Final Project:
Development Proposal
Introduction to the Construction Industry
[QSB30105]
Lee Xin Ying 0322432
Lau Hui Ming 0323827
FNBE March Intake 2015
Tutor: Puan Hasmanira Mokhtar
![Page 2: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/2.jpg)
Content
1. Project Background
2. Introduction to Site
3. Location & Key Plan & Site Plan
4. Site Context
5. Analysis + Inventory + Observation
- Circulation
- Microclimate
6. Individual Proposal ( Lau Hui Ming)
7. Individual Proposal ( Lee Xin Ying )
![Page 3: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/3.jpg)
Project Background
This is the final project of Introduction to the
Construction Industry. This project consist of 10%
of group work and 30% of individual work. The
objective of this project is to enable students to
develop an understanding of the building team, its
organization, duties and inter-relations. In addition,
it is also to develop an awareness of their
professional responsibilities and to appreciate
their profession in the construction industry.
In a group of 2 students, we need to find a
specific empty land to initiate a small construction
project. The size of the land shall between 50m x
50m (2500 ㎡) – 50m x 70m(3500 ㎡).
![Page 4: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/4.jpg)
Introduction to the Site
After doing a few research and consulting with our
tutor, we decided to choose this site for our project
which is located at Jalan PJS 9/30, Bandar Sunway,
Petaling Jaya, Selangor, Malaysia. It is a land with some
trees and it has a sidewalk along the land as shown in
the pictures above.
This location can be found around the residential
area and few meters away from a commercial area.
The commercial area consists of shopping centre, and
small shops such as restaurants, banks, stationary shop
and etc. There are two universities inside the
commercial area which is The One Academy and A Cut
above Academy.
![Page 5: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/5.jpg)
Site Location: Jalan PJS 9/30
Bandar Sunway
47500 Petaling Jaya
Selangor, Malaysia
![Page 6: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/6.jpg)
Site Plan
Site
Commercial Area
Education
Tree
Residential Area
Police Station
![Page 7: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/7.jpg)
Site Context
Site
Commercial area
Residential area
Police station
Education
![Page 8: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/8.jpg)
Site Observation
The site with the sidewalk.
The residential area beside the site.
The commercial area opposite the site.
![Page 9: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/9.jpg)
Site Analysis
Microclimate
Site
Commercial Area
Education
Tree
Residential Area
Police Station
Sunset Sunrise
![Page 10: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/10.jpg)
Microclimate
Site
Commercial Area
Education
Tree
Residential Area
Police Station
Wind flow
Wind flow from two direction.
![Page 11: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/11.jpg)
Circulation
Site
Commercial Area
Education
Tree
Residential Area
Police Station
Circulation 1 Circulation 2
![Page 12: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/12.jpg)
At first, we went to the site by walking from Sunway
Pyramid and passed through the commercial area. After that,
we passed through the road and reached residential area of
PJS 9.
There are a lot of vehicle come from Bandar Sunway.
Traffic jam will occur at 7.00 am to 8.00 am, 12.00pm to 2.00
pm and 7.30pm to 9.00 pm. However, the site is easily to
access because the residents are entering site by walking and
cycling. For the foreigners, they can go to site easily because
there is a big road beside there for vehicles to use.
![Page 13: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/13.jpg)
From Picture Distance (km)
Time (Min)
The One Academy
1 4
Sunway Pyramid
1.9 6
Papa John’s Pizza
2.1 9
Wawasan Open University
1 3
Public Bank
2 8
![Page 14: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/14.jpg)
Final Project:
Development Proposal
Introduction to the Construction Industry
[QSB30105]
Lau Hui Ming 0323827
FNBE MARCH 2015
Tutor : Pn. Hasmanira
![Page 15: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/15.jpg)
Content
No. Title Page
1 Introduction 1
2 Rationale 2
3 Benefits and Impacts 3 4 Bubble Diagram 4
5 Plan 5
6 Concept and Ideas 6
7 Image of Ideas 7
8 List of Professions Involved 8
9 Tasks of Professions Involved 9-13 10 Costing 14
11 Conclusion and References 15
![Page 16: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/16.jpg)
Introduction
In this final project, we are given a task to find
a specific empty land with the size between 2500
㎡ to 3500㎡ to initiate a small construction project
on it in a group of 2 people.
I have decided to develop a recreation area on
the land that we found. I decided to a leisure park
because the land is surrounded with residential
area, education area, commercial area and also
service area which means a lot of people will go
through this land everyday.
1
![Page 17: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/17.jpg)
Rationale to Build a Playground
Near housing area so that people from this area
can go to the location easily.
Enable children from Mega Kids Child
Development Center & Learning Academy which is
nearby the site to play.
Can have a leisure time with their children.
Easy accessibility to the site location.
Near shopping mall and other shops which enable
people come here for a rest when they finish
shopping.
2
![Page 18: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/18.jpg)
Benefits and Impact to build a
Playground
Increase social skills when they play with other children they learn to communicate, share, collaborate and empathise with others.
Increase their imagination and creativity because outside play is often open-ended and children need to be creative about what and how games are played.
Increase thinking and problem solving skills as children assess risks and tackle new challenges they learn about having a go, persistence and perseverance and the success those attributes can bring.
Improve sense of self as they master new skills and play with other children they improve their competence and confidence in their own physical and social abilities.
Improve sense of connection to place, to peers and to their local community and environment.
Increase self care skills in managing physical and social challenges which help children to learn about keeping themselves safe.
3
![Page 19: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/19.jpg)
Bubble Diagram of Proposal
4
Net
Climber
Playground
Gazebo
Play
Structure
Swing
Benches
Lawn
Play
Structure
Shade
Canopy
![Page 20: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/20.jpg)
Plan of Proposal
5
![Page 21: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/21.jpg)
Concept and Ideas of Proposal
The construction plan proposal is designed based on the
50m x 50m empty land located at Jalan PJS 9/30, Bandar
Sunway, Petaling Jaya, Selangor. The aim of this construction
is to transform the unused empty land into a place that can
benefit the residents.
After surveying, I have found that there is no any place
provided for the residents to have a time to enjoy with
nature. Thus, I decided to start a construction of a
playground.
The playground is open for everyone. It provides two
types of play structures. First structure is for the children
with the age between 2-5 years old and there is a shade
canopy over the play structure so that the small children will
not feel hot easily. The second play structure is for the
children with the age between 5-12 years old.
In addition, the playground also provides arch swing and
Net Climber for residents to play. The children can sit on the
special designed springer which is in octopus’ shape. Parent
can watch their children by sitting on the benches or gazebo
for a rest.
6
![Page 22: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/22.jpg)
7
![Page 23: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/23.jpg)
List of Professions Involved
1. Landscape Architect
2. Civil Engineer
3. Quantity Surveyor
4. Project Manager
5. Construction Worker
8
![Page 24: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/24.jpg)
Task of Professions Involved
Landscape Architect
- Developing new or improved theories and
methods to promote environmental awareness and undertaking planning, design, restoration, management and maintenance of cultural and/or historic landscapes, parks, sites and gardens.
- Planning, design, management, maintenance and monitoring functional and aesthetic layouts of built environment.
- Contributing to the planning, aesthetic and functional design, location, management and maintenance of infrastructure.
- Identifying and developing appropriate solutions regarding the quality and use of the built environment in urban, suburban and rural areas and making designs, plans and working drawings, specifications of work, cost estimates and time schedules.
9
![Page 25: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/25.jpg)
Civil Engineer
- Analyze survey reports, maps, drawings, blueprints,
aerial photography, and other topographical or geologic
data to plan projects.
- Plan and design transportation or hydraulic systems
and structures, following construction and government
standards, using design software and drawing tools.
- Compute load and grade requirements, water flow
rates, and material stress factors to determine design
specifications.
- Inspect project sites to monitor progress and ensure
conformance to design specifications and safety or
sanitation standards.
- Direct construction, operations, and maintenance
activities at project site.
- Direct or participate in surveying to lay out installations
and establish reference points, grades, and elevations to
guide construction.
10
![Page 26: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/26.jpg)
Quantity Surveyor
- Managing the finances.
- Working to keep project on time.
- Working to keep project within the budget.
- Making sure that construction cost and production
are managed as efficiently as possible.
- Resolving disputes between contracting parties.
- Preparing insurance replacement estimates for all
kinds buildings.
11
![Page 27: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/27.jpg)
Project Manager
Planning and Defining Scope
Activity Planning and Sequencing
Resource Planning
Developing Schedules
Time Estimating
Cost Estimating
Developing a Budget
Documentation
Creating Charts and Schedules
Risk Analysis
Managing Risks and Issues
Monitoring and Reporting Progress
Team Leadership
Strategic Influencing
Business Partnering
Working with Vendors
Scalability, Interoperability and Portability Analysis
Controlling Quality
Benefits Realisation
12
![Page 28: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/28.jpg)
Construction Worker
- Mop, brush, or spread paints, cleaning solutions, or
other compounds over surfaces to clean them or to
provide protection.
- Operate jackhammers and drills to break up concrete
or pavement.
- Place, consolidate, and protect case-in-place concrete
or masonry structures.
- Position, join, align, and seal structural components,
such as concrete wall sections and pipes.
- Shovel cement and other materials into portable
cement mixers; and mix, pour, and spread concrete.
- Signal equipment operators to facilitate alignment,
movement, and adjustment of machinery, equipment,
and materials.
13
![Page 29: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/29.jpg)
Costing
No. Item Unit Quantity Amount (RM)
1 5-12 year old play structure
㎡ 1 149,759.00
2 2-5 year old play structure
㎡ 1 146,542.00
3 Shade canopy ㎡ 1 200.00
4 Gazebo No. 1 8,542.00 5 Swing No. 2 600.00 6 Net climber No. 1 145.15 7 Benches no. 1 340.00 8 Seesaw No. 2 236.80 9 Walkway (Big) No. 19 362.90 10 Walkway (Small) No. 32 320.00 11 Maintenance - - 500.00
Total 307,547.85
14
![Page 30: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/30.jpg)
Conclusion
I found it is a tough work to do however I have learned
new things and gain new knowledge. I also got
experience when I went to visit the site with my
partner, Xin Ying. I also understand the responsibilities
of the professions involved in this project.
References
http://sfrecpark.org/project/west-sunset-playground/
http://www.kidsafewa.com.au/playgroundimportance.
htm
http://www.fixr.com/costs/build-playground
http://www.moduplay.com.au/blog/playground-
planning/what-does-it-cost-to-build-a-playground/
https://www.google.com/search?q=plan+view+of+play
ground&safe=active&biw=1366&bih=643&tbm=isch&t
bo=u&source=univ&sa=X&ved=0CCgQsARqFQoTCKb3r
Lru88YCFcQYpgodwRwAeA#safe=active&tbm=isch&q=
benches&imgrc=tCawnhDK85Hm4M%3A
15
![Page 31: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/31.jpg)
Final Project:
Development Proposal
Introduction to the Construction Industry
[QSB30105]
Lee Xin Ying 0322432
FNBE MARCH 2015
Tutor : Pn. Hasmanira
![Page 32: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/32.jpg)
Content
Title
Page
1. Introduction
3
2. Rationale and Benefits
4
3. Conceptual Plan
5-6
4. Floor Plan
7
5. Images of Ideas
8-13
6. Plan View
14
7. Professions Involved
15-21
![Page 33: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/33.jpg)
Introduction
In this final project, we are given a task to find
a specific empty land with the size between 2500
㎡ to 3500㎡ to initiate a small construction project
on it in a group of 2 people.
I have decided to develop a commercial area
and recreation area on the land that we found. I
decided to build a cafe and a leisure park because
the land is surrounded with residential area,
education area, commercial area and also service
area which means a lot of people will go through
this land everyday.
There is onsists of 2 floor. First floor is the car
park and leisure park and second floor is the cafe.
![Page 34: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/34.jpg)
Rationale and Benefits
To provide healthy and delicious food to
customers.
To provide a comfortable place to customer to
have a meal and chitchat.
To unite neighbourhood relationship between
each other.
To provide a place to leisure in the spare time.
To offer a place to the residents to exercise
and communicate.
To provide a open space to the children play
with each other.
The site is easy to access.
Nearby housing area and commercial area.
![Page 35: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/35.jpg)
Conceptual Plan
1st Floor
42m
42m
![Page 36: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/36.jpg)
Scale 1:250
2nd
Floor
Scale 1:200
37m
37m
![Page 37: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/37.jpg)
Floor Plan (2nd
Floor)
![Page 38: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/38.jpg)
Washroom
Kitche
n
Entrance
Bar Counter
![Page 39: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/39.jpg)
Scale 1:200
![Page 40: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/40.jpg)
Images of Ideas
1st
Floor
Exercise Area
Exercising today is very important to a person health. Exercising is
mainly for cardiovascular fitness. Some people do it because they just
enjoy it. Exercising also gently improves health. Health benefits such as
helping weight management, improve quality of life, and reducing the
feelings of depression and anxiety. Social benefits is one of the best
ways to meet new people while exercising. Exercise also can combats
health conditions and diseases, improves mood, boosts energy,
promotes better sleep and also can be fun.
Facilities:
![Page 41: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/41.jpg)
Children Playground
It is a vital part of childhood that helps children develop physical strength, coordination and balance. It can also provide opportunities for children to learn and develop:
Social Skills - when they play with other children they learn to communicate, share, collaborate and empathise with others.
Imagination and creativity - outside play is often open-ended and children need to be creative about what and how games are played.
Thinking and problem solving skills - as children assess risks and tackle new challenges they learn about having a go, persistence and perseverance and the success those attributes can bring.
Sense of self - as they master new skills and play with other children they improve their competence and confidence in their own physical and social abilities.
Sense of connection - to place, to peers and to their local community and environment.
Self-care skills - managing physical and social challenges helps children to learn about keeping themselves safe.
Facilities:
![Page 42: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/42.jpg)
Recreation Area
A place to relax, communicate and breath the fresh air.
Picnic Table Wall Fountain
Fountain Bench
![Page 43: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/43.jpg)
Vegetation
Exterior Spiral Staircase
Space saving
Have strong aesthetic appeal in the right situation.
![Page 44: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/44.jpg)
Stepping Stone
2nd
Floor
Seating Area
![Page 45: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/45.jpg)
Bar Counter
Kitchen
![Page 46: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/46.jpg)
Toilet
![Page 47: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/47.jpg)
Plan View
Drive Way Parking Area
Trees and Shrubs
Outdoor Staircase
![Page 48: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/48.jpg)
Scale 1:250
Profession Involved
Architect
Control a project from start to finish and work with a number of construction professionals.
Discussing the objectives, requirements and budget of a project.
Consulting with other professionals about design.
Preparing and presenting feasibility reports and design proposals to the client.
Advising the client on the practicality of their project.
Using IT in design and project management, specifically ucing computer-aided design software.
Keeping within financial budgets and deadlines.
Producing detailed workings, drawings and specifications.
Specifying the nature and quality of materials required.
Preparing tender applications and presentations.
Negotiating with contractors and other professionals.
Preparing applications for planning and building control departments.
Drawing up tender documents for contracts.
Project managing and helping to coordinate the work of contractors.
Regular site visits to check on progress, ensuring that the project is running on time and to budget.
Resolving problems and issues that arise during construction.
Ensuring that the environmental impact of the project is managed.
![Page 49: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/49.jpg)
Landscape Architect
Overseeing the design of a variety of projects, including
urban regeneration schemes, pedestrian schemes, road
or retail schemes, and maintaining the character of sites of
natural beauty.
Establishing general landscape requirements with clients.
Conducting preliminary studies of the sites (including
contours, soil, ecology, buildings, roads).
Assessing a site’s potential to meet the client’s
specifications.
Carrying out environmental impact assessments.
Seeking and taking into account the views of local
residents, potential users, and parties with a vested
interest in the project.
Accurately preparing and presenting detailed plans and
working drawings, including applications, construction
details and specifications for the project using computer-
aided design (CAD) packages or similar design software.
Presenting proposals to clients, dealing with enquiries and
negotiating any amendments to the final design.
Matching the client’s wishes with the knowledge of what
will work best.
Contacting and coordinating manufacturers and suppliers.
Putting work out to tender, selecting a contractor and
manager, and leading cross-functional teams.
Making site visits.
Ensuring deadlines are met.
Liaising with other professionals on the project.
Monitoring and checking work on-site.
Authorising payment once work has been satisfactorily
completed.
![Page 50: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/50.jpg)
Attending public inquiries to give evidence if necessary.
Generating new business opportunities.
Project Manager
Schedule the project in logical steps and budget time required
to meet deadlines.
Determine labor requirements and dispatch workers to
construction sites.
Inspect and review projects to monitor compliance with
building and safety codes, and other regulations.
Interpret and explain plans and contract terms to
administrative staff, workers, and client, representing the
owner or developer.
Prepare contracts and negotiate revisions, changes and
additions to contractual agreements with architects,
consultants, clients, suppliers and subcontractors.
Obtain all necessary permits and licenses.
Construction Worker
unload, carry and stack building materials and place tools and equipment in position
dig trenches using hand tools or jackhammers to break up rock and concrete, so that footings and services can be laid
place and compact filling and quarry materials
help to erect and dismantle scaffolding (subject to certification in some states and territories), ramps, catwalks, barricades and warning lights
mix, pour and spread concrete under supervision
use wheelbarrows to remove rubble and rubbish from building sites
dismantle small structures and strip materials in preparation for new construction
![Page 51: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/51.jpg)
operate construction machinery (such as excavators), subject to any licensing and accreditation requirements
clean surfaces for painters.
Quantity Surveyor
Seeking funding sources and submitting bids
Carrying out feasibility studies
Preparing plans, contracts, budgets, bills of quantities and other documentation
Performing risk analysis evaluations
Cost control
Writing reports
Preparing and submitting final accounts
Making valuations
Arranging payments to suppliers and contractors
Providing advice and forecasts about costs
Supervising staff.
Structural Engineer
Preparing reports, designs and drawings
Making calculations about loads and stresses Selecting appropriate construction materials
Providing technical advice
Obtaining planning and/or building regulations approval
Liaising with relevant professional staff
Monitoring and inspecting work undertaken by contractors
Administering contracts Managing projects
Inspecting properties to check conditions/foundations
![Page 52: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/52.jpg)
Mechanical Engineer
Read and interpret blueprints, technical drawings, schematics, and computer-generated reports.
Confer with engineers and other personnel to implement operating procedures, resolve system malfunctions, and provide technical information.
Research and analyze customer design proposals, specifications, manuals, and other data to evaluate the feasibility, cost, and maintenance requirements of designs or applications.
Specify system components or direct modification of products to ensure conformance with engineering design and performance specifications.
Research, design, evaluate, install, operate, and maintain mechanical products, equipment, systems and processes to meet requirements, applying knowledge of engineering principles.
Investigate equipment failures and difficulties to diagnose faulty operation, and to make recommendations to maintenance crew.
Assist drafters in developing the structural design of products, using drafting tools or computer-assisted design/drafting equipment and software.
Provide feedback to design engineers on customer problems and needs. Oversee installation, operation, maintenance, and repair to ensure that
machines and equipment are installed and functioning according to specifications.
Conduct research that tests and analyzes the feasibility, design, operation and performance of equipment, components and systems.
Recommend design modifications to eliminate machine or system malfunctions.
Develop and test models of alternate designs and processing methods to assess feasibility, operating condition effects, possible new applications and necessity of modification.
Develop, coordinate, and monitor all aspects of production, including selection of manufacturing methods, fabrication, and operation of product designs.
Estimate costs and submit bids for engineering, construction, or extraction projects, and prepare contract documents.
Perform personnel functions, such as supervision of production workers, technicians, technologists and other engineers, and design of evaluation programs.
Solicit new business and provide technical customer service. Establish and coordinate the maintenance and safety procedures, service
schedule, and supply of materials required to maintain machines and equipment in the prescribed condition.
Study industrial processes to determine where and how application of equipment can be made.
Write performance requirements for product development or engineering projects.
Apply engineering principles and practices to emerging fields, such as robotics, waste management, and biomedical engineering.
Design test control apparatus and equipment and develop procedures for testing products.
![Page 53: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/53.jpg)
Electrical Engineer
Provide technical assistance and resolution when electrical or engineering problems are encountered before, during, and after construction.
Assemble electrical and electronic systems and prototypes according to engineering data and knowledge of electrical principles, using hand tools and measuring instruments.
Install and maintain electrical control systems and solid state equipment. Modify electrical prototypes, parts, assemblies, and systems to correct
functional deviations. Set up and operate test equipment to evaluate performance of
developmental parts, assemblies, or systems under simulated operating conditions, and record results.
Collaborate with electrical engineers and other personnel to identify, define, and solve developmental problems.
Build, calibrate, maintain, troubleshoot and repair electrical instruments or testing equipment.
Analyze and interpret test information to resolve design-related problems.
Write commissioning procedures for electrical installations. Prepare project cost and work-time estimates. Evaluate engineering proposals, shop drawings and design comments
for sound electrical engineering practice and conformance with established safety and design criteria, and recommend approval or disapproval.
Draw or modify diagrams and write engineering specifications to clarify design details and functional criteria of experimental electronics units.
Conduct inspections for quality control and assurance programs, reporting findings and recommendations.
Prepare contracts and initiate, review and coordinate modifications to contract specifications and plans throughout the construction process.
Plan, schedule and monitor work of support personnel to assist supervisor.
Review existing electrical engineering criteria to identify necessary revisions, deletions or amendments to outdated material.
Perform supervisory duties such as recommending work assignments, approving leaves and completing performance evaluations.
Plan method and sequence of operations for developing and testing experimental electronic and electrical equipment.
Visit construction sites to observe conditions impacting design and to identify solutions to technical design problems involving electrical systems equipment that arise during construction.
![Page 54: Final project(2)](https://reader030.vdocuments.mx/reader030/viewer/2022032513/55d3157ebb61ebad268b4655/html5/thumbnails/54.jpg)
Civil Engineer
Investigate sites to determine the most suitable foundation for a proposed construction
Research and advise on the best engineering solution to meet a client's needs and budget
Prepare engineering calculations required for the design of projects, and supervise the drafting of plans
Produce detailed designs and documentation for the construction and implementation of civil engineering projects
Organise the delivery of materials, plant machinery and equipment needed for the construction project and supervise labour
Develop detailed programmes for the coordination of site activities
Work with other engineers, architects, landscape architects and environmental scientists
Assist government bodies in preparing yearly works programmes (such as work on car parks, drainage, roads, aerodromes or sewerage systems) within set budgets
Operate computers to assist with the design of civil engineering projects
Coordinate and direct research, development and testing of materials, processes or systems related to civil engineering works
Research, advise on and plan the control and minimisation of air, water and solid waste pollution, and the management of water resources
Supervise the testing and commissioning of completed works Analyse and interpret reports on loading, labour, productivity,
quality, materials and performance Analyse risks associated with natural disasters (including
cyclones, earthquakes, fires and floods), and design structures and services to meet appropriate standards
Arrange for geological and geophysical investigations and carry out feasibility studies.