    2/1/2012

    PGP

    GROUP OF COMPANIES

    SUGAR DIVISION

  • 8/3/2019 FINAL 24.01.13 11 AM

    3/24

    2/1/2012

    STRATEGY FOR

    2011-2012 C.S ( in Lac Tons)

    PARTICULARS UNIT-I UNIT-II UNIT-III TOTAL

    Target for Crushing 2.25 9.00 10.00 21.25

    Registered cane 2.50 8.00 6.40 16.90

    Unregistered cane 0.50 1.00 3.60 5.10

    TOTAL 3.00 9.00 10.00 22.00

  • 8/3/2019 FINAL 24.01.13 11 AM

    4/24

    PERFORMANCE AS ON 23-01-2012

    PARTICULARS UNIT-I UNIT-II UNIT-III TOTAL

    CANE CRUSHED TONS 39600 110510 167932 318042

    REGD. CANE 35895 109460 139534 284889

    UNREGD. CANE 3705 1050 20456

    25211Diversion from other our

    Unit -- -- 7942 7942

    RECOVERY % On Date 8.80 10.00 9.90

    To Date 8.34 9.31 9.27

    SUGAR BAGGED QNTLS 29950 97410 148210 275570

  • 8/3/2019 FINAL 24.01.13 11 AM

    5/24

    CANE PLANTING TARGET

    2012-2013 C.S ( In Acres)

    PARTICULARS UNIT-I UNIT-II UNIT-III TOTAL

    Target 19000 26000 23000 68000

    Plant 13000 12000 7500 32500

    Ratoon 6000 14000 15500 35500

  • 8/3/2019 FINAL 24.01.13 11 AM

    6/24

    CANE REGISTERED

    as on 22.01.2012 (Acres)

    PARTICULARS UNIT-I UNIT-II UNIT-III TOTAL

    Target 1919 7462 4650 14031

    ACHIVEMENT

    Plant 843 2146 1110 4099

    Ratoon 876 1456 3327 5659

    Total 1719 3602 4437 9758

    Achievement % 90 48 95 70

  • 8/3/2019 FINAL 24.01.13 11 AM

    7/24

    CANE YIELD TONS /ACRE

    2010-11 C.S

    PARTICULARS UNIT-I UNIT-II UNIT-III

    PLANT 33 40 36

    RATOON 29 35 35

    AVERAGE 31 37 35

  • 8/3/2019 FINAL 24.01.13 11 AM

    8/24

  • 8/3/2019 FINAL 24.01.13 11 AM

    9/24

    Technologies for Quality Improvement

    Healthy cane cultivation.

    Maintaining high sucrose varieties.

    Harvesting the matured cane based on age /Hand Brix Meter Reading / SMT Results.

    Supply of clean cane.

    Harvesting the cane close to the soil.Transporting the cane to mill immediately

    after harvesting.

  • 8/3/2019 FINAL 24.01.13 11 AM

    10/24

    2/1/2012

    Management Information System ( MIS)

    PARTICULARS UNIT-I UNIT-II UNIT-III Crushing tons / season

    Day.1485 3147 3075

    Total Losses 1.84 1.95 1.85

    Power / Ton of cane

    Units28.89 23.15 20.61

    Power Generated / Ton

    of cane units --- 71.28 117.45

    Power Exported / Ton

    of cane units--- 36.66 85.43

  • 8/3/2019 FINAL 24.01.13 11 AM

    11/24

    DISCIPLINE IN ADMINISTRATION

    WORK DISCIPLINE:

    Wearing of proper Uniform.

    Proper maintenance of Uniform.

    Punctuality in attending the duty.

    Generating the attendance report in time,

    reporting and follow up.

  • 8/3/2019 FINAL 24.01.13 11 AM

    12/24

    Leave Procedure

    Should get approval before availing leave.

    Avoiding leave for many at one period.

    Restriction of leave during season.

    Encashment of unavailed leave.

  • 8/3/2019 FINAL 24.01.13 11 AM

    13/24

    RECRUITMENT POLICY

    The following is the existing policy :

    Training - 1 or 2years

    Probation and - 1 year

    Confirmation - Wageboard/

    Executive cadre.

  • 8/3/2019 FINAL 24.01.13 11 AM

    14/24

    TRAINING

    Periodical Quarterly evaluation for TraineesPerformance.

    Poor performer Elimination at the end ofevery evaluation.

    Well designed training during ProbationPoor performer Not to be confirmed.

    No more complaint after confirmation.

    It is the responsibility of the HOD.

    To have one or two additional Trainees .

  • 8/3/2019 FINAL 24.01.13 11 AM

    15/24

    HOUSE KEEPING

    Breakdowns occur due to

    improper house keeping.

    Creation of awareness onhouse keeping from the Training

    Period.

  • 8/3/2019 FINAL 24.01.13 11 AM

    16/24

    MAINTNANCE

    PREVENTION IS BETTER THAN CURE

    Preventive Maintenance schedule.

    Regular servicing of equipments.

    Reduction of maintenance cost per unit ofproduction.

    Proper usage of spares.

    A clear knowledge on equipments as peroperation manual.

  • 8/3/2019 FINAL 24.01.13 11 AM

    17/24

    INVENTORYHigher Inventory amounts to locking of working

    capital , causing interest burden.

    Identification of spares as per A B C Analysis.

    Data generation for minimum stock level at whichindent to be raised.

    Identifying materials which are readily available inthe market.

    Accounting the unused spares returned afterindenting.

    Reusable of old spares - stock maintenance.Periodical Stock Verification.

    Identifying spares - not used for long period andadvising to other Units.

  • 8/3/2019 FINAL 24.01.13 11 AM

    18/24

    18

    WELFARE

    Family Mediclaim Policy for employees

    more than 10 years of service.

    Safe Drinking water at factory as well atquarters.

    Canteen hygiene and Toilet hygiene.

    Employees

    F

    amily tour once in twoyears.

    Community Hall.

  • 8/3/2019 FINAL 24.01.13 11 AM

    19/24

    Management Information System

    Bio Metric attendance system for all canedivisional offices.

    Data generation and communication tocontrol office through system.

    CUG mobile facility to all cane field staff.

    Online data communication system toCorporate Office from units.

  • 8/3/2019 FINAL 24.01.13 11 AM

    20/24

    2/1/2012

    Organisational Healthiness & Prosprity

    Depends on:

    A) Control on Input Cost

    B) Maximise Returns Sales Realisation

    C) Minimise Cost of Production

    i) Maximise Output for given Input

    ii) Control on Variable cost

    a) Maintenance Cost

    b)Maximise production per unit time

    c) Reducing Losses, etc.,

  • 8/3/2019 FINAL 24.01.13 11 AM

    21/24

    2/1/2012

    VACANCY POSITION

    DEPARTMENT UNIT-I UNIT-II UNIT-III

    ADMN 3 7 6

    CANE 6 21 2

    ENGINEERING 10 11 1

    PRODUCTION 3 4 5

    COGENERATION 0 3

    DISTILLERY 4

    TOTAL 26 43 17

  • 8/3/2019 FINAL 24.01.13 11 AM

    22/24

    Strategies for Unit-III

    Commisisoning of 110 KLPD Distillery:

    Slow firing on 29-01-2012

    Steam flow to Turbine 20-02-2012

    Commissioning of Refinery at Unit-IIICanteen facility

    Cane farm

    Road work inside factory particularly cane yard

    Common Lab facility to fulfill statutory obligations.

    2/1/2012

  • 8/3/2019 FINAL 24.01.13 11 AM

    23/24

    STRATEGIES UNIT-I & II

    Installation of new 25 MW Cogen plantHigher coverage area under Drip Irrigation

    and 6 ft planting.

    Expansion of Mechanical Harvester in unitsOwn building for Divisional offices and

    Fertilizer Godown

    Modernisation of canteen at Unit-I

    2/1/2012

  • 8/3/2019 FINAL 24.01.13 11 AM

    24/24

    UNIT-III DISTILLERY OPERATION FROM APRIL 2012.

    MOLASSES AVAILABILITY

    PARTICUALRS UNIT -I UNIT -II UNIT -III TOTAL

    BALANCE CANE ( Lac Tons) 2.55 7.6 8.4 18.55

    MOLASSES PRODN (TONS)12113 36100 39900 88113

    + OPENING STOCK 3002 1308 3269 7579

    TOTAL MOLASSES

    AVAILABLE15115 37408 43169 95692

    MOLASSES FOR UNIT-I UPTO SEPT 38250

    MOLASSES FO RUNITIII UPTO SEPT 52500

    TOTAL 90750

    NET SURPLUS 4942