11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 8–1 Florida Department of TRANSPORTATION Final Estimates Level 2 Module 8‐ Final As‐Built Plans Module 8- Final As-Built Plans 8 - 1 Final Estimates Level 2 Final As-Built Plans are important to construction, maintenance, future designers, utilities and final estimates office. Refer to the CPAM 5.12 for more detailed information. For instance: 1. Maintenance will need final plans because they must maintain the project after construction, more importantly bridge structures are inspected periodically. 2. Designers may use final plans when designing future projects. 3. Utilities will need final plans to assist with future utility locations and installations. 4. Final Estimates needs the final plans to assist in accounting for final pay quantities. These plans must be updated as the project progresses. Don’t wait until the end of the project, people forget details. In this module, we will discuss what is expected from you with regards to the Final As-Built Plans. November 2017

Upload: lenhu

Post on 30-May-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–1

Florida Department of

TRANSPORTATION

Final Estimates Level 2Module 8‐ Final As‐Built Plans

Module 8- Final As-Built Plans

8 - 1

Final Estimates Level 2

Final As-Built Plans are important to construction, maintenance, future designers, utilities and final estimates office. Refer to the CPAM 5.12 for more detailed information.

For instance:

1. Maintenance will need final plans because they must maintain the project after construction, more importantly bridge structures are inspected periodically.

2. Designers may use final plans when designing future projects.

3. Utilities will need final plans to assist with future utility locations and installations.

4. Final Estimates needs the final plans to assist in accounting for final pay quantities.

These plans must be updated as the project progresses. Don’t wait until the end of the project, people forget details.

In this module, we will discuss what is expected from you with regards to the Final As-Built Plans.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–2

Module Content

• Final As‐Built Plans• Original Contract Plans• Revised Plan Sets• As‐Built Process

• Methods of Revision• Marking Conventions• Revise Entire Sheet• Revise a Portion of a Sheet

• Revisions to Major    Sheet Types:

• Key Sheet• Signature Sheet• Typical Sections• As‐Built Data Form• Summary Boxes• Plan Sheets• Drainage Summary Sheets• Drainage Structure Sheets• Optional Materials Tabulation• Cross Section Sheets• Bridge Plans• Revisions after PAR

Module 8- Final As-Built Plans

8 - 2

Final Estimates Level 2

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–3

What are Final “As‐Built” Plans?

• One complete set of digitally signed and sealed contract plans reflecting the “as‐built” conditions 

• 11”x17” sheets in PDF file format • All changes from the original contract plans shall be clearly delineated

•A part of the final estimate package submitted to the District Final Estimate Office (DFEO)

Module 8- Final As-Built Plans

8 - 3

Final Estimates Level 2

The Final Plans shall include all changes, both Design and Construction, with all shop drawings, including adequate sketches, dimensions and notes. The contents will vary but SHALL ALWAYS contain those sheets necessary to completely cover all work performed.

All additions, deletions and revisions shall be clearly delineated in red to reflect the “As-Built” conditions for the completed project.

The Resident Office (RO) should read their contract and contact the DFEO to determine how Final As-Built Plans should be submitted – EDMS, FTP Site, CD, Thumbdrive, Project Solve, Dropbox, etc.

Final As-Built Plans are the permanent historical record of the Construction project.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–4

Receiving Original Contract Plans

• Prior to construction, the Resident Office (RO) will save the original electronic Contract Plans in the Original Plans folder of the collaboration site.

• The Contract Plans will be extracted by component, if not received that way, and saved in the As‐Built Plans folder of the collaboration site.

• Any and all changes made to the contract will be electronically reflected on the extracted set of plans within the collaboration site.  This is the Final As‐Built Plans set.

Module 8- Final As-Built Plans

8 - 4

Final Estimates Level 2

Project Solve SharePoint (PSSP) has been chosen by the Department as the collaboration site for the Department and its stakeholders in order to conduct business in a paperless environment.

Each project will have its own site within PSSP and each user will require an account for access to the site.

See http://www.fdot.gov/construction/eConstruction/ProjectSolve.shtm for more information.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–5

Receiving Revised Plan Sets

• Prior to or during construction, revisions by the EOR may be necessary.

• The Resident Office (RO) will save the Revised Plan Set in the project files.

• Then, extract the Revised Plan Set and                                  Signature Sheet(s) for                                                               use with the Final                                                         As‐Built Plans.

• Revised sheets will be                               incorporated into the                                              Final As‐built Plans.

Module 8- Final As-Built Plans

8 - 5

Final Estimates Level 2

Revised Plans Sets include a Signature Sheet and the revised plan sheets. The revised plan sheets may consist of one or multiple plan sheets.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–6

“As‐built” Process

• Methods of Revision:

– Electronically mark‐up Final As‐Built Plans

– Revising MicrostationCADD Files

Module 8- Final As-Built Plans

8 - 6

Final Estimates Level 2

Electronically: A Resident Office makes changes electronically to show as-built conditions (i.e.. field changes such as extended sidewalk or curb and gutter using the cloud revision tool or redline revision.

If Revisions are performed other than cloud revision, such as completely manipulating the native CADD file, all changes will conform to the same procedures and requirements outlined in the CADD Manual, Chapters 2,4 & 5, and the PPM, Vol. 1, Chapter 19 & 20 and Vol. 2, Chapter 30. After the native CADD file has been revised to reflect “as-built” conditions then a PDF version shall be created for the Final As-Built Plan set.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–7

“As‐built” Process

• Marking Conventions– Resident Office

• Project Personnel ‐ Redline Revision• Quality Assurance ‐ Orange Revision

– District Office• Initial Reviewer – Blue Line Revision• Overviewer – Green Line Revision

Module 8- Final As-Built Plans

8 - 7

Final Estimates Level 2

All changes discussed in this module will be made in red by the Resident Office.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–8

When do you revise an entire plan sheet?

When:• EOR makes a needed correction• Contractor’s EOR makes approved changes (example: Cost Savings Initiative)

• Typically, an engineering analysis is required.

“As‐built” Process 

Module 8- Final As-Built Plans

8 - 8

Final Estimates Level 2

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–9

How do you revise an entire sheet?

• Place “VOID” in red across the original sheet• Place revised sheet behind original with the exception of Key Sheet. The revised Key Sheet will be placed before the original Key Sheet

• Never discard a plan sheet

“As‐built” Process 

It will be the Resident Engineer’s responsibility to digitally sign and seal all changes made in the field not requiring an engineering analysis.

For revisions not made by the EOR, the proper language of qualification is required on the Final As-Built Signature Sheet reflecting those changes. This language should note that, by signing the disclaimer, the responsible Engineer is only taking responsibility for the specific changes in the plans, not for the entire set of plans.

Module 8- Final As-Built Plans

8 - 9

Final Estimates Level 2

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–10

When do you revise a portion of a plan sheet?

• Field Change• Plan Error• Typically, an engineering analysis is NOT required.

“As‐built” Process 

Module 8- Final As-Built Plans

8 - 10

Final Estimates Level 2

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–11

“As‐built” Process 

How do you revise a portion of a plan sheet?

• Strikethrough through information changed

• Add new data• Cloud entire change• All changes will be made 

in red

Module 8- Final As-Built Plans

8 - 11

Final Estimates Level 2

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–12

“As‐built” Process 

• The Key Sheet    

should include:

– “Final As‐Built Plans” Title

– Name of all      responsible parties 

– Date Work Started and Final Acceptance

– Index of the Final Plans

– All revisions listed including sheet number, date and a brief description

Module 8- Final As-Built Plans

8 - 12

Final Estimates Level 2

Final As-Built Plans shall be prominently shown across the top of the sheet in place of or above the “Contract Plans” or “Plans of Proposed” preprinted line. The words “Plans of Proposed” shall be lined through or completely deleted.

On the right side and near the lower corner, the following information shall be on the key sheet:1. Name of contractor2. Name of Prime consultant(s) involved3. District Secretary, Resident Engineer & Project Manager4. Project Administrator5. Date work started6. Date work final accepted or completed

A complete Index of the Final Plans shall be shown on the left side of the Key Sheet.A complete list of permanent field books and a general description of their contents shall be shown.

(Note: It is recommended to use Form No. 700-050-61 - Final Measurement "Miscellaneous“ in lieu of field books as a cost savings to the Department.)

All revisions to the Final Plans during construction shall be added to the revision list on the left side of the sheet below the Index of Roadway Plan Sheets. This information shall be entered electronically on the Key Sheet All project descriptions, Financial Project ID Numbers, project lengths, etc. shown on the Key Sheet shall be revised to reflect the construction completion information before the Final As-Built Plans are submitted.Additional plans, such as shop drawings, required “as-built” drawings, etc. and permanent field books (if used) shall be shown in the Index of Final Plans on the Key Sheet of the first component of the Final As-Built Plans.

November 2017

Module 8- Final As-Built Plans

8 - 13

Final Estimates Level 2

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–14

“As‐built” Process

• Digital Signing, Sealing and Certifying– The Department requires National Institute of Standards & Technology (NIST) Assurance Level 3 or higher digital certificates

– EORs will digitally sign documents• Locks the document ‐ does not allow any changes 

– REs will digitally certify documents• Locks the document ‐ does not allow                                                                 any changes

• Will allow markups by the DFEO

Module 8- Final As-Built Plans

8 - 14

Final Estimates Level 2

The digital certificate contains a unique digital ID that can be validated for authenticity. FS 668.003(3) defines using a certificate as a digital signature. For more information on digital signatures: http://www.dot.state.fl.us/Construction/eConstruction/DigitalSignatures.shtm

FAC 61G15-23.004(1) indicates the affixing a digital signature shall constitute the sealing of engineering work as defined in FS 471.025 and FAC 61G15-23.004(2)(d)2 indicates the pictorial representation of the seal is not required.

The icons on the slide are the Bluebeam indicators for Digital Signature and Digital Certification.

The markups made by the DFEO are comparable to “post-it” notes on traditional paper As-built Plan sheets. The markups will not modify what the RE has digitally signed and sealed, just like “post-it” notes do not change traditional paper As-built Plan sheets. If changes affecting the integrity of the plans are necessary, the RO will update the Final As-Built Plans and re-certify the plans.

Contact your DFEO if you have any questions regarding the use of digital certificates.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–15

“As‐built” Process 

• Final As‐Built Signature Sheet – Statement of Disclaimer will be placed on the Final As‐Built Signature Sheet• If changes are made*• If NO changes are made**

– All changes to the Final As‐Built Plans will be listed

– Changes are digitally signed, sealed, and dated by the responsible Engineer with text required by FAC (Signature Appearance on next slide)

– The pictorial seal is not required.– Table will include names of each person to mark up or review the Final              As‐Built Plans

Module 8- Final As-Built Plans

8 - 15

Final Estimates Level 2

There are two scenarios to language of qualification

• "The above named professional engineer shall be responsible for the following changes, indicated in redline revision, in accordance with Rule 61G15-23.004, F.A.C. This project was constructed in substantial compliance with these plans as provided by the Engineer of Record.”

• "This project was constructed in substantial compliance with these plans as provided by the Engineer of Record. These plans reflect "as-built" conditions and no changes were made to the plan sheets.“

All additions, deletions, and revisions shall be clearly delineated to reflect the final “as built” conditions of the completed project.

November 2017

NO

TE

: The

pic

toria

l sea

l can

be

adde

d to

the

Fin

al A

s-B

uilt

Sig

natu

re S

heet

, per

the

Sta

tute

, if

pref

erre

d by

the

Res

iden

t E

ngin

eer.

Module 8- Final As-Built Plans

8 - 16

Final Estimates Level 2

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–17

“As‐built” Process

• Typical Sections– All Changes to the Typical Section(s) shall be noted on the plan sheets• Material usage/substitution including base option

• Change in pay items

• Alteration of Limits as denoted on the plans

• Additional/Deleted items of work

• Increase or decrease in thickness

Module 8- Final As-Built Plans

8 - 17

Final Estimates Level 2

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–18

• Typical Sections

“As‐built” Process

684 + 50

(2”)

Module 8- Final As-Built Plans

8 - 18

Final Estimates Level 2

November 2017

Roadway As-Built Pavement Data Form 700-050-12Module 8- Final As-Built Plans

8 - 19

Final Estimates Level 2

Historically, the purpose of the Roadway-As-Built Pavement Data, Form No. 700-050-12 was used to record main line pavement data as the pavement operation progresses. The objective was to provide a Pavement Design Engineer with sufficient information for future roadway development, design, maintenance, etc.

When the Asphalt Roadway-Daily Report of Quality Control was automated, the State Construction Office and State Pavement Design Office decided to utilize the more accurate and detailed data in the QCRR rather than continue to duplicate effort with the As-Built Data form. We are currently transitioning to a new source for our as-built data information.

Effective with DCE Memo 03-17, all projects let prior to July 2015, which use Form 675-030-20 are required to submit the as-built pavement data (excel spreadsheet) to: [email protected]. This form is not submitted as part of the Final As-Built Plans.

All other projects let July 2015 and forward, or projects currently using Form 675-030-20A, will submit Form 675-030-20A to the State Materials Office after final acceptance in lieu of form 700-050-12.

Refer to CPAM 5.12.7(4) for more details.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–20

“As‐built” Process

• Plan Summary Boxes

– Plan Summary Boxes are located within the Summary of Quantities Sheets and summarize all the quantities originally proposed and completed on the project.

– The Plan Summary Boxes must be revised to indicate the final quantities and any necessary revisions. 

– Revisions can include:• Plan errors and authorized field changes• Changes in stations, offset dimensions and elevations

• Changes in material (i.e. sizing, type)

• Deleted items

Module 8- Final As-Built Plans

8 - 20

Final Estimates Level 2

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–21

• Plan Summary Boxes

“As‐built” Process

21.824.5

46.346.3

Module 8- Final As-Built Plans

8 - 21

Final Estimates Level 2

Circles are added for emphasis in presentation and are not part of “as-built” markups.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–22

“As‐built” Process

• Plan Sheets– Plan sheets reflect plan view and can show profile– Revisions should strike through all incorrect data and show revisions with redlines for the following items:• Revisions to the horizontal and vertical alignments

• Added or Revised Stations or equations • Drainage structure adjustments

• Sidewalk and Curb and Gutter modifications

• Updated driveway data• Adjusted ditch locations and grades

– Revisions on Plan sheets should only be done by the responsible Engineer and not the Final Estimates staff

Module 8- Final As-Built Plans

8 - 22

Final Estimates Level 2

Other revisions to note:

• Intersection & crossover details that have been modified or relocated.

• Sign locations that were changed and pavement markings that were modified.

• All signal details that change during Construction.

• All Bridge, Approach Slab and Lighting details that differ from the actual Construction.

• Bench Mark descriptions for BM’s that were set during Construction shall be added to the profile portion of the plan sheets.

• All utility relocates and or conflicts shall be reflected on the utility adjustment sheets.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–23

“As‐built” Process

• Plan Sheet

32" PIPE

Module 8- Final As-Built Plans

8 - 23

Final Estimates Level 2

Plan sheet revisions need to be clouded for emphasis of the areas which have been revised.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–24

“As‐built” Process

• Drainage Summary Sheets

– List all revisions including:• Material, Size, Length, Flow Line, Station or Offset

– Differentiate between ‘field changes’ and ‘plan errors’

– Add final quantities, notes and references

Module 8- Final As-Built Plans

8 - 24

Final Estimates Level 2

Some other example revisions are:

• Changes in elevations

• Deleted structures

• Changes of inlet and manhole types constructed shall be indicated

When the method of measurement is on the basis of plan quantity for cross drain and storm sewer pipes, plan errors shall be distinguished from field revisions due to different tolerances being applicable.

Lateral Ditch Sheets: All adjustments in horizontal alignment of flow line grade shall be delineated on the plan and profile sheets. The cross section shall be adjusted to reflect the revisions if a pay quantity adjustment is required.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–25

“As‐built” Process

90

75

• Drainage Summary Sheet

Module 8- Final As-Built Plans

8 - 25

Final Estimates Level 2

Circles are added for emphasis in presentation and are not part of “as-built” markups.

November 2017

Mat

’l&

Thi

ckne

ss16

GA

CA

P

Drainage Structure Shee

tsModule 8- Final As-Built Plans

8 - 26

Final Estimates Level 2

Exa

mpl

e of

a D

rain

age

Str

uctu

re S

heet

sho

win

g pi

pe m

ater

ial a

nd th

ickn

ess.

Type

of p

ipe

mat

eria

l and

thic

knes

s us

ed a

t eac

h st

ruct

ure

shal

l be

show

n on

the

Dra

inag

e S

tru

ctu

res

Sh

eets

November 2017

x x

Optional M

aterials Tab

ulation

Module 8- Final As-Built Plans

8 - 27

Final Estimates Level 2

Pla

n S

umm

ary

Box

Exa

mpl

e.T

he “

As-

Bui

lt” c

olum

n w

ill b

e ch

ecke

d to

indi

cate

wha

t typ

e of

pip

e m

ater

ial a

nd th

ickn

ess

was

use

d at

eac

h st

ruct

ure.

T

he c

ircle

s ha

ve b

een

adde

d em

phas

is in

the

pres

enta

tion

and

are

not a

par

t of t

he “

as-b

uilt”

mar

kups

.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–28

“As‐built” Process

• Cross Section Sheets– Earthwork plots should include all revisions– Any additional cross sections performed should be included within the sheets

Module 8- Final As-Built Plans

8 - 28

Final Estimates Level 2

Plots from Multiline or other approved methods or software shall be included with the Final Estimates Package.

Many earthwork pay items are plan quantity. Subsoil is an example of an earthwork pay item that is final measure. Final cross section sheets and volumetric calculations are to be prepared and submitted with the Final As-Built Plans for final measure items. These records are required to reflect the actual work accomplished and are the basis of final pay quantities.

Form 700-050-35 Earthwork Survey/Cross Section Waiver is submitted prior to construction and will determine when cross sections are required.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–29

“As‐built” Process

• Bridge Plans should include:– Electronic "As‐Builts"– Load ratings– Drill shaft inspection records– Pile Driving Records– Document all crack observations– Indicate ALL changes– Request for Correction (RFC)– Cost Saving Initiative Proposal (CSIP) plans

Module 8- Final As-Built Plans

8 - 29

Final Estimates Level 2

The Structures and Facility Engineers need to have accurate bridge records available for inspection, maintenance, rehabilitation, emergency repair operations and future widening operations.

The following information shall be recorded on the proper matrix, plan sheets, log books and forms. Load ratings based on as-built conditions shall be recorded on the appropriate forms and submitted with the Final As-Built Plans.:

- Drill shaft inspection records shall be scanned into EDMS

- Pile Driving Log Books / Pile Driving Records shall be recorded appropriately, marked as permanent record and scanned into EDMS.

- Consultant Contracts will be expanded to require “As-Built” bridge plans (category II) be prepared electronically during the Construction process.

- All crack observations on the structures shall be documented through detailed sketches or “Crack Maps”. It is the responsibility of CEI inspector to perform the inspection.

- Engineer approved repairs due to Request for Corrections (RFC) not included in the "as-built" plans.

Cost Saving Initiative Proposals (CSIP) will be signed, sealed and dated by the responsible Engineer.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–30

“As‐built” Process

• After submittal of the final estimates package, it is the RO responsibility to make any changes required due to findings by the DFEO during the PAR.

Module 8- Final As-Built Plans

8 - 30

Final Estimates Level 2

CPAM 5.12.8 provides more information.

Post Audit Reviews will be discussed in Module 9 of this course.

November 2017

11/1/2017 FDOT Final Estimates Level 2 Release 11,  Module 8–31

Florida Department of

TRANSPORTATION

ANY QUESTIONS?

Remember the Procedures for Final As-Built Plans Process are in CPAM 5.12.

Module 8- Final As-Built Plans

8 - 31

Final Estimates Level 2

November 2017