final project preliminary plant design of gypsum …eprints.ums.ac.id/56310/2/approval page.pdfakan...
TRANSCRIPT
i
FINAL PROJECT
PRELIMINARY PLANT DESIGN OF GYPSUM USING LIMESTONE
AND SULFURIC ACID WITH CAPACITY OF 100,000 TONS/YEAR
By:
LATEEFEE YANGOK
D 500 112 001
Supervisor:
1. Kusmiyati, S.T., M.T., Ph.D.
2. Eni Budiyati, S.T., M.Eng
DEPARTMENT OF CHEMICAL ENGINEERING
FACULTY OF ENGINEERING
UNIVERSITAS MUHAMMADIYAH SURAKARTA
2017
ii
THE APPROVAL SHEET
DEPARTMENT OF CHEMICAL ENGINEERING
FACULTY OF ENGINEERING
UNIVERSITAS MUHAMMADIYAH SURAKARTA
Name LATEEFEE YANGOK
Nim D500112001
Title of Final Project Preliminary Plant design of Gypsum using
Limestone and sulfuric acid with capacity of
100,000 tons/year
Supervisors 1. Kusmiyati, S.T.,M.T.,Ph.D.
2. Eni Budiyati, S.T., M.Eng
Surakarta,
August 2017
Has been approved by
First Supervisor Second Supervisor
Kusmiyati, S.T.,M.T.,Ph.D. Eni Budiyati, S.T., M.Eng
NIDN 0617037102 NIDN 0601017302
Dean of Engineering Head of Department
of Chemical
Engineering
Ir.Sri Sunarjono,M.T.,Ph.D. Rois Fatoni, S.T., M.Sc.,
Ph.D.
NIK.682 NIK.892
iii
PRELIMINARY PLANT DESIGN OF GYPSUM USING LIMESTONE
AND SULFURIC ACID WITH CAPACITY OF 100,000 TONS/YEAR
Abstract
Gypsum or calcium sulfate dihydrate requirement in Indonesia is fulfilled
with domestic production and imported from abroad. Domestic gypsum
production is still not sufficient to meet the needs of gypsum in Indonesia.
Therefore, imports from foreign countries are still needed. By establishing the
gypsum industry in Indonesia, it is expected to meet the needs of gypsum in
Indonesia
Gypsum is production from the reaction between limestone (CaCO3) and
sulfuric acid solution (H2SO4) 50% of weight in Continuous Stirred-Tank Reactor
(CSTR) ) with the capacity of product 100,000 tons/year in the reactor at the
operating conditions of temperature at 93 °C and pressure at 1 atm. Raw material
for the plant required are limestone (CaCO3) 7,549 kg/hour and sulfuric acid
solution (H2SO4) 6,898 kg/hour with the general reaction as follows like below :
CaCO3 (s) + H2SO4 (l) + H2O (l) CaSO4.2H2O (s) + CO2 (g) and the weight
ratio between the limestone and sulfuric acid entering the reactor is 1:1 in
kilograms. The residence time in the reactor was 10 minutes.
Plant will be build at 2030 in the Indarung,Padang with area is 16,940 m2
.The result of calculate that Fixed Cost (Fa) is 41,797,168,267. Regulated Cos
(Ra) is 505,053,337,480 Cost of raw material (Sa) is 1,358,239,263,511.Variable
cost (Va) is 629,447,458,716.get the value of BEP is 51.52% (at range 40% -
60%) and get the value of SDP is 51.52% for POT after tax is 1.8 years
(maksimmum 5 years). we get value of Internal Rate of Return (IRR) = 19,35%
So if this plant will be build so many advantages and very profitably.
Keywords: Gypsum, calcium sulfate dihydrate, CaSO4.2H2O
iv
PRARANCANGAN PABRIK GYPSUM DARI BATU KAPUR DAN ASAM
SULFAT DENGAN KAPASITAS 100.000 TON / TAHUN
Abstrak
Kebutuhan gipsum di Indonesia dicukupi dengan produksi dalam negeri
dan impor dari luar negeri. Produksi gipsum dalam negeri masih belum
mencukupi untuk memenuhi kebutuhan gipsum di Indonesia. Oleh karena itu
masih diperlukan impor dari luar negeri. Dengan pendirian industri gipsum di
Indonesia, diharapkan mampu mencukupi ketubutuhan gipsum di Indonesia
Gypsum diproduksi dari reaksi antara batu kapur (CaCO3) dan
larutan asam sulfat (H2SO4) 50% berat dalam Continuous Stirred-Tank Reactor
(CSTR)) dengan kapasitas produk 100.000 ton / tahun pada kondisi operasi suhu
dalam reaktor. Pada suhu 93° C dan tekanan pada 1 atm. Bahan baku untuk pabrik
yang dibutuhkan adalah batu kapur (CaCO3) 7,549 kg / jam dan larutan
asam sulfat (H2SO4) 6,898 kg / jam dengan reaksi umum seperti berikut:
CaCO3 (s) + H2SO4 (l) + H2O (l) CaSO4.2H2O (s) + CO2 (g) dan
perbandingan berat antara batu kapur dan asam sulfat yang masuk ke dalam
reaktor adalah 1: 1 dalam kilogram. Waktu tinggal di reaktor adalah 10 menit.
Pabrik akan dibangun pada 2030 di Indarung, Padang dengan luas 16.940
m2. Hasil perhitungan Biaya Tetap (Fa) adalah 41.797.168.267. Regulated Cos
(Ra) adalah 505.053.337.480 Biaya bahan baku (Sa) adalah
1.358.239.263.511.Variable cost (Va) adalah 629.447.458.716.mendapatkan nilai
BEP adalah 51,52% (pada kisaran 40% - 60%) dan mendapatkan nilai SDP adalah
51,52% untuk POT setelah pajak 1,8 tahun (maksimmum 5 tahun). kita
mendapatkan nilai Internal Rate of Return (IRR) = 19,35% Jadi jika pabrik ini
akan membangun begitu banyak keuntungan dan sangat menguntungkan
Kata kunci: Gypsum, kalsium sulfat dihidrat, CaSO4.2H2O
v
UNIVERSITAS MUHAMMADIYAH SURAKARTA
DEPARTMENT OF CHEMICAL ENGINEERING
FACULTY OF ENGINEERING
STATEMENT OF AUTHENTICITY
The undersigned below:
Name : LATEEFEE YANGOK
Nim : D500112001
Study Program : Chemical Engineering
Title of Final Project : Preliminary Plant design of Gypsum using Limestone
and sulfuric acid with capacity of 100,000 tons/year
State the fact that final project results that I make and submit this is the result of
my own work except for quotation and summaries that everything. I have
explained the sources. If the final project is plagiarism and other scientific or
research work, then I am ready to accept the sanction both academically and law.
Surakarta, 23 September 2017
Author
Lateefee Yangok
vi
MOTTO
“Successful indeed are the believers, those who offer their Salat (prayers) with all
solemnity and full submissiveness”
[Quran: surat Al-Muminoon, verses 1-2]
“Try not to become a man of success, but rather try to become a man of value”
vii
DEDICATION
I dedicate this work to:
My beloved mother and father. Thank you for your prayer, support, love, and
education you’ve given.
My beloved sister who always gives support, and advice.
My future Faeelah Deemae who always gives support, inspiration and spirit.
All of my friends are ready for help me.
All of my classmate in the International class 2011 who gave me comfort when
learning.
Thanks’ you for all
viii
FOREWORDS
Bismillahirrohmanirrohim
Assalamualaikum warrohmatullohi wabarokatuh
The final project would like to express his deep gratitude to Alloh SWT,
the most kind who has given guidance, healthy, and ability, so that the final
project could accomplish this final project paper on time.
However, this success would not be achieved either without the helping of
many individuals and institution. Thus, his special thanks and gratefulness are
contributed to:
1. Both Parent for always provide support in completing the final project
2. Faeelah Deemae for always gives support, inspiration and spirit.
3. Kusmiyati, S.T., M.T., Ph.D. as first supervisor of final project
4. Eni Budiyati, S.T., M. Eng as second supervisor of final project
5. Rois Fatoni, ST, MSc. PhD as head of Chemical Engineering
6. Everyone who has supported the author to carry out this work placement very
well.
Author wish this report to be beneficial to those my concern.
Wabillahittaufiq wal hidayah
Wassalamu’alaikum warrohmatullohi wabarokatuh
Surakarta, 23 September 2017
Lateefee Yangok
ix
CONTENT
TITLE ....................................................................................................................... i
APPROVAL ............................................................................................................. ii
ABSTRACT ............................................................................................................. iii
ABSTRAK ............................................................................................................... iv
STATEMENT OF AUTHENTICITY ...................................................................... v
MOTTO .................................................................................................................... vi
DEDICATION ......................................................................................................... vii
FOREWORDS ......................................................................................................... viii
CONTENT ............................................................................................................... ix
LIST OF TABLES..................................................................................................... xi
LIST OF FIGURES .................................................................................................. xiii
CHAPTER I INTRODUCTION .............................................................................. 1
1.1.Background of Plant Design .............................................................................. 1
1.2.Selection of Plant Capacity................................................................................. 2
1.3.Selection of Plant Location................................................................................. 6
1.4.The Process Selection.......................................................................................... 8
1.5. Theory Description ............................................................................................ 11
CHAPTER II PROCESS DESCRIPTION ............................................................... 14
2.1.Spesification of Material...................................................................................... 14
2.2.Proses Concept .................................................................................................... 16
2.3.Thermodynamics Overview................................................................................. 17
2.4.Kinetic Overview................................................................................................. 20
2.5.Step Process......................................................................................................... 21
2.6.Mass and Heat Balance........................................................................................ 27
2.7.Layout and Plant Equipment....................................................................... …… 35
CHAPTER III EQUIPMENT SPECIFICATIONS .................................................. 40
3.1. Main Equipment ……………………………………………………………. 40
3.2. Supporting Equipment ……………………………………………………… 45
CHAPTER IV UTILITY AND LABORATORY..................................................... 57
4.1.Utility.............................................................................. …................................ 57
4.2.Laboratory .......................................................................................................... 86
x
CHAPTER V PLANT MANAGEMENT ................................................................. 91
5.1.Type of Plant ....................................................................................................... 91
5.2. Organizational Structure .................................................................................... 92
5.3. Duties and Power................................................................................................ 95
5.4. Distribution of Work Time of Employee .......................................................... 101
5.5. Employee Status and Wage System................................................................... 103
5.6. Job Position, Ammount of Employees, and Salariess .................................... 104
5.7. Employee Social Welfare.................................................................................... 105
5.8. Occupational Safety and Health.......................................................................... 106
CHAPTER VI ECONOMIC ANALYSIS ............................................................... 108
6.1. Estimation of Equipment Cost............................................................................ 108
6.2. Base of Calculation............................................................................................. 110
6.3. Cost Calculatuion ............................................................................................... 110
6.4. Calculation Result............................................................................................... 113
6.5. Economic Analysis ............................................................................................. 124
REFERENCES
APPENDIX
xi
LIST OF TABLES
Table 1.1 The Import of Gypsum Demand in Indonesia……………………………… 3
Table 1.2 The Plant of Gypsum in Indonesia………………………………………... 5
Table 1.3 The Price of Raw Material and Product........................................................ 5
Table 1.4 Selection Process Based Technical and Economic ………………………… 9
Table 2.1 The Value of Molecular Weight and ΔHf each component……………..... 18
Table 2.2 Data of Gibbs Energy of Raw Materials and Products Components……… 19
Table 2.3.Total Mass Balance……………………………………………………….. 27
Table 2.4. Mass Balance In Mixer -01………………………………………………. 27
Table 2.5. Mass Balance In Mixer -02 ……………………………………………… 28
Table 2.6. Mass Balance In Reactor…………………………………………………. 28
Table 2.7. Mass Balance In Rotary Drum Filter…………………………………….. 29
Table 2.8. Mass Balance In Rotary Dryer…………………………………………… 29
Table 2.9. Mass Balance In Ball Mill ………………………………………………. 30
Table 2.10. Mass Balance In Vibrating Screen…………………………………….... 30
Table 2.11 Heat Balance In Mixer-01 ………………………………………………. 31
Table 2.12 .Heat Balance In Mixer-02……………………………………………… 31
Table 2.13.Heat Balance In Reactor………………………………………………… 32
Table 2.14.Heat Balance In Rotary Drum Filter …………………………………… 32
Table 2.15 Heat Balance In Rotary Dryer.................................................................. 33
Table 2.16 Heat Balance In Ball Mill ……………………………………………... 33
Table 2.17 Heat Balance In Vibrating Screen …………………………………… 34
Tabel 2.18 Large of Plant Building ........................................................................... 36
Table 4.1. Demand of Cooling Water ........................................................................ 75
Table 4.2. Demand of Steam ……………………………………………………….. 76
Table 4.3. Demand of Sanitation Water ……………………………………………. 77
Table 4.4. Demand of Electrical Power of Process ………………………………… 79
Table 4.5. Demand of Electrical Power of Process ………………………………… 80
Table 4.6. Demand of Electricital Power of Utility ………………………………… 80
Table 4.7. Demand of Electricital Power of Pump ………………………………… 81
Table 4.8. Total Demand of Electrical Power of Plant …………………………….. 83
Table 4.9. Anlysis Procedure of Process Unit. …………………………………….. 88
xii
Table 5.1. Schedule of Distribution Groups of Shift Employees ………………….. 102
Table 5.2. Clasification of Position, Qualification, Ammount and Salaries of
Employee ……………………………………………………………… 104
Table 6.1 Cost Index of Equipment …………………………………………….... 108
Table 6.2 Cost of Main Equipment ............................................................................ 114
Table 6. 3 Cost of Supporting Equipment.................................................................. 114
Table 6.4 Total Cost of Unit Process ……………………………………………… 115
Table 6.5 Fixed capital investment (FCI).................................................................. 116
Table 6.6 Working capital investment (WCI) ......................................................... 117
Table 6.7 Direct manufacturing cost (DMC).............................................................. 117
Table 6.8 Indirect manufacturing cost (IMC) ……………………………………… 118
Table 6.9 Fixed manufacturing cost (FMC)............................................................... 118
Table 6.10 General expense (GE) .............................................................................. 119
Table 6.11 Cost of Raw Material................................................................................ 119
Table 6.12 Salary of Employee …………………………………………………….. 119
Table 6.13. Cost of Product ....................................................................................... 121
Table 6.14. Cost of Utility and Waste Treatment Unit............................................... 121
Table 6.15 Economic Analysis and Limitation Value ……………………………… 126
xiii
LIST OF FIGURES
Graph 1.1. The Import Gypsum Demand in Indonesia ............................................... 4
Figure 1.2. Map of Indarung City ………………………………………………….. 7
Figure 2.1. Shrinking Spherical Particles …………………………………………… 20
Figure 2.2. Flow diagram qualitative ............................................................................. 24
Figure 2.2. Flow diagram quantitative............................................................................ 25
Figure 2.3. Process Flow Diagram of Gypsum Plant ……………………………… 26
Figure 2.4. Plant Layout................................................................................................ 37
Figure 2.5. Layout of Main Process ………………………………………………… 39
Figure 4.1. Unit of Water treatment ........................................................................... 64
Figure 5.1. Flow Diagram of Plant Management of Organization ………………… 94
Picture 6.1. Graph of Chemical Cost Index ……………………………………… 109
Figure 6.2 Economic Analysis ...................................................................................... 126