FMP on River Tawi and FMP on River Chenab respectively up to
ending March, 2012. It is pertinent to mention that during the year 2011-
12 in FMP on Chenab project, no releases and expenditure was made, which
hampered the completion of project works in time. Such slackness must be
avoided as these projects are time frame projects which must be completed
within stipulated time so that cost must not run over expenditure. The
implementing Department must complete all formalities which are required
for getting funds released from the Central Govt. At the same time, the
Central Govt. must also release the commited amount at the earliest and
should not hold back funds unnecessarily. This much needed coordinative
effort would pave way for timely completion of the projects without involving
any cost revision.
Table 2.4
Physical Achievements of Sample Projects
S No
FMP Villages Benefited
Population Benefited
Erosion Control
Submergence Protection to Assets
Tgt (No)
Ach. ( No)
Tgt(No) Ach.( No) Tgt (Hect)
Ach. ( Hect)
Tgt (Hect)
Ach. ( Hect)
Public Assets
Pvt. Assets
Tgt (no)
Ach .(no)
Tgt (no)
Ach. (no)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 1 Tawi 69 60 45000 40000 450 350 8000 6500 10 08 7000 5500 2 Chenab 21 21 150000 140000 80 75 5000 4500 10 09 5000 4500 Total
90 81 195000 180000 530 425 13000 11000 20 17 12000 10000
%age 90 92.30 80 67.8 85 83
The above table reveals about the physical achievements made by the
Department up to ending March, 2012. Out of total of 90 villages which were
to be covered under flood protection works, 90% had been covered. The total
population to be covered under both the sample projects was 195000 people
out of which 92.30% was covered by the end of 2011-12. In case of soil
erosion works, 530 hectts. of land was to be protected out of which 80% was
achieved. The target of land to be protected under submergence was 13000
ha out of which 11000 hectts of land was protected from being submerged
i.e. 67.85%.
In case of Assets Protection, against a target of 20 public assets to be
protected, there was 85% achievement. As against 12000 private assets to
be protected, 83% was achieved up to ending March, 2012 as reported by
the Implementing Agency.
Table 2.5
Activity Wise Physical Achievements of Sample Projects
S No Name Earth Embankment Crate Revetment Studs/spur Target
(In Mtrs) Ach.
(In Mtrs)
Target (In Mtrs)
Ach. (In Mtrs)
Target (In
nos.)
Ach. (In
nos.)
1 2 3 4 5 6 7 8 1 Tawi 32072 21010 32072 21010 89 108 2 Chenab 5485 2325 1789 11580 93 85 Total 37557 23335 33861 32590 182 193 %age 62.1 96.25 106
The above table indicates activity wise targets and achievements made
by the project authorities in sample projects. There were three types of
activities undertaken by the project authorities in the sample area, namely
earth embankments, crate revetments and stud/spur works. In case of
earth embankments in river Tawi, against the target of 32072 mtrs, 65.5%
i.e. 21010 mtrs, were achieved. In case of crate revetments, against a total
target of 32072 mtrs, nearly 65.5 % was achieved. In case of studs/spurs
works, against target of 89 studs/spurs, the project authorities had
constructed 108 studs/spurs.
In case of earth embankments in river Chenab, against the target of
5485 mtrs, 42.46% i.e. 2325 mtrs was the achievement. In case of crate
revetments, out of total target of 1789 mtrs, 647.29% i.e11580 mtrs was
achieved. In case of studs/spurs works, against target of 93 studs/spurs,
the project authorities had constructed 85 studs/spurs i.e. 91.4% was the
achievement.
Indeed the Flood Division Akhnoor has done a commendable job by
achieving 647.29% against target of 1789 mtrs of Crate revetments. It was
clarified by the Executing Agency that the works under crate Revetment were
taken-up keeping in view the priority, local condition and impact of floods
during the previous seasons, which altered the site conditions drastically by
way of making some other locations more vulnerable and alarming. This
necessitated altering the proposed works both in terms of specifications and
in terms of locations also.
Table 2.6
Activity Wise Financial Achievements and work done liability
S No
Activity FPW on River Tawi (`.. In lacs)
Work done Liabilty (`. in lacs)
FPW on River Chenab (`.. In lacs)
Work done Liabilty
Approved.Cost
Releases Exp. Approved Cost
Releases Exp.
1 2 3 4 5 6 7 8 9 10 2
Earth Embankment 1881.50
1182.30
1182.30
524.19
392.42
129.28
129.28
36.24
3
Crate Revetment 945.45
854.35
854.35
338.87
4
Stud/Spurs
332.56
265.83
265.83
34.77
547.26
428.62
428.62
97.77
5
others
68.07
10.00
10.00
--
59.87
--
--
--
Total
2282.13
1458.06
1458.06
558.96
1945.00
1412.24
1412.24
472.88
The above table reveals that in master plan Tawi, against the
approved cost of `.2282.12 lacs under all the three activities i.e. earth
embankment, crate revetments and studs/spurs, `.1458.06 lacs were
released which was fully utilized by the Executing Agency. The work done
liability as on 31st March, 2012 was `. 558.96 lacs as per the reports of the
Executing Agency.
In master plan Chenab, against the approved cost of `.1945 lacs
under three activities i.e. earth embankment, crate revetments and
studs/spurs, `.1412.24 lacs was released which was fully utilized by the
Executing Agency. It must be noted that Flood Division, Akhnoor had
installed 11580 Crate revetments against the target of just 1789 thereby
creating liability to the tune of `. 338.87 lacs. It is a matter of concern how
the Executing Agencies had exceeded the approved cost on this Component
of the Project. The total work done liability as on 31st March, 2012 was `. 472.88 lacs as reported by the Executing Agency.
Chapter-1II
Field Findings:
The Instant Evaluation Study was carried out by the Directorate of
Economics and Statistics at the behest of State Level Evaluation Committee
(SLEC) to study the impact of project activities in the project area. The Field
Findings are based on the observations & eye estimations of Evaluation
Teams, personal enquiry from the Knowledgeable Persons and the physical
verification of the assets created. The field findings can thus be categorized
into:-
I). Physical verification of the assets/Eye-estimation
II). Response of Knowledgeable Persons
I. Physical verification of the assets/Eye-estimation:
08 number of projects were taken up in Jammu Division under the
Flood Management Programme and were in progress by the end of March
2012. A total of 02 projects where maximum amount was utilized viz; FPW
on Master plan Tawi and FPW on Master plan Chenab were selected for the
purpose of current Evaluation Study.
There were three major activities taken up by the project authorities
viz; Earth Embankments, Crate Revetments and construction of
Studs/spurs to protect the project area from havoc of floods. In the
selected projects, 10 Sites from each of the sample project were selected
where Flood Protection Works were executed. The villages immediately
adjoining the sites were also selected for the purpose of getting
beneficiary/Knowledgeable persons feedback. Only those activities which
were under taken during reference period i.e. 2008-09 to 2011-12 were
considered. The number of sample selected and degree of response obtained
is indicated below:
Table 3.0
Activity Wise Sample Selection of the Selected Projects.
Sno Name of the Project
Earth Embankment Crate Revetments Studs/Spurs Achievement
(mtrs) Sample Selected (mtrs)
Achievement (mtrs)
Sample Selected (mtrs)
Achievement (Nos.)
Sample Selected
(Nos.)
1 2 3 4 5 6 7 8 1 Master plan Tawi
21010 11850 21010 11850 108 55
2 Master Plan Chenab
2325 1080 11580 5740 85 50
Total 23335 12930 32590 17590 193
105
%age 55.40 53.97 54.40
The above table reveals that the achievement of the Department for
both the projects was 23335 mtrs under Earth embankments, 32590mtrs
under Crate revetments and 193 Studs/spurs. The sample selected for the
instant evaluation study was 12930mtrs for earth embankments,17590mtrs
for crate revetments and 105 studs/spurs respectively i.e. more than 50% of
sample was selected keeping in view the ground situation of works
executed. As the field protection works were executed on the banks of
respective rivers on vulnerable spots, the sample procedure was adapted
accordingly. Instead of going for village selection, the approach of site
selection was deemed appropriate. For this purpose, the Projects were divived
into different sites and 50% of them were selected at random. The selection of
Knowledgeable Persons was made from the villages adjacent to the selected
sites. Thus practically, keeping in view the ground situation of executed
works, site selection approach was adopted instead of village selection
approach.
The below mentioned table provides details about the selection
of sites under both the sample projects.
Table 3.1
No. of Sample Selected Sites
Sno Name of the Project Total Sites covered under the project
Sites Selected Sample %
1 2 3 4 5 1 Master plan Tawi 20 10 50% 2 Master Plan Chenab 21 10 50% Total 41 20 50%
A total of 20 Sites were covered under master plan River Tawi and 21 under
master plan Chenab, out of which 10 Sites from each project were selected for the
purpose of Physical Verification. Thus a total of 20 sites were selected from both
the selected projects.
Table 3.2
Status of Works executed in the sample projects
Sno Name of the Project
Sample Sites
Physically verified
Whether work existed on Ground
Status of work Identified Site is genuine
Yes No Complete In Progress
Left Half way
Yes No
1 2 3 4 5 6 7 8 9 10 1 Master plan Tawi 10 10 0 10 0 0 10 0 2 Master Plan Chenab 10 10 0 10 0 0 10 0
Total 20 20 0 20 0 0 20 0
%age 100 0 100 0 0 100 0
Table 3.2 reveals that out of total of 20 selected Sites from both the projects, 100% of works executed were found existing on the ground as on day of verification. In both the projects, 100% of the selected works were completed and 100% of sites where the work had been executed were found genuine and feasible by the investigating team. It is pertinent to mention that although the sites were found genuine and works were apparently seen on the ground yet it was very difficult for the investigating team to locate the works executed by the executing agency in both the sample projects. None of the sites had any sign boards or hoardings without which practically it was very difficult for any investigating team to locate the works executed without being accompanied by the Executing Agency.
Table 3.3
Physical Status of Earth Embankments in sample projects
Sno Name of the Project
Sample Sites
Physically verified
Earth Embankments Condition of the Embankment Length (mtrs)
Width(mtrs) Height(ft) Intact Partially Damaged
Fully Damaged
1 2 3 4 5 6 7 8 9 1 Master plan
Tawi 10 11850 Base 20 ft
Top 10 ft 20 8 2 0
2 Master Plan Chenab
10 1080 Base 10 ft Top 7 ft
10 10 0 0
Total 20 12930 18 2 0
%age 90 10 0
Table 3.3 reveals that earth embankment was executed in both the
projects. In master plan Tawi project, 11850 mtrs of earth embankment
were physically verified from 10 selected village sites. The width of the
embankments of master plan Tawi was 20 ft at base and 10 ft at the top.
The height of the embankments was 20ft.
In master plan Chenab, 1080 mtrs of Earth embankment was
physically verified from 10 selected villages. The width of the embankments
of master plan Chenab was 10 ft at base and 7 ft at the top. The height of
the embankments was 10ft. 90% of earth embankments were found intact
and in good condition, leaving aside the paths made by tractors and trolleys
operators for their petty personal benefits which had damaged the assets at
some places.
During the course of physical verification it was observed by the
evaluation team that no name and nomenclature was present on the
embankments created causing thereby problems in locating and tracing the
embankments constructed under both the projects. The investigating team
found that there were other embankments which stood created under other
schemes/projects and identification of specific works was very difficult.
Earth Embankment and Revetment on River Tawi at Chak Sardar dessa Singh
Earth Embankment and Revetment on River Chenab at Chajwal
Table 3.4
Physical Status of Crate Revetments in sample projects
Sno Name of the Project
Sample Sites
Physically verified
Crate Revetments Condition of the Revetment Length (mtrs)
Width (No. of crates)
Height (ft)
Intact Partially Damaged
Fully Damaged
1 2 3 4 5 6 7 8 9 1 Master plan
Tawi 10 11850 Base 2 no crates
Top 1 crate 10 8 2 0
2 Master Plan Chenab
10
5740 Base 3 no crates Mid. 2 no. crates
Top 1 crate
15 7 3 0
Total 20 17590 15 5 0
%age 75 25 0
In master plan Tawi project, 11850 mtrs of crate revetment was physically
verified from 10 selected village sites. The width of the crate revetments was 02
crates at base and one crate at the top. The height of the crate revetments was 10
ft. Out of 10 sites of crate revetments, 08 were found in good condition and two
were partially damaged.
In master plan Chenab, 5740 mtrs of crate revetment was physically verified
from 10 selected village sites. The width of the crate revetments was 3 crates at
base and 2 crates at the middle and one crate at the top. The height of the crate
revetments was 15ft. Out of 10 sites of crate revetments, seven were found intact
and three were partially damaged.
Out of total of 20 sites of crate revetments in both the sample projects, 75%
were found intact and in good condition and 25% were partially damaged.
During the course of verification, again in case of crate revetments, it was
found that no name and nomenclature was there for locating and tracing the crate
revetments installed/constructed under the FMP Project. It was also observed in
master plan Tawi, that the Department had left some vulnerable patches of land
uncovered which could cause damage to the villages namely Chak Desa Singh,
Wazirachak, Tope, Lakshanpura, Sumb, Sampuranpur Kullian , Indru De kothey
etc. Two sites near the two Crushers were also found left uncovered inspite of being
vulnerable. The Evaluation Teams found that water was entering into the villages
from the spot but to benefit the Crusher owners, same were left endangering the
community. Similarly In Master Plan Chenab, certain gaps of revetments at NS
pura, Pangali and Chanjwan were also left uncovered causing thereby flood water
to enter into villages.
It is, therefore, suggested that such things must be avoided as it causes heavy loss to the
community as a whole as compared to petty gains to handful of people. When such type of gap is
left in revetments, it allows the water to enter into the villages, thereby, causing flood like
situations, land erosions, loss of movable and immovable property and ultimately huge loss to
mankind and thus the whole purpose of creating revetments at such sites becomes meaningless
and non beneficial.
Gap at River Tawi at Sampuranpur Kullian
Revetment at River Chenab at Malabela
Revetment at River Chenab at Chanjwan
Table 3.5
Physical Status of Studs/Spurs in sample projects
Sno
Name of the Project
Sample Sites
Physically
verified
Total Studs
constructed in
project area
No. of Studs
verified
Studs Condition of the Studs
Length (mtrs) Width (crates) Height
(feet) Intact Partially
Damaged Fully
Damaged
1 2 3 4 5 6 7 8 9 10 11 1 Master plan
Tawi 10 108 55 33---24
22---18 Base 5no. Mid 4no. Top 3no.
15 41 14 0
2 Master Plan Chenab
10
85 50
13---36 28---24 09---18
Base 5no. Mid 4no. Top 3no.
15 31 19 0
Total 20 193 105 72 33 0
%age 54 69 31 0
Table 3.5 reveals about the stud/spur works done by the Executing Agencies
in both the sample projects. In master plan Tawi, a total of 108 nos. of studs/spurs
were constructed out of which 55 were physically verified. Out of 55 no. of
studs/spurs physically verified, 33 nos. of studs/spurs were of 24 mtrs and 22
were of 18 mtrs in length and the height of all the studs/spurs was 15 ft. The width
of studs/spurs at base level was 5 crates, 4 crates at middle and 3 crates at the
top. Out of 55 studs/spurs at River Tawi, 41 were found intact and in good
condition and 14 were found partially damaged.
In master plan Chenab, a total of 85 nos. of studs/spurs were constructed
out of which 50 were physically verified. Out of 50 studs/spurs physically verified,
13 nos. were of 36mtrs, 28 nos. of studs/spurs were of 24 mtrs and 9 nos.
studs/spurs were of 18 mtrs in length. The height of all the studs was 15 ft. The
width of studs/spurs was 5 crates at base level, 4 crates at middle and 3 crates at
the top. Out of 50 studs/spurs physically verified at River Chenab, 31 were found
intact and 19 were partially damaged, i.e. 38% of studs/spurs were partially
damaged.
Out of total of 105 no. of studs/spurs physically verified, nearly 69% were
found intact and in good condition and 31% were partially damaged.
Studs/Spurs force the water to change its direction i.e. they divert the water to the main stream
which prevent the earth cutting of banks of the river and thus prove beneficial to protect both movable
and immovable property of the villagers. It is important to mention here that Irrigation and
Flood Control Div. Jammu had constructed 108 studs/spurs against the target of
89 on both the banks of the river Tawi.
Studs at River Tawi at Ganeshu Chak
Stud at River Chenab at Malpur
Stud at River Tawi at Bhagwati Nagar
Table 3.6
Population Benefitted and Land Protected from Erosion and Submergence in sample projects
Sno Name of the Project
Sample Sites
Physically
verified
Villages Benefitted
Population Benefitted
Land Erosion Protected (in Kanals)
Land protected from Submergence
(in Kanals) Irrigated Un-irrigated Irrigated Un-irrigated
1 2 3 5 6
7 8 9 10
1 Master plan Tawi
10 29 32200 1850 200 4400 800
2 Master Plan Chenab
10
21 48200 3050 200 2500 250
Total 20 50 80400 4850 400 6900 1050
While going for Physical verification of the selected sites, the Evaluation
Teams attempted, as per the stipulations of the study, to make an eye estimation of
the land protected from erosion and submergence as a result of the works executed
at each selected site. Besides this, assessment was also made in respect of the
villages who managed protection and the approximate population residing in these
villages. The aggregate figures showed that the Flood Protection Works at the
sample sites provided protection to 50 villages with a population of approximately
80400 souls. The Works executed at sample sites were able to protect 4850 kanals
of irrigated and 400 kanals of un-irrigated land from erosion. The land protected
from submergence was of the magnitude of 7950 kanals of which 6900 kanals was
of irrigated nature.
The department has done commendable job in protecting the irrigated and
un-irrigated land from floods and by converting such land for agricultural use
to help the people to earn their livelihood. Land being protected at newly
constructed bridge at River Tawi is an example of land protection works being
done by the executing department. The Flood Protection Works have no direct bearing on the increase in
productivity and production of crops. It aims at providing protection to the movable and immovable property including land
both of agricultural and non-agricultural nature. It would not be feasible to attribute any increase in the production and
productivity of crops to the Flood Control measures undertaken in any Project area. However, whatever production and
productivity levels are there in the project area, the same were given protection as a result of project works executed under
Flood Control Programme.
Land Reclaimed at Bhagwati Nagar
Table 3.7
Public and Private Assets Protected in sample projects
Sno Sample Sites Physically verified
Sample selected
sites
Public Assets Private Assets Schools Buildings Temples Houses Shops Land(in
Kanals) 1 2 3 4 5 6 7 8 9 1 Master plan Tawi 10 5 6 5 500 30 7250 2 Master Plan
Chenab 10 7 2 2 700 0 6000
Total 20 12 8 7 1200 30 13250
Table 3.7 indicates that both the private and public property was
protected by the Department by undertaking FPW on both the projects. A
total of 12 school buildings, 08 Govt. and public buildings and 07 temples
were protected in the sample area. Shamshan Ghat at Bhagwati nagar,
Bapu Asa ram Ashram and Yatri Bhawan at Bhagwati nagar , pumping
station at Sikanderpur were prominent buildings protected under the
project. So far as protection to private assets is concerned, it has been
observed that wherever the works have been executed, the whole village has
been protected. The impact of such protection works has also been felt in the
adjoining villages. Approximately 1200 houses situated on both the banks of
the rivers were given protection from floods. Besides, 30 shops and 13250
kanals of private land was also being protected through the creation of
revetments, embankments and studs/spurs.
II .Response of the Knowledgeable Persons:
The Flood Protection Works are basically of Community Oriented
nature. A single Flood Protection Work may provide protection to different
assets of different people including houses, land, shops, schools, hospitals,
religious places, water supply lines etc. In such a situation, instead of
eliciting opinion from the beneficiaries of diverse nature, the observations of
the Evaluation Teams were deemed feasible and appropriate for assessing
the objectivity of the works executed. However, to have an assessment of the
immediate beneficiaries of the Project area, Knowledgeable Persons of the
area who incidently were the beneficiaries as well were tapped for the
purpose. The feedback of three Knowledgeable Persons from the adjacent
villages aggregating to 60 from the sample project sites was enough for
assessment of the efficiency and satisfaction parameters. They were asked to
express their views in respect of various components of the project and
implementation process of the scheme as observed by them, in their
respective areas.
Table 3.8
Sample selection of Knowledgeable Persons
Sno Name of the project Village sites covered
Sample selected per site
Total Sample selected
No. Responded %age responded
1 2 3 4 5 6 7 1 Master plan Tawi
10 3 30 30 100
2 Master Plan Chenab 10 3 30 30 100
Total 20 3 60 60 100
%age 100
A total of 30 Knowledgeable Persons were selected from each project
covering 3 from each selected site. 60 Knowledgeable Persons were
interviewed to elicit their views regarding the implementation of the
programme. The response of Knowledgeable Persons was 100%.
Status of Knowledgeable Persons:
Knowledgeable Person is considered as one who is well versed with the local
problems of the areas. The below mentioned table reveals the occupational status
of the Knowledgeable Persons.
Table No -3.9
Occupational Status of Knowledgeable Persons
S.
No
Name of sample project No. of
Knowledgeable Persons
Self
Employed
Agriculturists Salaried Labourers
1 2 3 4 5 6 7
1 Master plan Tawi 30 10 18 0 02
2 Master Plan Chenab 30 02 24 04 0
Total 60 12 42 04 02
%age 100 20 70 6.67 3.33
The above table shows that out of 60 Knowledgeable Persons, 20% were self
employed in non-agriculture activities, 70% were employed in agriculture sector,
6.67 % belongs to salaried class, and 3.33% were labourers. It is clearly evident
from the table itself that approximately 2/3rd of the sample Knowledgeable Persons
were directly engaged in Agriculture activities. The reason for taking such number
of Knowledgeable Persons from agriculture class is that they are the people who are
directly affected by havoc of floods. The knowledgeable person also includes Panchs
and Sarpanchs of the concerned areas and the views of such people help in
construing the exact picture of work being executed by the Department.
Table 3.10
Educational qualification of Knowledgeable Persons
Sno Name of the Project Sample Size
Education Qualification Beneficiary illiterate Primary Middle Matric 10+2 Graduate+
1 2 3 4 5 6 7 8 9 1 Master plan
Tawi 30 0 0 12 10 06 2
2 Master Plan Chenab
30 0 0 12 07 10 1
Total 60 0 0 24 17 16 3 %age 40 28.33 26.67 5
Table 3.10 reveals that out of 60 Knowledgeable Persons from both the
projects, 40% were middle pass, 28.33% were matriculate, 26.67% were 12th
pass and 5% were graduate and post graduate. The table clearly shows that
no Knowledgeable Person was illiterate, and thus all were able to
understand the ground realities as well as the impact of the various
activities being undertaken in their localities under the programme.
Table 3.11
Opinion of Knowledgeable Persons regarding works executed in sample projects
Sno Name of the project
Sample Site appropriate Status of work executed Nature of work Yes No Complete In Complete Erosion
works Submergence Flood Protection
works
1 2 3 4 5 6 7 8 9 10
1 Master plan Tawi
30 30 0 30 0 30 30 30
2 Master Plan Chenab
30 30 0 30 0 30 30 30
Total 60 60 0 60 0 30 30 60 %age 100 0 100 0 100 100 100
The above table reveals that in both the sample projects, 100% of
Knowledgeable Persons asserted that the sites selected for execution of FPW were
feasible and appropriate. In all the selected sites of both the projects, 100% works
have been executed. So far as nature of works is concerned, all the KP’s reported
that the works were either Erosion Control Works, Submergence Works or Flood
Protection works.
Table 3.12
Opinion of Knowledgeable Persons on Quality of work Executed in sample projects
Sno Name of the project Sample Quality of work executed Poor Average Good
1 2 3 4 5 6 1 Master plan Tawi 30 2 23 5 2 Master Plan Chenab 30 1 11 18 Total 60 3 34 23 %age 5 57 38
The above table shows that out of total of 60 Knowledgeable Persons from
both the sample projects, only 38% were of the view that quality of works executed
was good , 57% reported as average and 5% rated the quality as poor. The
Implementing Department must evolve all possible measures to ensure that
quality works are executed and no compromise on this account should be
tolerated. The supervision of each and every work by the middle level and
higher level supervisory officers must be ensured to pave way for
installation/construction of quality assets. The installation/construction of
below the standard Flood Protection Works could also be eliminated/
minimized by involving the PRIs and elected representatives in different
processes of the Programme. Maintaining the standard in the execution of
works, particularly incase of community oriented works is much desired in
view of them being exposed to all kinds of interventions. The views of
Knowledgeable Persons on the quality of works is much below the desired
levels and the Department is under obligation to order for the departmental
enquiry to establish the standardization of all the executed works under the
FMP and fix responsibility for any wrong doing. Further, to ensure that in
future the quality of works does not get compromised, all possible measures
must be put in place. The supervision of each executed work and involvement
of PRIs would definitely go a long way in improving the quality of works to a
great extent.
Earth Embankment and Revetment at River Tawi from Bhagwatinagar to Seora
Table 3.13
General opinion and views of Knowledgeable Persons
S no
Name of the project Sample Consulted with locals
Local People engaged
Satisfied with works executed
Approached for execution of works
Works beneficial
Yes No Yes No Yes No Yes No Community Individual 1 2 3 4 5 6 7 8 9 10 11 12 13 1 Master plan Tawi 30 24 6 20 10 26 4 20 10 30 0 2 Master Plan Chenab 30 26 4 25 05 25 5 10 20 30 0 Total 60 50 10 45 15 51 9 30 30 60 0
%age 83 17 75 25 85 15 50 50 100 0
The above table revealed about the level of satisfaction and general views of the Knowledgeable Persons towards the works executed by the project authorities. 83% of Knowledgeable Persons were of the view that works had been executed with the consultation of local people, 75% of Knowledgeable Persons asserted that local people were engaged in execution of works, 85% of Knowledgeable Persons were satisfied with the works executed by the department, 50% of Knowledgeable Persons asserted that they had approached to the department for the execution of works in their areas and 100% believed that the works executed under the programme were beneficial for both the individuals and the community as a whole.
No doubt, the Department has done a great job in preventing villages from floods, yet as revealed by certain Knowledgeable Persons that in some areas, the height of studs was below the requirements and there were also gaps which should be filled immediately. Further -more, the repairs must be done on periodical basis so that revetments and studs/spurs are protected. Besides, it was
also revealed to the evaluation team during the course of field enquiry by the Knowledgeable Persons that the standard crate boxes were not installed and they varied from site to site. The quality/standard of crate boxes was also observed poor at some sites. It is suggested that a standard size of crate boxes must be ensured to be used for undertaking such works and no compromise should be done on this account.
Chapter-1V
Summary of Findings and Suggestions
1. The programme, Flood Management Programme (FMP) is a Centrally
Sponsored Scheme, the funding pattern for central assistance to Special
Category States is 90% central share and 10% State Share, while as of
other states it is 75% central share and 25% state share. The Special
category states cover North Eastern States, Sikkim, Himachal Pradesh,
Jammu and Kashmir and Uttarakhand.
2. Eight Flood Management Projects were undertaken in Jammu Province. Two
Flood Management Projects were started during 2007-08 and remaining 06
Flood Management Projects were started during 2008-09. As per the
guidelines, FMP works were expected to be completed in a time bound
manner, but none of the projects had been completed by the end of 2011-
12.
3. The projects of FMP in J&K state are being executed by Department of
Irrigation and Flood Control with the objective of providing relief from
floods by executing Flood protection works, anti-erosion works and
improvement in drainages of the rivers/nallahs.
4. Out of 08 projects, 02 FMP projects where the maximum amount had been
incurred, i.e. FMP of Master plan on River Tawi and FMP of Master Plan on
River Chenab were selected for evaluation study. The project works on
River Tawi were executed by Flood Control Division, Jammu and on River
Chenab were executed by Flood Control Division, Akhnoor.
5. The total estimated cost of eight projects was `.12674 lacs out of which
90% was central share i.e. `.11406.60 lacs and 10% was state share i.e. `.1267.40 lacs.
6. Against the total estimated cost of `.12674lacs of all the projects, an
amount of `.8218.79 lacs, was released out of which `.8198.79lacs, was
utilized upto ending March, 2012.
7. The total availability of the funds of two sample projects w.e.f 2007-08 to
2011-12 was `.2870.31 lacs, up to March, 2012 which was fully utilized by
executing agencies, `.1458.06lacs incurred on Master Plan on River Tawi
and 1412.25lacs incurred on Master Plan on River Chenab.
8. On physical side, against the target of 37557 mtrs. of Earth embankment,
23335 mtrs was completed. Against the target of 33861 mtrs of crate
revetments, 32590 mtrs was completed and against the targets of 182
studs/spurs, 193 were constructed in the two sample projects.
9. The official data reveals that 81 villages with the population of 1.80 lacs.
in both the sample projects were benefited.
10. Since the works were executed on the banks of both the rivers, for selection
Purpose, the whole area of Master Plan Tawi and Chenab was divided into
sites where works were executed. A total of 41 sites were identified. Out of
41 sites, 10 sites from each project were selected for the purpose of
Physical Verification.
11. The sites were found genuine and works were apparently seen on ground.
It was very difficult for the investigating team to locate the works executed
by the executing agency in both the sample projects. None of the sites had
any sign boards or hoardings and practically it was impossible for any
investigating team to locate and identify the work executed without being
accompanied by the Executing Agency.
12. Approximately 12930 mtrs. of Earth embankment, 17590 mtrs crate
revetment and 105 studs/spurs were physically verified in both sample
projects. 90% Earth embankment works executed were found intact and in
good condition. The remaining 10% were damaged in both the sample
projects. Likewsie 75% of crate revetment works were found intact and in
good condition and 25% were partially damaged. In both sample projects,
69% of studs/spurs were found intact and in good condition and 31% were
found partially damaged.
13. No name and nomenclature was found on the site of embankments
created causing thereby problems in locating and tracing the embankments
constructed under both the projects as the team found that there were
some other embankments also created under other schemes/projects.
14. During the course of evaluation/verification, it was also observed in master
plan Tawi, that the Department had left some patches of land uncovered
endangering the villages namely Chak Desa Singh ,Wazirachak, Tope,
Lakshampura, Sumb, Sampuranpur Kullian, Indru De kothey and other
adjoining villages. During the course of field enquiry, two crusher sites
were also found where no revetments were constructed and there was an
apprehension of water entering into the villages. Similarly, in Master Plan
Chenab, certain gaps in revetments at NS pura, Pangali and Chanjwan
were also left behind which might endanger the villages during floods. It
is, therefore, suggested that such things must be avoided as it causes
heavy loss to the community as a whole. When a gap is left in
embankment/revetment, it allows the water to enter into the villages
thereby causing flood like situations and thus the whole purpose of
creating embankment/revetments at such sites becomes meaningless and
non beneficial.
15. In both the sample projects of selected sites about 4850 kanals of irrigated
land and 400 kanals of un irrigated land was protected from erosion.
Besides this, approx. a total of 6900 kanals of irrigated and 1050 kanals
of un-irrigated land was also protected from submergence in sample area.
The Department has done commendable job in protecting the irrigated and
un-irrigated land from floods and converting such land for agricultural use
to help the people to earn their livelihood. Land protected at newly
constructed bridge at River Tawi is an example of land protection works
being done by the Executing Department. The figures are purely based on
eye-estimation of Evaluation Teams made on the spot of sites.
16. A total of 12 school buildings, 08 Govt. and public buildings and 07
temples were protected in the sample area. Shamshan Ghat at Bhagwati
nagar, Bapu Asa Ram Ashram and Yatri Bhawan at Bhagwati nagar ,
pumping station at Sikanderpur were prominent buildings protected under
the project works. So far as protection to private assets is concerned, it
was observed that the work executed had protected the whole villages
which included houses, shops, commercial establishments etc. The impact
of such protection work was visible in the adjoining villages also.
Approximately 1200 houses which are situated on banks of both the rivers,
30 shops and 13200 kanals of private land were also protected through
creation of revetments, embankments and studs/Spurs.
17. In order to have an assessment of the effect and impact of various
activities implemented in the project areas, enquiries were made from 60
Knowledgeable Persons from 20 nearby villages of the selected sites. 3
Knowledgeable Persons from each of the selected sites as proposed in the
sample design of the study were asked to express their views in respect of
various components of the project and implementation process of the
scheme as observed by them in their areas.
18. 100% of Knowledgeable Persons asserted that the sites selected for
execution of FPW were feasible and appropriate. In all the selected sites of
both the projects, 100% works were executed. So far as nature of works is
concerned, these included Erosion Control Works, Submergence Works and
Flood Protection works.
19. Out of 60 Knowledgeable Persons from both the sample projects, only 38%
were of the view that quality of works executed was good, 57% rated them
as average and only 5% opined the quality of works executed as poor.
20. 83% of Knowledgeable Persons were of the view that works were executed
with the consultation of local people. 75% of Knowledgeable Persons
asserted that local people were engaged in FPWs as labourers, 85% were
satisfied with the works executed by the Department, 50% asserted that
they had approached the Department for the execution of works in their
areas and 100% believed that the works executed were beneficial for both
the individuals and the community as a whole.
21. No doubt, the department has done a great job in preventing villages from
floods, yet as revealed by certain Knowledgeable Persons that in some
areas the height of embankments was too low to protect occasional huge
floods. They suggested that the gaps left during execution be filled-in
immediately and the repairs be done on periodical basis so that
embankments, revetments and studs/spurs were protected. Further-more,
it was also revealed by the Knowledgeable Persons during the course of
physical verification that standard crate boxes were not installed which
needed to be looked into.
22. Various types of assets created have been got damaged in the normal
course at the hands of men, Tractor trolleys and from natural factors.
Repairs and maintenance of assets be provided, otherwise the assets
would be damaged/washed away. The people must be made aware by
organizing awareness campaigns in the project areas so that people could
understand the scope and utility of these assets and work for their safety,
maintenance and protection.
23. Although the provision of plantation was provided in the projects
guidelines, but to the contrary, it was observed that no plantations were
made along the earth embankments. The planting of trees/plants holds the
land intact and protects the soil erosion. The Department must look into
this aspect and plantation must be done at both the banks of the rivers as
it can lessen future expenditures on repairs and maintenance. Non
adherence of guidelines is a matter of serious concern and must be looked
into seriously by the Executing Agencies.
24. During the course of physical verification it was observed that tractors
trolleys while extracting sand, stones and other materials from the rivers
cause damage to the studs/spurs and embankments. This must be
stopped particularly at vulnerable spots. The extraction of material at some
spots may prove fruitful where it could be allowed/ encouraged. As such
the flood control Department should classify the spots where extraction
could be allowed and those where it should be strictly dis-allowed. This
way the assets would be protected besides ensuring smooth flow of rivers.
ANNEXURES
Evaluation Study on
“ Flood Management Programme” in Jammu Division.
Schedule-I (For official data)
Source-I. Chief Engineer Jammu
II.Ex. Engineer FC division concerned
Project Information
1.Name of Sample Project_________________________________________________
__________________________________________________________
2.Name of FC Div./I&FC Div.(Executing Agency)________________________________
3.Name of District________________________________________________________
4.Name of constituency___________________________________________________
5.Total No. of villages benefitted a) Target___________b) Achievement____________
6.Target group of population(souls) a) Target___________b) Achievement_________
7.Total land protected(Ha)
I. Erosion Control.
a) Target___________b) Achievement_________
II. Submergence
1 a) Target___________b) Achievement_________ III). Protection of Assets:-
a) Public Assets : Target___________ b) Achievement_________ b) Private Assets : Target___________ b) Achievement_________
8.Approved cost of the project(Rs. in lakhs)___________Revised cost(Rs. in lakhs)______
9.Year-wise Availability of funds/ Expenditure during the period(2008-12)(Rs. in lakhs)
S.No.
Year Outlay Actual Availability Expenditure
Reasons for shortfall in C/S S/S Total C/S S/S Total
availability
1 2 3 4 5 6 7 8 9
1 2008-09
2 2009-10
3 2010-11
4 2011-12
5 Total
10. Balance cost of the project yet to be released_______________________________
11. Work done liability if any as on 31.03.2012_________________________________
12.Cost overrun if any_____________________________________________________
13.Reasons for cost overrun_______________________________________________
14.Target date of completion______________________________________________
5.Actual date of completion_______________________________________________
16. Reasons for time overrun if any_________________________________________
17. Man days potential
Labour component Physical Progress Financial Progress
Target Achievement Allocation Expdt.
Skilled
Un –skilled
Total
Signature of the concerned HOD/ Xen.
Evaluation Study on
“ Flood Management Programme” in Jammu Division.
Schedule-II (For official data)
Source- Ex. Engineer FC division concerned
Workwise Information
1.Name of Sample Project_________________________________________________
__________________________________________________________
2.Name of FC Div./I&FC Div.(Executing Agency)_________________________________
3.Name of District________________________________________________________
4.Name of constituency___________________________________________________
5.Name of sample work___________________________________________________
___________________________________________________
6. Identification of sample work
i)Name of Nallah________________________________________________
ii) Name of village with actual site where executed_____________________
_____________________________________________________
_____________________________________________________
a) C.D Block________________________________________
b) Constituency_____________________________________
7.Estimated cost of work(Rs. in lakhs)________________________________________
8. Total Funds released ( Rs. in lakhs)_________________________________________
9.Cumulative expdt. Ending 31.03.2012_______________________________________
10.Balance cost if any______________________________________________________
11.Work done liability if any_________________________________________________
12. Year-wise breakup of Availability of Funds(Rs. in lakhs).
S.No. Year Availability of funds
Expenditure
During the year
Cumulative
expenditure
01 2008-09
02 2009-10
03 2010-11
04 2011-12
13.Date of start of sample work_______________________________________________
14.Target date of completion_________________________________________________
15.Actual date of completion_________________________________________________
16.If under progress expected date of completion________________________________
17.Reasons for cost overrun if any_____________________________________________
18. Reasons for time overrun if any__________________________________________
19.No. of villages benefitted
i) Target____________________
ii) Ach. _____________________
20..Population benefitted(Souls)
i) Target__________________
ii) Ach. ____________________
21. Nature of work (Tick relevant)
i) Erosion control
ii) Submergence
iii) Protection to assets(public/private)
22. Erosion Control
Land protected(Ha)
i) Target__________________
ii) Achievement_____________
23 . Submergence
Land protected(Ha)
i) Target__________________
ii) Achievement_____________
24.Protection to assets
i) Details of Public assets with location
a)_______________________________________________________
b)_______________________________________________________
c)_______________________________________________________
d)_______________________________________________________
ii) Details of Private assets with location
a)_______________________________________________________
b)_______________________________________________________
c)_______________________________________________________
d)_______________________________________________________
25.Man days potential
Labour component Physical Progress Financial Progress
Target Achievement Allocation Expdt.
Skilled
Un –skilled
Total
26. Item wise details of sample work
S. No. Item of work/components
Unit Approved cost
Expdt. Work done, liability if
any
Signature of the concerned Ex.Er.
Evaluation Study
on
“ Flood Management Programme” Jammu Division
Schedule-III (For official data)
Source --Ex. Engineer FC division
Project List of Works
1.Name of Sample Project_________________________________________________
_________________________________________________
2.Name of FC Div./I&FC Div.(Executing Agency)________________________________
3.Name of District________________________________________________________
4.Name of constituency___________________________________________________
5.Locational list of works.
S.No.
Name of Nallah
Name of village /habitation
Name of work
Actual location of site
Estimated cost
Cumulative expdt.
Date of start of work
Date of completion
Work done
liability if any
Nature of work
Erosion/submergence/
protection to assets
1 2 3 4 5 6 7 8 9 10
Signature of the concerned Ex. Engineer(FCD/I&FC)
Note: The detail of all the enlisted works be provided as per schedule II.
Evaluation Study
on
“Flood Management Programme”
Jammu Division
Schedule-IV (For physical
verification of sample works)
1.Name of Sample Project_________________________________________________
_________________________________________________
2.Name of FC Div./I&FC Div.(Executing Agency)________________________________
3.Name of District________________________________________________________
4.Name of constituency___________________________________________________
5.Name of village ________________________________________________________
6.Name of Nallah_________________________________________________________
7.Name of sample work ___________________________________________________
___________________________________________________
8. Name of actual site where sample work executed____________________________
____________________________
______________________________
9.Estmated cost (Rs. in lakhs)________________________________________________
10. Expdt. (Rs. in lakhs) ____________________________________________________
11.Physical status of sample work on ground
a) Work existing on ground (Yes/No)_______________________________
b) Complete/ Under progress/Left half way (Tick mark) ________________
c) Condition of work found intact/ Partially damaged/Fully damaged (Tick mark)
d)Identification of site feasible and genuine(Yes/No)________________________
e) Length__________Width_______Height____(In ft.)
f) Type of work( Cement concrete/Crate work/ Earth Embarkment/ Studs/Spurs/others(Specify ___________) [Tick mark]
g) Quality of work(Tick mark)
Good /Average/Poor
12.No. of villages benefitted
i) Target____________________
ii) Ach. _____________________
13.Population benefitted(Souls)
i ) Target____________________
ii) Ach. _____________________
14) Nature of work (Tick relevant)
i) Erosion control
ii) Submergence
iii) Protection to assets(public/private)
15). Erosion Control
i) Land protected(Kanals)
a) Irrigated_______________
b) un-irrigated_____________
c) others_________________
16) Submergence (Land protected(Kanals)
a) Irrigated_______________
b) un-irrigated_____________
c) others_________________
17.Protection to assets
i) Details of Public assets with location
a)______________________________________________________
b)______________________________________________________
c)______________________________________________________
d)_______________________________________________________
ii) Details of Private assets with location
a)_______________________________________________________
b)______________________________________________________
c)______________________________________________________
d)______________________________________________________
18) Views of verifying officer / official_________________________________________
_________________________________________
_________________________________________
Signature of the verifying officer/official Signature of supervisor
Name_______________________ Name_______________________
Desig._______________________ Desig.______________________
Date________________________
Date________________________
Evaluation Study
on
“Flood Management Programme”
Jammu Division
Schedule-V (For Knowledgeable person)
1.Name of Sample Project_________________________________________________
_________________________________________________
2.Name of FC Div./I&FC Div.(Executing Agency)________________________________
3.Name of District________________________________________________________
4.Name of constituency___________________________________________________
5.Name of village ________________________________________________________
6.Name of Nallah________________________________________________________
7.Name of sample work __________________________________________________
___________________________________________________
8. Name of actual site where sample work executed____________________________
_____________________________
9. Name of the knowledgeable person________________________________________
10.Parentage____________________________________________________________
11.Residential address
a) village____________________________________
b) Mohallah_________________________________
c) C.D. block_________________________________
12. Occupation status_____________________________________________________
13. Education status______________________________________________________
14. Opinion/ Views of knowledgeable person
a) Execution of work at identified site is feasible and genuine(Yes /No)
b) Executed work- Complete/Incomplete(Tick relevant)
c)Nature of work, Erosion control/Submergence/ Flood protection works(Protection to public/
private assets) [Tick relevant]
d) Quality of work – Average/Poor/Good [Tick relevant]
e) Erosion control,
i) Land protected (in kanals ). Irrigated________ Un-irrigated________
others___________
f) Submergence,
i) Land protected (in kanals ). Irrigated________ Un –irrigated________
Others_________
g) Flood protection works
Details of public/private assets protected
i) public assets _____________________________________
_____________________________________
_____________________________________
ii) Private assets_____________________________________
_____________________________________
__________________________________
h.Year of execution_________________________________________________
i.Year of completion________________________________________________
j. Executing agency_________________________________________________
k. Whether Cosultation done with locals before execution (Yes/No
l. Whether Engagement of labourers within the local area (Yes/ No)
m. Whether Satisfied over execution of sample work (Yes / No)
n. Whether Approached to executing agency for execution of sample work (Yes/No)
o . Whether Work executed is community benefited/ individual one(Tick mark)
p. Comments if any further____________________________________________
____________________________________________
____________________________________________
Signature/Thumb Impression of Knowledgeable person
Signature of the verifying officer/official Signature of supervisor
Name_______________________
Name_______________________
Desig._______________________
Desig.______________________
Date________________________
Date________________________
Earth Revetment and Crate revetment at Gasitpur
Stud/spur works on River Chenab at Pargwal