final report - odisha _road.pdf · 2019-03-15 · and blocks spread across the state to prepare a...

67
FINAL REPORT On TECHNICAL EVALUATION OF CEMENT CONCRETE ROADS Submitted to Planning & Coordination Department GOVERNMENT OF ODISHA Prepared by School of Infrastructure INDIAN INSTITUTE OF TECHNOLOGY BHUBANESWAR February 2016

Upload: others

Post on 09-Apr-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

FINAL REPORT 

 

On 

 

TECHNICAL EVALUATION OF CEMENT 

CONCRETE ROADS 

 

Submitted to 

 

Planning & Coordination Department 

GOVERNMENT OF ODISHA 

 

 

Prepared by 

 

School of Infrastructure 

INDIAN INSTITUTE OF TECHNOLOGY 

BHUBANESWAR 

February 2016 

 

Page 2: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

1  

CONTENTS 

 

Section  Description  Page No. 

1  Introduction  1 

2  Background  2 

3  Objectives of this Study  5 

4  Methodology  5 

5  Selection of Roads  5 

6  Detailed Methodology  12 

7  Field Investigations  19 

8  Laboratory Investigations  28 

9  Analysis of Results  30 

10  Conclusions and Recommendatios  39 

11  Photograpghs  41 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 3: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

2  

1. INTRODUCTION 

Government  of Odisha  has  constructed  large  number  of  concrete  roads  (rigid  pavement)  through 

Panchayati Raj Department in the village areas across the state for providing connectivity to various 

habitations  under  different  blocks  and  Tehsils.  It  has  been  observed  that  some  of  these  concrete 

roads  have  lost  their  functional  and  structural  performance  and  therefore  unable  to  provide  the 

desired level of services for the socio‐economic upliftment to the targeted population due to variety 

of reasons.  

 

Therefore,  taking  into  account  the  huge  investment  made  for  development  of  such  roads,  the 

Planning and Coordination  (P&C) Department, Government of Odisha has decided  to evaluate  the 

quality of implementation of these roads. Also, the Government wanted to assess the advantages of 

these concrete roads over similar type of bituminous roads. In this regard, IIT Bhubaneswar has been 

entrusted  for  carrying  out  the  Technical  Evaluation  of  these  roads  (vide  letter  No.  8262  Dated 

04.07.2015). A contract was signed between both the parties on 29th October 2015 in the office of 

the Director (DF&C)‐cum‐Additional Secretary to Government, P & C Department, Govt. of Odisha. 

 

The investigating team from IIT Bhubaneswar visted different road sections in the identified districts 

and  blocks  spread  across  the  state  to  prepare  a  list  of  12  CC  roads  and  12  bituminous  roads  for 

taking  up  the  evaluation  study.  The  report  presents  a  detailed  methodology  of  the  evaluation 

process, investigations results, discussions, conclusions and recommendations. 

 

2. BACKGROUND 

The  Panchayati  Raj  Department,  Government  of  Odisha  have  taken  initiative  in  the  past  for 

construction of Cement Concrete (CC) roads  in the villages through various major funding schemes 

like  Backward  Regions  Grant  Fund  (BRGF),  Gopabandhu  Gramin  Yojana  (GGY)  and  Finance 

Commission  Award  (FCA)  in  order  to  improve  the  quality  of  life  and  hygienic  conditions  in  the 

villages.  

 

Backward  Regions  Grant  Fund  (BRGF) was  implemented  in  19  districts  of  Odisha.  Construction  of 

Cement Concrete Roads is  a major activity being taken up under the scheme. The minimum amount 

given to a village is Rs. 2 Lakh. 

 

Gopabandhu  Gramin  Yojana  (GGY)  provides  development  assistance  to  11  non‐BRGF  districts.A 

village is entitled to get Rs. 3 to 15 Lakh depending upon its population. 

Page 4: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

3  

CC Road under Finance Commission Award (FCA): Panchayati Raj Institutes (PRIs) receive funds under 

Finance  Commission  Grant  for  operation  and  maintenance  of  water  supply  and  for  improving 

sanitation in villages. Construction of CC road with drain is a major activity that has been taken up in 

the villages for improving sanitation under this scheme. A Panchayat gets between Rs. 2.62 Lakh to 

3.20 Lakh depending upon population during a year. 

 

Apart of these major schemes, CC roads have also been constructed through vaious other schemens 

such as RLTAP, Biju KBK/ Kandhamal/ Gajapati, MLALAD, MPLAD, WODC, IAP, ITDA Grants, FDR Grant 

etc.  Considering  the  large  scale  demand  of  CC  roads  in  the  State,  the  department  launched  a 

dedicated scheme called “Cement Concrete Road” in 2010‐11.  The focus was on construction of CC 

roads  in  SC/ST/PVTG  habitations.  A  village  is  entitled  to  get  an  amount  between  3  to  7  Lakh 

depending upon its population. 

 

2.1. Guidelines issued for construction of CC roads 

As per  the  initial  guidelines, DRDAs were  following  standard  specification of  3 meter width  and 7 

inches (175 mm) thickness of concrete layer (75‐100 mm 1:2:4 plain cement concrete over 100 mm 

1:3:6 plain cement concrete) over 100 mm of sand for construction of such roads, which cost Rs. 32‐

33 lakhs per Km. as per the prevailing prices. 

 

The following guidelines were issued during the initial phases of the scheme: 

The width of the road shall be 3‐3.5 meters with expansion joint on each 5 meters interval. 

During  casting of  concrete  like C.C.  (1:3:6)  (metal  concrete) & C.C.  (1:2:4)  (chips  concrete) 

plate vibrator shall be used. Without plate vibrator no casting of concrete will be made. 

If  the  length  of  the  road  is more  than  100 meter  then  8‐10  tons  roller  shall  be  used  for 

compacting the sub‐base. 

Efforts should be made for 3% cambering of the road. 

Minimum seven days curing for the concrete road shall be made and the concerned JE/GPTA 

has to ensure it. 

The concerned JE/GPTA shall verify the site personally and accordingly prepare the drawing 

of the concrete road as per the approved plan. 

During  casting  of  concrete  the  concerned  JE/  GPTA  shall  be  personally  present  on  the 

worksite and as per his or her direction mixture of concrete will be prepared. 

The Assistant Engineer of Block shall visit at least once to every concrete road during casting 

of C.C. (1:3:6) & C.C. (1:2:4). 

Page 5: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

4  

In a recent guideline issued in 2013 by Panchayati Raj Department, few changes in the cross section 

have been made with  respect  to  the earlier design practices. Detailed drawings as per  the  revised 

guidelines are given in Fig.1 and Fig.2. The guidelines released in this regard are given in Annexure‐I. 

 

Fig. 1: Typical Cross Section of CC Roads in Black Cotton Soil Area 

 

 

Fig. 2: Typical Cross Section of CC Roads in Hard Soil Area 

 

 

Page 6: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

5  

3. OBJECTIVES OF THE STUDY 

With the background as discussed earlier, the objectives of the present study are: 

Structural Evaluation of the Selected road sections 

Distress identification and mapping 

Functional evaluation of roads 

Drainage performance 

Life Cycle cost analysis and comparison of Bituminous (BT) and CC roads 

Suggest measures for improvement in  CC road constructions 

 

4. METHODOLOGY 

Pavement evaluation is generally carried out in two ways; i.e. Structural and Functional. 

1. The following procedure will be adopted for Structural evaluation of the road sections: 

Residual Strength estimation by cutting cores and determination of its compressive 

strength  

Non‐destructive testing of concrete roads using Rebound Hammer 

Test pits for BT roads and evaluation of materials used 

2. The following procedure will be adopted for Functional evaluation of the road sections: 

Distress Identification 

Distress mapping 

Roughness measurement using Roughometer 

3. Drainage performance evaluation 

4. Life Cycle Cost Analysis of the pavements considering the following costs: 

Construction Cost 

Maintenance cost 

Service period 

 

5. SELECTION OF ROADS 

A total of 24 roads (12 CC and 12 BT surfaced) have been selected from the three revenue divisions 

selecting one district from each based on number of completed CC road projects.   Two blocks from 

each district were also identified in consultation with Panchayti Raj Department for carrying out this 

study. 

 

 

 

Page 7: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

6  

5.1. Identified Districts and Blocks 

Based  on  the  maximum  number  of  completed  projects,  three  districts  have  been  identified  by 

Panchayati Raj Department with one from each revenue division (RD) as given below: 

1. Cuttack 

2. Keonjhar 

3. Kalahandi 

 

Four blocks  (2 with max. coverage and 2 with min. coverage)  from each sample district have been 

identified for carrying out this study. The details of the selected sites are given below in Table‐1: 

 

Table‐1: District and Blocks Selected for this Study 

Division  District  Block 

Max Coverage  Min Coverage 

Central  Cuttack  Athagarh  Banki‐Dampada 

Mahanga  Niali 

Northern  Keonjhar  Anandpur  Jhumpura 

Ghatagaon  Harichandanpur 

Southern  Kalahandi  Kesinga  Golamunda 

Thuamul Rampur  Koksara 

 

Page 8: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

7  

 

Fig.3. Map Showing the Study Area in Cuttack District 

 

ATHAGARH

MAHANGA

BANKI‐DAMPADA

NIALI

Page 9: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

8  

 

Fig.4. Map Showing the Study Area in Keonjhar District 

 

JHUMPURA 

GHATAGAON

ANANDPUR

HARICHANDANPUR 

Page 10: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

9  

 

Fig.5. Map Showing the Study Area in Kalahandi District 

 

 

 

 

 

 

 

 

 

 

KESINGA

THUAMUL RAMPUR

KOKASARA 

GOLAMUNDA 

Page 11: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

10  

5.2. Road Sections 

The following roads have been finaised for carrying out this study: 

 

District: Cuttack 

Block: Athagarh 

CC Road: Khuntakata Internal Village Road, GP‐Khuntakata 

BT Road: PWD Road to Badabhuin, GP‐Badabhuin 

Block: Mahanga 

CC Road: Kuhunda Internal Village Road, GP‐Kuhunda 

BT Road: PWD Road to Basudevbpur, GP‐Basudevpur 

Block: Niali 

CC Road: Nuasatanga Village CC road, GP‐ Krushnaprasad 

BT Road: Krushnaprasad to Tampada, GP‐ Krushnaprasad 

Block: Banki‐Dampada 

CC Road: MDR‐77 (Kalika Prasad) to Muraripur, GP‐Partapur 

BT Road: RD Road to Brahmania, GP‐Gadjit 

 

 

 

District: Keonjhar 

Block: Anandpur 

CC Road: NH215 to Kolimati Village (CC portion),GP‐Kolimati  

BT Road: NH215 to Kolimati Village (BT portion), GP‐Kolimati 

Block: Ghatagaon 

CC Road: Bhalukipatala Internal Village Road,GP‐Bholabeda 

BT Road: Bholabeda to Balukipatala,GP‐Bholabeda 

Block: Jhumpura 

CC Road: Durgapur to Bhaluka Nala,GP‐Arsala 

BT Road: Arsala to Chauthia,GP‐Arsala 

Block: Harichandanpur 

CC Road: Dehuri Sahi to Juanga Sahi (CC portion),GP‐Rebana 

BT Road: Dehuri Sahi to Juanga Sahi (BT portion),GP‐Rebana 

 

 

Page 12: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

11  

District: Kalahandi 

Block: Kesinga 

CC Road: NH to Kasurpada Village Road, GP‐Kasurpada 

BT Road: Kokomunda to Gokuleswar, GP‐Gokuleswar 

Block: Thuamul Rampur 

CC Road: Peramanji to Adibasi Pada , GP‐KarlaPada 

BT Road: Srimaska to Sindhipadar,GP‐Sindhipadar 

Block: Golamunda 

CC Road: Faranga Internal Village Road, GP‐Faranga 

BT Road: Faranga to Kumbhari, GP‐Faranga 

Block: Kokasara 

CC Road: NH26 to Gountiapada,GP‐ Barahadanga 

BT Road: NH26 to Kundaguda, GP‐Ampani 

Page 13: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

12  

6. DETAILED METHODOLOGY 

6.1. Measurement of Roughness 

Pavement roughness  is generally defined as an expression of  irregularities  in the pavement surface 

that adversely affect the ride quality of a vehicle. Roughness of pavement surface can be measured 

using different equipment such as Merlin, Response type road roughness meters, Profilographs etc. 

Response  type  road  roughness  meters  (RTRRMs)  provide  indirect  measure  of  longitudinal  road 

profile. These systems measure the response of a vehicle to the road surface. A response type road 

roughness meter is an instrument mounted in a vehicle to monitor pavement roughness. It records 

the displacement of the vehicle chassis relative to the rear axle per unit distance travelled, usually in 

terms of counts per kilometer or meters per kilometer.  In this study, the Australian Road Research 

Board  (ARRB)  make  Roughometer‐III  (as  shown  in  Fig.  6)  has  been  used  for  determination  of 

roughness of the road surfaces.  

 

 

Fig.6. ARRB Make Roughometer‐III 

 

Main Features of Roughometer‐III are: 

Accurate and repeatable outputs regardless of vehicle type, suspension and passenger loads 

Axle‐mounted inertial sensor used to determine road profile and roughness 

Integrated GPS for location data with on‐screen display of satellite tracking status 

Outputs in International Roughness Index (IRI)  

Can be installed in most passenger and light commercial vehicles 

Fast and simple download of data, to laptop or computer, using USB connection 

 

6.2. Pavement Condition Survey 

Various typical pavement distresses were observed by visual inspection in the considered roads. The 

different distresses considered for bituminous and concrete pavements are described below: 

 

Page 14: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

13  

Distresses in Bituminous Pavement 

Cracking,  raveling, pot holes and patching are visually observed and recorded as percentage of  the 

area are reported 

 

Rutting: Rutting is a surface depression in a wheel path and is a load‐associated distress. 

 

Potholes: These are small, bowl‐shaped depressions in the pavement surface that penetrate all the 

way through the bituminous layer down to the base course.  

 

 

Fig.7. Photograph Showing the Distresses in a Bituminous Pavement 

 

Patching:  Patches  are  repairs  made  to  previous  distress,  indicating  prior  maintenance  activity. 

Improper patching  can  introduce a degree of  roughness,  further  deterioration at  the edges of  the 

patch, or even  failure of  the patch  itself  can happen  if  the underlying problem was not addressed 

during patching. 

 

Block  Cracking:  Block  cracking  is  a  climate/materials  related  distress,  where  shrinkage  of  the 

bituminous surface or underlying stabilized base causes interconnected cracks that divide the surface 

into irregular pieces. 

 

Alligator  Cracking:  This  distress  is  also  known  as  fatigue  cracking  and  is  a  traffic  loading  related 

distress that is initiated in the wheel paths. 

Page 15: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

14  

 

Longitudinal  Cracking:  These  cracks  or  discontinuities  may  appear  anywhere  along  a  shoulder  or 

driving lane and run roughly parallel to the pavement centerline 

 

Raveling:  Raveling  is  the progressive  loss of  surface aggregates  caused by weathering,  traffic, or  a 

combination of the two. 

 

Distresses in Concrete Pavement 

Following are the common distresses in a concrete pavement. 

 

Spalling:  This can be described by cracking, breaking or chipping of joint/crack edges. Usually occurs 

within  about  0.6 m  of  joint/crack  edge.  Due  to  spalling,  the  problems  generated  on  the  road  are 

loose debris on the pavement, roughness, etc. This is generally an indicator of advanced joint/crack 

deterioration. 

 

Faulting: A difference in elevation across a joint or crack usually associated with un‐doweled JPCP is 

known as faulting. Faulting is noticeable when the average faulting in the pavement section reaches 

about 2.5 mm. 

 

Polished Aggregate: These are areas of pavement where the portion of aggregate extending above 

the  cement  paste  is  either  very  small  or  there  are  no  rough  or  angular  aggregate  particles.  This 

results in decreased skid resistance. 

 

Shrinkage Cracking: This may be described by hairline cracks formed during PCC setting and curing 

that  is  not  located  at  joints.  Usually,  they  do  not  extend  through  the  entire  depth  of  the  slab. 

Shrinkage cracks are considered as distress if they occur in an uncontrolled manner 

 

Linear Cracking: These are  linear cracks not associated with corner breaks or blowups that extend 

across the entire slab. Typically, these cracks divide an individual slab into two to four pieces. This is 

often referred to as “panel cracking”. This creates roughness, allows moisture infiltration leading to 

erosion of base/subbase support, and also  these cracks will eventually spall and disintegrate  if not 

sealed. 

 

Page 16: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

15  

 

Fig.8. Photograph Showing a Distressed Concrete Pavement 

 

Corner  Break:  This  is  a  crack  that  intersects  the  PCC  slab  joints  near  the  corner.    A  corner  break 

extends through the entire slab and is caused by high corner stresses. Problems associated with the 

corner  break  are  roughness,  moisture  infiltration,  severe  corner  breaks  will  fault,  spall  and 

disintegrate. 

 

Popouts: Small pieces of PCC that break loose from the surface leaving small divots or pock marks. 

Popouts range from 25 – 100 mm in diameter and from 25 – 50 mm deep. Problem associated with 

popouts is roughness which is usually an indicator of poor material. 

 

6.3. Non‐Destructive Structural Evaluation of Pavements 

Rebound hammer test: 

Rebound  hammer  test  is  used  to  provide  a  convenient  and  rapid  indication  of  the  compressive 

strength of concrete. It consists of a spring controlled mass that slides on a plunger within a tubular 

housing.  This  equipment  has  been  used  to  assess  the  strength  of  the  concrete  pavements.  The 

rebound hammer and its operation are shown in the figures 9 and 10.  

 

 

Page 17: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

16  

 

Fig.9. Photograph Showing a Rebound Hammer 

 

 

 

Fig.10. Working Principle of Rebound Hammer 

 

When the plunger of rebound hammer is pressed against the surface of concrete, a spring controlled 

mass with a constant energy is made to hit concrete surface to rebound back. The extent of rebound, 

which  is a measure of surface hardness,  is measured on a graduated scale. This measured value  is 

designated as Rebound Number (rebound index). A concrete with low strength and low stiffness will 

absorb more energy to yield in a lower rebound value. 

 

In‐situ Evaluation of Pavement Layers using Dynamic Cone Penetrometer (DCP) 

DCP is an effective device for in‐situ evaluation of subgrade and granular layers due to its relatively 

small and lightweight design and easy operation. DCP equipment has two main components, i.e. the 

lower shaft and the upper shaft. The lower shaft is of 16 mm diameter and 800 mm long and can be 

extended to 1200 mm using an extension rod. This carries an anvil on top and a 60° hardened alloy 

cone  of  20  mm  base  diameter  at  its  bottom.  The  upper  shaft  carries  a  sliding  hollow  cylindrical 

hammer of 8 kg weight, which strikes the anvil with a fixed fall of 575 mm. Because of its simple and 

Page 18: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

17  

economical design, DCP  is being used  in  the  field  to characterize  the subgrade and base materials. 

One of the greatest advantages of the DCP device lies in its ability to provide a continuous record of 

relative  soil  strength  with  depth.  By  plotting  a  graph  of  penetration  index  versus  depth,  one  can 

observe  the  profile  showing  layer  depths  and  strength  conditions.  Fig.11  shows  a  DCP  test  in 

progress. 

 

 

Fig.11. Investigation of pavement layers at a site using DCP 

 

6.4. Extraction of Cores from Concrete Pavement 

The  examination  and  compression  testing  of  cores,  extracted  from  hardened  concrete  is  a  well‐

established method, which enables  visual  inspection of  the  interior  region of  a  structure.  This will 

provide  an  idea  about  the  thickness  of  the  concrete  layers.  It  can  be  coupled  with  strength 

estimation and physical properties such as density, water absorption, etc. The cores can be used as 

samples  for  analysis  subsequent  to  strength  testing.  For  extracting  the  core  from  the  concrete 

pavements, a core cutter is needed which should be firmly supported and braced against concrete to 

prevent  relative movement which will  result  in  a  distorted  or  broken  core.  The  photograph  given 

below shows a core cutter used for taking out a core form the concrete pavement. 

Page 19: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

18  

 

Fig.12. Taking Cores from a Concrete Pavement 

 

6.5. Test Pit in Bituminous Pavements for Material Evaluation 

Test pits (Figure 13) are excavated in the bituminous pavements close to the edge of the carriageway 

to  collect pavement  layer  composition data.  Thicknesses of different  layers are observed  from  the 

test pits and recorded for analysis. Materials from different pavement layers including sub grade are 

collected from the pit  for  laboratory evaluation. Different tests are conducted  in the  laboratory on 

the materials collected from site.  

 

 

Fig.13. Trial Pit in Bituminous Pavements 

 

Page 20: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

19  

7. FIELD INVESTIGATIONS 

This section presents the results obtained from various field and laboratory investigations carried out 

during this study. 

 

7.1. Pavement Composition 

7.1.1. Composition of CC Road Pavements 

A typical CC road pavement consists of 75‐100 mm layer of PCC (1:2:4) over a lean PCC (1:3:6) layer 

laid over 50‐100 mm sand. Concrete cores have been taken from the CC road pavements to find out 

the composition of  the  layers. Table‐2 presents  the thicknesses of different  layers observed during 

the field investigations. 

Table‐2: Pavement Composition of CC Roads 

Sec. 

No. 

Road Section  Block  Thickness (mm) 

CC 

(1:2:4) 

CC 

(1:3:6) 

Sand 

1  Khuntakata Internal Village Road  Athagarh  70‐75  75‐100  50‐100 

2  Kuhunda Internal Village Road  Mahanga  85‐95  70‐100  50‐75 

3  Nuasatanga Village CC road  Niali  70‐75  75‐95  50‐75 

4  MDR‐77 (Kalika Prasad) to Muraripur  BankiDampada  65‐78  75‐90  50‐75 

5  NH215 to Kolimati Village (CC portion)  Anandpur  88‐97  90‐100  50‐100 

6  Bhalukipatala Internal Village Road  Ghatagaon  65‐77  70‐90  50‐75 

7  Durgapur to BhalukaNala  Jhumpura  55‐65  70‐95  50‐75 

8  DehuriSahi to JuangaSahi (CC portion)  Harichandanpur  60‐84  75‐95  50‐75 

9  NH to Kasurpada Village Road  Kesinga  55‐65  75‐95  50‐75 

10  Peramanji to AdibasiPada  Th. Rampur  55‐60  65‐85  50‐75 

11  Faranga Internal Village Road  Golamunda  68‐82  70‐95  50‐75 

12  NH26 to Gountiapada  Kokasara  65‐75  75‐90  50‐75 

 

7.1.2. Composition of Bituminous Road Pavements 

A typical rural road bituminous pavement consisted of 150‐200 mm of granular subbase (moorum), 

150 mm of Base (WBM) and 20‐25 mm of premix carpet. The pavement layer composition obtained 

through trial pits made in the bituminous test sections are given below in table‐3.  

  

 

Page 21: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

20  

Table‐3: Pavement Composition of Bituminous Roads 

         Thickness (mm) 

Sl 

No. 

Road Section  Block  Sub‐base  Base  Surfacing 

1  PWD Road to Badabhuin  Athagarh  180  170  25 

2  PWD Road to Basudevbpur  Mahanga  100  130  20 

3  Krushnaprasad to Tampada  Niali  250  170  25 

4  RD Road to Brahmania  BankiDampada  150  180  25 

5  NH215 to Kolimati Village   Anandpur  40  75  30 

6  Bholabeda to Balukipatala  Ghatagaon  150  150  25 

7  Arsala to Chauthia  Jhumpura  270  90  40 

8  DehuriSahi to JuangaSahi  Harichandanpur 130  150  20 

9  Kokomunda to Gokuleswar  Kesinga  175  160  25 

10  RD Road to Sirimaska  Th. Rampur  125  150  20 

11  Faranga to Kumbhari  Golamunda  100  75  25 

12  NH26 to Kundaguda  Kokasara  75  150  25 

 

7.2. Pavement Condition  

7.2.1. Condition of CC Roads 

Cement Concrete roads taken up under this study were mostly 2‐5 years old. The overall condition of 

these roads were found to be fair to poor.  The following paragraphs present some of the problems 

associated with CC roads.  

 

Fig. 14. High Edge Drop in CC Roads 

Page 22: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

21  

 

There is no provision of shoulders in the CC road sections. Therefore the edge drop was found to be 

very high at places. The photogragh shown in Fig.14 presents a simlilar section, where the difference 

in levels of the road surface and the adjacent land is about 150 mm. This creates safety concern for 

the vehicles plying on ths road during crossing and overtaking maneuvres. Also, the edges are prone 

to damage in such conditions. The following photograph shows damage of edges and corners of the 

slabs due to movement of wheels along the edges. 

 

    

Fig. 15. Edge and Corner failure in CC Road Pavements 

 

Cracking  in  the concrete pavements were also observed  in many cases. The cracking seen  in some 

sections are longitudinal cracks, which mostly happens due to differential settlement of the subgrade 

soil. The photograpghs presented below shows these cracks in some CC road sections. 

 

    

Fig.16. Cracks in CC Road Pavements 

 

Drainage has been found to be one of the major problem in the habitation areas. Damages are found 

to be more in roads with poor drainage condition.  

Page 23: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

22  

 

 

Fig.17. Poor Drainge in Village Areas 

 

In  few road sections,  it was  found  that,  the aggregates  in  the  cement concrete  layers are exposed 

due  to erosion of cement mortar. This happens motly due to  low cement content  in  the concrete. 

The photograph shown in Fig.18 presents exposed aggregates in a concrete road surface. 

 

 

Fig.18. CC Road Surface in Poor Condition 

 

 

Page 24: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

23  

7.2.2. Condition of Bituminous Roads 

Bituminous roads taken up under this study were mostly 3‐5 years old. Some roads were observed 

with  distresses  like  rutting,  raveling  and  potholes  apart  from  local  settlements.  Fig.  19  shows  two 

moderately distressed road section and Fig. 20 shows heavily distressed road sections. 

 

     

Fig.19. Low to Moderate Distresses in Bituminous Roads 

 

     

Fig.20. Heavliy Distressed Bituminous Road Surface 

 

Table‐4  and  Table‐5  present  the  pavement  condition  data  of  CC  Roads  and  Bituminous  roads 

respectively.

Page 25: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

24  

Table‐4: Pavement Condition Data‐ CC Road Sections 

 

 

Sec No. 

Road Section  Block  Road Width (m) 

Shoulder  Edge Drop (mm) 

Cracking  Drainage  Joint Condition 

Surface Finish 

Riding Comfort 

1  Khuntakata Internal Village Road 

Athagarh  3.6  No  0‐150  Mild cracking in one phase of construction

Poor  Fair  Fair to Poor 

Fair to Poor 

2  Kuhunda Internal Village Road 

Mahanga  3.0‐3.5  No  0‐100  Low‐Mild cracks in older constructions 

Poor  Fair  Fair to Poor 

Fair to Poor 

3  Nuasatanga Village CC road 

Niali  3.0‐3.5  No  0‐100  Mild‐severe cracks in older constructions 

Poor  Poor  Fair to Poor 

Fair to Poor 

4  MDR‐77 (Kalika Prasad) to Muraripur 

Banki Dampada  3.65  No  0‐150  Mild‐severe cracks in older constructions 

Poor  Poor  poor  Fair to Poor 

5  NH215 to Kolimati Village (CC portion) 

Anandpur  3.8  No  0‐100  Mild‐severe cracks in older constructions 

Poor  Fair  Fair to Poor 

Fair to Poor 

6  Bhalukipatala Internal Village Road 

Ghatagaon  3.5  No  0‐150  Mild‐severe cracks in older constructions 

Poor  Poor  poor  Poor 

7  Durgapur to BhalukaNala 

Jhumpura  3.5  No  0‐150  Low   Poor  Poor  Fair to Poor 

Fair to Poor 

8  DehuriSahi to JuangaSahi (CC portion) 

Harichandanpur  3.5  No  0‐100  Low   Poor  Poor  poor  Fair to Poor 

9  NH to Kasurpada Village Road 

Kesinga  3.0‐4.0  No  0‐50  Low‐Mild cracks in older constructions 

Poor  Fair  Fair to Poor 

Fair to Poor 

10  Peramanji to AdibasiPada 

Th. Rampur  3.0‐3.5  No  0‐100  Mild‐severe cracks in older constructions 

Poor  Poor  poor  Poor 

11  Faranga Internal Village Road 

Golamunda  3.0‐3.5  No  0‐150  Mild‐severe cracks in older constructions 

Very Poor 

Poor  Poor  Fair to Poor 

12  NH26 to Gountiapada  Kokasara  3.5  No  0‐75  Low   Fair  Poor  Fair to Poor 

Fair to Good 

Page 26: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

25  

Table‐5: Pavement Condition Data‐ Bituminous Road Sections 

Sec No. 

Road Section  Block  Road Width (m) 

Shoulder  Rutting  Ravelling  Cracking  Potholes  Drainage  Riding Comfort 

1  PWD Road to Badabhuin 

Athagarh  3.8  Yes  Low  Low  Low  Low  Good  Fair 

2  PWD Road to Basudevbpur 

Mahanga  3.75  Yes  Moderate  Low  Low  Low  Fair  Fair 

3  Krushnaprasad to Tampada 

Niali  3.75  Yes  Severe  Moderate  Moderate  Moderate  Fair  Poor 

4  RD Road to Brahmania 

BankiDampada  3.75  Yes  Low  No  No  No  Good  Fair to Good 

5  NH215 to Kolimati Village 

Anandpur  3.8  Yes  Low  No  No  No  Good  Fair 

6  Bholabeda to Bhalukipatala 

Ghatagaon  3.75  Yes  Low  Low  Low  Low  Good  Fair 

7  Arsala to Chauthia  Jhumpura  3.75  Yes  Low  Moderate  Low  Low  Good  Fair 

8  DehuriSahi to JuangaSahi 

Harichandanpur  3.75  Yes  Low  Low  No  No  Good  Fair 

9  Kokomunda to Gokuleswar 

Kesinga  3.75  Yes  Low  Low  Low  Low  Good  Fair to Poor 

10  RD Road to Sirimaska 

Th. Rampur  3.0  Yes  Low  No  Low  No  Fair  Fair 

11  Faranga to Kumbhari 

Golamunda  3.75  Yes  Low  No  Low  No  Good  Fair 

12  NH26 to Kundaguda  Kokasara  3.0  Yes  Low  Low  Moderate  Low  Good  Fair 

Page 27: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

26  

7.3. Roughness of Road Surfaces 

Roughness of the road surfaces were measured using ARRB make Roughometer attached to the axle 

of a vehicle. The observed roughness values are presented below in tables ‐ 6 and 7 

 

Table‐6: Roughness of CC Road Surfaces 

Sec. No.  Road Section  Roughness (IRI) 

1  Khuntakata Internal Village Road  9.05 

2  Kuhunda Internal Village Road  6.1 

3  Nuasatanga Village CC road  11.8 

4  MDR‐77 (Kalika Prasad) to Muraripur  11.5 

5  NH215 to Kolimati Village (CC portion)  9.4 

6  Bhalukipatala Internal Village Road  11.8 

7  Durgapur to BhalukaNala  9.25 

8  DehuriSahi to JuangaSahi (CC portion)  5.45 

9  NH to Kasurpada Village Road  8.9 

10  Peramanji to AdibasiPada  11.5 

11  Faranga Internal Village Road  8.7 

12  NH26 to Gountiapada  10.45 

 

Table‐7: Roughness of Bituminous Road Surfaces 

Sec.  No.  Road Section  Roughness (IRI) 

1  PWD Road to Badabhuin  6.85 

2  PWD Road to Basudevbpur  9.1 

3  Krushnaprasad to Tampada  12.4 

4  RD Road to Brahmania  10 

5  NH215 to Kolimati Village   6.7 

6  Bholabeda to Balukipatala  9.85 

7  Arsala to Chauthia  8.1 

8  Dehuri Sahi to Juanga Sahi  10.4 

9  Kokomunda to Gokuleswar  11.2 

10  RD Road to Sirimaska  8.6 

11  Faranga to Kumbhari  8.9 

12  NH26 to Kundaguda  10.85 

 

Page 28: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

27  

7.4. Dynamic Cone Penetrometer Test 

In‐situ strength of subgrade soils were measured using a DCP. The field CBR values estimated from 

the DCP penetration are presented below in tables ‐ 8 and 9. 

 

Table‐8: Field CBR from DCP Tests for CC Roads 

Sl No.  Road Section  Block  Field CBR (%) 

1  Khuntakata Internal Village Road  Athagarh  23.84 

2  Kuhunda Internal Village Road  Mahanga  5.43 

3  Nuasatanga Village CC road  Niali  4.66 

4  MDR‐77 (Kalika Prasad) to Muraripur  Banki Dampada  11.9 

5  NH215 to Kolimati Village (CC portion)  Anandpur  13.86 

6  Bhalukipatala Internal Village Road  Ghatagaon  4.73 

7  Durgapur to Bhaluka Nala  Jhumpura  11.02 

8  Dehuri Sahi to Juanga Sahi (CC portion)  Harichandanpur  3.77 

9  NH to Kasurpada Village Road  Kesinga  15.69 

10  Peramanji to Adibasi Pada   Th. Rampur  24.56 

11  Faranga Internal Village Road  Golamunda  17.11 

12  NH26 to Gountiapada  Kokasara  12.1 

 

Table‐9: Field CBR from DCP Tests for BItuminous Roads 

Sl No.  Road Section  Block  Field CBR (%) 

1  PWD Road to Badabhuin  Athagarh  13.47 

2  PWD Road to Basudevbpur  Mahanga  8.44 

3  Krushnaprasad to Tampada  Niali  12.38 

4  RD Road to Brahmania  Banki Dampada  20.3 

5  NH215 to Kolimati Village   Anandpur  57.28 

6  Bholabeda to Balukipatala  Ghatagaon  13.45 

7  Arsala to Chauthia  Jhumpura  21.06 

8  Dehuri Sahi to Juanga Sahi  Harichandanpur  3.55 

9  Kokomunda to Gokuleswar  Kesinga  18.52 

10  Srimaska to Sindhipadar  Th. Rampur  15.53 

11  Faranga to Kumbhari  Golamunda  9.54 

12  NH26 to Kundaguda  Kokasara  31.69 

 

 

 

Page 29: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

28  

7.5. Rebound Hammer Test results 

Surface  modulus  of  the  concrete  pavements  were  determined  using  the  rebound  hammer 

mechanism.  Tests  were  conducted  at  regular  intervals  with  three  blows  at  each  location  for  the 

entire test section. Table‐10 presents the average strength of the concrete core obtained for the test 

sections under this study. 

 

Table‐10: Strength of Concrete Roads usong Rebound Hammer 

Sec. 

No. 

Name of Road Section  Block  Strength of Concrete 

(MPa) 

1  Khuntakata Internal Village Road  Athagarh  27.24 

2  Kuhunda Internal Village Road  Mahanga  27.32 

3  Nuasatanga Village CC road  Niali  21.80 

4  MDR‐77 (Kalika Prasad) to Muraripur  BankiDampada  16.40 

5  NH215 to Kolimati Village (CC portion)  Anandpur  25.93 

6  Bhalukipatala Internal Village Road  Ghatagaon  17.19 

7  Durgapur to BhalukaNala  Jhumpura  10.90 

8  DehuriSahi to JuangaSahi (CC portion)  Harichandanpur  11.88 

9  NH to Kasurpada Village Road  Kesinga  37.65 

10  Peramanji to AdibasiPada  Th. Rampur  7.81 

11  Faranga Internal Village Road  Golamunda  11.89 

12  NH26 to Gountiapada  Kokasara  8.42 

 

 

8. LABORATORY IVESTIGATIONS 

 

8.1. Soil Strength Characterization 

Soil  samples were  collected  from each  test  section  and  tested  in  the  laboratory  to  determine  the 

Proctor compaction parameters as well as the CBR value of the soils. Table‐11 and Table‐12 present 

the results obtained from the laboratory tests carried out on the soil samples collected from CC roads 

and Bituminous roads respectively. 

 

 

Page 30: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

29  

Table‐11: Results of the Tests Conducted on Soil Samples Collected from CC Roads 

Sec No 

Name of the Road   Block  Standard Proctor Compaction Test 

Soaked CBR (%) 

OMC (%)  MDD (gm/cc) 

1  Khuntakata Internal Village Road  Athagarh  8.70  2.21  14.16 

2  Kuhunda Internal Village Road  Mahanga  11.40  1.89  5.60 

3  Nuasatanga Village CC road  Niali  10.50  1.92  6.70 

4  MDR‐77 (Kalika Prasad) to Muraripur 

Banki  14.20  1.97  4.00 

5  NH215 to Kolimati Village (CC portion) 

Anandpur  12.40  1.96  6.90 

6  Bhalukipatala Internal Village Road 

Ghatagaon  11.15  2.07  7.52 

7  Durgapur to BhalukaNala  Jhumpura  15.04  1.75  2.93 

8  DehuriSahi to JuangaSahi (CC portion) 

Harichandanpur 

9.80  1.96  9.98 

9  NH to Kasurpada Village Road  Kesinga  11.10  2.00  19.88 

10  Peramanji to AdibasiPada  Th. Rampur  14.50  1.81  4.39 

11  Faranga Internal Village Road  Golamunda  13.20  1.87  4.16 

12  NH26 to Gountiapada  Kokasara  10.80  2.00  6.41 

 

Table‐12: Results of the Tests Conducted on Soil Samples Collected from Bituminous Roads 

Sec. No 

Name of the Road Section  Block  Standard Proctors Compaction Test 

CBR Soaked (%) OMC (%) MDD (gm/cc) 

1  PWD Road to Badabhuin  Athagarh  10.60  2.12  12.31 

2  PWD Road to Basudevbpur  Mahanga  17.45  1.63  1.45 

3  Krushnaprasad to Tampada  Niali  14.50  1.97  4.08 

4  RD Road to Brahmania  Banki  13.50  2.02  17.34 

5  NH215 to Kolimati Village   Anandpur  9.20  2.05  26.86 

6  Bholabeda to Balukipatala  Ghatagaon  13.80  2.02  5.70 

7  Arsala to Chauthia  Jhumpura  11.20  2.00  4.50 

8  DehuriSahi to JuangaSahi  Harichandanpur 16.30  1.67  1.52 

9  Kokomunda to Gokuleswar  Kesinga  11.70  2.02  6.01 

10  RD Road to Sirimaska  Th.Rampur  12.10  1.97  18.21 

11  Faranga to Kumbhari  Golamunda  13.50  1.85  2.55 

12  NH26 to Kundaguda  Kokasara  15.50  1.88  3.70 

 

Page 31: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

30  

8.2. In‐direct Tensile Strength (IDT) Test results 

The cores taken from the CC road pavements were tested for its failure strength in terms of Tensile 

Strength using Split Tensile Strength test (Indirect Tensile Strength Test). Compressive strength of the 

cores  were  obtained  using  the  correlation  between  IDT  and  UCS.  The  cube  strengths  were  later 

predicted using the correlation between the cylinder strength and cube strength of cement concrete 

samples.  The  ratio of  standard  cylinder  to  cube  strength has been  taken as 0.8.  The  table  – 13 as 

given  below  presents  the  IDT,  UCS  and  the  predicted  cube  strength  values  for  all  the  samples 

collected for the CC road sections. 

 

Table‐13: Strength of Concrete Cores Taken from CC Roads 

Sec. No. 

Road Section  Block  IDT (MPa)  UCS (MPa)  Cube Strength (MPa) 

1  Khuntakata Internal Village Road 

Athagarh  1.5‐3.4  15‐34  18.8‐42.5 

2  Kuhunda Internal Village Road  Mahanga  1.4‐3.2  14‐32  17.5‐40.0 

3  Nuasatanga Village CC road  Niali  1.9‐2.9  19‐29  23.8‐36.2 

4  MDR‐77 (Kalika Prasad) to Muraripur 

BankiDampada  1.45‐2.52  14.5‐25  18.1‐31.5 

5  NH215 to Kolimati Village (CC portion) 

Anandpur  2.68‐3.23  27‐32  33.5‐40.4 

6  Bhalukipatala Internal Village Road 

Ghatagaon  1.00‐2.38  10‐24  12.5‐29.8 

7  Durgapur to BhalukaNala  Jhumpura  1.95‐2.66  19‐27  24.4‐33.3 

8  DehuriSahi to JuangaSahi (CC portion) 

Harichandanpur  1.69‐2.01  17‐20  21.1‐25.1 

9  NH to Kasurpada Village Road  Kesinga  2.43‐2.94  24‐29  30.4‐36.8 

10  Peramanji to AdibasiPada  Th. Rampur  0.84‐1.86  8.4‐18.6  10.5‐23.3 

11  Faranga Internal Village Road  Golamunda  0.78‐0.88  7.8‐8.8  9.8‐11.0 

12  NH26 to Gountiapada  Kokasara  0.65‐0.67  6.5‐6.7  8.2‐8.4 

 

9. ANALYSIS AND DISCUSSION 

9.1. Strength of Concrete Pavements 

This  is  to mention  that  the  strength  of  top  concrete  layer  in  CC  road  pavement  is made  of  1:2:4 

cement concrete, that corresponds to a characteristic compressive strength of 20 MPa. From Fig.21, 

it may be observed that more than half of the CC road sections are not meeting the desired strength 

of 20 MPa. This indicates that adequate quality control in material selection and during construction 

has not been done by the executing agency. 

Page 32: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

31  

 

 

Fig.21. Results of rebound hammer test conducted on CC Road Pavements 

 

The average indirect tensile strength of the concrete, assessed through the cores taken from CC road 

pavements are presented in Fig.22. The tensile strengths of the concrete samples were found to be 

less compared to the requirement to meet the stresses generated under standard axle load. 

 

 

Fig.22.  Results of IDT tests conducted on the Cocrete Cores 

 

Fig.23 shows the predicted cube strength of the concrete estimated from the strength of the cores 

taken from the CC road pavements. 

0.00

5.00

10.00

15.00

20.00

25.00

30.00

35.00

40.00

S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12

Strength (MPa)

Section No.

Rebound Hammer Test

0

0.5

1

1.5

2

2.5

3

3.5

4

1 2 3 4 5 6 7 8 9 10 11 12

IDT (M

Pa)

Section No.

Indirect Tensile Strength on Cores

Page 33: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

32  

 

 

Fig.23. Predicted Cube Strength of Concretes 

 

It may be observed from the graph that, except three sections (i.e. Sections 11 and 12), the average 

cube  stength  of  all  the  concrete  samples  are more  than  15 MPa.  This  is  to mention  that,  though 

these values differ from rebound hammer test results, the results obtained from testing of cores are 

considered to be more accurate than the rebound hammer, as  it gives the surface hardness of the 

concrete. 

 

9.2. Roughness of Pavement Surfaces 

Roughness  (in  terms of  IRI)  of  the CC  road  sections  are presented  in  Fig.24.  The  roughness  values 

were found to be high for most of the sections due to presence of badly constructed and maintained 

joints and uneven pavement surfaces indicating bad workmanship. 

 

Roughness of the bituminous road surfaces may be attributed to local depressions, rutting, raveling 

and potholes. The roughness values observed for the bituminous road surfaces are presented in Fig. 

25. 

0.0

5.0

10.0

15.0

20.0

25.0

30.0

35.0

40.0

45.0

1 2 3 4 5 6 7 8 9 10 11 12

Strength (MPa)

Section No.

Predicted Cube Strength

Page 34: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

33  

 

Fig.24. Roughness of CC Road Sections 

 

 

Fig. 25. Roughness of Bituminous Road Sections 

 

9.3. Life of CC Road Pavements 

As observed  from the  structural  condition of  the various CC Roads constructed  in different phases 

and  under  different  schemes  and  taking  into  account  the  quality  control  measures  during  the 

construction process,  it may be stated that the  life of such pavements would not be more than 10 

years. As mentioned, in rural roads manual, the life of bituminous roads constructed as per PMGSY 

0

2

4

6

8

10

12

14

1 2 3 4 5 6 7 8 9 10 11 12

Rough

ness (IRI)

Section No.

Roughness of CC Road Surfaces

0

2

4

6

8

10

12

14

1 2 3 4 5 6 7 8 9 10 11 12

Rough

ness (IRI)

Section No.

Roughness of BT Road Surfaces

Page 35: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

34  

guidelines is also 10 years, in which one carpeting layer is to be done after 5 years along with regular 

annual maintenance. 

 

9.4. Life Cycle Cost Analysis 

Flexible Pavements have been  the preferred choice because of  low  initial  cost as compared  to  the 

Rigid Pavements. The superiority of rigid pavements over flexible pavements is well recognized world 

over. Initial cost of the concrete pavement on rural link roads is more by about 25% over the flexible 

pavement,  but  in  lifecycle  costing,  concrete  pavement  has  proved  to  be  economical  over  flexible 

pavement.  

 

9.4.1. Initial Cost 

This  is  the  cost  of  construction  of  the  pavement,  which  mainly  depends  upon  the  pavement 

thickness, governed by the strength of subgrade soiI and traffic loading, cost of materials and cost of 

execution of the work.  

 

9.4.2. Maintenance Cost 

The maintenance cost includes the maintenance of pavement during the design life of pavement to 

keep the pavement at the specified service level.  

 

9.4.3. Life Cycle Cost Analysis 

The choice of the appropriate economically advantageous pavement type,  flexible or rigid,  is made 

by carrying out Life Cycle Cost (LCC) analysis which takes into account the initial investment cost and 

also  the maintenance/rehabilitation  cost over  the design  life of  the pavement  structure.  Life  cycle 

cost analysis can be defined as a procedure by which a pavement design alternative is selected, that 

provides  a  satisfactory  level  of  service  at  the  lowest  cost over design  life.  The  selection  criteria of 

type  of  pavement,  flexible  or  rigid,  should  be  based  not  on  the  initial  cost  of  construction,  but 

lifecycle  cost, which  includes  the  discounted maintenance  and  pavement  strengthening  costs  that 

are  incurred  during  the  design  Iife  of  the  pavement.  The  economic  analysis  methods  used  most 

commonly for this purpose include present worth, annualized cost, and rate of return. The analysis is 

most sensitive to the factors of inflation, discount rate, and analysis period. 

 

9.4.4. Flexible Pavement Design and Cost of Construction per km 

The  design  of  flexible  pavements  depends  upon  the  CBR  value  of  sub  grade  and  number  of 

commercial vehicles per day that will use the road during its design life, which is 10 years for Rural 

Page 36: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

35  

Roads. A  typical pavement composition based on SP:72‐2015 and  its  cost  for  rural  roads with CBR 

value of 3 to 4 and traffic T3 category is given below: 

GSB      = 175 mm 

WBM      = 150 mm 

Premixed Carpet   = 20 mm 

The cost of the above 3.0 m wide pavement will thus be about Rs.23.03 lakhs per km. 

 Table‐14 : Rate of Materials in Bitumnous Road Pavement Construction used for Analysis 

Sl No.  Item  Dimension  Unit  Rate (Rs.) 

1  Granular Subabse  175 mm Thick  Cum  1000 

2  Water Baound Macadam  150 mm Thick  Cum  2500 

3  Premixed Carpet with other  layers such 

as Prime coat, Tack coat and seal coat 

20 mm Thick  Sqm  200 

 

9.4.5. Maintenance Cost of Flexible Pavement 

• It  has  been  assumed  that  one  layer  of  WBM  (75  mm)  will  be  laid  every  10th  Year  after 

construction. 

• Surface renewals (20 mm Premix Carpet) are to be provided once in every 5 years. 

• The  cost  of  ordinary  repairs  for  rural  roads with  bituminous  pavement  has  been  taken  as 

Rs. 20, 000 per year (average) for analysis. 

 

9.4.6. Cost of Construction of CC Road per km. 

The section considered for analysis has been taken as given by Panchayati Raj Department for non‐

expansive soil area. This consists of the following configuration: 

Sand       : 100 mm 

PCC 1:3:6 (M10)  : 100 mm  

PCC 1:2:4 (M15)  : 100 mm 

 

Table‐15: Rate of Materials used in CC Road Pavement Construction 

Sl No.  Item  Dimension  Unit  Rate (Rs.) 

1  PCC 1:2:4  100 mm Thick  Cum  4800 

2  PCC 1:3:6  100 mm Thick  Cum  3800 

3  Sand  100 mm Thick  Cum  400 

4  Cut off (both side)  300 mm x 225 mm  Cum  3800 

Page 37: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

36  

 

As per PRI department estimate, The cost of above pavement composition will be about Rs. 32.3 lakh 

per km. 

 

9.4.7. Maintenance Cost of Rigid Pavement 

The average yearly maintenance cost of rigid pavement willbe about Rs. 10,000/‐ per km for a single 

lane  rural  road  tocover  filling  of  sealing  compound  in  the  joints,  repairs  ofconcrete  spalling  etc. 

Rehabilitation/  strengthening of  the CC Road pavement has been proposed after 10 years with 75 

mm of cement concrete (1:2:4). For a 3.0 m wide road this cost will be Rs. 3.60 lakhs per km using the 

rate of concrete adopted for life cycle cost analysis. 

 

9.4.8. Life Cycle Cost Analysis 

Period of  analysis  has been  considered as  20  years,  being  the design  life of  concrete  pavement  in 

rural  area.  The  discountrate  of  10%  has  been  taken.  Inflation  rate  of  5%  has  been  considered  for 

future rise in prices of materials. 

 

Cost Estimate: 

1. Initial Cost of Flexible Pavement = Rs. 23.05 lakh per km 

2. Initial Cost of Rigid Pavement = Rs. 32.30 lakh per km 

3. Annual Maintenance of flexible pavement= Rs. 0.20 lakh per km. 

4. Renewal of wearing course of flexible pavement is considered in every 5 years. In 5th and 15th 

year after completion, renewal cost = 200 x 3.00 x 1000= Rs. 6.00 lakhs 

5. Strengthening with WBM and pre‐mix carpet every 10th year: 

WBM 75 mm = 0.075 x 3.00 x 1000 x 2500 = Rs. 5.625 lakhs 

PC 20mm = 200 x 3.00 x 1000= Rs. 6.00 lakhs 

Total Cost= Rs. 11.625 lakhs 

6. Average maintenance cost of CC road pavement is Rs.0.10 lakh per year 

7. Rehabilitation/  strengthening  of  the  concrete  pavement  after  10  years  with  75  mm  of 

cement concrete 1:2:4 = Rs. 10.80 lakhs per km. 

 

DATA ASSUMPTION: 

Analysis Period    : 20 Years 

Discount Rate    : 10% 

Inflation Rate     : 5% Per Year 

Page 38: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

37  

 

Cost (Rs. In Lakhs) Per Km.   

          Bituminous Pavement    CC Road Pavement 

Construction Cost        23.03        33.20 

Routine Maintenance/Year      0.20 (avg)      0.1 (avg) 

Renewal (5 Years)        6.00        ‐ 

Strengthening (10 Years)      11.625        10.80 

 

Table‐16: Life Cycle Cost Analysis of Bituminous and Concrete Pavement 

Year  Bituminous Road Pavement  CC Road Pavement 

Const. Cost  Maint. Cost  NPV  Const. Cost  Maint. Cost  NPV 

0  23.03  ‐  23.03  32.30  ‐  32.30 

1    0.2  0.18    0.11  0.00 

2    0.22  0.18    0.11  0.09 

3    0.23  0.17    0.12  0.09 

4    0.24  0.17    0.12  0.08 

5    7.66  4.75    0.13  0.08 

6    0.27  0.15    0.13  0.08 

7    0.28  0.14    0.14  0.07 

8    0.30  0.14    0.15  0.07 

9    0.31  0.13    0.16  0.07 

10    18.94  7.30    17.59  6.78 

11    0.34  0.12    0.17  0.06 

12    0.36  0.11    0.18  0.06 

13    0.38  0.11    0.19  0.05 

14    0.40  0.10    0.20  0.05 

15    12.47  2.99    0.21  0.05 

16    0.44  0.10    0.22  0.05 

17    0.46  0.09    0.23  0.05 

18    0.48  0.09    0.24  0.04 

19    0.51  0.08    0.25  0.04 

20    0.53  0.08    0.27  0.04 

Total NPV Cost  40.22    40.29 

*All amounts are mentioned in Rupees (in lakhs) 

Life Cycle cost of flexible pavements and rigid pavements wiII be almost same for a  service life of 20 

years. 

 

Page 39: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

38  

9.4.9. Economic Analysis 

The details of economic analysis based on net present worth method,  i.e., net present value of total 

construction cost and maintenance cost over the analysis period of 20 years are provided in Table‐17 

for flexible and rigid pavement. The summary of Initial and Life Cycle Costs are given below: 

 

Table‐17: Summary of Initial and life Cycle Cost 

Sl No.  Pavement Type  Initial Cost (Rs. In 

Lakhs) 

Life Cycle Cost (for 20 yrs period) 

(Rs. In Lakhs) 

1  Flexible/bituminous  23.03  40.22 

2  Rigid/concrete  32.30  40.29 

 

• The Iife cycle cost of a concrete pavement (as per present practice) for construction/maintenance 

costs is approximately same to bituminous pavements considering an anlysis period of 20 years. 

• From the above, it can be concluded that although the initial cost of concrete pavement is higher, 

the life cycle cost is at par with bituminous pavement considering a 20 years of period of service life. 

•  Besides,  life  cycle  cost  consideration,  several  sites  demands  for  concrete  pavement  from 

climatic/environmental  considerations  such  as  locations  in  heavy  rainfall/waterlogged  areas,  road 

stretch  passing  through  village  portion  or  sub‐grade  soil  having  low  CBR  values.  Some  of  these 

advantages are mentioned in para 9.5. 

 

9.5. Suitability of Pavement Surface (Concrete vs Bituminous) 

The following points favour the selection of concrete roads for rural areas: 

Concrete roads are more durable than bituminous roads.  

Frequent repairs are not needed for concrete roads when compared to bituminous roads.  

Concrete roads are less affected by the drainage condition of the road 

No  ruts  form  in  concrete  pavements  and  also  no  potholes,  therefore  smoother  ride  in  wet 

weather conditions. 

Concrete  pavements  are  common  choice  for  regions  subjected  to  an  aggressive  natural 

environment and also for steep slopes. 

Extreme weather  conditions  are  liable  to  cause more damage  to  asphalt  roads  than  concrete 

roads. 

When looking at the environmental aspects, concrete  is the better option as bitumen produce 

polluting gases when heated at very high temperature. 

 

Page 40: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

39  

The following points favour the selection of bitumen surfaced roads: 

When comparing the cost, concrete roads come with a higher initial paving cost than bituminous 

roads.  

Maintenance  is  easier  with  asphalt  roads.  Maintenance  of  a  part  of  the  bituminous  road  is 

possible. Moreover, these roads can be re‐layered, which is not very convenient with concrete 

roads. 

Bituminous roads provide a smooth riding surface compared to concrete roads due to absence 

of joints. 

When compared  to concrete  roads, bituminous  roads have better  skid  resistance and provide 

good traction providing better safety condition. 

 

10. CONCLUSIONS AND RECOMMENDATIONS 

10.1. Conclusions 

The following conclusion may be drawn from the present study: 

The quality of construction of the concrete pavements were found to be poor at some locations. 

There is no provision for shoulder construction under this scheme. Good shoulders will reduce 

edge damage significantly and also will improve the safety condition of the road. 

Finishing of the CC road surfaces with proper camber was not observed, which may be due to 

lack of expertise among the persons taking up such  works. 

Out of  the  twelve CC  road  sections  considered  in  this  study,  compressive  strength of  the  top 

concrete layers for nine sections met the desired strength corresponding to the specified mix. 

Roughness of  the CC were found to be high due to unevenness of  the pavement surfaces and 

badly constructed and maintained joints. 

Bituminous pavements are providing smooth riding surface than the concrete pavements. 

Higher roughness  for some bituminous roads were observed due to  local settlements,  rutting, 

raveling and potholes of different severity level. 

Drainage condition of the roads was found to be affecting road performance significantly. 

Subgrade strength as well as the quality of materials used in pavement construction were found 

to affect the pavement performance to a large extent. 

As per the present practice of CC road construction, the life of pavements can be expected to be 

10 years, if properly constructed. 

From  the  life  cycle  cost  analysis,  it  was  observed  that,  life  cycle  cost  of  rigid  pavement 

constructed under the CC road schemes compares well with typical flexible pavement structures 

adopted for rural roads considering a 20 years of service life. 

Page 41: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

40  

 

10.2. Recommendations: 

The standard of concrete pavement construction needs to be improved in the following manner: 

As these roads are usually constructed in thickly habitated village portions which are prone 

to drainage problems, concrete pavements are more suited to these conditions. 

Width  of roads needs to be at least one lane, i.e. 3.75 m.  

Adhoc  design  approaches  need  to  avoided  and  IRC  guidelines  should  be  followed  for 

rational pavement design. 

Proper drainage measures (i.e. side drains and cross drains) should be provided to ensure 

better performance of the roads.  

Shoulders  should  be  provided  to  reduce  edge  failures  and  improve  safety    of  the  roads 

avoiding sudden edge drops. 

Grades of the concrete should be mentioned in the guidelines instead of the corresponding 

mix  proportion  as  per  nominal  mix.  Quality  or  grade  of  concrete  surface  (top  concrete 

layer)  may  be  adopted  as  per  the  rural  roads  manual  (i.e.  M30),  to  address  the  tensile 

stresses  in  the  concrete  under  standard  axle  loading.  However,  considering  the  present 

performance  of  the  1:2:4  concrete,  this may  still  continue  to  be  adopted  for  light  traffic 

conditions with proper quality conctrol mechanism.  

Interdepartmental co‐ordination should be ensured for utilisation of field laboratories of RD 

and  PWD  departments  considering  the  fact  that,  PRI  department  does  have  its  own 

laboratory facility at block levels. 

As per  the mandate of  this programe, construction of such roads are usually  taken up by 

village  level  leaders,  who  generally  lacks  technical  expertise  in  executing  such  works. 

Therefore,  capacity  building  of  the  supervisors  and masons  should  be  taken  up  at  block 

level.  Cement manufactures  like  Ultratech,  ACC  etc.  can  be  roped  in  for  this  as most  of 

them  undertake  such  capacity  building  programs  for  masons/technicians.  It  is  also 

suggested  to develop a construction manual  in  local  language  (Odia) with simple drawing 

and sketches.  

A quality assurance cell may be developed to ensure good quality in construction. 

For  light  traffic  conditions,  interlocking paver  blocks  should  be used  for making  concrete 

pavements, which has the advantage of high quality products with lesser supervision effort.  

Also,  new  low  cost  concrete  pavement  technologies  like  cell  filled  concrete  pavement 

(developed  by  IIT  Kharagpur)  and  paneled  concrete  pavements,  can  be  adopted  to  build 

concrete roads at a lower cost. 

Page 42: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

41  

11. PHOTOGRAPGHS 

 

     

 

 

    

 

 

     

 

Photographs taken during Field Investigations at Anandpur, Keonjhar 

Page 43: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

42  

 

     

 

 

     

 

 

     

 

Photographs taken during Field Investigations at Ghatagaon, Keonjhar 

 

 

Page 44: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

43  

 

     

 

 

     

 

 

     

 

Photographs taken during Field Investigations at Harichandanpur, Keonjhar 

 

Page 45: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

44  

 

     

 

 

     

 

 

     

 

Photographs taken during Field Investigations at Jhumpura, Keonjhar 

 

 

Page 46: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

45  

 

     

 

 

     

 

 

     

 

Photographs taken during Field Investigations at Athagarh, Cuttack 

 

Page 47: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

46  

 

     

 

 

     

 

 

      

 

Photographs taken during Field Investigations at Banki‐Dampada, Cuttack 

 

Page 48: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

47  

 

     

 

 

     

 

 

     

 

Photographs taken during Field Investigations at Niali, Cuttack 

 

Page 49: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

48  

 

     

 

 

     

 

 

     

 

Photographs taken during Field Investigations at Mahanga, Cuttack 

 

 

Page 50: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

49  

 

     

 

 

    

 

 

     

 

Photographs taken during Field Investigations at Kesinga, Kalahandi 

 

Page 51: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

50  

 

     

 

 

     

 

 

     

 

Photographs taken during Field Investigations at Golamunda, Kalahandi 

 

 

Page 52: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

51  

 

   

 

 

     

 

 

    

 

 

Photographs taken during Field Investigations at Th. Rampur, Kalahandi 

Page 53: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

52  

 

     

 

 

     

 

 

     

 

Photographs taken during Field Investigations at Kokasara, Kalahandi 

 

 

Page 54: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

53  

 

 

 

 

 

 

 

Annexure‐I 

Page 55: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

Government of Odisha PANCHAYATlRAJ DEPARTMENT

No. 17-STGR-22-2049- LjO 7/; /PR

From

To

Smt. Aparajita Sarangi, lAS Commissioner-cum-Secretary

All Collectors All PO, ORDAs All BOOs

By fax/e-ma il

~OO 9OOI1£),

900110, fl16. ~6'6I1~-'m 00 ~

Odisha Secretarial Sachibalaya Marg, 8hubaneswar-751001

T,I-0674-2536680, 2322875 Fax, 0674-2391413.

£[email protected]

Date: 7-/1; }:;I- ,;tl'/..3

Sub : Comprehensive Guidelines for Cement Concrete Road Scheme.

Madam/Sir,

I am enclosing herewith the Resolution No.3984/PR of 07th

February, 2013 along with enclosures (Plan, Design and Estimate in

Annexure 'A ' & ' B ') for information and necessary follow up action . The

copy of the same may be made available to each GP with technica l

speCification and quality control for their information and perusal.

Your faithfully,

~16pages.

Page 56: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

L

- .

Gove rnment of Odisha Panchayati Raj Department

No. 39 2$ It / STGR-22-204 9 dt. 0 70'1 .!3

RESOLUTION

Sub: Comprehensive guidelines for 'Cem ent Concrete Road Scheme'.

The Panchayati Raj Department, Government of Odisha have taken

initiative in the past for construction of Cement Concrete Road in the village

under various schemes in order to improve the quality of life and hygienic

conditions in the v illages. It has become a very popular scheme and one of the

most sought after schemes in the rural areas. In t he past , though cement

concrete roads were taken up under different schemes, all the villages have not

yet been covered. The State Government has decided to give thrust to the

scheme for construction of intra village cem ent concrete roads in the villages

with the objective of attaining saturation in the State w ith special focus on PVTG

(Particularly Vulnerable Tribal Groups) / ST / SC habitations.

2. Fund Allocation & Implementing Agency-GP is treated as a unit for the purpose of planning. Funds will be allocated

to the Blocks each year depending upon number of GPs.

Block will be the implementing agency fo r the purpose. For Administrative

Approval and Technical Sanction the procedure and delegation of power as

enumerated under the Panchayat Samiti Accounting Procedu re Ru les, 2002 shall

be followed.

3. Flow of Funds: i) Provision of no lakhs per GP is envisaged in the scheme.

ii) Out of no lakhs, ~2 . 00 lakhs shall be given out of 'Devolution of

funds' provided to t he GP under the 3rd State Finance Commission and

balance ~8.00 lakhs shall be provided under the State Plan.

Page·lo(6

Page 57: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

.z.:,.'y!,,,-~ ... ~ --7'

/' / ,.

iii) Funds from other sources namely Stote Plan, Centrally Sponsored

Schemes, Centra l Schemes, Externally Aided Projects can be converged

with this scheme.

4. Target: Certain no. of villages will be taken up each year w.e.f. 01.04.13 in a

need based man ner with an aim to cover all villages under the scheme with a

definite time frame with focus on habitation of weaker and most vulnerable

sections of society in convergence with other schemes.

5. Selection of Villages: i) Grama Panchayat will select t he proj ects for each Panchayat keeping in

view the need of the area out of the project list prepared and passed by

Palli Sabha and Grama Sabha during Grama Sabha Shasaktikaran

Karyakram (GSSK). GSSK list will be used for shortlisting projects for a

period of three years w.e.f. 2013 .14 on till it gets exha usted, whichever is

earlier.

ii) The Grama Panchayat is authorized to select the villages / projects to

be taken up in their Grama Panchayat area in the fo llowing manner.

a) The villages / habitations inhabited by Particularly Vulnerable

Tribal Groups (P.V.T.Gs) with no coverage of Cement

Concrete Road should be given first preference.

b) P.V.T.G. vi llages partially covered with Cement Concrete

Roads shall get second priority .

c) After covering habitations falling under category (i) and (ii)

above, vil lages inhabited by Schedu led Tribes in majority with

no coverage of Cement Concrete Road wi ll be considered.

d) ST villages partially covered with Cement Concrete Roads

shall be given next priority.

e) After covering habitations falling under categories mentioned

above, villages of SC Community with no coverage of Cement

Concrete Road shall be considered.

Page-2o(6

Page 58: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

1

-7

f) SC vi llages partially covered with Cement Concret e Roads

shall be given next priority .

g) If all t he vi llages / hab itations fall ing under the above

categories have been covered villages / habitations belong ing

to other category shall be considered giving preference to

habitations, with more population having no coverage of

Cement Concrete Road.

h) In other habitations, the Cement Concrete Roads should be

planned for execution f rom the ST / SC Basti towards t he

main habitation and not vice versa.

i) The villages belonging to other category already covered with

500 meters or more of Cement Concrete Roads should not be

ordinarily conside red under this scheme.

6. Preparation of Annual Action Plan: i) Grama Panchayat shall draw up a perspective plan by listing all the

habitations / villages for their Grama Panchayat in t he order of priority

described above out of project list prepared and passed by Palli Sabha

and Grama Sabha during GSSK-2012.

ii) The Annual Action Plan should be drawn up out of t he perspective plan

so prepared keeping in view the availability of resources. Only after

., coverage of all the habit ations / villages mentioned in the category (i)

above, category (ii) cases will be included in the plan . Sa me logic shall

apply for category (iii ) and subsequently category (iv) and other villages.

iii) List of projects f inalized by the Grama Panchayat as envisaged in

Para - 5 shall be scrutinized by BDO and submit ted to the Co llector for his

approval.

iv) Collector shall draw up a holistic plan Grama Panchayat wise taking

into consideration t he likely f low of fund under various schemes and

possibility of convergence.

Poge-30f6

Page 59: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

.....l

T .... T~ JT :---, .. .-"

'" r

v} If some port ion of the villages has already been covered with Cement

Concrete Road earlier, the balance port ion can be taken up out of this

scheme.

vi) There should be complete t ransparency in the choice of project and

location. The prioritized list of proj ects and the reasons for taking up

those projects including the crit eria for choice of locations must be

reflected in the Grama Panchayat Pla n and be made available in the

district website as well as website of Panchayati Raj Department . . vii) Every year, the Action Pla n consisti ng of the list of villages to be

taken up, population of t he village with specific reference to PVTG, ST /

SC and the project cost for each project shall be prepared by Grama

Panchayat following the proced ure prescribed above and submitted to

Collector by 31st January to be considered for the next Financial Year.

Collector shall ensure approval of the Action Plan based on the principles

enunciated in Para-S above and communicate the same to the respective

Grama Panchayat latest by 28th / 29th February with a copy to Block

Development Officer.

viii) As soon as the f irst installment of the allocation is received by the

Blocks, they should issue Work Orders to the already identified VLLs as

per the approved action plan for the year.

7. -Execution of Work: i) The works shall be executed by VLL selected by Pa lli Sabha.

ii) Cost of each project shall not be less than ~2 lakhs. In case the project

cost is less than ~2 lakhs. special permission shou ld be obtained from

Collector with proper Justification .

iii) In case a project selected by Grama Panchayat cannot be executed

due to some reason or the other it can be diverted to next prioritized

project in the Grama Panchayat with prior approval of Collector.

iv} Overall responsib ility for implementation of the Scheme shall lie with

Collector and Project Director of DRDAs and they shall be wholly

responsible for effective and timely implementation of the scheme and Paqe-40{6

Page 60: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

, n

utilization Df funa. The PD, DRDA snail furn ish Monthl\" Progress Report

(MPR) on Financial and Physical achievements of t he schem e to

Panchayati Raj Department by the 5t h of every month from t he

preceding months.

8 . Quality Control, Inspect ion and Supervision Mechanism: i) The District Administration shall be ensuring construction of good

quali ty of roads. The Assistant Engineer of the Block shall check 100% of all

Cement Concrete Road fo llowed by 10% by Addl. PD (Tech.), 5% by PD, DRDA

and 1 % by Collector and District Mag istrate. The mO'del estimates, design along

with technica l specifications are attached at Annexure 'A' & ' 8 '.

ii) Non-negotia ble items.

a) The width of t he road shall be 3-3.5 meters with expansion joint

on each 5 meters interva l.

b) During casting of concrete like e.e. (1: 3 :6) (metal concrete) &

c.c. (1:2:4) (ch ips concrete) plate v ibrat or shall be used.

Without plate v ibrator no casting of concrete will be made.

c) If the length of the road is more than 100 meter then 8 - 10

tons' roller shall be used for compacting t he sub-base.

d) Efforts should be made for 3% camberi ng of t he road.

e) Minimum seven days curing fo r the concrete road shall be made

and the concerned JE / GPTA has to ensure it .

f) The concerned JE / GPTA shall verify the site personally and

according ly prepare the drawing of the concrete road as per the

approved plan.

g) During casti ng of concrete the concerned JE / GPTA shall be

personally present on the work site and as per his / her direction

mixture of concrete will be prepared.

h) The Assistant Engineer of Block shall visit at least once every

concrete road during casting ofe.e. (1:3 :6) &e.c. (1:2:4) .

Page-S 0{6

Page 61: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

/ / .

, I'

9. Social Aud it: Social Audit and Vigilance shall be encouraged at grass roots level.

Collector of the district shall also prepare schedules of inspection which

prescribed the minimum number of field visits for each supervisory level

functionary and shall ensure that the inspection schedules are faithfully followed

by supervisory level functionaries.

10. Other Matters: Panchayati Raj Department shall be responsible for clarifying doubts, if

any, and ensure that the bottlenecks in the implementation of the scheme are

removed as expeditiously as possible and communicated to all concerned.

11. The Resolution No.25997-II-Dev-6/2010 dt. 4th September, 2010 is

hereby superseded. The present Resolution will be effective from 1st April,

2013.

Order-Ordered that this Resolution be published in the Extraordinary Gazette of the

Government of Odisha for general information and copy be communicated to

all the Departments of Government and other concerned.

By order of he Governor

APARAJI

Commissio um-Secretary

to GOV1fTi'\

Page-60(6

Page 62: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

TYPICAL CROSS SECTION OF CEMENT CONCRETE ROAD

( 3.0M WIDE IN BLACK COTTON SOIL AREA)

EARTH FILLING

100MM THICK C.C (1 :2:4) 100MM THICK C.C ( 1 :3:6)

200MM THICK SAND FILLING 3.0% SLOPE_

GROUND LEVEL

ALL DIMINESIONS ARE IN MM

ESTIMATED COST :-RS 33.20 LAKHS/KM

~\'\~ ~

EARTH FILLING

I '. •

;,

ANNEXURE:-A

(£' .,)

Page 63: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

Length 1000.00 Mtr Width 3.00 MIT

A Estimate for the Work, " Construction of CC road with off wall ( 3.0 M wide In Black cotton soil

Est.Cost - Rs 3320000.00

Item of Worl<

Fme dressing of eanh

work in ordinary or hard

soi l in road formaton

according to the direction

of the department including

cutting or filling eanh upto 0.15m depth of surface.

1 x 1000.00 X 3.000 X 3000.00 Sqm

@ Rs 153.00 1100 Sqm Rs 4590.00 2 Earth work in exavation in

hard soil with initial lead and lift including dressing &Ievelling the foundation bed and depositing the exavated earth away from work site etc. complete.

Cu1 off wall 2 x 1000.00 X 0.225 X 0.15 67.50 Cum

67.50 Cum @ Rs 78.95/cum Rs 5329.00

3 Filling foundation and plinth with sand well watered and rammed etc. complete.

C.C.Road Base ;- 2 x 1000.00 X 1.275 X 0.22 567.38 Cum Cut off wall 3x 1000.00 X 0.225 X 0.05 = 33.75 Cum

601 .13 Cum @ Rs 237.01 leum Rs 142474.00

4 Cement concrete of prop.(1 :3:6) using 4cm. Size H.G.(C.8':) metal in foundation etc. complete.

C.C.Road 1 x 1000.00 X 2.55 X 0.10 = 255.00 Cum Cut off wall 2x 1000.00 X 0.225 X 0.40 = 180.00 Cum

435.00 Cum @ Rs 3575.95 leum Rs 1555540.00

5 Cement Concrete of prop. (1 :2:4) using 12 mm size Cr.b.h.g. chips including cost of all materials & labour T&P etc. complete.

C.C.Road (Wearing Coat) :- 1 x 1000.00 X 3.00 X 0.10 300.00 Cum 300.00 Cum

@ Rs 4636.34 leum Rs 1390902.00 7 Rigid and smooth centering

and shuttering etc

2x 1000.00 X 0.30 600.00 sqm 2 x 1000.00 X 0.40 800.00 sqm

1400.00 sqm @ Rs 68.20/Sqm Rs 95480.00

8 Hire charges of vibrator Total concrete = 735.00 Cum

~,~:?

Page 64: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

.L

")

& Provid ing Salilex Board to the expansion joints

10 Earth work in ordinary soil with 5 KM mechanical carriage etc

Side berm filling

11 Add for unforseen item if any

12 Add Cess :-

13 Provision for Display Board 14 Add W.C.

@2.5 Cumlhr; 294.00 Hrs

@ Rs 106.00/Hr Rs 12466.00

200 x 3.00 x 0.10 ; 60.00 Sqm

or 5.574 sqm

@ Rs 593.00/sqm Rs 3305.00

2 x 1000.00 X 0.25 X 0040 200.00 Cum

@ Rs 151.90 /cum

L.S (Subject to actual)

Or Say

Rs 30380.00

LS 5000.00

Rs 33200.00 Rs 5000.00 Rs 33200.00 Rs 3316866.00

Rs 3320.000.00

I I

"

Page 65: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

TYPICAL CROSS SECTION OF CEMENT CONCRETE ROAD WTH cun OFF

( 3.0M WIDE IN HARD SOIL AREA)

OOMM THICK C.C ( 1 :2:4) 1 OOMM THICK C.C ( 1 :3:6)

OOMM THICK SAND FILLING

GROUND LEVEL

EARTH FILLING

ALL DIMINESIONS ARE IN MM

ESTIMATED COST :-RS 32.30 LAKHS/KM

~~~ ~)

EARTH FILLING

'" ....,

ANNEXURE:-B I

..r ~

-

r

Page 66: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

length 1000.00 Mtr Width 3.00 Mtr

B Estimate for the Worle, " Cons truction of CC ,·oad with off wall ( 3.0 M wide In Hard soil area).

Est.Cost -SJ.

Item ofWotX No

Fine dressing of earth work in ordinary or hard soil in road formaton according to the direction of the department

including cutting or filling earth upto O.l5m

depth of surface.

1 x 1000.00 X 3.000 X 3000.00 Sqm

@ Rs 153.00 1100 Sqm Rs 4590.00 2 Earth work in exavation in

hard soil with initial lead and lift induding dressing &Ievelling the foundation bed and depositing the exavated earth away from work site etc. complete.

Cut off wall 2x 1000.00 X 0.225 X 0.25 112.50 Cum

112.50 Cum

@ Rs 78.95 /cum Rs 8882.00 3 Filling foundation and pfinth

with sand well watered and rammed etc. complete.

C.C.Road Base ;- 2x 1000.00 X 1.275 X 0.12 312.38 Cum Cut off wall 3x 1000.00 X 0.225 X 0.05 33.75 Cum

346.13 Cum

@ Rs 237.01 lcum Rs 82037.00 4 Cement concrete of

prop.(l :3:6) using 4cm. Size H.G.(C.B.) metal in foundation etc. complete.

C.C.Road 1 x 1000.00 X 2.55 X 0.10 255.00 Cum Cut off wall 2x 1000.00 X 0.225 X 0.40 180.00 Cum

435.00 Cum @ Rs 3575.95 lcum Rs 1555540.00

5 Cement Conaete of prop. (1 :2:4) using 12 mm size Cr.b.h.g. chips including cost of all materials & labour T&P etc. complete.

C.C.Road (Wearing Coal) :- 1 x 1000.00 X 3.00 X 0.10 300.00 Cum

300.00 Cum @ Rs 4638.34 lcum Rs 1390902.00

7 Rigid and smooth centering and shuttering etc

2x 1000.00 X 0.30 600.00 sqm 2x 1000.00 X 0.20 400.00 sqm

1000.00 sqm @ Rs 68.20/Sqm Rs 68200.00

8 Hire charges of vibrator Total concrete = 735.00 Cum

@2.5 Cumlhr 294.00 H", @ Rs 106.00 IHr Rs 12468.00

9 Providing Salitex Board to the expansion jOints

*\'I';)P\~

Page 67: FINAL REPORT - Odisha _Road.pdf · 2019-03-15 · and blocks spread across the state to prepare a list of 12 CC roads and 12 bituminous roads for ... The report presents a detailed

10 Earth wor1< in ordinary soil 'Nith 5 KM mechanical carriage etc

Side berm filling

11 Add for unforseen item if any

12 Add Cess :-13 Provision for Display Board

14 Add W.C.

200 x

2 x

3.00

@

1000.00 @

x

Rs

X Rs

0.10 =

593 .00/sqm

0.25 X 151.90 lcum

L.S (Subject to actual)

60.00

0.30

Sqm or

Or

5574

150.00 Cum

Say

sqm Rs 3305.00

Rs 22785.00

LS 10000.00

Rs 32300.00

Rs 5000.00 Rs 32300.00 Rs 3228307.00

Rs 3230000.00