final report for rosemount / empire / umore area ......final report for rosemount / empire / umore...
TRANSCRIPT
Final Report for
Rosemount / Empire / Umore AreaTransportation System Study
In Collaboration with
Dakota County, Rosemount, Empire Township, University of Minnesota&
Minnesota Department of Natural Resources
June 2010
Prepared by:
ROROROROROROROOROOOROROOROOORORORORORROSESESESESESESESESESESESEESEEEEEEEEEEEESEEEMOMOMOMOMOMOMOMOMOOMOMMOMMMOMOMOMOMOMOMOMOMOMOMMOMMOMOMMOMOMMMMOMOMOMMMMMMOMOOMOMOOMM UNUNUNUNUNUNUNUNUNUUUNUNUNUNUNUNUNUNUNUNNUNUUU TTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTT
TBG113009192205MKE
UmUmUmUmUmUmUmmUUmUUmUUmUmmorororrrororooo e eeeee ee PaPPaPaPaPaaPaaaPaaaaaPaPaPaPaaaarkrkrkrkrkrkrkkrkkkrkrkrkrkrkrkrrkkrkrkrkrkrkrrkrkrkkrkrkrkrkrkrkUmUmUU orroreeeee aPaaPaPPaPaPPaPaParrrkrrkrkrkrkrrrrkr
PrPrPrPrPrPrPPrPPrroopopopopopopopppppopopppppopppppppposososoososososososososososooosssssedededededededededededdedededededeeedeedeeedededeRRRReReReReReReReReRRReReeeeeR gigigigigigigigigigigigiigigigigiiiiiiiigggg ononononononnonnoononoononnonnonoonono alalalalalalaaalalalaaaaala
PaPaPaPaPaPaPPaPaPaP rkrkrkrkrkrkkkrkrkkkkkrrkrkrkkrkkrr
EMEMEMEMEMEMEMEEEMEMEMEMEMEMEMEMMEMEMEMEMEMMMPPPPPPIPIPIPIPPPIPIPIPIPIPPPIPPIP REREREREREREREREREREREREREEREREEEEREEERREEEREEEEETWTWTWTWTWTTWTWTWTWTWTWWWWTWTWWTWWWWTWWTWWWTWWWWWWWWWWT PPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPP
VeVeVeVeVeVVeVeVeVeVeVVeVeVeVeVeVeVeVVeVVeV rmrmrmrmrmrmrmrmmrmrmrmrmrmrmrmrmrmmmililililillililililllillillililllllllllllililililillllllililllllililililililililililililililililililililililliiilliililioooooooonoonononononononooonononooonnoonoooonnoononononnonnoonnonnoon H H HHHHHHH HHH H HHH HH HHHHHH HHHHHH HHHHHHHHH Higigigigigigiggigigigigigigiggigigigigigigigggggggigggiggigggggggghlhlhlhlhlhlhlhhlhlhlhlhlhlhlhlhlhlhllhlhhlhlhlhlhlhhlhlhlhlhhhlanananananaanananananannanananananannnananananannanananannananananannanannnananananaaana dsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdsdddddsdssdsddsdddsdd
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORT
Table of Contents Executive Summary .............................................................................................................................I 1.0 Introduction.................................................................................................................................... 1
1.1 Study Area.............................................................................................................................. 1 1.2 Study Background................................................................................................................. 1
1.2.1 Purpose of Study and Anticipated Study Outcomes ............................................. 1 1.2.2 Relation to Other Studies & Development Planned within Study Area.............. 3 1.2.3 Existing and Forecast Traffic Volumes and Regional Transportation System Needs .................................................................. 3
1.3 Supporting Roadway Network ........................................................................................... 5 1.3.1 Roadway Functional Classification Guidelines ...................................................... 5 1.3.2 Existing Roadway Network Functional Classification .......................................... 5 1.3.3 Recommended General Transportation System (Not Specific Corridor Alignments) ................................................................................... 7
2.0 Study Phases, Schedule, and Stakeholder Involvement .......................................................... 9
2.1 Study Phases and Schedule.................................................................................................. 9 2.2 Study Team and Public Involvement ................................................................................. 9
2.2.1 Project Management Team (PMT) ............................................................................ 9 2.2.2 Public Involvement..................................................................................................... 9
3.0 Corridor Option Evaluation Criteria ........................................................................................ 12 4.0 Development of Transportation Corridor Options ................................................................ 12
4.1 Initial Universe of East-West Corridor Options.............................................................. 13 4.2 Initial Universe of North-South Corridor Options ......................................................... 15
5.0 Alignment Option Evaluation and Refinement ...................................................................... 17 5.1 Step 1: “Fatal Flaw” Alignment Option Evaluation ....................................................... 17 5.2 Step 2: Corridor Level Evaluation and Continued Alignment Refinement................ 18 5.3 Step 3: System Level Evaluation........................................................................................ 27
6.0 Final Corridor Alignment Recommendations and Roadway Characteristics .................... 27 7.0 Activities to Implement Recommended Alignments ............................................................. 34
7.1 Activities and Timing to Implement Recommendations............................................... 34 7.2 Right-of-Way Acquisition .................................................................................................. 34 7.3 Context-Sensitive Solution Considerations ..................................................................... 34
8.0 Other Transportation Considerations....................................................................................... 35 8.1 Supporting Local Road System, Intersection Spacing, and Other Possible Roadway Projects............................................................................................ 35 8.2 Pedestrian and Bicycle Facilities ....................................................................................... 37 8.3 Future Transit Service......................................................................................................... 37
TABLE OF CONTENTS – PAGE 1 OF 2
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORT
TABLE OF CONTENTS – PAGE 2 OF 2
TablesTable 1—Spacing Guidelines for Functionally Classified Roads.................................................. 5 Table 2—Recommended Transportation System Summary ......................................................... 7 Table 3—Open House Dates and Key Objectives ........................................................................... 9 Table 4—Evaluation Categories and Criteria ................................................................................ 12 Table 5—Fatal Flaw Analysis—Findings and Corridors Eliminated from Further Consideration ...................................................................... 17 Table 6—Corridor Level Evaluation—Findings ........................................................................... 23 Table 7—Final Corridor Evaluation—Findings ............................................................................ 31
FiguresSummary of Recommended Regional Arterial Corridors ........................................................... III Figure 1, Study Area Location ........................................................................................................... 2 Figure 2, Study Area Daily Traffic Volumes ................................................................................... 4 Figure 3, Functionally Classified Roadway System ....................................................................... 6 Figure 4, Recommended Transportation System............................................................................ 8 Figure 5, Study Schedule .................................................................................................................. 10 Figure 6, PMT Member Roles and Responsibilities...................................................................... 11 Figure 7, Universe of Alternatives, East/West Corridor Options .............................................. 14 Figure 8, Universe of Alternatives, North/South Corridor Options ......................................... 16 Figure 9, East-West Corridor Options Remaining after First Level Evaluation ....................... 19 Figure 10, North-South Corridor Options Remaining after First Level Evaluation ................ 20 Figure 11, Remaining & Refined Regional, Arterial Corridor Options, Engineered to Defined Design Criteria ............................................................................. 21 Figure 12, Known Plant and Animal Resources ........................................................................... 25 Figure 13, Hydric Soils...................................................................................................................... 26 Figure 14, East-West Regional Arterial Corridor Options Final Evaluation Results ............... 28 Figure 15, North-South Arterial Corridor Options Final Evaluation Results........................... 29 Figure 16, Recommended Regional Arterial Corridors ............................................................... 30 Figure 17, Representative 2-land and 4-lane Cross-Sections....................................................... 33 Figure 18, Context Sensitive Opportunities for Future Consideration ...................................... 36
AttachmentsAttachment A: Purpose/Need for a Study and Expected Study Outcomes Attachment B: Public Open House Summaries and Select Comments Attachment C: Evaluation Criteria Back-up Information
Executive Summary
Dakota County, the City of Rosemount, Empire Township, the University of Minnesota, the Minnesota Department of Natural Resources (DNR), and the Minnesota Department of Transportation (Mn/DOT) have spent several months planning for the future transportation needs for a study area that includes UMore Park, Vermillion Highlands, and a new regional park. The end result is a recommended transportation system that will meet the needs of the travelling public into the future and allow for phased implementation, in response to future development.
Prior to implementation, this study will serve as a planning tool for communities and agencies with interests in the area. The recommendations will assist Dakota County, the City of Rosemount, Empire Township, the University of Minnesota, and the Minnesota Department of Natural Resources (Mn/DNR) with prioritizing future improvements, coordinating roadway system needs with development and land use needs, and with right-of-way preservation.
The recommendations of this study include:
The regional arterial road network as shown on the Recommended Regional Arterial Corridors map will serve as a planning tool for this area as it develops. This recommended system will be used by study partners and surrounding communities as land use and transportation plans are implemented.
The roadway system recommended in this study will form a “back bone” arterial network. This network was developed using the best information available for a long-term corridor planning study. The recommended corridors may be refined in response to changing circumstances and new information. Any refined corridors would undergo the same level of evaluation as was completed for the recommended corridors.
Each of the agencies involved should update comprehensive and/or transportation plans to properly reflect the study recommendations and subsequent planning activities. This includes the Concept Plan for UMore Park.
Implementation of the recommended regional arterial corridors in the study area will be coordinated with development as it occurs. Any activities/changes made within Vermillion Highlands should also take the recommended regional arterial corridors into account. Through these processes, the following Transportation System Summary recommendations should be considered:
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORT JUNE 2010
I
Recommended Transportation System Summary
Corridor Existing # of Regional Lanes
Recommended # of Regional Lanes
Required # of New Lanes
East/West Corridors 6- to 8-Lanes
CSAH 42 4-lanes 4- to 6-lanes 0- to 2-lanes
CSAH 46 2-lanes 4- to 6-lanes 2- to 4-lanes
CSAH 66/200th St. 2-lanes 2-lanes None
Hwy. 50 2-lanes 2-lanes None
North/South Corridors 4- to 6-Lanes
Hwy. 3 2-lanes 2-lanes None
Biscayne Ave. & CR 73/Akron Ave.
N/A (not a regional road)
2- to 4-lanes 0- to 2-lanes
Blaine Ave. & CR 81/Clayton Ave.
N/A (not a regional road)
2-lanes, possible 4-lanes where needed
0- to 2-lanes
In future months and years, this study’s team should continue to address transportation network needs for this area; including a local road network, future greenway and bicycle/pedestrian connections, and transit connections. As a complete transportation network for this area continues to be developed, the study team will continue to use a stakeholder based approach to develop a complete transportation system; this includes working with additional partners as appropriate.
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORT JUNE 2010
II
Farmington
CastleRock Township
Empire Township
Hampton
Township
Coates
Rosemount
Vermi llion
River
UMore Park
WastewaterTreatment
Fac.
WMA
VermillionHighlands
AMA
42C
hil
i A
ve
Alb
atross C
ir
Co
lora
do
Ave
An
ne
tte
Av
e
Berr
ing
Ave
170th St E
202nd St W
Ca
mb
od
ia A
ve
197th St W
Ah
ern
Blv
d
199th St
Sta
tion Tr
170th St W
An
ne
tte
Av
e
205th St W
203rd St W
Bis
ca
yn
e A
ve
190th St W
Highland Cir
Ch
ev
ell
e A
ve
200th St W
194th St W
209th St W
201st St W
50
3
3
52
3
150th St W
200th St W
210th St E
160th St E
Cla
yto
n A
ve
Akro
n A
ve
Elm St
Bla
ine
Av
e E
210th St W
160th St W
145th St E
200th St E
170th St W
Vermilli
on River Tr
213th St W
145th St W
81
62
79
7342
71
46
66
74
52
Rosemount/UMore/Empire Area Transportation System Study
0 10.5 Miles
Regional Park
Study Area
Summary of Recommended Regional Arterial Corridors
CSAH 46 - Use existing
alignment; expand to
4- to 6-lanes.
CSAH 42 - Use existing
alignment; consider
expanding to 6-lanes
Blaine & CR 81/Clayton Ave -
Provide connection from
Blaine Ave. to Clayton Ave.
For north-south and east-west corridors, connections to roads outside of the study area will be determined in later studies.
Biscayne Ave./Akron Ave. -
Connect Biscayne to Akron
Ave. via a 2- to 4-lane road.
Option A
Option B
Hwy. 3 - Use
existing road.175th St. Extension -
Provide connection
from Hwy. 3 to
new Biscayne Ave./
Akron. Ave. alignment.
CSAH 66/200th St. - Provide two
new connections from Hwy. 3 via
190th St. and Biscayne Ave.; and
a re-aligned Vermillion River Trail.
Recommended, Regional Corridors
Previously Planned County Corridor
Study Boundary
Build one of two possible connections between CR 81/Clayton Ave. to CSAH 71/Blaine Ave.
Option A is the preferred option. Adjacent to Vermillion Highlands, the location of the corridor will be based on the location of the powerline that currently runs between the WMA's eastern border WMA and private property.
Option B would occur if Mn/DNR expands Vermillion Highland boun-daries by purchasing land from willing owners and receives necessary County and Township approvals. (Note: Mn/DNR's practice is to acquire land from willing land owners; the agency has not typically used condemnation).
Hwy. 50 - Use
existing road.
Blaine & CR 81/Clayton Ave -
Use existing alignment between
CSAH 42 and CSAH 42.
2-lanes are planned; 4-lanes
will be considered based on
future traffic needs.
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORT JUNE 2010
1
1.0 Introduction This report documents the process completed by the Rosemount/Empire/UMore Area Transportation System Study (the study) Project Management Team (PMT) to plan for the future transportation needs of the study area, which includes the future UMore Park and Vermillion Highlands. The end result is a recommended transportation system that will meet the needs of the travelling public into the future and allow for phased implementation, in response to future development.
Prior to implementation, this study will serve as a planning tool for communities and agencies with interests in the area. The recommendations contained in this report will assist Dakota County, the City of Rosemount, Empire Township, the University of Minnesota, and the Minnesota Department of Natural Resources (Mn/DNR) with prioritizing future improvements, coordinating roadway system needs with development and land use needs, and also facilitate right-of-way preservation.
1.1 Study Area Figure 1 shows the study area and its regional orientation. Located within southern Dakota County, this area is now on the edge of suburban development of the Twin Cities Metropolitan Area. Parts of Rosemount and Empire Township are within the study area. The Metropolitan Council forecasts that the population of these two communities will reach a combined 45,000 by 2030, up from 16,500 in 2000. Much of this growth will come from the 5,000-acre UMore Park development, planned to be completed in 25 to30 years.
The growing communities of Farmington, Lakeville, and Apple Valley are north and west of the study area; the communities of Hastings, Northfield, and Cottage Grove, which have recently experienced substantial population growth, are located to the south and east. Given these circumstances and future land use plans at UMore Park, this area is located within an expanded Twin Cities Metropolitan Area, despite the current predominance of rural agricultural land uses and undisturbed natural areas.
1.2 Study Background 1.2.1 Purpose of Study and Anticipated Study Outcomes Prior to starting this study, the PMT developed a Purpose/Need for a Study. In summary, this document notes that it is timely for the PMT and the general public to:
…develop a plan that addresses transportation issues in this area of Dakota County in a coordinated and balanced manner with area land use development plans. Such a plan will allow these agencies to develop a transportation system together over time that will result in safe and efficient travel in the area as cost-effectively as possible, while at the same time developing land use plans in the area that will accomplish the objectives of the City of Rosemount, Empire Township, the University of Minnesota, the Department of Natural Resources, and Dakota County.
The Purpose/Need for a Study and the Expected Study Outcomes documents, which were developed by the PMT, are included in Attachment A.
AMA
AMA
Rosemount
InverGrove
Heights
Bloomington
Lakeville
Burnsville
AppleValley
EurekaTwp.
Farmington
CastleRockTwp.
EmpireTwp.
Nininger
CottageGrove
HamptonTwp.
VermillionTwp.
St.Paul Park
Eagan
UMore Park
VermillionHighlands
Lewiston Blvd
Aher
n Bl
vd180th St E
150th St E
Denm
ark A
ve
245th St W
170th St E
Fisc
her A
ve
Hoga
n Ave
222nd St E225th St W
Bisc
ayne
Ave
250th St E
Ipav
a Ave
250th St E
270th St E265th St W
215th St E
Inga
Ave
170th St E
Bisc
ayne
Ave
190th St W
230th St W
Cliff Rd
150th St W
160th St E
125th St W
Ceda
r Ave
Pilo
t Kno
b Rd
200th St E
McAndrews Rd
150th St W
160th St W 160th St W
Coun
ty Hw
y 11
Cliff Rd
Keat
s Ave
S
240th St E
Diamond
Path
280th St W
212th St W
Northfi
eld Blvd
Blain
e Ave
210th St W
Dodd
B lvd
280th St W
Dodd Blvd
245th St E
145th St E
280th St E
Donn
elly
Ave
Good
win
Ave
190th St E
255th St WHo
gan
Ave
Galax
ie Av
e 260th St E
135th St E
280th St E
170th St W
Clay
ton
Ave
32
42
35E
6647
56
30
23
85
31
31
28
42
46
86
38
31 66
46
9
42
38
86
11
47
9
85
42
86
32
63
80
23
71
9
80
43
73
46
2350
32
62
71
46
30
70
83
87
17
31
7889
79
73
33
81
51
53
53N
83
81
27
81
28
75
84
64
79
19
62
80S
82
38
78
56
613
13
50
50
77
77
55
55
52
3
55
13
35E
52
3
52
35E
3
149
52
3
55
52
61
State Highway
County State Aid Highway (CSAH)
County Road
0 2.5 51.25 Miles
Study Area
Rosemount/UMore/Empire AreaTransportation System Study
Figure 1Study Area Location
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORTJUNE 2010
3
1.2.2 Relation to Other Studies & Development Planned within Study Area The study area is currently the subject of a great deal of land use and preservation planning. The intensity of development proposed for this land ranges from large tracts of open spaces within Vermillion Highlands and Dakota County’s Regional Park to relatively dense planned urban development within UMore Park and existing and future development in City of Rosemount and Empire Township. As such, this study was developed with consideration of the transportation and land use elements of the following documents (listed chronologically):
Dakota County 2025 Transportation Plan (July 2004)
Creating Common Ground, A report to the Minnesota Legislature (January 2007)
Dakota County Parks, Lakes, Trails and Greenways Vision, 2030 (2007)
Draft Rosemount Transportation Plan (April 2008)
Draft of Concept Master Plan for Vermillion Highlands (June 2008)
City of Rosemount Draft 2030 Comprehensive Land Use Plan (August 2008)
Empire Township 2030 Future Land Use Map and data (March 2009) and Sewer Staging (June 2008)
Concept Master Plan for the University of Minnesota’s New Sustainable Community at UMore Park (January 2009)
It is noteworthy that the Dakota County 2025 Transportation Plan (see Figure T-6 Dakota County Highway Capacity Deficiencies, 2025) currently includes a direct connection between CR 79 and CSAH 71 via Blaine Avenue. This connection was planned before the creation of Vermillion Highlands. This study was undertaken in part to re-consider this alignment as it would bisect the newly created Vermillion Highlands.
1.2.3 Existing and Forecast Traffic Volumes and Regional Transportation System Needs Figure 2 shows existing and future (year 2025 or 2030, depending on the data sources noted on the figure) daily traffic volumes for roadways in the study area. Much of the growth in traffic is anticipated to come from planned development within UMore Park and the City of Rosemount.
Traffic forecasts show that future demand for north-south roads will be 50,500 vehicles per day, which will require six- to eight-lanes on regional roads.1 An additional four to six north-south lanes are needed within the study area to meet future traffic demand.2 Currently, this area includes one regional, north-south roadway—Highway 3—which has two to three lanes depending on location. Based on anticipated traffic, an additional four to six north-south regional highway lanes are needed to meet future demand.
1 The number of lanes needed to accommodate future traffic volumes in both the north-south and east-west directions are based on the assumption that regional, arterial roadways would accommodate an average of 7,000-8,000 vehicles per lane per day. These volumes are consistent with the average, daily capacities for arterials assumed in the UMore Park Development Study. Design capacities are determined based on the relationship between level of service and average daily traffic volumes. Assumptions for this analysis include a maximum flow rate of 800 vehicles/hour/lane and LOS D for arterials. 2 A range of the number of north-south and east-west lanes on regional roadways are based on planning level traffic forecasts (versus design level forecasts). This range allows for flexibility in responding to traffic needs as land use planning for this area evolves and is implemented.
Regional Park
UMore Park
WastewaterTreatment
Fac. WMA
Vermillion Highlands
AMA
Farmington
Castle RockTownship
Empire
Township
Hampton
Township
VermillionTownship
Coates
Rosemount42
66
50
46
46
71
74
79
72
62
73
81
81
42
52
Ah
ern
Blv
d
Station Tr
190th St W
197th St W
Calg
ary
Tr
Bis
cayn
e A
ve
Be
au
mo
nt
Ave
255th St W
170th St E
Bis
cayn
e A
ve
Be
rrin
g A
ve
230th St E230th St W
An
nett
e A
ve
50
52
3
3
52
Elm St
160th St E
Ash St
210th St W
Vermill
ion
River Tr
Cla
yt o
n A
ve
Dars
on
Av
e
Akro
n A
ve
170th St W
150th St W
190th St E
160th St W
Bla
ine
Av
e E
213th St W
200th St E
County Hwy 46
145th St W
200th St W
210th St E
145th St E
Bla
ine
Ave
E
Rosemount/Empire/UMore Area
Transportation System Study
08-24-09
Study Area Daily Traffic Volumes
Study Boundary
0 3,000 6,0001,500 Feet
Legend
Future CSAH 42 Access
3/4 Access
Interchange
Traffic Signal
Unsignalized
10,90028,00029,100
9,00014,200
26,000
15,30028,00044,400
13,20031,00041,300
30
010
,00
016
,00
0
1,5
00
6,0
00
10
,60
0
75
01,0
00
7,7
00
18,00015,00040,600
4,3007,0008,900
5901,000
13,600
5,90012,0009,100
0 NA
10
,50
0
55
01,0
00
3,5
00
2,4006,4009,000
2,4005,000
NA
3,3006,8009,000
15
040
08,9
00
38
080
0N
A
48
580
0N
A
35
51,0
00
NA
66
01,0
00
NA
80900NA
44
01,0
00
NA
10,4
00
NA
23,9
00
10
,40
0N
A27
,60
0
14
,00
026
,50
012
,80
0
9,6
00
19
,00
014
,70
0
Figure 2
State Highway
County State Aid Highway (CSAH)
County Road
AMA
1,234
1,234
1,234
Existing Daily Traffic Volumes
Forecasted Daily Traffic Volumes
(MnDOT 2007 Volume Maps)
(North of 46 - Rosemount 2030 Tran Plan South of 46 - Dakota Co 2025 Tran Plan)
Forecasted Daily Traffic Volumes(UMORE Park Development Study)
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORTJUNE 2010
5
Traffic forecasts show that in the future, east-west roadways will be used by over 100,000 vehicles per day, which would require 12-14 lanes on regional roadways. The study area now includes three regional roadways: CSAH 42 (4-lanes), CSAH 46 (2-lanes), and Highway 50 (2 lanes); for a total of eight existing east-west, regional roadway lanes. An additional four to six east-west regional highway lanes are needed to meet future demand.
1.3 Supporting Roadway Network 1.3.1 Roadway Functional Classification Guidelines Developed areas are best served with a classified system of roads where a small fraction provides high mobility and the majority of the roads provide access to adjacent land. All roads can be categorized into one of these categories:
Principal Arterials—Primarily provide mobility and speed for the long, uninterrupted distances with controlled access.
Minor Arterials—Provide a combination of mobility and access with reasonable speed for some extended distance, with some access control.
Collectors—Collect traffic from local roads, and providing connection to land with little or no through movements; usually function at lower speeds and for shorter distances.
Local Streets—Provide access to land with little or no through movement; includes all roads not classified as arterials or collectors.
Table 1 provides the Metropolitan Council’s roadway spacing guidelines, which aid in the planning of future transportation systems within developed and developing areas.
TABLE 1 Spacing Guidelines for Functionally Classified Roads
Land Use Characteristics
Principal Arterials Minor Arterials Collectors Local Streets
Developed Areas 2 to 3 miles ¼ to ½ mile ⅛ to ½ mile As needed to access land uses Developing Areas 3 to 6 miles 1 to 2 miles ½ to 1 mile
Rural Areas 6 to 12 miles 4+ miles As needed to access land uses
Source: Metropolitan Council, Metropolitan Development Guide, Appendix F and Federal Highway Administration, Highway Functional Classification
1.3.2 Existing Roadway Network Functional Classification Figure 3 shows the location, spacing, and functional classification of highways in the study area. The existing road system, with highways spaced at intervals of one-mile or more, provides adequate levels of mobility for existing rural land uses and relatively low levels of commuting. The study area includes three east-west arterials (CSAH 42, CSAH 46, and Highway 50) and one north-south arterial (Highway 3). The Metropolitan Council’s guidelines for a functionally classified road system indicate that the study area would include a total of five east-west and four north-south arterials. This means there is currently is a shortage of roadways to meet future demand in this developing area.
08/09/2009
Rosemount/UMore/Empire Area Transportation System Study Functionally Classified
Roadway System
Figure 3
over 5 miles between TH 3 and TH 52
over
6 m
iles
betw
een
TH 5
0 an
d C
SAH
42
Within the study area a roadway system based on the Metropolitan Council’s Spacing Guidelines for Functionally Classified Roads would include:
EAST/WEST2 Principal Arterials3 Minor Arterials
NORTH/SOUTH1 Principal Arterial3 Minor Arterials
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORTJUNE 2010
7
The existing rural system is not robust enough to reasonably serve the trips that would be generated by the higher density urban development planned in UMore Park, Rosemount, and Farmington, or other nearby areas. The existing transportation system will need to be upgraded to accommodate development, population growth, and increased commuting levels between this area and employment centers within the Twin Cities Metropolitan Area. The likely consequence of an under built transportation system will be substantial increases in traffic on the few available roads.
1.3.3 Recommended General Regional Transportation System (Not Specific Corridor Alignments)
As noted above, a regional road system based on the Metropolitan Council’s roadway spacing guidelines would include:
East/West Roadways: two principal arterials and three minor arterials North/South Roadways: one principal arterial and three minor arterials
Based on these basic traffic capacity needs, the PMT developed a recommended transportation system—package of corridors (not specific alignments). Figure 4 shows these corridors and the number of lanes that would meet anticipated future traffic needs. This recommended system would enhance the arterial network by providing corridors that connect to the regional network. Table 2 describes what would be included in the regional transportation system.
TABLE 2 Recommended Transportation System Summary
Corridor New Right-of-Way (ROW)Required?
Existing # ofRegional
Lanes
Recommended # of Regional Lanes
Required # of New Lanes
East/West Corridors 6- to 8-Lanes
CSAH 42 Possible—Existing CSAH 42 includes 150’ ROW; more ROW needed if lanes are added
4-lanes 4- to 6-lanes 0- to 2-lanes
CSAH 46 Yes—Existing CSAH 46 includes approx. 66’ ROW
2-lanes 4- to 6-lanes 2- to 4-lanes
CSAH 66/200th St.
Yes—Existing CSAH 66 includes approx. 66’ ROW
2-lanes 2-lanes None
Hwy. 50 No—Currently a Mn/DOT highway; no jurisdictional change anticipated
2-lanes 2-lanes None
North/South Corridors 4- to 6-Lanes
Hwy. 3 No—Currently a Mn/DOT highway; no jurisdictional change anticipated
2-lanes 2-lanes None
Biscayne & Akron Aves.
Yes— Existing CRs include 66’ ROW
N/A (not a regional road)
2- to 4-lanes 0- to 2-lanes
Blaine Ave. and/or CR 81/Clayton Ave.
Yes— Existing CRs include 66’ ROW
N/A (not a regional road)
2-lanes, consider 4-lanes where needed
0- to 2-lanes
22--LanesLanes
22 --La
nes
Lane
s
44--LaneLane = existing regional road and # of lanes
44--LaneLane = potential future regional road and # of lanes
Future traffic volumes indicate that the study area will need 6-8 north-south lanes and 12 to 14 east12 to 14 east--west west laneslanes to operate at an acceptable level (LOS D/E). This graphic shows the system that has been recommended to achieve lane these capacity goals.
44--LanesLanes
10/30/2009
Rosemount/UMore/Empire Area Transportation System Study Recommended Transportation System
Study Area Boundary
4 N
ew L
anes
4 N
ew L
anes
2 N
ew L
anes
2 N
ew L
anes
22--LanesLanes
2 New Lanes2 New Lanes22--LanesLanes
Note: Lines representing lanes do not infer any particular alignment.Figure 4
Additional 2 New Lanes on Either CSAH 42 or CSAH 46, TBDAdditional 2 New Lanes on Either CSAH 42 or CSAH 46, TBD
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORT JUNE 2010
9
2.0Study Phases, Schedule, and Stakeholder Involvement 2.1 Study Phases and Schedule The study began in January 2009 and ended in December 2009; it was divided into phases, which are shown on the study schedule (Figure 5) along with the timing of decision points, key meetings, and open houses.
2.2 Study Team and Public Involvement 2.2.1 Project Management Team (PMT) Figure 6 shows the communities and agencies that served on the PMT and the group’s responsibilities. This group developed the recommended transportation system. Throughout the course of this study, the full PMT met ten times, as shown on the project schedule.
2.2.2 Public Involvement Three public open houses were held during which the latest study developments were shared and input was obtained from the public. All open houses were held during the late afternoon and early evening at the Rosemount Community Center. Table 3 provides the dates and key objectives of each open house:
TABLE 3 Open House Dates and Key Objectives
Open House Date Key Objectives
1. April 1, 2009 Develop universe of transportation corridor options and identify issues to assist with developing evaluation criteria
2. June 29, 2009 Review universe of corridor options and evaluation criteria
3. November 12, 2009 Review recommended regional roadway system and identify any implementation issues
Comments received at open houses and throughout the duration of the study help the PMT identify community values and goals, develop a range of alternatives, and evaluate alternatives. Summaries of comments and select representative comments received from the public are included in Attachment B.
Phase I – Existing Conditions & Stakeholder Goals Technical Tasks
1.1 Data Gathering
1.2 Document Existing & Future Conditions
1.3 Confirm Problems & Needs
1.4 Identify Stakeholder Visions and Goals (Performance Criteria)
1.5 Develop Matrix Methodology for Evaluation
Outreach & Coordination1.6 PMT Meetings (#1 - 3)
1.6 Public Open House #1
Phase II – Develop AlternativesTechnical Tasks
2.1 Develop Future Alignment Options & Alternatives
Outreach & Coordination2.2 PMT Meetings (#4 – 6)
2.2 Public Open House #2
Phase III – Apply Methodology to Evaluate AlternativesTechnical Tasks
3.1 Apply Evaluation Criteria and Refine Alternatives
3.2 Identify Transportation System Recommendations
3.3 Prepare Draft Study Report
Outreach & Coordination3.4 PMT Meetings (#7 – 9)
3.4 Public Open House #3
Phase IV – Implementation & Stakeholder RolesTechnical Tasks
4.1 Community Presentations & Stakeholder Implementation Roles
4.2 Final Study Report
Outreach & Coordination4.3 PMT Meeting (#10)
January February March April May June July August September October November December
2009
Opportunity to Provide Input
Opportunity to Provide Input
Opportunity to Provide Input
10/30/2009
Rosemount/UMore/Empire Area Transportation System Study Study Schedule
Figure 5
08/09/2009
Rosemount/UMore/Empire Area Transportation System Study Project Management Team (PMT)
Member Roles & Responsibilities
Figure 6
Rosemount/Rosemount/Empire/UMore AreaEmpire/UMore Area
Transportation System Transportation System StudyStudy
PublicPublic
Project Management TeamProject Management Team
Project Management Team includes:Project Management Team includes:
•Dakota County (Project Lead)•Rosemount•Empire Township•UMore Park/U of MN•Minnesota DNR
- Review and comment on the study
ConsultantConsultant –– CH2MCH2M HILL HILL - Engage in exchange of information with the PMT
- Facilitate development and evaluation of alternatives
- Complete final report
- Act as liaison between PMT and elected/appointed officials and the public
- Provide input for these key tasks: 1. Identify of opportunities & constraints
2. Develop evaluation criteria and transportation system alternatives
3. Identify preferred transportation system
4. Implement decisions into Comprehensive/Master Plans
5. Preserve right-of-way for future transportation system (as applicable)
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORT JUNE 2010
12
3.0 Corridor Option Evaluation Criteria Based on input from the PMT and the public during Open House #1, evaluation criteria were developed to compare transportation corridor options. Table 4 shows these criteria, which are grouped into three categories; this table also shows which criteria were used during each of the three levels of evaluation.
TABLE 4 Evaluation Categories and Criteria
3 Levels of Evaluation
Community Planning & Identity
Natural Resources & Environment
Transportation
I. Fatal Flaw Screening
Is the alignment consistent with transportation and land use elements of area plans?
Does the corridor support opportunities to manage and expand recreational and natural areas?
Does the corridor provide direct connections to the County transportation system?
II. Corridor Screening
Can the corridor be implemented along with planned development?
Does the corridor avoid severances of recreational and natural areas? Private farms?
Is the alignment consistent with County design guidelines?
Does the corridor allow for future development beyond the study area?
Does the corridor avoid right-of-way impacts?
Does the corridor provide access consistent with plans and guidelines?
Does the corridor avoid wetland impacts?
Does the corridor provide opportunities for cost-effective implementation (e.g., re-use of existing right-of-way, roads, and bridges)?
Does the corridor avoid impacts to threatened and endangered species, and/or cultural resources?
Would the corridor divert regional trips from local roads?
III. System Screening
Do the County roads provide adequate access to communities?
Does the County road network provide adequate access to recreational and natural areas?
Would the corridor allow for development of a multi-modal system (integration of roads with transit, trails, greenways, and wildlife corridors)?
Does the system accommodate land use plans, including aggregate mining activities?
Would the corridor provide sufficient spacing and capacity of north/south and east/west roads to meet future demand?
Does the system allow for development of local road network?
Would the corridor result in a significant change in travel time for re-routed alignments?
4.0 Development of Transportation Corridor Options The initial universe of transportation corridor options was developed based on PMT input and comments received during the first public open house. The following statement from the PMT’s vision was also used as a starting point: The road network provides connectivity and
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORT JUNE 2010
13
functional capacity reflective of the demand for transportation services in both the north-south and east-west directions.
4.1 Initial Universe of East-West Corridor Options The universe of east-west corridor options initially developed for this study is shown on Figure 7 and summarized below.
CSAH 42 Option A. CSAH 42—Upgrade CSAH 42 as planned and documented in the County Transportation
Plan and County Plat Map (which reflects the CSAH 42 Final Study and Amendment, and studies completed by Rosemount).
CSAH 46 Options B. CSAH 46—Use existing CSAH 46 alignment
C. CSAH 46, UMore Concept—Realign CSAH 46 based on the alignment shown in the UMore Park Concept Master Plan
D. CSAH 46 via 170th St.—Realign CSAH 46 onto new alignment and 170th St. through UMore Park (in-between Hwy. 3 and CR 81/Clayton Ave.)
170th St. Options E. 170th St.—Use 170th St. alignment (per public comment), extend 170th St. east of CR
79/Blaine Ave.
F. 170th St. with Extension to Future County Hwy. and CR 81/Clayton Ave.—Extend future east-west County highway (just south of existing 170th St.) to CR 81/Clayton Ave. (near Hwy. 52/CSAH 46 intersection), via 170th St. through UMore
180th St. Option G. 180th St. Extension to Future County Hwy., through Park, Vermillion Highlands—Extend
future east-west County highway (just south of 170th St.) to Hwy. 52 via new 180th St. alignment through County Park and Vermillion Highlands
CR 62/190th St. Option H. 190th St. Extension—Use 190th St. alignment, including new connection between Hwy.
3 and Biscayne Ave.
CSAH 66/200th St. Option I. 200th St.—Extend future east-west County highway (along 190th St. alignment) from
Hwy. 3 to CSAH 66/200th St.; includes a new Vermillion River Bridge
210th St. Option J. 210th St.—Use 210th St. alignment
Hwy. 50 Option K. Hwy. 50—Use Hwy. 50 alignment
10/05/2009
Rosemount/UMore/Empire Area Transportation System Study Universe of Alternatives
East/West Corridor Options
Figure 7
Option K
Option A
Option C
Option E
Option H
Option I
Option B
Option D
Option F
Option G
Option J
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORT JUNE 2010
15
4.2 Initial Universe of North-South Corridor Options The universe of north-south corridor options initially developed for this study is shown on Figure 8; each option is summarized below.
Hwy. 3 Options 1. Hwy. 3 through Rosemount—Use Hwy. 3 alignment
2. Hwy. 3 to CR 73/Akron Ave.—Use Hwy. 3 alignment; connect to CR 73/Akron Ave. at CSAH 42
Biscayne Ave. Options 3. Hwy. 3 to Biscayne Ave.—Use Hwy. 3 alignment through Farmington; connect and use
Biscayne Ave. up to CSAH 42
4. Hwy. 3 to Biscayne Ave. to CR 73/Akron Ave.—Use Hwy. 3 alignment through Farmington; connect to and use Biscayne Ave. alignment to just north of CSAH 46; connect to CR 73/Akron Ave.
5. Biscayne Ave. to CR 73/Akron Ave.—Extend Biscayne Ave. to Hwy. 50; use Biscayne Ave. corridor to just south of 170th St.; connect to CR 73/Akron Ave. via new alignment
CR 73/Akron Ave. Options 6. West Park/WMA Boundary to CR 73/Akron. Ave.—Extend CR 73/Akron Ave. south from
CSAH 42 to Hwy. 50, passing along western border of new County Park and WMA/AMA.
7. Annette Ave. to CR 73/Akron Ave.—Extend CR 73/Akron Ave. south from CSAH 42 to Hwy. 50, passing along Annette Ave. and eastern border of new County Park and WMA/AMA, and through part of Vermillion Highlands
CR 79/CSAH 71/Blaine Ave. Options 8. CR 79 to CSAH 71 via direct Blaine Ave. Connection—Directly connect CR 79 to CSAH
71 via Blaine Ave. (in County’s current 2025 Transportation Plan)
9. CR 79 to CSAH 71 via New Connection—Use existing CR 79/Blaine Ave. alignment and Vermillion River crossing; connect to CSAH 71 via new alignment.
CR 81/Clayton Ave. Options 10. CR 79 to CSAH 71 via CR 81/Clayton Ave. (190th St. to 170th St.)—Use existing CR
79/Blaine Ave. alignment and Vermillion River crossing; connect to CR 81/Clayton Ave.; connect to CSAH 71 via new alignment
11. CR 79 to CSAH 71 via CR 81/Clayton Ave. (210th St. to north of 190th St.)—Connect to and upgrade CR 81/Clayton Ave., including possible construction of a new Vermillion River bridge (public comments at Open House #1 recommended upgrading CR 81)
12. CR 79 to TH 52/CSAH 46 via CR 81/Clayton Ave.—Connect to and upgrade CR 81/Clayton Ave., including possible construction of a new Vermillion River bridge, terminating at CSAH 46.
Universe of AlternativesUniverse of AlternativesNorth/South Corridor OptionsNorth/South Corridor Options
10/05/2009
Rosemount/UMore/Empire Area Transportation System Study Universe of Alternatives
North/South Corridor Options
Figure 8
Option 2
Option 3
Option 4
Option 5
Option 6
Option 7
Option 8
Option 9
Option 12
Connection from Hwy 50 to south of Farmington would be determined in later study
Connection from Hwy 50to south would be
determined in later study
Option 1
Option 10
Option 11
Connection from Hwy 50 to south of Farmington would be determined in later study
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORT JUNE 2010
17
5.0 Alignment Option Evaluation and Refinement The screening process was divided into three levels of evaluation as shown in Table 5. As part of a “Context Sensitive Solutions” (CSS) process (described more fully in Section 7.3), a fundamental component of alignment option evaluation was the initial determination of criteria. These criteria were set prior to the development of options to place priority on the stated goals and objectives of project team members. The integrity of a CSS process relies on it being driven by the priorities and objectives of all project participants.
5.1 Step 1: “Fatal Flaw” Alignment Option Evaluation Table 5 below documents the corridors recommended for elimination from the universe of options during the first evaluation—the fatal flaw evaluation. Corridors with a “fatal flaw” were considered to be in direct conflict with key criteria identified by the project team in one of three categories: 1) community planning and identity; 2) natural resources and environment; or 3) transportation network design and function. Attachment C includes a complete description of the Fatal Flaw Analysis methodology and a table that documents the PMT’s discussion during this step—including consideration of opportunities lost by alignment dismissal, and any potential to use dismissed corridors as local roads.
TABLE 5 Fatal Flaw Analysis—Findings and Corridors Eliminated from Further Consideration
Community Planning & Identity
Natural Resources & Environment
Transportation Network Design & Function
Corridors Recommended for Elimination from Universe Options
Is the alignment consistent with transportation and land use elements of area plans?
Does the corridor support opportunities to manage and expand recreational and natural areas?
Does the corridor provide direct connections to the County transportation system?
North/South Corridors
1. Hwy. 3 through Rosemount Improvements
No—Inconsistent with Rosemount’s Land Use and Transportation Plans.
3. Hwy. 3 to Biscayne Ave.—Inconsistent with
No—Inconsistent with Rosemount’s Land Use and Transportation Plans
7. Annette Ave. to CR 73/Akron Ave.
No—Inconsistent with UMore and Vermillion Highlands Plans.
No—Presents management challenges within Vermillion Highlands.
8. CR 79 to CSAH 71 via direct Blaine Ave. connection
No—Inconsistent with UMore and Vermillion Highlands Plans Yes—Consistent with Dakota County 2025 Transportation Plan
No—Presents management challenges within Vermillion Highlands.
12. CR 79 to Hwy. 52/CSAH 46 via CR 81/Clayton Ave.
No—Doesn’t provide adequate connection to County road system.
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORTJUNE 2010
18
TABLE 5 Fatal Flaw Analysis—Findings and Corridors Eliminated from Further Consideration
Community Planning & Identity
Natural Resources & Environment
Transportation Network Design & Function
Corridors Recommended for Elimination from Universe Options
Is the alignment consistent with transportation and land use elements of area plans?
Does the corridor support opportunities to manage and expand recreational and natural areas?
Does the corridor provide direct connections to the County transportation system?
East/West Corridors
E. 170th St. No—Doesn’t provide necessary level of connectivity to County System.
G. New alignment (extension of 180th St. alignment) through Park, Vermillion Highlands
No—Inconsistent with UMore and Vermillion Highlands Plans.
No—Impedes long-term plans for Vermillion Highlands expansion to River.
H. 190th St. No—Corridor is inconsistent with County, UMore, and Vermillion Highlands Plans.
No—Impedes long-term plans for Vermillion Highlands expansion to River.
J. 210th St. No—Inconsistent with Dakota County Plans.
No—Doesn’t provide necessary level of connectivity to County System.
The fatal flaw analysis resulted in dismissing five north-south corridors and four east-west corridors from further consideration (see Figures 9 and 10). Corridors of note that were eliminated include all north-south and east-west options that bisect Vermillion Highlands in half. The remaining corridors were carried forward into the next level of evaluation, discussed below.
5.2 Step 2: Corridor Level Evaluation and Continued Alignment Refinement For the second, corridor level evaluation, more defined alignments were developed for each of the remaining corridors. These alignments, shown in Figure 11, were developed for these corridors using the following design features:
60 mile per hour design speed3,
1,500 minimum curve radius, and
150 foot right-of-way (which would accommodate both 2-lane and 4-lane rural roadways).
3 The 60 mph design speed does not infer that the speed limit would be 60 mph; the statutory speed limit on rural roads is 55 mph. Speed studies may be necessary to determine whether the speed limit should be higher, lower, or that there should be no change from the statutory speed limits.
10/05/2009
Rosemount/UMore/Empire Area Transportation System Study East-West Corridor Options Remaining
after First Level (Fatal Flaw) Evaluation
Figure 9
Option A
Option C
Option B
Option D
Option F
Option K
Option E: Lacksadequate connectivity to County system
Option G: Inconsistent with Plans; Impedes expansion of area
Option H: Inconsistent with Plans; Impedes expansion of area
Option J: Inconsistent with Plans; Lacks adequate connectivity to County System
Option I
Option 6
Connection from Hwy 50 to south of Farmington would be determined in later study
Connection from Hwy 50 to south of Farmington would be determined in later study
Connection from Hwy 50to south would be
determined in later study
Option 1: Inconsistent with Plans
Option 2
Option 3: Inconsistent with Plans
Option 4
Option 5
Option 7: Inconsistent with Plans; presents land manageme nt challenges
Option 8: Inconsistent with Plans; presents land manageme nt challenges
Option 9
Option 10
Option 11
Option 12: Lacksadequate connectivity to County system
Rosemount/UMore/Empire Area Transportation System Study North-South Corridor Options
Remaining after First Level (Fatal Flaw) Evaluation
Figure 10
AMA
Regional Park
ÉÉ52
ÉÉ3
ÉÉ50
ÉÉ3 ÉÉ52
ÉÉ3
ÉÉ3
!(79
!(79
!(81
!(81
!(72
!(73
!(81
!(81
!(81
!(62
£¤52
Û450
Û446
Û474
Û471
Û446 Û446
Û442
Û466 Û466
Û442
Û446
!(42
WastewaterTreatment
Fac.
WMA
VermillionHighlands
AMA
UMorePark
Elm St
210th St W
Ver
mill
ion River Tr
150t
h St W
160th St W
190th St E
160th St E
145th St E
Bla
ine
Av
e E
Ash St
200th St E
170th St W
145th St W
200th St W
210th St E
Cla
yto
n A
ve
± Æÿ State Highway
Û4 County State Aid Highway (CSAH)
!( County Road
11/05/2009
0 3,000 6,0001,500 Feet Numbered transportation corridors representnorth/south options; lettered corridors represent east/west options.
Option A
Option 4
Option B
Option C1
Option 9A
Option 10A
Option 11
Option I
Option K
Corridors were developed based on the following design criteria: - 60 mile per hour design speed - 1,500 minimum curve radius - 150 right-of-way corridor, which could accommodate up to a 4-lane road
For all remaining north-south corridor options, connections from Hwy. 50 to south of Farmington would be determined in later studies.
For all remaining north-south corridor options, connections to other roads north of CSAH 42 would be determined in later studies.
Option 9C
Option 9B
Option C2
Option 10B
Option 5
Option 6
Option D
Option F
Option 11A
Option 11B
Common PortionOptions 9, 10, & 11
Rosemount/UMore/Empire Area
Transportation System Study
Exhibit 11Remaining & Refined Regional,
Arterial Corridor Options Engineered
to Defined Design Criteria
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORT JUNE 2010
22
These corridors were then evaluated based on the criteria that had been identified for the second level of evaluation (see Table 3). The results of this evaluation are shown in Table 6. The PMT opted not to dismiss any corridor options during the second phase of evaluation. As a result, all corridor options were brought into the system level evaluation, discussed below.
This evaluation included a high level environmental resource scan that reviewed existing data related to wetlands and hydric soils; rare plants and animals; and historical and archaeological features (results shown on Table 6). Initially, this data was used to develop and then refine corridor alignments. Where reasonable, alignments were shifted to avoid known occurrences of rare plants and animals (see Figure 12) and to avoid wetlands and hydric soils (see Figure 13). As mentioned above, this evaluation relied on existing information. As project development progresses for any recommended corridor, more in-depth impact reviews—including more detailed review of contaminated properties—will be completed by responsible communities and agencies.
ROSEMOUNT/EMPIRE/UMORE TRANSPORTATION SYSTEM STUDY JUNE 2010
23
TABLE 6Corridor Level Evaluation—Findings
Implement with Development
How much of the corridor be implemented with planned development (from Rosemount and Empire Twp. 2030 land use plans and UMore Park Concept Plan)? (Length and % of alignment in area identified for future development)
Land Severance
How many recreational areas and private parcels would the corridor sever? (# of parcels severed)
Right-of-Way
Would the corridor require right-of-way acquisition? (# of parcels affected & acres of right-of-way needed)
Wetlands
How many acres of wetlands would the corridor impact? (acres of wetland affected)
Rare Plants & Animals
Is the corridor near important plant and animal habitat locations?
Historic and Archaeological Features
Is the corridor near known historic (farms and GOW) or archaeological sites? Are sites avoidable?
Cost-effective Implementation
What is the potential for cost effective implementation (e.g., re-use of existing right-of-way, roads, and bridges)? (high, medium, low)
Diversion of RegionalTrips What is the potential that the corridor would divert regional trips from local roads? (high, medium, low)
NORTH/SOUTH-BOUND CORRIDORS OPTIONS
Rec./Natr’l. Private
Hwy.
3, Bi
scay
ne, A
ve., a
nd C
R 73
/Akr
on A
ve. Option 2: Hwy. 3 to CR 73
7.6 miles 2.6 miles
34%
0 4 43 parcels affected
99 acres right-of-way needed
3.2 acres No Yes, sites are likely avoidable Medium—Amt. of corridor using: --existing alignment = 65% --existing ROW = 29% Potential to use bridge—Yes
High
Option 4: Hwy. 3 to Biscayne Ave. to CR 73
8.0 miles
4.4 miles
55%
0 1 35 parcels affected
100 acres right-of-way needed
3.9 acres No Yes, sites are likely avoidable High—Amt. of corridor using: --existing alignment = 71% --existing ROW = 31% Potential to use bridge—Yes
High
Option 5: Biscayne Ave. to CR 73
8.0 miles
4.1 miles
51%
0
5 20 parcels affected
118 acres right-of-way needed
8.0 acres No No Low-existing alignment = 42%--existing ROW = 19% Potential to use bridge—Yes
High
Option 6: West Park/WMA Boundary to CR 73
7.7 miles
2.5 miles
32%
1 to Dakota. Co. Park; 11 acres (2.4%)
2 14 parcels affected
128 acres right-of-way needed
41.0 acres Yes No Low—Amt. of corridor using: --existing alignment = 21% --existing ROW = 9% Potential to use bridge—No
Medium
CR 79
/CSA
H 71
/Blai
ne A
ve. a
nd C
R 81
/Clay
ton
Ave.
Option 9A: CR 79 to CSAH 71 via new connection
8.0 miles
1.9 miles
24%
2 to WMA; 347 acres (12.2 %)
1 to Dakota Co. Parcel 25 acres (20%)
5 25 parcels affected
110 acres right-of-way needed
6.6 acres Yes Yes, sites are likely avoidable Low—Amt. of corridor using: --existing alignment = 54% --existing ROW = 24% Potential to use bridge—No
Low
Option 9B:
8.2 miles
1.9 miles
23%
2 to WMA; 16+190=206 acres (7.2%)
1 to Dakota Co. Parcel; 25 acres (20%)
4 24 parcels affected
116 acres right-of-way needed
5.4 acres Yes Yes, sites are likely avoidable Low—Amt. of corridor using: --existing alignment = 50% --existing ROW = 22% Potential to use bridge—No
Low
Option 9C:
8.8 miles
1.9 miles
22%
3 to WMA; 16+4+73 =93 acres (3.3%)
1 to Dakota Co. Parcel 25 acres (20%)
6 27 parcels affected
112 acres right-of-way needed
5.2 acres Yes Yes, sites are likely avoidable Medium—Amt. of corridor using: --existing alignment = 68% --existing ROW = 30% Potential to use bridge—No
Low
Option 10A: CR 79 to CSAH 71 via CR 81
8.8 miles
1.9 miles
22%
1 to WMA; 59 acres (2.1%)
1 to Dakota Co. Parcel; 40 acres (33%)
15 37 parcels affected
124 acres right-of-way needed
5.3 acres Yes Yes, sites are likely avoidable Low—Amt. corridor using: --existing alignment = 53% --existing ROW = 23% Potential to use bridge—No
Low
Option 10B:
8.8 miles
1.9 miles
22%
1 to WMA; 4 acres (0.1%)
1 to Dakota Co. Parcel; 40 acres (33%)
10 41 parcels affected
114 acres right-of-way needed
5.2 acres Yes Yes, sites are likely avoidable High—Amt. of corridor using: --existing alignment = 64% --existing ROW = 28% Potential to use bridge—No
Low
ROSEMOUNT/EMPIRE/UMORE TRANSPORTATION SYSTEM STUDY JUNE 2010
24
TABLE 6Corridor Level Evaluation—Findings
Implement with Development
How much of the corridor be implemented with planned development (from Rosemount and Empire Twp. 2030 land use plans and UMore Park Concept Plan)? (Length and % of alignment in area identified for future development)
Land Severance
How many recreational areas and private parcels would the corridor sever? (# of parcels severed)
Right-of-Way
Would the corridor require right-of-way acquisition? (# of parcels affected & acres of right-of-way needed)
Wetlands
How many acres of wetlands would the corridor impact? (acres of wetland affected)
Rare Plants & Animals
Is the corridor near important plant and animal habitat locations?
Historic and Archaeological Features
Is the corridor near known historic (farms and GOW) or archaeological sites? Are sites avoidable?
Cost-effective Implementation
What is the potential for cost effective implementation (e.g., re-use of existing right-of-way, roads, and bridges)? (high, medium, low)
Diversion of RegionalTrips What is the potential that the corridor would divert regional trips from local roads? (high, medium, low)
Option 11A: CR 79 to CSAH 71 via CR 81
8.2 miles
1.9 miles
23%
2 to WMA; 182 acres (6.4%)
1 to Dakota Co. Parcel 25 acres (20%)
4 26 parcels affected
122 acres right-of-way needed
2.7 acres Yes Yes, sites are likely avoidable Medium—Amt. of corridor using: --existing alignment = 49% --existing ROW = 21% Potential to use bridge—Yes
Low
Option 11B
8.3 miles 1.9 miles
23%
2 to WMA; 98+38=136 acres (4.8%)
1 to Dakota Co. Parcel; 12 acres (9.8%)
8 26 parcels affected
116 acres right-of-way needed
2.7 acres Yes Yes, sites are likely avoidable Medium—Amt. of corridor using: --existing alignment = 52% --existing ROW = 23% Potential to use bridge—Yes
Low
EAST/WEST-BOUND CORRIDOR OPTIONS Rec./Natr’l. Private
CSAH
42 Option A: CSAH 42
4.7 miles N/A no new right-of-way required
0 0 0 parcels affected
0 acres right-of-way needed
* ROW may be needed if CSAH 42 is expanded to 6-lanes
0 acres Yes No High— Amt. of corridor using:
--existing alignment = 100%
--existing ROW = 100%
High
CSAH
46
Option B: CSAH 42
4.8 miles 3.9 miles
81%
0 0 5 parcels affected
49 acres right-of-way needed
0.1 acres Yes No Medium— Amt. of corridor using:
--existing alignment = 100% --existing ROW = 44%
High
Option C1: CSAH 46, UMore Concept
5.2 miles
3.6 miles
70%
0 1 5 parcels affected
72 acres right-of-way needed
0 acres Yes No Low—Amt. of corridor using:
--existing alignment = 54% --existing ROW = 24%
High
Option C2
4.8 miles 3.3 miles
69%
1 to Dakota Co. Parcel; 44 acres (36%)
3 5 parcels affected
83 acres right-of-way needed
0 acres Yes No Low—Amt. of corridor using:
--existing alignment = 12%
--existing ROW = 5%
High
Option D: CSAH 46 via 170th St.
5.2 miles
2.5 miles
48%
1 to WMA; 163 acres (5.8%)
4 9 parcels affected
64 acres right-of-way needed
0 acres Yes No Medium— Amt. of corridor using:
--existing alignment = 73% --existing ROW = 32%
High
Option F: 170th St. with Extension to Future County Hwy. and CR 81/Clayton Ave. 5.5 miles
1.9 miles
34%
1 to WMA; 253 acres (8.9%)
2 8 parcels affected
68 acres right-of-way needed
0 acres Yes No Medium— Amt. of corridor using:
--existing alignment = 73% --existing ROW = 32%
Low
CSAH 66
Option I
6.9 miles
1.4 miles
20%
0 5 21 parcels affected
87 acres right-of-way needed
12.4 acres No Yes, sites are likely avoidable. Medium— Amt. of corridor using:
--existing alignment = 71% --existing ROW = 31%
Medium
Hwy.
50
Option K 5.7 miles 0 miles
0%
0 0 46 parcels affected
58 acres right-of-way needed
11.1 acres No No Medium— Amt. of corridor using:
--existing alignment = 100% --existing ROW = 44%
High
AMA
Regional Park
52
4646
42
66
46
71
42
46
66
74
42
50
WastewaterTreatment
Fac.
WMA
VermillionHighlands
AMA
UMorePark
3
3
3
3
50
52
52
81
72
73
81
81
62
79
81
81
79
42
Ash St
210th St W
150t
h St W
160th St W
190th St E
145th St E
Elm St
Bla
ine
Ave
E
160th St E
200th St E
170th St W
Ver
mill
ion River Tr
145th St W
200th St W
210th St E
Cla
yto
n A
ve
12/09/2009
0 3,000 6,0001,500 Feet
Option A
Option 4
Option B
Option C1
Option 9A
Option 10A
Option 11
Option I
Option K
Option 9C
Option 9B
Option C2
Option 10B
Option 5
Option 6
Option D
Option F
Option 11A
Option 11B
Common PortionOptions 9, 10, & 11
Rosemount/UMore/Empire Area
Transportation System Study
Figure 12
Known Plant and
Animal Resources
Rare Plant or Animal Species General Locations
Sites State-wide Biodiversity Significance
Regionally Significant Ecological Areas
Ecological Score
Moderate
High
Outstanding
Copyright 2009 State of Minnesota, Department of Natural ResourcesData included here were provided by the Division of Ecological Resources, Minnesota Department of Natural Resources (DNR), and were current as of June 12, 2009. These data are not based on an exhaustive inventory of the state. The lack of data for any geographic area shall not be construed to mean that no significant features are present.
AMA
Regional Park
6666
42
50
4646
4646
74
42
71
Ver
mill
ion River Tr
160th St E
Ash St
150t
h St W
Elm St
210th St W
160th St W
190th St E
145th St E
Bla
ine
Av
e E
200th St E
170th St W
145th St W
200th St W
210th St E
Cla
yto
n A
ve
WMA
UMorePark
VermillionHighlands
AMA
WastewaterTreatment
Fac.
3
50
52
3
3
3
52
42
79
81
81
62
79
73
81
72
81
81
52
12/09/2009
0 3,000 6,0001,500 Feet
Option A
Option 4
Option B
Option C1
Option 9A
Option 10A
Option 11
Option I
Option K
The nature of hydric soils makes road constuction through these areas difficult. Also, hydric soils often indicatethe presence of wetlands, which are also usually avoided.
For Option 11, the curve from CR 79/Blaine Ave. to CR 81/Clayton Ave. shows a refinement made upon learningthat hydric soils were present. The alignment now skirts to the south of these soils
Option 9C
Option 9B
Option C2
Option 10B
Option 5
Option 6
Option D
Option F
Option 11A
Option 11B
Common PortionOptions 9, 10, & 11
Rosemount/UMore/Empire Area
Transportation System Study
Figure 13
Hydric Soils
Hydric Soils
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORTJUNE 2010
27
5.3 Step 3: System Level Evaluation This phase of evaluation moved beyond individual corridors and assessed how remaining options would function as part of a regional transportation system. Referencing back to Figure 4, the PMT agreed to identify a regional roadway system that would generally provide roadway capacity in the areas identified during the earlier phases of this study. Table 7 and Figures 14 and 15 capture the recommendations developed by the PMT over a series of PMT meetings during the summer and fall of 2009.
6.0 Final Corridor Alignment Recommendations and Roadway Characteristics
Figure 16 shows the recommended transportation system developed by the PMT. The recommendations of this study include:
The regional arterial road network as shown on the Recommended Regional Arterial Corridors map will serve as a planning tool for this area as it develops. This recommended system will be used by study partners and surrounding communities as land use and transportation plans are implemented.
The roadway system recommended in this study will form a “back bone” arterial network. This network was developed using the best information available for a long-term corridor planning study. The recommended corridors may be refined in response to changing circumstances and new information. Any refined corridors would undergo the same level of evaluation as was completed for the recommended corridors.
The unshaded rows in Table 7 describe the recommended number of lanes and the recommended functional classification system for each alignment. The combination of corridors composing the recommended regional road system for the study area is not consistent with spacing guidelines, but represents a compromise that provides:
Reasonable spacing and connectivity,
Consistency with and support for local plans, and
Minimum impact to area resources.
When Dakota County constructs or re-constructs any of the regional roadways recommended in this study, it is anticipated that the County would use either two-lane or four-lane cross-sections, as shown in Figure 17, based on an assessment of the forecast volume of traffic in each of the corridors. Details, such as whether or not four-lane cross-sections will be divided will be determined during subsequent phases of project development. This study assumed a 150 foot right-of-way to initially assess corridor impacts; this width would accommodate both 2-lane and 4-lane rural roadways.
AMA
Regional Park
160th St E
190th St E
145th St E
Bla
ine
Av
e E
200th St E
Elm St
170th St W
Ash St
145th St W
210th St W
200th St W
210th St E
Ver
mill
ion River Tr
Cla
yto
n A
ve
150t
h St W
160th St W
42
46
71
50
74
46
66
46
66
42 42
46
WastewaterTreatment
Fac.
WMA
VermillionHighlands
AMA
UMorePark
52
42
81
79
62
79
81
81
81
72
73
81
3
3 52
52
3
3
50
52
10/30/2009
Option K - Continue to useexisting Hwy. 50; no new lanes.
0 3,000 6,0001,500 Feet
Rosemount/UMore/Empire Area
Transportation System Study
Figure 14East-West Regional
Arterial Corridor Options
Final Evaluation Results
175th St. Extension,Implement with previously plannedCounty Road; Tie-intoBiscayne Ave. alignment
CS
AH
42
Co
rrid
or
Option A, Implement Previously Planned Intersections Improvements; Consider expanding to 6-lanes
Option B, ImplementExpansion to 4-lanes;Consider expansion to 6-lanes
Option C1,Eliminate
Option K
Option C2, Eliminate
Option D,Eliminate
Option I - Continue to useexisting CSAH 66; no new lanes.
Option I, Implement Planned County Road along with Biscayne Ave. alignment to con-nect to CSAH 66
Eliminate Diagonal; re-consider direct connection in future if required by increasing traffic
CS
AH
46
& 1
70
th S
t. C
orr
ido
rsC
SA
H 6
6.2
00
th S
t. C
orr
ido
rH
wy.
50
. C
orr
ido
r
AMA
Regional Park
UMorePark
WastewaterTreatment
Fac.
WMA
VermillionHighlands
AMA
42
200th St E
160th St E
170th St W
Elm St
145th St W
Ash St
200th St W
210th St W 210th St E
Cla
yto
n A
ve
Ver
mill
ion River Tr
150t
h St W
160th St W
190th St E
145th St E
Bla
ine
Av
e E
52
42
46
71
50
74
46
66 66
42 42
4646
81
79
62
79
81
81
81
72
73
81
3
3 52
52
3
3
50
52
10/07/2009
Option 2, Eliminate
Option 9A, Eliminate
Option 10A,Eliminate
Option 11,Implement
Option 10B,Eliminate
Option 1 - Continue to useexisting Hwy. 3; no new lanes.
0 3,000 6,0001,500 Feet
Rosemount/UMore/Empire Area
Transportation System Study
Figure 15North-South Regional
Arterial Corridor Options
Final Evaluation Results
Option 4
Options 9, 10, 11Common Alignment,Implement
Option 5, Implement
Option 6, Eliminate
Option 9B, Eliminate
Option 9C, Eliminate
Option 11B, Implement thisor Option 11A
Option 11A, Implement thisor Option 11B
Hwy. 3 Corridor Biscayne Ave. & Akron Ave. Corridor Blaine Ave. & CR 81/Clayton Ave. Corridor
AMA
Regional Park
Dako
ta C
ou
nty
T1
30
4
UMorePark
WastewaterTreatment
Fac.
WMA
VermillionHighlands
AMA
74
46
50
71
46
42
42
66 66
46
42
81
81
72
62
81
73
81
79
81
79
42
170th St E
197th St W
Ah
ern
Blv
d
Statio
n Tr
170th St W
An
ne
tte
Ave
Bis
cayn
e A
ve
190th St W
52
Ash St
210th St W
Elm St
145th St W
210th St E
150t
h St W
190th St E
Cla
yto
n A
ve
160th St W
200th St W
160th St E
145th St E
Bla
ine
Av
e E
Ver
mill
ion River Tr
200th St E
3
52
52
50
3
3
3
12/10/2009
0 3,000 6,0001,500 Feet
Option A
Option B
Option 11
Option K
For north-south and east-west corridors, connections to roads outside of the study area will be determined in later studies.
Option 5
Option I
Option I
Option 11
Option 11A
Option 11B
County Park
Hwy. 3
Planned Dakota County Highways
Recommended, Regional Arterial Corridors
175th St Extension
Rosemount/UMore/Empire Area
Transportation System Study
Figure 16
Recommended Regional
Arterial Corridors
Option 11A is the preferred option. Adjacent to Vermillion Highlands,the location of the corridor will bebased on the location of the powerlinethat currently runs between the WMA's eastern border WMA and private property.
Option 11B would occur if Mn/DNR expands Vermillion Highland boun-daries by purchasing land from willing owners and receives necessary County and Township approvals. (Note: Mn/DNR's practice is to acquire land from willing land owners; the agency has not typically used condemnatio
n).
ROSEMOUNT/EMPIRE/UMORE TRANSPORTATION SYSTEM STUDY - JUNE 2010
31
TABLE 7 Final Corridor Evaluation—Findings
Recommendation Number of Lanes Functional Classification Date of PMT Concurrence
Note: Shaded cells indicate a recommendation to eliminate a transportation corridor option; unshaded cells indicate a recommended option. Refer to the map, “Remaining & Refined Regional, Arterial Corridor Options”
NORTH/SOUTH-BOUND CORRIDORS OPTIONS
Hwy.
3
Option 1 Continue to use existing Hwy. 3 between Hwy. 50 and CSAH 42. Hwy. 3 won’t be expanded because Mn/DOT has no plans or funding and because of limited opportunity to expand through Rosemount.
No change—3-lanes through Rosemount; 2-lanes through rest
A-Minor Arterial (no change)
08/03/09 Option 2 Eliminate Option 2 given the limited opportunity to expand Hwy. 3 and
Rosemount’s lack of support. Identify an additional north-south roadway in close proximity to Hwy. 3 (see the Biscayne Ave. Corridor).
N/A N/A
Bisc
ayne
Ave
.
Option 4 Eliminate due to inconsistencies with City of Rosemount land use plans. N/A N/A
09/17/09
Option 5 Implement Option 5 along Biscayne Ave. in the south and connecting to Akron Ave. in the north.
4-lanes: CSAH 42 to 170th Street; 2-lanes: 170th Street to Hwy. 50 (with possible 4-lanes)
A-Minor Arterial (Hwy. 3, no change; Biscayne Ave. upgrade)
Option 6 Dismiss Options 6 because of potential environmental impacts and diminished ability to serve future demand, compared to Option 5. N/A
CR 79
/CSA
H 71
/Blai
ne A
ve.
Option 9A Eliminate Options 9A, 9B, and 9C due to impacts to Vermillion Highlands and natural resources within.
N/A N/A
10/15/2009
Option 9B
Option 9C
Option 10A Eliminate due to lack of regional transportation advantage and because of engineering challenges presented by Little Lone Rock. Option 10B
Option 11A
Implement Option 11. Near Vermillion Highlands, Option 11A is the preferred option. Option 11B would occur if Mn/DNR expands Vermillion Highland boundaries by purchasing land from willing owners and receiving necessary County and Township approvals.
2-lanes on new north-south alignment
Minor Arterial (new regional road) Option 11B
ROSEMOUNT/EMPIRE/UMORE TRANSPORTATION SYSTEM STUDY - JUNE 2010
32
TABLE 7 Final Corridor Evaluation—Findings
Recommendation Number of Lanes Functional Classification Date of PMT Concurrence
Note: Shaded cells indicate a recommendation to eliminate a transportation corridor option; unshaded cells indicate a recommended option. Refer to the map, “Remaining & Refined Regional, Arterial Corridor Options”
EAST/WEST-BOUND CORRIDOR OPTIONS
CSAH
42 Option A Use existing CSAH 42 as planned and documented in the CH 42 Final Study, including planned access management. (Attachment A: Updated Recommended Roadway Improvements Segment 15: TH 3 to TH 52, 2007).
4-lanes (no change from existing; consider future 6-lanes)
Principal Arterial (no change) 08/03/2009
CSAH
46 &
170th
St.
Option B Expand existing CSAH 46 alignment by 2- to 4-lanes.
4- to 6-lanes (expand by 2- to 4-lanes)
A-Minor Arterial (no change)
9/17/09
Option C1 Eliminate Options C1 and C2 as these would not best meet regional transportation needs, or the transportation needs of Rosemount and Empire Township.
N/A N/A
Option C2
Option D Eliminate as regional roadway option because of incompatibility with UMore Park planned development.
Option F Eliminate as regional roadway option because of incompatibility with UMore Park planned development.
CSAH
66 Option I Use phased approach to implement a connection between Hwy. 3 and
CSAH 66/200th Street. Initially, use 190th Street alignment to Biscayne Ave.; use Biscayne Ave. south to connect to CSAH 66/200th St. Reconsider a direct connection (similar to diagonal shown on Figure 12) from Hwy. 3 to CSAH 66 if traffic levels warrant in the future.
2-lanes (no change)
Hwy.
50 Option K Continue to use existing Hwy. 50; no changes in function or geometry
recommended. 2-lanes (no change) A-Minor Arterial (no change) 08/03/09
08/09/2009
Representative 2-lane and 4-lane Cross-Sections
Figure 17
ThroughLane
ThroughLane
Shoulder Shoulder
150 ftRight-of-Way
ThroughLane
Shoulder ShoulderThroughLane
Median ThroughLane
ThroughLane
Divided Urban 4Divided Urban 4--Lane CrossLane Cross--SectionSection
Rural 2Rural 2--Lane CrossLane Cross--SectionSection
Alternative Concept Design CriteriaAlternative Concept Design Criteria
Sidewalk/Trail
Sidewalk/Trail
150 ftRight-of-Way
• Assumed a 60 mph design speed
• 1,500 feet minimum curve radius (Source: Mn/DOT Road Design Manual – minimum for 60 mph is 1,349 feet with full superelevation)
• 150-foot Right-of-Way to accommodate a divided 4-lane roadway
(Source: Dakota County Contiguous Plat Ordinance)
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORT JUNE 2010
34
7.0 Activities to Implement Recommended Alignments 7.1 Activities and Timing to Implement Recommendations Future roadway construction will be coordinated with development. When traffic levels or development in an area warrant, consideration will be given to construction of new roads or upgrading existing regional roads. The schedule for implementing study recommendations varies by area.
Dakota County, the City of Rosemount, Empire Township, the University of MN, and Mn/DNR have formally adopted or recognized the recommendations through their governing bodies either by resolution or letter of support, all of which are included in Attachment D. Within the next few years, communities will update their comprehensive land use and/or transportation plans to reflect study recommendations.
In the longer term, construction of regional roads will occur as land uses change (e.g., UMore Park) and development is approved by local governments. UMore Park plans currently show the northern part of the parcel developing first. Total build-out is expected in 30 years, however, as with any development, this too will be subject to market forces.
This network was developed using the best information available for a long-term corridor planning study. This included current environmental resource information, engineering considerations, and land use management plans. The recommended corridors may be refined in response to changing circumstances and new information. Any refined corridors would undergo the same level of evaluation as was completed for the recommended corridors.
Implementation of specific corridors is all subject to phasing, in response to development. For example, northern portions of the north-south alignments for Biscayne Avenue/Akron Avenue and Blaine Avenue may be initially built to accommodate UMore Park, as it develops. However, the southern portions of these corridors may not get built until much later, in response to future development.
7.2 Right-of-Way Acquisition The acquisition of right-of-way for transportation facilities requires significant financial resources and is a time consuming process. Jurisdictions responsible for road development (state, county, city, etc.) will use available right-of-way preservation tools. For Dakota County, this includes requiring plat dedication for highway corridors to preserve the right-of-way required to implement any of the recommended alignments. In areas that do not develop, a condemnation process would be used to acquire additional right-of-way.
7.3 Context-Sensitive Solution Considerations Development evaluation criteria and processes, as well as potential transportation corridor options was structured according to the principles of a Context Sensitive Solutions (CSS) process. Given the unique setting for this project—including the unique UMore Park development and Vermillion Highlands—the CSS approach is valuable because decision-making is focused on project context and stakeholder-based criteria. Through this process, the PMT accomplished transportation objectives while developing a project that reflects community values. A four-step approach to CSS was implemented, as follows:
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORT JUNE 2010
35
1. Community Inventory and Values;
2. Goals and Criteria;
3. Alternatives Development and Evaluation; and
4. Implementation Planning and Roles.
CSS is a process that will continue to take place through all upcoming stages related to implementing the recommended transportation system. Given the early nature of this study, CSS was applied to identifying project context and issues important to stakeholders. However, the PMT did broadly contemplate geographic areas within the study area which should be given a higher level of CSS consideration moving forward into next steps. These areas are shown on Figure 18.
8.0 Other Transportation Considerations 8.1 Supporting Local Road System, Intersection Spacing, and Other Possible
Roadway Projects The regional roadway network recommended for this study area will be used by the County, local communities, and the University of Minnesota to plan a supporting local road system to complement the transportation network and serve any future land development. Specifically, the Metropolitan Council’s roadway spacing guidelines shown in Table 1 will be used to aid in the planning of the local road network in developing areas, including UMore Park.
Intersection spacing is directly tied to the implementation of a supporting road network, discussed above. As such, this topic will be considered in tandem with planning of a supporting, local road network. Dakota County access spacing guidelines will be adhered to in any future access planning.
In addition to any future access spacing planning, previous recommendations for the CSAH 42 corridor will be implemented as planned (see the CH 42 Final Study planned access management and Attachment A: Updated Recommended Roadway Improvements Segment 15: TH 3 to TH 52, 2007). The PMT recognizes that there is potential for some recommended corridors to impact the need for intersection improvements identified in the CH 42 Study. For example, the Biscayne Ave./Akron Ave. north-south alignment may result in a diversion of traffic from Highway 3 that could reduce traffic levels at the intersection of Highway 3 and CSAH 42 to the point that a previously recommended interchange may not be necessary. Any impact this study’s recommendations would have on plans for other corridors in or near the study area would need to be studied in detail. Dakota County will work with local communities and Mn/DOT to assess all future capacity issues, necessary improvements, and the interrelatedness of future transportation improvements.
During this study, the need to plan for future crossings of Highway 52 were discussed, including the possibility of grade separating crossings at 170th Street and CSAH 66/200th. While these intersections are outside of this study area and therefore were not considered in detail, it should be noted that Mn/DOT, Dakota County, and local communities may consider grade separations at these locations in the future.
Streams and natural areas may provide opportunities for modified highway crossings that promote safety for people and/or wildlife
by passing underneath the roadway.
Hydric soils in the project area may present opportunities for wetland restoration projects that serve as mitigation for impacts related to highway construction.
Preservation of greenway corridors through this study area will involve the
development of grade-separated highway crossings for trail users, access to natural
resource assets such as the Vermillion River, and trail continuity for a regional
trail system.
Fields south of County Road 46 and west of Clayton Avenue are intensively used by farmers serving local farmers markets
Gravel mining in UMore Park and Empire Township will create opportunities for new lakes and related recreational activities.
These lakes offer an opportunity to extend a natural/recreational area corridor beyond the
County Park and WMA to the south.
Areas shaded orange on this base map are “Hydric Soils”– generally wet locations that are indicative of wetlands or the potential for wetlands.
11/02/2009
Context Sensitive Opportunities for Future Consideration
Figure 18
ROSEMOUNT/EMPIRE/UMORE AREA TRANSPORTATION SYSTEM STUDY REPORT JUNE 2010
37
8.2 Pedestrian and Bicycle Facilities Dakota County has plans to implement a north-south and an east-west regional greenway corridor within the study area. The currently planned greenway corridors are shown on Figure 18. These greenway alignments are concepts; the actual location of these greenways will be the result of further planning actions by Dakota County, the City of Rosemount, Empire Township, the University of Minnesota, and Mn/DNR. Specifically, the preferred trail alignment for crossing the Vermillion River will be mutually evaluated by appropriate agencies and determined as part of the 2010 master planning process. At any points where greenways will intersect an existing or planned County highway, a grade-separated highway crossing will be considered for trail users. Specific details regarding funding will be addressed during future inter-agency coordination.
8.3 Future Transit Service The study area currently includes primarily rural and open space land uses and is not served by transit. However, plans for UMore Park and surrounding communities will likely increase the intensity of land uses in coming decades. The UMore Park Concept Master Plan shows that light rail, commuter bus, and internal bus service may some day service the development. Additionally, the Robert Street Corridor Transit Feasibility Study’s Long Term Corridor Vision shows a “potential transitway” extending down Highway 3 (to just south of CSAH 42) and providing transit access into UMore Park. None of the above mentioned transit concepts have been planned or funded. However, Dakota County will continue to coordinate with the University of Minnesota, the Metropolitan Council, and local communities regarding any future transit concepts that would service the study area.
Dakota County’s Transit Plan (Review Copy, December 2007) has identified specific transit needs for service beyond anything that is included in regional or county plans. Within the study area, the County’s Transit Plan has identified needs on CSAH 42, CSAH 46, Highway 3, and Highway 50. As noted in the Transit Plan, implementation of these improvements is considered very long range. Moving forward with any County Highway improvements the Plan does recommend that, “All County arterial highways should provide appropriate level of infrastructure for transit service including adequate widths, shoulders, pullouts, and trails” (Dakota County Transit Plan, December 2007, Chapter Seven: Page 4 of 7).