final detailed design report - musita _ majanji road

121
GOVERNMENT OF UGANDA UGANDA NATIONAL ROADS AUTHORITY CONSULTANCY SERVICES FOR FEASIBILITY STUDY, DETAILED ENGINEERING DESIGN, TENDER ASSISTANCE AND PROJECT MANAGEMENT FOR UPGRADING OF ROADS TO BITUMINOUS STANDARDS LOT E FINAL DETAILED DESIGN REPORT PKG 1 ROAD E1.1/E1.2 MUSITA-LUMINO/BUSIA-MAJANJI AUGUST 2012 IN ASSOCIATION WITH

Upload: soleb

Post on 14-Dec-2015

134 views

Category:

Documents


26 download

DESCRIPTION

HIGHWAY DESIGN REPORT

TRANSCRIPT

Page 1: Final Detailed Design Report - Musita _ Majanji Road

GOVERNMENT OF UGANDA UGANDA NATIONAL ROADS AUTHORITY

CONSULTANCY SERVICES FOR FEASIBILITY STUDY, DETAILED ENGINEERING DESIGN, TENDER ASSISTANCE

AND PROJECT MANAGEMENT FOR

UPGRADING OF ROADS TO BITUMINOUS STANDARDS LOT E

FINAL DETAILED DESIGN REPORT

PKG 1 ROAD E1.1/E1.2

MUSITA-LUMINO/BUSIA-MAJANJI

AUGUST 2012

IN ASSOCIATION WITH

Page 2: Final Detailed Design Report - Musita _ Majanji Road

Project Name:

Feasibility Study, Detailed Design, Tender Assistance and Project Management for Upgrading of Roads to Bituminous Standards

Project Number:

5116004

Report for:

FINAL DETAILED DESIGN REPORT

PREPARATION, REVIEW AND AUTHORISATION

Revision # Date Prepared by Reviewed by Approved for Issue by

1

31 Aug 2012

Nuruddin Wajihi/Michael Ogola/Edward Byaruhanga

Various

Nuruddin Wajihi

ISSUE REGISTER

Distribution List Date Issued Number of Copies

Client: UNRA

31-08-2012

5

SMEC staff: Project Manager

31-08-2012

1

Associates: NEWPLAN

Office Library (SMEC office location):

SMEC Project File: Kampala 31-08-2012

1

SMEC COMPANY DETAILS

SMEC INTERNATIONAL PTY LIMITED

Kipro Centre. 3rd Floor, Sports Road, Westlands, Nairobi

Tel: +254 20 4441541/2

Fax: +254 20 441543

Email: [email protected]

www.smec.com

The information within this document is and shall remain the property of SMEC INTERNATIONAL PTY LTD.

Page 3: Final Detailed Design Report - Musita _ Majanji Road

Detailed Design Report (FINAL)

for

FEASIBILITY STUDY, DETAILED ENGINEERING DESIGN, TENDER ASSISTANCE AND PROJECT MANAGEMENT FOR UPGRADING ROADS TO BITUMINOUS STANDARDS – LOT E

PACKAGE 1 : ROAD E1.1/E1.2

MUSITA-LUMINO/BUSIA-MAJANJI ROAD

For: UGANDA NATIONAL ROADS AUTHORITY AUGUST 2012

| FINAL Detailed Design Report_Rev.1-AUG.2012 |

Page 4: Final Detailed Design Report - Musita _ Majanji Road

KUMI

BUKUNGU

PACKAGE – 2A TIRINYI-PALLISA/

PALLISA-KUMI

PACKAGE – 4 NAMAGUMBA-BUDADIRI- NALUGUGU

NALUGUGU

PACKAGE – 5 KAMULI - BUKUNGU

PALLISA

PACKAGE– 2B

PALLISA-KAMONKOLI

BUDADIRI

NAMAGUMBA

TIRINYI

KAMONKOLI BUMBOBI

KAMULI PACKAGE – 3

BUMBOBI-BUBULO- LWAKHAKHA

BUBULO

LWAKHAKHA

MUSITA BUSIA

PACKAGE – 1 MUSITA-LUMINO/ BUSIA-MAJANJI

LUMINO

MAJANJI

LOCATION OF LOT E ROADS

Page 5: Final Detailed Design Report - Musita _ Majanji Road

i

TABLE OF CONTENTS

EXECUTIVE SUMMARY ES-1

E1. Introduction

E2. Economic Evaluation

E3. Topographical Survey

E4. Traffic Surveys

E5. Traffic Growth and Projected Traffic

E6. Axle Load Survey

E7. Pavement Design

E8. Materials Investigation

E9. Hydrology

E10. Drainage Design

E11. Geometric Design

ES-1

ES-2

ES-2

ES-3

ES-3

ES-4

ES-5

ES-6

ES-7

ES-10

ES-12

1 INTRODUCTION 1 1.1 Background 1 1.2 Contract Details 2 1.3 Terms of Reference 2 1.4 Preliminary Design Report 3 1.5 Packaging of the Project Roads 3 1.6 This Report 3

2 ENGINEERING STUDIES 4 2.1 Project Location

2.1.1 Description of Project Road 4

4 2.1.2 Topography 7 2.1.3 Geology 8 2.1.4 Soils

2.2 Topographical and Aerial Survey

2.2.1 General

8

8

8 2.2.2 References and Datum 8 2.2.3 Ground Control And GPS Measurements 10 2.2.4 Interim Beacons And Total Station Measurements 10 2.2.5 Aerial Survey 10 2.2.6 Final Products

2.3 Traffic Surveys

2.3.1 Terms of Reference

11

11

11 2.3.2 Existing Traffic 12

Page 6: Final Detailed Design Report - Musita _ Majanji Road

ii

2.3.3 Traffic Counts 12 2.3.4 Base Traffic 13 2.3.5 Traffic Growth 15 2.3.6 Growth in normal traffic 15 2.3.7 Diverted Traffic 15 2.3.8 Generated traffic 15 2.3.9 Projected Traffic growth 15 2.3.10 Origin/Destination Surveys 16 2.3.11 Axle Load Survey 22 2.3.12 Overloading 23 2.3.13 Cumulative Equivalent Standard Axles (CESA) 24 2.3.14 Summarized Road Usage 25 2.3.15 Sensitivity Analysis 26

2.4 Soils and Materials Investigations 27

2.4.1

General

27 2.4.2 Sub-grade Soil Investigation 27 2.4.3 Gravel and Hardstone Sources 27 2.4.4 Laboratory Testing 28

2.5 Hydrological Studies 29

2.5.1 Objectives 29 2.5.2 General Objective 29 2.53 Specific Objectives 29 2.5.4 Background 29 2.5.5 Hydrological Analysis – Criteria and Practices 30 2.5.6 Hydrological Analysis – Methodology 30 2.5.7 Data Collection 31 2.5.8 Topography, Catchment Area Delineation and Watershed Parameters 31 2.5.8 Watershed Characteristics 32

2.6 Swamp Investigations 36 2.7 Drainage Investigations 36

2.7.1 Assessment of Existing Drainage Structures 36 2.7.2 Classification of Drainage Structures 36 2.7.3 Side Ditches 37 2.7.4 Pipe Culverts 37 2.7.5 Box Culverts 37 2.7.6 Bridges 37 2.7.7 Existing Bridges 38

Page 7: Final Detailed Design Report - Musita _ Majanji Road

iii

2.7.8 Summary 38

2.8 Environmental and Social Studies 38

2.8.1 General 38

2.8.2 Geographical Location 38

2.8.3 Biophysical Environment 39

2.8.4 Socio-economic and Cultural Environment 39

2.8.5 Predicted Environment and Social Impacts 40 3 DETAILED DESIGN 43

3.1 Geometric Design 43

3.1.1 Introduction 43

3.1.2 Design Standards 43

3.1.3 Design Speed 45

3.1.4 Design Departures 47

3.1.5 Cross-Section 48

3.1.6 Embankment Design 48

3.1.7 Adopted Design Parameters and Standards 49

3.1.7 Summary of Adopted Design Speeds 50

3.1.8 Design Road Alignment 50

3.1.9 Alignment Details 51

3.1.10 Low Lying Area 54

3.1.11 Junctions and Accesses 56

3.1.12 Footpaths, Busbays and Road Furniture 57

3.1.13 Service Roads 57

3.1.14 Climbing Lanes 58

3.2 Pavement Design 61

3.2.1 Introduction 61 3.2.2 Design Period 61 3.2.3 Pavement Design Input Data 62 3.2.3 Subgrade 62 3.2.4 Soft spots and Marshy areas 63 3.2.5 Pavement Materials 63 3.2.6 Pavement Design Catalogue 63 3.2.7 Pavement Structural Design 63 3.2.8 Design Traffic Loading 64 3.2.9 Design Subgrade CBR 64 3.2.10 Design Subgrade Class 66 3.2.11 Proposed Pavement Structure 66

Page 8: Final Detailed Design Report - Musita _ Majanji Road

iv

3.3 Drainage Design 67

3.3.1 Design Return Period 67

3.3.2 Frequency Distribution Models 67

3.3.3 Design Flood Estimation 70

3.3.4 Runoff Models 70

3.3.5 Frequency analysis 70

3.3.6 The TRRL East African Flood Model 71

3.1.8 Design Discharges 79

3.4 Structure Selection 80

3.4.1 Design Philosophy 80

3.4.2 Bridges 81

3.4.3 Slab/Box Culverts 84

3.4.4 Pipe Culverts 85

3.4.5 Paved Side Ditches 87

3.5 Hydraulic Design 87

3.5.1 Minor Drainage Structures 87

3.5.2 Major Drainage Structures 88

3.6 Structural Design 90

3.6.1 Minor Drainage Structures 90

3.6.2 Major Drainage Structures 90

3.7 Quantity and Cost Estimation 97

3.7.1 Determination of Quantities 97 3.7.2 Unit Rates 97 3.7.3 Provisions 97 3.7.4 Construction Cost Estimates 98 3.7.5 Road Construction Packages 98

APPENDICES

Appendix 1 – Terms of Reference (Detailed Design)

Appendix 2A – Survey Location Map Appendix 2B – Daily Count Results Appendix 2C – Estimated AADT Appendix 2D – Derivation of Growth Rates Appendix 2E – Traffic Forecast Appendix 2F – O/D Survey Results Appendix 2G – Sensitivity Analysis Results

Appendix 3 – Summaries of Test Results

Appendix 4 – Delineated Catchments

Page 9: Final Detailed Design Report - Musita _ Majanji Road

v

Appendix 5A – Drainage Inventory Appendix 5B – Photographic Inventory Appendix 5C - Design Flows and Proposed Structures

Appendix 6 - Structural Design Calculations

Appendix 7 - Geometric Alignment Data

Page 10: Final Detailed Design Report - Musita _ Majanji Road

ES-1 | FINAL Detailed Design Report_ Rev.1-AUG 2012 |

EXECUTIVE SUMMARY

E1. Introduction

The Uganda National Roads Authority (UNRA) became a legal entity in 2006 and began operations in July 2008 with the following objectives at local level:

1. To improve access to goods/passenger transport services and to reduce transport costs along the route;

2. To improve access to social and economic development opportunities along the route by providing high capacity infrastructure;

3. To ensure no roadside communities become worse off as a result of the road upgrading works

In pursuance of the above objectives, UNRA has embarked on upgrading selected roads in several districts of Uganda. To this end, in September 2009, UNRA commissioned SMEC International Pty in association with NEWPLAN Ltd. of Uganda to provide consultancy services for the upgrading of several roads, referred to as Lot E, in the Eastern districts and comprising the following roads,

Road Reference

No.

Road Name(s)

E1 Musita-Lumino and Busia-Majanji roads (104 Km) E2 Tirinyi-Pallisa-Kumi and Pallisa-Mbale roads (114 Km) E3 Mbale-Bubulo-Lwakhakha road (41 Km) E4 Namagumba-Budadiri-Nalugugu road (29 Km) E5 Kamuli-Bukungu road (64 Km)

with the following Terms of Reference:

(i) Feasibility Study, including consideration of alternative routes and pavement options,

environmental and social impact study, road safety, land acquisition, preliminary design, economic and financial analysis;

(ii) Detailed engineering design for the approved road option; including all necessary data collection, field surveys and analysis to cover all aspects of detailed design;

(iii) Environmental and Social Impact Assessment (EIA) in accordance with Ugandan legislation and NEMA guidelines;

(iv) Preparation of a full Resettlement Action Plan and associated surveys to identify and value property that will be affected by the road upgrading works and the establishment of the road reserve;

(v) Preparation of bidding documents based on the approved detailed designs.

The Feasibility Study and the Preliminary Designs of the five project roads were undertaken between January 2010 and January 2011 and the Preliminary Reports submitted to UNRA variously between October 2010 and January 2011.

Page 11: Final Detailed Design Report - Musita _ Majanji Road

ES-2 | FINAL Detailed Design Report_ Rev.1-AUG 2012 |

Following consultations with UNRA, the five roads were divided into six (6) packages as follows:

Package 1 : Road E1 : Musita-Lumino/Busia-Majanji roads

Package 2A : Road E2.1/E2.2 : Tirinyi-Pallisa/Pallisa-Kumi road

Package 2B : Road E2.3 : Pallisa-Kamonkoli road

Package 3 : Road E3 : Bumbobi-Busumbu-Lwakhakha

Package 4 : Road E4 : Namagumba-Budadiri-Nalugugu

Package 5 : Road E5 : Kamuli-Bukungu road

This Detailed Design report refers to Package 1: Road E1: Musita-Lumino/Busia-Majanji roads.

The Project road starts from Musita trading center along the Jinja-Iganga highway passing through Mayuge, Nankona, Buyinja and ends at Lumino trading center, another link starts from Busia town through Lumino ending at Majanji. It acts as a shortcut from Busia town to Jinja and also serves as a link to a number of landing sites along Lake Victoria including Majanji, Lufudu, Omenya, Wakawaka and Kigandala.

E2. Economic Evaluation

The economic evaluation of Road E1 indicated the upgrading of these roads to bitumen standards to be economically viable with the following Economic Internal Rates of Return:

Table 1: Results of the Economic Evaluation (Net Present Value-NPV)

SN Road name/Road section Type of

HDM 4 analysis

NPV

E1 Musita-Lumino/Busia/Majanji Project 50.682 ●1.1-Musita-Lumino Section 28.764 ●1.2-Busia-Majanji Section 21.918

Table 2: Results of the Economic Evaluation (Internal Rate of Return)

SN Road name/Road section Type of HDM 4 analysis

EIRR (%)

E1 Musita-Lumino/Busia/Majanji Project 19.6 ●1.1-Musita-Lumino Section 18.0 ●1.2-Busia-Majanji Section 24.0

E3. Topographical Survey

Aerial photography supplemented by ground control was carried out during the preliminary design stage and formed the basis of the preliminary and detailed alignment designs.

Page 12: Final Detailed Design Report - Musita _ Majanji Road

ES-3 | FINAL Detailed Design Report_ Rev.1-AUG 2012 |

AA

DT

E4. Traffic Surveys

Manual classified counts were carried at seven stations along the route for seven days, from 25th to 31st March 2010. Night counts were carried for one weekday and one weekend day at each station. The average annual daily traffic (AADT) in the current year (2010) is indicated in the chart below, with vehicular traffic ranging from 154 to 557 vehicles/day.

2500

2000

1500

1000

564

2090

946

829

1430

557

1046

500

0

154

337 272 200

246

5km after Lumino

5km before Busia

5km before Namayingo

5km from Mayuge

5km from Musita

5km before Lumino

Sation name

AADT (with Motorcycles) AADT (without motorcycles)

The proportion of motorcycles to the other traffic is high as seen from the chart above.

Origin/Destination (OD) survey was conducted during the month of April 2010 using enumerators hired and trained from along the project road. Information gathered through road side interviews of vehicle drivers was analyzed to understand the origin-destination characteristics of traffic plying the project roads. Since these interviews were conducted on a sample of vehicles, the collected information was expanded to reflect the total volume of traffic plying on the road on that particular day. The results are discussed fully in the main text.

E5. Traffic Growth and Projected Traffic

Deriving traffic growth from traffic data involves analysis of the growth of the various traffic classes over a long period of say 10-20 years. This growth will give a trend in the growth of traffic over the years. This trend is then used to project the traffic growth in the project period. It was noted that analysis of historical data was not feasible as there was no adequate historical data.

Traffic growth factors were derived using traffic proxies such as fuel consumption, vehicle registration trends, GDP growth etc. No data on historical traffic growth was available for this road.

It was assumed that road construction shall commence in the year 2011 and end in 2015. Projections were made for a design period of 15 years and 20 years. Therefore projections were made up to the year 2030 and 2035 using the corresponding growth factors.

The following tables gives the forecast growth rates for the varios classes of vehicles for three scenarios, namely pessimistic (low), realistic (medium) and optimistic (high).

Page 13: Final Detailed Design Report - Musita _ Majanji Road

ES-4 | FINAL Detailed Design Report_ Rev.1-AUG 2012 |

Vehicle class

Pessimistic normal traffic growth (%) 2010-2013

2014-2018

2019-2023

2024 and beyond

Cars 4.7 5.7 3.7 2.4 Pick up and vans (Petrol) 4.7 5.7 3.7 2.4 Pick up and vans (Diesel) 4.7 6.8 4.4 2.9 Minibuses (Petrol) 4.7 5.7 3.4 2.4 Minibuses (Diesel) 4.7 6.8 4.4 2.9 Buses & Trucks 4.7 6.8 4.4 2.9

Vehicle class

Realistic normal traffic growth (%)

2010-2013

2014-2018

2019-2023 2024 and

beyond Cars 4.7 7.2 4.7 3.2 Pick up and vans (Petrol) 4.7 7.2 4.7 3.2 Pick up and vans (Diesel) 4.7 8.5 5.6 3.8 Minibuses (Petrol) 4.7 7.2 4.7 3.2 Minibuses (Diesel) 4.7 8.5 5.6 3.8 Buses & Trucks 4.7 8.5 5.6 3.8

Vehicle class Optimistic normal traffic growth (%)

2010-2013 2014-2018 2019-2023 2024 and beyond Cars 4.7 8.6 5.7 3.9 Pick up and vans (Petrol) 4.7 8.6 5.7 3.9 Pick up and vans (Diesel) 4.7 10 6.8 4.6 Minibuses (Petrol) 4.7 8.6 5.7 3.9 Minibuses (Diesel) 4.7 10 6.8 4.6 Buses & Trucks 4.7 10 6.8 4.6

E6. Axle Load Survey

A three day traffic axle load survey and counts was carried at Nabigingo along the project road between 6th May and 22nd May 2010.

Weighing was done for both directions simultaneously using a portable weighbridge to Transport Research Laboratories (TRRL) specifications.

The vehicles weighed were:

- Medium Buses - Large Buses - Light Goods Vehicles - Medium Goods Vehicles - Heavy Goods Vehicles - Very Heavy Goods Vehicles

The tables below shows the summary of axle load equivalence factor for each class of the heavy vehicles.

Page 14: Final Detailed Design Report - Musita _ Majanji Road

ES-5 | FINAL Detailed Design Report_ Rev.1-AUG 2012 |

Vehicle category

Average

gross weight

Average equivalence

factor (80KN)

MB 1.2 4.77 0.01 LB 1.2 14.68 1.69 LGV (1.2) 4.26 0.07 MGV(1.2) 4.10 0.00 HGV 1.2 5.38 0.11 VHGV 1.2 18.65 9.61

E7. Pavement Design

The pavement design of the project roads is based on the Ministry of Works, Housing and Communications Road Design Manual Vol. 3: Pavement Design, Part I: Flexible Pavements (July 2005).

The economical analysis of the project roads is based on a 20 year analysis period. Hence a 20 year pavement design period has been adopted.

Projected traffic loading for low, medium and hight growth scenarios are:

Estimated traffic growth rate (low) = 8.7x106

Estimated traffic growth rate (medium) = 8.99x106

Estimated traffic growth rate (high) = 9.37x106

Estimated traffic growth rate (medium) = 8.99x106 is adopted for the design of the pavement structure

Traffic class obtained is: T6

Subgrade Class: Analysis of soaked CBR test results for the road alignment subgrade soil is presented in summary form as shown below.

Musita - Lumino

Road Chainage Road

Length

(Km)

90th percentile

value

Design

CBR (%)

Subgrade Class From To

Musita-Lumino 0+000- 74+000 74.0 6 6 S3 Busia-Majanji 0+000-26+000 26.0 6 6 S3

Following the submission of the Preliminary Design Report, UNRA instructed the Consultant to adopt Chart W2 of the Design Manual for the selection of the pavement structure.

Page 15: Final Detailed Design Report - Musita _ Majanji Road

ES-6 | FINAL Detailed Design Report_ Rev.1-AUG 2012 |

On the basis of the projected traffic loading, the following pavement structure has been recommended:

Pavement layer Type of material Layer

thickness

SURFACING AC(Asphalt Concrete) 50 mm BASE COURSE GB(Granular Base) 150 mm SUBBASE CSB(Cemented Subbase) 175 mm IMPROVED SUBGRADE G15 (Natural Gravel CBR >15%) 125 mm

AC – Asphalt Concrete GB – Granular Base (Graded Crushed Stone) CSB – Cement Stabilized Base (Gravel) G15 – Gravel Class 15 (min.CBR=15)

E8. Materials Investigation

The preliminary materials investigations were conducted in accordance with the Terms of Reference. It consisted of site reconnaissance, field exploration and analysis of the findings of the field exploration.

The sub-grade soil investigation along the existing road alignment comprised sub-grade soil sampling by means of trail pits, DCP testing and laboratory testing.

Sub-grade Soil Investigation

Trial pits were excavated at two (2) kilometre interval on alternate side of the carriageway to depths of generally 1 m.

Trial Pits

The pits were dug to varying depths from the surface to sub-grade level with a total of 34 pits dug over the total road length of the project road 68 km.

The vertical profile of the pavement in each trial pit was recorded and representative sub-grade sample taken for laboratory testing.

DCP tests were conducted at intervals of 500m as stipulated in the ToR to measure the in-situ bearing strength (CBR) of the sub-grade.

DCP Investigations

To avoid weak spots (thin layers) from being overlooked and to identify layer boundaries fairly accurately, readings were taken at 1-5 blow intervals, depending on the rate of penetration.

Gravel and Hardstone Sources

- Assessment of the suitability and extent of the material source.

- Excavation of trial pits.

- Logging of the layers encountered.

- Retrieval of samples for laboratory testing.

- Backfilling of the trial pits.

Page 16: Final Detailed Design Report - Musita _ Majanji Road

ES-7 | FINAL Detailed Design Report_ Rev.1-AUG 2012 |

At each site, trial pits were excavated and depths of overburden and gravel were logged. In some instances, material was sampled from rock outcrops, talus, or existing quarries, in which cases, test pit excavation was not required. The volumes of both overburden and gravel were also estimated.

Gravel and Hardstone Sources

A total of 20 existing and potential gravel sources and 3 rock sources were identified and investigated along the five project roads as listed below:

As a requirement under the Contract, the Consultant fabricated a mobile laboratory in a 40-foot container at its offices in Kampala. Upon completion of fabrication and fitting out the laboratory

Laboratory Testing

was transported and erected at the compound of UNRA’s regional offices in Jinja. Gravel Samples

Samples of sub-grade material recovered from trial pits and samples from the gravel sources were transported to the mobile laboratory in Jinja where they were subjected to the following tests:

- Natural moisture content determination

- Particle size analysis

- Atterberg limits

- Moisture content – Dry density relationship (BS 1377 test method)

- CBR (4-day soak compacted at 90%, 95% and 98% MDD)

- Swell tests Rock Samples

To confirm the test results obtained on surface samples, during the detailed design stage the existing operational quarry along Musita-Lumino road was drilled at one location down to 15 m. Samples of cores were taken to the Ministry of Works’ central testing laboratory at Kireka where they were tested for:

- Specific Gravity

- Ten Percent Fines Value (TFV) - dry

- Ten Percent Fines Value (TFV) – wet

- Water adsorption

- Sodium Sulphate Soundness

- Bitumen Affinity

The investigations and the test results indicate that there is sufficient gravel and rock meeting the specifications available for the designed pavement structure.

E9. Hydrology

The objectives of the services as per the terms of reference (TOR) issued to the Consultants are:

Page 17: Final Detailed Design Report - Musita _ Majanji Road

ES-8 | FINAL Detailed Design Report_ Rev.1-AUG 2012 |

� To undertake hydrological and hydraulic assessment for the project roads under Lot E � To prepare Hydrological Reports as per the Terms of Reference

Specific Objectives are:

� Collect and compile hydrological data for the project roads � Carry out hydrological analysis for various drainage basins and channels traversed by the

road, � Computation of design discharges for the existing and proposed drainage structures along

the roads � Preparation of hydrological report for the project

The Road Drainage Design Manual (2005) guidelines require a designer to develop a clear understanding of the existing drainage conditions for a given assignment before determining the capacity of the existing cross and lateral drainage structures.

Minor drainage structures e.g. side ditches are to be designed to carry a 10-year flood while major ones must be evaluated for the 25-100 year storm. The RDDM (Table 3.2) suggests suitable return periods for various structural categories. Whenever possible, it is required that adequate openings are provided to limit backwater effects and excessive bed scour.

The TRRL East African Model has been widely applied and found to be more relevant in East Africa since a number of small catchments were extensively studied prior to establishing the required parameters for its application.

The watersheds draining to project road have distinct characteristics largely due to their geographical location, climate and land use characteristics. The relatively common aspect is that the watersheds are intensively cultivated, human settled and predominantly rolling.

The Musita-Lumino/Busia-Majanji roads are characterized by:

� Natural vegetation similar to tropical forest/ grassland. � Low-lying areas � Tropical climate with rainfall having two seasons i.e. from March to June and from

September to November (Bimodal) � Agriculture (sugar canes, maize, cassava, sweet potatoes, millet and sorghum), Cattle

rearing and mining like gold, uranium, iron core, lake sand and oil.

Design Discharges

The tables below gives the design discharges of the project road under the project for the different return periods.

Page 18: Final Detailed Design Report - Musita _ Majanji Road

ES-9 | FINAL Detailed Design Report_ Rev.1-AUG 2012 |

Summary of design floods for different return period Road E1.1- Musita-Lumino

Catch. Ref.

Chainage from Musita

Northing

Easting

Catch. area

(km2)

Design flood discharge (m3/s)

10-yr 25-yr 50-yr 100-yr 283 5+060 546926 55901 1.34 6.28 7.02 7.69 8.75 284 5+440 547329 55567 1.18 5.56 6.22 6.80 7.74 286 7+276 548534 54543 8.62 40.47 45.27 49.56 56.36 287 11+250 551778 51971 0.74 3.66 4.09 4.48 5.09 289 11+660 554420 50807 1.24 3.83 4.28 4.69 5.33 290 15+870 556063 50594 4.78 14.72 16.46 18.02 20.50 292 16+833 558983 50334 1.54 7.86 8.79 9.62 10.94 293 18+800 559865 50573 0.42 1.28 1.44 1.57 1.79 294 19+700 561223 50599 0.21 0.64 0.72 0.78 0.89 295 21+100 562439 50433 0.40 1.24 1.39 1.52 1.73 296 24+000 564029 50880 2.03 6.26 7.00 7.66 8.72 297 25+810 565785 50809 0.29 0.88 0.99 1.08 1.23 298 28+640 568503 50122 0.73 2.24 2.50 2.74 3.11 299 29+465 569306 50281 1.18 5.53 6.18 6.77 7.69 300 30+910 570662 50663 0.71 2.17 2.43 2.66 3.03

31+970 571704 50447 0.44 1.29 1.46 1.59 1.99 301

34+360 574025 50099 14.32 44.12 49.35 54.03 61.44 574151 50076

302 37+960 577490 50202 3.75 11.56 12.93 14.16 16.10 303-306 40+240 579850 50501 24.97 88.43 98.91 108.29 123.15

582090 50406 582238 50370

307 45+990 585222 49136 9.09 42.58 47.63 52.14 59.3 308 50+260 588250 46187 11.47 49.98 55.9 61.2 69.6 309 54+130 591146 41090 13.18 42.82 47.89 52.43 59.63 310 54+870 591696 43504 10.54 32.48 36.33 39.77 45.23 311 58+590 594212 40880 12.42 30.38 33.98 37.2 42.31 312 63+270 597842 38019 1.13 7.01 7.84 8.59 9.76 313 73+330 607154 35225 3.26 17.82 19.93 21.82 24.81 314 76+660 610229 36199 0.97 3.00 3.36 3.67 4.18

Summary of design floods for different return period Road E1.2- Busia-Majanji

Catch. Ref.

Chainage from Busia

Northing

Easting

Catch. area (km2)

Design flood discharge (m3/s)

10-yr 25-yr 50-yr 100-yr 325 1+125 620283 51064 0.19 0.88 0.98 1.07 1.22 324 1+480 619949 50892 0.57 2.87 3.21 3.51 3.99 323 6+970 616014 47143 2.0 10.03 11.22 12.29 13.97 322 10+310 614350 44331 0.88 4.41 4.94 5.4 6.14 321 10+885 614081 43819 0.16 0.81 0.90 0.99 1.12 320 11+860 613606 42931 8.35 24.68 27.61 30.22 34.37

318

16+310 611423 38133 3.96 17.82 19.94 21.83 24.82 17+390 610871 36614

317 21+600 610325 34182 4.96 22.18 24.81 27.16 30.89

Page 19: Final Detailed Design Report - Musita _ Majanji Road

ES-10 | FINAL Detailed Design Report_ Rev.1-AUG 2012 |

316 23+180 610300 32610 0.80 3.12 3.49 3.82 3.12 315 25+500 610374 30420 1.38 5.36 5.99 6.56 7.46

E10. Drainage Design

Assessment of Existing Drainage Structures

A visual assessment of the drainage structures was carried out by the Bridge/Drainage Engineer and the Hydrologist.

Each minor and major drainage structure was inspected and relevant basic measurements were taken. Data on hydraulic performance and history of any overtopping and history of rehabilitation measures undertaken were collected from local residents and branch of the ministry of works.

Moreover, observations were made relating to:

Hydraulic performance Physical condition Possible causes of damage Materials used for construction and their performance Period of service Possible reasons for poor performance Possibility of maintenance or repair Performance in respect to traffic safety Replacement options

A detailed photographic inventory and assessment of all the existing drainage structures are prepared following the field inspection.

For the purpose of this project, all drainage structures are classified in two broad classes namely, minor and major drainage structures.

Classification of Drainage Structures

Minor drainage structures are those pipes having single or multiple cell opening either made from concrete or corrugated metal sheet (Armco) and all the road side drainage facilities.

Minor Structures

Structures included in Major Structure’s category are box culverts, slab culverts and reinforced concrete /composite/ steel / bridges.

Major Structures

Slab culverts are those with top slab resting on abutments done separately, and box culverts are those having monolithic top slab, bottom slab and the vertical walls.

Stone pitched side channels and flow checks are found along a certain sections of the project roads. Some are recently constructed and are in very good condition. But in general it is observed that due to lack of regular repair, water flows out of the channel damaged the road pavment and make it difficult for road users. Please refer to table 1 in Appendix 8.2 for details.

Side Ditches

According to the structures inventory data, there are over 300 existing pipe culverts along all the project routes. The majority of the existing pipe culverts are made from either reinforced concrete

Pipe Culverts

Page 20: Final Detailed Design Report - Musita _ Majanji Road

ES-11 | FINAL Detailed Design Report_ Rev.1-AUG 2012 |

with internal diameter ranging from 300mm to 1000mm or Armco sheet ranging from 600mm to 2000mm internal diameter.

During assesmsnt of the drainage structures along the project route, thefollowing major deficiencies or problems were observed at pipe culverts:

� Damaged or missing headwalls � Siltation in pipes due to low invert level � Poor workmanship at the head walls and at pipe joints. � Insufficient length of pipes as compared to the width of the road � Insufficient hydraulic capacity � Lack of regular cleaning � Missing or damaged aprons and energy dissipaters at inlets and outlets

More than six box/slab culverts are found along the entire project route. Box Culverts

The following major deficiencies or problems were observed at box/slab culverts during the assessment:

� Deteriorated slab concrete � Cracked, damaged abutments and wing walls � Insufficient hydraulic capacity � Eroded bank and scoured bed. � Damaged inlet and outlet aprons (either broken down or dislodged)

There are no existing bridges along Musita- Lumino and Busia - Majanji roads. Bridges

The list of recommended drainage structures are listed in the Appendix to this report. They comprise:

Recommeded Structures

Pipe Culverts:

Single 900 mm : 53 No. Twin 900 mm : 7 No. Single 1050 mm : 7 No. Twin 1050 mm : 1 No. Single 1200 mm : 4 No. Twin 1200 mm : 4 No.

Box Culverts:

2m x 2m single cell: 6 No. 3m x 2m single cell: 3 No. 4m x 2m single cell: 4 No. 4m x 2m twin cell: 3 No. 4m x 2.5m single cell: 3 No. 4m x 2.5m twin cell: 3 No.

Page 21: Final Detailed Design Report - Musita _ Majanji Road

ES-12 | FINAL Detailed Design Report_ Rev.1-AUG 2012 |

E11. Geometric Design

In accordance with the requirements of the TOR, and as confirmed by UNRA, the designs were to be based on the Ugandan MoWH&C Road Design Manual of July 2005. In order to realize the

Design Standards

most economic design solution this Manual was complimented by recognised design manuals from neighbouring counties including;

� Kenya’s Road Design Manual – Part 1: Geometric Design Manual

� Tanzania’s Draft Road Manual

� Code of Practice for Geometric Design (SATCC-1998) – Trunk Road Design Standards

On the basis of the Ugandan Road Design Manual, the ideal functional classification for the project road is Class C or a Primary road. These are described as roads linking provincially important centers to each other or to a higher class roads (urban/rural centers). They provide linkage between districts, local centers of population and development areas with higher class road. Their major function is to provide both mobility and access

A paved Class II road standard was adopted for design; the applicable geometric design standards for which are presented in Figure 4.2a and 4.2b of Section 4 of the Design Manual.

For a Bitumen Class II road traversing a flat terrain (max grades of 5.5%), a design speeds of 90 km/h was recommended. It should however be noted that many sections of the existing road are long and straight and higher speeds than these will be possible.

Design Speed

Through the more populated centres along the route, a design speed of 50 kph has been set. This speed applies in sections and locations given in the Table 10.2 in the main report.

The traffic speed in the above locations shall be regulated through the installation of road signage, speed bumps and rumble strips.

After consultation with UNRA a cross section comprising 3.5 m lanes and 1.5 m shoulders was adopted for the project road. In towns/urban areas the shoulder width was increased to 2.0 m.

Cross-Section

Summary Of Adopted Design Parameters And Standards

The following parameters and standards have been adopted in the designs:

Design life: 20 years.

Cross-section: 7.0 m wide carriageway at 2.5% normal camber

1.50 m wide shoulders at 4.0 % normal crossfall (2.0 m in urban areas)

1.0 m wide side drain.

Page 22: Final Detailed Design Report - Musita _ Majanji Road

ES-13 | FINAL Detailed Design Report_ Rev.1-AUG 2012 |

Design Speed Parameters:

Design Speed

90 Km/h

70 Km/h

Min. Horizontal Radius

320 m

185 m

Max. Superelevation

7%

Max Gradient (Absolute)

5.5%

7.5%

Rate of Change of Superelevation

0.4-0.6 max

Minimum Crest Curve Kmin (stopping sight distance)

71

31

Minimum Sag Curve Kmin

41

25

Stopping Sight Distance (SSD)

170 m

111 m

Passing sight Distance

750 m

550 m

Selection Of Alignment

The following principles were adopted during selection of an appropriate alignment for the detailed design:

� Conformity to the specified geometric design parameters.

The alignment was designed to conform to or surpass the geometric design parameters as recommended in the design manual.

� Follow the general corridor of the existing road.

The general approach to the route alignment was to use the corridor of the existing road as much as possible. This was done to retain the present social function with minimum disruption to existing and long-term residents. Minor realignments were however introduced to improve the road geometry and remove potentially dangerous curves. This was also done at locations of new bridges.

� Keep the works within the existing right of way.

In most sections, the alignment design was carried out to follow the existing road as much as possible to enable the use of existing pavement materials to form new a subgrade.

� Improve junctions.

Page 23: Final Detailed Design Report - Musita _ Majanji Road

ES-14 | FINAL Detailed Design Report_ Rev.1-AUG 2012 |

In order to improve safety at the approach junctions, the project road has been realigned to approach the main highway at a right angle.

� Re-align at trading centres.

There are a number of large trading centers along the project roads with heavy population and agricultural activities. The possibility of having a bypass at some of these centers was investigated. Preliminary realignments outside the centers were designed. These were then presented to the Resettlement and Land Acquisition specialist who also visited the project road to evaluate the impact of the bypasses against keeping the alignment through the centers, compensating where necessary and maintaining the current social function of the road.

Page 24: Final Detailed Design Report - Musita _ Majanji Road

1 | FINAL Detailed Design Report _ Rev.1-AUG.2012 |

1 INTRODUCTION

1.1 Background

The Uganda National Roads Authority (UNRA) became a legal entity in 2006 and began operations in July 2008 with the mission:

“to develop and maintain a national road network that is responsive to the economic development needs of Uganda, to the safety of all road users, and to the environmental sustainability of the national road corridors.”

At local level UNRA’s objectives are:

4. To improve access to goods/passenger transport services and to reduce transport costs along the route;

5. To improve access to social and economic development opportunities along the route by providing high capacity infrastructure;

6. To ensure no roadside communities become worse off as a result of the road upgrading works

On This contract was executed on 1st September 2009. Under the agreed terms and conditions of the contract the effective date of commencement of the services was set at 27th November 2009.

In pursuance of the above objectives, UNRA has embarked on upgrading selected roads in several districts of Uganda.

To this end UNRA accepted the proposal of SMEC International Pty in association with NEWPLAN Ltd. of Uganda to provide consultancy services for the upgrading of several roads, referred to as Lot E, in the Eastern districts and comprising the following roads:

Road Reference No.

Road Name(s)

E1.1/E1.2 Musita-Lumino and Busia-Majanji roads (104 Km) E2.1/E2.2/E2.3 Tirinyi-Pallisa-Kumi and Pallisa-Mbale roads (114 Km)

E3 Mbale-Bubulo-Lwakhakha road (41 Km) E4 Namagumba-Budadiri-Nalugugu road (41 Km) E5 Kamuli-Bukungu road (64 Km)

Page 25: Final Detailed Design Report - Musita _ Majanji Road

2 | FINAL Detailed Design Report _ Rev.1-AUG.2012 |

1.2 Contract Details

This contract was executed on 1st September 2009. Under the agreed terms and conditions of the contract the effective date of commencement of the services was set at 27th November 2009.

CLIENT Uganda National Roads Authority CONSULTANT SMEC International Pty Ltd. In association with

NEWPLAN Ltd

CONTRACT PHASES Phase 1: Feasibility Study and Detailed

Engineering Design

Phase 2: Tender Assistance

Phase 3 : Project Management CONTRACT TIME Phase 1 & Phase 2: 10 months

Phase 3 : 48 months CONTRACT VALUES Phase 1 : UGX 320,881,504 + USD 3,307,169

Phase 2 : UGX 7,630,560 + USD 122,557

Phase 3 : UGX 609,074,334 + USD 2,116,351 CONTRACT EXECUTION DATE

1st September 2009

CONTRACT COMPLETION DATE

Phase 1 + Phase 2 : 30th September 2010

Phases 2 and 3 were subsequently omitted by the Client.

1.3 Terms of Reference

The main objectives of these Consultancy Services are:

(vi) Feasibility Study, including consideration of alternative routes and pavement options, environmental and social impact study, road safety, land acquisition, preliminary design, economic and financial analysis;

(vii) Detailed engineering design for the approved road option; including all necessary data collection, field surveys and analysis to cover all aspects of detailed design;

(viii) Environmental and Social Impact Assessment (EIA) in accordance with Ugandan legislation and NEMA guidelines;

(ix) Preparation of a full Resettlement Action Plan and associated surveys to identify and value property that will be affected by the road upgrading works and the establishment of the road reserve;

(x) Preparation of bidding documents based on the approved detailed designs.

The Terms of Reference relating to the detailed design phase are included in Appendix 1.

Page 26: Final Detailed Design Report - Musita _ Majanji Road

3 | FINAL Detailed Design Report _ Rev.1-AUG.2012 |

1.4 Preliminary Design Report

The Preliminary Design Report was submitted to UNRA in October 2010. The Report was submitted in two (2) volumes, namely:

Volume 1A: Main Text Volume 1B: Appendices Volume 2.1: Book of Drawings – Road 1 (Musita-Lumino/Busia-Majanji) Volume 2.2: Book of Drawings – Road 2 (Tirinyi-Pallisa-Kumi/Pallisa-

Kamonkoli) Volume 2.3: Book of Drawings – Road 3 (Bumbobi-Bubulo-Busumbu-

Lwakhakha) Volume 2.4: Book of Drawings – Road 4 (Namagumba-Budadiri-Nalugugu) Volume 2.5: Book of Drawings – Road 5 (Kamuli-Bukungu)

The Consultant received the Client’s comments on the Preliminary Design Report variously in February and July 2011.

1.5 Packaging of the Project Roads

Based on the preliminary construction cost estimates, the lengths and geographic locations of the project roads, the Consultant recommended, and agreed by the Client, that the project be divided into six (6) distinct packages for the purpose of bidding as follows:

Package 1 : Road E1 : Musita-Lumino/Busia-Majanji roads

Package 2A : Road E2.1/E2.2 : Tirinyi-Pallisa/Pallisa-Kumi roads

Package 2B : Road E2.3 : Pallisa-Kamonkoli road

Package 3 : Road E3 : Bumbobi-Busumbu-Lwakhakha road

Package 4 : Road E4 : Namagumba-Budadiri-Nalugugu road

Package 5 : Road E5 : Kamuli-Bukungu road

1.6 This Report

This report relates to the Detailed Design for

Package 1 - Road E1.1/E1.2 : Musita-Lumino/Busia-Majanji roads.

Page 27: Final Detailed Design Report - Musita _ Majanji Road

| FINAL Detailed Design Report _ Rev.1-AUG.2012 |

2 ENGINEERING STUDIES

2.1 Project Location

Lot E roads are located in the Eastern districts of Uganda and cover the five roads as indicated on the frontispiece.

2.1.1 Description of Project Road

The project road is discussed below. The lengths indicated are based on the final design chainages.

Road Links

Name Length (km)

(i) Musita – Nankoma 36 (ii) Nankoma - Buyinja 26 (iii) Buyinja – Lumino 15 (iv) Busia – Majanji 26

TOTAL

103

4

Page 28: Final Detailed Design Report - Musita _ Majanji Road

MUSITA

BUSIA

-

LUMINO

MAJANJI

Figure 1 : Location of Musita-Lumino/Busia-Majanji Roads 5

Page 29: Final Detailed Design Report - Musita _ Majanji Road

6 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

(a)

Alignment

The road traverses the Mayuge, Bugiri and Busia districts, starting at the Musita trading centre at its junction with the Jinja - Iganga road.

The terrain is flat to gently rolling terrain and the horizontal and vertical alignments are gentle with good visibility.

The riding surface width is generally 5m – 5.5m. The Nankoma-Namayingo link has recently been subjected to periodic maintenance by UNRA involving regravelling

Start at Musita Km 0+000

Alignment at Km 2

Alignment at Km 27

Alignment and surface at Km 30.8

(b)

Road condition

The road is a gravel road with generally good riding surface with a few exceptions where gullies have developed on the road surface.

-

Km 5 – Gullies in the road surface

Stretch along Busia- Majanji road

( c) Land use Basically subsistence agriculture with maize, potatoes, cassava and rice. Cash crop grown along the road is sugarcane. Rice is grown in the marshy areas.

Km 4.5 – Sugarcane being transported

Km 5.5 – Rice paddy in swamp

(d) Drainage

Minor drainage structures consist of concrete pipes. There are no major structures in this section. Pipe culverts are generally silted up due to invert Levels being below ground level.

There are stretches where erosion in side drains is evident.

Erosion in side drain

Lined Drain at Km 31.6

Typical Mitre Drain

Page 30: Final Detailed Design Report - Musita _ Majanji Road

7 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

(e)

Construction materials

There is an existing rock quarry at Km 2.6 and an existing borrow pit at Km 14. In addition, potential rock sources exist at Km 2.9, Km 11.8 and Km 18.2.

Existing Rock Quarry at Km.2.6

Rock Outcrop at Km.

11.8

Rock Outcrop at Km 30.6

Rock Outcrop at Km 31.4

(f)

Trading Centres

The link passes several trading centres, namely Buluba at Km 2, Mayuge at Km 13 and Mpungwe at Km 20.7.

Km. 2 – Buluba Trading Centre

Km 13 – Mayuge Trading centre

-

Namayingo Trading

Centre

Lumino trading centre end

of link Km 49.3

2.1.2 Topography

The topography of the project area is relatively flat with high ridges and isolated hills, adulating low lands and perch vents with a few higher residual features.

The hills are linear and of a convex nature scope and almost flat valleys. Some of the hills include Irimbi, Bululu and Namakoko in Bugiri district.

The lowest point of about 1,200m above sea level is in the south along the Lake Victoria and the highest 1500m above sea level is found in the north.

Page 31: Final Detailed Design Report - Musita _ Majanji Road

8 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

The project area has a long shoreline of Lake Victoria in the south with several islands. (Statistical

2.1.3 Geology

In terms of geology, the project area is made up Precambrian rocks with bare granitic rocks at several places heavily eroded. Deposits of eroded soil can be witnessed in some parts of the low lands on farmers’ gardens and these tend to increase towards the lowlands.

2.1.4 Soils

The soils covering most of the project area are mainly loamy and sand loams with spots of clay at the valley areas. These soils have fine texture with rather loose structure, which are easily eroded and leached. The soil types can be summarized as;

� Yellow-red sandy, clay loam soils varying from dark grey to dark. These occur

on gently undulating –hilly topography. � Brown yellow clay loams with laterite horizon with a variety of dark brown to

dark grayish brown. These occur on flat ridge tops or as of undulating topography.

� Light –grey- white mottled loamy soils with laterite horizon ground, structures- less loamy sands. These are acidic-allocative and mainly found on lower and bottom slopes.

� Clay soils are limited to the swamps in the valleys. (Busia District State of Environment Report, 2005 and Bugiri District Development Plan 2009/10-2011/2012).

2.2 Topographical and Aerial Survey

2.2.1 General

The project roads with a total length of approximately 364 km was covered by colour aerial photographs to scale 1:8,000 in March 2010. Ground control designed for aerial triangulation was carried out for subsequent line and orthophoto mapping.

Two inter-visible permanent beacons with description and photo, consisting of an iron pin in concrete 30 x 30 x 40 cm or a hole drilled in rock were constructed at intervals of 3 km along the specified routes i.e. Roads 1, 2, 3, 4, and 5 to serve as control for the inter-visible interim beacons which were constructed in between these control beacons along the routes. The interim beacons consists of an iron pin set in concrete 20 x 20 x 30 cm or a hole in rock when suitable.

2.2.2 References and Datum

Three units Leica GPS Receivers System 300 Instruments and Software

SKI software version 2.3 One Wild NA2 Automatic Level One Wild A0 Automatic Level One Zeiss NI2 Automatic Level

Page 32: Final Detailed Design Report - Musita _ Majanji Road

9 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Two units Geodimeter 400 Total stations One Garmin, Etrex, handheld GPS receiver

Datum : Arc 1960 (NEW) Projection : Transverse Mercator

References

Grid : UTM, Zone 36 N Units : Metric

Datum Points in Plan and HeighUP50

t E = 569809.367 N = 51853.173

51X1 E = 485710.686 N = 152493.050 52X2 E = 509491.943 N = 126569.501 52X3 E = 510506.248 N = 113620.011 53X2 E = 598100.184 N = 146594.827 53X8 E = 607124.549 N = 112349.993 53X10 E = 592040.310 N = 131016.272 Z = 1148.182 Ground level 54X3 E = 635475.290 N = 131108.840 Z = 1486.205 Ground level 64X1 E = 640423.259 N = 86844.067 Z = 1502.050 Ground level 64X2 E = 624537.248 N = 109977.442 62GP1 E = 518178.070 N = 110401.090 Z = 1064.210 Brass bolt 74GP1 E = 614717.168 N = 35615.815 Z = 1179.330 Brass bolt

K2 E = 535978.005 N = 60268.398 K3 E = 532200.518 N = 56074.307

UP50 Pillar destroyed, but holes in rock after anchor iron found and restored to within 5 cm.

51X1 Pillar destroyed, but holes in rock after anchor iron found and restored to

within 5 cm.

52X2 Pillar destroyed, but holes in rock after anchor iron found and restored to within 5 cm.

52X3 Pillar destroyed, but holes in rock after anchor iron found and restored to

within 5 cm.

53X2 Pillar destroyed, but holes in rock after anchor iron found and restored to within 5 cm.

53X8 Pillar destroyed, but holes in rock after anchor iron found and restored to

within 5 cm.

53X10 Pillar destroyed, but holes in rock after anchor iron found and restored to within 5 cm.

54X3 Pillar destroyed, but holes in rock after anchor iron found and restored to

within 5 cm.

64X1 Pillar destroyed, but holes in rock after anchor iron found and restored to within 5 cm.

64X2 Pillar destroyed, but holes in rock after anchor iron found and restored to

within 5 cm.

Page 33: Final Detailed Design Report - Musita _ Majanji Road

10 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

62GP1 Short ground pillar with brass bolt found intact.

74GP1 Short ground pillar with brass bolt found intact.

K2 Iron pin in concrete found intact.

K3 Iron pin in concrete found intact.

2.2.3 Ground Control And GPS Measurements

A total of 219 GPS Beacons were constructed as inter-visible pairs after every 3 km along the five road alignments divided as follows:

Musita-Lumino Road : ML01 – ML44 Busia-Majanji Road : LM1- LM5 and LB1 – LB12

A description card + photo was prepared for each of these points. Inter-visible Beacons were also constructed between the GPS Beacons with a maximum length not exceeding 500 m between the Beacons.

Static Differential GPS measurements in combination with double run spirit leveling was deployed to obtain coordinates to cm accuracy in plan and height for the photo control points as well as GPS Beacons used as control points for the densification of beacons in between. This was coordinated using a Total station and measured as traverses between the control points with closing errors not less than 1:10,000 in plan. Double run spirit leveling was carried out to obtain reliable heights also for these points.

2.2.4 Interim Beacons And Total Station Measurements Coordinates in

plan are based on the following Trig stations: Musita-

Lumino/Busia-Majanji Road : UP50, 74GP1, K2 and K3

Heights are based on the following Trig stations:

Musita-Lumino/Busia-Majanji Road : 74GP1 (brass bolt)

Static Differential GPS observations was carried out with observation times between 20 to 30 minutes on every station to obtain Cartesian coordinates in the WGS 84 system with subsequent transformation into the UTM System Arc 1960 datum using SKI software based on the control points mentioned above.

Double run Spirit Levelling was carried out for all permanent Beacons, with re- levels done for cases where error was greater than 10mm/km between forward and backward levelling.

Heighting

2.2.5 Aerial Survey

Permission to fly over the project roads was obtained from Uganda Civil Aviation Flight Permission

Authority on: 8 February 2010 for a 3-month period up to 8 May 2010.

Page 34: Final Detailed Design Report - Musita _ Majanji Road

11 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Aerial photography for Musita-Lumino/Busia-Majanji roads was undertaken on Flight Dates

11th March 2010 and completed on 13th March 2010 with flight altitude of 705m above mean ground level

� Aircraft: Piper Navajo PA 31 reg. 5Y-MAP, white with blue stripes Equipment

� Camera equipment: Wild RC-10 � Flight planning equipment: IGI WIN MP � Navigation equipment: IGI CCNS NOVATEL DL-V3 � Film used: Agfa AVIPHOT X 100PE1 � Film processing and printing:FUGRO/BKS, Northern Ireland

2.2.6 Final Products

Final products delivered after aerial photography and post-processing included:

1. Colour aerial photography at 1:8,000 scale inclusive of a ground GPS station operated simultaneously as the aerial photography was undertaken.

2. Quick View digital orthophoto for a minimum of 1.5 km width.

3. Digital photogrammetric line mapping for a 60 m wide corridor inclusive of

mapping streams 500 m upstreams and 500 m downstreams for a 100 m width at 10 bridge sites.

Other deliverables included: a) Hard and soft copy of the Aerial Photographs b) Flight Plans c) Caliberation Certificates d) DTM and x, y , z ground points @ 5 m intervals e) Detailed Survey Report

Both the horizontal and vertical accuracies achieved were within the tolerances agreed with the Client, namely,

Horizontal : As per ToR Vertical : +/- 70mm

2.3 Traffic Surveys

2.3.1 Terms of Reference

The ToR called for:

Assembling all traffic data on the project roads with a view to determine the present pattern of traffic growth by vehicle class.

Agreement with UNRA on the location of and the number of traffic count

stations (an average at one per 20km, and at least 5km from major junctions) where counts of motorized and non motorized vehicles, pedestrians and animals best represent present road usage.

Page 35: Final Detailed Design Report - Musita _ Majanji Road

12 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Conducting classified counts at each location for a continuous period of not less than five days 12-hour and two days (1 week day and 1 weekend) for 24-hour taking into account fluctuations caused by local factors e.g. market days.

Determining traffic predictions by class for each station, for assumed low,

medium and high growth predictions.

Carrying out axle load survey over a minimum period of 3 days per road, which was to include information on origin and destination of all vehicles stopped.

Classified counts were carried out in the months of March, April and May 2010.

2.3.2 Existing Traffic

Table 1 shows the historic data obtained from UNRA.

Table 1: Historical data obtained from UNRA

Road name

ADT excludi

ng motorcy

cles

ADT includin

g motorcy

cles

ADT NMT

Musita-Mayuge-Nankoma- Namayingo-Lumino (U)

78

552

2628

Busia – Majanji (U) 63 263 1540

Table 1 shows that the road has a high number of NMT and motorcycles traffic.

2.3.3 Traffic Counts

Manual classified counts were carried at seven stations for seven days, from 25th

to 31st March 2010. Night counts were carried for one weekday and one weekend day at each station.

The locations are described in Table 2 below and shown in Appendix 2A. The scope of non-motorized traffic (NMT) included bicycles, pedestrians and carts. The results from the study are attached in Appendix 2B.

It was assumed that no traffic would be diverted from the alternative routes since these routes are shorter than the project road.

Page 36: Final Detailed Design Report - Musita _ Majanji Road

13 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Table 2: Traffic Count Stations

Locations Dates Type of survey

1. 5km after Lumino

2. 5km before Busia

3. 5km before Namayingo

4. 5km before Namayingo (NMT)

5. 5km from Mayuge

6. 5km from Musita

7. 5km before Lumino

25th - 31st March, 2010

26th – 27th March, 2010

Classified

Count Classified

Count (Night Count)

12h counts were expanded to 24h using the ratios of 24h to 12h traffic for each vehicle type and separately for weekday and weekend traffic. The details are shown in Table 3.

Table 3: Observed ratio of 12 to 24 hour traffic

Station number

Station location Week day Week end 12 hour traffic as a

percentage of 24 hour traffic

12 hour traffic as a percentage of 24 hour

traffic 1 5km after Lumino 87.3% 80.6% 2 5km before Busia 90.0% 88.2% 3 5km before

Namayingo

71.0%

74.0% 4 5km from Mayuge 76.1% 69.5% 5 5km from Musita 77.7% 76.4% 6 5km before Lumino 73.9% 79.7%

2.3.4 Base Traffic

Table 4 shows the observed ADT at each of the counts station.

Table 4: Summary of observed ADT at Count Stations Station no

Count station

Direction A Direction B Both directions Directional distribution

Vehicles PCU Vehicles PCU Vehicles PCU Vehicles PCU 1 5km after

Lumino 117 147 120 173 237 319 49:51 46:54

2 5km before Busia

1,010 1,173 1,078 1,274 2,089 2,446 48:52 48:52

3 5km before Namayi ngo

472 578 473 671 945 1,249 50:50 46:54

4 5km from Mayuge

408 539 420 536 828 1,075 49:51 50:50

5 5km from Musita

706 1,153 724 1,236 1,430 2,389 49:51 48:52

6 5km before Lumino

607 761 442 579 1,049 1,340 58:42 57:43

Page 37: Final Detailed Design Report - Musita _ Majanji Road

14 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

AA

DT

As noted from Table 4, traffic increases towards the towns and trading centers such Busia and Musita.

The traffic surveys were conducted in the period February – May 2010. Therefore the observed ADT needed to be factored for the season to arrive at the Annual Average Daily Traffic (AADT). However due to the absence of such data, a seasonal factor of 1 was assumed.

Using the assumed seasonal factor of 1 (one), the AADT was calculated using the equation below.

Where

𝐴𝐴𝐷𝑇 = 𝐴𝐷𝑇 × 𝑆𝑒𝑎𝑠𝑜𝑛𝑎𝑙 𝑓𝑎𝑐𝑡𝑜𝑟

AADT – Average Annual Daily Traffic. ADT – Average Daily Traffic.

Figure 2 below shows estimated base year traffic composition at each of the study locations.

2500

2000

1500

1000

500

0 5km after Lumino

5km before

Busia

5km before Namayingo

5km from Mayuge

5km from

Musita

5km before

Lumino Sation name

AADT (with Motorcycles) AADT (without motorcycles)

Figure 2: Base year traffic composition at each of the study locations.

The proportion of motorcycles to the other traffic is high as seen from Figure 2.

Appendix 2C contains details of the estimated AADT at each of the locations along the project roads.

Page 38: Final Detailed Design Report - Musita _ Majanji Road

15 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

2.3.5 Traffic Growth

In order to estimate the AADT in the project period, the Consultant needed to determine the traffic growth rate over this period. This growth is represented by a growth in normal traffic, diverted traffic and generated traffic.

2.3.6 Growth in normal traffic

To derive growth in normal traffic, analysis of either historical traffic data over the years or traffic proxies can be used.

Deriving traffic growth from traffic data involves analysis of the growth of the various traffic classes over a long period of say 10-20 years. This growth will give a trend in the growth of traffic over the years. This trend is then used to project the traffic growth in the project period. It was noted that analysis of historical data was not feasible as there was no adequate historical data.

Traffic growth using traffic proxies involves the comparison of traffic growth with proxies such as fuel consumption, vehicle registration trends, GDP growth etc.

Appendix 4D shows the trends in growth of the various traffic proxies as well as the derived traffic growth trends.

2.3.7 Diverted Traffic

It was assumed that no traffic would be diverted from the alternative road since the project road was longer in distance than the alternative road.

2.3.8 Generated traffic

Generated traffic is additional traffic which will occur in response to the provision or improvement of a road. This will in the short term arise from increased number of trips of existing vehicles or generation of new trips which were never present before the improvement of the road. In the long term the traffic generation will be due to increased economic activity along the project road after it has been improved / upgraded.

Derivation of generated traffic is shown in Appendix 2D.

These factors were used in the derivation of generated traffic at the various study locations.

2.3.9 Projected Traffic growth

It was assumed that road construction shall commence in the year 2011 and end in 2015. Projections were made for a design period of 15 years and 20 years. Therefore projections were made up to the year 2030 and 2035 using the corresponding growth factors.

Results obtained are shown in Appendices 2E.

Page 39: Final Detailed Design Report - Musita _ Majanji Road

16 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

2.3.10 Origin/Destination Surveys

OD Survey Locations

Table 5 shows the locations used for the survey.

Table 5: Origin Destination Survey Locations Station

no. OD stations, Motorized

traffic OD station, Non motorized

traffic 1 5Km from Musita (Bufulubi) 2 5km before Busia (Dabani) 3 5Km from Namayingo (Buyima)

At these locations, a 7 day - 12 hour Origin Destination Survey was conducted.

Data Collection and Compilation

The OD survey was carried out during the month of April 2010 using enumerators hired and trained from along the project road.

Information gathered through road side interviews of vehicle drivers was analyzed to understand the origin-destination characteristics of traffic plying the project roads. Since these interviews were conducted on a sample of vehicles, the collected information was expended to reflect the total volume of traffic plying on the road on that particular day.

To analyze the traffic interactions between the various sub-regions of the country and outside of it, the spatial delineation of the entire region is needed for convenience of analysis. For this study, it was felt that the district/sub county boundaries would be a convenient unit of spatial delineation as each district/sub county has documented information about its demographic and socio-economic indicators.

Station 1: 5km from Musita (Bufulubi)

a.

Trip Frequency

Figure 3 shows the frequency of trips made through 5 km from Musita

Page 40: Final Detailed Design Report - Musita _ Majanji Road

17 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Perc

ent o

f trip

s mad

e

Perc

enta

geof

trip

s

100%

90%

80%

70%

60%

50%

40%

30%

20%

10%

0%

Several times a day Once per day Several times a week Once a week Several times a month Once a month

Several times a year

Once a year

Rarely

Vehicle type

Figure 3: Frequency of trips made through 5 km from Musita

As seen in Figure 3, Lorries capacity > 3.5 tons and motorcycles make several trips a day while the large buses make one trip per day through the study point.

b.

Trip purpose

Figure 4 shows the purpose of trips made through the study point.

As noted in Figure 4, most of the trips are made for business while the least trips are made for Leisure/Social purposes.

100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0%

To/from Home To/From Work To/From School Business Shopping Government / Official Leisure / Social Tourism Other

Vehicle type

Figure 4: Purpose of trips made through 5km from Musita.

Page 41: Final Detailed Design Report - Musita _ Majanji Road

18 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Num

ber o

f pas

seng

ers

Perc

enta

ge tr

ips m

ade

c.

Vehicle occupancy

Observed passenger occupancy in various types of vehicles plying through the study location is shown in Figure 5.

80 70 60 50 40 30 20 10 0

Vehicle type

Figure 5: Observed passenger occupancy per vehicle passing through the study location

It was noted that both the medium buses and the large buses provide motorized transport along the project road.

Station 2: Dabani (5km before Busia)

a.

Trip Frequency

Figure 6 shows the frequency of trips made to through the study point.

100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0%

Several times a day

Once per day

Several times a week

Once a week

Several times a month

Once a month

Several times a year

Once a year

Rarely

Vehicle type

Figure 6: Trip frequency at 5km from Busia

Page 42: Final Detailed Design Report - Musita _ Majanji Road

19 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Perc

enta

getr

ips

As can be seen from the Figure 6, Lorries and motorcycles make several trips a day

b.

Trip purpose

Figure 7 shows purpose of trips made through the study location.

100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0%

Vehcile type

To/from Home

To/From Work

To / From School

Business

Shopping

Government / Official

Leisure / Social

Tourism

Other

Figure 7: Purpose of trips made through the study location

From Figure 4.6, the greatest percentage of trips is made for Business followed by to/from work or home. The least trips are made for Tourism and Leisure/Social.

c.

Occupancy of Vehicles

Figure 87 shows the observed passenger occupancy in various types of vehicles passing through the study point.

Page 43: Final Detailed Design Report - Musita _ Majanji Road

20 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Num

ber o

f pas

seng

ers

50

40

30

20

10

0

Vehicle type

Figure 8: Average Vehicle Occupancy for vehicles through study point

Vehicle occupancy at this station is lower than that at 5km from Musita. It can be concluded that

� Lorries and motorcycles make several trips a day while the large buses make one trip per day through the study point,

� Most of the trips through the project road are made for business while the least trips are made for Leisure/Social purposes.

� Small buses, medium buses and the large buses provide motorized transport along the project road.

Station 3: 5km from Namayingo (Buyima) NMT

a.

Trip Frequency

Figure 9 shows the frequency of trips made to through the study point.

Trips by Non motorized traffic are mostly made several times a day and once a day.

Page 44: Final Detailed Design Report - Musita _ Majanji Road

21 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Perc

ent o

f trip

s m

ade

Perc

enta

ge tr

ips

mad

e

100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0%

Bicycle Pedestrian Cart

Vehicle type

Several times a day Once a day Several times a week Once a week Several times a month Once a month

Several times a year

Once a year

Rarely

Figure 9: Frequency of trips made through the study point.

b.

Trip purpose

Figure 10 below shows the purpose of vehicles moving along the project road.

100%

90%

80%

70%

60%

50%

40%

30%

20%

10%

0%

Bicycle Pedestrian Carts

Vehicle type

To/from Home

To/From Work

To/From School

Business

Shopping

Government / Official Leisure/Social Tourism Other

Figure 10: Purpose of Non Motorized vehicles moving along the project road

From Figure 10, the greatest percentage of the Non motorized vehicle trips are made for the Business (45%) and to/from home trips (24%). There are no trips made for tourism.

Other information derived from this survey included the following;

� Origin and Destination characteristics

� Cargo type

� Traffic generating zones

� Passenger origin and destination

Page 45: Final Detailed Design Report - Musita _ Majanji Road

22 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

� Passenger trip frequency

� Passenger trip purpose

� Passenger employment

Appendix 2F contains a summary of the results obtained from this study.

2.3.11 Axle Load Survey

Survey Methodology

A three day traffic axle load survey and counts was carried at Nabigingo out along the project road between 6th May and 22nd May 2010.

Weighing was done for both directions simultaneously using a portable weighbridge to Transport Research Laboratories (TRRL) specifications.

The vehicles weighed were:

I. Medium Buses

II. Large Buses

III. Medium Goods Vehicles

IV. Heavy Goods Vehicles.

V. Very Heavy Goods Vehicles

Data Collection and Compilation

The axle load survey was carried out during the month of May 2010 using enumerators hired and trained from along the project road. These were assisted by trained axle load equipment operators. The logistics and supervision of the surveys were managed by a Traffic Engineer.

The traffic of eligible vehicles along the project road is not high to warrant sampling. All vehicles eligible were thus weighed.

Equivalence Factors

The axle load so obtained was used to calculate Equivalence Factors (E.F.) using Liddle's formula as follows:

E.F = (Ls/8200)4.5 ……………………………………………..........1

In computing the average equivalence factors for each vehicle type, each two lane was considered separately.

Tables 6 and 7 show the summary of axle load for each direction respectively.

Page 46: Final Detailed Design Report - Musita _ Majanji Road

23 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Table 6: Axle load for Vehicles from Musita Vehicle category

Average gross weight

Average equivalence factor (80KN)

Total vehicles

LGV (1.2) 4.26 0.07 22 MGV(1.2) 4.10 0.00 1

Total 23

Table 7: Axle load for vehicles to Musita Vehicle

category Average gross

weight Average equivalence

factor (80KN) Total

vehicles LB 1.2 14.68 1.69 6 LT 1.2 5.38 0.11 18 MB 1.2 4.77 0.01 3 MT 1.2 18.65 9.61 1 Total 28

2.3.12 Overloading

Figures 11 and 12 show the level of overload for the vehicles weighed at this station.

Figure 11: Level of overload from Musita

Page 47: Final Detailed Design Report - Musita _ Majanji Road

24 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Figure 12: Level of overload to Musita

Table 8 shows the level of overload for each of the axle load configuration along this road.

It is deduced that the level of overload from Busia is higher than that to Busia.

Table 8: Level of overload along Musita – Nankoma – Lumino – Busia/Majanji Axle

configuration Axle load

Axle load

>5 tons >8 tons >10 tons >5 tons >8 tons >10 tons To Busia From Busia LB (1.2) 91.7 25 8.3 LT (1.2) 6.8 0 0 11.1 0 0 MB (1.2) 0 0 0 MT (1.2) 0 0 0 50 50 50

2.3.13 Cumulative Equivalent Standard Axles (CESA)

The Cumulative Equivalent Standard Axles were estimated based on the assumed growth rates as summarized in Table 9.

Table 9: Adopted Traffic Growth rates for LB, LGV, MGV and HGV

Growth Scenario

2010- 2013

2014- 2018

2019- 2023

2024- 2030

2024- 2035

Pessimistic 4.7 6.8 4.4 2.9 2.9 Realistic 4.7 8.5 5.6 3.8 3.8 Optimistic 4.7 10 6.8 4.6 4.6

It was assumed that the construction works will commence in 2011 and last for 4 years.

Page 48: Final Detailed Design Report - Musita _ Majanji Road

25 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Based on these growth factors the Cumulative Equivalent Axles were determined by road section using the formula below.

𝐶𝑆𝐴 = 365𝑥𝑇𝑥�(1 + 𝑟)𝑛 −

1�

𝑟

Tables 10 and 11 give the equivalent standard axles in the periods 2015-2030 and 2015-2035 respectively.

Table 10: Equivalent Standard axles in the period 2015-2030. Count station Equivalent Standard Axles period 2015-2030 (x 1 million)

Direction A Direction B Pessimistic Realistic Optimistic Pessimistic Realistic Optimistic 5km after Lumino 0.44 0.49 0.56 0.00 0.00 0.00 5km before Busia 2.25 2.57 2.91 0.03 0.03 0.04 5km before

Namayingo 1.86 2.13 2.41 0.01 0.02 0.02

5km from Mayuge 1.86 2.13 2.41 0.01 0.02 0.02 5km from Musita 10.10 11.57 13.11 0.01 0.01 0.01 5km before Lumino 1.71 1.96 2.22 0.03 0.03 0.04

Table 11: Equivalent Standard axles in the period 2015-2035. Count station Equivalent Standard Axles period 2015-2035

Direction A Direction B Pessimistic Realistic Optimistic Pessimistic Realistic Optimistic 5km after Lumino 0.62 0.73 0.84 0.00 0.00 0.00 5km before Busia 3.22 3.79 4.40 0.04 0.05 0.06 5km before

Namayingo 2.66 3.13 3.64 0.02 0.02 0.03

5km from Mayuge 2.66 3.13 3.64 0.02 0.02 0.03 5km from Musita 14.43 16.98 19.73 0.02 0.02 0.02 5km before Lumino 2.46 2.89 3.35 0.04 0.05 0.05

2.3.14 Summarized Road Usage

Estimated Number of Passengers using the Road

This was estimated from the Average Annual Daily Traffic (AADT) and the average vehicle occupancy.

Table 12 shows the number of passengers passing through the study locations using motorized transport per day.

Table 12: Passengers passing through the study locations (using motorized transport) per day Study location

Passengers per day

5km from Musita 4,177 5km before Busia 4,076

Page 49: Final Detailed Design Report - Musita _ Majanji Road

26 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Car

go p

er d

ay, t

onne

s

It is noted that there are more passengers moving the 5km from Musita that 5km from Busia.

Estimated Cargo Tonnage using the Road

This was estimated from the Average Annual Daily Traffic (AADT) as determined during the traffic survey and axle load weight less the tare weight as determined from the axle load survey.

Figure 13 shows the cargo passing each study location along the project roads per day.

1,600 1,400 1,200 1,000

800 600 400 200

0

5km from

Musita

5km from Mayuge

5km before Namayingo

5km before

Busia

5km after Lumino towards

5km before

Lumino

Station name Majanji

Figure 13: Cargo passing through each study point along the project roads

2.3.15 Sensitivity Analysis

As part of the ToR, for the final pavement design, the Consultant was required to;

1. Increase the design axle load by 5% or more if historical and present overload data does not indicate a progressive tightening of overload controls.

2. Carry out a sensitivity analysis on the axle load and traffic ADT variation (+/-5%, +/-10% and +/-40%) and assess how this affects the pavement designs.

Appendix 2G shows results from the analysis.

Page 50: Final Detailed Design Report - Musita _ Majanji Road

27 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

2.4 Soils and Materials Investigations

2.4.1 General

The materials investigations were conducted in accordance with the Terms of Reference. It consisted of site reconnaissance, field exploration and analysis of the findings of the field exploration.

The Draft Final Soils and Materials Report has been produced as a separate Volume. The following is the summary.

2.4.2 Sub-grade Soil Investigation

The sub-grade soil investigation along the existing road alignment comprised sub- grade soil sampling by means of trial pits, DCP testing and laboratory testing.

Trial pits were excavated at two (1) kilometre interval on alternate side of the carriageway to depths of generally 1 m.

Trial Pits

The pits were dug to varying depths from the surface to sub-grade level with a total of 180 pits dug over the total road length of the five project roads of 365 km.

The vertical profile of the pavement in each trial pit was recorded and representative sub-grade sample taken for laboratory testing. The trial pit logs are included in the Soils and Materials Report.

DCP tests were conducted at intervals of 500m as stipulated in the ToR to measure the in-situ bearing strength (CBR) of the sub-grade. Standard DCP

DCP Investigations

apparatus with the following parameters was employed:

� 570mm dropping height � 8 kg falling weight � 60˚ tipped cone having 20mm diameter

To avoid weak spots (thin layers) from being overlooked and to identify layer boundaries fairly accurately, readings were taken at 1-5 blow intervals, depending on the rate of penetration.

There are no major swamps along Musia-Lumino/Busia-Majanji roads. Swamp Investigations

2.4.3 Gravel and Hardstone Sources

Field Exploration

The field exploration for this project consisted of:

- Assessment of the suitability and extent of the material source.

- Excavation of trial pits.

- Logging of the layers encountered.

Page 51: Final Detailed Design Report - Musita _ Majanji Road

28 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

- Retrieval of samples for laboratory testing.

- Backfilling of the trial pits.

At each site, trial pits were excavated and depths of overburden and gravel were logged. In some instances, material was sampled from rock outcrops, talus, or existing quarries, in which cases, test pit excavation was not required. The volumes of both overburden and gravel were also estimated.

Gravel and Hardstone Sources

A total of 20 existing or potential gravel sources and 3 rock sources were identified and investigated along Musita-Lumino/Busia-Majanji road as listed below:

Table 13: Borrow Pits and Quarries

No. of No. of Road No. Road/Link Name Borrow Quarries Pits

E1.1

Musita – Lumino

13

2

E1.2

Busia – Majanji

7

1

TOTAL

20

3

The location of the materials sources are included in Appendix 3.

2.4.4 Laboratory Testing

As a requirement under the Contract, the Consultant fabricated a mobile laboratory in a 40-foot container at its offices in Kampala. Upon completion of fabrication and

Mobile Laboratory

fitting out the laboratory was transported and erected at the compound of UNRA’s regional offices in Jinja.

Testing

Gravel Samples

Samples of sub-grade material recovered from trial pits and samples from the gravel sources were transported to the mobile laboratory in Jinja where they were subjected to the following tests:

- Natural moisture content determination

- Particle size analysis

- Atterberg limits

- Moisture content – Dry density relationship (BS 1377 test method)

- CBR (4-day soak compacted at 90%, 95% and 98% MDD)

- Swell tests

Page 52: Final Detailed Design Report - Musita _ Majanji Road

29 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Rock Samples

During the detailed design stage one potential quarry from each of the five project roads was drilled down to 15 m.

Along Musita-Lumino road, there is an existing commercial quarry at Km 2+600 at Lugolole. Besides a sample from a stockpile of existing crushed aggregate, a hole was drilled down to 15 m. Sample of the crushed aggregate and the rock core from the drilled hole were taken to the Ministry of Works’ central testing laboratory at Kireka where they were tested for:

- Specific Gravity

- Ten Percent Fines Value (TFV) - dry

- Ten Percent Fines Value (TFV) – wet

- Water adsorption

- Sodium Sulphate Soundness

- Bitumen affinity

The test results are included in the Soils and Materials Report. Summaries of the results are given in Appendix 3.

2.5 Hydrological Studies

2.5.1 Objectives

The objectives of the services as per the terms of reference (TOR) issued to the Consultants are:

2.5.2 General Objective

� To undertake hydrological and hydraulic assessment for the project roads under Lot E

� To prepare Hydrological Reports as per the Terms of Reference

2.53 Specific Objectives

� Collect and compile hydrological data for the project roads � Carry out hydrological analysis for various drainage basins and channels

traversed by the road, � Computation of design discharges for the existing and proposed drainage

structures along the roads � Preparation of hydrological report for the project

2.5.4 Background

A detailed hydrological study of LoT E roads was carried out in accordance with the Road Drainage Design Manual (RDDM) - Vol. 2: Drainage Design procedures

Page 53: Final Detailed Design Report - Musita _ Majanji Road

30 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

and methodologies including other hydrological analysis methods. Among the available methods in the RDDM, the TRRL East African Flood Model and Flood Frequency Analysis Methods (Log-Pearson III Distribution) have been considered to be the most appropriate methods given the available data.

2.5.5 Hydrological Analysis – Criteria and Practices

The Road Drainage Design Manual (2005) guidelines require a designer to develop a clear understanding of the existing drainage conditions for a given assignment before determining the capacity of the existing cross and lateral drainage structures.

Among the initial understandings is the production of a concept map illustrating the drainage system, catchment delineation and existing utilities during the investigation. The manual suggests a wide ranging number of methods that can be adopted to determine the design discharges for drainage design based on the circumstances encountered. It is required that the choice of return period to be selected for the design of drainage structures should be made by the designer in relation to cost of facility, risk associated with damages associated with large events etc.

Minor drainage structures e.g. side ditches are to be designed to carry a 10-year flood while major ones must be evaluated for the 25-100 year storm. The RDDM (Table 3.2) suggests suitable return periods for various structural categories. Whenever possible, it is required that adequate openings are provided to limit backwater effects and excessive bed scour.

The TRRL East African Model has been widely applied and found to be more relevant in East Africa since a number of small catchments were extensively studied prior to establishing the required parameters for its application.

2.5.6 Hydrological Analysis – Methodology

In undertaking the hydrological study and analysis, the following operations are undertaken:

(a) Visual inspection and capacity assessment of all existing cross drainage

structures

(b) Review, collection and analysis of all existing data including rainfall and runoff records

(c) Catchment area delineation

(d) Catchment characteristics determination (e.g. quantification of key catchment

parameters - catchment area, mainstream length and slope for all existing and proposed road crossings)

(e) Analysis of rainfall and flow data

(f) Selection of hydrologic procedure (e.g. determination of TRRL design

parameters (soil cover, land use, etc.) in accordance with the provisions of the Road Drainage Design Manual

(g) Return period adoption

Page 54: Final Detailed Design Report - Musita _ Majanji Road

31 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

(h) Peak flow or discharge estimation

2.5.7 Data Collection

The following data sets were collected during the fieldwork in Uganda and some had already been collected and compiled for the project.

(a) Topographic Maps of scale: 1:50,000 and 1:250,000: [Source: GIS Database -

SMEC Office in Uganda]

(b) Meteorological data: [Source: Ministry responsible for Meteorological data in Uganda]

(c) Hydrological and Flood Flow Data: [Source: Ministry responsible for Water

Resources]

(d) Uganda Soil Map of scale 1:1,500,000: [Source: SMEC Office in Uganda]

(e) Digital Elevation Model (DEM): [GIS Database - SMEC Office in Uganda]

(f) Site visit inspection and assessment information

2.5.8 Topography, Catchment Area Delineation and Watershed Parameters

To investigate the information and data, the essential items like relief type, catchment parameter or the streams along the route, data pertaining to roughness and runoff coefficients, topographic maps, land use and land cover, soil and geomorphology maps, the field visit inspection and assessment were used. In the study of the watershed characteristics, extensive study has been done using topographic maps (1:50,000) for all the watercourse catchments draining across the roads.

The catchment areas have been delineated from the topographic maps and Digital elevation model (DEM) for Uganda. The process includes the digitization of the stream networks from topographic map, and georeferencing to UTM coordinate system, datum Arc 1960, Spheroid 1880. The DEM for Uganda and the digitized river networks are then uploaded in the ArcHydro tool in ArcGIS 9.3 to delineate the watersheds.

The GPS location for the various roads drainage crossings as determined during field visit are uploaded and superimposed on the delineated watersheds. Further onscreen digitization is done to clearly define the watersheds to respective road drainage points followed by determination of catchment parameters such as area, catchment length and slope, length of mainstream from the remotest point to the crossings, elevation differences and stream slope.

The four Districts of Mayuge, Iganga, Bugiri and Busia have two main drainage systems of Lake Victoria and Lake Kyoga.

The Lake Victoria drainage system consists of Lake Victoria, River Nalioba, Nasigombe-Nalwire- Hone and Sango-Sio. The Lake Kyoga drainage system is constituted by River Lumboka and River Malaba wetland system. Other wetland

Page 55: Final Detailed Design Report - Musita _ Majanji Road

32 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

systems can be traced in Mayuge District such as Lumbuye wetland system in Mpungwe Sub County and Kyankuzi wetland system in Baitabongwe Sub County.

The small streams inform of swamps and marshes cutting across the project road feed into these wetland systems. The area can therefore be summed as having wetlands and several networks of swamps.

There are both surface and underground water sources, wetlands and rivers forming part of the boundaries between villages, Sub Counties and/or Districts in form of valleys. (Busia District Local Government Three Year Development Plan 2008/9-2009/10).

2.5.8 Watershed Characteristics

The watersheds draining to project road have distinct characteristics largely due to their geographical location, climate and land use characteristics. The relatively common aspect is that the watersheds are intensively cultivated, human settled and predominantly rolling.

General Characteristics

The Musita-Lumino/Busia-Majanji roads are characterized by:

� Natural vegetation similar to tropical forest/ grassland. � Swampy areas � Tropical climate with rainfall having two seasons i.e. from March to

June and from September to November (Bimodal) � Agriculture (sugar canes, maize, cassava, sweet potatoes, millet and

sorghum), Cattle rearing and mining like gold, uranium, iron core, lake sand and oil.

The delineated catchments are given in Appendix 4.

According to Uganda Soil Map, the soil type of the project area are characterized as Ferrallitic soils (sandy loam and sandy clay loams) especially in lowland areas,

Soil Type

Ferrisols, Humid Ferrallitic and Halomorphic soils in areas surrounding Mt. Elgon.

The soils covering most of the project area are mainly loamy and sand loams with spots of clay at the valley areas. These soils have fine texture with rather loose structure, which are easily eroded and leached. The soil types can be summarized as;

� Yellow-red sandy, clay loam soils varying from dark grey to dark. These occur

on gently undulating –hilly topography. � Brown yellow clay loams with laterite horizon with a variety of dark brown to

dark grayish brown. These occur on flat ridge tops or as of undulating topography.

� Light –grey- white mottled loamy soils with laterite horizon ground, structures- less loamy sands. These are acidic-allocative and mainly found on lower and bottom slopes.

� Clay soils are limited to the swamps in the valleys. (Busia District State of Environment Report, 2005 and Bugiri District Development Plan 2009/10-2011/2012).

Page 56: Final Detailed Design Report - Musita _ Majanji Road

33 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Air T

empe

ratu

re (o

C)

Uganda has a typically tropical climate with little variation in temperature throughout the year. Distinctive wet and dry seasons characterize the climate of

Climate

Uganda. Uganda's equatorial climate provides plentiful sunshine, moderated by the relatively high altitude of most areas of the country. Mean annual temperatures range from about 16°C in the southwestern highlands to 25°C in the northwest; but in the northeast, temperatures exceed 30°C about 254 days per year. Daytime temperatures average about eight to ten degrees warmer than nighttime temperatures in the Lake Victoria region, and temperatures are generally about fourteen degrees lower in the southwest.

Except in the northeastern corner of the country, rainfall is well distributed. The southern region has two rainy seasons, usually beginning in early April and again in October. Little rain falls in June and December. In the north, occasional rains occur between April and October, while the period from November to March is often very dry. Mean annual rainfall near Lake Victoria often exceeds 2,100 mm, and the mountainous regions of the southeast and southwest receive more than 1,500 mm of rainfall yearly. The lowest mean annual rainfall in the northeast measures about 500 mm.

Available temperature data for the project area have been collected. Figure 7.1 provides the monthly Minimum, Maximum, and Average Temperature for the Jinja

Temperature

Meteorological Station.

35.0

30.0

25.0

20.0

15.0

10.0

5.0

0.0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Max. 29.1 30.1 29.1 28.1 27.6 27.3 27.4 27.9 28.4 28.7 28.3 28.3 Min. 17.0 17.4 18.0 17.9 17.7 17.1 16.4 16.4 16.8 17.2 16.9 16.6

Mean 23.1 23.7 23.6 23.0 22.6 22.2 21.9 22.2 22.6 22.9 22.6 22.5

Figure 14: Mean Monthly Maximum, Minimum and Average Temperature at Jinja Met. Station for the period (1999 – 2008)

Available rainfall data for the study area have been collected from the Department of Water Resources in Uganda. Table 14 presents the mean monthly rainfalls at

Rainfall

the Jinja and Ikulwe stations.

Page 57: Final Detailed Design Report - Musita _ Majanji Road

34 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

These rainfall stations were considered to have data of sufficient length that are important in deriving statistical information for the determination of the design rainfall at specific recurrence interval, covering a period of 39 and 22 years, respectively.

Table 14: Mean monthly rainfall (mm)

Months

Total

Station

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec Jinja 75.9 70.2 144.4 190.7 143.6 64.1 64.6 97.6 108.9 123.0 153.8 85.5 1322.2 Ikulwe 63.1 55.4 119.7 151.1 127.0 83.1 56.9 84.6 78.1 115.1 138.2 111.6 1184.0

Table 15 presents the maximum daily (24-hours) rainfall at the six stations. These rainfall stations were considered to have data of sufficient length that are important in deriving statistical information for the determination of the design rainfall at specific recurrence interval. The records for Jinja and Ikulwe cover 39 and 22 years respectively.

Table 15: Maximum daily rainfall data (mm)

Jinja Ikulwe Year Rainfall Year Rainfall Year Rainfall Year Rainfall 1960/61 1982/83 56.5 1960/61 57.0 1982/83 33.9 1961/62 1983/84 43.0 1961/62 62.0 1983/84 60.9 1962/63 1984/85 83.0 1962/63 60.0 1984/85 56.5 1963/64 1985/86 60.5 1963/64 45.3 1985/86 44.5 1964/65 1986/87 54.9 1964/65 62.5 1986/87 34.5 1965/66 1987/88 29.7 1965/66 36.0 1987/88 56.2 1966/67 1988/89 43.8 1966/67 1988/89 52.1 1967/68 1989/90 79.6 1967/68 1989/90 37.2 1968/69 1990/91 70.8 1968/69 1990/91 31.5 1969/70 87.4 1991/92 40.8 1969/70 1991/92 84.6 1970/71 89.8 1992/93 53.7 1970/71 1992/93 67.8 1971/72 101.3 1993/94 76.6 1971/72 1993/94 49.8 1972/73 69.9 1994/95 116.7 1972/73 1994/95 46.2 1973/74 46.4 1995/96 112.1 1973/74 1995/96 57.0 1974/75 60.5 1996/97 39.9 1974/75 1996/97 62.0 1975/76 111.0 1997/98 78.6 1975/76 1997/98 46.2 1976/77 72.9 1998/99 117.5 1976/77 1998/99 1977/78 60.4 1999/00 73.2 1977/78 1999/00 1978/79 67.0 2000/01 62.1 1978/79 2000/01 1979/80 78.0 2001/02 73.1 1979/80 2001/02 1980/81 68.5 2002/03 65.7 1980/81 2002/03 1981/82 57.6 2003/04 94.8 1981/82 2003/04

2004/05 99.7 2004/05 2005/06 103.4 2005/06 2006/07 85.1 2006/07 2007/08 47.5 2007/08 2008/09 2008/09

Table 16 presents the important statistics of the rainfall data from the two stations with the most reliable and long records.

Page 58: Final Detailed Design Report - Musita _ Majanji Road

35 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Rai

nfal

l (m

m)

Table16: The important rainfall statistics data Name

Station Code

Highest

(mm)

Lowest

(mm)

Mean

(μ) (mm)

Stdev ()

(mm)

Coef. of

Variation (Cv)

Coef. of

Skew (Cs)

Jinja Met. Station 89330430 117.5 0.0 72.6 22.7 0.3 0.970 Ikulwe Farm Institute 89330390 84.6 0.0 52.0 13.0 0.3 0.767

300

250

200

150

100

50

0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Months

Jinja Ikulwe

Figure 15: Mean Monthly Rainfall of the stations with good rainfall records

Existence of gauged stream flow data of sufficient length (at least 10 years), permits estimates of the peak discharge in terms of its probability of frequency of occurrence by employing statistical methods. In the study area, such data are not readily available, except for Manafa River that has some gauged data spanning for 11 years (1999-2009). The yearly maximum daily flow data were extracted from the daily time series for each year and analysed to estimate the flood design discharges at a specific return period (e.g. 100 years).

Stream flows

For un-gauged catchments, the rainfall data of the project surrounding area were used to compute design rainfall and used in the TRRL East African Food Model to estimate the design flood discharge at their corresponding delineated catchment crossing points. For catchments with no properly defined channels/streams, extrapolation of design flow was made using drainage area ratios provided the areas had similar characteristics and within the same metrological zone.

Page 59: Final Detailed Design Report - Musita _ Majanji Road

36 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

2.6 Swamp Investigations

The locations of swamps or marshy areas along the Musita-Lumino/Busia-Majanji roads were visited in order to provide a preliminary assessment of their likely impacts upon the design of these roads.

Along Musita-Lumino road 14 no. low lying marshy areas were identified. There are no swamps along the route.

2.7 Drainage Investigations

2.7.1 Assessment of Existing Drainage Structures

A visual assessment of the drainage structures was carried out by the Bridge/Drainage Engineer and the Hydrologist.

Each minor and major drainage structure was inspected and relevant basic measurements were taken. Data on hydraulic performance and history of any overtopping and history of rehabilitation measures undertaken were collected from local residents and branch of the ministry of works.

Moreover, observations were made relating to:

Hydraulic performance Physical condition Possible causes of damage Materials used for construction and their performance Period of service Possible reasons for poor performance Possibility of maintenance or repair Performance in respect to traffic safety Replacement options

A detailed photographic inventory and assessment of all the existing drainage structures are prepared following the field inspection. These schedules are included in Appendix 5A and 5B.

2.7.2 Classification of Drainage Structures

For the purpose of this project, all drainage structures are classified in two broad classes namely, minor and major drainage structures.

Minor Structures

Minor drainage structures are those pipes having single or multiple cell opening either made from concrete or corrugated metal sheet (Armco) and all the road side drainage facilities.

Major Structures

Structures included in Major Structure’s category are box culverts, slab culverts and reinforced concrete /composite/ steel / bridges.

Page 60: Final Detailed Design Report - Musita _ Majanji Road

37 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Slab culverts are those with top slab resting on abutments done separately, and box culverts are those having monolithic top slab, bottom slab and the vertical walls.

2.7.3 Side Ditches

Stone pitched side channels and flow checks are found along a certain sections of the project roads. Some are recently constructed and are in very good condition. But in general it is observed that due to lack of regular repair, water flows out of the channel damaged the road pavement and make it difficult for road users. Please refer to Appendix 5A for details.

2.7.4 Pipe Culverts

According to the structures inventory data, we found out that there are over 300 existing pipe culverts along all the project routes. The majority of the existing pipe culverts are made from either reinforced concrete with internal diameter ranging from 300mm to 1000mm or Armco sheet ranging from 600mm to 2000mm internal diameter. Please refer to Appendix 5A and 5B for details.

` During assessment of the drainage structures along the project route, the following major deficiencies or problems were observed at pipe culverts:

� Damaged or missing headwalls � Siltation in pipes due to low invert level � Poor workmanship at the head walls and at pipe joints. � Insufficient length of pipes as compared to the width of the road � Insufficient hydraulic capacity � Lack of regular cleaning � Missing or damaged aprons and energy dissipaters at inlets and outlets

2.7.5 Box Culverts

More than six box/slab culverts are found along the entire project route. Please refer to Appendix 5A for details.

The following major deficiencies or problems were observed at box/slab culverts during the assessment:

� Deteriorated slab concrete � Cracked, damaged abutments and wing walls � Insufficient hydraulic capacity � Eroded bank and scoured bed. � Damaged inlet and outlet aprons (either broken down or dislodged)

2.7.6 Bridges

All drainage structures where the top slab is exposed for direct contact to traffic wheel load regardless of their span are categorized as bridges. More than 10 bridges are identified for the entire project. The following table demonstrates the current condition of the existing bridges.

Page 61: Final Detailed Design Report - Musita _ Majanji Road

38 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

2.7.7 Existing Bridges

There are no existing bridges along Musita- Lumino road.

2.7.8 Summary

The following summary is made based on the assessment of drainage structures along the entire project roads.

Drainage is a major issue along the project roads and it is the prime factor for

the road damage. And almost in all cases existing drainage facilities are found inadequate.

A certain sections of the roads traverse through major flood plains and marshy

areas. And in most cases these roads are over-topped during the regular rainy season.

Inadequate opening size of most pipe culverts provided, forced the placement

of additional pipes by the side of the existing ones which has done little in alleviating the drainage problem but reducing the riding quality of the road.

Luck of enough cover over pipe culverts resulting either broken concrete pipes

or tiered Armco pipes

Insufficient length of structures provided resulting in narrow road section

Poor overall workmanship and lack of regular maintenance

Long year of service

Inadequate structural capacity

2.8 Environmental and Social Studies

2.8.1 General

An Environmental and Social Impact Assessment was carried out for the project roads and surrounding areas during 2010/2011, with a summary of the findings presented below.

Detailed assessment of the impacts upon the project and the mitigation measures are given in the Final ESIA Report.

2.8.2 Geographical Location

The Musita-Lumino/Busia-Majanja roads are situated in the Eastern part of Uganda. They traverse four already established districts of Mayuge, Iganga, Bugiri and Busia Districts and the newly approved District of Namayingo which is to be carved out of Bugiri District.

Page 62: Final Detailed Design Report - Musita _ Majanji Road

39 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

2.8.3 Biophysical Environment

The topography of the project area is relatively flat with high ridges and isolated hills, adulating lowlands and perch vents with a few higher residual features.

In terms of geology, the project area is made up of Precambrian rocks with bare granitic rocks at several places heavily eroded. The soils covering most of the project area are mainly loamy and sand loams with spots of clay at the valley areas.

It has two main drainage systems of Lake Victoria and Lake Kyoga. According to Busia District State of Environment Report, 2005.

The area has noted fluctuations in rainfall figures over the last seven years. In October-December 1997, Busia and the neighboring districts experienced heavy rains (El-Nino), with figures averaging ten times the normal and resulting in disastrous flooding.

The mean annual maximum temperature in the project area is 28.70C and the mean annual minimum is 16.20C. The mean monthly maximum is 270C, while the mean minimum sometimes falls to 160C especially at dawn (early morning).

The vegetation observed in the project area has undergone considerable changes and this can be attributed to continuous cultivation, burning or clearing for different purposes.

The project road is not very rich in faunal diversity given the level of interference inflicted upon the natural vegetation; the would-be in habitats of this diversity.

2.8.4 Socio-economic and Cultural Environment

According to the 2002 Population and Housing Census, the total population in the 16 Sub Counties through which the road traverses is 123,669 persons of which 59,271 are males and 64,398 are females and the average household size is 5 persons.

The results indicate that the general literacy levels within the project area are very low as the majority of the households (49.6%) did not exceed primary level.

The majority of the households (80.3%) along the road in all the four districts are married while 19.7% are not married.

The major ethnic groups in the project area are Basoga (45.4%), Basamia (26.8%), Banyole (12.5%), Japadhola (4.4%), Iteso (3.1%), and Bagwere (2.5%). Other ethnic groups in the area include Baganda, Bagisu, Badama, Bakenye and Lugbara.

As regards religion, the majority of the population in the four districts belongs to the Anglican/protestant and Moslem religions followed by Catholics.

The most common land tenure system in the project area is customary. The land is comprised of farming land, settlements, manmade forests and swamps. In terms of size, the results indicate that the average land size owned by the households in the project area is 2 acres.

The predominant economic activity is subsistence agriculture. The main crops grown include maize, rice, sugarcanes, bananas, cassava, sweet potatoes and

Page 63: Final Detailed Design Report - Musita _ Majanji Road

40 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

beans. The main cash crops are cassava, rice and sugarcanes. According to the household survey, the average monthly income for households in the project area is UGX 163,300 while the average annual income is UGX 1,908,000.

Most (36%) of the households in the project area are temporary made of mud and wattle, 35.6% are semi permanent and 28.4% are permanent. Most of the permanent structures are found in trading centres.

The main source of water is public boreholes 56.5%, followed by protected springs/wells (19.9%), 15.7% depend on unprotected springs/wells, 2.9% depend on privately owned boreholes. Other water sources include stand posts, valley tanks/earth dams and others buy from water vendors.

2.8.5 Predicted Environment and Social Impacts

There are several positive impacts that might accrue as a result of the upgraded the road and these include the following:

Creation of job opportunities to the local unskilled persons as well as

skilled persons in the community. Improved accessibility to markets. Easy and comfortable transportation. Improved transport and communication after construction of the road. Improved market for locally available resources needed for road

construction e.g. stones, sand, gravel among others. Land value appreciation Increased retention of qualified personnel Increase beauty of the area. Increased trade between districts, regions and Kenya. Improved road drainage infrastructure and general discharge of storm

water from the road/carriageway.

However a number of negative impacts were also identified as described below.

Biophysical impacts will include increased noise, deterioration of air quality, aesthetics, vegetation clearing ,forest degradation in areas as in Kyebando- Mayuge,Mpumu and Lumino having planted forests of bamboo, pines and ornamental trees by the road side, impacts from quarrying and gravel mining activities.

Social impacts identified include high social expectations, loss of structures which will include graves, about 1,561 structures which are temporary, semi permanent and permanent in nature. In addition, several institutions will also be affected through loss of land, structures and these include about 51 educational institutions, 13 health centres, and religious places among others. The acquisition of about 1,285 acres of land will lead to loss of land for many households and this will greatly affect their livelihood as the majority depends on agriculture as the main source of income. Note: The actual number of affected property will be established during the preparation of the Resettlement Action Plan.

Other potential negative impacts include the influx of people especially during the construction. This will bring about an increase in the spread of sexually transmitted diseases like HIV/AIDS, syphilis, gonorrhea among others, increased stress on social services like education, water and health. Community or public infrastructure like water sources, electricity lines will be disrupted.

Page 64: Final Detailed Design Report - Musita _ Majanji Road

41 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

However, all the social impacts represent a potentially more serious effect of the project. All impacts of the project have however been found to be manageable provided mitigation measures which have been proposed are implemented.

Table 17 below shows the predicted negative environmental and social impacts without mitigation.

Table 17:Overall Impact Assessment

Study Value/vulnerability of the Environment Component

Magnitude of impacts Overall impact Assessment (without mitigation measures)

Scale Low/Med./High

-♦-

Negative Positive High Medium Little/No Med. High

Planning Phase

Social Expectations -♦- -♦- Large negative impact(---) Land use -♦- -♦- Medium negative (--) Construction Phase

Employment -♦- -♦- Medium positive (++) Increased market -♦- -♦- Medium positive (++) Soil erosion -♦- -♦- Minimal/No impact (0)

Installation of road furniture

-♦- -♦- Medium positive (++)

Aesthetic value -♦- -♦- Small negative (-) Waste generation

(soil &vegetation material and other solid waste)

-♦- -♦- Medium negative (--)

Potential cont. of water sources

-♦- -♦- Minimal or No impact (0)

Drainage & wetlands

-♦- -♦- Minimal or No impact (0)

Air quality -♦- -♦- Medium negative (--) Noise -♦- -♦- Large negative (---) Impacts of quarry

devt. -♦- -♦- Large negative (---)

Vegetation & forests

-♦- -♦- Small negative (-)

Disruption of wildlife

-♦- -♦- Minimal or No impact (0)

Influx of people -♦- -♦- Medium negative (--) Increased STDs &

HIV/AIDS Medium negative (--)

Displacement & loss of housing

-♦- Large negative (---)

Page 65: Final Detailed Design Report - Musita _ Majanji Road

42 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Study Value/vulnerability of the Environment Component

Magnitude of impacts Overall impact Assessment (without mitigation measures)

Scale Low/Med./High

-♦-

Negative Positive High Medium Little/No Med. High

Land acquisition -♦- -♦- Large negative (---) Educational -♦- -♦ Medium negative (--) vulnerable groups -♦- -♦- Medium negative (--) Disruption of

water supply -♦- -♦- Medium negative (--)

Disruption of other infrastructure

-♦- -♦- Medium negative (--)

Agriculture -♦- -♦- Large negative (---) Health and Safety -♦- Medium negative (--) other economic

activities -♦- -♦- Small negative (-)

Impact on Gender -♦- -♦- Medium negative (--)

Cultural Heritage -♦- -♦- Small negative Operational and Maintenance (O&M)

Transport & com. -♦- -♦- Large positive (++) Staff retention -♦- -♦- Small positive (+) Land appreciation -♦- -♦- Medium negative (++) Access to HC -♦- -♦- Small positive (+) Loss of livelihood -♦- -♦- Minimal or No impact (0) Community

conflicts -♦- -♦- Minimal or No impacts (0)

Increased Accidents

-♦- -♦- Medium negative(--)

Air pollution from bitumen during re- surfacing

-♦- -♦- Medium negative (--)

Poor silt disposal -♦- -♦- Medium negative(--)

Details of proposed mitigation measures are detailed in the Final ESIA Report.

Page 66: Final Detailed Design Report - Musita _ Majanji Road

43 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

3 DETAILED DESIGN 3.1 Geometric Design

3.1.1 Introduction

In developing the design for the upgrading of Musita-Lumino and Busia-Majanji roads, the objectives as set out in the Terms of Reference were considered in detail.

A number of alignment options were developed with due regard to the following considerations;

� Design manual criteria

� Balance between cut and fill

� Minimise land take

� Affordable and acceptable accommodation works for frontages

� Minimise utility protection/relocation

� Avoid geological, hydrological and environmental problems

� Avoid extensive and expensive bridge works

� Protect vulnerable road users

� Provide in-build safety measures

� Provide adequate road users facilities

The resulting alignment options were further assessed by our resettlement and land acquisition team and discussed extensively with the Client before a final option was approved and considered for detailed design.

3.1.2 Design Standards

The geometric design of the project road was carried out as per the guidelines contained in the Ugandan MoWH&C Road Design Manual of July 2005. This was in accordance with the requirements of the TOR, and as confirmed by UNRA. The Manual was complimented by recognized design manuals from neighboring counties including;

� Kenya’s Road Design Manual – Part 1: Geometric Design Manual

� Tanzania’s Draft Road Manual

� Code of Practice for Geometric Design (SATCC-1998) – Trunk Road

Design Standards

Page 67: Final Detailed Design Report - Musita _ Majanji Road

44 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Lot E roads have been packaged into the following contracts;

1. Package 1: Road E1.1 Musita-Lumino and Road E1.2 Busia – Majanji

2. Package 2A: Road E2.1 Tirinyi – Pallisa and Road E2.2 Pallisa – Kumi

3. Package 2B: Road E2.3 Pallisa – Kamonkoli

4. Package – 3: Road E3 Bumbobi - Bubulo – Busumbu – Lwakhakha

5. Package – 4: Road E4 Namagumba – Budadiri – Nalugugu

6. Package – 5: Road E5 Kamuli - Bukungu

Package 1 comprises two links, Musita – Lumino and Busia Majanji.

The Musita – Lumino link starts from Musita trading center along the Jinja-Iganga highway. It continues on an eastwards direction passing through Mayuge, Nankona, Buyinja and ends at Lumino trading center.

The Busia – Majanji link commences at Busia town continuing southwards through Dabani, Masafu Lumino and ending at Majanji on the shores of Lake Victoria.

The project road is an alternative link between Jinja and Busia town and also serves as a link to a number of landing sites along Lake Victoria including Majanji, Lufudu, Omenya, Wakawaka and Kigandala. From Lumino, one can also access Lwanda border post which has been earmarked for upgrading by Uganda Revenue Authority (URA).

On the basis of the Design Manual, the project road can be classified as Class C or a Primary road. These are described as roads linking provincially important centers to each other or to a higher class roads (urban/rural centers). They provide linkage between districts, local centers of population and development areas with higher class road. Their major function is to provide both mobility and access

A paved Class II road standard was adopted for the geometric design of the project road; the applicable geometric design standards for which are presented in Figure 4.2a and 4.2b of Section 4 of the Design Manual and reproduced below as Table 18 and Table 19 for ease of reference.

Page 68: Final Detailed Design Report - Musita _ Majanji Road

45 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Table 18: Road Design Classes

Design Class

Capacity

[pcu x 1,000/day]

Road-way width[m]

Maximum Design speed

Kph Functional

Classification

Level Rolling Mountainous A B C D E Ia Paved 12 - 20 20.80-24.60 120 100 80 √ Ib Paved 6 – 10 11.0 110 100 80 √ √ II Paved 4 – 8 10.0 90 70 60 √ √ √ III Paved 2 – 6 8.6 80 70 50 √ √ √ A Gravel 4 – 8 10.0 90 80 70 √ √ √ B Gravel 2 – 6 8.6 80 60 50 √ √ C Gravel 6.4 60 50 40 √

Table 19 : Road Design Classes (continued)

Design class Right of Way

width [m]

Road way width [m]

Carriage way Shoulder width [m]

Median width [m]

Width [m]

Lane width [m]

No. of lane

Ia Paved 60 20.80-24.60 14.6 3.65 4 2 x 2.5 1.2 – 5.0 Ib Paved 60 11.0 7.0 3.5 2 2 x 2.0 - II Paved 50 10.0 6.0 3.0 2 2 x 2.0 - III Paved 50 8.6 5.6 2.8 2 2 x 1.5 - A Gravel 40 10.0 6.0 3.0 2 2 x 2.0 - B Gravel 30 8.6 5.6 2.8 2 2 x 1.5 - C Gravel 30 6.4 4.0 4.0 1 2 x 1.2 -

3.1.3 Design Speed

The road sections between Musita and Lumino and Busia – Majanji has been classified as flat, having gradients not exceeding 5.5%. A design speed of 90 kph has been recommended as per the Design Manual Table 6-15. It should however be noted that many sections of the existing road are long and straight and higher speeds than these will be possible.

Through the more populated centres along the route, the design speed of 90 kph has been maintained for the selection of appropriate geometric elements, however the posted speed limit of 50 kph has been set for pedestrian safety.

Table 20 is a schedule of centers where it has been proposed that the traffic speed be regulated through the installation of road signage, speed bumps and rumble strips. Other centres noted along the project road and for which the

Page 69: Final Detailed Design Report - Musita _ Majanji Road

46 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

design speed may only be regulated by installing appropriate traffic signs are listed in Table 20 below.

TABLE 20 - SECTIONS WITH DESIGN SPEED OF 50 Km/h REGULATED BY BUMPS AND RUMBLE STRIPS

Road E 1.1 Musita-Lumino

FROM TO LOCATION Km 0 + 000 Km 0 + 400 Musita Bypass Km 12 + 800 Km 14 + 000 Mayuge Township Km 35 + 100 Km 37 + 500 Nankoma Township Km 46 + 900 Km 48 + 600 Muterere Km 50 + 500 Km 52 + 100 Bukoli Km 56 + 500 Km 57 + 600 Namavundu Km 62 + 400 Km 63 + 500 Buyinja

Road E1.2 : Busia-Majanji

FROM TO LOCATION Km 0 + 000 Km 1 + 300 Busia Town Km 5 + 800 Km 6 + 500 Dabani Km 7 + 800 Km 9 + 300 Masafu Km 19 + 100 Km 19 + 600 Lumino Km 26 + 500 Km 26 + 732 Majanji

TABLE 21 – SECTIONS WITH 50Km/h REGULATED SPEED USING ONLY TRAFFIC SIGNS

Road E1.1 : Musita-Lumino

FROM

TO

LOCATION

Km 1 + 700

Km 2 + 600

Lugolole

Km 6 + 000

Km 6 + 500

Bufulumbi

Page 70: Final Detailed Design Report - Musita _ Majanji Road

47 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Km 16 + 300

Km 16 + 800

Maina

Km 20 + 200

Km 21 + 300

Mpunge

Km 26 + 100

Km 26 + 600

Bunalwenyi

Km 30 + 100

Km 30 + 700

Bwamula

Km 32 + 700

Km 33 + 600

Itakaibolu

Km 41 + 200

Km 42 + 000

Namabingo.

Km 66 + 700

Km 67 + 300

Lunyo

Km 72 + 200

Km 72 + 500

Bwaniha

Road E1.2 : Busia-Majanji

FROM TO LOCATION Km 13 + 700 Km 14 + 600 Mailo Eight Km 15 + 700 Km 16 + 100 Mailo Seven

Given these design speeds, the horizontal alignment adopted has been chosen to suit the topography and minimize overall cost, whilst the vertical alignment is very much governed by drainage requirements and the need to raise embankments at low lying areas or wetlands.

3.1.4 Design Departures

The design speed and the recommended geometric elements were adopted as much as possible, however in sections where the terrain required expensive and uneconomical earthworks or the resulting cost of acquisition became too high, design departures were recommended.

As stated above both Musita – Lumino and Busia – Majanji roads can be classified as flat with a recommended design speed of 90 km/h.

However along the Musita – Lumino road at Km 0+250 a horizontal curve of 200m radius has been proposed as opposed to the minimum of 320m recommended for a 90 km/h. This has been done to provide a straight approach to the main junction with adequate sight distance. This has been mitigated by recommending 50 km/h speed limit signs.

Page 71: Final Detailed Design Report - Musita _ Majanji Road

48 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Between Km 44+700 and 45+900 a steep grade of 6.7% is encountered. It has therefore been necessary to reduce the design speed at this section to 70 km/h in order to save on expensive earthworks that may be required to maintain a 90 km/h design speed over the section.

3.1.5 Cross-Section

The Road Design manual proposes a cross section of 3m lanes and 2m shoulders totaling 10m for a Design Class II Paved road. This is presented in Table 4-2b of the manual. However, in consideration of safety, the anticipated traffic growth and further consultations with UNRA, it was agreed that a cross section comprising 3.5m lanes and 1.5m shoulders in the rural areas and 2m in Urban/Trading areas be adopted for the project road..

Additional separated Service Lanes and Pedestrian walkways have been proposed at locations given in Table 22 below:

TABLE 22 – SECTIONS WITH PEDESTRIAN WALKWAYS

FROM TO LOCATION Km 12 + 800 Km 14 + 000 Mayuge Township Km 35 + 100 Km 37 + 500 Nankoma Township Km 46 + 900 Km 48 + 600 Muterere Km 50 + 500 Km 52 + 100 Bukoli Km 56 + 500 Km 57 + 600 Namavundu

3.1.6 Embankment Design

In order to reduce earthworks and shoulder works to a minimum, the following embankment slopes have been proposed

� for fill height hf < 1 m = 1:4 (vertical:horizontal)

� for fill height hf > 1 m = 1:2

� for cut height hc < 1 m = 1:2

� for cut height hc > 1 m = 1:2

Page 72: Final Detailed Design Report - Musita _ Majanji Road

49 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

It should be noted, however, that such an approach does have safety ramifications. From a safety perspective side slopes of 1 in 6 for embankment are recommended to reduce the likelihood of vehicle overturning. In terms of stability, a slope of 1 in 2 is stable for the embankments heights proposed for the project.

The steeper slopes tend to perform better in terms of erosion, as the quantity of water landing on the slope during rain is less. The water running off the road clearly travels faster down the slope and causes an erosion channel, probably more so than on a flatter slope. Where this occurs, chutes are to be provided to cater for the run-off.

It has also been recommended that the pavement layer construction should be extended to cover the full width of the shoulders in order to meet the following principal objectives:

(a) to enable heavy goods vehicles to pass each other safely making use of the

full road width;

(b) to make provision for the high level of cycle and pedestrian traffic along the project road; and

(c) to prevent damage to and erosion of the shoulder and carriageway edge.

3.1.7 Adopted Design Parameters and Standards

The following parameters and standards have been adopted in the designs:

Design life: 20 years.

Cross-section: 7.0 m wide carriageway at 2.5% normal camber (3% at flat sections)

2.0 m wide shoulders at 4.0 % normal crossfall

1.0 m wide side drain.

Design Speed Parameters:

Design Speed

90 Km/h

70 Km/h

Min. Horizontal Radius

320 m

185 m

Max. Superelevation

7%

Max Gradient (Absolute)

5.5%

7.5%

Page 73: Final Detailed Design Report - Musita _ Majanji Road

50 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Rate of Change of Superelevation

0.4-0.6 max

Minimum Crest Curve Kmin (stopping sight distance)

71

31

Design Speed

90 Km/h

70 Km/h

Minimum Sag Curve Kmin

41

25

Stopping Sight Distance (SSD)

170 m

111 m

Passing sight Distance

750 m

550 m

3.1.7 Summary of Adopted Design Speeds

Musita – Lumino:

Km 0+000 – 44+700: Flat terrain - Design speed = 90 km/h

Km 44+700 – 45+900: Rolling terrain – Design speed = 70 km/h

Km 45+900 – 77+140: Flat terrain – Design speed = 90 km/h

Busia – Majanji:

Km 0+000 – 26+811: Flat terrain – Design speed = 90 km/h

3.1.8 Design Road Alignment

3.1.8.1 General

The geometric characteristics of the existing road alignment were obtained from ground data capture generated from aerial photography surveys.

During this exercise, control points were established alongside the road. This data was ultimately tied onto the National grid system. Ground data capture was generated at 5 m square grids and covering a corridor of 35m either side of the existing centreline. This data was then imported into AutoCAD Civil 3D software to generate a digital ground model of the route corridor.

A geometric record of the plan and profile of the existing road, both for the assessment and creation of a model to act as the basis for the alignment designs were then carried out.

Page 74: Final Detailed Design Report - Musita _ Majanji Road

51 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

3.1.8.2 Selection of Alignment

The following principles were adopted during selection of the appropriate alignment for the preliminary design:

� Conformity to the specified geometric design parameters.

The alignment was designed to conform to or surpass the geometric design parameters as recommended in the design manual.

� Follow the general corridor of the existing road.

The general approach to the route alignment was to use the corridor of the existing road as much as possible. This was done to retain the present social function with minimum disruption to existing and long-term residents. Minor realignments were however introduced to improve the road geometry and remove potentially dangerous curves. This was also done at locations of new bridges.

� Keep the works within the existing right of way.

In most sections, the alignment design was carried out to follow the existing road as much as possible to enable the use of existing pavement materials to form new a subgrade.

� Improve junctions.

In order to improve safety at the approach junctions, the project road has been realigned to approach the main highway at a right angles.

� Re-align at trading centres.

There are a number of large trading centers along some of the project roads with heavy population and agricultural activities. The possibility of having a bypass at some of these centers was investigated. Preliminary realignments outside the centers were designed. These were then presented to the Resettlement and Land Acquisition specialist who also visited the project road to evaluate the impact of the bypasses against keeping the alignment through the centers, compensating where necessary and maintaining the current social function of the road.

A section-by-section description of the existing road features and proposed realignments follows.

3.1.9 Alignment Details

3.1.9.1 Road E1.1 : Musita-Lumino

(A) Horizontal Alignment

Page 75: Final Detailed Design Report - Musita _ Majanji Road

52 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

(1)

Realignment of the junction at Musita (Km 0 + 000 to Km 0+400)

The project road joins the Jinja – Iganga highway at a skew angle. The taxis stop at the junction to pick up passengers and despite the provision of deceleration and acceleration lanes, the junction still remains a safety hazard.

In order to improve safety at the approach junction, the following solution has been proposed:

� The project road has been realigned to approach the main highway at a

right angle with the junction some 200m from the existing junction;

� Care was taken to locate the realignment where there would be minimal compensation and affected buildings;

� A 6 m wide service road with 1 m shoulder has been proposed for Musita

trading center, however to restrict motorist from joining the main road through this access road it has been proposed that it be blocked at the current junction by constructing a deep lined-side drain.

� A right-turn lane has been provided to enable safe maneuver of heavy

goods vehicles. Acceleration and deceleration lanes have also been provided and appropriate taxi-bays.

(2) End of Musita Bypass to the start of Lumino Bypass

(Km 0+400 to Km 76 + 400)

The existing alignment along this section of the road is generally has long straights with gentle curves. A roundabout has been proposed at Mayuge Km 13+166 to improve the traffic flow at the four intersecting roads.

A bypass was initially proposed between Km 12+800 to 15+100. A review of the proposed bypass by the Resettlement and Land Acquisition Specialist revealed that it impacted a health center at Km 12+800 together with several buildings, a mosque and a church at Km 13+400 and a heavily populated area with homesteads and cultivated land. It was agreed that the alignment be passed through the available 25m ROW through the center, set the Right of Way at 30m and at least compensate for the affected structures on one side.

Mayuge

Nankoma A bypass was proposed from Km 34+750 to 37+200. It was found to impacted Nankoma Primary school, Nankona HC-IV including a new outpatient department as well as buildings and cultivated land.

After confirming that the existing road corridor within the town was between 22 to 29m, it was agreed that the centreline be passed through the town and affected structures be compensated.

Page 76: Final Detailed Design Report - Musita _ Majanji Road

53 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

The proposed bypass at this center was between Km 56+100 to 58+100. It was found to impact Kifuyo CoU Primary School as well as a church and many

Namavundu

homesteads. The existing road corridor within the town was found to vary between 24 to 30m. It was therefore agreed that the alignment be passed through the town and after fixing the ROW at 30m, the affected structures be compensated.

(3)

Lumino By-pass (Km 76 + 400 to Km 77 + 129)

The existing road through Lumino trading center is very narrow and inappropriate for the anticipated high volume of traffic and pedestrian safety.

A bypass has been proposed to connect to the Busia – Majanji road at a right angle improving the visibility splay at the junction and road user safety. A roundabout has been recommended for this junction to provide a link connecting to the existing Lumino-Lwanda road.

A service road comprising 6 m carriageway and 1 m shoulders have been proposed to serve the shops and the business community at Lumino.

(4)

Lwanda Link Road

A link road connecting to the existing Lumino – Lwanda road from the end of the Musita – Lumino road has been proposed. This is in anticipation of the soon-to-be expanded Lwanda border post.

(B) Vertical Alignment

The terrain along the Musita – Lumino road can be classified as follows;

� Km 0+000 – 44+700: Flat – Recommended design speed = 90 kph

� Km 44+700 – 45+900: Rolling – Recommended design speed = 70 kph

� Km 45+900 – 77+140: Rolling – Recommended design speed = 90 kph

The digital terrain model (DTM) generated from survey data was used to produce the existing ground profile along the centreline of the horizontal alignment.

A vertical alignment was then designed to comply with the recommended design speeds and the vertical profile parameters as provided for in the Geometric Design Standard for Type II paved road.

(C) Gradients

Km 0+000 – 44+700

Page 77: Final Detailed Design Report - Musita _ Majanji Road

54 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

The terrain between Km 0+000 and 64+000 of the project road is generally flat with gradients between 0.0 and 5.2%, however the section from Km 44+780 and 45+880 has a steep drop with a gradient of 6.7%. This is still within the recommended maximum gradient for rolling terrain.

Km 44+700 – 45+900

The section has a steep drop of 6.7% grade and can therefore be classified as rolling. This has necessitated a design departure as earlier discussed.

Km 45+900 – 77+140

The road section between Km 45+900 and 73+700 is generally flat with gradients ranging between 0.5 and 5.0%.

3.1.9.2 Road E1.2 : Busia-Majanji

(A) Horizontal Alignment

No major realignment has been proposed for this road. The existing alignment has gentle curves which accommodated the design parameters. A roundabout has been proposed at the start of the project along the Busia – Iganga road to control the traffic flow from the border post, Tororo and Iganga.

A second roundabout has been proposed for the junction at Lumino to control the traffic to Lumino center, Majanji and Lwanda.

At Majanji the administration had earlier requested the design consultant to consider extending the project road upto the existing landing site which has recently been rehabilitated. On subsequent discussions with UNRA, it was agreed that the request be considered.

The road section ends at Km 26+847.

(B) Vertical Alignment

Km 0+000 – 26+847

As mentioned before, the terrain over this road section is generally flat with gradients ranging from 0.0 to 4.1%.

Details of the horizontal and vertical alignment design for the entire project are presented in -

3.1.10 Low Lying Area

The project route traverses substantial stretches of lowlying areas nd marshland. The upgraded road has been designed to have an embankment

Page 78: Final Detailed Design Report - Musita _ Majanji Road

55 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

height of at least 2.5 m in height to minimize the effects of water rising up beneath the sealed pavement through capillary action. The embankments supporting the existing gravel surfaced road are generally only one to one and a half metres in height.

The wetlands and low lying areas were noted at the following sections of Musita – Lumino road:

From Km

To Km

Length (m)

DESCRIPTION

SOIL TYPE

4 + 900

5 + 200

300

Marsh Silty/Sandy Clay

6+650

7+350

700

Marsh Silty/Sandy Clay

10+400

10+600

200

Marsh Silty/Sandy Clay

15+800

15+950

150

Marsh Silty/Sandy Clay

18+700

18+900

200

Swamp(seasonal) Silty/Sandy Clay

19+600

19+800

200

Marsh Silty/Sandy Clay

21+050

21+150

100

Marsh Silty/Sandy Clay

22+250

22+400

150

Marsh Silty/Sandy Clay

23+700

24+200

500

Marsh Silty/Sandy Clay

28+550

28+870

150

Marsh Silty/Sandy Clay

34+100

34+600

500

Marsh Silty/Sandy Clay

37+650

38+050

400

Marsh(Rice Paddies)

Silty/Sandy Clay

40+000

40+400

400

Marsh(Rice Paddies)

Silty/Sandy Clay

54+050

54+150

100

Marsh Silty/Sandy Clay

54+800

54+950

150

Marsh Silty/Sandy Clay

Along Busia – Majanji road, the following low lying areas were identified:

Page 79: Final Detailed Design Report - Musita _ Majanji Road

56 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

� Km 6+800 – 7+100 : 300m

� Km 14+750 – 12+000 : 250m

� Km 17+250 – 17+500 : 250m

� Km 21+400 – 21+700 : 300m

3.1.11 Junctions and Accesses

Intersections have been proposed as per the Design manual guidelines as well as considering the traffic flows and the design speed.

The following intersections/junctions have been proposed for Musita – Lumino link. In addition, several access junctions providing access to properties adjacent to the project road have also been proposed.

CHAINAGE

SIDE

JUNCTION TYPE

DESCRIPTION

Km 0+000

START

Type-C

Start of the Project road

Km 0+140

LHS

Type-B

Access to Musita

Km 2+100

CROSS

Type-A

At Lugolole

Km 13+166

R/ABOUT

Type-D

At Mayuge

Km 20+925

CROSS

Type-A

At Mpuge

Km 26+210

CROSS

Type-A

At Bunalwenyi

Km 30+490

LHS

Type-A

At Bwamula

Km 35+800

LHS

Type-A

To Buwunga

Km 36+160

RHS

Type-A

At Nankoma

Km 47+470

CROSS

Type-A

At Muterere

Km 51+540

LHS

Type-A

At Bukoli

Km 63+300

LHS

Type-A

To Bulesa

Km 63+300

RHS

Type-A

To Lugala

Page 80: Final Detailed Design Report - Musita _ Majanji Road

57 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Km 66+760

RHS

Type-A

At Lunyo

Km 76+670

LHS

Type-B

To Lumino

Km 77+129

R/ABOUT

Type-D

At Lumino

Along the Busia – Majanji road intersections have been proposed at the following

locations:

CHAINAGE

SIDE

JUNCTION TYPE

DESCRIPTION

Km 0+000

START

Type-D (roundabout)

At Busia

Km 19+660

RHS/LHS

Type-D (roundabout)

To Musita/Lwanda

Km 26+732

RHS

Cross junction

To Landing site

3.1.12 Footpaths, Busbays and Road Furniture

3.1.12.1 General

Segregated 2m wide footpaths/cycle paths are proposed at trading centres with high level of non-motorized traffic (NMT) and pedestrian traffic.

The footpaths/cycle paths will be separated from the main carriageway and shoulders by an open Invert Block Drain (IBD).

Bus bays will be provided at all trading centres, near institutions (e.g. schools, colleges, health clinics, etc) and near all major junctions.

Traffic calming measures including rumble strips, bumps and appropriate warning signs will be provided where considered necessary to enhance safety.

3.1.13 Service Roads

Due to ROW constraints and safety requirements, the horizontal alignment has been designed to bypass both Musita and Lumino trading centers. In order to access these centers 6m wide access roads with 1m shoulders have been proposed as follows:

� Musita – 460m � Lumino – 588m

Page 81: Final Detailed Design Report - Musita _ Majanji Road

58 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

In addition, service roads have also been proposed at the following trading centers to minimise conflict between local traffic and through traffic. Table below lists the locations and centres where service roads are proposed.

Location

Position

From Km

To Km

Length (m) MAYUGE LHS

RHS 13+300 13+300

13+900 13+900

600 600

NANKOMA LHS RHS

35+200 35+200

36+000 36+000

800 800

MUTERERE LHS RHS

47+250 47+250

47+800 47+800

550 550

BUKOLI LHS RHS

50+800 50+800

51+400 51+400

600 600

NAMAVUNDU LHS RHS

56+800 56+800

57+500 57+500

700 700

TOTAL 6,500

Along the Busia – Majanji section service roads have been proposed at Busia town and Majanji trading center.

3.1.14 Climbing Lanes

3.1.14.1 Introduction

The need for Climbing Lanes has been assessed using guidelines contained in the Kenya’s Road Design Manual Part 1: Geometric Design of Rural Roads.

The Manual stipulates that Climbing lanes should be introduced where longitudinal gradients are long enough and steep enough to cause significant increase in speed difference between cars and heavy vehicles.

In assessment of the need for a Climbing Lane the following guidelines are considered:

i. Climbing lanes are NOT required for roads with AADT < 2000 p.c.u. in

Design year 10 and in all Class D(secondary) and E(minor) roads even if AADT exceeds 2000 p.c.u. in Design Year 10.

ii. Where passing opportunities are limited on the gradients, then Climbing

lanes must be considered on all A(International trunk roads),B(National trunk roads) and C(primary roads) Class roads with AADT between 2000 and 6000 p.c.u.

iii. Climbing Lanes is required on roads with AADT>6000 in Design Year 10.

Page 82: Final Detailed Design Report - Musita _ Majanji Road

59 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

3.1.14.2 Assumptions and Application

Where Climbing lanes are required, they shall be introduced as follows:

� In Class A roads, where the speed of a typical heavy vehicle falls by 15 kph from that speed which the same vehicle would maintain in a level or downhill section of the same road.

� In Classes B and C roads they are applied where speed drops by 20 kph. � For design purpose, it may be assumed that the highest obtainable speed

on a level or downhill section of road for a typical heavy vehicle will be 80% of the Design Speed or 80 kph whichever is the lower.

� Climbing lane shall be terminated when the speed of a typical heavy vehicle reaches the speed at which the Climbing lane was introduced.

� Where Climbing Lanes are required, the widths of the traffic lanes and adjacent shoulders shall be reduced.

� The introduction and termination of a Climbing lane shall be effected by tapers of 60m but this not considered as part of the Climbing Lane.

� The start and end of Climbing lane section is calculated based on the performance of a typical heavy vehicle of power to weight ratio 90 kg/h.p. on various gradients.

� For the Year 10 Design traffic in p.c.u., the highest forecast traffic flow for each road section was used and converted to p.c.u. using conversion factors listed in Chapter 3 page 3.9 and considering rolling terrain of the Kenya Design Manual Part 1.

i. Passenger cars – 1.0 ii. Light Goods vehicle – 1.5 iii. Medium Goods Vehicle – 5.0 iv. Heavy Goods vehicle – 8.0 v. Buses – 4.0

3.1.14.3 Assessment of Climbing Lane Need

Lot E roads have been assessed based on Class C road as specified in the Kenya Design Manual.

ROAD E1.1: MUSITA – LUMINO

� Road Class C � Year 10 Traffic = (4x34+1.5x342+5x812+8x44) = 5061 p.c.u. in Year 20

(2030) � Need for CL evaluation = Yes � Assume Design Speed = 90 km/h

Page 83: Final Detailed Design Report - Musita _ Majanji Road

60 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

� Typical heavy vehicle speed on level or downhill section = 80% of 90 km/h = 72 km/h

� CL to be introduced when heavy vehicle speed drops to = 72 – 20 = 52 km/h

FROM (Km)

TO (Km)

LENGTH (m)

SLOPE (%)

DISTANCE TO START OF CL (m)

MINIMUM LENGTH

OF CL (m)

COMMENT

3+800 4+900 1100 4 400 700 Provide 900m Climbing Lane-LHS?

10+800 11+240 440 5 300 140 Not Economical 16+000 16+400 400 4 400 NA Not required 16+900 17+400 500 4 400 100 Not Economical 21+200 21+500 300 4 400 NA Not required 27+700 28+100 400 4 400 NA Not required 30+000 30+360 360 5 300 60 Not Economical 30+600 30+900 300 4 400 NA Not required 30+900 31+300 400 5 300 100 Not Economical 31+000 31+300 300 5 300 NA Not required 31+400 32+000 600 4 400 200 Not Economical 39+500 40+000 500 5 300 200 Not Economical 40+500 41+200 700 4 400 300 Not Economical 43+300 44+500 1200 4 400 800 Provide 1000m

Climbing Lane- LHS

44+700 46+000 1300 7 200 1100 Provide 1400m Climbing Lane-

RHS 46+100 46+600 500 4 400 100 Not Economical 55+100 55+600 500 4 400 100 Not Economical 58+800 59+200 400 4 400 NA Not required 76+700 77+000 300 5 300 NA Not required

Page 84: Final Detailed Design Report - Musita _ Majanji Road

61 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

ROAD-1.2: BUSIA – MAJANJI

� Road Class C � Year 10 Traffic = (4x15+1.5x360+5x134+8x11) = 1358 pcu in Year 20

(2030) � Need for CL evaluation = No � Assume Design Speed = 90 km/h � Typical heavy vehicle speed on level or downhill section = 80% of 90

km/h = 72 km/h � CL to be introduced when heavy vehicle speed drops to = (72 – 20) = 52

km/h

FROM (Km)

TO (Km)

LENGTH (m)

SLOPE (%)

DISTANCE TO START OF CL (m)

MINIMUM LENGTH

OF CL (m)

COMMENT

10+600 10+840 240 4 400 NA Not required 16+800 17+340 540 4 400 140 Not Economical

3.2 Pavement Design

3.2.1 Introduction

The project roads are intended to be upgraded to bitumen standard with 7.0m carriageway and 2.0m wide shoulders both sides.

The pavement design of the project roads is based on the Ministry of Works, Housing and Communications Road Design Manual Vol. 3: Pavement Design, Part I: Flexible Pavements (July 2005).

3.2.2 Design Period

The economical analysis of the project roads is based on a 20 year analysis period. Hence a 20 year pavement design period has been adopted.

It does not mean that at the end of the design period the pavement will be completely worn out, but strengthening may be required so that it continues to carry traffic satisfactorily for a further period. However, some routine

Page 85: Final Detailed Design Report - Musita _ Majanji Road

62 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

maintenance is expected to be performed on regular basis throughout the design period to curtail major distress propagation.

3.2.3 Pavement Design Input Data

All the project roads fall in the tropical rain zone and have most rains in March to Climate

June and August to November. They are therefore in the predominantly wet regions.

The traffic loading classes for the different roads were obtained from the traffic count studies. It is found that all the project roads fall between T1 and T4 Traffic

Traffic Loading Class

Load Classes.

Traffic Loading classes are as stipulated in the design manual:

Design traffic loading

(E80 x 106

Traffic load class

<0.3 T1 0.3-0.7 T2 0.7-1.5 T3 1.5-3.0 T4 3.0-6.0 T5 6.0-10 T6 10-17 T7 17-30 T8

3.2.3 Subgrade

The subgrade soils were tested for soaked CBR determination. These CBR values were analysed and design CBR and soil subgrade classes were obtained. Subgrade Strength Classes are as stipulated in the design manual:

Design CBR %

Subgrade Strength

Class

2 S1 3-4 S2 5-7 S3

8-14 S4

Page 86: Final Detailed Design Report - Musita _ Majanji Road

63 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

15-29 S5 30+ S6

3.2.4 Soft spots and Marshy areas

Where such sections are encountered (outside swampy sections) a selected fill material or rock fill is assumed necessary to raise the subgrade design CBR to 8%. The selected fill material shall need to be a minimum depth of 450mm, and care should be taken to ensure that there are no weak materials underlying this layer which may lead to detrimental performance.

3.2.5 Pavement Materials

Pavement materials were obtained during field investigation. It was found that plenty of lateritic gravels are available along the project roads. These gravels are suitable for stabilization with cement or lime.

Field investigation also revealed the availability of rock sources along the project roads, these rocks will be suitable for crushed stone base, and bituminous pavement works.

3.2.6 Pavement Design Catalogue

The pavement design catalogue to be adopted for the design shall be as obtained from Chart W2 (Granular base/Cemented subbase) and Chart W3 (Cemented base/Cemented subase). (Road Design Manual Vol. 3: Pavement Design, Part I: Flexible Pavements).

The pavement layer thicknesses given in charts shall be adjusted to provide layer thickness which is convenient during construction, and also increase thicknesses of lower layers which are cheaper than the upper layers.

However care has to be taken to ensure that the proposed layers are structurally superior to those of the charts.

The pavement structures presented in these charts represent alternate construction approaches differing basically in base course and surfacing materials. These are expected to render equal quality to road user perception cost.

3.2.7 Pavement Structural Design

Two options for the pavement structure have been provided.

Option no. 1:

Page 87: Final Detailed Design Report - Musita _ Majanji Road

64 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

The pavement structure is composed of Granular Base Course on Cemented Subbase Course. The surfacing given is asphalt concrete.

This pavement is much durable with minimal maintenance. However, the construction cost for the asphalt concrete is much higher compared to that of surface dressing.

The pavement structure in this option is composed of Cemented base and Option 2:

Cemented subbase, the surfacing is Double surface dressing.

This option was not considered further during the detailed stage as the Client indicated its preference for Option 1 that uses asphalt concrete for bituminous surfacing

3.2.8 Design Traffic Loading

Traffic studies show cumulative number of standard axles as follows: Estimated traffic growth rate (pessimistic) = 8.7x106

Estimated traffic growth rate (realistic) = 8.99x106

Estimated traffic growth rate (optimistic) = 9.37x106

Estimated traffic growth rate (realistic) = 8.99x106 is adopted for the design of the pavement structure

Traffic class obtained is: T6

3.2.9 Design Subgrade CBR

Analysis of soaked CBR test results for the road alignment subgrade soil involves establishing the design CBR for the section as obtained from 90%-ile chart.

The 90%-ile value for a section is the CBR value which 10% of the test results fall below. This is obtained by plotting a graph of CBR values (arranged in ascending order) against the test number and obtain the CBR value corresponding to

d = 0.1 x (n-1)

where d = is the value in the horizontal axis starting from sample 1 n = number of tests used in the design.

Page 88: Final Detailed Design Report - Musita _ Majanji Road

65 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

CB

R (%

)

1 2 3 4 5 6 7 8 9 10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

CB

R (%

)

0

DESIGN CBR (Road no.1 Musita-Lumino)

70 65 60 55 50 45 40 35 30 25 20 15 n = 34 tests 10 d = 0.1 x (n-1)

5 = 3.3 0

TEST

Figure 16 : Musita-Lumino Subgrade Analysis

From the above figure, the design CBR = 6%

DESIGN CBR FOR (Road no. 1 Busia - Majanji)

70

60

50

40

30

20 n = 9 tests d = 0.1 x (n-1)

1 = 0.8

0

1 3 5 7 9 TEST

Figure 17 : Busia-Majanji Subgrade Analysis

Page 89: Final Detailed Design Report - Musita _ Majanji Road

66 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

From the above figure, the design subgrade CBR = 6%

3.2.10 Design Subgrade Class

The design subgrade class is presented in summary below.

Musita -Lumino Chainage Road

Length

(Km)

90th percentile

value

Design CBR (%)

Subgrade Class S/No

From

To

1 0+000- 74+000 74 6 6 S3

Busia – Majanji

Chainage Road Length

(Km)

90th percentile

value

Design CBR (%)

Subgrade Class S/No

From

To

1 2+000- 26+000 24 6 6 S3

3.2.11 Proposed Pavement Structure

From design chart Chart W2 (T6, S3), the following has been adopted.

Pavement layer Type of material Layer thickness

SURFACING AC(Asphalt Concrete) 50 mm

BASE COURSE GB(Granular Base) 150 mm

SUBBASE CSB(Cemented Subbase) 175 mm

IMPROVED SUBGRADE G15 (Natural Gravel CBR >15%) 125 mm

Page 90: Final Detailed Design Report - Musita _ Majanji Road

67 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

3.3 Drainage Design

3.3.1 Design Return Period

The frequency of the flood for the design of drainage structures depends on the risk to be taken, that defines the degree of risk that we run in designing a structure during the anticipated service life. Therefore, the estimation of the design floods considered the ERA Drainage Design Manual, 2002 (in Road Design Manual, Vol.2 Drainage Design, 2005) which is summarized in Table 23.

Table 23: Design Average Recurrence Intervals for Flood/Storm (yrs) by Geometric Design Criteria (Source: ERA Drainage Design Manual, 2002 in Road Design Manual, Vol.2 Drainage Design, 2005)

Structure Type Geometric Design Standard Paved Ia, Paved Ib, Paved II

Paved III, Gravel A

Paved III, Gravel B

Gravel C

Gutters and Inlets* 10/5 2 2 - Side Ditches 10 10 5 5 Ford/Low-Water Bridge - - - 5 Culvert, pipe (see Note) Span < 2m

25 10 5 5

Culvert, 2m < span < 6m 50 25 10 10 Short Span Bridges 6m < span < 15m 50 50 25 25 Medium Span Bridges 15m < span < 50m

100 50 50 50

Long Span Bridges spans > 50m 100 100 100 100 Check/Review Flood 200 200 100 100

Note 1: Span in the above table is the total clear-opening length of a structure. For example, the span for a double 1.2-meter diameter pipe is 2.4 meters, and the design storm frequency is therefore “culvert, 2m<span <6m.” Similarly a double box culvert having two 4.5 meter barrels should use the applicable design storm frequency for a short span bridge and a bridge having two 10-meter spans is a medium span bridge.

3.3.2 Frequency Distribution Models

In flood frequency analysis, the objective is to estimate a flood magnitude corresponding to any required return period of occurrence. The resulting relationship between magnitude and return period is referred as the Q-T relationship. Return period, T, may be defined as the time-interval (on the average) for which a particular flood having magnitude QT (also known as quantile) is expected to be exceeded.

Page 91: Final Detailed Design Report - Musita _ Majanji Road

68 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

In this work, a compatible distribution model has been considered for hydrological analysis. The comparison between the goodness of fit assessments for different distributions indicate that the Gumbel Extreme Type I distribution is more reasonable and reliable to the hydrologic events and has been widely used for estimating the design rainfall at any given return period. Therefore, the rainfall frequency analysis has been carried out using Gumbel Type I frequency distribution.

A general equation for frequency analysis of hydrologic events is given as (Chow, 1964).

The equation for the quantile estimate is given by:

R T = ∝ + K T ⌠ [Equation 1]

where

RT = daily rainfall amount for return period T µ = central tendency from fitted probability distribution ⌠ = standard deviation from fitted probability distribution KT = reduced variate of the probability distribution depending on

return period and sample size read from probability distribution tables

For Generalized Extreme Value (GEV) distribution which best fitted the data for most stations, KT can be estimated from:

𝟏 =𝟏

𝐊𝐓 =

�𝟏 − (−𝐥𝐧

𝐓) � [Equation 2]

The analysis has been carried out for return period of 10, 25, 50 & 100 years as per design standard of the project. Table 24 presents the estimated design rainfall at different return period.

Page 92: Final Detailed Design Report - Musita _ Majanji Road

69 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Table 24: Estimates of design rainfall at different return periods

Station Name

Station Code

Statis. Distrib.

T

Quantile for Return Period (T), QT [mm]

10000

1000

100

20

10

5

2

1.5

1.33

1.3

1.11

1.05

1.02

p

0.01

0.1

1

5

10

20

50

67

75

80

90

95

98

Jinja

89330430

GEV

157.2

142.9

125.6

110.1

101.8

82.3

72.6

62.9

57.3

53.5

43.5

35.2

25.9

Page 93: Final Detailed Design Report - Musita _ Majanji Road

70 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

3.3.3 Design Flood Estimation

The term design flood refers to the flood hydrograph or peak discharge value that is finally adopted as the basis for design after giving due consideration to the flood characteristics, frequency and damage potential, including economic and other related factors.

By make use of the estimated design rainfall, watershed characteristics and physical data from field visit, the design floods for the different road drainage watersheds were calculated. The adopted models are discussed hereunder.

3.3.4 Runoff Models

Despite of the model used, accurate estimation of the design discharge depends on accurate assessment of the various parameters used in the model. Among the parameters include the flow data, rainfall data, catchments area and characteristics such as mainstream length and slope, curve number, coefficient roughness, time of concentration, length of the channel and slope and catchment land use and cover. In this study, the TRRL East African Flood Model (un- gauged catchment) and Frequency analysis (gauged catchment) were used.

3.3.5 Frequency analysis

There exist different types of frequency distributions in frequency analysis models. The most applicable type of models for peak flood analysis, Log Pearson Type III distribution programmed in Excel spreadsheet was used.

Table 25: Estimate of design floods at different return period

Flood Frequency Calculations using log-Pearson Analysis III

(period of record 1999-2009)

Return Period (years)

Skew Coefficient Discharge K (-0.0403) Q (m3/s)

2 0.0068 46 5 0.8436 64

10 1.2772 76 25 1.7369 91 50 2.0322 102

100 2.2962 113 200 2.5381 125

Page 94: Final Detailed Design Report - Musita _ Majanji Road

71 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

3.3.6 The TRRL East African Flood Model

The TRRL East African Flood Model has been recommended as the most appropriate model for the estimation of design floods for the different un-gauged catchments in East Africa and has been widely used.

In the TRRL model, the base time is assumed to be the time from 1 per cent of peak flow on the rising limb to 10 per cent of peak flow on the falling limb of the hydrograph. For East African catchments, it has been found to vary between 2.7 and 11.0 unlike the US hydrographs, where the ratio of base time to time to peak is approximately 3.0. Owing to wide range, the use of a single hydrograph base on time to peak was therefore considered not appropriate.

A much more stable ratio was found to be the peak flow (Q) divided by the average flow measured over the base time (Q) (Peak Flow Factor).

F = Q Q

[Equation 3]

The peak flow was estimated if the average flow during the base time of the hydrograph can be calculated.

The total volume of runoff is given by:

RO = (P � Y )C A * A *103 (m3) [Equation 4]

Where: P = rainfall (mm) during time period equal to the base time

Y = initial retention CA = contributing are coefficient A = catchment area (km2)

If the hydrograph base time is measured to a point on the recession curve at which the flow is one tenth of the peak flow, then the volume under the hydrograph is approximately 7 per cent less than the total runoff.

The average flow (Q) is therefore given by:

Q = 0.93 * RO 3600 * TB

[Equation 5]

Where:

TB = hydrograph base time (hrs.)

Page 95: Final Detailed Design Report - Musita _ Majanji Road

72 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Estimates of Y and CA are required to calculate RO and lag time K to calculate TB.

Initial Retention (Y) In arid and semi arid zones an initial retention of 5 mm is considered, and zero elsewhere

Contributing Area Coefficient (CA) Contributing area coefficient is a coefficient that reflects the effects of the catchment wetness and the land use. A grassed catchment at field capacity is taken as a standard value of contributing area coefficient. The design value of the contributing area coefficient was estimated from the following equation.

C A = CS * CW * C L [Equation 6]

Where: CS = the standard value of contributing area coefficient for a grassed catchment at field capacity

CW = the catchment wetness factor CL = the land use factor

The three factors are given in Tables 5.2, 5.3, and 5.4 of the TRRL Laboratory Report 706 (Tables 26, 27 and 28 below).

Table 26: Standard Contributing Area Coefficient (wet zone catchment, short grass cover) (Source: TRRL Laboratory Report 706)

Catchment Slope

Soil Type

Well Drained Slightly Impeded

Drainage Impeded Drainage

Very Flat < 1.0 % Moderate 1-4 % Rolling 4-10 % Hilly 10-20 % Mountainous > 20 %

0.09 0.10 0.11 0.12

0.15 0.38 0.45 0.50

0.30 0.40 0.50

Page 96: Final Detailed Design Report - Musita _ Majanji Road

73 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Table 27: Catchment Wetness Factor (Source: TRRL Laboratory Report 706)

Rainfall Zone

Catchment Wetness Factor Perennial Streams Ephemera Streams

Wet Zone Semi Arid Zone Dry Zones (except West.

Uganda) West Uganda

1.0 1.0 0.75 0.60

1.0 1.0 0.50 0.30

Table 28: Land Use Factor (Base assumes short grass cover)

(Source: TRRL Laboratory Report 706)

Land Use Land Use Factor Largely bare soil Intense cultivation (particularly in valleys) Grass cover Dense vegetation (particularly in valleys) Ephemeral steam, sand filled valley Swamp filled valley Forest

1.50 1.50 1.00 0.50 0.50 0.33 0.33

Catchment lag Time (K) The appropriate values of lag time were estimated from Table 29. Care was take in assessing which category to place a given catchment, as generally only small areas on either side of the stream are contributing to the flood hydrograph.

Table 29: Catchment Lag Time (Source: Table 5.5 of TRRL Laboratory Report 706)

Catchment Type Lag Time (K) in hrs Arid Very steep small catchments (slope > 20 %) Semi arid scrub (large bare soil patches) Poor pasture Good pasture Cultivated land (down to river bank) Forest, overgrown valley bottom Papyrus swamp in valley bottom

0.1 0.1 0.3 0.5 1.5 3.0 8.0 20.0

Page 97: Final Detailed Design Report - Musita _ Majanji Road

74 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

c

d

Base Time The rainfall time (TP) is the time during which the rainfall intensity remains at high level. This was approximated by the time during which 60 per cent of the total rainfall occurs. Using the general intensity duration frequency equation,

i = a (0.33 + td )

[Equation 7]

The time to give 60 per cent of the total rainfall is given by solving equation 7.

0.6 = t d

c 24.33

24 t + 0.33

[Equation 8]

Values for the various rainfall zones of East Africa are given in Table 30.

Table 30: Rainfall Time (TP) for East African 10 year Storm (Source: Table 5.6: TRRL Laboratory Report 706)

Zone

Index 'c' Rainfall time (TP) (hr)

Inland zone Coastal zone Kenya Aberdare Uluguru Zone

0.96 0.76 0.85

0.75 4.0 2.0

The flood wave attenuation (TA) was estimated from equation 9.

T = 0.028 L [Equation 9] A 1 1

Q 4 S 2

Where:

L = length of main stream (km) Q = average flow during base time (m3/s) S = average slope along main stream

The base time was estimated as:

TB = TP + 2.3K + TA

[Equation 10]

Page 98: Final Detailed Design Report - Musita _ Majanji Road

75 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

The iterative/ trial and error solution was carried out. Initially TA was assumed

zero, and two iterations were considered adequate. Knowing Q and F, the peak was calculated using equation 3.

The following pages illustrate the computation process using the TRRL East African Flood Model in one of the drainage catchment. The same approach programmed in excel spreadsheet was used in the computation of the design floods in other watersheds.

Page 99: Final Detailed Design Report - Musita _ Majanji Road

76 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

b) Catchment Lag time (K): 3 hr TRRL 706_Table 7

Arid

0.1

Very steep small catchments (>20%) 0.1 Semi arid scrub (bare soil patches) = 0.3 Poor Pasture = 0.5 Good pasture = 1.5 Cultivated land (down to river banks) 3 Forest, overgrown valley bottom 8 Papyrus swamp in valley bottom 20 c)

STD Contributing area coefficient Cs = Soil type (Slightly impended drainage) Catchment slope (Rolling 4-10%)

0.45

TRRL Table 4 pp 18 TRRL Fig 15: soil zones

a) Catchment characteristics : Catchment area, A (km2) 8.623 km2 Land slope, S = 0.045 Main stream average Slope, Sc = 0.032 Major stream flow length, L (m) 4016 m

Land use: Gently sloping catchment, cultivated down to river channel banks (sugarcane, maize, cassava) and settlement

pp 20

d) Antecedent Rainfall zone17

TRRL Table 3 pp

NYANZA UG Potential ET 5.6 mm/day TRRL Fig. 14 2 day antecedent 21.1 mm 7 day antecedent 48.4 mm Soil Moisture recharge 60.9 Mm

e) Catchment wetness factorTable 3-pp17 &

, Cw 1 TRRL 706_

Table 5-pp 19 Rainfall Zones Catchment wetness factor (Cw)

Perennial strea ms

Ephemeral streams

Wet zones 1 1 Semi arid zone 1 1 Dry zones

(exept West Uganda)

0.75 0.5

West Uganda 0.6 0.3

Page 100: Final Detailed Design Report - Musita _ Majanji Road

77 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Area, A 8.62 km2 Time, T = TB = 7.65 hr ARF = 0.94

Average rainfall, (P) = ARF * RTB 94.53 mm/ l)

Volume of runoff, RO (m3) = (CA * (P - Y) * A * 1000)

521125.67

m3

f) 1.5 Land use factor CL TRRL Table 6 pp 19

Largely bare soil 1.5 Intense cultivation (Particularly in valleys) 1.5 Grass cover 1 Dense vegetation (particularly in valleys) 0.5 Ephemeral stream, sand filled valley 0.5 Swamp filled valley 0.33 Forest 0.33 g)

Contributing area coefficient, CA

= (Cs*Cw*CL) 0.675

Eqn 8 , TRRL h)

Initial Retention, Y 5

mm

TRRL 706

If Semi arid or West Uganda

Elsewhere, Y =

5

0

Page 11 (summary, (h)) and Fig.14

i)

Rainfall time, Tp for EA 10 year storms: 0.75

hrs

TRRL 706_Fig 16 & Table 8

Inland zone Tp = 0.75 Index, "n" = 0.96

j)

Design rainfall during time interval (TB), P (mm):

10 year daily point rainfall = 108.16 mm

k) 1st Iteration of Base time, TB (hr): (Tp + 2.3K + TA)

Assuming 1st Iteration TA = 0

7.65 hr TRRL Eq 12

Rainfall during base time RTB = RTB = (TB/24)*(24/(TB + 0.33))^n * R10/24 100.53 mm/d

Where: Index, n for 10 yr design storm 0.96 hr TRRL 706_Fig 16 &

Table 8 10 yr max average daily rainfall, R10/24 108.16 mm/d

Area Reduction Factor, ARF = 1- 0.04*T^(-1/3) *A^(0.5)

d

TRRL Eqn 6

Page 101: Final Detailed Design Report - Musita _ Majanji Road

78 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Qav TB TA 17.5979 7.65 0 17.5959 7.6509 0.0009 17.5959 7.6509 0.0009

Q25:Q2 1.667 Q10:Q2 1.490 Q100:Q10 1.393 Q100 56.36 m3/s Q50:Q10 1.225 Q50 49.56 m3/s Q25:Q10 1.119 Q25 45.27 m3/s

m) Average flow

TB (2nd approximation iterative procedure) ITERATION OF Qav and TB

Qav = (0.93*RO/(3600*TB) =17.60 m3/sec TRRL Eq 13

New values after Iteration: 10 year daily point rainfall R10/24 = 108.16 mm/d Rainfall during base time, RTB = (TB/24)*(24/(TB + 0.33))^n * R10/24 = 100.53 mm/d

Area Reduction Factor, ARF = 1- 0.04*T^(-1/3) *A^(0.5) Area, A 8.62 km2

Time, T = TB = 7.65 hr ARF = 0.94

Average rainfall, (P) = ARF * RTB 94.53 mm

n) Volume of runoff, RO (m3)

= (CA * (P - Y) * A * 1000) 521131.95 m3 TRRL Eqn 6

Average flow, Qav = 17.60 m3/sec

o) DESIGN PEAK FLOW

Where peak flood factor, F is given as: 2.3 , Q = (F* Qav) 40.47 m3/sec TRRL Eqn 5

Computed K = 3 hr For K < 0.5 hr, F = 2.8 For K > 1.0 hr, F = 2.3

Therefore Q10 = 40.47 m3/sec

Design Peak flow for T= 25, 50, 100 years Peak Discharge Factor Q100:Q2 2.075 TRRL Laboratory

Report 623 Q50:Q2 1.825 Appendix 1,

Fig. 3

Page 102: Final Detailed Design Report - Musita _ Majanji Road

79 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

3.1.8 Design Discharges

Tables 31 and 32 present the design discharges of the project road under the project for the different return periods.

Table 31: Summary of design floods for different return period Road E1.1- Musita-Lumino

Catch. Ref.

Chainage from Musita

Northing

Easting

Catch. area

(km2)

Design flood discharge (m3/s)

10-yr 25-yr 50-yr 100-yr 283 5+060 546926 55901 1.34 6.28 7.02 7.69 8.75 284 5+440 547329 55567 1.18 5.56 6.22 6.80 7.74 286 7+276 548534 54543 8.62 40.47 45.27 49.56 56.36 287 11+250 551778 51971 0.74 3.66 4.09 4.48 5.09 289 11+660 554420 50807 1.24 3.83 4.28 4.69 5.33 290 15+870 556063 50594 4.78 14.72 16.46 18.02 20.50 292 16+833 558983 50334 1.54 7.86 8.79 9.62 10.94 293 18+800 559865 50573 0.42 1.28 1.44 1.57 1.79 294 19+700 561223 50599 0.21 0.64 0.72 0.78 0.89 295 21+100 562439 50433 0.40 1.24 1.39 1.52 1.73 296 24+000 564029 50880 2.03 6.26 7.00 7.66 8.72 297 25+810 565785 50809 0.29 0.88 0.99 1.08 1.23 298 28+640 568503 50122 0.73 2.24 2.50 2.74 3.11 299 29+465 569306 50281 1.18 5.53 6.18 6.77 7.69 300 30+910 570662 50663 0.71 2.17 2.43 2.66 3.03

31+970 571704 50447 0.44 1.29 1.46 1.59 1.99 301

34+360 574025 50099 14.32 44.12 49.35 54.03 61.44 574151 50076

302 37+960 577490 50202 3.75 11.56 12.93 14.16 16.10 303-306 40+240 579850 50501 24.97 88.43 98.91 108.29 123.15

582090 50406 582238 50370

307 45+990 585222 49136 9.09 42.58 47.63 52.14 59.3 308 50+260 588250 46187 11.47 49.98 55.9 61.2 69.6 309 54+130 591146 41090 13.18 42.82 47.89 52.43 59.63 310 54+870 591696 43504 10.54 32.48 36.33 39.77 45.23 311 58+590 594212 40880 12.42 30.38 33.98 37.2 42.31 312 63+270 597842 38019 1.13 7.01 7.84 8.59 9.76 313 73+330 607154 35225 3.26 17.82 19.93 21.82 24.81 314 76+660 610229 36199 0.97 3.00 3.36 3.67 4.18

Page 103: Final Detailed Design Report - Musita _ Majanji Road

80 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Table 32: Summary of design floods for different return period

Road E1.2- Busia-Majanji

Catch. Ref.

Chainage from Busia

Northing

Easting

Catch. area (km2)

Design flood discharge (m3/s)

10-yr 25-yr 50-yr 100-yr 325 1+125 620283 51064 0.19 0.88 0.98 1.07 1.22 324 1+480 619949 50892 0.57 2.87 3.21 3.51 3.99 323 6+970 616014 47143 2.0 10.03 11.22 12.29 13.97 322 10+310 614350 44331 0.88 4.41 4.94 5.4 6.14 321 10+885 614081 43819 0.16 0.81 0.90 0.99 1.12 320 11+860 613606 42931 8.35 24.68 27.61 30.22 34.37

318

16+310 611423 38133 3.96 17.82 19.94 21.83 24.82 17+390 610871 36614

317 21+600 610325 34182 4.96 22.18 24.81 27.16 30.89 316 23+180 610300 32610 0.80 3.12 3.49 3.82 3.12 315 25+500 610374 30420 1.38 5.36 5.99 6.56 7.46

3.4 Structure Selection

3.4.1 Design Philosophy

Provision of efficient and adequate drainage system is extremely important for the life of the road in terms of reducing maintenance cost and preventing adverse environmental impacts. Inadequate drainage design will contribute highly to the deterioration of the pavement structure. Areas to which attention should be given could be categorized as surface and subsurface drainage along the road and cross drainage.

The design of side ditches, culvert capacities and bridge waterway openings are governed by the criteria specified in the UNRA manual.

The surface drainage system, which will take care of rain water from the pavement surface, adjacent cut slopes and the ground cross fall will be treated by proper cambering of the roadway and by the introduction of side ditches.

Minor drainage structures are specified as standard structures and are recommended based on hydraulic efficiency, terrain condition, type of foundation material, the safety of the surrounding dwellers and road traffickers.

Except for the bridges, standard drawings are adopted unless there is a call for site specific design.

The type and size of drainage structure specified for a particular location is often determined based on site specific conditions. But a generalized structures

Page 104: Final Detailed Design Report - Musita _ Majanji Road

81 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

selection effort is made to initially identify the benefits of a certain types of structure based on the general prevailing local condition, like availability of local material at the project vicinity, skilled labour, capacity of the construction industry and cost efficiency.

Bridge is recommended where it is more economical than a culvert, perhaps due to the need to bury a culvert under a high level of fill. They are also employed to satisfy land use requirements, to mitigate possible environmental harm with a culvert, to avoid floodway or irrigation canal encroachments, and to accommodate large debris.

Culverts are used where bridges are not hydraulically required, where debris is tolerable, and where they are more economical than a bridge. Culverts can be concrete box culverts, concrete slab, reinforced concrete pipe culverts, or corrugated metal culverts or plastic.

Concrete box/slab culverts are constructed with a square or rectangular opening, and with wing walls at both ends. They are usually specified for larger flows, where the area of the opening is larger than a practical pre-cast circular concrete pipes. There may also be the case where the cost estimate of concrete box/slab

culverts constructed on site are less expensive than manufactured and/or imported pipe culverts.

3.4.2 Bridges

The choice of a bridge type is a matter of

� Safety

� Environmental factors

� Economics

� Availability of local construction materials in enough quantity and quality

� Availability of semi skilled and skilled labour in enough number to be

deployed for the project work

� The current capacity of the construction industry

� The possibility and ease of construction

� The possibility, ease and frequency of regular maintenance

3.4.2.1 Bridge Material

The following table highlights the comparison of various bridge construction materials that the consultant has taken into account in reaching a decision on the

Page 105: Final Detailed Design Report - Musita _ Majanji Road

82 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Reinforced Concrete Composite /steel& concrete/ Steel

Availability

of material

� Sand /available at the project route/

� Aggregate /can be crashed from

quarry within the project site/

� Cement /locally produced at Tororo/

� Reinforcement bars/ imported/

� Sand /available at the project route/

� Aggregate /can be crashed from

quarry within the project site/

� Cement /locally produced at Tororo/

� Reinforcement bars/ imported/

� Steel profiles/imported/

� Steel profiles all /imported/

Advantage

� Low cost

� Flexibility in design

� Common practice

� Structural advantage to reduce dead

load

� False work not required

� Fast to assemble

� No shuttering and false

work

Disadvantage

� Heavy self weight

� Takes quite some time to build

� Requires false work to be erected in

the river course unless precast used

� Relatively higher cost

� Needs regular maintenance effort � Higher cost

� Needs regular maintenance

effort

� Some times required special

welding task

Priority &

reason

First

� can easily be done by the available

skilled labor in the market

� Concrete inputs are very easily

available within the project route

which can result in higher cost

reduction

� Labour intensive hence creates

money temporary jobs

second third

Abutment/Wing walls Reinforced Concrete Masonry

Availability

of material

� Sand /available at the project route/

� Aggregate /can be crashed from quarry within the project

site/

� Cement /locally produced at Tororo/

� Reinforcement bars/ imported/

� Stone /available at the project route/

� Sand /available at the project route/

� Cement /locally produced at Tororo/

Page 106: Final Detailed Design Report - Musita _ Majanji Road

83 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Advantages

� Freedom of having taller heights

� Reduced self weight

� Good to distribute load to weak foundation material

� No risk of quality, concrete is mixed at batching plants.

� Lower cost

� economical for height less than 10m

� masonry work is a common practice can be done

easily

� do not require shuttering work

Disadvantage

� Relative higher cost

� Requires shuttering & scaffolding work � Supervision difficulty in controlling the quality of

mortar used

Priority &

reason

First

� Better quality, long live despite the relative higher cost Second

� Relative lower costs due to quality masonry

stone is available within the project route

selection of the type of material for the construction of all bridges in the project.

Incorporating the general factors for the choice of a bridge type above and taking into consideration the following points:

1. evaluating the result of existing structures assessment 2. results of the detail geotechnical foundation investigation 3. discussions and approval made by the client /UNRA/

reinforced concrete for both super structure and abutments/wing walls is selected for all new bridges of the entire project roads.

3.4.2.3 Bridge Structural System

Though the selection of the bridge system is mostly site specific, simply supported structural bridge system with 12 meter length and its multiple, is selected as a standard bridge for the entire project roads. The following important points were considered in selecting the bridge system.

1. Standardizing is the TOR requirement 2. Standardizing minimizes cost by allowing repeated us of

forms, reduced effort in bar bending and easy to master the details for the construction task force

3. Discussions made with UNRA bridge team

Page 107: Final Detailed Design Report - Musita _ Majanji Road

84 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

3.4.2.5 Bridge Construction System

In view of the topographic formation of the project routes and river crossings, the design consultant opts to adopt precast superstructure standard system of construction for all the new bridges for the entire project roads.

The following important additional points are also taken into consideration in selecting the standard precast system.

1. The existence of new bridges in swamps crossings, demands

fast way of construction to finalize the construction of the bridges during the dry period where the water flow is low

2. Risk of settlement and difficulty in using props to support formworks on the soft bed material unless replaced.

3. The availability of hauling and lifting equipments, capacity of the construction industry is assessed, discussed and agreed with UNRA bridge team.

3.4.3 Slab/Box Culverts

As defined earlier, slab culverts are those with top slab resting on gravity type abutments (usually masonry) each done separately, and box culverts are those having monolithic top slab, bottom slab and the vertical walls.

Slab culverts are usually recommended in road sections having good foundation or bed material with minimum risk of settlement and scouring at abutment foundation.

Box culverts are proposed on areas where the foundation material is found weak and to avoid any possibility of foundation failure.

After putting in to consideration the following points:

� Considerable number culverts are required in areas where the

project roads intercept the swamps and their detail geothechnical investigation revealed that the foundation material at shallow depth is weak.

� Having difficulty to control the quality of mortar to be used in the formation of masonry abutments in case of slab culverts

� The better quality and rigidity of the box culverts is demanded and approved by the client.

Box culverts are selected for the entire project roads.

Page 108: Final Detailed Design Report - Musita _ Majanji Road

85 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

To allow a repeated use of formwork and minimize cost and time, standard span box sizes are adopted for the entire project roads. Their detailing is shown on the standard box culverts in the book of drawings.

3.4.4 Pipe Culverts

The minimum size of pipe culvert proprosed to be used as cross-drainage on entire project roads is 900mm in conformity with the UNRA drainage design manual.

Because of economy, easy of production at site and durability standard concrete pipe is selected to be used for the entire project roads. Their detail is shown in the standard pipe culverts drawings

Concrete headwall is selected to be used for the pipe culverts in the entire road project roads despite its relative higher cost after considering the following facts.

� Better quality at relative higher cost than brick or masonry � Demanded and agreed by the client/UNRA/

The concrete head wall is designed in three different models to suite the smooth inflow of water into the pipes. The selection is made site specific to avoid potential scour at the inlet and outlet. Their detail is shown on the standard pipe culverts in the book of drawings.

The table below highlights the comparison made between the various material alternatives proposed for pipe culverts.

Page 109: Final Detailed Design Report - Musita _ Majanji Road

86 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

Pipe options Head wall options Concrete Plastic Armco Masonry Brick Concrete

Material

Availability � Sand /available at the

project route/ � Aggregate /can be

crashed from quarry within the project site/

� Cement /locally

produced at Tororo/ � Reinforcement bars/

imported/

Imported Imported � Stone /available at the project route/

� Sand /available at the

project route/ � Cement /locally

produced at Tororo/

� Brick /everywhere available at the project route/

� Sand /available at the

project route/ � Cement /locally

produced at Tororo/

� Sand /available at the project route/

� Aggregate /can be

crashed from quarry within the project site/

� Cement /locally

produced at Tororo/ � Reinforcement bars/

imported/ Advantage � Low cost

� Can be produced at site

� durable

� easy handling

and transport � easy handling

and transport � low cost

� manageable to build several culverts along the route

� moderate cost

� manageable to build several culverts along the route

� better quality

� extended life

� easy to control material

quality Disadvantage � handling � higher cost

� could be attacked by chemicals

� higher cost

� could be attacked by chemicals

� possibility of corrosion

� mostly stolen

� difficult to control

quality of mortar � requires plastering

� lower durability

� difficult to control quality

of mortar

� relative higher cost

� reqiures shattering

priority &

reason

First

� lower cost due to availability of local materials within the project vicinity

� higher durability

� avoids at large hard currency requirement

Second Third First

� relative lower cost Second Third

Page 110: Final Detailed Design Report - Musita _ Majanji Road

87 | FINAL Detailed Design Report_Rev.1-AUG.2012 |

3.4.5 Paved Side Ditches

Grouted stone pitching side ditches/ road gutters/, if well done and maintained regularly, can serve the purpose they are intended for as the design consultant looked around at the existing roads and on the main trunk roads.

Grouted stone pitching trapezoidal open channel side ditches are selected as standard paved side ditches for road gradient exceeding 3% in the entire project roads outside of town or trading centres. Very low relative cost as compared to a precast or cast-insitu concrete paved ditch is the prime factor for the selection of grouted stone pitching side ditches as standard.

However, paved side ditches in towns and trading centres need to be covered to allow access for pedestrians and traffic at selected locations. To secure safe and long lasting covered paved ditches the design consultant selected rectangular reinforced concrete paved side ditches with cover at selected positions as standard for all the towns and trading centres in the entire project roads. The selection was also discussed and agreed with client’s engineer team. Please refer to book of drawings for the Standard Paved Side Ditches and Standard Paved Side Ditches for Urban and Trading Centres for details.

3.5 Hydraulic Design

3.5.1 Minor Drainage Structures

3.5.1.1 Paved Side Ditches

The size of side drains is determined from the Manning’s open channel equation,

Q= (1/n)*A*(R2/3)*S1/2

Where, Q= discharge in m3/s A= area of flow in m2

R= hydraulic radius s= bed slope n= roughness coefficient

And the depth of flow is kept 0.4m according to UNRA Drainage Manual to protect possible saturation and erosion of road pavement. The channels from the road surface are estimated using the rational formula:

Where, Q=0.278*C*I*A

Q= Discharge in m3/s C= Run – off coefficient I= Intensity of rainfall in mm/hr for 10min storm with ten years

return period A= Area contributing to channel flow in Km2

Flow from connecting channels to these side drains is determined according to the specific situation.

Page 111: Final Detailed Design Report - Musita _ Majanji Road

88 | FINAL Detailed Design Report_Rev.1-AUG 2012 |

3.5.1.2 Pipe Culverts

The hydraulic capacity of existing pipe culverts has been obtained from the tables in the UNRA Drainage Manual against their opening sizes, bed roughness of 0.015 and bed slop of 1% and allowing only 50% efficiency; please find these tables in Appendix 9.19 of the same manual.

The discharge capacity of each and every pipe is compared with calculated channel design discharge with 25 years recurrent period. We found that in most of the cases the existing pipe culverts have inadequate hydraulic capacity to accommodate the anticipated design discharge.

A table incorporating the opening sizes, type and hydraulic capacity of existing pipe culverts, the corresponding design discharge, the new structure opening size and its hydraulic capacity is prepared for detail clarification and presentation.

Except for the relief and local pipes all the new pipe culverts are checked against head water depth ratio (Hw/D) greater than 1.2 to avoid scour damage to the inlet side of the road embankment and also to avoid excessive flooding upstream allowing 250mm free board below the road final level on the same table using HY- 8 computer software.

Please refer to the table in Appendix-6.

3.5.2 Major Drainage Structures

3.5.2.1 Box Culverts

Where the design discharge is found over the capacity of the maxmum size of double pipe culverts, the box culvert is selected.

The preliminary size of all box culverts is verified using HY-8 computer software after having the final road levels and bed slop. Both inlet and outlet control flows shall be checked by applying the final invert level and available upstream flow head after allowing 250mm free board below the road final level.

Based on the result obtained from the computer program and soil particle size of the flow bed channel, bed protection work shall be recommended to avoid or minimize bed erosion. Please refer Appendix 6.

The project box culverts schedule showing the following details of each and every box is prepare:

� the invert level, � culverts slope � flow direction � skew angle if any � culverts length and head wall quantities � additional protection work if there is any

Page 112: Final Detailed Design Report - Musita _ Majanji Road

89 | FINAL Detailed Design Report_Rev.1-AUG 2012 |

3.5.2.2 Bridges

Bridges are selected in defined river flows where there are existing bridges, the design flow couldn’t be accommodated by box culverts and at least to maintain the opening size of the existing bridge and told by the local community repeated over flooding even though not supported by the hydrology analysis. And in swamps where, the design discharge is over the capacity of box culverts in series, to allow passage of expected debris and to assure free movement of the aquatic life, bridges are also recommended.

The capacity of the existing bridges and the preliminary opening size of the new bridge required to accommodate the design discharge for each particular bridge location is determined from the Manning’s Equation for open channel flow and allowing free board of 1.5m according to UNRA Manual.

Q= (1/n) .A. R2/3 . S1/2

However, the preliminary bridge opening size is verified using WSPRO or HEC-2 software to insure the provided opening is safe against upstream flooding and excessive flow velocity. Please refer to the bridge hydraulic calculations and results in Appendix-4.

Scour at bridge location is very important for the safety of bridge. We studied the local scour problems at those bridges where the bed material is other than rock bed. The local scour at pier is a function of bed material size, flow characteristics, fluid properties and the geometry of the pier.

The scour depth at pier as given by the CSU (Colorado State University) equation is;

Ys = 2Y1K1K2 K3

0.65

a

Fr 0.43

Where; Y1

Ys = scour depth Y1 = flow depth directly upstream of the pier, [ft] K1 = Correction factor for pier nose shape K2 = Correction factor for angle of attack of flow K3 = Correction factor for bed condition a = Pier width, [ft] V1 = mean velocity of flow directly upstream of the pier, [ft/sec]

1/2 Fr1 = Froude number = V1/ (gy1) For the constants and detail of the formula please refer to UNRA’s drainage manual section 10.8.3.

Where the demand for scouring protection, river training and bank protection work exists their design is explained on the same sheet of the bridge hydraulic design.

Page 113: Final Detailed Design Report - Musita _ Majanji Road

90 | FINAL Detailed Design Report_Rev.1-AUG 2012 |

3.6 Structural Design

3.6.1 Minor Drainage Structures

3.6.1.1 Paved Side Ditches

Paved side ditches are constructed as v-shaped channel following the natural stable soil slope except at towns and trading centres where rectangular channels used. The rectangular channels are designed to resist lateral earth pressure and traffic live loading at places where covering slab required. The concrete covers are also designed to withstand the traffic live loading safely. Please refer to Appendix 6-Structural Design Calculations.

3.6.1.2 Pipe Culverts

Structural design of concrete pipes usually done at standard level so that they can withstand the design live loading and the surrounding soil pressure safely. And these designs are confirmed by laboratory testing according to standard specification.

Standard concrete pipes sizes, detailed and specified according to AASHTO standard specification M-170 or M-242 are adopted for this project.

Basically a minimum soil cover of 600mm is adopted to reduce the effect of concentrated live load unless otherwise an additional slab is put on the top of the pipe.

Class-C bedding is adopted for all concrete culvert pipes bedding for the entire project unless otherwise Class-A or Class-B bedding is approved by the engineer according to specific need.

3.6.2 Major Drainage Structures

3.6.2.1 Box Culverts

Box culvert structures are designed as rigid frame structural system. The following loadings are considered in the design.

1. Earth pressure from surrounding backfill material 2. Weight of soil above 3. Design live loading 4. Weight of water if exists.

Design calculation is carried out for all box culverts which are selected as standard for the project all according to UNRA Manual and BS5400 Standard. SAP 2000 software is used for the structural frame analysis. Please refer to Appendix 6- Structural Design Calculations.

3.6.2.2 Bridges

List of New Bridges

No new bridges are required on Musita-Lumino/Busia-Majnaji roads.

Page 114: Final Detailed Design Report - Musita _ Majanji Road

91 | FINAL Detailed Design Report_Rev.1-AUG 2012 |

)

Material Quality

a) Concrete Quality

Concrete quality of Grade 30 (with characteristic strength 30MPa of 150mm cube at 28 days according to BS 5400 section 5.1.4 table-5) is adopted for all the bridge super and substructures in the entire project.

b) Reinforcement Quality

Reinforcement steel quality of Grade 460 (with minimum characteristic strength of 460MPa according to BS Cl 5.1.4 table-6) is adopted for all the bridge super and substructures in the entire project.

Design Method

The bridge reinforced concrete members are design to the ultimate limit state design and checked for crack width control and servicibility limit state all according BS5400 Part-4 for concrete structures.

Bridge Loading

All the structural design loadings of the new bridges are considered according to UNRA Bridge Design Manual together with BS5400 Part-2 for loading.

a) Live Loading

The bridge structure and its elements are designed to resist the more severe effects of either:

Design HA loading (see UNRA 6.4.1) or Design HA loading combined with design HB loading (see UNRA 6.4.2).

Where,

b) HA loadings

HA loadings are a formula loading representing normal traffic. It consists of a uniformly distributed load/UDL/ and knife edge load /KEL/combined, or of a single wheel load, including 25% impact.

The UDL shall be taken as 30kN per linear meter of notional lane for loaded lengths up to 30m, and for loaded lengths in excess of 30m it shall be derived from the equation.

W = 151 (1

0.475

L but not less than 9

Where, L is the loaded length (in m) and W is the load per meter of lane (in KN)

The KEL per notional lane shall be taken as 120kN.

c) Single Nominal Wheel

One 100kN wheel placed on the carriageway and uniformly distributed over a circular contact area assuming an effective pressure of 1.1N/mm2 (i.e 340 mm

Page 115: Final Detailed Design Report - Musita _ Majanji Road

92 | FINAL Detailed Design Report_Rev.1-AUG 2012 |

diameters) shall be considered. Alternatively, a square contact area may be assumed, using the same effective pressure (i.e. 300mm side).

d) HB loadings

Those derived from the nature of exceptional industrial loads (e.g. electrical transformers, generators, pressure vessels, machine presses, etc.) One unit shall be taken as equal to 10 KN per axle (i.e. 2.5 KN per wheel).

The overall length of the H B vehicle shall be taken as 10, 15, 20, 25 or 30 m for inner axle spacing of 6, 11, 16, 21 or 26 m respectively, and the effects of the most severe of these cases shall be adopted. The overall width shall be taken as 3.5 m.

The minimum number of units to be used shall be 25 units for all public highway bridges. After having discussion and approval by UNRA 37.5 units of HB loading are used for the design all the bridges in the entire project.

Fig 16: Dimensions of HB vehicles

e) Longitudinal Loading

The longitudinal load resulting from traction or braking of vehicles and shall be taken the more severe of

1) The nominal load for HA shall be 8 kN/m of loaded length plus 200 kN,

subject to a maximum of 700 kN, applied to an area one notional lane wide x the loaded length or

2) The nominal load for HB shall be 25 % of the total nominal HB load adopted, applied as equally distributed between the eight wheels of two axles of the vehicle, 1.8 m apart

and applied at the road surface in one notional lane only.

f) Accidental Load Due to Skidding

A single nominal point load of 250KN is considered in one notional lane only, acting in any direction parallel to the surface of the highway.

Page 116: Final Detailed Design Report - Musita _ Majanji Road

93 | FINAL Detailed Design Report_Rev.1-AUG 2012 |

g) Wind Load

All the project bridges are categorized into terrain category 1 with velocity pressure of 0.81KN/m2 structure height of 5m. However, wind load is not considered in our design since all the bridges in the entire project are small at low level and wind loading doesn’t govern.

h) Live Load Surcharge

Live load surcharge for properly consolidated backfill material:

(a) for HA loading : 10kN/m2; (b) for HB loading 37.5 units : 16.25kN/m2

(c)

i) Earthquake Loading

The project bridges are located in Zone 2 with acceleration coefficient (A) = 0.07 and iImportant classification(IC) of class I. Seismic performance category (SPC) = 2 and soil profile type II with site coefficient(S) = 1.2.

Detailed seismic analysis is not required for a single span bridge or for bridges classified as SPC 1 & 2 (Cl.9.4.2 UNRA).

But the connection of the superstructure to the substructure shall be designed to resist a horizontal seismic force equal to 0.20 times the dead load reaction force in the restrained directions.

Bearing seats supporting the expansion ends of girders shall be designed to provide a minimum support length N (in mm) measured normal to the face of an abutment or pier, not less than that specified below:

N = 203 + 1.67L + 6.66H (mm)

where

L = length, in meters of the bridge deck to the adjacent expansion joint, or to the end of the bridge deck.

H = average height, in meters of columns supporting the bridge deck to the next expansion joint for abutments

H = column or pier height in meters for columns and/or piers

3.6.2.3 Substructure

Reinforced concrete type substructures designed to safely transfer all loads from the superstructure to the underlying soil strata within its bearing capacity without excessive setlement.

a) Pier

Twin wall type reinforced concrete pier with common footing pad and independent hammer head beam seat is designed to safely transfer superstructure loads to the foundation material for all the bridges in the entire. In the design all fractional values are taken to the full numbers which allow us to have a few sizes for construction simplicity and economy. Simi-circular shape edge is provided for a better hydraulic performance and durability.

Page 117: Final Detailed Design Report - Musita _ Majanji Road

94 | FINAL Detailed Design Report_Rev.1-AUG 2012 |

The following loads are considered in the design processes.

1. Earthquake forces from the superstructure and the pier itself 2. Longitudinal forces from the superstructure 3. Self weight and dead load from superstructure 4. Live load reaction

Please refer to Appendix 6-Structural Design Calculations.

Figure 17 : Longitudinal Elevation

b) Abutment

Cantilever reinforced concrete abutment with 45 degrees flared wing walls is designed to safely transfer all loads from the superstructure and the back fill soil to the foundation material.

The following loads are considered in the design processes of abutments:

1. Self weight and dead load reaction from superstructure 2. Live load reaction from superstructure 3. Traffic surcharge load 4. Lateral earth pressure 5. Longitudinal forces from the superstructure

Please refer to Appendix 6-Structural Design Calculations.

Figure 18 : Elevation

Page 118: Final Detailed Design Report - Musita _ Majanji Road

95 | FINAL Detailed Design Report_Rev.1-AUG 2012 |

3.6.2.4 Superstructure

Voided slab type superstructure is used for the standard bridge superstructure for the entire project. The voided slab is split into mid and end pre-cast units to facilitate the pre-cast production and having reduced lifting weight.

Figure 19 : Precast Units

Raised walkway with removable cover utility channel is provided on bothsides of the carriage way.

Figure 20 : Precast Units

The lifting weight of the end unit is around 10 tons and 11 tons for the mid unit. Carriage way width of 7.5meters with sidewalks way of 2.0meters width each side is agreed with UNRA bridge engineers and provided for all the bridges in the entire project. The total bridge width is therefore 11.5 meters. Accordingly two end units and eight units of mid units are put side by side to formulate the total bridge width.

Page 119: Final Detailed Design Report - Musita _ Majanji Road

96 | FINAL Detailed Design Report_Rev.1-AUG 2012 |

Figure 21 : Bridge Cross-section

The pre-cast voided slab units are modeled and designed as single beam each shearing the live load as the same way it is assumed distributed in sold slab. It is assumed that the 10cm thick cast-insitu slab will fully helps in distributing the wheel loads. Please refer to Appendix 6-Structural Design Calculations.

3.6.2.5 Bearings

No special type of bearing except PTFE/similar pads at each precast voided slab beam at one of the two ends is provided to insure horizontal load transfer at one end only. At the other end fixity can be achieved using steel dowels or any other suitable system which be worked with the precast units.

3.6.2.6 Expansion Joints

No expansion joint detail is required for short span bridges like 12m span bridges.

3.6.2.7 Railings

Prefabricated steel tube sections which can be assembled at site and bolted to the precast end unit are selected for the bridge railing. This can help to facilitate the early completion of the bridge work. The steel railing is simple looking and can easily be maintained after traffic damage.

All the railing components are designed to resist the specified design load according to the manual. Please refer to Appendix 6-Structural Design Calculations.

3.6.2.8 Deck Drainage

Deck drainages at every end quarter point of the span on both sides are provided. 200mm by 75mm rectangular galvanized steel hollow section is selected to allow enough opening without clogging by silt for the perfect flow of water which is a common major problem at most bridge sites.

Page 120: Final Detailed Design Report - Musita _ Majanji Road

97 | FINAL Detailed Design Report_Rev.1-AUG 2012 |

3.7 Quantity and Cost Estimation

3.7.1 Determination of Quantities

Determination of the quantities for the various aspects of the design has been made for each of the five project roads.

Civil 3D road design programme has been used to produce the various road component quantities up to wearing course level.

The cross-section costed is that detailed in the Book of Drawings, incorporating a 7.0 m wide carriageway with 1.5 m shoulders.

For all other items, quantities have been calculated based on preliminary design requirements as determined from the site investigations.

3.7.2 Unit Rates

Considering the nature and extent of the Works to be undertaken for this project, it is deemed that only highly experienced and well-equipped contractors could successfully undertake and complete the works in a competent and satisfactory manner. All costing, therefore, are based on this assumption.

The unit rates are based on the presumption of a non-restricted tender in which contractors from countries with low foreign personnel costs and overheads, who are - or have been - active in Uganda or elsewhere in the region, can be expected to submit very competitive bids, with rates appreciably below conventionally derived unit rates.

For the major construction items the unit rates have been derived from first principles and compared with the rates in force on an ongoing project of a similar nature being undertaken by the Client.

The breakdown of unit rates was presented in a separate volume during the Preliminary Design stage and remains unchanged.

3.7.3 Provisions

Preliminary and General Items have been estimated at 10% of the Works Items, whilst Dayworks have been estimated at 2% of the Works Items.

A 10% allowance has been made for physical contingencies and a 5% allowance for financial contingencies during the period of construction.

The estimate is in Uganda Shillings and no separate provision is made for escalation between the present and commencement of construction.

The cost of design has been omitted, whilst a 5% provision has been made for construction supervision.

The estimated costs for land take, environmental mitigation and removal and relocation of services have also been taken into account.

Page 121: Final Detailed Design Report - Musita _ Majanji Road

98 | FINAL Detailed Design Report_Rev.1-AUG 2012 |

3.7.4 Construction Cost Estimates

The draft final cost estimates for Musita-Lumino/Busia-Majanji roads are presented separately in Volume 3A.

3.7.5 Road Construction Packages

Determination of the contract strategy to be adopted and the number of contract packages will be undertaken in consultation with UNRA during detailed design phase.

However, for the purposes of the study and taking due account of the geographical locations of the five project roads and their respective lengths and the estimated value of the construction works, it is anticipated that four contract packages will be required, namely:

Package 1: Musita-Lumino & Busia-Majanji roads (Total length = 101 km)

Package 2A: Tirinyi-Pallisa/Pallisa-Kumi roads (Total length = 64 km)

Package 2B: Pallisa-Kamonkoli road (Total length = 45 km)

Package 3: Bumbobi-Bubulo-Busumbu-Lwakhakha (Total length = 44 km)

Package 4: Namagumba-Budadiri-Nalugugu roads (Total Length = 29 km)

Package 5: Kamuli-Bukungu road (Total Length = (68 km)

Such an arrangement would allow smaller local or regionally based companies to tender, whilst providing packages which individually or in combination would still remain attractive for internationally based contractors. It would also enable implementation and financing to be phased, should this prove to be more attractive.