THE UNITED REPUBLIC OFTANZANIA
Ministry of Water, Construction,Energy, Lands and Environment,Zanzibar
THE REPUBLIC OFFINLAND
Ministry for Foreign Affairs
Department of Water Development
I 924 TZZA91 1Finnish International DevelopmentAgency FINNIDA
ZANZIBAR URBAN WATER SUPPLYDEVELOPMENT PROJECT
I Implementation Phase
1991 - 1994
Project DocumentJune 1991
IIIIIIIIIIIIIIIIIIIII
PROJECT FACT SHEET
Project Title:
Project Number:
Sector:
Subsector:
Project location:
Duration:
Starting date:
Project financing:
Competent authorities:
Implementing agency:
Executing agency:
Zanzibar Urban Water Supply Project,Implementation Phase I
282 095 02-2
Social Infrastructure
Urban Water Supply
The town of Zanzibar on Unguja islandand the towns of Chake Chake, Weteand Mkoani on Pemba island inZanzibar. Zanzibar forms part of theUnited Republic of Tanzania.
1991 -
January
FINNIDARGoZ
1994
1991
PIMFIM(TAS
50,2,
126,
000,520,000,
000000000)
TOTAL FIM 52,520,000
Ministry of Finance, Tanzania
Ministry for Foreign Affairs,Finland/FINNIDA
Ministry of Water, Construction,Energy, Lands and Environment of Zan-zibar
Plancenter Ltd, Finland
Department of Water Development,Zanzibar
Arrangements for Coordination of Project Implementation:
The Steering Committee will supervisethe implementation of the project.
LIBRARY, IN1F.RMATIONAL RE^ERB'Ch \o^ffKF- V-('•'< COMMiJNn.Y WAiilR SUPPLY \
\ AN;.; s,\i\2:;C9 AD
I d . K . i / 0 ; t>i 4 . n i : ; - x t . 1 4 1 / 1 4 ^
LO:
IIIIIIIIIIIIIIIIIIIII
CONTENTS
PROJECT PACT SHEET
ABBREVIATIONS AND CURRENCY EQUIVALENTS
MANAGEMENT SUMMARY Page
1 BACKGROUND AND JUSTIFICATION 1
1.1 Project area and population 11.2 Economic setting in Zanzibar
1.2.1 Institutional system 21.2.2 Social infrastructure 21.2.3 External assistance 21.2.4 Economic performance 2
1.3 Present situation in the sector 31.3.1 Urban water supply 31.3.2 Urban sanitation 71.3.3 Water resources 7
1.4 Project history 101.5 Justification of project 10
2 TARGET GROUPS/ ENVIRONMENTAL SETTINGS ANDINSTITUTIONAL FRAMEWORK 12
2.1 Target groups 122.2 Environmental settings 122.3 Institutional framework 14
3 OBJECTIVES AND INDICATORS 16
4 COMPONENTS, OUTPUTS AND OUTPUTSPECIFICATIONS 18
5 PROJECT STRATEGY 27
5.1 Overall strategy of the project 275.2 Approach to the implementation
of the work 285.3 Economic and institutional
development 285.4 Water supply development 315.5 Water resources and environmental
development 32
6 ACTIVITIES 33
7 INPUTS 38
7.1 Finnish inputs 387.2 Tanzanian inputs 39
I
IIIIIIII
iii
II
ABBREVIATIONS AND ACRONYMS
• DWD Department of Water Development
EIA Environmental Impact Assessment
| FIM Finnish Mark
FINNIDA Finnish International Development Agency
GoF Government of Finland
• GoT Government of Tanzania
HRD Human Resources Development
I MOF Ministry of Finance
IO&M Operation and Maintenance
B PIU Project Implementation Unit
• RGoZ Revolutionary Government of Zanzibar
TAS Tanzanian Shilling
I UWS Urban Water Supply
WSDP Water Supply Development Plan
MWCELE Ministry of Water, Construction, Energy,Lands and Environment
CURRENCY EQUIVALENTS (June 1991)
USD 1 = FIM 3.95
FIM 1 = TAS 0.019
IIIIIIIIIIIIIIIIIIIII
11
8
9
10
11
PROJECT BUDGET
ASSUMPTIONS AND EXTERNAL FACTORS
9.1 Financial and organizationalsustainability
9.2 Other external factors
PROJECT ORGANIZATION
REPORTING, MONITORING AND EVALUATION
11.1 Reporting systems and reports11.2 Monitoring11.3 Evaluation
FIGURES:
Figure 1.Figure 2.Figure 3/1
and 3/2
Figure 4/1Figure 4/2Figure 5/1.Figure 5/2.
ANNEXES:
Annex 1.
Annex 2.
Annex 3.
Annex 4.
Annex 5.
40
41
4142
43
44
444546
Map of ZanzibarGroundwater Development Areas of Unguja
Organization of the Ministry of Water,Construction, Energy, Lands andEnvironmentOrganization of DWD, UngujaOrganization of DWD, PembaProject OrganizationProject Implementation Unit
Project Analysis1/1 Problem analysis1/2 Community participa-
tion analysis1/3 Environmental analysis
Tentative Work Plan 1991
Staffing Plan 1991
Job Descriptions
Budget
IIIIIIIIIIIIIIIIIIIII
IV
MANAGEMENT SUMMARY
1. Project Background
The Government of the United Republic of Tanzaniahas requested FINNIDA to consider financing thefirst implementation phase 1991 - 1994 of theUrban Water Supply Project of Zanzibar, which isa part of the overall Zanzibar Urban Water SupplyProgramme.
The planning phase of the project took place in1989 - 1990 consisting of Financial Analysis,Institutional Study, Water Resources Study, Phy-sical Planning and Environmental Impact Assess-ment. These different components are compiled inthe Urban Water Supply Development Plan 1991-2015.
This project document gives a framework for theyears 1991 - 1994. More detailed work plans andbudgets will be prepared for each year separate-
2. Macroeconomic background of Zanzibar
The economy of Zanzibar is dominated by agricul-ture, principally the production of cloves. Dueto many economic setbacks over the last years,the governmental and parastatal bodies have haddifficulties generating sufficient revenue tomeet expenditure needs. To improve the situationthe Government commenced an economic recoveryprogramme in 1987. The main targets of the prog-ramme are reducing subsidies on imported food andstimulating home production, controlling govern-ment spending, and developing the private sector,especially concerning non-agricultural sectors aswell as liberalizing trade through the removal ofstate controls.
IIIIIIIIIIIIIIIIIIIII
3. Project justification
The present water supply system is comprised offour urban schemes, one in the town of Zanzibaron Unguja island and one in each town of Pembaisland (Wete, Chake Chake and Mkoani). The condi-tions of the schemes are poor and water qualityis bacteriologically unsatisfactory due to pollu-tion through unprotected intakes, broken pipesand unhygienic storage tanks. Distribution in-terruptions are common mainly due to power fai-lures, and service coverage inadequate due to aninsufficient quality of infrastructure and pooroperation and maintenance.
The inadequate water supply together with poorwaste water and solid waste disposal systemscause a severe health risk to the urban popula-tion.
The four towns accommodate one third (about230,000 people in 1990) of the whole populationof the Zanzibar islands. The urban population isestimated to be almost 340,000 by the year 2000and nearly 600,000 by the year 2015. This popula-tion development would lead to very densely popu-lated urban areas with large suburban fringeareas, which would mean enormous problems interms of space and employment especially in thetown of Zanzibar.
Successful urban water supply and sewerage deve-lopment will establish economic self-relianceamong the water organization and will also con-tribute significantly to the success of the na-tional economic recovery programme, facilitatingthe development of tourism and industry. Theproject will make it possible to meet the futureincreased demands of water, as well as increasingskills and awareness among authorities, officialsand the public. Water supply development willcontribute to the environmental health situationof Zanzibar.
IIIIIIIIIIIIIIIIIIIII
vi
Institutional framework
The Ministry of Water, Construction, Energy,Lands and Environment of Zanzibar has, throughthe Department of Water Development (DWD), fullresponsibility for the provision of water sup-plies in Zanzibar. The DWD is the sole nationalauthority for all water-related undertakings inthe two islands.
The Competent Authorities of the two Governmentsfor the implementation of the Project are theMinistry for Foreign Affairs of Finland, repre-sented in Finland by the Finnish InternationalDevelopment Agency, FINNIDA, and in Tanzania bythe Embassy of Finland in Dar es Salaam, and theMinistry of Finance of Tanzania. However, inmatters pertaining to the substance of the pro-ject and not affecting the overall respon-sibilities of the Government of Tanzania, theDepartment of Water Development in the Ministryof Water, Construction, Energy, Lands and Enviro-nment of Zanzibar has the right to represent theMinistry of Finance.
The other organizations of Zanzibar involved inproject implementation are the Municipal Councilof Zanzibar and the Town Councils of Pemba, theIrrigation Department of the Ministry of Agricul-ture, the Commission for Lands and Environment,the Institute of Marine Science of the Universityof Dar es Salaam, the Ministry of Health, theMinistry of Education, the Ministry of Trade andIndustry, and the State Fuel and PowerCorporation.
5. Objectives
The general development objective of the projectis that of providing its beneficiaries with safewater in a sustainable, cost-effective way withminimum environmental risks, and to provide waterauthorities institutional capability to effec-tively operate, manage and maintain the facili-ties.
IIIIIIIIIIIIIIIIIIIII
VII
The development objectives of each sub-projectare the following:
Economic and institutional development
To contribute to the development of a clear-cutpolicy and strategy for urban water supply andachievement of economic efficiency, as well as toimprove financial performance, institutionalcapacity, and the quality of human and materialresources of the organization in charge of watersupply. In addition, the involvement of consumersto water issues will be encouraged.
Water supply development
To establish adequate and safe urban watersupply systems appropriate to prevailing economicand functional conditions.
Water resources and environmental development
To guarantee the adequate share of waterresources for urban water supply and improve theenvironmental and health status of the Unguja andPemba islands by improving the water quality andto minimize any possible environmentaldeterioration due to project activities.
6. Project strategy
The first implementation phase 1991-1994 of theproject shall concentrate on financial, institu-tional, human resources, community participationand environmental development, as well as on theverification of groundwater development plans andthe development of preventive and correctivemaintenance systems. The main emphasis in thebeginning shall be on developing a tariff policyfor the water organization. The technical partof this phase of the project mainly consists ofthe most urgent repair works and the technicalplanning for the following phases.
IIIIIIIII
IIIIIIIII
viii
The project is divided into three sub-projects:(1) economic and institutional development, (2)water supply development and (3) water resourcesand environmental development.
The target of economic and institutional develop-ment is that of gradually developing economicallyself-reliant water organization which shall becapable of effectively managing, operating andmaintaining the water supply systems.
Providing urban water organization with the ne-cessary management authority, financial indepen-dence and legal basis for operation is the res-ponsibility of the political bodies and authori-ties of Zanzibar. The role of the project is tocontribute by participating in preparatory com-mittee work and drafting proposals and estimateswith local experts and officials. The decisionmaking responsibility lies with the Zanzibari au-thorities.
I Human resources development is part of institu-
tional development. It is a continuous processof assessing the shortcomings in manpower and
• organization.To solve the problems regarding the inadequacy of
I the contacts between the beneficiaries and water
authorities and the lack of knowledge about waterissues, the beneficiaries need to be informed,educated and motivated through an extensive com-munity education and participation programme.The implementation of the water supply develop-ment activities shall be based on revised waterpolicies and guidelines of the Government of Zan-zibar as well as on the action plan outlined inthe Urban Water Supply Development Plan 1991-2015. The construction and renovation programmesshall be devised in relation to the progress ofthe financial, institutional and human resourcesdevelopment components, subject to frequentreviews in connection with the annual work plans.
Water resources development, including drillingand monitoring activities and the establishmentof a coordinating system for ground waterutilization, shall be initiated already in theearly stages of the first implementation phase.
IIIIIIIIIIIIIIIIIIIII
ix
Development of the water quality and environmen-tal monitoring facilities and capabilities shallbe emphasized from the beginning of the firstimplementation phase and maintained throughoutthe project periods.
The preliminary environmental impact assessment(EIA) for the project was done during the plan-ning phase. The work shall be continued by car-rying out further EIA study during the rainy sea-son.
The capacities and facilities of the existing DWDwater laboratory established during the planningphase shall be extended during the first imple-mentation phase. Extensive water quality monito-ring programmes are to be prepared and implement-ed. Special studies on ground water pollutionshall also take place.
7. Inputs of the two Governments
Finnish input
The Finnish implementation agency will providespecialist advisors for the project. The Finnishlabor input will be strongest during the firstyear of the first implementation phase of theproject, and will be decreased over the followingyears.
The FINNIDA budget is FIM 50,000,000, and in-cludes the costs of Finnish staff, materials andequipment needed to support the implementingagency, materials and equipment required by DWDfor the project, and costs of construction con-tracts that will be awarded.
Tanzanian/Zanzibari input
It is essential for the success of the projectthat the Department of Water Development providethe necessary full-time specialists for theproject. These experts would form, together withthe staff of the Finnish implementing agency, theProject Implementation Unit, which will workwithin the DWD.
IIIIIIIIIIIIIIIIIIIII
A fixed budget amount shall be allocated for theProject in Tanzanian shillings for the procure-ment of spare parts and materials for upkeepingthe present service level. A spare parts andmaterials list is to be issued by the local waterauthority. These supplies will be used by thelocal organization. The local allocation is 10 %of the total budget, except for technical assis-tance costs.
The UWS office, workshop and store plot at Mablueand Madema in Zanzibar Town and laboratory plotwith ready made house in Saateni are to beprovided by the Government of Zanzibar, as wellas the premises needed in Pemba.Constructing/finalizing and equipping thebuildings will be done by the project after thenew UWS organization is approved.
8. Risks and assumptions
Zanzibar is going through a period of politicalchange and is also having to cope with repercus-sions arising from the Gulf Crisis. There is arisk that it will take some time yet before theimprovements proposed by the project are sus-tained by a viable organization. Both governmentand individual water users lack finances. Thetiming of the reintroduction of charges for do-mestic beneficiaries after a gap of over 15 yearsmay be critical.
Other factors which may delay the scheduledimplementation of the project include delays ininternational procurement; delays in transporta-tion of equipment due to difficulties in connec-tions between Dar es Salaam, Zanzibar and Pemba;temporary power failures, especially in Pemba;inadequacy of staff for training; non-availabili-ty of adequately skilled local contractors; anddelays in the progress of the sewerage and drain-age project of the Stone Town.
IIIIIIIIIIIIIIIIIIIII
1 BACKGROUND AND JUSTIFICATION
1.1 Project area and population
Zanzibar consists of two major islands, Unguja and Pem-ba, which were formed out of a large delta formation ofthe Ruvu River, emerging during the rift faulting ofcoastal East Africa. Unguja is separated from the Tan-zanian mainland by a shallow ocean floor approximately4 0 km wide, and Pemba by the 700 m deep Pemba Channel.The islands are located a few hundred kilometers southof the equator. Unguja and Pemba cover areas of 1660km2 and 984 km2 respectively (figure 1) . There are fourtowns on the islands, Zanzibar Town on Unguja and ChakeChake, Wete and Mkoani on Pemba.
The future population projections are in this documentbased on today's estimated population growth. The fol-lowing tables present figures for the two islands andseparately for the four towns which are the targetareas of the project.
Population projections for Unguja and Pemba:
1988 1990 2000 2015
Unguja 387428 413240 571800 936800
Pemba 265039 279000 360700 530100
ZanzibarGrand Total 652462 692240 935500 1466900
Population projections for the four towns:
Zanzibar Town
Chake Chake
Wete
Mkoani
1988
176231
13972
19196
7327
1990
190000
14380
20800
7400
2000
275300
20900
30000
9900
2015
483000
36500
54800
15600
IIIIIIIIIIIIIIIIIIIII
1.2. Economic setting in Zanzibar
1.2.1 Institutional system
Since 1964 Zanzibar has been an integral part of theUnited Republic of Tanzania, at the same time retainingconsiderable autonomy. Zanzibar has its own constitu-tion, president and government, giving the countryauthority over the legislative and executive affairs aswell as its economic policies.
The Revolutionary Government of Zanzibar has appliedsocialist principles to a centrally planned economy.There is almost total state ownership, including theownership of land.
1.2.2 Social infrastructure
The Arab and Indian communities, who earlier dominatedthe political and business life of Zanzibar, left thecountry after the revolution. This, combined with theambitious policies of free education, free housing andfree health care at a time of economic decline led to amajor breakdown of the infrastructure through a lack offunding and a lack of skills at all levels. Shortagesof teachers, doctors and engineers were particularlyacute. Schools are currently overcrowded, hospitalsare ill-equipped and understaffed, and housing andwater services are in a state of disrepair.
1.2.3 External assistance
The UN agencies, Finland and Denmark are major sourcesof external assistance and are at present fundingprograms in the health, agriculture, forestry, water,communication and education sectors.
1.2.4 Economic performance
Zanzibar's economy is dominated by agriculture, whichaccounts for between 50 % and 60 % of its G.N.P. Thisheavy dependence on agriculture becomes even more sig-nificant in light of the fact that the economy relieson its clove crop as the main source for foreign ex-change. Apart from cloves the remaining agriculturalactivity consists of subsistence farming.
IIIIIIIIIIIIIIIIIIIII
Overproduction of cloves in Indonesia has resulted inmajor drops in clove prices on the world market strik-ing a serious blow to the economy of Zanzibar. Infla-tion has soared and services have deteriorated evenmore rapidly. Consumer prices have risen at more than20 % per annum since 1982 with prices doubling between1987 and 1989.
The price of imports significantly affects domesticprices. The combined effect of rising import pricesand a major depreciation of the Tanzanian Shilling(from a mid-1987 eguivalent of TAS 65 to one USD, to anequivalent of TAS 190 to one USD at the end of 1990)are the cause of rapid increases in domestic prices.
All these factors have had a major impact on the finan-ces of the government and of administrative bodies,resulting in an inability to generate sufficientrevenue to cover expenditures. This in turn has led tothe lowering of wages in real terms, a severe cut-backin maintenance and in the growth of the public sectordebt on a massive scale.
Recognizing the seriousness of the situation thegovernment is continuing to pursue a comprehensive eco-nomic recovery programme first undertaken in 1987. Themain targets of this programme are:
1) to reduce subsidies on imported food andstimulate home production
2) to control government spending
3) to develop the private sector, especiallyregarding non agricultural area
4) to liberalize trade through the removal ofstate controls.
1.3 Present situation in the sector
1.3.1 Urban water supply
The present water supply system is comprised of foururban schemes: Zanzibar Town, Wete, Chake Chake andMkoani.
The existing urban water supply organization andmanpower is presented in figures 3/1, 3/2, 4/1 and 4/2.
Zanzibar Town
The scheme covers approximately 24 km2, 145 km ofpipeline ranging in diameter from 50 mm to 600 mm. Thepopulation served is 157,640 people (1988).
IIIIIIIIIIIIIIIIIIIII
Water sources
Urban Zanzibar gets its water supply from eight watersources (5 boreholes, 2 springs and 1 cave) with anaverage production of between 15,000 - 18,000 m3/day.None of the water sources are properly protected andthere is a high risk of pollution and contamination.Also, water is neither treated nor disinfected.
Water pipelines
The total length of high pressure network pipeline is132.5 km with diameters ranging from 50 mm to 450 mm.The low pressure mains located in limited areas of town(Bububu, Mtoni and Harbour) cover a 12.5 km length ofpipeline ranging from 150 mm to 600 mm (C.I.)-
Some portions of pipe network are in poor condition(old systems, lack of spare fittings, etc.) and needproper maintenance and replacement.
Storage facilities
The storage facilities include overhead pressed steeltanks, underground concrete tanks and on-ground steeltanks. Five tanks (3 underground, 2 overheads) locatedat the Saateni water works serve the town area pipenetwork and east distribution pipe network. Two tanks(1 underground, l on-ground) located at the Welezohigh-level zone serve the suburban area pipe network.The total storage capacity of the above tanks is 7820m3.
Most of the tanks are in bad condition (corroded andleaking), and need repair or replacement.
Saateni booster station
The station receives water from two spring sources (Bu-bubu and Mtoni) amounting to 5,000 - 13,000 m3/day. Itis made up of the following structures:
a) inlet house with weirs and chlorination basin,where water from Bububu and Mtoni springs iscollected
b) three underground concrete reservoirs, two ofthem being 1000 m3 and one 2250 m3
c) booster station equipped with the followingpumps:
1 electric driven pump 504 m3/h x 52 m2 electric driven pumps 225 m3/h x 63 m1 diesel driven pump 450 m3/h x 30 m
IIIIIIIII1IIIIIIIIIII
d) two overhead reservoirs of a volume of 4 50 meach.
e) two small workshop office buildings on locale.
Due to old age and poor conditions, the Saateni waterworks structure needs repair or replacement for utili-zation in the future.
Wete
The scheme covers approximately 10 km2, 2 0 km ofpipeline (diameter 50 mm - 200 mm). The populationserved is 30,000 people (1988).
Water sources
The town of Wete is served by three water sources (2springs and 1 borehole). The average production ofthese sources is 2100 m3/day - 2760 m3/day. None of thesources are properly protected. The pumping systemsand structural facilities are poor and need replacementor proper maintenance. No water sources have disin-fection facilities.
Pipelines
The high pressure pipe network is old and some portionsare in poor condition (due to a lack of spare fit-tings) . It must be properly repaired or replaced inorder to reduce leakage.
Storage facilities
The water tanks, which include one on-ground and twooverheads located at Mtemani, serve the town area pipenetwork distribution mains. The total storage capacityof these tanks is 52 0 m3. The tanks are in poor condi-tion (leaking and corroded) and need renovation.
Mtemani booster station
Mteraani booster station is made up of steel elevatedtanks and a booster station for pumping water intothem. The existing booster pumps are very old and inpoor condition. They should either be renovated orpreferably replaced by a direct high-pressure zonepumping out of one of the existing or future watersources.
IIIIIIIIIIIIIIIIIIIII
Water sources
The town of Mkoani is served by two water sources(boreholes). The average pumping of the sources is 320to 400 m3/day« The water sources are not properlyprotected. The condition of the sources is poor (sil-ting problem) and its pumping facilities are worn-outand need replacement.
Pipelines and storage facilities
The pipelines are in poor condition (leakage due to alack of spare parts). Only one overhead tank is lo-cated at Uweleni with a capacity of 180 m3. The tank isin fairly good condition and does not require majorrenovation. Additional storage facilities would beneeded at the same location in the future.
1.3.2 Urban sanitation
The waste water and solid waste disposal system of thetowns of Unguja and Pemba is at the moment poor, butsome improvement for the waste water disposal is to beseen with the Sewerage and Drainage Project. The pro-ject is planned to be started soon, but will con-centrate only on the area of the Zanzibar Stone Town.
At the moment, there are centralized sewerage systemsonly for some areas, such as the Stone Town and theKikvajuni Housing Scheme in Zanzibar. Even in theseplaces the sewers are often blocked due to poor main-tenance, misuse and sand brought in by tides. There-fore, although the waste waters are in principal dis-charged into the sea through various outlets to dif-ferent parts of the coast, the waste often does notreach the sea, but seeps into the ground thereby pol-luting the ground water. In the areas where the wastewaters have reached the sea, the coastal water has beenfound polluted and unsuitable for swimming in.
In the Zanzibar Stone Town 80 % of the population haveflush toilets with septic tanks and the rest have pitlatrines. There is, however, no easy access for trucksin the cleaning of the septic tanks, resulting in over-flow and contamination. In the suburban areas scat-tered around Zanzibar Town and in the towns of Pembapit latrines are mainly used. In those areas open airdefecation is also common.
1.3.3 Water resources
Groundwater is the only feasible alternative for meet-ing the water demands of the municipalities of Ungujaand Pemba. The ground water resources are also neededfor rural water supplies and for irrigation purposes.
IIIIIIIIIIIIIIIIIIIII
Based on the estimated daily water demand, the need forground water in urban areas will be as follows:
Unguj a:
low domestic
Zanzibar Town
by 1990 - 13000 m3/day
by 2000 - 27300 m3/day
by 2015 - 59500 m3/day
Pemba:
by 1990
by 2000
by 2015
Wete
1200
2600
6800
ChakeChake
800
1800
4100
Mkoani
400
800
1700
Pemba Totalm3/day
2400
5100
12600
The possibilities for drawing these quantities fromground water sources are discussed in the followingchapters.
Zanzibar:
The Bumbwi Corridor runs across Unguja Island fromnorth to south, passing a few kilometers east of Zan-zibar. It offers a feasible ground water developmentarea for drawing water for the town, up to anapproximate quantity of 70,000 m3/day.
Altogether 8,000 - 10,000 m3/day could eventually beobtained from Bububu Spring and Mtoni Spring, which arelocated just near the Zanzibar town center and there-fore would be very economical sources. Mtoni Spring,however, has some problems with water quality whichmust first be solved.
Another potential source could be the Kisima Mchangasub-corridor (20,000 m3/day), which lies at a distanceof about 15 - 25 km from Zanzibar. However, thisdistance may be a rather uneconomical pumping distance.Another potential source is the Koani-Kiongoni area, ata distance of 6 - 8 km, which could yield up to10,000 -20,000 m3/day.
IIIIIIIIIIIIIIIIIIIII
The feasibility of different alternatives is to be stu-died during 1991 - 1994, through test drilling and testpumping programs. The location of the proposedgroundwater development areas is presented in figure 2.
The planned intake areas are to be gazetted as areasrestricted for groundwater development for Zanzibartown. Possible excess water resources may be allocatedfor rural and irrigation use, to be decided upon by theproposed water board.
The water quality in the corridor areas is very goodfor domestic purposes. There is a theoretical chancefor sea water intrusion from the southern end of theBumbwi Corridor as the potentiometric gradient decrea-ses to only +2 m above the mean annual seawater level.However, the recently obtained test pumping resultsshow that large quantities of groundwater can be pumpedfrom this area without overly changing the water tableconditions.
Town of chake Chake:
Kwapweza Spring would offer a supply source of up to 50% of today's water demand for the Chake Chake area.Three to four test/production boreholes should be dril-led in the Kwapweza and Msingeni areas to determine theavailable additional ground water potential. Based onvery tentative estimates a total of about 1,000 m3/dayof groundwater could eventually be obtained from theKwapweza valley.
According to geoelectrical sounding results, highyielding boreholes - over 50-100 nr/hour - can be drill-ed in the Kiziwamaji area, about 4 km northeast ofKwapweza.
The valley in which the Jamvini C7 borehole is locatedis a continuation of the Kwapweza valley and offers thefirst alternative well-field location, with possibleyields of 3000 - 6000 m3/day.
The Changaraweni borehole valley could yield about 4000m3/day* This area requires careful monitoring and de-tailed study as there is a chance for sea water in-trusion. The water contains iron and must be treated.Changaraweni should not be considered a priority areain future well-field plans.
IIIIIIIIIIIIIIIIIIIII
10
1.4 Project history
The Rural Water Supply Plan was prepared by a Germanconsultant, during 1987 - 1990, based on African Deve-lopment Bank finance and under the coordination of theDepartment of Water Development.
FINNIDA and the United Republic of Tanzania signed anagreement in October 1989 on the preparation of an Ur-ban Water Supply Development Plan, covering the townsof Zanzibar, Chake Chake, Mkoani and Wete.
Project operations commenced in November 1989 asplanned. The expected time for completion of a draftUrban Water Supply Development Plan is by the end of1990. During the planning phase the following studieshave taken place:
Water Resources StudyInstitutional StudyHousehold SurveyPhysical Planning of Water SuppliesFinancial and Economic AnalysisPreliminary Environmental Impact As-sessment
The Government of the United Republic of Tanzania hasfurther requested FINNIDA to consider financing thefirst implementation phase, 1991 - 1994.
The KfW, a German development funding agency, hasagreed on financing preparation of the Urban Drainageand Sewerage Development Plan for Zanzibar, due tocommence in 1991.
The Government of Zanzibar has nominated a committeefor the preparation of a General Water Policy. The Ur-ban Water Supply Development Plan Project is represent-ed in the committee.
1.5 Justification of the project
The four towns accommodate one third (about 230,000 in1990) of the whole population of the Zanzibar Islands(Unguja and Pemba). Zanzibar has a population of176,000 and is the main commercial, industrial andtourism center of the islands. With today's growth ratethe urban population is estimated to be almost340,000 by the year 2000 and nearly 600,000 by the year2015. This population development would lead to verydensely populated urban areas with a large suburbanfringe area, which would mean enormous problems interms of space and employment, especially in Zanzibarproper.
Trade in spices, especially cloves, is traditionallythe main source of foreign income for the islands. The
IIIIIIIIIIIIIIIIIIIII
11
price of cloves has gone down, and the foreign exchangereserve of Zanzibar has decreased drastically. Theeconomy of the islands is undergoing a recoveryprogramme phase, seeking ways and means of saving andgenerating adequate foreign currency funds for the pro-curement of necessities such as spare parts, machinesand food products and for achieving self sufficiency,especially in agricultural production.
The present urban water supply schemes are supposed toserve about 200000 inhabitants at the moment. However,the conditions of the present water supply systems arepoor and water quality is bacteriologically unsatisfac-tory due to pollution through unprotected intakes,broken pipes and unhygienic storage tanks. Distribu-tion interruptions are common mainly due to shortagesof electricity, and service coverage inadequate due toan insufficient quality of infrastructure and poor ope-ration and maintenance. Ultimate reasons for all thiscan be found in an insufficient institutional set-up,poor financial performance and a lack of motivation andskills, as well as a lack of water policies and legis-lation.
The inadequate water supply together with the poorwaste water and solid waste disposal systems cause asevere health risk to the urban population, which isalso partly due to a poor level of knowledge aboutwater, sanitation and health issues among thebeneficiaries.
Successful urban water supply and sewerage developmentwill establish economic self-reliance among the waterauthorities and will also essentially contribute to thesuccess of the national economic recovery programme,facilitating the development of tourism and industry.It will make it possible to meet the future increaseddemands of water as well as increasing skills andawareness among authorities, officials and the public.Water supply development will contribute to theenvironmental health situation Zanzibar.
IIIIIIIIIIIIIIIIIIIII
12
2 TARGET GROUPS, ENVIRONMENTAL SETTINGS AND INSTITUTIONALFRAMEWORK
2.1 Target groups
The primary target groups of the Urban Water SupplyProject are the inhabitants of the four towns in Zan-zibar and the industries and other commercial usersserved by the supplies. These are the groups whichwill benefit from the improved water supply. Directproject assistance, however, is given to the waterauthorities in order to develop their capabilities ofimproving the water supply situation.
2.2 Environmental settings
The environment of the islands of Zanzibar is stillquite unspoiled but also very sensitive, and so thereare some risks to be taken into account in futuredevelopment activities.
From the environmental and health point of view the im-pacts of the water supply project are more beneficialthan adverse, and the project will assist in solvingsome of the problems already identified in Zanzibar.However, some negative impacts can also be foreseen ifproper care is not taken concerning the environmentalaspects.
Environmental issues related to around water quantity
As mentioned before, ground water reserves are the onlywater resource for urban and rural water supplies forboth Unguja and Pemba. These include boreholes,springs and caves. Ground water is also needed forrural water supplies. Shallow wells are very importanteven in urban areas for replacing the piped water supp-ly when there is no electricity (in Pemba about half ofthe time) or when there are some other problems in thefunctioning of the town supplies. Agriculture is a biguser of ground water for irrigation purposes.
At the moment the ground water reserves seem to begood. The remarkable increase in the use of groundwater for future town water supplies, together withother uses such as irrigation and a probable increasein the use of water due to the development of tourism,may cause some problems in the future. The possibleconsequent drop in the level of ground water will firstaffect the shallow wells, which obviously will dry up.
The possible salinization of ground water will beanother major problem regarding effective ground wateruse.
IIIIIIIIIIIIIIIIIIIII
13
Environmental issues related to ground water qualityand health
Most of the health problems in Zanzibar result from orare caused by poor living conditions. They are mainlyrelated to factors such as socio-economic status,climate, cultural practices, poverty, rapid growth ofpopulation and inadequate and unsanitary livingconditions, including the inadequate quality ofdrinking water and the poor personal hygiene habits.
Almost all the water intakes of urban water supplies inUnguja and Pemba were found to be bacteriologicallypolluted, and therefore also the whole network. Evenfecal pollution seems to take place. The sources areusually not covered or otherwise protected and there-fore any kind of pollution is possible- The pollutionmay also take place within the network due to leakagesof pipelines and unhygienic storage tanks. The shallowwells also appeared polluted. The microbiological pol-lution of drinking water can be considered the mostacute water related health problem for the public atthe moment.
Historically the ground water sources and water supplyof Zanzibar have had a very good reputation for clean-liness and good taste. According to the first resultsof the household survey done during the planning phaseof the project, the quality of the water of theZanzibar Town supply is also considered good.
In Zanzibar the soil is generally very permeable (dueto sand and coral) and therefore any waste materials orchemicals discharged into the ground without treatmentcan easily pollute the groundwater and thus create ahealth hazard.
In the future the increased amount of domestic wastewater due to expanded water supply systems may add tothe problem of poor waste water disposal andgroundwater pollution. This can be avoided by properplanning and coordination of the activities of theproject with the forthcoming sanitation project inStone Town of Zanzibar. The problem of sanitationoutside the Stone Town is still unsolved. It was notincluded in this project.
The physical and chemical quality of the ground wateris generally good. The intrusion of sea water into theground water could be a problem, but no alarmingresults have been found so far. One possible risk tothe quality of ground water is the pesticides and fer-tilizers used in agriculture, especially in rice cul-tivation, where evidently a lot of herbicides are usedto control weeds. In forestry activities chemicalsare used only in nurseries, which limits the problem toa few small areas. Evidently the level of chemical usein industry in Zanzibar is not high. However, there are
IIIIIIIIIIIIIIIIIIIII
14
some potential pollution risks - especially becausethere are no controls on the discharge of waste watersand waste matters.
Other environmental issues related to the project
The construction activities of the project may havesome indirect environmental impacts, such as landscapedegradation and beach erosion due to the use of graveland sand. Possible hazards to ground water due to con-struction activities should also be taken into account.Setting up open water storage places on constructionsites should also be avoided, as the sites can be bree-ding places for mosquitos. The project may add to theproblem of unplanned expansion by creating new job op-portunities. It may also promote tourism, which againhas its adverse effects on environment. These and otherpossible risks, which may seem small at this stage,should be considered throughout the implementation ofthe project. The awareness of possible environmentalrisks must be increased among the authorities andproject personnel.
2.3 Institutional framework
The Ministry of Water, Construction, Energy, Lands andEnvironment (MWCELE) has full responsibility, throughthe Department of Water Development (DWD), for theprovision of water supplies (see the organization,figures 3/1, 3/2, 4/1 and 4/2). DWD is the sole na-tional authority for all water-related undertakings onthe two islands, including the issuing of permits todrill boreholes for agricultural purposes.
In 1986 responsibility for the urban drainage and sewerfunctions was given to the local government, being nowunder the supervision of the Municipal Council ofZanzibar Town and the Town Councils in Pemba.
The Ministry of Health has on occasion undertaken theresponsibility of water quality monitoring, though noton a regular basis.
The Ministries of Finance and Planning approve andallocate the budget, and the Price Commission approvestaxes and rates. Since 1982 only commercial andindustrial consumers such as hotels, factories andships have been charged for water.
Other Ministries, Departments and Institutions of Zan-zibar which will be involved with or affected by theproject are as follows:
Cooperation with the Irrigation Department ofthe Ministry of Agriculture in the planning ofground water resources will be undertaken.
IIIIIIIIIIIIIIIIIIIII
15
The Commission for Lands and Environment, inparticular its Department of Environment,plays an important role in intersectoral co-operation on environmental issues, which theproject will also promote.
The Institute of Marine Science (in Zanzibar)of the University of Dar es Salaam is involvedin water quality control studies and otherenvironmental research. Plans for cooperationwith the project already exist.
Hygiene and health education activities of theproject will be implemented in conjunctionwith the Ministry of Health.
The Ministry of Education will be involved inplanning the training programs of the project,which will also affect the existing teacher'straining and school programs of the Ministry.
The Ministry of Trade and Industry will assistthe project in providing development forecastsfor industry and trade.
Functioning cooperation should exist with theState Fuel and Power Corporation to guaranteethe availability of their services.
IIIIIIIIIIIIIIIIIIIII
16
OBJECTIVES AND INDICATORS
The project has one general development objective, asdetermined in 1989 and stated in the project documentof the planning phase. In addition, each of the threesub-projects have their own long term development ob-jectives. All these objectives are to be graduallyachieved by the end of the planned deadline for theDevelopment Plan.
Each sub-project has various immediate objectives,which are to be achieved during the first implementa-tion phase 1991-1994. These immediate objectives withachievement indicators are presented in table 1.
The achievement of objectives will be followed up byusing indicators (table 1). This monitoring will bedone in the process of progress reporting, and will becomplied with ideas for revising the project plans whenthe indicators are not met.
The general development objective of the project is:
To provide beneficiaries with:
safe water in a sustainable, cost-effective way with a minimum of en-vironmental risks
and to provide water authorities with:
institutional capability toeffectively operate, manage and main-tain the facilities
The development objectives of each sub-project are thefollowing:
sub-project l: Economic and institutional development
Development objective:
To contribute to the development of a clear-cut policy and strategy for urban water supplyand achievement of economic efficiency, aswell as to improve financial performance, in-stitutional capacity, and the quality of humanand material resources of the organization incharge of water supply. In addition, theinvolvement of consumers to water issues willbe encouraged.
IIIIIIIIIIIIIIIIIIIII
17
Development indicators:
Existence of a new policy and strate-gy for a self-supporting urban watersupply organization.
Existence of a self-reliant urbanwater organization.
Water systems function without pro-blems related to an inadequate or-ganizational set up.
Sub-project 2: Water supply development
Development objective:
To establish adequate and safe urban watersupply systems appropriate to the prevailingeconomic and functional conditions.
Development indicators:
Inhabitants of the four towns aresupplied with a safe and adequatewater systems.
Sub-project 3: Water resources and environmentaldevelopment
Development objective:
To guarantee the adequate share of waterresources for urban water supply and improvethe environmental and health status of theUnguja and Pemba islands by improving thewater quality and to minimize any possibleenvironmental deterioration due to projectactivities.
Development indicators:
Plans exist for meeting the futurewater supply needs.
Ground water quality meets the stan-dards set for safe and good drinkingwater.
No apparent environmental deteriora-tion due to project activities can beseen.
IIIIIIIIIIIIIIIIIIIII
18
COMPONENTS, OUTPUTS, OUTPUT SPECIFICATIONS
The project has three sub-projects, which are furtherdivided into components. The sub-projects, components,outputs and output specifications are presented intable l.
The division to sub-projects should not be consideredtoo important and rigid, but the work should be done asteam work, where all the experts of different fields -local and expatriate - plan and implement theactivities together.
TABLE 1. Components, Objectives, Indicators, Outputs and Output Specifications
SUB-PROJECT 1. ECONOMIC AND INSTITUTIONAL DEVELOPMENT
DEVELOPMENT OBJECTIVE DEVELOPMENT INDICATORS
To contribute to the develop-ment of a clear-cutpolicy and strategy forurban water supply andachievement of economic efficiencyas well as to improvefinancial performance,institutional capacity andthe quality of human andmaterial resources within theorganization in chargeof water supply. In addition,increased involvement ofof consumers to water issueswill be encouraged.
Strategy for self-supportingurban water supply organizationis included in the generalwater policy.
Existence of serf-reliant urbanwater supply organization.
Water systems function withoutproblems related to an inadequateorganizational set up.
COMPONENT
1.1 Financialandeconomicdevelopment
IMMEDIATE OBJECTIVES
- To develop a basicstructure for selfsupporting urban watersupply organization
- Introduction of watercharges
ACHIEVEMENT INDICATORS
- Comments on overall policygiven
- Existence of a detailedprogramme for a gradualchange to a self supportingwater organization
- Local and foreign accountopened
- Domestic revenue collectionstarted
- Training material exists- The output specifications
are fulfilled
OUTPUTS
- Guidelines and policy paperfor UWS
- Revenue billing system
OUTPUT SPECIFICATIONS
- Water works rulesprepared
- Financial policiesdefined
- Rules for revenue collectionestablished
COMPONENT IMMEDIATE OBJECTIVES ACHIEVEMENT INDICATORS OUTPUTS OUTPUT SPECIFICATIONS
1.2 Institutional - To develope an organiza-arrangements tional structure suitableand management for operating anddevelopment maintaining the urban
water supply systems
- To increase the capabilityof the urban water suppfyorganization for developingits management andoperational activities andtaking corrective actions
- To create functioningrelations and coordinationwith sewerage & drainage,health and other authorities
- Organization chart preparedand duties of departmentspecified
- Recommendations for optimumstaffing pattern and requiredqualifications prepared
- Basic indicators for monitoringand control prepared and putinto use
- Dynamic system of jobdescriptions and performanceevaluation introduced andconnected with personnel policy
- Output specificationsfulfilled
- Specification of the scopeof authority of the urbanwater supply organizationtaking into accountfunctioning relations withrelated sectors
New organizational structuresuitable for operating andmaintaining the urban watersupply system
Increased capability of theorganizatbn for developingits management andoperational activities andtaking corrective actions
The goals and tasks of theurban water supply organi-zation specified in waterpolicy and legislationThe scope of the authority ofUWS and the rights andresponsibilities of consumersdefined in water works rules
Measures taken to transformthe present organization intoa self reliant one
- Recommendations for an adequatemanpower information systemgiven
- Personnel policy prepared- An annual financial and
operational planning andmonitoring system and theintegration of this in thethe decision-making introduced
- Job descriptions and standardsfor work performance preparedfor each employee
- Training programme concerningthe use of managerial toolsand a management informationsystem prepared
roo
COMPONENT IMMEDIATE OBJECTIVES ACHIEVEMENT INDICATORS OUTPUTS OUTPUT SPECIFICATIONS
1.3 Humanresourcesdevelopment
To create adequate abilitiesamong the staff in handlingnew working tools, andlo be able to adopt anddevelop new working methodsTo devebpe managerial andoperational staff resourcesappropriate to the tasks ofurban water supplyTo upgrade the level of theurban water supply inproducing and implementinghuman resources developmentplans and training programmesTo upgrade the level ofprofessional and vocationalskills of the urban watersupply authority and improvehuman resources
- Detailed staffing plan prepared- Guidelines for the development
of a qualitative and quantitativestaffing structure prepared
- Plans including budget proposalsproduced
- Training practices introducedand people responsible fortraining determined
- Basic on the job trainingmaterial prepared
- Training of the trainersexecuted
- Detailed plans for participationin basic professional andvocational training in Zanzibar,the mainland and abroad prepared
- Comprehensive training programmefor the fields of management,design, operation, maintenanceand construction prepared
- Development plan preparedjointly with the Ministry ofEducation
- Managerial and operationalstaff resources appropriateto the tasks of urban watersupply organization
Improved level of skills inthe urban water supplyorganization for producingand implementing humanresources development plansand training programmedevelopment
Improved level ofprofessional and vocationalskills in the urban watersupply organization andimproved human capacity
Staffing structure andqualification requirementsspecifiedRecommendations given foradditonally required managerialand operational manpower
Plans developed for a continu-ous system for assessingmanpower and training needsfor providing annual andlong-term staff plansPatterns for on-the-jobtraining developedTraining programme of infernaltrainers prepared
Training needs assessed andprioritized, expertise needsestimatedA comprehensive trainingprogramme for every tradegroup covering the entirefield of activities of theurban water organizationprepared in conjunction withrelevant training institutionsRecommendations made fordeveloping relevant vocationaltraining in Zanzibar
ro
COMPONENT IMMEDIATE OBJECTIVES ACHIEVEMENT INDICATORS OUTPUTS
1.4 Communityeducation andparticipation
- To increase theresponsibility of urbaninhabitants regardingwater issues
- To increase the awarenessof water, health andenvironmental aspects amongurban inhabitants
- To strengthen the cooper-ation between differentauthorities on waterissues as well os toengourage the involvementof local governments inincreasing awareness ofwater related issuesamong urban inhabitants
Communication strategy existsCitizen's water supply guideexistsConsumer service activitiesspecified and assigned withinthe UWS
Curriculum prepared of watersubjects to be integrated intothe teachers' training syllabusTeaching material for teachersand for the campaign preparedPilot "Water Day" conducted,programme and material revisedbased on the pilot campaign[nformation spots on radio, andadvertisements and articlesin newspapers commenced;proposal drawn up for TVprogrammes concerningwater issues
Joint programme forcooperation between differentauthorities exists
- increased responsibility ofurban inhabitants concerningwater issues
Consolidation ofenvironmental educationrelated to water inprimary schoolsPlan for disseminatingwater information viamass media supportingactivities carried outby urban water supplyorganization and loco!governments
Strenghtened cooperationwith other authoritiesrelated to water issues aswell as involvement of localgovernments in efforts toincrease awareness of water-related matters among urbaninhabitants
OUTPUT SPECIFICATIONS
- Relationships betweenbeneficiaries and waterauthorities are defined bywater works rules
- Orientation programme forteachers trainers prepared
- Plan for campaignsfor schools preparedand scheduled
- Joint programme with theMinstry of Health on waterand helth for health workersespecially for those workingwith mothers
- Plan for seminar seriesprepared jointly with localgovernments concerningopportunities for themto contribute to theimprovement of urban watersupply
SUB-PROJECT 2. WATER SUPPLY DEVELOPMENT
DEVELOPMENT OBJECTIVE
To establish adequate and safeurban water supply systemsappropriate to prevailingeconomic and functionalconditions.
DEVELOPMENT INDICATORS
Inhabitants of the four townsare supplied with safe andadequate water systems.
COMPONENT IMMEDIATE OBJECTIVE ACHIEVEMENT INDICATORS OUTPUTS OUTPUT SPECIFICATIONS
2.1 Improvementof UWSschemes
- To increase volume of watersupply by maximizing the useof existing installations
- To improve the pressurelevel in existingdistribution network
- To safequard the drinkingwater quality from healthhazards
- To complete the immediaterepair works within thedistribution network
- To complete basic facilitiesfor supporting activitiesneeded for O & M of watersupply system
- Better correlation betweenpumpages and collected revenue
- Improvements in meetingthe water demand
Continuous disinfectionof the supplied water
Continuous supply ofequipment and toolsReduced losses and periodsof non-operation duringpower failures, etc.
Availability of engineeringdesigns, specifications andmanuals
- Improved service in themulti-storey housing areas
- Decreased water losses
Improved water quality inthe network
Improved yield from existingintakes
Engineering designs andmanuals
- Increased water volume- Improved pressure levels- Decreased water losses
- No seepage back to network
Imported equipment, sparesand tools are available
Detailed designs for newworks and rehabilitationsare availableCost estimates for civil,mechanical and electricalworks, material equipment andchemicals are available
- To improve the planningof future activities
- Availability of annualimplementation programmesfor 1991-1994
- Availability of implementationprogramme for 1995-2000 and2000-2015
- Implementation programmes- Revised master plan
Detailed designs forsupporting constructions areavailable
U>
COMPONENT IMMEDIATE OBJECTIVE ACHIEVEMENT INDICATORS OUTPUTS OUTPUT SPECIFICATIONS
2.2 Operation,maintenanceand monitoringof the schemes
- To guarantee sustainedsupply of water
To monitor the input andoutput of water quantities inthe distribution network
To monitor the conditionof the network
- To monitor the drinkingwater quality in the network
Appropriate manuals availablefor each implemented watersupply schemeContinuous supply ofspare parts
Availability of daily pumpingrecordsAvailability of operationfailure records
The report of leakage preparedwith technical and economicrecommendations forrenovation
Availability of water qualityrecords
- O & M programme anddevelopment plans
- O & M manuals- Improved service level
of the schemes
- Data base for monitoringthe schemes
- Leakage study results
- Water quality monitoringsystem (see component 3.3)
- O & M manuals are available- Imported spare parts and
tools are available- Minimized operational
failures in the network
- Data collected and recordedof daily supplies,operation failures andleakages
- Leakage records available
- Water quality recordsavailable
ro
SUB-PROJECT 3. WATER RESOURCES AND ENVIRONMENTAL DEVELOPMENT
DEVELOPMENT OBJECTIVE DEVELOPMENT INDICATORS
To quarantee the adequateshare of water resources forurban water supply andto improve the environmentaland health status of Hie Ungujaand Pemba islands by improvingwater quality and to avoid/minimize any possibleenvironmental deterioration dueto the project activities.
Plans exist for meetingthe future water supply needs
Ground water quality meets thestandards for safe and gooddrinking water.
No apparent environmentaldeterioration due to theproject activities can be seen.
COMPONENT IMMEDIATE OBJECTIVE ACHIEVEMENT INDICATORS OUTPUTS OUTPUT SPECIFICATIONS
3.1 Water resources - To coordinate Hie use ofdevelopment water resources
To monitor ground waterlevels and water quality aswell as meteorologicalinformation, to establisha reliable system forgathering long termmonitoring information
To guarantee the availabilityof water for urban watersupplies
- Coordinating system for groundwater utilization estsbiished
- Ground water resources inventoryfinalized
- Pumping and managementprocedures determined
- Economic aspects summarizedconcerning the ground waterprogramme
- Detailed drilling programmesexists up to the year 2015
- Coordinated use of waterresources
• Data base for ground watermonitoring
- Revised ground waterutilization plans
- Drilling programmes for1991-1994, 1995-2000 and2000-2015
- Water board established- Ground water legislation
and rules approved
- Meteorological and hydro-geological data gathered andprocessed
- Test drilling and pumpingresults available
- Ground water monitoringnetwork created
- Existing resourcesdevelopment plans verified
- Well-field layouts completedand long term drillingprogramme prepared
- Well production pacecoordinated with plans
COMPONENT IMMEDIATE OBJECTIVES ACHIEVEMENT INDICATORS
3.2 Protection ofwater sources
To improve and protect theenvironment of the existingwater intakesTo see that the future watersources and supplies meet theenvironmental and healthrequirements
- Protection plans existfor each existing andplanned intake
OUTPUTS
- Protected water intakes
OUTPUT SPECIFICATIONS
- Protection plans forintakes prepared
3.3 Environmentalmonitoring
To strengthen water andwaste water monitoringcapacities and develop anextensive programme formonitoring the quality ofground water, as well assewage and sea waterTo establish a pragmaticenvironmental monitoringprogramme to avoid anyadverse environmental impactsdue to ground waterexploitation, increased wastegeneration, constructionactivities and projectside-effects
Water quality monitoringprogramme exists
Pragmatic environmentalmonitoring planStudy reports
Functioning water andwaste water monitoringsystem
Functioning environmentalmonitoring system
Functioning water and wastewater laboratory withtrained staff
Environmental monitoringplan prepared
3.4 Environmentalawareness
To improve environmentalawareness
All training programmesmentioned in 1.3, 1.4, 2.1and 2.2 include environ-mental issuesOrientation programme forauthorities in environmental issues
Increased environmentalawareness within waterauthorities, technicalpersonnel and community
Environmental issuesincluded in all training
3.5 Coordination - To strengthen coordinationof environmental of activities of environmentalactivities concern in cooperation
environmental, health,education, agriculture,forestry and tourismauthorities
Action plan for joint activitieswith environmental, health,agricultural, forestry and othersectors
Strengthened cooperationon environmental issuesbetween different sectororganizations
Action plan for jointactivities prepared
roc*
IIIIIIIIIIIIIIIIIIIII
27
5 PROJECT STRATEGY
5.1 Overall project strategy
The long-term programme for the development of the ur-ban water supply in Zanzibar consists of the planningphase, which took place in 1989-1990, and threeimplementation phases, 1991-1994, 1995-1998 and 1999-2002. The fourth phase, 2003-2006 will be the finalphase with FINNIDA support. By the end of the year 2006a self supporting urban water supply organizationshould exist and function.
During the planning phase a Master Plan for Urban WaterDevelopment has been prepared.
The first implementation phase 1991-1994 will con-centrate on financial, institutional, human resources,community participation and environmental development,as well as on the verification of groundwater develop-ment plans and the development of preventive and cor-rective maintenance systems. The main emphasis in thebeginning must be on developing a tariff policy for thewater organization. Depending on the progress of theeconomic and institutional changes, major renovationworks of water schemes can be considered. Detailedplanning for physical development will also take placeduring this phase.
The second implementation phase will place greater em-phasis on physical development and the monitoring offinancial, institutional, human resources, communityparticipation and environmental development. It ishoped that the water organization will be a self reli-ant unit by the end of the third phase (the year 2002).
The third implementation phase is the preparation forceasing from FINNIDA support. The fourth phase(phasing out) will concentrate on institutionalcoordination. Some import support will still be givenduring this phase.
Technical assistance must be gradually decreased.There may be one long term and a few short term ad-visers in the third phase. Technical assistance mustconcentrate on advising and training with particularattention given to managers, trainers, foremen and in-structors. In connection with training, local institu-tions will be used and their capacities strengthened.
The institutional development and training as well asthe ground water development programs will cover theentire project area egually.
IIIIIIIIIIIIIIIIIIIII
28
The participation of women in all training activitiesof the project must be emphasized. This does not meanonly education at the community level, but also theimprovement of professional capabilities and theemployment situation of women.
5.2 Approach to the implementation of the work
The project team will work within the existingorganization in charge of water supply in Zanzibarimplementing the policies and guidelines of the RGoZ.The role of the consultant is to advise in policy, or-ganizational and technical development as well as insocio-economic and environmental aspects.
The project will be implemented by working in closecooperation with all the sector agencies involved inwater supply development. Those organizations are lis-ted in the section 2.3 of this report. In addition,coordination links will be created with other donoragencies and NGO's working in Zanzibar in relatedsectors and fields.
It is emphasized that the technical plans for the urbanwater supply development should be considered asobjectives, which may be reached only if theinstitutional and economic development proceedaccording to the predictions of the Master Water Plan.Should the institutional and economic development atany stage fail to meet its obligations set in the UrbanWater Supply Development Plan (1990), the progress ofthe technical programme will be delayed until asatisfactory position prevails.
5.3 Economic and institutional development
Financial and economic development
The target of the policy and economic development isthat of gradually developing an economically self-reliant water organization capable of effectivelymanaging, operating and maintaining the water supplysystems.
For a self-supporting water organization the financingwould come from various income-generating systems. Thelocal revenue would be generated from water and servicecharges. Money could also be raised through a develop-ment tax and through selling services such as planning
IIIIIIIIIIIIIIIIIIIII
29
and drilling to other government programs and theprivate sector, in case the private sector is notproviding enough of these services/Foreign currencyincome would be generated by selling water for foreigncurrency, for instance to foreign ships which filltheir water reservoirs at the Zanzibar harbor.Expatriates, tourist hotels and some industries couldpay their water bill in foreign currency.
A consumer affordability analysis and analyses oftourism and industry have been done during the planningphase. During the first implementation phase in 1991-1994, the revenue billing options will be studied and atariff system developed and put into practice.
To reach the goals of financial and economicdevelopment, new water policy and legislation has to beprepared and approved by RGoZ, and the urban watertariff system for all beneficiaries prepared, approvedand implemented.
Institutional arrangements and management development
Two institutional prerequisites should be fulfilled inorder to achieve progress towards the set goals and toguarantee that the project resources will beeffectively utilized:
1. An entity should be established and entrustedwith sole responsibility for the developmentand operations of the urban water supply andperhaps sewerage (Urban Water Supply Sectionwithin the Department of Water Development).
2. A coordinating body for the utilization ofwater resources should be established.
It is also necessary to prepare Water Work Rules forZanzibar. Existing rules dating back to colonial timescould be utilized as background material, since theyare still to a limited extent applied in practice.
Providing the urban water organization with the neces-sary management authority, financial independence andlegal basis for its operation is the responsibility ofthe political bodies and authorities of Zanzibar. Therole of the project is that of contributing by parti-cipating in preparatory work in committees and draftingproposals and estimates with local experts and of-ficials in charge. The decision-making responsibilitylies with the Zanzibari authorities.
IIIIIIIIIIIIIIIIIIIII
30
The first step for the new institutional arrangementshas been the preparation of a proposal for the or-ganization of urban water supply organization, whichwas done during the planning phase in 1990. This willbe followed by approval of the proposal, establishingthe urban water supply organization and a water boardand recruitment of staff during the first implementa-tion phase.
Human resources development
Human resources development is a continuous process ofassessing the short-comings of the manpower and admi-nistration.
Manpower and staff training needs will be defined as aresult of the analysis of tasks and skills during thefirst implementation year. This will be followed byformulating a training strategy, and based on that,annual training plans.
The basic structure for a new manpower planning systemhas already been developed during the manpower inven-tory, carried out in the project planning phase. Themanpower planning system, together with the training,will create opportunity for career development of thepersonnel.
The first group to be trained are the trainers, whichincludes staff of managerial level in the water organi-zation and those of the technical staff with trainingtasks. Professional and vocational training will bearranged for a number of groups during the project im-plementation. The local training institutions will beused when possible, and their capacities developed.
Community education and participation
The relationship between the beneficiaries and thewater authorities at present is unclear and inadeguate.Information on water issues is also quite limited amongthe urban population. To solve these problems and toobtain the beneficiaries' contribution to the watersupply, the people need to be informed, educated andmotivated regarding water issues.
The household survey, which was carried out during theplanning phase, indicates that in some parts of theproject area people are willing to contribute to waterdevelopment by providing their labor something verymuch appreciated. In the areas where this is possible,people must be given the chance to provide work insteadof being charged for water.
The project will further study the required behavioralchanges and the best ways of promoting communicationbetween the water authorities and the beneficiaries. Acommunication strategy and water supply guide will be
IIIIIIIIIIIIIIIIIIIII
31
prepared and necessary training and education programsarranged in the form of campaigns, meetings, schoolprograms and radio and TV spots.
The main target groups for consumer education programsare mothers and children. Mothers are usually incharge of water and health matters at home and also oftaking care of the small children, who are the mostsensitive to water-related diseases. School childrenare an important link between homes and new developmentand knowledge.
The educational programs of the project must be plannedand organized in cooperation with the Department ofEducation and the Department of Health. Education willbe mainly given by health care personnel and teachers,who must go through project orientation.
5.4 Water supply development
The implementation of the Urban Water Supply Develop-ment is expected to be based on revised water policiesand guidelines of the Zanzibar Government and also on aclear-cut action plan outlined in the Urban Water Supp-ly Development Plan.
The construction and rehabilitation programs mustdepend on the progress of the financial, institutionaland human resources development components, subject tofrequent reviews in connection with the annual workplans.
If the physical development plan materializes, a strongdonor input is required for financing of repairs andconstruction. The present service level must be main-tained throughout the project area through a materialsupport component, although the renovation and con-struction programs will concentrate on Zanzibar Townand Chake chake. Contributions will be made to Weteand Mkoani through material support.
An effective operation and maintenance system has to bedeveloped to ensure that the present systems and theefforts to rehabilitate and improve them will be fullyutilized. Preparation of the system will be started inthe beginning of the firs project phase.
The water intakes of Zanzibar Town will be improved tofacilitate the pumping of water to the existing networkso that the full capacity of the network can be util-ized. The pressure level within the network area willbe improved.
The renovation of the water supply in Chake Chakewould be commenced simultaneously or slightly laterthan that of the Zanzibar.
IIIIIIIIIIIIIIIIIIIII
32
The construction part of the programme will be imple-mented by a main contractor (most likely Finnish)together with the Urban Water Organization of Zanzibar,and supervised by the consultant.
The contractor will be responsible for renovation, con-struction and the contractual part of drillingprograms. Part of the drilling programme will becarried out by the local water organization. The actualfield work will be mainly carried out by local sub-contractors.
Since the Urban Drainage and Sewerage Development andthe Urban Water Supply Development Programs work inclosely related sectors and similar locations, theyshould be implemented in close cooperation andcoordination especially in terms of their activities inthe Zanzibar Stone Town area.
5.5 Water resources and environmental development
Ground water development, including drilling andmonitoring activities and establishing coordinatingsystems for ground water utilization, will commencealready in the early stages of the first implementationphase.
The use of ground water is to be submitted under inter-departmental coordination (under the planned WaterBoard), where the Department of Water Development,together with the planned Urban Water Supply Organiza-tion, will play a leading role. Other relevant author-ities will be the Department of Irrigation and the Com-mission of Lands and Environment.
Development of the water quality and environmentalmonitoring facilities and capabilities must beemphasized from the beginning of the first implementa-tion phase and maintained throughout the projectperiods.
The preliminary environmental impact assessment (EIA)for the project was made during the planning phase.
The work will be continued by carrying out further EIAstudies during the rainy season (the first part of theEIA report being done in the dry season).
The Department of Water Development established a smallwater laboratory during the planning phase. Thecapacities and facilities of this laboratory will beextended during the first implementation phase. Exten-sive water quality monitoring programs will be preparedand implemented. Special studies on ground waterpollution will also be made, such as a study onpesticide pollution.
IIIIIIIIIIIIIIIIIIIII
33
Since one of the biggest environmental problems at themoment is the condition of water intakes, plans forprotection of intakes must be prepared.
Environmental awareness will be strengthened amongauthorities, institutions and communities, and col-laboration on environmental issues intensified betweenvarious authorities and institutions.
Environmental monitoring plans to be followed in allproject activities will be prepared in the early stageof the project.
ACTIVITIES
This section gives the framework for the activities ofthe project for 1991-1994. A rough time schedule forthem is given in annex 2. This rough draft will be anoutline for more detailed annual work plans to beprepared each year.
Sub-project 1. Economic and institutional develop-ment
The main activities are:
Financial and economic development
The following studies will be carried out:
study on accounting and financialcontrol systems
study on invoicing options
- Training in economics and development offinancial management system
Development and introduction of revenue bill-ing system
Institutional arrangements and management development
Approval of proposed urban water supply organ-ization and staffing by RGoZ
Preparation for establishment of urban watersupply organization and recruitment of staff
Institution building
Preparing standards for institutional perfor-mance and the creation of a management infor-mation system
II
34
Developing and introducing an institutional
• strategy and annual planning system
Preparing job descriptions and standards
I - Developing a manpower register
Developing a personnel policy
• - Carrying out management training
• Human resources development
Carrying out a task and skill analysis
•Developing a human resources development plan,including:
I - training strategy
manpower planning system
g - annual training plans
_ - Preparation of training material
• - Preparation and implementation of programs for
training of trainers
Arranging vocational training
Community education and participation
Studies to be carried out:
• - study on required behavioral changes
study on communication channels
| - Guidelines to be developed:
B - guidelines for communication strategy
citizen's water supply guide
I - Training and education to be implemented:
orientation of relevant authorities
orientation of health workers
_ - educational campaigns
™ - information spots in mass media
I - trainers of teacher's training
II
I
II
35
Sub-project 2. Water supply development
The main activities are:
Improvement of UWS schemes
™ - Preparation of designs, drawings and documen-
tation
I - Water works
• - Implementing rehabilitation work
Material support for DWD for water schemes
I - On-the-job training
Preparation of annual implementation programs• for 1991-1994
Preparation of implementation programme for• 1995-1998 including cost estimates
Preparation of implementation programme for_ 1999-2002 including cost estimates
• - Updating the master plan
• Operation and maintenance of UWS schemes
Data collection and reporting system
J - Leakage study
•
Developing the operation and maintenancesystem
Preparation of operation and maintenance• manuals
- Training in operation and maintenance
IIIIIII
II
I
36
Sub-project 3. Water resources and environmentalm development
The main activities are:
Water resources development
Establishing a coordinating system for ground• water utilization by RGoZ
Developing a data collection and storing sys-
• tern:
ground water level monitoring
I - water quality monitoring
meteorological information
I - Carrying out drilling and monitoring
activities:
I - drilling
- geoelectrical soundings
• - quality control
• - Preparing revised maps and plans:
resistivity contour map
I - storativity map
transmitivity map
• - potentiometric map
• - chemical quality map
Material purchases
• - On-the-job training
Protection of water sources
Preparation of plans for intake protectionzones
Preparation of plans for site selection
IIIII
II
Environmental monitoring
• - Monitoring ground water quality
_ - Monitoring scheme water quality
• - Monitoring waste water quality
• - Monitoring sea water qualityFollow-up on the development of industry and
m possible pollution
- Studying the use of pesticides
I - Monitoring other environmental aspectsStudies to be carried out in the early stage
I of the project:
EIA during rainy season
• - basic studies on the spread of fecalpollution
37
I basic study on the quality of waste
water
II - Training, education and orientation to be
I
water
basic study on pesticide pollution
Environmental awareness
carried out:
orientation of authorities
intersectoral seminars
| - environmental issues to be includedin all training programs of other
_ sub-projects
™ - training of laboratory personnel
Coordination of activitiesIPreparation and implementation of action plan
• for joint activities with other sectors
IIII
IIIIIIIIIIIIIIIIIIIII
38
Support services
The following activities and support services are to beimplemented:
Establishment of offices for urban waterorganization
Establishment of and running of mainlaboratory in Zanzibar Town and a bacteriologyunit in Pemba
Establishment and running of workshops in Zan-zibar Town and Pemba
Establishment of stores for Zanzibar Town andPemba
Purchasing project vehicles/other purchases
7 INPUTS
7 . l Finnish inputs
Manpower
The Finnish manpower input will be strongest during thesecond year (1992) of the first implementation phase ofthe project, and will be decreased over the followingyears. The first year is carried out by limited staffresources.
The following expatriate specialists are reguired:
Project CoordinatorTraining and Management ConsultantWater Supply EngineerDrilling EngineerOperation and Maintenance EngineerConstruction and Maintenance TechnicianNetwork TechnicianHydrogeologist (short term)Environmental and Laboratory Expert (shortterm)Economic Adviser (short term)Home office coordinator and administrator(short term, in Finland)
In addition, other short term consultants will beprovided if the need arises.
A manpower estimate for consultants and job des-criptions for expatriate specialists are presented inannexes 3 and 4 respectively.
IIIIIIIIIIIIIIIIIIIII
39
Material and equipment
The Finnish input for the materials and equipment willbe limited in the first year (1991) to includefollowing:
vehicles (1 or 2), tractors (1 or 2)limited amount of
drilling equipmentspumpsfittingstoolswater metersspare partsmonitoring instruments
limited amount of office equipment:micro computer (1 pc)printer (2 pc)copy machineother office material andstationery
laboratory chemicalssome training equipment and materialbasic furniture for expatriate housing
The equipment purchased during the planning phase areto be utilized, as well.
The major purchases will be done in 1992, 1993 and1994.
7.2. Tanzanian inputs
Manpower
It is essential for the success of the project that theDepartment of Water Development provide the followingfull-time specialists for the Project ImplementationUnit, which will work within the DWD:
Officer i/c ZanzibarOfficer i/c PembaFinancial OfficerTraining Officers (2)Water Supply EngineerOperation and Maintenance EngineerNetwork TechnicianHydrogeologistDrilling EngineersMonitoring Technicians (2)ChemistLaboratory Technicians (5 - one for Pemba)Procurement OfficerAccountant
This group may later form the foundation team for theproposed urban water supply organization.
IIIIIIIIIIIIIIIIIIIII
40
Material and equipment
Fixed budget amount to be allocated to the Project inTanzanian shillings for the procurement of spare partsand materials required to maintain the present servicelevel. A spare parts and materials list is to beissued by the local water authorities. These supplieswill be used by the local organization. The contractorand the consultant will not be involved in the use ofthem aside from having an advisery role, particularlyin the case of the consultants.
Of f ice,., and other facilities
The UWS office, workshop and store plot at Madema inZanzibar Town and laboratory plot with ready made housein Saateni are to be provided by the Government ofZanzibar, as well as the premises needed in Pemba.Constructing/finalizing and equipping the buildingswill be done by the project after the new UWSorganization is approved.
The office for the Project Implementation Unit (PIU)could in the beginning be a rented house or flat. Assoon as a permanent office facility for the new urbanwater supply organization is allocated the PIU wouldmove in. Workshop and store facilities are neededboth in Zanzibar Town and Pemba. The office, workshopand stores should be equipped and available by the endof the first implementation phase.
Adequate housing - at least 60 mz - is needed for aproper laboratory in Zanzibar. One room is needed inPemba for the bacteriology unit. The laboratoryfacilities should be made ready in 1991.
8 PROJECT BUDGET
The FINNIDA budget includes the costs of Finnish staff,materials and equipment needed to finance the costs of theimplementing agency, the materials and equipment requiredby DWD for the project, and the costs of construction con-tracts to be awarded.
The local budget allocation includes additional costs ofthe DWD and agencies involved with the project. The localallocation is 10 % of costs other than those concerningtechnical assistance.
IIIIIIIIIIIIIIIIIIIII
41
The project budget for 1991-1994 is as follows (units of1000 FIM):
FINNIDA
Localcomponent
TOTAL
1991
6,000
630
6,630
1992
13,000
630
13,630
1993
16,000
630
16,630
1994
15,000
630
15,630
TOTAL
50,000
2,520
52,520
A more concise budget is given in annex 5. It will berevised in the annual work plan. Operational budget willbe presented in the annual work plan.
9 ASSUMPTIONS AND EXTERNAL FACTORS
9.1 Financial and organizational sustainability
The progress of the project as a whole depends on the prog-ress of institutional and legislative development. Thebasic strategy for achieving the self-sustainability of theurban water supply organization is a threefold process ofcreating external preconditions (legal and financial basisfor operation), improving institutional performance(showing results) and training, all partly at the sametime.
The two latter factors are mainly depending on the projectactivities, but strongly affected by the realization ofexternal factors, which are under the responsibility of thepolitical bodies and authorities of Zanzibar.
Any institution needs time for adopting reforms. Thereforeit is preferred that providing the urban water supplyorganizations with the necessary management authority,financial independence and legal basis for operation takesplace gradually.
Consequently, the measures needed from the Governmentshould be taken in sequence. A course of necessary actionsfor the smoothly progress is to be summarized and scheduledas follows:
By the end of the year 1991
The Urban Water Supply Section (UWSS) has beenformed within the Department of Water Development.
Proposals for a decree to establish Zanzibar UrbanWater Supply Authority and Ground Water Ordinancehave been submitted to the political decision-makers.
IIIIIIIIIIIIIIIIIIIII
42
By the end of the year 1992
Administrative preparations have been completedfor the UWSS to function autonomously on a trialbasis.
By the end of the year 1993
The UWSS has readiness and right to master an ownaccount and to charge for its services
Relations between the UWSS and beneficiaries aswell as the rights and responsibilities ofconsumers have been defined in the Water WorkRules.
By the end of the year 1994
The UWSS has readiness to start functioning as anUrban Water Supply Body and possesses legal basisfor its operation.
However, it is important to keep in mind that also thebest-designed institutional change will always encounterunforeseen obstacles that require creative reprogramming.
The Government of Zanzibar should, in these circumstances,undertake to guarantee that the standards achieved as aresult of the resources contributed to the project will bemaintained on a long-term basis. This would mean that anydeficit in income from charges required to maintain thesestandards will be made up for with government funds.
The local component allocation - 10 % of investment relatedcosts - is a precondition for full FINNIDA's budgetallocation.
9.2 Other external factors
Other factors which may delay the scheduled implementationof the project are:
delays in procurement from abroaddelays in transportation of equipment due to dif-ficulties in connections between Dar es Salaam,Zanzibar Town and Pembapower failures, especially in Pembainadequacy of staff for trainingdelays in the progress of the sewerage anddrainage project of Stone Townnon-availability of adequately skilled local con-tractors
IIIIIIIIIIIIIIIIIIIII
43
10 PROJECT ORGANIZATION
The Competent Authorities of the two Governments for theimplementation of the Project are the Ministry for ForeignAffairs of Finland, represented in Finland by the FinnishInternational Development Agency, FINNIDA, and in Tanzaniaby the Embassy of Finland in Dar es Salaam, and the Mini-stry of Finance of Tanzania. However, in matters pertain-ing to the substance of the project and not affecting theoverall responsibilities of the Government of Tanzania, theMinistry of Water, Construction, Energy, Lands and Enviro-nment of Zanzibar/Department of Water Development has theright to represent the Ministry of Finance.
The project will have a project implementation unit (PIU),which consists of the staff of the Finnish implementingagency and full-time specialists from DWD appointed for theproject. This unit (PIU) will work within the organizationof DWD.
The project will be supervised by a steering committee,composed of representatives from:
FINNIDAMinistry of Finance, TanzaniaMinistry of Water, Construction, Energy, Planningand Environment, ZanzibarMinistry of Finance, ZanzibarMinistry of Planning, ZanzibarMinistry of Agriculture, ZanzibarMinistry of Health, ZanzibarMinistry of Education, ZanzibarCommission for Lands and Environment, ZanzibarMunicipal Council, ZanzibarProject Implementation UnitStone Town Conservation and Development Authority
The organization of the project is presented in figures 5/1and 5/2.
IIIIIIIIIIIIIIIIIIIII
44
11 REPORTING, MONITORING AND EVALUATION
11.1 Reporting systems and reports
The basic plans of the project as defined in terms of theobjectives, outputs, inputs, activities and other aspectsare formulated in:
- The project document
The annual plan of operation (annual work plan),which will detail the annual activities, outputsand other major aspects related to the year'soperations.
The annual plan of operation will be prepared by theproject, and sent through the Finnish implementing agencyto FINNIDA for approval two months before the end of theyear. The first annual plan of operation will be submittedat the latest two months after the commencement of theproject.
The purpose of the reporting is to compare the progress ofthe implementation with the planned progress, and theimpact of the project with the planned impact. The formeris accomplished by comparing the planned and achievedoutputs. The latter is carried out by comparing theplanned development and achievements with the actualdevelopment and achievements using the formulatedachievement and development indicators. At the same, ananalysis of the factors influencing the impact, the need torevise objectives, the state of the assumptions, etc. willbe carried out.
The reports will be based on the internal monitoring andevaluation system of the project. The following reportswill be produced:
Actual monthly expenditures and a comparison withplanned expenditures
Quarterly expenditures and estimates for thefollowing quarters of the year. The quarterlyreports will also include comparison of theplanned and actual progress in terms ofachievement outputs. They are to be submittedwithin a month of each quarter's end.
IIIIIIIIIIIIIIIIIIIII
45
Annual reports are to be submitted within 45 daysafter the end of each year which:
compare the planned and actualachievement by using achievementindicators
compare the planned and actual deve-lopment by using development indicatorsas well as assess the probability ofachieving the planned development
compare the planned and actual progressin terms of achievement outputs as wellas assess the possibilities of achievingthe planned outputs over the remainingduration of the project
analyze the factors which influence theannual achievements, the state ofassumptions, etc. as well as suggesteventual required actionsto be taken
The final report, which includes the comparison ofplanned and actual development as well as plannedand real outputs, inputs, etc. The final reportalso includes the review of the factors having aninfluence on the outcome of the project, the stateof the assumptions, etc. Furthermore, the finalfinancial statement as well as a detailedinventory of vehicles, equipment, materials, etc.will be made. The final report is to be submittedwithin two months after the termination of theproject.
Workshop and seminar reports/minutes will beannexed to the quarterly/annual reports.
11.2 Monitoring
There will be an annual field review mission by a monitor-ing team to review and monitor the progress of the projectand recommend required actions. The first mission willtake place after the first annual plan of operation isready, and thereafter annually after the annual report isready. The monitoring team will be appointed by FINNIDAand the executing agency will be invited to nominate amember of the team.
IIIIIIIIIIIIIIIIIIIII
46
11.3 Evaluation
A mid-term evaluation will be made two years aftercommencement of the project. The evaluation will assessthe achievement of planned development and progress andwill make recommendations for improving project efficiency,effectiveness, relevance and impact- FINNIDA will appointthe mid-term evaluation team and the executing agency willbe invited to appoint a member of the evaluation team.
FINNIDA will nominate, if needed, a team for the executionof the final project evaluation, and carry out an appraisalof the project document for Phase II of Zanzibar UrbanWater Supply Project.
FIGURE 2. GROUND WATER DEVELOPMENT AREAS OF UNGUJA
~ DONGE RIDGE
GROUND WATER FLOWDIRECTION
UPENJA RIDGE
WATER SHED(TOPOGRAPHICAL)
BUMBWI CORRIDOR 'MAIN GROUND WATERD I V I D E (STRUCTURAL)
LOWER MWERAVALLEY
ZANZIBAR TOWN
MASINGINI RIDGE
KISIMA MCHANGA
IIIIIIIIIIIIIIIIIIIII
FIGURE 3/1. ORGANIZATIONAL CHART OF MINISTRY OFWATER, CONSTRUCTION, ENERGY, LANDS AND ENVIRONMENT
MINISTER
PRINCIPAL SECRETARY
DIRECTOR OFCONSTRUCTION
DIRECTOR OFPLANNING ANDADMINISTRATION
DIRECTOR OFWATER DEPARTMENT
GENERAL MANAGERPOKER AND FUELCORPORATION
EXECUTIVESECRETARYCOMMISSION OFLANDS ANDENVIRONMENT
OFFICER IN CHARGEMINISTRY OF WATERCONSTRUCTION,ENERGY, LANDS ANDENVIRONMENT, PEM3A
OFFICER IN CHARGEDEPARTMENT OFCONSTRUCTIONPEMBA
PLANNING OFFICERPLANNING ANDADMINISTRATIONPEMBA
OFFICER IN CHWCEDEPARTMENT OFWATER PEMBA
OFFICERIN CHARGECOMMISSION OFLANDS ANDENVIRONMENTPEMBA
ASSISSTANT MANAGERFUEL AKD POKERCORPORATIONPEMBA
IIIIIIIIIIIIIIIIIIIII
FIGURE 3/2. PRESENT ORGANIZATION OF THE WATER SUPPLY
Minister of Water, Construction, Energy,Lands and Environment (WCELE)
Principal Secretary of the Ministry of WCELE
Ministry of WCELE in Pemba
Director of the DWD
Executive Engineer-in Onguja
Water Supply
Construction
Plants '
Development
Administration
Southern Region
Chake ChakeDistrict
Water Supply
Construct ion
Plant
Development
Admin is t rat ion
DWD in Pemba - Officerin charge
Plant Superintendent
water Supply Superintendent
Northern Region
MkoaniDistrict
Water Supply
Construct ion
Plant
Development
Administrat ion
wete
water Supply
Construct ion
Plant
Adrni n i s t r a t i o n
M ichewen1
- water Supply
II
FIGURE 4/1. EXISTING ORGANIZATIONAL CHART OF DEPARTMENT OFWATER DEVELOPMENT - UNGUJA
IIIIIIIIIIIIIII
DIRECTOR
Electric Engineer
( l)
EXECUTIVE- ENGINEER
2-Clvil Engineer1-Geology
(3)
WATER SUPPLY
Water SupplyTechnic ian Supervisor
I 1)
WATER WORKS
10-waterTechnician( 10)
LABORATORY
3-LaboratoryTechnicians
1-AssistantLaboratoryTechnician
OPERATION iMAINTENANCE
1-Senior Plutoer]-Regional Water
Officer28-Plunders27-Ass. Plumbers
1-Ass. Fundi1-Ass,p.Station
Supervisor61-Pu^pers
1-water 4 MineralAssistant
6-watcrtnenII-Cleaners
I 1.18)
CONSTRUCTION
Civ i l TechnicianSupervisor
LL1
53 :s
MASONRY
2 - C i v i l Tech.5-Me»onry5 - A E S . Masonry1-Painter2-Carpenters1-Ass, Carpenter1-Ass. civil
Technician
(17)
TANK1-Tank Superv.5-Tank Tech.3-Ass.TanJt
Technician(9)
PLANT
Plant TechnicianSupervisor
, ( l )
ELECTRICAL
4-Elec t .Tech .7-Ass. E l e c t .
Technicians
Mil
GARAGE
1-Mechanic Sup.3-MechanicaA'Ass.Mechanics
( 8 )
POWER1-Plant Superv .3-Kechonic Tech•1-Mechanics1-Ass. Mechanic
(9)
DEVELOPMENT
Foreman D r i l l e r
(1)
DRAWING S. MAPPING
1- Draughtman
(1)
SURVEY1-Ass. Supervisor
(U
DRILLING9-Orillers
(9)
INVESTIGATIONAND RECORDS
1-Kater Tech .
(1)
WORKSHOP
1-F i t t e r £ TurnerSupervisor
8-Fi t ter t. Turner3-Mechanical Tech2-Welders2-Blacksniths1-Ass, Slacks™.tb
(17)
TRANSPORT
1-Tr«nsportOfficer
6-Drivers(7)
ADMINISTRATION
Administration OfficerAss. Officer
(2)
ACCOUNT
2-A$sist3nt Cashier1-Revenue Clerk;
Supervisor1-Revenue collector2-Revenue Clerk1-eill Man
STORE
1-Supervisor StoreKeeper
1-Ass. SupervisorStore Keeper
1-Store Keeper1-Store Clerk3-watchmen4-Cleaners
(11)
CHIEF CLERK
1-Office Superintendent1-Secretery2-Typists3-Registry Clerkl-Messanger6-watchmen7-Cleaners
(21 j
IIII
IIIIIIIIIIIIIIIIIIIII
FIGURE 5/1. PROJECT ORGANIZATION
GoT/RGoZ
MOF 1 MWCEPE \
DWDZANZIBAR
\ /
STEEICOMM]
UNG[TTEE
///
PROJECT
.
GoF
FINNIDA 1
/
/
DWDPEMBA
DWDDIRECTOR
EXECUTIVEENGINEERZANZIBAR
PROJECT 1KPLEMETATIONUNIT (PIU)
EXECUTIVEENGINEERPEMBA
PROJECT IMPLEMENTATION UNITHQ
PROJECT COORDINATOR (1)OFFICER I/C ZANZIBAR (Z)
OFFICER I/CPEMBA(Z)
ui
to
ECONOMICADVISOR (E)
FINANCIALOFFICER (Z)
TRAINING ANDMANAGEMENTCONSULTANT
(E)
TRAININGOFFICERS (Z)
WATER SUPPLYENGINEERS
(Z + E)
OPERATIONAND
MAINTENANCEENGINEERS
<Z + E)
NETWORKTECHNICIANS
(Z + E)
HYDRO-GEOLOGISTS
(Z + E)
DRILLINGENGINEERS
(Z + E)
MONITORINGTECHNICIANS( Z )
ENVIRONMEN-TAL
LABORATORYSPECIALIST (E)
CHEMIST (Z)
LABORATORYTECHNICIANS
(Z)
PROCUREMENTOFFICER (Z)
ACCOUNTANT(Z)
f
E = EXPATRIATEZ = ZANZ1BARIAN
PROBLEM ANALYSIS
INADEQUATE RESOURCES
NOH AVAILABILITY OPWATER POLICY
IKADEQUATE ORGANIZATIONALINDE PEN DEKCE/sEPARATEHATER t SEWERAGE AUTHORITIES
LACK OF CLEAR CUT ACTIONPLANS FOR PROGRAMMES
INEFFICIENT USE OFLIKITED RESOURCES
IATER POLICYMO•EGISLATIOHO BE WRITTEN
APPROVED
INADEQUACY OFQUALIFIED STAFF
INADEQUATE LEGISLATION
LACK OF URBAN HATER AltOSEHERAGE AUTHORITY
CLEAR CUT ACTIONPLANS TO BEPRODUCED- LONGTERM- SlfORTTERH
- INADEQUATE USER CONTROL- NOH CO-OROINATEO USE OFHATER RESOURCES
HATERLEGISLATIONTO BEREVISED
URBAN WATER AUTHORITYTO BE ESTABLISHEDAND FINANCIALLY ANDINSTITUTIONALLYIHDEPENDENT
WATER BOARDTO BEESTABLISHED
NON-AVAILABILITYOF MATERIALS
FINANCIAL CONSTRAINTS LACK OF KNOWLEDGE ONSAFE DRINKING WATER
LOW SALARY LEVELS
INADEQUATE PLANNINGINADEQUATE OPERATION 1 MAINTENANCEINADEQUATE POWER SUPPLYLACK OF STORE-PARTS t MATERIALSLACK OF TOOLS * INSTRUMENTS
DETERIORATED CONDITION OF SCHEMESLOW SERVICE LEVELDISSATISFACTION WITH BENEFICIARIESUNSATISFACTORY INSTITUTIONAL PERFORMANCE
REVENUE COLLECTIONTO UE STARTED
EDUCATION ANDTRAININGPROGRAMMES TOBE LAUNCHED
LOW MOTIVATION FOR HIGHWORKING PERFORMANCE
SPREADING OF HATER-BORNEDISEASES, INFANT MORTALITY
IMPLEMENTATIONOF PHYSICALDEVELOPMENTPLAN
SALARY INCREASES TOUE INTRODUCED BASEDON IMPROVEMENT OFECONOMY THROUGHINSTITUTIONAL AHDFINANCIAL IMPROVEMENTS
COMMUNICATIONSTRATEGY TO BEHADE ANDIMPLEMENTED
3(D
COMMUNITY PARTICIPATION ANALYSIS
UNSPECIFIED RELATIONSHIPSBETWEEN CONSUMERS ANDWATER AUTHORITY
CAUSES POOR MAINTENANCE
UNRELIABLEWATER SUPPLY
_£FREQUENT BREAKDOWNS OFINSTALLATIONS AND FITTINGSWITHIN THE PREMISES
PROBLEMS
DISSATISFIEDCUSTOMERS
LEGISLATION ANDWATER WORK RULES
SOLUTIONS
RELIABLE WATERDISTRIBUTION
POOR KNOWLEDGEABOUT WATER ISSUES
NO FINANCIAL RESPONCIBILITYFOR DOMESTIC WATER USE
EXTRAVAGANTUSE OF WATER
WATER RELATED AUTHORITIESINSUFFICIENT COOPERATION
CONTAMINATION OFWATER SOURCES BYDOMESTIC ACTIVITIES
UNCLEAR RIGHTS ANDDUTIES OF CONSUMERS
• N?
SPREAD OF WATERRELATED DISEASES
CONSUMERS'INFORMATIONSERVICES ANDEDUCATION
DOMESTIC CONSUMERSCONTRIBUTION TOTO WATER SUPPLYCOSTS
STANDARDS FORINSTALLATION &FITTINGS
ENVIRONMENTAL ANDHEALTH EDUCATION- JOINT ACTIVITIESRELATED SECTORS, MASSMEDIA & EDUCATION
3
to
TRAINING OFDWD STAFF
ENVIRONMENTAL ANALYSIS
(a) Problems related to increased use of ground water (b) Problems related to quality of water and health
PROJECT OTHER DEVELOPMENT ACTIVITIES PROJECT
INCREASED USE OFGROUND WATER FORTOWN SUPPLIES
EXISTING SITUATION
INCREASED USE OFGROUND WATER FORTOURISM RELATEDACTIVITIES
USE OF GROUKDWATER FORIRRIGATION
INCREASED AMOUNTOF WASTE WATER
INCREASED AMOUNTOF DOMESTICKASTE WATER
±SHORTAGE OFGROUND WATER
SALINIZATIONOF GROUNDWATER
PERCHED WATER- EVAPORATION- SALIHIZATION
SEE (b) LACK OF WATERIK SHALLOWWELLS
POOR SOLIDWASTE ANDWASTE WATERMANAGEMENT- DOMESTIC- INDUSTRY
L
STAGNANTWASTEWATER
IMPACTS TOAGRICULTURE(AND FORESTRY)
SOCIO-ECONOMICPROBLEMS
EROSION DUETO LACK OFVEGETATION
USE OF PESTICIDESAND FERTILIZERSIN AGRICULTUREAND FORESTRY
NON-PROTECTEDWATER SOURCES- BOREHOLES- SPRINGS- LOCAL WELLS
POOR MAINTENANCEOF WATERSUPPLIES
SHORTAGEOFELECTRICITY
MICROBIOLOGICAL AND CHEMICALPOLLUTION OF GROUD WATER(AND SEA WATER)
BREAKAGES, LEAKSAND BLOCKAGES OFPIPED SYSTEMS
SHORTAGEOF WATER
INADEQUATE QUALITY OFDRINKING AND BATHINGWATER
CALCIUMIN WATER
SPREAD OF WATER ANDHYGIENE RELATED DISEASES
SOIL QUALITY(LIME STONE)
SOCIO-ECONOMIC PROBLEMS
X
U)
IIIIIIIIIIIIIIIIIIIII
Annex 2 1(6)
TENTATIVE WORK PLAN 1991-1994
1. ECONOMIC AND INSTITUT1ONALDEVELOPMENT
1.1 Financial and economicdevelopment
studies- accounting end financialcontrol systems
- study on invoicing
Training
Revenue collection system
1.2 Institutionalarrangements andmanagement development
Approval of proposed UUAorganization and staffing
Preparation forestablishment of UUA endrecruitment of staff
Institution building
Standards for institutionalperformance and creationof management informationsystem
Institutional strategy andannual planning system
Job description andstandards
Manpower registry
Personnel policy
Management training
1991 1992 1993 1994
IIIIIIIIIIIIIIIIIIIII
Annex 2 2(6)
1.3 Human resourcesdevelopment
Task and skill analysis
Training strategy
Manpower planning system
Annual training plans
Preparation of trainingmaterial
Training of trainers
Vocational training
1.4 Community educationand participation
Studies- required behaviourchanges
- communication vehicles
Guidelines- communication strategy- citizen's water supplyguide
Training and education- orintation of relevantauthorities
- orientation of healthworkers
* educational campaigns- information spots inmass media
- teacher's trainerstraining
IIIIIIIIIIIIIIIIIIIII
Annex 2 3(6)
2. WATER SUPPLYDEVELOPMENT
2.1 Improvement of UWSschemes
Designs and drawingsand documentation:
Intake structures- Zanzibar- Pemba
Water works- Zanzibar- Pemba
Distribution networks- Zanzibar- Pemba
Rehabilitation work- Zanzibar- Pemba
Water schemes:Material support for DWD
On-the job training
Annual implementationprogrammes for 1991-1994- Zanzibar- Pemba
Implementation programmefor 1995-2000 includingcost estimates- Zanzibar- Pemba
Updated master plan
IIIIIIIIIIIIIIIIIIIII
Annex 2 4 ( 6 )
2.3 Operation and maintenanceof UWS schemes
Data collection andreporting system- Zanzibar- Pemba
Leakage study- Zanzibar- Pemba
Developing the O&M system
Preparation of O&M manuals
Training in O&M
3. WATER RESOURCES AMDENVIRONMENTAL DEVELOPMENT
3.1 Water resources development
Coordinating system forground water utilization
Data collection andstoring system- ground water levelmonitoring
- water quality monitoring- meteorological information
Drilling and monitoringactivities- drilling- geoelectrical soundings- quality control
Revised maps and plans- ground water- resistivity contour map- storativity map- transmitivity map- potentiometric map- chemical quality map ]
Material purchase |
On-the-job training |
...
i11
- - 1•1
1
1
1
t
IIIIIIIIIIIIIIIIIIIII
Annex 2 5(6)
3.2 Protecting water sources
- plans for site selection- plans for intakeprotection zones
3.3 Environmental monitoring
Monitoring- ground water quality- scheme water quality- waste water quality- sea water quality- pollution of industry* use of pesticides- other environmetalaspects
Studies- ElA during rainy season* baseline studies onspread of fecal pollution
- baseline study on qualityof waste water
- baseline study onpesticide pollution
3.4 Environmental awareness
* orientation of authorities!* intersectoral seminars* environmental issues inHRD and CP progranmes
- Training of laboratorypersonnel
3.5 Coordination of activities
Action plan for jointactivities with othersectors
4 ANNUAL WORK PLANS
Annual work plan 1991
Annual work plan 1992
Annual work plan 1993
Annual work plan 1994
•I
IIIIIIIIIIIIIIIIIIIII
Annex 2 6(6)
5. SUPPORT SERVICES,
IMPLEMENTATION AND PURCHASES|
UWA, offices, impl.
UWA, Laboratory, impl.
UWA, Workshop, inpt.
UWA, Stores, impl.
Project vehicles/sparepart purchases
Project stationary purchases
MANMOMTH ESTIMATE 1991-1994
EXPATRIATE CONSULTANT/ [ 1991 | 1992 | 1993 | 1994
K E H - c l a s s i f i c a t i o n | J F M A M J J A S O H D | J F H A H J J A S O N D | J F N A M J J A S O N D | J F M A H J J A S O N D Z F
(months)
Tot
LONG TERM:
Project Coordinator/
KEH 2
Training and Management
Consultant/KEH 3
Hater Supply Engineer/
KEH 3
Dri11 ing Engineer/
KEH 4
Operation and Maintenance
Engineer/KEH 3
Construction and Maintenance
Technician/KEH 4
Network Technician/
KEH 4
SHORT TERM:
Hydrogeologist/
KEH 2
Environmental andLaboratory Expert/KEH 2Economic Advisor/KEK 2Other short term
and back-up personnel
HOME OFFICE:
Home Office Coordinator/
KEH 1
Home Office Secretary/
KEH 5
************************ ************************ ************************ ************************
************************
**********
************
************
************************
************************
**************
************************
************************
************************
******************
************
************
************
************
************************
**********
*********
**********
(to be determined later)
44
34
45
23
23
29
23
12
2
2
0
0
0
0
0
0
0
44
34
45
23
23
29
23
7
10
10
3
3
2
10
13
12
18
22
19
20
24
264
**** full time Uork in Zanzibar (Z).... part time Uork in Finland (F)
55 319
IIIIIIIIIIIIIIIIIIIII
Annex 4 1(9)
JOB DESCRIPTIONS
Job Description/ Project coordinator
The main duties of the Project Coordinator are the co-ordination of the technical assistance activities ofthe project as well as - together with the Officers i/cZanzibar and Pemba - the overall management of all thesub-projects.
The tasks include but are not limited to the following
(a) Coordinating the execution of all the sub-projects and liaise with the executing andparticipating organizations;
(b) Coordinating the preparation of internal moni-toring and evaluation system of the project,as well as all reporting;
(c) Coordinating the arrangement of all the speci-fied meetings, workshops and seminars;
(d) Managing the implementation project reviews,preparation of plans, monitoring, evaluationand reporting;
(e) Participating in all planning, implementationand evaluation;
(f) Coordinating all inhouse training (includingorientation training)
riiiiiiiiiiiiiiiiiiii
Annex 4 2(9)
Job Description, Training and Management Consultant
The duty of the Training and Management Consultant is,together with the Economic Adviser, to manage the sub-project "Economic and Institutional Development", espe-cially being responsible of the components: "Institu-tional arrangements and management development", "Humanresources development" and "Community education andparticipation", and to be in charge of all trainingactivities of the project. The tasks include:
(a) Planning, implementation and evaluation of theinstitutional development of the executing or-ganization;
(b) Assisting in planning, implementation and eva-luation of training, which supports the imple-mentation of other sub-projects;
(c) Assisting in planning, implementation and eva-luation of inhouse training programmes (in-cluding orientation training);
(d) Planning, implementation and evaluation of on-the-job training of management and middle man-agement staff;
(e) Participation in all planning and implementa-tion as training expert;
(f) Training of staff of the executing and partic-ipating organizations;
(g) Planning consumer education activities, con-sumer participation methods and consumer par-ticipation evaluation system;
(g) Reporting the progress of the relevant projectcomponents.
rAnnex 4 3(9)
Job Description/ Water Supply Engineer
| The main responsibility of the Water Supply Engineer isto manage the sub-project "Water Supply Development".
M The duties of Water Supply Engineer include:
(a) Preparation of plans for improvement of thewater systems;
(b) Revising the Master Water Plan;
(c) Conducting leakage study and leakage protec-tion planning;I
|
(d) Assisting in training the staff of the execut-ing agency to develop a planning capability;
(e) Assisting in monitoring, evaluation and train-ing r<j ect ;
I ing related to the 0 & M elements in the pro-
I (f) Conducting review and design of the primarydistribution system elements;
|
(g) Preparation of standard design details forsecondary distribution system and house con-nections;
|(h) Conducting review and design of water storage
facilities;
• (i) Assisting in system monitoring and control;
(j) Assisting in contract administration and su-_ pervision;
• (k) Coordinating of procurement and delivery ofmaterial support component;
I (1) Reporting the progress of the relevant projectcomponents.
IIIIIII
I_ Annex 4 4(9)
Job Description/ Drilling Engineer
I The Drilling Engineer will be responsible forcommencing the drilling operations with two drilling
I units.
The duties include:
I (a) Organizing and training the drilling teams to
carry out the drilling work;
|
(b) Preparing borehole construction designs withthe local hydrogeologist;
|
(c) Arrangements for test pumping, organizing oftest pumping teams, commencing the testpumping activity and doing the related dataprocessing;
• (d) Following up the collection of hydrogeologicaland drilling data;
| (e) Training of the staff of the executing agency;
|
(f) Preparing of future drilling programmes withthe local hydrogeologist;
|
(g) Procuring of drilling material and spare partsfor the drilling rig;
(h) Reporting on the drilling and test pumping• activities with the local hydrogeologist.
IIIIIIIII
IIIIIIIIIIIIIIIIIIIII
Annex 4 5(9)
Job Description, operation and Maintenance Egineer
The Operation and Maintenance Engineer will be incharge of the component "Operation and maintenance ofUWS schemes".
The duties include:
(a) Guidance on preparing 0 & M manuals by thestaff of the executing agency;
(b) Supervising and administrating the contractsfor extending the primary distribution systemand providing additional water storage. Thisincludes resolving contractual disputes, claimnegotiations, etc;
(c) Advising and assisting local sub-consultantsin project supervision and administration;
(d) Arrangements related to maintenance of projectvehicles;
(e) Data collection and participation in mechani-cal and construction design work;
(f) Supervising and administrating contracts inrelevant parts
(g) Assistance with procurement of materials forthe project;
(h) Reporting the progress of the relevant projectcomponent.
IAnnex 4 6(9)
Job Description, Construction and Maintenancem Technician
The duties include:
I (a) Participating in design work in relevant
parts;• (b) Organizing of maintenance systems;
(c) Training of the staff of the executing agencym in mechanical works and maintenance;
(d) Site supervision of the executing agency inconstruction works on the water system;
• (e) Monitoring, evaluation and training inputsrelated to contract supervision and adminis-
• tration;
(f) Reporting the progress of the relevant projectH component.
• Job Description, Network Technician
I The duties of the Network Technician include:
(a) Responsibility for everyday operational pro-
I ject activities in Pemba. Duty station ChakeChake;
(b) Organizing of 0 & M system in Pemba;
• (c) Coordinating of collection of monitoring re-sults and data for design work in Pemba. Par-
I t i c i p a t i n g in design work within relevantparts;
|
(d) Supervising of preparation of 0 & M manuals inPemba;
(e) Reporting the progress of the relevant projectM activities.
IIIII
IIIIIIIIIIIIIIIIIIIII
Annex 4 7(9)
Job Description, Hydrogeologist (short term)
The main duty of the hydrogeologist is to follow up theimplementation of the component "Water resourcesdevelopment" including:
(a) Assistance to development of coordinating sys-tem for ground water utilization;
(b) Development of ground water monitoring system.Interpretation of monitoring results;
(c) Preparation of well field designs and drillingplans. Preparation of test pumping programmesand interpretation of results;
(d) Revision of maps and plans;
(e) Participating in material purchase;
(f) Participating in planning of training in rele-vant fields;
(g) Reporting the progress of the relevant projectcomponent.
Job Description, Environmental and Laboratory Expert(short term)
The duty of the Environmental and Laboratory Expert isto follow up the environmental development activitiesof the project including:
(a) Assisting in developing the protection plansfor water sources;
(b) Establishing water laboratories (Zanzibar andPemba) and planning water guality monitoringin Zanzibar and Pemba;
(c) Planning and implementing environmental moni-toring activities and environmental studies;
(d) Participating in planning, implementation andevalutation of environmental training and edu-cation;
(e) Assisting in preparation of action plan forjoint activities between different sector or-ganizations;
(g) Reporting the progress of the relevant projectcomponents.
IIIIIIIIIIIIIIIIIIIII
Annex 4 8(9)
Job Description, Economic Adviser (short term)
The duty of the Economic Adviser is to coordinate theexecution of the component "Financial and economicdevelopment". The tasks are to
(a) Plan, partly implement and follow up all theactivities of the project component "Policyand economic development";
(b) Participate in all planning, implementationand evaluation as a financial and economicexpert;
(c) Plan and implement the system for financialreporting of the project;
(d) Train staff of the executing and participatingagencies;
(e) Reporting the progress of the relevant projectcomponent.
Job Description, Electrical Engineer (short term)
(a) Evaluation of the present electricalinstallations, assess the future electricityconsumptions and the level of the controlsystem;
(b) Reviewing and planning of the electricalstandard designs of water supplies;
(c) Reviewing and creating material for O&Mtraining
(d) Monitoring, evaluation and training inputs tothe contract supervision;
(e) Reporting the progress of the relevant projectactivities.
IAnnex 4 9(9)
Job Description, Project Coordinator (Home office)
Duties
I (a) Responsible for all the administrative activi-• ties of the project in Finland, including ac-
counting and cost monitoringI (b) Overall responsibility of reporting the
project progress and monitoring towardsm FINNIDA
(c) Overall management and supervision of thehome-office work for the project
II
IIII
(d) Responsible for the recruitment of expatriatepersonnel
(e) Responsible for planning the orientation trai-ning in Finland
• (f) Assisting the mobilization of the project, ar-rangement of housing facilities, vehicles and
_ procurements from Finland
™ (g) Available for short time consultancy for theproject in relevant areas
IJob Description, Project secretary (Home office)
I Duties
I (a) Assisting in all administrative activities
regarding the project in Finland(b) Preparing the statements of accounts for FIN-
• NIDA
(c) Cost monitoring
• (d) Duties related to purchasing:
inquiriesorderingcontacts to forwarding companies
|
(e) Correspondence between the project, home of-fice and FINNIDA
(f) Assisting in preparing project reports
I - ordering
I Annex 5 1 (2)
I ANNUAL BREAKDOWN OF PROJECT BUDGET ACCORDING TO FINNIDA CODES
Code
2131-3
2131-3
2133-1
2133-1
2153-7
2153-7
2311-1
2313-9
2221-7
2321-4
2331-7
2223-5
2323-2
2333-5
2233-8
3211-3
3212-2
3213-1
3221-6
3222-5
3223-4
3231-9
3232-8
3233-7
wmmm
•III
Specification
Fees and wages (Expatriate experts)(including home office support)
Travelling, accommodation (Expatriate experts]
Fees and wages (Zanzibarian experts)
Travelling, accommodation
Fees and wages (Other local pers.
Travelling, accommodation
Services, Finland (communications
)
Services, Tanzania (communications)
Finland
Consumption equipment*
Recurrent costs*
Others and unspecified*
Tanzania
Consumption equipment*
Recurrent costs*
Others and unspecified*
Unspecified goods*
Investment equipment, Finland*
Investment equipment, other IC*
Investment equipment, Tanzania*
Consumption equipment, Finland*
Consumption equipment, other IC*
Consumption equipment, Tanzania*
Unspecified goods, Finland*
Unspecified goods, other IC*
Unspecified goods, Tanzania*
TOTALContingencies 10%
TOTAL
wmmmmmmmmmmmmmZanzibar, calculated total (FIM)
mmmmm
iilliiili!
1991
3,434,960
445,949
80,000
30,000
25,000
15,000
70,000
60,000
80,000
30,000
0
70,000
60,000
40,000
40,000
530,000
600,000
160,000
90,000
40,000
20,000
60,000
20,000
40,000
6,040,909589,091
6,630,000
M
188,000
1992
5,470,248
960,934
350,000
50,000
150,000
20,000
80,000
50,000
220,000
100,000
70,000
100,000
30,000
40,000
50,000
1,900,000
1,800,000
350,000
100,000
100,000
40,000
100,000
50,000
40,000
12,221,1821,408,818
13,630,000
xfxmmr509,000
1993
4,173,359
999,096
370,000
50,000
160,000
20,000
80,000
50,000
250,000
130,000
70,000
170,000
30,000
100,000
50,000
6,000,000
1,500,000
600,000
100,000
50,000
60,000
180,000
200,000
40,000
15,432,4551,197,545
16,630,000
953,000
1994
3,965,005
1,039,360
400,000
50,000
170,000
20,000
80,000
50,000
280,000
150,000
40,000
170,000
30,000
40,000
50,000
4,900,000
1,800,000
600,000
100,000
40,000
60,000
180,000
200,000
40,000
14,454,3651,175,635
15,630,000
• 1 ^ 0 ^ ^
868,000mmmmmmwmam
TOTAL
17,043,572
3,445,339
1,200,000
180,000
505,000
75,000
310,000
210,000
830,000
410,000
180,000
510,000
150,000
220,000
190,000
13,330,000
5,700,000
1,710,000
390,000
230,000
180,000
520,000
470,000
160,000
48,148,9114,371,089
52,520,000
2,518,000
Local component is calculated to be 10 % of total investment and procurement costs (marked by *)
1IIIIIIIIIIIIIIIIIIII
Annex 5 2 ( 2 )
ANNUAL BREAKDOWN OF PROJECT BUDGET TO CONSULTANCY SERVICES, RECURRENT COSTS AND INVESTMENT COSTS
Investment costs*
Specification
Consultancy services
Recurrent costsa) procurements*b) others
TOTALContingencies 10%
TOTAL
Zanzibar, calculated total
mmmm
1991 1992 1993 1994
3,880,909 6,431,182 5,172,455 5,004,365
470,000 850,000 1,010,000 960,000280,000 700,000 730,000 770,000
1,410,000 4,240,000 8,520,000 7,720,000
6,040,909 12,221,182 15,432,455 14,454,365589,091 1,408,818 1,197,545 1,175,635
6,630,000 13,630,000 16,630,000 15,630,000
188,000 509,000 953.000• :• :• ̂ : - : o : - : - : • : • : • ^ •:•:•:•.•>:•:•:•:•:•:•:•:•:•:•:•:•:•.•:•;•>•:•:•: ' :•. r: • : • / . . : . ' . : . : • . :j • : . . - . - : : . o . - > . . : • : . : - : ->:- :->: r- x • : • : • : • • : • ^ • : • : • .
ifilil
TOTAL
20,488,911
3,290,0002,480,000
21,890,000
48,148,9114,371,089
52,520,000
2,518,000
itiillil
Local component is calculated to be 10 % of total investment and procurement costs (marked by *)
A breakdown of the operational budget will be given in the work plan